You are on page 1of 11

deep Technology news from Subsea 7

2015

Pioneering Buoy
Supported Riser System

Sapinhoá-Lula NE
technical success
see pages 12/13
2
deep7 - 2015

The many types of For Total technology it’s


innovation at Subsea 7 the sum of the parts
by Thomas Sunde, Vice President - Technology by Jeremy Cutler, Head of Technology Innovation, Total E&P UK Ltd

Welcome to the 2015 At Total innovation to design a robot capable of managing a certain Contents
How we approach innovation is largely focused on number of tasks in hazardous environments. The
edition of deep7 • Reactive - These are project- technical research robots which are being developed might need Bridging the gap from
driven and require a swift and engineering to be able to climb stairs, or take a reading on a onshore to offshore -
Since the beginning of the response which is linked to gauge, or turn a valve, or undertake a series of
offshore oil and gas industry, DONG Siri project
• Proactive - These are innovations the development of reporting tasks.
technology has played a page 5
which require incremental technology. More
fundamental role in supporting improvements recently it has been Currently we have shortlisted five teams for the Aasta Hansteen
the safe and efficient • Process - These are step change recognised that challenge which is drawing talent from across provides a reel
exploration, development and innovations which can produce a innovation isn’t solely about producing Europe and there will be a bursary for the
deepwater challenge
production of hydrocarbons. revolutionary outcome technical solutions and it now encompasses winning team.
page 6
• Strategic - These are innovations the way we work organisationally.
This edition of Deep 7 that will deliver solutions to future This is one way of obtaining support for Material gains –
discusses the importance challenges. Within the company we formally recognise the innovation from outside Total. We are also
innovation in epoxy
efforts of individuals, or more frequently teams, supporters of ITF, The Industry Technology
of innovation and how the pipeline repair
in order to solve problems. We encourage Facilitator, which has its headquarters in
industry as a whole needs page 8
innovation in many different ways and we Aberdeen but is spreading across the world.
to continue to invest in the When assessing the emerging and formally recognise it through our annual Best Through our sponsorship of ITF we have the Missing flow
development of cost saving fundamental problems that our clients Innovators Awards. In terms of our external opportunity to take part in different Joint Industry
and enabling technologies. without a trace
In today’s low oil price environment, face, we have to find a way to bridge relations, there are ongoing efforts to encourage Partnerships (JIPs).
From the successful page 10
innovation and technology are more the gap between what exists and and foster innovation across industry. Our role
deployment of a wholly new important than ever in meeting the what’s required. This is called Process in this respect is to effectively identify the best Within Total we promote four key areas of Mechanically Lined
subsea technology previously challenges facing the subsea industry. innovation. It leads to improvements disruptive technologies and to pursue and innovation through the Technology Leadership
Pipe is a qualified
only used in the onshore and operational streamlining through support those technologies which we believe Board which is supported by Philippe Guys,
success
construction industry, to non- The pursuit of innovation as a platform an understanding of how a solution is will make a difference. Our approach is not just Managing Director of Total E&P UK.
page 11
destructive testing equipment for future business growth requires developed from the current position. about taking a particular problem and finding
used on the Boeing 787 commitment, particularly when revenue a solution, but rather identifying technology These four areas of innovation include: Sapinhoá-Lula NE - a
is reduced and profits are challenged. Development of the Subsea 7 Bundle areas and promoting them through our own Intelligent Operations and Maintenance which
Dreamliner now being tested deepwater technical
Subsea 7 is fully committed to building on solution is a good example. Having R&D, or through the R&D efforts of the industrial encompasses integrity, wireless monitoring,
on subsea equipment, we triumph
its track record of successful innovation to identified a need for subsea tie-backs community. smart technologies and robotics; Subsurface
have examples of how to be delivered in a more cost effective Imaging which is linked to the sub-surface
page 12
drive future growth in its business over the
spin-out technologies are coming years. manner, and utilising our experience The challenge here is to be focused as we definition of structures and the identification of
increasingly being used From airline pipe
in the execution of subsea projects, obviously cannot support every area of interest. small pools and structures containing oil and gas
across the oil and gas dream to subsea
Why? Because there is a proven we engineered a product to meet the We have therefore transformed our R&D efforts, for future possible extraction within the North
industry. inspection solution
correlation between organisations that future needs and challenges of our from some 28 different projects down to eight Sea; Drilling is the investigation of more cost
invest in this way during leaner times and clients. major programmes which are linked to sub- effective drilling technologies; Long Distance page 14
The one clear theme which improved business performance when surface geoscience areas as well as other Subsea Tiebacks is an investigation into cheaper
Global opportunities
binds all of this content is market conditions once again begin to Strategic innovation describes a subjects like Deepwater exploration. and lighter all-electric control systems and how
in the pipeline for
partnership which needs to improve. wider approach over time which to get power to subsea processing.
recognises that the status quo will not Much of our R&D is therefore undertaken
Bundle technology
be central to the industry’s
Innovation – The Subsea 7 approach be maintained. Long-term planning in-house through these eight programmes These are the four key areas of technology page 16
approach to sustainability.
At Subsea 7 our projects are Innovation occurs at the most basic level and investment is required to establish and it is through these endeavours that we innovation for Total.
Tackling hidden
as a function of general engineering. a position of technology leadership. identify different research opportunities. These
successful because of the challenges of the
Problems arise during the course of Innovation from this type of approach opportunities may be developed through a We recognise that there are challenging times
partnerships we have forged Arctic environment
projects that were not anticipated at will be used to develop new solutions joint industry project and by doing this we are ahead, but we continue to support our R&D
with academia, research the bid stage, and require an immediate to future challenges. looking to leverage our R&D budget with other function as our experience shows that we page 18
institutes, and suppliers. This resolution. This type of innovation can companies in order to share costs. Another need to be positioned for the upturn and if
approach means that we can Building for
be viewed as Reactive or Project Driven At Subsea 7 we innovate every day. approach might be to pursue a research area we cut back now we’ll lose the opportunities
encourage and support the innovation. We work with our clients to embrace through a leading university. when they come. This is why we continue to
the future
development of knowledge, their challenges and find new ways to support innovation within our industry, and page 19
skills, and technologies which Innovation driven by the organisation and deliver projects in the most efficient A classic example of how we nurture innovation also study other industries for possible spin-
provide us with the ability sponsored by our leadership teams can way possible. We look outside of our is in the area of robotics where we have identified out technologies which may introduce greater
to successfully undertake be viewed as Proactive innovation. This industry for transferable technology. the potential for surface based robots to have an efficiencies. Industries such as the aerospace
some of the most challenging is characterised by gradual, incremental Our goal is to find solutions that impact in our industry. At our test facility in Lacq industry, with its long-standing commitment to
projects in the world. improvements, focused on optimisation sustain the long-term future of the in the South of France we have established an new, lighter materials, and the nuclear industry
and standardisation and largely driven at offshore oil and gas industry. initiative called the ARGOS Challenge where we with its deep understanding of inspection
a local level. have approached industry and asked companies technologies, remain of abiding interest to us.
3
4
deep7 - 2015

