Professional Documents
Culture Documents
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by
COTO on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and
Bridge Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body (RCB)
to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years, after which
it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 1: GENERAL ................................................................................................................................................ 1-1
1.1 GENERAL PREAMBLE ........................................................................................................................................... 1-1
PART A: SPECIFICATIONS...............................................................................................................................................................................................1-1
PART B: LABOUR ENHANCEMENT .................................................................................................................................................................................1-3
PART C: MEASUREMENT AND PAYMENT .....................................................................................................................................................................1-4
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES.......................................................................................................................................1-7
CONTENTS
PART A: SPECIFICATIONS
A1.1.1 SCOPE
A1.1.2 DEFINITIONS
• Scope
• Definitions
• General
• Design by Contractor / Performance based systems
• Materials
• Construction equipment
• Execution of the works
• Workmanship
Part A of this Section A1.1 only contains definitions that are generic and which are relevant or applicable to the other Sections and Chapters of
this Standard Specification.
The intention is that this Standard Specification should be compatible with the applicable Conditions of Contract. However, due to differences in
the terminology and terms of the different standard contract conditions, there are instances were there may be conflict between the Conditions
of Contract and the requirements given in this Standard Specification. In such instances the terminology and provisions given in the Conditions
of Contract will prevail.
A1.1.2 DEFINITIONS
Definitions of various items are given in Part A of each Section of every Chapter of this Standard Specification where they are most applicable.
Where relevant these definitions shall apply throughout this Standard Specification.
The definitions for the various contractual terms are given in the Conditions of Contract but as various contract conditions may be used the
terminology used and the definitions of the terms may differ. The terms below are therefore defined for the purposes of interpreting this
Standard Specification. In the event of any discrepancy, the terms given in the applicable Conditions of Contract shall be used. The meaning of
any other contractual terms not defined below shall be as given in the applicable Conditions of Contract.
The meaning of any other words and phrases used in this Standard Specification shall be interpreted in accordance with the applicable
definitions and/or descriptions given in the unabridged version of the Oxford English Dictionary.
Conditions of Contract - addresses the risks, liabilities and obligations of the contracting parties and the agreed procedures for the
administration of the contract. The latest edition, or the applicable edition as defined in the Contract Documentation, of one of the following three
standard conditions of contract, which have been recommended by the South African Construction Industry Development Board (CIDB) for road
and bridge Works, shall apply as specified in the Contract Documentation:
• Conditions of Contract for Construction for Building and Engineering Works designed by the Employer as published by the International
Federation of Consulting Engineers (FIDIC Red Book).
• General Conditions of Contract for Construction Works as published by the South African Institution of Civil Engineering (GCC).
• NEC Engineering and Construction Contract Documentation as published in the United Kingdom.
Contract - is a binding legal agreement between the Employer and the Contractor in terms of which the Works as defined in the Contract
Documentation shall be carried out.
CONTENTS
B1.1.1 SCOPE
B1.1.2 DEFINITIONS
B1.1.3 GENERAL
B1.1.5 MATERIALS
B1.1.1 SCOPE
The scope of any labour enhancement and the methods and specifications related to labour enhanced construction are contained in Part B of
each of the relevant Sections of this Standard Specification. The requirement for the use of labour enhanced construction methods to satisfy any
particular project goals will be set out in the Contract Documentation.
The specifications given in Part A of this Standard Specification will apply to all work carried out using labour enhanced construction methods
unless some of the specifications in Part A are replaced with revised specifications in Part B that are specifically applicable to the specified
labour enhanced construction methods.
B1.1.2 DEFINITIONS
Labour Enhancement – Labour enhancement is the process of improving the scope for the use of manual labour as an alternative to using
machines to increase employment opportunities on a project.
Labour Intensive – Labour intensive operations are those operations which, by their basic nature, require a significant amount of manual labour
and to a large extent exclude the use of machines.
Project Labour Goals – Project labour goals are the requirements specified for a project to enhance the use of labour in the normal
construction operations and/or to use additional labour intensive methods to replace or augment traditional construction methods that usually
involve lower levels of manual labour.
B1.1.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
Clauses B1.1.4 to B1.1.8 are not applicable to this Section.
CONTENTS
C1.1.1 PREAMBLE
C1.1.2 MEASUREMENT
C1.1.3 PAYMENT
C1.1.4 VARIATION FROM SPECIFIED NOMINAL RATES OF APPLICATION OR FROM NOMINAL MIX PROPORTIONS
C1.1.1 PREAMBLE
The general measurement and payment conditions which are applicable to all the Chapters of this Standard Specification as well as elsewhere
in the Contract Documentation, unless specified differently, are given below.
The measurement and payment of the various items required for the Works is described in the payment items which are given in Part C of each
separate Section contained in the different Chapters of this Standard Specification. Each Part C of each separate Section contains a list of items
that are not measured separately as well as a list of items that are measured and paid for using items specified in other Sections or Chapters.
If additional payment items are required for a particular contract they will be specified in the Contract Documentation for that contract.
The following terms relating to payment shall be applicable as specified in the Conditions of Contract and shall have the meanings given below:
• Lump sum - a fixed sum tendered by the Contractor which covers all his costs, incidentals, overheads and profit for providing materials
and supervising and carrying out the work and/or services that are specified under the relevant pay item.
• Prime cost sum - a sum to cover the actual cost of the supply of materials and/or work that will be provided by a supplier and/or
subcontractor that will be nominated by the Employer or a sum to cover the costs of items and/or services provided by an outside
provider where the cost is not known in advance.
• Provisional sum - a sum to cover the actual cost of materials and/or work that cannot be clearly defined before the Contract was
awarded. The Contractor will usually be asked to obtain several quotations for the materials and/or work required and submit them to
the Engineer who will approve one of the quotations and instruct the Contractor to appoint the selected service provider or
subcontractor. Alternatively, the Contractor may be asked to submit a price for providing the materials and carrying the work out himself
for approval by the Engineer.
If alternative meanings are given in the Conditions of Contract those meanings will apply instead of the meanings given above.
C1.1.2 MEASUREMENT
C1.1.2.1 Pricing Schedule
The quantities set out in the Pricing Schedule (sometimes referred to as the bill or schedule of quantities) are estimated quantities and are used
for the comparison of tenders and for awarding the contract. It must be clearly understood that only the actual quantities of work done, or
materials supplied, will be measured for payment and that the scheduled quantities may be increased or decreased as provided for in the
Contract Documentation.
C1.1.3 PAYMENT
C1.1.3.1 Contract rates
a) Computation of payment and applicability of contract rates
In computing the final contract amount, payment shall be based on the actual quantity of authorised work done in accordance with the
specifications, instructions and drawings. The contract rates shall apply, subject to the provisions of the Contract Documentation, irrespective of
whether the actual quantities are more or less than the scheduled quantities.
b) No rate or price entered in the Pricing Schedule
Where no rate or price has been entered against a pay item in the Pricing Schedule by a Contractor, it shall be accepted that no compensation
for such work is required, or will be paid, regardless of the final measured quantity of any work described in that pay item being required and
carried out.
c) No pay item entered in the Pricing Schedule
Where, a pay item described in this Standard Specification does not appear in the Pricing Schedule for a specific contract it means that the pay
item should not be required for that specific contract. However, if any item of work that is not included in the Pricing Schedule is required, and is
approved by the Engineer, the Contractor shall receive reasonable compensation for such work unless anything to the contrary has been
determined elsewhere. The compensation shall be determined in accordance with the provisions of the applicable Conditions of Contract with
respect to additional work.
d) Prime cost and provisional sums
Any prime cost or provisional sums shall be paid in accordance with the provisions of the applicable Conditions of Contract.
C1.1.3.8 Reduced payments and penalty/damage amounts with respect to the contract price
adjustment amount
Where provision for reduced payments, or for the deduction of penalty or damage amounts, is made in the Contract Documentation, such
reduced payments shall not be deducted from the value of work done in calculating the contract price adjustment amount.
CONTENTS
D1.1.1 SCOPE
D1.1.2 GENERAL
D1.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D1.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D1.1.5 VISUALLY ASSESSED PROPERTIES
D1.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D1.1.7 EVALUATION FOR ACCEPTANCE
D1.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D1.1.9 NOTIFICATION OF REMEDIAL WORK
D1.1.10 REMEDIAL WORKS
D1.1.1 PREAMBLE
The requirements for any performance guarantees and/or compliance certificates are specified in Part D of each Chapter where applicable.
All product quality / performance / safety certificates issued by the South African Bureau of Standards (SABS) and by Agrément South Africa (ASA)
will be accepted.
Product quality / performance / safety certificates issued by testing authorities based in foreign countries will only be accepted if specified in the
Contract Documentation or at the discretion of the Employer.
Clauses D1.1.2 to D1.1.10 are not applicable to this Section.
CONTENTS
PART A: SPECIFICATIONS
A1.2.1 SCOPE
A1.2.2 DEFINITIONS
A1.2.3 GENERAL
A1.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A1.2.5 MATERIALS
A1.2.6 CONSTRUCTION EQUIPMENT
A1.2.7 EXECUTION OF THE WORKS
A1.2.8 WORKMANSHIP
A1.2.2 DEFINITIONS
Acceptance Quality Control - encompasses those actions carried out by the Employer and/or the Engineer to inspect, sample, test and
measure each constructed part or section of the Works to determine whether the quality and workmanship is acceptable in terms of the
Specifications.
Process Quality Control - encompasses those actions carried out by the Contractor to assess and control materials and construction
processes to ensure that the quality of the final product/s meets all the specified requirements. It includes a quality plan with defined actions,
inspections, sampling, testing and measurement for each construction process to ensure that the quality control process is carried out
effectively.
Stakeholder liaison - the process whereby the Employer and the Contractor engage with interested and affected parties, in particular the local
authorities, local residents, schools etc., in order to inform them how the Works will affect the local community, to discuss how any adverse
effects of the Works on the local community and/or environment can be eliminated or alleviated and to provide any health and safety information
that is relevant to the local community regarding construction of the Works.
A1.2.3 GENERAL
The following Clauses include specifications for various general items which are not included in any of the other specific Chapters and Sections.
A1.2.3.1 Contractor's activities in respect of property outside the road reserve provided by the
Employer
The Contractor may occupy and make use of property outside the road reserve that is provided by the Employer for purposes of executing the
contract, on condition that:
• The Contractor complies strictly with the requirements of such statutory provisions, particularly with respect to the matters relating to
serving written notice to the owner before the Contractor enters the property.
• The Contractor shall provide the Engineer with a copy of the written notice and inform the Engineer of any further consultations that may
have taken place, or additional agreements reached, with the property owner.
• The Contractor adheres to all the written agreements made by the Employer with owners of the property outside the road reserve in
respect of the following matters:
− The location, extent and use of borrow pits, haul roads, construction roads and bypasses outside the road reserve,
A1.2.3.2 Contractor’s activities in respect of property which is not provided by the Employer
Should the Contractor use property which is not provided by the Employer, for haul roads, site offices and workshops, the Engineer’s offices and
laboratory, or for storing of equipment or materials required for construction or disposal, it shall be subject to the following:
• The Engineer shall agree to the use of any property selected for this purpose.
• Such property shall be physically separated from any production plant or activities and suitably fenced in.
• The area used for the aforesaid purpose shall be surveyed, and, where the land does not belong to the Contractor, he shall sign a lease
agreement with the owner of such property in respect of the full period for which such property shall be used for such purpose. The
lease agreement shall stipulate that the property owner shall not have any right whatsoever to any material stockpiled on such property
during the duration of the contractual lease agreement.
• A lease agreement shall be concluded by the Contractor with the owner or owners of such property for the full period that such property
is required. The lease agreement shall provide for possible extensions to match the duration of the contract. The lease agreements shall
also provide for the contract being terminated by Contractor’s default or liquidation and the resulting possibility for the lease agreement
to be taken over by a succeeding Contractor.
• Copies of all lease agreements shall be submitted to the Engineer for comment prior to signature by the signing parties and copies of
the final signed agreements shall lodged with the Engineer. Notwithstanding the Engineer’s comments on the conditions of a lease the
Contractor shall be solely responsible for adhesion to the terms of the lease agreements.
• Suitable permanent reference beacons shall be placed next to any material storage area, at the cost of the Contractor, to demarcate the
storage area and, if applicable, for use by the Engineer for taking cross-sections for determining quantities.
• Only material that is to be used for the Works shall be stored on such property.
• The Contractor shall comply with all the requirements of the environmental and any other legislation which is applicable to the property
being used.
On completion of his operations, the Contractor shall obtain, from the owner concerned, a written statement to the effect that:
• The Contractor has fulfilled his obligations under any written agreement that he made with the owner.
• The owner has received all the compensation he is entitled to and is also satisfied that all property that was occupied, including borrow
pits, haul roads and construction roads, has been properly restored and handed over to the owner in a satisfactory condition.
• With respect to fences, services or any other items moved, altered, damaged or affected in any way the owner is satisfied that
everything that was affected has been handed back to him by the Contractor in a satisfactory condition.
All such statements shall be signed and dated and copies shall be delivered to the Engineer. The obtaining of any such written statements will
not relieve the Contractor of the execution of any of his obligations to the satisfaction of the Employer or the owner or authority concerned.
A1.2.3.7 Legal and contractual requirements and responsibility to the public and the Employer
The Contractor shall comply with all the legislative and regulatory requirements of all the relevant statutory bodies pertaining to his site
establishment and to the execution of the Works. The Contractor shall also comply with the requirements given in the Contract Documentation
and with his legal and general obligations to the public, particularly with regard to obtaining and maintaining all the insurances and sureties
required for the duration of the Contract and the Defects Notification Period.
A1.2.3.8 Tolerances
The work specified in all the chapters of this Standard Specification shall comply with the various dimensional and other tolerances specified in
each case. No representation is made that the full specified tolerances will be available independently of each other, and the Contractor is
cautioned that the liberal or full use of any one or more tolerances may deprive him of the full or any use of tolerances relating to other aspects
of the work. The latter would apply particularly in respect of level tolerances on layer work and the related requirements regarding layer
thicknesses.
Where no tolerances are specified, the standard of workmanship shall be in accordance with normal good practice.
STRUCTURE / PIPELINE TYPE AND CONDITION MAXIMUM PEAK PARTICLE VELOCITY (PPV)
(mm/sec measured at a frequency of 50 Hz)
Fragile buildings (old and / or poorly constructed) 2,5
Old or low quality houses 5,0
Well built houses 12,5
Concrete structures 12,5
Industrial buildings 12,5
Steel pipelines 15,0
uPVC pipelines 10,0
Asbestos cement / fibre cement pipelines 5,0
NOTE: The PPV values given in the above table are subject to review during the period that this Standard Specification is still published as a
Draft Standard.
At the start of any work involving equipment that will generate ground vibrations all vulnerable structures must be monitored closely by the
Contractor. If there are any signs that any damage is being caused by the ground vibrations the work shall be stopped immediately and the
Engineer shall be informed. The level of the ground vibrations generated at the closest corner of the affected building shall then be measured
and checked against the allowable limits given in Table A1.2.3-1 above. The Engineer shall then decide if work may continue of if the Contractor
must alter his working methods to reduce the ground vibration levels.
Any damage that may occur to buildings, structures, fencing, walls, services and anything else on the property that may be affected by the
construction activities shall be repaired or rectified to the satisfaction of the owner at the Contractor’s expense unless the Engineer is satisfied
that all the necessary and specified precautions were taken by the Contractor and the damage was unavoidable.
A1.2.3.21 Water
The Contractor shall make his own arrangements for procuring, transporting, storing, distributing and applying the water needed for construction
and other purposes, except where otherwise specified.
Obtaining water from streams, rivers, dams or boreholes shall be subject to the Contractor obtaining the required permit from the relevant
authority.
Obtaining water from a municipal or other water supply authority shall be subject to the Contractor entering into a supply agreement with the
relevant supply authority.
The Contractor shall submit to the Engineer for comment two A0 paper copies of each drawing and all relevant design calculations prepared by,
or on behalf of, the Contractor and signed by a registered competent person. Electronic versions of the drawings and all relevant design
calculations should also be provided in the specified format. The standard of detailing and quality of print shall be the same as those of the
drawings supplied to the Contractor under the Contract Documentation.
Accepted designs and/or drawings shall form an integral part of the Contract Documentation. Any designs and/or drawings not accepted by the
Engineer will not be permitted on the site of the Works for construction purposes and/or used for the manufacture of any item. Notwithstanding
the acceptance and/or signing of the designs and/or drawings by the Engineer or the Employer, the Contractor shall take full responsibility for all
details, discrepancies, omissions, errors, etc. in respect of the said designs and/or drawings as well as for all consequences arising therefrom.
The Contractor shall submit only fully completed and checked designs and/or drawings in accordance with this Standard Specification and shall
not be entitled to claim for any delays resulting from the submission of incomplete or incorrect drawings. Unless already specified elsewhere in
the Contract Documentation, the Contractor shall agree with the Engineer the amount of time required by the Engineer to consider and
comment on the designs and/or drawings. The same time frame requirements will apply to any resubmissions of the designs and/or drawings
that may be required.
A1.2.4.2 Designs and drawings for temporary works provided by the Contractor
The Contractor shall be responsible for the design and execution of all temporary work and structures that are required for the construction and
completion of the Works. This includes all deviations, temporary drainage and flood diversion or control measures, drilling and blasting,
excavations, scaffolding, shuttering, shoring, support structures and all other work that is necessary for the construction of the permanent
Works.
The design of all such temporary work must be carried out by experienced persons who are suitably and, where required by legislation,
professionally qualified to carry out such designs. The Contractor shall ensure that the design of all temporary works has been carried out in
accordance with all relevant legislation and that the construction / erection of the temporary works is carried out by and supervised by
competent, experienced persons.
All design calculations and drawings required for the temporary works shall be submitted to the Engineer for comment when the Contractor is
requested to do so. Unless already specified elsewhere in the Contract Documentation, the Contractor shall agree with the Engineer the amount
of time required by the Engineer to consider and comment on the designs and/or drawings. The same time frame requirements will apply to any
resubmissions of the designs and/or drawings that may be required.
A1.2.5 MATERIALS
A1.2.5.1 General
The Contractor shall confirm the quantities of all manufactured items or materials required for the completion of the Works with the Engineer
before finalizing any orders or production processes.
The Contractor, before using manufactured articles or materials that are required to comply with any specification, shall furnish the Engineer
with certificates showing that the materials do comply with that specification. Where so specified, materials shall bear the official mark of the
appropriate authority. All materials and products which should comply with a South African National Standard Specification (SANS) shall carry
the certification mark of a SANAS accredited certification body.
Samples ordered or specified for inspection, comment and/or approval by the Engineer prior to the manufactured articles or materials being
ordered, procured or used in the Works shall be delivered to the Engineer's site office at least seven calendar days, or such longer period that
may be specified in the Contract Documentation, before such comment or approval is required.
Unless otherwise specified, all proprietary materials shall be used and placed in strict accordance with the relevant manufacturer's current
published instructions. Agrément certified products shall be used and placed in accordance with their Agrément certification criteria.
All manufactured articles or materials supplied by the Contractor for the permanent Works shall be new and unused unless stated otherwise in
the Contract Documentation. Manufactured articles and materials to be included in the Works shall not be damaged in any way and, should they
be damaged during manufacture, delivery or by the Contractor during handling, transportation, storage, installation or testing they shall be
replaced, or repaired to comply with the original specification, by the Contractor at his own cost.
All places where articles and materials are being manufactured or obtained for use in the Works, and all the processes in their entirety
connected therewith, shall be open to inspection by the Engineer (or other persons authorised by the Engineer) at all reasonable times.
A1.2.7.3 Services
The specifications relating to the location, identification, protection of and/or moving and reinstating of existing services that may be affected by
the construction of the Works are given in Clause A2.1.3.2 b), c) & d) of Chapter 2.
A1.2.8 WORKMANSHIP
The quality of the workmanship, products, elements and goods provided by the Contractor shall be controlled by a process control system
executed by the Contractor as well as by a system of acceptance control executed by the Employer, the Engineer or any other appointed agent
as specified below. This quality assurance process, including the liability for the payment of the testing required, is specified in Chapter 20 of
this Standard Specification.
CONTENTS
B1.2.1 SCOPE
B1.2.2 DEFINITIONS
B1.2.3 GENERAL
B1.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B1.2.5 MATERIALS
B1.2.6 CONSTRUCTION EQUIPMENT
B1.2.7 EXECUTION OF THE WORKS
B1.2.8 WORKMANSHIP
B1.2.1 SCOPE
Any requirements for the labour enhancement of some of the work activities will be stated in the Contract Documentation.
The Contractor shall indicate how these specified requirements will be met in his Works programme.
B1.2.2 DEFINITIONS
Definitions as provided in Clause A1.2.2 shall also apply.
B1.2.3 GENERAL
Any activity specified in PART A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B1.2.5 MATERIALS
The provisions of Part A shall apply.
B1.2.8 WORKMANSHIP
The provisions of Part A shall apply.
Provision and later removal of the contract sign boards. A1.2.3.12 C1.3.2 of Chapter 1
Provision of all site security measures for the Contractor’s
facilities and equipment and at the Site of the Works,
A1.2.3.17 C1.3.1 of Chapter 1
quarries, borrow pits and traffic accommodation facilities and
equipment.
Provision of security at the engineer’s offices, laboratories, A1.2.3.17 C1.4.8 of Chapter 1
and site and rented accommodation.
Identification, protection and relocation of existing services A1.2.7.3 C2.1.1 & C2.1.2 of Chapter 2
Acceptance quality control – sampling and testing requested
A1.2.8.2 C20.1.2.2 of Chapter 20
by the Engineer
C1.2.1.2 Dedicated environmental officer (if specified in the Contract Documentation) month
The unit of measurement for item C1.2.1.1 is the month or part thereof that the service is required and provided during the approved
contract period. The contract rate shall include full compensation for the regular monitoring of compliance with and reporting on the
EMP in accordance with the specified requirements.
C1.2.2.6 Preparation and submission of all information and reports specified in the Contract month
Documentation
The unit of measurement for item C1.2.2.1 shall be the lump sum. The lump sum shall include full compensation for preparing and
submitting a Scheme 1 Programme, including providing software and tutorials to the Engineer if required.
The unit of measurement for item C1.2.2.2 shall be the month or part thereof that the service is provided during the approved contract
period. The monthly rate shall include full compensation for reviewing and updating the Scheme 1 Programme as required and for
submitting a copy of the current programme to the Engineer at the end of each month.
The unit of measurement for item C1.2.2.3 shall be the lump sum. The lump sum shall include full compensation for preparing and
submitting a Scheme 2 Initial Programme, including providing software and tutorials to the Engineer if required
The unit of measurement for item C1.2.2.4 shall be the lump sum. The lump sum shall include full compensation for preparing and
submitting a Scheme 2 Full Programme.
The unit of measurement for item C1.2.2.5 shall be the month or part thereof that the service is provided during the approved contract
period. The monthly rate shall include full compensation for reviewing and updating the Scheme 2 Initial and Full Programmes as
specified in the Contract Documentation and for submitting of a copy of the current programme to the Engineer at the end of each
month.
The unit of measurement for item C1.2.2.6 shall be the month or part thereof that the service is provided during the approved contract
period. The monthly rate shall include full compensation for collecting and reporting on all data and information specified in the
Contract Documentation and for submitting it to the Engineer at the specified times.
C1.2.3.5 Base patching using crushed stone material stabilised with bitumen emulsion and cement cubic metre (m3)
C1.2.3.6 Base and/or surface patching using cold premixed asphalt kilogram (kg)
C1.2.3.7 Base and/or surface patching using hot plant mixed asphalt ton (t)
C1.2.3.9 Grading of temporary gravel deviations and existing roads used as detours kilometre (km)
C1.2.3.10 Watering of temporary gravel deviations and existing roads used as detours kilolitre (kl)
C1.2.3.11 Other road maintenance work ordered by the Engineer provisional sum
C1.2.3.12 Handling cost, profit and all other charges in respect of item C1.2.3.11 percentage (%)
Payment will only be made under items C1.2.3.1 to C1.2.3.13 when the relevant item of routine maintenance work has been ordered
by the Engineer in writing and the Engineer has confirmed in writing the scope, quantity and/or frequency of work that is to be carried
out.
The unit of measurement for item C1.2.3.1 shall be the hectare. The contract rate shall include full compensation for cutting and
removing grass in restricted and steep access areas with hand tools in addition to mowing and removing grass in more accessible
areas.
The unit of measurement for item C1.2.4 shall be the month or part thereof that the service is provided during the approved contract
period. Part of a month shall be calculated to two decimal places. The contract rate shall include full compensation for all on-going
stakeholder liaison that the Contractor is required to carry out after the contract has been awarded as specified in Section A1.2,
Clause A1.2.3.18, including informing stakeholders of the Works procedures and of the accommodation arrangements for
pedestrians and non-motorised traffic through or over the site of the Works, providing health and safety information to stakeholders,
arranging and attending meetings, providing meeting facilities and sandwiches, tea, coffee or soft drinks. Payment of the monthly
sum shall be made every month for the duration of the approved contract period regardless of the amount of stakeholder liaison
required during that month.
The unit of measurement for item C1.2.5.1 shall be the lump sum. The lump sum shall include full compensation for assessing the
risks associated with the Works, reviewing and taking cognisance of the Employer’s health and safety specifications and/or
requirements, preparing the Contractor’s health and safety plan and for the submission of a copy of the plan to the Engineer.
The unit of measurement for item C1.2.5.2 shall be the month, or part thereof for the duration of the approved contract period. Part of
a month shall be calculated to two decimal places. The contract rate shall include full compensation for implementing the health and
safety plan, including the provision of a dedicated, full time health and safety officer, carrying out all the required site health and
safety training and briefings, staff medical evaluations, monitoring and administrating the health and safety plan and for supplying all
transport, personal protection safety items, other health and safety equipment, safety notices and any other health and safety related
items that are required on site. The contact rate shall also include the provision of a monthly health and safety compliance report to
the Engineer.
C1.2.6.3 Handling cost, profit and all other charges in respect of item C1.2.6.2 percentage (%)
The unit of measurement for item C1.2.6.1 shall be the number of properties adjacent to the Works that need to be surveyed, as
agreed in advance with the Engineer. The contract rate shall include full compensation for carrying out all the requirements given in
clause A1.2.3.13.
The provisional sum allowed under item C1.2.6.2 shall provide for all additional preventive and/or mitigation measures required that
are approved by the Engineer as being necessary after the Contractor has implemented all other reasonable measures to avoid
and/or reduce the damaging effects relating to carrying out the Works adjacent to properties. The amount payable to the Contractor
shall be calculated in accordance with the requirements given in the Contract Documentation or agreed to by the Engineer.
The percentage under item C1.2.6.3 is a percentage of the amount spent under item C1.2.6.2 which shall include full compensation
for all handling costs, profit and all other charges in connection with arranging and carrying out the agreed preventive and/or
mitigation measures.
C1.2.7.2 Handling cost, profit and all other charges in respect of item C1.2.6.1 percentage (%)
C1.2.7.4 Handling cost, profit and all other charges in respect of item C1.2.6.3 percentage (%)
The provisional sum allowed under item C1.2.7.1 shall be used to pay the actual cost of appointing an independent auditor and
carrying out a Stage 4 work zone traffic management audit as prescribed in the SARSAM and in Clause A1.2.3.20 a) and for
preparing the audit report and submitting two copies of the report to the Employer and the Engineer.
The percentage under item C1.2.7.2 is a percentage of the amount spent under item C1.2.7.1 which shall include full compensation
for all handling costs, profit and all other charges in connection with arranging and carrying out the specified audit.
The provisional sum allowed under item C1.2.7.3 shall be used to pay the actual cost of appointing an independent auditor and
carrying out a Stage 5 pre-opening stage traffic safety audit as prescribed in the SARSAM and in Clause A1.2.3.20 b) and for
preparing the audit report and submitting two copies of the report to the Employer and the Engineer.
The percentage under item C1.2.7.4 is a percentage of the amount spent under item C1.2.7.2 which shall include full compensation
for all handling costs, profit and all other charges in connection with arranging and carrying out the specified audit.
C1.2.8.1 Personnel
C1.2.8.4 Materials
(b) Contractor's handling costs, profit and all other charges in respect of item C1.2.8.4(a) percentage (%)
The unit of measurement for items C1.2.8.1(a) to C1.2.8.1(f) shall be the hour that the personnel are engaged on the work inclusive
of transport to and from the site. Non-working hours for meal breaks, rest periods, transport breakdowns, lack of construction
equipment or materials or any other reason shall not be measured. The contract rates shall include full compensation for all overhead
charges and profit, leave pay, bonuses, subsistence, allowances, Employer's contributions, additional payment for overtime where
applicable, insurances, housing, site supervision, provision and use of small hand tools and appliances, non-mechanical plant and
equipment and consumable stores as well as for all administrative, supervisory, operative and contingent costs related to the supply
of personnel.
The unit of measurement for items C1.2.8.2(a) to C1.2.8.2(g) shall be the hour that the construction equipment is engaged on the
work inclusive of transport to and from the site. Non-working hours for operator meal breaks and rest periods, equipment breakdowns
and maintenance, lack of materials or any other idle time or reason shall not be measured. The contract rates shall be an all-inclusive
hire charge for the use of the construction equipment and operator and shall include full compensation for all administrative,
supervisory, fuel, maintenance, operational, transportation, depreciation and any other contingent costs and profit relating to the
operation of the construction equipment. The contract rates shall be based on the type and size of equipment that the Contractor
intends to provide for the construction of the main Works.
The unit of measurement for items C1.2.8.3(a) to C1.2.8.3(d) shall be the kilometre travelled by the vehicle while engaged on the
dayworks. The contract rates for shall be an all-inclusive hire charge for the use of the vehicle, the driver and the driver’s assistant/s if
required. The contract rates shall also include full compensation for all administrative, supervisory, fuel, maintenance, operational,
transportation, depreciation and any other contingent costs and profit relating to the operation of the vehicle.
The provisional sum allowed under item C1.2.8.4(a) shall include full compensation for the cost of all materials (excluding value
added tax) that are required for the dayworks as ordered by the Engineer. The provisional sum shall be paid in accordance with the
provisions of the Contract Documentation.
The percentage under item C1.2.8.4(b) is a percentage of the amount spent under item C1.2.8.4(a) which shall include full
compensation for all handling costs, profit and all other charges for ordering, providing, transporting and handling the materials.
C1.2.9.1 Disposal of non-useable assets identified in the Contract Documentation at time of tender rate (per asset)
(list items and quantity)
C1.2.9.2 Disposal of non-useable assets not identified at time of tender provisional sum
C1.2.9.3 Handling cost, profit and all other charges in respect of item C1.2.9.2 percentage (%)
The unit of measurement for item C1.2.9.1 shall be the lump sum tendered by the Contractor to dispose of the listed non-useable assets that
are described in the Contract Documentation and listed under this item. The rate tendered by the Contractor can be positive or negative
depending on the cost of disposing of the assets against the value that the Contractor may wish to place upon them.
The provisional sum allowed under item C1.2.9.2 shall provide for the disposal of any non-useable assets that were not already identified in the
Contract Documentation under item C1.2.9.1. The amount payable to the Contractor shall be calculated in accordance with the requirements
given in the Contract Documentation or agreed to by the Engineer. The provisional sum may be positive or negative depending on the cost of
disposing of them against the value that the Contractor may wish to place upon them.
The percentage tendered under item C1.2.9.3 is a percentage of the amount spent under item C1.2.9.2 which shall include full compensation for
all handling costs, profit and all other charges in connection with arranging and disposing of the non-useable or not required road furniture
assets. If the provisional sum agreed under item C1.2.9.2 is a negative amount, then this item C1.2.9.3 will not be applicable.
CONTENTS
D1.2.1 SCOPE
D1.2.2 GENERAL
D1.2.3 PERFORMANCE GUARANTEE REQUIREMENTS
D1.2.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D1.2.5 VISUALLY ASSESSED PROPERTIES
D1.2.6 INSTRUMENTALLY ASSESSED PROPERTIES
D1.2.7 EVALUATION FOR ACCEPTANCE
D1.2.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D1.2.9 NOTIFICATION OF REMEDIAL WORK
D1.2.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A1.3.1 SCOPE
A1.3.2 DEFINITIONS
A1.3.3 GENERAL
A1.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A1.3.5 MATERIALS
A1.3.6 CONSTRUCTION EQUIPMENT
A1.3.7 EXECUTION OF THE WORKS
A1.3.8 WORKMANSHIP
A1.3.2 DEFINITIONS
Construction camps - are all areas used for erecting offices, stores, workshops, testing facilities, plant parking areas, and equipment and
material storage areas.
General Obligations - the Contractor's General Obligations shall include the following:
• Setting up, providing, insuring and maintaining the personnel, construction camps, staff accommodation, furniture, office equipment and
stationery, other temporary structures, fencing and construction equipment on the site and their removal on completion of the contract.
• Providing transport to, from and on the Site of the Works for all permanent and temporary staff and local labour, including transporting
local employees to and from their places of residence when or where necessary.
• Compliance with the requirements of the Conditions of Contract and with all the general requirements included in this Chapter 1.
• Compliance with all legislative and regulatory requirements.
• Assessing, dealing with and/or insuring all risks associated with the Contractor’s General Obligations and with the construction,
maintenance and protection of the Works.
• The protection and/or safeguarding of private property and livestock.
• The provision of security for all the Contractor’s personnel, facilities and equipment on the Site of the Works, including quarries, borrow
pits, stockpile areas and storage yards as well as for any traffic accommodation facilities and equipment that may be placed on the
approaches to, or the exit from, the Site of the Works.
• All other general obligations, overhead costs, financing charges, insurance costs and all other general items which are not specifically
included in, or covered by, this Standard Specification.
• The preparation and submission of all designs and drawings prepared by the Contractor for the temporary works or any alternative
design proposals.
A1.3.3.2 Housing
The Contractor shall not erect any housing or other accommodation facilities on the site in urban areas and shall make all the necessary
arrangements for accommodation of his personnel and site staff off the site, unless otherwise stated in the Contract Documentation.
The Contractor shall not erect any housing or other accommodation facilities on the site before he has obtained the written permission of the
Employer and, where applicable, the land owner and has complied fully with all applicable legislative and regulatory requirements.
A1.3.5 MATERIALS
The Contractor shall be responsible for the selection and purchase of all materials required to construct the site facilities. All applicable
legislative and regulatory requirements with regard to building standards and health and safety shall be complied with.
A1.3.8 WORKMANSHIP
The Contractor shall control the quality of materials and workmanship used for the construction and fitting out of the construction camps to
ensure that the applicable legislative and regulatory requirements related to building standards and to health and safety are adhered to.
CONTENTS
B1.3.1 SCOPE
B1.3.2 DEFINITIONS
B1.3.3 GENERAL
B1.3.5 MATERIALS
B1.3.1 SCOPE
There are no additional labour enhancement requirements for Section A1.3.
B1.3.2 DEFINITIONS
Definitions as provided in Clause A1.3.2 shall also apply.
Clauses B1.3.3 to B1.3.8 are not applicable to this Section.
The lump sums under items C1.3.1.1 and C1.3.1.2 and the contract rate per month for item C1.3.1.3 shall together include full compensation for
all the Contractor's costs, charges, overheads and profits in respect of all the Contractor's General Obligations as specified in Clause A1.3.2.
Item C1.3.1.1
The unit of measurement for item C1.3.1.1 is the lump sum. The lump sum shall include full compensation for the fixed part of the Contractor's
general obligations, i.e. that part which is substantially fixed and is not a function of the value of the Works or of the time required for the
completion of the Contract.
• The second instalment, 35 % of the lump sum, will be paid when the value of the Work done reaches one half of the Contract Amount,
excluding contingencies and price adjustments in terms of the Contract Documentation.
• The third and final instalment, 15 % of the lump sum, will be paid when the Works have been completed and taken over by the
Employer.
Item C1.3.1.2
The unit of measurement for item C1.3.1.2 is the lump sum. The lump sum shall include full compensation for that part of the Contractor's
general obligations which is a function of only the value of the Works, but not of the period of completion of the Works.
Should the final value of the Works (excluding any contract price and special material adjustment payments made in terms of the Contract
Documentation) increase or decrease in relation to the tendered contract price (less any allowances, if any, in the tendered contract price for
contract price adjustment and special material adjustment payments), the lump sum for payment item C1.3.1.2 will be increased or decreased
accordingly pro rata. The adjusted lump sum will be the full settlement of any difference in value-related general obligations resulting from an
increased or decreased value of the work.
Payment of this lump sum will be made in instalments in each payment certificate (usually issued monthly). The value of each instalment will be
in proportion to the value of Work done up to the date that the payment certificate is prepared (excluding the value of any price adjustments
made in terms of the Contract Documentation).
Item C1.3.1.3
The unit of measurement for item C1.3.1.3 is the month or part thereof that the services are provided for the approved duration of the contract.
Part of a month shall be calculated to two decimal places.
The contract rate shall include full compensation for that part of the Contractor's general obligations which are mainly a function of construction
time. The contract rate will be paid monthly, pro rata for parts of a month, from the date of commencement in terms of the Contract
Documentation until the end of the original Contract Period specified for completion of the Works.
If the original Contract Period for completion has been extended in terms of the Contract Documentation, then time-related obligations for the
extensions shall be compensated for as stipulated by the Contract Documentation.
• Should the progress of the Contractor, calculated in terms of the value of the work done to date, be in arrears by more than 10 %
relative to the accepted cash flow estimate (suitably adjusted for any change in the scope of work and/or extension of time granted) then
the payments in respect of this item may be limited to a total payment to date which is in the same ratio as the actual value of Work
done relative to the estimated total value of all the Work that has to be done.
The unit of measurement for item C1.3.2 is the total square metre (m2) area of the approved contract sign boards (usually two) provided and
erected by the Contractor in the positions on site indicated by the Engineer. The contract rate for item C1.3.2 shall include full compensation for
all costs associated with providing, erecting and for the later removal of the contract signboards as soon as the Works have been completed.
CONTENTS
D1.3.1 SCOPE
D1.3.2 GENERAL
D1.3.3 PERFORMANCE GUARANTEE REQUIREMENTS
D1.3.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D1.3.5 VISUALLY ASSESSED PROPERTIES
D1.3.6 INSTRUMENTALLY ASSESSED PROPERTIES
D1.3.7 EVALUATION FOR ACCEPTANCE
D1.3.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D1.3.9 NOTIFICATION OF REMEDIAL WORK
D1.3.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A1.4.1 SCOPE
A1.4.2 DEFINITIONS
A1.4.3 GENERAL
A1.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A1.4.5 MATERIALS
A1.4.6 CONSTRUCTION EQUIPMENT
A1.4.7 EXECUTION OF THE WORKS
A1.4.8 WORKMANSHIP
A1.4.2 DEFINITIONS
Engineer’s site facilities - the Engineer’s site accommodation, laboratories and offices are temporary buildings provided on site, or existing
buildings on or near the site. Together with the required water, sewage, telecommunication, internet and electricity services these shall be
known as the Engineer’s site facilities. (The Engineer’s site facilities shall be provided by the Contractor for the duration of the Contract to house
the Engineer’s site personnel, accommodate all the materials testing equipment required to carry out the Engineer’s acceptance control testing
and to provide office space for the Engineer’s site personnel.)
A1.4.3 GENERAL
Where not already provided in the Contract Documentation, the Engineer shall furnish the Contractor with full details, in writing, regarding the
number, type, layouts and furnishing of all site accommodation, laboratories and offices required for the use of the Engineer’s site personnel.
The Contractor shall not order or make any arrangements for the provision of any buildings, materials, equipment or fittings on the basis of what
is specified or scheduled without written confirmation by the Engineer. No buildings shall be rented, purchased, erected, refurbished or altered
without the Engineer's written approval of the exact position, layout and orientation of the buildings.
Buildings for staff accommodation, laboratories and offices may comprise one or more of the following:
• Rented existing permanent structures in residential, business, industrial or farming areas.
• Temporary structures erected on property rented by the Contractor or on property provided by the Employer.
• Mobile structures parked on property rented by the Contractor or on property provided by the Employer.
• Permanent structures provided by the Employer.
Existing permanent structures may require refurbishment and partitioning to suit the requirements of the Engineer.
All buildings provided for the Engineer’s staff accommodation, laboratories and offices shall where possible be located in an area where landline
and/or cellular telecommunication and internet connectivity is available. If any of these services are not available dedicated services to that
effect shall be provided.
Unless otherwise specified in the Contract Documentation, or agreed to by the Employer, the buildings provided for the use of the Engineer’s
personnel shall be erected near the Contractor's construction camp. Should the Contractor decide to move the construction camp to a new site
during the construction of the Works, the buildings erected for the use of the Engineer shall be moved to the new site and re-erected if required
DRAFT STANDARD (DS) OCTOBER 2020 1-36
by the Engineer, or alternative buildings which meet the specified and the Engineer’s requirements shall be provided by the Contractor. No
additional costs related to moving the Engineer’s site facilities, or providing new site facilities, shall be incurred by the Employer or by the
Engineer and all such costs shall be borne by the Contractor.
The Contractor may not proceed with the permanent Works before the specified site accommodation, laboratory and office buildings required by
the Engineer have been provided, serviced and furnished by the Contractor. All the site accommodation, laboratory and office buildings shall be
provided as soon as possible after the Contractor has been given possession of the site of the Works and not later than six weeks after the
Contract commencement date.
If any additional site facilities are required by the Engineer during the construction of the Works, the Engineer shall inform the Contractor of the
additional requirements at least 30 calendar days before such additional facilities are required.
The Contractor shall be responsible for servicing the Engineer’s site facilities and for maintaining the facilities in a serviceable condition for the
duration of the contract.
The ownership of all offices, laboratories, housing, sanitary facilities, laboratory equipment, furniture, office equipment and other items provided
by the Contractor shall revert to the Contractor when the Engineer confirms in writing that he no longer requires them. The Contractor shall then
remove them from the site or terminate the rental lease for any rented buildings.
As specified in Clause A1.2.3.17 the Contractor shall provide adequate security measures to prevent unauthorised entry to the Engineer’s
offices, laboratories, site accommodation and any rented accommodation.
The Contractor shall ensure that all the site facilities and services provided comply with the applicable statutory and regulatory provisions,
building standards and health and safety requirements.
A1.4.5 MATERIALS
The Contractor shall be responsible for the selection and purchase of all materials required to provide the Engineer’s site facilities. The
Contractor shall ensure that the specified standards are met and that all applicable legislative and regulatory requirements, building standards
and health and safety requirements are complied with.
A1.4.7.2 Housing
a) Prefabricated houses
If prefabricated houses are scheduled to be provided by the Contractor the minimum requirements for the different types of houses that may be
required are as specified below, unless specified otherwise in the Contract Documentation.
The general requirements for all prefabricated house types shall be as follows:
• All rooms shall have concrete floors covered with vinyl or ceramic tiles in the bathroom and in the kitchen and with durable, wall to wall
carpets or carpet tiles in all the other rooms.
• The window area in each room shall be equivalent to at least 25 % of the floor area and at least 40 % of the total window area shall be
openable. All windows shall be provided with approved burglar proofing and adjustable venetian blinds or similar approved.
• All houses shall have a 220 volt single phase electricity supply and every room, except the bathroom, shall be provided with two 15
ampere electric plug sockets.
• Lights shall be 11 W compact fluorescent bulbs or 7W LED bulbs.
• The clear height of all rooms between floor and ceiling shall be at least 2,4 m. Every room shall have a ceiling with approved insulation
material installed above the ceiling.
• Each door shall be provided with a lock and two keys and all exterior doors shall be fitted with security doors of adequate strength with a
5-lever lock and/or a secure padlock.
• Portable firefighting equipment shall be provided for all site accommodation/housing in accordance with the requirements of the latest
statutory regulations and specifically with the requirements specified in SANS 10400-T:2011 Part T: Fire Protection. Fire extinguishers
shall be the all-purpose dry powder type manufactured in accordance with the requirements given in SANS 1910:2009 and shall be
suitable for types A, B and C fires. The extinguishers shall contain not less than 9,0 kg of extinguishing chemical and shall be installed,
maintained and serviced by competent persons in accordance with the requirements specified in SANS 1475-1 and SANS 10105-1.
• Each kitchen shall be equipped with:
− A single-bowl stainless steel basin with draining board, mounted on a cupboard unit with a clean potable hot and cold water supply,
taps, a plug and a waste drain,
− a kitchen cupboard 1,0 m³ in volume with a melamine or similar counter top,
− a fridge/freezer with a capacity of at least 0,5 m3 / 0,2 m3 for the fridge and freezer compartments respectively,
− a stove with an oven and four hot plates,
− a microwave cooker, a kettle and a toaster,
− a cutlery set consisting of six knives, forks, dessert spoons and teaspoons, two kitchen knives, two serving spoons, cheese grater,
cutting board, can opener and bottle opener,
− three cooking pots with lids and a frying pan and
− a crockery set consisting of six dinner plates, six side plates, six dessert bowls and six coffee mugs.
• Each bathroom shall be equipped with:
− A water borne sewage system with a septic tank if required,
− one vitreous enamel WC pan with a PVC seat and cover, a flush cistern and a toilet roll holder,
− one vitreous enamel bath with a clean potable hot and cold water supply, taps, a plug and a drain,
− one vitreous enamel wash basin with a clean potable hot and cold water supply, taps, a plug and a drain,
− a shower with a clean potable hot and cold water supply and a drain,
− a mirror and a towel rail and
− one covered wastepaper bin.
• Each bedroom shall be furnished with:
− Two three quarter sized beds - each bed supplied with a good quality sprung mattress, two fitted sheets, a duvet with two duvet
covers and two pillows with four pillowcases,
− a cupboard with a capacity of 1,5 m3, divided equally into a shelved section and a hanging section, and
− a chest of drawers with at least three drawers,
− Each lounge shall be furnished with a comfortable lounge suite consisting of a sofa and two lounge chairs and a coffee table.
− Each dining room shall be furnished with a dining room table and six dining chairs.
The houses shall be painted with an approved paint after erection. The paintwork shall be maintained in good condition for the duration of the
Contract.
The various house types that may be specified in the Contract Documentation shall have the number of rooms with their respective minimum
floor areas as shown in Table A1.4.7-1 overleaf. If other house types and/or size and/or furnishing requirements are required they will be
b) Rented accommodation
The Engineer shall usually be responsible for providing suitable accommodation for his site staff in a hotel, guesthouse, rented house or a
rented apartment in the nearest town or on a nearby farm.
The Engineer may instruct the Contractor to pay for any hotel or other accommodation or leased houses required. If so instructed by the
Engineer the Contractor shall enter into the necessary contracts for the lease of such accommodation as may be required and shall not
unreasonably object to the terms and conditions of such leases to be negotiated by the Engineer.
Where appropriate, and in the case where the rented accommodation is not deemed to be the primary residence of the site staff member, the
lease agreement shall include full compensation for a periodic garden service.
A1.4.7.3 Services
a) Sanitary arrangements
The Contractor shall be responsible for providing all sanitary services necessary for keeping latrines in a clean, neat and hygienic condition.
When no municipal sewage treatment is available, the Contractor shall provide the necessary septic tanks for all latrines. Waste water and
septic-tank effluent shall be taken into properly designed French drains. The Contractor shall also make provision for the removal of all rubbish.
Where the construction of septic tanks or a water-borne sewerage scheme is unfeasible, the Contractor shall provide conservancy tanks and
make arrangements for the removal and disposal of sewage.
A1.4.8 WORKMANSHIP
The applicable legislative and regulatory requirements regarding building standards and health and safety shall be complied with.
CONTENTS
B1.4.1 SCOPE
B1.4.2 DEFINITIONS
B1.4.3 GENERAL
B1.4.5 MATERIALS
B1.4.1 SCOPE
There are no additional labour enhancement requirements for Section A1.4.
B1.4.2 DEFINITIONS
Definitions as provided in Clause A1.4.2 shall also apply.
Clauses B1.4.3 to B1.4.8 are not applicable to this Section.
C1.4.1.3 Open concrete working floors and verandas square metre (m2)
C1.4.1.4 Roofs over open concrete working floors and verandas square metre (m2)
C1.4.1.14 Contractor's handling costs, profit and all other charges in respect of item C1.4.1.13 percentage (%)
2
The unit of measurement for items C1.4.1.1 to C1.4.1.5 shall be the square metre (m ) of each facility, measured according to the internal floor area.
The contract rates shall include full compensation for the construction or provision of these Engineer’s facilities all complete in accordance with the
specifications given in the Contract Documentation. Where offices are provided in existing buildings the passageways, hallways and any other office
space in excess of the Engineer’s requirements shall not be measured for payment.
The unit of measurement for items C1.4.1.6 to C1.4.1.12 shall be the number of units provided. The contract rates shall include full compensation for
the construction or provision of these Engineer’s facilities all complete in accordance with the specifications given in the Contract Documentation.
The contract rates for items C1.4.1.1, C1.4.1.2, C1.4.1.3, C1.4.1.6, C1.4.1.7, C1.4.1.8,C1.4.1.9, C1.4.1.10, C1.4.1.11 and C1.4.1.12 shall also
include full compensation for clearing and grubbing the areas under and around the buildings, the excavation and backfilling of any foundations
required, the loading and hauling of the excavated material to spoil if required, regardless of haul distance, and the provision and maintenance of a
trafficable surface to provide all weather mud and dust free access for vehicles and pedestrians to and around the buildings.
The percentage under item C1.4.1.14 is a percentage of the amount spent under item C14.1.13 which shall include full compensation for all handling
costs, profit and all other charges in connection with arranging and paying for the rented accommodation.
C1.4.2.2 Work benches with a concrete slab top square metre (m2)
C1.4.2.4 Constant-temperature baths of concrete and/or plastered brick square metre (m2)
C1.4.2.5 Concrete footings and pedestals for laboratory equipment square metre (m2)
C1.4.2.10 Galvanised wire mesh fencing for store rooms square metre (m2)
C1.4.2.11 Galvanised wire mesh store room gate with a padlock square metre (m2)
The unit of measurement for items C1.4.2.1 to C1.4.2.11 shall be the square metre (m2) of the item supplied and installed as specified. The area shall
be determined from the authorised outside dimensions in plan. The contract rates shall include full compensation for the construction or provision of
these items all complete in accordance with the specifications given in the Contract Documentation.
C1.4.3.5 Office desk with 3 drawers (at least one lockable drawer) number (No)
C1.4.3.14 400/231 volt 3-phase power outlet plug point number (No)
C1.4.3.15 Single 1 500 m, 58 watt fluorescent tube ceiling light number (No)
C1.4.3.16 Single 1 500 mm, 22 watt LED tube ceiling light number (No)
C1.4.3.23 Fire extinguisher 9,0 kg, dry powder type number (No)
C1.4.3.35 3,0 m aluminium straight edge complete with two measuring wedges number (No)
C1.4.3.38 Standpipe complete with 30 m of 19 mm dia. heavy duty hose pipe number (No)
The unit of measurement for items C1.4.3.1 to C1.4.3.38 shall be the number of each item supplied and installed as specified. The contract rates
shall include full compensation for the provision and installation of these Engineer’s facilities all complete in accordance with the specifications given
in the Contract Documentation. On completion of the contract these items will be returned to the Contractor and the contract rates shall make
allowance for any depreciation in value over the duration of the contract period.
C1.4.4.1 Cell phones costs, including pro-rata rentals, for calls made in connection with contract prime cost sum
administration
C1.4.4.2 Handling costs and profit in respect of item C1.4.4.1 percentage (%)
C1.4.4.3 The provision of a direct independent telephone line for the Engineer, including the monthly prime cost sum
rental charges and the cost of business calls
C1.4.4.4 Handling costs and profit in respect of item C1.4.4.3 percentage (%)
C1.4.4.5 The provision of internet connectivity and WiFi data for Engineer’s site staff prime cost sum
C1.4.4.6 Handling costs and profit in respect of item C1.4.4.5 percentage (%)
C1.4.4.7 The provision of paper and ink for a combination colour printer/copier/scanner prime cost sum
C1.4.4.8 Handling costs and profit in respect of item C1.4.4.7 percentage (%)
C1.4.4.9 The provision of a complete 220/250 volt single phase electrical power installation, including all prime cost sum
poles, insulators, wiring, switchboards, mains connections, meters etc.
percentage (%)
C1.4.4.10 Handling costs and profit in respect of item C1.4.4.9
C1.4.4.11 The provision of a complete 440/231 volt three phase electrical power installation, including all prime cost sum
poles, insulators, wiring, switchboards, mains connections, meters etc.
C1.4.4.12 Handling costs and profit in respect of item C1.4.4.11 percentage (%)
C1.4.4.13 Provision of a 440/231 volt three phase electricity generator if electricity from a power supply prime cost sum
authority is not available on site
C1.4.4.14 Handling costs and profit in respect of item C1.4.4.13 percentage (%)
C1.4.4.15 The provision of all gas installations required at the site offices, laboratories and at the prime cost sum
Engineer’s staff accommodation (if required), including gas storage cylinders, tubing,
regulators, gas burners and shut-off cocks
C1.4.4.16 Handling costs and profit in respect of item C1.4.4.15 percentage (%)
The percentage for items C1.4.4.2, C1.4.4.4, C1.4.4.6, CC1.4.4.8, C1.4.4.10, C1.4.4.12, C1.4.4.14 and C1.4.4.16 is a percentage of the amount
spent under the relevant prime cost item. It shall include full compensation for the handling costs of the Contractor and the profit for providing the
specified service.
The unit of measurement for item C1.4.5 shall be the lump sum. The lump sum shall include full compensation for all costs, administration charges
and other general costs related to providing the specified services for the Engineer’s site facilities. These services include the provision of a potable
water supply, a sewerage system, septic tanks, conservancy tanks, refuse containers etc. as well as the excavation and backfilling of any service
trenches required and the loading and hauling of the excavated material to spoil if required, regardless of haul distance.
The unit of measurement for item C1.4.5.2 shall be the month or part thereof for the duration of the approved contract period. The contract rate shall
include full compensation for the provision of electricity and gas, sewage removal, refuse and rubbish removal, cleaning services, maintenance and
repairs as specified and required. The contract rate shall also include the partial cost, proportional to the amount of electricity supplied to the
Engineer’s offices, laboratory and site accommodation, of running a generator only when electricity from a power supply authority is not available on
site.
The unit of measurement for items C1.4.6.1 and C1.4.6.2 is the month or part thereof for the duration of the approved contract period. The contract
rate shall include full compensation for providing the specified staff member and for all wages, Employer contributions, accommodation, transport and
other staff related costs incurred by the Contractor.
C1.4.7.1 Provision of a bus, mini-bus or combi van for site inspection purposes (specify type and size of per day
vehicle)
The unit of measurement for item C1.4.7.1 is a day regardless of the number of hours that the vehicle is used during that day. The contract rate shall
cover all the costs of providing the specified vehicle with an experienced licensed driver when required by the Engineer.
The unit of measurement for item C1.4.7.2 is the total kilometres travelled during the site inspection by the vehicle, as instructed by the Engineer. The
contract rate shall include full compensation for all fuel, maintenance and depreciation costs. Any kilometres covered in delivering and removing the
vehicle from site will not be measured for payment.
C1.4.8.1 Supply and installation of all required security measures at the Engineer’s site offices and lump sum
laboratories
C1.4.8.2 Provision of security guards / watchmen and an armed response service at the Engineer’s site month
offices and laboratories
C1.4.8.3 Supply and installation of all required security measures at the Engineer’s site accommodation lump sum
C1.4.8.4 Provision of security guards / watchmen and an armed response service at the Engineer’s site month
accommodation
C1.4.8.5 Supply and installation of an alarm system at the Engineer’s rented accommodation (No. of lump sum
houses stated ………)
C1.4.8.6 Provision of an armed response service at the Engineer’s rented accommodation (No. of month
houses stated ………)
The unit of measurement for items C1.4.8.1 and C1.4.8.3 is the lump sum. The lump sum shall include full compensation for the provision of all
security measures required at the at the Engineer’s site office, site laboratory and site accommodation as specified in Clause A1.2.3.17.
The unit of measurement for items C1.4.8.2 and C1.4.8.4 is the month or part thereof that the services are provided at the engineer’s site office, site
laboratory and site accommodation as specified in Clause A1.2.3.17. Part of a month shall be calculated to two decimal places.
CONTENTS
D1.4.1 SCOPE
D1.4.2 GENERAL
D1.4.3 PERFORMANCE GUARANTEE REQUIREMENTS
D1.4.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D1.4.5 VISUALLY ASSESSED PROPERTIES
D1.4.6 INSTRUMENTALLY ASSESSED PROPERTIES
D1.4.7 EVALUATION FOR ACCEPTANCE
D1.4.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D1.4.9 NOTIFICATION OF REMEDIAL WORK
D1.4.10 REMEDIAL WORKS
D1.4.1 SCOPE
Certificates showing compliance with the applicable SANS Specifications referred to in Clause A1.4.7 in this Section shall be provided by the
Contractor if requested by the Employer or the Engineer.
Regulatory compliance certificates for the electrical wiring and gas supply installations at the site accommodation, laboratories and offices shall
be submitted to the Engineer upon completion of the various facilities and before any payment is made for these facilities.
Clauses D1.4.2 to D1.4.10 are not applicable to this Section.
CONTENTS
PART A: SPECIFICATIONS
A1.5.1 SCOPE
A1.5.2 DEFINITIONS
A1.5.3 GENERAL
A1.5.4 DESIGN BY THE CONTRACTOR / PERFORMANCE BASED SYSTEMS
A1.5.5 MATERIALS
A1.5.6 CONSTRUCTION EQUIPMENT
A1.5.7 EXECUTION OF THE WORKS
A1.5.8 WORKMANSHIP
A1.5.2 DEFINITIONS
Barriers - consist of concrete, plastic or steel sections which are placed across or along the road to stop or divert the traffic or alongside /
around the work area to separate the traffic and pedestrians from the work area. Barriers may be used either as channelization devices or as
vehicle restraining systems depending on their type and on their fixing arrangements.
Channelization devices - moveable channelization devices used for diverting and/or separating vehicles, non-motorised traffic and pedestrians
from the work areas include barriers, delineators and traffic cones. These moveable channelization devices may be supplemented by additional
temporary road markings and road studs.
Delineators - are rectangular warning signs with a directional chevron on one or both sides which indicates which side of the roadway is open
for use by the vehicles, non-motorised traffic and/or pedestrians.
Detour - a detour is any section of another existing road onto which traffic is diverted around the work areas.
Road markings - include all the regulatory road markings painted on the surface of existing or newly constructed roads as well as temporary
road markings painted on the surface of deviations and detours.
Partial width or half width construction - this is a construction strategy wherein part of a roadway is constructed or reconstructed/rehabilitated
as a phase without encroaching on the remaining width of the roadway in order to accommodate traffic. (Typically, a two-lane two-way road will
usually be constructed in two half width phases whereas a multi-lane road will be constructed in several partial width phases.)
Road signs - include all the regulatory road signs erected along existing or newly constructed roads as well as the temporary road signs
erected along temporary deviations and detours.
Road restraint systems - temporary road restraint systems used for preventing vehicles from leaving the permitted lanes, or for separating two
opposing streams of traffic, during the construction of the Works may consist of either movable precast concrete or steel barriers or steel
guardrails that comply with the specifications given in Chapter 11.
A1.5.3 GENERAL
A1.5.3.1 Access to properties
The Contractor shall provide and maintain access to all public and private properties which fall within or adjoin the Works at all times, unless
alternate provision is specified in the Contract Documentation.
A1.5.3.4 Late occupation of traffic lanes, interchange ramps and cross roads
If specified in the Contract Documentation the Contractor shall be charged a lane occupation levy for any occupation of traffic lanes, interchange
ramps and any cross roads beyond the completion dates and times agreed with the Employer. The lane occupation levies shall be specified in
the Contract Documentation and they shall be deducted from payments due on the relevant interim payment certificates. If specified in the
Contract Documentation the Contractor shall also be charged a lane occupation levy for traffic lanes, interchange ramps and cross roads
occupied by the Contractor for the purpose of carrying out remedial work during or after completion of the Works.
A1.5.3.11 Services
Services affected by temporary deviations shall be located, protected and relocated in a similar manner as services affected by the permanent
Works as specified in Clause A2.1.3.2 of Chapter 2. The requirements given in the Contract Documentation shall also be applicable to any
services affected by the construction of temporary deviations.
A1.5.5 MATERIALS
A1.5.5.1 Material used for construction of temporary deviations
All material required for the construction of temporary deviations, which includes the earthworks, pavement layers, stabilised layers, asphalt and
bituminous surfacing layers shall comply with the specifications for these materials given in Chapters 4, 9 and 10 respectively.
A1.5.7.3 Accommodation of traffic where the road is constructed in half or partial widths
Where, for reasons related to traffic, geometric or other restraints, the provision of a detour, or the construction of a temporary deviation
alongside or in close proximity to the roadworks, is not possible or impracticable, the Contractor shall construct the Works on a half or partial
width of the existing road so as to allow public and construction traffic to use that remainder of the road surface which is currently not under
construction.
Half or partial width traffic accommodation shall be carried out in accordance with the requirements of this Section, any additional requirements
given in the Contract Documentation and any further written instructions issued by the Engineer. The specifications given in this section shall
also apply to a road that is being constructed in half or partial widths.
The length of the half or partial width construction sections where the traffic can only pass in one direction at a time shall not exceed the length
specified in the Contract Documentation. The number of one-ways sections under construction at any one time shall not exceed the number
permitted in the Contract Documentation and two-way traffic sections of at least 2.0 km in length shall be provided between each of the one-way
construction sections.
The start and end points of the half or partial width construction sections shall be as specified in the Contract Documentation or as decided on
site by the Engineer and confirmed to the Contractor in writing. All start and end points shall be positioned to ensure that there is sufficient traffic
queueing length before the traffic control point to ensure that oncoming traffic has a sufficient stopping sight distance as specified in Figure
13.25 given in Chapter 13 of Volume 2 of the SARTSM before the traffic queueing area.
The work zone and the one-way traffic lane shall be separated from each other by delineators and/or temporary barriers as specified in Volume
2 of the SARTSM and/or in the Contract Documentation and by the Engineer where applicable.
The Contractor shall maintain the portion of the road which is being used to accommodate the traffic in a safe, clean and trafficable condition at
all times.
The one-way traffic shall be controlled by a STOP / GO system manned by an adequate number of traffic controllers, flagmen and/or traffic
signals, signs, barricades, lights and the necessary supervisory staff to ensure a reasonably free flow of traffic alternately in each direction
throughout the entire period when the roadway is open to one-way traffic only.
Whenever the one-way STOP / GO system is operation during hours of darkness the use of traffic signals to control the traffic in addition to the
traffic controllers shall be compulsory. Flashing amber lights shall be mounted on top of the initial advance warning signs (usually positioned 1,0
km before the control point) and the traffic stopping and queueing length areas shall be illuminated with pole mounted floodlights.
The Contractor shall programme the Works in such a way to ensure that there are no STOP / GO one-way traffic sections in operation and that
two-way traffic can be accommodated safely within the contract limits during the Contractor’s annual shutdown period between December and
January or during any other shutdown periods which may be specified in the Contract Documentation. The Contractor shall endeavour to ensure
that there is no vertical step between two opposing traffic lanes during a shutdown period. If a step between opposing traffic lanes is
unavoidable then delineators or barriers shall be erected between the opposing traffic lanes as specified in the Contract Documentation or as
instructed by the Engineer. These traffic accommodation measures must be maintained by the traffic safety personnel for the full duration of the
shutdown period,
The Contractor shall programme his work taking due cognizance of all restrictive conditions associated with accommodating the traffic in half or
partial width construction sections.
CONTENTS
B1.5.1 SCOPE
B1.5.2 DEFINITIONS
B1.5.3 GENERAL
B1.5.5 MATERIALS
B1.5.1 SCOPE
The nature of the work required to accommodate the traffic is labour intensive and no additional labour enhancement requirements are specified
for Section A1.5.
B1.5.2 DEFINITIONS
Definitions as provided in Clause A1.5.2 shall also apply.
Identification, protection and relocation of existing services A1.5.3.11 C2.1.1 & C2.1.2 of Chapter 2
(a) Gravel surfaced pedestrian walkways / cycle paths square metre (m2)
(b) Bitumen surfaced pedestrian walkways / cycle paths square metre (m2)
(c) 60 mm concrete block paved pedestrian walkways / cycle paths square metre (m2)
The unit of measurement for item C1.5.1.1 shall be the month or part thereof that the accommodation of pedestrian and/or non-motorised traffic
is required on site during the approved Contract Period. No distinction will be made with respect to the type and/or number of pedestrian
crossings, walkways and cycle paths required.
The contract rate for item C1.5.1.1 shall include full compensation for the costs of complying with all the general obligations of the Contractor,
including keeping pedestrians and non-motorised traffic informed of the accommodation arrangements and facilities, for the costs of placing,
maintaining and relocating temporary signage and all other traffic control facilities as often as required and for any other related costs that are not
covered by, or included in, the other items given below.
The unit of measurement for items C1.5.1.2(a), (b) and (c) shall be the square metre of temporary pedestrian walkways and/or cycle paths
constructed as specified in the Contract Documentation. The contract rate shall include full compensation for all design and supervision costs
together with any other general costs associated with providing the temporary pedestrian walkways and/or cycle paths. It shall also include full
compensation for the cost of constructing and later removing the walkways and/or cycle paths when they are no longer required.
All loading and hauling of material required, for the construction of walkways and cycle paths shall be included in the contract rates.
Item Description Unit
C1.5.2 Accommodation of vehicular traffic month
The unit of measurement for item C1.5.2 shall be the month or part thereof that the accommodation of vehicular traffic is required on site during
the approved Contract Period. No distinction will be made with respect to the type and/or number of detours, deviations or partial / half width road
sections used to accommodate the traffic. The contract rate for item C1.5.2 shall include full compensation for complying with all the general
obligations of the Contractor, including keeping motorists informed of the traffic accommodation arrangements and facilities, for the costs of
placing, maintaining, relocating and protecting from damage all temporary and permanent signage and all other traffic control facilities as often as
required for constructing the Works and for carrying out testing and inspections and for any other related costs that are not covered by, or
included in, the other items given below.
Item Description Unit
C1.5.3 Liaison with traffic authorities month
The unit of measurement shall be the month or part thereof that the liaison with the traffic authorities, or the Employer’s traffic control centre, is
required on site, regardless of the frequency of liaison that is required during each month during the approved Contract Period.
The contract rate for item C1.5.4 shall include full compensation for all the Contractor’s costs incurred while complying with all the requirements
specified in Clause C1.5.7.7.
Item Description Unit
C1.5.4 Construction of temporary deviations
The applicable payment items required for the construction of temporary deviations shall be
taken from the relevant chapters and sections in Chapters 1, 3, 5, 9 and 10 and inserted into
the Pricing Schedule here. Each payment item for the construction of temporary deviations
shall be preceded by the main payment item number C1.5.4 / followed by the payment
number for the applicable payment item.
The unit of measurement for each item shall be as specified in the relevant payment item given in the applicable section of the pricing schedule.
The contract rates for these items shall include full compensation for the construction of temporary deviations or the repair / upgrading of detours
as specified in the relevant section of these Specifications.
C1.5.5.5 Base patching using crushed stone material stabilised with bitumen emulsion and cement cubic metre (m3)
C1.5.5.6 Base and/or surface patching using cold premixed asphalt kilogram (kg)
C1.5.5.7 Base and/or surface patching using hot plant mixed asphalt tonne (t)
C1.5.5.9 Grading of temporary deviations and existing roads used as detours kilometre (km)
C1.5.5.10 Watering of temporary deviations and existing roads used as detours kilolitre (kl)
C1.5.5.11 Other road maintenance work ordered by the Engineer provisional sum
C1.5.5.12 Handling cost, profit and all other charges in respect of item C1.5.6.11 percentage (%)
Payment will only be made under items C1.5.5.1 to C1.5.5.12 when the relevant item of maintenance work has been ordered by the Engineer in
writing and the Engineer has confirmed in writing the scope, quantity and/or frequency of work that is to be carried out.
The unit of measurement for item C1.5.5.1 shall be the hectare. The contract rate shall include full compensation for cutting grass in restricted
and steep access areas with hand tools in addition to mowing grass in more accessible areas.
The unit of measurement for items C1.5.5.2 shall be the kilometre of side or median drain cleaned. Each drain shall be measured separately.
The contract rate shall include full compensation for the removal of all silt, mud, gravel, rocks and any other obstructions in the drain as well as
for loading and hauling the removed material to spoil regardless of the haul distance.
The unit of measurement for item C1.5.5.3 shall be the cubic metre. The contract rate shall include full compensation for the removal of all silt,
mud, gravel, rocks and any other obstructions from inside the culvert or from the culvert entrance and exit as well as for loading and hauling the
removed material to spoil regardless of the haul distance.
The unit of measurement for item C1.5.5.4 shall be the kilometre measured along the centreline of the temporary deviation. The contract rate
shall include full compensation for collecting all the rubbish / litter alongside the temporary deviation and carting it to an approved disposal site
regardless of the haul distance.
The unit of measurement for items C1.5.5.5, C1.5.5.6 and C1.5.5.7 shall be the cubic metre, kilogramme and tonne respectively. The contract
rates shall include full compensation for excavating the failed area of the temporary deviation to the depth indicated by the Engineer, cleaning out
and squaring off the excavation, priming the compacted surface or the floor of the excavation, and the sides of the excavation as applicable, and
then backfilling the excavation as specified in the Contract Documentation. The contract rates shall also include full compensation for all final site
cleaning and removal to spoil of all surplus material regardless of the haul distance.
The unit of measurement for item C1.5.5.8 shall be the linear metre of guardrail replaced. The contract rate shall include full compensation for
removing the damaged guardrails to spoil or storage as specified by the Engineer, reinstating or replacing any displaced or damaged guardrail
posts and providing and installing a new guardrail in the correct position.
The unit of measurement for item C1.5.5.9 shall be the kilometre of gravel surfaced temporary deviation which is graded smooth with a motor
grading to remove all corrugations and to redistribute the bladed gravel material evenly across the road surface. The contract rate per kilometre
shall include full compensation for providing and maintaining the motor grader and grading the road surface to restore the riding quality as
specified in the Contract Documentation, regardless of any variations in the width of roadway being graded.
The unit of measurement for item C1.5.5.10 shall be the kilolitre of water sprayed on the surface of temporary deviations as and when instructed
by the Engineer in writing. The contract rate shall include full compensation for providing, transporting and spraying the water on the road
surface.
The provisional sum allowed under item C1.5.5.11 shall provide for all other maintenance work carried out by the Contractor on the temporary
deviations that may be required as specified in the Contract Documentation or as ordered by the Engineer. The provisional sum shall be paid in
accordance with the provisions given in the Contract Documentation. Where applicable existing contract rates or accepted day work rates will be
used.
The percentage under item C1.5.5.12 is a percentage of the amount spent under item C1.5.5.11 which shall include full compensation for all
handling costs, profit and all other charges in connection with arranging and carrying out the maintenance works.
Item Description Unit
C1.5.6 Removal of temporary deviations kilometre (km)
The unit of measurement for item C1.5.6 shall be the kilometre. The contract rate shall include full compensation for removing temporary
deviations as specified in Clause A1.5.7.10g). The contract rate shall include for all removal, loading and hauling operations required regardless
of the haul distance.
Item Description Unit
C1.5.7 Temporary traffic control facilities
(a) Single sided, reversible left or right (size indicated) number (No)
(b) Double sided, reversible left or right (size indicated) number (No)
(a) Sign mounted flashing amber lights (2 lights with the specified power supply) mounted on a number (No)
backing board which is:
(i) 900 mm wide x 150 mm high number (No)
(ii) 1 200 mm wide x 200 mm high number (No)
(d) Illuminated road sign – TW series (length of sides indicated) number (No)
(f) Mobile variable message sign with a speed measuring and display capability month
(a) Sign mounted flashing amber lights (a pair of two lights mounted on a separate backing board) month
(f) Mobile variable message sign with a speed measuring and display capability month
(c) 150 mm high x 3 m wide asphalt speed control humps metre (m)
The unit of measurement for items C1.5.7.1(a), C1.5.7.1(b) and C1.5.7.2 shall be the number of delineators or traffic cones used on site. The
contract rates shall include full compensation for the provision, placing and relocation of delineators and traffic cones as often as required.
Payment for these items shall only be made once when they are first provided on site regardless of how many times they are repositioned and
reused during the construction of the Works.
The unit of measurement for items C1.5.7.3 and C1.5.7.4 shall be the number of flagmen and traffic controllers respectively employed for a
working shift in accordance with the requirements specified in Clause A1.5.7.11(e). The contract rate shall include full compensation for the
provision of trained flagmen and traffic controllers and for all wages, Employer contributions, accommodation, transport and other staff related
costs incurred by the Contractor, including their recruitment and training costs.
The contract rate shall also include full compensation for providing all flagmen and traffic controllers with conspicuous orange or bright yellow
clothing and safety boots, safety jackets utilizing retro-reflective and/or fluorescent panels in red, yellow and/or white as well as a red warning
flag or an amber LED strobe wand during hours of darkness as specified in Clauses A1.5.6.2e) and f).
The unit of measurement for items C1.5.7.5(a) to C1.5.7.5(f) shall be the number of illuminated traffic signs that are supplied and delivered to site
as specified in the Contract Documentation and/or as specified by the Engineer. The contract rates shall include full compensation for the
provision of the illuminated traffic signs, including poles and brackets, portable mounting frames and ballast and portable trailers where
applicable, and for removing them from site when they are no longer required.
The unit of measurement for items C1.5.7.6(a) to C1.5.7.6(f) shall be the month or part thereof during the approved Contract Period that these
traffic safety devices are erected / positioned on site as specified. The contract rates shall include full compensation for maintaining the warning
signs, providing a suitable electricity power supply and relocating the warning signs as often as required during the construction period and for
removing them from site when they are no longer required.
The unit of measurement for items C1.5.7.7(a), C1.5.7.7(b) and C1.5.7.6(c) shall be the metre of rumble strip or speed control hump installed on
the road. The contract rates shall include full compensation for the provision and construction of the traffic calming devices.
The unit of measurement for item C1.5.7.8 shall be the month or part thereof during the approved Contract Period that each traffic control station
is in operation on the site of the Works. The contract rate shall include full compensation for the provision and construction/erection of the traffic
control shelter complete as specified in clause A1.5.6.1f) including the provision of the specified traffic signals, communication devices, flood
lighting and the cost of supplying electricity. The contract rates shall also include full compensation for moving the traffic control points to new
locations as often as required and for removing them from site when they are no longer required.
The unit of measurement for item C1.5.7.9. shall be the month or part thereof during the approved Contract Period that the traffic signs and
delineators on the Site of the Works are kept clean. The contract rate shall include full compensation for the cleaning of all the delineators and
signs on site at least once a week and more often if required as specified in Clause A1.5.7.11d).
Item Description Unit
C1.5.8 Traffic safety officer Man-month
The unit of measurement for item C1.5.8 shall be the months or part thereof during the approved Contract Period that each traffic safety officer is
deployed on the site of the Works. The contract rate shall include full compensation for the provision of a trained and experienced traffic safety
officer and for all wages, Employer contributions, accommodation, transport and other staff related costs incurred by the Contractor, including
their recruitment and training costs.
The contract rate shall also include full compensation for the provision of a safety jacket utilizing retro-reflective and/or fluorescent panels in red,
yellow and/or white, a cell-phone and anything else the traffic safety officer requires to fulfil his duties and obligations as specified in Clause
A1.5.7.12.
The contract rate shall also include full compensation for the provision, operation and maintenance of a vehicle provided for the sole use of the
DRAFT STANDARD (DS) OCTOBER 2020 1-67
traffic safety officer as specified in Clause A1.5.6.4, including the provision of an amber flashing roof light or light bar and a “TRAFFIC
CONTROL” warning sign.
Item Description Unit
C1.5.9 Traffic safety vehicle month
The unit of measurement for item C1.5.9 shall be the month or part thereof during the approved Contract Period that the traffic safety vehicle is
deployed on the site of the Works.
The contract rate shall include full compensation for the provision, operation and maintenance of a traffic safety vehicle, including the driver and
any assistants required, as specified in Clause A1.5.6.3, including the provision of an amber flashing roof light or light bar, a “TRAFFIC
CONTROL” warning sign, a high visibility reflective rear chevron panel and an approved proprietary rear mounted impact attenuator device.
Item Description Unit
C1.5.10 Tow trucks
C1.5.10.1 Provision of a tow truck on call for light vehicles weighing less than two tonnes month
C1.5.10.2 Provision of a tow truck on call for heavy vehicles weighing two tonnes or more month
The unit of measurement for items C1.5.10.1 and C1.5.10.2 shall be the month or part thereof during the approved Contract Period that the tow
trucks are ordered by the Engineer to be on call for use on the site of the Works whenever they are required.
The contract rate shall include full compensation for the provision when required, the operation and the maintenance of the tow trucks.
Payment for towing vehicles off the road and/or on to a storage or repair facility will not be made as this cost is to be recouped from the owner of
the towed vehicle by the Contractor or the tow truck operator.
Item Description Unit
C1.5.11 Provision of safety equipment for visitors
C1.5.11.1 Provision of reflective safety vests for visitors number (No.)
C1.5.11.2 Provision of hard hats for visitors number (No.)
The unit of measurement for items C1.5.11.1 and C1.5.11.2 shall be the number of each item provided as specified, and approved by the
Engineer. The contract rates for the various safety items shall include full compensation for provision thereof and maintenance in good working
order.
Item Description Unit
C1.5.12 Additional traffic accommodation facilities ordered by the Engineer:
C1.5.12.1 Provision of additional traffic accommodation facilities prov sum
C1.5.12.2 Handling cost, profit and all other charges in respect of item C1.5.12.1 percentage (%)
The provisional sum allowed under item C1.5.12.1 shall cover for the provision, erection and later removal of all additional traffic accommodation
items that may be ordered by the Engineer. The provisional sum shall be paid in accordance with the provisions of the Contract Documentation.
The percentage under item C1.5.12.2 is a percentage of the amount spent under item C1.5.12.1 which shall include full compensation for all
handling costs, profit and all other charges for the provision, erection and later removal of the additional traffic accommodation facilities.
CONTENTS
D1.5.1 SCOPE
D1.5.2 GENERAL
D1.5.3 PERFORMANCE GUARANTEE REQUIREMENTS
D1.5.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D1.5.5 VISUALLY ASSESSED PROPERTIES
D1.5.6 INSTRUMENTALLY ASSESSED PROPERTIES
D1.5.7 EVALUATION FOR ACCEPTANCE
D1.5.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D1.5.9 NOTIFICATION OF REMEDIAL WORK
D1.5.10 REMEDIAL WORKS
D1.5.1 SCOPE
The product quality and safety compliance certificates mentioned in Clauses A1.5.5 and A1.5.6 shall be provided if requested by the Employer
or the Engineer.
