Professional Documents
Culture Documents
Rate Analysis - Mesh With Fresh Submitted
Rate Analysis - Mesh With Fresh Submitted
Shuttering material
2.10 cft
2.42 cft 15% for wastage, nail, wires
1016.31 tk 420Tk/cft with carriage
254.078125 Tk using 4 times
Shuttering Labour
For a footing base size 8 ftx 8ft
Casting volume of cc work (8.5 ftx8.5 ftx 3in)
18.0625 cft
Shuttering material
For a footing base size 8 ftx 8ft
Casting volume of RCC work (8 ftx8 ftx 12in)
64 cft
Shuttering material
5.26 cft
### tk 420Tk/cft with carriage
552.34 Tk using 4 times
Shuttering Labour
For a footing base size 8 ftx 8ft
Casting volume of RCC work (8 ftx8 ftx 12in)
64 cft
RCC Casting for Column, beam & Stair Base: Cement : sand : Stone Chips=1 : 1.5 : 3 ( for 1st floor)
considering 100 cft of work
1 Cement (ordinary portland) 22 bag @ 410 tk per bag 9020
2.a Stone chips (3/4 inch with wastage) 46 cft @ 145 Tk per cft 6670
2.b Stone chips (1/2 inch and pie with wastage) 46 cft @ 140 Tk per cft 6440
3 Sylhet Sand (F.M = 2.5, with wastage) 45 cft @ 35 tk per cft 1575
4 Labour costing ( RCC Casting , Material loading, curi 100 cft @ 20 tk per cft 2000
5 Labour costing ( Shuttering) 100 cft @ 28.8 tk per cft 2880
6. Shuttering material cost 100 cft @ 39.84 tk per cft 3984
7. Mixture machine, pump, local carriage, sundries, T & 100 cft @ 5 tk per cft 500
Subtotal = 33069.00
Contractors profit 8.00 % = 2645.52
Overhead 2.50 % = 826.725
36541.25
VAT = 0.00 %
Grand Total = 36541.25
Shuttering material
For a column size 15 in x 15 in x10 ft
Casting volume of RCC work (15 in x 15 in x10 ft)
27.78 cft
Shuttering material
Wood 7.40 cft
3106.25 tk 420Tk/cft with carriage
776.56 Tk using 4 times
Bamboo 132 ft
3.77 nos bamboo
1320 Tk
330 Using 4 times
Material Cost /cft= 39.84 Tk
Shuttering Labour
For a column size 15 in x 15 in x10 ft
Casting volume of RCC work (15 in x 15 in x10 ft)
27.78 cft
Shuttering material
Wood 20.86 cft
8760.94 tk 420Tk/cft with carriage
2190.23 Tk using 4 times
Bamboo 252 ft
7.20 nos bamboo
2520 Tk 350/ each
630 Using 4 times
Material Cost /cft= 2.26 Tk
Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft
Shuttering material
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft
Shuttering material
Wood 10.92 cft
4587.73 tk 420Tk/cft with carriage
1146.93 Tk using 4 times
Bamboo 780 ft
22.29 nos bamboo
7800 Tk 350/ each
1950 Using 4 times
Material Cost /cft= 2.48 Tk
Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft
Shuttering material
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft
Shuttering material
Wood 10.92 cft
4587.73 tk 420Tk/cft with carriage
1146.93 Tk using 4 times
Bamboo 780 ft
22.29 nos bamboo
7800 Tk 350/ each
1950 Using 4 times
Material Cost /cft= 2.48 Tk
Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
1250.00 cft
Grand total =
Rate per Kg =
Supplying, fabrication etc of M.S. rod in RCC works : 72.5 / 60 grade deformed bar (1st Fl)
Considering 50 kg of work
1 Cost of materials:
i) M.S. rod: 72.5 / 60 grade 50 kg @ Tk. 61.00 Per kg. =
iii) G.I. wire 1 kg @ Tk. 95.00 Per kg. =
2 Cost of labour 50 kg Tk. 5.50 Per kg. =
Unloading, Equipment charge,
3 50 Kg @ Tk. 2.00 Per kg.
Utility
Total =
Contractor's profit 10.00% =
Overhead expenses 3.00% =
Grand total =
Rate per Kg =
Supplying, fabrication etc of M.S. rod in RCC works : 72.5 / 60 grade deformed bar ( 2nd Fl)
Considering 50 kg of work
1 Cost of materials:
i) M.S. rod: 72.5 / 60 grade 50 kg @ Tk. 61.00 Per kg. =
iii) G.I. wire 1 kg @ Tk. 95.00 Per kg. =
2 Cost of labour 50 kg Tk. 6.00 Per kg. =
Unloading, Equipment charge,
3 50 Kg @ Tk. 3.00 Per kg.