Ensuring risk does not Bridging the gap from onshore


outweigh reward to offshore - DONG Siri project
by Andrew Duncan, Group Leader, Asset & Management Systems, DNV GL by Alan Cassie, Project Manager

to buy into success or walk away if Each party here is an Innovator and will Transferable technologies are critical some of which were complex and that the alignment of the cable between
the asset is no longer attractive. They win from the process. to the future development of the required specialist manufacturing and the clamps was very accurate. In turn
also use cost-price averaging to their subsea industry. When the DONG testing. This added significantly to this required that the clamps were
advantage, spreading investment over There are ways to reduce the inherent E&P operated Siri Platform suffered the complexity of the cable assembly installed to a very tight tolerance of
time, balancing opportunities. risk of deploying innovation. API 17N extensive cracking to a part of the process. The modified design required plus or minus 0.15° degrees. To achieve
and DNV GL’s Technology Qualification substructure supporting the wellhead the cable ends to be held vertically for this the clamps were located using
Differently from pure financial recommended practice, DNV RP- area and wellhead caisson, a well- over 36 hours while the anchorage ends pre-installed guide clamps, and clamp
products, an organisation should not A203, provide frameworks for the used onshore technique was adopted were sealed with layers of wax and headings were measured using survey
lose all its money if an ‘Option’ (an innovator. When such processes are to extend the operating life of the epoxy resin. gyros. Fine alignment was carried
innovation project that may or may followed, fewer mistakes are made, or installation. out using local rigging before bolt
not deliver something valuable in the are made earlier and therefore more Once the design, fabrication and tensioning.
future) doesn’t work out. At worst, cheaply. If the research progresses to The novel reinforcement solution manufacture of the clamps and cables
the Basic research carried out never a successful product, then it will not identified by the Subsea 7 team was were complete the project team was At the time the concept was selected it
leaves humanity poorer in knowledge; just be more robust and able to fulfil based on the application of cable left with several difficult installation was anticipated that cable tensioning
At DNV GL, we are privileged to something that may yet find a use and the customers’ needs, but also the stay technology in combination with a challenges. The size of the clamps used would be carried out using standard
support innovators who are taking deliver value has been developed. Innovator will possess validated new seabed support structure for the was one such challenge. The clamps methodology. As the project progressed
their ideas towards sustainable, evidence to wellhead area and caisson. weighed around 150Te and included 56 it became clear that this approach was
commercial deployment. Working An alternative to the ‘gambling’ support that claim, assuring M90 bolts per clamp. The handling of unsuitable. In response, Subsea 7
so closely with extraordinary people approach of ‘Innovating Boldly’ might the stakeholder that they Cable stays are widely used in bridges, these clamps and the heavy rigging that designed, fabricated and tested a
from different types of organisations, be to stack risk differently, this time in are not being asked but there is no history of their use in went with them required a large amount bespoke tensioning system which
at different points in the value chain, your favour. A professional gambler will to bear intolerable the scale proposed for offshore use by of detailed engineering and analysis to allowed for the cable catenary to be
we see the challenges they face in work with marginal advantages over the risk (despite Subsea 7. The solution required the ensure that this could be carried out removed and an intermediate tension
making innovation commercially casino, but they will find it very difficult the product’s platform legs to be stiffened in order to safely and efficiently. To assist in the applied in a single stroke. 
successful. to collaborate with the casino. If an novelty). reduce platform motion. This concept installation of the bolts, hydraulically
Innovator can collaborate openly with reduced the natural period of platform operated bolt racks were designed and During the offshore campaign the
We note that the number of innovations its customers and suppliers, then the motion – from 6.5 to 6.9 seconds in its fabricated. These significantly reduced equipment and procedures worked as
actively moving towards deployment risk can not only be shared but, more damaged condition – to around three the amount of manual handling to be planned. The clamps were installed
appears to have increased. The importantly, the advantages of insider seconds. The concept is based on the carried out, making the task of installing within tolerance, the cable stays were
common challenge faced is how to knowledge and shared resources will installation of pairs of cross-braced the bolts both safer and more efficient. installed and tensioned without damage
fulfil their vision while being adopted by reduce the total risk. cables on each of the three faces of the to the anchorage thread or the water
industry. platform, the cables supported at each Owing to the weight of the clamps and tight duct, and platform natural period
Knowledge Transfer programmes, end by clamps at the top and bottom the attendant issues associated with reduced from a little over 6.5 seconds
Innovation is risky, but it is innovation JIPs and other collaborations with Oil of the platform legs. Once installed the heavy rigging, complex engineering to three seconds, with corresponding
that is vital to reducing the economic Majors and Vessel Owners can provide cables were tensioned to 1,250Te. analysis was required. In order to avoid reduction in platform motion.
risks faced by the current market access to resources and facilities fatigue issues, the cable design required
situation with suddenly lower oil prices. otherwise unattainable, which The project presented a number of
So now is a very good time to bring can help Innovators to mature challenges. The complexity of the
whole new ways of doing things to their nascent technologies solution’s design was an early issue
the marketplace – not incremental towards market acceptance. for the project team. The process was
improvements; indeed the less risky In return, the other extremely complex, with separate
strategy may be to innovate boldly. party gains access to design houses looking at the clamps
potential solutions and cables and the global design of
However, on any risk scale, innovating to their problems. the overall platform. These efforts were
boldly can be a gamble, especially separate but related, with changes
if focused on just one area. What’s made in one area having an impact
required is a portfolio that gives the on another. The process was further
return needed in the long run while complicated by fabrication being carried
exposing company’s to acceptable risk. out in parallel with design.
A parallel can be seen with financial
managers spreading risk across a The most significant alteration
basket of assets, using ‘put’ and ‘call’ undertaken to the cable stay design
options, maintaining the possibility was the introduction of a water tight
duct. This required a full redesign
of the end anchorages, including a
Installation of the 150Te clamps to the platform legs required the design and fabrication of hydraulically
number of entirely new components, operated bolt racks, to make the task safer and more efficient for the rigging crew
The Seven Oceans reeling DNV qualified
BuBi® pipe in the Sapinhoá-Lula NE field

5
6
deep7 - 2015

Aasta Hansteen provides a reel


deepwater challenge
by Kjetil Moen, Project Engineering Manager and Maria Eidesvik, Project Manager