Clauses D1.5.2 to D1.5.10 are not applicable to this Section.
CONTENTS
PART A: SPECIFICATIONS
A1.6.1 SCOPE
A1.6.2 DEFINITIONS
A1.6.3 GENERAL
A1.6.4 DESIGN BY THE CONTRACTOR / PERFORMANCE BASED SYSTEMS
A1.6.5 MATERIALS
A1.6.6 CONSTRUCTION EQUIPMENT
A1.6.7 EXECUTION OF THE WORKS
A1.6.8 WORKMANSHIP
The clearing and grubbing of areas required for site offices, laboratories and the Engineer’s site accommodation shall be included in the work
required to erect these facilities.
A1.6.2 DEFINITIONS
Clearing - is the removal, loading and disposal of all trees (including designated and protected trees if approved for removal), grass, brush,
shrubs, other vegetation, rubbish/litter, rocks and boulders of up to 0,15 m 3 in size which are exposed or lying on the surface and all other
unsuitable or waste material on or above ground level.
Clearing shall also include the removal of existing buildings, walls and other structures which encroach on or obstruct the Works and which can
be broken down and removed with a medium sized bulldozer. (Breaking down of reinforced concrete shall be specified separately in the
Contract Documentation if required.)
Removal of temporary works installed by the Contractor shall not be measured or paid for as clearing.
The removal, loading, transport, offloading and stacking (or disposal if specified in the Contract Documentation or by the Engineer) of existing
fences, road signs, guardrails, kerbing, channelling etc. shall be carried out as specified in the relevant sections of this Standard Specification.
Designated trees - are indigenous trees or heritage trees that may not be removed without the approval of the relevant local authority.
Designated spoil areas - are spoil or dump sites identified by the Employer in the Contract Documentation or identified by the Engineer on site
and those identified by the Contractor in the Contractor’s materials management and utilisation plan, as prepared in accordance with the
environmental regulations and the environmental management plan.
There are two types of designated spoil areas:
• Unsuitable material spoil areas identified on or near the site of the Works and which have been agreed to by the Engineer. In urban or
peri-urban areas the use of the spoil areas shall be approved by the local municipal authority in writing before any general unsuitable
material is deposited there.
• Hazardous waste spoil areas which shall be commercial or municipal waste sites that are registered to receive and dispose of
hazardous waste material.
A1.6.3 GENERAL
Not required for Section A1.6.
A1.6.5 MATERIALS
Not required for Section A1.6.
A1.6.7.2 Clearing
Clearing, as defined in Clause A1.6.2, shall be done with equipment which suits the type of material and terrain to be cleared and in a manner
which will result in minimal loss of topsoil. The cleared material shall be separated into re-usable material, unsuitable material and hazardous
waste and it shall be loaded and removed from the site immediately and transported to a designated stacking area, a designated spoil area or
an approved hazardous waste site as appropriate.
All undesignated trees, together with those protected trees or designated (indigenous or heritage) trees where the required permission to
remove them has been obtained, shall be cut down unless instructions have been given to retain any particular trees in the Contract
Documentation or by the Engineer.
The Contractor shall take the necessary precautions to prevent damage to structures and other private or public property. If necessary, the trees
shall be cut in sections from the top downwards.
The branches of any trees outside the roadbed area that are designated to be left standing shall be trimmed to provide a 7,0 m clearance above
the finished road level. The trimming of branches shall be done neatly by saw cutting as near as possible to the base of the branches.
Where clearing and grubbing would involve the cutting down of indigenous forest or commercial plantations the Contractor shall inform the
relevant authority or owner at least two months in advance before commencing with clearing and grubbing of such areas to allow them time to
salvage any usable timber before the trees are removed.
Where specified by the Engineer or in the Contract Documentation, clearing of hydraulic structures, where such work requires working to
prescribed levels or working without damaging existing structures, shall be carried out as specified in Chapter 3.
The removal, breaking up and disposal of existing kerbing, channelling, down-chutes etc. shall be carried out as specified in Chapter 3.
All re-usable fencing wire shall be neatly wound into reels and all such wire, together with all fence posts and other usable material shall be
removed as specified in Clause A11.5.7.9 of Chapter 11 and neatly stacked at sites indicated by the Engineer.
All re-usable road furniture such as road signs, guardrails, down-chutes etc. shall also be removed as specified in Clauses A11.4.7.3 and
A11.6.7.7 of Chapter 11 and neatly stacked at sites indicated by the Engineer.
All existing buildings and structures which encroach on or obstruct the Works shall be removed. All buildings and structures that must be
removed will be identified in the Contract Documentation and shall be confirmed with the Engineer in writing before the Contractor demolishes
and/or removes any structures or buildings.
A1.6.7.4 Grubbing
All stumps and roots, including matted roots, in the roadbed area shall be removed to a depth of at least 1,0 m below the cleared roadbed
surface.
Outside the roadbed area only stumps and roots, including matted roots, exceeding 75 mm in diameter shall be removed to a depth of at least
75 mm below the original ground level. The grubbed material shall be loaded and removed from the site immediately and disposed of at a
designated spoil area.
The foundations of any buildings or structures, buried rubbish, old rubbish tips, rubble or other unsuitable material shall be removed unless
otherwise instructed by the Engineer. The building material and unsuitable or waste material shall be loaded and removed from the site
immediately and disposed of at a designated spoil area.
Except in borrow areas, all cavities resulting from the grubbing shall be backfilled with approved material and compacted to a density of at least
the density of the surrounding ground.
A1.6.8 WORKMANSHIP
Reserved for future use.
CONTENTS
B1.6.1 SCOPE
B1.6.2 DEFINITIONS
B1.6.3 GENERAL
B1.6.5 MATERIALS
B1.6.1 SCOPE
Where specified in the Contract Documentation labour enhancement methods shall be used to carry out the applicable clearing and grubbing
operations or parts of these operations.
B1.6.2 DEFINITIONS
Definitions as provided in Clause A1.6.2 shall also apply.
B1.6.3 GENERAL
Any activity specified in PART A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B1.6.5 MATERIALS
Not required for Section A1.6.
B1.6.8 WORKMANSHIP
Not required for Section A1.6.
C1.6.1.1 Clearing with machines and some hand labour where necessary hectare (ha)
C1.6.1.2 Clearing with hand labour only when labour enhanced work is specified hectare (ha)
C1.6.1.3 Clearing for new fence lines (over a width of 2,0 m) kilometre (km)
C1.6.1.4 Clearing for service trenches (over the agreed width required) square metre (m2)
The unit of measurement for items C1.6.1.1 and C1.6.1.2 is the hectare. The quantity shall be taken as the area (to the nearest 0,01 ha)
designated by the Engineer and cleared in accordance with this Standard Specification.
The unit of measurement for item C1.6.1.3 is the kilometre of 2,0 m wide cleared fence line strip.
The unit of measurement for item C1.6.1.4 is the square metre of cleared area along the service trench. The area to be measured shall be
calculated by multiplying the length cleared by the agreed width required to excavate the trench, temporarily stockpile the excavated material
alongside and place the service materials alongside the trench prior to installation.
The contract rate shall include full compensation for all work necessary for the clearing of the surface, the removal of rocks and boulders up to
0,15 m3 each in size, the removal of grass, bushes, shrubs, any other vegetation, all trees with a girth of less than 1,0 m, cutting of branches,
demolishing of structures or parts of structures (except those structures specifically listed in the Contract Documentation and measured
separately under item C1.6.4,) and the loading of the cleared material.
Hauling of the cleared material to a designated spoil area will be measured from the point of loading to the centroid of the designated spoil area
following the shortest practical route. Payment for haulage will be made under item C1.7.2.
No additional payment will be made for the removal of a certain amount of sand, soil or gravel material which may be inherent in, or
unavoidable, during the process of clearing, regardless of the quantity removed.
Where topsoil can be removed without the necessity of first doing clearing, no payment will be made for clearing.
C1.6.2.1 Grubbing with machines and some hand labour where necessary hectare (ha)
C1.6.2.2 Grubbing with hand labour when labour enhancement work is specified or it is not practical to hectare (ha)
use a machine
C1.6.2.3 Grubbing by hand for new fence lines (over a width of 2,0 m) kilometre (km)
C1.6.2.4 Grubbing by hand for service trenches (over the agreed width required) square metre (m2)
The unit of measurement for items C1.6.2.1 and C1.6.2.2 is the hectare. The quantity shall be taken as the area measured in hectares (to the
nearest 0,01 ha) as designated by the Engineer in writing and grubbed in accordance with these specifications.
The unit of measurement for item C1.6.1.3 is the kilometre of 2,0 m wide cleared fence line strip.
The unit of measurement for item C1.6.1.4 is the square metre of cleared area along the service trench. The area to be measured shall be
calculated by multiplying the length cleared by the agreed width required to excavate the trench, temporarily stockpile the excavated material
alongside and place the service materials alongside the trench prior to installation.
The contract rate shall include full compensation for all work necessary for the grubbing the area, removing all tree roots larger than 75 mm in
diameter and all tree stumps, backfilling of cavities, demolishing and disposal of foundations of buildings and structures, the removal of rubbish,
rubble or other unsuitable or waste material and the loading and offloading of the grubbed material. Hauling of the grubbed material to a
designated spoil area will be measured from the centroid of the loading area to the centroid of the designated spoil area following the shortest
practical route. Payment for haulage will be made under item C1.7.2.
No additional payment will be made for the moving of a certain amount of soil or gravel material which may be inherent in, or unavoidable,
during the process of grubbing, regardless of the quantity removed.
Only the areas confirmed in writing by the Engineer to be grubbed shall be measured for payment.
C1.6.3.1 Girth equal to or exceeding 1,0 m up to and including 2,0 m number (No)
The unit of measurement for items C1.6.3.1 to C1.6.3.3 shall be the number of trees of each size removed. The girth of trees and stumps shall
be measured as specified in Clause A1.6.7.1. Trees and stumps with a girth exceeding 1,0 m shall be measured individually and classified in
size increments exceeding 1,0 m up to 2,0 m, exceeding 2,0 m up to 3,0 m and exceeding 3,0 m, as indicated in the items above. (Trees with a
girth of less than and up to 1,0 m shall not be paid for individually and the cost of removing all small trees and bushes with a girth of less than
and up to 1.0 m shall be included in the contract rates for item C1.6.1 and item C1.6.2.)
The contract rates shall include full compensation for all work necessary for the removal and grubbing of trees and stumps of all sizes, including
removal of the roots, the backfilling and compaction of the cavities left after the stump and roots have been removed with approved material,
C1.6.4.1 (Identify type and location of each building or structure with a separate sub-item) lump sum
The unit of measurement for each building or structure that is removed shall be the lump sum. The lump sum shall include full compensation
for all work necessary for demolishing and removing the buildings or structures, including removal of the foundations and the loading and
offloading of all the material. Hauling of the removed building or structural material to a designated spoil area will be measured from the point
of loading to the centroid of the designated spoil area following the shortest practical route. Payment for haulage will be made under item
C1.7.2.
C1.6.8.3 Removal, storage and maintenance of trees, girth up to and including 1,0 m number (No)
C1.6.8.4 Removal, storage and maintenance of trees, girth exceeding 1,0 m up to and including 2,0 m number (No)
C1.6.8.5 Removal, storage and maintenance of trees, girth exceeding 2,0 m up to and including 3,0 m number (No)
C1.6.8.6 Removal, storage and maintenance of trees, girth exceeding 3,0 m number (No)
The unit of measurement for item C1.6.8.1 shall be the number of temporary nurseries established on site as agreed with the Engineer. The
contract rate shall include full compensation for clearing and levelling the nursery site, installing fencing, shade netting and wind breaks, for
providing plant containers where necessary and for installing a water supply system.
The unit of measurement for items C1.6.8.2 to C1.6.8.6 shall be the number of shrubs or trees of each size removed from site and
replanted/stored and maintained in a temporary nursery. The contract rate shall include full compensation for all work necessary for carefully
removing the shrubs and trees with their root systems intact and for correctly replanting, storing, watering and maintaining them in a
temporary nursery until they are removed for replanting.
CONTENTS
D1.6.1 SCOPE
D1.6.2 GENERAL
D1.6.3 PERFORMANCE GUARANTEE REQUIREMENTS
D1.6.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D1.6.5 VISUALLY ASSESSED PROPERTIES
D1.6.6 INSTRUMENTALLY ASSESSED PROPERTIES
D1.6.7 EVALUATION FOR ACCEPTANCE
D1.6.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D1.6.9 NOTIFICATION OF REMEDIAL WORK
D1.6.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A1.7.1 SCOPE
A1.7.2 DEFINITIONS
A1.7.3 GENERAL
A1.7.4 DESIGN BY THE CONTRACTOR / PERFORMANCE BASED SYSTEMS
A1.7.5 MATERIALS
A1.7.6 CONSTRUCTION EQUIPMENT
A1.7.7 EXECUTION OF THE WORKS
A1.7.8 WORKMANSHIP
A1.7.2 DEFINITIONS
Hauling - is the moving of loaded construction material from the point of excavation, or from a stockpile or windrow, to the point of use on the
site or to designated spoil areas. The hauling operation shall include the off-loading of the material at the point of use on site, at the temporary
stockpiles or at the designated spoil sites as applicable.
Haul roads - are temporary roads constructed by the Contractor, or existing public or privately owned roads, or any part or section of the road
under construction, used for the purposes of hauling construction materials or for carting material to spoil.
Loading - is the operation of picking up the material from an excavation, stockpile or windrow and placing it in a haul vehicle.
A1.7.3 GENERAL
A1.7.3.1 Measurement of haul distance
The haul distance shall usually be measured from the centre of volume (centroid) of the excavation in the cutting (or part of a cutting), trench or
borrow pit, or from the centre of the stockpile position where applicable, to the centroid of the fill (or part of a fill), to the mid-point along the road
centreline of the section of the road layer where the material is placed, to the centre of the temporary stockpile position in a borrow pit, quarry or
on site or to the centre of the designated spoil area where the material is off loaded as applicable. The haul distance will be measured to the
nearest 0,1 km.
For those operations where the material is usually disposed of, and/or reused, near the source of the material the relevant pay item may state
that the cost of hauling the material for the first 1,0 km shall be included in the contract rate for that pay item. For these operations the hauling of
the material shall only be measured if the actual haul distance exceeds 1,0 km and the haul distance to be measured for payment shall be
measured from a point starting 1,0 km from the centre of volume (centroid) of the excavation in the trench or borrow pit, or from the centre of the
stockpile position where applicable, up to the centroid of the fill (or part of a fill), up to the mid-point along the road centreline of the section of
the road layer where the material is placed or up to the centre of the designated spoil area where the material is off loaded as applicable. The
haul distance will be measured to the nearest 0,1 km.
The haul distance shall be measured along the shortest route as instructed by the Engineer as being safe and practical. The haul distance shall
include any distance that the haul vehicle must travel to make use of a safe turning point or the next off ramp before making the return trip.
Should the Contractor choose to haul material over some other longer route, computations for payment shall nevertheless be based on the haul
distance measured along the shortest route instructed by the Engineer.
A1.7.5 MATERIALS
Not required for Section A1.7.
A1.7.8 WORKMANSHIP
Reserved for future use.
CONTENTS
B1.7.1 SCOPE
B1.7.2 DEFINITIONS
B1.7.3 GENERAL
B1.7.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B1.7.5 MATERIALS
B1.7.6 CONSTRUCTION EQUIPMENT
B1.7.7 EXECUTION OF THE WORKS
B1.7.8 WORKMANSHIP
B1.7.1 SCOPE
Where specified in the Contract Documentation, or where it is more practical to do so, the loading operations shall be carried out using hand
labour instead of construction equipment.
B1.7.2 DEFINITIONS
Definitions as provided in Clause A1.7.2 shall also apply.
B1.7.3 GENERAL
Any activity specified in PART A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B1.7.5 MATERIALS
Not required for Section A1.7.
B1.7.8 WORKMANSHIP
Not required for Section A1.7.
C1.7.1.1 Loading from stockpile using machines and some hand labour where necessary cubic metre (m3)
C1.7.1.2 Loading from heaps or windrows using machines and/some hand labour where necessary cubic metre (m3)
C1.7.1.3 Loading by hand only from stockpile or heaps when labour enhancement work is specified or cubic metre (m3)
it is not possible to use machines
Loading is generally considered to be part of the operation that produced the material which is being loaded, such as excavation, grubbing,
cleaning, demolition etc., and it is therefore not usually measured separately for payment. Loading shall only be measured separately for
payment for loading stockpiled material and for loading material that has been placed in heaps or windrows where the relevant payment item
specifically states that the loading will be paid for separately.
The unit of measurement for items C1.7.1.1 to C1.7.1.3 shall be the cubic metre of material loaded into the hauling vehicles. These pay items
shall only apply for those activities where the relevant pay item does not specify that the loading is included in the contract rate for that pay item.
The quantity of all soil and gravel materials loaded for hauling for use on the site of the Works shall be the compacted volume of material
measured in its final position in the Works calculated using the dimensions given in the Contract Documentation or specified in writing by the
Engineer.
The quantity of all materials loaded for hauling to temporary stockpile for later use in the Works, to borrow pits for backfilling purposes or for
disposal at designated spoil areas shall be taken as 70% of the measured load volume of the haul vehicle being used to transport soil and gravel
material and 50% of the measured load volume of the haul vehicle being used to transport hard material and/or boulders.
The contract rate for item C1.7.1.1 shall include full compensation for loading material from a stockpile and loading it into the hauling vehicles.
The contract rate for item C1.7.1.2 shall include full compensation for loading excavated material from heaps or windrows at the point of
collection, including any windrowing and/or localised sorting / stockpiling that may be required, and loading it into the hauling vehicles.
The contract rate for item C1.7.1.3 shall include full compensation for loading excavated material at the point of collection on site or loading it
from stockpile by hand and loading it by hand into the hauling vehicles. This item is only applicable when the Contractor has been instructed to
load the material by hand in the Contract Documentation or by the Engineer to enhance the labour component of the Works or if it is not practical
to use machines due to the restricted nature of the work.
C1.7.2.1 Hauling material for use in the Works and off-loading it on the site of the Works:
(a) Soil, gravel, crushed stone and pavement layer material cubic metre - kilometre (m3 - km)
(b) Boulders and hard material cubic metre - kilometre (m3 - km)
C1.7.2.2 Hauling material to spoil and off-loading it at a designated spoil or stockpile area:
(a) Cleared and grubbed material (organic matter and all other unsuitable or waste cubic metre - kilometre (m3 - km)
material)
(b) Soil and gravel material cubic metre - kilometre (m3 - km)
(c) Boulders, hard material and concrete cubic metre - kilometre (m3 - km)
The unit of measurement for items C1.7.2.1 and C1.7.2.2 shall be the cubic metre – kilometre (m3 - km) which is calculated as the product of the
quantity of material loaded, as measured in items C1.7.1.1, C1.7.1.2 or C1.7.1.3, multiplied by the applicable haul distance which shall be
calculated as defined in Clause A1.7.3.1.
These pay items shall only apply for those activities where the relevant pay item does not specify that all the hauling is included in the contract
rate for that pay item.
The quantity of all soil and gravel materials hauled for use on the site of the Works shall be the compacted volume of material measured in its
final position in the Works calculated using the dimensions given in the Contract Documentation or specified in writing by the Engineer.
The quantity of all materials hauled to temporary stockpile for later use in the Works, to borrow pits for backfilling purposes or to designated spoil
areas shall be taken as 70 % of the measured load volume of the haul vehicle being used to transport soil and gravel material and 50 % of the
measured load volume of the haul vehicle being used to transport hard material and boulders.
The quantity of all organic matter hauled to borrow pits or to designated spoil areas shall be taken as 50 % of the measured load volume of the
haul vehicle being used.
The contract rate shall include full compensation for hauling the material and off-loading it at the required or designated position.
CONTENTS
D1.7.1 SCOPE
D1.7.2 GENERAL
D1.7.3 PERFORMANCE GUARANTEE REQUIREMENTS
D1.7.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D1.7.5 VISUALLY ASSESSED PROPERTIES
D1.7.6 INSTRUMENTALLY ASSESSED PROPERTIES
D1.7.7 EVALUATION FOR ACCEPTANCE
D1.7.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D1.7.9 NOTIFICATION OF REMEDIAL WORK
D1.7.10 REMEDIAL WORKS
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 2: SERVICES ......................................................................................................................................... 2-1
2.1 GENERAL REQUIREMENTS AND TRENCHING FOR SERVICES ........................................................... 2-1
PART A: SPECIFICATIONS .............................................................................................................................................................................. 2-1
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................... 2-16
PART C: MEASUREMENT AND PAYMENT ................................................................................................................................................... 2-18
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ...................................................................................................................... 2-28
CONTENTS
PART A: SPECIFICATIONS
A2.1.1 SCOPE
A2.1.2 DEFINITIONS
A2.1.3 GENERAL
A2.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A2.1.5 MATERIALS
A2.1.6 CONSTRUCTION EQUIPMENT
A2.1.7 EXECUTION OF THE WORKS
A2.1.8 WORKMANSHIP
SANS 51008 Mixing water for concrete – Specification for sampling, testing and assessing the suitability of
water, including water recovered from processes in the concrete industry, as mixing water for
concrete
Where the documents referenced are undated the latest edition of the referenced document (including any amendments) shall apply. Where
references are dated only the edition cited shall apply.
A2.1.3 GENERAL
For the purposes of Clause A2.1.3 the definition of Services under Clause A2.1.2 shall be deemed to include any pipes, culverts or other
infrastructure provided for surface or subsurface drainage purposes.
A2.1.3.3 Safety, Method Statements, safeguarding the works and accommodation of traffic
a) Safety and Method Statements
All installation of services work shall comply with the health and safety requirements of Clause A1.2.3.6 of Chapter 1 and as specified in the
Contract Documentation.
The Contractor shall prepare and submit to the Engineer for review and approval as required, the Method Statements required in terms of the
relevant health and safety legislation, the specification or the Contract Documentation. Construction Method Statements shall include, but not be
limited to, those indicated in Table A2.1.3-1.
Table A2.1.3-1: Method Statements
Section / Clause Activity to be Covered by Method Statement
A2.1.3.1 Installation of all new services
A2.1.3.2b) Location of existing services
A2.1.3.2d) Protection of services
A2.1.3.4 Protection of existing road carriageways, footways, verges and other infrastructure
A2.1.3.4 Protection of existing road carriageways, footways, verges and other infrastructure
Before construction equipment for services related work is allowed onto surfaced road carriageways or paved footways or verges, the Contractor
shall submit, for acceptance by the Engineer, the proposals of how the Contractor intends operating construction equipment without causing
damage to any of the existing surfaces. Protection proposals may include the following:
• The use of gravel, wood, tyres, etc. as ramps where kerbs have to be negotiated;
• The use of tyres and rubber mats where crawler-tracked equipment is used;
• The placing of wooden blocks under the hydraulic stabilising arms of excavators or cranes etc.;
• The placing of wooden blocks under the tined buckets of excavating equipment when fully lowered; and
• The use of loading equipment fitted with buckets without tines to remove dumped material to a minimum of 200 mm above any paved
surface with the remaining 200 mm of material removed by means of hand work.
The Contractor shall adhere to the accepted proposals and will be held liable for repairing the damage caused by construction equipment or
activities to any surfaced roads, footways or verges or kerbing etc. and restoring them to their original condition.
Before any construction commences the Contractor shall submit, for acceptance by the Engineer, the proposals regarding how the Contractor
intends to work in the vicinity of any existing infrastructure or road furniture (such as traffic barriers, bollards, traffic lights, traffic signs, fencing,
stays and struts for poles and gantries and street lighting) without causing damage to the existing infrastructure.
A2.1.4.3 Designs
Where the Contractor is responsible for the design of the civil engineering component of any service installations which form part of the permanent
works in a road reserve, as may be specified in the Contract Documentation, such work shall be carried out by sufficiently qualified and competent
registered professional civil engineers.
Any such designs of the permanent works by the Contractor shall be submitted to the Employer for acceptance before any construction of the
designed work may commence. Although the designs will be evaluated by the Employer or his representative, the professional liability for such
designs shall remain with the Contractor.
A2.1.5 MATERIALS
A2.1.5.1 Trench backfill material
Backfill for ducts, pipes or cables installed by methods other than by micro or mini trenching, unless otherwise specified in the Contract
Documentation, shall be a material that:
• Contains no detectable deleterious, organic or hazardous waste material.
• Can be placed without significant voids.
• In areas not subject to vehicular traffic loads has a maximum aggregate size of 100 mm and complies with the requirements for a G9
material in terms of Table A4.1.5-3 in Clause A4.1.5.6 of Chapter 4.
• In areas subject to vehicular traffic loads has a maximum aggregate size of 75 mm and complies with the requirements for a G7 or G8
material as specified in Table A4.1.5-3 in Clause A4.1.5.6 of Chapter 4.
• Can be compacted in accordance with the requirements of Clause A2.1.8.2.
A2.1.5.3 Water
The requirements of Clause A1.2.3.21 of Chapter 1 shall apply to the use of water for all services work dealt with in Chapter 2.
Water used for the compaction of any backfill, fill blanket, bedding or layer works dealt with in Chapter 2 shall comply with the requirements of
Clause A4.1.5.18 of Chapter 4. For the purposes of Clause A4.1.5.18 of Chapter 4 backfill, fill blanket and bedding material shall be deemed to
be earthworks.
Water used for mixing concrete shall comply with SANS 51008. In addition, potable water used for concrete shall comply with the requirements
of SANS 241-1 for drinking water.
A2.1.5.4 Other material requirements for dry, wet and energy services
Other material requirements for dry, wet and other services shall be as specified in Clauses A2.2.5, A2.3.5 and A2.4.5.
Where two or more pipes are to be placed in a trench the authorised width (W) shall not be less than the sum of the external diameters / widths
of the pipes plus the side allowance for each of the outer pipes plus, between each pair of adjacent pipes, the average of the side allowance for
each pipe. For the installation of more than one duct in a trench refer to Clause A2.2.7.2a).
The minimum authorised width (W) for ducts or pipes of outside diameter not exceeding 125 mm and laid to a depth not exceeding 1,5 m may be
less than 400 mm for flexible continuous ducts or pipes that, in terms of the specification, do not require bedding or jointing and provided that the
backfilling can be compacted in accordance with the requirements of Clause A2.1.8.2.
Where ducts or pipes are to be encased in concrete or soil cement the trench width shall be determined either by the width of the encasement, or
as indicated in the Contract Documentation or as instructed by the Engineer.
The Contractor may slope the trench sides or bench the trench from a point above the top of a duct or pipe in compliance with the relevant safety
regulations and obligations at his own cost.
The depth of excavations shall be as specified in the Contract Documentation or as indicated by the Engineer on site. Trenches for water pipes
shall, unless otherwise specified, be excavated at a constant depth to follow the general surface contours wherever possible.
Trenches shall be neatly trimmed to line and level. The Contractor shall maintain the correct line and grade throughout the work. Trenches shall
be straight along the centre line and between pegs, where applicable. Between pegs the trench bottom shall be carefully graded and tested by
sight rails and boning rods or other means.
Trenches shall, except where otherwise indicated or permitted, or in the case of a statutory safety requirement, be excavated with vertical sides
without any undercutting of the sides.
The cost of trimming excavations by hand or machine shall not be paid for separately but shall be included in the rates tendered for excavation.
Should the Contractor for any reason whatsoever excavate beyond the limits of the authorised dimensions, the Contractor shall, at his own cost,
carry out the additional backfilling that will be required as a result of such excess excavation, and he shall use the same material that has been
used for the rest of the trench at the level in question. Where the trench has been excavated deeper than the required depth, the bottom shall be
reinstated to the correct level as specified for the applicable service.
i) Classes of excavation
Where mechanical excavation equipment is used the excavation of material in trenches shall be classified as follows:
(i) Hard Excavation
Hard excavation shall be excavation of material which will require breaking up before removal by one of or a combination of the
following:
• An excavator fitted with a hydraulic percussion hammer or fitted with a ripper,
• Hand operated pneumatic or electro mechanical equipment such as jackhammers or pavement breakers,
• Drilling and using non-explosive rock-breaking products such as injecting chemical expansion agents, or
• Drilling and blasting.
Excavation of individual large boulders, core stones and lumps of hard material in excess of 20 m3 shall also be classified as hard
excavation.
Any material where boulders, each exceeding 0,1 m3 in size, make up more than 40 % of the volume of the material will be classified
as hard material.
(ii) Stabilised Layers
All material which has been stabilised with any stabilising agent and requires careful cutting and excavation without damage to
surrounding existing road layers, by whatever method, shall be classified as stabilised material.
(iii) Soft Excavation
All material not classified as hard or boulder material or stabilised material shall be classified as soft material.
j) Excavation using Labour Enhanced Construction Methods
Where the planned use of mechanical excavating equipment is likely to cause damage to services, trees or property, the Contractor shall advise
the Engineer thereof, who may then instruct, in writing, that the excavations be made by means of labour enhanced construction methods and
paid under the relevant items for such excavation. However, no such instruction or payment will be required or applicable where the planned or
A2.1.8 WORKMANSHIP
The requirements of Clause A1.2.8 of Chapter 1 shall apply to the process and acceptance quality control for all services work dealt with in Section
A2.1.
The Engineer may, at his discretion, elect to use some of the Contractor’s process control test results if the Engineer is satisfied that the
Contractor’s process control requirements are acceptable for acceptance quality control purposes.
The requirements of Clause A1.2.3.14 of Chapter 1 shall apply to any remedial work required where any work or material does not comply with
the specified requirements.
The requirements of Clause A12.7.8.1 of Chapter 12 shall apply to the testing of any services installed using trenchless methods.
A2.1.8.2 Compaction
The method to be used for backfill and trench bottom compaction acceptance quality control shall be either relative density compaction control or
DCP compaction control as indicated below. If it is not clear which method is applicable to a particular situation, due to the conditions or
circumstances on site or due to any discrepancy in relevant information, relative density compaction control shall apply.
a) Relative density compaction control
Relative density compaction acceptance quality control shall be used for all areas except where DCP control is permitted as indicated in Clause
A2.1.8.2c). Relative density compaction control shall, in particular, be used under any road carriageways or lined drains or under any paved
footways, sidewalks or walkways or under any other area indicated in the Contract Documentation. Relative density compaction control shall be
used for trenches in embankments, fills or cut slopes unless DCP control is permitted in the Contract Documentation or as agreed by the Engineer.
(i) Areas not subjected to vehicle traffic loads
In areas not subjected to vehicle traffic loads (deemed to only include the unpaved verge of a road reserve) trenches and trench
bottoms shall be backfilled in layers of thickness (after compaction) that do not exceed 150 mm and the material shall be compacted
to a minimum of 90 % of MDD or a minimum of 100 % of MDD where sand (as defined for fill in Clause A4.1.5.9 of Chapter 4) is
used. The compacted material shall comply with the acceptance requirements indicated in Clause A2.1.8.2b).
(ii) Areas subjected to vehicle traffic loads or within the road prism
In areas subjected to vehicle traffic loads (deemed to include any road carriageways, lined drains or any paved footways, sidewalks
or walkways or any other areas indicated in the Contract Documentation) or within the road prism (deemed to include any fill or
embankment or any other areas indicated in the Contract Documentation) or on cut slopes, trenches and trench bottoms shall be
backfilled in layers of thickness (after compaction) that do not exceed 150 mm and the material shall be compacted to a minimum
of 93 % of MDD or a minimum of 100 % of MDD where sand (as defined for fill in Clause A4.1.5.9 of Chapter 4) is used. The
compacted material shall comply with the acceptance requirements indicated in Clause A2.1.8.2b).
(iii) Compacted layer thickness
Where the minimum specified degree of compaction cannot be achieved using pedestrian type (walk-behind) rollers or other hand
operated compactors (tampers) the thickness of the layer compacted shall be reduced to achieve the required densities.
b) Compaction and moisture content tolerances
The compaction and moisture content tolerances for backfill shall comply with the requirements of Clause 5.2.2.2 of SANS 2001-DP1.
c) DCP compaction control
DCP compaction acceptance quality control shall only be used for trenches in the unpaved verge of a road reserve.
Where compaction control testing for backfill and trench bottoms is done using a Dynamic Cone Penetrometer (DCP) the following requirements
shall apply:
The above DCP acceptance criteria may not be used in the following situations:
• In dolomitic areas where the criteria will be as specified in the Contract Documentation.
• At fills, embankments or cut slopes where the criteria will be provided in the Contract Documentation or as confirmed by the Engineer
if DCP control is permitted.
• In marshy conditions where the in situ soil has a DCP penetration rate above 50 mm per blow and where backfilling material type and
density shall be as specified in the Contract Documentation or as confirmed by the Engineer.
Relative Density
(% of MDD) SANS 3001-GR35 50 m3 or a minimum of 3
tests per day All
(sand replacement)
or
SANS 3001-NG5
(Nuclear)
*1 Only when instructed by the Engineer.
The statistical principles in Chapter 20 are not applicable to this Clause.
CONTENTS
B2.1.1 SCOPE
B2.1.2 DEFINITIONS
B2.1.3 GENERAL
B2.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B2.1.5 MATERIALS
B2.1.6 CONSTRUCTION EQUIPMENT
B2.1.7 EXECUTION OF THE WORKS
B2.1.8 WORKMANSHIP
B2.1.1 SCOPE
Part B covers the scope for labour enhanced construction associated with the installation of services in a road reserve. Traditionally the installation
of services offers a relative high labour component especially if trenching is done by hand.
Typical activities which can be performed using labour enhanced techniques are clearing and grubbing, removal of surfacing and paving materials
on the trench line, excavation, digging of pilot holes, preparing the bottom of the trench, duct or pipe installation, preparation of backfilling material
and trench backfilling.
Labour enhanced construction methods shall only be used where specified in the Contract Documentation or as ordered by the Engineer.
B2.1.2 DEFINITIONS
Definitions as provided in A2.1.2 shall also apply.
B2.1.3 GENERAL
Any activity specified in Part A where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B2.1.5 MATERIALS
The provisions of Part A shall apply.
Material which can be excavated by means of a suitable shovel with or without the use of a pick or other
Soft
hand-swung tool.
Material which is difficult to excavate by hand even with the aid of a crowbar and requires the assistance of
Intermediate
pneumatic tools for economic removal.
B2.1.8 WORKMANSHIP
The provisions of Part A shall apply.
C2.1.1.2 Permanent services relocation or protection work by others prime cost (PC) sum
C2.1.1.3 Handling costs and profit in respect of item C2.1.1.2 above percentage (%)
C2.1.1.4 Permanent services relocation or protection work by the Contractor provisional sum
The lump sum tendered under item C2.1.1.1 shall be in full compensation for all the Contractor’s obligations under Clauses A2.1.3.2, A2.1.3.3a),
A2.1.3.3b) and A2.1.3.5 for the location, identification and protection of existing services and for safety and safeguarding and the programming
for services.
The prime-cost item C2.1.1.2 shall be paid for work done by others in accordance with the provisions of the conditions of contract for work ordered
or agreed by the Engineer. The tendered percentage for item C2.1.1.3 is a percentage of the amount actually spent under the prime-cost item,
which shall include full compensation for the handling, supervision and liability costs of the Contractor and the profit in connection with providing
the specified service.
The provisional sum under item C2.1.1.4 shall be paid for work done by the Contractor accordance with the provisions of the conditions of contract
for work ordered or agreed by the Engineer.
C2.1.2.1 Using specialist detection services (ground penetrating radar, radio detection etc.) prime cost (PC) sum
C2.1.2.2 Handling costs and profit in respect of item C2.1.2.1 above percentage (%)
C2.1.2.3 Survey to verify existing service positions prime cost (PC) sum
C2.1.2.4 Handling costs and profit in respect of item C2.1.2.3 above percentage (%)
C2.1.2.5 Using hand excavation to locate, expose and verify services cubic metre (m3)
The prime-cost item C2.1.2.1 will cover the costs of any specialist detection services used to locate, detect and verify existing services. The use
of any specialist detection service providers shall be approved by the Engineer prior to their appointment.
The prime-cost item C2.1.2.3 will cover the costs of any survey services used to determine, fix and record the positions of an existing service after
it has been located. The use of any survey service providers shall be approved by the Engineer prior to their appointment.
The prime-cost items C2.1.2.1 and C2.1.2.3 shall be paid for in accordance with the provisions of the conditions of contract. The tendered
percentage for items C2.1.2.2 and C2.1.2.4 shall be a percentage of the amount actually spent under the prime-cost item, which shall include full
compensation for the handling, supervision and liability costs of the Contractor and the profit in connection with providing the specified service.
The unit of measurement for item C2.1.2.5 shall be a cubic metre of material excavated within the lengths and widths authorised by the Engineer
and the depth required to expose the service. Excavation in excess of the authorised dimensions shall not be measured for payment.
The tendered rate for item C2.1.2.5 shall include full compensation for all excavation, backfilling, compacting to 90 % of MDD, disposing of any
surplus excavated material, keeping the excavations safe, dealing with any surface or subsurface water, taking special care to ensure that services
are not damaged in any way and any other operation necessary for completing the work. The tendered rate shall also include the transporting of
surplus excavated material for a haul distance of 1,0 km. Any damage to a service caused by the Contractor’s negligence shall be repaired at his
own cost, to the satisfaction of the owner of the service and the Engineer. No distinction will be made between the classes of material, neither
will distinction be made between the various types of services to be exposed or the depths to which excavations are taken.
C2.1.4.2 Handling costs and profit in respect of item C2.1.4.1 above percentage (%)
The prime-cost item C2.1.4.1 shall be for any deposits or for the costs of any guarantees required by any service owners or other authorities
before any work is permitted in the vicinity of their services etc. and the item shall be paid for in accordance with the provisions of the conditions
of contract. Payment under this item will be made when deposits or guarantee payments have been made by the Contractor and acceptable proof
of such deposits or payments have been provided to the Engineer. No interest will be paid to the Contractor on these amounts. Where any
deposits or guarantee amounts are returned to the Contractor payment under this item will be reversed accordingly. The tendered percentage for
item C2.1.4.2 is a percentage of the amount actually spent under the prime-cost item, which shall include full compensation for the handling,
supervision and liability costs of the Contractor and the profit in connection with providing the specified service. Payment under item C2.1.4.2 will
not be reversed when any deposits or guarantee payments are returned.
(c) Over 2,0 m deep etc. to be inserted, increased by additional 1,0 m depths as required cubic metre (m3)
(c) Over 2,0 m deep etc., increased by additional 1,0 m depths as required cubic metre (m3)
Trenches over 2,0 m wide and up to 3,0 m etc., increased by additional 1,0 m widths as
C2.1.6.3
required
(a) Up to 1,0 m deep cubic metre (m3)
(c) Over 2,0 m deep etc., increased by additional 1,0 m depths as required cubic metre (m3)
The unit of measurement shall be the cubic metre of material excavated as if in soft material, classified according to the various width and depth
ranges listed. The depth classification shall be in accordance with the total depth of the trench for each length of trench excavated and not in
accordance with the depth range in which material is situated before excavation i.e. for a section of trench which is up to 1,0 m wide and 1,3 m
deep the total volume of excavation will be measured under pay item C2.1.6.1(b). For measurement purposes the width of a trench shall be
determined from the authorised dimensions and the depth of excavation shall be measured to the underside of the bedding, except where no
bedding is required, in which case it shall be measured to the underside of the duct or pipe.
The tendered rates shall include full compensation for setting out, clearing and grubbing the trench areas except for trees with a girth larger than
1,0 m, the temporary removal of improvements from the line of the trench, the removal and stacking of any surfacing and paving material as
applicable, for excavating the trench, preparing the bottom of the trench, separating topsoil, material unsuitable for backfill and selected backfill
material, for safeguarding and keeping the excavations safe, which includes the provision, installation and later removal of temporary timbering,
shoring and strutting, dealing with any surface or subsurface water and for the temporary stockpiling of material unless otherwise specified in the
Contract Documentation. The tendered rates shall include full compensation for trimming trench excavations by hand or by using mechanical
equipment and for hauling material within a haul limit of 1,0 km. Excavations in bolsters i.e. tunnels less than 3,0 m in length will be measured
and paid for as trench excavations. Where saw-cutting of the excavation edge is required and/or ordered prior to excavation it will be measured
and paid under the relevant items.
C2.1.7 Extra over items C2.1.6, C2.1.8 and C2.1.16 for excavating in:
C2.1.8 Excavations outside the normal trench profile cubic metre (m3)
The unit of measurement shall be the cubic metre of material excavated, if necessary, using excavating equipment or by hand outside the normal
trench profile as specified in Clause A2.1.7.1k).
The tendered rate shall include full compensation for excavating outside the normal trench profile, trimming the excavations, preparing the bottom
of the excavation, separating any material unsuitable for backfill from selected backfill material, keeping excavations safe, dealing with any surface
or subsurface water and for the temporary stockpiling of material unless otherwise specified in the Contract Documentation.
C2.1.9.2 Trenches over 1,0 m and up to 2,0 m wide (in soft material)
C2.1.9.4 Trenches over 1,0 m and up to 2,0 m wide (in intermediate material)
(e) From commercial sources (state material type) cubic metre (m3)
C2.1.11.2 Backfill compacted to 90 % (100 % for sand) of MDD or complying with the DCP
requirements of Clause A2.1.8.2c) (areas not subject to traffic loads) using material:
(a) From the excavated trench material cubic metre (m3)
(e) From commercial sources (state material type) cubic metre (m3)
The unit of measurement for items C2.1.11.1 and C2.1.11.2 shall be the cubic metre of backfill material in place after compaction calculated from
the specified or authorised trench excavation dimensions and placed above the fill blanket or bedding, as applicable. Backfill required for trenches
excavated outside the specified or authorised dimensions will not be measured unless such excavation is authorised and measured under item
C2.1.8.
The tendered rates shall be in full compensation for the backfilling of trenches including placing the material in the trench, watering and compacting
the backfill to the specified minimum density using relative density or DCP compaction control as applicable.
The tendered rates for items C2.1.11.1(b), C2.1.11.1(c), C2.1.11.2(b) and C2.1.11.2(c) shall include full compensation for the additional cost of
excavation in all materials, for loading the material from an excavation on site or from a borrow pit, for hauling the material within a haul limit of
1,0 km and for unloading the material for placement. The tendered rate for items C2.1.11.1(c) and C2.1.11.2(c) shall include full compensation
for all operations at borrow pits not subject to any specified separate pay item.
The tendered rates for items C2.1.11.1(d), 2.1.11.1(e), C2.1.11.2(d) and C2.1.11.2(e) shall include full compensation for the payment of any
royalties or charges for procuring and furnishing the material from sources provided by the Contractor or from commercial sources as well as for
transporting the material over an unlimited haul distance.
C2.1.13 Extra over item C2.1.11 for backfilling with soil cement or stabilised material
C2.1.13.1 Backfilling trenches using soil cement using (state type of material i.e. G5, G7 or G8) cubic metre (m3)
material
C2.1.13.2 Backfilling trenches using stabilised (state type of material i.e. G5, G7 or G8) material cubic metre (m3)
compacted to 93 % of MDD
C2.1.13.3 Backfilling around poles using stabilised (state type of material i.e. G5, G7 or G8) material cubic metre (m3)
compacted to 95 % of MDD
C2.1.14 Extra over items C2.1.11, C2.1.12 and C2.1.13 for additional compaction of backfill
C2.1.18.2 Timbering, strutting and shoring opposite a structure or service (state reference in Contract metre (m)
Documentation or indicate drawing number etc.)
Item C2.1.18.1 will only be applicable, as indicated in Clause A2.1.7.1l)(ii), where the Engineer instructs that timbering, strutting and shoring be
permanently left in place in excavations. The unit of measurement for item C2.1.18.1 shall be the square metre of tunnel wall or roof or trench
wall against which timbering and shoring is required to be left in position permanently on the Engineer's instructions. Each side of the trench or
tunnel shall be measured.
Item C2.1.18.2 will only be applicable, as indicated in Clause A2.1.7.1l)(ii), where separate payment for timbering and shoring is indicated and
described in the Contract Documentation. The unit of measurement for item C2.1.18.2 shall be the metre of trench shored opposite a structure
or service as agreed by the Engineer. The length measured for payment will be that of the centre-line of the trench regardless of whether supports
are placed on one or on both sides of the trench.
The tendered rate for item C2.1.18.1 shall include full compensation for leaving the timbering and shoring permanently in position, for ensuring
that the timbering and shoring will not be disturbed during backfilling, and that the backfilling is compacted fully around the shoring.
The tendered rate for item C2.1.18.2 shall include full compensation for the cost, for both sides of the trench if necessary, of the supply, placing,
maintenance and removal of timbering and other support measures together with any cost that results from the inconvenience of working in the
supported trench and the cost of any risks inherent in the operation.
C2.1.21.1 Biodegradable bags (state bag size, material type and description) number of bags (No)
C2.1.21.2 Geofabric bags (state bag size, material type and description) number of bags (No)
The unit of measurement shall be the number of bags filled with soil installed in accordance with the Clause A2.1.7.1n). The tendered rates shall
include full compensation for supplying the bags and suitable material to fill the bags, filling of the bags with soil and placing the bags as required
and shall also include all associated transport costs. The tendered rates shall include full compensation for removing the bags when no longer
required.
(a) State type and size of each intersecting service number (No)
(b) State type and size of each intersecting service number (No)
(c) State type and size of each intersecting service etc. number (No)
Services that adjoin a trench (parallel to or at an angle between
C2.1.22.2
centre-lines in plan of less than 45 o)
(a) State type and size of each adjoining service metre (m)
(b) State type and size of each adjoining service metre (m)
(c) State type and size of each adjoining service etc. metre (m)
The unit of measurement for item C2.1.22.1 shall be the number of underground services intersected by the trench excavated. Existing water
pipes, sewers, stormwater pipes, concrete-lined channels and drains, box culverts, electric or other telecommunication cables, ducts, kerbs,
channels, erf connections and various sizes of pipes and services that intersect a trench of specified width and require various degrees of care,
whether or not their presence was known before they were uncovered, will be measured separately. The unit refers to one service, but services
that are so grouped that they can be contained within a horizontal dimension of 300 mm measured at right angles to the axis of the services will
be measured as one unit.
The unit of measurement for item C2.1.22.2 shall be the metre of trench excavated where there are adjoining services. In a case where a trench
of specified width:
• Runs parallel to or at an angle (in plan) of less than 45 o to an existing service, and
• Is such that the nearer side of the bottom of the trench lies at least partly between a vertical plane and a plane that lies at an angle of
45 o below the horizontal, both planes passing through the axis of the service,
the length of service within the minimum base width of the trench, determined in accordance with Clause A2.1.7.1h), will be measured for payment
under this item and the remaining length, the side of the trench which, as agreed by the Engineer, is rendered liable to collapse because of the
existence of such service, will be measured for shoring.
The tendered rates for items C2.1.22.1 and C2.1.22.2 shall include full compensation for the additional cost of:
• Care in excavation necessitated by the presence of services adjacent to, in or across a trench;
• Protecting and maintaining such services in operation by means of temporary supports or shoring, as necessary;
• Delays and disruption of the progress of the work due to the existence of the services; and
• Repairs necessitated by damage caused by the Contractor.
Item C2.1.22 shall not be applicable where any services are to be removed and where payment will therefore be made under item C1.2.25.
C2.1.23.3 Stabilised subbase material (state material type and source e.g. C3 or C4, cubic metre (m3)
commercial/borrow pit etc. and layer thickness) using (state percentage and type of
stabilising agent) compacted to (state minimum compaction) % of MDD
C2.1.23.4 Base material (state material type and source e.g. G1 or G2, commercial/quarry etc. and cubic metre (m3)
layer thickness) compacted to (state minimum compaction either 102 % for G2 or 104 % for
G1) % of MDD
C2.1.23.6 Tack coat (state type of material and application rate) square metre (m2)
C2.1.23.7 Asphalt material (state asphalt type e.g. continuously graded, binder type, layer thickness ton (t)
and minimum density)
C2.1.23.8 Surface treatments (state surfacing type, binder type and application rate, aggregate size square metre (m2)
and application rate etc.)
The unit of measurement for items C2.1.23.1, C2.1.23.2, C2.1.23.3 and C2.1.23.4 shall be the cubic metre of compacted pavement layer
constructed during the reinstatement of existing surfaced roads. The unit of measurement for items C2.1.23.5 and C2.1.23.6 shall be the square
metre of prime or tack coat placed during the reinstatement of existing surfaced roads. The unit of measurement for item C2.1.23.7 shall be the
ton of compacted asphalt and the unit of measurement for item C2.1.23.8 shall be the square metre of surface treatment both placed during the
reinstatement of existing surfaced roads. Items C2.1.23.1 to C2.1.23.8 will be measured in accordance with the authorised dimensions for the
reinstatement area required. Any reinstatement required beyond the agreed or instructed dimensions owing to damage caused by the Contractor
will not be measured for payment.
The tendered rates shall include full compensation for procuring, furnishing, placing, compacting and finishing all the materials including stabilising
the layers as may be required and including full compensation for providing all labour and construction equipment, preparing the edges of the
existing surfacing and protecting and maintaining the completed reinstatement as specified. The tendered rate shall also include full compensation
for any temporary backfilling with excavated material and for compacting, maintaining and later removing the temporary material as specified in
Clause A2.1.7.2b).
Where the materials are supplied from sources provided by the Contractor or from commercial sources the tendered rates shall include full
compensation for the payment of any royalties or charges for procuring the material from sources provided by the Contractor or from commercial
sources as well as for transporting the material over an unlimited haul distance. Where the materials are sourced from borrow pits or quarries
provided by the Employer or other sources on site the tendered rates shall include full compensation for hauling the materials within the haul limit
of 1,0 km, for unloading the material for placement and for all operations at borrow pits or quarries not subject to any specified separate pay item.
The backfill of the trench up to the bottom of the layers measured under item C2.1.23 will be paid for under items C2.1.11, C2.1.12, C2.1.13 and
C2.1.14 as applicable.
(c) Exceeding 100 mm but not exceeding 150 mm square metre (m2)
(c) Exceeding 100 mm but not exceeding 150 mm square metre (m2)
(c) Exceeding 100 mm but not exceeding 150 mm square metre (m2)
The unit of measurement shall be the square metre of cut area, saw-cut before excavation in accordance with Clause A2.1.7.1d), calculated in
accordance with the authorised length of cut and the average depth measured after excavation of the material.
The tendered rates for item C2.1.24 shall include full compensation for all construction equipment, tools, labour, supervision, materials, transport
and for all incidentals for cutting the asphalt, concrete or other materials complete as specified and also for work in restricted areas.
C2.1.25.1 State type and size of each service (duct, pipe or cable) removed metre (m)
C2.1.25.2 State type and size of each service (duct, pipe or cable) removed metre (m)
C2.1.26.1 State type and size of each service (duct, pipe or cable) disposed of metre (m)
C2.1.26.2 State type and size of each service (duct, pipe or cable) disposed of metre (m)
CONTENTS
D2.1.1 SCOPE
D2.1.2 GENERAL
D2.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D2.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D2.1.5 VISUALLY ASSESSED PROPERTIES
D2.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D2.1.7 EVALUATION FOR ACCEPTANCE
D2.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D2.1.9 NOTIFICATION OF REMEDIAL WORK
D2.1.10 REMEDIAL WORKS
D2.1.1 SCOPE
D2.1.1.1 Proprietary products and materials
The Contractor shall provide detailed specifications and certificates from independent agencies for all proprietary materials that are proposed for
use. These certificates shall demonstrate conformance with the performance requirements stipulated in these standard specifications or in the
Contract Documentation.
Unless otherwise specified all proprietary products and materials shall be used strictly in accordance with the relevant manufacturer’s or supplier’s
current published instructions or requirements for the specified product.
Agrément certified products shall be used and placed in accordance with their Agrément certification criteria.
CONTENTS
PART A: SPECIFICATIONS
A2.2.1 SCOPE
A2.2.2 DEFINITIONS
A2.2.3 GENERAL
A2.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A2.2.5 MATERIALS
A2.2.6 CONSTRUCTION EQUIPMENT
A2.2.7 EXECUTION OF THE WORKS
A2.2.8 WORKMANSHIP
SANS 1936-1 Development of dolomite land Part 1: General principles and requirements
SANS 1936-3 Development of dolomite land Part 3: Design and construction of buildings, structures and
infrastructure
SANS 2001-DP1 Earthworks for buried pipelines and prefabricated culverts
EN 124-2 Gully tops and manhole tops for vehicular and pedestrian areas Part 2: Gully tops and manhole
tops made of cast iron
EN 124-3 Gully tops and manhole tops for vehicular and pedestrian areas Part 3: Gully tops and manhole
tops made of steel or aluminium
EN 124-4 Gully tops and manhole tops for vehicular and pedestrian areas Part 4: Gully tops and manhole
tops made of steel reinforced concrete
EN 124-5 Gully tops and manhole tops for vehicular and pedestrian areas Part 5: Gully tops and manhole
tops made of composite materials
EN 124-6 Gully tops and manhole tops for vehicular and pedestrian areas Part 6: Gully tops and manhole
tops made of polypropylene (PP), polyethylene (PE) or unplasticised poly (vinyl chloride) (U-
PVC)
Where the documents referenced are undated the latest edition of the referenced document (including any amendments) shall apply. Where
references are dated only the edition cited shall apply.
A2.2.2 DEFINITIONS
The following definitions shall apply to these specifications:
Fibre Optic Telecommunication - fibre optic communication is a method of transmitting information from one place to another by sending pulses
of light through an optical fibre. The light forms an electromagnetic carrier wave that is modulated to carry information.
Handhole - a shallow form of manhole giving access to ducts in an underground cable (normally communications) system.
Micro Trenching – a trench (slot), with a width up to but not exceeding 40 mm, providing at least 300 mm cover over the upper most duct in a
duct bank, cut into a road or footway.
Mini Trenching - a trench (slot), with a width greater than 40 mm but not exceeding 100 mm, providing at least 300 mm cover over the upper
most duct in a duct bank, cut into a road or footway.
A2.2.3 GENERAL
A2.2.3.1 Location, identification, protection and relocation of existing services
The location, identification, protection and relocation of existing services, unknown or unrecorded services shall be managed in accordance with
Clause A2.1.3.2.
A2.2.5 MATERIALS
The type of duct to be installed shall be as specified in the Contract Documentation. All ducts shall be joined with watertight couplings made from
the same material as the duct.
Unless indicated otherwise in the Contract Documentation ducts shall comply with the following requirements:
A2.2.5.2 Bedding
Bedding for ducts, installed by methods other than by micro or mini trenching, unless otherwise specified in the Contract Documentation, shall be
material of a granular, non-cohesive nature that is free draining, has a maximum aggregate size of 15 mm, a maximum plasticity index (PI) of 6
and has a compaction fraction, determined in accordance with Clause 5.1.4 of SANS 2001-DP1, that does not exceed 0.2.
A2.2.5.3 Backfill
a) Backfill for trenches (excluding micro or mini trenching)
Backfill for ducts installed by methods other than by micro or mini trenching, unless otherwise specified in the Contract Documentation, shall
comply with the requirements of Clause A2.1.5.1.
b) Backfill for micro or mini trenching
Where micro or mini trenching is dealt with in terms of Clause A2.2.7.6 the materials used for bedding, backfilling and reinstatement shall be in
accordance with the details provided in the Contract Documentation.
A2.2.5.5 Concrete
All concrete required for duct installation shall comply with the applicable requirements of Section A13.4 of Chapter 13 for strength class (Class
C) concrete as specified in the Contract Documentation.
Where applicable different colours shall be used to mark service types. As applicable the colours used shall be in accordance with SANS 10140-
3.
b) Route markers
Where duct route markers are required they shall be installed in accordance with the requirements of the Contract Documentation.
c) Road crossing markers
Where, in accordance with the Contract Documentation, duct or other service crossings have to be marked on kerbs, the position and type of the
ducts or group of ducts crossing shall be marked on the kerbs by cutting the letters, as indicated in Clause A2.2.7.4a), as 75 mm high 35 mm wide
letters 5,0 mm deep into the concrete surface with an angle grinder followed by a number indicating the number of ducts or services at the crossing.
Kerbs where the lettering or symbols have been precast into the kerb face may also be used. The symbol or lettering shall be painted the
applicable colour indicated in Clause A2.2.7.4a).
Where duct crossings cannot be marked on kerbs, markers shall be placed as specified in the Contract Documentation or as ordered by the
Engineer.
A2.2.8 WORKMANSHIP
The requirements of Clause A1.2.8 of Chapter 1 shall apply to the process and acceptance quality control for all services work dealt with in
Section A2.2.
The Engineer may, at his discretion, elect to use some of the Contractor’s process control test results if the Engineer is satisfied that the
Contractor’s process control requirements are acceptable for acceptance quality control purposes.
The requirements of Clause A1.2.3.14 of Chapter 1 shall apply to any remedial work required where any work or material does not comply with
the specified requirements.
The requirements of Section A12.7 of Chapter 12 shall apply to any ducts installed using trenchless methods.
A2.2.8.1 Tolerances
The installation of ducts installed using trenching (excluding micro or mini trenching) shall comply with the requirements stated below:
a) Horizontal alignment
The maximum deviation of the centre line from the specified position shall be ± 35 mm. Successive deviations from the specified position shall
be in the same direction to avoid creating s-bends. The maximum deviation of the centre line from the specified alignment shall be 1:250 when
taken over any section exceeding 10 m in length.
b) Vertical alignment, grade and level
The maximum deviation from the specified level shall be ± 35 mm.
The maximum deviation of the vertical alignment and grade from the specified alignment, or from the line between duct inverts at successive
manholes or access chambers, as applicable, shall be 1:250 when measured over any section exceeding 10 m length, and all such deviations
shall be gradual. Reverse falls are unacceptable.
c) Compaction and moisture content tolerances
The compaction and moisture content tolerances for bedding shall comply with the requirements of Clause 5.2.2 of SANS 2001-DP3.
CONTENTS
B2.2.1 SCOPE
B2.2.2 DEFINITIONS
B2.2.3 GENERAL
B2.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B2.2.5 MATERIALS
B2.2.6 CONSTRUCTION EQUIPMENT
B2.2.7 EXECUTION OF THE WORKS
B2.2.8 WORKMANSHIP
B2.2.1 SCOPE
Apart from the scope for labour enhancement as described under Section B2.1 no additional scope for labour enhancement is defined under
Section B2.2 for Dry Services.
B2.2.2 DEFINITIONS
Definitions as provided in A2.2.2 apply.
B2.2.3 GENERAL
Any activity specified in Part A where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B2.2.5 MATERIALS
The provisions of Part A shall apply.
B2.2.8 WORKMANSHIP
The provisions of Part A shall apply.
C2.2.1.2 State for each duct the material type, class, joint type etc.
The unit of measurement shall be the metre of duct supplied and laid.
The tendered rates shall include full compensation for procuring, furnishing and laying and jointing the ducts excluding end plugs and draw wires
as well as for proving the duct as specified, but excluding excavation, bedding, backfilling and encasing which shall be measured and paid for
under the relevant items.
C2.2.2 Extra over item C2.2.1 for the provision of split ducts
C2.2.2.1 State for each duct the material type, class, etc.
C2.2.2.2 State for each duct the material type, class etc.
The unit of measurement shall be the metre of split duct installed and laid.
The unit of measurement shall be full compensation for all the additional costs associated with the provision and installation of split ducts including
any cutting and binding required.
C2.2.4 Bedding for ducts compacted to 90 % of MDD (100 % for sand) using material:
C2.2.4.1 Selected from the excavated trench material cubic metre (m3)
C2.2.4.4 Selected from sources provided by the Contractor cubic metre (m3)
(b) Crushed stone material (state material type) cubic metre (m3)
C2.2.4.6 Extra over items C2.2.4.1 to C2.2.4.5 for stabilising material with cement cubic metre (m3)
C2.2.4.7 Cement (state class/type of cement) for stabilising bedding kilogram (kg)
The unit of measurement for items C2.2.4.1 to C2.2.4.5 shall be the cubic metre of bedding material in place after compaction and the quantity
shall be calculated from the specified dimensions of the bedding and backfilling as specified or authorised by the Engineer. The volume occupied
by the ducts shall be subtracted when calculating the volume of bedding.
The unit of measurement for item C2.2.4.6 shall be the cubic metre of bedding material stabilised with cement in place after compaction and the
unit of measurement for item C2.2.4.7 shall be the kilogram of cement used to stabilise the bedding.
The tendered rates for items C2.2.4.1 to C2.2.4.5 shall include full compensation for procuring, furnishing and placing the bedding material under,
alongside and over ducts and for watering and compacting the bedding material to the specified minimum density. The tendered rates for items
C2.2.4.2 and C2.2.4.3 shall include full compensation for the additional cost of excavation in all materials, for loading the material from an
excavation on site or from a borrow pit, for hauling the material within the haul limit of 1,0 km and for unloading the material for placement. The
tendered rate for item C2.2.4.3 shall include full compensation for all operations at borrow pits not subject to any specified separate pay items.
The tendered rates for items C2.2.4.4 and C2.2.4.5 shall include full compensation for the payment of any royalties or charges for procuring and
furnishing the material from sources provided by the Contractor or from commercial sources as well as for transporting the material over an
unlimited haul distance.
The tendered rate for item C2.2.4.6 shall include full compensation for mixing the material with the cement where applicable. The tendered rate
for item C2.2.4.7 shall include full compensation for supplying the cement required for stabilising bedding.
C2.2.5.2 Concrete encasement of ducts (state class of concrete) cubic metre (m3)
The unit of measurement shall be the cubic metre of concrete placed and the quantity shall be calculated from the dimensions of the excavation
as shown on the drawings or as specified or authorised by the Engineer, irrespective of whether the actual excavation exceeds the specified or
authorised dimensions, minus the volume occupied by the ducts.
The tendered rate shall include full compensation for procuring, furnishing and placing all the materials, formwork and pedestals and for all the
labour and construction equipment necessary to complete the work as specified.
C2.2.6 Duct accessories (markers, marking, draw wires and end caps etc.)
(a) State depth range (example over 1,0 m and up to 1,5 m deep) number (No)
(b) State depth range (example over 1,5 m and up to 2,0 m deep) number (No)
(a) State type, depth range and drawing reference etc. number (No)
(b) State type, depth range and drawing reference etc. number (No)
The unit of measurement shall be the number of handholes, manholes, access chambers or other structures completed as specified. Separate
items will be scheduled for handholes, manholes, access chambers and other structures etc. of each type and of each depth in increments of 0,5
m.
The tendered rates shall include full compensation for all the labour, construction equipment and materials required to complete the handholes,
manholes, access chambers or other structures completed as specified but excluding excavation and backfilling which shall be measured and
paid for separately under the relevant items.
The tendered rates shall exclude the provision and installation of covers and frames which shall be measured and paid for under the relevant
items.
C2.2.8 Covers and frames for duct handholes, manholes and access chambers
C2.2.8.1 State type, strength class and size of cover and frame number (No)
C2.2.8.2 State type, strength class and size of cover and frame number (No)
C2.2.8.3 State type, strength class and size of cover and frame number (No)
C2.2.9.2 State type, strength class and size of cover and frame number (No)
C2.2.9.3 State type, strength class and size of cover and frame number (No)
CONTENTS
D2.2.1 SCOPE
D2.2.2 WARRANTIES FOR PRODUCT OR ELEMENT DESIGN AND INSTALLATION OF PROPRIETARY SYSTEMS
D2.2.3 PERFORMANCE SPECIFICATIONS
D2.2.4 VISUALLY ASSESSED PROPERTIES
D2.2.5 INSTRUMENTALLY ASSESSED PROPERTIES
D2.2.6 EVALUATION FOR ACCEPTANCE
D2.2.7 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D2.2.8 NOTIFICATION OF REMEDIAL WORK
D2.2.9 REMEDIAL WORKS
D2.2.1 SCOPE
Refer to Clause D2.1.1.
CONTENTS
PART A: SPECIFICATIONS
A2.3.1 SCOPE
A2.3.2 DEFINITIONS
A2.3.3 GENERAL
A2.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A2.3.5 MATERIALS
A2.3.6 CONSTRUCTION EQUIPMENT
A2.3.7 EXECUTION OF THE WORKS
A2.3.8 WORKMANSHIP
A2.3.2 DEFINITIONS
The following definitions shall apply to these specifications:
SANS 2001 Definitions - the definitions as indicated in Clause 3 of SANS 2001-DP2, SANS 2001-DP4 and SANS 2001-DP6 shall be applicable.
Where there are any conflicts between the definitions in these SANS specifications and those provided elsewhere in Chapter 2 the latter shall
take precedence.
A2.3.5 MATERIALS
A2.3.5.1 Sewers
a) Pipes and fittings
Materials for sewer pipes and fittings (excluding rising mains) shall comply with the requirements of Clauses 4.1.1 to 4.1.11 of SANS 2001-DP4.
Materials for rising main sewer pipes and fittings shall comply with the relevant requirements of SANS 2001-DP2.
b) Manholes and chambers
Materials for sewer manholes and chambers shall comply with the requirements of Clause 4.1.12 of SANS 2001-DP4.
Precast concrete manhole sections shall comply with the requirements of SANS 1294 and shall be manufactured using dolomite aggregate. Joints
between precast manhole units shall be of the interlocking, self-centring type. Precast slabs shall comply with the requirements for heavy duty
(HD) slabs.
Step irons shall be of the copolymer polypropylene type with a 12 mm diameter high tensile steel reinforced core and shall be of a length suitable
for fixing in brick, precast concrete or reinforced fibre cement as applicable.
Covers and frames for manholes and chambers for sewers shall comply with the requirements of SANS 50124. Unless otherwise specified in the
Contract Documentation Class D 400 covers and frames shall be used.
c) Materials testing
The requirements of Clause 5.2 of SANS 2001-DP4 shall apply to the testing of sewer materials.
A2.3.5.3 Bedding, fill blanket and backfill material for sewers and water mains
a) Bedding and fill blanket
Bedding and fill blanket materials for sewers and water mains shall comply with the requirements of Clauses 4.1.1 to 4.1.4 and 4.2.3 of SANS
2001-DP1.
The class of bedding (Class A, B, C or D) applicable for each rigid or flexible pipeline shall be as specified in the Contract Documentation.
For the purposes of this Clause A2.3.5.3a) all U-PVC and HDPE pipes shall be treated as flexible pipes.
A2.3.7.2 Sewers
a) General construction and pipe laying
The construction and laying of sewers shall comply with the requirements of Clauses 4.2 and 4.3 of SANS 2001-DP4.
b) Construction of manholes and inspection chambers
Manholes and inspection chambers for sewers shall be constructed in accordance with the requirements of Clause 4.4 of SANS 2001-DP4.
c) Concrete casings
Concrete encasement of sewers shall be constructed in accordance with the requirements of Clause 4.5 of SANS 2001-DP4 and Clause 4.2.3.8
of SANS 2001-DP1.
d) Raising or lowering of existing manholes and connecting sewers
The raising or lowering of manholes and the connection of sewers shall be in accordance with the requirements of Clauses 4.6 and 4.7 of SANS
2001-DP4.
A2.3.8 WORKMANSHIP
The requirements of Clause A1.2.8 of Chapter 1 shall apply to the process and acceptance quality control for all services work dealt with in Section
A2.3.
The Engineer may, at his discretion, elect to use some of the Contractor’s process control test results if the Engineer is satisfied that the
Contractor’s process control requirements are acceptable for acceptance quality control purposes.
The requirements of Clause A1.2.3.14 of Chapter 1 shall apply to any remedial work required where any work or material does not comply with
the specified requirements.
The requirements of Section A12.7 of Chapter 12 shall apply to any sewers or water mains installed using trenchless methods.
A2.3.8.1 General
a) Compaction and moisture content tolerances
The compaction and moisture content tolerances for bedding for sewers and water mains shall comply with the requirements of Clause 5.2.2 of
SANS 2001-DP1.
A2.3.8.2 Sewers
a) Tolerances
Unless otherwise specified in the Contract Documentation the requirements of Clause 5.1 of SANS 2001-DP4 shall apply to tolerances for sewers
installed by trenching.
b) Construction tests
(i) General
Unless otherwise specified in the Contract Documentation the requirements of Clause 5.3 of SANS 2001-DP4 shall apply to the
construction tests for sewers. The Contractor shall be responsible for carrying out the specified construction tests and reporting the
results to the Engineer.
(ii) Water tightness of manholes
Where manholes are to be tested in accordance with Clause 5.3.4 of SANS 2001-DP4 the manholes shall be tested, on completion
but before backfilling, for water tightness by completely filling the manhole with water up to the underside of the manhole cover
frame after the pipes leading from manholes have been closed off for the test. The manhole shall be allowed to stand for one hour
to allow initial absorption to take place, after which the water shall be topped up if necessary. After topping up, the water level shall
not drop by more than 20 mm in one hour.
The Contractor shall be responsible for the disposal of the water used in the test by pumping or other approved means.
The Engineer reserves the right to determine whether or not each and every manhole shall be tested. Should it be decided not to
test all manholes, the Engineer will determine which of the manholes shall be tested.
(iii) Camera Inspections
Where required in the Contract Documentation sewers shall be inspected by means of a closed-circuit television camera (CCTV)
on completion of the backfill and manhole construction. The CCTV camera used shall be equipped with inclinometers so that a
pipeline profile can be produced. On completion of the inspection the Contractor shall provide the Engineer with a report in the
agreed electronic or hard format.
CONTENTS
B2.3.1 SCOPE
B2.3.2 DEFINITIONS
B2.3.3 GENERAL
B2.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B2.3.5 MATERIALS
B2.3.6 CONSTRUCTION EQUIPMENT
B2.3.7 EXECUTION OF THE WORKS
B2.3.8 WORKMANSHIP
B2.3.1 SCOPE
Apart from the scope for labour enhancement as described under Section B2.1 no additional scope for labour enhancement is defined under
section B2.3 for Wet Services.
B2.3.2 DEFINITIONS
Definitions as provided in A2.3.2 apply.
B2.3.3 GENERAL
Any activity specified in Part A where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B2.3.5 MATERIALS
The provisions of Part A shall apply.
B2.3.8 WORKMANSHIP
The provisions of Part A shall apply.
C2.3.1.1 State for each sewer the pipe material type, class, joint type and the class of bedding etc.
C2.3.1.2 State for each sewer the pipe material type, class, joint type and the class of bedding etc.
C2.3.2.1 State for each sewer special the type, class, etc.
C2.3.2.2 State for each sewer special the type, class, etc.
The unit of measurement for items C2.3.3.1 and C2.3.3.2 shall be the cubic metre of bedding or fill blanket material in place after compaction and
the quantity shall be calculated from the specified dimensions of the bedding and blanket as specified or authorised by the Engineer. The volume
occupied by the pipes shall be subtracted when calculating the volume of bedding.
The unit of measurement for item C2.3.3.3 shall be the cubic metre of bedding or blanket material screened as instructed by the Engineer and in
place after compaction. The quantity measured shall be increased by including 70 % of the loose volume, measured in stockpile, of the material
screened out and discarded.
The tendered rates shall include full compensation for procuring and furnishing the bedding or fill blanket material and placing the material
alongside and under the pipes and for watering and compacting the bedding or blanket material. The tendered rates for items C2.3.3.1(b),
C2.3.3.1(c), C2.3.3.2(b) and C2.3.3.2(c) shall include full compensation for the additional cost of excavation in all materials, for loading the material
from an excavation on site or from a borrow pit, for hauling the material within the haul limit of 1,0 km and for unloading the material for placement.
The tendered rate for items C2.3.3.1(c) and C2.3.3.2(c) shall include full compensation for all operations at borrow pits not subject to any specified
separate pay items.
The tendered rates for items C2.3.3.1(d), C2.3.3.1(e), C2.3.3.2(d) and C2.3.3.2(e) shall include full compensation for the payment of any royalties
or charges for procuring and furnishing the material from sources provided by the Contractor or from commercial sources as well as for transporting
the material over an unlimited haul distance.
The tendered rate for item C2.3.3.3 shall include full compensation for the additional handling and transport necessary, for screening the material
and for disposing of the material screened out.
Trench backfill (above the fill blanket) will be measured and paid under separate items.
C2.3.4.1 Concrete (Class A) bedding (state class of concrete) cubic metre (m3)
C2.3.5.2 Extra over item C2.3.5.1 for backdrops for manholes (state type and drawing reference etc.)
C2.3.6 Covers and frames for sewer manholes, inspection chambers and other structures
C2.3.6.1 State type, strength class and size of cover and frame number (No)
C2.3.6.2 State type, strength class and size of cover and frame number (No)
C2.3.6.3 State type, strength class and size of cover and frame number (No)
C2.3.7 Sewer accessories (anchor blocks, marker posts, plug stoppers etc.)
C2.3.7.1 Anchor blocks (state type and drawing reference) number (No)
C2.3.7.2 Anchor blocks (state type and drawing reference) cubic metre (m3)
C2.3.7.3 Marker posts (state type and drawing reference) number (No)
C2.3.8.1 Erf connections (state type, depth range and drawing reference)
C2.3.8.2 Erf connections (state type, depth range and drawing reference)
(a) State manhole type and drawing reference and height raised number (No)
(b) State manhole type and drawing reference and height raised number (No)
(a) State manhole type and drawing reference and height lowered number (No)
(b) State manhole type and drawing reference and height lowered number (No)
The unit of measurement for items C2.3.9.1 and C2.3.9.2 shall be the number of manholes raised or lowered as specified or shown on the
drawings.
The tendered rates shall include full compensation for all the labour, construction equipment and materials required to raise or lower the manholes
as specified including removing the cover and frame, demolishing the top of the manhole if required, rebuilding the manhole and setting and
grouting the cover and frame to the new level specified.
Note:
Pay items C2.3.12 to C2.3.20 have been deliberately left for use for additional contract specific sewer related pay items inserted via the
Contract Documentation.
b) Measurement and Payment Items for Water Mains (Items C2.3.21 to C2.3.36)
(i) Corrosion protection
The rates for pipes, valves, specials and couplings for items C2.3.21 to C2.3.26 shall also cover the cost of mortar lining and
sheathing, mortar encasing, wrapping and all other corrosion protection as may be specified. The rates shall also cover the costs
of all measures deemed necessary to safeguard the specified protection against any damage during transportation, stacking,
storage, installation and bedding and backfilling etc and the rates shall also cover the costs of any repairs required as a result of
any such damage.
(ii) Temporary Valves etc
Payment for the supply or loan of temporary valves, end caps, blank flanges, or other isolating devices ordered by the Engineer in
terms of Clause 5.3.1.1 of SANS 2001-DP2 will be made at daywork rates or at rates to be agreed by the Engineer, unless the
method of payment for the work has been dealt with in the Contract Documentation and a suitable special item included in the
schedule.
C2.3.22.2 State for each water main fitting or special the type, class etc.
C2.3.23 Extra over item C2.3.21 for supplying and fixing water main valves
C2.3.23.1 State for each water main valve the type, class etc.
C2.3.23.2 State for each water main valve the type, class etc.
C2.3.24.2 State for each water main the pipe material type and coupling type
C2.3.25.2 State for each water main the pipe collar and special coupling type
C2.3.26 Supplying and installing pipes, specials and valves on short pipe runs
C2.3.26.1 State for each short run water main the pipe material type, class and class of bedding etc.
C2.3.26.2 State for each short run water main the fitting, bend or special type, class etc.
C2.3.27.1 State for each water main the number of joints to be encased (wrapped)
C2.3.30 Concrete for bedding (Class A) and encasement for water mains
C2.3.30.1 Concrete (Class A) bedding (state class of concrete) cubic metre (m3)
C2.3.31 Manholes, valve and hydrant chambers etc. for water mains
C2.3.31.3 Hydrant chambers (state type etc. and drawing references etc.)
C2.3.31.4 Other structures (state type etc. and drawing reference etc.)
C2.3.32.2 Describe manhole or chamber and state type of cover and frame number (No)
C2.3.32.3 Describe manhole or chamber and state type of cover and frame number (No)
C2.3.33 Water main accessories (anchor or thrust blocks, pedestals or marker posts etc.)
C2.3.33.1 Anchor or thrust blocks (state type and drawing reference) number (No)
C2.3.33.2 Anchor or thrust blocks (state type and drawing reference) cubic metre (m3)
C2.3.33.4 Pedestals (state type and drawing reference) cubic metre (m3)
C2.3.33.5 Marker posts or blocks (state type and drawing reference) number (No)
(a) State manhole type and drawing reference and height raised number (No)
(b) State manhole type and drawing reference and height raised number (No)
(a) State type and drawing reference and height lowered number (No)
(b) State type and drawing reference and height lowered number (No)
The unit of measurement for items C2.3.35.1 and C2.3.35.2 shall be the number of manholes or valve or hydrant chambers raised or lowered as
specified or shown on the drawings.
The tendered rates shall include full compensation for all the labour, construction equipment and materials required to raise or lower the manholes
or valve or hydrant chambers as specified including removing covers and frames, any demolition required, rebuilding and setting and grouting the
covers and frames to the new levels specified. This pay item does not cover the costs of the lowering of pipes.
CONTENTS
D2.3.1 SCOPE
D2.3.2 GENERAL
D2.3.3 PERFORMANCE GUARANTEE REQUIREMENTS
D2.3.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D2.3.5 VISUALLY ASSESSED PROPERTIES
D2.3.6 INSTRUMENTALLY ASSESSED PROPERTIES
D2.3.7 EVALUATION FOR ACCEPTANCE
D2.3.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D2.3.9 NOTIFICATION OF REMEDIAL WORK
D2.3.10 REMEDIAL WORKS
D2.3.1 SCOPE
Refer to Clause D2.1.1.
There are no specific items in this Section.
Where applicable, details are provided in the Contract Documentation.
CONTENTS
PART A: SPECIFICATIONS
A2.4.1 SCOPE
A2.4.2 DEFINITIONS
A2.4.3 GENERAL
A2.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A2.4.5 MATERIALS
A2.4.6 CONSTRUCTION EQUIPMENT
A2.4.7 EXECUTION OF THE WORKS
A2.4.8 WORKMANSHIP
A2.4.2 DEFINITIONS
The following definitions shall apply to these specifications:
Extra high voltage (EHV) - the set of nominal voltage levels that are used in power systems for bulk transmission of electricity in the range 220
kV < Un < 400 kV.
Fuel - see Gas and Fuel.
Gas and fuel - any hydrocarbon gas fuel transported by pipeline.
Gaseous fuel - fuel which is in a gaseous state at a temperature of 15oC and a pressure of 1 bar.
High voltage (HV) - the set of nominal voltage levels that are used in power systems for bulk transmission of electricity in the range 44 kV < Un
< 220 kV.
Low voltage (LV) - the set of nominal voltage levels that are used for the distribution of electricity and whose upper limit is generally accepted to
be an a.c. voltage of 1 000 V (or a d.c. voltage of 1 500 V). Note that in certain fields of technology, for example electric motors and mining,
voltages up to and including 1 100 V are traditionally regarded as low voltage.
