You are on page 1of 15

Earth work in foundation trenches up to 1.

5 m depth and 60 m lead including protecting and


maintaining the trench.
Considering 1000 cft. work
1. Mason 0.5 No. @ Tk. 500.00 each = Tk. 250.00
2. Ordinary labour 10 Nos. @ Tk. 300.00 each = Tk. 3,000.00
3. Skilled labour 2.5 Nos. @ Tk. 400.00 each = Tk. 1,000.00
4. For lay-out:
i) Head mason 0.25 No. @ Tk. 550.00 each = Tk. 137.50
ii) Lime for marking 0.5 kg @ Tk. 60.00 Per kg = Tk. 30.00
iii) Bamboo for spikes 5 rft. @ Tk. 10.00 Per rft. = Tk. 50.00
5. Tools and plant, sundries etc. L.S. = Tk. 100.00
Total = Tk. 4,567.50
Contractor's profit 10.00% = Tk. 456.75
Overhead expenses 3.00% = Tk. 137.03
Tk. 5,161.28
VAT 0.00% = Tk. -

Grand total = Tk. 5,161.28

Rate per cft. = Tk. 5.16


Extra rate for each additional 1 meter depth exceeding 1.5 meter
Considering 1000 cft. work
1. Mason 0.125 No. @ Tk. 500.00 each = Tk. 62.50
2. Ordinary labour 3 Nos. @ Tk. 300.00 each = Tk. 900.00
Total = Tk. 962.50
Contractor's profit 10.00% = Tk. 96.25
Overhead expenses 3.00% = Tk. 28.88
Tk. 1,087.63
VAT 0.00% = Tk. -

Grand total = Tk. 1,087.63

Rate per cft. = Tk. 1.09

Total Rate /cft = Tk. 6.25


One layer brick flat soling in foundation or in floor.
Considering 100 sft of work
1. Bricks 350 Nos. @ 7.00 Per Nos. = 2,450.00
2. Fine sand (with wastage) 5.25 cft. @ 10.00 Per cft. = 52.50
3. Labor Charge 100 sft @ 3.00 each = 300.00
6. Local carriage, sundries, T & P etc. L.S. = 80.00
Total = 2,882.50
Contractor's profit 10.00% = 288.25
Overhead expenses 3.00% = 86.48
3,257.23
VAT 0.00% = -
Grand
= 3,257.23
total
Rate per sft. = 32.57
CC Casting (Cement : Sand: Brick chips= 1:3:6) with brick chips & 100% local sand of F.M. 1.2
consider 100 cft work
1 Bricks for 90 cft chips(with wastage) 780 nos @ 7 tk per nos 5460
2 Sand ( Local, F.M = 1.2, with wastage) 46 cft @ 20 tk per cft 920
3 Cement (ordinary portland) 12 bag @ 410 tk per bag 4920
breaking chips incl. screening, stacking,
4 wetting, 90 cft @ 7 tk per cft 630
Labour costing ( Material loading,RCC Casting,
5 Curing ) 100 cft @ 20 tk per cft 2000
i) Labour costing (Shuttering) 100 cft @ 15 tk per cft 1500
ii) Shuttering material 100 cft @ 14 Tk/cft 1400
iii) Mixture machine, pump, local carriage, sundries, T & P etc. 1000
Subtotal = 17830.00
Contractors profit 5.00 % = 891.5
Overhead 3.00 % = 534.9

Grand Total = 19256.40

Rate per cft = 192.56


Shuttering material
For a footing base size 8 ftx 8ft
Casting volume of cc work (8.5 ftx8.5 ftx 3in)
18.0625 cft

Shuttering material
2.10 cft
2.42 cft 15% for wastage, nail, wires
1016.31 tk 420Tk/cft with carriage
254.078125 Tk using 4 times

Material Cost /cft= 14.07 Tk

Shuttering Labour
For a footing base size 8 ftx 8ft
Casting volume of cc work (8.5 ftx8.5 ftx 3in)
18.0625 cft

