You are on page 1of 15

Journal of Cleaner Production 15 (2007) 203e217

www.elsevier.com/locate/jclepro

GIS and rural electricity planning in Uganda


Elizabeth Kaijuka
IT Power (UK) Uganda Office, Plot 7B, Innovations House, Acacia Avenue, PO Box 10631, Kampala, Uganda
Received 6 July 2005; accepted 30 November 2005
Available online 18 May 2006

Abstract

Sustainable development is literally fuelled by the energy sector. In Uganda, the electricity sector has experienced dramatic market liberation
in recent years. This reform was centred around the unbundling of the main government utility, Uganda Electricity Board (UEB), a monopoly
divided into three companies created to introduce competition into the market. Market reform has also led to the creation of a regulatory body
and a rural electrification fund with the aim of subsidising rural electricity investments. Through a multi-sectoral programme financed by the
World Bank and the Global Environment Facility (GEF), the Ministry of Energy is developing a Rural Electrification Master Plan to provide
a more systematic tool for rural electricity investments. Unlike previous approaches, this plan is demand driven. This paper discusses the use of
Geographic Information Systems (GIS) in the planning process for rural electrification. The aim is to identify patterns of demand and priority
areas for investment. By creating a demand-side scenario, electricity can then be supplied to targeted areas. A cross-sectoral view is taken to
examine the energy demand patterns using physical data and available country statistics, incorporated into a GIS master database. Based on geo-
referenced data of population and existing infrastructure, the initial priority demand-side sectors targeted are education and health. An energy
benefit point system is then applied to each sector based on local conditions and needs assessments. Their aggregated points then provide an
indicator of energy demand distribution for electricity planning at district level. As a result of this preliminary work, specific areas could
then be targeted for investment and optimised supply systems could be designed, which include off-grid renewable energy plants such as
small-scale hydropower schemes.
Ó 2006 Elsevier Ltd. All rights reserved.

Keywords: Uganda; GIS; Electricity planning

1. Introduction experience shows that many projects will only last as long
as their financing does. In the case of Uganda, funds usually
The pace of rural electrification over much of the developing flow, with strings attached, from the donor or lender institution
world is painfully slow, and Uganda is no exception. This comes to the receiving or borrowing government body who, in turn,
as no surprise since rural communities not only have low popu- will subsidise the utility company and then finally to the con-
lation densities, but they are often the poorest, making private sumer who will foot the bill. The whole operation needs to be
sector investment unattractive due to the high capital and oper- financially profitable in the long-term in order to be ultimately
ating costs. Attracting investors for rural electrification projects, sustainable, and so financial viability is therefore one of the
especially in politically unstable less developing countries first priorities for rural electrification projects. Although
(LDCs) is therefore the overriding challenge. necessity is the mother of invention, scarce resources do not
Typically, in a LDC like Uganda, before even arriving at leave any room for unaffordable options, however innovative
a technological solution, the financial and economic costs first they may be. So before any new and renewable energy
have to be justified. New innovative technologies come after technologies can be adopted in rural Uganda, a host of cost-
cost considerations since the means justify the end, and benefit decisions have to precede the final technology selec-
tion, which must also be the least-cost option.
The planning process first requires a defined ‘Rural Electri-
E-mail address: elizabeth.kaijuka@itpowergroup.com fication Criteria’, specific to the country’s situation. In Uganda,

0959-6526/$ - see front matter Ó 2006 Elsevier Ltd. All rights reserved.
doi:10.1016/j.jclepro.2005.11.057
204 E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217