Medium voltage (MV) - the set of nominal voltages that lie above low voltage and below high voltage in the range 1 kV < Un < 44 kV.
Ultra-high voltage (UHV) - the set of nominal voltage levels that are used in power systems for bulk transmission of electricity in the range Un >
400 kV.
A2.4.3 GENERAL
The location, identification, protection and relocation of existing services, unknown or unrecorded services shall be managed in accordance with
Clause A2.1.3.2.
A2.4.5 MATERIALS
A2.4.5.1 General
All materials for energy services or other types of services (not specified elsewhere in Chapter 2 or in this Section) shall be in accordance with the
standards or specifications indicated in the Contract Documentation.
All cable depth measurements shall be made to the top of the cable when laid directly in ground or to the top of the duct or sleeve
where these are provided. The above depths shall apply to the top layer where cables are installed in layers. The Contractor may
only deviate from the above depths provided prior authority in writing has been obtained from the Engineer. In the event that the
minimum depths cannot be achieved the cables shall be protected with a suitable concrete covering.
The depth of cable ducts or pipes beneath railway lines or roads shall be not less than 1,1 m below the formation or road level as
applicable.
Trenches shall be excavated to a total depth which take into account the bedding thickness requirements indicated in Clause
A2.4.7.3.
(iii) Cable spacing
Cables installed in the same trench shall be laid parallel to each other with the following minimum spacings between cables (for the
purposes of the list below MV refers to voltages up to 11kV).
Table A2.4.7-2: Minimum electric power cable spacings
Cable Type Minimum Cable Spacing
LV/LV 2 cable diameters (minimum 25 mm)
LV/MV 150 mm
MV/MV 200 mm
LV/MV/PILOT 1 cable diameter
Where MV and LV cables have to be installed in the same trench, both shall be laid at a depth of 800 mm and then covered with
200 mm of bedding material. The bedding shall then be placed and compacted and the trench then backfilled and compacted layer
by layer.
Cables for telephones, communication systems and other low voltage systems (less than 50V) shall be separated from power cables
by at least 1,0 m horizontally. All control or pilot cables without a lead sheath and steel armouring shall be laid at least 300 mm
from power cables.
Cables shall not be installed on top of each other unless separating layers are specified. The minimum spacing between layers
shall be 200 mm. Where cables are to be installed on top of each other the work shall be done in accordance with the details
provided in the Contract Documentation.
Cable laying shall be planned so that as far as possible cables do not cross each other. Where crossing is unavoidable, a vertical
separation of not less than 150 mm shall be provided for cables of the same voltage and of 300 mm for cables of differing voltage.
Refer to Clause A2.4.7.7 where security risks dictate the use of concrete bedding.
A2.4.8 WORKMANSHIP
The requirements of Clause A1.2.8 of Chapter 1 shall apply to the process and acceptance quality control for all services work dealt with in Section
A2.4.
The Engineer may, at his discretion, elect to use some of the Contractor’s process control test results if the Engineer is satisfied that the
Contractor’s process control requirements are acceptable for acceptance quality control purposes.
The requirements of Clause A1.2.3.14 of Chapter 1 shall apply to any remedial work required where any work or material does not comply with
the specified requirements.
A2.4.8.1 General
The quality of materials and workmanship for energy services or other types of services (not dealt with elsewhere in Chapter 2) shall be in
accordance with the standards or specifications indicated in the Contract Documentation.
CONTENTS
B2.4.1 SCOPE
B2.4.2 DEFINITIONS
B2.4.3 GENERAL
B2.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B2.4.5 MATERIALS
B2.4.6 CONSTRUCTION EQUIPMENT
B2.4.7 EXECUTION OF THE WORKS
B2.4.8 WORKMANSHIP
B2.4.1 SCOPE
Apart from the scope for labour enhancement as described under Section B2.1, no additional scope for labour enhancement is defined under
Section B2.4 for Energy and Other Services.
B2.4.2 DEFINITIONS
Definitions as provided in A2.4.2 apply.
B2.4.3 GENERAL
Any activity specified in Part A where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B2.4.5 MATERIALS
The provisions of Part A shall apply.
B2.4.8 WORKMANSHIP
The provisions of Part A shall apply.
C2.4.1.1 Selected from the excavated trench material cubic metre (m3)
C2.4.1.4 Selected from sources provided by the Contractor cubic metre (m3)
(b) Crushed stone material (state material type) cubic metre (m3)
The unit of measurement for items C2.4.1.1 to C2.4.1.5 shall be the cubic metre of bedding material in place after compaction and the quantity
shall be calculated from the specified dimensions of the bedding and backfilling as specified or authorised by the Engineer.
The tendered rates for items C2.4.1.1 to C2.4.1.5 shall include full compensation for procuring, furnishing and placing the bedding material under,
alongside and over cables. The tendered rates for items C2.4.1.2 and C2.4.1.3 shall include full compensation for the additional cost of excavation
in all materials, for loading the material from an excavation on site or from a borrow pit, for hauling the material within the haul limit of 1,0 km and
for unloading the material for placement. The tendered rate for item C2.4.1.3 shall include full compensation for all operations at borrow pits not
subject to any specified separate pay item.
The tendered rates for items C2.4.1.4 and C2.4.1.5 shall include full compensation for the payment of any royalties or charges for procuring and
furnishing the material from sources provided by the Contractor or from commercial sources as well as for transporting the material over an
unlimited haul distance.
C2.4.2 Concrete for bedding and encasement for electric power cables
C2.4.2.2 Concrete encasement of cables (Class C16/20-20 concrete) cubic metre (m3)
The unit of measurement shall be the cubic metre of concrete placed, and the quantity shall be calculated from the dimensions of the excavation
as shown on the drawings or as specified or authorised by the Engineer, irrespective of whether the actual excavation exceeds the specified or
authorised dimensions.
The tendered rate shall include full compensation for procuring, furnishing and placing all materials, formwork and pedestals and for all the labour
and construction equipment necessary to complete the work as specified.
C2.4.3 Cable laying accessories (warning tape, protection slabs, markers etc.)
C2.4.3.2 Concrete slab protection (state type and dimensions etc) metre (m)
CONTENTS
D2.4.1 SCOPE
D2.4.2 GENERAL
D2.4.3 PERFORMANCE GUARANTEE REQUIREMENTS
D2.4.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D2.4.5 VISUALLY ASSESSED PROPERTIES
D2.4.6 INSTRUMENTALLY ASSESSED PROPERTIES
D2.4.7 EVALUATION FOR ACCEPTANCE
D2.4.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D2.4.9 NOTIFICATION OF REMEDIAL WORK
D2.4.10 REMEDIAL WORKS
D2.4.1 SCOPE
Refer to Clause D2.1.1.
There are no specific items in this Section.
Where applicable, details are provided in the Contract Documentation.
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 3: DRAINAGE ........................................................................................................................................ 3-1
3.1 DRAINS ......................................................................................................................................................... 3-1
PART A: SPECIFICATIONS .............................................................................................................................................................................. 3-1
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................. 3-8
PART C: MEASUREMENT AND PAYMENT ................................................................................................................................................... 3-10
PART D: GUARANTEES & COMPLIANCE CERTIFICATES ........................................................................................................................... 3-17
3.3 CONCRETE KERBING AND CHANNELING, ASPHALT BERMS, CHUTES, DOWNPIPES, AS WELL AS
CONCRETE, STONE PITCHED AND GABION LININGS FOR OPEN DRAINS ................................................. 3-39
PART A: SPECIFICATIONS ............................................................................................................................................................................ 3-39
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................... 3-46
PART C: MEASUREMENT AND PAYMENT ................................................................................................................................................... 3-48
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ...................................................................................................................... 3-53
CHAPTER 3: DRAINAGE
3.1 DRAINS
CONTENTS
PART A: SPECIFICATIONS
A3.1.1 SCOPE
A3.1.2 DEFINITIONS
A3.1.3 GENERAL
A3.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A3.1.5 MATERIALS
A3.1.6 CONSTRUCTION EQUIPMENT
A3.1.7 EXECUTION OF THE WORKS
A3.1.8 WORKMANSHIP
A3.1 DRAINS
PART A: SPECIFICATIONS
A3.1.1 SCOPE
Drainage under this Section covers mainly open drains as well as subsoil drains and their associated works. This Section covers the work required
for adequate surface, subsurface and piped drainage to ensure that the road and ancillary structures drain freely and without damage or risk to
infrastructure and road users. It covers all work, both rehabilitation and new work, in connection with the excavation and construction of open
drains, channels, subsoil drainage and banks and dykes at the locations and to the sizes, shapes, grades and dimensions as shown on the
drawings, or as specified by the Engineer.
It also covers the cleaning of existing open drains, as well as the test flushing of existing and new subsoil drains and the repairing of existing
subsoil drainage. In particular circumstances this work may be executed outside the road reserve.
Also covered is the clearing of existing culverts, including the removal of all materials which have accumulated in and around inlet and outlet
structures and in the barrels of the culverts, which is likely to adversely affect the operation of the drainage system.
Excluded are the lining of any drains such as with concrete, stone pitching, vegetation, synthetic and alternative materials and wired mesh, which
are covered under Section A11.1 of Chapter 11.
A3.1.2 DEFINITIONS
No specific definitions.
A3.1.3 GENERAL
No specific items.
A3.1.5 MATERIALS
A3.1.5.1 General material specifications
The material specifications are the required specifications for the materials as provided, placed and/or processed in final position for the drainage
elements.
It is the Contractor’s responsibility to ensure that the materials delivered and utilised for the drainage elements shall meet the specified
requirements.
Crushed stone used for natural permeable material shall comply with the requirements given in SANS 1083: Table 3: Stone for Concrete, and
shall be either be fine (14 mm nominal size) or coarse (20 mm nominal size) as specified. Crushed stone shall be clean with not more than 5,0 %
of the material passing through the 0,075 mm sieve.
When no suitable sand and/or crushed stone is available from borrow pits or designated quarries, the Engineer may require that it be procured
from commercial sources.
c) Geotextiles
Should the use of geotextiles be specified in subsoil drainage systems, or as filter separation blankets, or for any other purposes, it shall comply
with the requirements as specified in Section A12.11 of Chapter 12.
(i) Testing
The Contractor shall, at his own cost, submit a certificate by an approved laboratory to prove compliance with specified tests as
stated in Chapter 20. Alternatively, verifiable testing by the supplier may be submitted for approval to the Engineer.
The tests to be carried out on geotextiles relate to the material and the method of manufacture and are mainly to ascertain that the
correct grade and type of geo-textile is supplied, and that the material is equivalent in quality to that specified for use in the works.
This includes geotextile qualities regarding soil retention; permeability; clogging; durability and strength. Compatibility testing can
be done for filtration using the ASTM D5101 - Measuring the Soil-Geotextile System Clogging Potential by the Gradient Ratio.
d) Polymer film sheeting
Plastic for subsoil drainage systems to be used shall be polymer film type sheeting of 150 to 250 micron (0,15 to 0,25 mm) thickness, complying
with SANS 952-1.
The geotextile shall comply with the properties in Section A12.11 of Chapter 12. The Engineer shall specify the grade and type of geotextile
required to fully enclose the drainage core.
a) Mesh-structured pipe component of geo-composite drain.
The drainage pipe used for this purpose shall meet the following requirements:
Pipes for in-plane subsoil drainage systems shall have an internal diameter of 65 or 100 mm, as specified. The pipe shall be manufactured from
High Density polyethylene (HDPE) with a solid 5,0 mm wall thickness. It shall be extruded in an open lattice wall structure, with 70 % of the
diameter consisting of open area and a 30 % solid area along the invert. Perforations in the open structure of the pipe shall be greater than 5,0
mm but less than 12 mm.
The infiltration capacity of the pipe, without geotextile, under a 200 mm static head shall not be less than the following:
• For 65mm ID pipe = 20 litres per metre per second
• For 100mm ID pipe = 55 litres per metre per second
b) Geo-composite strip drains or prefabricated vertical drains (wick drains):
Geo-composite strip drains shall consist of a drainage core enclosed in geotextile.
The drainage core shall act as a flow net and combined with the geotextile shall include the physical characteristics as listed in Table A3.1.5-3.
Table A3.1.5-3: Physical characteristics of the geo-composite strip drain
Properties Units Composite Strip Drain Test Method
Drain Width mm 100 250 330
Geotextile As specified in Clause A3.1.5.2c)(i)
Manufacture
Core HDPE
Mass Core g/m² 80 200 220 SANS 9864 /
ISO 9864
Minimum under
Thickness Geotextile & Core mm 4,5 4,5 4,5
250kPa
Minimum Discharge Capacity Of Geo-composite strip drain
under 20kPa l/s 0,1 0,07 0,10
ISO 12958 /
Discharge Capacity under 50kPa l/s 0,05 0,06 0,09
ASTM D4716
under 250kPa l/s 0,02 0,03 0,04
Boulders exceeding 0,1 m3; where more than 40 % by volume of any material consists of boulders, each
exceeding 0,1 m3 in size, the volume of material so defined shall be classified as hard material
Existing stabilised road Existing layer material which has been stabilised (irrespective of stabilising agent) and requires careful cutting
layers: and excavation without damage to surrounding existing road layers, by whichever method.
Soft material: All material not classified as hard material or existing stabilised road layers shall be classified as soft material.
All new or
Side-slope Steeper than existing drains
(steepest side-slope not applicable 1v : 4h Flatter than within the road
n/a prism namely
is the determining (n/a) (v=vertical; 1v : 4h
slope) h=horisontal) median drains,
side drains and
drains on cut or
fill slopes.
Where clearing and/or grubbing is required for new open drains to be constructed, it shall be executed as specified in Section A1.6 of Chapter 1.
Open drains shall be constructed within 5 % true to line, grade and cross-section and shall be so maintained for the duration of the contract. Open
drains shall at all points be graded to flow in the direction of intended flow without low points where water may pond.
Care shall be taken to avoid excavation below the required grades for the open drains and any excavation carried out below the required grade
shall be backfilled with material of minimum G7 quality and compacted to at least 93 % of MDD by the Contractor at no cost to the Employer.
Material resulting from the excavations for open drains shall be used in the construction of fills, banks and dykes, or for other purposes, or shall
be disposed of to spoil, all as specified by the Engineer.
In respect of material resulting from open-drain excavation and not taken to spoil but used elsewhere in the construction of the works, payment
will be made for open drain excavation as well as for any item of temporary or permanent construction built from such material. Material from open
drain excavation, which is taken to spoil will be paid for as open-drain excavation only. Where specified by the Engineer that existing open drains,
but excluding new open drains constructed by the Contractor, shall be cleared and, where necessary, shaped by removing the sediment and
trimming the floors and side slopes, the specified requirements for constructing new open drains shall apply similarly to clearing and shaping
existing open drains.
Any concrete, stone pitched or wire mesh enclosed lining of open drains shall be done in accordance with the requirements of Clause A11.1.5 of
Chapter 11.
The Contractor shall remove all materials that will adversely affect the performance of the constructed drainage, including all silt, sediment,
driftwood, vegetation, debris and rubble that have accumulated in and around the culvert inlet and outlet structures and in the culvert barrels.
Unless such work forms part of specified work to rehabilitate or clear existing drains, no payment shall be made for such work, as it shall be
deemed to form part of normal finishing and trimming operations. All materials resulting from the clearing operations shall be disposed of at
specified locations. The clearing shall preferably be done with hand tools in order to prevent damage to existing drainage and other structures.
All structures damaged by the Contractor shall be repaired and made good at no cost to the Employer, all as instructed by the Engineer.
Measurement and payment in respect of the clearing and shaping of existing open drains, as classified in Table A3.1.7-1 shall be made under the
relevant items in Sections C3.1, C4.2 of Chapter 4 and C5.2 of Chapter 5.
A3.1.8 WORKMANSHIP
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular layer for which it will be used.
The Engineer shall carry out quality control testing and may, at his discretion, elect to use the Contractor’s test results if he is satisfied that the
Contractor’s process control requirements are acceptable for quality control purposes.
Any work or materials which do not comply with the specified requirements, shall be removed and replaced with work or materials which comply
with the requirements or, if the Engineer so agrees, shall be repaired so that it shall comply with the specified requirements after having been
repaired.
CONTENTS
B3.1.1 SCOPE
B3.1.2 DEFINITIONS
B3.1.3 GENERAL
B3.1.5 MATERIALS
B3.1.1 SCOPE
This Part covers additional specifications for work to enhance the labour component of construction activities, over and above labour employed
for conventional construction activities, where specified in Part A. This Section includes concrete mixed by hand and construction of banks and
dykes.
B3.1.2 DEFINITIONS
The provisions of Part A shall apply.
B3.1.3 GENERAL
The provisions of Part A shall apply.
B3.1.5 MATERIALS
The provisions of Part A shall apply.
Material which can be excavated by means of a suitable shovel with or without the use of a pick or other
Soft
hand-swung tool.
Material which is difficult to excavate by hand even with the aid of a crowbar and requires the assistance of
Intermediate
pneumatic tools for economic removal.
*1 Only applicable to materials comprising not more than 10 % gravel of size less than 10 mm and materials containing no cobbles or
isolated small boulders.
*2 Classification depends on the moisture content of the cohesive material.
B3.1.8 WORKMANSHIP
The provisions of Part A shall apply.
C3.1.1.1 Excavating all material situated within the following depth ranges below the surface level
using conventional methods:
C3.1.2 Clearing, shaping and disposal of accumulated sediment in existing unlined open
drains
C3.1.3 Excavation, clearing and disposal of accumulated sediment in existing lined drains and
drainage systems
(a) Manholes and inlet and outlet structures cubic metre (m3)
(a) Manholes and inlet and outlet structures cubic metre (m3)
(a) Manholes and inlet and outlet structures cubic metre (m3)
C3.1.4.1 Excavating in all material situated within the following depth ranges below the surface:
C3.1.4.5 Extra over sub-item C3.1.4.1 for excavation through stabilised existing road layers cubic metre (m3
C3.1.4.6 Excavation and disposal of material for composite in-plane fin-drain type drainage systems
using a trenching machine:
C3.1.5.1 Un-stabilised natural gravel obtained from approved sources on the site cubic metre (m3)
C3.1.5.3 Extra over items C3.1.5.1 and C3.1.5.2 for stabilisation with 4,0 % CEM II (32.5) cement cubic metre (m3)
The unit of measurement shall be the cubic metre of completed backfill, measured in place in the subsoil drainage systems and shall be calculated
in accordance with the authorised dimensions.
The tendered rate for item C3.1.5.1 shall include full compensation for procuring, furnishing, placing and compacting the backfilling.
Loading and hauling, where applicable, including a haul of 1,0 km, shall be measured and paid under Section C1.7 of Chapter 1.
The tendered rate for item C3.1.5.2 shall include full compensation for procuring, furnishing and transporting G5 material from commercial
suppliers, including the cost of transporting the material to the site irrespective of haul distance, and placing the materials as specified.
The tendered extra over rate for item C3.1.5.3 shall include full compensation for all additional costs for procuring, furnishing, mixing and placing
the cement stabilised backfill.
C3.1.6.1 Banks and dykes using conventional methods cubic metre (m3)
C3.1.6.2 Banks and dykes using labour enhanced construction methods cubic metre (m3)
The unit of measurement shall be the cubic metre of material, measured in place in the banks or dykes, and calculated in accordance with the
authorised dimensions. Where open drain with bank/dyke combinations are constructed, excavation shall be measured and paid under item
C3.1.1.
The tendered rate shall include full compensation for procuring, furnishing, placing, watering, compacting, shaping and trimming the material in
the banks and dykes.
Loading and hauling, where applicable, including a haul of 1,0 km, shall be measured and paid under Section C1.7 of Chapter 1. Where
excavation is specified by means of labour enhanced construction methods, the tendered rates shall include loading and transport by wheelbarrow
if the material is disposed of or utilised within a radius of 50 m, alternatively loading by hand onto transport vehicles for such disposal or utilisation
elsewhere, within a haul distance of 1,0 km.
C3.1.7 Natural permeable material in subsoil drainage systems (approved crushed stone):
C3.1.7.1 Crushed stone obtained from approved sources on the site (state grade and size) cubic metre (m3)
C3.1.7.2 Crushed stone obtained from commercial sources (state grade) cubic metre (m3)
The unit of measurement for item C3.1.7.1 shall be the cubic metre of approved crushed stone in place in the drains, calculated in accordance
with the authorised dimensions. The volume occupied by the pipes shall be deducted when calculating the volume of the natural permeable
material.
The tendered rate shall include full compensation for procuring, furnishing and placing the material as specified.
Loading and hauling, where applicable, including a haul of 1,0 km, shall be measured and paid under Section C1.7 of Chapter 1.
For payment purposes a distinction shall be made between the different grades of approved crushed stone.
The unit of measurement for item C3.1.7.2 shall be the cubic metre of crushed stone in place in the drains, calculated in accordance with the
authorised dimensions. The volume occupied by the pipes shall be deducted when calculating the volume of the natural permeable material.
The tendered rate shall include full compensation for procuring, furnishing and transporting approved crushed stone from commercial suppliers,
including the cost of transporting the material to the site irrespective of haul distance, and placing the materials as specified.
For payment purposes a distinction shall be made between the different grades of approved crushed stone.
C3.1.8 Natural permeable material in subsoil drainage systems (approved natural sand):
C3.1.8.1 Natural sand obtained from approved sources (state grade & source) cubic metre (m3)
C3.1.8.2 Natural sand from commercial sources (state grade) cubic metre (m3)
C3.1.9.1 U-PVC pipes and fittings, normal duty, complete with couplings (state size and whether or metre (m)
not perforated or slotted)
The unit of measurement for pipes shall be the metre of pipe, measured in place along its centreline, including the length of fittings.
The tendered rate shall include full compensation for procuring, furnishing, laying and jointing the pipes and fittings as specified.
C3.1.10 Polymer film sheeting or similar approved material, for lining subsoil drainage
systems:
The unit of measurement shall be the square metre of polymer film sheeting installed, measured net from the specified dimensions.
The tendered rate shall include full compensation for procuring, supplying, cutting, overlapping, jointing, placing and protecting the sheeting as
specified, as well as for wastage.
The unit of measurement shall be the square metre of geotextile supplied and installed as specified in Section A12.11 of Chapter 12.
The tendered rate shall include full compensation for furnishing, procuring, cutting, overlapping, jointing, placing and protecting the geotextile as
specified, as well as for wastage.
C3.1.12.1 In-plane drainage systems (state size, type of core and type grade, etc. of geotextile) metre (m)
C3.1.12.2 Vertical subsoil strip drainage systems (state size, type of core and type grade, etc. of metre (m)
geotextile)
C3.1.12.3 Panel drainage systems (state size, type of core and type grade, etc. of geotextile) metre (m)
C3.1.12.4 Alternative drainage systems as detailed in Contract Documentation (state size, type and metre (m)
other details)
The unit of measurement shall be the metre of composite or alternative drainage system as specified, measured in place along the centre line of
the system.
The tendered rate shall include full compensation for procuring, furnishing, assembling, installing and jointing the composite or alternative drainage
system, including perforated or other types of drainage core, complete as specified.
C3.1.13 Concrete outlet structures, manhole boxes, junction boxes and cleaning eyes for
subsoil drainage systems:
C3.1.13.1 Outlet structures (specify each type and drawing reference) number (No)
C3.1.13.2 Inspection boxes (specify each type and drawing reference) number (No)
C3.1.13.3 Junction boxes (specify each type and drawing reference) number (No)
The unit of measurement shall be the number of outlet structures, manhole boxes, junction boxes and cleaning eyes for subsoil drainage systems
constructed in accordance with the details on the drawings and the Engineer’s instructions.
The tendered rates shall include full compensation for all excavation, backfilling, compacting to 93 % of MDD, disposing of surplus excavated
material, keeping the excavations safe, dealing with any surface or subsurface water, procuring and furnishing all materials, providing, erecting
and removing formwork, mixing, transporting, placing and curing the concrete, and all labour and constructional plant required for constructing the
concrete outlet structures, subsoil drain inspection boxes, subsoil junction boxes and cleaning eyes, complete as specified.
The tendered rate shall also include full compensation for procuring and finishing the galvanised woven wire mesh, cutting, waste, installing the
wire mesh at outlets and keeping the wire mesh in the pipe openings clean for the duration of the contract period.
C3.1.14.3 Other (Glass fibre reinforced, PVC etc.) (specify) number (No)
The unit of measurement shall be the number of caps supplied as specified, and the tendered rate shall include full compensation for supplying
and installing the caps.
C3.1.16 Loading and hauling of material in excess of 1,0 km cubic metre-kilometre (m3-km)
The measurement and payment for hauling material referred to in items C3.1.1, C3.1.2, C3.1.3, C3.1.4, C3.1.5, C3.1.6, C3.1.7, C3.1.8, C3.1.17
and C3.1.18, if any, shall be in accordance with Section C1.7 of Chapter 1.
The unit of measurement shall be the cubic metre of approved granular material placed and compacted to 93 % of MDD, measured in place after
compaction. Where such measurement is impractical or impossible, as decided by the Engineer, quantity measurement shall be determined as
70 % of the loose volume of imported material.
The tendered rate shall include full compensation for procuring, furnishing, transporting, placing and compacting the granular material and
including haul of 1,0 km. Where trimming or benching of the side drains and disposal of resulting material is required, it shall be measured and
paid under item C3.1.3.
The unit of measurement shall be the cubic metre of compacted material and the quantity shall be calculated from the authorised dimensions
given on the drawings or as specified by the Engineer.
The tendered rate shall include full compensation for procuring, as if from soft excavation or borrowpits, breaking down, placing and compacting
the material in 150 mm layers, transporting of the material transport over a haul of 1,0 km as well as for shaping the top surface in accordance
with the drawings.
The unit of measurement shall be the cubic metre of material removed to expose the drain for the purposes of refurbishment existing drains. This
item shall not be applicable in cases where complete substitution or replacement of existing drains is specified.
The tendered rate shall include full compensation for all labour and tools required for removing the material. The re-instatement of the drain
elements, as may be specified, shall be paid for under the relevant items for constructing a new drain.
C3.1.20 Breaking into existing drainage structures and install subsoil drain pipe number (No)
The unit of measurement shall be the number of subsoil drain pipes built into existing drainage structures in accordance with the details on the
drawings or as specified by the Engineer.
The unit of measurement for clearing of existing subsoil drains shall be the metre of drain cleared with a sewer cleaning rod and brush, thorough
flushing and mandrill testing.
The unit of measurement for hydro jetting will include the establishment on site, hydro jetting and vacuuming of specified drains at various locations
on site.
The tendered rate shall include full compensation for all labour, equipment, tools, water and transport required for clearing existing subsoil drains
and for disposal of the cleared material to approved sites.
The unit of measurement shall be the number of tests satisfactorily completed on newly installed or unblocked sections of drain system, irrespective
of its length. No payment will be made for tests, which have to be repeated due to blocked pipes or faulty workmanship.
The tendered rate shall include full compensation for the provision of a water tanker, water, equipment and labour necessary to carry out the tests,
complete as specified.
C3.1.23 Subsoil drain outlet marker (type or drawing specified) number (No)
The unit of measurement is the number of subsoil outlet markers installed in accordance with the details on the drawings.
The tendered rate shall include full compensation for procuring and furnishing the subsoil drain outlet marker and installation in accordance with
the details on the drawing.
The provisional sum given for the Contractor to provide the Engineer with as built drawings pertaining to all subsoil drains on the site. The drawings
must contain the location, co-ordinates of in- and outlets, length and depth and must be provided to the Engineer prior to the site hand over.
CONTENTS
D3.1.1 SCOPE
D3.1.2 GENERAL
D3.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D3.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D3.1.5 VISUALLY ASSESSED PROPERTIES
D3.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D3.1.7 EVALUATION FOR ACCEPTANCE
D3.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D3.1.9 NOTIFICATION OF REMEDIAL WORK
D3.1.10 REMEDIAL WORKS
A3.2 CULVERTS
PART A: SPECIFICATIONS
A3.2.1 SCOPE
Drainage under this Section covers mainly culverts and conduits and their associated works in water courses or from natural or shaped areas, but
may also cover drainage of road or bridge surfaces. This Section covers work in connection with the construction of in situ constructed and
prefabricated culverts and other closed conduits to provide such drainage, together with inlet and outlet structures, manholes and other
appurtenant structures. Different Road Authorities may differentiate between minor culverts, lesser culverts or major culverts. Major culverts are
covered in Chapters 13 and 14.
The replacing and/or lengthening of existing culverts, modification of and repairs to existing drainage structures and catch pits as well as sleeving
or lining, partly of fully, of the insides of existing culverts are also included in this Section.
A3.2.2 DEFINITIONS
Culvert: is a structure other than a bridge which provides an opening under the carriageway or median for drainage or other purposes.
Major Culvert: is a cellular structure with dimensions less than those defining a bridge but with any clear span length (as measured horizontally
at the soffit perpendicular to the faces of its supports) equal to or larger than 2,1 m, or diameter equal to or larger than 2,1 m, or a culvert with a
total cross-sectional opening equal to or larger than 5,0 m2. (TMH19)
Minor Culvert: all culverts smaller than that defined as a Major Culvert are classified as lesser culverts. (TMH19)
A3.2.3 GENERAL
The attention of the Contractor is drawn to the requirement that information given on the drawings, longitudinal sections or drainage schedules
may have to be verified and reviewed to suit actual site conditions and therefore the Contractor shall only construct these culverts after the
Engineer has amended or verified the information on the drawings based on detail surveys taken on site.
Prefabricated units shall be ordered by the Contractor from actual measurements of lengths determined on site and not from lengths stated in the
drainage schedules or from the schedule of quantities.
All existing stormwater culverts, which are to be extended, shall be inspected on site and any defects reported to the Engineer prior to extensions
being constructed. Likewise, existing and new culverts are to be inspected for possible damage after completion of layerworks over the culverts.
A3.2.5 MATERIALS
A3.2.5.1 General material specifications
The material specifications are the required specifications for the materials as placed and/or processed in its final position.
It is the Contractor’s responsibility to ensure that the materials delivered to the site shall meet these specified requirements.
Prior to the manufacture of any prefabricated units by the Contractor’s manufacturer, the manufacturer shall submit his Quality Plan to the Engineer
to verify that all prefabricated units will be manufactured in full compliance with the relevant SANS requirements. No prefabricated units shall be
ordered until the Engineer has satisfied himself that the proposed units have been or will be manufactured to the required specifications and
tolerances as well as the load bearing requirements. In particular the manufacturer shall check each prefabricated portal culvert unit for steel cover
compliance, and random checking of units shall not be accepted. The Engineer’s representative may visit the factory at any stage to ascertain
adherence to the quality plan. Should the manufacturer fail to adhere to their Quality Plan the Engineer may exercise the right to reject the use of
products from the manufacturer concerned. No claim from the Contractor for any resultant cost or delay due to such rejection, and due to
procurement from a new manufacturer, shall be entertained.
Materials removed under this Section from existing works, except where excavated materials are specified to be reused or disposed of, or except
where provision has been made in Part C for their reuse or specific disposal, shall be deemed to be the property of the Contractor.
A3.2.8 WORKMANSHIP
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular layer for which it will be used. These
required testing frequencies shall be stated in the borrow pit and quarry management and utilisation plans.
A copy of the Contractor’s process control test results, which should cover all the above quality control tests, shall be submitted to the Engineer
for comments.
CONTENTS
B3.2.1 SCOPE
B3.2.2 DEFINITIONS
B3.2.3 GENERAL
B3.2.5 MATERIALS
B3.2.1 SCOPE
This Part covers additional specifications for work to enhance the labour component of construction activities, over and above labour employed
for conventional construction activities, where specified in Part A.
B3.2.2 DEFINITIONS
The provisions of Part A shall apply.
B3.2.3 GENERAL
The provisions of Part A shall apply.
B3.2.5 MATERIALS
B3.2.5.1 General material specifications
The provisions of Part A shall apply.
Material which can be excavated by means of a suitable shovel with or without the use of a pick or other
Soft
hand-swung tool.
Material which is difficult to excavate by hand even with the aid of a crowbar and requires the assistance of
Intermediate
pneumatic tools for economic removal.
B3.2.8 WORKMANSHIP
The provisions of Part A shall apply.
C3.2.1.1 Excavating in all material situated within the following depth ranges below the surface level:
C3.2.1.2 Excavating soft material 0 m to 1,5 m below the surface level using labour enhanced cubic metre (m3)
construction methods, or instructed by hand under Clause A3.2.7.2d):
C3.2.1.3 Excavating intermediate material 0 m to 1,5 m below the surface level using labour cubic metre (m3)
enhanced construction methods, or instructed by hand under Clause A3.2.7.2d):
C3.2.1.4 Extra over sub-item C3.2.1.1 for excavation in hard or boulder material, cubic metre (m3)
irrespective of depth
C3.2.1.5 Extra over sub-item C3.2.1.1 for excavation in stabilised existing road layers, irrespective of cubic metre (m3
depth
The unit of measurement shall be the cubic metre of material excavated within the specified widths over the lengths and depths authorised by the
Engineer in each case, measured in place before excavation. Excavation in excess of the widths specified or authorised by the Engineer shall not
be measured for payment.
When measuring excavation for the removal of existing culverts, the volume occupied by the culvert shall not be subtracted from the calculated
volume of excavation.
In the case of manholes, catchpits and inlet and outlet structures, the dimensions for determining the volume of excavation shall be the neat
outside dimensions of the structure, plus an allowance of 0,5 m of working space around the structure.
Payment made for either hard; boulder or stabilised existing road layers shall only be measured for the one applicable extra over category.
The tendered rates shall include full compensation for all excavation, temporary timbering, shoring and strutting, for preparing the bottom of the
excavation for the culvert beds, the disposal of excavated material unsuitable for backfilling, keeping excavations safe, dealing with any surface
or subsurface water, and for any other operations necessary for completing the work as specified.
Irrespective of the total depth of the excavation, the quantity of material in each depth range shall be measured and paid for separately.
Excavation shall be done using conventional construction methods and/or labour enhanced construction methods as specified and measured.
The tendered rates shall include full compensation for the excavation of the material to the required dimensions, lines, levels and grades, the
trimming of the bottom of the excavation and the loading and disposal/utilisation of the materials directed, including haul of 1,0 km when using
conventional construction methods.
Loading and hauling, where applicable, including a haul of 1,0 km, shall be measured and paid under Section C1.7 of Chapter 1. Where the
excavation of material is specified by means of labour enhanced construction methods, the tendered rates shall include loading and transport by
wheelbarrow if the material is disposed of or utilised within a radius of 50 m, alternatively loading by hand onto transport vehicles for such disposal
or utilisation elsewhere, within a haul distance of 1,0 km.
For payment purposes a distinction shall be made between materials as classified according to Clause A3.2.7.2a) under Classification of Materials.
C3.2.2 Backfilling:
C3.2.2.3 Extra over sub-items C3.2.2.1 and C3.2.2.2 for soil cement backfilling
(a) With wet mixture (specify cement content) of 3 % cement cubic metre (m3)
(b) With dry mixture (specify cement content) of 3 % cement cubic metre (m3)
C3.2.2.4 Extra over sub-items C3.2.2.1 and C3.2.2.2 for screed layers (class of concrete indicated) cubic metre (m3)
The unit of measurement shall be the cubic metre of material backfilled in place after compaction. The quantity shall be calculated from the leading
C3.2.3.5 Provision of skew ends of pipe culvert (type and diameter indicated) number (No)
The unit of measurement for concrete pipe culverts shall be the metre of culvert laid as shown on the drawings or ordered by the Engineer. The
length shall be measured along the soffit centre of the culvert or along each barrel for multiple barrel units. The unit of measurement for the skew
ends of culverts shall be the number of skew end units provided; in- and outlets and multiple barrels shall be measured separately. The tendered
rate shall include for all costs to provide the skew end unit from the manufacturer to the specified length and skew including all wastage.
The tendered rates shall include full compensation for providing, testing, loading, transporting and unloading the culverts, for providing and placing
all specified bedding but excluding concrete bedding, and for the installation, laying and jointing of the culverts, as specified.
Where a half-length pipe unit is required, i.e. a pipe unit of which the length is equal to half the standard length, and provided that such half-length
pipe units are normally supplied by the manufacturers, the actual length of such half-length pipe unit will be measured for payment, and no
additional compensation will be paid in respect of such half-length pipe unit.
For the purposes of payment, differentiation shall be made between the various types and sizes of culverts and between the culverts placed on
A, B, C and D Classes of bedding as well as the different size skew ends requirements.
C3.2.4.2 Provision of skew or bevelled ends for metal culverts number (No)
C3.2.4.4 Protective coating to metal culverts (culvert size; inside/outside/ both sides; coating type & metre (m)
thickness indicated)
The unit of measurement for metal culverts and protective coating shall be the metre of culvert laid as shown on the drawings or ordered by the
Engineer. The unit of measurement for the skew/bevelled ends of culverts shall be the number of skew/bevelled end units provided; in- and outlets
and multiple barrels shall be measured separately. In the case of a metal or U-PVC pipe, the culvert length shall be measured along the pipe
centreline. In the case of a metal pipe arch, the culvert length shall be measured along the bottom/invert of the pipe arch. In all cases the length
of bevelled and/or skew ends shall be included.
The tendered rates shall include full compensation for providing, testing, loading, transporting and off-loading the culverts, for providing and placing
fine-grained material where required for the installation of culverts, and for installing, laying and jointing the culverts as specified. For the purposes
of payment, a differentiation shall be made between the various types and sizes of culverts and also between culverts with differing wall
thicknesses.
Payment shall be made separately for the provision of bevelled and/or skew ends for metal culverts, and the tendered rate shall include full
compensation for all work in connection with the provision of specified ends. U-PVC culverts may be cut to skew ends, but no additional payment
will be made for cutting skew ends.
The tendered rate per anchor bolt shall include full compensation for procuring, providing and installing the bolts.
C3.2.5.1 Prefabricated portal culverts; wall and roof combination (size and type indicated) metre (m)
C3.2.5.2 Prefabricated floor slabs (size and type indicated) metre (m)
C3.2.5.3 Prefabricated roof slabs (size and type indicated) metre (m)
Payment will be made separately for cast in situ concrete wall, floor and/or roof slabs as well as formwork of culverts under item C3.2.7; and for
brickwork walls and plastering under items C3.2.16 and C3.2.17.
The unit of measurement for rectangular culverts constructed of prefabricated elements shall be the metre of culvert as per the relevant item(s)
constructed as shown on the drawings or as specified by the Engineer. Payment for a culvert may be made as a combination of prefabricated
elements as relevant.
The length shall be measured along the centre of the soffit of the culvert or along each barrel of multiple barrel units.
The tendered rates shall include full compensation for the supply and installation of all precast materials required to complete the culverts,
supplying, testing, loading, transporting and off-loading of all prefabricated portals, floor and roof slabs, providing and placing the fine-grained
material where required for installing the prefabricated culvert floors, and installing, laying and jointing the prefabricated slabs as specified,
including cutting them on the site, and waste. Where precast elements are installed on cast in situ concrete floors or walls or on brickwork walls,
no additional payment shall be made for any additional costs arising from the change between cast in situ and precast work.
Payment shall distinguish between the different sizes of rectangular culverts precast elements.
Payment for inlet and outlet structures shall be measured separately as specified in accordance with items C3.2.7 and C3.2.18 to C3.2.21 and
such other items as may be necessary.
C3.2.6 Extra over items C3.2.3, C3.2.4 and C3.2.5 for constructing inclined culverts metre (m)
The unit of measurement shall be the metre of culvert installed at a grade steeper than 1:4 as specified in Clause A3.2.7.15.
The tendered rate shall include full compensation for additional or more difficult work of any nature in regard to laying, excavating and backfilling
as may be required for installing the culverts at a grade steeper than 1:4.
C3.2.7.2 In complete in situ floor slabs for rectangular culverts, manholes and catchpits including cubic metre (m3)
formwork, joints and Class U2 surface finish (class of concrete indicated) (installed at a
standard depth of 1,0 m)
C3.2.7.3 In walls, excluding formwork but including Class U2 surface finish (class of concrete indicated) cubic metre (m3)
C3.2.7.4 In roof slabs for rectangular culverts, excluding formwork but including Class U2 surfacing cubic metre (m3)
finish and joints (class of concrete indicated)
C3.2.7.5 In inlet and outlet structures including kerbs, chutes and downpipes, skewed ends, catchpits, cubic metre (m3)
manholes, thrust and anchor blocks, excluding formwork but including Class U2 surfacing finish
(class of concrete indicated)
C3.2.7.6 Formwork of concrete under items C3.2.7.3 to 5 above (Class of finish indicated) square metre (m2)
C3.2.7.7 Concrete linings for the inverts of metal culverts, including formwork and Class U2 surface cubic metre (m3)
finish (class of concrete indicated)
Measurement of formwork and cast in situ concrete shall be as specified in Section A13.4 of Chapter 13 of these specifications.
Payment for formwork and cast in situ concrete shall be made as provided in Chapter 13 of these specifications, except that payment for the
formwork for concreting in items C3.2.7.1 and C3.2.7.2 shall not be made separately, and the Contractor's rates for concrete shall include full
compensation therefore item C3.2.7.2 shall be subject to an extra over payment under item C3.2.15.4 in the case of manholes or catchpits deeper
than 1,0 m.
No separate payment shall be made for the construction of joints in culvert floor and roof slabs or at inlet and outlet structures and the tendered
rates for concrete shall include full compensation for forming the joints complete in accordance with the details shown on the drawings.
The tendered rates shall also include full compensation for mixing and/or procuring concrete as indicated, curing and the transport thereof to the
final placement location.
C3.2.8 Concrete backfill or encasement for culverts (Type and Class of concrete indicated) cubic metre (m3)
Measurement of cast in situ concrete shall be as specified in Section A13.4 of Chapter 13 of these specifications.
C3.2.9 Prefabricated concrete inlets and outlets to culverts (size and type indicated) number (No)
Prefabricated concrete inlets and outlets for concrete pipe culverts shall be measured per inlet or outlet, complete in position.
The tendered rate shall include full compensation for procuring, providing, loading, transporting, off-loading and installing the inlets or outlets as
specified.
C3.2.10 Reinforcement:
The unit of measurement and tendered rate shall be as specified under item C14.5.1 of Chapter 14.
C3.2.12.1 Full member or element (location and description) cubic metre (m3)
C3.2.12.2 Partial member or element (location and description) cubic metre (m3)
The unit of measurement shall be the cubic metre of existing concrete removed according to authorised dimensions.
The tendered rates shall include full compensation for all demolition as specified in item C14.3.1 of Chapter 14.
C3.2.13.1 Removing and stacking existing culverts for re-use (size and type indicated) metre (m)
C3.2.13.2 Removing and re-laying existing culverts without stacking (size and type of bedding metre (m)
indicated)
C3.2.13.3 Re-laying existing culverts from stacking (size and type of bedding indicated) metre (m)
The unit of measurement shall be the metre of existing pipe or prefabricated portal culvert removed, stacked and/or re-laid.
The tendered rate shall include full compensation for lifting, loading, transporting for a haul distance within 5,0 km without additional payment, off-
loading, stacking (if required) and laying pipes according to the specifications.
Payment for any excavation and backfilling required for the removal and relaying of existing pipes or portals shall be made separately under items
C3.2.1 and C3.2.2.
C3.2.14 Protective mastic asphalt coating for corrugated metal culvert units (state whether square metre (m2)
to be applied by brush or by spray gun)
The unit of measurement shall be the square metre of protective coating applied as specified and as directed by the Engineer. When both inside
and outside surfaces are treated, both surfaces shall be measured.
The tendered rate shall include full compensation for procuring and furnishing the mastic asphalt, applying the material, and for all other additional
work and incidentals required for providing the protective coating as specified.
The unit of measurement shall be the cubic metre of benching, measured in plan, constructed in class C20/25-14 concrete with granolithic
rendering.
The tendered rate shall include full compensation for procuring and furnishing all materials, placing the concrete benching, and rendering with the
specified granolithic rendering.
C3.2.19 Accessories:
C3.2.19.2 Inlet grids or covers (description and reference to drawing) number (No)
C3.2.19.3 Manhole frames (type, load bearing and SANS specification indicated) number (No)
C3.2.19.4 Manhole covers or gratings (type, load bearing and SANS specification indicated) number (No)
C3.2.19.5 Inlet channel frames (type, load bearing and SANS specification indicated) number (No)
C3.2.19.6 Inlet channel gratings (type, load bearing and SANS specification indicated) number (No)
C3.2.19.7 Step irons (description and SANS specification indicated) number (No)
The unit of measurement shall be the number of each type of accessory delivered and installed. Accessories shall only be measured and paid
where such items are not included in unit prices for complete structures such as under item C3.2.15
The tendered rates shall include full compensation for procuring, furnishing and installing the accessories as specified.
The unit of measurement shall be the complete anchor installed, including straps, bolts, etc, but excluding any concrete work, which shall be
measured under item C3.2.7.
The tendered rate shall include full compensation for procuring, providing and installing the anchors.
C3.2.21 Prefabricated reinforced-concrete skew end units for concrete culverts constructed at number (No)
a skew angle ( type and dimensions of unit and class of bedding indicated)
The unit of measurement shall be the number of each type and size of prefabricated reinforced-concrete skew end unit provided and installed,
irrespective of the angle of skew.
The tendered rates shall include full compensation for providing, testing, loading and unloading the units, constructing the prescribed class of
bedding, and for installing, laying and joining the units, complete as specified and in accordance with the details shown on the drawings.
The unit of measurement shall be the number of pipes that have been cut on the instruction by the Engineer. The tendered rate shall be fill
compensation for the cutting, by means of mechanical saw (angle grinder) and finishing off the pipes for the specific angle of skew at which the
pipes must be laid.
Cutting of the pipes shall only be paid for if the headwall or the wingwalls are at such a skew angle in respect to the centre line of the pipes that
cutting is required and where non-standard lengths are required. The maximum skew angle at which pipes are allowed to be cut shall be 30
degrees and the maximum length of pipe measured along the shortest side, shall be 1,5 m.
C3.2.23 Breaking into existing drainage structures and building in pipes or culverts of the number (No)
following size (pipe diameter and/or culvert size to be stated)
The unit of measurement is the number of each type and size of existing drainage structure that is being modified as shown on the drawings or
as specified by the Engineer.
The tendered rates shall include full compensation for providing all labour, constructional plant and materials required, for all excavation, breaking
into existing drainage structures, building into the newly formed accesses, sealing around the edges and making the joints watertight, breaking
out existing benching and channelling where required and reconstructing them complete with granolithic rendering to suit the new drainage
arrangement, backfilling and compacting to at least 93 % of MDD and dealing with the flows in the existing structures.
C3.2.24.1 Preparation and compaction of in situ bedding material to 90 % of MDD (depth indicated) cubic metre (m³)
C3.2.24.2 Extra-over sub-item C3.2.24.1 for compaction to 93 % of MDD (depth indicated) cubic metre (m³)
The unit of measurement shall be the cubic metre of material ripped and compacted as specified.
The tendered rate shall include full compensation for the ripping of the in situ material to the specified width and depth, wetting the material to
such an extent that the density can be achieved.
C3.2.25 Painting of exposed steel bars with two coats of zinc rich primer (Type specified) litre (ℓ)
C3.2.26 Repair with cementitious mortar or concrete (Class) to (description) litre (ℓ)
The unit of measurement shall be the litre of mortar or concrete as specified by the Engineer and measured in place, used for the repair of specified
concrete defects, including curing.
The tendered rate shall be as specified under item C14.4.1 of Chapter 14. Payment for larger concrete extensions shall be made under item
C3.2.7.
CONTENTS
D3.2.1 SCOPE
D3.2.2 GENERAL
D3.2.3 PERFORMANCE GUARANTEE REQUIREMENTS
D3.2.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D3.2.5 VISUALLY ASSESSED PROPERTIES
D3.2.6 INSTRUMENTALLY ASSESSED PROPERTIES
D3.2.7 EVALUATION FOR ACCEPTANCE
D3.2.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D3.2.9 NOTIFICATION OF REMEDIAL WORK
D3.2.10 REMEDIAL WORKS
A3.3.2 DEFINITIONS
No specific definitions.
A3.3.3 GENERAL
A3.3.3.1 Types of structures
Kerbing shall include barrier kerbs, mountable and semi-mountable types. All these elements may be prefabricated on site or elsewhere or
constructed in a continuous operation using slipforms. Kerb inlets shall generally be cast in situ concrete.
Channeling may be cast in situ concrete, prefabricated units, slipform construction, stone pitched or gabion lined.
Chutes may be prefabricated units, cast in situ concrete, stone pitched or gabion lined.
Lining of open channels may be cast in situ concrete or stone pitched or gabions, except that side slabs may be precast on site or elsewhere.
Downpipes shall be prefabricated elements, of concrete, steel or U-PVC or HDPE.
Asphalt berms may be cast in situ in moulds or constructed by means of a suitable machine.
The bond coat shall consist of a stable grade bituminous emulsion diluted to have 30 % net bitumen content
The bituminous binder to be used in the specified mix shall be a bitumen emulsion and conform to the specifications in Clause A9.1.5.2 of Chapter
9.
m) Polymer film sheeting
Plastic for drainage systems to be used shall be polymer film type sheeting of 150 to 250 micron (0,15 to 0,25 mm) thickness, complying with
complying with SANS 952-1
n) Alternative materials
Alternative materials, if any, shall be specified and detailed in the Contact Documentation. Where alternative materials are proposed by the
Contractor, they shall be submitted for approval, accompanied by the verification of being fit for purpose, specific performance guarantees.
A3.3.8 WORKMANSHIP
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular purpose for which it will be used.
CONTENTS
B3.3.1 SCOPE
B3.3.2 DEFINITIONS
B3.3.3 GENERAL
B3.3.5 MATERIALS
B3.3.1 SCOPE
This part covers additional specifications for work to enhance the labour component of construction activities, over and above labour employed
for conventional construction activities, where specified.
B3.3.2 DEFINITIONS
The provisions of Part A shall apply.
B3.3.3 GENERAL
The provisions of Part A shall apply.
B3.3.5 MATERIALS
The provisions of Part A shall apply.
B3.3.8 WORKMANSHIP
The provisions of Part A shall apply.
C3.3.1.1 Prefabricated kerbing (description of type of kerb and bedding with reference to drawing)
(a) State type of kerb and bedding with reference to drawing metre (m)
(a) State type of kerb, class of concrete with reference to drawing metre (m)
The unit of measurement shall be the metre of concrete kerbing complete as specified and detailed on the drawings, measured along the front
face of the kerb.
The tendered rate for each metre of concrete kerbing shall include full compensation for the necessary excavation and preparation of bedding,
backfilling, formwork, finishing and curing of cast in situ kerbing, alternatively for procuring, furnishing and installing all materials for prefabricated
kerbing, protecting work against staining, supporting the kerbs with in situ cast concrete, and filling and pointing all construction or contraction
joints, and producing and sealing all expansion joints, all complete as specified.
All concrete shall conform to the required specification.
The unit of measurement shall be the metre of concrete kerbing or kerbing-channeling combination complete as constructed, measured along the
front face of the kerb.
The tendered rate for each metre of concrete kerbing and/or kerbing-channeling combination shall include full compensation for the necessary
excavation and preparation of bedding, backfilling, formwork, finishing and curing of cast in situ kerbs and channels, alternatively for procuring,
furnishing and installing all materials for prefabricated kerbing and channeling, protecting work against staining, supporting the kerbs with in situ
cast concrete, and filling and pointing all construction or contraction joints, and producing and sealing all expansion joints, all complete as specified.
All concrete shall conform to the required specification.
C3.3.3 Extra over items C3.3.1 and C3.3.2 for concrete kerbing or concrete kerbing and
channeling on curves
C3.3.3.1 On curves of radii more than or equal to 5,0 m but less than 20 m metre (m)
C3.3.3.2 On curves with radii more than or equal to 1,0 m but less than 5,0 m metre (m)
C3.3.4 Extra over item C3.3.2 for drop kerbs at pedestrian crossings and driveways metre (m)
The unit of measurement shall be the meter of drop kerb installed measured from the starting point where the kerb on one side starts tapering
down, across the lowered section as specified, up to the end where the kerb is at its correct level on the other side.
C3.3.5.1 Asphalt berms placed where there are no vehicle restraint systems (drawing reference metre (m)
indicated)
C3.3.5.2 Asphalt berms placed at existing vehicle restraint systems (drawing reference indicated) metre (m)
The unit of measurement for items C3.3.5.1 and C3.3.5.2 shall be the metre of asphalt berm constructed as specified.
The tendered rates shall include full compensation for procuring, furnishing, mixing and placing the material, and all other work necessary for
the completing the asphalt berms as specified
The unit of measurement for items C3.3.5.3 and C3.3.5.4 shall be the square metre of completed prime or bond coat, applied in accordance
with the specifications.
The tendered rates shall include full compensation for procuring and providing all material and for mixing and applying the prime and bond coats
complete as specified, including cleaning, compacting and trimming the surface being primed or tacked.
Payment shall be made under this item for the prime coat only if it is specified by the Engineer, and it is applied in a separate strip independently
from the prime coat of the road or shoulder surface. If prime is applied as an integral part of the prime coat of the road or shoulder surface, by
that prime coat being applied over a wider area to provide for the berms, payment for the prime shall not be made under this item, but under the
item for priming the road or shoulder.
C3.3.6.1 Prefabricated concrete chutes (description of type with reference to drawing) metre (m)
C3.3.6.2 Cast in situ concrete chutes (description, with reference to drawing and class of concrete and metre (m)
finish indicated)
C3.3.6.3 Stone pitched chutes (description with reference to drawing and class of concrete indicated) metre (m)
The unit of measurement shall be the metre of completed chute as constructed, including any overlap, measured along the slope as constructed
but excluding transition sections and inlet and outlet structures measured separately.
The tendered rate per metre shall include full compensation for procuring, furnishing and installing the completed chutes as specified and for all
excavation and the preparation of bedding, backfilling, formwork and finishing required.
All concrete shall conform to the required specification.
(a) Grouted stone pitching (type of chute indicated) square metre (m2)
(b) Grouted stone pitching on a concrete bed (class of concrete and type of chute indicated) square metre (m2)
Measurement and payment for formwork and concrete shall be as specified in Section A13.4 of Chapter 13. Payment for excavation trimming and
gravel or soil backfilling shall be measured and paid for separately under Section C3.1, all applicable items.
All concrete shall conform to the required specification.
The unit of measurement for stone pitching shall be the square metre of stone pitching calculated from the drawings or as specified by the
Engineer, and shall include compensation for a concrete bed where required.
The tendered rates for stone pitching shall include full compensation for all labour, plant, material, formwork, concrete, stone and other incidentals
as may be required and specified on the drawings.
C3.3.8.1 Cast in situ concrete lining (class of concrete and type of open drain indicated) cubic metre (m3)
C3.3.8.2 ClassU2 surface finish to cast in situ concrete (type of open drain indicated) square metre (m2)
(a) Grouted stone pitching (type of open drain indicated) square metre (m2)
(b) Grouted stone pitching on a concrete bed (class of concrete and type of open drain square metre (m2)
indicated)
Measurement and payment under this item shall include items for inlet, outlet, transition and similar structures.
Measurement of and payment for formwork and concrete shall be as specified in Section A13.4 of Chapter 13.
The unit of measurement for surface finish shall be the square metre of finished concrete surface. The tendered rate for surface finish shall include
full compensation for all labour, plant, material and other additional work and incidentals required for trimming the concrete lining as specified,
and curing of the concrete.
The unit of measurement for stone pitching shall be the square metre of stone pitching calculated from the drawings or as specified by the
Engineer, and shall include compensation for a concrete bed where required.
The tendered rates for stone pitching shall include full compensation for all labour, plant, material, formwork, concrete, stone and other incidentals
as may be required and specified on the drawings.
Measurement and payment for gabion linings shall be as per item C11.2.3 of Chapter 11.
C3.3.9 Formwork to cast in situ concrete lining for open drains (Class F2 surface finish):
C3.3.9.1 To sides with formwork on the internal face only square metre (m2)
C3.3.9.2 To sides with formwork on both internal and external faces (each face measured) square metre (m2)
C3.3.10 Sealed joints in concrete and stone pitched linings of open drains (description of each metre (m)
type with reference to drawing)
The unit of measurement shall be the metre of completed joint of each type.
The tendered rate shall include full compensation for the supply of all materials and for all labour, formwork and incidentals necessary for sealing
the joint as shown on the drawings or required in the Contract Documentation.
C3.3.11 Concrete screed or backfill below chutes (thickness and class of concrete indicated) cubic metre (m3)
The unit of measurement shall be the cubic metre of concrete screed or backfill as may be specified by the Engineer to be placed below chutes.
The tendered rate shall include full compensation for furnishing, procuring and placing the concrete in screed or backfill.
C3.3.12 Reinforcement:
C3.3.13 Polymer film sheeting (thickness specified) for concrete-lined open drains square metre (m2)
The unit of measurement shall be the square metre of area covered with polymer film sheeting.
The tendered rate shall include full compensation for procuring, furnishing and installing the polymer film sheeting, including wastage and overlap.
C3.3.14 Cutting bituminous surfacing and pavement layers for concrete kerbing, channeling metre (m)
or concrete-lined drains
The unit of measurement shall be the metre of bituminous surfacing and pavement layers cut where specified by the Engineer. The depth of
various layers shall not be measured separately for payment.
The tendered rate shall be regarded as an extra over to include full compensation for all labour, plant and materials required for cutting the
surfacing and pavement layers to the required depth of the kerbs, channels or drains, special excavation, and protecting and keeping the surfacing
clean, all as specified. The normal excavation and removing and disposing of the debris as required for kerb or channel installation shall be
deemed included in the normal price for such kerbs and channels, as measured elsewhere.
C3.3.16 Demolition and removal of existing kerbs and/or channel (specify maximum size) cubic metre (m3)
The unit of measurement shall be the cubic metre of material demolished measured in situ before demolition or excavation, but including any
cementitious bedding removed with the kerbs and channels. Alternatively, the volume of debris will be calculated as 70 % of loose volume
measured in haulage vehicles.
The tendered rate shall include full compensation for breaking up the existing kerbs and/or channel to a specified maximum size, of 300 mm x
300 mm removal from site to an approved spoil site, clearing the excavation of all loose debris and to backfill the excavation where new concrete
is not required. Loading and hauling, if any, will be paid under Section C1.7 of Chapter 1.
CONTENTS
D3.3.1 SCOPE
D3.3.2 GENERAL
D3.3.3 PERFORMANCE GUARANTEE REQUIREMENTS
D3.3.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D3.3.5 VISUALLY ASSESSED PROPERTIES
D3.3.6 INSTRUMENTALLY ASSESSED PROPERTIES
D3.3.7 EVALUATION FOR ACCEPTANCE
D3.3.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D3.3.9 NOTIFICATION OF REMEDIAL WORK
D3.3.10 REMEDIAL WORKS
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 4: EARTHWORKS AND PAVEMENT LAYERS: MATERIALS ................................................................ 1
4.1 BORROW MATERIALS ......................................................................................................................................... 1
PART A: SPECIFICATIONS ................................................................................................................................................................................. 1
PART B: LABOUR ENHANCEMENT .................................................................................................................................................................. 27
PART C: MEASUREMENT AND PAYMENT ...................................................................................................................................................... 28
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ......................................................................................................................... 35
CONTENTS
PART A: SPECIFICATIONS
A4.1.1 SCOPE
A4.1.2 DEFINITIONS
A4.1.3 GENERAL
A4.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A4.1.5 MATERIALS
A4.1.6 CONSTRUCTION EQUIPMENT
A4.1.7 EXECUTION OF THE WORKS
A4.1.8 WORKMANSHIP
A4.1.2 DEFINITIONS
The relevant definitions in Chapter 1 shall also be applicable to this section. Additional definitions for this Section are listed below.
Borrow or sourced material - any road construction material obtained from borrow pits and quarries which is compliant for the construction of
earthworks and road pavement layers. The purpose of a borrow pit or quarry is to borrow or source or procure the material, or to win the material
as defined in the South African Minerals and Petroleum Act. Borrowing or sourcing material from borrow pits and quarries requires statutory
authorisation and approval in South Africa.
Borrow pit area or quarry area - an area clearly defined by physical boundaries, that delineate the overall area within which the sourced material
is to be excavated, stockpiled and produced.
A4.1.3 GENERAL
A4.1.3.1 Employer identified borrow pits and quarries
Borrow materials shall be obtained from sources listed and described in the Contract Documentation for which the required statutory authorisation
and approvals have been obtained by the Employer to source the materials.
The geotechnical information provided for the borrow pits and the quarries reflects the results of site investigations including the excavation of trial
pits and/or drilling, and laboratory tests conducted by or on behalf of the Employer. This information is indicative of, but not confirmation of, the
sufficiency in quantity and quality of the material. The provision of this information shall not in any way be construed as limiting the obtaining of
material from the borrow pit or quarry areas and/or to the depth of working shown on the drawings. However, borrow pits and quarries shall not
be extended beyond the limits shown on the drawings without prior written approval by the authority that authorised the use of the borrow pit or
quarry.
The decision as to which material sources the Contractor shall use at any time shall rest with the Employer or the Engineer. The Contractor shall,
at any stage of the work, use the approved source of supply that is the most compliant with regard to the quality and quantities of the various types
of available materials and the ultimate cost of the works to the Employer. The Employer shall also have the right at any stage during the
construction period to identify new borrow pits and quarries, and to have them approved by the relevant authority.
The Contractor shall be instructed by the Employer and/or the Engineer as to the applicable usage of materials, always employing the best
economic alternative (lowest construction cost in terms of tendered rates) after taking cognizance of the following:
• Quality of the material,
• Haulage distance,
• Hardness of the material, and
• Overburden removal and re-use for rehabilitation of the borrow pit.
The Contractor shall not use borrow material for any purpose other than for the execution of the contract. Material shall not be disposed of,
whether processed or not, either by sale or donation to any person without the written authorisation of the Employer.
On completion of the construction works, the Employer or his agent shall apply for a borrow pit or quarry closure certificate. The application shall
consist of the required reports compiled by or on behalf of the Employer, and the closure plan compiled by the Contractor.
A4.1.5 MATERIALS
A4.1.5.1 General
The material specifications in Clause A4.1.5 are the required specifications for the materials constructed on the road, or for the materials produced
as applicable.
The materials shall also not contain any visible materials of the following:
• Organic materials, grass and shrubs,
• Wood chippings, tree bark, and roots,
• Plastic (bags, polystyrene and so forth),
• Refuse or other non-compliant material,
• Free asbestos, or
• Any of the hazardous material listed in Clause A4.5.5.5.
The relevant test methods related to the material specifications and control thereof are listed in Clauses A20.1.3.2, A20.1.4 and A20.1.5 of
Chapter 20 with mention of special tests in Clause A20.1.6. Any ambiguity concerning the relevance and the need for additional test methods
shall be brought to the attention of the Engineer for a ruling.
SANS 3001-GR1: Wet preparation and particle size analysis, shall be mandatory and the default test method for the material grading.
SANS 3001-GR2: Dry preparation and dry particle size analysis of gravels and sands, shall only be used for the grading on clean non-plastic
sands, gravels and crushed stone for a quick indicator or where the fines are not critical.
Amphibolite
Andesite
Anorthosite
Basalt Quartz very scarce or absent. The end products of
Diabase decomposition are clay minerals of the smectite group,
Dolerite particularly montmorillonite. These rocks are more
Basic crystalline rocks
Gabbro susceptible to decomposition than all others and require
Greenschist the most careful assessment of durability, particularly
Norite where Weinert N ≤ 5.
Peridotite
Phonolite
Serpentinite
Felsite (quartz porphyry)
Orthoclase and quartz are the two major components
Gneiss
except in syenite. The end product of decomposition is
Granite
Acid crystalline rocks kaolinite, mostly with quartz, and a smectite stage is
Pegmatite
absent. May require special attention when used where
Rhyolite
Weinert N ≤ 2.
Syenite
Chert Composed almost entirely of quartz or amorphous
Hornfels silica. Disintegration is the only mode of weathering.
High silica rocks
Quartzite These rocks are the most durable of all road building
Vein Quartz materials.
Arkose
Quartz grains in different kinds of matrix. Cementing of
Conglomerate
matrix determines largely the suitability as road building
Gritstone
Arenaceous rocks material. All members are sedimentary rocks.
Mica schist
Disintegration is the predominant form of weathering in
Quartzitic sandstone
all environments.
Sandstone
A4.1.5.4 Sand, normal and coarse fill material in the earthworks layers
Compliant sand fill shall have a CBR ≥ 7 % and a swell ≤ 1 % at 100 % of MDD.
The CBR of compliant normal and coarse fill shall comply with the requirements in Table A4.1.5-2.
Table A4.1.5-2: Requirements for normal and coarse fill
Position of the roadbed below the final road surface CBR and swell
Within the material depth of: ● 1 200 mm for freeways, major interurban roads, rural
and urban arterials. (Class 1/Category A roads).
● 1 000 mm for interurban collectors, major rural roads,
major commercial roads, urban arterials. (Class 2/
Category B roads).
CBR ≥ 7 % at 93 % of MDD.
● 800 mm for lightly trafficked rural and urban collector
Swell ≤ 2 % at 100 % of MDD.
and distributor roads, bus routes and commercial
roads. (Class 3 and 4/Category C roads).
● 600 mm for low volume roads, rural local roads, and
urban local residential streets carrying few heavy
vehicles. (Class 5/Category D roads).
CBR ≥ 3 % at 93 % of MDD.
Below the applicable material depth up to 10 m.
Swell ≤ 2 % at 100 % of MDD.
The normal and coarse fill materials may contain inactive clay and silt, provided that the CBR strength requirements are complied with.
Type of material
Property
G7 G8 G9
All materials
SOIL CONSTANTS except PI ≤ (3xGM) + 10.
ON THE P0,425 calcrete
FRACTION (= % passing
the 0,425 mm sieve)
Calcrete PI ≤ 20.
Note:
(1)
The minimum CBR requirement shall be increased to 18 % at 93 % of MDD for an otherwise compliant G7 material that requires modification
such as lime treatment or mechanical modification to bring the CBR within specification.
50 100 100
20 61 – 91 61 – 91
GRADING
14 48 – 82 None specified. 48 – 82 None specified.
ENVELOPE
5 31 – 66 31 – 66
2 20 – 50 20 – 50
0,425 10 – 30 10 – 30
0,075 5 – 15 5 – 15
GRADING MODULUS (GM) None specified 1,75 (base) / 1,5 (subbase) – 2,5. None specified 1,75 (base) / 1,5 (subbase) – 2,5.
(a) All materials except calcrete: (a) All materials except calcrete: (a) All materials
LL ≤ 25. LL ≤ 30. except calcrete:
PI ≤ 6. PI ≤ 10. PI ≤ 2GM + 10.
LS ≤ 3 %. LS ≤ 5 %. LS ≤ 7 %.
SOIL CONSTANTS ON THE (b) Calcrete: (b) Calcrete: (b) Calcrete:
P0,425 FRACTION(1) LL 30. LL 45. LL ≤ 45.
(= % passing the 0.425 mm sieve) PI 8. PI 15. PI ≤ 15.
LSM 170. LS 6 %. LS 6 %, or
LSM 320. LSM ≤ 320, whichever
is the more stringent
requirement.
CBR ≥ 45 % at 95 %.
STRENGTH (CBR at % of MDD) Except In the dry western parts of Southern Africa
CBR ≥ 80 % at 100 %. (Weinert N ≥ 10) and when the E80s < 3 million, then CBR ≥ 25 % at 95 %.
the subbase CBR ≥ 25 % at 95 % provided that
the base thickness ≥ 150 mm.
Note:
(1)
The LS and the LSM shall be the primary soil constants for acceptance control of calcrete, and the PI for all other materials.
Sound(1), clean(2), unweathered(3) Sound(1), clean(2) rock and Sound(1), rock and boulders, or
PARENT MATERIAL
high quality rock. boulders. coarse gravel.
Only fines crushed from the same May contain up to 10 % by mass May contain up to 15 % by mass of
sound parent rock may be added for of approved natural fines not approved natural fines not obtained
grading correction provided that added necessarily obtained from the from the same parent rock. Added
ADDITIONAL FINES
fines shall have a LL ≤ 25 and a PI ≤ 4. same parent rock. Added fines fines shall have a LL ≤ 25 and a
The quantity of fines shall not exceed shall have a LL ≤ 25 and a PI ≤ 6.
10 % by mass. PI ≤ 6.
10 % Fines Aggregate Crushing Value (10 % FACT) and Aggregate Crushing Value (ACV)
AGGREGATE STRENGTH
specified in table A4.1.5-6
FLAKINESS INDEX Flakiness index ≤ 35 on all individual fractions above 14 mm.
For crushed materials at least 50 % by mass of the individual fractions
FRACTURED FACES All faces shall be fractured faces. retained on each standard sieve 5 mm and larger shall have at least one
fractured face.
(a) All materials except calcrete:
LL ≤ 25.
Fraction E80s > 15 million E80s ≤ 15 million PI ≤ 6.
smaller than LL ≤ 25. LS ≤ 3 %.
SOIL PI ≤ 6.
LS ≤ 3 %. (b) Calcrete:
CONSTANTS
LL ≤ 25. LL ≤ 30.
0,425 mm PI = NP. PI ≤ 4. PI ≤ 8.
LS ≤ 2 %. LSM ≤ 170.
0,075 mm PI ≤ 8 PI ≤ 12 PI ≤ 12.
MAXIMUM PARTICLE SIZE 37,5 mm 37,5 mm 28 mm
Crushed stone for G1 and G2 material shall not be processed from the following rock groups:
• Arenaceous rocks except quartzitic sandstone.
• Argillaceous rocks.
• Pedogenic materials, including calcrete.
10 % FACT ACV
Rock group
(dry) (maximum)
(minimum)
Diamictites 200 kN 21 %
Calcrete 80 kN 29 %
Note:
(1)
When there is a contradiction between the 10 % FACT and the ACV test results about the acceptance of the material, the Engineer shall
instruct whether the material shall be evaluated for acceptance on the 10 % FACT or on the ACV test results.
A4.1.5.9 Sand in fill and pavement layers of sealed low volume roads
Natural untreated sand in the fill and pavement layers of sealed low volume roads shall comply with the requirements in Table A4.1.5-7.
Table A4.1.5-7: Requirements for natural untreated sand in sealed low volume road layers(1)
Property Base and shoulder(2) Subbase Selected Fill
% Passing 2 mm 95 – 100
ACV ≤ 29 %, or
STRENGTH(1) 10 % FACT (dry) ≥ 100 kN and the
wet/dry ratio ≥ 75 %
Sieve
Percentage passing by mass Percentage passing by mass Percentage passing by mass
size(mm)
28 0–5 0 – 50 85 –100
20 0 0 – 25 0 – 30
14 0 0-5 0-5
Note:
(1)
When there is a contradiction between the 10 % FACT and the ACV results about the acceptance of the material, the Engineer shall instruct
whether the material shall be evaluated for acceptance on the 10 % FACT or on the ACV test results.
b) Fine aggregate
The fine aggregate in a dry-bound, waterbound or penetration macadam layer shall comply with the requirements in Table A4.1.5-9.
Table A4.1.5-9: Requirements for fine aggregate in a macadam layer
Property Requirement
Percentage passing
Sieve size (mm)
by mass
0,075 10 – 20
LL ≤ 25
SOIL CONSTANTS ON THE P0,425
FRACTION (= % passing the 0,425 mm PI ≤ 6
sieve)
LS ≤ 3 %
The slurry material for a slurrybound macadam is covered in Chapter 10: Surface Treatments.
Sand shall not be used for untreated shoulder material due to its high erodibility, except for low volume roads in dry areas (Weinert
N ≥ 10), and it shall also not be used when the sand does not conform to the base layer sand specification in Table A4.1.5-7.
LL 30 - 65 22 - 48 20 - 40 18 - 36
Notes:
(1)
LS between 2,0 and 2,6 may cause slight looseness and dust.
(2)
LSM between 70 and 100 may cause slight looseness and dust.
(3)
A minimum APV of 14 % is permissible if the AFV ≥ 75 %.
50 100
37,5 74 – 100
28 56 – 98
14 42 – 69
5 25 – 37
2 15 – 20
0,425 4–9
0,075 0–4
0,150 5 – 25
0,075 0–5 0 – 10
3. Percentage secondary minerals as in the publication “The natural road Durability lines in Table 11 on page 95
construction materials of Southern Africa”, by HH Weinert of the publication
Notes:
(1)
Tests to be carried out in sequence of numbering. Results in a set to be assessed, thereafter samples that fall way
below (or above) the limiting values shall be disqualified without further testing.
(2)
i) 10 % FACT can be estimated from the Aggregate Impact Value (AIV) (test method BS 812-112:1990):
10 % FACT = 10(2,915 – 0,03AIV)
ii) After soaking, rinse aggregates with water followed by immediate towel drying and air drying at temperatures not exceeding
70 °C.
(3)
i) Gradings of samples shall be identical.
ii) Soaking only of material retained on the 2,0 mm sieve.
iii) After soaking, rinse and dry material as for 10 % FACT.
(4)
Spot Counting test to be carried out by an experienced geologist.
In areas where Weinert N ≤ 2, all crushed stone bases to be constructed with material derived from basic crystalline rocks
shall be treated with lime, irrespective of the smectite content.
Diamictites 70 125 35
Calcrete 60 480 40
Notes:
(1)
Materials with a 10 % FACT wet to dry ratio of less than the minimum ratio, except for calcrete, may be used, provided that the
soaked value is equal to or more than the specified dry limit in Table A4.1.5-6.
G5B 90 kN I or II
G6 80 kN I or II
Mudrock shall not be used for material types G3 to G5A, unless approved by an experienced road materials specialist.
Acids pH ≥ 6,0
• Base and subbase material with the EC > 0,15 S/m can be used, provided that the pH of the material is within specification or treated with
lime to specification, if required, and that precautionary measures are prescribed by an experienced road materials specialist.
• Where the material is not compliant on both the EC and pH evaluations, the material shall only be considered for use by the Engineer when
it has been evaluated and the material has been recommended fit for use by an experienced engineering geologist or road materials
specialist.
c) Micas
Crushed stone base aggregates shall not contain more than 2 % by mass of free mica, especially muscovite, when assessed by visually separating
the particles, or more than 4 % by volume when assessed by means of microscopic slides. Other road pavement material that contains free mica
that can be detected with the naked eye shall not be used, unless its durability (density reduction, CBR and/or ITS strengths and wet-dry durability)
has been evaluated and the material has been recommended fit for use by an experienced engineering geologist or road materials specialist.
4. Other layers and materials 370 mS/m 2400 mg/l 4,0 – 10,0 -
Note:
(1)
Siemens per metre (S/m) is the standard SI unit. The salinity of water can also be expressed in milligram per litre (mg/ℓ) or percentage (%). The
relationships between the units are: 1 000 mg/ℓ = 0,1 % = 150 mS/m.
Purified waste water, also known as effluent, and water from other sources that may contain visible quantities of physical and aesthetical, chemical
or organic determinants expected to have a detrimental effect on the road layers, can be considered for the construction of the earthworks and
the road pavement layers, provided that it complies with the requirements in the above table. In addition, for chemical stabilised layers, the
stabilised material shall comply with the strength requirements for UCS and ITS at extended 28-day curing periods and the durability (WDD)
requirements specified in Table A4.4.5-2. Water containing raw sewage shall not be used anywhere in the construction.
The use of brackish water and sea water can be considered for the compaction, provided that the saline water shall be used instead of the
prescribed distilled water in the pH and EC tests and that the requirements for soluble salts in Table A4.1.5-18 shall not be exceeded, except with
recommendations by an experienced road materials specialist and proved in a trial experimental section. Brackish water and seawater shall not
be used for the curing of any stabilised layer.
Turbid water can be used for compaction without further testing in addition to the tests specified in Table A4.1.5-19, except for crushed stone
bases where strict requirements for the PI and the P0,075 apply. In this instance, a sample shall be prepared of the crushed stone material mixed
with the required quantity of turbid water to reach optimum moisture content. After drying out of the material, the PI and P0,075 shall be tested
and evaluated for compliance with the specified limits in Table A4.1.5-5.
Effluent, brackish water and sea water shall not be used for bituminous stabilisation or for diluting a bitumen emulsion, unless the use of the water
has been approved in writing by the supplier.
A4.1.7.3 Stockpiles
a) Preparation of the stockpile site
Stockpile sites shall be prepared in positions as indicated on the borrow pit or quarry plans, or at positions agreed to and indicated on the M&U
plans.
Before any stockpiling may be done the area shall be cleared and grubbed as specified in Section A1.6 of Chapter 1. The area to be cleared and
grubbed shall be 2,0 m wider than the footprint of the stockpile or to 2,0 m beyond the outer edge of temporary banks and dykes, as applicable.
Topsoil and overburden material can remain in place, except when it has insufficient bearing strength for the height of the stockpiled material or
where a platform of fill material must be constructed. The topsoil shall then be removed and stockpiled in an area that will not be affected by
construction activities nor impede the natural flow of water. The stockpiled topsoil and its immediate surrounds shall be kept free of all undesirable
vegetation.
Trees and tree stumps shall be removed to 75 mm below the cleared surface.
Stockpile areas shall be constructed with a minimum slope of 2 % to ensure proper drainage. The surface (floor) shall be scarified to a depth of
150 mm, watered, and compacted to a minimum density of 90 % of MDD. Further instructions will be given for the treatment of soft in situ material
with low bearing strength, in accordance with the roadbed treatments specified in Section A5.1 of Chapter 5.
On steep sloping landforms, a platform shall be constructed so that the cross fall does not exceed 5 %. The platform shall be constructed of fill material
in layers compacted to a minimum density of 90 % of MDD. The compacted surface for stockpiling shall be firm and clean of loose material.
Stockpile areas shall be large enough to allow the different types of material to be stockpiled without overlapping or exceeding the limits of the borrow
pit or quarry area or indicated stockpile area.
The Contractor shall ensure that stockpiled material is not washed away during rain. Temporary banks must be constructed on the high side of
stockpiles to divert surface water. Care must also be taken to prevent water from damming up against the stockpiles. On the lower side of the stockpile
material, temporary banks with stormwater outlets shall be constructed to contain any stockpile material that is washed down during rain.
The Contractor shall only commence the stockpiling activities after the areas have been prepared and approved by the Engineer.
b) Stockpiling of the material
The material shall be off-loaded and spread uniformly in layers in the stockpile. Segregation of the material during the handling shall be avoided.
The different material stockpiles shall be sign posted according to the material type and intended use.