Shuttering labor charge


17.00 sft
272.00 tk Tk 16 /sft labour charge

labour Cost /cft= 15.06 Tk


RCC Casting for footings : ( Cement : sand : Stone Chips=1 : 1.5 : 3 )
considering 100 cft of work
1 Cement (ordinary portland) 22 bag @ 410 tk per bag 9020
2.a Stone chips (3/4 inch with wastage) 46 cft @ 145 Tk per cft 6670
2.b Stone chips (1/2 inch and pie with wastage) 46 cft @ 140 Tk per cft 6440
3 Sylhet Sand (F.M = 2.5, with wastage) 45 cft @ 35 tk per cft 1575
4 Labour costing ( RCC Casting , Material loading, curing) 100 cft @ 20 tk per cft 2000
5 Labour costing ( Shuttering) 100 cft @ 10.5 tk per cft 1050
6. Shuttering material cost 100 cft @ 8.5 tk per cft 850
7. Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 4 tk per cft 400
Subtotal = 28005.00
Contractors 8.00 % = 2240.4
Overhead 3.00 % = 840.15
31085.55
VAT = 0.00 %
Grand Total = 31085.55

Rate per cft = 310.86

Shuttering material
For a footing base size 8 ftx 8ft
Casting volume of RCC work (8 ftx8 ftx 12in)
64 cft

Shuttering material
5.26 cft
### tk 420Tk/cft with carriage
552.34 Tk using 4 times

Material Cost /cft= 8.63 Tk

Shuttering Labour
For a footing base size 8 ftx 8ft
Casting volume of RCC work (8 ftx8 ftx 12in)
64 cft

Shuttering labor charge


Shuttering Area= 42.50 sft
Shuttering labour cost/footing= 680.00 tk Tk 16 /sft labour charge

labour Cost /cft= 10.63 Tk


RCC Casting for Column, beam & Stair Base: Cement : sand : Stone Chips=1 : 1.5 : 3 ( for Ground floor)
considering 100 cft of work
1 Cement (ordinary portland) 22 bag @ 410 tk per bag 9020
2.a Stone chips (3/4 inch with wastage) 46 cft @ 145 Tk per cft 6670
2.b Stone chips (1/2 inch and pie with wastage) 46 cft @ 140 Tk per cft 6440
3 Sylhet Sand (F.M = 2.5, with wastage) 45 cft @ 35 tk per cft 1575
4 Labour costing ( RCC Casting , Material loading, curi 100 cft @ 20 tk per cft 2000
5 Labour costing ( Shuttering) 100 cft @ 28.80 tk per cft 2880
6. Shuttering material cost 100 cft @ 39.84 tk per cft 3983.625
7. Mixture machine, pump, local carriage, sundries, T & 100 cft @ 3.5 tk per cft 350
Subtotal = 32918.63
Contractors profit 8.00 % = 2633.49
Overhead 2.50 % = 822.9656
36375.08
VAT = 0.00 %
Grand Total = 36375.08

Rate per cft = 363.75

RCC Casting for Column, beam & Stair Base: Cement : sand : Stone Chips=1 : 1.5 : 3 ( for 1st floor)
considering 100 cft of work
1 Cement (ordinary portland) 22 bag @ 410 tk per bag 9020
2.a Stone chips (3/4 inch with wastage) 46 cft @ 145 Tk per cft 6670
2.b Stone chips (1/2 inch and pie with wastage) 46 cft @ 140 Tk per cft 6440
3 Sylhet Sand (F.M = 2.5, with wastage) 45 cft @ 35 tk per cft 1575
4 Labour costing ( RCC Casting , Material loading, curi 100 cft @ 20 tk per cft 2000
5 Labour costing ( Shuttering) 100 cft @ 28.8 tk per cft 2880
6. Shuttering material cost 100 cft @ 39.84 tk per cft 3984
7. Mixture machine, pump, local carriage, sundries, T & 100 cft @ 5 tk per cft 500
Subtotal = 33069.00
Contractors profit 8.00 % = 2645.52
Overhead 2.50 % = 826.725
36541.25
VAT = 0.00 %
Grand Total = 36541.25

Rate per cft = 365.41

Shuttering material
For a column size 15 in x 15 in x10 ft
Casting volume of RCC work (15 in x 15 in x10 ft)
27.78 cft

Shuttering material
Wood 7.40 cft
3106.25 tk 420Tk/cft with carriage
776.56 Tk using 4 times

Bamboo 132 ft
3.77 nos bamboo
1320 Tk
330 Using 4 times
Material Cost /cft= 39.84 Tk

Shuttering Labour
For a column size 15 in x 15 in x10 ft
Casting volume of RCC work (15 in x 15 in x10 ft)
27.78 cft

