SUPPLIER DELIVERABLE LIST Date: 02/02/16

object_name zatrstr_numeroproveedor title zatrstr_comentariosprop zatrstr_numerocliente zatrstr_presentarclientzatrstr_reqaprobcliente zatrstr_proveedor zatrstr_ordencompra zatrdat_ordencompra zatrstr_numerodocumento zatrdat_prevrecepzatrdat_reprogprevrecep
original zatrstr_numremitodelprov
original zatrdat_remitodelprov
zatrstr_revision
zatrstr_revisionproveedor
zatrstr_estadoemision
original zatrstr_numremitoalcliente
original zatrdat_remitoalcliente
original zatrstr_numremitodelcliente
original zatrdat_remitodelcliente
original zatrstr_estadoaprobcliente zatrdat_emision zatrstr_reviewer_code
zatrstr_listadistribucion_code
zatrstr_numremitoalaespec zatrstr_estadoaprobespec zatrdat_aprobespec zatrstr_numremitoalcliente zatrdat_remitoalcliente zatrstr_numremitodelcliente zatrdat_remitodelcliente zatrstr_estadoaprobcliente zatrstr_numremitoalprov zatrdat_remitoalprov
zatrstr_statusdocumento

Supplier Document Information Client Information Supply Information Reception from Supplier Original distribution to Client Internal Distribution and Qualification Distribution of qualified version to Client Distribution of qualified version to Supplier EME List Highlights
Original Version Original Version Qualified Version Qualified Version Qualified Version Qualified Version
Techint Number for Supplier Pucharse Order Schedule Recep. Reschedule Recep. Transmittal From Supplier Original Version Internal Qualified Version Status Responsabil Days to Days to Limit date to Sent to Received Sent to
Supplier Document Number Title ELN Document Number ENEVA Document Number Show to Client? Critical Documents Supplier Name Requisition Document Number Techint Revision Supplier Revision Issue State Transmittal To ENEVA Transmittal From ENEVA Owner Distribution List Discipline Evaluation Transmittal To ENEVA Transmittal From ENEVA Transmittal To Supplier Status Critical to ENEVA Critical from ENEVA To Supplier Supplier Limit date Doc N° Name Rev Qualification Critic
Document Date Date ENEVA Approval State Distribution Date ENEVA Approval State (TECHINT) ity qualify expire send ENEVA ENEVA from ENEVA SUPPLIER
Number Date Number Date Number Date Number Date TR Number Approval State Approval Date Number Date Number Date Number Date
fil_1 fil_2 fil_3 fil_4 fil_5 fil_6 fil_7 fil_8 fil_9 fil_10 fil_11 fil_12 fil_13 fil_14 fil_15 fil_16 fil_17 fil_18 fil_19 fil_20 fil_21 fil_22 fil_23 fil_24 fil_25 fil_26 fil_27 fil_28 fil_29 fil_30 fil_31 fil_32 fil_33 fil_34 fil_35 fil_36
6960-SIED-M-VD-004-001 E1B100560768 DCS GENERAL ELECTRICAL PREMISES - ELECTRICAL AND CONTROL DESIGN 21-1-00-DAB-IH-2400-501 NO NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 27-Feb-20 2020-04-06_Transmittal Note_136 06-Apr-20 3 3 01 - For Approval 29-May-20 M E - MM - I - II - M - G - TDC APP - Approved 29-May-20 6960-TBRA-G-TT-000-1413 29-May-20 MERIDIAN 02-Jun-20 LS - Liberado sem Comentarios 6960-TARG-M-TT-004-0015 29-May-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS GENERAL 3 APP - Approved NO N/A 29-May-20
6960-SIED-M-VD-004-002 E1B100560765 PLANT OPERATION DESCRIPTION - ELECTRICAL AND CONTROL DESIGN 21-1-00-CRP-IH-2400-501 YES YES SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 22-Mar-21 Transmittal Note_221 01-Apr-21 3 D 00 - For Information 13-Apr-21 I I - II - E - TDC - MM - M - G APP - Approved 09-Apr-21 6960-TBRA-G-TT-000-4563 13-Apr-21 MERIDIAN 29-Apr-21 LC - Liberado com Comentarios 6960-TBRA-M-TT-004-0004 13-Apr-21 Qualified 08-Apr-21 13-Apr-21 ENVIADO SIED - SIEME APPROVED 6960-SIED-M- PLANT OPERA 3 APP - Approved YES 8-Apr-21 13-Apr-21