A4.1.8 WORKMANSHIP
The Engineer and the Contractor shall determine and agree on the testing protocol and frequency of the applicable process and quality control
tests required for each type of the sourced borrow materials to ensure that the quality of materials produced meets the specified requirements for
the particular road pavement layer for which it will be used. These required laboratory tests and testing frequencies shall be stated in the borrow
pit and quarry M&U plans.
Measurement, testing, and evaluation of all individual components and constructed products shall be in accordance with the methods prescribed
in this Section or in Chapter 20 as relevant.
CONTENTS
B4.1.1 SCOPE
B4.1.2 DEFINITIONS
B4.1.3 GENERAL
B4.1.5 MATERIALS
B4.1.1 SCOPE
This Section covers the work involved in sourcing materials from borrow pits and quarries that are developed and operated to supply materials for
a specific road construction project or projects.
A relatively small proportion of activities as defined in Part A under the various sections are considered suitable for labour enhancement.
Part B only provides additional specifications, not contained in Part A.
B4.1.2 DEFINITIONS
Definitions as provided in Chapter 1 and Clause A4.1.2 shall also apply.
B4.1.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B4.1.5 MATERIALS
The provisions of Part A shall apply.
B4.1.8 WORKMANSHIP
The provisions of Part A shall apply.
C4.1.1.1 For borrow pits (list all borrow pits separately) number (No)
The unit of measurement shall be the number of compiled M&U plans for borrow pits and quarries.
The tendered rates shall include full compensation for gathering all information and compiling the plans, for topographical surveys and for ensuring
the implementation of the plans during the operation of the borrow pit or quarry.
C4.1.2.1 Cost of additional trial pits and/or drilling and laboratory testing provisional sum
C4.1.2.2 Handling costs and profit in respect of item C4.1.2.1 percentage (%)
C4.1.3.3 Handling cost and profit in respect of item C4.1.3.2 percentage (%)
The unit of measurement for item C4.1.3.1 shall be the kilometre of temporary unsealed haul and access roads constructed in the contract.
The tendered rate for item C4.1.3.1 shall include full compensation for all loading and hauling material, constructing the completed road,
maintaining it including watering for dust control, removing the road, banks and dykes at the end of its use and for revegetation.
Any haul costs shall be included in the tendered rate of item C4.1.3.1.
Drainage culverts and fencing shall be measured separately.
Item Description
Unit
C4.1.4 Removing of the overburden
C4.1.4.2 In quarries:
C4.1.5 Excavating of materials in the borrow pits and quarries, material obtained from
The unit of measurement in each class of excavation shall be the cubic metre of material excavated.
The quantities shall be measured in place in the compacted earthworks or pavement layers. The quantities shall not include excess material,
overfill material or additional material placed for bulking (settlement during compaction).
The quantities for earthworks shall be measured from the difference between surveyed cross sections at 20 m maximum intervals taken before
and after the construction of the earthworks.
The quantities for pavement layers shall be calculated from the authorised dimensions of the layers. Where the pavement layer materials are
placed in stockpile for some time before used on the road, the Engineer and the Contractor shall agree on the interim method of measuring the
quantities for this item.
Item Description
Unit
C4.1.6 Providing crushing, screening and related plants
C4.1.6.5 Etc, for other plants (as stated by the Engineer and/or the Contractor) number (No)
The unit of measurement shall be the number of complete plants supplied and erected on the project.
The tendered rates shall include full compensation for providing the plant, transporting the plant to the project, erecting, commissioning and finally
dismantling it, and removing it when it is no longer required for the project.
Payment of this item shall be made in two instalments as follows:
• The first instalment, 85 % of the tendered rate, shall be paid after erection and commissioning of the plant.
• The final instalment, 15 % of the tendered rate, shall be paid after removal of the plant from the contract.
C4.1.7.5 Etc, for other plants (as stated by the Engineer and/or the Contractor) cubic metre (m3)
The unit of measurement shall be the cubic metre of material crushed or crushed and screened and finally used in the construction.
The quantity shall be measured in place in the compacted earthworks or pavement layers. The quantities shall not include excess material,
screened out material that is not used in the works, overfill material, or additional material placed for bulking (settlement during compaction).
The quantities for earthworks shall be measured from the difference between levelled cross sections at 20 m maximum intervals taken before and
after the construction of the earthworks.
The quantities for pavement layers shall be calculated from the authorised dimensions of the layers.
Where the materials are placed in stockpile for some time before used on the road, the Engineer and the Contractor shall agree on the interim
method of measuring the quantities for this item.
The tendered rates shall include full compensation for hauling the material from the excavation to the producing plant, for off-loading and producing
the material. The cost of loading the material at or in the excavation shall be included under item C4.1.5.
No haul shall be paid separately for moving material on the same borrow pit or quarry area. Hauling shall only be paid for material moved from
another borrow pit or quarry area than where the crushing and screening plant are located. Haul shall then be measured from the point where the
material is loaded to where it is off-loaded.
Item Description Unit
C4.1.8 Moving and re-erecting the crushing, screening and related plants on the site
C4.1.8.5 Etc, for other plants (as stated by the Engineer and/or the Contractor) number (No)
C4.1.10 Compacting the floor of the stockpile sites cubic metre (m3)
C4.1.11 Constructing a platform for the stockpile site cubic metre (m³)
The unit of measurement shall be the cubic metre of compacted fill in the platform.
The quantity shall be measured in place at the platform, from the difference between levels taken after compaction of the stockpile floor and levels
taken after the construction of the platform.
The tendered rate shall include full compensation for excavating the material on the stockpile site or elsewhere on the borrow pit or quarry area,
moving or loading and hauling the material, for off-loading, and for placing, mixing, watering and compacting the fill material in the platform.
No difference shall be made between different types of fill material.
Any haul costs shall be included in the tendered rate of item C4.1.11.
Item Description Unit
C4.1.13 Removing surplus material from the stockpile cubic metre (m3)
The unit of measurement shall be the cubic metre of stockpiled material not used.
The quantity shall be measured in the haul vehicles by taking the volume to be the equivalent of 70 % of the loose volume of the material in the
haul vehicles.
The tendered rate shall include full compensation for loading and hauling the material to the borrow pit or the quarry or a designated site, for off-
loading and spreading the material.
Material shall be considered as surplus only when an instruction was given to stockpile the material or where the stockpile material was placed
by others. Removal of surplus material resulting from over production by the Contractor shall not be measured and paid.
No haul shall be paid separately for moving material within the same borrow pit or quarry area. Hauling shall only be paid for material moved to a
designated site not at the same borrow pit or quarry area. Haul shall then be measured from the point where the material is loaded to where it is
off-loaded.
C4.1.14 Removing the fill platform and temporary banks at the stockpile sites upon completion
C4.1.15 Shaping and finishing the borrow pit and quarry areas, and the stockpile sites
C4.1.15.1 Shaping and finishing the borrow pit and quarry areas, and the stockpile sites:
(a) Borrow pits (list all borrow pits separately) hectare (ha)
C4.1.15.2 Finishing of the borrow pit and quarry areas, and the stockpile sites using labour enhanced
methods of construction:
(a) Borrow pits (list all borrow pits separately) hectare (ha)
The unit of measurement shall be the hectare of area shaped and finished.
The quantities shall be measured from topographical surveys, measured in plan.
The tendered rates for borrow pits and quarries shall include full compensation for shaping and finishing the sides and floor of the excavation to
the specified slopes and gradients, forming smooth contours using soft material, placing of spoil or excess material in the floor and covering it,
removing all excess material, reconstructing temporary berms or constructing new berms, and final preparation of the slopes prior to the topsoiling
and revegetation operations.
Replacing overburden not used in the works in the borrow pit or quarry and levelling of the material are included in item C4.1.4.
The tendered rate for stockpile sites shall include full compensation for ripping and shaping the stockpile floor to the original contours.
Measurement and payment to remove any surplus material, the fill platform and the temporary banks shall be made under items C4.1.13 and
C4.1.16 Personnel
The unit of measurement shall be the time in month (or part thereof) that the respective personnel are employed on the contract to carry out the
specified duties.
The tendered rates shall include full compensation to cover the full cost of the respective personnel including all overhead charges and profit,
bonuses, subsistence, allowances, Contractor’s contributions, insurances, accomodation and vehicles for transport.
The unit of measurement for item C4.1.17.1 shall be the lump sum.
The tendered rate for item C4.1.17.1 shall cover the cost for providing and erecting the weighbridge and the weighbridge office including all fittings,
for the power supply, and for providing and calibrating the scale equipment as specified and for the required computer hardware and software.
Payment of the item shall be made in two instalments:
• The first installment, 85 % of the lump sum, shall be paid after the weighbridge is commissioned.
• The final installment, 15 % of the lump sum, shall be paid when the weighbridge and office are removed from the contract.
The unit of measurement for item C4.1.17.2 shall be the time in months or part thereof that the weighbridge facility is operational and used for the
works.
The tendered rate for item C4.1.17.2 shall cover the cost for operating and maintaining the weighbridge, including the cost of the weighbridge
operator and all incidentals.
Item Description Unit
C4.1.18.2 Handling costs and profit in respect of item C4.1.18.1 percentage (%)
WHERE CRUSHED STONE MATERIAL IS EXCAVATED, PRODUCED AND STOCKPILED FOR USE ON OTHER PROJECTS, THE ITEMS
HEREUNDER SHALL APPLY.
C4.1.20.2 Multi-stage crushing and screening cubic metre (m3) or ton (t)
C4.1.21 Stockpiling the crushed material cubic metre (m3) or ton (t)
The unit of measurement for every item shall be either of the following as specified in the Contract Documentation:
• The volume of loose material measured in the stockpile, or
• The mass of the material in the stockpile as determined by a weighbridge.
DRAFT STANDARD (DS) OCTOBER 2020 4-33
The tendered rate for item C4.1.19 shall include full compensation for excavating and loading the material.
The tendered rate for item C4.1.20 shall include full compensation for hauling the material from the excavation to the crushing plant, for off-loading
and producing the material.
The tendered rate for item C4.1.21 shall include full compensation for loading the material at the producing plant, hauling the material to the
stockpile, and for off-loading, spreading and maintaining the material in the stockpile.
No haul shall be paid separately for moving material within the same borrow pit or quarry area. Hauling shall only be paid for material moved to a
crushing plant not located at the same borrow pit or quarry area from where the material is excavated, or where the stockpile site is not located at
the producing plant. Haul shall then be measured from the point where the material is loaded to where it is off-loaded.
CONTENTS
D4.1.1 SCOPE
D4.1.2 GENERAL
CONTENTS
PART A: SPECIFICATIONS
A4.2.1 SCOPE
A4.2.2 DEFINITIONS
A4.2.3 GENERAL
A4.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A4.2.5 MATERIALS
A4.2.6 CONSTRUCTION EQUIPMENT
A4.2.7 EXECUTION OF THE WORKS
A4.2.8 WORKMANSHIP
A4.2.2 DEFINITIONS
The relevant definitions in Chapter 1 and Clause A4.1.2 shall also be applicable to this Section. Revised or additional definitions for this Section
are listed below.
Cuttings - are shallow or deep excavations made in the in situ material required for the construction of the road within the road reserve where the
road level results in a cutting slope or batter to be constructed and finished. Further or additional excavations, also referred to as under cuts,
below the road pavement layers to remove unsuitable stable material in the same excavation operation within the cutting shall be deemed part of
the cutting excavation.
Box cuts - are shallow excavations made in the in situ material required for the construction of the road pavement layers below the natural ground
level. Additional or further excavations, also referred to as under cuts, below the pavement layers to remove unsuitable stable material in the same
excavation operation within the box cut shall be deemed part of the box cut excavation. Box cuts are backfilled with the pavement layer, fill or with
other compliant material. Unlike cuttings and designated excavations, box cuts do not have side slopes that must be finished.
Cut material - any material excavated from cuttings, box cuts or designated excavations.
Designated excavations - are excavations for open drains and channels, canals including channels to direct the course of water flow, that can
yield compliant material for use in the works. The excavation criteria for open drains and channels to be classified as designated excavations are
provided in Table A3.1.7.2-1 of Chapter 3.
A4.2.3 GENERAL
A4.2.3.1 Employer requirements
The geotechnical information provided for the cuttings, box cuts and designated excavations reflects the results of site investigations including the
excavation of trial pits and/or drilling, and laboratory tests conducted by or on behalf of the Employer. This information is indicative of, but not
confirmation of, the sufficiency in quantity and quality of the material.
A4.2.5 MATERIALS
A4.2.5.1 General
The specifications given in Clause A4.1.5 shall also apply to cut materials and are the required specifications for the cut material as finally
processed and constructed on the road.
A4.2.7.2 Stockpiles
The preparation of the stockpile site, stockpiling of the material and reinstatement of the stockpile site shall be done in accordance with the
requirements of Clause A4.1.7.3.
Unless the material being obtained from cuttings, box cuts and designated excavations is very variable a full time stockpile controller is not
necessarily required.
A4.2.8 WORKMANSHIP
The Engineer and the Contractor shall determine and agree on the testing protocol and frequency of the applicable process control tests required
for each type of the sourced cut materials to ensure that the quality of materials produced meets the specified requirements for the particular layer
for which it will be used. These required laboratory tests and testing frequencies shall be stated in the cutting M&U plans.
Measurement, testing, and evaluation of all individual components and constructed products shall be in accordance with the methods prescribed
in this Section or in Chapter 20 as relevant.
CONTENTS
B4.2.1 SCOPE
B4.2.2 DEFINITIONS
B4.2.3 GENERAL
B4.2.5 MATERIALS
B4.2.1 SCOPE
This Section covers the sourcing of materials that can be used for the construction of earthworks and pavement layers from cuttings, box cuts and
designated excavations.
A relatively small proportion of activities as defined in Part A under the various Sections are considered suitable for labour enhancement.
B4.2.2 DEFINITIONS
Definitions as provided in Chapter 1 and Clause A4.2.2 shall apply.
B4.2.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B4.2.5 MATERIALS
The provisions of Part A shall apply.
B4.2.8 WORKMANSHIP
The provisions of Part A shall apply.
The volume referred to in the description shall be the total volume of material in place that must be removed. It includes the volume of topsoil and
overburden, the material compliant for earthworks and pavement layers and any spoil material.
The unit of measurement shall be the number of cuttings for which M&U plans have been compiled. A distinction shall be made between the
various cuttings based on the total volume of material to be excavated in the cutting. When several cuttings between 5 000 m3 and 10 000 m3 are
covered by a representative M&U plan they shall all be measured together as one plan.
C4.2.2.1 Cost of additional trial pits and/or drilling and laboratory testing provisional sum
C4.2.2.2 Handling costs and profit in respect of item C4.2.2.1 percentage (%)
The unit of measurement for items C4.2.3, C4.2.4 and C4.2.5 shall be the cubic metre of material excavated for use on the road.
The volume shall be measured in place in its original position in the cutting, box cut or designated excavation. It shall be calculated from the
difference between levels taken or topographical surveys carried out after the removal of the topsoil, and from levels taken or surveys done after
completion of the excavation of the different material classes. The volume of classified unavoidable overbreak in hard or boulder material shall be
included in the measurement.
For boulder material, the Engineer may approve that the quantities be measured in haul vehicles as an alternative when the boulder material
cannot be identified accurately prior to excavating, by taking the in situ volume of the boulder material as equal to 50 % of the loose volume of the
material in the haul vehicles.
The tendered rates for items C4.2.3, C4.2.4 and C4.2.5 shall include full compensation for breaking down the cut materials in the various classes
to the specified maximum particle sizes, for excavating, and loading the material. Should the Contractor choose for designated excavations to
temporarily place the excavated material next to the excavation for loading later, it shall not be considered as stockpile of material nor shall the
loading be considered as a separate activity for compensation.
The excavation of hard material by blasting shall exclude the cost of blasting, which shall be measured and paid for under item C12.10.1 of
Chapter 12.
The excavating and disposing of unsuitable and spoil material shall be measured and paid for under item C4.2.7 and under item C4.2.8 or C4.2.9
as applicable.
The unit of measurement shall be the cubic metre of material excavated during the widening of existing cuttings.
Widening of existing cuttings shall be a widening more than 2,5 m deep (measured vertically from the top of the cutting to the shoulder breakpoint),
and where the cutting is widened by less than 4,0 m. Widenings of existing cuttings larger than these dimensions shall be measured and paid for
under item C4.2.3.
Measurement of the material shall be in place in the original position in the cutting, and the quantity shall be computed by the method of average
end areas from surveyed cross-sections at intervals not exceeding 20 m measured along the centre line of the road or from topographical surveys,
before and after removal of the material.
For boulder material, the Engineer may approve that the quantities be measured in haul vehicles as an alternative when the boulder material
cannot be identified accurately prior to excavating, by taking the in situ volume of the boulder material as equal to 50 % of the loose volume of the
material in the haul vehicles.
The tendered rates shall include full compensation for breaking down the various classes to the specified maximum particle sizes, excavating, and
loading the material.
The excavation of hard material by blasting shall exclude the cost of blasting, which shall be measured and paid for under item C12.10.1 of
Chapter 12.
The unit of measurement shall be the cubic metre of material removed to spoil in accordance with the Engineer’s instructions.
The volume shall be measured in place in its original position and shall be calculated in accordance with the authorized dimensions.
The tendered rates shall include full compensation for excavating and loading the material in the floor of the excavation, and for disposing the
material. Payment under this item shall only be made when the material is removed in a separate excavation operation after the bulk excavation
is completed on instruction by the Engineer, else the material shall be classified as spoil material and then measured and paid for under item
C4.2.8 or C4.2.9 as applicable.
Haul shall be measured from the point where the material is loaded to where it is off-loaded.
Item Description Unit
C4.2.8 Excavate material to spoil in sites designated by the Employer, material obtained from
C4.2.8.1 Soft excavation, overburden and unsuitable material cubic metre (m3)
The unit of measurement shall be the cubic metre of material excavated and spoiled.
The quantities shall be measured in place in its original position in the cutting, box cut or designated excavation, and shall be computed from
topographical surveys. The Engineer may approve that the quantities be measured in the haul vehicles as an alternative when the quantities of
the spoil material cannot be calculated accurately prior to excavating, by taking the in situ volume of the material in the case of soft excavation as
equal to 70 % of the loose volume of material in the haul vehicles, and in the case of boulder and hard material as equal to 50 % of the loose
volume of material in the haul vehicles.
The tendered rates shall include full compensation for breaking down the various classes to sizes required for hauling, excavating and loading,
and for off-loading and disposing the material, including shaping and levelling-off any heaps of spoil material.
Haul shall be measured from the point where the material is loaded to where it is off-loaded.
Item Description Unit
C4.2.9 Excavate material to spoil in sites designated by the Contractor, material obtained
from
C4.2.9.1 Soft excavation, overburden and unsuitable material cubic metre (m3)
The unit of measurement shall be the cubic metre of material excavated and spoiled.
The quantities shall be measured in place in its original position in the cutting, box cut or designated excavation, and shall be computed from
topographical surveys. The Engineer may approve that the quantities be measured in haul vehicles as an alternative when the spoil material
cannot be identified accurately prior to excavating, by taking the in situ volume of the material in the case of soft excavation as equal to 70 % of
the loose volume of material in the haul vehicles, and in the case of boulder and hard material as equal to 50 % of the loose volume of material in
the haul vehicles.
The tendered rates shall include full compensation for negotiations with the landowner or legal occupant of the property or of the spoil site, for
breaking down the various classes to sizes required for hauling, excavating, loading and hauling the material to the spoil sites irrespective of the
haul distance, for off-loading and disposing the material, and for finishing the spoil site and obtaining the approval of the property or spoil site
owner, if applicable.
The excavation of hard material by blasting shall exclude the cost of blasting, which shall be measured and paid for under item C12.10.1 of
Chapter 12.
The tendered rates shall also include the cost of spoiling at a municipal site, if applicable.
All haul costs shall be included in the tendered rates of item C4.2.9.
C4.2.10.2 Soil cement (stiff mix with 3 % cement) cubic metre (m3)
C4.2.10.3 Soil cement (wet mix with 5 % cement) cubic metre (m3)
The unit of measurement shall be the cubic metre of material used in the backfilling.
The quantities shall be measured from the quantity of material placed in the overbreak.
The tendered rates shall include full compensation for providing the material, and for placing, backfilling and compacting the material in the
overbreak.
Payment for backfilling of overbreak shall only be made when the Engineer approves that the overbreak was unavoidable.
The unit of measurement shall be the cubic metre of oversize material that is broken down.
The quantity shall be measured by the volume of individual boulders or lumps of hard material. Where material is moved for breaking down the
Engineer may approve that the quantity be measured by taking the volume to be equivalent to 50 % of the loose volume in the haul vehicles of
the material to be broken down, as an alternative to measuring the individual volumes.
Breaking down of the cut material to the specified maximum particle sizes in Clause A4.2.7.1h) during the excavation operation or on the road by
construction equipment shall not be measured under this item. Only further breaking down by conventional construction equipment of oversize
cut material, as instructed or approved by the Engineer, shall be measured and paid.
The tendered rate shall include full compensation for breaking down the material.
No distinction shall be made between varies methods of breaking down the oversize material.
No haul shall be paid where oversize material must be moved for breaking down.
C4.2.12.1 Cuttings:
(d) In soft material using labour enhanced methods of construction square metre (m2)
C4.2.12.3 Designated excavations using labour enhanced methods of construction square metre (m2)
The unit of measurement for cuttings shall be the square metre of the finished side slope areas.
The unit of measurement for designated excavations shall be the square metre of the side slope areas and the floor (invert) area where applicable.
The areas shall be measured from topographical surveys, or from tape measurements at 5,0 m cross section intervals where accurate tape
measurements can be undertaken.
The tendered rates for finishing shall include full compensation for finishing the side slopes, and for loading, hauling and disposing of any excess
material arising or brought down during the finishing operations. Placing of topsoil and vegetation shall be measured and paid separately.
Any haul costs shall be included in the tendered rates of item C4.2.12.
Specialised slope protection measures shall be measured and paid in Section 12.9 of Chapter 12.
CONTENTS
D4.2.1 SCOPE
D4.2.2 GENERAL
CONTENTS
PART A: SPECIFICATIONS
A4.3.1 SCOPE
A4.3.2 DEFINITIONS
A4.3.3 GENERAL
A4.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A4.3.5 MATERIALS
A4.3.6 CONSTRUCTION EQUIPMENT
A4.3.7 EXECUTION OF THE WORKS
A4.3.8 WORKMANSHIP
A4.3.2 DEFINITIONS
The relevant definitions in Chapter 1 and Clause A4.1.2 shall also be applicable to this Section. Additional definitions for this Section are listed
below.
Cemented material - also referred to as bound material, is existing stabilised or treated road layer material that can only be removed by milling,
or by pulverising prior to excavation by using conventional road construction equipment.
Milling - a process to break down (pulverise) and remove, all or part of bituminous surfacing layers (seals and asphalt), and/or pavement layers
by a milling machine.
Reclaimed road materials - are obtained by breaking up and excavating material in controlled separate layers from the existing earthworks and
pavement layers and bituminous surfacing layers, producing compliant material by crushing and/or stockpiling it if required, and then hauling or
moving it for use elsewhere on the same road, or on another road project or for other construction purposes.
Reconstructed road materials - are existing layer and bituminous surfacing materials that are scarified or pulverised (broken down) by ripping
or broken down by a recycling machine and then subsequently processed in situ, for the construction of reconstructed road pavement layers.
A4.3.3 GENERAL
A4.3.3.1 Employer identified existing road materials
The road layer information provided in the Contract Documentation for the existing layers reflects the results of trial pits and laboratory tests
conducted by or on behalf of the Employer. This information is indicative of the type of road layer materials and layer thicknesses. The provision
of this information shall not in any way be construed as defining or limiting the extent and thickness of materials nor the quality to be obtained
from the existing road.
A4.3.5 MATERIALS
A4.3.5.1 Reclaimed and reconstructed gravel and crushed stone materials
The specifications given in Clause A4.1.5 for the materials shall also apply to reclaimed and reconstructed gravel and crushed stone materials.
The material requirements for stabilised materials are given in Table A4.4.5-2, and for bitumen stabilised materials in Table A4.4.5-3.
These material specifications are the required specifications for the reclaimed or reconstructed material finally processed and constructed on the
road. The Contractor may be instructed to modify or blend reclaimed or reconstructed material by the addition of some imported material and/or
treatment agents in order to produce a material that complies with the specified material properties.
A4.3.7.4 Milling
Before milling may be commenced, the surface of the existing road shall be cleaned of all vegetation, dirt, recent fuel spillage, road studs and any
other foreign material.
Where the milled material is to be re-used in road pavement layers, the Contractor shall execute trial milling on the various materials to be milled.
Trial milling shall consist of milling one strip not longer than 40 m. Trial milling shall not be required for material that is to be milled to spoil or
re-used for general filling purposes. During the trial milling, the Contractor shall vary the speed of the milling machine, the speed of rotation of the
milling drum and the milling depth, to select the desired optimum milling operation parameters to provide the required material quality and to prove
that the milling machine is fit for purpose. The Engineer shall instruct the depth of milling the layer(s) after the trial milling.
Care shall be exercised to avoid damage to any concrete elements such as bridge expansion joints and joint nosings, manholes, kerbing, kerb
inlets and any other roadside furniture during the milling and the excavation. Damage caused to any element forming part of the permanent works
shall be repaired at no cost to the Employer.
The floor of a milled excavation shall have an even texture without any loose local areas. Loose areas shall be remedied as specified in the
Contract Documentation or as instructed by the Engineer.
The floor of a milled excavation shall be tested in the longitudinal direction with a 3,0 m straight-edge, and in other directions with a straight-edge
of such length as fits between the longitudinal sides of the excavation. The surface of the milled area shall not deviate by more than
7,0 mm from the bottom edge of the straight-edge.
A4.3.7.11 Saw-cutting
When specified or instructed that existing pavement layers are to be saw-cut, the equipment shall be capable of saw-cutting the pavement layers
in a single operation without fragmenting the material, and in straight lines. The depth of saw-cutting shall be specified in the Contract
Documentation or instructed by the Engineer. Requirements for saw-cutting and the construction of joints between existing and new layers are
specified in Clause A5.3.3.7 of Chapter 5.
A4.3.8 WORKMANSHIP
The material properties of the existing road layers shall always be verified by drilling of cores or by additional trial pits in the road and by subsequent
laboratory testing, before any milling and/or excavation is carried out. The depths of the core drilling and trial pits and applicable laboratory tests
shall be determined by the intended use of the material in the existing road, whether the material is to be reclaimed or recycled.
Testing shall be more comprehensive for recycling of layers. The effects of patching and repairs, the variable thickness of layers and the variable
addition of new material may result in the fluctuation of material properties. The impact of the fluctuation of these properties must be properly
managed.
For the recycling of asphalt and/or bound (stabilised) materials, slabs of the materials shall be removed from the road trial pits and then crushed
manually or with a small laboratory crusher to simulate the material produced by the recycler.
Agreement shall be reached with the Engineer on the testing, protocol of the applicable tests and frequency of process control testing on the
existing road materials, to ensure that the quality of the materials meets the specified requirements for the particular layer for which it will be used.
Measurement, testing, and evaluation of all individual components and constructed products shall be in accordance with the methods prescribed
in this Section or in Chapter 20 as relevant.
CONTENTS
B4.3.1 SCOPE
B4.3.2 DEFINITIONS
B4.3.3 GENERAL
B4.3.5 MATERIALS
B4.3.1 SCOPE
This Section covers existing road construction materials that are obtained from reclaiming or reconstructing existing road earthworks, pavement
layers and asphalt materials (whether used as a pavement layer or used as the wearing course).
A relatively small proportion of activities as defined in Part A under the various sections are considered suitable for labour enhancement. Therefore,
Part B only provides additional specifications not contained in Part A.
B4.3.2 DEFINITIONS
Definitions as provided in Chapter 1 and Clause A4.3.2 apply.
B4.3.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B4.3.5 MATERIALS
The provisions of Part A shall apply.
B4.3.8 WORKMANSHIP
The provisions of Part A shall apply.
Producing the material by crushing and screening A4.3.2 Section C4.1 - All applicable items
Stabilising the floor of reclaimed asphalt material stockpile sites A4.3.7.11 C5.4.2 of Chapter 5
C4.3.1.1 Cost of additional core drilling and trial pits, sampling of asphalt and laboratory testing provisional sum
C4.3.1.2 Handling cost and profit in respect of item C4.3.1.1 percentage (%)
C4.3.2.2 Handling costs and profit in respect of item C4.3.2.1 percentage (%)
C4.3.3 Removal of bituminous seal surfacing (thickness not exceeding 30 mm) square metre (m2)
The unit of measurement shall be the square metre of seal surfacing removed separately.
The quantity shall be measured from the authorised dimensions.
The tendered rate shall include full compensation for blading or milling off the existing seal surfacing, and for loading and hauling the material to
spoil sites identified by the Contractor.
All haul costs shall be included in the tendered rate of item C4.3.3.
The removal of a bituminous seal surfacing together with the underlying base layer shall not be measured in this item, but the cost shall be included
with the excavation of the base layer under items C4.3.9 and C4.3.10 respectively.
C4.3.4 Saw-cutting existing materials within the following average depth ranges
The unit of measurement shall be the metre of saw-cut. The length in each depth range shall be measured and paid separately.
The quantities shall be measured from the authorised length of saw-cut, and the depth specified or instructed by the Engineer.
The tendered rates shall include full compensation for saw-cutting the material.
Where asphalt and the underlying layer(s) are both to be saw-cut and the asphalt is less than 50 mm thick, separate measurement and payment
shall not be made for the asphalt saw-cutting in item C4.3.4.1. The asphalt thickness shall then be added to the thickness of the material in items
C4.3.4.2 and/or C4.3.4.3 as applicable.
C4.3.5.1 Small milling machine with a cutting width of 1,2 m or smaller number (No)
C4.3.5.2 Large milling machine with a cutting width exceeding 1,2 m number (No)
The unit of measurement shall be the number of milling machines provided on the site, or the number of times a milling machine is brought onto
the site where it had to be removed temporarily with prior approval. De-establishment and subsequent re-establishment shall also only be
measured if undertaken with prior approval.
The tendered rates shall include full compensation for establishment and for de-establishment of the milling machine.
Payment for returning the machine to the site after removal shall be made only where the removal was in accordance with the Contractor’s
approved programme of work and not for any other reason. Payment shall not be made for replacing any defective plant.
Payment shall also not be made for moving the milling machine around on the site.
Item Description Unit
C4.3.6 Milling and removal of existing asphalt layers with an average milling depth
(Contractor takes ownership)
C4.3.7 Milling and removal of existing asphalt layers with an average milling depth
(Employer takes ownership)
The unit of measurement for items C4.3.6 and C4.3.7 shall be the cubic metre of material milled from the existing pavement.
The quantities shall be computed in accordance with the authorised dimensions of the excavation.
When instructed, split milling and removal of the different existing asphalt layers shall be measured individually.
The tendered rates for item C4.3.6 shall include full compensation for demarcating the excavation, for milling (excavating) the material, for loading
and hauling to a site identified by the Contractor, and for spoil or re-use by the Contractor. All haul costs shall be included in the tendered rates of
item C4.3.6.
The tendered rates for item C4.3.7 shall include full compensation for demarcating the excavation, for milling, loading, hauling and
off-loading the material at a site designated by the Employer. Haul shall be measured from the point where the material is loaded to where it is
off-loaded.
Trial milling shall be measured and paid for under items C4.3.6 or C4.3.7, and no separate payment shall be made for it.
Trial milling shall be measured and paid for under item C4.3.8, and no separate payment shall be made for it.
The unit of measurement shall be the cubic metre of excavated material, by using conventional road building equipment.
The quantities shall be measured in place on the existing road before the excavation commenced.
The tendered rates shall include full compensation for excavating and loading the material.
The tendered rate for cemented material shall include for ripping or pulverising the material prior to excavating.
Item Description Unit
The unit of measurement shall be the cubic metre of excavated material, by using labour enhanced methods of construction.
C4.3.11 Breaking down a stabilised layer by using conventional road construction equipment cubic metre (m3)
The unit of measurement shall be the cubic metre of stabilised material that is broken down, by using conventional road building equipment.
The quantities shall be measured in place on the existing road, from thickness measurements determent by drilling cores or in trial pits.
The tendered rate shall include full compensation for all equipment, labour and supervision to break the stabilised layer. No distinction shall be
made between ripping the material with a grader, or pulverising the material with a recycler or rotary machine.
Measurement and payment in this item shall only be made when the existing material is used in a side-cut to new pavement layer operation. For
excavating the existing material and then remove it to stockpile or to spoil, measurement of item C4.3.9 shall apply that includes the breaking
down by ripping or pulverising.
C4.3.12 Removing of existing concrete material within the following average depth ranges
(b) Exceeding 150 mm but not exceeding 250 mm cubic metre (m3)
(b) Exceeding 150 mm but not exceeding 250 mm cubic metre (m3)
C4.3.13 Lifting of existing paving blocks (specify the type or size and thickness)
(i) In situ concrete kerbing and edge beams cubic metre (m3)
(ii) Precast concrete kerbing (specify type or figure number) metre (m)
(iii) Precast concrete kerbing (specify type or figure number) and situ concrete channel metre (m)
(specify dimensions)
C4.3.14.2 Removing of existing road edging using labour enhanced methods of construction:
(i) In situ concrete kerbing and edge beams cubic metre (m3)
(ii) Precast concrete kerbing (specify type or figure number) metre (m)
(iii) Precast concrete kerbing (specify type or figure number) and situ concrete channel metre (m)
(specify dimensions)
The unit of measurement for items C4.3.14.1(a)(i) and C4.3.14.2(a)(i) shall be the cubic metre of concrete removed.
The unit of measurement for items C4.3.13.1(a)(ii) and (iii) and C4.3.14.2(a)(ii) and (iii) shall be the metre of precast kerbing removed. For items
C4.3.14.1(a)(iii) and C4.3.14.2(a)(iii) the length of in situ concrete channel shall not be measured separately.
The unit of measurement for items C4.3.14.1(b) and (c) and C4.3.14.2(b), (c) and (d) shall be the number of inlets.
The quantities shall be measured in place on the road before the items are removed.
The tendered rates shall include full compensation for excavation, breaking down and removing the edging.
Distinction shall be made between the construction methods used.
C4.3.16.1 Paving blocks (specify type or size and thickness) number (No)
C4.3.16.2 Precast concrete kerbing (specify type or figure number and length of sections) number (No)
The unit of measurement shall be the number of units that are neatly stacked at the approved stockpile site.
The quantities shall be measured in the stockpile (stack).
The tendered rates shall include full compensation for cleaning the paving blocks or road edging items, for loading and hauling to the stockpile
(stacking) site or to a position as indicated by the land or property owner, for off-loading and stacking.
Any haul costs shall be included in the tendered rates of item C4.3.16.
C4.3.17.2 Crushed stone, macadam, gravel and sand material cubic metre (m3)
C4.3.18.2 Crushed stone, macadam, gravel and sand material cubic metre (m3)
The tendered rate shall also include the cost of spoiling at a municipal site, if applicable.
All haul costs shall be included in the tendered rates of item C4.3.18.
C4.3.19 Spoiling of paving blocks and road edging in spoil sites designated by the Employer
C4.3.19.2 Precast and in situ concrete kerbing, edge beams and channels at precast kerbing cubic metre (m3)
C4.3.19.3 Kerb and grid inlets, and other services structures number (No)
C4.3.20 Spoiling of paving blocks and road edging in spoil sites designated by the Contractor
C4.3.20.2 Precast and in situ concrete kerbing, edge beams and channels at precast kerbing cubic metre (m3)
C4.3.20.3 Kerb and grid inlets, and other services structures number (No)
CONTENTS
D4.3.1 SCOPE
D4.3.2 GENERAL
CONTENTS
PART A: SPECIFICATIONS
A4.4.1 SCOPE
A4.4.2 DEFINITIONS
A4.4.3 GENERAL
A4.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A4.4.5 MATERIALS
A4.4.6 CONSTRUCTION EQUIPMENT
A4.4.7 EXECUTION OF THE WORKS
A4.4.8 WORKMANSHIP
A4.4.2 DEFINITIONS
The relevant definitions in Chapter 1 and Clause A4.1.2 shall also be applicable to this Section. Additional definitions for this Section are listed
below.
Commercial materials - are natural gravel, sand or crushed rock materials:
• Sourced from commercial suppliers. These materials are sold by commercial suppliers and are generally crushed materials acquired
from quarry operations or from stockpiles of non-ore containing material excavated during mining operations and shall already comply
with the gradation and other material requirements, or
• Sourced from private or other non-commercial suppliers identified by the Employer or the Contractor, or material from the Employer’s
or Contractor’s own sources. These materials are usually natural materials available in excavations or stockpiles, and the primary
objective for excavating the material is/was not for road construction purposes. It is distinguished from material sourced from borrow
pits and quarries in Section 4.1, in that the excavation or sourcing does not require a mining right or a mining permit in terms of South
African legislation, although other legislative approvals may be required. Commercial materials from private or other non-commercial
suppliers or from the Employer’s own sources may require removal or breaking down of oversize material, screening, crushing or
crushing and screening.
Dust palliatives - are products applied to the surface of a wearing course of an unsealed road or worked into the layer to reduce the dust and
loss of fines.
A4.4.3 GENERAL
A4.4.3.1 Employer identified commercial materials
a) Materials from commercial suppliers
The Employer may identify and include test results of compliant materials from commercial suppliers in the Contract Documentation. However,
the Contractor shall still be responsible for sourcing the material and for ensuring the sufficiency in quantity and quality of the material intended
for use in the contract.
The Employer will usually not conclude any arrangements with these commercial suppliers, and the Contractor shall enter into negotiations with
them and conclude contracts for the price, payments, rate of supply and the like.
Once the Contractor has chosen one or more of the commercial suppliers identified by the Employer, further dealings with the supplier and
procuring the material shall be undertaken by the Contractor.
b) Materials from private or non-commercial suppliers
The sources and results of any material testing of materials from private or non-commercial suppliers that have been identified by the Employer,
will be included in the Contract Documentation. This information is indicative as to the sufficiency in quality and quantity of the material.
The Contract Documentation shall also specify the arrangements made with the suppliers and specifically those that the Contractor must comply
with, and any further negotiations that the Contractor shall conclude.
c) Materials from the Employer’s own sources
The material is free issued to the Contractor, unless otherwise stated in the Contract Documentation when any conditions of the Employer shall
then also be specified.
The results of any material testing will also be included in the Contract Documentation.
A4.4.5 MATERIALS
A4.4.5.1 Earthworks and pavement layer materials
The specifications for a pioneer layer, fill material and crushed stone for earthworks given in Clause A4.1.5 shall also apply to commercial materials.
These material specifications are the required specifications for the commercial material finally processed and constructed on the road.
Test results from representative samples recently processed shall be submitted for review by the Engineer. The Engineer shall declare the
sourced or produced material fit for use before construction on the road may commence.
When specified in the Contract Documentation, material procured from commercial suppliers shall be stockpiled separately at the supplier when
it cannot be used immediately after producing. The Contract Documentation may then also specify that the stockpile be fenced and sign posted
as belonging to the Employer.
Cement, preferably CEM II 32.5N, and hydrated lime shall comply with the requirements of Clauses A4.4.5.2a) and A4.4.5.2b) above respectively.
Type of material before stabilisation At least G4B quality At least G5B quality
Grading, P0,075, PI and DMI for BSM-emulsion and BSM-foam Refer the Sabita Guideline TG2
Notes:
(1)
All tests are carried out on specimens conditioned at 25 °C.
(2)
Specimens cured to constant mass at 40 °C. ITS values determined using constant displacement loading.
(3)
Requirements in brackets when the reclaimed asphalt in the material exceeds 50 %.
(4)
Specimens conditioned to 40 °C for 8 hrs before sealing in a bag and curing at 40 °C for 48 hours.
The selection of the bituminous stabilising agent is covered in Clause A4.4.7.1.
CONTENTS
B4.4.1 SCOPE
B4.4.2 DEFINITIONS
B4.4.3 GENERAL
B4.4.5 MATERIALS
B4.4.1 SCOPE
This Section covers the supply of materials for a specific road construction project or projects which are procured from commercial and other
private sources. It includes information on the requirements for providing commercial materials for earthworks and pavement layers as an
alternative to sourcing these materials from borrow pits, from quarries, from cuttings, box cuts and designated excavations or from existing roads
and that can be used for the construction of the road earthworks and pavement layers.
A relatively small proportion of activities as defined in Part A under the various sections are considered suitable for labour enhancement. Therefore,
Part B only provides additional specifications, not contained in Part A.
B4.4.2 DEFINITIONS
Definitions as provided in Chapter 1 and Clause A4.4.2 shall apply.
B4.4.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B4.4.5 MATERIALS
The provisions of Part A shall apply.
B4.4.8 WORKMANSHIP
The provisions of Part A shall apply.
(iii) Items to be measured and paid for using items specified elsewhere in the specifications
For commercial materials from private or non-commercial suppliers identified by the Employer and that must still be excavated, produced and/or
stockpiled, the Employer may decide to have a cost breakdown of the individual activities such as excavation, crushing and so forth. The pricing
of item C4.4.1 will then not be applicable, and measurement and payment shall be made in accordance with the applicable items in Section C4.1.
(iv) Items specifically for this Section of the specifications
(c) – (l) Etc, for other Type G3 to G9 materials cubic metre (m3)
(m) Sand for the base and shoulder layers cubic metre (m3)
(p) Natural or crushed gravel material for an unsealed shoulder layer cubic metre (m3)
(q) Natural or crushed gravel material for the wearing course of an unsealed road cubic metre (m3)
C4.4.1.4 Soil cement material (pre-blended by the supplier) cubic metre (m3)
C4.4.2 Commercial materials identified by the Contractor from commercial, private or other
non-commercial suppliers
(c) – (l) Etc, for other Type G3 to G9 materials cubic metre (m3)
(m) Sand for the base and shoulder layers cubic metre (m3)
(p) Natural or crushed gravel material for an unsealed shoulder layer cubic metre (m3)
(q) Natural or crushed gravel material for the wearing course of an unsealed road cubic metre (m3)
C4.4.2.4 Soil cement material (pre-blended by the supplier) cubic metre (m3)
C4.4.3 Cost to procure commercial materials identified by the Employer from private or
non-commercial sources
C4.4.3.2 Handling cost and profit in respect of item C4.4.3.1 percentage (%)
C4.4.6 Fillers for bituminous stabilisation (specify filler types separately) ton (t)
C4.4.7 Sampling and material testing by a commercial laboratory for the stabilisation designs
C4.4.7.2 Handling cost and profit in respect of item C4.4.7.1 percentage (%)
CONTENTS
D4.4.1 SCOPE
D4.4.2 GENERAL
D4.4.1 SCOPE
Dust palliatives shall be subject to the provision of a performance guarantee by the manufacturer and/or supplier of the dust palliative.
D4.4.2 GENERAL
The Employer shall identify the location and extent of the unsealed road for which a dust palliative is required.
The Employer will provide the following basic information of the gravel wearing course material and requirements of the guarantee:
• Properties of the wearing course material,
• Expected volume and type of traffic on the road,
• Performance and other requirements for the palliative, whether for dust control, strengthening or both,
• Duration and format of the guarantee,
• Payment conditions of the guarantee, and
• Assessments and testing criteria for the treated material during the guarantee period.
The Contractor shall submit the following information about the dust palliative:
• The type of dust palliative, whether it be one of the following types:
- A surfactant that is added to water in order to improve its ability to wet and penetrate the gravel wearing course,
- A non-bond forming palliative that is applied directly onto the wearing course surface and where there is no gluing of the surface,
or
- A bond forming or gluing palliative that bonds the dust particles and that is applied by mixing the palliative into the wearing course.
• The basis material of the palliative,
• Further application intervals during the guarantee period,
• Restriction on the use such as near watercourses or other environmentally sensitive areas,
• Construction and application methods,
• Construction equipment required to apply the palliative,
CONTENTS
PART A: SPECIFICATIONS
A4.5.1 SCOPE
A4.5.2 DEFINITIONS
A4.5.3 GENERAL
A4.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A4.5.5 MATERIALS
A4.5.6 CONSTRUCTION EQUIPMENT
A4.5.7 EXECUTION OF THE WORKS
A4.5.8 WORKMANSHIP
A4.5.2 DEFINITIONS
The relevant definitions in Chapter 1 and Clause A4.1.2 shall also be applicable for this Section. Additional definitions for this Section are listed
below.
Alternative materials - include all recovered materials considered compliant for the construction of earthworks and pavement layers, with or
without additional processing, that are obtained from operations not necessarily related to road construction. Such operations include, but are not
limited to:
• Construction and demolition of structures.
• Industrial operations.
• Mining operations.
Geosynthetic materials built into the earthworks and road pavement layers are not defined as alternative materials.
Construction and demolition material - is produced in the process of construction, renovation, or demolition of structures. Structures include
buildings of all types (both residential and non-residential), as well as roads and bridges.
Components of construction and demolition material typically include concrete, bricks, mortar, asphalt, metals, floor tiles, roofing and ceiling
materials, dry walls, window materials, pipes, floor materials and other components. It may also contain some wood fragments, soil and rock
fragments. Construction and demolition material is also referred to as construction or building rubble.
Industrial operations material - material from industrial operations is typically a by-product produced by an industrial activity that includes any
surplus, unwanted or discarded material resulting from a manufacturing process at factories, mills, and so forth.
Mining operations material - material from mining operations generally consists of unprocessed surplus overburden material or non-ore bearing
material that was removed and stockpiled during the mining operation. It is generally not compliant for direct use in the road layers, and requires
removal of unwanted material, crushing and screening, and selection as applicable.
Hazardous material - contains organic or inorganic elements or compounds which may have a detrimental impact on health and the environment
owing to the inherent physical, chemical, toxicological, radioactive or carcinogenic characteristics of the material.
A4.5.5 MATERIALS
A4.5.5.1 General
The material specifications given in Clause A4.1.5 shall also apply to any alternative materials produced for use in the earthworks and pavement
layers. These material specifications are the required specifications for the alternative materials finally processed and placed in the road.
Crushing and screening or modification, etc of the materials may be required to comply with these specifications.
Construction and demolition material to be used for the construction of earthworks and pavement layers shall not contain any of the following
materials:
• Timber,
• Reinforcing steel or mesh, steel, iron or other scrap metal,
• Asbestos products,
• Plastic and PVC materials,
• Dry walling materials,
• Pipes,
• Aluminum,
• Window and door frames,
b) Ash
Ash from coal burning power plants is generally compliant for fill layers. It may also be compliant for the pavement layers of lower category roads,
or for the wearing course of unsealed roads. However, the properties of ash vary considerably from one source to another, and any ash proposed
for use in the works shall be tested for compliance with the relevant material specifications given in Clause A4.1.5.
Pulverised fuel ash (PFA), also known as fly ash, is a very fine material that is difficult to compact and may liquefy under wet conditions. It may
be compliant for use in fill provided the necessary precautions are taken during the placing, processing and compaction operations but it shall not
be used without the written approval of the Engineer.
Furnace bottom ash (FBA) can generally be used for fill layers and possibly for the lower pavement layers.
Ash generates dust that shall be contained during transport, placing and compaction.
A4.5.8 WORKMANSHIP
The Engineer and the Contractor, shall determine and agree on the testing protocol and frequency of the applicable process control tests on any
alternative material being used, to ensure that the quality of the materials produced complies with the specified requirements for the particular
layer for which it will be used.
In addition to the standard tests used for the testing of earthworks and pavement layers materials, the following material tests shall be carried out
where applicable:
• Chemical analysis by a recognised chemical laboratory to determine the presence and quantity of deleterious minerals and
hazardous material.
• Determine the amount of expansion and degree of disintegration of the material when immersed in water for a prolonged period.
The required soaking period will depend on the particular material.
• Hardness and durability tests depending on the use of the material. The relevant material properties specified in Clause A4.1.5 shall
be applicable unless otherwise specified in the Contract Documentation.
• Determine the presence of unwanted material and hazardous material listed in Clauses A4.5.5.2 and A4.5.5.5 respectively.
Measurement, testing, and evaluation of all individual components and constructed products shall be in accordance with the methods prescribed in
this Section or in Chapter 20 as relevant.
CONTENTS
B4.5.1 SCOPE
B4.5.2 DEFINITIONS
B4.5.3 GENERAL
B4.5.5 MATERIALS
B4.5.1 SCOPE
This Section covers the work requirements for sourcing alternative materials that can be used for the construction of road earthworks and
pavement layers, and which are obtained from sources other than from borrow pits and quarries, or from cuttings, box cuts and designated
excavations, or from the existing road or from commercial sources.
Part B only provides additional specifications, not contained in Part A.
B4.5.2 DEFINITIONS
Definitions as provided in Chapter 1 and Clause A4.5.2 shall apply.
B4.5.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B4.5.5 MATERIALS
The provisions of Part A shall apply.
B4.5.8 WORKMANSHIP
The provisions of Part A shall apply.
C4.5.1.2 Handling cost and profit in respect of item C4.5.1.1 percentage (%)
C4.5.2 Removing unwanted material from alternative materials identified by the Employer
C4.5.2.2 Handling cost and profit in respect of item C4.5.2.1 percentage (%)
C4.5.2.4 Handling cost and profit in respect of item C4.5.2.3 percentage (%)
C4.5.3.2 Handling cost and profit in respect of item C4.5.3.1 percentage (%)
CONTENTS
D4.5.1 SCOPE
D4.5.2 GENERAL
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 5: EARTHWORKS AND PAVEMENT LAYERS: CONSTRUCTION .................................................... 5-1
5.1 ROADBED .......................................................................................................................................................... 5-1
PART A: SPECIFICATIONS .............................................................................................................................................................................. 5-1
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................... 5-10
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................... 5-11
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ....................................................................................................................... 5-19
CONTENTS
PART A: SPECIFICATIONS
A5.1.1 SCOPE
A5.1.2 DEFINITIONS
A5.1.3 GENERAL
A5.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A5.1.5 MATERIALS
A5.1.6 CONSTRUCTION EQUIPMENT
A5.1.7 EXECUTION OF THE WORKS
A5.1.8 WORKMANSHIP
A5.1 ROADBED
PART A: SPECIFICATIONS
A5.1.1 SCOPE
This Section covers the work requirements for normal roadbed treatment. This is all work in connection with the preparation and compaction of
the roadbed, the removal to spoil of material not approved for use in the roadbed and for the replacement of the spoiled roadbed material. Normal
roadbed treatment includes dealing with collapsible subgrades, unsuitable material and clay.
Specialist roadbed treatment shall be dealt with in accord with Clause A5.1.3.3.
The following Sections contain relevant specifications for Section A5.1:
• Section A1.2 of Chapter 1 – General requirements and provisions
• Section A1.5 of Chapter 1 – Accommodation of traffic
• Section A1.6 of Chapter 1 – Clearing and Grubbing
• Chapter 4 – Earthworks and pavement layers: Materials
• Section A12.3 of Chapter 12 – Ground improvement
• Section A12.10 of Chapter 12 – Hard excavation by blasting
A5.1.2 DEFINITIONS
The relevant definitions elsewhere in the standard specifications are applicable. Additional definitions for this Section follow.
Batter - a slope inclined upwards or downwards between the outer edge of a constructed platform area and the outer edge of a second constructed
platform area located above or below the first constructed platform. The slope gradient shall be as indicated in the Contract Documentation.
Clay activity - clays are either inactive, normal or active. The activity of clay (A) is measured by the ratio of the plasticity index (PI) to the
percentage passing the 2µm (P0,002) sieve opening.
Potential expansiveness of clay is also dealt with in TRH9 (van der Merwe method).
Collapsing soil or sand - a soil with a collapsible grain structure. It is a soil which can withstand relatively large imposed stresses with small
settlements at a low in-situ moisture content but exhibits a decrease in volume and associated additional settlement with no increase in the applied
loading if wetting up occurs. The change in volume is associated with a change in soil structure (the collapse of the grain structure).
Normal roadbed treatment - normal roadbed treatment is treatment that does not need to be designed by specialist geotechnical engineers nor
does it need to be constructed using specialist geotechnical construction equipment.
Roadbed - the constructed, treated or improved natural in place material on which the fill or the pavement layers is constructed directly. The
roadbed is constructed prior to the construction of the fill or pavement layers.
Road prism – is the area disturbed during previous or new road construction. The road prism extends between the top of slopes where in cut and
between the bottom or toe of slopes where in fill. Where the road cross section is in cut and fill, the road prism shall extend between the top of the
cut slope and the bottom or toe of the fill slope. Additionally, the road prism shall include the median width and all side drains when the nearest
edge of the side drain is located within 0,5 m of the top of the cut slope or located within 0,5 m of the bottom or toe of the fill slope.
Roller-pass (conventional roller) - an area will be taken to have received one roller-pass when a roller has passed over the area once. Additional
passes made as a result of nominal overlapping of at least 200 mm so as to ensure full coverage of the area, shall not be taken into account.
Roller-pass (high-energy impact compactor or roller HEIC) - an area will be taken to have received one roller-pass when an HEIC has passed
over the area twice. Additional passes made as a result of nominal overlapping of at least 200 mm so as to ensure full coverage of the area shall
not be taken into account.
Note: With the continued enhancement of HEIC compaction technology this definition may need to be adjusted or augmented to suit the
compaction equipment. Any adjusted definition shall be included in the Contract Documentation.
Side-cut or benching - the excavation of material to form benches or steps. Suitable excavated material is bladed or placed directly by excavator
or dozer into the final position of the material. The material is used for the construction of a roadbed fill, a fill widening or a backfill behind a
retaining structure without it having to be loaded and hauled to the place of final use. Material excavated in this manner is termed side-cut or
benching to fill.
Subgrade - the completed earthworks within the road prism before the construction of the pavement layers. This comprises the treated in-situ
material of the roadbed and the fill material.
A5.1.3 GENERAL
A5.1.3.1 Roadbed material investigation
The geotechnical information provided in the Contract Documentation for the roadbed reports the results of site investigations including the
excavation of test pits and/or drilling, and laboratory tests conducted by or on behalf of the Employer. This provides information as to the quality
of the roadbed material and the type of roadbed treatment required.
If not already specified in the Contract Documentation, the Engineer shall instruct the Contractor regarding the different types of normal roadbed
treatment or ground improvement, required in terms of Section A5.1 and Section A12.3 of Chapter 12. Normal roadbed treatment excludes
specialist roadbed treatment listed in Clause A5.1.3.3.
The Engineer shall give final instructions regarding any additional investigation and testing requirements and the treatment of the roadbed
materials prior to the commencement of the programmed roadbed construction period. If any undocumented roadbed conditions are found during
construction, the Engineer shall be notified immediately so that any further instructions that may be required, can be issued.
The road prism must be surveyed and correctly staked before any roadbed related operations commence to ensure that the correct extent of
roadbed is demarcated for treatment.
A5.1.5 MATERIALS
A5.1.5.1 Remove unwanted material
Prior to construction or treatment of the roadbed, the in-situ roadbed material shall not contain any of the following materials listed hereunder.
These unwanted materials shall be removed to a designated spoil site.
• Organic materials, grass and shrubs;
• Wood chippings, tree bark and roots;
• Plastic (bags, polystyrene and so forth);
• Refuse or other non-compliant material;
• Free asbestos; or
• Any of the hazardous material as listed in Clause A4.5.5.5 of Chapter 4.
A5.1.5.2 Topsoil
Topsoil shall be obtained from wherever suitable topsoil material occurs within the road prism ahead of the roadbed construction and within the
road reserve as detailed in the Contract Documentation and as specified in Clause A1.6.7.6 of Chapter 1.
Where required an inspection pit shall be dug and the material sampled. An undisturbed sample for carrying out a single oedometer test shall be
taken. The single oedometer test, also known as the collapse potential (CP) test, shall be performed to assess collapse potential. Table A5.1.5-2
summarises the potential for collapse in terms of the single oedometer test result. The undisturbed sample for the oedometer test shall be taken
at a depth of between 0,8 m and 1,0 m below the material depth detailed in Table A4.1.5-2 of Section A4.1 of Chapter 4.
0–1% No potential
5 % - 10 % Definite potential
10 % - 20 % Severe potential
Some collapsing soils exhibit two separate optimum moisture content (OMC) values with two separate maximum dry densities. The collapsibility
of these soils is very sensitive to small increases or decreases in compaction moisture content.
A5.1.8 WORKMANSHIP
A5.1.8.1 Inspection of the works
The Engineer shall do routine inspections and conduct routine tests to determine whether the quality of material and workmanship provided,
complies with the requirements of the Contract Documentation.
CONTENTS
B5.1.1 SCOPE
B5.1.2 DEFINITIONS
B5.1.3 GENERAL
B5.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B5.1.5 MATERIALS
B5.1.6 CONSTRUCTION EQUIPMENT
B5.1.7 EXECUTION OF THE WORKS
B5.1.8 WORKMANSHIP
B5.1.1 SCOPE
This Section covers the work requirements for normal roadbed treatment, which is all work in connection with the preparation and compaction of the
roadbed, the removal to spoil of material not approved for use in the roadbed and for the replacement of the spoiled roadbed material.
This Section therefore includes work with a component of labour. This work is included in Part A of this specification as well as the specification
of other sections.
This Part therefore only covers additional specifications for work to enhance the labour component of construction activities where specified.
B5.1.2 DEFINITIONS
Definitions as provided in Clause A5.1.2 shall apply.
B5.1.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B5.1.5 MATERIALS
The provisions of Part A shall apply.
B5.1.8 WORKMANSHIP
The provisions of Part A shall apply.
Material which can be excavated by means of a suitable shovel with or without the use of a pick or other
Soft
hand-swung tool
Material which is difficult to excavate by hand even with the aid of a crowbar and requires the assistance of
Intermediate
pneumatic tools for economic removal.
Table C5.1-2: Classification of materials in terms of consistency and shear strength for labour enhancement
NUMBER OF DCP BLOWS TO PENETRATE
CONSISTENCY
MATERIALS 100 mm *
CLASSIFICATION
Granular soil Cohesive soil Granular soil Cohesive soil **
*Only applicable to materials comprising not more than 10 % gravel of size less than 10 mm and materials containing no cobbles or
isolated small boulders.
**This could be subjective depending on the moisture content of the cohesive material
After completion of the topsoil removal the Contractor, shall at no cost to the Employer, take cross-sections at a maximum spacing of 20 m so as
to determine the new ground line and subsequently the quantities of topsoil removed ahead of the commencement of the roadbed treatment.
After completion of the roadbed treatment the Contractor, shall at no cost to the Employer, take cross-sections at a maximum spacing of 20 m so
as to determine the final roadbed levels and subsequently the quantities of any roadbed levelling operations, if any, ahead of the cut to fill
operations commencing.
The Engineer shall take control measurements to determine the accuracy and adequacy of the cross-sections, and shall instruct the Contractor
to correct any out of tolerance work and to take such additional measurements and cross-sections as may be deemed necessary. Such cross-
sections shall be taken before any cut or fill work is done.
Where the Contractor proceeds with further construction work before the Contractor and the Engineer have reached agreement on the accuracy
and adequacy of the cross-sections, the Engineer's decision regarding the cross-sections to be used shall be final and binding on the Contractor.
C5.1.1.6 Compaction of in-situ sand roadbed to 100 % of MDD cubic metre (m3)
The unit of measurement shall be the cubic metre of roadbed material prepared and compacted as specified. The quantity of the in-situ material
shall be computed in accordance with the authorised dimensions of the completed layers. The quantity of imported material shall be measured in
the haul vehicles, by taking the volume of the imported material to be the equivalent of 70 % of the loose volume in the haul vehicles.
The tendered rates for items C5.1.1.3 and C5.1.1.4 shall include full compensation for shaping, scarifying with in-situ material where required and
mixing of the imported material or the in-situ/imported material blend, then preparing and compacting the material to the specified MDD.
The tendered rates for items C5.1.1.3 and C5.1.1.4 shall include for loading and off-loading the imported material. The haul of the imported
material shall be measured from the point of loading until the point of off-loading as per Section A1.7 of Chapter 1.
All material that requires being imported for the construction of the roadbed, to replace spoil material measured under item C5.1.2, or to replace
unsuitable material measured under C5.1.3, except the levelling layer which shall be paid under item C5.1.12, shall be measured and paid for
under this item C5.1.1.
C5.1.2.1 Excavate material to spoil from roadbed construction, material obtained from:
C5.1.2.2 Excavate material to spoil from roadbed construction, using labour enhancement, material
obtained from:
The unit of measurement shall be the cubic metre of material measured in its original position in cut and computed by the method of average end
areas from levelled cross-sections taken as specified.
Where measurement by cross-sections is considered by the Engineer to be impractical, cut to spoil may be measured in the haul vehicles, by
taking the in situ volume of the material to be the equivalent of 70 % of the loose volume in the haul vehicles.
For payment purposes a distinction shall be made between using conventional construction methods and using labour enhancement.
The tendered rates of item C5.1.2.1 shall include full compensation for excavating and loading from the road prism and roadbed the material in
the different classes of excavation. Haul shall be measured and paid for from the point of loading to the point of off-loading.
The tendered rates of item C5.1.2.2 shall include full compensation for using labour enhancement for excavating and loading from the road prism
and roadbed in the different classes of excavation. Haul shall be measured and paid for from the point of loading to the point of off-loading.
The excavation of hard material by blasting shall exclude the cost of blasting which shall be measured and paid for under item C12.10.1 in Section
C12.10 of Chapter 12.
C5.1.3.1 Excavate material to spoil from roadbed construction, material obtained from:
C5.1.3.2 Excavate material to spoil from roadbed construction, using labour enhancement, material
obtained from:
The unit of measurement shall be the cubic metre of material measured in its original position in cut and computed by the method of average end
areas from levelled cross-sections taken as specified.
Where measurement by cross-sections is considered by the Engineer to be impractical, cut to spoil may be measured in the haul vehicles, by
The unit of measurement shall be the cubic metre of unsuitable material removed by the Contractor to spoil in accordance with the Engineer's
instructions, and it shall be the in-situ volume of the material calculated in accordance with the authorised dimensions. Where the use of authorised
dimensions proves to be unsatisfactory, then the unit of measurement shall be 70 % of the loose volume measured in the haul trucks.
The tendered rates shall include full compensation for excavating and loading the material from the road prism and roadbed in the different classes
of excavation.
Hauling shall be measured and paid for from the point of loading to the point of off-loading as per Section C1.7 of Chapter 1.
The removal of unsuitable stable material in cuttings is measured and paid for under item C4.2.7 of Chapter 4.
Item Description Unit
C5.1.5.3 In-situ treatment by drilling and splitting the material using non-explosive, rock-breaking cubic metre (m3)
products
The unit of measurement shall be the cubic metre of material treated in-situ as specified. The quantity shall be calculated from the authorised
dimensions of the in-situ treatment.
The tendered rates for items C5.1.5.1 and C5.1.5.2 shall include full compensation for ripping or for drilling and blasting, shaping, scarifying,
sizing, mixing of in-situ and imported material if required, processing and compacting the material as specified. Payment shall distinguish between
in-situ treatment by ripping only and in-situ treatment by drilling and blasting.
The excavation of hard material by blasting for item C5.1.5.2 shall exclude the cost of blasting which shall be measured and paid for under item
C12.10.1 in Section C12.10 of Chapter 12.
The tendered rates for item C5.1.5.3 shall include full compensation for drilling the holes, procurement of the rock-breaking product(s), charging
the drilled holes and splitting the material. The tendered rates shall also include for shaping, scarifying, sizing, mixing of in-situ and imported
material if required, processing and compacting the material as specified.
All imported material shall be measured and paid for under Section C5.2.
No separate payment shall be made for oversize or surplus material excavated to spoil as a result of this treatment.
Surplus material shall be measured and paid under item C5.1.1 if used in the roadbed.
Item Description Unit
The unit of measurement shall be the square metre of roadbed compacted in accordance with the specification for a single roller-pass. The
quantity will be measured in accordance with the authorised dimensions of the area to receive single roller-pass compaction.
The area to be roller-pass treated will be adjusted to be commensurate with the number of roller-pass treatments instructed. The authorised area
will be doubled when two roller-pass compaction is specified or trebled when three roller-pass compaction is specified in the Contract
Documentation, or instructed by the Engineer, and so forth.
The tendered rates shall include full compensation for shaping, providing the rollers, keeping the rollers operational and ready for when soil-
moisture conditions are favourable, and for compacting the roadbed with the specified number of roller-passes.
The Contractor shall base the tendered rates on a single, one direction pass for each specified type, size and weight of roller. The area covered
by the nominal roller overlap width required to ensure full coverage of the area being compacted shall not be measured for additional payment. If
the rollers available on site are different types, sizes and weights than those specified in the Contract Documentation, then revised rates which
take into account the percentage increased or reduced compaction effort per roller-pass, shall be agreed with the Contractor based on the same
percentage increase or decrease.
The unit of measurement for the addition of water shall be the kilolitre of water applied as required.
The tendered rates for the addition of water to achieve the required compaction shall include full compensation for the supply, delivery and
application of the water when required.
Item Description Unit
C5.1.7.1 Non wetting-up collapsing soil trial section at in-situ moisture content using conventional rollers cubic metre (m3)
and/or HEIC
C5.1.7.2 Non wetting-up collapsing soil trial section by excavating the soil to stockpile and then cubic metre (m3)
importing the soil from the stockpile to controlled compacted layers
C5.1.8.2 Non wetting-up collapsing soil roadbed construction at in-situ moisture content using HEIC cubic metre (m3)
C5.1.8.3 Non wetting-up collapsing soil roadbed construction by excavating the soil to stockpile and cubic metre (m3)
then importing from the stockpile to controlled compacted layers
C5.1.8.5 Water for wetting-up collapsing soil roadbed construction kilo-litre (kℓ)
The unit of measurement for items C5.1.8.1, C5.1.8.2, C5.1.8.3 and C5.1.8.4 shall be a cubic metre of collapsing soil material constructed
according to the authorised dimensions in the Contract Documentation, measured in-situ prior to the commencement of any construction.
The tendered rates shall include full compensation for setting out the collapsing soil material sections, for preparing and providing the construction
programme for the roadbed construction and preparing the existing roadbed surface where required.
The tendered rates shall include full compensation for construction of the roadbed treatment all in terms of the Contract Documentation and/or in
terms of the relevant compliant trial section constructed as per item C5.1.7. The tendered rates shall include full compensation for all labour,
construction plant including conventional rollers (C5.1.8.1) or HEIC (C5.1.8.2), equipment and incidentals required to carry out the construction of
the roadbed in collapsing soil material as specified.
The unit of measurement for item C5.1.8.4 shall be a kilolitre of water used to wet-up the collapsing soil.
The tendered rates for item C5.1.8.4 shall include full compensation for the provision and application of water for the construction of item C5.1.8.3,
applied as per the compliant trial section under item C5.1.7.3.
Item Description Unit
The unit of measurement shall be a cubic metre of inactive clay material constructed according to the authorised dimensions in the Contract
Documentation and down to a depth of 200 mm for both items C5.1.9.1 and C5.1.9.2.
The tendered rates shall include full compensation for setting out each inactive clay section and preparing the existing roadbed surface where
required. The tendered rates for C5.1.9.1 shall also include for loading the material.
The tendered rates for items C5.1.9.1 and C5.1.9.2 shall also include full compensation for construction of the roadbed treatment of inactive clay
by material modification or lime modification, respectively, as specified. The tendered rates for each item shall also include full compensation for
all labour, construction plant, equipment and incidentals required to carry out the construction of the roadbed by material modification or lime
modification as specified.
The hauling of compliant fill material shall be measured and paid for from the point of loading to the point of off-loading as per Section A1.7 of
Chapter 1.
The production of the compliant material is measured and paid for under Sections C4.1 and/or C4.2 of Chapter 4.
The procurement and mixing of the lime is specified and measured in Section A4.4 of Chapter 4 and Section C5.4 respectively.
Item Description Unit
The unit of measurement shall be a cubic metre of active clay material constructed according to the authorised dimensions in the Contract
Documentation.
The depth of treatment for item C5.1.10.1 shall be 200 mm unless otherwise instructed in the Contract Documentation or by the Engineer. The
depth of treatment for item C5.1.10.2 is the depth indicated in the Contract Documentation up to a limit of 750 mm unless instructed otherwise in
the Contract Documentation or by the Engineer.
The procurement and mixing of the lime for item C5.1.10.1 is specified and measured in Section A4.4 of Chapter 4 and Section C5.4 respectively.
The tendered rates shall include full compensation for setting out each active clay section and preparing the existing roadbed surface as specified.
The tendered rates for item C5.1.10.1 shall also include full compensation for construction of the roadbed treatment of active clay using lime
modification as specified.
The tendered rates for C5.1.10.2 shall also include for loading and off-loading the active clay. The hauling of the active clay material shall be
The unit of measurement shall be a cubic metre of pioneer layer material constructed in the authorised areas specified in the Contract
Documentation or as instructed by the Engineer.
The compacted volume of the pioneer layer of material shall be taken as equal to 70 % of the loose volume of material in the hauling vehicles.
The tendered rate for the construction of the roadbed treatment using a pioneer layer over water-logged or soft clayey ground as per the Contract
Documentation shall include full compensation for all labour, construction plant, equipment and incidentals required to carry out the construction
of the roadbed using a pioneer layer as specified.
The loading and hauling of compliant pioneer material for the roadbed construction is measured and paid for as specified in Section A1.7 of
Chapter 1.
The production of the compliant pioneer material is measured and paid for under Sections C4.1 and/or C4.2 of Chapter 4.
Item Description Unit
The unit of measurement shall be the cubic metre of material measured in its original position in cut and computed by the method of average end
areas from levelled cross-sections taken as specified. The cross-sections shall be taken prior to excavating the cut for the benches.
Excavations shall be done using conventional construction and/or labour enhancement as specified and measured.
The tendered rates for excavating of benches under item C5.1.12.1 shall include full compensation for excavating from the road prism and roadbed
in the class of excavation indicated. The rate shall also include full compensation for moving, by bull-dozer or excavating and loading the fill
material a maximum of 1,0 km into its final location in the fill or for excavation, loading, off-loading and disposing of the spoil material at designated
spoil sites up to a maximum of 1.0km, as instructed by the Engineer, including shaping and levelling-off any piles of spoil material.
The tendered rates for excavating of benches under item C5.1.12.2 using labour enhancement, shall include full compensation for excavating
from the road prism and roadbed in the class of excavation indicated, loading the fill material, off-loading and disposing of the spoil material at
designated spoil sites, as instructed by the Engineer, including shaping and levelling-off any piles of spoil material. The tendered rates shall
include wheelbarrow transport over a haul distance of 100 m.
Hauling beyond 1,0 km when using conventional construction plant and 100 m using labour enhancement, shall be measured and paid for under
Section C1.7 of Chapter 1.
Construction of the fill is measured and paid for under Section C5.2.
Construction of the cut, exposed benched area, shall be measured and paid under the appropriate item in Section C5.1.
For payment purposes a distinction shall be made between materials as classified above.
Item Description Unit
C5.1.13.1 Over roadbed treatment in hard material compacted to 90 % MDD cubic metre (m3)
C5.1.13.2 Over a constructed pioneer layer compacted to 90 % MDD cubic metre (m3)
The unit of measurement shall be the cubic metre of material measured in its final position and computed by the method of average end areas
from levelled cross-sections taken as specified. The cross-sections shall be taken prior to the importation of the levelling layer and after completion
of the levelling layer.
When measurement by cross-sections is considered impractical the Contract Documentation may specify that the volume of the levelling layer
CONTENTS
D5.1.1 SCOPE
D5.1.2 GENERAL
D5.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D5.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D5.1.5 VISUALLY ASSESSED PROPERTIES
D5.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D5.1.7 EVALUATION FOR ACCEPTANCE
D5.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D5.1.9 NOTIFICATION OF REMEDIAL WORK
D5.1.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A5.2.1 SCOPE
A5.2.2 DEFINITIONS
A5.2.3 GENERAL
A5.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A5.2.5 MATERIALS
A5.2.6 CONSTRUCTION EQUIPMENT
A5.2.7 EXECUTION OF THE WORKS
A5.2.8 WORKMANSHIP
A5.2 FILL
PART A: SPECIFICATIONS
A5.2.1 SCOPE
This Section covers the work requirements for off-loading and the subsequent processing of compliant fill material.
The work requirement for loading and hauling the fill material is specified in Section A1.7 of Chapter 1.
The fill material is produced as specified in the relevant Sections of Chapter 4.
A5.2.2 DEFINITIONS
The relevant definitions in the standard specifications are applicable. Additional definitions for this Section are included here.
Haul material - any construction material that is hauled between the point of loading, or the point of collection and the point of off-loading.
Construction material may include all borrow, cut and reclaimed materials produced as specified in Sections A4.1, A4.2 and A4.3 of Chapter 4
and all spoil, and unsuitable material. Material obtained from commercial sources or from alternative sources, as specified in Sections A4.4 and
A4.5 of Chapter 4, shall not be classified as haul material.
A5.2.3 GENERAL
A5.2.3.1 Fill dimensions and shape
The dimensions of fills shall be in accordance with the road design reflected in the typical cross-sections and other details contained in the Contract
Documentation.
The Contract Documentation shall contain relevant details regarding the following:
• the required slope/batter of each fill,
• geometric layout details of each fill at interchanges and intersections,
• the proposed use of material for each fill,
• the method and classification of compaction for the fills as per Clause A5.2.3.4.
• any physical restrictions or material conditions that may affect the construction of the fill, and
• the proposed sequence of fill construction along the length of the project.
During compaction, the fill layer shall be maintained to the required shape and cross-section.
The compacted fill layers shall be adequately drained and shaped to prevent water from standing on the fill layers or scouring the completed work.
A5.2.5 MATERIALS
A5.2.5.1 Material specification
The material specifications for use in the construction of fills are given in Section A4.1 of Chapter 4 in the following clauses:
• Clause A 4.1.2 Definitions for Sand fill, Normal fill, Coarse fill and Rock fill material under sub-heading Fill layers
• Clause A4.1.5.4 Sand, normal and coarse fill material in the earthworks
• Clause A4.1.5.5 Rock fill material in the earthworks layers
• Clause A4.1.5.9 Sand in fill and pavement layers of sealed low volume roads
• Clause A4.1.5.13 Drainage layer material
Material excavated for the construction of infrastructure such as open drains, subsoil drains, culverts, bridge foundations and other structures,
shall, if compliant and instructed by the Engineer, be used for the construction of fills.
A5.2.8 WORKMANSHIP
A5.2.8.1 Inspection of the works
The Engineer shall do routine inspections and conduct routine tests to determine whether the quality of material and workmanship provided,
complies with the requirements of the Contract Documentation.
The Engineer shall do specific inspections of completed layers prior to the next layer being imported and specifically to determine whether the
layer is still intact and after a rainfall to determine whether the layer has become saturated due to poor provision for temporary drainage.
The in-situ measured density of the fill layer being tested complies with the compaction requirements when the results of at least 75 % of the in-
situ density tests of any lot, located as per the Contract Documentation, are equal to or exceed the specified value and no single density is more
than 3 percentage points below the specified value.
CONTENTS
B5.2.1 SCOPE
B5.2.2 DEFINITIONS
B5.2.3 GENERAL
B5.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B5.2.5 MATERIALS
B5.2.6 CONSTRUCTION EQUIPMENT
B5.2.7 EXECUTION OF THE WORKS
B5.2.8 WORKMANSHIP
B5.2.1 SCOPE
This Section covers the work requirements for off-loading and the subsequent processing of compliant fill material. The work requirements for
loading and hauling the fill material is specified in Section A1.7 of Chapter 1.
This Section therefore includes work with a component of labour. This work is included in Part A of this specification. This Part therefore only
covers additional specifications for work to enhance the labour component of construction activities where specified.
B5.2.2 DEFINITIONS
Definitions as provided in A5.2.2 apply.
B5.2.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B5.2.5 MATERIALS
B5.2.5.1 General material specifications
The provisions of Part A shall apply.
B5.2.8 WORKMANSHIP
The provisions of Part A shall apply.
C5.2.1.1 For fills more than 10 000 m3 (list all fills separately) number (No)
C5.2.1.2 For fills 1,0 km in length when less than 10 000 m3 (list all fills separately) number (No)
The unit of measurement shall be the number of compiled M&U plans for the construction of the fills.
The tendered rates shall include full compensation for gathering all information and compiling the plans and for ensuring the implementation of
the plans during the construction of each fill for which an M&U plan has been compiled.
C5.2.2.1 Normal fill material in compacted layer thicknesses of 200 mm and less:
C5.2.2.2 Coarse fill material in compacted layer thicknesses exceeding 200 mm: but less than
500 mm
(a) Compacted to 90 % of MDD cubic metre (m3)
C5.2.2.3 Sand fill material in compacted layer thicknesses of 400 mm and less, compacted to 100 % of cubic metre (m3)
MDD
C5.2.2.4 Rock fill material all as per Clause A5.2.7.6 cubic metre (m3)
The unit of measurement except for items C5.2.2.1(c) and C5.2.2.2(d) shall be the cubic metre of material measured in the compacted fill. The
measurement of fill shall distinguish between the different types of fill and methods of processing and compacting.
The unit of measurement for items C5.2.2.1(c) and C5.2.2.2(d) shall be the square metre of roadbed compacted in accordance with the
specification for roller-pass compaction.
The quantity measured for items C5.2.2.1(c) and C5.2.2.2(d) shall be in accordance with the authorised dimensions of the area to receive roller-
pass compaction as specified in Clause A5.1.7.3.
The quantity measured for items C5.2.2.1, C5.2.2.2, C5.2.2.3 and C5.2.2.4 except for items C5.2.2.1(c) and C5.2.2.2(d) shall be computed by the
method of average end areas from levelled cross-sections. The cross sections shall be prepared from the ground line after completion of clearing
and grubbing, after the removal of topsoil and after the completion of any roadbed treatment, but immediately prior to the construction of the fill.
The final specified or authorised fill cross-sections in the Contract Documentation shall be superimposed thereon at 20 m intervals along the
centre line of the road. All measurement shall be neat, and that part of the fill placed in excess of the authorised cross-sections, shall not be paid
for, irrespective of the tolerances in workmanship allowed under the contract.
Where the roadbed has subsided under the fills, the fill quantities shall be adjusted to make allowance for such subsidence, as set out in Clause
C5.2 (v).
The quantity measured for items C5.2.2.5, C5.2.2.6 and C5.2.2.7 shall be calculated from the authorised dimensions.
The tendered rates for all items shall include full compensation for preparing, processing, shaping, watering, mixing, and compacting the materials
to the densities or in the manner specified. The tendered rates shall also include for breaking down or removing and disposing of any oversize
material up to 5 % of the compacted volume from the road after processing, including loading and hauling the material to designated spoil sites.
The limit of 5 % shall apply to individual layers and not to all the layers together.
C5.2.3 Side-cut to fill compacted to 93 % of MDD in compacted layer thicknesses of 200 mm cubic metre (m3)
and less
The unit of measurement shall be the cubic metre of material measured in the compacted fill.
