Professional Documents
Culture Documents
Storage Shed
The building where the cement bags are to be stored must be a totally watertight
structure
The sidewall of the shed should have a minimum 9" brick masonry
plastered on both faces.
The roof of cement shed/godown can be either of a leak-proof reinforced
concrete slab or of adequately sloped water tight galvanized/asbestos
sheets.
The small windows are provided at the sill level and normally kept tightly
shut. Due to this, the moisture or rainwater is prevented from entering into
the shed.
The bottom level of the truck and the plinth of the cement
godown is of the same height.
The height of the plinth of the cement godown should be built in such a
way that the bottom level of the truck is of the same height as that of the
godown so that, the loading/unloading operations of the bags are done
conveniently.
All bags must be stored at least 0.3 m away from the walls. For better and
easy handling 1 m wide passages are required to be kept in such a manner
that old stock of cement can be removed without disturbing the fresher
stocks stored in the godown.
To reduce the air circulation the stacks of cement bags must be uce stored
as close as as close as possible.
When the bags are to be removed, care should be taken that all bags are
not removed from the top layer. It is recommended that bags should be
removed from two or three layers in a stepwise manner so that the pile is
stable and will not topple easily.
Owing to the pressure on the lower layers of bags the cement lumps
together within the bag. If there is moisture ingress from the floor and if
the bags in lower layers are not properly protected as suggested in points
hard set cement lumps will be formed in the bags. If there is no moisture
ingress caking of cement particles will develop within the bags and will
cause what is called a "Warehouse pack". This can be easily removed by
rolling the bag just before removing it from the storage shed.
Trucks should not be allowed to enter the storage sheds if the plinth of the
shade is at the road level. Dirt and moisture or even water will create
problems of cement contamination and damage.
Loading and unloading of cement bags onto the trucks should be done
under proper cover during the monsoons.
Cement should not be loaded onto the trucks directly. The plastic sheet
must be spread on the truck's floor and then cement bags unloaded over it.
Due to huge gaps between the wooden planks on the truck's floor water
often gets splashed onto the lower layers of bags thereby damaging the
cement in it.
Tarpaulin sheets are not waterproof. Water can seep through them if
collects on the top. It is therefore recommended that cement bags after
being loaded onto the trucks should be properly covered with plastic heets
and if 1 second layer tarpaulin cover over the if required i plastic sheet can
be given for more rigidity.
The open stockpile should be well covered with polyethylene sheets and
sheets be properly weighed down. This protects cement against moisture
ingress from the atmosphere. An additional layer of tarpaulin over the
plastic sheet can give better protection to cement and reduce the chances
of damage to the plastic sheet.
In this article, you will know the guideline or the techniques to be used for the
stacking and storage of cement. Following are the guideline to be followed for the
storage of cement.
Cement should be stored at the construction site only in an industrial shed or
in a building. Ensure that the shed or building should be dry, leakproof, and
having no moisture present. The shed or Building should have a minimum
number of doors, close-fitting, and windows and keep closed as far as possible.
Cement Bags should be stacked off on wooden planks in order to prevent
them from dampness or moisture. It should be store in such a manner that at
any point in time it can be inspected by an individual.
Cement shall be stored at least 6 inches to 8 inches above from PCC Bed or
some alternatives like Two flat bricks or wooden planks can be used.
Stacked Cement Bags should be placed at a distance of at least 600 mm from
all external walls.
Cement Bags should be kept close together in order to reduce the circulation
of air as much as possible.
The stacked height of cement Bags shall not be more than 10 bags in order to
prevent the chances of lumping up under pressure.
Stacked shall be stored in such a way that the First in First out (FIFO) system of
materials issue can be adopted.
Cement shall be issued for construction only after testing and confirming the
specification as per requirement.
Cement bags in store for more than 3 months shall be used only after testing
and confirming with objectives.
There should be a gap of a minimum of 600 mm between two stacked cement
Bags.
During the Rainy season or intend to store for a longer period in that situation,
cement bags shall be covered with a polythene sheet.
Cement bags shall be stacked in a manner to facilitate their removal and use in
the order in which they are received; a label showing date of receipt of cement
bags shall put on each stage to know the age of cement.
15. To guarantee the top quality of your cement, you should take the following precautions.
(a) Check the freshness of the cement before buying. It should be free from any lumps which cannot be
pulverized between thumb and forefinger.
(b) Bring on site only the number of sacks needed for a short period.
(c) Protect your cement from humidity. Store it off the ground (a simple wooden platform is suitable) in
a dry, well-sheltered place.
(d) Use the cement while it is as fresh as possible, and rotate your stocks properly.
What are the points to be checked before buying a cement?/14 things to consider before buying a
cement bag.
Following are the 14 points that should be observed, before buying a cement bag.
1. Brand name :
While purchasing the cement, you should always go for the branded cement having good popularity (5
🌟). The branded cement may cost 5 to 15% more, in comparison to other local cement, but they are
worth that price as there is no compromise in their quality. Check for the correct spelling of the printed
brand name, to confirm the originality of cement bags.
2. Trademark/logo:
All type of branded cement has their unique trademark logo printed on the bag as shown above. Look
out for those logos to avoid duplication.
3. ISI mark:
If the cement bag has no ISI mark (India ) printed over them, then stand apart from such bags to have a
longer life span for your construction works. If the manufactured cement bags are not according to the
industrial standards compliance( ISI ), don't buy such bags to maintain the quality of construction works.
4. IS code :
While manufacturing the cement, different types of IS codes are followed to meet the required
standards. You should check for the type of IS code ( as shown above ), to know the specification &
cement characteristics.
5. Grade of cement:
Cement bags are manufactured in various grades like 33, 43, 53, etc. to denote the cement cube
strength after 28 days of curing. You should look out for the required grade, that suits your work, to get
better results.
6. Type of cement:
Different types of cement are manufactured, to match the type of structural work, working situation,
and climatic conditions. Check over the bag, to know the type of cement you are dealing with.
The most common weight of the cement bags that are available in the market is 50kg. You can check
over the bags mentioned as net Qty -50kg., for the confirmation of actual weight.
The white cement bags are packed in different weights like 1kg, 10kg, 25kg, 50kg, etc. for purchasers'
convenience. Calculating the weight vs price for each type of bag, before buying, helps you to save
money.
8. Company address:
You do require the manufacturer's address for communication, in case you have any complaints to
register against the dealer or the quality of supplied cement.
9. Use no hooks:
MS hooks are used by some workers while loading & unloading the cement bags for transportation.
Although using hooks make them work fast, these hooks create small openings in the cement bags. You
have to look for such openings if any, while buying the cement bags. These openings give a passage for
the air to circulate in the bags, which ultimately decreases the cement strength. Strictly avoid such bags,
to maintain the cement standards.
Cement loses its original strength gradually as the day progresses from its production date. Any bags
older than 3 months from the manufactured date are unfit for the construction works. So, check the
manufactured week and month, to know the expiry date of cement. Always go for the fresh cement to
utilize its full specified strength.
11.The printed price (MRP ) :
Observing the MRP of the cement bag helps you to know, whether you are paying the right amount of
money or the delivered bags are overpriced.
Refilling the cement by mixing with other components in the factory-made bags can be found out by
checking the bag stitchings. To avoid duplicate adulterated cement, check the cement bag stitchings
precisely. The restitched bags certainly look different, as they cannot mimic the original factory-made
stitching.
Always, try to buy the cement from the authorized outlet in your locality, to avoid duplication and to get
a fresh stock of cement.
If the bags in the godowns are not stored according to the procedure, the cement in the bags may
develop tiny grain-like lumps due to the absorption of atmospheric moisture. Press the bag hardly and
pinch the corner end of the bags with your fingers, to feel the powdery softness of cement. If you feel
stiff bag with grainy feelings, avoid such bags.
Note:
1. The printed location over the cement bags are not alike, & they are unique to each brand. For your
observation, the MRP & manufactured date of the cement bags of two different companies are shown in
checklists no. 10. & 11.
field test for good quality of cement/field test for cement/cement tests/different site test for cement
Following are some field tests, that should be carried out to know the quality of cement.
1. Date of packing:
2. Lumps test:
It should be free from any lumps which might be formed due to the atmospheric moisture.
3. Colour test:
4. Float test:
When little quantity of cement is poured into a bucket of water, some part of it should float on water for
a few seconds, forming pockets before sinking.
5. Setting test:
A thick paste of cement should be applied evenly over the piece of a glass. After an initial setting time of
30 minutes, it should be kept in water for 24 hours. Next day, when you test the cement, it should be
hard in a single piece, if it breaks into several pieces then the cement is not of good quality.
6. Adulteration test:
When cement is rubbed between two fingers, you should get the smooth feeling of fine powders. If you
feel the rough grainy texture, then there is a possibility of adulteration.
7. Temperature test:
When kept over the palm, you should feel the normal atmospheric heat. It should not be much warmer.
Selecting the water to use
16. The water should be clean and neutral or slightly alkaline (pH 7 to 8.5). It should be free from organic
matter, oil, alkali or acid. Avoid using saltwater or a water too rich in sulphates (more than 250 ppm).
17. If you have to use brackish water or dirty water, add a tablespoon of soap powder for every sack of
cement used. Dissolve the soap into a small amount of water and add it to the mix.
Accurate cutting, bending, and fixing of steel bars are a must, so that correct
cover is maintained and steel is adequately protected.
While the rounded mild steel bars are manufactured by hot rolling of mild steel,
the high yield steel is made by either hot rolling a low alloy steel or by cold
twisting and stretching of the mild steel bar.
By visual inspection the engineer can know if the bar is plain mild steel, hot rolled
deformed, cold worked deformed ribbed (TOR) or cold worked twisted (TOR).
Site Arrangements
Storage
The bars must be laid, so that the correct type,size,and length are located
easily without double handling.
The bars must not get contaminated by materials like mud,oil, and grease.
The bars should be stored on a raised platform or wooden sleeper/precast
concrete supports, so that,they do not get contaminated with mud,water,
moisture,or humidity and start rusting. The supports should lose enough so
that,bars do not develop a band on account of improper storage. In
addition, a suitable all-around protective cover of polythene sheeting is
preferred and it remarkably improves the performance of reinforcement
steel as it prevents rusting to a great extent during storage.
