You are on page 1of 1

1.

0 – MECHANICAL COMPLETION PACKAGE


1. System and sub system number assigned as per SFI code
2. Prepare dossier and compile related documentation consisting if any: 2.0 PRE – COMMISSIONING 3.0 COMMISSIONING
a. System mechanical completion certificate Generate and issue a ready for
commissioning certificate to signify 1. Generate and issue commissioning
b. Mechanical completion status index that system/subsystem can be
handover for pre-commissioning notification permit
c. Mechanical completion check record and as built drawing
activity to commence and certificate 2. Relevant permit to be issued
d. Punch list record shall be issued by company to client
e. Commissioning procedure (energizing permit, LOTO,etc)

1.1 System Mechanical Completion 1.2 Mechanical Completion 1.3 Mechanical Completion 1.4 1.5 Commissioning Procedure
Certificate
Status Index Check Record * Punch List Record 1. Issued approval commissioning procedure which
consists:
1. Generate and issue certificate when attained Generate a list form which listing the 1. Generate specific record that
mechanical completion status where status of all mechanical completion check documents the results of check and tests * Punch List Register
system/subsystem are inspected & tested for record, each discipline of punch list, performed during mechanical 1. Generate punch list record (Punch A and B) for punch raised
mechanical completion based on mechanical system boundaries drawing, as built completion for a specific tagged item during mechanical completion. Punch list record should consists a) Cover page of the procedure, interdisciplinary
completion check record. Certificate shall be system/subsystem number, punch list record number, commissioning check list, commissioning
drawing, vendor data sheet, testing 2. Generate database and update contractor name & date when corrective actions were carried completi on or certi fi cate and index sheet
issued by company to client for approval and procedure and technical queries during mechanical completion check record for out, company name & date when corrective actions were
sign off. preparation of mechanical completion tracing the status of completion inspected & accepted and client’s sign off acceptance
package
2. Clear and close punch items 2. Generate punch list register database for tracing the punch
clearance.
b) Safety precauti on, system pre-requisites,

Mechanical Completion Mechanical Completion Record Mechanical Completion Mechanical Completion


Mechanical Completion Record Mechanical Completion Mechanical Completion
Record (Piping) (Instrumentation and Telecom) Record (HVAC) Record (Electrical)
(Compartment Completion) Record (Architecture) Record (Mechanical)

- Venti lati on fans - Low voltage cable


- Instrument cable - Dampers
Structure - Skid installati on - Line Check - Instrument installati on
- Generator / Alternator
- Strainer - Air handling unit - Power, current, voltage
- Hydrotest check
- Tank - Ductwork installati on transformers
- Flushing - Intrinsically safe system
Outfitting - Heat Exchanger - Heati ng / Cooling coil - Low voltage switchboard
- Reinstatement - Equipment rack installati on
- Centrifugal pump - Refrigerati on - Variable speed drive
check compressor unit
- Submersible pump - Distributi on boards
- Valve and ancillaries’ - Refrigerati on circuit
- Coupling alignment - Lighti ng circuit
installati on installati on
- Diesel engine - Small power circuit
- Orifi ce Plate inspecti on - Air conditi oning
- Compressor - Electric motor (AC/DC)
- Tubing leak test and compressor unit
- Air dryer - Batt ery charger and UPS
fl ushing - ETC
- Centrifuge - Batt ery bank
- Inspecti on and calibrati on
- Freshwater maker - Trace heati ng tape/circuit
of fi eld instrument
- Winch - Electric heater
- Relief valve
- Lifeboat/Rescue - Miscellaneous Equipment
- Control panel / Juncti on
boat davit - Earth resistor and earthing
box
-Lifeboat/Rescue boat - Control or relay panel
- Fire and Gas instrument
-Sprinkler/Deluge - Control stati on / Juncti on box
installati on
- Pedestal crane - Certi fi ed equipment
- Telecom fi eld device
- Foam monitor - Cable ladder, rack and tray
installati on check
- Hyd. Power unit - ETC
- ETC
- Miscellaneous
Equipment & ETC

You might also like