Far from land and established to the Nyhavna gas terminal on the Welding of the SCRs will be completed BuBi® pipe reel-lay installation using a water filling spread, mobilised developed. Connection to the reel is
infrastructure, the challenge of Norwegian west coast. by Subsea 7’s Pipeline Production Team onboard the pipe-lay vessel with via a slip ring system which allows for
recovering resources from the Aasta (PPT) using a mechanised procedure for During the load-out and installation connection to the pipeline on the permanent connection of the water
Hansteen field in the Norwegian Sea The infield pipeline system consists of mainline welding of both 12” production of the BuBi® pipe, the pipeline was reel. The pipeline will be filled from filling spread on the vessel deck to
makes it one of the most demanding four 12” Outer Diameter (OD) thermally SCRs and 14” Gas Export SCRs using water filled and pressurised to avoid the lay vessel for each stalk pull, the pipeline and thereby enhanced
engineering projects in the world. insulated BuBi® pipe flowlines with a Gas Metal Arc Welding (GMAW) and wrinkling of the liner. The minimum with a set of high differential pigs control of the pressure without having
As such Aasta Hansteen is an total length of 16.5km. One flowline runs a Cold Metal Transfer (CMT) process required pressure had been determined creating the barrier between what will to stop reeling operations. The system
enduring example of how Subsea 7 from a template to template location, for root pass and Pulsed Gas Metal through detailed design and technical be approximately four Bar internal also allows for recirculation and
constantly seeks out new solutions while the other three connect the Arc Welding (PGMAW) for hotpass qualification. pressure during the stalk tie-in containment of a finite amount of the
to the challenges it faces. The project template location to the SPAR platform fill and cap. The welding process is welding. Specifically designed plugs fresh water and MEG mixture.
teams are multidisciplinary, cross- and are tied in via 12” OD thermally adopted for both fatigue sensitive Technical qualification of the 12” will be installed at the stalk end and
departmental groups which bring insulated metallurgically-clad pipe SCRs areas and non-fatigue sensitive areas. BuBi® pipe for reel-lay installation on internal pressure in the order of 30 ULTRA® pipeline coating
together a unique combination of each measuring approximately 2000m. This welding procedure was originally with DNV is to be performed in to 40 Bar, which is to be established
skills and expertise in order to deliver The pipeline system also includes developed for the Sapinhoá-Lula NE parallel with the project, building on before each stalk pull takes place. Aasta Hansteen is the first Subsea 7
solutions to complex problems. coating, fabrication and installation of project and subsequently refined during previously approved qualifications of project to use the ULTRA® insulation
one 14” OD corrosion protection coated a preliminary welding programme at the the 8” to 10” pipe. Based on lessons learned from the coating system developed and
The Aasta Hansteen field is located in carbon steel pipe gas export SCR, Global Pipeline Welding Development Sapinhoá-Lula NE project, a solution provided by Bredero Shaw. The
the northern Norwegian Sea, 300km approximately 2,000m long. Centre in Glasgow. Operationally, the water filling and for an improved water filling system ULTRA® coating provides significantly
offshore Bodø in a water depth of pressurisation is to be obtained by onboard the lay vessel has been improved thermal insulation properties
1300m, and is currently the deepest The flowlines and the SCRs will be The work involved two main elements, over the conventional PP Foam
development in Norwegian waters. fabricated at Vigra Spoolbase in Norway refining the weld quality experienced systems. For the flowlines with a
and installed by the reel-lay vessel on Sapinhoá-Lula NE by incorporating U-value of 4.0 the reduction in coating
The field is being developed with three Seven Oceans. The SCRs will be laid PPT’s latest developments in welding thickness of ULTRA® compared to
subsea production templates, tied back down temporarily for subsequent pull-in technology and updating the welding PP Foam is from 80mm to 50mm
to a SPAR FPSO via mechanically- and hang-off after tow-out and mooring programme to deal with the specific corresponding to approximately 40%
lined (BuBi®) flowlines and clad Steel of the SPAR platform. The 12” OD SCRs requirements of Aasta Hansteen’s large reduction. This means that more
Catenary Risers (SCRs). Gas export are welded to the flowlines via tapered diameter (323.9mm and 355.6mm product may be stored on the pipelay
will be through the POLARLED pipeline transitions. OD) and heavy Wall Thickness (WT) vessel reel.
which is to be connected from the field (28.6mm) SCR pipe.
Controlled lateral buckling
The SCRs include fatigue zones at
the top and in the touch-down areas The temperature of the flowlines
where stringent defect criteria apply, during operating condition is such
together with cap sanding requirements that control of end expansion and
in order to obtain the necessary fatigue lateral buckling is required. End
performance. The specific requirements expansion control is achieved by
to the fatigue zones involves stringent conventional rock dumping solution
AUT acceptance criteria with a whereas controlled lateral buckling
maximum allowable defect height of is obtained by distributed buoyancy
1.5mm, zero weld repairs, so any installed on the pipeline.
rejects have to cut-out and re-welded
and weld caps fully removed and 100% There are in total five lateral buckling
post removal surface inspection by zones over the four flowlines, with
Magnetic Particle Inspection (MPI) and each buckling zone consisting of 25
Dye Penetrant Inspection (DPI). buoyancy modules distributed over a
length of 100m.
Performance in this area was verified
by a number of fatigue tests containing Distributed buoyancy provides a
seeded welding defects, as requested cost effective solution compared
by the client, a relatively novel approach to sleepers and rock carpets and
within the industry. provides low stress levels which
makes the solution suitable also for
(Installation methodology includes licenses
from Statoil Petroleum AS). BuBi® flowlines.

Asta Hansteen has number of milestones, including the world’s


largest SPAR FPSO with Steel Catenary Riser (SCR) system and
The welding process on the Aasta Hansteen project was originally developed for the Sapinhoá-Lula NE project and
reeled installation of BuBi® mechanically lined pipe
subsequently refined during a preliminary welding programme at the Global Pipeline Welding Development Centre in Glasgow.

7
8
deep7 - 2015

Material gains – innovation in


epoxy pipeline repair
by Kenneth Bryson, Mick Fowkes, Paul Booth and Christopher Mock, Subsea 7

