7.2.3.1 Natural Resources Enforcement and Regulatory Program 34
7.2.3.1.1 Natural Resources Management Arrangement/ Agreement and Permit 34
Issuance 34
7.2.3.1.1.1 Forest and Forest Resource Use 34
7.2.3.1.1.2 Land and Land Resource Use 35
7.2.3.1.1.3 Protected Areas, Wildlife, Coastal and Marine Resources 36
7.2.3.1.2 Operations against Illegal ENR Activities 36
7.2.3.2 Natural Resources Conservation and Development Program 38
7.2.3.2.1 PA, Caves, and Wetlands Dev’t & Management Sub-Program 38
7.2.3.2.1 Wildlife Resources Conservation Sub-Program 43
7.2.3.2.2 Coastal and Marine Ecosystems Rehabilitation Sub-Program 44
7.2.3.2.3.2 Manila Bay 47
7.2.3.2.3.3 Pasig River Rehabilitation 49
7.2.3.2.4 Land Management Sub-Program 50
7.2.3.2.4.1 Land Survey Disposition and Records Management 50
7.2.3.2.4.2 For the Requirements of the Comprehensive Agrarian Reform
Program (CARP) 52
7.2.3.2.5 Forest and Watershed Management Sub-Program 52
7.2.3.2.5.1 Forest Development, Rehabilitation and Maintenance and Protection 52
7.2.3.2.5.2 Soil Conservation and Watershed Management including River basin
Management and Development 58
OO3: Adaptive Capacities of Human Communities and Natural Systems Improved 60
7.2.3.3 Environment and Natural Resources Resiliency Program 60
8.0 Foreign-Assisted and Special Projects (FASPs) 61
9.0 Environmental Management Bureau (EMB) 62
10.0 Mine and Geo-sciences Bureau (MGB) 67
11.0 NAMRIA 73
12.0 National Water Resources Board (NWRB) 74
13.0 PCSDS 75
14.0 Gender and Development (GAD) 76
15.0 Program Budget 77
16.0 Budgetary Impositions 78
17.0 Schedules and Deadlines 79
18.0 Responsibility 80
19.0 Review Mechanism 81
20.0 Reporting Requirements 82
21.0 Cash Budgeting System 85
2
Republic of the Philippines
Department of Environment and Natural Resources
Visayas Avenue, Diliman, Quezon City
1.0 Rationale
The achievement of the above-mentioned goals and outcomes within the Department
depends upon how well the policies and frameworks are translated into programs.
The programs shall also put focus on water security and water resilience as a
policy thrust and direction to cope with and/or recover from the setback caused by
COVID-19 pandemic, adapt to climate change, and enable economic growth by
providing the conditions for a healthy environment. Similarly, the programs should be
translated into activities and measurable outputs. It is therefore crucial to critically
formulate the Work and Financial Plans (WFPs) consistent with the policies and
guidelines from the policies and frameworks in order to attain the desired outcomes.
Such harmonized objectives will bring larger impact to the ENR protection,
conservation and development during the COVID-19 pandemic. Hence, this
operational guidelines in the formulation of WFPs for FY 2022 is hereby presented.
In consideration to the new normal strategies, the Department of Budget and
Management (DBM) has recommended a total budget of PhP26,308,629,000
including automatic appropriations for the Department as articulated in the FY 2022
National Expenditure Program (NEP). The Department will also continue in
implementing its programs anchored and based on the national development agenda
defined in the 2017-2022 Philippine Development Plan (PDP).
3
2.0 Purpose
This Operational Guidelines and its attachments shall serve as the DENR’s
Operational Blueprint for its PhP26,308,629,000 budget recommended by the DBM
as articulated under FY 2022 NEP. Likewise, this document shall serve as guide of
various DENR offices in the preparation of their respective Work and Financial Plans
(WFPs) and utilization of their budget consistent with the mandate, priorities and
targets of the Department.
These guidelines, prescribes procedures and requirements for the preparation and
submission of the WFPs of the DENR, its Bureaus, Regional Offices, and Attached
Agencies, consistent with the policy and framework of the DENR. It also spells out
authorized budgetary impositions and priorities for funding for the year, including new
instructions of the Secretary and oversight agencies; hence, compliance hereof is
mandatory.
This Operational Planning Guidelines shall adhere to the following legal frameworks:
1
National Budget Call for FY 2022
2
Budget Priorities Framework for the Preparation of the FY 2022 Agency Budget Proposals
3
Directing all Agencies and Instrumentalities, including Local Government Units, to implement the Philippine Development
Plan for the period of 2017-2022
4
An Act Mainstreaming Climate Change Into Government Policy Formulations, Establishing the Framework Strategy and
Program on Climate Change, Creating for this Purpose the Climate Change Commission, and for Other Purposes
5
Anticipatory and Forward Planning (AFP)
6
Full Devolution of Certain Functions of the Executive Branch to Local Governments, Creation of a Committee on
Devolution, and for Other Purposes
7
Strengthening Rehabilitation and Recovery Efforts in Typhoon-Hit Areas through the Creation of the Build Back Better
Task Force
8
Expanding the Coverage of National Greening Program
4
4.0 Coverage
This Operational Guidelines shall cover all DENR offices as stipulated under
General Appropriations Act (GAA). These include the following:
5
Automatic Appropriations 988,691 1,013,040 24,349 2.46%
6
MGB 1,305,020 1,341,525 36,505 2.80%
7
MOE 42,291 46,004 3,713 8.78%
MOOE
9,900 10,500 600 6.06%
8
CO 25,100 29,500 4,400 17.53%
9
PS 810,344 837,540 27,196 3.36%
10
PS 746,893 779,993 33,100 4.43%
11
CO 5,238 6,518 1,280 24.44%
DENR, TOTAL
24,584,025 26,308,629 1,724,604 7.02%
OBLIGATIONS
The implementation of P/P/As shall be anchored on eight (8) key strategies of the
Department: (i) utilization of unified mapping in situational analysis, decision making
and strategic planning; (ii) adoption of watershed/river basin as planning unit; (iii)
closing of open access areas in public lands, especially forestlands, by granting
appropriate tenurial instruments; (iv) convergence with other government agencies
and stakeholders; (v) area management approach where all basic societal and
economic services are delivered in an area for more impacts; (vi) continuously
capacitate DENR front liners, local government units, civil society organizations
partners and people’s organization; (vii) intensify information, education and
communication (IEC) campaign, advocacy and social mobilization; and (viii)
implementation of certification systems and chain of custody of the products.
12
In compliance with the Mandanas Ruling promulgated by the Supreme Court that
clarified the “just share” in the national taxes of Local Government Units (LGUs), the
Department shall devolve some of its activities. The Supreme Court declared that the
basis of computation of LGUs’ just share must be from “all collections of the National
Taxes except those that are accruing to special purpose funds and special allotments
for the utilization and development of the national wealth.” One of the measures to
mitigate the fiscal impact of the SC ruling is the full devolution of certain functions of
the Executive Branch to the LGUs. As such, some of the programs, projects and
activities being implemented by the Department shall be devolved to LGUs starting
2022.
As stipulated in the Section 17 of the R.A 7160, otherwise known as the Local
Government Code (LGC) of 1991, it mandated the devolution of several basic
services and facilities of the NGAs to the LGUs. The DENR has functions that were
prior devolved and some of it are, but not limited to, community-based forestry
projects which include social forestry programs, management and control of
communal forest, establishment of tree parks, greenbelts, and similar forest
development projects. Likewise, services related to general hygiene and sanitation
such as solid waste management or environmental management systems. In
addition, this also includes programs in other mandated or subsequent laws such as
Clean Air Act and Clean Water Act in support of the LGC.
13
and Financial Plan of DENR Offices, as far as applicable, will ensure that the DENR
priority programs can prepare to respond to the 1.5 degrees Celsius scenario.
Also, Climate Change concerns shall be incorporated in all the major programs in
consonance with the Republic Act 97259 (Climate Change Act), international
commitments and protocols including the operationalization of the Philippine
Nationally Determined Contribution under the Paris Agreement, and other existing
development plans of the country, and to include adherence to specific requirements
of the IATF Anticipatory and Forward Plan on addressing the COVID-19 and
emerging infectious diseases. The Climate Change Service (CCS), in coordination
with the PPS-PPD, shall review the PPAs and identify specific areas for
mainstreaming of climate change concerns and its enhancements. Such shall form
part of the annual accomplishment reports of the central office, bureaus, attached
agencies and regional offices.
The following forms shall be the attachments of the FY 2022 WFPs (Budget
Execution Document Forms):
14
7.1.3 Regional Planning and Budgeting
Prior to the preparation of the final WFPs, all Regional Offices (ROs) shall conduct
consultation workshops with their respective CENROs, PENROS, Technical Division
Chiefs, Protected Area Superintendents (PASu), River Basin Management Office
(RBMO), Planning and Budget Officers, Climate Change focal persons, FASPs
Project Manager/Coordinator/Focal Person, including Civil Society Organizations
(CSOs) and other stakeholders. Priorities should include the RRP provinces and
areas as articulated in the local development and sectoral plans (i.e., Comprehensive
Land Use Plans (CLUPs), Community Development Plans (CDPs), Provincial
Development and Physical Framework Plans (PDPFPs), Regional Development
Plans (RDPs), Local Climate Change Action Plans (LCCAPs), Local Disaster Risk
Reduction and Management Plans (LDRRMPs), Protected Area Management Plans
among others and River Basin Master Plans have to be carefully considered in the
planning and budgeting process. Targets and financial requirements shall, as much
as possible, be precise, especially for the banner programs (i.e., eNGP, CMEMP,
etc.).
The Regional Environment and Natural Resources Medium-term Plans of all Regions
shall be the basis in the formulation of their WFPs. All activities to be undertaken by
the Region shall be placed under the appropriate Programs, Projects, and Activities,
(P/P/A) of the Department.
All Regional Planning Offices (RPOs) shall prepare a Monthly Implementation Plan
(MIP) reflecting the process activities/indicators (with target and budget) which shall
serve as guide by the Regional Finance Division in the preparation of Monthly
Disbursement Program (MDP) for submission to DBM. The MDP shall be the basis of
the DBM in releasing the Notice of Cash Allocation (NCA). Preparation of MIP and
MDP should be in close coordination with technical people.
