Professional Documents
Culture Documents
Operational Feasibility
Legal Feasibility
Feasibility Study
Schedule Feasibility
Conceptual Study
Economical Feasibility
Design Basis
Pre Feed
Product Specification
Front End Engineering PFD , Process Equipment List
Preliminaries Engg Drw Heat & Mass Balance
Process Simulation HAZOP
FEED Equipment GAD , Cost Estimation
PEP , Operational Philosophy
Line List
Inst & Valve Data sheet
Engineering
Detail Engg Drw. Bulk MTO
Issue Code 1 & Code 2 Drws Final P&ID
Model Review Isometric & Spool Fab Drw
Detail Engineering Structure Drw
Civil Drw
PIB & Sub Station Drw
E&I Cable scheduling & Drw
Material Purchase Order
Procurement Bulk Procurement Equipment Purchase Order
Service ProcuremenServices Work Order
Earth Work Area Grading
Foundations
Super Structures Pipe Racks
Civil Paving
Fabrication Spool Fabrication
Structural Fabrication
Erection Structure
Equipment
Construction
Mechanical Piping
Cable Tray
Sub Station
PIB
Electrical & Instrumentation
Switch Gear
Painting
Insulation
Fire Proofing
Testing Hydro testing
Pneumatic Testing
Flushing Steam Blowing
Pre Commissioning Air Blowing
Instrument Testing Instrument Testing Dry Loop and Wet Loop Checking
Loop Checking Charging of Substation and Testing
Pre Commissioning
op Checking
n and Testing
SL NO MILESTONE DESCRIPTION PLANNED FORECAST ACTUAL VARRIANCE
BASIC ENGINEERING
REMARKS