This item shall apply to fill constructed with material bladed directly from cut to fill including material cut from the side slope of existing fills,
pavement layers and from benches, using construction equipment such as a grader or bulldozer without having to load and haul the material to
its point of use. The quantity of material shall be computed from the cross-sections as described for items C5.2.2 and/or the authorised dimensions
of side-cuts or benches to be cut into the side slope of existing fills, superimposed thereon.
The tendered rate shall include full compensation for side-cutting the material by bull-dozing it side-ways, or by another appropriate construction
method, to fill, placing the material along with the simultaneous cutting of benches to the shape and dimensions specified followed by the
compaction of the material.
The tendered rate shall also include full compensation for preparing, placing the material, processing, shaping, watering, mixing, and compacting
the material to the densities or in the manner specified herein.
Item Description Unit
C5.2.4 Correcting rock fills that are deficient in fine material, extra over C5.2.2.4 cubic metre (m3)
The unit of measurement shall be the cubic metre of corrected rock fill.
The tendered rate shall include full compensation for procuring and furnishing approved material that passes through the 5.0 mm sieve, including all
transport, for loading and off-loading, for placing and spreading, watering and rolling, for removing all excess fines from the surface of the rock fill, and
for all other incidentals necessary for completing the work as specified.
Item Description Unit
C5.2.5.2 Fill material in sidewalk compacted to 93 % of MDD using labour enhanced methods of cubic metre (m3)
construction and light hand equipment.
The unit of measurement shall be the cubic metre of material measured in the compacted fill as calculated from the authorised dimensions of the
sidewalk.
The tendered rates shall include full compensation for preparing, processing, shaping, watering, mixing, and compacting the material to the
specified density or in the manner specified in the Contract Documentation irrespective of the source of the material. The tendered rates shall also
include full compensation for building up or reinstating the fill in the sidewalk.
The tendered rates shall also include for breaking down or removing and disposing of any oversize material from the road after processing.
A distinction shall be made between construction using conventional construction methods and labour enhancement methods.
Loading of the fill material shall only be measured when the material is taken from stockpile, when approved by the Engineer. The haul of the fill
material shall be measured from the point of loading/collection to the point of off-loading as per Section A1.7 of Chapter 1.
Item Description Unit
C5.2.6.1 Fill material in shoulder widening compacted to 93 % of MDD cubic metre (m3)
C5.2.6.2 Fill material in shoulder widening compacted to 93 % of MDD using labour enhancement and cubic metre (m3)
light hand equipment.
The unit of measurement shall be the cubic metre of material measured in the compacted fill as calculated from the authorised dimensions.
The tendered rates shall include full compensation for preparing, processing, shaping, watering, mixing, and compacting the materials to the
densities or in the manner specified herein irrespective of the source of the material.
Loading of the fill material shall only be measured when the material is taken from stockpile, when approved by the Engineer. The haul of the fill
material shall be measured from the point of loading/collection to the point of off-loading as per Section A1.7 of Chapter 1.
The tendered rates shall also include for breaking down or removing and disposing of any oversize material from the road after processing.
A distinction shall be made between construction using conventional construction methods and labour enhancement methods.
The unit of measurement for a trial section shall be the cubic metre of material processed during construction of the trial section according to the
authorised dimensions as specified in the Contract Documentation measured along the centre line of the road. A total length of at least 150 m of
trial section and no more than 200 m will be measured for payment as a trial section. The authorised depth and width of the trial sections shall be
representative of what will ultimately be constructed as per the Contract Documentation.
The tendered rates shall include full compensation for setting out the trial section, preparing and providing the plan for the specific trial section
and preparing the existing road surface where required.
The tendered rates shall also include full compensation for the application of water, all laboratory testing and for the full documentation of the
rolling techniques and combination of rollers all as specified.
C5.2.8.1 By normal grid rolling as per clause A5.3.7.3b) (i) to (vii) square metre-pass (m2-pass)
The unit of measurement shall be the square metre-pass calculated by multiplying the layer surface area covered by the agreed number of roller-
passes used to break down the material satisfactorily.
The tendered rates for each square metre-pass instructed by the Engineer shall include full compensation for all supervision, labour, equipment,
fuel, materials, work and incidentals necessary for completing the work. The same rates shall be applicable should there be a reduction in the
number of roller-passes for a specific type of roller.
The tendered rates shall include full compensation for supplying the roller and removing the roller after completion of the breaking down process.
The items shall differentiate between the different types of rollers used.
The unit of measurement shall be the cubic metre of oversize material which cannot be broken down on the road and is removed for re-crushing
or removed to spoil as instructed by the Engineer in excess of the 5 % of the compacted layer volume of oversize material included in the rates
tendered for item C5.2.2.
The volume measured for payment shall be taken as 70 % of the loose volume in excess of 5 % of the measured volume of the layer as measured
in the haul vehicles.
The tendered rate shall include full compensation for removing the oversize material from the fill layer, loading it into the hauling vehicles and off-
loading it at the agreed point of disposal.
The haul of the oversize material in excess of 5 % by volume per layer shall be measured from the point of loading/collection to the point of off-
loading as per Section A1.7 of Chapter 1.
C5.2.10.1 Finishing off rock fill slopes with soft material cubic metre (m3)
C5.2.10.2 Finishing off rock fill slopes with soft material using labour enhancement and light, hand cubic metre (m3)
equipment.
The unit of measurement shall be the cubic metre.
The volume shall be measured as 70 % of the loose volume measured in the trucks.
The soft material instructed by the Engineer to be dumped over the sides of rock fills for finishing will be measured and paid for as material in
addition to the net specified dimensions of the road prism as indicated on the road cross-sections.
The tendered rates for finishing cut or fill slopes, medians and interchange areas shall include full compensation for all labour, equipment, materials
and other incidentals and work required for finishing as specified, including the loading, transporting and disposal of any material brought down
during the finishing operations.
Loading of the fill material shall only be measured when the material is taken from stockpile, when approved by the Engineer. The haul of the fill
material shall be measured from the point of loading/collection to the point of off-loading as per Section A1.7 of Chapter 1.
A distinction shall be made between construction using conventional construction methods and labour enhancement.
The unit of measurement shall be the square metre of cut or fill slopes or medians and interchange areas finished off as specified.
The areas shall be measured from topographical surveys measured along the slopes. It shall be the sloping area between the shoulder breakpoint
and the toe of the fill in the case of fill slopes. The medians shall include the full width of the median between the inner edges of the shoulders.
The extent of median areas which are to be finished off shall be determined in accordance with the drawings.
Areas, except fill slopes, required to be lined with cast in place or precast concrete linings, kerbing, channelling or chutes, as specified, shall not
be measured and paid for under item C5.2.9. All fill slopes and channel bottoms of open drains resulting from open-drain excavations as defined
in Chapter 3, as well as the floors and sides of existing open drains that are trimmed during the clearing and shaping of existing open drains as
defined in Chapter 3, shall not be measured and paid for under item C5.2.9.
The tendered rates for finishing the fill slopes, medians and interchange areas shall include full compensation for all labour, equipment, materials
and other incidentals and work required for finishing as specified, including the loading, transporting and disposal of any material arising or brought
down during the finishing operations.
CONTENTS
D5.2.1 SCOPE
D5.2.2 GENERAL
D5.2.3 PERFORMANCE GUARANTEE REQUIREMENTS
D5.2.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D5.2.5 VISUALLY ASSESSED PROPERTIES
D5.2.6 INSTRUMENTALLY ASSESSED PROPERTIES
D5.2.7 EVALUATION FOR ACCEPTANCE
D5.2.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D5.2.9 NOTIFICATION OF REMEDIAL WORK
D5.2.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A5.3.1 SCOPE
A5.3.2 DEFINITIONS
A5.3.3 GENERAL
A5.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A5.3.5 MATERIALS
A5.3.6 CONSTRUCTION EQUIPMENT
A5.3.7 EXECUTION OF THE WORKS
A5.3.8 WORKMANSHIP
A5.3.2 DEFINITIONS
The relevant definitions elsewhere in the standard specification are applicable. Additional definitions for this Section are included here.
Single-operation - a single-operation is the amount of work that can normally be carried out during the course of a single work shift using the
applicable construction equipment.
A5.3.3 GENERAL
A5.3.3.1 Sources of material
The sourcing of material shall take place as specified in Chapter 4.
Material shall be obtained from approved sources such as borrow areas, cuts, stockpiles or reclaimed road materials from existing road pavement
layers. Reclaimed road material shall be processed as specified in Section A4.3 of Chapter 4 to produce a material compliant with the material
properties specified in Chapter 4 for the particular intended use of the material, as specified in the Contract Documentation.
Material may also be obtained from compliant commercial and alternative material sources as detailed in the Contract Documentation.
Crushed stone material shall be obtained from approved sources such as quarries, commercial sources and approved cuttings.
A5.3.5 MATERIALS
A5.3.5.1 Material information
The required material properties for each individual pavement layer for a specific pavement design shall be clearly specified in the Contract
Documentation.
The Contract Documentation shall specify which types of materials are to be used for a PMPL layer.
Any anticipated mechanical modification of material shall be stated in the Contract Documentation.
Shoulder layer 95 %
In restricted areas the compacted dry density of the individual pavement layers shall also comply with the requirements given in Table A5.3.5-1
unless specified otherwise in the Contract Documentation.
c) Crushed stone pavement layer compaction requirements (G1 to G4A and G5A materials)
The minimum compacted dry density of a crushed stone pavement layer shall be as specified in Table A5.3.5-2 unless specified otherwise in the
Contract Documentation.
Table A5.3.5-2: Minimum compaction densities for crushed stone pavement layers
Compaction as % Maximum Dry Density (MDD) or as % Bulk Density (BD) or as %
Layer
Apparent Density (AD)
G3 and G4A base layer 98 % to 100 % of MDD (for G3 and G4A) or 85 % of BD for G3 only
PMPL pavement layer (lean mix concrete) Cube crushing strength as specified in Contract Documentation. No density requirement.
The density of the compacted crushed stone base layers (G1 and G2 layers only) shall be tested to the full depth of the layer using a nuclear
gauge.
In restricted areas the in-situ dry density of the crushed stone subbase and base layers shall also comply with the requirements given in Table
A5.3.5-2 unless specified otherwise in the Contract Documentation.
After the construction of the BM rock matrix to the required compaction density the subsequent treatment of the compacted BM layer can vary
and shall be specified in the Contract Documentation or instructed by the Engineer.
Single size rock matrix, usually 63 mm, filled with dry fine filler aggregate using compaction
Dry-bound macadam (DBM)
equipment only. Smooth swept surface.
A DBM slushed afterwards by saturating the filled rock matrix, usually 63 mm, and rolling
Water-bound macadam (WBM) with a steel drum roller. Where the climate does not allow the fine filler aggregate to dry
sufficiently, it may be washed into the coarse aggregate. Smooth swept surface.
Construct a DBM or WBM. Broom away excess aggregate fines and some of the fine filler
Partially penetrated macadam (PPM) aggregate in the exposed open voids. Rough swept surface. Apply slurry which will therefore
only penetrate partially.
Construct the lower portion of the layer as a DBM or WBM. Construct the upper portion of
Composite macadam (CM)
layer of SBM using 50 mm or 37,5 mm aggregate. See Table A4.1.5-8.
During the construction of the trial section these Clauses shall be validated and/or modified where necessary. Any resultant modifications of these
Clauses shall then be implemented during the subsequent construction of the particular crushed stone layer.
The trial section shall establish or verify the following specific aspects:
• The spacing between the off-loaded heaps of crushed stone;
• Compaction moisture content and the compaction factor;
• Compaction passes, compaction frequency and roller amplitude settings;
• The pre-shape level to allow for settlement during compaction;
• The types and method of operation of compaction equipment during slush-compaction of G1 material;
• How long the slush-compaction process shall continue until there are no more air bubbles, the expelled water is clean and movement or
‘heaving’ under compaction has ceased;
• Brooming equipment and the brooming process;
• Progressive development of compaction density in the layer;
• Surface finish evaluation;
• Minimum construction base width where there is no shoulder containment, to ensure that the specified density is achieved across the full
travelled roadway width;
• Grading and plasticity index, post-construction; and
• Approximate drying out time until the moisture content has been reached to allow the layer to be primed.
• The surface regularity shall be checked for compliance.
e) Trial section for a PMPL layer
Before commencing with the construction of the specified PMPL pavement layer in the works, the Contractor shall construct a trial section. The
following Clauses listed in Table A5.3.7-2 are applicable to the construction of this trial section.
Table A5.3.7-2: Clauses applicable to the construction of a PMPL layer
Clause Description
During the construction of the trial section the specification of the Clauses referenced in Table A5.3.7-1 shall be validated and modified where
necessary. Any resultant modifications of these Clauses shall be implemented during the subsequent construction of the PMPL layer in the works.
• The surface regularity shall be checked for compliance.
f) Trial section for a bound macadam (BM) layer
There are several types of BM layers. The Contract Documentation shall specify which specific BM layer shall be constructed for the project and
this BM layer shall be constructed for the trial section. The different BM layers are listed in Table A5.3.5-4.
No BM pavement layer material, other than the compliant material required for the actual trial section, shall be placed on the road prior to the
A5.3.7.10.3 Spreading the aggregate Use labour enhancement for all BM layer
A5.3.7.10.7 Surface finish of BM layer As per the Contract Documentation and Chapter 10 : Surface Treatments
During the construction of the trial section the aspects of these Clauses shall be validated and modified where necessary. Any resultant
modifications of these Clauses shall then be implemented during the subsequent construction of the BM pavement layer.
This trial section shall be constructed where it can be trafficked and monitored during the course of the project. The location of the trial section
shall be as detailed in the Contract Documentation and could form part of the pavement for the deviation. The BM shall be constructed with edge
restraints and on a subbase with the same specification as for the pavement design for the works. The performance of the layer in the trial section
shall be assessed prior to acceptance thereof and use in the main works.
The trial section shall also be used to establish or verify the following aspects:
• The loose to tight compaction factors for the coarse aggregate.
• The loose volume of fine aggregate required per cubic metre of completed layer.
• The loose depth of coarse aggregate required to provide the specified final layer thickness.
• To establish or verify construction techniques, tools and procedures that will achieve the maximum possible density and produce the specified
surface finish.
• To confirm the average density achieved by means of the ‘Rondavel’ test (Clause A5.3.8.3).
• To establish the optimum time to prime.
• The surface regularity shall be checked for compliance.
A5.3.8 WORKMANSHIP
A5.3.8.1 Inspection of the works
The Engineer shall do routine inspections and conduct routine tests to determine whether the quality of material and workmanship provided,
complies with the requirements of the Contract Documentation.
Selected layer 25 mm 33 mm
Subbase layer 15 mm 20 mm
Level control for the different pavement layers shall be done at the following intervals given in Table A5.3.8-2:
Table A5.3.8-2: Pavement layer level control intervals
Layer Longitudinal interval Transverse interval
Selected, sub-base, shoulder and wearing course Centre-line, yellow line and outer edges plus at
20 m
layers intermediate mid-points
c) Grade tolerances
Deviations from the specified longitudinal grade shall not exceed the values given in Table A5.3.8-4 in respect of the specified grades on the
completed base. These allowable deviations are also valid for BM base layers:
2 0,354 %
5 0,224 %
10 0,158 %
20 0,112 %
30 0,091 %
The following formula shall be applicable for any other lengths (ℓ) over which the grade deviations may be calculated:
𝟎. 𝟓
𝒈(%) =
√𝒍
d) Width tolerances
The average width of the layer shall not be less than the specified width, and nowhere shall the outer edge deviate by more than the measurement
shown in Table A5.3.8-5 from the designed road edge lines shown in the Contract Documentation:
Table A5.3.8-5: Pavement layer width tolerances
Layer Maximum deviation from designed edge lines
Selected layer 80 mm
Subbase layer 75 mm
Base layer 50 mm
Adjustment to the payment for the base will be reflected separately in the Contractor’s monthly certification of the works. The adjustment will be
calculated by multiplying the full payment value for each 100m section, for payment items *** _________________ by the payment adjustment
factor derived from Table A5.3.8-6. Contract Price Adjustment shall not be applicable to the payment adjustment for the base. The payment
adjustment shall apply to the total base layer width placed over the 100m section in question.
Surfaced shoulders less than 2,0 m wide will be assumed to have the same roughness measurements as the adjacent lane and the quantity of
material in the shoulder shall be added to the quantity of material of the adjacent lane for determination of the payment adjustment factor.
On sections where the Average IRI100 m is worse than the cut-off value listed in the Contract Documentation the section shall be rejected and
corrective work shall be necessary.
Any corrective work required shall be made by the removal of the total base layer width placed, over the 100 m section in question, followed by
reinstatement. Surfaced shoulders less than 2,0 m wide shall be treated the same as the adjacent slow lane. Corrective work shall not commence
until the Engineer has reviewed the Contractor’s method statement. If the Contractor proposes any other corrective procedure he shall apply to
the Engineer for the Employer’s approval of the proposal. Corrective work shall be done at no cost to the Employer and shall be completed prior
to determining the pavement thickness. After completion of the corrective work, the 100 m sections shall be re-evaluated according to the
B5.3.1 SCOPE
B5.3.2 DEFINITIONS
B5.3.3 GENERAL
B5.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B5.3.5 MATERIALS
B5.3.6 CONSTRUCTION EQUIPMENT
B5.3.7 EXECUTION OF THE WORKS
B5.3.8 WORKMANSHIP
B5.3.1 SCOPE
This Section covers the preparation of the roadbed/subgrade on an existing alignment, the construction of selected subgrade layers (where
applicable), subbase, bases (unstabilised and treated/stabilised in accordance with Section A5.4: Stabilisation), wearing courses and shoulders
with natural and crushed gravel using labour enhanced methods of construction and light plant.
Material for the road pavement layers is produced as specified in the relevant Sections of Chapter 4.
The addition and mixing of stabilising agents either as an integral part of the PMPL process or for some of the conventionally placed road pavement
layers that require treatment and/or stabilisation is specified in Section A5.4.
The reconstruction of existing road pavement layers is specified in Section A5.5.
B5.3.2 DEFINITIONS
Definitions as provided in Clause A5.3.2 apply.
B5.3.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
The relevant specifications of A5.3.3 of Part A shall be applicable.
B5.3.5 MATERIALS
B5.3.8 WORKMANSHIP
B5.3.8.1 Inspection of the works
The provisions of Part A shall apply.
(a) Lower selected subgrade layer (layer thickness indicated) compacted to 93 % of MDD cubic metre (m3)
(b) Lower selected subgrade layer (layer thickness indicated) compacted to 95 % of MDD cubic metre (m3)
(c) Upper selected subgrade layer (layer thickness indicated) compacted to 95 % of MDD cubic metre (m3)
(d) Upper selected subgrade layer (layer thickness indicated) compacted to 97 % of MDD cubic metre (m3)
(e) Sand layer (layer thickness indicated) compacted to 97 % of MDD cubic metre (m3)
(f) Sand layer (layer thickness indicated) compacted to 100 % of MDD cubic metre (m3)
(g) Gravel wearing course layer (layer thickness indicated) compacted to 95 % of MDD cubic metre (m3)
(h) Gravel shoulder layer (layer thickness indicated) compacted to 95 % of MDD cubic metre (m3)
(i) Lower subbase gravel layer (unstabilised) (layer thickness indicated) compacted to 95 % of cubic metre (m3)
MDD
(j) Lower subbase gravel layer (chemically stabilised) (layer thickness indicated) compacted to cubic metre (m3)
95 % of MDD
(k) Upper subbase gravel layer (unstabilised), (layer thickness indicated) compacted to 97 % of cubic metre (m3)
MDD
(l) Upper subbase gravel layer (chemically stabilised), (layer thickness indicated) compacted to cubic metre (m3)
95 % of MDD
(m) Gravel base layer (unstabilised), (layer thickness indicated) compacted to 100 % of MDD cubic metre (m3)
(n) Gravel base layer (chemically stabilised), (layer thickness indicated) compacted to 97 % of cubic metre (m3)
MDD
(o) G5B crushed rock/boulder subbase layer (layer thickness indicated) compacted to 97 % of cubic metre (m3)
MDD
(p) G5B crushed rock/boulder base layer (layer thickness indicated) compacted to 100 % of MDD cubic metre (m3)
(q) G5A crushed rock/boulder subbase layer (layer thickness indicated) compacted to 97 % of cubic metre (m3)
MDD
(r) G5A crushed rock/boulder base layer (layer thickness indicated) compacted to 100 % of MDD cubic metre (m3)
(s) G4A crushed rock/boulder lower subbase layer (unstabilised or chemically stabilised) (layer cubic metre (m3)
thickness indicated) compacted to 95 % of MDD
(t) G4A crushed rock/boulder upper subbase layer (unstabilised or chemically stabilised) (layer cubic metre (m3)
thickness indicated) compacted to 97 % of MDD
(u) G4A crushed rock/boulder subbase layer compacted to 97 % of MDD cubic metre (m3)
(v) G3 crushed stone subbase layer (unstabilised or chemically stabilised) (layer thickness cubic metre (m3)
indicated) compacted to 97 % of MDD
(w) G3 crushed stone base layer (layer thickness indicated) compacted to 85 % of BD cubic metre (m3)
(x) G2 crushed stone base layer (layer thickness indicated) compacted to 88 % of BD cubic metre (m3)
(y) G2 crushed stone base layer (layer thickness indicated) compacted to 88 % of AD cubic metre (m3)
(z) G1 crushed stone base layer (layer thickness indicated) compacted to 86 % of AD cubic metre (m3)
(aa) G1 crushed stone base layer (layer thickness indicated) compacted to 88 % of AD cubic metre (m3)
(bb) Bound macadam layer (layer thickness indicated) compacted to 90 % of AD cubic metre (m3)
(cc) PMPL wet lean-mix concrete layer (Cube crushing strength and layer thickness indicated) cubic metre (m3)
C5.3.2.2 Construction of layers using labour enhancement:
(a) Lower selected subgrade layer (layer thickness indicated) compacted to 93 % of MDD cubic metre (m3)
(b) Upper selected subgrade layer (layer thickness indicated) compacted to 95 % of MDD cubic metre (m3)
(c) Sand layer (layer thickness indicated) compacted to 97 % of MDD cubic metre (m3)
C5.3.3 Construction of crushed stone base supplied by the Employer cubic metre (m3)
This item is for crushed stone base constructed from type G1 or G2 material supplied from the Employer’s stockpile (state location of stockpile)
at R………………….. per ton (layer thickness indicated) and compacted to 88 % AD or 86% AD respectively as specified in the Contract
Documentation.
The unit of measurement shall be the cubic metre of completed crushed-stone base in-situ and compacted to the specified density. The quantity
shall be calculated from the net authorised dimensions of the layer as shown on the drawings or prescribed by the engineer. No adjustments shall
be made to the net specified dimensions for level and thickness tolerances, overbuilding and/or other wastage.
The tendered rate shall include compensation for the purchase of the material from the Employer at R.......................per ton, weighing on the
calibrated weighbridge, furnishing and placing all materials, including crusher fines for correcting the grading of the crushed-stone and hauling the
material to the point of use, rolling slushing and correcting the layers, and for testing, protecting and maintaining the work all as specified.
Item Description Unit
C5.3.4 Deductions for G1 crushed stone base material supplied by the Employer ton (t)
The unit of measurement shall be the ton of material supplied by the Employer.
The value of material supplied by the Employer and to be deducted from payments due to the contractor, shall be determined as the sum of
audited weighbridge documentation and delivery notes.
Item Description Unit
C5.3.5.1 By additional normal grid rolling as per clause A5.3.7.3b) square metre-pass (m2-pass)
The unit of measurement shall be the square metre-pass calculated by multiplying the layer surface area covered by the agreed number of roller-
passes used to break down the material satisfactorily.
The tendered rate for each square metre-pass instructed by the Engineer shall include full compensation for all supervision, labour, equipment,
fuel, materials, work and incidentals necessary for completing the work. The same rates shall be applicable should there be a reduction in the
number of roller-passes for a specific type of roller.
The unit of measurement shall be the cubic metre of oversize material which cannot be broken down on the road and is removed for re-crushing
or removed to spoil as instructed by the Engineer in excess of the 5 % of the compacted layer volume of oversize material included in the rates
tendered for item C5.3.2.
The volume measured for payment shall be taken as 70 % of the loose volume in excess of 5 % of the measured volume of the layer as measured
in the haul vehicles.
The tendered rate shall include full compensation for removing the oversize material from the pavement layers, loading it into the hauling vehicles
and off-loading it at the point of disposal.
The haul of the oversize material in excess of 5 % by volume per layer shall be measured from the point of loading/collection to the point of off-
loading as per Section A1.7 of Chapter 1.
Item Description Unit
The unit of measurement shall be the cubic metre of the recombined material added to and mixed into the pavement layer as specified in Clause
A5.3.7.2. The volume measured for payment shall be taken as 70 % of the loose volume of recovered material as measured in the haul vehicles.
The tendered rate shall include full compensation for mixing the recombined recovered material binder into the layer to form one homogeneous
layer.
Payment for the construction operations required to process and compact the recombined layer will be paid for under item C5.3.2 and other
relevant items
The haul of the recovered material shall be measured from the point of loading/collection to the point of off-loading as per Section A1.7 of Chapter
1.
Item Description Unit
C5.3.8 Processing of coarse gravel subbase or base layers cubic metre (m3)
The unit of measurement shall be the cubic metre of material in the compacted layer calculated using the layer work dimensions given in the
Contract Documentation.
The tendered rate shall include full compensation for carrying out the processing and finishing work for a coarse layer as specified in Clause
A5.3.7.4.
Item Description Unit
(a) Stabilised gravel layer (layer thickness indicated) trial section cubic metre (m3)
(b) Crushed stone subbase layer (layer thickness indicated) trial section cubic metre (m3)
(c) Crushed stone base layer (layer thickness indicated) trial section cubic metre (m3)
(d) PMPL layer (layer thickness indicated) trial section cubic metre (m3)
(e) Bound macadam layer (layer thickness indicated) trial section cubic metre (m3)
(a) Stabilised gravel layer (layer thickness indicated) trial section cubic metre (m3)
(b) Gravel base layer (layer thickness indicated) trial section cubic metre (m3)
(c) Bound macadam layer (layer thickness indicated) trial section cubic metre (m3)
The unit of measurement shall be the cubic metre of layer trial section constructed, tested and accepted. The quantity shall be calculated based
on the authorised dimensions of the trial section layer.
The tendered rate shall include full compensation for providing all the material and constructing the particular layer for the trial section as specified.
The tendered rate shall also include for any costs associated with a delay up to a maximum of ten working days, to allow for testing between
completion of the trial section and the acceptance thereof.
A distinction shall be made between construction using conventional construction and labour enhancement.
The unit of measurement shall be the cubic metre of compliant trial section layer removed to a designated site when instructed by the Engineer.
The tendered rates shall include full compensation for breaking up the trial section layer and for loading the broken up layer material..
The haul of the material to the designated site as instructed by the Engineer and off-loading the material shall be measured from the point of
loading/collection at the trial section to the point of off-loading as per Section A1.7 of Chapter 1.
The removal to spoil of a non-compliant trial section layer shall be done by the Contractor at no cost to the Employer.
Item Description Unit
The unit of measurement shall be the kilometre of riding quality measurements taken in each wheel path, measured along the wheel path as
specified in Clause A5.3.8.5.
The tendered rates shall include full compensation for the cost of all traffic accommodation arrangements required, for several possible
establishments and de-establishments of testing equipment, for the measurement of the riding quality with the specified instrument and the
processing, analysis and interpretation of the riding quality measurements.
Item Description Unit
The unit of measurement shall be the cumulative monetary value of each 100 m section of the completed base layer as measured and
paid under item C5.3.2, multiplied by the applicable payment adjustment factor obtained from Table A5.3.8-6.
CONTENTS
D5.3.1 SCOPE
D5.3.2 GENERAL
D5.3.3 PERFORMANCE GUARANTEE REQUIREMENTS
D5.3.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D5.3.5 VISUALLY ASSESSED PROPERTIES
D5.3.6 INSTRUMENTALLY ASSESSED PROPERTIES
D5.3.7 EVALUATION FOR ACCEPTANCE
D5.3.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D5.3.9 NOTIFICATION OF REMEDIAL WORK
D5.3.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A5.4.1 SCOPE
A5.4.2 DEFINITIONS
A5.4.3 GENERAL
A5.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A5.4.5 MATERIALS
A5.4.6 CONSTRUCTION EQUIPMENT
A5.4.7 EXECUTION OF THE WORKS
A5.4.8 WORKMANSHIP
A5.4 STABILISATION
PART A: SPECIFICATIONS
A5.4.1 SCOPE
This Section covers the work requirements for the treatment of the material properties of natural roadbed, fill layers or pavement layers and
crushed material by stabilisation, all in terms of the definition of Stabilisation in Clause A4.4.2 of Chapter 4.
A5.4.2 DEFINITIONS
The relevant definitions in the standard specifications are applicable. Additional definitions for this Section are included here.
Mechanical modification - mechanical modification, also referred to as granular stabilisation, is a form of stabilisation as defined in Clause A4.4.2
of Chapter 4. Mechanical modification of a pavement layer involves the addition and mixing together of various materials from different sources
to produce a uniformly mixed material that is compliant with the properties required for the pavement layer for which the modified material is being
used.
Lamination layer - a term used to describe the layer formed when a compacted layer delaminates and forms loose and unbonded layers on top
of the layer when incorrect compaction techniques are used. A colloquial term, biscuit layer, is also used for the lamination layers.
Breaking of emulsion - this term describes the process that occurs when the suspended bitumen in the emulsion separates from the water and
the water evaporates, leaving behind bitumen. It is also referred to as the setting of the emulsion.
Filler a filler is a commercially available product. A filler is often a cementitious agent. The quantity added is sufficient to result in improvement of
the properties of the material it is added to, but insufficient to result in the stabilisation of the material should the filler have been added in isolation.
A5.4.3 GENERAL
A5.4.3.1 Stabilisation agents
The type and quantity of cementitious or bituminous stabilisation agent to be used for each layer of material shall be determined as described in
Clauses A4.4.7.1c) and A4.4.7.1d) of Chapter 4.
The different types of cementitious and stabilisation agents are specified in Clauses A4.4.5.2, A4.4.5.3 and A4.4.5.4 respectively of Chapter 4.
Should a non-traditional stabilising or soil treatment agent be proposed by the Contractor, it will only be considered if the requested details specified
in Clause 4.4.5.4 of Chapter 4 are provided.
d) Weather restrictions
No stabilisation shall be done during windy conditions, wind speed more than 15 km/h (4 m/s), wet weather and cold weather when the air
temperature is below 3°C or with falling air temperatures, 7°C and falling.
No stabilisation work shall be commenced if the surface temperature of a compacted stabilised layer may fall below 1°C during the first three (3)
days after stabilisation. The Contractor shall take the necessary precautions and the construction programme for the stabilisation work shall take
the actual and predicted weather conditions into account.
All stabilised layers damaged by rain, frost or by the formation of ice in the layer shall be removed and replaced by the Contractor at no cost to
the Employer.
e) Traffic limitations
No vehicles or construction equipment except that used for mixing the stabilising agent into the layer shall be allowed to travel over the spread
stabilising agent.
No traffic or construction equipment except that required for curing or priming shall be allowed to travel over the compacted stabilised layer during
the specified curing period as per Clause A5.4.7.6, unless specified otherwise in the Contract Documentation.
A5.4.5 MATERIALS
A5.4.5.1 General
For chemically stabilised layers the natural material or the reclaimed road material, even if previously stabilised, shall comply with the requirements
of Table A4.4.5-2 in Chapter 4.
The moisture content at the specified saturation degree (Sr) shall be determined as follows:
Wv = Sr {Xw/Xd - 1000/Gs}
A5.4.8 WORKMANSHIP
A5.4.8.1 Inspection of the works
The Engineer shall do routine inspections and conduct routine tests to determine whether the quality of material and workmanship provided,
complies with the requirements of the Contract Documentation.
Any stabilised layers with lamination layers such as biscuit layers, as identified visually and/or by the hollow sound caused when a heavy chain is
dragged over the stabilised layer, shall be rejected.
The material in the rejected sections of the completed layer shall be ripped and removed and replaced with new material. The new material shall
then be stabilised and compacted according to the specifications prior to the construction of any subsequent layers.
Alternatively, the material in the rejected sections can be recycled in-situ with an additional quantity of stabilising agent as determined by testing
and instructed by the Engineer. In-situ recycling will only be permitted provided that the properties of the recycled material are compliant with the
specified requirements for that layer of material.
All remedial work shall be carried out at no cost to the Employer.
A5.4.8.4 Tolerances
a) Rates of application
(i) Chemical stabilisation
The average rate of application of a cementitious stabilising agent when applied by mechanical bulk spreading equipment and
measured by the canvas patch method shall be within 5 % of the specified rate of application over any section not exceeding 1,0
km in length. No single measurement shall deviate by more than 20 % from the specified rate.
When hand placed and spread, or spotted, stabilising agents shall be spread exactly to the specified rate of application.
The rate of application of the cementitious stabilising agents added to the material in a central mixing plant shall be controlled by
means of weighing the stabilising agent before it is introduced into the mixing plant.
CONTENTS
B5.4.1 SCOPE
B5.4.2 DEFINITIONS
B5.4.3 GENERAL
B5.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B5.4.5 MATERIALS
B5.4.6 CONSTRUCTION EQUIPMENT
B5.4.7 EXECUTION OF THE WORKS
B5.4.8 WORKMANSHIP
B5.4.1 SCOPE
This Section covers the work requirements for the modification or treatment of the material properties of natural roadbed, fill or pavement layer
materials, by treatment with a soil treatment agent. This treatment normally takes place prior to stabilisation of the respective materials or is used
on its own where stabilisation is not required.
This Section also covers the work requirements for the stabilisation of roadbed, fill, pavement layer materials or plant-mixed paver-laid (PMPL)
layers by the addition of a cementitious stabilising agent and/or a bituminous stabilising agent, followed by a curing treatment.
A proportion of activities as defined in Part A under the various sections are therefore suitable for labour enhancement methods.
B5.4.2 DEFINITIONS
Definitions as provided in Clause A5.4.2 apply.
B5.4.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B5.4.5 MATERIALS
The provisions of Part A shall apply.
B5.4.8 WORKMANSHIP
The provisions of Part A shall apply.
Processing and compaction of layer material A5.4.7 Section C5.3 – All applicable items
Section C6.1 of Chapter 6 and
Curing – membrane or prime A5.4.7.6c) / A5.4.7.6d)
Chapter 10 – All applicable items
C5.4.1.1 Pre-treatment of (insert layer thickness) gravel layer cubic metres (m3)
C5.4.1.2 Pre-treatment of (insert layer thickness) gravel layer using labour enhanced methods of cubic metres (m3)
construction
The unit of measurement shall be the cubic metre of pre-treated material, the quantity of which shall be determined in accordance with the
authorised compacted dimensions of the layer being treated.
No distinction be made in respect of the type of treatment agent used, the time taken for completion, or the specific layer being treated. The rate
tendered shall furthermore apply to any combination of agents. Delivering the agent to the point of use and the distinction in respect of the manner
in which the stabilising agent is spread, whether it be by hand using bags or by mechanical bulk spreader shall be paid under item C5.4.5.
The tendered rates shall include full compensation for watering and compacting the surface of the placed material prior to spreading the
pretreatment agent for mixing the specified amount of pre-treatment agent, for the addition of any water required, and all materials, supervision,
labour, equipment, tools and incidentals necessary for completing the specified work including for leaving the layer dormant for a period of 24
hours after being treated.
Distinction shall also be made in respect of the method of mixing and construction of the layer, either using mechanical methods of construction
or using labour enhancement methods. The layer thickness can be varied by up to 20 mm and the rate for this pre-treatment work shall remain
applicable.
C5.4.2.1 Chemical stabilisation (layer thickness indicated) of pavement layers (layer to be stabilised cubic metres (m3)
indicated)
C5.4.2.2 Chemical stabilisation (layer thickness indicated) of pavement layers (layer to be stabilised cubic metres (m3)
indicated) using labour enhanced methods of construction
The unit of measurement shall be the cubic metre of stabilised material, the quantity of which shall be determined in accordance with the authorised
dimensions of the compacted chemically stabilised layers
No distinction shall be made in respect of the type of treatment agent used, the time taken for completion, or the specific layer being treated. The
rate tendered shall furthermore apply to any combination of agents. Delivering the agent to the point of use and the distinction in respect of the
manner in which the stabilising agent is spread, whether it be by hand using bags or by mechanical bulk spreader shall be paid under Item C5.4.5.
The tendered rates shall include full compensation for watering and compacting the surface of the placed material prior to spreading the stabilising
agent, for the mixing of the specified amount of stabilising agent and all materials, supervision, labour, equipment, tools and incidentals necessary
for completing the specified work. No distinction shall be made in respect of the type of cementitious stabilising agent used or the time for
completion or the specific layer being stabilised. Distinction shall be made in respect of the method of mixing and construction of the layer, either
using mechanical methods of construction or using labour enhancement methods. The layer thickness can be varied by up to 20 mm and the rate
for this chemical stabilisation work shall remain applicable.
Item Description Unit
C5.4.3 Stabilised crushed stone PMPL layer (pavement layer, type of material and source cubic metre (m3)
indicated)
The unit of measurement shall be the cubic metre of stabilised material for the PMPL layer, the quantity of which shall be calculated in accordance
with the authorised dimensions of the final layer.
The tendered rate shall include full compensation for mixing the specified amount of stabilising agent at the central mixing plant and all materials,
supervision, labour, equipment, tools and incidentals necessary for completing the specified work. No distinction will be made in respect of the
type of cementitious stabilisation agent used, the time for completion or the specific layer being treated.
Item Description Unit
C5.4.4 Wet lean-mix concrete pavement PMPL layer (indicate specific pavement layer): cubic metres (m3)
The unit of measurement shall be the cubic metre of wet lean-mix concrete for the PMPL layer, the quantity of which shall be calculated in
accordance with the authorised dimensions of the final layer.
The tendered rate shall include full compensation for mixing the specified amount of cementitious agent, water and material at a mixing plant
(PMPL) and all materials, supervision, labour, equipment, tools and incidentals necessary for completing the specified work. No distinction will be
made in respect of the type of cementitious stabilisation agent used, the time for completion or the specific layer being treated.
Item Description Unit
C5.4.5.1 Addition of cementitious stabilisation agents (specify agent separately) for pavement layers
(b) And so forth for other agents (for pavement layers) ton (t)
C5.4.5.2 Addition of cementitious stabilisation agents (specify agent separately) for pavement layers
and spreading the agent using bags and labour enhancement methods.
(b) And so forth for other agents (for pavement layers) ton (t)
The unit of measurement shall be the ton of cementitious stabilising agent spread and mixed into the prepared layer material in-situ.
The tendered rates shall include full compensation for the supply and delivery of the agent to the point of use. The tendered rates shall also include
for spreading the specified amount of cementitious stabilising agent, and all materials, supervision, labour, equipment, tools and incidentals
necessary for completing the specified work. The layer thickness can be varied by up to 20 mm and the rate for this work shall remain applicable.
A distinction shall be made between spreading the cementitious soil stabilisation agents by mechanical bulk spreaders or using labour
enhancement methods.
C5.4.6 Addition of cementitious stabilisation agents (specify agent separately) for a PMPL layer
The unit of measurement shall be the ton of cementitious stabilising agent mixed into the material at a central mixing plant at the specified
application rate.
The tendered rates shall include full compensation for delivery of the agent from storage to the mixing plant and introducing the specified amount
of cementitious agent and water into the mixing plant for the PMPL layer and all materials, supervision, labour, equipment, tools and incidentals
necessary for completing the specified work. No distinction shall be made in respect of the type of cementitious stabilisation agent used, the time
for completion or the specific layer being produced whether that is a wet lean-mix concrete or a chemically stabilised crushed stone material.
Item Description Unit
C5.4.7.1 Bituminous stabilisation (layer thickness indicated) of pavement layers (layer to be indicated) litres (ℓ)
C5.4.7.2 Bituminous stabilisation (layer thickness indicated) of pavement layers (layer to be indicated) litres (ℓ)
using labour enhanced methods of construction
The unit of measurement shall be the cubic metre of stabilised material, the quantity of which shall be determined in accordance with the authorised
dimensions of the bituminous stabilised compacted layer.
The tendered rates for bituminous stabilisation shall include full compensation for watering and compacting the surface of the placed material prior
to spreading the stabilising agent, for mixing the specified amount of stabilisation agent and material and shall include full compensation for all
incidentals. No distinction shall be made with regard to the type of bituminous stabiliser used, the time for completion, and the particular layer to
be stabilised with bitumen. The tendered rate shall apply to any combination thereof.
The layer thickness can be varied by up to 20 mm, and the rate for this cementitious stabilisation work shall remain applicable.
A distinction shall be made between spreading the cementitious soil stabilisation agents by mechanical bulk spreaders or using labour
enhancement methods.
Item Description Unit
The unit of measurement shall be the litre of bituminous stabilising agent mixed into the road layer at the specified application rate. For bitumen
emulsion this shall be the litre of 60 % emulsion mixed into the material. For foamed bitumen this shall be the litre of bitumen that is foamed.
For bitumen emulsion stabilisation the tendered rates shall include full compensation for diluting and introducing the specified amount of
stabilisation agent at the point of use, and shall include full compensation for all incidentals. No distinction shall be made in regard to the type of
bituminous stabiliser used, the method of application, the time for completion, and the particular layer to be stabilised with bitumen and the
tendered rates shall apply to any combination thereof. The layer thickness can be varied by up to 20 mm, and the rate for this bituminous
stabilisation work shall remain applicable.
For foamed bitumen, the rate shall also include for foaming the bitumen on the recycler, including the water and any other additive that may be
required to achieve the minimum foaming characteristics and for injecting the foamed bitumen into the material being processed
The tendered rates shall also include full compensation for heating and the transfer into tankers of the bitumen. It shall also include for coupling
to the recycling train, for all transport on site, for any re-heating required, for all wastage and for strict adherence to all safety measures required
when handling warm or hot bitumen.
Item Description Unit
C5.4.9.1 Filler for bituminous stabilisation (specify agents separately) ton (t)
C5.4.9.2 Filler for bituminous stabilisation spreading the agent or filler using labour enhanced methods ton (t)
of construction (specify agents separately)
The unit of measurement shall be the ton of cementitious agent mixed into the road layer at the specified application rate.
The tendered rates shall include full compensation for the supply and the blending of the specified amount of filler with the bituminous stabilisation
process and all materials, supervision, labour, equipment, tools and incidentals necessary for completing the specified work. No distinction will be
made in respect of the type of filler used, the time for completion or the specific layer being treated.
A distinction shall be made between spreading the filler by mechanical bulk spreaders and using labour enhancement methods.
The unit of measurement shall be the kilolitre of water provided and applied for curing a chemically stabilised layer.
The tendered rate shall include full compensation for furnishing, transporting and applying the water.
Item Description Unit
C5.4.11 Curing by covering with the subsequent layer square metre (m2)
The unit of measurement shall be the square metre of chemically stabilised pavement layer being cured by covering it with the subsequent layer.
The quantity will be determined by the plan area of the authorised dimensions of the layer being cured
The tendered rate shall include full compensation for incidentals in respect of applying the subsequent layer for curing as specified, including the
cost of regularly supplying and applying water.
Item Description Unit
The unit of measurement shall be the litre of curing material measured at spraying temperature and sprayed as specified.
The tendered rates shall include full compensation for supplying the material, preparation of the surface before applying the curing membrane,
applying the membrane material and maintaining the surface as specified.
Item Description Unit
C5.4.13 Trial section for a PMPL layer (specify width) square metre (m2)
The unit of measurement for the trial section of the plant-mixed paver-laid pavement layer shall be the square metre of trial section of the specified
width as specified in the Contract Documentation measured along the centre line of the road. A total length of at least 250m of trial section and
no more than 350 m will be measured for payment as a trial section.
The tendered rate shall include full compensation for supplying, introducing and mixing the cementitious stabilising agent at the specified rate at
the mixing plant for the construction of the trial section.
Item Description Unit
C5.4.14 Trial section for a chemically stabilised layer cubic metre (m3)
The unit of measurement for the trial section of a chemically stabilised pavement layer shall be the cubic metre of trial section as per the authorised
dimensions. A total length of at least 150 m of trial section and no more than 200 m will be measured for payment as a trial section.
The tendered rate shall include full compensation for placing spreading and mixing the stabilising agent at the specified application rate during
the construction of the trial section.
Item Description Unit
C5.4.15 Trial section for a bituminously stabilised layer (specify width) square metre (m2)
The unit of measurement for the trial section of a bituminously stabilised pavement layer shall be the square metre of trial section of the specified
width as specified in the Contract Documentation measured along the centre line of the road. A total length of at least 250 m of trial section and
no more than 350 m will be measured for payment as a trial section.
The tendered rate shall include full compensation for placing spreading and mixing the bituminous stabilising agent and filler at the specified
application rate during the construction of the trial section.
Item Description Unit
The unit of measurement shall be the cubic metre of material in the compacted layer which has been mechanically modified as per Clause
A5.4.7.2a) calculated using the layer work dimensions given in the Contract Documentation.
The tendered rate shall include full compensation for mixing all the different materials together to form one homogeneous layer as per Clause
A5.4.7.2.
Payment for the construction operations required to process and compact the modified layer shall be made under item C5.3.2.
Item Description Unit
The unit of measurement shall be the cubic metre of soil binder added to and mixed into the pavement layer as per Clause A5.4.7.2b). The volume
CONTENTS
D5.4.1 SCOPE
D5.4.2 GENERAL
D5.4.3 PERFORMANCE GUARANTEE REQUIREMENTS
D5.4.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D5.4.5 VISUALLY ASSESSED PROPERTIES
D5.4.6 INSTRUMENTALLY ASSESSED PROPERTIES
D5.4.7 EVALUATION FOR ACCEPTANCE
D5.4.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D5.4.9 NOTIFICATION OF REMEDIAL WORK
D5.4.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A5.5.1 SCOPE
A5.5.2 DEFINITIONS
A5.5.3 GENERAL
A5.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A5.5.5 MATERIALS
A5.5.6 CONSTRUCTION EQUIPMENT
A5.5.7 EXECUTION OF THE WORKS
A5.5.8 WORKMANSHIP
A5.5.1.1 Patching
Patching covers the work requirements for the patching of existing pavement layers, and in exceptional cases patching fills and the roadbed, with
the purpose of repairing local failures. Patching involves excavating the existing failed sections to the specified depth and area, removing the
excavated material and reconstructing the excavated fills and pavement layers with the specified material.
Patching specified in this Section A5.5 is applicable when the project scope of works is predominantly the reconstruction of Pavement Layers.
Patching specified in Section A8.8 is applicable when the project scope of works is predominantly the construction of Asphalt Layers.
This scope also covers the work requirements for the repair of edge breaks.
Resurfacing the repaired failed area does not form part of this scope and is provided for in Chapters 8 and 9.
A5.5.2 DEFINITIONS
The relevant definitions in the standard specification are applicable. Additional definitions for this Section are included here.
Conventional equipment - this is equipment that is normally used for the construction of the Works. This equipment excludes equipment
specifically designed and used for in-situ reconstruction works and/or for the recycling of materials.
Cross-mixing - this is the mixing of layer materials horizontally across a layer width when the material properties of the layer are not the same
throughout the width and the depth of the layer. Cross-mixing cannot be carried out using a recycler.
Edge break - an edge break is a defect in which the outer edge of the wearing course and part of the underlying pavement layer (asphalt or
crushed stone or gravel) is broken and/or worn away resulting in an irregular road edge line with an average defect width of 250 mm or less. Edge
breaks wider than 250 mm are defined as patching.
In-situ - this means in the actual original or final location without moving the material elsewhere.
Patching - means the repair of failures in fill and/or pavement layers when the failed width is less than 1,0 m or the failed length is less than 25
m or the failed area is less than 100 m2. Patching does not include the pretreatment of a surfacing, or the repair/patching of surfacing defects, or
the rehabilitation of a concrete pavement which is covered in Chapters 8 (pretreatment), 8 (surface defects) or 7 (repair of concrete).
Reconstruction - this is the reconstruction of existing pavement layer material (in-situ or reclaimed material) with or without stabilisation.
Reconstruction in several construction phases can be accomplished using conventional construction equipment to reclaim and reconstruct layer
work material or in a single construction phase using a recycler along with some conventional construction equipment to achieve the reclaiming
and reconstruction of layer work material.
A5.5.3 GENERAL
A5.5.3.1 Traffic accommodation
The traffic accommodation arrangements required during the reconstruction of existing roadworks in urban and rural areas are specified in Chapter
1 of the specifications.
The works-specific details shall be specified in the Contract Documentation.
A5.5.5 MATERIALS
The Contractor shall ensure that reclaimed material complies with the specified requirements of Chapter 4 prior to use in the particular pavement
layer.
Further specifications for patching of existing road pavement layers and for the processing and compaction of existing road pavement layer
materials using a recycler, are contained in this Section A5.5.
a) Recycler
(i) Recycler performance
The recycler shall comply with the following requirements:
• The recycler shall have sufficient power to break down and mix the existing pavement material while pushing or pulling bulk
supply tankers.
• Have a level-control system which is capable of maintaining the cut depth within a tolerance of 10 mm of the specified depth
during continuous operation.
• The cutter shall have a minimum cut width of 2,0 m with the capability to change the speed of rotation and forward movement.
The machine shall be capable of reconstruction to the specified depth in a single pass. Maximum depth capability of the
recycler shall be 0,4 m.
• The maximum speed of advance recommended by the manufacturer of the particular recycler shall be provided by the
Contractor for acceptance. A maximum speed of advance of 10 m/min shall not be exceeded.
(ii) Recycler liquid application
The liquid application system of the recycler shall comply with the following requirements:
• A liquid application system dedicated to adding water to the material in the mixing chamber shall be fitted.
• Where a bituminous stabilising agent is to be applied, a second separate liquid application system shall be fitted to add the
stabilising agent to the material in the mixing chamber. The system shall be appropriate for the addition of either bitumen
emulsion or foamed bitumen as required.
• The application systems shall be controlled by a micro-processor / flow meter combination that can accurately regulate pump
delivery or flow rate in accordance with the speed of advance of the recycler and the volume of material being processed.
• All liquid application systems shall include a dedicated spray bar that spans the full width of the mixing chamber. Each spray
bar shall be equipped with multiple injection nozzles mounted equidistant along the length of the bar at a maximum interval
of 200 mm with the ability to close off selected nozzles, thereby allowing the required width of application to be set.
• Where two liquid application systems are used, the water application spray bar shall be mounted ahead of the other spray bar
(relative to the direction of rotation of the cutter) such that the material encounters the water spray before encountering the
stabilising agent.
The liquid application system shall also have the following specific features installed on the recycler, for foamed bitumen:
• Each injection nozzle on the spray bar fitted with an expansion chamber capable of adequately foaming the bitumen.
• Gauges installed on the bitumen supply line for monitoring the bitumen temperature and pressure.
• A feature to demonstrate that all expansion chambers are free of blockages in both the water and bitumen feed lines.
• A test nozzle to provide a representative sample of foamed bitumen at any stage during normal operations.
• A micro-processor that shall continuously monitor the actual bitumen consumption whilst working and provide a continuous
accumulative total that allows immediate reconciliation with the theoretical consumption required to meet the specified nett
bitumen application rate.
(iii) Mixed material placement by the recycler and subsequent compaction
The recycler shall be capable of breaking down the material to the specified depth in the layer or layers of the existing pavement
and then blending that material together with additional material as and when required, with a stabilising agent, with water and
any other specified agents or additives. The machine shall be capable of breaking down the material and of achieving the required
blend and consistency of mix in a single pass.
The in-situ material mixed by the recycler and then levelled and placed behind the recycler, shall be compacted using suitable
compaction equipment and graders to construct a layer that meets the specified requirements.
Sufficient construction equipment shall be utilised to enable the stabilised material to be processed and finished within the time
limitations specified in Table A5.4.3-1.
b) Milling machine
When the Contractor intends to use construction equipment such as a track-mounted milling machine to pulverise the existing layer material in-
e) Water tanker
Self-propelled water tankers with a minimum capacity of 15 000 litres are essential.
Water tankers involved with bitumen emulsion stabilised materials shall only ever transport diluted emulsion. Each water tanker must be equipped
with a circulating pump system to circulate the emulsion after standing for two days and before each water tank spray. These water tanks shall
not be equipped with a spraybar but with a concave dish located beneath a vertical outlet pipe. The emulsion must be released by opening an
audco-type valve immediately above the concave dish. The shape of the concave dish will ensure a widespread spray distribution of emulsion.
This is a cold application process of emulsion.
f) Compaction equipment
The primary compaction rollers shall be selected by the Contractor to suit the material type and layer thickness being compacted and to achieve
the specified density requirements. A primary compaction roller may be a single drum vibrating roller. A padfoot drum is normally fitted to the
primary roller when the layer thickness exceeds 150 mm. A pneumatic-tyred roller (PTR) may be used along with a padfoot primary roller as the
primary compaction roller combination when processing fine material. A padfoot roller along with a smooth drum roller may be used as the primary
compaction rollers to compact a coarse material.
Table A5.5.6-1: Primary roller: Recommended static mass
Layer thickness (mm) Static mass (ton)
< 150 12
150 - 200 15
200 - 300 20
300 - 350 25
The secondary compaction rollers shall be selected by the Contractor for finishing the surface of the layer such as a suitable smooth-drum vibratory
roller and/or a PTR or in combination.. A single or tandem smooth drum roller may be used. The rollers shall be used to compact the upper portion
of the layer and to produce a well-knit, smooth surface finish.
A 20 ton PTR as a finishing roller may work well once the grader has completed cutting the layer to level and cross-fall, to achieve a tightly-knit
surface finish.
A trial section shall be constructed to resolve the best roller combinations for the primary rollers, the secondary rollers and the finishing rollers.
A5.5.8 WORKMANSHIP
A5.5.8.1 Inspection of the works
The Engineer shall do routine inspections and conduct routine tests to determine whether the quality of material and workmanship provided,
complies with the requirements of the Contract Documentation.
Any reconstructed layer with lamination layers or biscuit layers, as identified by the hollow sound caused when a heavy chain is dragged over the
compacted layer or when the layer is tapped with a geological hammer shall be rejected. The material in the rejected sections of the completed
layer shall be reconstructed in accord with the specifications or in accord with instruction from the Engineer. The layer shall be reconstructed prior
to the construction of any subsequent layers at no cost to the Employer.
CONTENTS
B5.5.1 SCOPE
B5.5.2 DEFINITIONS
B5.5.3 GENERAL
B5.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B5.5.5 MATERIALS
B5.5.6 CONSTRUCTION EQUIPMENT
B5.5.7 EXECUTION OF THE WORKS
B5.5.8 WORKMANSHIP
B5.5.1 SCOPE
This Section covers the work requirements for the reconstruction of existing road pavement layers. This comprises patching and in situ
reconstruction.
A relative large proportion of activities as defined in Part A under the various sections are therefore suitable for labour enhanced methods of
construction.
B5.5.2 DEFINITIONS
Definitions as provided in Clause A5.5.2 apply.
B5.5.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B5.5.5 MATERIALS
The provisions of Part A shall apply.
B5.5.8 WORKMANSHIP
The provisions of Part A shall apply.
C5.5.1 Compiling and implementing M&U plans for the reconstruction of an existing road number (No)
pavement
The unit of measurement shall be the number of M&U plans for the reconstruction work. Several plans shall be required as specified in Clauses
A5.5.3.8 and A5.5.3.9.
The tendered rate shall include full compensation for gathering all information, compiling the plan(s) and for ensuring the implementation thereof
during the reconstruction work.
(b)
(a) Uniform section from km__________ to km__________ kilometre (km)
(c)
(b) Additional uniform sections kilometre (km)
(a)
(a) Uniform section from km __________ to __________ kilometre (km)
(b)
(b) Uniform section from km __________ to __________ kilometre (km)
(c)
(c) Additional uniform sections kilometre (km)
The unit of measurement shall be the kilometre of uniform section of road to be reconstructed and rehabilitated, measured along the centre-line
of the existing road. Each uniform section shall be measured separately. In the case of an undivided road carriageway this shall be measured
once along the centreline. In the case of a divided road carriageway this shall be measured once along each carriageway separately.
The tendered rates shall include full compensation for undertaking all the work required in preparation for reconstruction. This work includes all
survey and survey-related work such as setting out, checking the design levels and for preparing the information for submission to the Engineer
for approval of the final design levels.
The tendered rates shall also include for the removal of standing water, grass and weeds from the road surface including the shoulders.
Item Description Unit
C5.5.3 Construction equipment for sampling of in-situ material for mix design procedure number (No)
The unit of measurement shall be the number of positions for the sampling of in-situ material for the mix design procedure specified in Section
A4.4 of Chapter4
The tendered rate shall include full compensation for all costs to make available and to transport the recycler and other equipment to each sampling
position.
The tendered rate shall also include full compensation to provide the required traffic accommodation during the sampling process as specified in
the Contract Documentation
Item Description Unit
C5.5.4 Sampling of in-situ material for mix design procedure number (No)
The unit of measurement shall be the number of positions for sampling of in-situ material for the mix design procedure specified in Section A4.4
of Chapter 4.
The tendered rate shall include full compensation for all costs to operate the recycler and other equipment at each sampling position. This shall
include full compensation for breaking up the pavement for sampling and subsequent temporary patching of the sampled location by adding make-
The unit of measurement for the trial section using a recycler shall be the cubic metre of trial section constructed to the depth and width as
specified in the Contract Documentation. The quantity shall be calculated based on the cubic metre of the authorised dimensions of the trial
section. The trial section shall be at least 150 m long but no more than 200 m long.
The tendered rate shall include full compensation for setting out the trial section, preparing and providing the production plan for the trial section
specifically, preparing the existing road surface where required and breaking up the existing layer to the specified depth when this layer has not
been specified to be pre-milled or pre-pulverised. When specified, pre-milling or pre-pulverisation will be measured and paid for under item C5.5.7.
The tendered rate shall include breaking down the layer and preparing the material utilising a recycler, adding any extra water required and placing
the material followed by the primary and secondary compaction of the material all in accordance with Section A5.5. The rate shall include cutting
final levels to tolerance as well as the protection and maintenance of the layer and conducting process control and monitoring, for protecting the
adjacent pavement and for the repair thereof should it be damaged.
The tendered rate shall include full compensation for all labour, equipment and incidentals required to reconstruct the pavement layer as specified
in the Contract Documentation.
The procurement, storage, spreading and mixing in of the chemical and/or bituminous stabilising agent for the stabilisation of the layer shall be
measured and paid for in accord with the relevant payment items of Section C4.4 of Chapter 4 and Section C5.4.
The tendered rate shall include full compensation for any cost incurred by the Contractor while awaiting the approval of the trial section.
Item Description Unit
C5.5.6 Construction of a trial section using conventional construction equipment cubic metre (m3)
The unit of measurement for the trial section using conventional construction equipment shall be the cubic metre of trial section constructed to the
depth and width as specified in the Contract Documentation. The quantity shall be calculated based on the cubic metre of the authorised
dimensions of the trial section. The trial section shall be at least 150 m but no more than 200 m long.
The tendered rate shall include full compensation for setting out the trial section, preparing and providing the production plan for the trial section
and preparing the existing road surface where required. Pre-milling or pre-pulverising of the existing pavement layer shall be carried out as part
of the layer preparation when specified in the Contract Documentation. Where specified, pre-milling or pre-pulverisation will be measured and
paid for under item C5.5.7.
The tendered rate shall include for processing, which shall include breaking down the material when no pre-milling or pre-pulverisation is specified
and for cutting final levels to the specified tolerances, all in accordance with Section A5.3. The tendered rate shall include the removal of up to 5
% oversize material by volume of the compacted layer. The tendered rate shall include the protection and maintenance of the layer, conducting
process control and monitoring and protecting the adjacent pavement from being damaged and for the repair thereof should it be damaged.
The tendered rate shall include full compensation for all labour, equipment and incidentals required to reconstruct the pavement layer as specified
in the Contract Documentation.
The procurement, storage, spreading and mixing in of the chemical and/or bituminous stabilising agent for the stabilisation of the layer shall be
measured and paid for in accord with the relevant payment items of Section C4.4 of Chapter 4 and Section C5.4.
The tendered rate shall include full compensation for any cost incurred by the Contractor while awaiting the approval of the trial section.
Item Description Unit
C5.5.7.1 Pre-milling an asphalt wearing course (depth of pre-milling varies between 10 mm and 40 mm square metre (m2)
maximum).
C5.5.7.2 Pre-milling a seal wearing course (depth of pre-milling varies between 10 mm and 25 mm) square metre (m2)
The unit of measurement shall be a square metre of road surface pre-milled in accordance with the specifications. The quantity shall be
calculated based on the square metres of the actual pre-milling areas.
The tendered rates shall include full compensation for pre-milling ahead of reconstruction, for removing the isolated high spots with a minimum
milling depth of 10 mm and maximum milling depth of 40 mm or 25 mm for the asphalt wearing course or the seal wearing course respectively.
The tendered rates shall also include for directly loading and removing the milled material, for all plant movement over the site between isolated
high spots for providing all equipment, labour, supervision and incidentals for completing the work in accordance with the specifications.
The haul of the material shall be measured from the point of loading at the pre-milling section to the point of off-loading as per Section A1.7 of
Chapter 1.
C5.5.8.1 Asphalt wearing course (specify nominal depth) cubic metre (m3)
C5.5.8.2 Crushed stone base (specify nominal depth) cubic metre (m3)
C5.5.8.3 Stabilised crushed stone (specify nominal depth) cubic metre (m3)
C5.5.8.4 Stabilised gravel layer (specify nominal depth) cubic metre (m3)
The unit of measurement shall be the cubic metre of in-situ measured pavement layer that is pre-pulverised in-situ, regardless of the hardness or
type of material encountered in each pavement layer. The quantity shall be calculated from the measurement of the actual width and depth of the
layer that is pre-pulverised. The quantity shall not be adjusted to include any allowance for overlaps between adjacent cuts, nor for the number of
cuts required to cover the actual width of pre-pulverising.
The tendered rates shall include full compensation for setting out the works, for pre-pulverising each different type of material in the existing
pavement structure, for controlling the depth of pre-pulverising, for the addition of water whilst pre-pulverising, for mixing, placing, shaping, cutting
levels and compaction of the pulverised material as specified.
The tendered rates shall include full compensation for all transport, labour, equipment and incidentals required to pre-pulverise the material as
specified.
Item Description Unit
The unit of measurement shall be a cubic metre of material from an existing pavement layer, temporarily bladed to windrow and measured in its
original position before removal.
The tendered rate shall include full compensation for temporarily blading the layer material to windrow and later blading the material back and
also for all clearing-up work which may be necessary after the material has been bladed back.
Only material bladed to windrow on the instruction of the Engineer in order to expose the underlying layer shall be measured and paid for.
Material removed and temporarily stockpiled, will not be paid for under this item.
Item Description Unit
The unit of measurement shall be the square metre of exposed pavement layer compacted in accordance with the specification for a single roller-
pass. The quantity will be measured in accordance with the authorised dimensions of the area to receive single roller-pass compaction.
The area to be roller-pass compacted shall be adjusted to be commensurate with the number of roller-pass compaction instructed. The authorised
area will be doubled when two roller-pass compaction is specified or trebled when three roller-pass compaction is specified in the Contract
Documentation, or instructed by the Engineer, and so forth.
The tendered rates shall include full compensation for shaping, providing the rollers, keeping the rollers operational and ready for when soil-
moisture conditions are favourable, and for compacting the pavement layer with the specified number of roller-passes.
The Contractor shall base the tendered rates on a single, one direction pass for each specified type, size and weight of roller. The area covered
by the nominal roller overlap width required to ensure full coverage of the area being compacted shall not be measured for additional payment. If
the rollers available on site are different types, sizes and weights than those specified in the Contract Documentation, then revised rates which
take into account the percentage increased or decreased compaction effort per roller-pass, shall be agreed with the Contractor based on the same
percentage increase or decrease.
The unit of measurement for the addition of water shall be the kilolitre of water applied as required.
The tendered rates for the addition of water to achieve the required compaction shall include full compensation for the supply, delivery and
application of the water when required.
Item Description Unit
The unit of measurement shall be the kilolitre of water applied to the floor of the excavation that is to be compacted as per the instruction of the
Engineer, for roller-pass compaction only.
The tendered rate shall include full compensation for procuring and applying the water, including all transport costs of the water.
The unit of measurement shall be the cubic metre of surplus material removed from site. The quantity shall be taken as 70 % of the loose volume
measured in the haulage trucks. Accurate truck records shall be kept on site and submitted to the Engineer on a daily basis.
The tendered rate shall include full compensation for gathering the surplus material by windrowing or pushing it into heaps, for loading and
transporting to a designated spoil or stockpile site for offloading and spreading or stockpiling the material.
The tendered rate shall include full compensation for all labour, equipment and incidentals required to remove the material as specified.
The haul of the recovered material shall be measured from the point of loading or collection to the point of off-loading as per Section A1.7 of
Chapter 1.
Item Description Unit
C5.5.13 Cross mixing of material (specify nominal depth) cubic metre (m3)
The unit of measurement shall be the cubic metre of material to be cross mixed, as instructed by the Engineer, to ensure lateral mixing of the
material. The quantity shall be calculated from the actual authorised dimensions of the finally cross mixed and compacted layer. The authorised
dimensions shall be as per the Contract Documentation or as instructed by the Engineer.
The tendered rate shall include full compensation for cross mixing, adding water and spreading the material.
The tendered rate shall include full compensation for all labour, equipment and incidentals required to complete the cross mixing as specified.
Item Description Unit
(a) Using non-cemented material compacted to _________ mm thick cubic metre (m3)
(b) Using cemented material compacted to _________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to _________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to __________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to _________ mm thick cubic metre (m3)
(b) Using cemented material compacted to _________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to _________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to __________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to _________ mm thick cubic metre (m3)
(b) Using cemented material compacted to _________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to _________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to __________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
The unit of measurement for items C5.5.14; C5.5.15 and C5.5.16 above, shall be the cubic metre of in-situ reconstructed pavement layer, using
a recycler, the quantity of which shall be calculated in accordance with the authorised dimensions of the compacted layer.
The tendered rates shall include full compensation for setting out the works, preparing and providing the production plan(s) as per Clause
A5.5.8.5a), preparing the existing road surface where required and breaking up the existing layer to the specified depth.
The tendered rates shall include full compensation for breaking down the in-situ layer and preparing the material utilising a recycler, adding any
extra water required and placing of the material followed by the primary compaction and secondary compaction of the material. The rate shall
include full compensation for cutting final levels as well as the protection and maintenance of the layer, conducting process control and daily
monitoring, measuring and demarcating the work where layers are only partly reprocessed and for protecting the adjacent pavement and for the
repair thereof should it be damaged.
The tendered rates for items C5.5.14.1d), C5.5.14.2d) and C5.5.14.3d); items C5.5.15.1d), C5.5.15.2d) and C5.5.15.3d) and items C5.5.16.1d),
C5.5.16.2d) and C5.5.16.3d) shall also include full compensation for shaping and compacting the pre-pulverised material to 93% MDD.
The tendered rates shall include full compensation for the application of the bituminous stabilising agents in accord with the specifications of
Section A5.5.
The layer thickness to be stabilised can be varied by the Engineer by up to 20 mm, and the rate for this stabilisation work shall remain applicable.
The tendered rates shall also include for all labour, equipment and incidentals required to reconstruct the pavement layer.
The procurement, storage, spreading and mixing in of the chemical and/or bituminous stabilising agent for the stabilisation of the layer shall be
(a) Using non-cemented material compacted to _________ mm thick cubic metre (m3)
(b) Using cemented material compacted to _________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to _________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to __________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to _________ mm thick cubic metre (m3)
(b) Using cemented material compacted to _________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to _________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to __________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to _________ mm thick cubic metre (m3)
(b) Using cemented material compacted to _________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to _________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to __________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
(a) Using non-cemented material compacted to __________ mm thick cubic metre (m3)
(b) Using cemented material compacted to __________ mm thick cubic metre (m3)
(c) Using a combination of non-cemented and cemented material compacted to __________ mm cubic metre (m3)
thick
(d) Using pre-pulverised material (as per item C5.5.8) compacted to _________ mm thick cubic metre (m3)
The unit of measurement for items C5.5.17, C5.5.18 and C5.5.19 shall be the cubic metre of reconstructed pavement layer, using conventional
construction equipment the quantity of which shall be calculated in accordance with the authorised dimensions of the compacted layer.
The tendered rates shall include full compensation for setting out the works, preparing and providing the production plan(s) as per Clause
A5.5.8.5a), preparing the existing road surface where required and breaking up the existing layer to the specified depth when this layer has not
been specified to be pre-milled or pre-pulverised.
The tendered rates shall include full compensation for processing and compacting the in-situ material, which shall include breaking down any
oversize material, all in accord with Section A5.3 and cutting final levels to the specified tolerances. The tendered rates shall include full
compensation for the removal of up to 5 % oversize material by volume of the compacted layer as specified in the Contract Documentation. The
tendered rates shall include full compensation for cutting final levels. The tendered rates shall include full compensation for the protection and
maintenance of the layer, conducting process control and monitoring and protecting the adjacent pavement from being damaged and for the repair
thereof should it be damaged.
The tendered rates for items C5.5.17.1d), C5.5.17.2d) and C5.5.17.3d); items C5.5.18.1d), C5.5.18.2d) and C5.5.18.3d) and items C5.5.19.1d),
C5.5.19.2d) and C5.5.19.3d) shall also include full compensation for shaping and compacting the pre-pulverised material using one roller-pass
compaction with a static weight 15 ton smooth drum roller..
The layer thickness to be stabilised can be varied by the Engineer by up to 20 mm, and the rate for this stabilisation work shall remain applicable.
The tendered rates shall also include for all labour, equipment and incidentals required to reconstruct the pavement layer as specified in the
Contract Documentation.
The procurement, storage, spreading and mixing in of the chemical and/or bituminous stabilising agent for the stabilisation of the layer shall be
measured and paid for in accord with the relevant payment items of Section C4.4 of Chapter 4 and Section C5.4.
Item Description Unit
The unit of measurement shall be a cubic metre of make-up material required on the instruction of the Engineer. The quantity will be determined
by way of cross-sections unless the Contract Documentation specifies that the quantity shall be taken as 70 % of the loose volume measured in
the haulage trucks.
The tendered rates shall include full compensation for procuring, adding and spreading the material over the existing pavement layer to be
reconstructed. The tendered rates shall include full compensation for levelling and pre-compacting the material when a recycler will be used to
carry out the reconstruction.
The haul of the make-up or shortfall material shall be measured from the point of loading or collection to the point of off-loading as per Section
The unit of measurement for items C5.5.21.1 and C5.5.21.2 shall be the square metre of stabilised layer finished off by slushing with water or
diluted emulsion. The area shall be calculated from the authorised dimensions of the actual width and length of the stabilised layer so treated.
The tendered rates for items C5.5.21.1 and C5.5.21.2 shall include full compensation for the provision of all equipment, materials, labour and all
other incidentals to slush the layer as specified and for marking out the area to be slushed.
The unit of measurement for items C5.5.21.3 shall be the litre of diluted emulsion, measured at spraying temperature (see Chapter 8), applied in
accord with the Contract Documentation or as instructed by the Engineer.
The tendered rates for C5.5.21.3 shall include full compensation for the provision of all equipment, materials, labour and all other incidentals to
apply the diluted emulsion fog spray to the layer as specified. The tendered rates shall also include full compensation for marking out the area to
be sprayed with the diluted emulsion and for preparing the area as specified in Chapter 8.
The procurement, storage, handling and application of the bituminous emulsion for slushing or for spraying shall be measured and paid for under
the relevant items in Section C4.4 of Chapter 4 and Section C5.4 as part of the bituminous stabilising agent.
Item Description Unit
(a)
(i) Not exceeding 20 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(ii)
(b) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(iii)
(c) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm. cubic metre (m3)
(a)
(i) Not exceeding 20 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(ii)
(b) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(iii)
(c) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(d)
(i) Not exceeding 20 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(ii)
(e) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(iii)
(f) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm. cubic metre (m3)
C5.5.22.2 Excavate the following layers using labour enhanced methods of construction:
(g)
(i) Not exceeding 20 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(ii)
(h) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(iii)
(i) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(ii)
(e) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(iii)
(f) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(j)
(i) Not exceeding 20 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(ii)
(k) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(iii)
(l) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm cubic metre (m3)
The unit of measurement shall be a cubic metre of material excavated from the existing pavement including from the edge of the pavement for
edge repairs. The quantity shall be calculated in accordance with the authorised dimensions of the excavation.
The specified saw-cutting for the patch shall be measured and paid for under Section C4.3 of Chapter 4.
The tendered rates shall include full compensation for demarcating the excavation, excavating the material, placing the excavated material in
temporary stockpiles, for loading the material into haul trucks and for spoiling the material at a designated spoil site.
Payment shall distinguish between the different types of pavement material excavated as described in this item.
The haul of the excavated material shall be measured from the point of loading or collection to the point of off-loading as per Section A1.7 of
Chapter 1.
Distinction shall be made in respect of the method of construction specified. Where the excavation of material is specified by means of labour
enhancement methods, the tendered rates shall include wheelbarrow transport over a free haul distance of 50 m.
Item Description Unit
C5.5.23.1 Edge break cutting back when narrower than 250 mm metre (m)
C5.5.23.2 Edge break cutting back when narrower than 250 mm using labour enhanced methods of metre (m)
construction
The unit of measurement for cutting back the edges shall be the metre of pavement edge cut back and excavated as specified and measured
parallel to the road centreline. This item shall only apply to edge breaks of which the finally repaired width is less than 250 mm.
The tendered rates for cutting back the edge shall include full compensation for demarcating the edge repair cutting the edge to the line as
specified in the Contract Documentation or as instructed by the Engineer, excavating the material to the specified depth and for loading all
excavated and loose material and hauling to spoil.
The tendered rates shall also include full compensation for labour, material, and all incidentals necessary for completing all the work in accordance
with the specifications.
The haul of the excavated material shall be measured from the point of loading or collection to the point of off-loading as per Section A1.7 of
Chapter 1.
Distinction shall be made in respect of the method of construction specified. Where the cutting back of edge break is specified by means of labour
enhancement methods, the tendered rates shall include wheelbarrow transport over a free haul distance of 50 m.
Item Description Unit
C5.5.24.1 Edge break patching using emulsion treated base (ETB) material to a maximum depth of 150 metre (m)
mm
C5.5.24.2 Edge break patching using labour enhanced methods of construction and (ETB) to a maximum metre (m)
depth of 150 mm
The unit of measurement for patching the edges shall be a metre of pavement edge patched as specified and measured parallel to the road
centreline. This payment item shall only apply to edge breaks of which the finally repaired width is less than 250 mm.
The tendered rates for reconstructing pavement edges shall include full compensation for compacting the exposed pavement layer surface on which
the new edge is to be constructed.
The tendered rates shall also include full compensation for procuring, furnishing and mixing all materials as specified for ETB material in Clause
A4.1.5.14 of Chapter 4, for use in the edge break patch and then placing, compacting and trimming the material to the required lines and levels as per
the Contract Documentation or as instructed by the Engineer.
The tendered rates shall also include full compensation for loading the material into haul trucks, handling, labour, material, and all incidentals
necessary for completing all the work in accordance with the specifications.
Measurement and payment for the prime and asphalt surfacing for the edge repair shall be made as specified in Chapter 9.
The haul of the excavated material and of the material for the ETB shall be measured from the point of loading or collection to the point of off-
loading as per Section A1.7 of Chapter 1.
C5.5.25 Compacting the floor of the excavation for patching square metre (m2)
The unit of measurement shall be a square metre of excavation floor compacted and the quantity shall be computed in accordance with the
authorised dimensions of the excavation floor.
The tendered rate shall include full compensation for compaction of the floor of the excavation as specified in the Contract Documentation. Payment
shall not distinguish between the various methods of compaction or various density requirements.
Item Description Unit
(a) Chemically stabilised pavement layer material (specify the pavement layer, the material source
being from commercial or from stockpile, the % stabilising agent and the % of MDD) for a patch
with a surface area:
(m) Not exceeding 20 m2, including for edge repairs wider than 250 mm
(i) cubic metre (m3)
(ii)
(n) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(o) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm
(iii) cubic metre (m3)
(b) Emulsion treated base, or ETB pavement material (specify the pavement layer, the material
source being from commercial or from stockpile, the components as per Clause A4.1.5.14,
and the % of MDD) for a patch with a surface area:
(p)
(i) Not exceeding 20 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(ii)
(q) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(iii)
(r) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm. cubic metre (m3)
C5.5.26.2 Backfill with the following pavement layer material using labour enhanced methods of
construction:
(a) Chemically stabilised pavement material (specify the pavement layer, the material source
being from commercial or from stockpile, the % stabilising agent and the % of MDD) for a patch
with a surface area:
(s)
(i) Not exceeding 20 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(ii)
(t) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(u) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm.
(iii) cubic metre (m3)
(b) Emulsion treated base, or ETB pavement material (specify the pavement layer, the material
source being from commercial or from stockpile, the components as per Clause A4.1.5.14,
and the % of MDD) for a patch with a surface area:
(v)
(i) Not exceeding 20 m2, including for edge repairs wider than 250 mm cubic metre (m3)
(w) Exceeding 20 m2 but not exceeding 50 m2, including for edge repairs wider than 250 mm
(ii) cubic metre (m3)
(iii)
(x) Exceeding 50 m2 but not exceeding 100 m2, including for edge repairs wider than 250 mm. cubic metre (m3)
The unit of measurement shall be a cubic metre of the specified material placed and compacted in accordance with the specified requirements in
the Contract Documentation. The quantity shall be computed in accordance with the authorised dimensions of the layer.
The tendered rates shall include full compensation for providing all the compliant material for the specific layer, irrespective of the origin thereof,
for all mixing, including mixing all components as specified for ETB material in Clause A4.1.5.14 of Chapter 4, placing, compacting to the specified
density and finishing, and also for all machinery, equipment, labour, supervision and other incidentals for executing the work as specified.
The procurement, spreading and mixing of stabilising agents shall be measured and paid for under Section A4.4 of Chapter 4 and Section A5.4.
Measurement and payment for the prime and asphalt surfacing for the patch shall be made as specified in Chapter 8 and/or Chapter 9.
The haul of the material for the various backfill layers shall be measured from the point of loading or collection to the point of off-loading as per
Section A1.7 of Chapter 1. The tendered rates for backfilling with commercial material shall include all the transport costs of the commercial
material.
Distinction shall be made in respect of the method of construction specified.