6960-SIED-M-VD-004-004 E1B100560765 BLOCK DIAGRAMS 21-1-00-DDB-IH-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 04-Sep-20 23-Nov-20 I M - G - TDC - E - II - MM - I To Be Received . . . SIED - SIEME Delayed to RecSIED - SIEME - -426 4-Sep-20 6960-SIED-M- BLOCK DIAG NO N/A
6960-SIED-M-VD-004-005 E1B100747054 DCS HMI SCREENS - ELECTRICAL AND CONTROL DESIGN 21-1-00-DFU-IH-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 13-Oct-20 SIT Transmittal 212_GT 16-Feb-21 1 01 - For Approval 16-Feb-21 I M - MM - I - II - E - EE - TDC Received . . 02-Mar-21 SIED - SIEME Delayed To SuTECHINT - -247 2-Mar-21 6960-SIED-M- DCS HMI SCR 1 NO N/A
6960-SIED-M-VD-004-006 E1B100646918 DCS CIRCUIT DIAGRAM - ELECTRICAL AND CONTROL DESIGN 21-1-00-DIN-IH-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 13-Jan-21 Transmittal Note_221 01-Apr-21 2 D 00 - For Information 13-Apr-21 I TDC - G - M - MM - I - II - E - EE AWC - Approved with Comments 09-Apr-21 6960-TBRA-G-TT-000-4563 13-Apr-21 MERIDIAN 23-Apr-21 LC - Liberado com Comentarios 6960-TBRA-M-TT-004-0004 13-Apr-21 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS CIRCUIT AWC
2 - Approved with Comments
NO N/A 13-Apr-21
6960-SIED-M-VD-004-007 E1B100605260 DCS CONTROL CUBICLE LAYOUTS - ELECTRICAL AND CONTROL DESIGN 21-1-00-ARG-NG-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 23-Jul-20 2020-07-24_Transmittal Note_166 24-Jul-20 3 3 01 - For Approval 27-Jul-20 I E - II - I - MM - M - G - TDC APP - Approved 27-Jul-20 6960-TBRA-G-TT-000-2126 27-Jul-20 MERIDIAN 19-Aug-20 LS - Liberado sem Comentarios 6960-TARG-M-TT-004-0018 27-Jul-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS CONTROL 3 APP - Approved NO N/A 27-Jul-20
6960-SIED-M-VD-004-008 E1B100611763 DCS IO LIST - ELECTRICAL AND CONTROL DESIGN 21-1-00-RCP-IH-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 22-Mar-21 Transmittal Note_221 01-Apr-21 7 K 00 - For Information 13-Apr-21 I TDC - G - M - MM - I - E - II AWC - Approved with Comments 09-Apr-21 6960-TBRA-G-TT-000-4563 13-Apr-21 MERIDIAN 23-Apr-21 LC - Liberado com Comentarios 6960-TBRA-M-TT-004-0004 13-Apr-21 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS IO LIST AWC
7 - Approved with Comments
NO N/A 13-Apr-21
6960-SIED-M-VD-004-009 NETWORK COMMUNICATION DIAGRAMS 21-1-00-DMA-IH-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 05-Feb-20 2020-07-24_Transmittal Note_166 24-Jul-20 1 1 01 - For Approval 27-Jul-20 I E - II - I - MM - M - G - TDC WCR - Approved with Comments - Reis 27-Jul-20 6960-TBRA-G-TT-000-2126 27-Jul-20 MERIDIAN 19-Aug-20 LC - Liberado com Comentarios 6960-TARG-M-TT-004-0018 27-Jul-20 Qualified . . ENVIADO SIED - SIEME Qualified and SIED - SIEME - -451 10-Aug-20 6960-SIED-M- NETWORK COWCR -1Approved with Comments -NO
Reissue N/A 27-Jul-20
6960-SIED-M-VD-004-011 SPARE PART LIST 21-1-00-LSP-IH-2400-502 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 29-May-20 2020-07-10_Transmittal Note_163 13-Jul-20 1 1 01 - For Approval 23-Jul-20 I E - M - G - TDC - II - MM - I APP - Approved 23-Jul-20 6960-TBRA-G-TT-000-2086 23-Jul-20 MERIDIAN 27-Jul-20 LS - Liberado sem Comentarios 6960-TARG-M-TT-004-0017 23-Jul-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- SPARE PART 1 APP - Approved NO N/A 23-Jul-20