Long storage periods especially in high humidity conditions and monsoon
periods should be avoided. Alternatively, steel reinforcement must be
properly covered and protected from rain and moisture.
Generally, in our country, and bending of steel bars is done manually. Even coiled
steel is straightened manually at the site. Equipment is now easily available for
cutting, bending, and straightening reinforcement steel. The job can be done must
faster, giving better quality and economy.
The cutting area should be as close to the storing area as far as possible.
So that handling is simple and does not require long leads to transport. The
handling of the bars had to be done properly and carefully during each and every
operation. Avoid throwing the bars as bends and kinks will develop at undesired
locations which will be difficult to straighten at a later stage.
Before cutting, the bars should be correctly selected. The type of steel, diameter,
and length should be properly checked and verified. Proper planning of cutting
schedules is necessary. This can prevent unnecessary wastage and scrap
formation.
It is recommended to use steel tapes for measuring bars as there are fewer
chances of an error when steel taps are used.
The cutting length must be properly established from the bar bending schedules.
This is extremely necessary when bars required for stirrups are cut. If the length
cut is short, then the stirrups may not fit properly or may create problems of
increased cover or decreased effective depth. Similarly, if the length cut is more,
then the stirrup will be fixed in a skew manner and result in less cover or
congestion of reinforcement at certain locations.
Bending should be carried out with proper machines whether hand operated or
powered. The use of manual makeshift methods will produce poor results and are
dangerous.
It is also recommended not to leave the steel bars exposed for a long period of
time (more than two weeks) after they are fixed. This will cause rusting of steel
and subsequent staining of concrete.
The effect of rust on the bond between steel and concrete is often a debatable
issue on site. A little rust or brownish tinge on the bar is not harmful to reinforced
concrete. However, loose mill scales or excess flaky rust must be removed by firm
tapping or scraping. Reinforcement steel, before it is placed and embedded in
concrete, reacts with oxygen and moisture in the atmosphere while it is being
transported and stored. This causes the formation of a thin film of rust which is
reddish-brown in color. This reddish-brown film, so long as it is skin deep, is
considered desirable.
This brownish coating is said to improve bond quality and is not easily removable
even after wire brushing or scraping. The brownish tinge can remain and it needs
not to be removed. Besides improved bond quality,
this thin brownish film on the surface of the reinforcement also offers passivation
to the steel surface against corrosion.
Steel that is stored for a long period of time also needs to be checked for
cleanliness and excessive rusting before cutting and bending is done.
To protect the reinforcement from corrosion and for the composite action of the
reinforcement and concrete to be effective, it is absolutely necessary for the steel
bars to be surrounded by sufficiently impermeable strong concrete. If moisture
and chlorides penetrate into concrete the steel bars will rust and due to the
formation of ferrous oxide or ferrous hydroxide, there will be an expansion in the
volume of steel nearly 7 to 8 times its original size. This increase in the volume of
steel creates tensile forces in concrete and exposes the concrete to further attack.
It is important to use the correct size cover blocks to give the required depth of
protection to steel reinforcement. The cover blocks should be spaced at the
correct distance to ensure adequate and uniform protection to steel
reinforcement throughout. It is equally important to provide adequate cover to
both, main reinforcement as well as stirrups and ties which generally project
beyond the main reinforcement.
Mortar cover blocks are best made using cement mortar in 1:2 cement to sand
proportion, and water is added just sufficient enough to give dense concrete with
low permeability. Adequate precaution must be taken so that any wire cast into
the blocks is kept away from the exposed surface. If this is not done there will be
a risk of rusting or rust stains on the concrete surface.
Metal spacers should not be used when the structure is located in a corrosive
environment or is in contact with water. Do not use the stone chip timber pieces
as permanent covers/spacers.
The top and bottom reinforcement in suspended slabs have to be placed and
fixed correctly before concrete placing starts. They have to be properly secured so
that they are not displaced changing the effective depth and cover at the top and
bottom. Smaller cover blocks have to be used bottom. Mild steel chairs of
adequate size, the shape must be placed at such spacing that it can carry the top
steel and keep the required effective depth between the top and bottom steel,
uniformly and correctly. The cover blocks at the bottom of the steel cage should
be strong enough to take the foot load of workers.
In cantilever slabs, due to inadequate cover, it is observed that the top
reinforcement shifts to the bottom due poor fixing and movement of workers
over the bars during the concrete placing and compacting process. This often
results in failures, as the steel which is required at the top of the slab to take up
the required tensile forces and moments collapses or settles below due to the
reasons given above.
In the case of the slabs on grade which are singly reinforced, it is often convenient
to place the concrete up to a given level and then place the steel bars or steel
fabric before placing the rest of the concrete above the steel.
Never attempt to place the reinforcement age on the formwork and later try to
raise it as the concrete is being placed. This will never give the correct cover of
effective depth.
If spacers are allowed on the face of a beam or wall but not on the opposite face,
the reinforcing cage must be held in position by pulling it towards the formwork
on one side by means of wires attached to the cage and passing through holes in
the formwork. The wires are pulled towards the formwork so that the spacers on
this side prevent reinforcement from actually touching the formwork, thereby
giving a correct cover. This will also ensure proper cover on the side without
spacers. However, all wires must be removed soon after concrete is placed or it
will cause rust strains and future durability problems.
As we know that steel bars cover 25 -30% of the overall cost of the building so it is
very crucial that steel bars must be handled and stored with precaution on the
site. There are different processes or operations where laborers need to take care
of steel bar such as unloading, Stacking, Cutting, Bending, Fabrication, etc.
Reinforcement has the capability to resist lateral forces and provide strength and
ductility to the buildings, so it is very necessary that all these loading and
unloading operations should be done properly on site. Steel reinforcement is
highly corrosion in nature when it comes to direct contact with water and
moisture.
A separate area with fencing wire should construct at the site in order to
store the reinforcement.
Make ensure that area should be free from moisture and dust in order to
avoid rusting.
Ensure that the storage area should have proper drainage facilities.
Steel bar should be stored on the basis of diameter and length in order to
avoid confusion for identification.
All-steel bar tags or Mark should be at the same end because it will help the
person to identify the particular Bars.
Place the steel Bars on wooden sleepers so that they cannot touch the
ground.
Storage of Construction Materials
Cover the steel bar with a polythene sheet during nighttime that prevents
the reinforcement from moisture.
In order to protect the steel bar from scaling and rusting, coat the steel
reinforcement with cement wash.
If we stored the reinforcement for long period, then it should be stack at
least 6 inches above the ground level.
There should be separate storage for cut pieces of steel.
Following are the guidance regarding stacking and storage of Aggregate at site.
or. 5 5 1
or 5 1 0.5
For Fine Aggregate (sand), the suggested size of stacks are as follows;
or 5 5 1
or 5 1 0.5
Stacking and storage of Bricks at the site involves proper planning for space and
Location. The storage location of Bricks shall be near to the site because it will
reduce transportation time. While allocating the place, make sure that there
should be space for the vehicle to unload the Bricks. During unloading or handling
of bricks, there is a possibility of damage to corners, edges, or other parts of the
bricks that shall not be allowed. Following are the guideline to be followed for the
storage and stacking of
A good clay brick should have uniform Rectangular shape and size.
It shall be manufactured either hand or by machined.
All the arris should be straight edges.
It has to be well burnt.
Brick should have a uniform in deep red color that shows the uniformity in
chemical composition.
It should be hard enough to resist the compressive load.
It should be free from holes, lumps, or grit.
The surface of the bricks should not be smooth because mortar will not
stick to it.
It should be free from any kind of cracks.
Brick should have a uniform texture.
It should have surfaced so hard that cannot be scratched by the fingernail.
Good quality of bricks should have a metallic ring when one brick stuck
against another brick.
It should not break when it falls from a height of about 1.5 m on the
ground.
Water absorption of bricks shall be less than 20% of its dry weight when
immersed in water for 24 hours.
The percentage of soluble salt should not exceed 2.5 percent in burnt
bricks.
Silica (SiO2)
Good quality of bricks contains 50-60% silica. The presence of Silica controls
cracking, shrinkage, and warping of raw bricks. Aluminosilicate is formed when
Silica (SiO2) reacts with Alumina (Al2O3). If the amount of silica is more than
required then clay brick particles lose its cohesion between them. Due to the
excess amount of silica, a brick becomes brittle in nature.
Alumina (Al2O3)
Alumina is one of the compositions of bricks which play majors role in terms of
plasticity. Due to its plasticity property bricks can be molded into a rectangular
shape. If the amount of Alumina present in bricks is more than required, Crack
occurs in bricks when clay gets dried.
Lime (CaO)
In brick, the amount of lime is less than 10%. Lime prevent the brick from
shrinkage when it is under drying conditions. Excess amount of lime makes the
brick melt and it may lose its shape and size.
The main Function of Iron oxide is to provide red color to the bricks. The presence
of oxygen on burning helps the brick to achieve the red color and due to the
absence of oxygen, it will achieve dark brown or black color. If the amount of Iron
oxide is more than required that makes the bricks dark blue. Iron oxide enhances
the properties of impermeability, strength, durability, and hardness.
Magnesia (MgO)
Field Test
A field test is more important than laboratory results because it gives immediate
results. It plays a crucial role in terms of strength and durability. There is a
different practice to test the cement on site. Here is some applied method to
check the quality of cement.
Once the cement bags carrying vehicles are unloaded, Engineers should check the
color. Make sure that the color should be uniform and grey.
Once you insert your hand in cement bags, you will feel smooth or cool when
touched or rubbed in between fingers. If you feel cool then it indicates the quality
of cement is good, if not which means it is not suitable for construction work.
It should be free from lumps because it affects the strength of concrete. IF bags
containing lumps should be rejected for construction work.
Storage Specification
Keep the bags 1 foot from wall for the protection from moistures.
15 Numbers of bags should be placed in one row.
Cement bags should be placed 15- 25 cm from the floor level. Make sure
that it should be kept on wooden sleepers.
Bags should be stacked in 10-12 layers.