CONTENTS
D5.5.1 SCOPE
D5.5.2 GENERAL
D5.5.3 PERFORMANCE GUARANTEE REQUIREMENTS
D5.5.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D5.5.5 VISUALLY ASSESSED PROPERTIES
D5.5.6 INSTRUMENTALLY ASSESSED PROPERTIES
D5.5.7 EVALUATION FOR ACCEPTANCE
D5.5.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D5.5.9 NOTIFICATION OF REMEDIAL WORK
D5.5.10 REMEDIAL WORKS
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 6: CONCRETE LAYERS ....................................................................................................................... 6-1
6.1 PAVER LAID CONCRETE LAYERS ................................................................................................................. 6-1
PART A: SPECIFICATIONS .............................................................................................................................................................................. 6-1
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................... 6-19
PART C: MEASUREMENT AND PAYMENT ................................................................................................................................................... 6-22
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ...................................................................................................................... 6-26
CONTENTS
PART A: SPECIFICATIONS
A6.1.1 SCOPE
A6.1.2 DEFINITIONS
A6.1.3 GENERAL
A6.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A6.1.5 MATERIALS
A6.1.6 CONSTRUCTION EQUIPMENT
A6.1.7 EXECUTION OF THE WORKS
A6.1.8 WORKMANSHIP
- Jointed concrete pavement (JCP- Plain) – with or without dowels, for new construction or overlays
- Continuously reinforced concrete (CRCP) for new construction or overlays
It includes, inter alia, the specifications for materials, manufacture and construction requirements as relevant to the specific pavement as
prescribed.
This Chapter does not apply to the repair and or rehabilitation of concrete pavements, which is covered in Chapter 7: Maintenance and Repair of
Concrete Layers. The construction of concrete pavements utilising labour based methods or relatively small or isolated sections of concrete
pavement are covered in Part B of this Chapter.
A6.1.2 DEFINITIONS
Jointed Concrete Pavement (Plain JCP) - concrete pavements that contain sufficient joints to control all expected natural cracks. All necessary
cracking occurs at joints and not elsewhere in the slab. However, there may be load transfer devices (e.g. dowel bars) at transverse joints and
deformed steel bars (e.g. tie bars) at longitudinal joints, which are not considered as reinforcement.
Continuously Reinforced Concrete Pavement (CRCP) - concrete pavements that include continuous longitudinal reinforcement steel typically
between 0,50 and 0,70 % of the cross-sectional area of the pavement slab. They also typically include transverse reinforcing consisting of
individual bars placed at approximately 1,0 m intervals or as specified in the Contract Documentation.
Aggregate - granular material of natural, manufactured or recycled origin used in the manufacture of concrete products to the specific grade/class
as defined in these specifications and the latest published version of SANS 1083, or as may be otherwise specifically specified in the Contract
Documentation:
- Course aggregate – all aggregate > 5,0 mm as further defined in the latest SANS 1083 specification for the specific class of aggregate and
nominal maximum aggregate size as required.
- Nominal maximum particle size (NMPS) – designated as one sieve size larger than the largest sieve to retain a minimum of 15 % of the
aggregate particles.
- Fine aggregate – all aggregate fractions ≤ 5,0 mm and which shall consist of clean material derived from crushing competent parent rock,
or naturally occurring sand conforming to SANS 1083 and any further specified requirements listed herein.
Cement - as defined in SANS 50197-1 for the various classes as listed.
Cement extenders or supplementary cementitious materials - the following as defined in the relevant SANS documents:
- Ground Granulated Blast Furnace Slag: As defined in SANS 55167-1
A6.1.3 GENERAL
A6.1.3.1 Quality Plan
Prior to commencing with any permanent works, the Contractor shall submit a Quality Plan, for review and acceptance by the Engineer, detailing
all checks and hold points relating to construction of the specified product. All work shall be completed in accordance with accepted Plan, with
any deviations resubmitted to the Engineer for evaluation and acceptance prior to implementation thereof.
Where fc1, fc2 and fc3 shall be the 28-day compressive strengths determined from laboratory mixes as prescribed in Clause A6.1.4.3.
(i) If during the progress of the work the requirements set out in Clause A6.1.4.2 are not being met by concrete manufactured from the materials or
material mix proportions as approved, the Contractor shall immediately cease producing such concrete and shall effect such changes to the mix
proportions and/or materials as may be necessary in order to meet those requirements.
d) Changes in requirements
The Engineer shall have the power, at any time during the progress of the work, to order changes in the requirements set out in Clause A6.1.4.2.
In such cases the Contractor shall be compensated in accordance with the terms of the contract for the additional cost of materials or additional
handling, placing and/or other costs, if any, resulting from such changes. If such changes result in savings, the Engineer shall recover such savings
from the Contractor.
e) Mix designs
The mix design requirements as specified in Clause A1.2.5.2 will also apply. Testing for mix designs shall be performed by laboratories
accredited by SANAS for the relevant tests.
A6.1.5 MATERIALS
A6.1.5.1 Cementitious materials
The cementitious materials used for concrete shall comply with the following standards:
- Cement shall comply with SANS 50197-1 (EN 197-1) with a strength class of 32,5 or greater, and a rate of strength gain N or greater.
Cement shall hold valid certification in the form of a Letter of Authority issued as certified approval pursuant to the Compulsory Specification
for cement published by Government Notice R.544. Masonry cement shall not be used. The cement type and class incorporated in the mix
shall be appropriate to the type of pavement to be constructed and the placing, finishing and saw cutting constraints envisaged.
- Ground Granulated Blast Furnace Slag - SANS 55167-1
- Fly ash - SANS 50450-1
Blends of cement complying with SANS 50197-1 and supplementary cementitious materials complying with the above standards may be used
subject to a maximum of 20 % of the total cementitious content.
In order to promote resource sustainability principles, cement shall have a maximum average carbon dioxide emission value of 925 kg CO2e per
ton, determined in accordance with the World Business Council for Sustainable Development Greenhouse Gas Protocol.
All cementitious materials shall be protected from moisture until used, and there shall be sufficient facilities to ensure that the cementitious
materials to be used in the work are kept separate from each other and from other cementitious materials.
Where cementitious materials are stored in a silo, the silo must be emptied before using the silo for a different cementitious material. Blended
cements with a percentage of SCM differing by more than 2 % shall be considered different cementitious materials.
The cementitious binder shall comprise either cement, complying with SANS 50197-1, or an approved site blend of such cement and
supplementary cementitious materials that take appropriate cognisance of environmental conditions, durability and strength requirements. The
site blending of cement with supplementary cementitious materials shall only be conducted on the basis of an acceptable quality assurance
system approved by the Engineer.
A6.1.5.2 Water
Water for washing aggregates, mixing concrete, and curing shall comply with relevant requirements specified in SANS 51008.
The average 28 day drying shrinkage of 3 concrete samples made from each of the required three concrete mixtures for preparing the compressive-
strength and flexural-strength samples in accordance with Clause A6.1.4.3 shall not exceed 0,040 %. Drying-shrinkage tests shall be conducted in
accordance with SANS 3001-CO2-7. Where the drying shrinkage exceeds the specified maximum value, either alternative aggregates shall be used,
further investigations undertaken, or evidence shall be produced with a view to confirming the suitability of the aggregates proposed for use. The
historical behaviour of the aggregate in concrete may serve as a recommendation in such cases if accepted by the Engineer.
b) Alkali-aggregate reaction
Where there is any risk of a particular combination of aggregate and cement giving rise to a harmful alkali-aggregate reaction, the proposed
combination shall be tested in accordance with SANS 6245 (SANS3001- AG 46). Where the result indicates such potential reaction, the aggregate,
shall be replaced so that an acceptable combination may be obtained.
(i) Hardness
When tested in accordance with SANS 3001 No AG10, the 10 % FACT value shall comply with the following requirements:
The acid insolubility of the fine aggregate, or fine aggregate blend, as determined in accordance with SANS 642, shall exceed 40 %.
The fineness modulus (FM), as determined in accordance with SANS 3001 AG-1 and PR-5, FM of the fine aggregate (or mixtures thereof) shall not
deviate from the approved fine aggregate component (or mixtures thereof) by more than 0,20.
e) Additional requirements for aggregates
Where instructed by the Engineer, aggregates shall be checked and shall be free of the following deleterious substances:
(i) Tests for the presence of sugar shall be determined in accordance with SANS 3001-AG-30 (SANS 5833) and shall be free from the presence
of sugar;
(ii) Tests for soluble deleterious impurities shall be conducted in accordance with SANS 3001-AG-31 (SANS 5834) and shall have minimum
compressive strength of 85 % of the reference;
(iii) Test for the presence of material of low density shall be determined in accordance with SANS 3001-AG-?? (SANS 5837) and shall have
maximum 0,5 % by mass;
(iv) Tests for soluble salts shall be determined in accordance with SANS 3001-AG-40 (SANS 5849) and shall have maximum 0,5 % by mass;
(v) Tests for water soluble sulfates shall be determined in accordance with SANS 3001-AG-31 (SANS 5850-1) and shall have maximum 0,2 %
SO3 by mass; and
(vi) Tests for the presence of shell material shall be determined in accordance with SANS 3001-AG-35 (SANS 5840) and shall be maximum 5 %
by mass.
(i) Sealant
The silicone sealant shall be a one-component material with low-modulus properties. The use of acid cure sealants shall not be
permitted. Silicone joint sealant must be compatible with the surface it is applied to and have properties shown in the Table A6.1.5-
1:
The Contractor shall submit a certificate, less than six months old, from an approved testing laboratory, certifying that the sealant conforms
to all the specified requirements.
The silicone sealant shall be applied by means of pumping the sealant from a storage container by means of compressed air powered
pumping equipment and applied to the joint slot by means of nozzles designed to ensure that the slot is filled with sealant as indicated on
the drawings. Application of the sealant into the joint slot by hand shall not be permitted.
(ii) Silicone sealant applied in terms of a Product Performance Guarantee System
Sealant installed in accordance with the above shall be in accordance and be assessed in terms of Part D of these specifications
(iii) Additional materials for silicone sealant
Backer rods shall comply with ASTM D 5249, Type 1. The backer rod diameter shall be at least 25 % greater than the saw cut joint
width. Backer rod material shall be expanded, cross-linked, closed-cell polyethylene foam.
The sealant shall be supported by a bond breaker backing strip, and, unless otherwise recommended by the manufacturer and
approved by the Engineer, the faces of the joint groove shall first be treated with an appropriate primer.
Supporting and priming materials shall be compatible with adjacent materials or surfaces in contact with the materials and shall be
in accordance with the recommendations by the manufacturer and subject to approval by the Engineer. Any primer used shall
form a barrier layer between the silicone and the concrete.
(iv) Materials for cleaning, repairing and resealing of existing joints and cracks
Materials used for cleaning existing joints and for repairing and sealing or resealing joints and cracks shall comply with the
provisions of the Contract Documentation. Cleaning agents shall be such that they will not stain the concrete or cause the existing
bituminous or other material to soak into the concrete.
If necessary, the slip-form paver shall be equipped with traveling side forms of sufficient dimension, strength and of proper shape in order to
support the concrete laterally for a sufficient length of time during placing and finishing.
b) Electronic control systems
Where a slip-form paver is used, the alignment levels for placing the concrete, shall be controlled automatically from guide wires by sensors
attached at the four corners of the slip-form paving machine. The alignment and level of ancillary machines for finishing, texturing and curing shall
be automatically controlled relative to the guide wires and to the surface and edges of the slab. Guide wires shall be so designed, manufactured
and fixed that the paver will be capable of producing a completed slab which will comply with the requirements of Clause A6.1.8.
Other control methods, such as a string-less paving system incorporating appropriate 3D/GPS technology may be permitted after assessment
and approval by the Engineer.
Cement and supplementary cementitious material may only be used if stored and maintained at a temperature less than 45°C. In hot weather
concreting conditions, the cement and supplementary cementitious material storage facilities shall be painted with white high solar reflectance
paint and insulated to reduce any temperature rise in the stored cement or supplementary cementitious material.
Cement or supplementary cementitious material supplied in bags shall be closely and neatly stacked, separately to a height not exceeding 12 bags
and arranged so that they will not be in contact with the ground, the floor or the walls, and can be used in the order in which they were delivered
to the site.
Cement or supplementary cementitious material supplied in bulk shall be stored separately in waterproof containers so designed as to prevent
any dead spots from forming, and the cement or supplementary cementitious material drawn for use shall be measured by mass.
Cement shall not be kept in storage for longer than 8 weeks without the Engineer's permission, and different brands or types of the same brand
of cement or supplementary cementitious material shall be stored separately.
c) Aggregates
Aggregates of different nominal sizes, sources or types shall be stored separately. Intermixing of different materials and contamination by foreign
matter shall be avoided. Aggregates exposed to a chloride (XS) environment (refer Table A13.4.7-2 of Chapter 13) shall be covered to protect
them from salt contamination. Sufficient quantity of fine aggregate shall be stockpiled on site and handled in a manner that ensures the thorough
mixing of the various deliveries in order to achieve a stable fineness modulus within the specified limits.
In hot weather concreting conditions, both the coarse- and fine-aggregate stockpiles shall be shaded from the sun. When the ambient temperature
reaches and at all times when it exceeds 30°C, only the coarse aggregate shall be sprayed with water to assist cooling by evaporation. Water
shall be delivered by means of an approved water droplet sprayer system. The Contractor shall ensure adequate drainage of the aggregate
stockpile area.
Where concrete is batched on site, the aggregates shall be stored in bins with a minimum 150 mm thick concrete floor constructed below the
aggregate stockpile to prevent contamination during the storage and handling the aggregate. The floor slab shall be appropriately sloped to
facilitate drainage of the stockpile area. A 3,0 m wide concrete apron slab shall be constructed around the entrance and outer edge of the
aggregate stockpile area and sloped for drainage away from the main stockpile area. The aggregates shall be tipped on the concrete apron slab
to prevent contamination during the process of tipping and hoisting the aggregate.
d) Water
In hot weather concreting conditions, the sides and tops of water tanks for mixing water, including pipework leading to and from tanks, shall be
insulated.
e) Storage capacity
The storage capacity provided and the quantity of material stored, whether cement, supplementary cementitious materials, aggregates,
admixture or water, shall be sufficient to ensure that no interruptions to the progress of the work will be occasioned by any lack of materials.
f) Deteriorated material
Deteriorated or contaminated or otherwise damaged non-conforming material shall not be used in concrete. Such material shall be removed
from the site without delay.
(ii) Water
The mixing water for each batch shall be measured, either by mass or by volume, accurate to within 2 % of the required quantity.
The quantity of water added to the mix shall be adjusted to make allowance for any moisture in the aggregates.
(iii) Aggregates
All aggregates for concrete shall be measured separately by mass, except as otherwise provided in this Clause, accurate to
within 3 % of the required quantity.
(iv) Admixture
Admixtures shall generally be supplied in liquid form and accurately dispensed by a mechanical dosing unit, into solution with the
mixing water, except where the admixture cannot be dispersed homogenously into the mixing water. Unless extraordinary
circumstances dictate otherwise, under no circumstances shall admixtures be dispensed on to dry mix components. Where such
extraordinary circumstances do exist, in such cases, other methods of feeding into the concrete mixture shall be agreed with the
Engineer.
All admixtures shall be dispensed in quantities accurate to within 2 % by mass of the desired quantity. The mechanical dosing
unit shall be checked daily for accuracy using a nominal dispensing volume, typically 2 litres, or as recommended by the dosing
unit manufacturer or admixture supplier. At least once a week, the dosing unit shall be checked for accuracy using the full
dispensing volume suited to the concrete mixing procedures employed on site, typically for 6 cubic metre concrete batch mixed
by a standard mixing truck and proportionally for other standard batch volumes.
The volume of the mixed material by batch shall not exceed the volume recommended by the manufacturer of the mixer.
The mixing period for the materials shall be at least 90 seconds and may be reduced only if the Engineer is satisfied that the
reduced mixing time will produce concrete with the same strength and uniformity as concrete mixed for minimum 90 seconds.
The reduced mixing time, however, shall be not less than 50 seconds or the manufacturer's recommended mixing time,
whichever is the longer. A suitable timing device shall be attached to the mixer to ensure that the minimum mixing time for the
materials has been complied with.
The first batch to be run when starting with a clean mixer, shall contain only 75 % of the required quantity of coarse aggregate
to make provision for coating the mixer drum. Refer Clause A13.4.7.12g) of Chapter 13 for a similar provision for richer concrete
mix placed at horizontal construction joints.
Discharge shall be so carried out that no segregation of the materials will occur in the mix. The mixer shall be emptied completely
before it is recharged with fresh materials.
Before any concrete is mixed, the inner surfaces of the mixer shall be cleaned and all hardened concrete shall be removed.
Worn or bent blades and paddles shall be replaced.
A6.1.8 WORKMANSHIP
a) Process control
The Contractor shall conduct all and a sufficient number of tests necessary for ensuring compliance with the requirements, as specified in this
Chapter, during all phases of the work. Accelerated 20-hour compressive-strength tests as described in Clause A20.1.5.16 of Chapter 20 shall be
conducted regularly with a view to predicting the 28-day compressive strength of the concrete in consultation with the Engineer. Where the
accelerated tests indicate that the required 28-day compressive strengths will not be attained, the Contractor shall immediately effect the necessary
changes to the materials and/or mix proportions in order to ensure that further work will comply with the requirements.
b) Acceptance control
Routine inspection and testing will be carried out by the Engineer to determine whether the quality of materials and workmanship complies with
the requirements of this section. The lot sizes and sampling for compressive strength shall be done in accordance with Clause A20.1.7 of Chapter
20, using Judgement Plan B as stated in Clause A20.1.7.5b)(ii) of Chapter 20 for acceptance control. The assessment of test results and
measurements shall be done in accordance with the provisions of Chapter 20 as relevant. In addition to the above, the following shall also apply:
(i) The Engineer may, at his discretion, decide to use the Contractor's test results in the judgement plan if he is satisfied that the Contractor has
complied with all the process control requirements.
(ii) The relationship between the 28-day compressive and the 28-day flexural strengths of the concrete established by the preliminary tests shall be
monitored during paving operations by regular tests at the discretion of the Engineer.
(iii) For this purpose sets of three beams and three cubes shall be manufactured from the same batch of concrete and tested for flexural and
compressive strength respectively. If the test results indicate a relationship which deviates from that established by the preliminary tests, the
specified compressive strength, as specified in Clause A6.1.4.2 shall be adjusted accordingly.
(iv) Where air entrainment has been included in the specification, and any test for air content shows a value falling outside the specified limits, the
quantity of air-entraining agent added to the concrete mix shall be adjusted, until the air content of the concrete is within the specified limits.
The levels shall be taken in a random pattern or as directed by the Engineer, before and after the concrete layer has been
constructed, at exactly the same positions. The number of measurements representing the lot shall be a minimum of 30 or more.
The layer shall comply with the requirements specified if at least 90 % of the thickness measured for the lot:
- are equal to or thicker than the specified thickness minus the D90 tolerance of 14 mm
- the mean layer thickness for the lot is not less than the specified thickness minus the Dave tolerance of 1,0 mm and
- individual spots where the thickness is less than the specified thickness minus the Dmax tolerance of 18 mm be repaired as
agreed to by the Engineer to bring them within the D90 tolerance.
(iii) Grade
Deviations from the specified longitudinal grade on account of deviations from the specified levels shall not exceed those relevant
requirements given in Chapter 5.
(iv) Width of pavement
The average width shall be at least equal to the specified width and the edge of the pavement shall not deviate by more than 25
mm from the specified positions.
(v) Joints
Joints shall not deviate by more than 10 mm from their specified positions in the pavement or by more than 10 mm from the edge
of a 3,0 m straight-edge placed so as to touch the line of the joint. Neither shall the line of a joint be discontinuous. The tolerance
for the groove width of sawn joints shall be as follows:
- Longitudinal hinge joints ± 0,5 mm
- Transverse contraction joints ± 0,5 mm
(vi) Cross section
When tested with a 3,0 m straight-edge placed at right angles to the road centre line, the surface shall not deviate from the bottom
of the straight-edge by more than 6,0 mm.
(vii) Surface regularity
Surface regularity or roughness can be measured using one or a combination of instruments, as specified in the Contract
Documentation viz:
- Inertial High speed profilometers (IRI)
- Direct Contact Devices (IRI)
The above shall be subject to the rejection of a pavement with an average thickness of less than 93,1 % of the specified thickness or a
strength of less than 91,5 % of the specified strength, as determined above. Where both thickness and strength are deficient, it will be
rejected if P is less than 70 %. Where P exceeds 100 %, normal compensation only will be payable.
(iii) Any other deficiencies.
Any other deficiencies not accepted by the Engineer shall be repaired in accordance with Chapter 7: Maintenance and Repair of
Concrete Layers, as approved by the Engineer.
CONTENTS
B6.1.1 SCOPE
B6.1.2 DEFINITIONS
B6.1.3 GENERAL
B6.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B6.1.5 MATERIALS
B6.1.6 CONSTRUCTION EQUIPMENT
B6.1.7 EXECUTION OF THE WORKS
B6.1.8 WORKMANSHIP
B6.1.1 SCOPE
This Section covers all the material requirements and work pertaining to the construction of concrete layers utilising predominantly labour
enhanced methods for the following pavement types:
B6.1.2 DEFINITIONS
The definitions as listed in Clause A6.1.2 shall be applicable.
B6.1.3 GENERAL
B6.1.3.1 Quality plan
Prior to commencing with any permanent works, the Contractor shall submit a Quality Plan, for approval by the Engineer, detailing all methods
checks and hold points relating to construction of the specified product.
B6.1.5 MATERIALS
B6.1.5.1 Cementitious materials
All the requirements specified in Clause A6.1.5 shall apply. The cementitious materials incorporated in the mix shall, however, be such that,
dependant on the production rates achieved, the concrete shall have sufficient time to be transported, placed consolidated and finished prior to
initial setting occurring.
B6.1.5.2 Water
Water for washing aggregates, mixing concrete, and curing shall comply with the requirements in Clause A6.1.5.2.
B6.1.6.3 Paving
a) Side forms
Before any side-forms may be ordered or brought onto the site, particulars regarding the side-forms shall have been approved by the Engineer.
Side-forms and rails shall be so designed, manufactured, set and supported that the completed concrete pavement will comply with all the
requirements of Clause A6.1.8. When assessed with a 3,0 m straight-edge, the top edge of the form shall not deviate by more than 3,0 mm at
any place, and the sides by more not than 6,0 mm. The sides shall not deviate by more than 3,0 mm from the vertical. The height of the side-
forms shall not be less than the nominal thickness of the concrete slab less 15 mm.
b) Paving equipment
The paving equipment is not prescribed but the Contractor shall utilise appropriate hand operated equipment and construction methods in order
to achieve the desired final product as specified. The Contractor shall provide a comprehensive method statement and quality plan to the Engineer
for approval prior to commencing with any such work.
B6.1.8 WORKMANSHIP
Unless otherwise specifically stated in the Contract Documentation, all the requirements specified in Clause A6.1.8 shall be applicable.
C6.1.1.1 Mechanical construction (state pavement type and nominal thickness) square metre (m²)
C6.1.1.2 Labour enhanced construction (state pavement type and nominal thickness) square metre (m²)
The unit of measurement for the trial pavement shall be the square metre of completed trial section. Not more than a total length of 200 m of paver
laid trial pavement and not more than 60m of manually constructed trial pavement shall be measured for payment as described in Clause A6.1.3.2.
Item Description Unit
C6.1.2 Construction of jointed concrete pavement (JCP) (Excluding texturing and curing)
(a) Paver laid construction (state nominal thickness) square metre (m²)
(b) Labour enhanced construction (state nominal thickness) square metre (m²)
(a) Paver laid construction (state nominal thickness) square metre (m²)
(b) Labour enhanced construction (state nominal thickness) square metre (m²)
C6.1.2.3 Additional concrete placed to thicken up the slab at joints as specified in the Contract cubic metre (m³)
Documentation
(a) Paver laid construction (state nominal thickness) square metre (m²)
(b) Labour enhanced construction (state nominal thickness) square metre (m²)
The unit of measurement for payment items C.6.1.2 to C6.1.3 shall be the square metre of concrete pavement placed and finished in accordance with
the Contract Documentation. The quantity shall be calculated from the authorised dimensions of the completed surface, except when the Engineer
requires or the drawings show local deviations from the specified thickness, such as at bridge approach slabs. The volume of concrete in such cases
shall be converted into an equivalent area in square metres based on the specified thickness of the slab.
The tendered rate shall include full compensation for procuring and furnishing all the materials, storing the materials, providing all plant, determining
the mix proportions, mixing, transporting, placing and finishing the concrete, including formwork, repairs done to defective work, protecting the
pavement against damage, construction joints and process control.
The tendered rate shall also include full compensation for the provision of any additional width required by the Contractor to the earthworks and/or
pavement layers to suit the particular requirements of the paving equipment. It shall also include full compensation for the removal of the additional
widening which extends beyond the limits of the specified cross-section.
The quantity of additional concrete over and above the specified layer thickness and required at thickened joints shall be the cubic metre of concrete
determined from the dimensions as detailed in the Contract Documentation.
The tendered rates shall also include full compensation for constructing concrete pavements which cannot be constructed with conventional plant, as
envisaged in this Chapter.
Item Description Unit
C6.1.4.3 Curing:
The unit of measurement for texturing and curing shall be the square metre of completed pavement which has received the specified surface texturing,
and which was cured as specified. The quantity shall be calculated from the specified horizontal dimensions of the completed concrete surface in the
case of texturing and from the specified horizontal dimensions of the completed concrete surface, plus the surface area of the slab sides, in the case
of curing.
The tendered rate for texturing shall include full compensation for providing the plant and equipment required and for applying the specified surface
texture.
The tendered rate for curing shall include full compensation for providing the curing compound and its application as specified at the specified nominal
rates of application by means of an approved pressure distributor. The tendered rate shall also include compensation for spraying the curing compound
in unsealed joints after the sawing has been completed.
Item Description Unit
C6.1.5 Variation in the rate of application of the curing compound litre (ℓ)
The unit of measurement in respect of increases or decreases in the rate of application of the curing compound from the nominal application as
specified, shall be the litre. Payment for variations shall be made as specified in Chapter 1.
C6.1.6 Joints
(a) Sealed hinge joints (indicate type and reference to drawings) metre (m)
(b) Unsealed hinge joints (indicate type and reference to drawings) metre (m)
C6.1.6.3 Sealed transverse contraction joints sawn in two separate operations (widths as shown on metre (m)
the drawings)
C6.1.6.4 Dowel bars: mild steel inserted in new concrete (indicate diameter, length and position on
drawings):
(a) Inserted by mechanical dowel bar inserter number (No)
C6.1.6.6 Forming and sealing joints between asphalt and concrete pavements metre (m)
The unit of measurement for joints in the pavement shall be the metre of completed joint, except that dowel bars and tie-bars across joints shall be
measured separately by the numbers of each type installed.
Construction joints as such shall not be measured for payment and their cost shall be deemed to be included in the rate tendered for the concrete
pavement. However, if the position of a longitudinal construction joint coincides with that of a hinge joint, the Contractor will be paid at the rate tendered
for the type of hinge joint replaced by the construction joint, provided that the requisite number and sizes of tie bars for the hinge joints are installed.
Where the hinge joint replaced by the construction joint is a sealed hinged joint, the construction joint shall be sawn and sealed, in which case the
Contractor will be paid at the tendered rate for sawn and sealed hinge joints.
The tendered rates for expansion joints shall include full compensation for forming the joint, complete with joint filler, rounding or chamfering the
corners (if required) and installing the seal.
The tendered rates for longitudinal hinge joints shall include full compensation for sawing the joint (if required) and supplying and inserting the seal (if
required).
The tendered rate for transverse contraction joints shall include full compensation for sawing the joint and installing the specified type of seal, including
appurtenant materials, and for temporarily sealing the joint with paper rope.
The tendered rates for dowel bars and tie-bars shall include full compensation for supplying, cutting, placing, holding the bars in position, including a
supporting framework or cradles where required, and fixing the end caps and bond breaking materials to dowels.
The tendered rate for forming and sealing the joints between asphalt and concrete pavements shall include full compensation for supplying all the
necessary plant and materials, for forming a joint to the required dimensions in the asphalt seal, cleaning the joint and sealing as specified in Clause
A6.1.7.5b)
Item Description Unit
The unit of measurement for steel bars shall be the ton of reinforcing steel in place in accordance with the drawings or as authorised.
The unit of measurement for welded steel fabric shall be the kilogram of welded steel fabric in the panels of concrete paving which require non-
contiguous reinforcement as specified. The quantity shall be calculated from the area of the mesh used in accordance with the drawings or as
authorised.
The tendered rates shall include full compensation for supplying, delivering, cutting, bending, welding, placing and fixing the steel reinforcement,
including all tying wires, spacers and waste.
C6.1.8.1 100 mm cores drilled from pavement for testing of compressive strength number (No)
C6.1.8.2 150 mm cores drilled from pavement for testing of compressive strength number (No)
The unit of measurement shall be the number of cores drilled or drilled and tested on the instruction of the Engineer. Cores drilled by the Contractor
at his own initiative as part of his process control, or for testing cracks sealed at the Contractor's own cost, shall not be measured for payment.
The tendered rates shall include full compensation for drilling the cores and, where applicable, having them tested by an approved laboratory, and for
all labour, transport, testing charges and other incidentals, save only the cost of providing a core-drilling machine on the site, which shall be paid for
separately. It shall also include compensation for restoring the concrete pavement where holes were drilled.
CONTENTS
D6.1.1 SCOPE
D6.1.2 GENERAL
D6.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D6.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D6.1.5 VISUALLY ASSESSED PROPERTIES
D6.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D6.1.7 EVALUATION FOR ACCEPTANCE
D6.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D6.1.9 NOTIFICATION OF REMEDIAL WORK
D6.1.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A 6.2.1 SCOPE
A 6.2.2 DEFINITIONS
A 6.2.3 GENERAL
A 6.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A 6.2.5 MATERIALS
A 6.2.6 CONSTRUCTION EQUIPMENT
A 6.2.7 EXECUTION OF THE WORKS
A 6.2.8 WORKMANSHIP
A6.2.2 DEFINITIONS
Segmental block paving – a system of individual shaped blocks arranged to form a continuous hard-wearing and durable surface overlay.
A6.2.3 GENERAL
Not applicable to this Section.
A6.2.5 MATERIALS
A6.2.5.1 Paving blocks
Concrete paving blocks shall comply with the requirements of SABS 1058. The block shall be of the class, type and thickness specified in the Contract
Documentation. The surface texture and colour of all blocks shall be uniform.
A6.2.8 WORKMANSHIP
A6.2.8.1 Construction tolerances
The completed concrete block paving shall comply with the following construction tolerances:
a) Line of pattern
(i) Maximum deviation from a 3,0 m straight edge: 3,0 mm
(ii) Maximum deviation from a 20 m straight line: 10 mm
b) Vertical deviation from a 3,0 m straight edge
(i) At the edge beams: 3,0 mm
(ii) Elsewhere: 3,0 mm
c) Differences in the surface levels of adjacent units: 2,0 mm
CONTENTS
B6.2.1 SCOPE
B6.2.2 DEFINITIONS
B6.2.3 GENERAL
B6.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B6.2.5 MATERIALS
B6.2.6 CONSTRUCTION EQUIPMENT
B6.2.7 EXECUTION OF THE WORKS
B6.2.8 WORKMANSHIP
B6.2.1 SCOPE
The provisions of Part A shall apply.
B6.2.2 DEFINITIONS
The definitions as in Clause A6.2.2 shall apply.
B6.2.3 GENERAL
The provisions of Part A shall apply.
B6.2.5 MATERIALS
The provisions of Part A shall apply.
B6.2.8 WORKMANSHIP
The provisions of Part A shall apply.
C6.2.1.1 Concrete block paving (indicate class, type and thickness of blocks) square metre (m²)
The unit of measurement shall be the square metre of completed concrete block paving. The quantity shall be calculated from the dimensions
shown on the drawings or authorised by the Engineer. The tendered rate shall include full compensation for furnishing all materials,
constructing the sand bedding, laying and compacting the concrete pavement blocks, filling the joints with jointing sand and for all other work
necessary to complete the concrete block paving as specified.
The tendered rate shall include full compensation for furnishing all materials, constructing the sand bedding, laying and compacting the
concrete pavement blocks, filling the joints with jointing sand, and for all other work.
C6.2.2 Cast in-situ concrete edge and intermediate beams cubic metre (m³)
The unit of measurement shall be the cubic metre of concrete placed in edge and intermediate beams. The quantity shall be calculated from
the dimensions shown on the drawings or as authorised by the Engineer.
All prefabricated concrete kerbing and channelling shall be measured and paid for under Part C, Section C3.3 of Chapter 3 as relevant.
The tendered rate shall include full compensation for furnishing all materials, and constructing the edge and intermediate beams complete
as specified, including all excavation and backfilling in all classes of material.
C6.2.3.2 Contractor’s charges and profit added to the prime cost sum percent (%)
Payment under the prime cost sum for providing ant poison and herbicide and the Contractor's costs and profit in this respect shall be made
in accordance with the provisions of the general conditions of contract, but, in addition, the Contractor's tendered rate for costs and profit
shall include full compensation for applying the chemicals as specified.
C6.2.4.1 Concrete block paving (indicate class, type and thickness of blocks) square metre (m²)
The unit of measurement shall be the square metre of completed concrete block paving where re-sanding (filling) of the jointing sand is
required after initial completion of the work. The quantity shall be calculated from the dimensions shown on the drawings or authorised by
the Engineer. The tendered rate shall include full compensation for furnishing all materials to refill the joints with jointing sand where required.
CONTENTS
D6.2.1 SCOPE
D6.2.2 GENERAL
D6.2.3 PERFORMANCE GUARANTEE REQUIREMENTS
D6.2.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D6.2.5 VISUALLY ASSESSED PROPERTIES
D6.2.6 INSTRUMENTALLY ASSESSED PROPERTIES
D6.2.7 EVALUATION FOR ACCEPTANCE
D6.2.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D6.2.9 NOTIFICATION OF REMEDIAL WORK
D6.2.10 REMEDIAL WORKS
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
7.2 REPAIR TO EXISTING JOINTS AND UNCONTROLLED CRACKS IN CONCRETE PAVEMENTS .. 7-12
PART A: SPECIFICATIONS ............................................................................................................................................................... 7-12
PART B: LABOUR ENHANCEMENT .................................................................................................................................................. 7-19
PART C: MEASUREMENT AND PAYMENT ...................................................................................................................................... 7-20
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ......................................................................................................... 7-23
CONTENTS
PART A: SPECIFICATIONS
A7.1.1 SCOPE
A7.1.2 DEFINITIONS
A7.1.3 GENERAL
A7.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A7.1.5 MATERIALS
A7.1.6 CONSTRUCTION EQUIPMENT
A7.1.7 EXECUTION OF THE WORKS
A7.1.8 WORKMANSHIP
A7.1.2 DEFINITIONS
The definitions relating to concrete layers as stated in Chapter 6 shall also be applicable to this Chapter 7.
Joint sealants - cold poured self-levelling silicone liquid sealant for sealing joints in concrete.
Types of joints and associated pavement distress - as defined in the latest version of TMH9: Standard Visual Assessment Manual, Part C:
Concrete Pavements.
A7.1.3 GENERAL
The existing joint sealant shall be removed and the joint shall then be reamed, cleaned and the new sealant installed in accordance with the Contract
Documentation.
The Contractor shall submit a complete method statement for approval by the Engineer before the resealing of any joints commences. The Engineer
will have 5 days to study and comment on the method statement before approval shall be given.
A7.1.5 MATERIALS
A7.1.5.1 Sealant
The joint sealant shall be a cold poured self- levelling liquid silicone sealant conforming to the requirements as prescribed in Clause A6.1.5.7 of
Chapter 6 for the particular type of sealant specified.
A7.1.8 WORKMANSHIP
A7.1.8.1 Groove width
After reaming, the width and depth of the groove shall be ± 0,5 mm of that width specified in the Contract Documentation.
CONTENTS
B7.1.1 SCOPE
B7.1.2 DEFINITIONS
B7.1.3 GENERAL
B7.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B7.1.5 MATERIALS
B7.1.6 CONSTRUCTION EQUIPMENT
B7.1.7 EXECUTION OF THE WORKS
B7.1.8 WORKMANSHIP
B7.1.1 SCOPE
The provisions of Part A shall apply.
B7.1.2 DEFINITIONS
The provisions of Part A shall apply.
B7.1.3 GENERAL
The provisions of Part A shall apply.
B7.1.5 MATERIALS
The provisions of Part A shall apply.
B7.1.8 WORKMANSHIP
The provisions of Part A shall apply.
C7.1.1.2 Reaming of existing joints (indicate width and depth) metre (m)
C7.1.1.5 Installation of backing material in saw cut joints (to fit saw cut dimensions) metre (m)
The tendered rate for the removal of the existing seal and backing material for C7.1.1.1 and 2 shall include full compensation for providing labour
and equipment required. The tendered rate shall also include for the disposal of the removed seal and backing material.
The unit of measurement for reaming of joints in existing concrete pavements shall be the metre of reaming of the existing joint.
The unit of measurement for bevelling shall be the metre (m) of bevelling undertaken at longitudinal and transverse joints and cracks. Distinction
shall be made between different sizes of bevelling and for bevelling on one or both sides of joints/cracks.
The tendered rate for bevelling and routing shall include full compensation for providing the plant and equipment required and for cutting the
bevels and rout grooves to the required dimensions indicted on the drawings as well as for the cleaning of the routed crack/joint by means of high
pressure water jetting followed by oil free high pressure air jetting prior to the installation of the back-up material or sealant.
The tendered rate for the installation of the back-up material shall include full compensation for providing the labour and equipment required. The
tendered rate shall also include for the cleaning of the joint by means of high pressure water jetting followed by oil free high pressure air jetting
prior to the installation of the back-up material.
C7.1.2 Costs incurred due to repair and monitoring in terms of Product Performance Lump sum
Guarantee System (PPGS)
The unit of measurement provides for the costs incurred by the Employer during monitoring and evaluation (after certificate of completion) for
assessments during the PPGS phases, i.e. work undertaken by the Engineer.
CONTENTS
D7.1.1 SCOPE
D7.1.2 DEFINITIONS
D7.1.3 GENERAL
D7.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
D7.1.5 MATERIALS
D7.1.6 CONSTRUCTION EQUIPMENT
D7.1.7 EXECUTION OF THE WORKS
D7.1.8 WORKMANSHIP
D7.1.1 SCOPE
This Part deals with the installation of joint seals in terms of a Product Performance Guarantee System (PPGS). This Part shall also cover the re-
sealing of all joints in the longitudinal weakened plane, transverse and longitudinal contraction and longitudinal construction joints (where directed
by the Engineer) in the existing concrete pavement.
D7.1.2 DEFINITIONS
The definitions applicable to Clause A7.1.2 shall apply.
D7.1.3 GENERAL
This Section covers the specifications and work related to the functional condition of the liquid silicone, or such alternative product as may be
accepted by the Engineer, used for the sealing of saw cut joints in the longitudinal weakened plane, transverse contraction and longitudinal
construction joints in the concrete pavement in terms of a product performance guarantee.
The pre-treatment or accepted alternative specified herein shall in terms of this part of the specification automatically form part of the Product
Performance Guarantee System (PPGS).
The conditions contained in this section of the project document shall only be applicable to joints repaired under the contract with a cold poured
liquid sealant or such alternative product as may be accepted by the Engineer.
In support of any tender submitted either as proposed in these contract Documents, or as an alternative, the tenderer shall comply with the
followings additional requirements:
- Quality Assurance Plan
- Use of “Professional Partner”
- Design constraints for PPGS
- Technical report
D7.1.5 MATERIALS
D7.1.5.1 Materials for joints
Materials used for sealing of joints shall not be older than six (6) months. The age of sealant shall be certified by an approved testing facility.
The silicone sealant must be applied by means of pumping the sealant from a storage contained through compressed air powered pumping
equipment and applied to the joint slot by means of nozzles designed to ensure that the slot is filled with sealant as indicated on the drawings.
Application of the sealant to the joint slot by hand shall not be permitted.”
D7.1.8 WORKMANSHIP
D7.1.8.1 General
The onus rests entirely on the Contractor to produce work which conforms in quality to the specifications and requirements herein, or such other
specification and requirements as defined in the accepted tender that will perform in terms of the requirements of the Product Performance
Guarantee System (PPGS).
Any design constraints envisaged by the Contractor on the PPGS related product or alternative approved product shall be highlighted on the
relevant Returnable Schedules.
Furthermore, the Contractor shall, together with his programme of work stipulated in Chapter 1 as relevant, or at such time as approved by the
Engineer, submit proposals to the Engineer regarding the manner in which his quality management programme and testing frequencies are to be
undertaken.
The Engineer shall however, conduct such tests as he may deem applicable and shall retain all rights as determined in the General Conditions of
Contract related to bad workmanship or unacceptable materials. This shall also be applicable to accepted alternative material and related
specifications.
Any of the Engineers actions hereunder shall however not be construed to relive the Contractor of his responsibilities in terms of the PPGS
specified herein.
Method of assessment of data The ratio of the damaged seal to the total length of seal inspected for the
various types of distress measured in metres and expressed as a percentage.
Longitudinal and transverse joints to be measured separately
* This length can be measured over any 200 m section of carriageway and need not commence directly adjacent to the
termination of an abutting section, provided that no two sections shall overlap with one another
Time after Maximum permissible distress length calculated (percentage %) of segment of transvers or longitudinal
commencement of joint for the various types of distress
the PPG period
(yrs)
L T L T L T L+T L T
2 0 0 0 0 0 0 0 0 0
4 2 2.5 2 2.5 0 0 0 0 0
6 4 5 4 5 2 2.5 1 2 2.5
8 12 15 12 15 8 10 2 4 5
In the event of the types of distress listed in Table D7.1.8-2 occurring simultaneously, then the maximum permissible distress values (calculated
by the summation of the percentage listed in Table D7.1.8-2 for the specified times after opening the concrete pavement to traffic shall meet with
the criteria listed in Table D7.1.8-3.
D7.1.8.5 Procedures to be adopted in the event of failure during the guarantee period
Where failures have occurred relating to the performance of the sealant under traffic or any other reason due to workmanship or materials used,
the Contractor shall at his own expense, rectify all segments in which such defects occur which exceeds the permissible criteria as indicated in
Table D7.1.8-2 as to bring the number the number of defects within the permissible limits. Actual repairs required shall be agreed by the panel.
Repair works shall be carried out at any time when required during the Guarantee Period, but at least during 2, 4, 6 and 8 as specified. During
years 2, 4, 6 and 8 repair works shall be carried out within a reasonable time after the specified inspections as agreed with the Employer and
these repair works will not be subject to a lane rental. Where repair works are required before the inspection in year 2, a lane rental charge shall
be applicable as stated in the Contract Data. The lane rental fee units shall be per lane per hour. No lane rental charge is applicable after the
inspection in year 2.
In the event of the Contractor failing to undertake the required steps to rectify/reinstate the defects to conform with the specified requirements, the
Employer reserves the right to withhold payment of any monies which are payable to the Contractor or which may become payable under the
contract, or should no such monies be owing, to call in the guarantee issued under the PPGS.
Furthermore, the Employer shall employ all such powers vested in him in terms of the General Conditions of Contract to uphold and enforce the
requirements specified herein related to the extended performance guarantee.
Should an alternative tender or contract guarantee period be accepted, the repair programme shall be as per the accepted alternative.
At the end of the Guarantee Period, and when the applicable maintenance certificate has been issued, all repair and maintenance responsibilities
shall become the responsibility of the Employer, except for latent defects which may arise after the end of the product performance guarantee
period.
The Contractor shall commence with the remedial work within thirty (30) days from the date on which he site is handed to him by an order in
writing from the Employer or his agent after the submission of a programme within fourteen (14) days from the date of the order.
a) The Contractor shall at his own cost supply, erect and maintain the necessary temporary traffic control signs in accordance with the
requirements contained in Section A1.5 of Chapter 1, the drawings, and the latest edition of the South African Road Traffic Signs Manual.
Any future amendments to the aforementioned manual shall also be complied with.
b) The Contractor shall also, at his own cost, repair/reinstate such items as road studs, road marking etc. should these be damaged or influenced
by the required remedial work.
c) The only permissible types if liquid sealant material used for repairing the joints on this contract during the PPG Period shall be as follows:
• The product initially accepted to complete the project
• Any new or alternative product specifically accepted by the Employer
The costs incurred by the Employer for the repair and monitoring required in terms of the PPGS shall be deemed to be covered by the lump sum
allowed for in item C7.1.2.
Full details relating to alternative tenders such as field measurements, acceptance criteria and proposed remedial work shall be submitted in a
manner similar to that prescribed in Clause D7.1.8.4
Alternative materials, properties or remedial measures proposed by the Contractor shall be to the acceptance of the Employer or his designated
representatives.
CONTENTS
PART A: SPECIFICATIONS
A7.2.1 SCOPE
A7.2.2 DEFINITIONS
A7.2.3 GENERAL
A7.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A7.2.5 MATERIALS
A7.2.6 CONSTRUCTION EQUIPMENT
A7.2.7 EXECUTION OF THE WORKS
A7.2.8 WORKMANSHIP
- Repair of joints as well as uncontrolled cracking as part of the periodic maintenance/repair of existing pavements which includes repair to the
adjacent concrete. It may also require the retro-fitting of tie-bars and/or dowel bars in order to provide load transfer capacity over the crack or
joint as identified. This instance the area of repair shall be limited to only a portion of a panel adjacent to a joint, but may also traverse an existing
joint into a portion of an adjacent panel. In JCP pavements where the area covers a total existing panel area, the repairs shall be carried out in
conformance to the requirements specified in Section 7.3 as relevant.
A7.2.2 DEFINITIONS
Concrete Pavement Types - as defined in Clause A6.1.2 of Chapter 6.
Joint types - weakened-plane joints including transverse contraction, longitudinal hinge, expansion and transverse construction joints as indicated on
the Drawings.
Uncontrolled Cracking - as defined in TMH 9: Part C - Standard Visual Assessment Manual for Rigid Pavements.
A7.2.3 GENERAL
A7.2.3.1 General Requirements
Notwithstanding any specific requirements as prescribed in this Chapter, all work done shall be in conformance with all generally accepted good
practice recommendations as published in relevant industry guidelines to ensure adequate performance of the finished work. The Contractor shall
submit a method statement setting out the methodology he intends utilising for all operations envisaged to ensure conformance to all the specified
final requirements which shall be subject to the approval of the Engineer.
A7.2.5 MATERIALS
A7.2.5.1 Aggregates
The aggregates incorporated in the replacement concrete shall comply with all the requirements as prescribed in Clause A6.1.5 of Chapter 6. The
Nominal Maximum Size of the aggregate shall be appropriate to the thickness of concrete to be placed and the placing and finishing methodology
to be used.
A7.2.5.2 Water
The requirements for water incorporated into the concrete mix shall be as specified in Clause A6.1.5 of Chapter 6.
A7.2.5.3 Cement
A high early strength cement shall be used for all full depth repairs. The accelerated strength shall be gained by using CEM class 52,5 R in
conjunction with an accelerator if required, but only if approved.
A7.2.5.6 Tie bars, dowels, continuous reinforcing steel and steel mesh
The dimensions of any steel products shall be as specified in the Contract Documentation. The requirements for any steel shall be a specified in
Clause A6.1.5 of Chapter 6 as relevant.
A7.2.7.2 Repairing joints and cracks by full-depth removal of concrete adjacent to the crack or joint
The execution of the work shall be as specified below for the various types of treatments listed:
a) Transverse crack and joint repairs by full depth removal of existing adjacent concrete and incorporating the following
treatments:
(i) Type T1 Treatment
This treatment applies to active transverse cracks situated approximately in the middle third of a slab or series of transverse slabs.
The existing concrete on either side of the crack is to be broken up and removed after two parallel saw cuts are made at positions
indicated by the Engineer. Before the new concrete is replaced, tie bars are to be installed along one of the existing transverse
concrete faces by means of drilling horizontal holes in the existing concrete and fixing tie bars with an epoxy adhesive paste. The
vertical side of the existing concrete face with tiebars is then treated with a wet-to-dry epoxy adhesive. The other face is treated
with a bondbreaker. The concrete and mesh are placed. New concrete shall be rounded and existing concrete mechanically
bevelled along the line of contact. The line of contact between existing and new concrete which is not tied shall be sawn in one
operation to a specified width and depth and the installation of a back-up material and a liquid sealant.
(ii) Type T2 Treatment
This treatment applies to the repair of transverse cracks in close proximity to transverse joints where the one limit of the concrete
repair area coincides with an existing transverse joint. A saw cut parallel to the joint encompasing the crack is made at a position
indicated by the Engineer. The existing concrete on either side of the crack is to be broken up and removed. Before the new
concrete is replaced, tie bars are to be installed along the newly cut face opposite the joint face by means of drilling horizontal
holes in the existing concrete and fixing tie bars with an epoxy adhesive paste. The vertical side of the concrete face with tiebars
is then treated with a wet-to-dry epoxy adhesive. The other face is treated with a bondbreaker. The concrete and mesh are placed.
New concrete shall be rounded and existing concrete mechanically bevelled along the line of contact. A sawcut is made along the
same line of the existing transverse joint on the contact line of existing and new concrete in one operation to a specified depth and
width and installation of a back-up material and a new liquid sealant.
(iii) Type T3 Treatment
This treatment applies where existing concrete is removed on either side of an existing transverse joint due to an active transverse
crack crossing over the existing joint. The existing concrete on either side of the crack is to be broken up and removed after two
parallel saw cuts are made at positions indicated by the Engineer encompassing the extent of the crack. Before the new concrete
is replaced, tie bars are to be installed along both of the existing transverse concrete faces by means of drilling horizontal holes in
the existing concrete and fixing tie bars with an epoxy adhesive paste. The vertical sides of the existing concrete faces with tiebars
are then treated with a wet-to-dry epoxy adhesive. The concrete and mesh are placed. The sawing of the joint at the location and
line of the original joint is performed in two operations consisting of an early 3,0 mm wide saw cut followed by the reaming of the
joint to a minimum width of 6,0 mm and depth of 35 mm and the installation of a back-up material and a liquid sealant.
(iv) Type T4 Treatment
This treatment is identical to type T3 treatment but applies only where the concrete is on either side of the joint line in separate
operations. The new concrete on either side of the transverse joint is placed in two operations with dowel bars treated with an
approved bond breaking compound as shown on the drawings and installed across the joint during the casting of the first portion
of concrete. Before the second portion of concrete is cast the vertical surface of the newly cast concrete shall be treated with a
bond breaking agent. The transverse joint is then sawn in two operations and followed with the installation of a back-up material
and liquid sealant.
(v) Type T5 Treatment
This type of treatment is similar to Type T2 treatment but applies when small portions of concrete slabs are removed and replaced
due to corner breaks, short cracks or similar defects. The treatment entails the drilling of horizontal holes into the existing concrete,
the application of an epoxy adhesive and the installation of a minimum of 3 tie bars before the placing of new concrete. Due to the
small horizontal dimensions of the repair area the normal spacing of tie bars as specified will have to be adjusted to ensure that a
minimum of three tie bars are installed. Wet-to-dry epoxy adhesive shall be applied to the surfaces where tie bars are installed
and a bond breaking agent along the vertical face of existing concrete at the joint where movement is to take place. A sawcut is
A7.2.8 WORKMANSHIP
A7.2.8.1 General
The completed work shall exhibit no uncontrolled cracking.
A7.2.8.2 Level
When measured with a 3,0 m straight edge, the difference in level between the patch and the adjacent existing pavement shall be within ± 3,0
mm.
A7.2.8.3 Texture
The average depth of texture shall be between 2,0 and 4,0 mm as prescribed.
CONTENTS
B7.2.1 SCOPE
B7.2.2 DEFINITIONS
B7.2.3 GENERAL
B7.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B7.2.5 MATERIALS
B7.2.6 CONSTRUCTION EQUIPMENT
B7.2.7 EXECUTION OF THE WORKS
B7.2.8 WORKMANSHIP
B7.2.1 SCOPE
The provisions of Part A shall apply.
B7.2.2 DEFINITIONS
The provisions of Part A shall apply.
B7.2.3 GENERAL
The provisions of Part A shall apply.
B7.2.5 MATERIALS
The provisions of Part A shall apply.
B7.2.8 WORKMANSHIP
The provisions of Part A shall apply.
C7.2.1 Transverse and longitudinal crack and joint repairs incorporating the following
treatments
C7.2.1.1 Routing of active cracks (indicate width and depth) metre (m)
C7.2.1.2 Routing of non-active cracks (indicate width and depth) metre (m)
C7.2.1.3 Bevelling of one side of the crack (indicate dimension) metre (m)
C7.2.1.4 Bevelling of both sides of the crack (indicate dimension) metre (m)
C7.2.1.5 Saw cutting of cracks and joints in one operation (indicate depth and width) metre (m)
C7.2.1.6 Filling joint reservoir with cementitious non-shrink grout kilogram (kg)
C7.2.1.7 Installation of backing material in saw cut joints (to fit saw cut dimensions) metre (m)
The unit of measurement of routing shall be the metre (m) of transverse, longitudinal or random cracks routed. Distinction shall be made between
different widths and depths of routing.
The unit of measurement for bevelling shall be the metre (m) of bevelling undertaken at longitudinal and transverse joints and cracks. Distinction
shall be made between different sizes of bevelling and for bevelling on one or both sides of joints/cracks.
The unit of measurement of cold poured liquid sealant shall be the litre () of cold-poured liquid sealant applied to the joint reservoir. The tendered
rate for cold-poured liquid sealants shall include full compensation for the supply and delivery of the materials to the point of installation and the
installation of the sealant. The tendered rate shall also include for the supply and application of joint primer to the vertical faces of the joint groove.
The unit of measurement shall be the linear metre of crack grouted irrespective of width, in accordance with the Specifications, and the quantity
shall be the summation of individual lengths grouted measured along the line of the crack. The tendered rate shall include for the supply and
mixing of the grout, pouring it into the crack, repeating the process as often as is necessary to fill the crack, and for subsequent cleaning of the
slot and pavement surface of all grout.
C7.2.3.1 Saw cutting of slots in concrete pavement (indicate dimensions) number (No)
C7.2.3.2 Application of wet-to-dry epoxy to vertical faces and top of existing concrete litre (ℓ)
C7.2.3.3 Installation of 16 mm diameter deformed tie-bar (indicate length) including application of self- number (No)
levelling pourable epoxy grout and 7,1 mm aggregate.
C7.2.3.4 Filling of slot with high strength concrete Class 50/7,1 mm cubic metre (m³)
The tendered rate for cross-stitching by means of cutting slots shall include full compensation for the saw cutting slots in the concrete pavement,
excavating the concrete, cleaning of the slots by sand blasting followed by high pressure air jetting, and the removal of all waste material resulting
from this procedure.
The tendered rate for the installation of the tie bars shall include full compensation for supplying, cutting, placing, holding bars in position, the
application of self- levelling epoxy grout and for the 7,1 mm crushed stone aggregate placed on top of the epoxy grout.
The tendered rate for filling slots with a high strength concrete shall include full compensation for the placing of the high strength concrete, the
removal of any excess material to ensure that the slots are filled flush with the concrete surface and for the curing of the high strength concrete in
accordance with the manufacturer’s instructions as well as texturing the concrete by burlap drag.
C7.2.4.1 Saw cutting and preparation of slots in concrete pavement (indicate dimensions) number (No)
C7.2.4.2 Installation of new dowel bars as specified (indicate length and diameter) including number (No)
application of bond breaker on free end, end caps.
C7.2.4.3 Filling of slot with high strength concrete Class 50/7,1 mm number (No)
C7.2.6.2 Curing
C7.2.7 Variation in the rate of application of the curing compound litre (ℓ)
The unit of measurement in respect of increases or decreases in the rate of application of the curing compound from the nominal application as
specified, shall be the litre. Payment for variations shall be made as specified in Chapter 1.
Item Description Unit
The unit of measurement for steel bars shall be the ton of reinforcing steel in place in accordance with the drawings or as authorized.
The unit of measurement for welded steel fabric shall be the kilogram of welded steel fabric in the panels of concrete paving which require non-
contiguous reinforcement as specified. The quantity shall be calculated from the area of the mesh used in accordance with the drawings or as
authorized.
The tendered rates shall include full compensation for supplying, delivering, cutting, bending, welding, placing and fixing the steel reinforcement,
including all tying wires, spacers and waste.
CONTENTS
D7.2.1 SCOPE
D7.2.2 GENERAL
D7.2.3 PERFORMANCE GUARANTEE REQUIREMENTS
D7.2.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D7.2.5 VISUALLY ASSESSED PROPERTIES
D7.2.6 INSTRUMENTALLY ASSESSED PROPERTIES
D7.2.7 EVALUATION FOR ACCEPTANCE
D7.2.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D7.2.9 NOTIFICATION OF REMEDIAL WORK
D7.2.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A7.3.1 SCOPE
A7.3.2 DEFINITIONS
A7.3.3 GENERAL
A7.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A7.3.5 MATERIALS
A7.3.6 CONSTRUCTION EQUIPMENT
A7.3.7 EXECUTION OF THE WORKS
A7.3.8 WORKMANSHIP
A7.3.2 DEFINITIONS
Jointed Concrete Pavement (Plain JCP) - concrete pavements that contain sufficient joints to control all expected natural cracks. All necessary
cracking occurs at joints and not elsewhere in the slab. However, there may be load transfer devices (e.g., dowel bars) at transverse joints and
deformed steel bars (e.g., tie bars) at longitudinal joints, which is not considered as reinforcement. There may be isolated reinforced panels
(usually in the form of welded steel mesh at approximately 0,1 %, or higher, of gross slab cross-sectional area).
Continuously Reinforced Concrete Pavement (CRCP) - concrete pavements that include continuous longitudinal reinforcement steel typically
between 0,50 and 0,70 % of the cross-sectional area of the pavement slab. They also typically include transverse reinforcing consisting of
individual bars placed at approximately 1,0 m intervals.
Aggregate - granular material of natural, manufactured or recycled origin used in the manufacture of cemented products to the specific grade/class
as defined in these specifications and the latest published version of SANS 1083, or as may be otherwise specifically specified in the Contract
Documentation:
- Course aggregate – all aggregate > 5,0 mm as further defined in the latest SANS 1083 specification for the specific class of aggregate and
nominal maximum aggregate size as required.
- Nominal maximum particle size (NMPS) – designated as one sieve size larger than the largest sieve to retain a minimum of 15 % of the
aggregate particles.
- Fine aggregate – all aggregate fractions ≤ 5,0 mm and which shall consist of clean material derived from crushing competent parent rock,
or naturally occurring sand conforming to SANS 1083 and any further specified requirements listed herein.
Cement - as defined in SANS 50197-1 for the various classes as listed.
Cement extenders - The following as defined in the relevant publications:
- Ground Granulated Blast Furnace Slag: As defined in SANS 55167-1
A7.3.3 GENERAL
A7.3.3.1 Quality Plan and Method Statement
Prior to commencing with any permanent works, the Contractor shall submit a Quality Plan, for acceptance by the Engineer, detailing a complete
method statement, together with all checks and hold points, relating to construction of the specified product.
A7.3.5 MATERIALS
A7.3.5.1 Concrete
All the relevant concrete and other material requirements, as prescribed in Clause A6.1.5 of Chapter 6, shall be applicable.
A7.3.7.2 Preparing the underlying layer/s after concrete has been removed
a) Underlying layers remaining in place
Where the underlying layer does not have to be removed or reworked after the existing concrete pavement has been removed, it shall be prepared
as follows:
(i) Cemented layers
Where the layer consists of cemented material or cemented crushed stone in accordance with the classification of Chapter 4, and
unless otherwise instructed by the Engineer, its surface shall be swept clean and all loose, soft or poorly cemented material shall be
removed. A primer shall then be applied consisting of a stable spray grade emulsion complying with the requirements of SANS 4001
BT-3 cut back to 30 % net bitumen to result in a nominal net bitumen application rate of 0,4 l/m². No primer may be spilt onto the
existing concrete pavement.
After the primer has dried out sufficiently, the surface shall be tested for irregularities in all directions with a 3,0 m straight-edge. All
holes and depressions where the surface deviates by more than 25 mm from the bottom side of the 3,0 m straight-edge shall be filled
in with coarse slurry as specified in Chapter 10, with the exception that the void content in the micro surfacing shall be so designed as
to produce the lowest compacted void content as possible. The micro surfacing shall be thoroughly compacted with appropriate
compaction plant and finished flush with the surface of the layer. The levels of the layer shall be such that the concrete pavement
constructed on it will comply with all the tolerances applicable thereto.
Dependant on the rate of quantity required, the micro surfacing may either be batched in a purpose made slurry machine or in suitable
portable concrete mixers. The surface shall be fully cured and then thoroughly cleaned and dampened with water immediately before
the new concrete is placed.
(ii) Asphalt layers
The layer shall be cleaned and all damaged and loose sections removed. A bond coat consisting of a stable grade emulsion complying
with SANS 4001 BT- 3 cut back to 30 % net bitumen to result in a net bitumen application rate of 0,4 l/m² shall then be applied. No
bond coat may be spilt onto the existing concrete pavement.
The surface shall then be tested for irregularities in all directions with a 3,0 m straight-edge, and the surface may not deviate by more
than 25 mm from the bottom edge of the straight-edge at any point. Where the surface is too small for a 3,0 m straight-edge, a shorter
straight-edge shall be used. All holes and depressions where the surface deviates by more than 25 mm from the bottom side of the
straight-edge shall be filled in with coarse slurry as specified in Chapter 10, with the exception that the void content in the micro
surfacing shall be so designed as to produce the lowest compacted void content as possible. The micro surfacing shall be thoroughly
compacted with appropriate compaction plant and finished flush with the surface of the layer. The levels of the layer shall be such that
the concrete pavement constructed on it will comply with all the tolerances applicable thereto.
Where so instructed by the Engineer, a further coat consisting of 30 % stable-grade bitumen emulsion complying with SANS 4001 BT
shall be applied to the underlying layer immediately before the concrete is placed at a nominal net bitumen application rate of 0,4 l/m².
The emulsion shall be fully cured and the surface shall then be thoroughly cleaned immediately before the new concrete is placed.
(iii) Recompaction of existing underlying pavement layers
Where required, the Contractor shall break up and recompact existing pavement layers to the density specified in the Contract
Documentation. Particular attention shall be given, and appropriate equipment provided, to ensure compliance with the compaction
requirements in the corners of any excavation.
b) Removal of existing underlying pavement layers
Where existing underlying pavement layers are to be removed, the method, and associated equipment, shall be appropriate to the area of the
excavation, and be such to enable the particular layers to be removed without any damage to the surface of layer to remain in place, or any layers
adjacent to the excavation. The re-use of excavated material shall not be a requirement, except where it is specified in the Contract Documentation.
All excavated material shall be disposed of at an approved spoil/dump site.
A7.3.7.4 Reinstatement of tie bars, dowel bars continuous reinforcing and reinforcing mesh
a) Tie bars
(i) In new concrete
Tie bars installed across longitudinal hinge joints of panels consisting of new concrete shall be located at the spacing and depth as
indicated in the Contract Documentation. Treatment and installation shall be in accordance with Clause A6.1.7 of Chapter 6.
(ii) Between existing and new concrete
At longitudinal hinge joints between existing and new concrete, the tie bars extruding from the existing concrete after removal of the
concrete shall be cleaned and straightened and accurately aligned as specified. Existing tie bars that have been irreparably damaged
or destroyed as a result of poor workmanship by the Contractor during breaking up of the existing concrete, or by the sawing and lifting
out of the pavement method if so selected by the Contractor, shall be reinstated by the Contractor at no cost.
In such instances holes shall be drilled into the vertical face of the adjacent existing concrete slab at a spacing and depth equivalent
to that in the existing pavement, and shall be approved by the Engineer. The material requirements shall be as prescribed in Clause
A6.1.5 of Chapter 6, as relevant, and the dimensions of the bars shall be equivalent to those destroyed. The tie bars than then be fixed
into the existing concrete utilising an appropriate epoxy as approved by the Engineer and aligned prior to casting any adjacent new
concrete.
Where no tie bars exist, but are required, new tie bars shall be installed as specified above and shall be provided for, as relevant, in
Part C: Measurement and Payment.
Where no bars are required between the existing and new concrete but such bars do exist in the adjacent existing concrete, such bars
shall be cut off flush with the concrete edge.
b) Dowel bars
(i) In new concrete
Dowel bars installed across transverse contraction joints of new concrete shall be located at the spacing and depth as indicated in the
Contract Documentation. Treatment, installation and allowable tolerances shall be in accordance with Clause A6.1.7 of Chapter 6.
(ii) Between existing and new concrete
At transverse contraction joints, the existing dowels protruding from the face of the concrete exposed, after removal of the deficient
adjacent concrete, shall be cleaned, and where required, straightened to comply with the relevant tolerances prescribed. Where the
sliding end of any undamaged dowel bars occur in existing concrete, the dowel bar shall be extracted, cleaned, treated and then
replaced.
Where any existing dowel bars have been irreparably damaged or severed due to the Contractor’s method of breaking out the existing
concrete, any deficient dowel bars shall be cut off, and new dowel bars of similar dimensions installed at locations and spacing as
approved by the Engineer. No payment shall be applicable for any such associated costs. In such instances holes shall be drilled into
the vertical face of the adjacent existing concrete slab at a spacing and depth equivalent to that in the existing pavement and as
approved by the Engineer. The material requirements shall be as prescribed in Clause A6.1.5 of Chapter 6, as relevant, and the
dimensions of the bars shall be equivalent to those destroyed. The fixed end of the dowel bars than then be fixed into the existing
concrete utilising an appropriate epoxy as approved by the Engineer and aligned prior to casting any adjacent new concrete.
In such cases, no payment shall be applicable for such reinstatement.
Where the dowel bars have been previously damaged or severed, or where the saw and lift-off method has been prescribed in the
Contract Documentation, the dowel bars shall be reinstated in accordance with the drawings. Where no bars are required between
the existing and new concrete but such bars do occur in the existing concrete, such bars shall be cut off flush with the concrete edge.
In such cases payment shall be applicable in accordance with Part C: Measurement and Payment.
Before concrete is placed, all the bars shall be accurately aligned as indicated on the drawings and specified in Clause A6.1.8 of
Chapter 6. Where tie bars or dowels are shown on the drawings at joints between existing and new concrete, but no such bars occur
in the existing concrete, holes shall be drilled in the existing concrete and fresh bars placed and fixed as prescribed in the Contract
Documentation. In such cases, the dowels shall be placed with their sliding ends in the new concrete.
A7.3.8.3 Thickness
Where full depth panels or portions thereof, are replaced on top of the existing subbase layers, the nominal thickness of the concrete shall be
equal to the nominal thickness of the adjacent concrete pavement.
A7.3.8.6 Texture
The average depth of texture shall be between 3,0 and 4,5 mm as prescribed.
CONTENTS
B7.3.1 SCOPE
B7.3.2 DEFINITIONS
B7.3.3 GENERAL
B7.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B7.3.5 MATERIALS
B7.3.6 CONSTRUCTION EQUIPMENT
B7.3.7 EXECUTION OF THE WORKS
B7.3.8 WORKMANSHIP
B7.3.1 SCOPE
The provisions of Part A shall apply.
B7.3.2 DEFINITIONS
The provisions of Part A shall apply.
B7.3.3 GENERAL
The provisions of Part A shall apply.
B7.3.5 MATERIALS
The provisions of Part A shall apply.
B7.3.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be a cubic metre of concrete or underlying pavement layers broken up and removed to an approved spoil site. The
quantity shall be determined in accordance with the authorized dimensions the particular pavement layer removed.
The tendered rate shall include full compensation for breaking up the concrete, loading, and transporting it to an approved spoil site and removing any
remaining debris ad cleaning the excavation as specified. No overhaul shall be applicable. The tendered rate shall also include full compensation for
the protection of adjacent concrete and its repair should it be damaged.
Dowels and tie bars in existing concrete and stays used to keep the bars in position will not be regarded as reinforcing.
C7.3.2 Full depth repairs using hand placed concrete with CEM I 52,5 cubic metre (m³)
The unit of measurement shall be the cubic metre of pavement placed by hand and finished in accordance with the specifications and Drawings,
and the quantity shall be the summation of the individual areas calculated by multiplying the length by the width at the top surface of the repaired
panel by the average depth of the repair. The tendered rate shall include full compensation for:
• Procuring, furnishing and storage of all materials
• Provision of all plant
• Saw cutting including both pilot and final cuts
• Epoxy filling of overcuts at corners
• Breaking out and removing concrete
• Cutting existing reinforcement as required
• Preparing subbase including cleaning out and priming
• Determination of mix proportions
• Mixing, transporting, placing and finishing of the concrete, including formwork where required
• Mesh reinforcement including cutting, waste and placing
• Mechanical texturing, curing and surface protection
• Disposal of surplus material and cleaning up
• Sampling and testing
In addition, the tendered rate shall also include full compensation for the preparation of joint faces in accordance with the specifications and
drawings and shall include following:
• Cleaning of joint faces
• Supply and application of bond-breaker
• Supply and application of wet to dry epoxy
• Installation of joint former where required
• Initial saw cutting for crack control where two panels are cast together
• Saw cutting for installation of silicone sealant
• Forming of central key at longitudinal construction joints
• Provision of all plant and materials
• Disposal of surplus materials and cleaning up
C7.3.3 Partial Depth Repairs using hand placed fine concrete cubic metre (m³)
The unit of measurement shall be the square metre of partial depth repair placed by hand and finished in accordance with the Contract
Documentation, and the quantity shall be the summation of the individual repair areas measured at the surface of the slab. The depth of the repair
shall be a minimum of 50 mm and a maximum of 75 mm.
The unit of measurement shall be the number of tie-bars or dowels placed in accordance with the Drawings or as authorised by the Engineer.
C7.3.5 Partial Depth Repairs using hand placed acrylic resin grout square metre (m²)
The unit of measurement shall be the square metre of partial depth repair placed by hand and finished in accordance with the specifications and
drawings, and the quantity shall be the summation of the individual repair areas measured at the surface of the slab. The depth of the repair shall
be a minimum of 50 mm and a maximum of 75 mm.
C7.3.6 Reinstating the subbase with lean mix concrete cubic metre (m³)
The unit of measurement shall be the cubic metre of lean mix concrete placed by hand and in accordance with the specifications and drawings.
The quantity shall be the summation of the individual areas calculated by multiplying the length by the width at the top surface of the repaired
subbase by the average depth of the repair.
The unit of measurement shall be number of exposed stitches removed from the concrete pavement as indicated by the Engineer. The tendered
rate shall include full compensation for widening the slot by means of saw cutting, removing the steel bar from the slot and cleaning the slot.
Damage to the concrete pavement shall be at the Contractor's expense.
Item Unit
The unit of measurement shall be a square metre of saw-cut in the existing concrete as approved by the Engineer and sawn to the required depth,
measured once only irrespective of the number of times the sawing has to be repeated to obtain such depth. The quantity shall be the product of the
authorized length and depth of the saw-cut.
The tendered rate shall include full compensation for demarcating the saw line, providing and applying water and other material, and for sawing the
concrete to the satisfaction of the Engineer.
This item shall not apply to the sawing of joints.
Item Description Unit
The unit of measurement shall be a cubic metre of concrete or underlying pavement layers broken up and removed to an approved spoil site. The
quantity shall be determined in accordance with the authorized dimensions the particular pavement layer removed.
Dowels and tie bars in existing concrete and stays used to keep the bars in position will not be regarded as reinforcing.
C7.3.10 Preparing the underlying layers after the concrete has been removed
C7.3.10.2 Replacement of granular layers (material class and thickness indicated) square metre (m²)
C7.3.10.3 Replacement of stabilised layers (material class and thickness indicated) square metre (m²)
C7.3.10.4 Replacement of supporting layers with 10 MPa lean mix concrete (material class and square metre (m²)
thickness indicated)
C7.3.10.5 Replacement of subbase with hot mix asphalt (thickness indicated) ton (t)
C7.3.10.6 Levelling the surface with coarse slurry (micro surfacing) cubic metre (m³)
The unit of measurement shall be a square metre, cubic metre or ton, as relevant, of existing underlying layer prepared in accordance with the
requirements. The quantity shall be computed in accordance with the authorized dimensions of the prepared layer, or weigh bridge certificates as
relevant for asphalt.
The tendered rate shall include full compensation for preparing the layer in accordance with the specified requirements, testing for level, cleaning the
edge of the existing concrete and for removing any remaining loose material and waste.
Item Description Unit
C7.3.11.1 Replacement of concrete in JCP pavements (thickness indicated) square metre (m²)
C7.3.11.2 Replacement concrete in CRCP pavements (thickness indicated) square metre (m²)
C7.3.13.1 Burlap-dragged and texture (indicate groove or broom finish) square metre (m²)
The unit of measurement for texturing and curing shall be the square metre of completed pavement which has received the specified surface texturing,
and curing compound as specified. The quantity shall be calculated from the specified horizontal dimensions of the completed concrete surface. The
tendered rate for texturing shall include full compensation for providing the plant and equipment required and for applying the specified surface texture.
The tendered rate for curing shall include full compensation for providing the curing compound and its application as specified at the specified nominal
rates of application by means of an approved pressure distributor. The tendered rate shall also include compensation for spraying the curing compound
in unsealed joints after the sawing has been completed.
Item Description Unit
C7.3.14 Variation in the rate of application of the curing compound litre (ℓ)
The unit of measurement in respect of increases or decreases in the rate of application of the curing compound from the nominal application as
specified, shall be the litre. Payment for variations shall be made as specified in Chapter 1.
Item Description Unit
The unit of measurement for steel bars shall be the ton of reinforcing steel in place in accordance with the drawings or as authorized.
The unit of measurement for welded steel fabric shall be the kilogram of welded steel fabric in the panels of concrete paving which require non-
contiguous reinforcement as specified. The quantity shall be calculated from the area of the mesh used in accordance with the drawings or as
authorized.
The tendered rates shall include full compensation for supplying, delivering, cutting, bending, welding, placing and fixing the steel reinforcement,
including all tying wires, spacers and waste.
C7.3.16 Temporary Partial Depth Repairs using Asphalt Materials square metre (m²)
The unit of measurement shall be the square metre of repair at joint or surface spalling carried out in accordance with the specifications and
Drawing, and the quantity shall be the summation of the individual repair areas measured at the surface of the slab. The depth of the repair shall
be a minimum of 50 mm and a maximum of 75 mm.
The excavation and preparation of the repairs shall be paid for under C7.3.10.
CONTENTS
D7.3.1 SCOPE
D7.3.2 GENERAL
D7.3.3 PERFORMANCE GUARANTEE REQUIREMENTS
D7.3.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D7.3.5 VISUALLY ASSESSED PROPERTIES
D7.3.6 INSTRUMENTALLY ASSESSED PROPERTIES
D7.3.7 EVALUATION FOR ACCEPTANCE
D7.3.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D7.3.9 NOTIFICATION OF REMEDIAL WORK
D7.3.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A7.4.1 SCOPE
A7.4.2 DEFINITIONS
A7.4.3 GENERAL
A7.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A7.4.5 MATERIALS
A7.4.6 CONSTRUCTION EQUIPMENT
A7.4.7 EXECUTION OF THE WORKS
A7.4.8 WORKMANSHIP
A7.4.2 DEFINITIONS
Sub-sealing - the filling of voids under the concrete pavement as a result of hydraulic erosion or other causes.
Slab jacking - the lifting of panels that have settled in order to reinstate ride quality.
A7.4.3 GENERAL
A7.4.3.1 Weather conditions
Sub sealing or slab jacking shall only be undertaken when the ambient temperature is 5°C and rising, and shall cease when the temperature exceed
30°C.
A7.4.6.3 Sub-sealing
The purpose of slab stabilization is to fill existing voids and not to raise the slab. Close inspection is required by the contractor and the inspector
during the stabilisation operation, as lifting of the slabs can create additional voids and may lead to slab cracking. The success of the slab
stabilisation operations is highly dependent upon the skill of the contractor.
The grout injection should start with a low pumping rate and pressure and should be pumped until one of the following conditions occurs:
• The maximum allowable pressure of 0,69 MPa at the grout plant is obtained. Note that a short surge up to 1,38 MPa can be allowed
when starting to pump in order for the grout to penetrate the void structure, if necessary.
• The slab lift exceeds 3,0 mm.
• Grout is observed flowing from adjacent holes, cracks, or joints.
• Grout is being pumped unnecessarily under the shoulder, as indicated by lifting.
• More than about 1 minute has elapsed (any longer than this indicates the grout is flowing into a cavity).
The uplift for any given slab corner should be monitored using a modified Benkelman Beam or other similar device that is capable of detecting
0,025 mm of uplift movement.
The effectiveness of slab stabilization can be determined only by monitoring the subsequent performance of the pavement. The best early
indication of effectiveness is obtained by measuring slab deflections before and after grouting to determine if the magnitude of the deflection has
been significantly reduced by the process. If the retesting still indicates a loss of support, the slabs should be regrouted using new drilled holes. If
voids are still present after three attempts to stabilize the slab, other methods of repair should be considered (e.g., full-depth repair).
A7.4.6.4 Slab-jacking
Procedures must be developed to monitor the raising of the slab and to ensure that the profile meets the desired grade. The taut stringline method
is an excellent way to not only control the pumping sequence, but also to achieve the proper grade.
In the stringline method, small wooden blocks, 19 mm (0,75 in) high, are set on the pavement surface along the outer and inner edges and a
stringline is secured at least 3,0 m (10 ft) from each end of the depression. As material pumping proceeds, the exact amount of rise at each point
within the sag can be observed, allowing the pumping at specific holes to be carefully controlled. This method can consistently achieve profiles
within tolerances of 6,0- to 9,0 mm (0,25- to 0,38 in).
• After all preliminary work has been completed (holes drilled, relief opening cut if needed), the pavement is ready to be raised. The slab
must be raised only a very small amount at each hole at a time. A good rule is not to raise a slab more than 6,0 mm (0,25 in) while
pumping in any one hole. No portion of the slab should be more than 6,0 mm (0,25 in) higher than any other part of the slab (or an
adjacent slab) at any time. The entire working slab and all those adjacent to it must be kept in the same plane, within 6,0 mm (0,25 in),
throughout the entire operation to avoid cracking.
• Pumping should be done over the entire section so that no great strain is developed at any one place. If, for example, pumping was
started at either end of a dip, the tension on the top surface will be increased, and the slab will undoubtedly crack. However, if pumping
is started at the middle where the tension is on the lower surface, lifting will tend to reduce it, and the slab can be raised an appreciable
amount without any damage. As the section is brought back to its original profile, the pumping is extended farther and farther in either
direction until the entire dip is at the desired elevation.