The ROs shall download the corresponding allotment, including Project Management
and Supervision (PMS), if applicable, to concerned PENROs who will implement the
activities, breakdown as follows:
All Regional plans shall be formulated and approved in consultation with the
CSOs and key stakeholders, proof of which shall be submitted and attached to the
WFP. All Regional Plans should be ensured of their climate and gender
responsiveness, and approved in consultation with the CSOs and key stakeholders,
proof of which shall be submitted and attached to the WFP. The CCS and GAD
15
Office shall provide capacity building on climate and gender responsiveness
assessment of the regional plans/programs, among others.
Daily rate of the Contract of Service (COS) to be hired should be based on the
prescribed salary table from the Personnel Division.
Newly created Offices by virtue of a Special Order (S.O.) are required to submit
the detailed functions of their Office when submitting their WFP. This will serve
as one of the bases in reviewing and evaluating the WFP.
All Offices at the Central Office shall prepare their WFPs in consideration of the
pandemic situation. All activities shall observe the minimum health
requirements stated in the IATF Guidelines. The WFPs should be prepared
based on their needs but not exceeding the budget cap.
To improve planning and execution of the Department’s P/P/As, the following specific
measures shall be implemented:
Central Office shall submit to the DBM, copy furnished the Office of the
Cabinet Secretary, an implementation plan, detailing the quarterly financial
and physical plans and targets using the prescribed forms under National
Budget Circular (NBC) No. 2020-13 dated October 26, 2020, Circular Letter
(CL) No. 2016-9 dated October 27, 2016, as amended under Circular Letter
9
Directing All Heads of Departments and Agencies to Implement Measures to Facilitate Budget Execution for FY 2015 and
Subsequent Y
16
(CL) No. 2017-12 dated October 19, 2017 and Circular Letter (CL) 2018-10
dated 8 November 2018.
● All Regional Office shall submit online to the Central Office through
PMED-PPS the accomplishment of Full-time Delivery Units (FDU), the
consolidated monthly reports on target and budget on priority
programs and projects not later than the 5 th of the succeeding month,
copy furnished the Budget Division-FMS.
● Identify at the end of first quarter, agency programs and projects with
historical trends of low disbursement rates and those with anticipated
delays. The Office concerned shall submit justification on or before for low
utilization and formulate a catch-up plan (See ANNEX F).
● Evaluation of all WFPs shall consider last year’s budget utilization rate.
(BUR)
All WFPs shall be approved by the Undersecretary for Policy, Planning and, and
Undersecretary for Finance, except the WFPs of line bureaus (EMB and MGB) and
attached agencies (PCSDS, NAMRIA and NWRB). However, line bureaus and
attached agencies shall involve the Policy and Planning Service (PPS) and Financial
and Management Service (FMS) in the formulation of their respective WFPs.
Likewise, the offices concerned must submit their approved WFPs to the DENR
Central Office (PPS and FMS).
Work and Financial Plans for the funds to be downloaded by the Staff Bureaus to
Regional Offices shall be reviewed by PPS-PPD and FMS-Budget Division and
approved by the approving Undersecretaries. Regional breakdown of funds shall be
included in the Work and Financial Plan of Bureaus.
For P/P/As supported by the Central Office fund, the concerned Bureaus shall
prepare National WFP for proper guidance of ROs. Regions are not required to
submit for approval their specific/detailed WFPs. However, in case the Regional COA
17
required the RO to submit the details, the Central Office shall approve immediately
the WFP.
In line with AO No. 46, s. 2015 and DBM Circular 2018-08 dated 30 July 2018, the
DENR Central Office, Regional Offices and its Bureaus/ Attached Agencies shall
adopt the following measures to speed up the conduct of procurement procedures:
● Assign full-time support staff to their respective Bids and Awards Committee
(BAC) Secretariats, and require BAC members and Technical Working Groups
to give utmost priority to procurement assignments over all other duties and
responsibilities, until the requirements for the said assignments are completed.
If warranted, organize additional BACs for timely procurement of goods and
services.
● Increase the number of BACs in the Central Office and in the Regions including
PENROs where the number and the complexity of items to be procured so
warrant.
● Central Office, all Regional Offices/PENROs shall post the approved Indicative
Annual Procurement Plan based on NEP as part of the Transparency Seal
within the prescribed deadline set by Government Procurement Policy Board
(GPPB).
● By 4th quarter of 2021, at least fifty percent (50%) of the planned qualified
procurement projects as specified in the GPPB Resolution No. 14-2019, dated
17 July 2019 for FY 2022 should have been submitted by the end-user units to
the BAC of the respective PEs for processing and have been recommended for
award of contract to the winning bidder, in accordance with Section 7.6 of the
2016 Revised Implementing Rules and Regulations of RA 9184 and Section 19
of the General Provisions of the FY 2022 NEP.
● The issuance of Notice of Award of contract shall be made once the General
Appropriations Act (GAA) for the budget year has been approved and enacted
based on the amount authorized therein.
18
consolidation into an Indicative APP and the BAC to recommend the
appropriate procurement modality. Indicative APP and budget proposal shall be
simultaneously submitted to the HOPE for approval.
● Once the GAA for the budget year has been approved, the end-user or
implementing units shall revise and adjust PPMPs, if any, to reflect the
budgetary allocation for their respective P/P/As. The revised PPMPs shall be
submitted to the BAC, through its Secretariat, for final recommendation of the
methods of procurement. The indicative APP shall then be revised and
approved by the HOPE and submitted to the GPPB-TSO on the prescribed
period.
● DENR Central Office, Regional Offices, PENROs and CENROs shall ensure
timely submission of procurement reports to GPPB-TSO and DBM-PS and
should be in accordance with GPPB issuance/s related for the purpose.
7.1.8 Due to the pandemic, all Bureaus, Regions and Offices shall
conduct their training/workshop thru other modalities (i.e. zoom,
google meet etc.). In case of face to face training, proper protocol
shall be followed as provided by the IATF and Department of Health
(DOH).
● Targets stipulated in various sectoral plans of the Department (i.e., River Basin
Master Plans, Philippine Master Plan for Climate Resilient Forestry
Development, Philippine Biodiversity Strategy and Action Plan (PBSAP),
National Protected Area System Master Plan, Regional Medium-Term Plan,
among others).
19
and ecotourism sites shall be specified by municipality or by site. Maps of the
proposed sites shall be provided.
● The unit cost for each activity and performance indicators shall be consistent
with the prescribed standards by the concerned Bureaus as indicated in the
Unit of Work Measurements (UWMs) (ANNEX H).
● Targets for the construction of buildings and other structures must be based on
their respective construction/improvement plan. Corresponding budget
allocation for the purpose must be reflected in the WFP.
7.1.10 All funding requests from LGUs, including the Representation from
the House of Representatives and other stakeholders, shall be
handled and shouldered by the ROs following the Bottom-up
process. In cases the request was submitted after NEP/GAA
issuance, the Region should inform the proponent that the proposal
shall be considered in the next Budget Proposal.
10
stated in the 2015 NEP/GAA
20
● Funding allocation (Fund101 or Fund102) for all P/P/As charged against
the Central Office-Based Budget shall be downloaded directly to the
implementing units.
● For requests from Regional Offices, Bureaus and different Offices at the Central
Office, the PPS shall review the request based on the following: 1.) priorities of the
Department; 2.) pronouncement and/or instruction of the Secretary; 3.) urgency of the
request. The PPS shall process the WFP subject to the availability of fund/will recommend
the necessity to do the activities without asking funding clearance from the FMS per
Memorandum of the Undersecretary for Policy and Planning dated 18 March 2019. (See
ANNEX I). In case the FMS recommends that no fund is available, the FMS shall be
responsible to INFORM the requesting party.
● All Central Office-Based Fund (COBF) WFPs shall be supported by BED Form 1
(by Object of Expenditures) and BED Form 3 (Monthly Disbursement Program). Refer
to ANNEX J for the prescribed format.
● All regions shall accomplish the prescribed forms as required by the DBM.
Regional Offices Concerned should cover the twenty-four (24) priority
climate vulnerable provinces and shall include preparation of budget for
every critical target activity/object for the provinces, as stipulated in the
Risk Resiliency Program – Program Convergence Budgeting Guidance
Document. Inclusion of additional six (6) provinces are required to follow
the RRP process as required by the Cabinet Cluster on Climate Change
Adaptation, Mitigation and Disaster Risk Reduction (CCAM-DRR)
Resolution No.3, Series of 2019, Adopting the Cluster’s Program
Convergence Budgeting- Risk Resiliency Program Guidance Document
for 2020 to 2022. See ANNEX K for the list of provinces for 2022.
● All Bureaus shall involve the Regional Planning Chief and Technical
Division Chiefs in any meetings, leveling-off, updates on the recent
developments or orientation on priority programs to ensure that all
concerns are properly considered in the preparation of WFPs.
21
7.2 Specific Guidelines
● Regional Offices with motor vehicle budget allocation shall submit to DBM
clearance to procure vehicles with the required attachments (i.e.
specifications, etc.) upon approval of GAA to facilitate procurement.
Regions should prepare plan for re-fleeting of vehicles and buildings for
improvement and construction.
● All ROs shall allocate sufficient amount for the provision of janitorial
services and security guards (Blue Guards) on a 24-hour basis down to
the CENRO level to provide security and safeguard of personnel,
equipment and facilities.
● The increase in the GMS at the Regional Offices shall be allocated for
mandatories and other operating expenses.
● All PENROs shall allocate funds for the hiring of Administrative Assistants
to assist the PENRO Budget Officer and PENRO Accountant in the
preparation of Financial Reports and in the implementation of Budget and
Treasury Management System (BTMS).
● DENR 3 Regional Office shall allocate sufficient fund for the maintenance
and operation of the DENR Environment and Natural Resources
Academy at Carranglan, Nueva Ecija.
22
● DENR Region 2 shall allocate funds for the Research Site for Bamboo as
part of Task Force Build Back Better (TFBBB) interventions.
● Sufficient amount shall be allocated for the creation and operation of the
DBCMC, including its Technical Working Group
● Php 9.5 million shall be allocated to the Zero Backlog Task Force of the
Legal Affairs Service. Legal Affairs Service shall prepare the Work and
Financial Plan.
23
● EMS & QMS focal units shall implement the cascading in coordination
with HRDS. (EMS and QMS funding are under conduct of special study)
● Hiring of Contract of Service and Job Order Workers in the DENR shall be
in accordance with the CSC-DBM-COA Joint Circular No. 1 s. 2018 dated
9 November 2018 and inclusion in the WFP. (See ANNEX M)
● PhP 3.2 Million to cascade the Online Leave Management System in all
regional and field offices and bureaus. Personnel shall include the
cascading activity to their WFP.
