Feed-in Tariff Deployment Caps Monthly report for February 2016

Please be aware the following tables do not consist of real-time information. They are updated on a monthly basis. The information for each tariff period
is verified once the tariff period has ended, which means these figures may change when the report for the entire tariff period is published.

Deployment Caps Figures

Table 1 shows the capacity deployed1 per technology and capacity band in the tariff period 08 February – 31 March 2016.

Table 1 – Deployment progress for February 2016


Tariff Period 08 February – 31 March 2016

Capacity Date and time of last Number of Number of Number of


Cap limit Cap installation to qualify installations Full ROOFIT Preliminary ROOFIT
Deployment band deployed
(MW) Reached? for the cap Applications Applications
(MW)1
PV < 10kW 48.4 9.601 No N/A 4030 N/A N/A
PV 10-50kW 16.5 2.636 No N/A 97 N/A N/A
PV >50kW 14.1 7.938 No N/A 36 18 18
PV Standalone 5 9.119 Yes 08/02/2016 01:15:11.460 140 1 10
Wind <50kW 5.6 0 No N/A 0 N/A N/A
Wind 50-100kW 0.3 0.833 Yes 08/02/2016 00:15:14.430 9 0 9
Wind 100-1500kW 6.8 22.230 Yes 08/02/2016 00:18:34.297 30 0 30
Wind 1500kW-5000kW 5 0 No N/A 0 0 0
Hydro 0-100kW 1.1 0.952 No N/A 14 0 14
Hydro 100kW-5000kW 6.1 1.175 No N/A 3 0 3
AD (All) 5.800 17.653 Yes 08/02/2016 00:15:28.153 24 2 22
Accurate as at 00:00:00.000 on 01 March 2016

1
For the purposes of this table, “capacity deployed” includes the capacity of MCS installations and ROOFIT applications for preliminary and full accreditation that have
been counted towards the relevant cap in the tariff period.
Indicative status of deployment caps in future tariff periods

Table 2 shows the capacity limits for each deployment cap as provided for in the Feed-in Tariffs Order 2012.

Table 2- FIT Deployment Cap Limits (kW) (08 February 2016 – 31 March 2018)
2016 2017 2018
Deployment Band
TP1 TP2 TP3 TP4 TP1 TP2 TP3 TP4 TP1
PV <=10kW 48400 49600 50600 51700 52800 53800 54200 55900 57000
10 - 50kW 16500 17000 17400 17800 18200 18600 18700 19400 19800
>50kW 14100 14500 14900 15400 15800 16200 16400 17100 17600
Stand alone 5000 5000 5000 5000 5000 5000 5000 5000 5000
Wind <50kW 5600 5600 5500 5500 5600 5500 5500 5400 5500
50-100kW 300 300 300 300 300 300 300 300 300
100-1500kW 6800 6700 6600 6500 6400 6300 6200 6100 6100
>1500kW 5000 5000 5000 5000 5000 5000 5000 5000 5000
Hydro <100kw 1100 1100 1200 1200 1200 1300 1300 1300 1300
Hydro >100kW 6100 6200 6300 6300 6400 6400 6400 6400 6400
AD All 5800 5000 5000 5000 5000 5000 5000 5000 5000

Table 3 provides an indication of the available capacity under each cap based on the deployment figures currently available. This
information is an indicative estimate only; each month this data will be refreshed.

Table 3- Indicative capacity available in FIT Deployment Caps (kW) (08 February 2016 – 31 March 2018)
2016 2017 2018
Deployment Band
TP1 TP2 TP3 TP4 TP1 TP2 TP3 TP4 TP1
PV <=10kW 38799.42 49600 50600 51700 52800 53800 54200 55900 57000
10 - 50kW 13863.91 17000 17400 17800 18200 18600 18700 19400 19800
>50kW 6162.33 14500 14900 15400 15800 16200 16400 17100 17600
Stand alone 0 880.82 5000 5000 5000 5000 5000 5000 5000
Wind <50kW 5600 5600 5500 5500 5600 5500 5500 5400 5500
50-100kW 0 0 67 300 300 300 300 300 300
100-1500kW 0 0 0 4370 6400 6300 6200 6100 6100
>1500kW 5000 5000 5000 5000 5000 5000 5000 5000 5000
Hydro <100kw 148 1100 1200 1200 1200 1300 1300 1300 1300
Hydro >100kW 4925 6200 6300 6300 6400 6400 6400 6400 6400
AD All 0 0 0 3147 5000 5000 5000 5000 5000