the proposed ‘Indicative Rural Electrification Master Plan’ generation [1]. This aim could be addressed by the use of
can be broadly condensed into three steps: GIS which would allow accurate projections to be made in
terms of identifying energy needs, and the quantities required
 The case has to be made for grid-based or off-grid for any given specific area.
planning. Regarding global impacts, Uganda completed an inventory
 Plans subject to financial and economic cost/benefit anal- of it greenhouse gas emissions and is therefore obliged to
ysis in order to identify and prioritise possible electrifica- meet its commitments as a signatory to the UN’s Climate
tion projects. Change Convention (UNCCC). The promotion of renewable
 Technology selection must be made to suit these specific energy is therefore another important element of the Govern-
conditions. ment of Uganda’s rural electrification strategy, giving them
the opportunity to benefit from internationally sponsored pro-
At the district level, planning can then be done by assigning jects via organisations like the Global Environmental Facility
‘Energy benefit points’ to each establishment that would re- (GEF).
quire electrification within that administrative boundary,
such that the infrastructure necessary for supply could be de-
signed accordingly to match the relative demand. 2. Approach
Positive political will is crucial to the success of the plan-
ning process, and this has already been addressed in Ugan- A rational and systematic approach is needed for rural
da’s ‘Rural Electrification Strategy and Plan Covering the electricity planning in Uganda. GIS can provide a key set
Period 2001 to 2010’ by the Ministry of Energy and Miner- of components needed for planning in the form of geo-
al’s Development. Currently, grid-based electricity access in referenced data, using Global Positioning System (GPS)
rural areas stands at less than 2% of the population, whilst coordinates. It produces intelligent data that supports analy-
the overall national level is 5%. The minimum aim for the ses and allows displays of tabular and spatial information to
Rural Electrification Strategy and Plan is to increase connec- assist decision-makers. The planning process is very com-
tions to 10% by 2012, the equivalent of 400,000 new rural plex and multifaceted, and so a simplified approach needs
consumers. The primary objective is to reduce inequalities to be taken. For the purpose of this study, we can divide
in access to electricity and associated opportunities for in- the ‘problematique’ into the four inter-related themes shown
creased social welfare, education, health and income in Box 1.

Box 1.

Theme A: Supply Side Theme B: Demand Side

A1) Biomass B1) Households & Institutions


biogas houses
co-generation schools
gasification hospitals
A2) Hydropower B2) Industry & Commerce
large-hydro & mini-hydro factories
fuel cell technology businesses
A3) Solar B3) Transport & Agriculture
photovoltaic commercial farms
A4) Geothermal
A5) Wind

Theme C: Institutional Issue Theme D: Energy &


Environment
C1) Energy Policy
C2) Institutional Framework D1) Global Environmental Facility
C3) Critical Success Factors D2) Clean Development Mechanism
D3) Millennium Development Goals
E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217 205

This paper presents the demand-side aspect of electricity 3. Theme C: institutional issues
planning in Uganda. Taking a country-wide view, the initial
demand-sectors targeted are health centres, schools, house- 3.1. Energy policy
holds and local government headquarters. These could then
provide a priority-ranking pattern based on estimated benefit Uganda’s Electricity Act of 1999 aims at reforming the
points allocated to each ‘demand centre’. An example is power sector by introducing competition and liberalising the
given of a specific district whose benefit points have been al- electricity industry [2]. In order to make electrification afford-
located, and a priority pattern formed given its existing able to the rural population, it is planned that the government
infrastructure. will subsidise electrification projects, although the criteria and
Many other considerations for developing an appropriate level of subsidisation are still in the process of being deter-
methodology arise out of the four themes during this process, mined. The Rural Electrification Project (REP) in Uganda is
and it is within this context that the following questions are ap- being financed by the World Bank and the Global Environ-
plied to rural electricity planning in Uganda: ment Facility (GEF) through a multi-sectoral program called
Energy for Rural Transformation (ERT), with the overall
1. What are the institutional structures set up for Rural goal of increasing electricity access in rural areas from 1%
Electrification in Uganda? (Theme C) to 10% by 2012 [3].
2. What are the energy demand patterns in Uganda? An autonomous body, the Rural Electrification Agency
(Theme B) (REA) has also been set up, under the Ministry of Energy &
3. What are the possible off-grid renewable energy options? Minerals Development (MEMD), to implement Rural Electri-
(Theme A) fication policies and manage the Rural Electrification Fund

Box 2. Conceptual institutional framework of the Rural Electrification Project in Uganda

ERT
Energy for Rural Transformation
Programme

MOF
Ministry of Finance, Planning &
Economic Development

C
E
MEMD N
Ministry of Energy & Minerals T
Development R
A
REA
L
Rural Electrification Agency
G
O
V
MOE MWLE MOA E
MOH
Ministry of Ministry of Water, Ministry of R
Ministry of Health
Education Lands & Environment Agriculture N
M
E
N
T
MOLG
Ministry of Local Government