6960-SIED-M-VD-004-012 E1B100678947 DCS HAT TEST PROCEDURE PROTOCOL - ELECTRICAL AND CONTROL DESIGN 21-1-00-PRO-QG-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 27-Jul-20 Transmittal Note_219 19-Mar-21 2 01 - For Approval 26-Apr-21 I I - II - E - M - G - TDC - MM APP - Approved 24-Apr-21 6960-TBRA-G-TT-000-4623 26-Apr-21 6960-TBRA-M-TT-004-0005 26-Apr-21 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS HAT TES 2 APP - Approved NO N/A 26-Apr-21
6960-SIED-M-VD-004-013 E1B100846692 DCS SAT TEST PROCEDURE 21-1-00-PRO-QG-2400-502 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 20-Mar-20 20-Nov-20 Transmittal Note_214 03-Mar-21 0 00 - For Information 12-Aug-21 I I - II - E - B - MM - O - TDC - G - M - Q APP - Approved 12-Aug-21 6960-TBRA-G-TT-000-4971 12-Aug-21 6960-TBRA-M-TT-004-0007 12-Aug-21 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS SAT TE 0 APP - Approved NO N/A 12-Aug-21
6960-SIED-M-VD-004-014 SOFTWARE FAT PROCEDURE 21-1-00-PRO-QG-2400-503 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 17-Sep-20 2020-10-19_Transmittal Note_184 19-Oct-20 1 1 01 - For Approval 30-Oct-20 B II - E - TDC - G - M - MM - I - B APP - Approved 30-Oct-20 6960-TBRA-G-TT-000-3318 30-Oct-20 6960-TARG-M-TT-004-0023 30-Oct-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- SOFTWARE F 1 APP - Approved NO N/A 30-Oct-20
6960-SIED-M-VD-004-015 E1B100796062 SOFTWARE ACCEPTENCE TEST NO.2 21-1-00-PRO-QG-2400-504 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 06-Dec-20 Transmittal_226_GT 07-May-21 1 01 - For Approval 12-Aug-21 M G - II - I - TDC - M - MM APP - Approved 12-Aug-21 6960-TBRA-G-TT-000-4971 12-Aug-21 6960-TBRA-M-TT-004-0007 12-Aug-21 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- SOFTWARE A 1 APP - Approved NO N/A 12-Aug-21
6960-SIED-M-VD-004-018 E1B100578589 DCS COMMUNICATION PROTOCOL - ELECTRICAL AND CONTROL DESIGN 21-1-00-DMA-IH-2400-502 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 22-Mar-21 Transmittal Note_221 01-Apr-21 2 B 01 - For Approval 01-Apr-21 M G - TDC - M - I Received . . 15-Apr-21 SIED - SIEME Delayed To SuTECHINT - -203 15-Apr-21 6960-SIED-M- DCS COMMUNI 2 NO N/A
6960-SIED-M-VD-004-019 E1B100578247 DCS TYPICAL ELECTRICAL CIRCUITS - ELECTRICAL AND CONTROLINFORMACION 21-1-00-DTE-EF-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 01-Oct-19 2019-11-28_Transmittal Note_073 28-Nov-19 1 00 - For Information 07-Apr-20 M I - G - M - TDC APP - Approved 06-Apr-20 6960-TBRA-G-TT-000-974 07-Apr-20 MERIDIAN 22-Apr-20 LS - Liberado sem Comentarios 6960-TARG-M-TT-004-012 07-Apr-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS TYPICAL 1 APP - Approved NO N/A 7-Apr-20
6960-SIED-M-VD-004-020 E1B100605336 ESD PANEL LAYOUT - ELECTRICAL AND CONTROL DESIGN 21-1-00-DFU-IH-2400-502 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 10-Dec-19 2020-01-31_Transmittal Note_105 31-Jan-20 1 1 01 - For Approval 07-Apr-20 I E - II - I - MM - M - G - TDC APP - Approved 06-Apr-20 6960-TBRA-G-TT-000-974 07-Apr-20 MERIDIAN 20-Apr-20 LC - Liberado com Comentarios 6960-TARG-M-TT-004-012 07-Apr-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- ESD PANEL L 1 APP - Approved NO N/A 7-Apr-20
6960-SIED-M-VD-004-021 E1B100610350 DCS EQUIPMENT/APPARATUS LIST - ELECTRICAL AND CONTROL DESIGN 21-1-00-LIN-IG-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 07-Apr-20 2020-07-24_Transmittal Note_166 24-Jul-20 2 2 01 - For Approval 27-Jul-20 I E - II - I - MM - M - G - TDC AWC - Approved with Comments 27-Jul-20 6960-TBRA-G-TT-000-2126 27-Jul-20 MERIDIAN 19-Aug-20 LC - Liberado com Comentarios 6960-TARG-M-TT-004-0018 27-Jul-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS EQUIPME AWC
2 - Approved with Comments
