Professional Documents
Culture Documents
AN ASSIGNMENT ON
CASE ANALYSIS
SUBMITTED BY:
PP20024: Swapnil Patil
PP20041: Harsh patel
PP20042: Manish Patil
PP20046: Shubham Katore
PP20047: Yash raj Saxena
CASE SUMMARY
So to encapsulate, The arbitrator was unable to resolve non-arbitration cases and the award, as it
concerns non-arbitration disputes, is invalid from the point of view of law and is hereby annulled. The
contractor may bring an appropriate legal action to collect payment for the work performed.
Q) Did the dispute happen due to ambiguity or mistakes in any of the contract clauses?
How the dispute could have been prevented (in terms of better drafting of contract
clauses)?
No, there was no ambiguity in the contract that led to this dispute, and the dispute could have
been prevented by incorporating the following points in the clauses
1. The “excepted conditions” could have been clearly mentioned and their implications
should have been made more transparent to the contractor.
2. Provisions should have been made in the contract or BOQ for any extra work or change
in quantities which may lead to cost overruns by the contractor.
3. Separate contract clauses are supposed to be mentioned for change of scope by the
contractor but with the consent/prior approval of the engineer.
4. The scope/domain of arbitrator should have been made clear to both the parties as a part
of special conditions of contract.
5. The roles and responsibilities of Engineer, Chief Engineer (client’s side) should have
been also clearly mentioned in the context of change in financial/technical structure of
the project, if the situation arises in midway.
6. Special clause pertaining to Quantum Meruit compensation can be added in Special
Conditions of Contract
7. All payment related clauses should be arranged in correct sequential order as per timeline
of work scheduled.
8. The roles and responsibilities of the arbitrator should have been clearly defined in general
conditions of contract as to when, how and where to appoint him/her.
Q) Comment with reasons whether the dispute could have been avoided if FIDIC
provisions (Red/Yellow/Silver book, as applicable based on type contract used in the
selected case) were adopted instead of an Indian standard form contract. Cite the relevant
FIDIC clause to support your argument. However, if the case you have selected is already
based on FIDIC conditions, only provide your arguments for point ‘b’ above).
According to clause no. 67.1 of FIDIC Part-1 – General conditions with forms of
tender and agreement –
“If a dispute of any kind whatsoever arises between the Employer and the Contractor in
connection with, or arising out of, the Contract or the execution of the Works, whether during
the execution of the Works or after their completion and whether before or after repudiation or
other termination of the Contract, including any dispute as to any opinion, instruction,
determination, certificate or valuation of the Engineer, the matter in dispute shall, in the first
place, be referred in writing to the Engineer, with a copy to the other party. Such reference shall
state that it is made pursuant to this Clause. No later than the eighty-fourth day after the day on
which he received such reference the Engineer shall give notice of his decision to the Employer
and the Contractor.”
“If either the Employer or the Contractor be dissatisfied with any decision of the
Engineer, or if the Engineer fails to give notice of his decision on or before the eighty-fourth day
after the day on which he received the reference, then either the Employer or the Contractor
may, on or before the seventieth day after the day on which he received notice of such decision,
or on or before the seventieth day after the day on which the said period of 84 days expired, as
the case may be, give notice to the other party, with a copy for information to the Engineer, of
his intention to commence arbitration, as hereinafter provided, as to the matter in dispute. Such
notice shall establish the entitlement of the party giving the same to commence arbitration, as
hereinafter provided, as to such dispute and, subject to Sub-Clause 67.4, no arbitration in
respect thereof may be commenced unless such notice is given.”
“If the Engineer has given notice of his decision as to a matter in dispute to the
Employer and the Contractor and no notice of intention to commence arbitration as to such
dispute has been given by either the Employer or the Contractor on or before the seventieth day
after the day on which the parties received notice as to such decision from the Engineer, the said
decision shall become final and binding upon the Employer and the Contractor”.
The contractors discretion over additional work was not used in this instance, not in any
case, and there was no way to communicate differences with the other parties such as work
expected to happen later or things like that. There had been an 84 day notice periods for both
parties if the use of FIDIC conditions were to be used and if a dispute arose between the parties, the
notice could be sent again no later than 70 days to initiate the arbitration proceedings, but nothing like this was
observed in this case, the arbitrator was appointed directly without prior notice, the party excluded matters that
again become the subject of disputes / disagreements .
Coming to the excepted cases as mentioned in this contract, where as in on the contrary
there is no mention of the excepted cases in FIDIC standard form of contract.
It also happened in our case, The procedure that could have been avoided started way too
early as per clause fidic of the arbitration clause where it only started after the 56th day from the
initial notice of its start up to either party.
According to clause 67.4 - “Where neither the Employer nor the Contractor has given
notice of intention to commence arbitration of a dispute within the period stated in Sub-Clause
67 .l and the related decision has become final and binding, either party may, if the other party
fails to comply with such decision, and without prejudice to any other rights it may have, refer
the failure to arbitration in accordance with Sub-Clause 67.3. The provisions of Sub-Clauses
67.1 and 67.2 shall not apply to any such reference”.
If either party doesn't follow the proper communication channel with reference to
timelines or if there is no process for disagreeable matters then the decision that was made prior
to court shall be binding upon them.
It's almost certain that if the correct channel with references to timelines isn't used and no
process regarding disagreements addressed, the other party will assume final responsibility of the
disagreement.