Professional Documents
Culture Documents
S.
Reference Comments Responses to comments
No.
1 General Comments Each table and figure must be cited in the text with their Comment accepted, and the tables and
specific numbers and not using expressions such as “in figures are cited accordingly in the final
the figure below” or “in the table above.” report.
The 1995 EBCS volumes for foundations design and Comment accepted. EBCS EN 1997-1
seismic design (EBCS 7 -1995 and EBCS 8 – 1995) are & 2:2013 is now referred.
cited in the report. These codes are no more usable.
Accordingly, more pertinent and recent documents must
be employed.
The report identifies swampy/marshy sections at two Comment accepted, and a sketch
sections: on both sides of Km 7+600 to Km 8+400 and on (typical section) is included in this final
the LHS of Km 9+180 +9+360 and acknowledges the report (Appendix 3).
need for special treatment. However, the suggested
remedy needs clarity and should be supported using a
sketch showing the various layers stated in the
appropriate section (free-draining replacement to
subgrade level) with unambiguous terms.
The current rainy season prevails the existence of more Comment accepted. After having a
flooded plains and swampy section in addition to recent site visit, additional sections are
mentioned in the geotechnical report, and hence more included in this final report.
investigation must be done to identify those.
No slides and slumps are reported over the entire project
alignment. Neither are hazards anticipated from faults
and lineaments, according to the report.
The summary of soil test data provided in Table 3-1
shows that the material encountered over the great
majority of the stretch of Km 7+000 to Km 21+190
exhibited consistently high plasticity (LL>60; PI>30),
rather low strength (CBR of 1 to 2) and too large swelling
(5 to 10%). It is consistently classified as A-7-5(20)
according to the AASHTO classification system. The
material is thus characterized as unsuitable as a
S.
Reference Comments Responses to comments
No.
subgrade material. An exception to this is the short
section from Km 10+500 to Km 11+000, which is
described as a granular material classified as A-2-7(1).
Employer’s Requirement of the project
The summary further shows that a complete investigation states: ‘Collect Samples for CBR-value
along the route (including CBR and swell test) was (three point CBR) and moisture-density
conducted only at an interval of 1km. Unless, in this relationship at every 1km for pavement
particular case, the Contractor believes no value will be design.’ In addition, ERA Site
added by a more detailed investigation scheme, Investigation Manual – 2013 requires to
standards and manuals require that investigation at this conduct CBR and Swell tests at 1 km
stage be conducted at a 0.5km interval. interval.
It is stated in the draft report that, as
In regards to the treatment of the unsuitable subgrade per the Employer’s Requirement, the
material, the stretch is subdivided into shorter sections expansive soil stretches shall be
with one of the following three treatment methods treated in line with ERA Standard
recommended to each one (Table 3-2): Technical Specification, 2013, Section
Excavate and replace full road width for a 4106. The treatment methods have
minimum earthwork cover of 1.0m; also been incorporated in the draft
Excavate and replace full road width to a depth of report clearly.
0.6m;
Excavate and replace part of the width that is not
sealed to a depth of 0.6m.
The existence of only two bridge sites (at Km It Is stated in the draft report on the
S.
Reference Comments Responses to comments
No.
10+130 and Km 18+310) is described on Page same paragraph that ‘in addition to
25, whereas three sites are listed and briefly a newly designed pedestrian bridge
described in Table 5-2 on Page 27. … there are two major drainage
structures … found at 10+130 …
and … at 18+310.’ Thus, the
statement on the paragraph and
the table are consistent.
The foundation soil descriptions in Column 3 of It is indicated in the report that only
Table 5-2 appear suddenly without prior preliminary visual assessment has
description of what type of investigation was been conducted on locations of
carried out at each site. major drainage structures locations,
and together with geological map,
site characterization has been
conducted for the foundation soil
description.
In all three cases, it is stated in the table that an The preliminary thickness (from
upper soil layer overlies a basaltic rock formation visual assessment of the area and
without indicating the thickness of the soil layer. geological map) of the layers has
been indicated in column 5 of Table
5-2 of the draft report.
The two sites at Km 10+130 and Km 18+310 that Only preliminary visual assessment
are almost 8 km apart are described identically was conducted on the locations of
(word by word) casting doubt on reliability. major structures, and thus, the
materials will be described properly
during detailed investigation.
With regard to minor drainage structures, 10 It is clearly indicated in Table 5-3
locations are identified in Table 5-3. But it is not (column 6), Tables 5-8 to 5-13 and
clear whether DCP has been conducted or would Appendix 2 (DCP Data) that DCP
be conducted in the future (see 2nd paragraph on has been conducted in all minor
Page 28 that is suggestive of an investigation yet drainage (Box/Slab culvert)
to be investigated). structure locations. The statement
on the indicated paragraph is
rectified.
The use of the empirical relation given on Page Comment accepted, and the
28 to estimate the bearing capacity is not Contractor has tried to elaborate it
sufficiently described and demonstrated. This sufficiently in this final report.
S.
Reference Comments Responses to comments
No.
doubt is further exacerbated by rather low values
of the bearing capacity at some depths, as low as
30 kPa (see Tables 5-8 to 5-13).
In general, the investigation at the sites of the drainage
structures, especially the major ones, must be
investigated much more carefully, and the data analyzed
and interpreted by a well-qualified and experienced
geotechnical engineer. It is believed that this is also in
the best interest of the DB Contractor.