A7.4.6.9 Finishing
All loose concrete, joint filler or grout/foam accidentally or otherwise spilled on the surface of the concrete pavement or on the adjoining gravel
shoulder/median and any other construction waste material shall be removed and the surrounding areas shall be left in a neat and orderly condition
by the Contractor prior to final acceptance of the work.
A7.4.7 WORKMANSHIP
A7.4.7.1 Level and Grade
The level tolerance on any portion of full depth fresh concrete cast between existing panels or portions thereof, shall be governed by the levels
on the adjacent edges of the existing concrete. Where the fresh concrete is a portion of an existing panel the level shall be checked by a 3,0 m
straight-edge placed across the existing concrete edges and the level of the fresh concrete shall not deviate by more than ± 3,0 mm from the line
of the straight-edge.
Where complete panels are replaced between existing joints, the longitudinal grade tolerance of each replaced panel shall be governed by the
longitudinal grade along the edge of adjacent concrete panels remaining in position. The concrete shall be finished flush with the adjacent panels
and the maximum deviation from the existing longitudinal grade shall not exceed ± 3,0 mm.
For thin bonded arris and surface repairs the fresh concrete shall be finished flush with the surrounding concrete to within a tolerance of ± 3,0
mm.
A7.4.7.2 Thickness
Where full depth panels or portions thereof, are replaced on top of the existing subbase layers, the nominal thickness of the concrete shall be
equal to the nominal thickness of the adjacent concrete pavement.
CONTENTS
B7.4.1 SCOPE
B7.4.2 DEFINITIONS
B7.4.3 GENERAL
B7.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B7.4.5 MATERIALS
B7.4.6 CONSTRUCTION EQUIPMENT
B7.4.7 EXECUTION OF THE WORKS
B7.4.8 WORKMANSHIP
B7.4.1 SCOPE
The provisions of Part A shall apply.
B7.4.2 DEFINITIONS
The provisions of Part A shall apply.
B7.4.3 GENERAL
The provisions of Part A shall apply.
B7.4.5 MATERIALS
The provisions of Part A shall apply.
B7.4.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be the number of 50 kg pockets of cement used to complete the sub-sealing operation. The tendered rate shall
include full compensation for supplying all the equipment and incidentals necessary to carry out the sub-sealing operation complete and shall
include for all pozzolans, fly ash, water and admixtures used in the grout mixture.
The tendered rate shall also include for the cleaning of the pavement surface of all debris and grout spillage, wooden plugs and the sealing of
joints and other openings where the grout may escape. The tendered rate shall also include full compensation for supplying all equipment,
materials and incidentals required to drill the holes, cleaning and monitoring the holes and to fill the holes with a suitable cement/fine aggregate
mix after the sub-sealing operation has been completed.
CONTENTS
D7.4.1 SCOPE
D7.4.2 GENERAL
D7.4.3 PERFORMANCE GUARANTEE REQUIREMENTS
D7.4.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D7.4.5 VISUALLY ASSESSED PROPERTIES
D7.4.6 INSTRUMENTALLY ASSESSED PROPERTIES
D7.4.7 EVALUATION FOR ACCEPTANCE
D7.4.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D7.4.9 NOTIFICATION OF REMEDIAL WORK
D7.4.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A7.5.1 SCOPE
A7.5.2 DEFINITIONS
A7.5.3 GENERAL
A7.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A7.5.5 MATERIALS
A7.5.6 CONSTRUCTION EQUIPMENT
A7.5.7 EXECUTION OF THE WORKS
A7.5.8 WORKMANSHIP
A7.5.2 DEFINITIONS
Smoothness/riding quality – as measured by appropriate methods depending on the area/s being assessed, and may include:
- 3,0 m straight edge
- Rolling straight edge
- Direct Contact Roughness Measuring Devices
- High Speed Inertial Non-Contact Laser Profilometers
A7.5.3 GENERAL
In this Section, distinction is made as follows:
- Work required on newly placed concrete as a result of poor workmanship not meeting the required specifications
- Work required as a result of deficiencies in the existing concrete surface
In the case of poor workmanship, no payment for this work, including traffic accommodation and any additional riding quality measurements ordered
by the Engineer, shall be applicable.
A7.5.5 MATERIALS
Not applicable
A7.5.8 WORKMANSHIP
After completion of the grinding, the finished surface shall comply with all the smoothness requirements as specified in Clause A6.1.8 of Chapter 6 as
relevant, or any other requirement as may be specified in the Contract Documentation.
CONTENTS
B7.5.1 SCOPE
B7.5.2 DEFINITIONS
B7.5.3 GENERAL
B7.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B7.5.5 MATERIALS
B7.5.6 CONSTRUCTION EQUIPMENT
B7.5.7 EXECUTION OF THE WORKS
B7.5.8 WORKMANSHIP
B7.5.1 SCOPE
The provisions of Part A shall apply.
B7.5.2 DEFINITIONS
The provisions of Part A shall apply.
B7.5.3 GENERAL
The provisions of Part A shall apply.
B7.5.5 MATERIALS
The provisions of Part A shall apply.
B7.5.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be the square metre of surface treated. The tendered rate shall include full compensation for establishing the
appropriate equipment on site, grinding as required and disposing all removed material and or debris from the site to an approved spoil site.
CONTENTS
D7.5.1 SCOPE
D7.5.2 GENERAL
D7.5.3 PERFORMANCE GUARANTEE REQUIREMENTS
D7.5.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D7.5.5 VISUALLY ASSESSED PROPERTIES
D7.5.6 INSTRUMENTALLY ASSESSED PROPERTIES
D7.5.7 EVALUATION FOR ACCEPTANCE
D7.5.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D7.5.9 NOTIFICATION OF REMEDIAL WORK
D7.5.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A7.6.1 SCOPE
A7.6.2 DEFINITIONS
A7.6.3 GENERAL
A7.6.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A7.6.5 MATERIALS
A7.6.6 CONSTRUCTION EQUIPMENT
A7.6.7 EXECUTION OF THE WORKS
A7.6.8 WORKMANSHIP
A7.6.2 DEFINITIONS
Texture/mean profile depth – consisting of randomly spaced grooves formed in fresh concrete or sawn into hardened concrete normally 3,0 to 5,0
mm in depth.
A7.6.3 GENERAL
In this Section, distinction is made as follows:
- Work required on newly placed concrete as a result of poor workmanship not meeting the required specifications
- Work required as a result of deficiencies in the existing concrete surface
In the case of poor workmanship, no payment for this work, including traffic accommodation and any additional texture depth measurements required,
shall be applicable.
A7.6.5 MATERIALS
Not applicable
A7.6.8 WORKMANSHIP
The average depth of the grooves, as measured with a tyre tread depth gauge, shall be 4,0 mm and within the range of 3,0 to 5,0 mm and at a random
spacing between 12 and 25 mm.
Groove depth is the most important component that needs to be evaluated constantly, of importance in this respect is machine speed. At high
speeds blades tend to lift out of the concrete and shallow groove depths are obtained.
A minimum of 3 measurements per lane at random positions will be taken with a digital calliper at hourly intervals. The average depth, standard
deviation and coefficient of variation for every sample will be taken.
Allowable tolerances shall be as follows:
Groove width: 3,5 mm +-0,5 mm
Groove depth: 4,5 mm +-1,5 mm
CONTENTS
B7.6.1 SCOPE
B7.6.2 DEFINITIONS
B7.6.3 GENERAL
B7.6.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B7.6.5 MATERIALS
B7.6.6 CONSTRUCTION EQUIPMENT
B7.6.7 EXECUTION OF THE WORKS
B7.6.8 WORKMANSHIP
B7.6.1 SCOPE
The provisions of Part A shall apply.
B7.6.2 DEFINITIONS
The provisions of Part A shall apply.
B7.6.3 GENERAL
The provisions of Part A shall apply.
B7.6.5 MATERIALS
The provisions of Part A shall apply.
B7.6.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be a square metre of saw-cut texturing in the existing concrete surface according to the groove specifications, measured
once only irrespective of the number of times the sawing has to be repeated to obtain such depth.
The tendered rate shall include full compensation for demarcating the saw line, providing equipment and applying water or any other material. The
rate shall also include for the protection of the adjacent road verge and subsequent disposal of the paste at an approved spoil site.
CONTENTS
D7.6.1 SCOPE
D7.6.2 GENERAL
D7.6.3 PERFORMANCE GUARANTEE REQUIREMENTS
D7.6.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D7.6.5 VISUALLY ASSESSED PROPERTIES
D7.6.6 INSTRUMENTALLY ASSESSED PROPERTIES
D7.6.7 EVALUATION FOR ACCEPTANCE
D7.6.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D7.6.9 NOTIFICATION OF REMEDIAL WORK
D7.6.10 REMEDIAL WORKS
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied. No
warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 8: PRETREATMENT AND REPAIR OF EXISTING LAYERS .................................................................. 8-1
8.1 PRIME COAT ......................................................................................................................................................... 8-1
PART A: SPECIFICATIONS .................................................................................................................................................................................. 8-1
PART B: LABOUR ENHANCEMENT ..................................................................................................................................................................... 8-4
PART C: MEASUREMENT AND PAYMENT ......................................................................................................................................................... 8-5
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ............................................................................................................................ 8-7
8.2 COVER SPRAYS, FOG SPRAYS AND REJUVENATION SPRAYS ................................................................... 8-8
PART A: SPECIFICATIONS .................................................................................................................................................................................. 8-8
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................... 8-10
PART C: MEASUREMENT AND PAYMENT ....................................................................................................................................................... 8-11
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .......................................................................................................................... 8-13
8.3 TEXTURE TREATMENT ...................................................................................................................................... 8-14
PART A: SPECIFICATIONS ................................................................................................................................................................................ 8-14
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................... 8-16
PART C: MEASUREMENT AND PAYMENT ....................................................................................................................................................... 8-17
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .......................................................................................................................... 8-18
8.4 RUT AND/OR DEPRESSION CORRECTION ..................................................................................................... 8-19
PART A: SPECIFICATIONS ................................................................................................................................................................................ 8-19
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................... 8-22
PART C: MEASUREMENT AND PAYMENT ....................................................................................................................................................... 8-23
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .......................................................................................................................... 8-24
8.5 STANDARD CRACK SEALING........................................................................................................................... 8-25
PART A: SPECIFICATIONS ................................................................................................................................................................................ 8-25
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................... 8-28
PART C: MEASUREMENT AND PAYMENT ....................................................................................................................................................... 8-29
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .......................................................................................................................... 8-30
8.6 GEOSYNTHETIC CRACK SEALING .................................................................................................................. 8-31
PART A: SPECIFICATIONS ................................................................................................................................................................................ 8-31
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................... 8-33
PART C: MEASUREMENT AND PAYMENT ....................................................................................................................................................... 8-34
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .......................................................................................................................... 8-35
8.7 PLANING .............................................................................................................................................................. 8-36
PART A: SPECIFICATIONS ................................................................................................................................................................................ 8-36
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................... 8-38
PART C: MEASUREMENT AND PAYMENT ....................................................................................................................................................... 8-39
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .......................................................................................................................... 8-41
8.8 PATCHING AND EDGE BREAK REPAIR .......................................................................................................... 8-42
PART A: SPECIFICATIONS ................................................................................................................................................................................ 8-42
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................... 8-45
PART C: MEASUREMENT AND PAYMENT ....................................................................................................................................................... 8-46
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .......................................................................................................................... 8-49
8.9 REPAIR OF SURFACE DEFECTS ...................................................................................................................... 8-50
PART A: SPECIFICATIONS ................................................................................................................................................................................ 8-50
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................... 8-54
PART C: MEASUREMENT AND PAYMENT ....................................................................................................................................................... 8-55
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .......................................................................................................................... 8-57
CHAPTER 8: PRETREATMENT AND REPAIR OF EXISTING LAYERS
8.1 PRIME COAT
CONTENTS
PART A: SPECIFICATIONS
A8.1.1 SCOPE
A8.1.2 DEFINITIONS
A8.1.3 GENERAL
A8.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A8.1.5 MATERIALS
A8.1.6 CONSTRUCTION EQUIPMENT
A8.1.7 EXECUTION OF THE WORKS
A8.1.8 WORKMANSHIP
A8.1.2 DEFINITIONS
Prime coat - consists of a low viscosity bituminous binder, applied in a single application on a granular, cemented or treated base or subbase to
facilitate a good bond between the base and the bituminous surfacing or subbase and bitumen treated base.
A8.1.3 GENERAL
A8.1.3.1 Weather limitations
No prime shall be applied under the following adverse conditions:
• During foggy or wet conditions;
• When rain is imminent;
• When wind is blowing sufficiently hard to cause uneven spraying;
• When the surface of the layer is visibly wet, i.e. more than damp;
• When the temperature of the surface immediately prior to commencing with the application of the prime is below, or in the opinion of the
Engineer, likely to fall below 10°C;
• After sunset;
• When at any position within the layer the moisture content of a granular base layer is more than 50 % of the optimum moisture content
determined according to SANS 3001 No GR30. In the event of rain after priming, the base shall be allowed to dry out to meet the above
moisture content requirements prior to surfacing. Limiting moisture contents for treated layers before priming shall be specified in the
Contract Documentation.
A8.1.5 MATERIALS
A8.1.5.1 Bituminous material
The priming material shall be one of the following as specified in Part C: Measurement and Payment:
Table A8.1.5-1: Bituminous binder for priming the excavated area
Bituminous binder for priming the excavated area Specification
MC-10 cut-back bitumen SANS 4001 – BT2
MC-30 cut-back bitumen SANS 4001 – BT2
Inverted bitumen emulsion SANS 4001 – BT5
Certified by independent
Other appropriate product containing solvents
certification agency
Certified by independent
Other appropriate product containing no solvents
certification agency
The type of prime and application rate best suited for the base shall be determined after construction of the base. The Contractor shall provide
about 20 ℓ of at least three prime products and apply it at different application rates with a brush on the base. The Engineer shall evaluate the
performance of the prime in accordance with the latest version of TRH1/SABITA Manual 26 and then instruct the type of prime and application
rate to be applied. No payment shall be made for tests to determine the appropriate priming product.
A8.1.8 WORKMANSHIP
A8.1.8.1 Tolerances
The actual spray rates measured at spraying temperature shall not deviate by more than 8,0 % from that ordered by the Engineer. The Engineer
may conditionally accept application rates falling outside this tolerance at reduced payment in accordance with Table A8.1.8-1. Conditional
acceptance shall not relieve the Contractor of his contractual obligations.
A8.1.8.2 Testing
The Contractor shall give the Engineer at least 24 hours’ notice of his intention to spray prime material so that the actual spray rates can be
verified and approved by the Engineer. Unless otherwise agreed in advance, the Contractor shall only spray when the Engineer’s representative is
present.
The Contractor shall provide, at his cost, representative samples of every batch of prime delivered onto site.
Table A8.1.8-1: Payment reduction factors for conditionally accepted prime coat
Deviation specified spray rate at spraying Payment reduction factor of
temperature (%) tendered rate
±8,0 1.00
±9,0 0.97
±10,0 0.95
±11,0 0.90
±12,0 0.85
±13,0 0.80
Any deviation outside these limits shall not be paid for however, the Engineer shall have the right to instruct the Contractor to make up any
deficiency, or blind excessive prime without additional payment. If under-spraying occurs, and it is accepted by the Engineer, only the actual
quantities applied shall be paid for.
CONTENTS
B8.1.1 SCOPE
B8.1.2 DEFINITIONS
B8.1.3 GENERAL
B8.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.1.5 MATERIALS
B8.1.6 CONSTRUCTION EQUIPMENT
B8.1.7 EXECUTION OF THE WORKS
B8.1.8 WORKMANSHIP
B8.1.1 SCOPE
A large proportion of activities as defined in Part A under the various sections are considered labour intensive. Therefore, Part B only provides
additional specifications, not contained in Part A.
B8.1.2 DEFINITIONS
Definitions as provided in A8.1.2 apply.
B8.1.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B8.1.5 MATERIALS
The provisions of Part A shall apply.
B8.1.8 WORKMANSHIP
Unless revised tolerances are specified in the Contract Documentation, the provisions of Part A shall apply.
The unit of measurement shall be the litre of priming material measured at spraying temperature and sprayed as required.
The tendered rates shall include full compensation for supplying the priming material, cleaning and watering the layer to be primed, applying the
priming material and maintaining the primed surface as specified.
The unit of measurement shall be the cubic metre of aggregate used for blinding on the instructions of the Engineer.
The tendered rate shall include full compensation for procuring, furnishing and applying the aggregate for blinding where directed by the Engineer
C8.1.3 Extra over item C8.1.1 for applying the prime coat accessible only to hand-held or litre (ℓ)
light equipment
The unit of measurement shall be the litre of priming material measured at spraying temperature and sprayed in accordance with the requirements
for areas accessible only to hand-held or light equipment and shall include for all additional costs.
CONTENTS
D8.1.1 SCOPE
D8.1.2 GENERAL
D8.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.1.5 VISUALLY ASSESSED PROPERTIES
D8.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.1.7 EVALUATION FOR ACCEPTANCE
D8.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.1.9 NOTIFICATION OF REMEDIAL WORK
D8.1.10 REMEDIAL WORK
D8.1.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapter 9
and Chapter 10 shall apply.
D8.1.2 GENERAL
Not applicable to pretreatment works.
CONTENTS
PART A: SPECIFICATIONS
A8.2.1 SCOPE
A8.2.2 DEFINITIONS
A8.2.3 GENERAL
A8.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A8.2.5 MATERIALS
A8.2.6 CONSTRUCTION EQUIPMENT
A8.2.7 EXECUTION OF THE WORKS
A8.2.8 WORKMANSHIP
A8.2.2 DEFINITIONS
Cover spray - refers to the application of a diluted emulsion as a final binder application on single or double seals or before application of the
slurry, in case of Cape seals.
Fog spray or rejuvenation spray - is used for the application of diluted anionic emulsion or rejuvenator for purposes of adding additional binder to
the seal or rejuvenating the seal at a later stage of the seal life.
The convention for describing diluted emulsion in this document is to state the type of emulsion with the proportion of emulsion and water in
brackets e.g. 65 % cationic emulsion (60/40), which defines the mix as 60 % of the cationic emulsion and 40 % water.
A8.2.3 GENERAL
Fog sprays in the form of diluted anionic emulsion or inverted bitumen emulsion are applied during the service life of an existing bituminous
surfacing to add additional binder or to rejuvenate the existing binder. Fog sprays using stable grade diluted anionic emulsions are applied as a
pretreatment prior the application of a surfacing seal, if specified.
Diluted cationic spray grade emulsions are used as cover sprays during seal construction or shortly thereafter where the seal is sensitive to
aggregate loss.
A8.2.3.2 Nominal rate of application for cover sprays, fog sprays and rejuvenation sprays
The nominal rate of application for tender purposes shall be:
a) Diluted cationic emulsion cover spray at 1,0 l/m2
b) Diluted anionic or cationic emulsion cover spray, in the case of Cape seals, at 0,8 l/m2
c) Diluted anionic emulsion fog spray as enrichment treatment at 0,8 l/m2
d) Rejuvenation spray with cut-back inverted emulsion or other Agrément certified products at 0,5 l/m2
A8.2.5 MATERIALS
A8.2.5.1 Bitumen
a) Cover spray
Diluted 65 % cationic spray grade emulsion, or 60 % anionic stable grade emulsion, with the dilutions as specified in Part C: Measurement and
Payment.
b) Fog spray as enrichment treatment
A diluted 60 % anionic stable-grade emulsion (50/50) shall be used.
c) Rejuvenation spray
Agrément SA certified products or inverted bitumen emulsion complying with SANS 4001 – BT5, with the exception that the Viscosity at 60 °C on
residue from distillation shall be between 10 and 20 Pas.
A8.2.8 WORKMANSHIP
The requirements of Clauses A10.1.3.9 and A10.1.3.4 of Chapter 10 regarding joints between sprayed strips and the protection of kerbs,
channels, barriers, any structures, etc, shall apply.
CONTENTS
B8.2.1 SCOPE
B8.2.2 DEFINITIONS
B8.2.3 GENERAL
B8.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.2.5 MATERIALS
B8.2.6 CONSTRUCTION EQUIPMENT
B8.2.7 EXECUTION OF THE WORKS
B8.2.8 WORKMANSHIP
B8.2.1 SCOPE
A large proportion of activities as defined in Part A under the various sections are considered labour intensive. Therefore, Part B only provides
additional specifications, not contained in Part A.
B8.2.2 DEFINITIONS
Definitions as provided in Clause A8.2.2 apply.
B8.2.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B8.2.5 MATERIALS
The provisions of Part A shall apply.
B8.2.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be the litre of binder measured at spraying temperature and sprayed in accordance with the requirements.
The tendered rates shall include full compensation for cleaning and preparing the existing surface, for furnishing the material and applying the
binder and for all other incidentals necessary for completing the work as specified.
Item Description Unit
CONTENTS
D8.2.1 SCOPE
D8.2.2 GENERAL
D8.2.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.2.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.2.5 VISUALLY ASSESSED PROPERTIES
D8.2.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.2.7 EVALUATION FOR ACCEPTANCE
D8.2.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.2.9 NOTIFICATION OF REMEDIAL WORK
D8.2.10 REMEDIAL WORK
D8.2.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapters 9
and Chapter 10 shall apply.
D8.2.2 GENERAL
Not applicable to pretreatment works.
CONTENTS
PART A: SPECIFICATIONS
A8.3.1 SCOPE
A8.3.2 DEFINITIONS
A8.3.3 GENERAL
A8.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A8.3.5 MATERIALS
A8.3.6 CONSTRUCTION EQUIPMENT
A8.3.7 EXECUTION OF THE WORKS
A8.3.8 WORKMANSHIP
A8.3.2 DEFINITIONS
Texture treatment - refers to the application of a thin layer of slurry or microsurfacing to obtain a uniform fine texture prior to surfacing or
resurfacing.
A8.3.3 GENERAL
This treatment shall be used where the existing surface macro texture is coarse or varying to such an extent that one single and uniform binder
application rate for the seal to follow could result in the poor performance of the seal.
Texture slurry application on existing macro texture of 1,0 mm to 2,0 mm 0,003 m³/m²
Texture slurry application on existing macro texture of 2,0 mm to 4,0 mm 0,0045 m³/m²
A8.3.5 MATERIALS
A8.3.5.1 Bitumen
a) The bituminous binder for conventional slurry shall be a 60 % stable-grade anionic bitumen emulsion complying with SANS 4001 – BT3.
b) The bituminous binder for microsurfacing shall comply to the specifications of Clause A10.1.5.5 of Chapter 10.
A8.3.5.2 Aggregate
a) Aggregate for texture slurry shall comply with the specifications of Clause A10.15.17a) of Chapter 10 for fine slurry, fine grade or medium
grade.
b) Aggregate for texture treatment with microsurfacing shall comply with the specifications of Clause A10.15.18 of Chapter 10 for Type II
grading.
A8.3.8 WORKMANSHIP
The requirements of Clause A10.1.8 of Chapter 10 shall apply.
CONTENTS
B8.3.1 SCOPE
B8.3.2 DEFINITIONS
B8.3.3 GENERAL
B8.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.3.5 MATERIALS
B8.3.6 CONSTRUCTION EQUIPMENT
B8.3.7 EXECUTION OF THE WORKS
B8.3.8 WORKMANSHIP
B8.3.1 SCOPE
A large proportion of activities as defined in Part A under the various sections are considered labour intensive. Therefore, Part B only provides
additional specifications, not contained in Part A.
B8.3.2 DEFINITIONS
Definitions as provided in Clause A8.3.2 apply.
B8.3.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B8.3.5 MATERIALS
The provision of Part A shall apply.
B8.3.8 WORKMANSHIP
The provisions of Part A shall apply.
C8.3.1.2 Application of slurry for texture improvement, applied by spreader box (Indicate aggregate cubic metre (m³)
grade, type of emulsion, filler type)
C8.3.1.3 Application of microsurfacing for texture improvement, applied by spreader box (Indicate cubic metre (m³)
aggregate grade, type of emulsion, filler type)
The measurement for slurry shall be the cubic metre of saturated fine aggregate used, measured as described in item C10.1.20 of Chapter 10.
The tendered rates shall include full compensation for procuring and furnishing all the materials, for mixing and applying the slurry, demarcating all
areas to be treated and for all plant, labour and incidentals necessary to complete the work as specified.
CONTENTS
D8.3.1 SCOPE
D8.3.2 GENERAL
D8.3.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.3.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.3.5 VISUALLY ASSESSED PROPERTIES
D8.3.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.3.7 EVALUATION FOR ACCEPTANCE
D8.3.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.3.9 NOTIFICATION OF REMEDIAL WORK
D8.3.10 REMEDIAL WORK
D8.3.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapters 9
and Chapter 10 shall apply.
D8.3.2 GENERAL
Not applicable to pretreatment works.
CONTENTS
PART A: SPECIFICATIONS
A8.4.1 SCOPE
A8.4.2 DEFINITIONS
A8.4.3 GENERAL
A8.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A8.4.5 MATERIALS
A8.4.6 CONSTRUCTION EQUIPMENT
A8.4.7 EXECUTION OF THE WORKS
A8.4.8 WORKMANSHIP
A8.4.2 DEFINITIONS
Rut correction - refers to filling of ruts in the wheel tracks
Screeding - refers to level correction using coarse slurry, microsurfacing or asphalt where the road surface is uneven and where depressions,
humps or small grooves occur as a result of deformation of the pavement layers not due to structural failure of the pavement.
A8.4.3 GENERAL
Where both planing and screeding are specified, the screed shall only be placed after the planing has been completed.
When asphalt is specified for rut filling or screeding, longitudinal keys shall be cut in accordance with the Contract Documentation.
The existing surface shall be swept clean or cleaned by other approved methods to be free from dust, soil, gravel, loose stones or any other
undesirable materials. If required, due to brittleness and permeability of the existing surface, a fog spray in accordance with Section A8.2 shall be
applied as pre-treatment.
The bituminous material used for the screed shall be asphalt, coarse slurry or microsurfacing as specified in the Contract Documentation.
The design of asphalt shall be in accordance with TRH8, and the coarse slurry and microsurfacings in accordance with SABITA Manual 28 and
shall be submitted to the Engineer for approval.
A8.4.5 MATERIALS
Materials and references to requirements are as follows:
Table A8.4.5-1: Specifications for rut and depression correction materials
Component Binder Aggregate
Asphalt materials: Refer to Chapter 9 As specified As specified
Coarse slurry Clause A10.1.5.4 in Chapter 10 Clause A10.1.5.17 a) in Chapter 10 for Type 1 or Type 2
Microsurfacing Clause A10.1.5.5 in Chapter 10 Clause A10.1.5.18 in Chapter 10 for Type 2 or Type 3
A8.4.7.2 Microsurfacing
The mixing and application of the microsurfacing shall be done by a mixer designed to provide a rapid mixing time, and sufficient agitation within
the spreading system to prevent segregation or premature hardening.
The appropriate workability measured by the flow (Consistency test: ASTM 3910) shall be verified during the first application and recorded as part
of a method statement.
CONTENTS
B8.4.1 SCOPE
B8.4.2 DEFINITIONS
B8.4.3 GENERAL
B8.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.4.5 MATERIALS
B8.4.6 CONSTRUCTION EQUIPMENT
B8.4.7 EXECUTION OF THE WORKS
B8.4.8 WORKMANSHIP
B8.4.1 SCOPE
A large proportion of activities as defined in Part A under the various sections are considered labour intensive. Therefore, Part B only provides
additional specifications, not contained in Part A.
B8.4.2 DEFINITIONS
Definitions as provided in Clause A8.4.2 shall apply.
B8.4.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B8.4.5 MATERIALS
The provisions of Part A shall apply.
B8.4.8 WORKMANSHIP
The provisions of Part A shall apply.
C8.4.1.1 Bond coat using 50 % diluted stable grade bitumen emulsion litre (ℓ)
(a) Continuously-graded asphalt (State Nominal maximum aggregate size and binder type) ton (t)
(b) Semi-gap graded asphalt (State Nominal maximum aggregate size and binder type) ton (t)
(c) Cold applied asphalt (Agrèment SA certified for specific class as specified) ton (t)
(d) Coarse slurry (state aggregate grade and emulsion type) cubic metre (m³)
(e) Microsurfacing (state aggregate grade and binder type) cubic metre (m³)
The unit of measurement for the bond coat shall be the litre of emulsion applied, measured at spraying temperature. The unit of measurement for
asphalt shall be the ton of asphalt placed according to the specifications.
The of measurement for slurry and microsurfacing shall be the cubic metre of saturated fine aggregate used, measured as described in item
C10.1.20 of Chapter 10.
The tendered rate for asphalt shall include full compensation for procuring, furnishing and mixing all the materials, for placing the asphalt and for all
transport and other incidentals necessary for completing the work as specified.
The tendered rate for slurry and microsurfacing shall include full compensation for all materials, equipment and labour for producing and applying
the slurry, irrespective of the number of applications required to attain the required thickness.
CONTENTS
D8.4.1 SCOPE
D8.4.2 GENERAL
D8.4.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.4.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.4.5 VISUALLY ASSESSED PROPERTIES
D8.4.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.4.7 EVALUATION FOR ACCEPTANCE
D8.4.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.4.9 NOTIFICATION OF REMEDIAL WORK
D8.4.10 REMEDIAL WORK
D8.4.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapters 9
and Chapter 10 shall apply.
D8.4.2 GENERAL
Not applicable to pretreatment works.
CONTENTS
PART A: SPECIFICATIONS
A8.5.1 SCOPE
A8.5.2 DEFINITIONS
A8.5.3 GENERAL
A8.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A8.5.5 MATERIALS
A8.5.6 CONSTRUCTION EQUIPMENT
A8.5.7 EXECUTION OF THE WORKS
A8.5.8 WORKMANSHIP
A8.5.2 DEFINITIONS
Standard crack sealing - refers to the sealing of singular line cracks, such as longitudinal cracks, transvers cracks and large block cracks, using
cold or hot modified binders.
A8.5.3 GENERAL
The types of cracks to be treated shall be specified in the Contract Documentation. The Engineer shall instruct the Contractor regarding the type of
treatment to be used in the various cases.
A8.5.5.2 Bitumen
a) Primer for sealing cracks
The primer shall be an invert bitumen emulsion complying with SANS 4001 – BT5.
b) Modified binder crack sealant
The classification of modified binders for crack sealing, minimum required properties and requirements for short term handing and application,
shall be in accordance with the latest publication of TG1.
The binders to be used for the sealing of cracks shall be C-E1, CC-E1, C-R1 or C-R2 modified binder crack sealants as listed in the Pricing
Schedule.
c) Aggregate
Where so instructed, blinding material shall consist of crusher sand or river sand, with 100 % passing the 7,1 mm sieve and not more than 10 %
passing the 2,0 mm sieve. The aggregate shall be clean, hard and free from excessive dust and shall contain no clay, loam or other deleterious
matter.
A8.5.8 WORKMANSHIP
The Contractor shall ensure that the injected prime and sealant mixture actually penetrates the crack and does not merely cover the crack in the
form of a bandage. All excess sealant on the road surface wider than 30 mm on each side of the crack shall be removed and shall not be paid for.
CONTENTS
B8.5.1 SCOPE
B8.5.2 DEFINITIONS
B8.5.3 GENERAL
B8.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.5.5 MATERIALS
B8.5.6 CONSTRUCTION EQUIPMENT
B8.5.7 EXECUTION OF THE WORKS
B8.5.8 WORKMANSHIP
B8.5.1 SCOPE
A large proportion of activities as defined in Part A under the various sections are considered labour intensive. Therefore, Part B only provides
additional specifications, not contained in Part A.
B8.5.2 DEFINITIONS
Definitions as provided in Clause A8.5.2 apply.
B8.5.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B8.5.5 MATERIALS
The provisions of Part A shall apply.
B8.5.8 WORKMANSHIP
The provisions of Part A shall apply.
The tendered rates shall include full compensation for treating the crack as specified
Where cracks must be heated and/or rolled, the unit of measurement shall be a metre of crack heated/rolled.
CONTENTS
D8.5.1 SCOPE
D8.5.2 GENERAL
D8.5.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.5.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.5.5 VISUALLY ASSESSED PROPERTIES
D8.5.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.5.7 EVALUATION FOR ACCEPTANCE
D8.5.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.5.9 NOTIFICATION OF REMEDIAL WORK
D8.5.10 REMEDIAL WORK
D8.5.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapters 9
and Chapter 10 shall apply.
D8.5.2 GENERAL
Not applicable to pretreatment works.
CONTENTS
PART A: SPECIFICATIONS
A8.6.1 SCOPE
A8.6.2 DEFINITIONS
A8.6.3 GENERAL
A8.6.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A8.6.5 MATERIALS
A8.6.6 CONSTRUCTION EQUIPMENT
A8.6.7 EXECUTION OF THE WORKS
A8.6.8 WORKMANSHIP
A8.6.2 DEFINITIONS
Geosynthetic crack sealing - refers to the application of emulsion and a geosynthetic fabric over a cracked area, with or without a sand blinding
layer.
A8.6.3 GENERAL
The types of cracks to be treated with geosynthetic shall be specified in the Contract Documentation. The Engineer shall instruct the Contractor
regarding the degree (width) and types of cracks to be treated.
A8.6.5 MATERIALS
A8.6.5.1 Bituminous binder
The bituminous binder shall be one of the following listed in Table A8.6.5-1, and as prescribed in the Contract Documentation:
Table A8.6.5-1: Bituminous binder for geosynthetic crack sealing
Bituminous binder for geosynthetic crack sealing Specification
Cationic bitumen emulsion (solvents omitted) SANS 4001 – BT4
SC-E1(t) - (solvents omitted) TG1
Other appropriate product Certified by independent certification agency
A8.6.5.3 Aggregate
Aggregate shall comply with Clause A10.1.5.12 of Chapter 10 for sand seals.
A8.6.8 WORKMANSHIP
The geosynthetic patch shall have a neat appearance without excess binder extending further than 30 mm from the geosynthetic patch edge.
CONTENTS
B8.6.1 SCOPE
B8.6.2 DEFINITIONS
B8.6.3 GENERAL
B8.6.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.6.5 MATERIALS
B8.6.6 CONSTRUCTION EQUIPMENT
B8.6.7 EXECUTION OF THE WORKS
B8.6.8 WORKMANSHIP
B8.6.1 SCOPE
A large proportion of activities as defined in Part A under the various sections are considered labour intensive. Therefore, Part B only provides
additional specifications, not contained in Part A.
B8.6.2 DEFINITIONS
Definitions as provided in Clause A8.6.2 apply.
B8.6.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B8.6.5 MATERIALS
The provisions of Part A shall apply.
B8.6.8 WORKMANSHIP
The provisions of Part A shall apply.
C8.6.1.1 Sealing cracks with 200 mm wide geosynthetic (specify type of emulsion) metre (m)
C8.6.1.2 Sealing cracks with geosynthetic over areas (specify type of emulsion) square metre (m²)
The unit of measurement for the 200 mm wide geosynthetic shall be the linear metre crack sealed with the geosynthetic as specified in Clause
A8.6.5.2.
The unit of measurement for the area geosynthetic crack sealing shall be the square metre crack sealed with the geosynthetic as specified.
The tendered rate shall include full compensation for procuring and supplying all materials, labour, transport and other incidentals required to
complete the work in accordance with the specifications.
CONTENTS
D8.6.1 SCOPE
D8.6.2 GENERAL
D8.6.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.6.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.6.5 VISUALLY ASSESSED PROPERTIES
D8.6.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.6.7 EVALUATION FOR ACCEPTANCE
D8.6.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.6.9 NOTIFICATION OF REMEDIAL WORK
D8.6.10 REMEDIAL WORK
D8.6.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapters 9
and Chapter 10 shall apply.
D8.6.2 GENERAL
Not applicable to pretreatment works.
A8.7 PLANING
PART A: SPECIFICATIONS
A8.7.1 SCOPE
This Section covers the work in connection with planing before resurfacing.
A8.7.2 DEFINITIONS
Planing in the context of this Chapter refers to level correction where the road surface is uneven and where depressions, humps or small grooves
occur as a result of deformation of the pavement layers not due to structural failure of the pavement or the removal or surface irregularities through
precision milling to a specified depth, to obtain a clean and regular running surface.
A8.7.3 GENERAL
The work involves the planing down of high spots or ridges in the existing bituminous surfacing in accordance with the specified level or thickness
requirements.
A8.7.5 MATERIALS
The bituminous binder for the fog spray, where so specified, shall be anionic bitumen emulsion complying with SANS 4001 – BT3 diluted in
accordance with best practice guidelines.
A8.7.8 WORKMANSHIP
The planed surface shall be even without any ridges or steps between the longitudinal cuts. Where planning is required over only a portion of the
road width, the edge of the planned section shall be vertical and straight.
Upon completion, the entire treated surface shall be tested for levelness and unless otherwise specified in the Contract Documentation, the surface
shall not deviate by more than 5,0 mm from the bottom edge of the 3,0 m straight-edge placed in any direction.
CONTENTS
B8.7.1 SCOPE
B8.7.2 DEFINITIONS
B8.7.3 GENERAL
B8.7.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.7.5 MATERIALS
B8.7.6 CONSTRUCTION EQUIPMENT
B8.7.7 EXECUTION OF THE WORKS
B8.7.8 WORKMANSHIP
B8.7.1 SCOPE
Except for application of the fog spray, if required, this activity is not suitable for labour enhanced work.
B8.7.2 DEFINITIONS
Definitions as provided in Clause A8.7.2 apply.
B8.7.3 GENERAL
Application of the fog spray shall be executed in such a way as to maximise labour.
B8.7.5 MATERIALS
The provisions of Part A shall apply.
B8.7.8 WORKMANSHIP
The provisions of Part A shall apply.
C8.7.1 Planing
C8.7.1.1 Planing of road surface (Indicate thickness in mm) square metre (m²)
CONTENTS
D8.7.1 SCOPE
D8.7.2 GENERAL
D8.7.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.7.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.7.5 VISUALLY ASSESSED PROPERTIES
D8.7.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.7.7 EVALUATION FOR ACCEPTANCE
D8.7.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.7.9 NOTIFICATION OF REMEDIAL WORK
D8.7.10 REMEDIAL WORK
D8.7.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapters 9
and Chapter 10 shall apply.
D8.7.2 GENERAL
Not applicable to pretreatment works.
CONTENTS
PART A: SPECIFICATIONS
A8.8.1 SCOPE
A8.8.2 DEFINITIONS
A8.8.3 GENERAL
A8.8.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A8.8.5 MATERIALS
A8.8.6 CONSTRUCTION EQUIPMENT
A8.8.7 EXECUTION OF THE WORKS
A8.8.8 WORKMANSHIP
A8.8.2 DEFINITIONS
Structural patching - involves excavating existing failed areas and reconstructing the pavement layers, with specified pavement material.
Surfacing patching - involves the repair of only the failed surfacing layer (seal or asphalt) exposing but not affecting the underlying layer.
Edgebreak repair - involves repairing the edges of the paved area so that it lines up with the true edge of the original road or with such other edge
as may be required. Work could include excavation of pavement layers and backfilling with suitable material and if specified, sealing the joint with
a geosynthetic strip. Any excavation and backfilling extending into the wheel path shall be measured under patching.
A8.8.3 GENERAL
This Section covers the patching of existing pavement layers and surfacing, as well as repairing of edge breaks, prior to any resealing or
resurfacing. Extra overcompensation for work in restricted areas shall not be applicable to any patching and repairing edge breaks.
A8.8.5 MATERIALS
A8.8.5.1 Herbicide
Herbicide shall be a non-selective herbicide.
A8.8.8 WORKMANSHIP
A8.8.8.1 Tolerances
The backfilling shall be compacted to the appropriate thickness, density and level per layer specified in other relevant sections of this document or as
specified in the Contract Documentation.
The final riding surface on any particular point on patches and repaired edge-breaks shall not deviate more than 5,0 mm from the bottom of a 3,0
m long straight edge.
Edge repairs shall be true to line with a maximum deviation of 20 mm from the specified edge line.
A8.8.8.2 Testing
The Engineer shall carry out routine inspections and conduct routine tests to determine whether the quality of material and workmanship provided
comply with the requirements as specified in this Section. Any test results and measurements shall be assessed in accordance with the provisions
of Chapter 20, as applicable.
CONTENTS
B8.8.1 SCOPE
B8.8.2 DEFINITIONS
B8.8.3 GENERAL
B8.8.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.8.5 MATERIALS
B8.8.6 CONSTRUCTION EQUIPMENT
B8.8.7 EXECUTION OF THE WORKS
B8.8.8 WORKMANSHIP
B8.8.1 SCOPE
A large proportion of activities as defined in Part A under the various sections are considered labour intensive. Therefore, Part B only provides
additional specifications, not contained in Part A.
B8.8.2 DEFINITIONS
Definitions as provided in Clause A8.8.2 apply.
B8.8.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B8.8.5 MATERIALS
The provisions of Part A shall apply.
B8.8.8 WORKMANSHIP
The provisions of Part A shall apply.
Milling (where specified in the Contract Documentation) C8.8.2 C4.3.6 or C4.3.7 of Chapter 4
The unit of measurement shall be the metre of sawcut. The length in each depth range shall be measured and paid separately.
The tendered rate shall include full compensation for all plant, equipment, labour, supervision, materials, transport and for all incidentals for
sawing the asphalt and the cemented pavement layers, complete as specified and prescribed by the Engineer, and also for work in restricted
areas. The rate shall also include for any haul to an approved spoil site if so required.
Item Description Unit
(a) Not exceeding 10 m2 including for edge repairs wider than 250 mm cubic metre (m³)
(b) Exceeding 10 m² but not exceeding 50 m² including for edge repairs wider than 250 mm cubic metre (m³)
(c) Exceeding 50 m² up to 100 m² including for edge repairs wider than 250 mm cubic metre (m³)
C8.8.3 Compacting the floor of excavations for patching (specify density) square metre (m²)
The unit of measurement shall be a square metre of excavation floor compacted on the instruction of the Engineer, and the quantity shall be
computed in accordance with the authorized dimensions of the excavation floor.
The tendered rate shall include full compensation for compacting the floor of excavations complete as specified, and also for work in restricted
areas. Payment shall not distinguish between the various methods of compaction or various compaction requirements.
Item Description Unit
(b) Exceeding 10 m² but not exceeding 50 m² including for edge repairs wider than 250 mm cubic metre (m³)
(b) Exceeding 10 m² but not exceeding 50 m² including for edge repairs wider than 250 mm cubic metre (m³)
(c) Exceeding 50 m² up to 100 m² including for edge repairs wider than 250 mm cubic metre (m³)
C8.8.4.3 Asphalt for a patch with a surface area (state type and density)
(a) Not exceeding 10 m2 including for edge repairs wider than 250 mm ton (t)
(b) Exceeding 10 m² but not exceeding 50 m² including for edge repairs wider than 250 mm ton (t)
(c) Exceeding 50 m² up to 100 m² including for edge repairs wider than 250 mm ton (t)
C8.8.4.4 Granular base material (state type and density) for a patch with a surface area
(a) Not exceeding 10 m2 including for edge repairs wider than 250 mm ton (t)
(b) Exceeding 10 m² but not exceeding 50 m² including for edge repairs wider than 250 mm ton (t)
(c) Exceeding 50 m² up to 100 m² including for edge repairs wider than 250 mm ton (t)
The tendered rates shall include full compensation for design of backfill material, providing all the material, irrespective of its origin, including gravel,
for all mixing, placing, compacting and finishing as specified in this Section and other appropriate Sections of the specifications, for all transport,
work in restricted areas, and also for all machinery, equipment, labour, supervision and other incidentals for executing the work as specified.
The tendered rate shall also include full compensation for the provision and application of the stabilisation agents.
Item Description Unit
C8.8.5 Geosynthetic patching
C8.8.5.1 Sealing joints with geosynthetic strips (specify width and type of emulsion) metre (m)
The tendered rate shall also include full compensation for cleaning of the road surface, supply and application of the geosynthetic strips on the
emulsion. The geosynthetic strips shall be as specified in Section A12.11 of Chapter 12.
C8.8.6.1 Cutting back the edges of the existing surfacing for the repairing of edge breaks metre (m)
C8.8.6.2 Prime coat (state type and rate of application) litre (ℓ)
(a) Continuously-graded hot asphalt (state type and density) ton (t)
(b) Continuously-graded cold asphalt (Agrèment SA certified -state class and density) ton (t)
(c) Bitumen Stabilised Material (state type and level of compaction) cubic metre (m³)
Item C8.8.6 shall apply only to edge breaks with an average width of 250 mm and less. Repairing wider edge breaks shall be classified as
patching.
The unit of measurement for cutting back the edges shall be a metre of pavement edge cut back and excavated as specified.
The tendered rate for cutting back the edges shall include full compensation for cutting back the edges in accordance with instructions,
excavating the material to the specified depth, removing all excavated and loose material to spoil, and compacting the surface onto which the
fresh edge shall be constructed, all in accordance with the required lines and levels.
The tendered rates shall also include full compensation for all transport, handling, labour, material, and all incidentals necessary for completing
all the work.
CONTENTS
D8.8.1 SCOPE
D8.8.2 GENERAL
D8.8.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.8.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.8.5 VISUALLY ASSESSED PROPERTIES
D8.8.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.8.7 EVALUATION FOR ACCEPTANCE
D8.8.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.8.9 NOTIFICATION OF REMEDIAL WORK
D8.8.10 REMEDIAL WORK
D8.8.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapters 9
and Chapter 10 shall apply.
D8.8.2 GENERAL
Not applicable to pretreatment works.
CONTENTS
PART A: SPECIFICATIONS
A8.9.1 SCOPE
A8.9.2 DEFINITIONS
A8.9.3 GENERAL
A8.9.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A8.9.5 MATERIALS
A8.9.6 CONSTRUCTION EQUIPMENT
A8.9.7 EXECUTION OF THE WORKS
A8.9.8 WORKMANSHIP
A8.9.2 DEFINITIONS
Repair of surface defects - deals specifically with repair of early bleeding areas and/or aggregate loss during the Defect Notification Period as
defined in the conditions of contract.
Repair of surfacing failures (typically delamination) is dealt with under patching in Section A8.8.
Bleeding - occurs when excess binder moves upwards relative to the aggregate and reduces the surface texture depth
Aggregate loss (ravelling) - is the loss of surfacing aggregate
A8.9.3 GENERAL
When surface defects occur within the maintenance period, the Contractor shall search and find the cause and mechanism of distress, propose
and submit an appropriate repair method, in accordance with current good practice or specifications provided in this section, to the Engineer for
approval. The proposed method/s shall include a detailed method statement, materials, construction equipment, traffic accommodation and quality
plan.
Aggregate loss of Degree 2 or more and bleeding of Degree 3 and more according to the latest revision of TMH9 Part B, occurring within the
defects liability period, as prescribed in the General Conditions of Contract, shall be repaired.
Sections of the road where severe loss of aggregate (Degree 3 or more), or bleeding (Degree 4 or 5) have occurred shall be closed to traffic by
means of the statutory required road signs.
In case of aggregate loss, all loose stones shall be removed from the road surface and disposed of at an approved spoil site. The Contractor shall
make sure that all the remaining aggregate is satisfactorily embedded into the road surface.
This work shall be effected as soon as possible after the distress occurs. However, the Contractor may not commence with the repair work without
the Engineer’s approval.
Notwithstanding the proposed method/s of treatment, the Engineer may order any seal which has not been properly constructed to be removed
and replaced. The removal of the seal shall be done so as not to damage the existing substrate. All aggregate and binder shall be removed either
by grader or by hand tools and disposed of at an approved spoil site. Any damage done to the substrate surface shall be repaired to the satisfaction
of the Engineer.
A8.9.5 MATERIALS
Materials proposed and used for repair shall be appropriate materials complying with relevant referenced specifications in this document.
CONTENTS
B8.9.1 SCOPE
B8.9.2 DEFINITIONS
B8.9.3 GENERAL
B8.9.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B8.9.5 MATERIALS
B8.9.6 CONSTRUCTION EQUIPMENT
B8.9.7 EXECUTION OF THE WORKS
B8.9.8 WORKMANSHIP
B8.9.1 SCOPE
A large proportion of activities as defined in Part A under the various sections are considered labour intensive. Therefore, Part B only provides
additional specifications, not contained in Part A.
B8.9.2 DEFINITIONS
Definitions as provided in Clause A8.9.2 apply.
B8.9.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to maximise labour.
B8.9.5 MATERIALS
The provisions of Part A shall apply.
B8.9.8 WORKMANSHIP
The provisions of Part A shall apply.
C8.9.1.1 Establishing of heating apparatus on site for softening of the road surface lump sum
The unit of measurement for the heating of the road surface is the square metre heated as specified.
Except for the provision of heating apparatus, the tendered rate for heating the road surface shall include full compensation for all equipment,
materials and labour needed for the heating of the road surface, all in accordance with the specifications.
C8.9.2.2 Precoating of aggregate (state type and application litre/m3) cubic metre (m³)
The unit of measurement for the provision of aggregate shall be the cubic metre of aggregate as specified.
The tendered rate shall include full compensation for furnishing the aggregate, for precoating it, if required, with a bitumen based precoating fluid,
including the furnishing of the precoating fluid, and for heating it to the specified temperature, all in accordance with the specifications and
instructions of the Engineer.
The unit of measurement for the application and rolling in of the aggregate shall be the square metre of road treated in accordance with the
specifications and instructions of the Engineer.
The tendered rate shall include full compensation for cleaning the existing road surface, for the application of the aggregate, irrespective of the size,
with an approved chip spreader to the specified rate, for rolling in the aggregate as specified, for brooming off excessive aggregate as and when
C8.9.4 Trial sections for heating, application and rolling in of heated aggregate square metre (m²)
The unit of measurement shall be the square metre of trial section constructed as ordered.
The tendered rate shall include full compensation for the construction of the trial section as instructed. It shall only be paid more than once if it is
unsuccessful and the Contractor has executed all work according to the specifications and instructions.
The unit of measurement for the water cutting of the road surface is the square metre of road treated in accordance with the specifications and
instructions of the Engineer.
Except for the provision of water cutting equipment, the tendered rate for water cutting of the road surface shall include full compensation for all
equipment, materials and labour needed for water cutting of the road surface, including removal of material generated to an approved spoil site, all
in accordance with the specifications.
The tendered rate shall include full compensation for a trial section as instructed. It shall only be paid more than once if it is unsuccessful and the
Contractor has executed all work according to the specifications and instructions.
CONTENTS
D8.9.1 SCOPE
D8.9.2 GENERAL
D8.9.3 PERFORMANCE GUARANTEE REQUIREMENTS
D8.9.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D8.9.5 VISUALLY ASSESSED PROPERTIES
D8.9.6 INSTRUMENTALLY ASSESSED PROPERTIES
D8.9.7 EVALUATION FOR ACCEPTANCE
D8.9.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D8.9.9 NOTIFICATION OF REMEDIAL WORK
D8.9.10 REMEDIAL WORK
D8.9.1 SCOPE
Pretreatment and repair of existing layers form an integral part of the final surfacing. Therefore, the relevant requirements of Part D in Chapters 9
and Chapter 10 shall apply.
D8.9.2 GENERAL
Not applicable to pretreatment works.
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 9: ASPHALT LAYERS............................................................................................................................9-1
9.1 ASPHALT LAYERS ............................................................................................................................................9-1
PART A: SPECIFICATIONS .............................................................................................................................................................................. 9-1
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................... 9-20
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 9-22
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ...................................................................................................................... 9-28
CHAPTER 9: ASPHALT LAYERS
9.1 ASPHALT LAYERS
CONTENTS
PART A: SPECIFICATIONS
A9.1.1 SCOPE
A9.1.2 DEFINITIONS
A9.1.3 GENERAL
A9.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A9.1.5 MATERIALS
A9.1.6 CONSTRUCTION EQUIPMENT
A9.1.7 EXECUTION OF THE WORKS
A9.1.8 WORKMANSHIP
A9.1.2 DEFINITIONS
Asphalt mix types - a mixture of aggregate, with or without active filler, and an appropriate bituminous binder proportioned in such a manner as
to produce a final product conforming to all the relevant mix, and or, performance properties as specified. Asphalt mixes are classified into two
fundamental mix types and may incorporate either standard, homogenous modified or non-homogenous (bitumen-rubber) bitumen.
a) Sand skeletal mixes - where the loads on the layer are carried by a continuous matrix of the finer aggregate fraction. There is no
meaningful contact between the individual coarse aggregate particles and only provide bulk while not compromising the continuity of
the finer fraction. Examples include:
- Semi-gap graded asphalt (AS), as further defined in Sabita Manual 35; Design and Use of Asphalt in Road Pavements
- Gap-graded asphalt (AG), as further defined in Sabita Manual 35; Design and Use of Asphalt in Road Pavements
- Fine/medium continuously graded asphalt mixes (AC), as further defined in Sabita Manual 35; Design and Use of Asphalt in Road
Pavements
- Bitumen-rubber gap-graded (BRAGG), as further defined in Sabita Manual 19; Guidelines for the design, manufacture and
construction of bitumen rubber asphalt wearing courses
- Course aggregate – all aggregate > 5,0 mm as further defined in the latest SANS 1083 specification for the specific class of aggregate
and nominal maximum particle size as specified.
- Nominal maximum particle size (NMPS) – designated as one sieve size larger than the largest sieve to retain a minimum of 15
percent of the aggregate particles as defined in SANS 1083.
- Fine aggregate – all aggregate fractions ≤ 5,0 mm > 0,075 mm and which may consist of clean material derived from crushing
competent parent rock, or naturally occurring sand conforming to good practice and any further specified requirements.
- Filler – material predominantly < 0,075 mm which may consist of natural rock flour, extracted bag-house fines, or a manufactured active
filler such as hydrated lime or cement.
- Reclaimed asphalt (RA) – asphalt that has been appropriately milled off existing pavement layers, as well as asphalt discarded at the
mixing plant that is crushed, screened and tested in accordance with the requirements contained in the latest version of TRH 21: Use
of Reclaimed Asphalt in the Production of Asphalt.
Bitumen - a black viscous mixture of hydrocarbons obtained as a residue from crude oil distillation and processed according to specific grade
requirements.
Cellulose fibre - a constituent, either loose or in pellet form, introduced at manufacturing stage to prevent drain-down of the binder during storage,
transporting and placing of mixes such as Stone Mix Asphalt (SMA).
Bond coat - an appropriate bituminous product applied to an existing surface, (prime, spray seal, asphalt, or concrete pavement surface), in order
to ensure adequate bonding with the underlying substrate layer.
Prime coat - an appropriate low viscosity bituminous product applied in a single application for the purposes of sealing and protecting the surface
of granular or cemented base layers. The general requirements relevant to these products are covered in Chapter 8 of this document.
A9.1.3 GENERAL
A9.1.3.1 Nominal mix proportions and application rates
a) Mix composition. The mix proportions of bituminous binder, combined aggregates and filler for the various mix types, as well as bond coat
and rolled-in chip applications, as listed in Tables A9.1.3-1 to A9.1.3-3 below, are nominal, and shall only be used for tendering purposes.
The proportions actually used shall be as determined during the mix design, trial section and assessment requirements as specified in Clause
A9.1.3.3. Any approved variation to these nominal mix proportions, and or, application rates shall be subject to an adjustment in payment,
calculated in accordance with Clause C1.1.4 of Chapter 1 and relevant to the applicable variation rates tendered for each component as
listed under Measurement and Payment.
Cellulose fibre (%) N/A N/A N/A N/A N/A 0,5 0,5 N/A N/A N/A N/A
• The moisture content of the aggregate affects the uniformity of mix temperature
• Free water is present on the working surface, or if
• The moisture content of the upper 50 mm of a granular base layer exceeds 50 % of the optimum moisture content, as determined by the
Engineer.
Immediately after a rainy spell on an existing partly cracked and/or highly permeable surfacing and/or primed base resulting in the trapping of
moisture in the pavement structure. In such case the base shall be allowed to dry out to meet the above moisture content requirements prior to
placing the asphalt layer.
A9.1.5 MATERIALS
A9.1.5.1 General
The Contractor shall, as often as necessary, and in accordance with his approved quality plan, test and control the materials produced by himself,
or any materials received by him from suppliers, to ensure that the materials are uniform and always comply with the specified requirements.
Refer to the latest version of Sabita Manual 5: Guidelines for the manufacture and construction of hot mix asphalt.
Sufficient aggregate and bituminous binder for a minimum of 3 days production shall be separately stockpiled/stored and tested for conformance
and uniformity prior to use. The test results shall be made available to the Engineer on request.
A9.1.5.4 Aggregates
a) Aggregate properties
Aggregate shall consist of hard material derived from the crushing of solid rock or boulders. Coarse and fine aggregate shall be clean and free
from decomposed materials, vegetable matter or any other deleterious substances, and shall meet the requirements listed in Table A9.1.5-1 below
unless otherwise specifically stated in the Contract Documentation. All aggregates shall be handled and stockpiled in a manner that will prevent
contamination, segregation or degradation.
Asphalt mixes shall be manufactured using individual single size coarse aggregates fractions and crushed fine aggregates complying with the
latest version of SANS 1083 and appropriately blended to conform to the target grading as determined by the selected design methodology. The
use of natural sands shall only be permitted if approved by the Engineer and shall be limited to a maximum of 7 % by mass for continuously
graded mixes. For stone mastic asphalt mixes all aggregate fractions in excess of 2,0 mm shall consist of individual nominal single size fractions.
Polished stone value (PSV) SANS 3001–AG11 Coarse aggregate for surfacing ≥ 50*2
Particle shape and Sand skeletal mixes At least 50 % of all particles
texture should have three fractured
faces
Fractured faces ASTM 5821 Stone skeletal mixes and At least 95 % of all particles
rolled in chippings should have 3 fractured faces
7,1 20 25
10 30 35
14 45 50
20 80 90
28 110 120
Once the target grading has been fixed for each individual coarse aggregate fraction, the allowable tolerances shall not exceed 10 % of that
agreed for the target grading for each specific nominal maximum aggregate particle size. The Contractor shall note that commercial suppliers may
not be able to consistently supply all the required nominal single size aggregate to the specified tolerances. In such instances additional on-site
screening may be necessary, for which no additional payment shall be made. The use of run of crusher type materials shall not be permitted.
c) Fine aggregate grading
If approved by the Engineer, and if the specified mix properties are met, the fine aggregate component may contain natural fines not obtained
from the parent rock being crushed, on condition that such added material does not exceed 7,0 % by mass, unless otherwise specified in the
Contract Documentation. The added fines shall have a liquid limit not exceeding 25 % and a PI not exceeding 4. The Contractor shall submit full
details regarding the exact quantity and nature of such fine aggregate, before such permission will be considered. In the event of such added
material being natural sand, its impact on final mix properties shall be assessed from laboratory briquettes and cores obtained in the trial section.
The addition of natural fines shall only be by means of a separate plant cold-feed bin.
Table A9.1.5-4: Fine aggregate grading limits for relevant mix type
Grading Grade 1 Grade 2 Stockpile
Grade Tolerance
Percentage passing by mass
Sieve Size Class 1 Class 2
(mm) Percent Passing Percent Passing
When determined in accordance with SANS 3001-AG1, the Fineness Modulus (FM) of both the crushed and natural fine aggregates shall not
deviate by greater than 0,2 from that determined on the fine aggregate incorporated in the approved design mix.
The grading control points shown in Table A9.1.5-5 shall be considered as a guideline only and not a specification grading envelope.
Where the use of reclaimed asphalt has been prescribed, the reclaimed asphalt shall be crushed, screened, stockpiled, protected, tested and
utilised in accordance with the requirements contained in the latest version of Sabita Manual 36: Use of Reclaimed Asphalt in the Production of
Asphalt.
For open and gap graded mixes the proposed grading for the combined aggregate in the mix shall be as specified in the Contract Documentation
or if not specified, then the guidelines in Manual 35 and the applicable Sabita Manuals shall apply, e.g. Manual 17 for open graded mixes, Manual
19 for bitumen rubber mixes and Manual 33 for EME. Stone skeletal mixes and SMA shall follow the guidelines in Manual 35.
The grading of the combined aggregate, including any filler added, in an accepted mix design shall be designated as the target grading. Allowable
tolerances from such an approved target grading during production shall be as specified in Clause A9.1.8.5.
e) Rolled in chippings grading
The grading requirements for rolled in chippings shall be as listed in Table A9.1.5-6.
Table A9.1.5-6: Grading limits for rolled-in chippings
Percentage passing sieve size by mass by
mass
Sieve size (mm)
20,0 mm 14,0 mm 10,0 mm
-
20,0 100 -
14,0 0 – 20 100
100
10,0 0–5 0 – 20
A9.1.5.5 Fillers
Should the grading of the combined aggregates for asphalt mixes show a deficiency in fines, an approved filler may be used to improve the
grading. With the exception of stone mastic asphalt, in no instance shall more than 2 % by mass of active filler be used in a mix. Inert filler such
as rock dust used to improve a grading shall not be subject to this limitation. No payment will be made for any filler added to improve the grading.
The Engineer may order the use of any active filler to improve the adhesion properties of the aggregate. Active filler shall consist of hydrated
70 minimum
Active filler: Grading: % passing 0,075 mm 0,5 – 0,9 g/ml
Hydrated lime Bulk density in toluene 0,3 – 0,5 % SANS 3001-AG1
Portland cement Voids in compacted filler 5 maximum BS 812
Methylene blue test BS 812
SANS 6243
A9.1.5.6 Fibres
A nominal cellulose fibre content has been allowed for in stone mastic mixes. The Contractor shall prove that the fibre he intends using has the
proven ability to prevent any drain down of the bitumen in the mix during transportation and placing without compromising the in-place mix
properties.
A9.1.6.3 Paver
The mixture shall be laid by an approved type of self-propelled mechanical spreader and finisher fitted with automatic electronic screeds, capable
of paving to the required widths, thickness, profile, camber or cross-fall without causing segregation, dragging, tearing, or other surface defects.
Where leveling beams on multiple skids or sliding beams are used they shall be at least 12,0 m long, or as specified in the Contract Documentation.
A9.1.6.5 Rollers
Compaction shall be done by means of approved flat steel-wheeled, vibratory or pneumatic-tyre rollers. The frequency as well as the amplitude
of vibratory rollers shall be adjustable. Vibratory rollers shall be used only where there is no danger of damage being done to the asphalt, and to
the smoothness of the layer, bridge decks, or other layers. It will be indicated in the Contract Documentation whether any vibratory compaction
equipment may be used on bridge decks, and what the constraining parameters will be. The rollers shall be self-propelled and in good working
condition, free from back lash, and without any oil leaks. Rollers shall be equipped with adjustable scrapers to keep the drums clean and with
efficient, fully functioning means of keeping the wheels wet to prevent mixes from sticking to the rollers. Approved release agents may be used
on roller wheels but the use of petroleum products for this purpose shall not be permitted. The mass and tyre pressures shall be such so as to
ensure compaction complying with the specifications for surface finish and compaction.
The required type, and number, of rollers to be utilized shall be appropriate to the mix type being paved and rate of paving which shall be as
determined during the trial section. The Contractor shall take adequate precautions to eliminate any pick-up of the paved mat. For open-graded
asphalt and/or stone-mastic asphalt, only flat steel-wheeled rollers shall be used.
A9.1.6.7 Vehicles
The asphalt shall be transported from the mixing plant to the spreader in tip trucks that are in good condition having no oil leaks. They shall have
tight, clean smooth beds and sides that have been treated to prevent adhesion of the mixture to the truck bodies. A thin film of soapy water,
vegetable oil or approved release agents may be used to prevent adhesion but petroleum products shall not be used for this purpose. The truck
bins shall be designed to tip asphalt into the paver’s hopper without spillage.
To minimize temperature loss, all vehicles used for transporting asphalt to the site shall be fitted with appropriate bin covers. Where the expected
transport, and or, storage time of the asphalt is expected to exceed one hour in the truck, the use of thermal asphalt covers (canvas covers not
acceptable) shall be obligatory.
A9.1.7.7 Compaction
The compaction requirements for each mix type shall be in accordance with the requirements listed in the relevant Sabita Manuals as listed in
Clause A9.4.2 for the specific mix type prescribed. The sequence of rollers used in compaction shall be at the discretion of the Contractor provided
that the completed pavement shall meet the required compaction, profile, and surface texture as specified. The paved layer shall be compacted
as soon as possible after it has been laid by a combination of vibratory, static steel-wheeled and or pneumatic-tyre rollers in a sequence determined
and approved during the laying of trial sections. Rolling shall commence, and be continued, only for so long as it is effective and does not have
any detrimental effect.
Only steel-wheel rollers (non-vibratory) shall be permitted for the compaction of stone mastic asphalt as well as semi-open and open-graded
mixtures, although rubber tyre rollers may be on standby if required. During rolling the roller wheels shall be kept moist with only sufficient water
or an approved release agent to avoid picking up the material. The use of petroleum products or excesses of releasing agents (soap) to prevent
pick-up shall not be permitted. The use of vibratory rollers shall not be permitted on bridge decks.
Rolling shall commence from the edges of the paved mat and progress towards the center. On areas of super elevated curves, or where the
cross-fall exceeds 2 %, rolling shall commence on the low side and progress to the higher side, uniformly lapping each preceding track. During
breakdown-rolling the rollers shall move at a slow but uniform speed (not to exceed 5,0 km/h) with the drive roller nearest the paver, unless
otherwise specified on account of steep gradients.
Except for mixtures using warm mix asphalt technology, no movement of the asphalt layer shall occur under steel wheel rollers once the asphalt
temperature has dropped to below 100°C.
For thin layer asphalt (less than 30 mm) the compaction requirements shall be in accordance with the method statement as assessed and approved
in the accepted trial sections.
For open graded (Porous) asphalt the degree of compaction can be controlled indirectly by means of in-situ permeability tests calibrated during
the trial section and by visual evaluation of the aggregate to prevent crushing.
The Contractor shall utilize an appropriate and calibrated nuclear gauge for process control during compaction operations. Notwithstanding this
requirement, the acceptance control carried out to determine compaction shall still be based on cores taken from the compacted layer where the
layer thickness is appropriate.
A9.1.8 WORKMANSHIP
The onus shall be on the Contractor to consistently construct all elements conforming to the specifications and within allowable tolerances. The
Engineer shall continuously monitor the quality and consistency of work produced by means of visual inspection as well as by appropriate testing
and evaluation of results.
Measurement, testing, and evaluation of all individual components and constructed products shall be in accordance with the methods prescribed
in this Chapter or in Chapter 20 as relevant.
In the case of surfacing bridge decks, the difference in level between the new asphalt and any existing adjacent bridge joint or nosing shall not
exceed 3,0 mm
b) Width
The average width of both asphalt base and surfacing shall be at least equal to that shown on the drawings and nowhere shall the outer edge of
the layer be inside the lines shown on the drawings by more than 15 mm for both asphalt base and asphalt surfacing layers.
c) Thickness
The thickness tolerances shall be as listed in Table A9.1.8-2.
Table A9.1.8-2: Thickness Tolerances
Allowable Tolerances Asphalt Base (mm) Asphalt Surfacing (mm)
D 90 15 5
D Maximum 20 8
D Average 5 2
Run2 IRI100m Ave = (100m IRI Left wheel track + 100m IRIRight wheel track ) / 2
Run3 IRI100m Ave = (100m IRI Left wheel track + 100m IRIRight wheel track ) / 2
Average IRI100m = (Run1 IRI 100m Ave + Run2 IRI 100m Ave + Run3 IRI 100m Ave ) / 3
The Average IRI100m values is then evaluated and judged according to Table A9.1.8-3 to determine whether the 100m section needs corrective
work or payment adjustments.
The applicable Full Payment Bracket in Table A9.1.8-1 (Where value = 1.000) for the measured lanes and shoulders will be determined as follows:
Calculate the applicable Target IRI100m Ave for full payment as follows: Target IRI100m Ave = greater of 1.05 or [IRI100m Ave * {1-(NAT/100)}]
Where:
IRIb Ave = Average IRI100m before the construction of the asphalt surfacing as determined from:
The Average IRI100m , as calculated from the network roughness measurements performed by Employer not more than 12 months prior to
commencement of the contract, or
The Average IRI100m as calculated from the measurements performed as part of the assessment of the base as per Clause A5.3.8.5c) of Chapter
5 for granular bases.
NAT = Total New Asphalt Surface Thickness (measured in mm) applied over a section as part of this contract. For example, should 40 mm AC
be applied followed by 18 mm UTFC, then NAT = 58 mm.
1,01 to 1,10 1,000 1,010 1,025 1,050 1,050 1,050 1,050 1,050
1,11 to 1,20 0,990 1,000 1,010 1,025 1,050 1,050 1,050 1,050
1,21 to 1,30 0,975 0,990 1,000 1,010 1,025 1,050 1,050 1,050
1,31 to 1,40 0,955 0,975 0,990 1,000 1,010 1,025 1,050 1,050
1,41 to 1,50 0,930 0,955 0,975 0,990 1,000 1,010 1,025 1,050
1,51 to 1,60 0,900 0,930 0,955 0,975 0,990 1,000 1,010 1,025
1,61 to 1,70 0,865 0,900 0,930 0,955 0,975 0,990 1,000 1,010
1,71 to 1,80 Reject 0,865 0,900 0,930 0,955 0,975 0,990 1,000
1,81 to 1,90 Reject Reject 0,865 0,900 0,930 0,955 0,975 0,990
1,91 to 2,00 Reject Reject Reject 0,865 0,900 0,930 0,955 0,975
2,01 to 2,10 Reject Reject Reject Reject 0,865 0,900 0,930 0,955
2,11 to 2,20 Reject Reject Reject Reject Reject 0,865 0,900 0,930
2,21 to 2,30 Reject Reject Reject Reject Reject Reject 0,865 0,900
2,31 to 2,40 Reject Reject Reject Reject Reject Reject Reject 0,865
> 2,41 Reject Reject Reject Reject Reject Reject Reject Reject
On all road sections and in areas where the use of a profilometer is not possible, the rolling straight-edge, or 3,0 m, specification, as indicated
below, shall apply.
b) Using a rolling straight-edge.
When the number of surface irregularities measured in accordance with Chapter 20 shall not exceed those given below (applicable to base and
surfacing)
(i) Average number of irregularities per 100 m equal to or exceeding the specified value when taken over 300 m – 600 m lengths:
Freeways (3,0 mm irregularities)
Asphalt with rolled-in chippings 5
A9.1.8.5 Grading
The combined aggregate and filler grading during production shall not deviate from the approved target grading by more than the tolerances given
in Table A9.1.8-4. The mean grading of each lot of the working mix (minimum of 6 tests per lot) shall be determined from samples obtained in a
stratified random sampling procedure. Consistent non-conformance to these limits shall require a new design process to be undertaken.
Table A9.1.8-4: Combined aggregate grading tolerances for sand skeleton mixes
Size of aggregate passing Permissible deviation from target grading (%) for NMPS
sieve size (mm)
7.1 mm 10 mm 14 mm 20 mm
28 0 0 0 0
20 0 0 0 ±5
14 0 0 ±5 ±5
10 0 ±5 ±5 ±5
7,1 ±5 ±5 ±5 ±5
5 ±4 ±4 ±4 ±4
2 ±4 ±4 ±4 ±4
1 ±4 ±4 ±4 ±4
0,600 ±4 ±4 ±4 ±4
0,300 ±3 ±3 ±3 ±3
0,150 ±2 ±2 ±2 ±2
0,075 ± 1* ± 1* ± 1* ± 1*
*When Statistical methods are applied the permissible deviation for the 0,075 mm fraction is ± 2 %.
For open and gap graded mixes the permissible deviation from target grading for the combined aggregate in the mix shall be as specified in the
Contract Documentation or if not specified, then the guidelines in Manual 35 and the applicable Sabita Manuals shall apply, e.g. Manual 17 for
open graded mixes, Manual 19 for bitumen rubber mixes and Manual 33 for EME. Stone skeletal mixes and SMA shall follow the guidelines in
Manual 35.
A9.1.8.7 Voids
The void content of the mix shall be within the limits specified in the statistical judgment scheme in Clause A20.1.7.5d) of Chapter 20.
CONTENTS
B9.1.1 SCOPE
B9.1.2 DEFINITIONS
B9.1.3 GENERAL
B9.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B9.1.5 MATERIALS
B9.1.6 CONSTRUCTION EQUIPMENT
B9.1.7 EXECUTION OF THE WORKS
B9.1.8 WORKMANSHIP
B9.1.1 SCOPE
This Section covers the labour enhancement activities associated with the placing of asphalt layers as specified in Part A.
B9.1.2 DEFINITIONS
Definitions as provided in A9.1.2 shall apply.
B9.1.3 GENERAL
Any activity specified in Part A, where hand work is given as an alternative, shall be executed in such a way as to optimise labour.
B9.1.5 MATERIALS
The provisions of Part A shall apply.
B9.1.8 WORKMANSHIP
The provisions of Part A shall apply.
(a) Continuously graded base or surfacing (state binder type and level of design). Lump sum
(b) High modulus asphalt (EME) (state binder type and level of design) Lump sum
(c) Stone Mastic Asphalt (SMA) (state binder type) Lump sum
(d) Ultrathin Friction Courses (UTFC) (state binder type). Lump sum
(f) Bitumen rubber open and gap graded mixes (state mix type) Lump sum
(g) Other – as stated and defined in the Contract Documentation Lump sum
(a) Continuously graded base or surfacing (state binder type and level of design). Lump sum
(b) Semi-gap graded mixes (state binder type and level of design) Lump sum
(c) Gap graded mixes (state binder type and level of design). Lump sum
(e) Other (as stated and defined in the Contract Documentation) Lump sum
The unit of measurement shall be the Lump Sum for the design of each asphalt mix type specified. The design methodology, and or level of
design, shall be as stated in the Contract Documentation. The rate tendered shall include for all costs associated with producing a laboratory as
well as a plant mixed design, verified and accepted by the Engineer after completion of the trial section.
C9.1.2.2 Removal of trial section where so instructed by the Engineer. square metre (m²)
The unit of measurement for C9.1.2.1 shall be the square metre of asphalt placed in an approved trial section constructed for each mix type
specified. The tendered rate shall include for all costs associated with constructing the trial in order for the Engineer to assess the in-place
properties of the layer prior to commencing with permanent works. Assessment of the trial shall be as described in Clause A9.1.3.3. Any additional
trial sections required as a result of the final product not meeting all the specified requirements shall not be subject to additional payment.
The unit of measurement for C.9.1.2.2 shall be the square metre of trial section removed to an approved site and the area reinstated as required.
C9.1.3.1 Stable –grade 30 % net bitumen emulsion as specified. Applied with a calibrated distributer litre (ℓ)
C9.1.3.2 Applied in restricted areas using a portable pressure sprayer litre (ℓ)
C9.1.3.3 Applied by hand using brushes on all exposed transverse and longitudinal construction joints litre (ℓ)
C9.1.3.4 Other: (state type, such as standard, modified emulsion, “trackless”, Agrément certified, or litre (ℓ)
heated if applied for night work)
The unit of measurement shall be the litre of bond coat appropriately applied as specified in Clause A9.1.5.7. The tendered rate shall include full
compensation for procuring and applying the specified bond coat in the relevant applications. Payment for applications in restricted areas shall
only be made when application by means of a calibrated distributer is impractical.
C9.1.4.2 Rehabilitation
(a) Stone skeletal mix – continuously graded as defined (state layer thickness, binder type and ton (t)
design class/ level)
(b) Stone skeletal mix – High Modulus (EME) as defined (state layer thickness, binder type and ton (t)
design class/ level)
(c) Sand skeletal mix – continuously graded as defined (state layer thickness, binder type and ton (t)
design class/ level)
(d) Any of the above mix types where the use of reclaimed asphalt has been specified (indicate ton (t)
maximum % reclaimed asphalt or binder replacement limits)
(e) Certified: any mixes certified for specific applications by an approved agency as being fit for ton (t)
the purpose and as specified in the Contract Documentation.
(c) Stone skeletal mix - open graded as defined (state layer thickness and binder type) square metre (m²)
(d) Stone skeletal mix- gap graded as defined (state layer thickness and binder type) square metre (m²)
(e) Sand skeletal mix – continuously graded as defined (state layer thickness, binder type, square metre (m²)
design class/ level)
(f) Semi gap mix – as defined (state layer thickness, binder type and design level) square metre (m²)
(g) Sand skeletal mix – gap graded mix (state layer thickness, binder type design class/level) square metre (m²)
(h) Any of the above mix types where the use of reclaimed asphalt has been specified (indicate square metre (m²)
maximum % reclaimed asphalt or binder replacement limits)
(i) Certified: any mixes certified for specific applications by an approved agency as being fit for square metre (m²)
the purpose and as specified in the Contract Documentation.
C9.1.5.2 Rehabilitation
(a) Stone skeletal mix – continuously graded as defined (state layer thickness, binder type and ton (t)
design class/ level)
ton (t)
(b) Stone skeletal mix – SMA as defined (state layer thickness, binder type)
ton (t)
(c) Stone skeletal mix – gap graded as defined (state layer thickness and binder type)
ton (t)
(d) Stone skeletal mix- open graded as defined (state layer thickness and binder type)
(e) Sand skeletal mix – continuously graded as defined (state layer thickness, binder type, ton (t)
design class/ level)
ton (t)
(f) Sand skeletal mix – gap graded mix (state layer thickness, binder type design class/level)
(g) Any of the above mix types where the use of reclaimed asphalt has been specified (indicate ton (t)
maximum % reclaimed asphalt or binder replacement limits)
(h) Certified: any mixes certified for specific applications by an approved agency as being fit for ton (t)
the purpose and as specified in the Contract Documentation.
The unit of measurement shall be the ton of asphalt of a specific type and composition, less than 10 tons of which is produced on occasion, as
specified, and measured in accordance with certified weighbridge tickets issued in regard to the mix type used.
The tendered rate shall be paid as extra over rates tendered for the relevant payment items listed above and shall include full compensation for
all additional costs to produce and place small quantities of asphalt on instruction of the Engineer.
C9.1.7.2 Extra over payment items C9.1.4.2 and C9.1.5.2 (State layer thickness, mix class, binder ton (t)
type, nominal maximum particle size and placing technique (hand/paver))
Items C9.1.7 are applicable solely to work that has to be executed in a restricted area of which the width is less than 1,5 m and the length is less
than 100 m.
The unit of measurement shall be the ton of surfacing completed to the nominal thickness specified and measured according to certified
weighbridge tickets issued in respect to the actual mix used.
The tendered rate shall include full compensation for procuring, and furnishing of all materials, manufacturing of the asphalt, transport, placing
and finishing to the tolerances specified.
