Estimates and Estimating
Estimating: 2
Estimating methods
High
Accuracy
& Detail
Bottom-up
Parametric Estimate
Estimate
Comparative
Estimate
3-point
Estimate
Expert
Judge-
“Quick & ment
Dirty”
Perception Fact
Estimating: 3
Bottom-up estimating
Assumes that future costs for a product can
be predicted accurately from historical costs
of that product
Uses detailed costs of components, built up
into an end product (WBS/PBS)
e.g. 10,000 bricks, 250 tiles, 20 litres of paint =
total cost of £xxx
Estimating: 4
Parametric estimating
Estimating: 6
Other estimating methods
3-point estimates Expert judgement
Come up with 3 numbers: Ask the project team and
Realistic (most likely) Subject Matter Experts
Best case (optimistic)
Worst case (pessimistic)
Estimate =
(B + 4R + W)/6
N.B. the formula is usually
weighted (4 x R), but
sometimes is the “simple”
average of B, R & W
Estimating: 7