LC 5
(District Level)
Local Council 5
LC 3
(Sub-County Level)
Local Council 3
206 E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217

[4]. The agency is responsible for awarding subsidies to in- on countrywide schemes. It is eventually planned that the elec-
vestments in rural electrification projects in Uganda, whilst tricity tariffs will reflect the cost of production in order to
under this ERT program, the role of the Ministry is one of guarantee the financial viability of rural electrification invest-
overall coordination, monitoring and evaluation. The Private ments, subject to regulation by an Electricity Regulatory Au-
Sector Foundation (PSFU) (http://www.psfuganda.org) will fa- thority (ERA) (Box 2).
cilitate and develop business plans, and after the business
plans have been developed, they will then apply to REA for 3.2. Critical success factors
financial support (subsidy). In this way, the Government of
Uganda is looking to achieve their goal through a public/ Critical success factors (CSFs) are described by the UK
private partnership. Priority Rural Electrification Project Government’s Department for International Development
(PREP) packages are initially being prepared for bidding to (DfID) as key features of renewable energy programs that
the private sector in order to test the market before embarking need to be put in place to maximise the possibility that

Fig. 1. The electricity grid/transmission network and some 33 kV distribution lines plus proposed extensions.
E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217 207

a project will succeed. They use their experience and knowl- and to ensure that legislative, political and regulatory
edge of various energy projects from around the world to cat- frameworks are favourable.
egorise these CSFs into five key levels (adapted from http:// (ii) CSFs for funding bodies state that programmes should be
www.dfid-kar-energy.org.uk/html/r6143.htm): independent of day-to-day political involvement. They
should avoid conflict with wider development plans and
(i) Universal CSFs are the ones which form essential fea- should allow the market to choose or ‘pull’ the most ap-
tures, including: the use of proven designs or perfor- propriate technology. They need to ensure that all those
mance guarantees; the existence of an acceptable involved in the market chain benefit from the
economic and financial package; thorough market sur- programme.
veys and clear indication of social need. They state (iii) CSFs for managing agencies state that agencies should
that checks should be put in place to determine project encourage independent scrutiny to confirm objectivity
compatibility with the medium-term energy strategy, of key programmes. Their responsibility is to encourage

Fig. 2. The electricity grid roughly follows the road network; under full coverage these should ideally match.
208 E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217

a competitive energy market. Good project monitoring mini-hydro, biomass utilisation and energy from waste
must be supported by quick responses at early stages to all have attributes that need to be taken into account.
prevent major contractual differences.
(iv) CSFs for small niche markets, such as the provision of ba- 3.3. CSFs for small niche markets in Uganda
sic energy services to rural communities, offer particular
potential and problems. CSFs include the ability of the Some more specific CSFs for small niche markets that can
host community to absorb technology as well as its up- be applied to Uganda’s case during the rural electricity plan-
keep. Also, the impacts on local employment, education, ning process are cost recovery and community involvement.
training and infrastructure development need to be care- Cost recovery is one of the most decisive and crucial factors
fully considered. determining long-term effectiveness of rural electrification
(v) CSFs for individual technologies state that renewable en- programs. Dependence on high initial subsidies in investment
ergy technologies such as solar photovoltaic systems, costs might lead to eventual extortionate tariffs for poor rural

Fig. 3. Population distribution: a few pockets of densely populated areas; Kampala is the most densely populated region, Eastern Uganda is the least densely
populated region.
E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217 209

customer in order for the supplier to recover the loss incurred arise from electrification based on their natural resources
by the eventual reduction or removal of subsidies. and workforce.
Cost-saving opportunities, therefore, need to be exploited
from the beginning of the planning process. In order to create 4. Theme B: demand side
a win-win situation, a two-way approach needs to be taken
such that increased income generating activities would be cre- 4.1. Energy demand patterns
ated as a consequence of improved access to electricity. That
way, the rural consumer will be able to afford to pay his/her In Uganda, the ever-growing demand for electricity exceeds
electric bills, whilst private operators can in turn afford to pro- actual consumption, suppressed by the limited supply. The sit-
vide a decent service and make a modest profit. Rural commu- uation is exasperated further by recurrent load shedding im-
nities in Uganda could be mobilised under their Local posed almost daily on urban consumers in the capital city,
Councils to take advantage of the micro-finance loans on offer, Kampala, where demand is greatest. The capital’s electric sup-
and to create new income-generating activities that would ply is rationed whilst tariffs are on the increase, thus forcing