There should not be any opening in the storage room because to reduce
the moisture.
Silt.
Clay.
Salts.
Organic matter.
80 mm, 63 mm, 40 mm, 20 mm, 16 mm, 12.5 mm 10 mm, 4.75 mm, 2.36 mm.
10 mm, 4.75 mm, 2.36 mm, 1.18 mm, 600 micron, 300 micron, 150 micron.
Medium 2.6-2.9
Fine Aggregate will not stick with hand. If it contains clay will stick and if
the color of the palm changes that indicate fine aggregate has clay and silt.
If you add a small quantity of sand in a glass of water if it settles
immediately which means it is suitable for construction work if the sand
form different layer at the top that indicates that sand has a layer of silt at
the top. The thickness of the silt layer should not be more than the
thickness of the layer by 8%.
If we add caustic soda in a glass of water and later add sand inside the
glass, if water changes the color to brown then it shows that it has some
organic impurities which are not suitable for construction work.
It should be free from lumps, vegetable matter, organic impurities, etc.
Bulking of sand.
Silt content
Fineness modulus
Sieve analysis
H1= height of water in another container. Add the sand in water and measure the
height of sand in water is H2.
It is obtained by
13. Important information obtained from the different tests of Fine Aggregates.
Less than 5% moisture content in the fine aggregate is preferred for construction
work.
If Fine Aggregate having Fineness modulus greater than 3.2, then it is not suitable
for concrete.
a. 2% 15%
b. 3% 20%
c 4% 25%
d. 5%. 30%
Habitats, Vegetable matter, grass, etc which affect the setting and binding
property of concrete.
It should be chemically inert.
Fine Aggregate should be free from silt and clay.
Fine Aggregates should not contain more than 3 percent of silt.
It should not contain salts that contain sodium chloride that causes
corrosion to reinforcement.
The following are the 11 Important Points to Remember for Civil Engineer about
Aggregates.
Definition of Aggregates.
Coarse Aggregates are the particles which are retained on 4.75 mm sieve. Coarse
Aggregates are larger in size as compared to fine aggregates. It obtained by the
processing of igneous rocks such as pumice, scoria, and tuff. Some of the most
common natural aggregates are silica sand, gravel, crushed lightweight stone, etc.
It is used to produce concrete and any other stonework.
The I.S. sieve used for grading of Aggregates is different sizes such as 80 mm, 63
mm, 40 mm, 20 mm, 16 mm, 12.5 mm, 10 mm, 4.75 mm, 2.36 mm.
The Size of Coarse aggregates ranges from 4.5 mm to 80 mm. The sizes of
aggregates depend on the grade of concrete is to be made. For normal house or
Residential building, 10 to 20 mm aggregates sizes are used. The angular shape of
the aggregate is best for concrete making. The other sizes of aggregates used for
concrete making are 40mm, 20mm, 12.5 mm and 10mm, etc.
Fineness Modulus
20mm 6 to 6.9
75mm 7.5 to 8
Specific Gravity
Angular Aggregate
Angular particles have sharp, angular and rough and have High Surface area. Due
to the rough surface, It has a strong bond between the surface of angular
Aggregate and cement paste. It requires more water due to rough surface. It has a
high W/C ratio. Coarse Aggregate has low strength as compared to Rounded
aggregates. It is good in workability.
Flaky Aggregate
Flaky aggregates are one of the types of aggregate which is flat and elongated in
shape. Elongated aggregates are those aggregate whose length is 1.8 times its
mean dimension.
Rounded Aggregates
These aggregates are generally found in rivers and seashore. It has a smooth
texture. Less surface area. Due to the smooth surface, it gives poor concrete
because due to the lack of bonding between the surface aggregate and cement
paste. It requires less water due to the smooth surface. It has a low W/c ratio.
Due to the low W/C ratio results in higher strength as compared to angular
aggregates.
Characteristics of Aggregates
Bond strength.
Shape and texture.
Moisture content.
Bulk density.
Specific gravity.
Fine modulus.
Soundness.
Hi…
1.Footings concrete
1 Starters concreting
3 soil backfilling
4 water consolidation
6 marking on PCC
1 Starters concreting
2 columns casting
3 staicase concrete
5.Brick work
1 Hacking
6.Plastering work
1 Electrical conduting
7.Waterproofing
8.Painting work
9.Tiles work
10.Joinery works
1 internal final
9 handover key
Reason
The lime / sanla should be properly stacked before use. Slacked lime should be
left for some week to cool before use.
Reason
a) Movement of background
b) Shrinkage movement of
plastering mixes
c) Excessive trowelling
subsequent to plastering
3. Defect Observed= Falling of plaster
Reason
d) Absorption of water from mortar which is turn loose the strength of mortar
atleast 7 days
requirement
Reason
Reason
c) Movement in the plaster itself on account of the expansion (in case of lime
sand plaster) during drying
c) Keep plaster cool which is directly exposed to sun heat during its young age by
the help of wet gunny bags or by sprinkling water over it.
c) Cracking in the form of closed net and shrinkage cracks in honeycomb form
d) Structural cracking
Reason
b) These cracks appear due to movement of excessive silt after repeated dry &
wet conditions
a) Chicken mesh is applied on junction after carefully sealing the joint by rich
mortar & khadi maal is applied at junctions
b) If the silt content in sand is mare than 7% wash the sand before use
This is due to bond failure between ceiling concrete & coat of plaster
Closely hacking (tacha) @ Nos. notches/sft (500 nos./m2) & cleaning the ceiling
for making it free oily substances will sort out the problem
Reason
These appear on surface when plaster is applied on chicken mesh which is loosely
placed
Tight fixing of chicken mesh & cutting the excess projections of the mesh which
are coming out of plaster will sort out the problem
Reason
This is due to excessive dampness at certain points which make it soft. Reason of
such softness is undue thickness of the finishing coat, presence of deliquescent
salts & excessive suction of the undercoat
Improve the quality of workmanship & train the masons for good work
11.. Defect Observed= Peeling off top finish layer of internal plaster (Sanla /
Neeru finish)
Reason
a) Bad quality of sanla may lead to peeling off the top layer
b) Immediately apply the neeru on the base coat before setting of mortar
Formwork or shuttering work is a very delicate and precise job. A good shape or
size of a concrete structure depends on the precision of the shuttering, hence it is
a very important activity in construction that shall be carried out carefully
1. The material of the formwork should be cheap and it should be suitable for
re-use several times.
2. It should be practically waterproof so that it does not absorb water from
Concrete, Also, its shrinkage and swelling should be minimal.
3. It should be strong enough to withstand all loads coming on it, such as a
dead load of concrete and live load during its pouring, compaction, and
curing.
4. Shuttering should be stiff enough so that deflection is minimum.
5. It should be as to be light as possible.
6. The surface of the formwork should be smooth, and it should afford easy
stripping.
7. All joints of the formwork should be stiff so that lateral deformation under
loads is minimum. Also, these joints should be leakproof.
8. The formwork should rest on non-yielding supports.
Engineer.
Formwork/shuttering Supervisor
Skilled- Carpenter.
Semi-skilled Carpenter or Helper.
Tools-Used-In-Shuttering
Hard Wood (batten)- Battens are required to make the shuttering board.
there are different sizes of battens required for different purposes.
Shuttering Ply– Plywood is the very common material used in shuttering
work to make the form. The standard size of a shuttering ply is 2400mm X
1200mm and 12mm thick.
Shuttering Steel Plate– There are different sizes of steel shuttering plates
available but the standard sizes are 1200mm X 600mm, 1200mm X 500mm,
1200mm X 250mm.
Scaffolding or Stagging – scaffolding material is required for formwork
stagging means formwork for slabs
Stirrup Heads– A stirrup head is a “U” shaped head used to support the
shuttering or formwork. It is attached in front of a scaffolding pipe.
Telescopic Prop– Telescopic props are the vertical members available in
different sizes used below the beam or slab to support the formwork
structure.
Telescopic Beam – Telescopic beams are the steel adjustable steel beams
provided below the slab shuttering in case of heavily loaded or larger spans.
This beam is used to carry and distribute the load of the temporary
formwork.
Tie Rod & Bolt– Tie rod and blots are used to tie up the formwork.
The list does not end here, but these are the most commonly used shuttering
equipment in construction work. There are many more types of shuttering
materials that are used depending on the construction duration, budgets, and
quality needs. Such as Aluminum Shuttering, Plastic shuttering, Fabric shuttering,
etc.
Forms are classified as wooden, plywood, steel, combined wood-steel, used for
reinforced concrete, and plain concrete structures. Timber is the most common
material used for formwork. The disadvantage of the wooden formwork is the
possibility of warping, swelling, and shrinkage of the timber. However, those
defects can be overcome by applying them to the shuttering water-impermeable
coatings. This coating also prevents the shuttering from adhering to concrete and
hence makes the stripping easier.
Steel shuttering is used for major work where everything is mechanized. Steel
formwork has many advantages, such (i) it can be put to a high number of uses,
(ii) it provides ease of stripping, as follows : (iii) it ensures an even and smooth
concrete surface, (iv) it possesses greater rigidity, (v) it is not liable to shrinkage or
distortion. However, steel formwork is comparatively more costly.
However, the classification of the shuttering can be made in two ways. One is in
terms of Material Used another in terms of Technique Used in shuttering.
1. One use good quality of Film faced Plywood, Partially Seasoned Plywood,
Curved Plywood for formwork which is rigid and closely fitted, with
sufficient strength to support wet concrete.
2. We shall ensure the centering plates, planks, or plywood are properly
cleaned
3. We shall take care of Proper checks for line, level, plumb, dimensions,
Reinforcements tied and placed as per drawing, and supports placed
outside of formwork before starting concreting activity.
4. We shall ensure the proper placing of cover blocks on the forms.
5. We shall ensure Shuttering to be checked in stage-wise.
6. We shall ensure the Position of pockets, Anchor Bolts, and Insert to be
carefully placed and tied before placement of concrete.
7. We shall take care to apply a suitable release agent for forms before the
placement of reinforcement and after de-shuttering, proper cleaning of
formwork shall be made.