Submarine pipelines are the arteries With regard to epoxy based PRS, because the equivalent epoxy solution
of the oil and gas industry with most current solutions are based on is much simpler, requiring only seal
pipeline technology having advanced hyperbaric welded repairs, mechanical setting and no grip deployments.
dramatically over the past 30 repair clamps, or connectors, and repair
years and projects that were once spools. Repair hardware and installation Epoxy technology compares well when
mere dreams now a reality. Today, tools are well established and available equated to mechanical grip repair
breakthroughs in materials science from a small number of providers. For solutions such as ball bearings which
are helping to further improve the deepwater repairs, performed remotely are squeezed into a pipe thereby
integrity of offshore pipelines while by ROV, the repairs are much more generating hoop stress and effecting a
reducing ongoing costs. challenging and involve investment in repair. Weight versus pipeline diameter
specialist equipment. does not increase in the same ratio
Despite advances in pipeline technology as that for conventional mechanical
significant challenges remain, ranging Advantages of epoxy technology in connectors.
from problems presented by pipe pipeline repair
laying mechanics, buckle propagation, When performing repairs remotely in
interaction with sandwaves, and surface Subsea 7 is increasingly seeing clients deepwater the size and weight of the
tie-ins. Faced with these ongoing take a more proactive approach to repair hardware has a significant impact
challenges epoxy repair technology is pipeline repair, often specifying and on the installation vessel, deployment
set to make deepwater pipeline repairs procuring elements of a pipeline repair equipment and handling methods.
lighter, easier and more cost-effective. system as a contingency against future The use of epoxy technology permits
problems. a smaller, lighter solution leading to
Subsea 7’s epoxy hardener and micro overall reduced installation costs, even Epoxy technology compares well when
equated to mechanical grip repair solutions
glass sphere aggregate provides a With client engagements it is important when accounting for the epoxy injection
A 3D diagram of a epoxy filled slide-on connector
robust way to repair hairline cracks and to minimise CAPEX expenditure for a process. Most significant gains will
cavities while eliminating the possibility contingency system, while ensuring be achieved for major cut-out repairs Epoxy repairs – the way forward
of weakening caused by shrinkage. clients are able to minimise the need injection system has been developed that it is possible to carry out a repair where the use of epoxy couplers offers
The reduction in curing time, to just for upfront CAPEX expenditure for a to provide a repeatable process and within a predetermined timescale the greatest size and weight advantage Subsea 7’s epoxy technology is an
24 hours compared to seven days contingency system. produce consistent grout quality under should the need arise. The use of epoxy over equivalent couplers, or flange important development with many
for cement grout, also offers greater subsea installation conditions. Control technology allows significant reduction adaptor connectors. Ultimately, this applications in pipeline intervention
Inspection, Repair and Maintenance Subsea 7’s epoxy repair solutions are of grout quality includes: in CAPEX due to reduced lead times, leads to a reduction in the specification and repair. Deployed more rapidly
(IRM) cost management. With a wide lighter, cheaper, easier to install and simpler construction, reduced vessel requirements for installation while from smaller vessels, it can
range of applications, including pipe imposes fewer requirements on the • Testing curing strength requirements and overall reduced offering a bigger operational weather significantly lower the costs of field
branch connection, or tie-backs, underlying pipe. In 2006, Subsea 7 • Ensuring all critical gaps, cracks and installation schedule. window for deployment vessels. It also extensions or damage remediation.
valve replacements, by-pass for began collaborating with Advantica, crevices are filled with grout. permits the use of an infield support For contingency repair systems,
pipeline repairs and blocked removals, formerly the R&D Division of British Gas Key advantages offered by epoxy vessel rather than larger, costlier both the initial investment and the
its versatility is most evident when Corporation, to extend the use of epoxy Subsea 7 is currently working toward technology for pipeline repairs include offshore construction vessels. cost and time to repair are reduced.
deploying Subsea Grouted Tees (SSGT) hot tapping equipment for subsea industrialising the further development technical, schedule and installation Considerable testing has been
and Pipeline Repair Systems (PRS). pipelines. of epoxy repairs, replacing most if benefits. Technical advantages include Qualification Programme carried out and gives confidence that
not all conventional clamp, tee and the ability to transfer load from a epoxy systems can restore damaged
In particular, the principal advantages The key benefits of Subsea 7’s epoxy connector requirements. damaged pipeline section, quickly Significant test data exists to support pipelines to their original specification,
of epoxy resins come to the fore when grout solution and efficiently. This is particularly and provide confidence that epoxy or carry out modifications which
it is used in live interventions, or hot One important type of epoxy repair advantageous in situations where there based repairs provide the required meet current industry standards. It
tap applications. This is a technique • Compressive strength is the SSGT which can be used in a is wall thinning caused by internal or high level of integrity once installed. represents a significant new Life of
which allows a connection to be made • Shear strength (concentric rings) number of live intervention, or hot tap external corrosion and where the use of Field offering to Subsea 7’s clients
without shutting down whole systems • Adhesive & cohesive strength scenarios. Some unique key features a mechanical clamp type connector is Many tests and qualifications have and pipeline operators around the
and venting gas, resulting in significant • Tensile bond strength offer added operational benefit impossible because of the strength of taken place, including seals, epoxy, world.
technical, schedule and installation • Tensile Modulus such as offset acute angles, double the force imposed by the mechanical shell, branch and injection. These
benefits. • Minimal volumetric changes after branches and K configured branches. gripping system. tests included laboratory based
curing. Possible applications include pipe material and component testing,
Furthermore, as epoxy technology offers branch connections (tie-backs), valve In situations where pipelines require full scale testing and infield tests to
a significant reduction in component To control the above physical replacements, by-pass for pipeline major repairs and cut-out and repair ensure the highest quality repair is
lead time, simpler construction and a properties, and to allow epoxy grout to repair and blockage removal. spools cannot be deployed, the delivered.
reduction in the use of support vessels, be used at any depth, a seabed grout advantages are more significant. This is

9
10
deep7 - 2015

Missing flow without a trace Mechanically Lined Pipe is


by Neil Brown, Technology Manager - Norway
a qualified success
by Grégory Toguyeni, Principal Welding & Materials Engineer