Fig. 4. Population density is highest along the electricity grid; still many highly populated areas are out of reach.
210 E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217

customers to pay more for a lesser service. It would therefore and social welfare which should attract greater business
make practical sense to look at the demand that already exists opportunities.
in the country, and then design a targeted supply system to This analysis is based on available country statistics from
match it. the Uganda Bureau of Statistics (UBOS) and physical data in-
A cross-sectoral view is taken to examine energy demand corporated into a GIS database to create a base-case demand
patterns for Uganda using geo-referenced data, and to get scenario. At this stage of the analysis, agricultural productivity
a literal picture of the situation on the ground. A ‘demand and business activity input would be useful to add but that data
centre’ can be interpreted as any physical structure that is not yet readily available.
would require electrification. With a goal of kick-starting de-
velopment, the initial focus is on prioritising provision of 4.2. Data processing for GIS maps
electricity to schools and hospitals, powering a few small en-
terprises, mobile telecommunications, as well as providing The quality of data acquisition systems used for collecting
domestic electricity. This should stimulate improved services and monitoring resources in Uganda is poor, and in many

Fig. 5. Some demand centres: schools and village trading centres.


E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217 211

cases such data may have limited value in the context of com- The method of processing the data for creating the
mercial decision making. Being a less developed nation, GIS maps in this paper can be summarised by the following
Uganda faces greater challenges in creating such a database steps:
system. These challenges include: inadequate response from
data collectors, limited appreciation of data, data inconsis- (i) Existing data: this data was supplied by the Uganda Bu-
tencies and inaccuracies. The completeness and accuracy of reau of Statistics and the relevant Ministries as raw data
the data used in the analysis is crucial since it determines that contained various inaccuracies. From this original
the accuracy of the results. data, gaps were identified and noted.
The initial challenge therefore, is to assess the best way in (ii) Data collection: where relevant, more data was collected
which to convert the information into GIS format and to iden- by field teams in order to fill in these gaps.
tify what form of data is to be used for subsequent analysis to (iii) Data cleaning: as part of quality control, the data was
inform decision-making. then verified and final corrections made including

Fig. 6. Health centres.


212 E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217

Fig. 7. The demand pattern most activity congregates along the electricity grid.

alignment of projections and GPS coordinates as well as grid and the road network combined. We can see that the
spell checks. power lines roughly follow the road network, and this is par-
(iv) Data modelling: once the data had been verified, it was ticularly true in the rural parts. Ideally, under full coverage,
then modelled to create the GIS maps. these two networks should match. The road network also indi-
cates potential access to bigger markets for the rural busi-
Looking at the GIS maps created (Figs. 1e7), the existing nesses whose main activity is the transportation of
demand pattern for Uganda is already clear: most activity in agricultural produce. Fig. 3 shows the population distribution
the country clusters along the existing electric grid as a lifeline by sub-county. From this we can see that there are a few iso-
for power. lated pockets of densely populated areas. Kampala, being the
Fig. 1 shows the electric transmission network and some capital city, is the most densely populated region and the semi-
33 kV distribution lines including some of the proposed desert North-Eastern region is the least populated. Fig. 4
extensions for the suggested Priority Rural Electrification shows the population distribution along the grid. We can see
Project (PREP) areas. Fig. 2 shows the existing electricity that there are still many highly populated areas unconnected
E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217 213