Shuttering labor charge


Shuttering Area= 50.00 sft
Shuttering labour cost/footing= 800.00 tk Tk 16 /sft labour charge

labour Cost /cft= 28.80 Tk


RCC Casting for Ground Floor (Cement : Sand : Brick Chips=1 : 2 : 4)

consider 100 cft work


1 Cement (ordinary portland) 18 bag @ 410 tk per bag 7380
2.a Bricks for 90 cft chips(picket with wastage) 790 nos @ 7 tk per nos 5530
2.b breaking chips incl. screening, stacking, wetting, 90 cft @ 7 tk per cft 630
3.a Sand mixed (F.M = 1.2, with wastage) 24 cft @ 20 tk per cft 480
3.b Sand mixed (F.M = 2.5 with wastage) 24 cft @ 35 tk per cft 840
4 Labour costing ( Material loading,RCC Casting, Curing) 100 cft @ 20 tk per cft 2000
5 Labour costing ( Shuttering material fixing & removing) 100 cft @ 1.92 tk per cft 192
6 Shuttering material cost 100 cft @ 2.26 Tk/cft 226
7 Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 5 Tk/cft 500
Subtotal = 17778
Contractors profit 10.00 % = 1778
Overhead 3.00 % = 533
20089
Grand Total = 20089

Rate per cft = 201


Shuttering material
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering material
Wood 20.86 cft
8760.94 tk 420Tk/cft with carriage
2190.23 Tk using 4 times

Bamboo 252 ft
7.20 nos bamboo
2520 Tk 350/ each
630 Using 4 times
Material Cost /cft= 2.26 Tk

Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering labor charge


Shuttering Area= 150.00 sft
Shuttering labour cost/footing= 2400.00 tk Tk 16 /sft labour charge

labour Cost /cft= 1.92 Tk


RCC Casting for 1st Floor (Cement : Sand : Brick Chips=1 : 2 : 4)

consider 100 cft work


1 Cement (ordinary portland) 18 bag @ 410 tk per bag 7380
2.a Bricks for 90 cft chips(picket with wastage) 790 nos @ 7 tk per nos 5530
2.b breaking chips incl. screening, stacking, wetting, 90 cft @ 7 tk per cft 630
3.a Sand mixed (F.M = 1.2, with wastage) 24 cft @ 20 tk per cft 480
3.b Sand mixed (F.M = 2.5 with wastage) 24 cft @ 35 tk per cft 840
4 Labour costing ( Material loading,RCC Casting, Curing) 100 cft @ 22 tk per cft 2200
5 Labour costing ( Shuttering material fixing & removing) 100 cft @ 1.92 tk per cft 192
6 Shuttering material cost 100 cft @ 2.48 Tk/cft 248
7 Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 7.5 Tk/cft 750
Subtotal = 18250
Contractors profit 10.00 % = 1825
Overhead 3.00 % = 547
20622
Grand Total = 20622

Rate per cft = 206

Shuttering material
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering material
Wood 10.92 cft
4587.73 tk 420Tk/cft with carriage
1146.93 Tk using 4 times

Bamboo 780 ft
22.29 nos bamboo
7800 Tk 350/ each
1950 Using 4 times
Material Cost /cft= 2.48 Tk

Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering labor charge


Shuttering Area= 150.00 sft
Shuttering labour cost/footing= 2400.00 tk Tk 16 /sft labour charge

labour Cost /cft= 1.92 Tk


RCC Casting for 2nd Floor (Cement : Sand : Brick Chips=1 : 2 : 4)

consider 100 cft work


1 Cement (ordinary portland) 18 bag @ 410 tk per bag 7380
2.a Bricks for 90 cft chips(picket with wastage) 790 nos @ 7 tk per nos 5530
2.b breaking chips incl. screening, stacking, wetting, 90 cft @ 7 tk per cft 630
3.a Sand mixed (F.M = 1.2, with wastage) 24 cft @ 20 tk per cft 480
3.b Sand mixed (F.M = 2.5 with wastage) 24 cft @ 35 tk per cft 840
4 Labour costing ( Material loading,RCC Casting, Curing) 100 cft @ 24 tk per cft 2400
5 Labour costing ( Shuttering material fixing & removing) 100 cft @ 1.92 tk per cft 192
6 Shuttering material cost 100 cft @ 2.48 Tk/cft 248
7 Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 10 Tk/cft 1000
Subtotal = 18700
Contractors profit 10.00 % = 1870
Overhead 3.00 % = 561
21131
Grand Total = 21131

Rate per cft = 211

Shuttering material
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering material
Wood 10.92 cft
4587.73 tk 420Tk/cft with carriage
1146.93 Tk using 4 times