● Training programs that are not included in the L&D Plan has to be
approved by the HRD Service prior to its implementation.
24
Henceforth, all pertinent documents such as course design, draft
special order, and memorandum addressed to Undersecretary
supervising HRDS, requesting approval of the training program(s),
shall be submitted to the HRDS thirty days (30) before the target
date of implementation.
● All capacity building and other related personnel development trainings for
DENR Personnel and other stakeholders shall be funded under this
P/P/A. HRDS shall provide the list of trainings. Sufficient amount shall
be allocated for the capacity building of Planning Officers and other
technical personnel including training on the conduct of resource
valuation.
● Sufficient amount shall be allocated for the conduct of at least two (2)
batches each of ENR Academy frontline, basic training courses, and
specialized course on Environmental Law Enforcement.
25
Personnel Information System, conduct of HR audit, Sexual Harassment
Orientation Program and issuance of new DENR ID. The HRDS shall
prepare WFP.
● PhP 6.5 million shall be allotted for the implementation of Health and
Wellness activities/programs (i.e., flu and pneumonia vaccine, RT-PCR,
etc) of the Crisis Management Committee Medical Unit. HRDS shall
prepare the WFP.
o PhP 8 million for sixty (60) on-going grantees and thirty (30) new
grantees of online Master of Public Administration (MPA) program
for qualified employees. This is an online, blended and work-study
scholarship program being implemented by the Polytechnic University
of the Philippines Open University Systems (PUP-OUS).
26
● Sufficient amount shall be allocated to HRDS in support to the
operations and administration of the Capacity development Component
Working Group of the NCI-SRD Chaired by the DENR through the HRDS.
27
7.2.2 Support to Operations
Based on the Information Systems Strategic Plan (ISSP), the following shall be
charged against this PAP:
Within the regional budget, the following shall be charged under this PAP:
● The Regional Offices shall allocate at least 10Mbps and PENROs and
CENROs shall allocate sufficient bandwidth of at least 5Mbps in their
internet connection for LAMS operation. Those with separate LAMS office
shall be provided with a separate internet connectivity.
● Maintenance and updating of the DENR Control Map at the field offices in
accordance with the prescribed Guidelines and Standards in the
Establishment and use of DENR Control Map.
28
Within the Central Office Budget
● Sufficient amount shall be allocated for the conduct of GIS and ICT
training. WFP shall be prepared by KISS.
29
Within the Biodiversity Management Bureau
● PhP 20 million shall be allocated for the conduct of IEC and other tri-
media campaign activities of DENR programs and projects aimed to
create awareness on environment and natural resources protection and
conservation. These IEC campaigns to be funded shall include a
30
television and radio program (Ang Tinig Klima) on climate change and
other DENR programs. These platforms seek to promote awareness of
environmental programs and provide the public a better understanding on
climate change and other environmental issues and influence their
behavior towards the conservation and protection of the environment and
natural resources.
● Sufficient Amount shall be allocated for Tayo Ang Kalikasan (TAK) Task
Force related activities. The Task Force shall coordinate with SCIS on
their activities. The Task Force shall strengthen coordination with the
Regional TAK. The WFP shall be prepared by the TAK.
● PhP750 thousand shall be allocated for the Youth Desk and PWD/SC.
The SCIS – Stakeholder Management and Conflict Resolution Division
shall prepare the Work and Financial Plan
● Php2.5 million shall be allocated for the DENR Action Center Hotline.
11
The amount shall be on top of the annual budget of SAEPD
31
7.2.2.3 Legal Services including Operations on Unlawful Titling of Public
Lands
● Provision of funds for reversion cases including additional fund for Legal
and Personnel Discipline re: special investigation directed by DENR
Management during the year.
32
● Legal Service shall include in the preparation of their WFP the targets on
the inventory including the resolution of ageing cases and compilation of
all legal opinion and contracts review.
● The CCS shall provide capacity building and guidance to the Regional
Offices to help their selected highly urbanized cities set and achieve their
33
GHG reduction pledges and commitment. The process will involve setting
up the institutional structures, assessing policies, plans and capacity
needs in setting baseline city -level GHG emissions, building capacities of
the LGU through training and peer-to-peer learning exchanges,
stakeholder engagements, defining GHG reduction or avoidance targets,
prioritization of mitigation strategies, and developing Measurement,
Reporting and Verification plans, and implementing demonstration
projects and developing proposals to access finance. Sufficient fund shall
be allocated for this purpose, with work and financial plan to be prepared
by CCS.
● Php 1.5M (for verification with FMS) shall be allocated to review, and
facilitate the implementation and progress of projects and obligations to
34
the United Nations Framework Convention on Climate Change, Paris
Agreement, Kyoto Protocol, the ASEAN Working Group on Climate
Change, ASEAN Working Group on Environmentally Sustainable Cities,
among others. The CCS shall prepare the WFP.
● Php 950 thousand shall be allocated for the conduct of the preparatory
meetings and actual activities for the 2022 Pre-State of the Nation
Address (SONA) Report and Forum (i.e. Technical Working Group
Meetings, provision for services for development of audio-visual
presentations, printing of informational kit, etc.) for the 2022 Pre-SONA.
● PhP500 thousand shall be allocated for the National summit for River
Basins
● Sufficient amount to aid the research study on pollution load for selected
PAs.
● BMB shall coordinate with ERDB for the conduct of research studies for
the NIPAS MPAs and download sufficient amounts as may be
necessary.
● Sufficient amount to aid Carrying Capacity targets of ERDB and BMB for
selected PAs including capacity building.
35
o PhP500 thousand each for Regions MIMAROPA, IX, and X, XII and
CARAGA.
● All Regions involved in the BIMP-EAGA should have concrete output and
shall be submitted to PMED. Output of the quarterly meeting should not
just be minutes or report of the meeting conducted. Programs and
projects approved by BIMP-EAGA should be submitted for monitoring
and validation.
● PhP680 thousand (CO) for PENRO Lanao del Norte will finance the
maintenance and protection of 136 hectares agroforestry and
conservation farming under the INREM Project.
● PhP1 million shall be allocated for the Regional Planning Offices for
planning, monitoring and evaluation of DENR programs and projects.
This is net of Planning’s share from the PMS of all projects.
● The Regional PMD shall follow the template issued by the FMB thru
technical bulletin for validation of NGP and other priority programs
36
Technical Staff and Data Encoder to ensure all data requirements are
encoded in the system.
37
● Sufficient amount shall be allocated for payment of rendered overtime of
PPS-PPD and PMED and selected FMS staff (Budget and Accounting)
per priority activities that may warrant rendition of overtime services per
Civil Service Commission (CSC) and Department of Budget and
Management (DBM) Joint Circular No. 1. S.2015 dated November 25,
2015 and subject to the approval of the internal guidelines of DENR: CTO
for other offices
o Seasonal work, such as but not limited to, preparation of budget and
annual reports, in order to meet scheduled deadlines;
● PhP3 million for the formulation of land related policies for land
disposition, survey and records management.
38
o Formulation of RDE Program on Climate Change that will include
research proposals on baseline studies of ecosystems, climate
change responsive projects/studies, and rigorous scientific
projects/studies in order to assess and quantify the impacts of climate
change at all levels and across the different ecosystems. This is an
initial step to harmonize the ecosystem information which can serve
as a more comprehensive basis for long-term planning and
programming.
● Php96.014 million (MOOE) shall be allocated for the conduct of four (4) RDE
Programs and two (2) Support Programs formulated by the ERDB Main Office
and implementation of its six (6) Research, Development, and Extension
Centers (RDE Centers). These RDE Programs are based on the ERDB ENR
RDE Framework 2017-2022.
RDE Programs:
The allocation also includes the PhP500 thousand incentives for authors of
technical articles in the SYLVATROP journal as per DENR-MC No. 2016-04
Support Programs:
39
● ERDB Main Office and RDE shall intensify national and regional
dissemination and transfer of generated technologies to both
internal and external stakeholders. Activities for technology
transfer shall focus on the following:
● The RDE Centers shall submit the WFPs to ERDB Main Office for
review as basis for allocation of funds to implement Action
Research, Development and Extension (RDE) programs/projects
based on the Areas of Excellence.
● ERDB Main Office and PPS-PMED shall monitor and evaluate the
R&D programs/projects of the RDE Centers to ensure that the
expected milestones and/or outputs are delivered within the year.
Please refer to ANNEX Y for the list of projects/studies of each
RDE Programs with corresponding UWMs and duration.
7.2.3 Operations
The Regional Offices shall update their Forest Conservation Areas (FCAs) to
include NGP plantation sites that are no longer covered under Maintenance
and Protection. Presence of the patrollers will ensure the protection of NGP
graduated sites.
40
● Areas determined to be suitable for issuance of CBFM agreement and
other applicable forest tenure instruments based on the assessment of
potential investment areas shall be subjected to Community Organizing /
Development activities for subsequent issuance of CBFMA. Capacity
building / training activities shall be targeted for new CBFMA holders to
enhance their capacity in performing their responsibilities under the
agreement.
● For forest protection, all Regions shall follow the Menu of Activities
indicated in the approved National Forest Protection Program based on
regional peculiarities as reflected in their Regional Strategic Forest
Protection Action Plan. (See ANNEX Z)
41
had actions taken. The computation of target should include all patrollers
such as Forest Rangers, FPOs, and Forest Guard hired.
● Sufficient amount shall be allocated for the hiring of lawyers who will be
assigned in all PENROs and CENROs. The Office concerned should
secure from the Office of solicitor General's (OSGs) written conformity
and acquiescence, OSG deputation and Commission on Audit (COA’s)
written consent before hiring. In case, the implementing PENRO/CENRO
did not acquire the written consent from OSG, they may hire Legal
Assistant and Legal Researcher. Other incidental expenses shall be
shouldered by the Regional Office.
42
each other and from other revenues generated based on average
income for the past 3 years
o Monitoring in compliance to conditions of permits/lease/deeds
issued charged to PMS budget
● Php3 million shall be allocated for the Technical Support and Assistance
of LMB to Regional Offices.
● PA Community Management
43
● Sufficient amount shall be provided for the conduct of training programs
to strengthen the capacity of DENR employees in ENR management and
ENR law enforcement. Template on law enforcement training module
shall be provided by HRD Central Office under Operations against Illegal
Activities.
● Php 3 million (Capital Outlay) shall be allocated for the perimeter fence
(Php 1.5 million) and motorboat (Php 1.5 million) for Boracay Island under
PENRO Aklan. WFP shall be included in the regional office.
