MRT Underground Works Report

Cergas Setia Construction SDN BHD was inspecting a rectification crane at the Kampung Baru North Station site of the Mass Rapid Transit project connecting Sungai Buloh, Serdang, and Putrajaya. The two-page report documented the inspection date, items inspected, remarks on their condition rated as low risk, and plans for any needed rectification work to be completed by a named employee.

Uploaded by

aizuddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views2 pages

MRT Underground Works Report

Cergas Setia Construction SDN BHD was inspecting a rectification crane at the Kampung Baru North Station site of the Mass Rapid Transit project connecting Sungai Buloh, Serdang, and Putrajaya. The two-page report documented the inspection date, items inspected, remarks on their condition rated as low risk, and plans for any needed rectification work to be completed by a named employee.

Uploaded by

aizuddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

CERGAS SETIA CONSTRUCTION SDN BHD

PROJEK MASS RAPID TRANSIT LEMBAH KELANG – JAJARAN SUNGAI BULOH – SERDANG –
PUTRAJAYA (SSP) UNDERGROUND WORKS

Cergas Setia Construction SDN BHD


Rectification Crane Report

DATE OF
*DOC / NO. KBNS/CSC/001
INSPECTION

DATE OF ISSUE

SITE : KAMPUNG BARU NORTH STATION


Issued By : Mathan Raj

Remarks Action
No Description Evidence Taken
s
(Date)

Page 1 of 2
CERGAS SETIA CONSTRUCTION SDN BHD
PROJEK MASS RAPID TRANSIT LEMBAH KELANG – JAJARAN SUNGAI BULOH – SERDANG –
PUTRAJAYA (SSP) UNDERGROUND WORKS

LOW

Remarks :

Rectification by,

_______________________
(Position)
Name :
Date :

Page 2 of 2