Bamboo 780 ft
22.29 nos bamboo
7800 Tk 350/ each
1950 Using 4 times
Material Cost /cft= 2.48 Tk

Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft

Shuttering labor charge


Shuttering Area= 150.00 sft
Shuttering labour cost/footing= 2400.00 tk Tk 16 /sft labour charge

labour Cost /cft= 1.92 Tk


Supplying, fabrication etc of M.S. rod in RCC works : 72.5 / 60 grade deformed bar (GF)
Considering 50 kg of work
1 Cost of materials:
i) M.S. rod: 72.5 / 60 grade 50 kg @ Tk. 61.00 Per kg. =
iii) G.I. wire 1 kg @ Tk. 95.00 Per kg. =
2 Cost of labour 50 kg Tk. 5.00 Per kg. =
Unloading, Equipment charge,
3 50 Kg @ Tk. 1.25 Per kg.
Utility
Total =
Contractor's profit 10.00% =
Overhead expenses 3.00% =

Grand total =
Rate per Kg =
Supplying, fabrication etc of M.S. rod in RCC works : 72.5 / 60 grade deformed bar (1st Fl)
Considering 50 kg of work
1 Cost of materials:
i) M.S. rod: 72.5 / 60 grade 50 kg @ Tk. 61.00 Per kg. =
iii) G.I. wire 1 kg @ Tk. 95.00 Per kg. =
2 Cost of labour 50 kg Tk. 5.50 Per kg. =
Unloading, Equipment charge,
3 50 Kg @ Tk. 2.00 Per kg.
Utility
Total =
Contractor's profit 10.00% =
Overhead expenses 3.00% =

Grand total =
Rate per Kg =

Supplying, fabrication etc of M.S. rod in RCC works : 72.5 / 60 grade deformed bar ( 2nd Fl)
Considering 50 kg of work
1 Cost of materials:
i) M.S. rod: 72.5 / 60 grade 50 kg @ Tk. 61.00 Per kg. =
iii) G.I. wire 1 kg @ Tk. 95.00 Per kg. =
2 Cost of labour 50 kg Tk. 6.00 Per kg. =
Unloading, Equipment charge,
3 50 Kg @ Tk. 3.00 Per kg.
Utility
Total =
Contractor's profit 10.00% =
Overhead expenses 3.00% =

Grand total =
Rate per Kg =
ormed bar (GF)

Tk. 3,050.00
Tk. 95.00
Tk. 250.00

Tk. 62.50

Tk. 3,457.50
Tk. 345.75
Tk. 103.73
Tk. 3,906.98
Tk. 3,906.98
Tk. 78.14
med bar (1st Fl)

Tk. 3,050.00
Tk. 95.00
Tk. 275.00

Tk. 100.00

Tk. 3,520.00
Tk. 352.00
Tk. 105.60
Tk. 3,977.60
Tk. 3,977.60
Tk. 79.55

med bar ( 2nd Fl)

Tk. 3,050.00
Tk. 95.00
Tk. 300.00

Tk. 150.00

Tk. 3,595.00
Tk. 359.50
Tk. 107.85
Tk. 4,062.35
Tk. 4,062.35
Tk. 81.25
125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure (GF)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50 Tk per nos 3,600.00
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00 Tk per cft 360.00
3. Cement (portland) 1.75 bags @ 410.00 Tk per bag 717.50
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00 Tk per nos 480.00
5. Labour (Brick work) 100 sft. @ 10.00 Tk per sft 1,000.00
6. Scaffolding material & labour charge 25 sft. @ 12.00 Tk per sft 300.00
7. Local carriage, storage & sundries etc. L.S. 200.00
Total = 6,657.50
Contractor's profit 10.00% = 665.75
Overhead expenses 3.00% = 199.73
7,522.98
Grand
= 7,522.98
total
Rate per sft. = 75.23

125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure ( for 1st floor)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50 Tk per nos 3,600.00
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00 Tk per cft 360.00
3. Cement (portland) 1.75 bags @ 410.00 Tk per bag 717.50
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00 Tk per nos 480.00
5. Labour (Brick work) 100 sft. @ 11.00 Tk per sft 1,100.00
6. Scaffolding material & labour charge 25 sft. @ 13.00 Tk per sft 325.00
7. Local carriage, storage & sundries etc. L.S. 250.00
Total = 6,832.50
Contractor's profit 10.00% = 683.25
Overhead expenses 3.00% = 204.98
7,720.73
Grand
= 7,720.73
total
Rate per sft. = 77.21

