Professional Documents
Culture Documents
• Scope Baseline
• Resources Requirement
• Project Schedule
Realistic (r)
Optimistic (o)
Pessimistic (p)
A: 4 weeks
B: 6 weeks
C: 11 weeks
D: None of the Above
You are the project manager of Libra Travels SSS Project. You have decided to use the 3
point estimation technique for his project. For the “Test Corporate Bookings” activity, the
following estimates are available. O=4, P=9, R=5. What is the result of this estimate?
A: 5.5 weeks
B: Eighteen weeks
C: 33.33 Days
D: None of the Above
Reserve Analysis
• Contingency reserves are allocated for identified risks for
which mitigating responses are developed.
Training Rework
Equipment Scrap
Documentation
Testing Liability
Warranty
Inspections
Credibility
Project Management estimating software
• Spread sheets
• Simulation software
• Basis of estimates