SECTION Nº PÁG.
1. OBJECTIVE 3
2. SCOPE 3
3. SPECIFICATION 3
1. OBJECTIVE
The purpose of this document is to cover the minimum technical requirement for Three-
Phase 13.8 - 0.480 kV, 2.5 MVA Power Oil Transformer, required for Anaco Project-
Operaciones Centralizadas Campo Santa Rosa.
2. SCOPE
The document is an addendum to the Engineering specification “Technical
Specification for Liquid Immerse Transformer for 250 HP and larger, according to
PDVSA N 276, rev 0 and PIP ELSTR01. Which is the specification to be applied to this
project.
3. SPECIFICATION
The following paragraph of PDVSA N 276, rev 0 volume 4-I, shall be modified, Deleted,
Updated and/or clarified as indicated below. PDVSA manual is an attachment to this
specification: