A Wearing Course(Asphalt Conc.Pvmt.

) m2 6000

B Daily Output m2 4220

C A/B Duration, Days (8 Hrs/Day) Day 1.42

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.375 8 0.07 Mday

E2 Surveyor 1.000 8 0.18 Mday

E3 Equip Operator ( Medium ) 3.000 8 0.53 Mday

E4 Laborer 7.000 8 1.24 Mday

E5 Asphalt Paver 1.000 8 0.18 Mday

F Sum "E" Total Man 12.375

G F*D/B Manhour 0.02 8 0.19 Mday

H G*A Total Manhours 140.76 8 17.59 Mday

OD 3

Manpower/day 5.86

I Equipment: @ Hrs

I1 Tandem Roller, 9 Ton 1.000 8 0.18 Mday

I2 Roller, Pneumatic Wheel 1.000 8 0.18 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.004 8 0.03 Eday

L K*A Total Equiphours 22.75 8 2.84 Eday

OD 3.00

Equipment/day 0.95
A Binder Course(Asphalt Conc.Pvmt.) m2 6000

B Daily Output m2 5095

C A/B Duration, Days (8 Hrs/Day) Day 1.18

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.375 8 0.06 Mday

E2 Surveyor 1.000 8 0.15 Mday

E3 Equip Operator ( Medium ) 3.000 8 0.44 Mday

E4 Laborer 7.000 8 1.03 Mday

E5 Asphalt Paver 1.000 8 0.15

F Sum "E" Total Man 12.375

G F*D/B Manhour 0.02 8 0.16 Mday

H G*A Total Manhours 116.58 8 14.57 Mday

OD 3

Manpower/day 4.86

I Equipment: @ Hrs

I1 Tandem Roller, 9 Ton 1.000 8 0.15 Mday

I2 Roller, Pneumatic Wheel 1.000 8 0.15 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.003 8 0.03 Eday

L K*A Total Equiphours 18.84 8 2.36 Eday

OD 3.00

Equipment/day 0.79
A Compaction m3 5000

B Daily Output cu.m 1600

C A/B Duration, Days (8 Hrs/Day) Day 3.13

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Truck Driver 1.000 8 0.39 Mday

E2 Equip Operator ( Medium ) 1.000 8 0.39 Mday

E3 Laborer 1.000 8 0.39 Mday

F Sum "E" Total Man 3.000

G F*D/B Manhour 0.02 8 0.12 Mday

H G*A Total Manhours 75.00 8 9.38 Mday

OD 3

Manpower/day 3.13

I Equipment: @ Hrs

I1 Water Tanker, 25m3 1.000 8 0.39 Mday

I2 Sheepfoot Roller, 300 HP 1.000 8 0.39 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.010 8 0.08 Eday

L K*A Total Equiphours 50.00 8 6.25 Eday

OD 3.00

Equipment/day 2.08
A Backfilling m3 500

B Daily Output cu.m 100

C A/B Duration, Days (8 Hrs/Day) Day 5.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Equip Operator ( Medium ) 0.500 8 0.31 Mday

E2 Laborer 1.000 8 0.63 Mday

F Sum "E" Total Man 1.500

G F*D/B Manhour 0.12 8 0.96 Mday

H G*A Total Manhours 60.00 8 7.50 Mday

OD 3

Manpower/day 2.50

I Equipment: @ Hrs

I1 Roller Compact., 1000kg 1.000 8 0.63 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.080 8 0.64 Eday

L K*A Total Equiphours 40.00 8 5.00 Eday

OD 3.00

Equipment/day 1.67
A MANHOLES & CLEANOUTS EA 10

B Daily Output EA 1

C A/B Duration, Days (8 Hrs/Day) Day 10.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 0.16 Mday