● Php 6.5 million (Capital Outlay) shall be allocated for the purchase of one
(1) unit of Ground-Penetrating Radar (GPR) which shall be used for Coron,
El Nido and Puerto Galera under MIMAROPA Region. WFP shall be
included in the regional office.
● Php 1.5 million (Capital Outlay) shall be allocated for the purchase of
motorboat for Siargao Island. WFP shall be included in the regional office.
44
the performance of their actual duties and functions. Fund shall come
from DBM with reference to DBM National Budget Circular No. 582 dated
Dec 29 2020.
The Regional Planning Officers shall collaborate with the Regional CDD and
PAMOs/PASUs when preparing their respective WFPs based on their approved
PA Management Plans.
PA Management
● For PA activities that will be charged under the Special Provision under FY
2022 NEP on Integrated Protected Areas Fund (IPAF) (ANNEX AC), separate
WFPs as well as the complete requirement, shall be submitted by the ROs to
BMB on or before 29 October 2021. Prioritization of protected areas and
activities to be funded as well as the maximum amount of Special Budget
Request (SBR) shall be based on the BMB TB No 2021-03 (Guidelines on the
Use of the IPAF Protected Area Retained Income Account (PA-RIA), Special
Account in the General Fund (SAGF), and Protected Area Trust Receipts (PA-
TR) and Providing the Criteria for the Allocation of Funds Deposited Under the
IPAF-SAGF in the National Treasury).
● Funds from the IPAF- Special Account in the General Fund (SAGF) which
comprise the twenty-five percent (25%) of deposited collections in the
National Treasury, shall be used for the development of income-generating
programs, projects, and activities consistent with the PAMP, including the
PAMO Operationalization and capital outlay requirements of the PA. Other
programs, projects, and activities including other Capital Outlay requirements
of the PA duly approved by the PAMB may be also funded under this account.
Considering that only MOOEs are provided under the regular funds for PA
management, IPAF shall prioritize capital outlay needs of each protected
area. The BMB shall review and submit to DENR/FMS the consolidated WFP
for the IPAF on or before 15 November 2021.
45
● Establishment and management of the Integrated Protected Area Fund (IPAF)
is guided by the BMB Technical Bulletin No. 2019-02 (Adopting the Manual on
the Establishment and Management of IPAF) and BMB Technical Bulletin No.
2021-03 (Guidelines on the Use of the Integrated Protected Area Fund (IPAF)
Protected Area Retained Income Account (PA-RIA), Special Account in the
General Fund (SAGF), and Protected Area Trust Receipts (PA-TR) and
Providing the Criteria for the Allocation of Funds Deposited Under the IPAF-
SAGF in the National Treasury).
● For CY 2022 Special Budget Request, IPAF shall be used for the following
priority PAs. (ANNEX AD).
Funds under this PAP shall be used to implement the priority activities of
protected areas under the NIPAS. With the current NEP of Regions/PAs, priority
areas shall be given to Legislated PAs, followed by the Proclaimed PAs, then the
remaining initial components of NIPAS. Further activities to undertaken should be
consistent with the classification of protected areas discussed below:
Investments should focus on all legislated NIPAS areas (107) as per the NIPAS
Act as amended by ENIPAS Act. These investments shall include, among others:
boundary demarcation and monitoring and maintenance of monuments, buoys
and signage, preparation/updating of PA Management Plan (PAMP), conduct of
Survey and Registration of PA Occupants to determine the tenured migrants,
monitoring and validation of PA occupants based on the SRPAO, habitat
protection, Biodiversity Assessment and Monitoring System (BAMS), Biodiversity
Monitoring System (BMS), PAMB Operations, Communication, Education and
Public Awareness (CEPA), and delineation of management zones and buffer
zones as an integral part of PA Management Plan, Ecotourism Management
Planning and Impact Monitoring, Inventory of Existing Facilities within PAs,
Inventory of Alienable and Disposable Lands, Property and Private Rights,
Inventory of tenurial instruments, contracts, agreements, and issuances of permits
for resource use within the protected area, PA Rehabilitation, Management of
IPAF, and PAMB and PAMO Operationalization.
46
Protected Area Occupants (SRPAO) in accordance with DAO 2013-2020
(Revised Guidelines on SRPAO). Per Section 10 of DAO 2013-20, monitoring
and validation of PA occupants shall be undertaken for PAs with completed
SRPAO or SEAMS in CY 2016-2017. See Annex AF for the list of PAs with
complete SRPAO or SEAMS in CY 2016-2017 based on the submission to
the BMB.
● The results of the BAMS, BMS and SRPAO/SEAMS shall be used as inputs
to management planning particularly in the identification and delineation of
management zones and prescriptions and interventions.
● The Regions shall strictly follow the management zoning guidelines stipulated
in the BMB TB No. 2018-01 “Clarifying the Procedures in the Identification,
Designation and Delineation of Management Zones of PAs under the NIPAS.”
Zoning shall be an integral part of the management plan of the protected
areas and shall be the basis for management interventions to achieve the
vision, goals and objectives of protected areas.
47
conservation and rehabilitation, biodiversity management, climate change
adaptation and mitigation, waste sewage and septic management, recovery
plan on the impacts of the pandemic and gender and development, among
others.
● The Management Plan shall serve as the basic long-term framework plan for
the management of protected areas and shall be used as reference in the
preparation of the annual work and financial plan. The Regional Office shall
ensure that the PAMPS are reviewed based on the aforementioned
guidelines/checklist (BMB TB 2016-08 and BMB TB 2017-08) before
endorsing to the Undersecretary for Policy and Planning thru BMB for
affirmation.
48
● For infrastructures already constructed in previous years, ROs concerned
shall allocate sufficient funds for the maintenance and rehabilitation of PA
facilities for 2022, taking into consideration compliance to standard design
and specifications per DAO 2009-09. (Standard Design and Specification of
Signs, Buildings, Facilities and Other Infrastructure that may be Installed and/
or Constructed within Protected Areas) and BMB TB 2016-03 (Standard and
Climate-Resilient Design of Protected Area Information Center and Signs and
Markers). Further, policies on waste disposal, sewerage, pollution control,
easement and geohazard-prone areas should be implemented in ecotourism
sites.
● The priority activities for the initial component of NIPAS shall be the Protected
Area Suitability Assessment (PASA) and law enforcement.
● The conduct of PASA shall be guided by BMB Technical Bulletin No. 2016-04
entitled “Clarifying the Procedural Guidelines in the Conduct of Protected
Area Suitability Assessment (PASA)”. The PASA shall support the
recommendation for the establishment, modification of boundaries or
disestablishment of a protected area. If an initial component is found suitable
for establishment under the NIPAS, the PASA Report shall include the
recommended category of the protected area. The PASA Report shall include
a narrative of the results of assessments, Forms 1, 2 and 3 duly signed by the
concerned Regional/Field Officials, and maps of the protected area, and shall
be submitted to BMB for review and further appropriate action.
49
Cave Management
● Sufficient amount shall be allocated for the inventory of inland wetlands for
those Regions and corresponding PENRO/CENRO who have not conducted
nor completed the inventory of inland wetlands within their jurisdiction.
50
specifically in profiling inland wetlands with high biological significance and
ecotourism potential but are outside PAs.
● Php 500 thousand shall be allocated for the operation and development of
each declared Ramsar sites or Wetlands of International Importance. (ANNEX
AI)
● PhP 9 million shall be allocated for the implementation of activities for the
nine (9) priority ASEAN Heritage Parks (AHP) in the country, namely: (i) Mt.
Timpoong-Hibok-Hibok Natural Monument; (ii) Mt. Malindang Range Natural
Park; (iii) Mt. Apo Natural Park; (iv) Mt. Kitanglad Range Natural Park; (v)
Agusan Marsh Wildlife Sanctuary; (vi) Mts. Iglit-Baco Natural Park; (vii) Mt.
Hamiguitan Range Wildlife Sanctuary; (viii) Tubbataha Reefs Natural Park.,
including the proposed Pasonanca Natural Park. Specific activities for the 5
AHP sites with target on Socio-cultural documentation and mapping should
include: comprehensive documentation and map of the socio-cultural
practices or IKSPs of Indigenous Cultural Communities/Indigenous Peoples
pertaining to resource use and conservation, establishment of culture
preservation plan of the community and policy brief, among others. For other
AHP sites, activities should be based in the AHP Regional Action Plan which
contributes to the achievement of the Aichi Targets, particularly Aichi Target
11. WFP shall be prepared by the Regional Office concerned and BMB.
51
Procedures in the Conduct of Assessment of Urban Biodiversity. BMB will
provide further guidance in the implementation of the program.
To further strengthen the Urban Green Spaces (UGS) program of the DENR,
focusing on the major urban areas, the CCS shall coordinate and work with
ERDB, FMB, and BMB in the formulation of a framework and plan of action for
2022-2030.
Regional Offices (NCR, VI, VII, XI) will form part of the team to be created for the
UGS program.
● Sufficient amount shall be allocated for the site identification, selection and
assessment of biodiversity in selected green spaces/parks in other regions,
including contracting experts to help DENR on the UGS matter.
● IAS Management in Protected Areas shall be prioritized and shall form part of
the PA Management Plan.
● Sufficient amount shall be allocated for the operation of the Palawan Wildlife
Rescue and Conservation Center.
52
Establishment and Management of Critical Habitats (CH)
● The ROs shall prioritize the establishment and management of CHs as listed
in ANNEX AK. Targets for CH establishment should be those areas that host
threatened species.
● Php 1 million shall be allocated for the operation of the Palawan Wildlife
Rescue and Conservation Center.
o Marine Protected Areas Networking with NIPAS MPAs per level identified
in the MPAN Toolkit: Pre-assessment, establishment, strengthening,
sustaining and institutionalization.
53
o Demarcation of Legislated NIPAS
o Hiring of Coastal Extension officers and boat captain and crew based on
the provided Terms of Reference.
● Regions shall refer to the draft JMC on MPA Network and MPAN toolkit
manual on the implementation of MPA Networking provided by BMB.
54
● Regions shall work with State Universities/ in habitat assessment and MPA
Networks.
● Regions shall coordinate with regional EMB for the inclusion of NIPAS sites
on monitoring water quality parameters and provision of technical assistance
to PAs on Monitoring and/or capacity building.