8. We shall use tape or foam sheets for filling the Gaps.
9. The area inside the formwork shall be cleaned by hand, blower, or other
means before the start of concrete.
10.We shall ensure the top level of the concrete is marked on the form and the
same level is carried out throughout the form.
11.We shall take care in providing extra supports to prevent the bulging of
formwork.
12.We shall Leave slab formwork undisturbed till concrete gains 70% of the
required strength.
13.We shall take care not to damage the concrete while stripping the forms
off.
14.Removal of shuttering in view of time period should be as detailed below.
Removal Of Formwork
When de shuttering takes place, the components of formwork are removed and
then reused for the forms of another part of the structure. Such forms, whose
components can be reused several times are known as panel forms. In contrast to
this are stationary forms which are made for individual non-standard members
and structures, which have no repeatable elements, and also for structural
members, the form of work that cannot be stripped.
4 Slabs over 125mm thick and soffit formwork of Minor Beams (Props to
refixed immediately after Removal of formwork) 18 days 14 days
To conclude,
Shuttering can be explained as a temporary mold to hold the concrete mix until it
gets heard. Formwork is synonymous with shuttering.
Shuttering oils are used to lubricate the shuttering board or plate which makes it
easier to remove the shutter after concreting. And it shall be applied to the
shuttering board or plate properly, first by scrubbing and cleaning the shuttering
board or plate then applying the Shuttering Oil using a brush evenly throughout
the board or shuttering plate.
Tags: Formworkshuttering
TESTING OF CONCRETE.
Tamping rod of steel 16mm in diameter, 600mm long and rounded at one end.
This test is carried out to determine if fresh concrete is too hot or too cold. Hot
concrete stiffens rapidly and develops lower strengths at later stages. As per the
I.S., in hot weather, the temperature of hot concrete should not exceed 38
degrees centigrade while placing. In cold weather, a minimum temperature of 4.5
degrees centigrade is prescribed for the concrete at the time of placing.
Minimum 3 liters of fresh concrete is required for the test. At least 3 readings in
different parts of the batch should be taken. If the concrete is too hot. the
subsequent batches can be mixed by using cold water. Also, cool the aggregates
by sprinkling them with water.
1. Clean the standard cube moulds, 6 Nos. thoroughly & tighten all the nut-
bolts properly.
2. Apply oil to all contact surfaces of the mould. The size of the mould is
normally 150mm x 150mm x 150mm.
3. Take random samples from the mix in a ghamela, while concreting.
4. Pour concrete into the cubes in 3 layers.
5. Compact each layer with 35 Nos. of strokes with the tamping rod.
6. Finish the top surface by thapi trowel after compaction of the last layer.
7. Cover the mould by a damp Hessian cloth immediately to prevent loss of
water.
8. Each specimen should be taken from different locations of the proposed
concreting.
9. After 24 hours, remove the specimen from the control of the quantity of
three the mould.
10.While removing, take care to avoid breaking of the edges.
11.Code the cubes with paint or marker. Coding should be self-explanatory,
showing the site name, concrete location, building no., and the date of
casting.
12.Submerge the specimen in clean, freshwater until the time of testing.
13.Test 3 specimens for 7 days & 3 specimens for 28 days curing concrete.
C. TESTING OF CONCRETE CUBES
For testing the cubes in the in-house lab of the organization, observe the
following procedures
D. AGE ATTEST
Tests shall be carried out at ages prescribed for the test, the most usual being 7
days and 28 days.
E. PRECAUTIONS
Remove the mould after 24 hours and store the specimens in clean,
freshwater.
The place where specimens are stored shall be free of vibrations.
The water in which the specimens are submerged shall be replaced every 7
days.
Specimens shall not be allowed to dry out at any time before testing.
A non-destructive test is defined as one that does not damage the structural
element or member under investigation.
Plinth beam is a reinforced concrete beam constructed between the wall and its
foundation. It is a framed structure provided at or above/below ground level that
takes the load of the wall built on top of it.
Plinth beam is provided to prevent the extension or propagation of cracks from
the foundation into the wall above when the foundation suffers from settlement.
Plinth beams distributes the load of the wall over the foundation evenly.
Plinth Beam
1. Plotting of grid lines for the center of the column above the plinth floor
slab.
2. Locating and marking the centers of columns.
3. Binding & placing column reinforcement above the upper floor slab, as per
the required height, considering lap length of the bar.
4. Check for column reinforcement & their arrangements as per the drawing.
5. Ring spacing and their arrangements as per the R.C.C. drawing.
6. Proper binding of reinforcement with binding wire.
7. Fixing concrete or P.V.C. cover blocks to reinforcement.
Hacking of column
The following practices is done on-site to check the spacing between the stirrups
thought the beam.
First, find the spacing between stirrups from the drawings. (Let’s say 4
inches).
Measure the length of Main bars from face up to 6 feet (let’s say).
Find the Number of stirrups.
Number of stirrups = Length/Spacing +1
= 6 x 12/4+1 = 19 Nos.
Now check the number of stirrups. IF the number of stirrups is matching
with 19 till 6 feet length, then the spacing between the stirrups is correct.
Formwork plates shall be uniform in the surface. Uneven surface in the shuttering
board shall not be allowed.
Wooden shuttering shall be properly cleaned and free form concrete particles if it
is used formwork
The shuttering plate shall be rigid, firm, and durable so that it can carry
movement load.
The size of the formwork of each slab panel must be checked as per
Approved drawings.
Check the Slope and level of formwork of each slab panel.
Shuttering oil shall be used on shuttering plates in order to remove the
formwork after concrete gets strength.
Check the diagonal of slab formworks.
Check that vertical formwork shall be used along all the edges of the slab,
staircase void, internal voids, etc.
All the shuttering gaps shall be properly sealed or closed so that there is no
flow of slurry through those gaps.
The entire gap shall be made leakage proof by masking tape.
Before concreting of the slab, shuttering gaps such as beam-slab junction,
beam junction, columns, etc shall be supervised.
Mark the thickness level of the slab on each and every column.
Water tightness shall be done near column junctions.
The side plank of the slab along the periphery has to be supervised.
Slab shuttering board should be supported by Wooden batten also called
Chavis at an interval of 2 feet.
Ensure the steel props shall be tightened properly.
Check the sizes of wooden props, plumb, and soundness.
Runner spacing for slab formwork shall not be more than 1 feet.
Butt spliced on wooden props shall not be allowed.
Check the nut-bolt/shuttering clip is properly tightened or not.
CHECKING OF SHUTTERING
1. Height of slab from the plinth slab level.
2. Quality of shuttering material.
3. To ensure fixing of the cap on the column to take the load.
4. Width of the beam bottom plank. To ensure proper fixing of the beam
bottom over the cap.
5. Line and level of the beam bottom.
6. Depth of beam as per the R.C.C. drawing.
7. Proper fixing of props for the bottom in line and plumb, at every 2’0″ (0.60m)
interval.
8. For packing the below props, only one or two wooden plank pieces are
allowed. (Brick or blocks are not permitted).
9. Bamboo bracing for joining, prop to prop, at 4’0″ (1.2m) height from the
floor.
10.Proper fixing of the side of the beam in line, level, and plumb.
11.Support to the vertical joint of shuttering for 24″ (0.60m) beam or 3O”
(0.75m) beam.
12.Gaps in beam sides should be filled.
13.Ensure fixing of the steel plates over beam sides, in flush position.
14.Slab plates should be supported by 3″ x 3″ (75mm x 75mm) chawis at 2’0″
(0.60m) distance, centre to centre.
15.“Side plank’ for slab panel periphery.
16.Individual-level of each bay of the slab.
17.Mark the thickness of the slab.
18.Check if the joints of the plate and ghabadi work is watertight.
19.Oil the slab plates.
20.Internal panel measurements, beam to beam & diagonal of the panel.
21.Location and depth of the sunken slab.
22.The outer line of beam sides.
23.Check for room sizes & diagonals.
24.Check if the junctions of columns and beams are watertight.
To check the concealed electric conduit work for the slab, as per the drawing and
I.S.I. mark on the P.V.C. pipes. Note down the length of all pipes for billing
purposes.
1. Check the junctions and all electrical points as per the electric layout, the
position of fan points, M.S. boxes, junction boxes.
2. Avoid breaking of pipes during concreting.
3. Check the slab & the certificate from the architect.
4. Check the slab & obtain a certificate from the R.C.C. consultant.
5. Sieve analysis for sand to be carried out in advance, for the concrete mix
design.
6. To measure the silt content of sand.
when it is accompanied by the bar bending schedule. R.C.C. fitter gets familiar with the bar
cuttings and bent-up bar lengths before cutting of steel and mistakes in bending can be
avoided. Bar bending schedules also help in checking the slab reinforcement. With rapid
increases in the cost of steel, cost-effectiveness during construction can be maintained with the
use of a bar bending schedule. Every kilogram of extra steel used is a national waste and can be
avoided with the help of bar bending schedules.
1. Cutting should be done for the footing mesh (jali) bars considering the allowance for ‘L’
and covers on all the sides.
2. Footing jail should be prepared by tying the bars. Care should be taken to tie each and
every junction with a binding wire.
3. Cut the column bars to the required length considering the allowance for base ‘L’.
4. Cut the bars for column rings, single or double, as per the requirement of the length
accordingly.
5. Rings should be prepared on the fitters’ platform, considering the width and breadth of
the column and deduct the cover from the same, e.g. for a column of 150mm width and
300mm breadth, the ring can be of size 100mm x 250mm, considering 25mm cover on
both faces.
6. Footing jali should be kept in the footing shuttering with a column base tied to its
center, with binding wire. The center of the footing should be matched with the jali of
footing.
7. The proper cover should be maintained from the sides as well as from the bottom.
1. Consider floor to floor height and lap length 45D to be added into the length. (D is the
diameter of the bar).
2. Cutting should be done first for the main reinforcement.
3. Cut the bars for rings of the column, to the required length as explained earlier.
4. For lapping, make the joggle if the bar diameter is more than 12 mm.
5. Prepare column on the fitters’ platform by tying the rings to the main reinforcement, if
the size & No. of bars are not heavier.
6. Shift the column to the slab and erect it in the required position and tie it to the dowels
below the floor columns.
