ASSUMPTIONS: 

Sludge height is taken in 3 areas only and not as a whole, floating roof is currently tilted and sludge height can be either 
more or less; bottom sludge under roof is considered as per the pontoon height which can accommodate also sludge. 

Given: 

Oil Density: 920 kg/m3 

Sludge density shall be higher than that of the oil; for this calculation we will use oil density for comparison purposes. 

Tank Diameter: 22.6 meters 

Sludge Ht: 750 mm + 200 mm = 950 mm 

CALCULATION: 

 Ρ=m/v ; Formula No. 1 

Where:  

Ρ= Crude oil Density (kg/m3) 

M= mass of crude oil (kg) 

V= Volume of crude oil 

Calculate Crude Oil Volume inside tank 

Volume = π(r)2 x h ; Formula No. 2  

Volume = 3.1416 (11.3)2 x 0.95 

Volume of Crude Oil = 381.03 m3 

 
Substitute the Volume to Formula No. 1 to get the Sludge 
Weight in tons;  Roof Sludge 
(750 mm)  Floating Roof 
  Clean out 
920 = m / 381.03 

m = 920 x 381.03 ; m3 x kg/m3 ; Kg  `
m = 350,547.6 Kg or 350.4576 Tons 

  Bottom Roof 
Sludge 
(Est 200 mm) 
Qty of Tanker required: 

Tanker Capacity = 30 m3 

Tanker Qty = Crude oil Volume / Tanker Capacity 

Tanker Qty = 12.7 or 13 tankers 

Days to Empty the tanker 

1 tanker can fill in max 2 days (current condition of shoveling inside tank to hose) 

13 tanker x 2 days filling = 26 days or 1 month. 