Market demand remains strong for programme by performing full scale


High Pressure, High Temperature resonance fatigue tests up to a stress
(HPHT) pipeline materials which range of 200MPa.
are resistant to severely corrosive
environments. Subsea 7 continues When the stresses experienced during
its pioneering development of the fatigue cycling are above the
Mechanically Lined Pipe (MLP) material yield strength at first load,
technologies, with an extensive DNV failure can occur at a number of cycles
approved qualification programme much lower than if the material was
A feature of today’s subsea which led to the demonstration of stressed in its initial elastic domain. In
developments are the ever more its fitness for service when installed such instances we would refer to ‘low
challenging well streams that require by the reel-lay method for flowline cycle’ fatigue.
advanced solutions for the flow and Steel Catenary Riser (SCR)
assurance issues faced by operators. applications. On an MLP, high values of local
The need to limit uncontrolled wax stresses can be experienced at the pipe
and hydrate formation over longer Subsea 7 has recently expanded the end triple point where the Corrosion
distances presents a technology and diameter range of its reeled MLP with Resistant Alloy (CRA) liner is welded
engineering challenge that cannot a 16” outer diameter pipeline. This to an overlay weld. At this point, also
be economically addressed using components, bulk head penetrators, Some examples of the value of qualification involved full scale reeling referred to as a seal weld, the strain
standard pipeline solutions. electrical and fibre-optic wet-mate early operator engagement include simulation to confirm that no wrinkling combined with thermal cycling can
connectors and a fibre-optic monitoring qualification of the electrical system of the liner occurred, and a complete set generate a local bending moment that,
In response, Subsea 7 and ITP and communication system. for always-on operation, as well as of mechanical and corrosion testing to if of sufficient amplitude and number of
InTerPipe (ITP) have been working the ability to isolate wire groupings. ensure that the product was completely cycles, could produce failure of the liner FEA model with fine meshing at the pipe end seal weld
closely with other technical partners The ETHP system was initially qualified These features provide clients with the sound post installation. and exposition of the carbon steel outer
to commercialise the Company’s in a passive mode, without heating freedom to adapt heating requirements pipe to the corrosive environment.
Electrically Trace Heated Pipe-in- elements. Proof of concept for the in response to a changing production Another key milestone reached in 2014
Pipe (ETHP) system, which has been complete ETHP system was then profile throughout the life-cycle of has been the qualification of the reeled First, a detailed Finite Element Analysis attached close to the seal weld as a
developed for installation with the reel- performed in collaboration with DNV. the field. It also provides a level of MLP for in-service conditions involving (FEA) model was created with a fine means of controlling the applied loads.
lay method. A further qualification program for field redundancy in the electrical system a combination of high pressure, high meshing at the pipe ends where the
specific designs is currently on-going design that is not achieved by temperature and lateral buckling. In seal welds are located. Loading steps At a nominal axial stress range at the
ETHP within the subsea environment and is expected to be complete within competing or established technology. instances where the conditions during corresponding to project specific seal weld of 592MPa, the average
the 2015 - 2016 timeframe. the operation of the pipeline drives HPHT operational conditions were then number of cycles to failure was above
Subsea 7 has an established track From the system level perspective the design requirements due to high applied using the Abaqus® software. 27,000 cycles, thus far exceeding the
record of PIP design, fabrication Meeting the challenges of the subsea Subsea 7’s ETHP system provides the pressure, temperature conditions, This allowed an extraction from the FEA number of anticipated shutdown cycles
and installation, with more than 40 world ability to actively vary the heat input to or complex seabed topography, of the local axial stress range at the during the design life.
projects executed to date by different the pipeline system, meaning that it is occurrences of free spans along the line seal weld for all the different shutdown
installation methods, including J-lay, In developing the ETHP solution, possible to narrow the range of arrival and lateral buckling may develop. scenarios. This programme has demonstrated the
S-lay, towing and, most recently, reel– Subsea 7 collaborated with clients temperature at the downstream end suitability of the reeled BuBi® pipe for
lay. The ETHP solution builds on this to take a holistic approach to the of the pipeline in a manner that is not In such conditions, there is a need In parallel, bespoke small scale fatigue operational conditions involving HPHT
track record, using existing technology, production system design. This process possible with other solutions. to demonstrate how the MLP is able test specimens were designed from a and lateral buckling without the need for
and standardised, market ready is managed by a dedicated ETHP to withstand the various thermal and production BuBi® pipe (a type of MLP more expensive clad pipe sections at
components where possible. Task Force within Subsea 7, a multi- The resulting product is a system that mechanical loading modes during its produced by Butting). The pipe material the buckle zones.
disciplinary team, capable of performing is capable of delivering a significant operation and throughout a series of full used was first subjected to cyclic
The PIP mechanical design is an early phase engineering and concept reduction in CAPEX requirements and partial shutdowns. pre-straining up to two per cent strain, Subsea 7 continues to maintain its
evolution of the Enhanced PIP system studies through to detailed design. compared to competing technologies, simulating a 14” diameter pipe lined unrivalled project experience using
previously developed in collaboration improved reliability and operational In particular, shutdowns are the source with alloy 625 installed by the Seven reeled MLP with the installation of
with ITP. This enhanced system The insights gained collaborating flexibility over the life cycle of the field. of various cyclic loadings, namely: Oceans reel-lay ship and then aged the 70km of Sapinhoá-Lula NE SCRs
combines high performance Izoflex™ with clients have been instrumental in pressure, temperature and axial strain at 250°C for one hour. The specimens completed successfully in 2014, and on
insulation with reduced pressure in the defining the functionality and operating Subsea 7’s ETHP technology lends itself cycling. These can lead to a type of were then tested in fatigue at the actual the Statoil Aasta Hansteen project (see
PIP annulus to deliver a market leading philosophy for the ETHP system. As well to a large variety of applications fatigue cycling usually referred to as stress range predicted by FEA. The pages 6 and 7) with the deployment
thermal performance. a result, the system provides industry and can enable or enhance cost- low cycle fatigue, in contrast to the high testing was conducted at an elevated of 16.5km of 12” reeled BuBi® pipe
leading thermal performance combined effective architectures for deepwater cycle fatigue characteristic of SCRs. temperature of 105°C using calibrated progressing well.
The technologies developed specifically with power requirements that are subsea developments. The high cycle fatigue loading has servo-hydraulic machines and special
for the ETHP system include an significantly reduced compared to already been qualified for reeled MLP high temperature strain gauges
electrical heating system and competing technologies. in earlier phases of the development

11
12
deep7 - 2015

Sapinhoá-Lula NE - a deepwater
technical triumph
by Ivan Cruz, Senior Product Manager and Daniel Karunakaran, Chief Engineer, Technical Authority analysis and the ready understanding
of a simple technology. However, the
In 2011 Subsea 7 was awarded a installation is more complex, requiring
milestone Subsea Umbilical, Riser and welding offshore and the stiffness
Flowline (SURF) contract by Petrobras would require a more complex
for four decoupled riser systems to operation to adjust the lengths to
be installed in the Sapinhoá-Lula NE ensure proper load distribution and
fields located in the Santos Basin, ensuring the buoy was level in its
offshore Brazil. It is the largest submerged position. Additionally the
engineering, procurement, installation top connector was more expensive.
and commissioning (EPIC) SURF
contract awarded to date in Brazil. The sheathed spiral strand wire
Front cover : the BSR in the field prior to installation has a long track record in other
The project’s technical focus was the Tether adjustments mooring systems and was found
installation of four very large 2,800Te to meet all the requirements for 27
submerged buoys approximately 250m The main requirement for successful Another equally important technical years of service life. The stretch
below the surface. The system was BSR mooring was to use tether issue which needed to be addressed is no excessive, but is sufficient
designed to accommodate 45 risers/ adjustments to stabilise and position was the submerged tether weight, to help minimise the effects of
umbilicals for each field in a small area in each buoy. The principal challenge which had the potential to minimise length measurement tolerances, is
a decoupled arrangement. Subsea 7’s associated with this work was the impact on negative buoyancy and comparatively easy to install offshore
scope was specifically twenty-seven the selection of an appropriate dimensions. Different materials for the including locking of the lines in the
3.9km steel catenary risers of which tether material, thereby helping to buoy mooring lines were considered connectors at the required point.
eighteen were 7.5-inch production lines, ensure that the axial stiffness was in some detail. The three options
three 9.5-inch water injection lines and The BSR buoy top side with guiding chutes, moonpool and flexible jumper installed with ACM preferred in order to balance the considered were: After considering all of these factors
six 8-inch gas injection lines. desired tension adjustment, and to it was concluded the SSW was the
Leg Platforms (TLPs), but using The combined result of all these keep neighbouring tethers closely • Polyester fibre ropes best option, for both long term service
Petrobras and its partners selected spiral strand cables and chains for innovations, some incremental and together while dealing with the • Steel tendons reliability and from an installation
this Buoy Supported Risers (BSR) installation simplicity and to achieve resulting from existing technologies, and initial slackening during fabrication • Sheathed spiral strand wires (SSW) point of view.
system as the most effective solution the necessary dynamic performance; others entirely new and breakthrough, and installation. Although steel
for the project. In order to meet the gave rise to the complete BSR system. air filled pipe is a commonly used The polyester lines offered the lightest The BSR solution – overcoming
system’s performance and installation • A tether based tensioning system The following provides in greater detail material for Tension Leg Platforms option. However, this material can deepwater challenges
requirements, various innovative capable of withstanding top angle profiles on the Angular Connection (TLPs), a moderated decrease in lead to stretching and the need for
technologies were required. These were: variations associated with the buoys Module (ACM), and developments in the axial stiffness was preferred, longer chain tails and operational Introducing new technology into
natural offsets and the potential tether design and materials for BSR thereby creating a simple top tension time to adjust the length. Additionally, complex offshore exploration and
• An efficient method to install length variations of the almost two mooring. between adjacent tethers and length there is a potential for long term production projects is always
corrosion resistant alloy (CRA) kilometres long tethers; adjustments. A significant increase creep under service load, which might challenging given the stringent
mechanically lined BuBi® pipe by the The development of the Angular in tendon stretch, applied while the pose a risk to the buoy’s dynamic requirements of safety and reliability,
reeled-lay installation method; • A bottom connector device to Connection Module (ACM) BSR was in vertical motion, would not performance. together with the inevitable
simplify connections to foundations. have been an acceptable approach constraints posed by commercial
• The development of the Angular The creation of the Angular because of the high possibility of The steel tendons have a stiffness of imperatives. Innovation in the
Connection Module (ACM). This Connection Module (ACM) proved misalignment and damage to the more than three times the SSWs. This upstream sector is frequently driven
unique engineering capability integral to the BSR system by system. is attractive for the theoretical in-situ by the need to secure access to
greatly simplified buoy hardware by connecting the flexible jumpers to the hydrocarbons from reservoirs in
minimising the number of connections pre-installed buoys. Because of the ever more challenging deepwater
Table 1 – Tether material comparison
and potential leak paths; large number of risers installed, the environments.
buoys can take up different positions. Potential tether materials
• A fit for purpose 400Te tension The ACM allows connections to be Tether type Sheathed Spiral Polyester Steel Pipe Sapinhoá-Lula NE, with reservoir
capable riser installation tool, allowing made at misaligned angles of up Strand Wire clusters in the Santos Basin proved
for the reliable deployment of 27 to 15°, reliably and safely, thereby to be an extreme example of such
Diameter (mm) 101.6 184.15 304.8 OD / 20.05 wall
SCRs; reducing offshore hook-up time. challenges. The innovative BSR
Air Weight (kg/m) 57.6 21.9 140.5 concept was a demonstration
• A state-of-the-art fracture mechanics Within the BSR system the Wet weight (kg/m) 45.2 5.5 65.7 of how the early engagement of
engineering assessment for plastically introduction of the ACM reduced Break Force (Te) 1178 1000 1009 many different companies and the
strained pipe joints made of alloy 625 fluid flow to a single interfacing point, eventual adoption of numerous new
Stiffness (MN) 1017 265 3710
welds; thereby saving cost and enhancing technologies, produced breakthrough
reliability by eliminating further Length (m) 1890 1890 1890 solutions in one of the world’s
Angular Connection
• A novel tethered tensioned mooring Module (ACM) potential leak paths. Long (Te) 400 400 400 toughest field environments.
system, similar to that for Tension Stretch (m) 7.3 28.90 2.0
13
14
deep7 - 2015