7. Care should be taken to tie the dowels of the below floor columns firmly, to the upper
floor columns.
1. In R.C.C. drawings, the number of bottom bars, bent-up bars, and top bars along with
details of rings is normally mentioned.
2. Fitters generally take the actual measurements of the beam after shuttering and then
proceed for the cutting of the steel.
3. Cutting should be done beam-wise & for the total number of beams, required for the
slab.
4. Tie a chit of paper for easy identification, to the bunch of bars.
5. Then cutting of the rings should be done. Rings should be prepared out of these cut
bars.
6. The beam can be bound on the fitter’s platform along with the bent-up bars.
7. Shift the bound beams to the shuttering of the slab.
8. Place these beams to the position with proper anchorage in the end columns.
9. For continuous beams, bent-up bars should be properly extended in the adjacent beams
and tied with binding wire.
10. The proper cover should be provided to the bottom and sides of the reinforcement.
1. Take the measurement of the cutting length of the slab reinforcement and accordingly
the cutting can be done.
2. For continuous slabs, consider the projection of the bent-up bars in the adjacent slab
while calculating the cutting lengths of the slabs.
3. The cut bars should be stored in bunches slab-wise and can be transferred on the slabs
accordingly.
4. Marking for the c/c distance of the bars should be done on the slab plates with the help
of chalk.
5. Lay the main reinforcement as per the marking.
6. Place the distribution steel on the main reinforcement and every junction should be tied
with binding wire.
7. Bent-up bars should be bent at the required length from support as per the type of slab,
i.e. continuous or simply supported, etc.
8. Place the chairs under every bent-up bar to maintain the top reinforcement at the top.
9. Bent-up should be lifted considering the slab cover and slab thickness.
10. All hidden beams should be placed such that the center of the hidden beam should be
considered the center of the proposed wall on that beam.
11. The ring of the hidden beam should be bound such that it is just 1″ (25mm) less than the
thickness of the slab. e.g. for 5″ (125mm) thick slab, the ring for H.B. should be 4″
(100mm) in height.
1. For the water tank, reinforcement of the bottom slab, along with the beams, should be
placed and bound properly.
2. Through this slab reinforcement of vertical pardi (R.C.C. thin wall) should be taken with
necessary anchorage. Vertical bars of the pardi are normally erected first.
3. Provide Chamber bars at the corner as per the design.
4. Generally, double jali is provided to the bottom slab.
5. After casting of the bottom slab, horizontal reinforcement of the vertical pardi should be
bound with due care, on anchorage inside the pardi.
6. Provide horizontal reinforcement at both the faces of Pardi. Ensure a proper cover to
this reinforcement. Side chamber bars to be provided as per the specified spacing.
7. After casting off the side Pardi, the form-work of the top slab should be bound as per
the design.
8. Provide a manhole for the top slab along with a vent pipe hole. For the manhole, extra
bars should be provided along the periphery of the opening.
9. If cut-pieces are to be used for the top slab, the lap length of the same should be 69D,
where D is the diameter of the bar. Care should be taken to provide laps in a staggered
manner.
reinforcement-details-for-chajja
1. The top bars of beams are not bent in 90 degrees. The distance of bent-up from the face
of support differs.
2. The spacing of stirrups differs with specified drawings.
3. For the end support of beam bent up bars are not bent into beam or column up to the
required depth.
4. For 150mm wide beams, the pin is not provided to the bottom bars when the number of
bars exceeds two.
5. Side face reinforcement is not provided to the beams having a depth of more than
750mm.
6. Beam bars are not passing through column reinforcement.
7. The full bearing of beam bars is not given on the column.
8. The angle of 45° is not maintained for a bent-up bar in a beam.
Slab casting is the major concreting work, involving the use of high-cost materials
such as cement, steel, sand, metal, etc. along with substantial labor. The activity
must be managed properly, to prevent problems at a later stage.
1. Sieve analysis of the sand and metal should be carried out to decide the
volumetric mix design.
2. According to the importance of the structural member, the method of
mixing, i.e., volumetric by weight should be decided.
3. Levels of the slabs and their dimensions should be checked, well in
advance.
4. Slabs should be checked by the architect and R.C.C. consultants for the
correctness of dimensions and reinforcement.
5. The concealed electric conduit work should be checked for its quality as per
the requirements.
6. Arrangement for water and standby arrangements for the same should be
made.
7. A sufficient number of laborers should be present for concreting.
8. The contractor should be informed of the time of commencing the slab and
the maximum time allowed for slab casting, well in advance.
9. Decide the position of the reinforced cement concrete joints for a large slab
with the prior consent of the R.C.C. consultant.
10.Check all the machines for proper operation.
11.Check the availability of fuel for the machines such as mixers, vibrators,
lifts, etc.
12.Check whether a sufficient number of measuring boxes (farmas) are ready
or not.
13.Check a sufficient number of cube moulds for casting the cubes for
checking.
14.Ensure removal of wooden pieces, papers, dust, etc. from the slab and
beam before casting.
15.Check the arrangement of planks and M.S. walkways over the slab, for easy
labour movement; without disturbing concrete & reinforcement.
16.Ensure sufficient light arrangement for late-night concreting.
17.Ensure for the arrangement of staff & allot their duties.
Check that all the fan hooks boxes are placed in position.
Check whether the vibrator is properly placed over the stand for use during
concreting.
Ensure that one supervisor is present near the mixer for checking proper
mixing and the correct quantity of water for mixing the concrete. This
supervisor should maintain the register batchwise and control the
proportion of the ingredients. The slump cone & cube moulds must be
available with the supervisor.
Check whether the M.S. platform is placed over the slab, for delivery of the
reinforced cement concrete on the platform.
Buttering of the mixer should be done before starting the regular slab work.
Quality and consistency of the concrete mix is checked for the first batch
and alterations, if any, should be made in the mix proportion as per the
ingredients available.
Care should be taken first to cast the beams and compact layer-wise with
the help of the vibrator. Though vibrator is applied to beams, reinforced
cement concrete should be also compacted manually with the help of
tamping rods.
For the initial batch, the slump test should be carried out to find out the
consistency and workability of the concrete mix. The alterations in the
proportion of ingredients should be made if the mix is not consistent and
workable.
“Beams first and then slabs’: This method should be applied for concreting.
Ensure the proper level of the slab after finishing by the mason, by visual
inspection.
Ensure proper thickness and finishing of staircase steps and waste slab.
Do not allow anyone to walk over fresh and finished concrete.
Ensure the presence of a carpenter below the slab shuttering, during
casting, is in progress.
Ensure a proper bottom and side cover for slabs and beams at every stage
of concrete.
Ensure a proper finish to the slab panel, where lift delivers the concrete.
For concreting in hot weather conditions, cover the fresh slab by wet gunny
bags, to prevent drying of the top surface of the reinforced cement
concrete.
In case of rains, cover the slab with a big plastic turpentine sheet to protect
it.
Things to be Checked by the Client, Contractor and Engineer before and after
Concreting of Slab
In any construction project, there are three major entities i.e. Client, Contractor,
and consultant. The inspection of the project shall be done by three entities in
order to improve the quality of structure at their own level. IF the size of the
project is small then, material procurement, etc shall be managed by the clients
itself. Checklist of slab helps to reduce construction mistake and enhance the
quality of projects.
Things to be Checked by the Client and Contractor’s before and after Concreting
of the slab
Checklist that has to be adopted by the client, contractor, and engineers before
and after casting of the slab.
Reinforcement bars shall be free from rust, mud, oil, slurry, loose materials,
etc.
Grade of steel (for Example Fe 500 or Fe 500 D) for both main and
Distribution bars shall be checked as per approved drawings.
The diameter of Main Bars and Distribution along Shorter Span shall be
checked.
Diameter of Main Bars and Distribution along longer Span shall be checked.
Ensure the main reinforcement of the slab shall be passed through the
beam.
Reinforcement shall be bent up as per the approved structural drawings.
Length of bent up Bars shall be checked.
Length of bent up bars projecting in adjacent bays.
Check the Spacing between Main Bars and Distribution bars in both shorter
and longer span of each slab panel.
To confirm the spacing between the bars shall be done as per the following steps.
At first, let’s assume the spacing between the mains bars is 6″ (Refer to the slab
reinforcement plan).
Take the measurement of 5 feet length and count the number of bars. If the
number of bars shall be matched with the below-calculated value using the
formula, then the spacing between the bar is correct.
The depth of the cover block shall be checked as per Structural drawings.
Ensure that the cover blocks have the same grade as of concrete slab grade.
Ensure the position of the cover blocks is intact.
Cover Block shall be placed below between the intersection of Main Bars in
x-direction and Y-direction.
Cover Block shall be placed at a distance of 1 m from each other. It shall be
placed everywhere on the slab.
Make sure that Reinforcement shall not touch the formwork. If it touched,
the cover block shall be placed immediately.
CHECKLISTS
EXCAVATION & P.C.C.
Compaction of concrete.
BACKFILLING
Watering.
COLUMNS
General & reinforcement
Binding & placing column reinforcement above upper floor slab as per required
height, considering lap length of the bar.
Diagonals as required.
Oiling of shuttering.
Supports.
Six cube mould are kept ready to cast cubes from different batches.
Hacking of columns.
Cubes removed next day & kept for curing, with code numbers, cast code, site
name on cubes.
Curing of columns done for minimum 15 days. Wet nesian cloth wrapped around
it.
Testing of cubes on due dates i.e. after seventh & twenty eighth day.
Proper fixing of cap on column to take load of beam & slab shuttering.
Proper fixing of props for bottom in line & plumb at every 0.6 m internal.
Packing below props only one or two wooden plank pieces is allowed. (No bricks
or blocks are allowed).
Slab plates should be supported by 3″x3″ chavis at 2’0″ (0.60 m).distance center
to center.
Bamboo bracing for joining, prop to prop at 4’0″ height from floor.
Bottom bars, top bars, bentup bars, stirrups, distance of bentup bars from face of
supports, spacing of the stirrups as per R.C.C. drawing, proper tying of stirrups.
Location, proper binding diameter & length of fan hook & quality of the hook box.
