task_code status_code wbs_id task_name start_date end_date

Activity ID Activity Status WBS Code Activity Name (*)Start (*)Finish


2.1 Not Started Rig-Phys-1.1 Excavation 11-May-20 01-Jul-20
2.2 Not Started Rig-Phys-1.1 Constructing Of Check Point Room 20-May-20 25-May-20
16.2 Not Started Rig-Phys-1.4 Installing Sensor Type 1 20-May-20 24-May-20
16.3 Not Started Rig-Phys-1.4 Installing Sensor Type 2 25-May-20 31-May-20
16.4 Not Started Rig-Phys-1.4 Installing Anodes 01-Jun-20 03-Jun-20
16.5 Not Started Rig-Phys-1.4 Installing Control Wires 04-Jun-20 20-Jun-20
16.1 Not Started Rig-Phys-1.3 Digging Grounding Rod 3 M 21-Jun-20 24-Jun-20
15.1 Not Started Rig-Phys-1.2 Pipeline prepration 23-May-20 25-May-20
15.2 Not Started Rig-Phys-1.2 Pipeline assembling 02-Jul-20 09-Jul-20
15.3 Not Started Rig-Phys-1.2 Pipeline Welding 07-Jul-20 18-Jul-20
15.4 Not Started Rig-Phys-1.2 Pipeline Installation & Painting 19-Jul-20 30-Jul-20
PM01 Not Started Rig-Phys-1.5 Project Start 11-May-20
PM02 Not Started Rig-Phys-1.5 Project Finish 30-Jul-20
MD01 Not Started Rig-Phys-1.6 Grounding Rod 3 M delivery 11-May-20 13-May-20
MD02 Not Started Rig-Phys-1.6 Pipes delivery 11-May-20 21-May-20
MD03 Not Started Rig-Phys-1.6 delivery of Sensors Type 1 & Type 2 11-May-20 16-May-20
MD04 Not Started Rig-Phys-1.6 Anodes delivery 11-May-20 18-May-20
MD05 Not Started Rig-Phys-1.6 Wires delivery 11-May-20 16-May-20
perfm_complete_pct complete_pct target_drtn_hr_cnt target_work_qty
(*)Performance % Complete(%) Activity % Complete(%) Original Duration(d) (*)Budgeted Labor Units(h)
0 45 250
0 5 800
0 4 220
0 6 230
0 3 250
0 14 600
0 4 240
0 3 350
0 7 700
0 10 800
0 11 1200
0 100 0 0
0 0 0 0
0 100 3 0
0 90 10 0
0 50 5 0
0 100 7 0
0 100 5 0
act_work_qty act_equip_qty delete_record_flag
(*)Actual Labor Units(h) (*)Actual Nonlabor Units(h) Delete This Row
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
user_data
UserSettings Do Not Edit
DateFormat=dd'-'mmm'-'yy
CurrencyFormat=US Dollar
ActivityID Activity Name Original Duration Remaining Duration
Rig-Physical 70 70
ProjectMilstones 70 70
PM01 Project Start 0 0
PM02 Project Finish 0 0
MaterialDelivery 10 10
MD01 Grounding Rod 3 M delivery 3 3
MD02 Pipes delivery 10 10
MD03 delivery of Sensors Type 1 & Type 2 5 5
MD04 Anodes delivery 7 7
MD05 Wires delivery 5 5
CivilWorks 45 45
2.1 Excavation 45 45
2.2 Constructing Of Check Point Room 5 5
CommunicationWorks 27 27
16.2 Installing Sensor Type 1 4 4
16.3 Installing Sensor Type 2 6 6
16.4 Installing Anodes 3 3
16.5 Installing Control Wires 14 14
ElectricalWorks 4 4
16.1 Digging Grounding Rod 3 M 4 4
MechanicalWorks 60 60
15.1 Pipeline prepration 3 3
15.2 Pipeline assembling 7 7
15.3 Pipeline Welding 10 10
15.4 Pipeline Installation & Painting 11 11
Data Date 18-May
Start Finish Actual Start Actual Finish Performance % Complete New %
11-May-20 30-Jul-20 0%
11-May-20 30-Jul-20 0%
11-May-20 0% 100
30-Jul-20 0%
11-May-20 21-May-20 0%
11-May-20 13-May-20 0% 100
11-May-20 21-May-20 0% 90
11-May-20 16-May-20 0% 50
11-May-20 18-May-20 0% 100
11-May-20 16-May-20 0% 100
11-May-20 1-Jul-20 0%
11-May-20 1-Jul-20 0% 60
20-May-20 25-May-20 0% 20
20-May-20 20-Jun-20 0%
20-May-20 24-May-20 0%
25-May-20 31-May-20 0%
1-Jun-20 3-Jun-20 0%
4-Jun-20 20-Jun-20 0%
21-Jun-20 24-Jun-20 0%
21-Jun-20 24-Jun-20 0%
23-May-20 30-Jul-20 0%
23-May-20 25-May-20 0% 10
2-Jul-20 9-Jul-20 0%
7-Jul-20 18-Jul-20 0%
19-Jul-20 30-Jul-20 0%
Budgeted Labor Units Budgeted Nonlabor Units Actual Labor Units Actual Nonlabor Units
5640 300 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
1050 300 0 0
250 300 0 0
800 0 0 0
1300 0 0 0
220 0 0 0
230 0 0 0
250 0 0 0
600 0 0 0
240 0 0 0
240 0 0 0
3050 0 0 0
350 0 0 0
700 0 0 0
800 0 0 0
1200 0 0 0
Budgeted Total Cost Earned Value Cost Resources Total Float
$781,500.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 0
$0.00 $0.00 32
$0.00 $0.00 38
$0.00 $0.00 32
$0.00 $0.00 9
$0.00 $0.00 17
$0.00 $0.00 22
$56,500.00 $0.00 0
$36,500.00 $0.00 Rig Cost, Rig Quantity, Excavator, Labor 0
$20,000.00 $0.00 Rig Cost, Rig Quantity, Labor, Forman 6
$99,000.00 $0.00 6
$2,000.00 $0.00 Rig Cost, Rig Quantity, Sensor Technician, Helber 6
$4,000.00 $0.00 Rig Cost, Rig Quantity, Sensor Technician, Helber 6
$18,000.00 $0.00 Rig Cost, Rig Quantity, Labor, Electrican 6
$75,000.00 $0.00 Rig Cost, Rig Quantity, Labor, Electrican 6
$1,000.00 $0.00 6
$1,000.00 $0.00 Rig Cost, Rig Quantity, Labor, Electrican 6
$625,000.00 $0.00 0
$62,500.00 $0.00 Rig Cost, Rig Quantity, Labor 32
$125,000.00 $0.00 Rig Cost, Rig Quantity, Welder, Labor 0
$250,000.00 $0.00 Rig Cost, Rig Quantity, Welder, Labor 0
$187,500.00 $0.00 Rig Cost, Rig Quantity, Welder, Labor 0

You might also like