From airline pipe dream to


subsea inspection solution
by Bob Lasser, Imperium Inc., with John Rhodes and George Gair of Subsea 7

An ultrasound inspection technology continually explores ways to maximise technology incorporates a beamsplitter
used to examine the airframe of the effectiveness, efficiency and quality to collimate ultrasound in order to allow
the Boeing 787 Dreamliner is now in the delivery of its subsea inspection the lens to focus at multiple depths.
being used to test the boundaries of services. One new way in which
underwater inspection capabilities. efficiencies in underwater inspection The Acoustocam testing programme
Subsea 7’s Life of Field business can be introduced is through the use
teams have been looking at other of ultrasound technology. Imperium’s At the time of publication the camera Figure 4a Steel Plate Scan with Backwall
industries to source technologies Acoustocam is a real-time Cscan, high- is being tested in Aberdeen. In figures
and new approaches which can resolution, large field of view, ultrasound 1a and 1b Imperium’s pipe standard
yield benefits to the discipline of camera based on the company’s is shown with flat bottomed shapes
through-life support within the patented Digital Acoustic Video (DAV) milled into the inner wall. In figure 1a the
subsea environment. One such area technology. The Acoustocam has a Acoustocam is shown mounted on the
is the aerospace industry which is complete set of tools for weld and pipe with magnetic wheels for stability
now using state-of-the-art ultrasonic corrosion inspection including an A scan and positional information. Figure 3 V Notch Figure 4b Steel Plate Scan with V Notch area highlighted. Yellow thickness reading directly over notch area
imaging developed by US technology sensor for thickness measurements and
company, Imperium. off-line software for post processing.
Reducing in-water time and removing Figure 3 shows a V notch milled into The primary objective is to deliver
Founded in 1996, Imperium supplies specialist technicians and operators the back wall of the plate. The next one system that replaces the many
handheld ultrasonic devices to non- offers a significant saving to clients. Any images were taken with post processing devices currently in use, providing
destructive testing (NDT) professionals. improvement in inspection technology tool, the Imperium Analyzer. In figure high resolution data faster, with
Imperium’s range of cameras are that can reduce the time it takes to 4a a thickness reading of the back wall reduced reliance on skilled human
based on well-established technology perform these and other inspection is included in the scan. In figure 4b intervention.
and used widely within the aerospace tasks is of significant value. a thickness reading of the V notch is
industry. In 2013 it was selected by included with the scan. Note that on the
Boeing to be included in the Boeing 787 DAV technology is similar to that Figure 2a Pipe Standard Scan A-scan presentation in figure 4b the two
inspection procedure. used in a standard video camera. peaks form both legs of the V notch
As a video camera uses a flash, a are seen.
The cameras generate real-time two- lens, and an optical sensor, the DAV
dimensional images of subsurface uses an ultrasound source, a lens for In summary, preliminary results indicate
anomalies. Internal corrosion and cracks beamforming and a 120 row by 120 that the Imperium DAV technology
can be simply and quickly imaged column detector array for receiving can be translated from aerospace to
without extensive training, calibration and processing ultrasound. The DAV the subsea environment. The ease of
or equipment. use and clarity of imagery result in a
device that requires minimal training and
A simple setup procedure allows produces reliable, repeatable data that
Figure 2b Pipe Standard Scan
internal defects to be visualised, is easy to interpret.
providing instantaneous data on the
thickness and overall integrity of a Scans are shown in in figures 2a and
structure. The technique is based on 2b where multiple individual Cscan
optical practices, using a large area frames are stitched together into a
source of ultrasound, a beamsplitter, single large display. The pipe sample is
an acoustic lens set, and a two- of 0.300” wall thickness. In figure 2a the
dimensional imaging array. thickness of the back wall is shown with
Ascan presentation and in figure 2b the
The output of the patented approach thickness of the flat bottomed cross is
uses a real-time C-scan imager and the shown. Note the resolution and clarity of
output is extremely high resolution. Figure 1a Pipe STD with Acoustocam the stitched Cscan images.

