1.1 System Mechanical Completion 1.2 Mechanical Completion 1.3 Mechanical Completion 1.4 1.5 Commissioning Procedure
Certificate
Status Index Check Record * Punch List Record 1. Issued approval commissioning procedure which
consists:
1. Generate and issue certificate when attained Generate a list form which listing the 1. Generate specific record that
mechanical completion status where status of all mechanical completion check documents the results of check and tests * Punch List Register
system/subsystem are inspected & tested for record, each discipline of punch list, performed during mechanical 1. Generate punch list record (Punch A and B) for punch raised
mechanical completion based on mechanical system boundaries drawing, as built completion for a specific tagged item during mechanical completion. Punch list record should consists a) Cover page of the procedure, interdisciplinary
completion check record. Certificate shall be system/subsystem number, punch list record number, commissioning check list, commissioning
drawing, vendor data sheet, testing 2. Generate database and update contractor name & date when corrective actions were carried completi on or certi fi cate and index sheet
issued by company to client for approval and procedure and technical queries during mechanical completion check record for out, company name & date when corrective actions were
sign off. preparation of mechanical completion tracing the status of completion inspected & accepted and client’s sign off acceptance
package
2. Clear and close punch items 2. Generate punch list register database for tracing the punch
clearance.
b) Safety precauti on, system pre-requisites,