You are on page 1of 2

Sprayed seals – pre-spraying

to correct surface texture


work tips pavement work tips — no. 36
INTRODUCTION Binder application
January 2003

rates
Key Summary
Pre-spraying is a technique developed for:
• Resealing of roads where different binder The rate of
This issue of
application rates are required to compensate application of pre- 'pavement work tips'
for variations in texture in different areas of sprayed binder will provides a guide to
the existing surface. It is particularly used depend on differences pre-spraying of road
where there is a significant difference in texture in surface texture surfaces to
between wheel-paths and areas outside the allowances, traffic compensate for
wheel-paths. volume, pavement variations in surface
crossfall and alignment. texture and binder
• Sealing or resealing with geotextile fabrics
It is generally the application rates
where additional binder is required on outer
difference between the
edges or along centrelines and between wheel-
lower rate of
paths.
application designed for the low texture condition
• Pre-spraying of shoulders to enable the (usually the wheel-paths) and that required for the
pavement

shoulder and adjoining traffic lane to be coarse textured areas (outside the wheel-paths).
sprayed without a longitudinal join in the Rates of application are typically in the range of
finished surface. 0.3 to 0.5 L/m2.
Pre-spraying is done without cover aggregate Spraying of rates less than 0.3 L/m2 is generally
and is usually applied immediately ahead of the neither necessary nor practicable.
second binder application.
Pre-spraying of rates greater than 0.5 L/m2 in
traffic lanes is generally undesirable, as excess
SURFACE CORRECTION PRIOR TO binder may migrate into critical areas. Where the
RESEALING required rate exceeds 0.5 L/m2, consideration
General should be given to an alternative treatment.
Binder application rates for reseals are usually Alternative treatments include use of a smaller
designed for the wheel-path condition and can aggregate as a short-term corrective treatment,
generally tolerate a variation in surface texture treatment of excess binder in wheel-paths, or
allowances of up to about 0.2 L/m2. some other surfacing type such as slurry surfacing
Greater variation requires consideration of or hot mix asphalt (See also Work Tip No 7 –
alternative treatments or the use of variable Treatment of bleeding or flushed surfaces).
application rates. Some sprayers enable variable
application rates to be sprayed using complex Binder type
twin-bar systems. Pre-spraying should be done with the same
The pre-spraying technique can be readily binder type as that intended for the reseal.
applied using conventional equipment. continued on reverse

AUSTROADS

Figure 1. Variable pavement texture prior to treatment

pavement work tips is produced by AUSTROADS in conjunction with AAPA


Sprayed seals – pre-spraying to correct surface For more
information on any
texture – page 2 of the construction
practices discussed
Procedure procedures and may differ by a greater amount in "pavement work
than that applicable to surface correction within tips", please contact
Wheel-path areas must be carefully noted, either your local
particularly on winding alignments where traffic traffic lanes.
AUSTROADS
may wander across the pavement. It is important The difference between the two rates becomes Pavement Reference
to keep pre-spraying clear of actual wheel-path the pre-spray rate. For example: Group
areas to reduce risk of subsequent bleeding. This Shoulder design binder application rate = 2.2 L/m2 representative or
risk increases at higher traffic volumes and Traffic lane design binder application rate = 1.5 L/m2
AAPA —
increased numbers of heavy vehicles. tel (03) 9853 3595;
Difference in design rates = 2.2 – 1.5 = 0.7 L/m2 fax (03) 9853 3484;
The width and limits of areas to be pre-sprayed e-mail:
should be clearly marked for guidance of sprayer Procedure info@aapa.asn.au
driver and operator, allowing a suitable margin 1. Spray the shoulder only at a rate of application A complete list of
for small variations in sprayer alignment. equal to the difference in design rates (0.7 L/ "pavement work
Pre-spraying may not be practicable near m2 in above example). tips" issues is
intersections and turning lanes, and alternative 2. Spray the shoulder and traffic lane in a single available on AAPA's
treatments may need to be considered. web site:
width at the lower application rate (1.5 L/m2
www.aapa.asn.au
Where light rates of application are involved, in above example).
Issues may be
smaller spraying nozzles, e.g. AN 9, will reduce 3. Spread and roll aggregate as normal. downloaded using
the need for high sprayer forward speeds and assist Adobe Acrobat
in uniformity of application. Pre- spraying of shoulder on previous day Reader. Copies may
Two sprayers are generally required to enable Depending on job size, traffic volume, weather also be obtained
pre-spraying immediately ahead of main spray and site conditions, it may be feasible to undertake from AAPA.
application and avoid any risks involved in traffic pre-spraying of shoulders on the preceding Material may be
driving on pre-sprayed areas. afternoon. freely reproduced
To compensate for additional binder cooling, providing the source
is acknowledged.
PRE-SPRAYING OF SHOULDERS the pre-spray binder should be cut back with 2
parts (or 2%) more cutter oil than that otherwise This edition was
General prepared by
required. The total amount will depend upon
Pre-spraying of shoulders in conjunction with by John Rebbechi
aggregate type and condition and the prevailing
sealing of the adjoining traffic lane may be used and Walter Holtrop
traffic and weather conditions and should be not in consultation with
where the aggregates are of the same size and
less than 4 parts (4%). members of the
type and it is desired to reduce the number of
longitudinal joins and improve efficiency of The second application rate should be cut back National
as normal. The heat of the binder in the second Bituminous
spraying and spreading operations. Surfacings Research
application is generally adequate to combine with
Binder Application Rates Group.
the pre-sprayed binder for effective embedment
In this case the design binder application rates of aggregate provided that the binder is cut back
for the shoulder and the traffic lane are as recommended above and the pre-sprayed
determined separately using standard design binder has not been damaged by traffic.

Figure 2 Applying pre-spray Figure 3 Applying final spray

Austroads and AAPA believe this publication to be correct at the time of printing and do not accept responsibility for any consequences arising from the use of the information
herein. Readers should rely on their own skill and judgement to apply information to particular issues.

You might also like