Ultrasound technology in the subsea Another test sample is the 0.75” steel
world plate with a 5mm layer of polypropylene
placed on top. Polypropylene is one of
Subsea infrastructure is installed, the coating materials used by Subsea 7
often with little or no redundancy, in an and imaging through the coating is the
environment that is both challenging preferred process rather than removing
and expensive to work in. Within this the coating altogether in order to
challenging environment Subsea 7 Figure 1b Inner Wall FBHs perform the inspection.

15
16
deep7 - 2015

Global opportunities for


Pipeline Bundle technology Subsea installed large towhead structures and
incorporated elements of extant subsea
production of oil and gas projects
in the Arctic is considered more

Processing
processing infrastructure. technically challenging than in any
by Martin Goodlad, Strategic Technology Manager, Pipeline Bundles other environment so far.
The Total Jura Pipeline Bundle installed
Subsea 7 has designed, fabricated world. When one looks at other markets buoyancy would be used to make the by Sigbjørn Daasvatn, Strategic in 2008 incorporates two subsea Demanding offshore environmental
and installed Pipeline Bundles, or and regions, such as Brazil and the Bundle considerably lighter. Manager for Subsea Processing HIPPS units and cooling spools in loading conditions could potentially
towed pipeline production systems, move to 2000m+ water depths, and recoverable modules, allowing the influence the design and installation
for more than 35 years, with 75 the Gulf of Mexico with water depths Composites Pipeline Bundles offer one of the units to be recovered to the surface for of Pipeline Bundles with principal
Pipeline Bundles manufactured of 1000m, the difficulties of weight Weight reduction, greater design best platforms for the installation maintenance and repair. The BG Knarr areas of concern including
to date. and corrosion posed by deeper water integrity, fatigue resistance, of subsea processing facilities. The Bundle installed in 2014 incorporated Pipeline Bundle configurations,
becomes the principal concern for strengths and corrosion resistance ability to install large structures cooling spools at both ends of the thermal insulation, and
In recent years, Pipeline Bundles have Pipeline Bundle design. The deeper are all principal benefits offered by and complete all onshore testing Pipeline Bundle within the towheads, trenching requirements.
been accepted as a technically and the water, the more demands on the introducing composite materials in and commissioning of the systems along with diverless connectors. For
commercially attractive solution that collapse resistance of the carrier pipe Pipeline Bundles. Composites began significantly de-risks the installation. this project the Pipeline Bundle system
allows difficult fields to be successfully and the internal nitrogen pressures. life as a weight reduction measure, was designed as an integrated system,
developed. Bundle technology presents but in recent years the need for The pipeline section of a Bundle, whereby the cooling role of the cooling
significant potential for extending The greatest water depth for a Subsea 7 corrosion resistance has come to between the towheads and the spool was balanced with the insulation
existing facilities or opening up new Pipeline Bundle design to date is the fore. Cost reduction is also an towhead structures, can be used requirements of the pipeline sections
developments, and its global future 410m within BG’s Knarr development important issue as composites can be for the processing of hydrocarbons, in order to optimise the system and to
and prospects for further innovation are in Norway. It is expected that this can cheaper than many high performance thereby turning a Pipeline Bundle better support client requirements.
equally exciting. be extended in the future by use of metals, considering the whole project system into a processing facility. This
alternative buoyancy arrangements. cost. was demonstrated in a recent Cold The Jura and BG Knarr Towheads are
The technical benefits driving the Flow study for Statoil. The first phase the largest installed to date at 525te and
wider use of this technology are well At deeper water depths a Pipeline The increasing demands on materials of the R&D study has been completed 580te respectively. The new launchway
understood: Bundle will begin to take on a different to meet future technical requirements to demonstrate the further ability to design, installed at the Wester site in
look given the challenges posed by for risers, flowlines, spools and incorporate the subsea processing 2014, will allow towheads up to 700te to
• Highly-efficient insulation systems, greater water pressures and stability components such as stress joints is elements within the Pipeline Bundle be launched from the facility.
heated Pipeline Bundles using hot issues. Key to Bundle design in deep providing the impetus for Subsea 7 towheads.
water, or Electrical Trace-Heating. and ultra-deepwater will be the control to take a closer look at composite Arctic waters
of the bulk and weight. The adoption of applications in these more demanding The incorporation of Subsea processing
• Design/construction method allows composite materials will be increasingly environments, particularly in the within a Pipeline Bundle system is not It is well understood that
full system integration testing important to disminsh the effects of context of Pipeline Bundles and their new technology. Previously Subsea 7 the exploration and future
onshore allowing fast hook-up and corrosion. future use.
commissioning offshore; low stress
installation method by Controlled Subsea 7 presently has a target date Technical specifications to address
Depth Tow Method (CDTM) minimises of 2018 to incorporate composite the requirements associated with
stress and fatigue on internal flowlines within a Bundle. As a starting pressure, temperature, corrosion and A new way forward will be researched
flowlines. point Subsea 7 is looking to deploy fatigue are stretching the suitability of and specific requirements for stability
a composite water injection line as a established metallic and non–bonded of the Pipeline Bundle as a system
• Design of Pipeline Bundle cross- means to evaluate composite use on a flexible options. Composite solutions will be developed. This will involve
section/system allows expansion production line. for Pipeline Bundles include bonded close multidiscipline collaboration
at both ends, reducing build-up of composite thermoplastic pipe. between structures, bundles and
axial forces, reducing the need for Considerations for wider geotech and incorporate experimental
intermediate expansion spools, and Pipeline Bundle deployment Shallow waters testing as well as numerical and
allowing efficient design for High- around the world Pipeline Bundles have been installed detailed computer analysis.
Pressure, High-Temperature (HPHT) in shallow waters previously on
field developments. Deepwater Maersk Dan (42m) and Hess South Additionally the analysis will be
In deep and ultra-deep waters, a Arne (60m). In these water depths the benchmarked through the use of
• Pipeline Bundles eliminate Bundle could begin to look very on-bottom stability is crucial due to ‘as installed’ measured data from
requirements for specialised much like a Hybrid Riser Tower (HRT) the environmental effects. This has Pipeline Bundle systems. This
installation vessels (reel-lay, S-Lay, with a central core or buoyancy pipe previously been achieved through work will reduce the reliance on
J-Lay, and heavy lift) by using readily incorporated into the design. In such either filling the pipeline bundle secondary stability mitigation
available vessels, and incorporating environments Pipeline Bundles would annulus with heavy grout/barite slurry for Pipeline Bundles in
subsea structures within the towed need to be able to resist greater or partial rock dump. The on-bottom shallow water and open
Pipeline Bundle System. collapse pressures in the water. The stability requirements for the Pipeline up further market
current design does not allow the Bundle system are currently assessed opportunities.
Today, Subsea 7 has begun the work structure to be thick enough, therefore based on separate design codes for
to migrate Pipeline Bundles away from alternative design methods, such pipelines and structures.
their proving ground origins in the North as solid buoyancy and temporary
Sea, to other challenging parts of the