To check the concealed electrical conduit work for slabs as per drawing; check I.S.I
mark on P.V.C. pipes& note down the length of all pipes for billing purpose.
Check the junctions & all electrical layout, position of fan points, M,S, boxes,
junction boxes.
The stock of cement , sand & metal required for casting of slab.
Decide the position of concrete joints in case of big slab after consulting &
approval of R.C.C. Consultant.
Casting of slab with the help of mixer ,vibrator & measuring box.
Ensure cleaning of wooden pieces, papers etc. from slab, beam before casting.
Arrangement of planks over slab for labour movement along with the M.S. walk
ways for avoiding the disturbance to top reinforcement.
Ensure the working of materials lift before commencement of work. Ensure for
rigid scaffolding of lift.
Making small bonds in sand & cement mortar (1:10) for ponding method of curing
for slab, with each bay having maximum size of 2.0 m x 2.0 m.
Flooring is something which a owner of that house sees daily and feels
it. if it have damages, watta, bends, chips, color variation or any other
damages, its not a good sign.
A engineer incharge should check the floor tiling and tick all the points
in checklist if done correctly to ensure good quality work.
Next day joints of tiles slightly raked and filled with matching
approved grout
Curing of tiles done for 3 days
Joints of tiles covered with masking tape to avoid entry of
dust/dirt
Tiles covered for protection( POP cover with paper underneath
recommended )
Skirting tiles fixed over floor tiles.(skirting fixed generally after
masking of joints is complete)
Skirting tile to be fixed in plumb
Skirting tile edges and floor tile edges perfectly match
Skirting at offsets shall match at 45 degree to show a clean edge
Gap above skirting to be filled / trowelled perfectly matching with
wall finish surface
BRICK MASONRY
Cleaning the entire floor, before starting the line out of masonry.
Confirm dimensions & diagonals of room after first layer (line out).
First layer checked with beam top / bottom edge, offset & plumb.
Opening to be provided at first layer for doors & at sill level for windows & A.C.
units.
Cleaning of room
Service line like electrical & plumbing line chasing & filling of voids (Ghabadi).
Height & location of electrical points, switch boards, T.V. & Telephone frames.
AFTER PLASTERING
EXTERNAL PLASTER
The cement sand mortar between junction of bottom beam & the last layer of
masonry shall be filled well in advance before plastering.
3 to 4 days gap between two successive coats for double coat plaster.
Verticality of window opening jamb as well as horizontality of its bottom sills and
top to be checked during plastering work.
For parapet wall, leave a margin of 0.4m ht. in plaster at bottom level from
terrace side.
WATERPROOFING
Proper curing
Internal plaster of walls, leaving margin of 450mm from the final floor level be
completed.
Removal of all debris from toilet/ bathroom & chiseling of extra mortar, if any, to
expose the slab.
Completion of making holes in external walls for connecting nahani trap, p trap
etc. to external drainage line.
Maintain slope of 1:100 from entrance door towards water escape pipe (drainage
pipe) with cement mortar 1:4, thickness 25 mm to 40 mm.
Complete the base coat on walls up to height of 300 mm above toilet finish floor
level covering all beam top junction etc. properly.
Flood the base coat with water, upto slab drop top, for minimum 4 days for curing
& testing of leakage, if any.
Provide 25 mm G.I. / P.V.C. pipe for water escape outlet just above the base coat
of W.C./Bath/Toilet.
Lay well burnt brick bats, thoroughly soaked in water, on edge and fill the joint
cement mortar in 1:6 proportion with slope of 1:100 ,with waterproofing.
Fill the holes in wall for P.V.C./G.I. pipe connection is filled with waterproofing
coba.
Topping with 1:4 cement mortar with waterproofing compound and maintain
proper slope from entrance to nahani trap & finish with neat cement slurry.
Provide curing for minimum 7 days with water. Minimum 7.5 cm depth of water
to be maintained.
Remove extra mortar accumulated on terrace and clean the surface clean with
water.
Leave sufficient margin (approx. 150mm) w/p from terrace door bottom level.
Check for levels & proper slope towards, rain water pipe outlet.
Fix the bricks & fill the joints of brick bats with C.M. 1:6 and maintain a slope of
1:150 with waterproofing
Compound.
Spread the cement mortar of 1:4 proportion along with waterproofing compound
over brick bat coba.
Apply cement slurry over the surface along with waterproofing compound for
smooth finish.
Construct projected edge between the parapet & the watta on the next day.
Clean & cure the final coat atleast 21 days by ponding 150mm high water,
standing on it.
Cleaning the top of the chajja and chiselling out any extra mortar.
Applying finishing coat with C.M. 1:4 & water proofing method.
Ensure that all fixtures like bibcocks, mixers etc. are fixed properly.
Confirm that there is proper pressure to all the cocks / other C.P. fixtures.
Ensure that there is not any choke up in W.C. after continuous flow of water from
half turn flush cock.
Confirm that there not any cement lump observed in P-trap of W.C.
Ensure that there is not any choke up of Nahani trap of bath room after
continuous flow of water for five minutes.
Ensure that the hot & cold water mixer is operating properly.
Ensure that the low level water tank of E.W.C. is operating properly.
Confirm that the brackets of W.H.B. are painted with oil paint.
Confirm that there is no leakage from G.I. lines in duct after continuous water
flow for fifteen minutes.
Confirm that the fixing of G.I. / C.I./ P.V.C. lines in plumb and with proper
clamping.
Confirm that there are no cracks on white cement filled between wash basin and
wall.
Confirm that there is no leakage in the main inlet and outlet G.I. lines or water
tanks.
Ensure that the P.V.C. outlet pipes for wash hand basin and kitchen sink are fixed
properly.
Ensure that the escape spouts from W.C. and bath are provided.
Side of opening.
ALUMINUM WINDOWS
Covering paper
Thickness of glass.
Wall has been scrapped for all unwanted material like excess cement, mortar,
nails, dust etc.
Donga has been removed completely and wall surface is rubbed by fine grade
paper 120 No.
All the undulations of minor nature, dents, cracks, etc. are filled up with putty and
surface is smooth to receive paint.
Surface has been rubbed with fine paper to get smooth finish after 24 hours of
application of putty.
The floor has been cleaned immediately and first coat is allowed to dry for atleast
24 hours, before application of successive coat.
Cleaning of the window glass, terrace, floor, pipes, doors, fixtures, electrical
switches etc. has been done properly.
Oil paint
For M.S. Windows, doors, gates, grills & railings etc. Ensure & confirm:
All cement mortar, unwanted welding burr etc. are removed before application of
primer.
Application of zinc cromite metal primer before application of first coat of oil
paint.
Application of first coat of oil paint.
Application of second coat of oil paint after 24 hours drying of first coat.
Cleaning of the window glass, terrace, floor, pipes, doors, fixtures, electrical
switches etc. has been done properly.
The door frames for its line, level, plumb, quality and door shutter for its free
movement, bent, termite attack etc.
Putty has been filled in all the holes, gaps, depressions, etc. and the surface is
ready to get first coat.
Application of second coat after 24 hours drying of first coat and application of
putty.
Cleaning of the window glass, terrace, floor, pipes, doors, fixtures, electrical
switches etc. has been done properly.
All the electrical and plumbing holes are finished properly before the application
of the first coat.
The surface is watered for 12 hours before application of the first coat
The first coat for proper mix, preparation, thickness & finishing of surface.
Cleaning of the window glass, terrace, floor, pipes, doors, fixtures, electrical
switches etc. has been done properly.
Line, level and alignment of casing caping /switch boards/ light points.
Colour codes and size of wires used for various points are as specified.
The quality and tightening of all the screws with required spacing and with proper
gripes /rawal plugs.
The supply of all the points by megger or test lamp and final testing report is
prepared.
The wiring in meter cabinet for quality, colour codes of wires, gauge of wire, main
switches, connections in bus bar etc.
The name of the flat holder painted on concerned meter and main switch.
Waterproofing to the lift shaft & top of the machine room slab.
Size of the lift shaft, size of all door openings, floor levels & height of machine
room as per manufacturer’s requirement.
Scaffolding is made in the lift shafts is steady and approved by the lift erector.
Fixing of template.
All the door frames (Except ground floor ) are kept in the plumb line fixed by the
erector.
Rope hole in the bottom slab of machine room & pockets are made in the side
walls for clamping of angles.
For the machine room :- I.P.S.Flooring, Ventilation/ exhaust fan, shutter fixing &
painting of machine room.
Flooring in the landing is done as per levels fixed previously and slope of the
flooring is always away from the lift.
While the trial run of the lift that, there are no jerks and sudden stops, floor level
matching to the lift level at all floors.
The capacity of O.H.W.T. & a separate provision in that tank for fire fighting water
storage.
Other requirements as per Municipal Authorities mentioned in the provisional
N.O.C.
Civil work like excavation, making holes to the bricks, wall, concrete and
refinishing is done properly as per the requirement of working agency.
Scaffolding fixed in such a way that no work in fire fighting system erection is
disturbed.
All G.I. / M.S. pipelines for straightness, level, plumb etc. for perfectness.
All fire Extinguishers are working and are installed at proper locations.
General
Longitudinal and cross section of the existing ground level with respect to T.B.M.
The layers in foundation (sub base) and base course and thickness of wearing
surface.
The formation level with respect to plinth level of buildings and approach road.
Base coat
The pipes are laid for cross drain, electrical, drainage, water line and any other
service line.
Soling with stone laid on their edges and chips filled in voids properly.
Grouting pattern (semi grout/ full grout) & weight of bitumen per square meter
area.
Final levels.
Drawing showing lay out of concrete panels, expansion joints, construction joints.
Proper cleaning.
Broom finish
Curing by ponding
Approved drawing
Levels
Pattern of fixing
Approved drawing
Ensure that the storm water drain is not connected to sewage line in any case.
The material for the approved specifications prior to placing the order.
1. Land Survey
2. Excavation
3. Backfilling
4. Compaction
5. Rubble Soling
9. Internal Plaster
11. Waterproofing
12. Flooring
13. Door
14. Windows
24. Other Agencies Work like Solar Water System, Fire fighting Work, Gas
Pipeline, CCTV Camera, Video Door Phone, Ventilation System, Garbage Chute,
Lift, Sewage Treatment Plant, Organic Waste Unit, Vermiculture Pit, Children Play
Equipment, Swimming Pool, Etc.