● Regions shall follow the Memorandum guidance dated January 21, 2020 on
the implementation of the NIPAS MPA Capacity Building Program in Regional
Clusters including hosting. The national mentors per DENR S.O. No. 2018-
534 shall continue to assist its implementation. Selected regions to pilot test
application of NIPAS MPA Capacity Building Program modules.
● Region shall continue the initiatives of the previous and existing projects on
coastal and marine outside NIPAS MPAS through technical assistance
including monitoring and maintenance of the rehabilitation efforts (identified
now as demonstration sites) from previous projects (ICRMP, SCREMP,
SMARTSeas, ACCCOAST, SSME, PAME, etc).
● Region IVB to allocate funds for the Snake Island as National Coastal and
Marine Center for Research to support activities indicated in the Operational
Plan.
● Region shall refer to the existing technical bulletins and guidelines on coral
rehabilitation and coral bleaching for activities under maintenance and
protection.
● Php 21.388 Million shall be allocated for the establishment of the Chiquita
and Grande Island Marine Scientific Research Station which will be
spearheaded by ERDB in coordination with BMB and the concerned field
offices. ERDB shall prepare the WFP.
55
Within the BMB Budget
● The DENR, as one of the mandamus agencies and mandated to lead the full
implementation of the OPMBCS and AO 16 series of 2019, shall allocate
funds from its regular budget for the implementation of the OPMBCS
designed for water pollution reduction, rehabilitation of various habitats and
resources and other related interventions.
● MBCO shall prepare the Road Map (2021-2022) for the Manila Bay
Rehabilitation including Investment Plan anchored on the FY 2017-2022
OPMBCS. MBCO shall submit this on 30 March 2021.
56
● The MBCO shall consolidate and review all the WFPs concerning Manila Bay
Rehabilitation Activities. Specifically, sufficient amount shall be allocated for
the implementation of rehabilitation plan for the River System Recovery to
River System Resiliency, aimed at establishing resilient communities for
present and future generations shall be piloted.
● The ROs shall likewise allocate funds for the provision of Technical
Assistance to LGUs and other partners in such areas as, but not limited to,
Integrated Coastal Resource Management Plan (ICRMP) formulation, crafting
of 10-Year Solid Waste Management Plan, implementation of the Manila Bay
Database System, etc.
57
o In support to attainment of the outputs of Outcome 3 (Encroachment
Along Easement Areas Permanently Removed), ROs within the
Manila Bay Area shall allocate funds for the delineation, development
and management of easements along identified/prioritized waterways.
o In support to the operations of the Manila Bay Task Force (MBTF) the
ELEPS and MBCO shall assist in the following activities shall be
conducted:
58
outlay of the PRCMO pursuant to the Executive Order No. 93, series of
2019 in relation to Administrative Order 16 s. 2019 “Expediting the
Rehabilitation and Restoration of the Coastal and Marine Ecosystem of
the Manila Bay and Creating the Manila Bay Task Force”; and
Department Administrative Order No. 2020-02. The WFP shall be
prepared by PRCMO.
● The PRCMO shall lead, facilitate, and sustain the cleaning and
rehabilitation of the Pasig River and its tributaries to meet water quality
guidelines of Class C Water in support to the rehabilitation of Manila
Bay as well as the water quality monitoring of the Pasig River, and shall
carry out the identified functions pursuant to the letter of favorable
consideration from the Department of Budget and Management (DBM).
● Sufficient amount shall be allocated for the Water Quality and Waste
Management Program of the PRCMO which includes the
implementation of programs, projects, and activities in relation to the
exploration and adaptation of water quality improvement strategies,
interventions, and technologies that aim to improve the Pasig River
System and its environs; and the monitoring of water quality of the Pasig
River and its tributaries through the conduct of water and sediment
quality analysis together with partner agencies under the Pasig River
Unified Monitoring System (PRUMS)
The ROs shall continue to implement priority programs, projects and/or activities for
the following:
Sufficient amount shall be allocated for the following priority programs, projects
and/or activities:
59
For Land Distribution/Disposition:
For Land Records Management and Data Capture through Land Administration and
Management System (LAMS), the following activities shall be implemented:
60
the linking of PLA (in item 2) shall be done at the PENRO
(CENRO to deploy its personnel to PENRO).
● PhP10 million shall be allocated for the Rapid Land Tenure Appraisal and
other land records management activities. LMB to prepare mother WFP.
● PhP2.4 million shall be allocated for the projection of all issued and pending
patents and Resource Use Instruments (RUIs) falling within CADT/CALT as
per JAO 2012-01.
● The projection of CADTs/CALTs requires hiring of 1 GIS Operator for
every 3-5 CADTs/CALTs for the following activities:
➢ Verification of submitted data by NCIP
➢ Preparation of basemaps
➢ CENRO/PENRO identification of patents with pending
registration
➢ Projection/Map Overlay and Analysis
➢ Preparation of Findings
● Php4.60 million for Land Records Maintenance, activities under Item 4 which
will not be covered by the Regional Budget
● The target and budget per region under CARP is disaggregated in ANNEX
AS.
● For Special Provision for CARP under FY 2022 NEP, see ANNEX AT.
61
● CARP Secretariat to prepare the WFP following the prescribed BED Form.
“The amount of Three Billion Six Hundred Eighty Nine Million Four Hundred
Sixteen Thousand Pesos (Php 3,689,416,000.00) appropriated herein under
Forest Development, Rehabilitation, Maintenance and Protection shall be used
for the implementation of Enhanced National Greening Program.
The DENR shall coordinate with the SUCs in the establishment of nurseries
including clonal nurseries, the conduct of forest research and mangrove
reforestation activities and other similar activities within the scope of the NGP
in their campuses.”
The Secretary of Environment and Natural Resources and the agency’s web
administrator or his/her equivalent shall be responsible for ensuring that the status of
accomplishments of the NGP from 2011 – 2021, including the geo-tagged photos of
the sites and the impact of the program to the communities, are posted on the DENR
and the NGP websites.
This Program shall enhance the past NGP by intensifying and expanding activities
that provide direct benefits to the communities while doing reforestation/afforestation
of degraded forestlands. It will take into consideration the economic potential and
maximize the benefits that can be derived from the program.
Under this Program, all existing NGP areas within production forest shall be
transformed into vibrant economic zones by increasing and expanding the existing
established plantations, and promoting social entrepreneurship. Open areas and
brushlands shall also be reforested. Species to be utilized shall include fast-growing
and desired species such as Mahogany, Gmelina, Mangium, Falcata and Bamboo,
among others, in support to the wood industry. Convergence and integrated area
development/management approach shall be adopted as key strategies in the
implementation of eNGP.
62
Reports on the progress of the implementation of Mangrove, Beach Forest and
Bamboo development shall be submitted to the FMB for development under ENGP
and BMB for those within protected areas. ERDB shall continue to provide technical
guidance and performance-based monitoring jointly with FMB and BMB in aid of
research.
The Survey, Mapping and Planning (SMP) target for FY 2022 shall be the target of
the Regions for planting in FY 2023 onwards. The SMP done on the previous year
should be used in FY 2022 target setting
Planting sites which have undergone Survey Mapping and Planning in 2021 should
make use of all available data sets. In addition, the targets on SMP shall be broken
down by province and shall not be lodged under the Regional Office during its
planning and programming activities. Following are to be considered in proper
identification of the area:
● Using the One Control Map, priority areas should be within the 18 major river
basins where most of the 94 priority critical watersheds supporting the
National Irrigation Systems (NIS) are located. However, in cases where the
Regions are not included under the 18 major river basins and under the 94
priority critical watersheds, the Region shall focus on their watershed areas
considered as “priority” and/or “critical”.
● Within the major river basins/critical watersheds, Region shall use the Forest
Land Use Plan (FLUP) and Comprehensive Land Use Plan (CLUP) in
categorizing/identifying the PAs, Key Biodiversity Areas (KBAs), High
Conservation Value (HCV) and untitled Ancestral Domain. Zone the
watersheds into production, protection, and disaster risk areas. Areas that
should be prioritized are (1) beach and mangrove areas prone to storm surge
and tsunamis, (2) headwaters and upstream of flood prone to low lying areas,
(3) recharge zones at the downstream level with critical groundwater levels,
(4) all riparian zones - occupied and unoccupied in rural and urban areas, (5)
sloping and steep roadside (where interventions are needed to stabilize the
slopes), and (6) urban areas for mini parks.
63
prioritized in all protection zones while establishment of and tree plantation
(i.e., timber, fruit trees) shall be prioritized in the multiple-use and production
zones. All proposed interventions shall be reflected in the Five (5) Year
Reforestation Plan amounting to PhP 200,000.00 per plan per watershed that
will be prepared by the field offices with the watershed as the planning units.
● CADT communal areas can be considered as potential site for eNGP, except
areas with CALT. Provided that there is a written consent from the concerned
IPs.
● For the enhancement of NGP graduated sites with at least 50% survival rate,
bamboo commodity will be prioritized. For other commodities, site species
suitability shall be considered. Seedling production and replanting will be by
administration. The prevailing labor rate in the Region as per DOLE will be
followed per Technical Bulletin Number 10-A.
Seedling Production/Procurement
● The results of Survey, Mapping and Planning and Assessment shall be the
basis in selection of species to be planted in the area. Site-species suitability
should be the priority to ensure high survival rate of the planted seedlings.
Species such as indigenous and/or endemic trees, bamboo and other suitable
species, depending on the area to be planted, including species with high
potential to take up/sequester carbon s hall also be considered in the
selection of planting materials.
● All MMFN shall produce at least 1 million planting materials without additional
cost. The equivalent area for plantation establishment and first year
Maintenance and Protection should be included in the regular target of the
Regions.
● All Regional Offices/PENROs shall ensure that their Seed Production Areas
(SPAs) and Individual Plus Trees (IPTs) are being maintained properly to
produce quality seeds. Seeds collected from SPAs and ITPs shall be
submitted in Forest Tree Seed Center (FTSC) for seed viability testing and for
storage. Regions shall submit to FMB and ERDB reports on seeds collection,
submission and testing at FTSC, and distribution in MMFN.
● Regions shall include a budget for the maintenance of clonal nurseries and
continue the production of 20,000 cloned seedlings from clonal nurseries. No
separate funding will be allotted for the production of cloned planting
materials. Corresponding activity of plantation establishment and 1st Year
Maintenance and Protection (for the 20,000 cloned planting materials) shall
be budgeted as a regular target. Areas shall be identified and designated so
as not to mix cloned seedlings with regular planting materials. Reports
including shapefiles shall be submitted to FMB.