125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure ( for 2nd floor)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50 Tk per nos 3,600.00
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00 Tk per cft 360.00
3. Cement (portland) 1.75 bags @ 410.00 Tk per bag 717.50
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00 Tk per nos 480.00
5. Labour (Brick work) 100 sft. @ 12.00 Tk per sft 1,200.00
6. Scaffolding material & labour charge 25 sft. @ 14.00 Tk per sft 350.00
7. Local carriage, storage & sundries etc. L.S. 350.00
Total = 7,057.50
Contractor's profit 10.00% = 705.75
Overhead expenses 3.00% = 211.73
7,974.98
Grand
= 7,974.98
total
Rate per sft. = 79.75
10 inch Brick Work (1:3:6)
Considering 100 cft. of work:
1. Bricks ( With Wastage) 1152 Nos. @ 7.5 Per Nos. = 8,640.00
2. Sand (F.M 1.2) in/c wastage 46 cft. @ 20 Per cft. = 920.00
3. Cement (portland) 6 bags @ 410 Per bag = 2,460.00
Labour cost ( Soaking bricks,
4. 1152 Nos. @ each = 1,152.00
scraning sand) 1
5. Labour cost ( brick work) 100 cft. @ 12 each = 1,200.00
6 Scaffolding material & labour charge 25 sft. @ 12 Per sft. = 300.00
7 Local carriage, sundries, T & P etc. L.S. = 100.00
Total = 14,772.00
Contractor's profit 10.00% = 1,477.20
Overhead expenses 3.00% = 443.16
16,692.36
Grand
= 16,692.36
total
Rate per cft. = 166.92

10 inch Brick Work (1:6) ( for 1st floor)


Considering 100 cft. of work:
1. Bricks ( With Wastage) 1152 Nos. @ 8.5 Per Nos. = 9,792.00
2. Sand (F.M 1.2) in/c wastage 46 cft. @ 20 Per cft. = 920.00
3. Cement (portland) 6 bags @ 460 Per bag = 2,760.00
Labour cost ( Soaking & carrying,
4. 1152 Nos. @ each = 576.00
scraning sand) 0.5
5. Labour cost ( brick work) 100 cft. @ 13.5 each = 1,350.00

6 Scaffolding material & labour charge 25 sft. @ 11 Per sft. = 275.00

7 Local carriage, sundries, T & P etc. L.S. = 150.00


Total = 15,823.00
Contractor's profit 10.00% = 1,582.30
Overhead expenses 3.00% = 474.69
17,879.99
Grand
= 17,879.99
total
Rate per cft. = 178.80
RCC Casting for Lintel, Sun Shade and Drop Slab (1:2:4)

consider 100 cft work

1 Cement (ordinary portland) 18 bag @ 410 tk per bag 7380


2.a Bricks for 90 cft chips(picket with wastage) 790 nos @ 7 tk per nos 5530
2.b breaking chips incl. screening, stacking, wetting, 90 cft @ 7 tk per cft 630
3.a Sand mixed (F.M = 1.2, with wastage) 24 cft @ 20 tk per cft 480
3.b Sand mixed (F.M = 2.5 with wastage) 24 cft @ 35 tk per cft 840
4 Labour costing ( Material loading,RCC Casting, Curing) 100 cft @ 20 tk per cft 2000
5 Labour costing ( Shuttering material fixing & removing) 100 cft @ 94 tk per cft 9408
6 Shuttering material cost 100 cft @ 107 Tk/cft 10718
7 Mixture machine, pump, local carriage, sundries, T & P etc. 100 cft @ 10 Tk/cft 1000
Subtotal = 37986
Contractors profit 10.00 % = 3799
Overhead 3.00 % = 1140
42924
Grand Total = 42924

Rate per cft = 429

Shuttering material
For a lintle size 20 ft x 10 in x5 in
Casting volume of RCC work (20 ft x 10 in x5 in)
6.94 cft

Shuttering material
Wood 5.76 cft
2417.19 tk 420Tk/cft with carriage
604.30 Tk using 4 times

Bamboo 56 ft
1.60 nos bamboo
560 Tk 350/ each
140 Using 4 times
Material Cost /cft= 107.18 Tk

Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
6.94 cft

Shuttering labor charge


Shuttering Area= 40.83 sft
Shuttering labour cost/footing= 653.33 tk Tk 16 /sft labour charge

labour Cost /cft= 94.08 Tk

You might also like