PROBLEM INSTRUCTIONS

1.       Perform a Forward Pass and a Backward Pass of the network diagram above

2.       Which Activities has the same Early Finish as they have Late Finish?

Note: The project starts on Day “0”

REFERENCE: PMI Training


CRITICAL PATH METHOD SOLUTION PROBLEM
Early Start Duration Early Finish

Task Name

Late Start Slack Late Finsh 13 2 15 15 2 17


D E
31 18 33 33 18 35

0 3 3 3 4 7 7 6 13 13 4 17
A B C F 29 6 35
12 12 15 15 12 19 19 12 25 25 12 29 G
29 0 35

0 6 6 6 9 15 15 8 23 23 6 29
H I J K
0 0 6 6 0 15 15 0 23 23 0 29 29 4 33
N
31 2 35
15 9 24 24 3 27
L M
19 4 28 28 4 31

Answer to Question 2
Each of activities H, I, J,K, and G have the same Early Finish and Late Finish dates