Professional Documents
Culture Documents
(i) to handover
possession of the
Apartment, in conformity
with the Buyer's
Agreement, complete in
all respects, with all
additional facilities and to
execute necessary and
required
documents of the said
Apartment in favour of the
Complainants within eight
months from the
date of filing of the
Complaint;
Huda v. Parveen Kumar 2017 SCC OnLine The facts of the case are that
Jain NCDRC 672 the opposite party (OP) HUDA
allotted plot No. 25-SP in Sector
6, Hansi, Hisar, Haryana to the
complainant/respondent vide
their memo No. 11981 dated
23.07.1992. The total cost of the
plot was stated to be Rs.
3,11,472/-. It is stated in the
consumer complaint that the
complainant had paid the entire
price of the plot in question.
However, the HUDA did not
complete the development works
in that sector within a reasonable
time and did not offer possession
of the plot in question till March
1996. The HUDA sent memo No.
3478 dated 7.03.96, offering the
possession of the plot to the
complainant, but the same was
withdrawn by them vide memo
No. 6109 dated 04.04.96 on the
ground that a high tension
electricity line was passing over
the plot in question. The HUDA
again offered the possession of
the plot in question vide their
Memo no. 1573 dated 10.11.98.
The complainant alleged that the
development works in the sector
were not complete even at that
time and the HUDA had offered
the possession in order to avoid
their liability of payment of
interest on the amount deposited
with them. The complainant also
stated that prior to the offer of
possession on 10.11.98, the
HUDA had issued another letter
dated 03.09.1998, asking for the
consent of the complainant for
allotment of plot No. 10/P or 24/P
by draw of lots. The complainant
filed the consumer complaint in
question, seeking interest @18%
p.a. on the amount deposited by
him with the OP HUDA from the
date of deposit till the date of
offer of possession of the plot in
question and also to pay a
compensation of Rs. 1 lakh on
account of mental harassment
etc. and another sum of Rs. 1
lakh as difference in cost of
construction material prevailing
in the years 1992 and 1999. It
was also stated in the consumer
complaint that if the HUDA was
not in a position to offer
possession of plot No. 25SP due
to crossing of high-tension
electricity wires, they may offer
alternative plot 10P or 24P in the
same sector and refund the
excess amount of Rs. 51,912/- to
him.
2019 SCC OnLine
V vinamra Shyamji Sharma … In July 2017, it comes to the
NCDRC 1127
Versus knowledge of the complainant that
several facts were concealed and
Three C Shelters Pvt. Ltd. and
not disclosed by the opposite
Another
parties in the project layout plan,
brochure and the agreement, like
there is a huge sewage canal
passing through the middle of the
project and that the tower-8 in
which the complainant has been
allotted the apartment is adjacent
to this sewage canal and is in
close proximity. Also there is a
high tension electric wire passing
through the project. Hence, the
present consumer complainant
with following prayers:—