Table 1 Table 2
Benefit points allocation table Sum of Benefit Points for households [BPHH]
Sector Category Comment Suggested Benefit point Sub-county Sum of households ¼
or qualification formula average used sum of benefit
for Uganda points [BPHH]
Households Household or 1 1 Buhesi 6672
population Bukuuku 4294
per sub-county Busoro 5419
Health Health HC II 10 10 Central 5754
centres HC III 30 30 Eastern 3181
HC IV 70 70 Hakibale 8396
Hospital 100 þ 0.6pbeda 160 Karambi 5989
Education Schools Primary 8 þ 0.015 ppa 12 Kibiito N/A
Post primary 9 9 Kichwamba 5408
Secondary 12 þ 0.025 pp 22 Kisomoro 6159
Tertiary 16 þ 0.03 pp 35 Mugusu 4145
Other 11 11 Ruteete 9169
Non-formal 11 11 Rwimi 5351
Local District HQ LC 5 30 30 Southern 3452
government County HQ 20 20 Western 3734
Sub-county LC 3 10 10
HQ
Parish HQ 5 5
benefit point values were agreed upon at the ‘Rural Electrifica-
tion Criteria’ stakeholders’ workshop after comparison with
Source: IT Power Team, Indicative Rural Electrification Master Plan (IREMP)
Project, Uganda.
other studies done in South Africa and Namibia. The benefit
a
pp, per pupil; pbed, per bed. points averages were then allocated to each demand centre
(health centres, schools, local government HQs) throughout
the country.
to the grid. Such areas would therefore be good candidates for
off-grid planning. Fig. 5 shows some energy demand centres 4.4. Applied benefit point system at district level (LC5)
such as schools and village trading centres. Fig. 6 shows the
distribution of health centres (HCs) around the country which 4.4.1. Methodology used
have been aggregated into four levels as defined by the Minis-
try of Health according to capacity levels. At the highest level (1) For any sector (x), the sum of benefit points (BPx) is cal-
are hospitals, which take the highest energy load priority; then culated within each sub-county (LC3) administrative
HC IVs, which would use powered medical equipment; down boundary in that district as a function of that sector:
to HC IIIs and HC IIs which require basic electricity supply.
Fig. 7 shows the distribution of energy demand centres along BPx ¼ Ffxg
the electric grid, including population density, schools and vil-
lage trading centres. Their combined demand pattern shows where x is the sector description.
the congestion along the electric grid. These preliminary
results could then provide the basis for a priority-ranking (2) For each sub-county the overall total sum of benefit points
pattern. Once the demand scenario has been set, estimated for the combination of sectors is calculated:
load profiles or benefit points can then be allocated to each ÿ 
BPx þ BPy þ . ¼ BPfx;y.g
‘demand-centre’. These points could then be summed up
within each administrative boundary at either district, county Table 3
or parish level to give a priority pattern. Sum of Benefit Points for health centres [BPHC]
Subcounty No. health Sum of benefit
centres points [BPHC]
4.3. Benefit point allocation
Buheesi 1 30
Bukuku 1 70
The suggested benefit point allocations for Uganda are Busoro 2 20
given in Table 1 based on needs assessment in each sector Eastern 1 30
in terms of social value, willingness to pay for electricity ser- Hakibale 3 70
vices, future electricity consumption and long term sustain- Kibiito 4 160
Kicwamba 1 30
ability of a project. The aim is to reflect the relative
Kisomoro 1 30
importance of infrastructure and other facilities and to make Mugusu 3 50
an attempt to quantify these social benefits. Ruteete 4 60
Using a rural household as the unit reference point, all other Rwiimi 2 40
institutions are allocated benefit points against this reference Southern 3 300
Western 2 20
and their electrification is compared relative to this unit. These
214 E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217

Table 4 Table 6
Sum of Benefit Points for schools [BPSCH] Overall total sum of benefit points by sub-county in Kabarole district
Subcounty No. schools Sum of benefit Subcounty BPHH BPHC BPSCH BPHQ Total sum
points [BPSCH] BP{HC, SCH, HQ}

Buheesi 16 212 Buhesi 6672 30 212 15 257


Bukuuku 19 303 Bukuuku 4294 70 303 0 373
Busoro 7 104 Busoro 5419 20 104 0 124
East division 1 35 Central 5754 0 35 0 35
Eastern 11 182 Eastern 3181 30 182 0 212
Hakibale 12 187 Hakibale 8396 70 187 0 257
Karambi 10 140 Karambi 5989 0 140 0 140
Kibiito 25 366 Kibiito N/a 160 366 0 526
Kicwamba 17 223 Kichwamba 5408 30 223 0 253
Kisomoro 20 280 Kisomoro 6159 30 280 0 310
Mugusu 8 106 Mugusu 4145 50 106 0 156
Ruteete 21 315 Ruteete 9169 60 315 0 375
Rwiimi 14 198 Rwimi 5351 40 198 0 238
Southern 16 285 Southern 3452 300 285 0 585
Western 7 94 Western 3734 20 94 0 114