Utility
Total =
Contractor's profit 10.00% =
Overhead expenses 3.00% =
Grand total =
Rate per Kg =
ormed bar (GF)
Tk. 3,050.00
Tk. 95.00
Tk. 250.00
Tk. 62.50
Tk. 3,457.50
Tk. 345.75
Tk. 103.73
Tk. 3,906.98
Tk. 3,906.98
Tk. 78.14
med bar (1st Fl)
Tk. 3,050.00
Tk. 95.00
Tk. 275.00
Tk. 100.00
Tk. 3,520.00
Tk. 352.00
Tk. 105.60
Tk. 3,977.60
Tk. 3,977.60
Tk. 79.55
Tk. 3,050.00
Tk. 95.00
Tk. 300.00
Tk. 150.00
Tk. 3,595.00
Tk. 359.50
Tk. 107.85
Tk. 4,062.35
Tk. 4,062.35
Tk. 81.25
125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure (GF)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50 Tk per nos 3,600.00
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00 Tk per cft 360.00
3. Cement (portland) 1.75 bags @ 410.00 Tk per bag 717.50
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00 Tk per nos 480.00
5. Labour (Brick work) 100 sft. @ 10.00 Tk per sft 1,000.00
6. Scaffolding material & labour charge 25 sft. @ 12.00 Tk per sft 300.00
7. Local carriage, storage & sundries etc. L.S. 200.00
Total = 6,657.50
Contractor's profit 10.00% = 665.75
Overhead expenses 3.00% = 199.73
7,522.98
Grand
= 7,522.98
total
Rate per sft. = 75.23
125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure ( for 1st floor)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50 Tk per nos 3,600.00
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00 Tk per cft 360.00
3. Cement (portland) 1.75 bags @ 410.00 Tk per bag 717.50
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00 Tk per nos 480.00
5. Labour (Brick work) 100 sft. @ 11.00 Tk per sft 1,100.00
6. Scaffolding material & labour charge 25 sft. @ 13.00 Tk per sft 325.00
7. Local carriage, storage & sundries etc. L.S. 250.00
Total = 6,832.50
Contractor's profit 10.00% = 683.25
Overhead expenses 3.00% = 204.98
7,720.73
Grand
= 7,720.73
total
Rate per sft. = 77.21
125 mm brick work with 1st class bricks (Cement : Sand = 1:6) in superstructure ( for 2nd floor)
Considering 100 sft. work
1. Bricks 480 Nos. @ 7.50 Tk per nos 3,600.00
2. Sand (Local, F.M. 1.2 , with wastage) 18 cft. @ 20.00 Tk per cft 360.00
3. Cement (portland) 1.75 bags @ 410.00 Tk per bag 717.50
4. Labour (soaking & cleaning bricks, screaning sand) 480 No. @ 1.00 Tk per nos 480.00
5. Labour (Brick work) 100 sft. @ 12.00 Tk per sft 1,200.00
6. Scaffolding material & labour charge 25 sft. @ 14.00 Tk per sft 350.00
7. Local carriage, storage & sundries etc. L.S. 350.00
Total = 7,057.50
Contractor's profit 10.00% = 705.75
Overhead expenses 3.00% = 211.73
7,974.98
Grand
= 7,974.98
total
Rate per sft. = 79.75
10 inch Brick Work (1:3:6)
Considering 100 cft. of work:
1. Bricks ( With Wastage) 1152 Nos. @ 7.5 Per Nos. = 8,640.00
2. Sand (F.M 1.2) in/c wastage 46 cft. @ 20 Per cft. = 920.00
3. Cement (portland) 6 bags @ 410 Per bag = 2,460.00
Labour cost ( Soaking bricks,
4. 1152 Nos. @ each = 1,152.00
scraning sand) 1
5. Labour cost ( brick work) 100 cft. @ 12 each = 1,200.00
6 Scaffolding material & labour charge 25 sft. @ 12 Per sft. = 300.00
7 Local carriage, sundries, T & P etc. L.S. = 100.00
Total = 14,772.00
Contractor's profit 10.00% = 1,477.20
Overhead expenses 3.00% = 443.16
16,692.36
Grand
= 16,692.36
total
Rate per cft. = 166.92
Shuttering material
For a lintle size 20 ft x 10 in x5 in
Casting volume of RCC work (20 ft x 10 in x5 in)
6.94 cft
Shuttering material
Wood 5.76 cft
2417.19 tk 420Tk/cft with carriage
604.30 Tk using 4 times
Bamboo 56 ft
1.60 nos bamboo
560 Tk 350/ each
140 Using 4 times
Material Cost /cft= 107.18 Tk
Shuttering Labour
For a slab size 50 ft x 50 ft x6 in
Casting volume of RCC work (50 ft x 50 ft x6 in)
6.94 cft