E2 Equip Operator ( Medium ) 0.500 8 0.63 Mday

E3 Laborers 4.000 8 5.00 Mday

F Sum "E" Total Man 4.625

G F*D/B Manhour 37.00 8 296.00 Mday

H G*A Total Manhours 370.00 8 46.25 Mday

OD 3

Manpower/day 15.42

I Equipment: @ Hrs

I1 Crane 23 Tons 0.500 8 0.63 Mday

I2

J Sum "I" Total Equip 0.500

K J*D/B EquipHour 4.000 8 32.00 Eday

L K*A Total Equiphours 40.00 8 5.00 Eday

OD 3.00

Equipment/day 1.67
A STORM DRAINAGE LM 200

B Daily Output LM 48

C A/B Duration, Days (8 Hrs/Day) Day 4.17

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.07 Mday

E2 Skilled Worker 1.000 8 0.52 Mday

E3 Equip Operator ( Medium ) 0.500 8 0.26 Mday

E4 Common Laborer 1.000 8 0.52 Mday

F Sum "E" Total Man 2.625

G F*D/B Manhour 0.44 8 3.50 Mday

H G*A Total Manhours 87.50 8 10.94 Mday

OD 3

Manpower/day 3.65

I Equipment: @ Hrs

I1 Crane 11 Tons 0.500 8 0.26 Mday

I2 Tools Set 1.000 8 0.52 Mday

J Sum "I" Total Equip 1.500

K J*D/B EquipHour 0.250 8 2.00 Eday

L K*A Total Equiphours 50.00 8 6.25 Eday

OD 3.00

Equipment/day 2.08
A Sewer/Drainage Piping Lm 500

B Daily Output Lm 54

C A/B Duration, Days (8 Hrs/Day) Day 9.26

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.14 Mday

E2 Plumber Apprentice 1.000 8 1.16 Mday

E3 Equip Operator ( Medium ) 1.000 8 1.16 Mday

E4 Skilled Worker 1.000 8 1.16 Mday

E5 Common Laborer 1.000 8 1.16 Mday

F Sum "E" Total Man 4.125

G F*D/B Manhour 0.61 8 4.89 Mday

H G*A Total Manhours 305.56 8 38.19 Mday

OD 3

Manpower/day 12.73

I Equipment: @ Hrs

I1 Crane 11 Tons 0.500 8 0.58 Mday

I2 Tools Set 1.000 8 1.16 Mday

J Sum "I" Total Equip 1.500

K J*D/B EquipHour 0.222 8 1.78 Eday

L K*A Total Equiphours 111.11 8 13.89 Eday

OD 3.00

Equipment/day 4.63
A PIPE LAYING LM 200

B Daily Output LM 42

C A/B Duration, Days (8 Hrs/Day) Day 4.76

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.07 Mday

E2 Skilled Worker 1.000 8 0.60 Mday

E3 Equip Operator ( Medium ) 0.500 8 0.30 Mday

E4 Laborer 1.000 8 0.60 Mday

F Sum "E" Total Man 2.625

G F*D/B Manhour 0.50 8 4.00 Mday

H G*A Total Manhours 100.00 8 12.50 Mday

OD 3

Manpower/day 4.17

I Equipment: @ Hrs

I1 Crane 11 Tons 0.500 8 0.30 Mday

I2 Tools Set 1.000 8 0.60 Mday

J Sum "I" Total Equip 1.500

K J*D/B EquipHour 0.286 8 2.29 Eday

L K*A Total Equiphours 57.14 8 7.14 Eday

OD 3.00

Equipment/day 2.38
A Bedding m3 5000

B Daily Output m3/day 200

C A/B Duration, Days (8 Hrs/Day) Day 25.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Equip Operator ( Medium ) 1.000 8 3.13 Mday

E2 Helper 2.000 8 6.25 Mday

F Sum "E" Total Man 3.000

G F*D/B Manhour 0.12 8 0.96 Mday

H G*A Total Manhours 600.00 8 75.00 Mday

OD 3

Manpower/day 25.00

I Equipment: @ Hrs

I1 Backhoe Loader 50 HP 0.056 8 0.18 Mday

J Sum "I" Total Equip 0.056

K J*D/B EquipHour 0.002 8 0.02 Eday

L K*A Total Equiphours 11.20 8 1.40 Eday

OD 3.00

Equipment/day 0.47
A Excavation m3 5000

B Daily Output m3/day 290

C A/B Duration, Days (8 Hrs/Day) Day 17.24

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Equipment Operator 1.000 8 2.16 Mday