(3) Within the district administrative boundary (LC5), the (iii) Schools: A total of 204 schools were found in Kabarole
overall total sum benefit point value is applied to each district distributed throughout all 13 sub-counties. Of
sub-county and mapped to give a priority pattern for those this total there were four categories of school types found
sectors. and these were divided as: 154 primary schools, 40 sec-
(4) The priority pattern is colour-coded such that the areas ondary schools, 8 tertiary schools and 2 others. Their
with the highest benefit point value are coloured red and sum of benefit points was then calculated within each
the areas with the lowest benefit point value are coloured sub-county (Table 4).
green and those in between are coloured yellow. (iv) Local government HQs: The local government headquar-
ters are the seat of district planning, and act as a vital
link to central government. The main town council for
4.5. Example: Kabarole district Kabarole district is found in Fort Portal town where the
electricity sub-station is located. The parish HQ and the
Kabarole district is located in western Uganda. It contains sub-county HQ are located in the same sub-county and
15 sub-counties and for each of the following sectors, the their sum of benefit points is given in Table 5.
sum of benefit points was calculated within each sub-county
(LC3) boundary: These results then give the overall total sum of benefit points
within each of the sub-counties of Kabarole district, for the spe-
(i) Households (Table 2): In rural Uganda the household set- cific sectors calculated. The results are displayed in Table 6.
tlement patterns and population distribution are highly Fig. 8 shows the detailed infrastructure of Kabarole district,
random, so these results have been kept separate but adja- including the distribution of schools divided into categories,
cent to the benefit point allocations when developing the health centres divided into different grades, local government
overall priority pattern. Households are proportionate to headquarters and the population distribution by sub-county.
population and the assumption is made that 1 household The road network under the electric lines indicates where pos-
contains 5 people. According to the BP formulae, there- sible grid extensions could be made to target high benefit areas
fore, the estimated number of households is 1/5 of the and also where off-grid electricity generation could be targeted.
sum population within a sub-county which is equal to Fig. 9 shows the total sum benefit points (BP{HC,SCH,HQ})
the sum of benefit points and this is the base unit: 1 house- given for each sub-county in Kabarole district based on the
hold ¼ 5 people ¼ 1 benefit point. sector activity contained within it (not including population).
(ii) Health centres: In Kabarole District, a total of 28 health A clear priority pattern can already be seen in Kabarole dis-
centres were found of which there were: 11 HC IIs, 12 trict, with the red indicating the sub-counties with the highest
HC IIIs, 2 HC IVs and 3 hospitals. These HCs are distrib- benefit points and therefore the areas with the highest electri-
uted throughout 12 sub-counties and their benefit points fication needs, and the green indicating the sub-counties with
have been summed in Table 3. the lowest benefit points and therefore areas with relatively
lower electrification needs. This priority pattern is for electri-
Table 5
fying schools, hospitals and local government headquarters in
Sum of Benefit Points for local government headquarters [BPHQ]
Kabarole district at the level of district planning.
Subcounty No. local government Sum of benefit
This benefit point analysis can be used for any district. It
headquarters points [BPHQ]
can also be extended to other sectors and used as a planning
Buheesi 2 15
tool for privatisation. The areas with the highest BP could
E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217 215

Fig. 8. Kabarole district detailed infrastructure, including school by type, health centres by grade, local government headquarters and estimated sum population
pattern by sub-county.

