Professional Documents
Culture Documents
The Global Software Team: Jugaad Needed: Case Analysis OF
The Global Software Team: Jugaad Needed: Case Analysis OF
OF
SUBMITTED BY
SECTION: H GROUP: 1
PREETAM KUMAR AGRAWAL (2013IPM128)
JABEEN SHAIKH (2012IPM050)
SHIVAM KUMAR ARYA (2013IPM122)
USHLEEN KAUR (2016PGP449)
VAIBHAV GUPTA (2016PGP415)
KHAMBE AMEY SUNIL (2016PGP173)
ABHISHEK VERMA (2016PGP012)
EXECUTIVE SUMMARY
Mr. Jim Notrika has been appointed as Software Center Manager of Global
Networks Company’s newly established center in Mumbai. Leading a global team
based in Boston and Mumbai, Mr. Notrika has to deliver orders of a law company
in time. But only months into its first major project, the team was struggling to
meet deadlines. Blame was being passed in both directions, and when three
talented engineers in Mumbai quit, Notrika makes an emergency trip to Mumbai
to better understand the problem. Notrika has to ensure timely delivery of orders
and rebuilding relationship between the teams. Mr. Notrika has the following set
of options: hiring a new manager at Mumbai, swapping team members from both
the teams, setting up a back-up team in Boston and frequent written
communication and video conferencing. Out of the options, frequent
communication through mails and video conference meetings was found to be
the most optimal solution.
1
TABLE OF CONTENTS
1. SITUATION ANALYSIS
2. PROBLEM DEFINITION
3. OPTIONS
4. CRITERIA FOR EVALUATION
5. EVALUATION OF OPTIONS
6. RECOMMENDATIONS
7. ACTION PLAN AND IMPLEMENTATION
8. CONTINGENCY PLAN
2
SITUATION ANALYSIS
As illustrated in the article ‘The Global Software Team: Jugaad Needed’ ,2015
Mr. Jim Notrika has been appointed as Software Center Manager of Global
Networks Company’s newly established center in Mumbai. He is responsible for
leading a global team, one in Boston and other in Mumbai. Boston team is mainly
involved in client engagement. Mumbai team, on the other hand, is responsible
for technical support for the projects because Mr. Notrika felt that software
engineers in India were more qualified than those working in Boston. While
working on the first project for a law firm, certain problems occurred like missing
out on deliverable deadlines and blaming each other for the same, thus,
hampering the relationship between the two teams. But, the resignation of three
skilled Mumbai engineers prompted the intervention of Mr. Notrika as he flew
down to Mumbai to analyze the situation.
PROBLEM DEFINITION
How does Mr. Notrika rebuild the relationship between the two teams and deliver
the project deliverables on time?
OPTIONS
3
EVALUATION OF OPTIONS
4
them. Thus, effective communication takes place and global team conflicts can
be reduced. It is a cost effective measure and also give Mr. Notrika to interact
with both the teams at the same time.
CONTINGENCY PLAN
To increase the bonding of the team in the long term, the team building activities
and cross cultural activities can be undertaken. Thus, ensuring employee
retention and satisfaction in the long term.