64
● For Comprehensive Site Development, the contracted partners should conduct
seedling production, plantation establishment and Maintenance and
Protection of the established plantations.
● Production of planting materials should be done on-site or near the planting site
to avoid stress of seedlings during transportation and hauling.
Mode of Implementation
For 2022, the mode of implementation will be family approach. Family approach is
engaging upland and rural families in the implementation of the National Greening
Program (NGP) to contribute to the government’s objective of providing additional
income to families affected by the pandemic. Individual family contractors must meet
the qualifications and standards set by the Department at the time of entering into an
agreement. The Program covers single families and extended families. In addition, a
single person living alone is considered a separate family. It allows the Program
implementers to engage a single or extended family to enter into an agreement with
the Department, taking into consideration the rules and regulations provided under
the Manual on Community Participation in Government Procurement.
The Department, shall enter into a Memorandum of Agreement (MOAs) with People’s
Organizations (POs) which shall then enter into Letter of Agreements (LOAs) with the
family beneficiary for a period of three (3) years to conduct various modes of site
development in a parcel of forestland with an area of at least one (1) hectare and at
most ten (10) hectares. Each family may be engaged in establishment of timber and
non-timber plantations (bamboo, rattan), establishment of agroforestry plantations,
rehabilitation of forests using endemic timber and non-timber species, beach forest
and mangrove rehabilitation. They can also be engaged in protection and
maintenance of established plantations. (See ANNEX AU) (Amended FMB TB 30)
Monitoring of eNGP
ERDB shall provide technical guidance and assistance in the monitoring of clonal
nurseries and seed sources.
65
Within the Regional Budget
● Each PENRO shall establish an agroforestry model site based on the models
develop by ICRAF in the implementation of the INREM Project. The model
site shall be developed based on its site applicability, economic viability and
social acceptability. See ANNEX AV for the menu of models. In support to
strengthening the Bamboo industry, the PENROs shall likewise develop pilot
sites for bamboo plantation establishment. Guidelines for this shall be
provided by FMB.
● All certificates of site development and geo-tagged photos and GIS generated
maps of NGP sites/area planted from 2011 to 2021 shall be submitted to
FMB for evaluation. The shape files of the proposed FY 2022 planting sites
should be submitted to FMB for evaluation.
● PhP5 million per MMFN shall be allocated for the maintenance of all
operating MMFN and production of a minimum of one (1) million seedlings per
MMFN. For Regions with MMFN, seedling production through mechanized
nurseries shall be included in their regular targets.
● No other expenses shall be charged under this P/P/A except for indirect costs
e.g., water, fuel, rental, electricity, repair of vehicles and equipment used for
NGP activities, communication expenses (fax, mobile wi-fi) used for
monitoring and personal protective materials as provided in the NEP.
● Six (6) clonal nurseries will be retained at ERDB with corresponding budget
allocation of PhP2.1 million for its maintenance and development of macro-
propagation protocols for indigenous forest tree species. The target and
budget under this program is distributed per RDE Center. Please see ANNEX
AY.
● A corresponding amount of PhP1.2 million (CO) shall be allotted for the 2nd
and 3rd year maintenance and protection of plantations established in FY 2020
and 2021.
66
● PhP12 million shall be allocated for the maintenance of the six (6) existing
Forest Tree Seed Centers including forest tree seed processing, testing,
registration, source documentations and distribution. The FTSCs shall also
process, test, and verify sources of forest tree seeds for
certification/accreditation as per DAO 2021-21 and shall follow the procedures
stipulated in the Field Manual for Tree Seed Collection, Processing, and
Certification of Quality Planting Materials (see ANNEX AZ) of the said DAO.
● PhP10 million (MOOE) shall be allocated for the maintenance and full
operation of four (4) production facilities for mycorrhiza. ERDB shall produce
and provide mycorrhizal inoculants to all regions. See ANNEX BA for the
schedule of mycorrhizal inoculant delivery to the regional office and required
volume in terms of regional seedling production target. A sufficient amount
of the budget shall be allotted in the conduct of a built-in study on the
effectiveness of Hi-Q Vam1.
● PhP10 million (MOOE) shall be allocated for the maintenance and protection
of the 24 Experimental Forests. See ANNEX BB for the list of ERDB
Experimental Forests.
● PhP14 million shall be allocated for the continuous capacity building and
technical assistance for regional implementers; conduct of four (4) special
studies/activities (Whole-Ecosystem Carbon Stocks and Sequestration of
Forest Plantations under the National Greening Program in Davao and
Central Luzon Region; Time and Motion Study on the Production of Quality
Planting Materials using rooted Cuttings through Macro-somatic Cloning and
Seed-based Propagation Technology; Mapping of Soil Chemical and Physical
Properties of the FY 2021-2025 Priority NGP Planting Sites in the Philippines;
and Assessment and Maintenance of Selected Clonal Seed Orchards as
Source for Forest Seeds); monitoring and evaluation of eNGP activities, and
other related activities.
67
7.2.3.2.5.2 Soil Conservation and Watershed Management including River
basin Management and Development
● Sufficient amount shall be allocated for the Soil Conservation and Water
Conservation Measures i.e., small water impounding system, structural
measures (checkdam, gabions, etc.) and vegetative measures (wattling,
riverbank stabilization, etc.). Selection of areas shall be based on the
approved Integrated Watershed Management Plan and per FMB Technical
Bulletin Number 13, 13-A, and 15.
68
NIS. The IWMPs shall serve as the management framework and basis for
identifying development, conservation and protection targets.
● Watersheds with approved management plans (IWMPs) shall use said plans
as the overall development framework. Targets under the ENGP shall
prioritize rehabilitation of protection areas identified within the 94 priority
critical watersheds supporting NIS. Private sector investment shall be
strengthened/encouraged for the development of production areas.
● PhP8.5 million shall be allocated for the sustainable operation of RBCO. Key
activities include the continued rolling-out/ implementation of the Integrated
River Basin Management and Development Master Plan (IRBMDMP)
including the newly formulated master plan of the 8 clustered River Basins,
specifically the assessment of IRBMDMP that are being implemented for
more than 5 years, strengthening of River Basin Organizations (RBOs) and
Basin Governance, maintenance and updating of database and monitoring
and evaluation through the updating of control map per river basin, policy
formulation and review, coordination with water and water related NGAs for
effective and efficient water governance and participation to water related
events
● In cases where the River Basin Master Plan covers two (2) or more regions,
each region, for management purposes, shall come up with sub-basin/s
implementation plan which is consistent/anchor to the master plan.
● The region who has the larger (2 regions)/largest (more than 2 regions) area
covered in the major river basins shall take the lead role in coordinating
efforts, ensuring convergence and convening of the RBO concerned.
69
● Watershed Characterization cum Vulnerability Assessment shall be
completed /updated on all the identified 94 priority critical watersheds
supporting NIS (ANNEX BE). Regions may target Watershed
Characterization cum VA outside the priority critical watersheds supporting
NIS only if the Characterization cum VA including IWMP of the same within
their region has already been completed. Regions should always conduct the
Watershed Characterization cum VA prior to the preparation of IWMP.
(watershed characterization roadmap c/o FMB to be shared with PPD and
Budget).
● Php 1.5 Million per region shall be allocated for the conduct of study on
Carbon Sequestration following the methodology from ERDB (ANNEX BF,
___ technical bulletin) on NGP sites except regions NCR, III, XI and
CARAGA. The output/report shall be submitted to the PMED, copy furnished
the CCS.
● Php5.305 Million (MOOE) shall be allocated for the conduct of one (1)
Ecosystem Service Valuation study as pilot site for the development of an
ecosystems valuation protocol. Sufficient amount shall be allotted also under
this P/P/A for the provision of technical assistance for Regional Offices in the
conduct of Vulnerability Assessment of priority watershed and determination
of carbon sequestration on NGP sites.
70
● Monitoring and reporting of physical and financial accomplishment of FASPs
shall be the responsibility of the Bureau/Region through their respective
Planning and Finance where the projects are located. They shall also be
responsible for the preparation and regular submission of reports to the
Central Office (i.e. PPS copy furnish FASPS and FMS).
● Regions with Foreign Assisted Projects shall prioritize the FMP sites to catch
up with the project implementation. Strict monitoring of FMP implementation
should be done by the regions and shall ensure that the project is progressing
as planned.
The EMB shall continue to prioritize the three (3) programs included in the
Department’s major programs in CY 2022 and strengthen the implementation of
activities for the improvement of air and water quality, hazardous waste disposal and
increased compliance of LGUs on RA 9003.
TOTAL BUDGET
EXPENSE
GASS STO OPERATIONS TOTAL
CLASS
MOOE 101,725 123,077 899,753 1,124,555
CO - - 804,170 804,170
PS & RLIP 242,994 79,996 737,740 1,060,730
TOTAL 344,719 203,073 2,441,663 2,989,455
71
9.1 A.01 General Administration and Support Services
● Sufficient amount shall be allocated by the EMB Central Office for the
preparatory activities in organizing the conduct of Capacity Building for LGUs
on the EMB devolved functions
General Guidelines
Continuous capacity building with the PENROs and CENROs personnel shall be
conducted to orient them on the current guidelines as to its role in the implementation
of related EMB activities. Indicators and expected output from them shall be included
as well.
9.3 Operations
72
● PhP72.187 million shall be allocated for the analysis of samples, upgrading
of laboratory facilities, research studies, assessment/monitoring of
laboratories, capacity building, trainings and calibration/maintenance of
existing dioxins & furans and other laboratory which equipment of EMB
Central and Regional Offices which are vital to produce reliable and
accurate data.
● Sufficient amount shall be allocated for the conduct of capacity building for
LGUs on the Air Quality devolved functions by the EMB Central Office.
● PhP36.411 million shall be allocated for the monitoring of 16,915 firms with
issued Permit to Operate pollution devices and survey of 2,973 firms
without permits, to ensure its compliance with the Clean Air Act.
● Sufficient amount shall be allocated for the IEC and consultation activities
with the LGUs on the Air Quality devolved functions by the EMB Regional
Offices.
73
9.3.5 A.03.b.2 Implementation of Clean Water Regulation
● Sufficient amount shall be provided by the EMB Central Office for the
conduct of capacity building for LGUs on the Water Quality devolved
functions.
● PhP16.874 million for the promotion and other IEC activities for the “Adopt-
an Estero/Waterbody” program, monitoring of compliance to the signed
MOAs and engaging CSOs, LGUs and Academe partners in improving the
water quality of adopted esteros/waterbodies within Water Quality
Management Area (WQMA).