All the Above subject will be cover under this Course, and all topics will be cover
step by step with all information including the procedure of work and details
process to work out the Quantity and Estimation also we are trying to provide the
Checklists of each work.
Some of the above topics may not be cover in 1 session and might need more
than 1 session, suppose Reinforced Cement Concrete (RCC) can not be possible to
cover under one session so we are dividing this topic in the following Session.
1. Footing/Raft
2. Pile
3. Plinth Beam
4. Pile Cap
5. Column
6. Beam
7. Slabs
8. Retaining Wall
9. Shear Wall
10. Mivon System
13. Tremix
This is just an example of how we distribute all the topics to understand easily to
our followers.
We are trying to cover all the topics under the following head's which can be
easily understood to all.
1. Name of Work
2. IS Code No.
4. Location of Work
6. Checkpoints
9. Checklist
Before excavation work, we need to find out the SBC (Soil Bearing Capacity) with
the help of SBC we can easily prepare or assume how much excavation will be
done or what is an approximate depth of our structure foundation.
1. Soft Soil
2. Compacted Soil
3. Soft Murum
4. Hard Murum
5. Soft Rock
6. Hard Rock
2. IS Code No.
IS Code for Blasting and Related Drilling Work Code of Safety: IS 4081:1986
The following drawing needs to read before excavation work, or before starting to
excavation.
Plinth Section
4. Location of Work
1. Building Foundation
2. Podium Foundation
3. Basement
6. Culvert
7. Dam
8. Trench
2. Read the building foundation Plan and Calculate the building outer to outer
measurement.
3. Read Foundation drawing plan, where Footing and A raft of the building are
outside than building the line.
7. If the Depth of foundation is More than 1.5m then add 3.0m in foundation
outer to outer distance both sides.
8. Mark line for excavation as per building outer to outer distance plus 1.5m or
3.0m both sides for foundation workspace.
9. Check and Note down actual ground level with the help of Auto Level with the
same interval of 2m to 5m, Take 4 reading of each interval.
6. If excavation is done for a trench or only footing pit then use sheathing with the
help of cleat, strut & Wales for support to soil.
8. Check and Note down excavated area levels with help of Auto level by the
same interval as you have done during taking an actual ground level reading, Take
a minimum of 4 reading of each area.
6. Checkpoints
5. If using the breaker to break the rock up to the desired level keep taking
reading and level on time to time to avoid extra excavation than required.
6. After Shown, the hard strata arrange the RCC Designer visit to inspect the SBC.
7. Check the Plinth Level and desired level before complete the excavation.
8. Please check Depth of Soling, PCC, Footing/Raft, and Plinth Beam before
complete the excavation.
If permission is given by RCC Designer then you can keep the plinth
beam and the footing level is the same.
Manual Excavation can be done with the worker by using hand tools like shovels,
etc. but for mass excavation can not be possible manually. It will be too costly and
time consumable.
2. Mechanical Excavation.
With the help of advance technology excavation is made too much easy and cost-
effective as well as time-saving.
2. Excavator (Poclian)
6. Blasting
7. Tunnel Cutter
For the Calculation of the excavated area and quantity of excavated material, we
need the following points.
9. Checklist
6. Heavy equipment, such as excavating machinery and road traffic shall be kept
back from the excavated sides at a distance not less than the depth of trench or at
least 6 m for trench deeper than 6 m.
7.The use of power shovels or draglines in a trench, because of his violent thrust
or blows delivered, rapidly render the banks of the trench unstable and
dangerous to people working nearby. These conditions shall be watched for and
suitably remedied or eliminated.
8. Pathways shall be non-slippery and shall be of adequate width not less than 75
cm. They shall be strong enough to withstand the intended use.
BACKFILLING WORK
Backfilling Work is required to fill the excavated area of the foundation of the
building or any structure from a hard surface. Sometimes we need to do more
backfilling more than ground level due to increase the height of plinth level, on
infrastructure field backfilling, is most important part because the top level of
road and highways is calculated as per nearest dams or nearest river HFL (Highest
Flood Level).
Before excavation work, we need to find out the material quality of backfilling
work. With some laboratory tests and physical tests.
1 Soft Soil
5 Boulders
6 Debris
2. IS Code No.
3 Plinth Section
6 Road Level
7. Road Section
4. Location of Work
1 Building Foundation
2 Podium Foundation
3 Basement
5 Bridge Foundation
6 Culvert
7 Dam
8 Trench
9 Road
3 Read Foundation drawing plan, where Footing and Raft of the building are
outside then building lines.
5 Do site visit of Backfill material quarry. Please keep quarry distance nearest
form your site.
7 Finalize the rate as per your budgeted amount for backfilling work.
6 Do not allow keep the boulders near RCC structure, it can be damaged RCC
member.
7 Backfilling must be done by first filling the excavated soils in layers of 300–
500mm and tamping it with a vibrator. Till the desired level. The soil is moistened
up to the optimum moisture content to establish optimum compaction and best
results.
9 Check and Note down backfilled area levels with help of Auto level by the same
interval as you have done during taking an actual ground level reading.
6. Checkpoints
7 Rolling should be done with a 5-ton mechanical roller after sprinkling enough
water and core cutter samples taken for every 150sq.m
10 Back the filling must be done by first filling the excavated soils in layers of 30–
50 mm and tamping it with a vibrator. Till the desired level. The soil is moistened
up to the optimum moisture content to establish optimum compaction and best
results.
11 After completion of compaction arrange the architect visit to inspect the level
as per Sections.
Check the Plinth Level and desired level before complete the backfilling, also keep
down the level of backfilling area for Soling, PCC & Flooring, or for Road work
keep the level down for WBM, Tack Coat, Seal Coat Etc.
12 Please check Depth of Soling, PCC, Footing/Raft, and Plinth Beam before
complete the excavation.
Manual Backfilling
Manual Backfilling can be done with the worker by using hand tools like shovels,
etc. and 250-1000kg The compactor can be used for Compaction, Generally
manual backfilling must be done at the not accessible area for big machines like at
Parking, Under the Building, at Basement, Under the bridge, etc. but for mass
Backfilling can not be possible by manually. It will be too costly and time
consumable.
Mechanical Backfilling.
With the help of advance technology excavation is made too much easy and cost-
effective as well as time-saving.
2 Excavator (Poklain)
4 Mini Compactor
5 Plate Compactor
6 Road Roller
7 Grader
8 Vibro Roller
12 Water Tanker
13 Dozer
8. Measurement and Quantity Survey
For Calculation of backfilling area and quantity of backfilled material we need the
following points.
9. Checklist
2 Keep RCC Structure, Pipe Line, Chambers, Electrical Wire, etc. Safe
8 The use of power shovels or draglines in a trench, because of his violent thrust
or blows delivered, rapidly renders the banks of the trench unstable and
dangerous to people working nearby. These conditions shall be watched for and
suitably remedied or eliminated.
9 Pathways shall be non-slippery and shall be of adequate width of not less than
75 cm. They shall be strong enough to withstand the intended use.
Readers Experience: At an MNC Project the work order is for industrial plant shed
and area of the shed is approximate 30000 Sqft, but movable area and road this
plant plinth area is approximate 72000Sqft and height are approximately 7m from
the existing ground level. Total work completion time is given by the client is 6
months including Monsoon season. And the site location is in the hilly area. But
our bad luck is after cutting of grass and murum backfilling completed up to 2
meters, rain is started, and continuously falling up to more than 40 days. And for
dry this area again give 40 days. But when we have to restart the work, the
murum is not as much dry as we think, at that site we did a lot of work on it, we
removed 2 layers of that murum and refill it. Obviously, the client gives us 90
days extra as well as they understood the exact situation of work.
There are two types of rate analysis, but you are going to study some government
rates, we can found many types of back filling work which are depend on various
types are as follows
There are many types of back filling materials which are using at various types of
sites. In some important projects like Bridges foundations, metro projects
foundations are using crush sand for back filling, on railway track there are using
60-90 mm course aggregates, somewhere 10-20 mm course aggregates are using
for back filling, for earthen dams there is using soil for back filling, and some
projects of roads, embankments of bridges, building foundations, etc. are using
murum. In all world there are commonly using murum for back filling.
2. onsite material
Commonly back filling work is done after excavation work, so therefore lot of
excavated material is stock at site, and lot of times to avoid extra cost to buy
outside material there are using excavated material to back filling, this method is
very commonly using in all over world but sometimes the location of site, type of
excavated material, etc. need to buy outside materials.
3. outside material
In some projects which are located are near creek, near ocean, near sea, near
dam, near river, water land, there are water table is up to 5ft from ground level
and lot of black cotton soil is there so in these cases after excavation there need
to buy outside back filling materials.
4. Distance
When we are going to buy outside material to back filling work there is distance
factor is very affected on the rate of the material.
5. Manual
Sometimes need back filling work manually due to site condition or site location.
Like hilly area, under the building, small building in crowded public place, no
roads for machine travel. Etc.
6. Machine
Now a days we are using all work is done by machine, back filling work is on of
from those, now a days lot of types of mini machines are available which are
going every were on site like under the building. On road work there is lot of work
is done machines.
Now today we are just giving formal information about back filling work. Now we
will analyse the common using rate analysis of back filling work which can give
idea to how to work out the rate analysis.
There are main 2 types of rate analysis which are using commonly in society.
We are giving just these 2 types of analysis which are very useful to analyse to get
basic knowledge of analysis. After that you can also work on it as per your
material types and distance, etc. as we have given some differentiation factor
above.
In given table you can get easily idea about how we can prepare the analysis of
back filling work,
Know the constants required to desired unit to work. He are we are giving you
rate analysis details in Cum only, which are using comely in construction industry
but material procurement unit might be different than out rate analysis unit. You
need to focus on that. If out rate analysis unit is in Cum, but material
procurement unit is Brass, so you need to prepare the rate analysis according to
that and conversion of material constant will be according to it.