NO N/A 27-Jul-20
6960-SIED-M-VD-004-022 E1B100648340 DCS EXTERNAL CABLE-CONNECTION TABLE-NETWORK MAP 21-1-00-LCA-IH-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 05-Feb-20 2020-07-24_Transmittal Note_166 24-Jul-20 1 1 01 - For Approval 13-Aug-20 I G - TDC - E - II - I - MM - M RVD - Reviewed 13-Aug-20 6960-TBRA-G-TT-000-2330 13-Aug-20 MERIDIAN 17-Mar-21 LC - Liberado com Comentarios 6960-TARG-M-TT-004-0019 13-Aug-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS EXTERN 1 RVD - Reviewed NO N/A 13-Aug-20
6960-SIED-M-VD-004-023 BOP SEQUENCE DIAGRAM 21-1-00-DFU-IH-2400-504 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 21-Feb-20 20-Nov-20 I E - II - I - MM - M - TDC - G To Be Received . . . SIED - SIEME Delayed to RecSIED - SIEME - -622 21-Feb-20 6960-SIED-M- BOP SEQUEN NO N/A
6960-SIED-M-VD-004-024 E1B100674231 DCS IP PLAN - ELECTRICAL AND CONTROL DESIGN 21-1-00-RCP-IG-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 09-Jun-20 Transmittal Note_217 15-Mar-21 1 01 - For Approval 22-Mar-21 I TDC - G - M - MM - I - II - E AWC - Approved with Comments 20-Mar-21 6960-TBRA-G-TT-000-4431 22-Mar-21 MERIDIAN 23-Apr-21 LC - Liberado com Comentarios 6960-TBRA-M-TT-004-0003 22-Mar-21 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS IP PLAN AWC
1 - Approved with Comments
NO N/A 22-Mar-21
6960-SIED-M-VD-004-025 DCS OPERATING INSTRUCTION 21-1-00-MOP-IG-2400-501 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 23-Oct-20 23-Nov-20 SharePoint 08-Jun-21 0 00 - For Information 08-Jun-21 I TDC - G - M - MM - I - II - E AWC - Approved with Comments 08-Jun-21 6960-TBRA-G-TT-000-4789 08-Jun-21 6960-TBRA-M-TT-004-0006 08-Jun-21 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS OPERATI AWC
0 - Approved with Comments
NO N/A 8-Jun-21
6960-SIED-M-VD-004-026 E1B100813512 DCS SHUTDOWN AND INTERLOCK DESCRIPTION 21-1-00-MDE-IG-2400-502 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 22-Mar-21 23-Nov-20 Transmittal Note_221 01-Apr-21 2 01 - For Approval 13-Apr-21 I II - I - MM - M - G - TDC - E AWC - Approved with Comments 09-Apr-21 6960-TBRA-G-TT-000-4563 13-Apr-21 MERIDIAN 23-Apr-21 LC - Liberado com Comentarios 6960-TBRA-M-TT-004-0004 13-Apr-21 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS SHUTDO AWC
2 - Approved with Comments
NO N/A 13-Apr-21
6960-SIED-M-VD-004-027 E1B100656496 DCS SEQUENCE DIAGRAM - ELECTRICAL AND CONTROL DESIGN 21-1-00-DFU-IH-2400-503 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 13-Apr-21 Transmittal_226_GT 07-May-21 2 00 - For Information 07-May-21 I TDC - G - M - MM - II - I Received . . 21-May-21 SIED - SIEME Delayed To SuTECHINT - -167 21-May-21 6960-SIED-M- DCS SEQUENC 2 NO N/A
6960-SIED-M-VD-004-028 E1B100648374 DCS CONNECTION TABLE EXTERNAL CABLES 21-1-00-LCA-IH-2400-502 YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 24-Jul-20 2020-07-24_Transmittal Note_166 24-Jul-20 0 0 01 - For Approval 27-Jul-20 M II - G - M - MM - I - TDC RVD - Reviewed 27-Jul-20 6960-TBRA-G-TT-000-2126 27-Jul-20 MERIDIAN 19-Aug-20 LS - Liberado sem Comentarios 6960-TARG-M-TT-004-0018 27-Jul-20 Qualified . . ENVIADO SIED - SIEME APPROVED 6960-SIED-M- DCS CONNECT 0 RVD - Reviewed NO N/A 27-Jul-20
6960-SIED-M-VD-004-029 E1B100883990 PLANT OPERATING INSTRUCTION YES NO SIED - SIEMENS DCS NA 15-Aug-19 6960-TBRA-M-MR-100-001 07-May-21 Transmittal_226_GT 07-May-21 0 01 - For Approval 07-May-21 I TDC - M - MM - II - I Received . . 21-May-21 SIED - SIEME Delayed To SuTECHINT - -167 21-May-21 6960-SIED-M- PLANT OPERA 0 NO N/A