● PhP18.117 million shall be allocated for the survey of 3,000 firms without
permits and monitoring of 11,196 firms with Waste Water Discharge Permits
to ensure its compliance with the Clean Water Act.
74
evaluation of 10-Year Solid Waste Management Plans endorsed by the
EMB Regional Offices, validation of the Regional Offices’ accomplishments
and conduct of capacity building for the regional SWM focal persons,
ENMOs.
● Sufficient amount shall be provided by the EMB Central Office for the
conduct of capacity building of LGUs on the SWM devolved functions.
● PhP101.310 million shall be allocated for solid waste operations and other
support activities of the Regional Offices to include among others the
following: Implementation of Solid Waste Enforcers and Educators Program
to monitor LGUs’ compliance on SWM in public places, educate and assist
barangays to comply with its role in RA 9003, and assist LGUs in the
conduct of self-compliance monitoring with RA 9003, maintenance of
established Regional Ecology Centers nationwide and upgrading of
National Ecology Center, and conduct of IEC, training, summit.
75
10.0 Mines and Geo-sciences Bureau (MGB)
The MGB’s Major Programs and strategies for 2022 are the following:
FY 2022 Budget
MGB
(in Million Pesos)
Total 1,488.883
PS & RLIP 779.993
MOOE 604.137
CO 104.753
10.1 A.01 GENERAL ADMINISTRATION AND SUPPORT (GAS)
Capital
PS & RLIP MOOE TOTAL
Outlay
257,143 68,838 - 325,981
76
10.2 A.02 SUPPORT TO OPERATIONS (STO)
Outcome Indicators:
Output Indicators:
77
The activities and the corresponding budget and target to attain the Outcome
Indicators and Output Indicators are as follows:
Permit Issuance
Audit
● PhP3.693 million shall be utilized for the conduct of annual audit of the
monitoring system of the 15 MGB ROs to validate the results and
compliances of the 65 mining contracts/permits pursuant to the MGB
Memorandum Circular No. 2018-02 (Guidelines for Compliance
Monitoring and Rating/Scorecard of Mining Permits/Contracts) and other
pertinent laws, rules and regulations.
Enforcement
Mine Rehabilitation
Permit Issuance
● PhP0.253 million shall be allocated for the issuance of 135 mining
rights/contracts (MPP, ISAGP, EP) and 3,629 other mining-related
permits (OTP/OTC, Accreditations, CEMCRR/CoE);
Small-Scale Mining
Monitoring
78
Offices (ROs) shall monitor all the mining permits/contracts within its area
of jurisdiction and;
The monitoring of FTAA, MPSA and EP will be subjected to the MGB Memorandum
Circular No. 2018-02 (Guidelines for Compliance Monitoring and Rating/Scorecard of
Mining Permits/Contracts) and other pertinent laws, rules and regulations.
Enforcement
Outcome Indicators:
Output Indicators:
The activities and the corresponding budget and target to attain the
Outcome Indicators and Output Indicators are as follows:
Mineral Reservation
79
c) Research and development on mineral resources – geological mapping,
geochemical sampling for:
Geologic Mapping
Offshore Exploration
Geologic Mapping
80
OO3: Adaptive Capacities of Human Communities and Natural Systems Improved
Outcome Indicators:
Output Indicators:
The activities and the corresponding budget and target to attain the Outcome
Indicators and Output Indicators are as follows:
81
● PhP21.778 million (MOOE) for the conduct of Coastal Vulnerability Index
(CVI) in 112 coastal cities/municipalities.
FY 2022 Budget
Office
(in Million Pesos)
Total 1,304.193
PS 515.923
MOE 788.270
CO 0
Under Special Provisions of the FY 2022 NEP (see ANNEX BN), NAMRIA was allocated:
82
● Php 45.521 million shall be allocated for the modernization of the
Philippine Geodetic Reference System.
● Php 13.518 million shall be allocated for updating of land cover and
coastal resources maps in support to Disaster Risk Reduction
Management and Climate Change.
● Php 5.320 million shall be allocated to produce two (2) land classification
maps of the remaining Unclassified Public Forest (UPF) covering
municipalities of Don Carlos, Pangantukan and Valencia and
municipalities of Cabanglasan, Malaybalay and San Fernando, both in the
Province of Bukidnon.
FY 2022 Budget
Office
(in Million Pesos)
Total 135,467
PS 74,301
MOE 51,980
CO 9,186
For Special Provision under the FY 2022 NEP, see ANNEX BO.
Water Resources Vulnerability and Sustainability Assessment Program
● PhP7.400 Million shall be allocated for the Comprehensive Water
Resources Assessment for Major River Basins (Cagayan River Basin);
and
83
● PhP1.500 Million shall be allocated for the Water Level and Quality
Monitoring Information System.
● Php3.803 million shall be allocated for updating and ground validation of four
(4) municipal Environmentally Critical Areas Network (ECAN) maps; (Kalayaan,
Cagayancillo, Agutaya and Balabac) administration of ECAN Zones Scorecards,
policy research/development for ECAN zones.
● Php5.352 million shall be allocated for wildlife and cave management, including
implementation of Wildlife Resources Conservation and Protection Act, National
Caves and Cave Resources Management and Protection Act, Chainsaw Act,
and other environmental laws mandated to PCSD, and population studies on
threatened species
84
● Php 20.243 million shall be allocated for procurement of ICT requirements such
as equipment, software, supplies, training, and professional and other services,
as indicated in the approved PCSDS Information Systems Strategic Plan (ISSP)
(see ANNEX BP)
● PhP15 million from the Wildlife Management Fund, shall be allocated for the
following (see ANNEX BQ)
● GAD mandate and activities shall be mainstreamed in the regular P/A/Ps within
the national priority and respective sectoral programs of the Central Office,
Bureau, Regional Office, and Attached Agencies. The Gender and Development
Focal Point Systems (GADFPS) shall assist their respective offices/ sectors in
developing annual GAD plans and budget (GPBs), in monitoring and
assessment of the implementation of these plans and in preparing annual GAD
accomplishment reports (AR).
● Bureaus, Attached Agencies and Regional Offices shall prepare their respective
WFPs summarizing all GAD-related activities programmed in the various
sectoral PAPs, including priority programs and projects within the scope of
their responsibility. The National Gender and Development Focal Point
System (NGPFS) and Policy and Planning Service of the Central Office shall be
furnished with these WFPs.
● The NGADFPS shall be responsible for reviewing and consolidating all GAD
plans and budget, and accomplishment reports of the Central Office, Staff
Bureaus and DENR Regional Offices for submission to Philippine Commission
on Women (PCW), through the Gender Mainstreaming Monitoring System
(GMMS).
● The EMB and MGB shall consolidate GPBs and ARs of their subsidiary
units/offices, ensure alignment of their consolidated GPB with DENR’s GAD
Strategic Plan 2021-2025, and ensure full attainment of GPB targets as planned.
these consolidated GPBs, including such for attached agencies, will be
submitted to the Philippine Commission on Women, through the Gender
Mainstreaming and Monitoring System (GMMS). Copies of these consolidated
GPBs and ARs should be provided to NGFPS.
● All major programs and projects especially the national priority projects should
be subjected to the Harmonized GAD Guidelines (HGDG) using the HGDG
Program/Project Design Checklist for Natural Resources Management Projects
and submit the results, computation of attribution and means of verifications or
MOV documents to NGFPS along with annual GPBs.
85
● All major programs and projects, especially national priority programs should be
subjected to HGDG Program Project Implementation and Management,
Monitoring and Evaluation or PIMME Checklist, and submit the results,
computation of attribution and MOVs to the NGFPS, along with the annual ARs.
● Bureaus, Regional Offices, Attached Agencies and the Central Office as a whole
shall ensure that their consolidated GAD budget is at least 5% of the total budget
of their respective offices/agencies/organizations as authorized under the annual
GAA, and specifically stated under Section 6 of the PCW-NEDA-DBM Joint
Circular No. 2012-01. Apart from direct budget allocation for GAD activities,
Bureaus, Regional Offices, and Attached Agencies can augment their GAD
budget allocation by applying HGDG to the DENR priority programs or projects
that they manage/implement.
● Renovation of the Day Care Center, provision of the GAD Office, and other
requirements for the GAD Program shall be ensured.
In fulfilling the 0+10 Point Socio-economic Agenda, the level of prioritization has
been intensified with the inclusion of our budget in the Key Result Areas as laid out in
E.O. 24 (Reorganization of Cabinet Cluster System) and the Philippine Development
Plan 2017-2022, as follows:
● Climate Change Adaptation, Mitigation, and Disaster Risk Reduction
Cluster
● Human Development and Poverty Reduction Cluster
16.1 Applicable to DENR Central Office, EMB, MGB, NAMRIA, NWRB, including
Projects
● A 5% support fund based on MOOE (under Fund 101 and 102-GOP only) of the
net programmable budget shall be set aside/earmarked as contingency fund,
from where unprogrammed and related new priority activities shall be funded.
The use of this amount shall first be cleared with/approved by the Secretary upon
submission of a detailed plan/proposal.
● At least five (5%) of the total agency budget shall correspond to activities
supporting GAD plans and programs. The GAD budget shall be drawn from the
agency’s MOOE, capital outlay (CO) and personal services (PS). Utilization of
this fund shall be the head of the concerned office. Gender and Development
Guidelines (HGDG) should be adopted/implemented in the CY 2022 GAD WFPs
together with the DENR GAD Roadmap for CY 2022, as reflected in the
86
enhanced GAD Strategic Plan for 2020-2025. Of the 5% GAD allocation,
attribution should be done based on the Harmonized Gender and Development
Guidelines (HGDG).
● 1% of the net programmable budget shall be set aside for the implementation of
projects/activities for senior citizens, differently-abled persons, and the youth.
This can also be mainstreamed in DENR activities, e.g., in the construction of
office buildings with architectural facilities or structural features and designs that
shall reasonably enhance the mobility, safety and welfare of differently-abled
persons pursuant to B.P. Blg. 344 and R.A. 7277.
● A 5% support fund based on MOOE (under Fund 101 and 102-GOP only) of the
net programmable budget shall be the contingency fund from where
unprogrammed and related new priority activities shall be funded. The use of this
amount shall first be cleared with/approved by the Secretary upon submission of
detailed plan/proposal.