2. Back filling with outside material
As we discussed above as why need outside material, but outside material rate is
depend on distance from site. As well as type of material as discussed.
As per basic information from local source and local contractors practice of rate
for distance is considered with mutual understanding and previous business
relations with contractors.
But in general there are using a practice as follows
But lot of times this is depend on quantity of work, if there is huge quantity of
work, and then there is no one considering this distance factor.
Back filling rate analysis are generally as per given formats but rates are decided
are as per quantity of work, if there is huge quantity of work there will be rate are
decided as per the quantum of work.
In back filling work Compaction factor also affecting on rates if any clients given to
show the proctor test up to 95% then back filling work need to do very carefully.
The back filling work wants to do in layers in 300 mm to 600 mm thickness. As
well as back filling need to do under observation to avoid the using of boulders or
any other hard materials if using murum. As well as while compaction of murum
need to spray the water on compacted surface and then again need to do
compaction to achieve the 95% proctor test.
If anyone want to do rate analysis follow these processes and take care while
checking the rate of material and labour because it will directly affecting your
budget and may be face the losses.
(PCC)
1 Name of Work & Description
PCC is not a reinforced structure; this is just a part of sub-base structure to work
easily before foundation.
4 Screeding
5 slab Cushioning
6 Lime Concrete
7 Topping on Slab
8 Plum Concrete
2 IS Code No.
Specifications for fine & coarse aggregate from natural sources for concrete: IS:
383
As we discussed earlier PCC is a base structure which not taking the load, so no
separate drawing will be provided by any agency, in all drawing, there is only
mentioned thickness, offset of PCC and grade of concrete.
But sometimes in schedule drawing there are details motioned as well as sizes
and thickness are also given in the schedule. (As per Picture).
3 Layout of Foundation
5 Level Drawing.
4 Location of Work
Plain Cement concrete is the mandatory base before starting any foundation, the
following are some locations where we are found PCC Work.
6 Screeding on Slab
1 Checking of Excavation Level and Foundation depth, depth of PCC, plinth Level,
etc.
5 Marking of Corner Point with fixing of a rod, and marking of top-level of PCC on
it.
6 Fixing of shuttering ply side as per the size given in drawing, or keep offset to
the foundation at least 150mm to smooth working space.
7 Keep The top-level of PCC is uniform. If the excavated ground is not is level then
do plum concrete after discussing it with the RCC consultant. But keep PCC in
level.
8 Fill Concrete as per the given design mix. Which can be generally given in
drawing is M10 & M15.
9 Keep the thickness of the PCC uniform which is nearing 150mm or 100 mm as
per given in drawing.
6 Checkpoints
1 Excavation level
2 Plinth Top-level
3 Depth of Foundation
6 Shuttering of PCC
7 Thickness of PCC
8 Grade of Concrete
9 Quality of Concrete
10 Curing
2 Weight batcher
3 Wheel Borrow
5 Thapi,
6 Line Dori
7 Measurement Tape
Plain Cement Concrete is measuring in 2 units as Square Meter and Cubic Meter.
Following are the procedures to take and write the measurements of PCC.
1 Square Meter:
One side length of PCC: (1500mm +150mm (Offset) + 150mm (Offset)): 1800mm
2 Cubic Meters:
9 Checklists
2 All Loose Material Removed and Cleaned the PCC base surface.
3 Marking is Done including offset to foundation
Footing PCC
10 Quality Tests
Testing of Cement
Testing of Aggregate
11 On-site Experiences
Mr. Shankar
Plinth Beam
RCC (Reinforced Cement Concrete) Plinth Beam: Plinth Beam is a Structural which
is located at Plinth level and shearing a load of structures an transfer it to footing.
Plinth beam is necessary when foundation depth is more than 1m, as well as if
foundation depth is more than 3m, need to design tie beam below plinth beam
level. because Columns are vertical member and they are not capable to bear
vertical load more than 6m, in a column if reinforced steel is not more than 4m,
so need to design tie beam at 3m level and then plinth beam at plinth level.
1 Tie Beam
2 Plinth Beam
2 IS Code No.
Specifications for fine & coarse aggregate from natural sources for concrete: IS:
383
3 Layout of Foundation
5 Level Drawing.
4 Location of Work
Plinth beam is Located at below plinth level, that mean Plinth beam location is
Below Finish Floor Level, and tie beam location is 1m below ground level.
1 Checking of Excavation Level and Foundation depth, depth of PCC, plinth Beam
Level, etc.
6 Checkpoints
1 Excavation level
3 Depth of Foundation
4 Cutting of Steel
5 Reinforcement of Steel
8 Grade of Concrete
9 Quality of Concrete
10 Curing
2 Weight batcher
3 Wheel Borrow
6 Line dori
7 Measurement Tape
Following are the procedures to take and write the measurements of Plinth Beam.
Now we need to find out lenght of plinth beam from structural drawing or
architecture drawing, now a days we should we need to found autocad drawing
soft copy of structural drawing, with the help of this drawing we should be
measure length of beam.
9 Checklists
10 Quality Tests
Testing of Cement
Testing of Aggregate
11 On-site Experiences
Focous of Dowel bar installation process: we are generally follow typical process
of dowels bar installation process as lot of contractor follow wrong procedure
installation of dowels. they are using Ld(Development Length)+10d+lap lentgh of
bar in footing concrete after completion of footing concreting they are doing
plinth beam work, while plinth beam reinforment work, the steel need to rebend
and start the reinforcement but while rebending of steel there are lot of chances
of minor cracks on steel at bend, or many times steel will cut. so we need to
follow standard procedure as need to pass dowel bars from footing stuttering so
we should keep straight bar in plinth beam.which will be easier than old typical
procedure.
RCC (Reinforced Cement Concrete) Column: The vertical Member of any structure
called as Column, Column is a very important member in any structure, this
member is the main load transferring member, from building to the footing. All
RCC Structure need to design RCC Designer, they are calculating all the details
about the load calculation as well as per design the details of reinforcement steel.
Types of Column
1 Column
2 Y Columns
3. Inclined Columns
2 IS Code No.
Specifications for fine & coarse aggregate from natural sources for concrete: IS:
383
4 Location of Work
The column is the important part of any structural work, as the column is started
from Footing, Pile cap Foundation.
7 Fix and Binding of steel as per given schedule to column up to the middle of
next floor as per drawing.
9 Fixing the cover block to stirrups of the column and fix the shuttering.
12 Pour the Concrete as per given concrete grade with proper compaction,
tamping, without disturbing the column position of the column. This may
decenter the column or chances of bulging.
14 The next day needs to hacking the column because after the final setting time
completed hacking can not be more effective after 28 days.
6 Equipment and Machinery
2 Weight batcher
3 Wheel Borrow
5 Trowel
6 Line Dori
7 Measurement Tape
Following are the procedures to take and write the measurements of Column
Concreting.
If Size of Column is 600mm X 300mm and Height is given 3000mm (Floor to Floor),
If column height is given 3m Floor to Floor We need to calculate the Beam Depth
which is resting on this column, suppose beam depth is 0.45m Then We need to
cast Column up to 2.55m but standard plywood height is 1.22m X 2.44m i.e. We
can do shuttering of column up to maximum 2.40m height, so we need to
calculate the column concrete requirement as per the required height.
There are 2 points, If you are doing concrete you need to calculate the column
height as per your requirement like if 1st stage of column concreting then column
height need to calculate as per plywood height i.e 2.44m
If you are calculating the all over building quantities you need to calculate the
column height in 2.55m because beam and slab need to consider separately.
1 Cubic Meter:
Height: 2.44m
8 Checklists
2 All Loose Material Removed and Cleaned the PCC base surface.
9 Quality Tests
Compression test of Cube
Testing of Cement
Testing of Aggregate
10 On-site Experiences
The column is the most important structure of any structure but when we actually
execute the work, some of the engineers ignore the importance of this structure,
due to this negligence lot of times may chance to bare huge cost to contractor,
client, and time will require more to do rework if possible.
1.Reinforcement:
Column shuttering should be checked carefully the checkpoint of the column are
as follows like the diameter of steel, the spacing of bar as well as spacing of
stirrups, link position, and most important part is checking of lap length or if the
lap is not possible need to check coupler joint done properly. After all the
checking needs to check the position of the column as well as the position of a bar
that the mean center is shifted or not. If the center is shifted please take advice
from RCC consultant, do not joggle the bar, this is reducing the life and strength
of the structure. Also, check the cover is placed or not, some covers are inserting
in the bar, some covers are from the external side of the bar. So please check all
the points of column reinforcement and do the actual bar bending schedule to
claim in client bill.
2.Shuttering:
Before shuttering of the column we need to check the quality of plywood, as well
as please check the oil is applied to internal side or not, if not applied please apply
it and the place and fix it as per size, please take precautions while supporting the
column, like supporting by props, fixing of shikanja (MS Shuttering Clamp), anchor
bolt, and tie rods, etc. while checking of column shuttering need to check the size
of the column is proper or not, and line-level with the centerline of column, as
well as most important part is checking of plumb bob of column this check is very
very important to reduce the errors in the decentralization of the column on the
next floor. If you will put 5mm error while checking of column plumb bob, then
next upper floor column will be shift 5mm from its position. So please take proper
precautions while checking the column positions, the same criteria will be
applicable to retaining wall, Pardi, shear wall, etc. internal side should be smooth,
as well as oiled.
3.Concreting:
Before starting the concreting of the column we supposed to all above checks was
done and found clear and rectified if found any error, after that we should make a
proper scaffolding around the column to fill the concrete in it, do not apply more
force of column shuttering because this is a temporary structure and all positions,
size, plumb bob checking has been completed if we apply this more force on the
column shuttering may chance to decentralize the column. This practice is not
good. So please prepare the scaffold to do the concreting of the column. Also
please check the concrete slump cone while concreting. Also, Fill the Concrete
Cube for Compression test after 7 days, 15 days, and 28 days this is very good
practice to know the concrete strength is achieved or not. If possible please keep
a concrete cube near to the same column which is very useful, how may time
actual curing was done to column and cube will know by the strength report.
Mr. Somnath
(Project Co-Ordinator)
Soling Works
Signature Signature