be selected as priority rural electrification areas and tested af- to village. Beyond the road network and in between the trading
ter selective implementation of specific supply schemes. centres, are many rural households located in isolation amongst
farmland, plantations or natural vegetation following no partic-
5. Theme A: supply side ular layout plan. The natural terrain can also sometimes be
mountainous and less penetrable. In these remote, hard to reach
5.1. The case for off-grid options in rural Uganda areas where grid supplies are impractical, people generally
meet their energy needs for lighting and cooking by using
On the ground, the rural terrain and settlement patterns in wood fuel because it is ‘free’ [5].
Uganda are some of the major obstacles to electricity infrastruc- These areas would almost certainly benefit from small-scale
ture planning. Typically, a village is identified by its trading off-grid renewable energy generation such as mini-hydro. Their
centre where most business activity is centred. These trading standards of living would be elevated to socially and politically
centres are usually found along the main road and are often dis- acceptable levels, and it would also be environmentally benefi-
tributed sparsely and randomly, many miles apart from village cial by removing a dependence upon the combustion of woody
216 E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217

Fig. 9. Kabarole district benefit point allocation by sub-county: priority pattern for electrifying schools, health centres and local government headquarters; red
indicates greater benefits and higher priority, green indicates lesser benefits and lower priority.

biomass. Specific criteria therefore need to be sought for each lake, Lake Victoria, it also boasts the source of the mighty
area in order to judge the best technical options for off-grid sup- River Nile which starts at the waterfalls in Jinja, and runs all
ply to rural households. This should be based on the natural re- the way through the country, up to Egypt. In addition, there
sources available in each given area, though due to its relative are plenty more rivers and lakes that spill over from these
advantage compared to other natural resources in Uganda, the making it a very lush and fertile country. Hydropower is an
initial focus for the supply-side will be on hydro power. abundant natural resource over much of rural Uganda. Conse-
quently, Uganda’s electricity supply system is dominated by
5.2. Potential small-scale hydro schemes hydropower nearly 100 times greater than any other source.
The total hydropower capacity in Uganda is estimated to be
Uganda is at the heart of the Great Lakes region of East in excess of 2000 MW, compared with the current installed
Africa. Not only does it co-host the world’s largest freshwater generation of less than 250 MW [6]. There are therefore plenty
E. Kaijuka / Journal of Cleaner Production 15 (2007) 203e217 217

of potential sites for small-hydro schemes, which are, as yet, guidance and advice. I also wish to thank the IT Power
under-developed. team, particularly Dr Jonathan Bates, for useful discussions,
Small-scale hydro installations in rural areas could then of- and Chris Purcell and Duncan Brewer for the invaluable data
fer considerable financial benefits to the communities served, input. Thanks also to Professor Gaddi Ngirane-Katashaya,
particularly where careful planning identifies income-generat- Makerere University for his supervision. The views expressed
ing uses for power. Their simplicity means that small-hydro in these papers are those of the author.
schemes not only provide renewable energy, but are also
cheaper to maintain, given basic training. The main advantage
of small-hydro schemes is that they do not require a dam or
References
storage facility to be constructed; it simply diverts water
from the river, channels it into a valley and ‘drops’ it into a tur- [1] Ministry of Energy & Minerals Development (MEMD), Republic of
bine via ‘penstock’ (pipeline). This type of hydro generating Uganda. Rural electrification strategy and plan covering the period 2001
would thus avoid the damaging environmental and social ef- to 2010; 2001.
fects that larger hydroelectric systems can cause. It would [2] United Nations Environment Programme (UNEP), United Nations-
Department of Economic and Social Affairs (UN-DESA). African
seem that for Uganda’s rural population who are materially
experts meeting on the 10YFP. The African 10 year framework
poor but have a great wealth of nature at their disposal, this programme (10YFP) on sustainable consumption and production; 2005.
most basic, self-sustaining and least-cost method of power [3] Ministry of Energy & Minerals Development (MEMD), Republic of
generation could prove to be the most appropriate of all. Uganda. The energy policy for Uganda; 2002.
[4] Department for International Development (DFID), Knowledge and
Acknowledgements Research. Energy project summaries: <http://www.dfid-kar-energy.org.uk>.
[5] Ministry of Energy & Minerals Development (MEMD), Republic of
Uganda. National biomass energy demand strategy 2001 to 2010; 2001.
I wish to thank Dr Albert Rugumayo, Ministry of Energy [6] Government of Uganda. Uganda power sector restructuring and privatisa-
and Minerals Development, Uganda for his invaluable tion, new strategy plan and implementation plan; 1999.

You might also like