E2 Helper 1.000 8 2.16 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.06 8 0.44 Mday

H G*A Total Manhours 275.86 8 34.48 Mday

OD 3

Manpower/day 11.49

I Equipment: @ Hrs

I1 Shovel 0.056 8 0.12 Mday

I2 Hydraulic Excavator 1.000 8 2.16 Mday

J Sum "I" Total Equip 1.056

K J*D/B EquipHour 0.029 8 0.23 Eday

L K*A Total Equiphours 145.66 8 18.21 Eday

OD 3.00

Equipment/day 6.07
A Trench Excavation m3 5000

B Daily Output m3/day 268

C A/B Duration, Days (8 Hrs/Day) Day 18.66

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Equipment Operator 1.000 8 2.33 Mday

E2 Helper 1.000 8 2.33 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.06 8 0.48 Mday

H G*A Total Manhours 298.51 8 37.31 Mday

OD 3

Manpower/day 12.44

I Equipment: @ Hrs

I1 Hydraulic Excavator 1.15m3 1.000 8 2.33 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.030 8 0.24 Eday

L K*A Total Equiphours 149.25 8 18.66 Eday

OD 3.00

Equipment/day 6.22
Item Activity Activity SUB Unit

ID Description ACTIVITY

SITEWORKS

Z2V33-0000 Site Clearing M2

Z2V33-0010 Setting-out / Layout M

SUBSTRUCTURE

Z2V33-0020 Excavation for footings + Disposal of Materials For Excavation M3

For Disposal M3

Z2V33-0030 Formation Level & Compaction M3

Z2V33-0040 Anti-Termite Applications (Under PCC Footings)

Z2V33-0050 Backfill & Compaction upto bot. of PCC Tie-Beam

Z2V33-0060 Anti-Termite Applications (Under PCC Tie-Beam)

Z2V33-0070 Backfill & Compaction up to bot of PCC Grd. Slab

Z2V33-0080 Anti-Termite Applications (Under PCC Grade Slab)

Z2V33-0090 Shutters + 50mm Thk. PCC Under Footings

Z2V33-0100 50mm Protection Screed (Over W.P. Membrane-Ftg.)

Z2V33-0110 RCC For Footings Casting M3

Formworks M2

Rebars kg
Deshuttering M2
QTY Prod. Rate Days (H) Tot. Man Crew Tot. Mdays

(unit/day) (H) (I) Desc. (K)

(F) (G) (F/G) (H x I)

1,597.00 4,200.00 0.38 2 1 Operator, 1 Helper 0.76

163.88 76 2.16 3 2 Carpenter, 1 Helper 6.47

576 409.5 1.41

288 345.6 0.83

194 252 0.77

296 180 1.64 26 1 Carpenter, 18 Helper, 6 Mason, 1 Steel Fixer 42.76

1,184.00 12 98.67 3.056 2 Carpenter, 1 Helper, .056 Operator 301.53

53,280.00 250 213.12 2.056 1 Steel Fixer, 1 Helper, .056 Operator 438.17
1,184.00 35 33.83 3.056 2 Carpenter, 1 Helper, .056 Operator 103.38
OD (O) Manpower MAN-DAYS

/day

(N/O) Carpenter Mason Steel Fixer Helper Operator Driver Technician Painter

1 0.76 0.38 0.38

1 6.47 4.31 2.16

1 42.76

4 75.38 19.73 9.87 0.55

3 146.06 21.31 21.31 1.19


2 51.69 6.77 12.92 3.38 0.19

10 26.5 12.92 21.31 34.56 1.93 0 0 0


Tot. Eqmt. (X) Eqmt Tot. Edays (Z) E

Desc. (H x X)

Alum. Tech Waterproofer Dozer Shovel Dump T.

1 1 Dozer 0.38 0.38

0.5 .5 Vibrator 0.82

0.056 .056 M. Crane 5.53

0.056 .056 M. Crane 11.93


0.056 .056 M. Crane 1.89

0 0 0 0 0
EQMT-DAYS

B. Roller B. Cat S. Roller M. Crane Vibrator Excavator Tower Crane

0.08

0.55

1.19
0.19

0 0 0 1.93 0.08 0 0