● At least five (5%) of the total agency budget shall correspond to activities
supporting GAD plans and programs. The GAD budget shall be drawn from the
agency’s MOOE, CO and PS. Utilization of this fund shall be the responsibility of
the head of concerned office. The Harmonized Gender and Development
Guidelines (HGDG) should be adopted/ implemented in the CY 2022 GAD WFPs
together with the DENR GAD Roadmap for CY 2022. Of the 5% GAD allocation,
attribution should be done using the Checklists indicated in the HGDG.
● The Regional Offices must ensure timely submission to the Central Office of GAD
accomplishment reports for overall agency assessment and evaluation purposes.
● Php 300 thousand shall be intended for the maintenance and other
operational expenses of the Regional Internal Audit Focal Persons (RIAFPs)
under the Office of the Regional Executive Director (RED). RIAFPs shall
provide a copy of their respective WFPs approved by their Regional Executive
Directors to the Director of Internal Audit Service. The IAS shall provide a
template to the RIAFPs for uniformity of activities
● 1% of the net programmable budget shall be set aside for the implementation of
projects/activities for senior citizens, differently-abled persons, and the youth.
This can also be mainstreamed in DENR activities, e.g., in the construction of
office buildings with architectural facility pursuant to B.P. Blg. 344 and R.A. 7277.
● Bureau/ Regional FDUs shall monitor the execution of programs and projects
and undertaken promptly and in accordance with the set timelines or targets
pursuant to AO 46 issued by the President (DBM Circular Letter No. 2015-8
dated 08 June 2015) DENR S.O. No. 2015-766 dated 14 July 2015
87
● To cover the Personnel Services (PS) deficiency, the Expanded Plantilla (based
on PSIPOP) as of 31 December 2021 must be submitted to the Budget Division.
This must be supported by an Analysis Sheet to easily determine the PS
deficiency to be requested from the DBM to be charged under the Miscellaneous
Personnel Benefits Fund (MPBF)
● The appropriated amount for commonly-used office supplies and materials under
each PAP shall be pooled and managed by the Budget Division in coordination
with the Property and Supply Management Division (PSMD).
● Php 300 thousand shall be set aside to be intended for the maintenance and
other operational expenses of the Bureau Internal Audit Focal Persons (BIAFPs)
under the Office of the Bureau Director. BIAFPs shall provide a copy of their
respective WFPs approved by their Bureau Directors to the Director of Internal
Audit Service.
17. 1 Upon receipt of these guidelines, the concerned offices are required to prepare
their WFPs to conform to the approved budget and the priorities for the year as
well as to prepare their monthly cash program and other required budget
documents.
17.2 Planning Workshop for FY 2022 for Regional Offices will be conducted on
October 18-22, 2021.
The final WFP for FY 2022 consisting of two (2) sets of hard copies and an
electronic copy of all Regional Offices and FAPS shall be submitted to the Central
Office through the Planning and Programming Division (PPD) on or before
October 29, 2021.
Planning Workshop for FY 2022 for Central Office Services will be conducted on
November 15-19, 2021.
The final WFP for FY 2022 of Central Office/Bureaus (Staff and Line) and
Attached Agencies shall be submitted on or before November 24, 2021.
All other budget forms shall be submitted to the Budget Division on October 29,
2021.
88
● Approved APP based on the GAA submitted to the GPPB-TSO in the format
prescribed under GPPB Circular No. 02-2020 thru email address
app@gppb.gov.ph submitted on the prescribed period.
● DENR Central Office, Regional Offices, and PENROs shall ensure timely
compliance on the submission and/or electronic posting of procurement
reports to GPPB-TSO and DBM-PS and should be in accordance with the
latest GPBB issuance/s for the purpose.
● The Regional Offices shall monitor compliance of its respective PENROs and
CENROs and shall furnish a report with MOVs to the DENR-Central Office
through the Administrative Service thru its Property and Supply Management
Division (PSMD) at email address denrcoprocurement2020@gmail.com
and/or fax no. 926-2675 at least three (3) calendar days from the deadline set
by GPPB-TSO and DBM-PS.
17.5 Failure to submit all the required documents on the set deadlines shall be
considered as a demerit to the head of office and shall be considered as a
severe negligence of duty: this may be meted a penalty under the One-
Strike Policy in measuring performance of the concerned official.
18.0 Responsibility
18.1 The Planning Officers, Finance Officers and Budget Officers of the Staff/Line
Bureaus, Regions and attached agencies of the DENR shall prepare and submit
their respective WFPs and other required budgetary documents to Planning and
Programming Division (PPD) and Budget Division (BD) of DENR. The heads of
these offices shall sign as “Recommending Approval” in the document to be
submitted.
18.2 At the DENR Central Office, preparation and submission of the WFP shall be
done by service/office/unit. The heads of these offices shall also sign as
“Recommending Approval” in the document to be submitted. The document
shall also be submitted to PPD and BD.
18.3 The USEC for Policy and Planning and USEC for Finance are hereby authorized
to:
● Approve the final WFPs of the ROs, Staff Bureaus and Central Office
Services and Coordinating Offices.
18.4 At the Regional Offices, the CY 2022 Planning Guidelines shall also be
disseminated to the Field Offices including PASu Offices to facilitate better
planning and budgeting processes.
18.5 The Bureau Directors and Regional Executive Directors shall see to it that the
Audit recommendations are fully complied/implemented. Management
89
Division of FMS shall monitor the compliance and regularly submit report
to the USec for Finance, Information Systems and Climate Change through
the Asec for Finance, Information Systems and Mining Concerns. (Limits of
compliance statement c/o FMS-MD).
19.1 The review and evaluation of the submitted WFPs should be done jointly by the
Central Office Planning, Central Office Budget and Bureau Planning Officers
(except EMB, MGB and attached Agencies). EMB, MGB and attached agencies
must furnish a copy of their approved Work and Financial Plan to Policy, Planning
and Programming Service thru PPD and PMED on or before October 29, 2021 for
reference and monitoring purposes.
➢ Review of each Regional and Central Office WFPs by PPD shall be within
fifteen days upon submission of the Region and shall be endorsed for
approval to the Undersecretaries.
o For the DENR OSEC, the modification of allotment within MOOE and
Capital Outlay and within PAP shall be undertaken as follows:
For the Central Office, approval of modification shall follow the DENR
Manual of Authority upon the recommendation/request of the Head of
Offices/Service/Coordinating Office
For Staff Bureaus, the Director shall be responsible for the approval
upon the recommendation of the Chief Planning Officer and the
Budget Unit head.
For the Regional Field Offices (ROs and PENROs), the Regional
Executive Directors through the ARD for Management Services shall
be responsible for the approval upon the recommendation of the Chief
Planning Officer and the Chief Finance Officer.
90
Accomplishment of the targets per approved Work and Financial
Plans shall not be affected
Provision for mandatory expenditures under GAA for the year must
be fully settled
Per DBM-COA Joint Circular No. 2014-1 dated July 2, 2014 “Guidelines Prescribing
the Use of Modified Formats of the Budget and Financial Accountability Report
(BFARs).”, Joint Circular Letter No. 2019-1 dated January 1, 2019 “Updated
Guidelines Relative to Budget and Financial Accountability Reports starting FY 2019”
and Circular Letter No. 2019-13 dated October 31, 2019 and 2020-13 dated October
26, 2020 “Reminding Agency Submission of Budget Execution Documents (BEDs)”,
the ROs, Bureaus and Attached Agencies are required to submit the following reports
on the due dates hereunder prescribed:
91
Monthly Disbursement BED Form 29 November of Budget Division
Program No. 3 the current year
Annual Procurement Plan BED Form 15 December of Property and Supply
for Common Supplies No. 4 the current year Management Division
and Equipment (APP-
CSE)
B. BUDGET AND FINANCIAL ACCOUNTABILITY REPORTS (BFARs)
QUARTERLY
Type of Form Due Dates Due Dates Due Dates Office
Report No. of of of Primarily
Submissio Submission Submission Responsible
n to to Central to DBM for
Regional Office (CO) Consolidation
Office (RO) from (OPRC)
from Regional
PENROs Offices
Quarterly BAR Within 30 Program
Physical No. 1 days after Monitoring and
Report of the end of Evaluation
Operation each quarter Division
(QPRO) (PMED)
Statement of FAR On or On or before Within 30 Budget
Appropriations, No. 1 before the the 15th day days after Division
Allotments, 10th day following the the end of
Obligations, following end of each each quarter
Disbursements the end of Quarter
and Balances each
(SAAODB) Quarter
92
Statement of FAR On or On or before Within 30 Accounting
Obligations, No. 1- before the the 15th day days after Division
Disbursements, C 10th day following the the end of
Liquidations following end of each each quarter
and Balances the end of Quarter
(SODLB) for each
Inter-Agency Quarter
Fund Transfers
93
ANNUALLY
MONTHLY
Monthly Report FAR On or On or before On or before Accounting
of No. 4 before the the 5th day the 10th day Division
Disbursements 3rd day following the following the
(MRD) following end of the end of the
the end of month (to month
the month supplement
(supplement data on the
data on the SPMR/FMR)
SPMR/FMR
)
In this connection, the ROs, Staff Bureaus and Attached Agencies shall
submit the required reports to the Office Primarily Responsible for
Consolidation (OPRC) not later than the 15th day after the end of each quarter
and not later than the 5th day of the following month for the monthly reports.
94
After the end of validity period, all unreleased appropriations shall lapse, while
unexpended or undisbursed funds shall revert to the unappropriated surplus
of the General Fund in accordance with Section 28, Chapter 4, Book VI of E.O.
No. 292 and shall not thereafter be available for expenditure except by
subsequent legislative enactment. Department, bureaus and offices of the
National Government, including constitutional offices enjoying fiscal
autonomy, SUCs and GOCCs, shall strictly observe the validity of
appropriations and the reversion of funds.
For the FY 2022, the appropriations for infrastructure capital outlays, including
those subsidy releases to GOCCs for infrastructure projects, shall be valid for
obligation until December 31, 2022, while the completion of construction,
inspection, and payment shall be made not later than June 30, 2023. On the
other hand, appropriations for MOOE and other capital outlays item shall
likewise be valid for obligation until December 31, 2022, while the delivery,
inspection and payment shall be made not later than March 31, 2023.
Upon approval of the GAA of the budget year, and in case there are changes
made by Congress from the NEP, i.e. increase, decrease or other modifications
for existing programs and projects or introduction of new items, the
corresponding Work and Financial Plans shall be adjusted in accordance with
the GAA and shall be approved by the authorized official.
APPROVED:
ROY A. CIMATU
DENR Secretary