17
18
deep7 - 2015

Tackling hidden challenges of Building for the future


the Arctic environment by Stuart Smith, Vice President, Asset Development
• The 7,000Te underdeck carousel Seven Kestrel
by Dwayne Hopkins, Research & Development Engineer gives unrivalled capability to lay the
longest umbilicals and power cables Subsea 7’s latest DSV, the Seven
A collaboration study between Task 3: Economical analysis of obstacle for the Arctic. It can have associated with long step-outs, Kestrel, left the security of dry-dock
Subsea 7 and C-CORE, an single trench multi-pipe in terms a detrimental effect on the seabed power from shore, or developments and floated out into the harbour at
independent not-for-profit R&D of technology readiness, technical by scouring the sea floor up to with seabed processing Hyundai Heavy Industries yard on
corporation that creates value in issues, operational and life of field depression depths of in excess of 15 February 2015. She is now at
the private and public sectors by costs. 5 metres. These unique ice loading The Seven Arctic benefits from • The highly versatile and capable an advanced state of construction
undertaking applied research and conditions could potentially influence a 900t offshore crane rope luffing knuckle boom crane is with all main machinery and main
development, has looked at the Task 4: Results, discussions, and the design and installation of ideally suited to a range of tasks components of the dive system such
potential for Pipeline Bundle burial conclusions: offshore pipelines. Areas of concern Seven Arctic including installation of increasingly as the launch and recovery system,
through a six-month desktop study. for offshore pipelines include, but heavy manifolds and other seabed saturation dive chambers, gas
• What are the existing gaps in are not limited to: Pipeline Bundle The Seven Arctic Heavy Construction structures; very long spool pieces storage system and environmental
It is certain that in future Arctic knowledge and technologies? configurations, thermal insulation, Vessel is now rapidly taking shape and other equipment requiring high control units already located on
developments, especially in Alaska • What is the best practice for the and trenching requirements. in dry-dock at Hyundai Heavy lift heights; in addition to more board.
and the Beaufort Sea, there will be Grand Banks based on the available Industries. routine lifts from anywhere on the
a major requirement to bury Pipeline technologies and knowledge? Alaskan Beaufort Sea operations deck Work is continuing to progress well with
Bundles in order to avoid interaction • Determine future studies required. have helped establish a baseline Meanwhile at Huismans factory the the focus now changing to aspects
and damage from icebergs. The for future Arctic development with 600Te VLS and the 900Te crane is • Large strengthened deck area and such as finalising the electric cable
study will look at the challenges Objectives buried pipelines in a piggy-back progressing well on schedule. vessel stability suitable for general pulling, hook up of the dive system and
and benefits of transferring this Since the burial of pipelines in configuration in near shore oil project load of around 4,500Te at 5m outfit of the accommodation, and is all
technology to the Newfoundland the Grand Banks is a serious fields. Although installed during When delivered in 2016 the Seven above deck on schedule for operations in
offshore environment, which is consideration to protect Pipeline the winter season by trenching the Arctic will allow Subsea 7 to effectively early 2016.
now seen as a test bed for subsea Bundles from iceberg scour, it may seabed through the ice, the Alaskan execute ever more complex projects • Suite of auxiliary cranes for effective
technologies planned for use in be beneficial to place multiple experience has shown the viability of for our clients. The main operational multiple deployments to the seabed The saturation dive system is an 18 man
harsher and more remote locations pipelines and umbilical lines within using Pipeline Bundle technology as a differentiators include the following;- and manoeuvring complex systems system rated to 300m incorporating
within the Arctic region. a single trench. In this case the use solution for buried pipelines in Arctic / for hook-up at depth. twin bells, twin hyperbaric life boats,
of a Pipeline Bundle could prove to Sub-Arctic regions. • The 600Te VLS is amongst the largest two six man chambers, two three man
The study will help Subsea 7 bring be beneficial. To evaluate the use of in the world and will allow laying The crane was recognised as the chambers, four wet-pots, two TUP
this technology to the Canadian Pipeline Bundles for this purpose, this Newfoundland and Labrador of large diameter flexible pipes in Innovation of the Year at the annual chambers and a semi-automatic control
market as well as enhance the study will investigate their efficiency in provides an ideal location to support deepwater Offshore Support Journal conference. system. The main system is laid out
Company’s Pipeline Bundle portfolio. terms of trench construction, backfill, professionals working in and learning ergonomically on one deck with side
Feasibility and numerical calculations required U-values, field inspection, about the Arctic. Iceberg Alley, an mating bells to maximise efficiency.
will help determine the benefits and maintenance costs, and any other area stretching from the coast of
challenges of Pipeline Bundle burial. additional criteria identified during the Labrador to the northeast coast of the She has been specifically designed for
course of the study. island of Newfoundland, has led to North Sea operations as a capable and
Pipeline Bundle burial will depend the creation of world class research cost effective unit and complimentary
on regional geotechnical properties Rationale and facilities. with other DSVs and construction
that influence thermal conductive and Developments of offshore oil fields vessels in Subsea 7’s fleet.
methods of burial. in Arctic and Subarctic environments
present unique and challenging
The study will be carried out through obstacles that, on their own or in
four principals: a combination, create the need for
unique oil and gas development One of six HiMSEN 9H32 engines being installed
Task 1: Investigate the type of solutions. Some of these obstacles
required trench for Pipeline Bundle include: Main crane
burial and optimisation. Investigation • Type; Huisman Rope luffing Knuckle boom crane; hook travel 3,000m
will use lessons learned from previous • Sensitive environment • 300Te at 45m radius; 600Te at 30m radius; 900Te at 20m radius
C-CORE buried pipeline studies, • Remote operations • 40Te whip hoist; maximum radius 60m
The Seven Kestrel photographed soon after its float
including the Pipeline Response to Ice • Insufficient nearby shore This has also proved to be the • High lift mode; maximum 50m under-hook clearance ; maximum Radius 52m out event in February 2015
Gouging (PIRAM) study. infrastructure case with Subsea 7’s team leading • Hoisting speed single fall; 40m/min full load; 80m/min reduced load
• Extreme low air temperatures investigations into the deployment • Hoisting speed twin falls 20m/min on full load; 40m/min at reduced Load
Task 2: A study on benefits and • Short seasons for surface operations of Pipeline Bundles. Subsea 7 has • Active Heave compensation; operational stroke 8m for single line
drawbacks of buried Pipeline • Presence of ice in various forms been able to tap into local skills • Deep water lowering; wire rope spacer and deep water block
Bundles in terms of construction • Permafrost and hydrates and knowledge and draw upon a
Auxiliary Cranes
considerations, leak strategies, heat unique environment which shares
• Aux 1; 100Te at 15m radius; AHC; hook travel 3,000m Subsea 7’s new DSV, the Seven Kestrel, will feature an
18-man twin bell saturation diving system
recovery and flow assurance. Of the aforementioned challenges, many features which are common to • Aux 2; removable; 25Te at 16m radius; AHC; hook travel 3,000m
the presence of ice is a formidable numerous Arctic locations.

19
www.subsea7.com
deep7 2015
© Subsea 7, 2015. Information correct at time of going to press.

You might also like