Rolled in chippings shall be paid for separately under payment item C9.1.10 as applicable
The unit of measurement shall be the ton of specified size of rolled-in chippings applied at the approved application rate, measured loose in
hauling vehicles. The tendered rate shall include full compensation for the procuring, furnishing, pre-coating, spreading and rolling in of the
chippings and for any additional costs resulting from the construction of the asphalt surfacing with rolled-in chippings.
C9.1.10.3 Active filler (lime unless stated in Contract Documentation, or determined with mix design) ton (t)
C9.1.10.6 Bituminous bond coat – net bitumen (state type) ton (t)
The unit of measurement in respect of increases or decreases of any component of the approved mix from that specified in the nominal proportions
specified for the relevant mix type, shall be the ton. No payment shall be made for inert filler added by the Contractor.
Payment for variations shall be made as specified in Chapter 1.
The unit of measurement for item C9.1.14.1 shall be the number of times the particular piece of equipment is established and de-established on
site to perform acceptance control measurements, as approved by the Engineer, and shall include full compensation for providing and establishing
the equipment on site and subsequent de-establishing of the equipment from site when no longer required.
The unit of measurement for item C9.1.14.2 all be the kilometre of road surveyed in accordance with, and as specified in Clause A9.1.8.4 and
shall include full compensation for surveying the specified layer, and for analysing and determining the longitudinal profiles and 100 m International
Roughness Index (IRI), all as specified. The tendered rate shall also include full compensation for the number of runs per lane as specified.
C9.1.15.2 Milling of bridge decks and keys to bridge deck approaches cubic metre (m³)
CONTENTS
D9.1.1 SCOPE
D9.1.2 DEFINITIONS
D9.1.3 GENERAL
D9.1.4 DESIGN BY THE CONTRACTOR
D9.1.5 MATERIALS
D9.1.6 CONSTRUCTION EQUIPMENT
D9.1.7 EXECUTION OF THE WORKS
D9.1.6 ASSESSMENT CRITERIA
D9.1.7 EVALUATION FOR ACCEPTANCE
D9.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D9.1.9 NOTIFICATION OF REMEDIAL WORK
D9.1.10 REMEDIAL WORKS
D9.1.1 SCOPE
This Section covers the specifications related to the provision of functional and, or, structural layers of a road pavement structure comprising the
asphalt surfacing, and, or the base layer (where specified) in terms of either a design and/or a performance guarantee to be provided by the
Contractor. The duration of any such performance guarantees shall be as specified in the Contract Documentation and the issuing of a Taking-
Over Certificate for the whole of the project. It includes performance parameters, field measurements, acceptance criteria and remedial work
methodologies.
D9.1.2 DEFINITIONS
- Performance Period: The Performance Period shall be the number of years from the date of issue of the Taking-Over Certificate for the whole
of the works as specified in the Contract Documentation.
- Taking Over Certificate: As defined in the General Conditions of Contract for the project.
- Performance Certificate: As defined in the General Conditions of Contract for the project.
- Performance Guarantee Period: The performance period shall be the number of years from the date of issue of the Taking-Over Certificate
for the whole of the works as specified in the Contract Documentation.
- Performance Guarantees: Lodging of bank guarantees from an approved institution to the value and period as stated in the Contract
Documentation.
D9.1.3 GENERAL
D9.1.3.1 Extended Performance Warranty
The work shall be constructed in terms of an extended warranty as specified in the Contract Documentation. The extended warranty, in the form
of financial guarantees and in the format as prescribed by the Employer, shall be limited to the performance of the work. With the exception of
de-bonding between the asphalt layers and the substrate, the Contractor shall not be held liable for any failures that might occur as a result of
failure within the underlying layers. During the Extended Warranty Period, the Contractor shall also not be held liable for any damage to the layer/s
resulting from external sources, including, but not limited to:
a) Traffic accidents
b) Spillage of fuel, oils, hazardous materials, etc. from public vehicles
c) Materials falling off public vehicles
d) Travelling of construction/tracked plant (other than his own) after completion of the Works.
Prior to the issuing of the Taking-Over Certificate, the Contractor shall provide two guarantees, each valued at 5 % of the cost of the layer/s (as
per final constructed quantities measured under Part C of this Chapter (Measurement and Payment) for the performance of the layer/s. The
guarantees shall be issued by a bank or other institution approved by the Employer and shall become effective on issue of the Taking-Over
Certificate. They shall remain valid until released in terms of Table D9.1.3-1 and/or as specified in the Contract Documentation.
D9.1.3.6 Moisture
The requirements with respect to moisture as specified in Clause A9.3.5 shall be applicable in all instances.
D9.1.5 MATERIALS
Unless contrary to the requirements of a certified proprietary product, the constituents shall comply with the following requirements:
D9.1.5.3 Aggregates
a) The aggregates to be utilised in the mix shall comply in all respects with the relevant and appropriate requirements as specified in Part A of
this Chapter. Any deviation or amendments from these requirements shall be stated in Form E1: Quality Assurance.
b) The several aggregate fractions for the mixture shall be sized, graded and combined in such proportions that the resulting composite blend
consistently meets the required performance criteria.
No adjustment of compensation shall be made should the actual mix proportions used in the works vary from that nominated by the Contractor
on Form E1: Quality Assurance.
The Contractor shall submit to the Engineer his design for the asphalt mixes within thirty (30) days of the date of the Letter of Acceptance. The
target binder content, filler content and aggregate grading shall be subject to the tolerances given in Part A of this Chapter as relevant. All
production and application shall be carried out in terms of the details included under Form E1: Quality Assurance.
The application rate for the bond coat shall be nominated by the Contractor for a specific area, taking account of:
No adjustment in compensation shall apply should the actual tack coat application be higher or lower than that nominated by the Contractor.
At the approaches to exposed bridge joints the Contractor shall mill out the existing asphalt base or surfacing on the abutment side to a depth of
15 mm (or as may otherwise be prescribed) and for a distance of at least 5,0 m. The asphalt surfacing shall be placed to form a smooth transition
towards the bridge joint.
The Contractor shall be required to submit his detailed Quality Assurance Plan to the Engineer for approval within ten (10) days of the date of the
Letter of Acceptance. Once it has been approved, the Contractor shall not deviate from it without prior written agreement with the Engineer.
The onus rests with the Contractor to produce work which conforms in quality to the Quality Assurance Plan, the specifications and requirements
herein, and to other relevant specifications and standards defined in the submitted and accepted tender (e.g. in Form E1: Quality Assurance)
The Engineer shall, however, conduct such tests as he may deem applicable and shall retain all rights as determined in the relevant Conditions
of Contract related to bad workmanship and to unacceptable materials. This shall also be applicable to the accepted layers (or design) and related
specifications.
Aggregate sieve size (mm) Permissible deviation from target grading (%)
10 mm ± 4,0
7,1 mm ± 4,0
5,0 mm ± 3,0
2,0 mm ± 3,0
1,0 mm ± 3,0
0,600 mm ± 3,0
0,300 mm ± 3,0
0,150 mm ± 3,0
0,075 mm ± 1,5
Table D9.1.9-2: Performance parameters for the shoulders of dual and single carriageways and inner lanes of dual carriageways
Instrumentally Assessed
Visually Assessed Parameters Test Assessed Parameters
Parameters
1. Cracking 1. Deflection 1. Air Permeability
2. Bleeding 2. Rutting 2. Water Permeability
3. Raveling 3. Roughness 3. Marvil Permeability
Cracking shall be defined as either Surface Cracking and/or Longitudinal and/or Transverse and/or Crocodile Cracking as defined in TMH9 Manual
for Visual Assessment of Road Pavements, Part A and Part B referred to in Clause A20.1.4.11 of Chapter 20.
D9.1.10.2 Deflection
Deflection measurements shall be carried out as specified in Clause A20.1.5.5e) of Chapter 20. Where so specified in the Contract Documentation,
at the end of the Performance Guarantee Period, the structural capacity of the road pavement, as determined in terms of deflection measurements,
shall conform to be acceptance criteria presented in Table D9.1.10-2 below. The acceptance criteria is specified in terms of the maximum
deflection (Ymax), base layer index (BLI) and middle layer index (MLI) as calculated from FWD deflection measurements. Segment lengths of
1,0 km in length shall be identified for evaluation. The 90th percentile value per segment shall be used to judge acceptance.
D9.1.10.3 Rutting
At the end of the Performance Guarantee Period, as determined in terms of the specified methodology, the surface deformation (rutting) as
determined shall not exceed the values as specified in Table D9.1.10-3 below for the specific road class.
10 % 6 8 8 8 10
5% 8 10 10 10 15
0% 10 15 15 15 20
D9.1.10.4 Roughness
Roughness shall be measured in accordance with Clause A20.1.5.5c). At the end of the Performance Guarantee Period, as determined in terms
of the Specified Methodology, the surface roughness as determined in accordance with Clause A20.1.5.5c), shall not exceed the values as
specified in Table D9.1.10-4 below.
Maximum length (%) of Mean profile depth (mm) for Road Class
segment with mean
profile depth worse than
limiting value
Class 1 Class 2 Class 3 Class 4 Class 5
D9.1.11 EVALUATION
The following procedures shall be followed by the Contractor to determine acceptance of the pavement by the Employer at the end of the
Performance Guarantee Period or whether earlier remedial work is required in terms of the specified acceptance criteria.
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied. No warranty
or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be accepted by the
Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct, indirect, special, incidental,
consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO on 18
August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge Works for State
Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain unaffected
but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be mandatory for use in
procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written comments
may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the COTO
subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body (RCB) to COTO for
approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years, after which it may again be
reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites mentioned
below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd (SANRAL)
and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
A10.1.2 DEFINITIONS
Surface treatments - encompass thin bituminous surfacings applied as wearing courses for new construction or as reseals.
Bitumen - is a dark brown to black viscous liquid or solid, consisting essentially of hydrocarbons and their derivatives. It is soluble in trichloroethylene, is
substantially non-volatile, and softens gradually when heated. Bitumen is obtained by refining petroleum crude oil.
Penetration grade bitumen - is manufactured by straight-run distillation of crude oil or by blending two or more base components (one hard, such as
40/50 pen, and the other soft, such as 150/200 pen). Penetration grade bitumen is used either as a primary binder (70/100 pen for surface seal work in
South Africa) or as a base bitumen for the manufacture of cut back bitumen, modified binders or bitumen emulsions.
Bitumen emulsions - are two-phase systems consisting of a dispersion of bitumen droplets in water which contains an emulsifier. The emulsifiers are
added to assist in the formation of the emulsion, to render it stable, and to modify its properties. Different grades of emulsion are manufactured to allow
slower and faster curing e.g. stable grade (Slow setting) is required for labour intensive work and manufacturing of conventional slurries. Spray grade
(Rapid setting) emulsions are preferred for spray sealing. The terms cationic and anionic derive from the electrical charges on the bitumen globules. The
positively charged cationic emulsions are preferred for construction of sprayed seals due to superior adhesive properties with the mostly negatively
charges aggregate used for seal work in South Africa.
Cutback bitumens - are blends of penetration grade bitumen and slow, medium or rapid curing sol vents. The choice of solvent determines the rate at
which the bitumen will "set up" or cure when exposed to air. A rapid-curing (RC) solvent will evaporate more quickly than a medium-curing (MC) solvent,
which in turn will cure more rapidly than a slow-curing (SC) solvent. The viscosity of the cutback bitumen is determined by the proportion of solvent added.
MC-30 used for prime coats has a high percentage of medium curing solvent (45 %) with a very low viscosity. MC-3000 used for sprayed seal work has
approximately 12 % solvent allowing application at low road surface temperature.
Modified binders - modification is achieved by the introduction of polymers, crumb rubber, aliphatic synthetic wax or naturally occurring hydrocarbons
to a penetration grade bitumen. Modified binders for seal work are classified into:
• Hot homogeneous modified binder S-E1 and S-E2 for spray sealing and C-E1 for crack sealing (refer properties in TG1)
• Cold homogeneous modified binder SC-E1 and SC-E2 for spray sealing and CC-E1 for crack sealing
• Hot non-homogenous modified binder S-R1 and S-R2 for spray sealing and C-R1 and C-R2 for crack sealing
A10.1.3 GENERAL
A10.1.3.1 Requirements pertaining to all surface treatments
Adequate advance notice shall be given to the Engineer before the Contractor proceeds with any seal work. This notice shall include the program containing
exact dates and sections to be sealed as well as the stockpile/s which will be used for each section.
Seal work shall not commence until a design has been submitted for each section an approved by the Engineer.
The areas to be sealed shall be cleaned of all dust, dirt, dung, oil or any other foreign matter that may be deleterious to the seal.
Sealing work shall not commence until the Engineer has approved all preparatory works ordered on that section of road.
Unless otherwise agreed by the Engineer and subject to the outcome of a trial section, the Contractor shall programme all spraying to cease each working
day at 15:00.
The Contractor shall comply with the requirements of Chapter 1 regarding traffic over completed layers
Wherever reference is made to distance the measurements for length shall be taken as actual lengths measured along the road centreline.
All quantities of sprayed binder and variations shall be measured at spray temperature of the applied binder.
Conventional slurry shall not be applied at an air temperature of less than 7°C when temperatures are rising or less than 13°C when temperatures are
dropping.
During hot weather slurry operations shall be suspended when aggregate is being displaced by the spreader box or squeegees.
Rapid setting slurry or microsurfacing shall be sufficiently versatile to be laid in air temperatures of 4°C to 40°C as well as capable of being laid under damp
conditions. When the breaking process accelerates to such an extent that it renders the product unworkable to attain the required end result, no further
work shall be done until adjustments to the composition of the product have been proven through trial sections and approval by the Engineer.
The Engineer may reduce the specified curing period for slurry, microsurfacing and asphalt application, based on a representative corrected ball
penetration (SANS 3001-BT10), at the expected operating road surface temperature (Refer SABITA Manual 40) of less than 2,0 mm.
A10.1.3.13 Maintenance
The Contractor shall maintain the bituminous surface until the work is finally accepted by the Employer, after the specified Defects Notification Period.
Any damage related to design, materials and workmanship or any defects which may develop before the issue of the Performance Certificate, fair wear
and tear and 3rd party mechanical damage excepted, shall be corrected by the Contractor at his own cost.
Treatment of defects shall be carried out in accordance with Chapter 8.
Penalties in accordance with Part D of this Chapter shall apply, when applicable.
Table A10.1.3-3: Nominal rates of first application of binder and aggregate for multiple stone seals
Nominal rates of binder application for tack coat (l/m²) Nominal aggregate spread rate (m² per m³)
Nominal Conventional Homogeneous Hot applied Hot applied non- Aggregate spread rate for Aggregate
size of bitumen and modified homogeneous homogeneous conventional and spread rate
aggregate emulsion. emulsion. modified modified binders homogeneous modified for non-
mm (Residual (Residual cold bitumen at spray at spray binders homogeneous
cold binder) temperature temperature modified binders
bitumen)
20 1,2 1,2 1,3 2,0 75 65
14 0,9 0,9 1,0 1,8 110 90
Table A10.1.3-4: Nominal rates of application for second binder and final aggregate
Nominal rates of binder application for penetration coat (l/m²) Nominal aggregate spread rate (m² per m³)
Nominal Conventional Homogeneous Hot applied Hot applied non- Aggregate spread rate for Aggregate
size of bitumen and modified homogeneous homogeneous conventional and spread rate
aggregate emulsion. emulsion. modified modified binders homogeneous modified for non-
mm (Residual (Residual cold bitumen at spray at spray binders homogeneous
cold binder) temperature temperature modified binders
bitumen)
10 1,0 1,0 1,2 1,8 165 140
7,1 0,8 0,8 - 170
7,1 (1st n/a n/a - 250
layer)*
7,1 1,1
1 1 - 150
(2nd
layer)*
5 0,6 0,6 0,9 - 230
*Split application 20/7 double seal
Residual cold binder is defined as the net binder (bitumen, polymers and additives) cold at a temperature of 20°C. The hot applied binder is calculated
by multiplying the residual cold bitumen by the “Cold to hot” conversion factors published in TRH3.
c) Nominal binder application and aggregate spread rates for sand and grit seals
The nominal rates of application given in Table A10.1.3-5 shall be for the purposes of tendering only and the actual rates of application shall be as
approved by the Engineer.
Table A10.1.3-5: Nominal binder and aggregate application rates for sand and Grit seals
d) Nominal binder application and aggregate spread rates for Cape seals (Single seal component)
The nominal rates of binder and aggregate application provided in Table A10.1.3-6 shall apply for tender purposes only.
Residual cold binder is defined as the net binder (bitumen, polymers and additives) cold at a temperature of 20°C. The hot applied binder is calculated
by multiplying the residual cold binder by the “Cold to hot” conversion factors published in TRH3.
e) Nominal binder application and aggregate spread rates for Cape seals (Slurry component)
The following proportions per cubic metre of slurry shall apply for tendering purposes only:
(i) First or only slurry application
Slurry aggregate (saturated volume) .............................................................................................................................. 1,0 m³
Stable-grade emulsion at mixing temperature ................................................................................................................ 230 l
Cement .......................................................................................................................................................................... 16,5kg³
Water............................................................................................................................................................................. 210 l
(ii) Second slurry application
Slurry aggregate (saturated volume) .............................................................................................................................. 1,0 m³
Stable-grade emulsion at mixing temperature ................................................................................................................ 260 l
Cement .......................................................................................................................................................................... 16,5kg³
Water............................................................................................................................................................................. 200 l
The following spread rate of slurry (saturated aggregate volume) shall apply for tender purposes only:
Table A10.1.3-7: Nominal spread rate of slurry for Cape seals
Nominal size of aggregate First layer of slurry Second layer of slurry
(mm) (m² per m³) (m² per m³)
20 140 185
14 150
1 180
30 14 33 13
30 20
40 20 25 10
50 20
50 28 20 10
The following proportions per cubic metre of slurry shall apply for tendering purposes only:
Slurry aggregate (saturated volume) .............................................................................................................................. 1,0 m³
Stable-grade emulsion at mixing temperature ................................................................................................................ 230 l
Cement.......................................................................................................................................................................... 0,01m³
Water............................................................................................................................................................................. 200 l
If required, an adhesion agent approved by the Engineer shall be added to the precoating fluid at a rate of 0,5 % of the volume of precoating fluid.
(i) Aggregate
Aggregate properties shall be in accordance with the specifications for each individual seal type as stated in the relevant section of this
chapter.
(ii) Binder
Binder properties shall be in accordance with the specifications for each individual seal type as stated in the relevant section of this chapter.
Should a proprietary product be used, the relevant properties of the selected product, not meeting the generic specifications shall be stated
as well as the achievable specifications.
c) Performance Specifications
Performance specifications are provided in D10.1.
d) Remedial work
Requirements for remedial work are provided in D10.1.10.
A10.1.5 MATERIALS
A10.1.5.1 Conventional Bituminous Binders for seal work
Unless Performance Grade binder specifications SANS 4001 BT – 10 are specified in the Contract Documentation, conventional bituminous binders shall
comply with the following specifications:
• Penetration-grade bitumen complying with SANS 4001-BT1
• Cut-back bitumen complying with SANS 4001 – BT2:
• Anionic bitumen emulsion complying with SANS 4001 – BT3
• Cationic bitumen emulsion complying with SANS 4001 – BT4
Table A10.1.5-1: Temperature/time limits for conventional binders cut back to specific proportions
Quantity of MC-30 added Temperature limits
(parts per 100 parts of Lower limit Upper limit
bitumen by volume) °C °C
0 150 175
6 146 163
11 138 154
17 132 149
22 125 143
b) Hardness
When tested in accordance with SANS 3001 No AG10, the 10 % FACT value shall comply with the requirements in Table A10.1.5-4.
Table A10.1.5-4: Hardness
20 mm nominal size 30 30 25
14 mm nominal size 30 30 25
10 mm nominal size 35 35 30
7,1 mm nominal size 35 35 30
14 7,4 8 8
e) Durability
Grade A aggregate used in seals shall show a durability index of less than 4 as determined by the test method specified in Section A20.1 of Chapter 20.
Should the durability index be higher, additional testing according to current best practice shall be conducted and the results submitted to the Engineer
for evaluation.
7,1 100
0,300 0 - 15
0,150 0-2
Sand Equivalent
35
[%] (min)
Plasticity Index: Non-Plastic
The sand equivalent determined in accordance with SANS 3001 - AG5, shall be at least 35.
The immersion index of briquettes made with slurry aggregate and 70/100 penetration-grade bitumen at the specified net bitumen content for the slurry
shall be not less than 75 when tested in accordance with Chapter 20.
In addition, unless otherwise specified, for rapid setting slurries the supplier shall assess the compatibility of the binder offered with aggregates from
suitable sources nearest to the site prior to tender closure.
The slurry for Cape seals shall conform to the specifications in Table A10.1.5-11 for Fine Slurry, Fine or Medium as specified for each coat in the
Contract Documentation.
b) Filler for slurry
Ordinary portland cement and portland blast-furnace cement (PBFC) shall be SANS 50197 certified.
Road lime shall be SANS 824 certified (Lime for Soil Stabilisation).
Only one of the above materials shall be used throughout in order to prevent undesirable colour differences in the surface.
Overlay or Rut fill (up to 12 mm) Rut fill (more than 12 mm)
10 100 100
7,1 100 85 - 100 5%
5 90 - 100 70 - 90 5%
2 65 - 90 45 - 70 5%
1 45 - 70 28 - 50 5%
0.6 30 - 50 19 - 34 5%
0.3 18 - 30 12 - 25 4%
0.15 10 - 21 7 - 18 3%
0.075 5 - 15 5 - 15 2%
A10.1.6.3 Rollers
a) General
Sufficient operational rollers of each of the following types shall be available on the works to maintain the required tempo of work.
• Pneumatic tyred rollers (minimum two)
• Rubber-soled steel wheel rollers (as and when specified in the Contract Documentation)
• Light steel wheeled rollers of 2 – 4 tons (minimum two)
• Heavy steel wheel rollers of 5 – 12 tons (as and when specified in the Contract Documentation)
Micro surfacing 10 - 20 mm
A10.1.7.6 Microsurfacing
a) Application of microsurfacing
Microsurfacing shall be applied using a continuous slurry machine as specified in Clause A10.1.6.11.
The applied thickness of the microsurfacing, before compaction, should be 20-25 % more than the desired end thickness
The formulation of the product shall be such that complete curing will take place within a maximum of 4 hours, regardless of the climatic conditions during
construction, to allow opening to traffic.
Ball penetration (SANS 3001-BT10), corrected for the expected road surface temperature (refer SABITA Manual 40), on the product shall reduce to less
than 2,0 mm within a period of 4 weeks.
The aggregate of size and grade specified in the schedule of quantities and Contract Documentation shall be spread evenly to the specified thickness. It is
then levelled out with rakes, shovels, screed boards and compacted with a light pedestrian roller in static mode. The slurry is then mixed and evenly spread
over the macadam aggregate by wheelbarrow, shovels and squeegees. A pedestrian type plate vibratory compactor is then used to achieve penetration of
the slurry until all the voids within the Macadam are filled. A final slurry is then applied.
A moist burlap drag shall be drawn over the final slurry to ensure an overall and even texture. The burlap will be dragged perpendicular across the centre-
line of the road. Should breaking of the emulsion, segregation of the mix or formation of the lumps occur during the application of the slurry, the slurry
operations shall be discontinued at once and any defective material removed from the road. Successive strips of slurry shall overlap transversely by not
less than 25 mm not more than 150 mm. Any overlapping and any omitted areas shall be rectified with squeegees. The contractor shall ensure that either
edge of the slurry is finished to the prescribed widths and lines. All stones dislodged in the process of applying the slurry shall be removed from the road
and spoiled. Where slurry is spread by hand, the squeegee squad shall be allowed to complete the spreading of each batch onto the road, using squeegees,
before the next is discharged. The slurry shall then be worked from side to side criss-cross with aid of squeegees so as to fill as many voids as possible.
The finished slurry slayer shall present a smooth, dense and homogenous surface, true to level and camber on the cross fall and from tear cracks,
corrugation, rutting or any other irregularity. It shall be free from depressions or elevations and when a straight edge two meters long is laid on the treated
surface parallel or at right angles to the centre of the road, the surface shall nowhere vary from the lower edge by more than 3,0 mm along the treated area,
the outer edge of the slurry shall be formed neatly in a straight line to the widths ordered by the engineer.
In case a further surfacing layer is applied, the slurry shall be left open to the atmosphere to age and oxidize for a minimum period of 4 weeks, i.e. the slurry
shall not be overlaid with any seal or asphalt for 4 weeks
No slurry shall be laid when the ambient temperature is less than 10 o C and in any event not during rain or when free water standing on the surface.
A10.1.8 WORKMANSHIP
A10.1.8.1 General aspects related to quality and workmanship
a) Surface tolerances
Where newly constructed base or shoulder areas are to be sealed, the surfaces shall be checked for compliance with the surface tolerances and all other
requirements specified in Chapter 5. Any portions that do not meet these requirements shall first be either corrected or removed and reconstructed before
they are sealed.
Surface tolerances specified for the base shall also apply to the sealed surface.
The edges of the completed seal shall be continuously true to line with a maximum allowable deviation from the specified edge line of 15 mm.
b) General appearance
The completed seal shall be free from corrugations or any other wave effect where depressions are preceded and followed by humps or ridges.
The completed surfacing shall be of uniform texture without gaps or patches and shall be free from longitudinal and transverse corrugations and any loose
aggregate or binder spillage.
c) Repair of defects
Any areas which show signs of bleeding, aggregate loss, non-uniformity of texture and surface irregularities after the section has been opened to traffic
shall be corrected as specified in Chapter 8. Corrective work shall be carried out in such a manner as to blend in colour, texture and finish with adjacent
work.
In case of Cape seals, slurry or microsurfacing, any damage to the slurry by rain or traffic before the slurry has cured shall be rectified by the Contractor
at his own expense.
d) Aggregate spread rate and binder application
The maximum permissible variation from the rates of application of aggregate, as approved by the Engineer after verification during the trial section, shall
be plus or minus 5 %.
The maximum permissible variation in application rate from that specified (measured at spray temperature), shall be 5 % for all binders, except diluted
emulsions. In case of diluted emulsions, the variation shall be calculated in terms of the emulsion before dilution.
A lot for acceptance control purposes shall be at least 600 litres. Lots smaller than 600 litres shall be combined with succeeding lots until a combined lot
not less than 600 litres is obtained.
Provided that corrections to subsequent layers (penetration coat and/or cover sprays) could be applied in accordance with good practice, the Engineer
could conditionally accept out of tolerance variations at the reduced rates of payment listed in Table A10.1.8-1.
Variations in binder application rates in excess of those tabled shall be deemed rejected. No payment will be made for bituminous binder applied in excess
of the rate ordered plus the permitted tolerance.
Rejected sprays shall result in rejection of the total seal without any payment.
Conditional acceptance does not relieve the Contractor from his obligations related to the seal performance.
The equation for determining the reduced payment per binder layer is provided below:
𝑃 = −0.004𝐷2 + 0.0196𝐷 + 1.002
Where
P = % Payment of the tendered rate for the seal
D = Deviation from the specified rate
In the case of single seals, where a diluted emulsion cover spray is not specified, the Engineer may permit the application of a diluted emulsion fog spray
in instances where tack coat application rates are below the minimum allowable tolerances. In such instances, no additional payment over and above the
unit rate tendered for the accepted seal, plus or minus any variation from the nominal to the rate ordered, will be made.
In the case of single seals, where a diluted emulsion cover spray is specified, no payment will be made for bituminous binder in the tack coat applied in
excess or at a rate lower than the specified rate, plus or minus the permitted tolerance unless in the opinion of the Engineer, such overspray or any
shortages can be satisfactorily corrected by the adjustment to the application rate of the cover spray, or an additional cover spray, if such correction is
effected.
In the case of multiple stone seals, no payment will be made for any bituminous binder applied in excess of, or at a rate lower, than that specified, plus or
minus the permitted tolerance. In such instances the Engineer may permit the adjustment to any subsequent spray applications to achieve the total net
binder as determined and specified for the particular seal type. In the event of under application of binder, the Engineer may similarly approve the
application, or an increased application, of an appropriate cover spray if the overall integrity/performance of the surface seal is deemed not to be
compromised.
In the latter two cases, where some of the layers are conditionally accepted, a weighted payment adjustment shall be calculated based on the payment
adjustment for the specific layer and the proportional cost of the binder layer to the total binder cost, as determined from the tendered variation for each
binder. An example is provided in Table A10.1.8-2.
Second application
(penetration coat)
Hot: S-E1 1.30 1.20 7.69 91.61 Conditional 28.91 5.00 6.5 31.55
The weighted adjusted payment factor in the case of multiple binder applications could directly be calculated using the following equation:
10-24
DRAFT STANDARD (DS) OCTOBER 2020
B10.1 GENERAL REQUIREMENTS FOR SURFACE TREATMENTS
PART B: LABOUR ENHANCEMENT
CONTENTS
B10.1.1 SCOPE
B10.1.2 DEFINITIONS
B10.1.3 GENERAL
B10.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B10.1.5 MATERIALS
B10.1.6 CONSTRUCTION EQUIPMENT
B10.1.7 EXECUTION OF THE WORKS
B10.1.8 WORKMANSHIP
B10.1.1 SCOPE
All the preparation activities are suitable components for labour enhancement (sweeping and watering). The stone spray application is divided into two
main activities namely the binder spray application and the stone spreading. The binder spray application is suitable only if bitumen emulsions are used,
whilst the stone spreading is reasonably suitable using walk behind chip spreaders. Rolling the stone is a reasonably suitable labour component using
pedestrian rollers.
In the interest of limiting the exposure of workers to the burns and inhalation of fumes associated with the application of penetration bitumen by hand,
only bitumen emulsions are considered for labour intensive methods for spray seal work. Only emulsion products are suitable for binder applications by
hand methods.
B10.1.2 DEFINITIONS
The provisions of PART A shall apply.
B10.1.3 GENERAL
The provisions of PART A shall apply.
B10.1.5 MATERIALS
The provisions of PART A shall apply.
B10.1.6.4 Rollers
Sufficient suitably sized (± 1 ton) tandem vibratory pedestrian rollers having two equally sized drums in tandem with both drums driven, each drum to
have a separate eccentric shaft, shall be available and used to properly place the stone.
B10.1.6.5 Brooms
Sufficient hand-held brooms shall be available and used to further distribute the chips evenly as directed by the Engineer.
B10.1.8 WORKMANSHIP
The provisions of PART A shall apply.
C10.1.1 Single seals including a cover spray, if specified (indicate grade of aggregate and type
of binder):
C10.1.1.1 Using 5,0 mm aggregate square metre (m²)
The unit of measurement shall be square metre of completed and accepted seal in accordance with the approved method statement and additional
instructions.
The nominal rates for single seals indicated in Table A10.1.3-3 shall apply.
C10.1.3.2 20 mm and 7,1 mm aggregate (state grade of aggregate and type of binder to be used for square metre (m²)
each layer)
C10.1.3.3 14 mm and 7,1 mm aggregate (state grade of aggregate and type of binder to be used for square metre (m²)
each layer)
C10.1.3.4 14 mm and 5,0 mm aggregate (state grade of aggregate and type of binder to be used for square metre (m²)
each layer)
C10.1.3.5 20 mm with a split application of 7,1 mm aggregate (state grade of aggregate and type of square metre (m²)
binder to be used for each layer)
The unit of measurement shall be the square metre of completed and accepted seal in accordance with the approved method statement and additional
instructions.
The nominal rates for multiple stone seals indicated in Tables A10.1.3-4 and A10.1.3-5 shall apply. The tendered rate shall include full compensation inter
alia, for furnishing all materials, marking the centreline, spraying of binder spreading of aggregate, rolling, removing of dust or deleterious material,
supplying of water and spraying of haul roads and construction roads, trimming the edges of the completed surface, and all other incidentals necessary
for completing the work as specified, including the application of a fog spray, except the precoating of aggregate, which shall be paid for separately.
C10.1.4.2 Extra-over for sealing during the specified embargo period (State seal type, binder for each square metre (m²)
layer)
Payment for the rate tendered under item C10.1.6.1 only be applicable when sealing has to cease due to commencement of the embargo period as
specified, and due to any approved extension of time not due to the to that originally specified. The tendered rate shall include for all costs associated
with re-establishing all necessary plant and equipment in order to complete the works.
The rate tendered under item C10.1.6.2 shall only be applicable if the seal, as specified, cannot be constructed due to commencement of any winter
embargo period and where such a situation is due to legitimate and approved extensions of time or sealing during the embargo period is specified in the
Contract documentation. The rate tendered shall include for all costs associated with construction the surfacing with any appropriate binder type, reduced
production rates, increased traffic accommodation measures and obligations.
C10.1.5.1 Sand seal (state grades of aggregate and types of binders to be used) square metre (m²)
C10.1.5.2 Grit seal (state grades of aggregate and types of binders to be used) square metre (m²)
C10.1.6 Sand or Grit seals using (state: walk behind spreader or by hand):
C10.1.6.1 Sand seal (state grades of aggregate and types of binders to be used) square metre (m²)
C10.1.6.2 Grit seal (state grades of aggregate and types of binders to be used) square metre (m²)
The unit of measurement shall be square metre of completed and accepted seal in accordance with the approved method statement and additional
instructions.
The nominal rates for sand and Grit seals indicated in Table A10.1.3-6 shall apply.
The tendered rate shall include full compensation inter alia, for furnishing all materials, marking the centreline, spraying of binder spreading of aggregate,
rolling, removing of dust or deleterious material, supplying of water and spraying of haul roads and construction roads, trimming the edges of the completed
surface, and all other incidentals necessary for completing the work as specified, except the precoating of aggregate, which shall be paid for separately.
C10.1.7.1 Single minus 20 mm aggregate (state grades of aggregate and types of binders to be used) square metre (m²)
C10.1.7.2 Single minus 14 mm aggregate (state grades of aggregate and types of binders to be used) square metre (m²)
square metre (m²)
C10.1.7.3 Single minus 10 mm aggregate (state grades of aggregate and types of binders to be used)
square metre (m²)
C10.1.7.4 Extra over for sand seal (state grades of aggregate and types of binders to be used)
C10.1.8 Graded aggregate (Otta) seals, with aggregate applied by hand, using:
C10.1.8.1 Single minus 20 mm aggregate (state grades of aggregate and types of binders to be used) square metre (m²)
C10.1.8.2 Single minus 14 mm aggregate (state grades of aggregate and types of binders to be used) square metre (m²)
square metre (m²)
C10.1.8.3 Single minus 10 mm aggregate (state grades of aggregate and types of binders to be used)
square metre (m²)
C10.1.8.4 Extra over for sand seal (state grades of aggregate and types of binders to be used)
The unit of measurement shall be square metre of completed and accepted seal in accordance with the approved method statement and additional
instructions.
The nominal rates for Graded aggregate seals as indicated in the Contract Documentation shall apply.
The tendered rate shall include full compensation inter alia, for furnishing all materials, marking the centreline, spraying of binder spreading of aggregate,
rolling, removing of dust or deleterious material, supplying of water and spraying of haul roads and construction roads, trimming the edges of the completed
surface, and all other incidentals necessary for completing the work as specified
C10.1.9.3 Cationic Stable grade emulsion ((indicate bitumen content) litre (ℓ)
C10.1.9.5 Homogeneous modified binder (indicate type and bitumen content) cold applied litre (ℓ)
C10.1.9.6 Non-homogeneous modified binder (indicate class S-R1 or S-R2) litre (ℓ)
C10.1.9.7 Homogeneous modified binder (indicate type) hot applied litre (ℓ)
C10.1.9.8 Homogeneous modified binder S-E1 with 4,5% MC30 litre (ℓ)
The unit of measurement for bituminous binder in respect of an increase or a decrease in the specified rates of application shall be the litre measured at
spraying temperature (except for diluted emulsions, where the variation is calculated in terms of the emulsion before dilution)
Where MC30 is used to cut back the penetration-grade bitumen, the rate for MC-30 variation shall include full compensation for providing the MC-30 and
mixing it with the bituminous binder.
The unit of measurement for aggregate in respect of an increase or a decrease in the rates of application determined during the trial sections and
contained in the approved method statement, shall be the cubic metre of aggregate.
C10.1.11.2 60 % Diluted Anionic stable-grade emulsion (indicate dilution in % emulsion/%water) litre (ℓ)
C10.1.11.3 Diluted Cationic spray-grade emulsion (indicate % bitumen and dilution in % emulsion/%water) litre (ℓ)
C10.1.11.4 Diluted SC-E1 (indicate % bitumen and dilution in % emulsion/%water) litre (ℓ)
This pay item shall only apply when an additional cover spray is ordered by the Engineer. Cover sprays included as part of the seal design shall be
deemed to be included in the total rate for the pay item of the specific seal.
The nominal rates for cover sprays seals indicated in Clause A10.1.3.15 shall apply.
The unit of measurement shall be the litre of undiluted/diluted emulsion as specified, measured at spraying temperature.
The tendered rate shall include full compensation for furnishing the material and applying the cover spray as instructed.
Item Description Unit
C10.1.12 Application of cover spray by hand:
C10.1.12.2 60% Diluted Anionic Stable-grade emulsion (indicate dilution in % emulsion/%water) litre (ℓ)
C10.1.12.3 Diluted Cationic Spray-grade emulsion (indicate % bitumen and dilution in % emulsion/%water) litre (ℓ)
C10.1.12.4 Diluted SC-E1 (indicate % bitumen and dilution in % emulsion/%water) litre (ℓ)
This pay item shall only apply when an additional cover spray is ordered by the Engineer. Cover sprays specified as part of the seal are included in the
pay item of the specific seal.
The nominal rates for cover sprays seals indicated in Clause A10.1.3.15 shall apply.
The unit of measurement shall be the litre of diluted/undiluted emulsion as specified, measured at spraying temperature.
The tendered rate shall include full compensation for furnishing the material and applying the cover spray as instructed.
C10.1.13.1 Product containing low flashpoint solvent (indicate precoating fluid) litre (ℓ)
C10.1.13.2 Product containing no low flashpoint solvent (indicate precoating fluid) litre (ℓ)
C10.1.14.1 Product containing low flashpoint solvent (indicate precoating fluid) litre (ℓ)
C10.1.14.2 Product containing no low flashpoint solvent (indicate precoating fluid) litre (ℓ)
C10.1.15.1 Product containing low flashpoint solvent (indicate precoating fluid) litre (ℓ)
C10.1.15.2 Product containing no low flashpoint solvent (indicate precoating fluid) litre (ℓ)
The unit of measurement for the precoating of aggregate shall be the litres of precoating fluid for treatment of the specified aggregate in accordance
with the specified precoating method.
The nominal rates for precoating fluid as indicated Table A10.1.3-9 (non-plant) shall apply.
The tendered rate shall include full compensation for furnishing the equipment and materials and precoating the aggregate as specified, including the
handling, stockpiling and protecting of the stockpiles against inclement weather.
C10.1.19 Extra over item for work in areas inaccessible to mechanical equipment:
C10.1.19.3 Cape seals with one layer of slurry square metre (m²)
C10.1.19.4 Cape seals with two layers of slurry square metre (m²)
C10.1.20.1 Supply and application of geosynthetic membrane (state type) square metre (m²)
C10.1.21.1 Conventional slurry (indicate type and grade of binder and grade of aggregate) cubic metre (m3)
C10.1.21.2 Microsurfacing (indicate type and grade of binder and grade of aggregate) cubic metre (m3)
The unit of measurement for slurry and microsurfacing shall be the cubic metre of saturated fine aggregate as determined according to the method described
in Clause A20.1.5.13 of Chapter 20.
The nominal rates for slurry and microsurfacing as per Clause A10.1.3.14 shall apply.
The tendered rates shall include full compensation, for furnishing all materials, demarcating the working area, mixing and applying the slurry, rolling and
all other incidentals necessary for completing the work as specified, including the watering of haul and construction roads in and about the site.
C10.1.22 Bituminous single seal and slurry, including a cover spray if specified:
C10.1.22.1 Bituminous single seal with 20 mm aggregate and first slurry (indicate type of tack coat and square metre (m²)
cover spray binder and grade of aggregate)
C10.1.22.2 Bituminous single seal with 14 mm aggregate and slurry (indicate type of tack coat and square metre (m²)
cover spray binder, grade of aggregate and grade of slurry)
C10.1.22.3 Bituminous single seal with 10 mm aggregate and slurry (indicate type of tack coat and square metre (m²)
cover spray binder, grade of aggregate and grade of slurry)
C10.1.22.4 Extra over C10.1.22.1 for application of second slurry (State grade of slurry) square metre (m²)
The unit of measurement for the complete bituminous single seal with aggregate and slurry shall be the square metre.
The nominal rates for single seals and slurry as per Clause A10.1.3.14 shall apply.
The tendered rates shall include full compensation, for furnishing all materials, demarcating the working area, spraying the binders, spreading the
aggregates, rolling, mixing and applying the slurry, and all other incidentals necessary for completing the work as specified, including the watering of haul
and construction roads in and about the site.
The cost of providing the slurry seal over the final primed width shall be included in the rate for providing the seal with slurry over the bituminous surfaced
width
C10.1.23.2 Slurry-bound macadam seal with 20 mm aggregate and slurry (indicate thickness and grade square metre (m²)
of aggregate)
C10.1.23.3 Slurry-bound macadam seal with 28 mm aggregate and slurry (indicate thickness and grade square metre (m²)
of aggregate)
The unit of measurement for slurry variations shall be the cubic metre of saturated fine aggregate.
Payment for variations shall be made as specified in C1.1.4 of Chapter 1.
Item Description Unit
C10.1.25 Variation in active filler content (specify active filler) ton (t)
The unit of measurement in respect of increases or decreases in the active filler content from that specified in the nominal mix for tender purposes shall
be the ton. No payment shall be made for inert filler added by the Contractor.
Payment for variations shall be made as specified in C1.1.4 of Chapter 1.
Item Description Unit
C10.1.26 Trial sections for all seal types specified (specify seal type) Lump sum
The tendered rates shall include full compensation, for furnishing all materials, demarcating the working area, constructing the seal, and all other incidentals
necessary for completing the work as specified.
The tendered rate shall include the provision of a bank guarantee in respect of the Surfacing, for an amount equal to 10 % of the contract value, valid for
a period of two (2) years from Completion. The terms and conditions applicable to the release of the guarantee shall be as described under Clause
D10.1.7. The guarantee shall be valid for two years, after the issuing of the Completion Certificate.
The performance guarantee as required shall be delivered to the Employer by the successful Contractor before signing of the contract with the applicable
date of commencement of validity of the guarantee stated to be from the Completion Certificate and its estimated date.
The guarantee shall be prepared to the format provided in the Contract Documentation. The terms of the conditions applicable to the release of the
performance guarantee shall be as described under Clause D10.1.3.
The tendered lump sum shall not be subject to Contract Price Adjustment and shall become payable once the Contractor has submitted and the Employer
has accepted the guarantee.
CONTENTS
D10.1.1 SCOPE
D10.1.2 GENERAL
D10.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D10.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D10.1.5 VISUALLY ASSESSED PROPERTIES
D10.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D10.1.7 EVALUATION FOR ACCEPTANCE
D10.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D10.1.9 NOTIFICATION OF REMEDIAL WORK
D10.1.10 REMEDIAL WORK
D10.1.1 SCOPE
This Section covers the specifications and work related to the functional and structural condition of the bituminous surface treatment (surfacing seal) in
terms of a performance guarantee to be provided by the Contractor, valid for the specific period from the issue of a Completion Certificate for the whole
of the Works. It includes performance parameters, field measurements, acceptance criteria and remedial work methodologies.
D10.1.2 GENERAL
This specification supplements Clause A10.1.4.
The functional performance assessments undertaken in years 1 and 2 after the issuing of the Completion Certificate shall, as far as practicably possible,
coincide with the Employer’s regular road-assessment programme within those years. The roughness and surface macro-texture surveys will be
commissioned, and the costs thereof will be borne, by the Employer.
Extent The actual length affected, with a minimum recorded linear length per single occurrence
of 0,5 m.
Reporting, which shall be the responsibility of the Contractor, shall consist of the following:
- Completion and copying of report forms according to Employer’s format.
- Compiling of report on findings as well as remedial measures required.
The abovementioned requirements shall be completed and delivered in triplicate to the office of the Employer within one calendar month of the inspection
date.
Segment lengths 1 km
f) Acceptance criteria
Using the cumulative distribution graph for each segment, the measured surface macro-texture must meet the acceptance criteria presented in Table
D10.1.6-3.
Table D10.1.6-3: Acceptance criteria (Minimum) for initial surface macro-texture
20 Cape
14 Cape
10 mm
14 mm
20/7/7
20/10
14/7
20/7
Seal Type
Year 11 80.0 5%
75.0 0%
80.0 20 %
Year 21 75.0 5%
70.0 0%
Notes:
1. Time in years after the issuing of the Performance Certificate.
2. Mean Profile Depth value over 10 m.
Year 11 60.0 5%
55.0 0%
60.0 20%
Year 21 55.0 5%
45.0 0%
Notes:
1. Time in years after completion.
2. Mean Profile Depth value over 10 m.
Surface Failure Requirements in Table D10.1.5-3 not met Mill out full depth of defective surfacing and replace with
suitable asphalt surfacing
Surface Cracking Requirements in Table D10.1.5-3 not met Investigation
Surface Ravelling Requirements in Table D10.1.5-3 not met Application of a fog spray and slurry texture treatment
Surface Macrotexture Requirements in Table D10.1.6-4 and Table D10.1.6-5 not Water cutting of surfacing
met
COTO
Committee of Transport
Officials
DRAFT
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied. No
warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body (RCB)
to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years, after which
it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 11: ANCILLARY ROAD WORKS .......................................................................................................... 11-1
11.1 PITCHING, STONEWORK, CAST IN SITU CONCRETE FOR PROTECTION AGAINST EROSION ....... 11-1
PART A: SPECIFICATIONS ............................................................................................................................................................................. 11-1
PART B: LABOUR ENHANCEMENT ................................................................................................................................................................ 11-6
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................... 11-8
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 11-11
11.2 NON-STRUCTURAL GABIONS ................................................................................................................ 11-12
PART A: SPECIFICATIONS ........................................................................................................................................................................... 11-12
PART B: LABOUR ENHANCEMENT .............................................................................................................................................................. 11-15
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 11-16
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 11-19
11.3 GUIDE BLOCKS AND KILOMETRE MARKERS ...................................................................................... 11-20
PART A: SPECIFICATIONS ........................................................................................................................................................................... 11-20
PART B: LABOUR ENHANCEMENT .............................................................................................................................................................. 11-23
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 11-25
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 11-27
11.4 ROAD RESTRAINT SYSTEMS ................................................................................................................. 11-28
PART A: SPECIFICATIONS ........................................................................................................................................................................... 11-28
PART B: LABOUR ENHANCEMENT .............................................................................................................................................................. 11-33
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 11-34
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 11-40
11.5 FENCING .................................................................................................................................................... 11-41
PART A: SPECIFICATIONS ........................................................................................................................................................................... 11-41
PART B: LABOUR ENHANCEMENT .............................................................................................................................................................. 11-46
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 11-47
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 11-52
11.6 ROAD SIGNS ............................................................................................................................................. 11-53
PART A: SPECIFICATIONS ........................................................................................................................................................................... 11-53
PART B: LABOUR ENHANCEMENT .............................................................................................................................................................. 11-60
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 11-61
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 11-67
11.7 ROAD MARKINGS AND ROAD STUDS ................................................................................................... 11-68
PART A: SPECIFICATIONS ........................................................................................................................................................................... 11-68
PART B: LABOUR ENHANCEMENT .............................................................................................................................................................. 11-75
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 11-76
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 11-81
11.8 LANDSCAPING AND PLANTING PLANTS .............................................................................................. 11-82
PART A: SPECIFICATIONS ........................................................................................................................................................................... 11-82
PART B: LABOUR ENHANCEMENT .............................................................................................................................................................. 11-90
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 11-91
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 11-96
11.9 FINISHING THE ROAD AND ROAD RESERVE AND TREATING OLD ROADS .................................... 11-97
PART A: SPECIFICATIONS ........................................................................................................................................................................... 11-97
PART B: LABOUR ENHANCEMENT .............................................................................................................................................................. 11-99
PART C: MEASUREMENT AND PAYMENT ................................................................................................................................................ 11-100
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ................................................................................................................... 11-102
CHAPTER 11: ANCILLARY ROAD WORKS
11.1 PITCHING, STONEWORK, CAST IN SITU CONCRETE FOR
PROTECTION AGAINST EROSION
CONTENTS
PART A: SPECIFICATIONS
A11.1.1 SCOPE
A11.1.2 DEFINITIONS
A11.1.3 GENERAL
A11.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.1.5 MATERIALS
A11.1.6 CONSTRUCTION EQUIPMENT
A11.1.7 EXECUTION OF WORKS
A11.1.8 WORKMANSHIP
A11.1.1 SCOPE
This Section covers the furnishing of materials and the construction of protective coverings using stone, cast in situ concrete, bricks, prefabricated
concrete elements, wire or alternative materials on exposed surfaces such as earth slopes, drains and stream beds, as well as heavier protective
layers in the form of riprap and the construction of stone masonry for walls, as specified and shown on the drawings, or as specified in the Contract
Documentation.
A11.1.2 DEFINITIONS
No specific definitions.
A11.1.3 GENERAL
No general items.
A11.1.5 MATERIALS
The material specifications are the required specifications for the materials as placed and/or processed in its final position within the road reserve.
It remains the Contractor’s responsibility to ensure that the materials delivered to the road shall meet these specified requirements
Materials removed under this Section from existing works, except where excavated materials are specified to be reused or disposed of, or except
where provision has been made in Part C for their reuse or specific disposal, shall be deemed to be the property of the Contractor.
A11.1.5.2 Sand
a) Sand for concrete
Sand for concrete, cement slurry and cement mortar shall comply with the requirements of SANS 1083. This sand can be from natural sources,
crushed or obtained from commercial sources.
A11.1.5.6 Geotextiles
Geotextiles shall be of the grade and type specified in the schedule of quantities or Contract Documentation, and shall comply with the requirements
of Section A12.11 of Chapter 12.
A11.1.7.3 Riprap
a) General
Riprap shall consist of a course or courses of large rock placed on bank slopes and toes in stream and riverbeds and at other localities where
protection of this type may be required.
Two types of riprap are specified here, viz one type where the rocks are individually packed, which is designated as packed riprap, and the other
type where the rock is dumped and then spread by machines, which is designated as dumped riprap.
The surface of areas to receive riprap shall be neatly trimmed to line and level and all loose material compacted. The perimeters of riprap areas
shall be protected by the construction of either rock-filled trenches, walls or other structures as may be required. Perimeter trenches shall normally
be backfilled with rock of the same size and quality as that used in the construction of the adjoining riprap, but any voids shall be filled with smaller
stone and the entire backfill shall be well compacted.
A11.1.8 WORKMANSHIP
A11.1.8.1 General
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular layer for which it will be used.
The Engineer may, at his discretion, decide to use the Contractor’s test results if he is satisfied that the Contractor has complied with the process
control requirements.
Any work or materials which do not comply with the specified requirements, shall be removed and replaced with work or materials which comply
with the requirements or, if the Engineer so permits, shall be repaired so that it shall comply with the specified requirements after having been
repaired.
CONTENTS
B11.1.1 SCOPE
B11.1.2 DEFINITIONS
B11.1.3 GENERAL
B11.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B11.1.5 MATERIALS
B11.1.6 CONSTRUCTION EQUIPMENT
B11.1.7 EXECUTION OF THE WORKS
B11.1.8 WORKMANSHIP
B11.1.1 SCOPE
This Section covers the furnishing of materials and the construction of protective coverings using stone, cast in situ concrete, bricks or prefabricated
concrete blocks on exposed surfaces such as earth slopes, drains and stream beds, as well as heavier protective layers in the form of riprap and
the construction of stone masonry for walls, as specified and shown on the drawings, or as specified by the Engineer
This Section therefore includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A. This Section includes concrete mixed by hand.
B11.1.2 DEFINITIONS
The provisions of Part A shall apply.
B11.1.3 GENERAL
The provisions of Part A shall apply.
B11.1.5 MATERIALS
B11.1.5.1 General material specifications
When packed riprap is constructed using labour enhanced construction methods, the stone for the riprap shall have a maximum size of 0,03 m3 or
a maximum mass of 30 kg.
B11.1.5.2 Concrete
a) Concrete mixing by hand
Concrete may be mixed by hand or in hand-turned concrete mixers for small pours up to one (1) cubic metre. Larger pours greater than one cubic
metre shall be machine mixed with on-site mechanical mixers and/or batch plants.
The mix design shall be based upon obtaining an average concrete compressive strength sufficiently above the specified characteristic compressive
strength so that, considering the expected variability of the concrete and test procedures, no more than 5 % of strength tests will be expected to
fall below the specified characteristic compressive strength.
All concrete mixed on the site of works shall be weigh-batched unless the Contractor can demonstrate to the Engineer that his method of
proportioning the concrete ingredients consistently produces uniform concrete, which meets the strength requirements.
Material which can be excavated by means of a suitable shovel with or without the use of a pick or other
Soft
hand-swung tool.
Material which is difficult to excavate by hand even with the aid of a crowbar and requires the assistance of
Intermediate
pneumatic tools for economic removal.
*1 Only applicable to materials comprising not more than 10 % gravel of size less than 10 mm and materials containing no cobbles or
isolated small boulders.
*2 Classification depends on the moisture content of the cohesive material.
B11.1.8 WORKMANSHIP
The provisions of Part A shall apply.
C11.1.1.1 Excavating foundation trenches in soft material using labour enhanced construction methods cubic metre (m3)
0 m to 1,0 m depth
C11.1.1.2 Excavating foundation trenches in intermediate material using labour enhanced construction cubic metre (m3)
methods 0 m to 1,0 m depth
The unit of measurement shall be the cubic metre of material excavated for foundation trenches in accordance with the authorised dimensions,
measured in place before excavation.
Excavations shall be done using labour enhanced construction methods as specified and measured.
The tendered rates shall include full compensation for the excavation of the foundation trenches to the required dimensions, lines, levels and
grades, the trimming of the open drain and the loading and disposal of the material as directed.
Loading and hauling, where applicable, including a haul of 1,0 km, shall be measured and paid as specified in Section C1.7 of Chapter 1. Where
the excavation of material is specified by means of labour enhanced construction methods, the tendered rates shall include loading and transport
by wheelbarrow if the material is disposed of or utilised within a radius of 50 m, alternatively loading by hand onto transport vehicles for such
disposal or utilisation elsewhere, within a haul distance of 1,0 km.
Item Description Unit
C11.1.3 Riprap
C11.1.3.1 Packed riprap (“critical mass of stone” and thickness indicated) cubic metre (m3)
C11.1.3.2 Extra over item C1 1. 1. 3. 1 for constructing packed riprap using labour enhanced cubic metre (m3)
construction methods (Maximum size of stone shall be 0,03 m3 or a maximum mass of 30
kg)
C11.1.3.3 Dumped riprap (critical mass of stone and thickness indicated) cubic metre (m3)
(c) Geotextile (type, class and grade stated) square metre (m2)
The tender rate for item C11.1.3.4(a) and (b) will be as specified in Clause A3.1.5.2b) of Chapter 3 and A11.1.7.2b).
The unit of measurement for riprap and filter layer shall be the cubic metre of riprap or filter layer in place and shall include rock used in trench
backfill. The unit of measurement for item C11.1.3.4(c) shall be the square metre of geotextile laid as specified, including overlaps.
Item C11.1.3.2 is an extra over item which will be paid if instructed to construct packed riprap using labour enhanced construction methods.
The rates tendered shall include full compensation for preparing the surfaces, including excavation (but excluding excavation for trenches and bulk
excavations) and for the furnishing, transporting, handling and placing of riprap or filter layers. The rate tendered for item C11.1.3.4(c) shall include
C11.1.4.3 Extra over items C11.1.4.1 and C11.1.4.2 for procuring stone from commercial sources cubic metre (m3)
The unit of measurement for stone masonry walls shall be the cubic metre of actual walling constructed and accepted.
The tendered rate for each type of stonewall shall include full compensation for furnishing all materials, trimming the areas, placing the stones and
cement-mortared masonry where necessary, and all other work necessary for completing the walls in accordance with the specifications.
Excavation of foundation trenches and bulk excavations will be paid for separately.
The tendered rates shall also include full compensation for mixing and/or procuring concrete, mortar and grout as indicated.
The tendered rate for item C11.1.4.3 shall include full compensation for procuring, furnishing and offloading stone from commercial
suppliers, including the cost of transporting the material to the site irrespective of haul distance.
Item Description Unit
C11.1.5 Concrete pitching or paving
C11.1.5.1 Cast in situ concrete pitching or paving (class of concrete and thickness of pitching or paving square metre (m2)
indicated)
C11.1.5.2 Prefabricated concrete grass blocks (type and thickness indicated) square metre (m2)
C11.1.5.3 Welded steel fabric used for cast in situ pitching or paving (type indicated) kilogram (kg)
The unit of measurement shall be the square metre of each type constructed.
The tendered rates shall include full compensation for furnishing all materials, all excavation (but excluding bulk excavation and excavation for
foundation trenches and edge beams), compacting and trimming all the excavated areas, treating the prepared surface with an approved herbicide
and ant-poison, laying concrete grass blocks (item C11.1.5.2), topsoiling and grassing, (item C11.1.5.2), constructing concrete pitching or paving,
including normal formwork and the shaping of surfaces (item C11.1.5.1), making and cleaning weepholes (item C11.1.5.1) and for all other work
necessary for completing the work as specified.
The tendered rates shall also include full compensation for mixing and/or procuring concrete, mortar and grout as indicated.
Welded steel fabric used for cast in situ pitching or paving shall be as specified in Section A13.3 of Chapter 13.
C11.1.6 Concrete edge beams (class of concrete indicated) cubic metre (m3)
The unit of measurement shall be the cubic metre of concrete in edge beams constructed as specified.
The tendered rate shall include full compensation for furnishing all materials and labour, including formwork as necessary, placing concrete and
shaping all surfaces and all excavations required. Where excavations cannot be efficiently done by labour then machinery can be employed.
The tendered rates shall also include full compensation for mixing and/or procuring concrete as indicated.
C11.1.7.2 Contractor’s charges and profit added to the prime cost sum percent (%)
Payment under the prime cost sum for providing ant poison and herbicide and the Contractor's costs and profit, in this respect, shall be made in
accordance with the provisions of the general conditions of contract, but, in addition, the Contractor's tendered rate for costs and profit shall Include
compensation for applying the chemicals as specified.
CONTENTS
D11.1.1 SCOPE
D11.1.2 GENERAL
CONTENTS
PART A: SPECIFICATIONS
A11.2.1 SCOPE
A11.2.2 DEFINITIONS
A11.2.3 GENERAL
A11.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.2.5 MATERIALS
A11.2.6 CONSTRUCTION EQUIPMENT
A11.2.7 EXECUTION OF WORKS
A11.2.8 WORKMANSHIP
A11.2.2 DEFINITIONS
No specific definitions.
A11.2.3 GENERAL
None applicable.
A11.2.5 MATERIALS
A11.2.5.1 General material specifications
The required material specifications are for the materials as placed and/or processed in its final position within the road reserve.
It is the Contractor’s responsibility to ensure that the materials delivered shall meet the specified requirements as per Clause A12.6.5 of Chapter
12.
A11.2.5.2 Materials
a) Rock
As per Clause A12.6.5.2 of Chapter 12.
b) Wire
As per Clause A12.6.5.2 of Chapter 12.
A11.2.8 WORKMANSHIP
A11.2.8.1 General
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced meets the specified requirements for the particular layer for which it will be used. Similarly,
the Contractor shall conduct sufficient checks and controls during construction of the elements to ensure that the required lines, levels and finishes
are achieved.
The Engineer may, at his discretion, decide to use the Contractor’s test results if he is satisfied that the Contractor has complied with the process
control requirements.
Any work or materials which do not comply with the specified requirements, shall be removed and replaced with work or materials which comply
with the requirements or, if the Engineer so permits, shall be repaired so that it shall comply with the specified requirements after having been
repaired.
A11.2.8.2 Tolerances
Tolerances for gabion and mattress materials and dimensions shall conform to the requirements of EN 10223-3.
CONTENTS
B11.2.1 SCOPE
B11.2.2 DEFINITIONS
B11.2.3 GENERAL
B11.2.5 MATERIALS
B11.2.1 SCOPE
This Section covers the furnishing of materials and the construction of gabion aprons for constructing minor non-structural retaining walls, lining
channels, revetments and other anti-erosion and containment structures.
The construction of gabion boxes and mattresses shall be deemed to be a labour enhanced construction process.
This Section therefore includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A.
B11.2.2 DEFINITIONS
The provisions of Part A shall apply.
B11.2.3 GENERAL
The provisions of Part A shall apply.
B11.2.5 MATERIALS
The provisions of Part A shall apply.
B11.2.8 WORKMANSHIP
The provisions of Part A shall apply.
C11.2.1.1 Excavating all material situated within the following depth ranges below the surface level
C11.2.1.2 Extra over sub-item C11.2.1.1 for excavation in hard material, irrespective of depth cubic metre (m3)
C11.2.1.3 Excavating soft material within 1,5 m below the surface level using labour enhanced cubic metre (m3)
construction methods:
C11.2.1.4 Excavating intermediate material within 1,5 m below the surface level using labour cubic metre (m3)
enhanced construction methods:
The unit of measurement shall be the cubic metre of material excavated within the specified widths over the lengths and depths authorised by the
Engineer in each case, measured in place before excavation. Excavation in excess of the widths specified or authorised by the Engineer shall not
be measured for payment.
Irrespective of the total depth of the excavation, the quantity of material in each depth range shall be measured and paid for separately.
Excavation shall be done using conventional construction methods and/or labour enhanced construction methods as specified and measured.
The tendered rates shall include full compensation for the excavation of the material to the required dimensions, lines, levels and grades, temporary
timbering, shoring and strutting, including unavoidable overbreak, the trimming of the trenches and compacting the trench inverts, backfilling of
over excavation and compacting the backfill, keeping excavations safe, dealing with any surface or subsurface water and the loading and disposal
of the excess material as directed. The tendered rates shall also include full compensation for any other operations necessary for completing the
work as specified, but excluding surface preparation for bedding the gabions.
Loading and hauling, where applicable, including a haul of 1,0 km, shall be measured and paid as specified in Section C1.7 of Chapter 1. Where
the excavation of material is specified by means of labour enhanced construction methods, the tendered rates shall include loading and transport
by wheelbarrow if the material is disposed of or utilised within a radius of 50 m, alternatively loading by hand onto transport vehicles for such
disposal or utilisation elsewhere, within a haul distance of 1,0 km.
For payment purposes a distinction shall be made between materials as classified above under Classification of Materials.
C11.2.2 Surface preparation for bedding the gabion boxes and mattresses square metre (m2)
The unit of measurement for levelling and preparing surfaces for receiving the gabion boxes and mattresses shall be the square metre to the neat
dimensions of revetments, aprons or wall foundations.
The tendered rate shall include full compensation for excavating, filling any cavities with rock, and levelling the ground surface so as to be ready
for receiving the gabion boxes tor retaining walls, aprons and revetments.
C11.2.3.2 PVC coated gabion boxes (dimensions of box) cubic metre (m3)
CONTENTS
D11.2.1 SCOPE
D11.2.2 GENERAL
CONTENTS
PART A: SPECIFICATIONS
A11.3.1 SCOPE
A11.3.2 DEFINITIONS
A11.3.3 GENERAL
A11.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.3.5 MATERIALS
A11.3.6 CONSTRUCTION EQUIPMENT
A11.3.7 EXECUTION OF THE WORKS
A11.3.8 WORKMANSHIP
A11.3.2 DEFINITIONS
No specific definitions.
A11.3.3 GENERAL
No general items.
A11.3.5 MATERIALS
A11.3.5.1 General material specifications
The material specifications are the required specifications for the materials and guide blocks as manufactured placed and/or processed in their
final position within the road reserve.
It is the Contractor’s responsibility to ensure that the elements constructed and materials delivered to the road shall meet these specified
requirements.
Materials removed under this Section from existing works, except where excavated materials are specified to be reused or disposed of, or except
where provision has been made in Part C for their reuse or specific disposal, shall be deemed to be the property of the Contractor.
DRAFT STANDARD (DS) OCTOBER 2020 11-20
A11.3.5.2 Concrete
All concrete work shall be carried out as precast elements in accordance with the requirements of Section A13.4 of Chapter 13. Unless otherwise
specified, a mixture of four parts of concrete sand or grit to one part of cement (Cem II 32.5) shall be used.
A11.3.5.4 Paint
Paint for guide blocks shall be non-reflectorised roadmarking paint as specified in Section A11.7. Paint for the recess in the block shall be retro-
reflective solvent or water-based paint as specified in Section A11.7. Unless otherwise specified, paint for the block shall be of white colour.
A11.3.7.2 Fabricating
Precast units shall be fabricated to the dimensions specified and/or shown on the drawings. The forms shall be smooth and shall have accurate
dimensions. The concrete mixture shall be placed in the forms and vibrated on a vibrating table or by other approved means. The units shall be
reinforced as shown on the drawings and shall have an F3 surface finish.
The units shall be true to shape, smooth, and without any honeycombing or other blemishes. After curing of the concrete, the recess near the top
of the unit shall be painted with the reflective paint specified, while the remainder of the top half of the unit shall be painted with road marking paint
of the specified colour.
A11.3.7.4 Erecting
Guide blocks shall be erected after the surfacing has been completed.
Holes shall be excavated in the shoulder of the road and the blocks placed vertically and square to the road centre line.
Kilometre markers shall be erected after the completion of all machine trimming at the positions indicated on the drawings or as specified by the
Engineer.
Backfilling shall be compacted in layers not exceeding 100 mm from the bottom of the hole. Surplus excavated material shall be disposed of by the
Contractor at no additional payment.
The units shall be painted prior to installation. Care shall be exercised not to damage or soil the exposed painted surfaces during transportation
and installation.
Guide blocks and kilometre markers shall be maintained and protected during the entire construction period and any units damaged or broken
before the seal has been completed, the road markings have been painted or the certificate of completion has been issued, shall be repaired or
replaced, as may be required, at the Contractor's cost.
A11.3.8 WORKMANSHIP
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular layer for which it will be used.
The Engineer may, at his discretion, elect to use the Contractor’s test results if he is satisfied that the Contractor has complied with the process
CONTENTS
B11.3.1 SCOPE
B11.3.2 DEFINITIONS
B11.3.3 GENERAL
B11.3.5 MATERIALS
B11.3.1 SCOPE
This Section covers the manufacturing, supply and erection of guide blocks and kilometre markers, mainly constructed of precast concrete, in
positions and in accordance with the dimensions specified and/or shown on the drawings.
This Section therefore includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A. This Section includes concrete mixed by hand.
B11.3.2 DEFINITIONS
The provisions of Part A shall apply.
B11.3.3 GENERAL
The provisions of Part A shall apply.
B11.3.5 MATERIALS
The provisions of Part A shall apply.
B11.3.5.2 Concrete
a) Concrete mixing by hand
Concrete may be mixed by hand or in hand-turned concrete mixers for small pours up to one (1) cubic metre. Larger pours greater than one (1)
cubic metre shall be machine mixed with on-site mechanical mixers and/or batch plants.
The mix design shall be based upon obtaining an average concrete compressive strength sufficiently above the specified characteristic compressive
strength so that, considering the expected variability of the concrete and test procedures, no more than 5 % of strength tests will be expected to fall
below the specified characteristic compressive strength.
All concrete mixed on the site of works shall be weigh-batched unless the Contractor can demonstrate to the Engineer that his method of
proportioning the concrete ingredients consistently produces uniform concrete, which meets the strength requirements.
The sand shall be measured off, tipped onto the mixing floor and spread in a circle. The cement (one or two whole sacks, as required by the mix
design) shall then be spread evenly across the sand and mixed in with shovels, turning the mixture into the middle of the circle and out again.
When the colour is even, the mix shall be shaped with a hollow in the centre.
Part of the mixing water shall be poured into the hollow and mixed in. More water shall be slowly added and mixed in until all the water has been
added. The materials shall be turned into the middle of the circle and out again at least twice. The mix should be soft and even with no dry patches.
The mix shall then be spread in a circle.
B11.3.8 WORKMANSHIP
The provisions of Part A shall apply.
C11.3.3 Kilometre markers mounted on concrete reinforced pipes (diameter to be specified) number (No)
The unit of measurement shall be the number of units supplied and erected in accordance with the specifications and detailed on the drawings.
Excluded from items C11.3.2 and C11.3.3 shall be kilometre markers on posts measured under item C11.6.4.
The tendered rate shall include full compensation for supplying all materials and labour, manufacturing and transporting the precast units, setting
out, excavating and backfilling all the holes and disposing of surplus excavated material placing and painting the guide blocks and kilometre markers
and all the equipment the tools and incidentals necessary for completing and maintaining the works described in this section. Where kilometre
markers are erected in concrete pipe units, the tendered rate shall include the provision and installation of such concrete pipes, as detailed on the
drawings.
CONTENTS
D11.3.1 SCOPE
D11.3.2 GENERAL
CONTENTS
PART A: SPECIFICATIONS
A11.4.1 SCOPE
A11.4.2 DEFINITIONS
A11.4.3 GENERAL
A11.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.4.5 MATERIALS
A11.4.6 CONSTRUCTION EQUIPMENT
A11.4.7 EXECUTION OF THE WORKS
A11.4.8 WORKMANSHIP
A11.4.2 DEFINITIONS
Road Restraint Systems (RRS) – are primarily used to protect vehicle occupants from impacting road furniture or hazards and vehicles reaching
opposing carriageways. They are also intended to protect pedestrians, and any other entity using a roadway.
Vehicle Restraint Systems (VRS) – which include, but are not limited to:
• Longitudinal barriers
• Terminals and transitions
• Safety barriers
• Vehicle parapets
• Crash cushions
• Arrestor beds
A11.4.3 GENERAL
Road Restraint Systems, for both temporary and permanent use, shall be sourced from a reputable manufacturer or supplier, being affiliated to a
recognised industry association, and installed by a competent installer, who is either certified by the manufacturer or supplier, or affiliated to a
recognised industry association.
A11.4.5 MATERIALS
A11.4.5.1 General material specifications
The material specifications are the required specifications for the materials as placed and/or processed in its final position within the road reserve.
It is the Contractor’s responsibility to ensure that the materials delivered to site shall meet these specified requirements.
The type of non-performance based guardrail systems installed will be selected based on the Employer’s maintenance strategy to ensure that the
systems selected do not impose an onerous maintenance burden on the Employer for post construction repair or replacement requirements.
Materials removed under this Section from existing works, except where excavated materials are specified to be reused or disposed of, or except
where provision has been made in Part C for their reuse or specific disposal, shall be deemed to be the property of the Contractor.
A11.4.5.2 Materials
a) Steel guardrails for erection on timber posts
Steel guardrails shall comply with the requirements of SANS 1350 and carry the SABS mark or a mark by any other SANAS approved certification
body for the applicable SANS specification for 3,81 m length railings, as specified.
The dimensions of guardrails, end wings, bull noses and bridge adaptors shall be in accordance with the details indicated in the appropriate figures
defined in SANS 1350. The dimensions of end treatments and alternative bridge adaptors shall be in accordance with the details shown on the
A11.4.8 WORKMANSHIP
The completed vehicle restraint system shall have a neat appearance and shall not show any visible deviations from line and grade. Posts shall be
straight and vertical. Longitudinal elements shall not be warped but shall be in a vertical plane parallel to the road centreline except at flared terminal
sections. The galvanized surface on the vehicle restraint systems shall be smooth and continuous and free from abrasions or scratches. Any
damage to the surface shall be repaired or replaced at the Contractor's expense. The methods of repair to the galvanized zinc coating shall be as
specified in SANS 121. Zinc rich paint systems applied with aerosol techniques shall not be permitted.
Vehicle restraint systems, which do not comply with the prescribed requirements, shall be replaced or otherwise repaired.
The Contractor shall avoid any damage to completed road sections, or the spillage of concrete on completed road surfaces. Any such damage or
spillage shall be rectified at the Contractors cost.
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular use for which it is intended.
CONTENTS
B11.4.1 SCOPE
B11.4.2 DEFINITIONS
B11.4.3 GENERAL
B11.4.5 MATERIALS
B11.4.1 SCOPE
This Section covers the supplying, installing and maintaining of Road Restraint Systems at locations and in accordance with the specifications and
details, dimensions and design shown on the drawings.
The construction of guardrails on timber posts shall be deemed to be a labour enhanced construction process.
This Section therefore includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A.
B11.4.2 DEFINITIONS
The provisions of Part A shall apply.
B11.4.3 GENERAL
The provisions of Part A shall apply.
B11.4.5 MATERIALS
The provisions of Part A shall apply.
B11.4.8 WORKMANSHIP
The provisions of Part A shall apply.
(b) On steel posts used at specific locations (Drawing reference) metre (m)
(c) On concrete or other surfaces, with spacer blocks but without posts (Drawing reference) metre (m)
(d) Extra over C11.4.1.1(a) and C11.4.1.1(b) for excavating holes of posts using labour metre (m)
enhanced methods (soft and intermediate)
C11.4.1.2 Terminal sections for 3,81 guardrails comprising of:
(d) End treatments where single guardrail sections are specified (Drawing reference) number (No)
(e) End treatments where double guardrail sections are specified (Drawing reference) number (No)
(f) Bridge adaptors (including extra rails and posts) (Drawing reference) number (No)
(g) Extra over C11.4.1.2(d) and C11.4.1.2(e) for excavating holes for posts using labour enhanced number (No)
methods (soft and intermediate)
The unit of measurement for C11.4.1.1(a) (b) and (c) shall be the metre of new guardrail systems as erected, including curved guardrails but
excluding length of terminal sections. The use of steel posts shall be deemed relevant under this item.
The unit of measurement for item C11.4.1.1(d) shall be the metre of guardrail system erected with holes specified to be excavated using labour
enhanced methods, paid extra over items C11.4.1.1(a) and C11.4.1.1(b).
The unit of measurement for C11.4.1.2(a) to (f) shall be the number of complete new end treatments of each type installed.
The unit of measurement for C11.4.1(g) shall be the number of end treatments with holes excavated using labour enhanced methods of
construction, paid extra over items C11.4.1.2(d) and C11.4.1.2(e).
The tendered rates shall include full compensation for furnishing all materials and labour for erecting and galvanizing the guardrails, complete with
posts, spacer blocks, bolts, nuts, washers and reinforcing plates, and excavating holes in all classes of material, concrete, backfilling and removing
any surplus material. It shall also include full compensation for incidentals in respect of supplying and erecting guardrails, end treatments, and
turned down sections.
Reflective plates to guardrails and drilling and blasting of holes shall be paid for separately
The tendered rate of item C11.4.1.1(c) and C11.4.1.2(g) shall include full compensation for excavating the necessary holes using labour enhanced
construction methods where specified by the Engineer, and shall be paid as an extra over item.
(b) Cable barrier system (state criteria including containment level & working width) metre (m)
(c) Concrete barrier system (state criteria including containment level & working width metre (m)
(d) Etc for other types, permanent and temporary metre (m)
C11.4.2.2 Terminal sections for the following to EN 1317 or AASHTO MASH or NCHRP350 as
alternative where no MASH product is available:
(a) End treatments (State criteria EN or MASH and containment level) number (No)
(b) Crash cushions (State criteria EN or MASH and containment level) number (No)
(d) Other types (State criteria EN or MASH and containment level, etc.) number (No)
C11.4.2.3 Relocation of temporary systems (Type, EN or MASH, or NCHRP350 as alternative where no metre (m)
MASH product is available, containment level and working width indicated)
The unit of measurement for C11.4.2.1 shall be the metre of specified vehicle restraint system (complying with EN 1317) as fully erected, excluding
length of terminal sections but including curved guardrails.
The unit of measurement for C11.4.2.2 shall be the number of complete end treatments of each type fully supplied and installed compliant with
EN1317 or AASHTO MASH or NCHRP350 as alternative where no MASH product is available as relevant.
The tendered rate for item C11.4.2.3 shall be metre of temporary vehicle restraint system removed and relocated to a different position, regardless
of the distance relocated. The tendered rates shall include full compensation for furnishing all materials and labour for erecting or removing (where
applicable) and galvanizing the guardrails, complete with posts, spacer blocks, bolts, nuts, washers and reinforcing plates as may be required, and
excavating or making holes in all classes of material, concrete, backfilling and removing any surplus material. It shall also include full compensation
for incidentals in respect of supplying and erecting guardrails, end treatments, crash cushions, etc. as applicable.
Where end treatments are specified not to comply with EN 1317 or AASHTO MASH or NCHRP350 as alternative where no MASH product is
available, but as indicated on drawings or specified by the Engineer, measurement and payment shall be made under item C11.4.1.2 or C11.4.9.
Reflective plates and drilling and blasting of holes will be paid for separately.
Drilling and blasting will be paid for separately under item C11.4.11.
Item Description Unit
C11.4.3.3 Installation and removal of precast concrete barrier system (reference to drawing) number (No)
C11.4.3.4 Relocating or stacking precast barrier moved in excess of 1,0 km number (No)
The unit of measurement for items C11.4.3.1 and 2 shall be the metre of concrete balustrade constructed in place or precast in accordance with
the drawings and specifications in Section A13.8 of Chapter 13.
The unit of measurement for item C11.4.3.3 shall be the number precast units installed, initially and subsequently, and removed as instructed by
the Engineer, with installation and removal of precast units measured once only for any instructed location or position.
The tendered rate shall include full compensation for furnishing all materials and labour for installing and removal of precast units complete with
bolts, nuts, washers and reinforcing plates as may be required.
The unit of measurement for item C11.4.3.4 shall be the number of units moved in excess of 1,0 km, which each precast unit has been transported,
either for re-installation or for stacking.
Loading and hauling, where applicable, including a haul of 1,0 km, shall be measured and paid as specified in Section C1.7 of Chapter 1.
The tendered rate shall include full compensation for furnishing all materials labour equipment and transport required to relocate precast units of
all sizes for re-use or stacking, including all costs related to stacking the units.
C11.4.4.1 Extra over C11.4.1 and C11.4.11 for horizontally curved guard rails factory bent to a radius metre (m)
of less than 45 m
C11.4.4.2 Extra over C11.4.2.1(a) for horizontally curved guard rails factory bent to a radius of less metre (m)
than 45 m
The unit of measurement shall be the metre of curved guardrail specified and erected and measured in place.
The tendered rate extra over the rates tendered for items C11.4.12 and C11.4.11 or C11.4.2.1(a) shall include full compensation for all incidentals
in respect of supplying and erecting curved guardrails of radius less than 45 m.
Item Description Unit
The unit of measurement for additional guardrail posts shall be the number erected over and above those erected in accordance with the normal
spacing shown on the drawings.
The unit of measurement for item C11.4.5.3 shall be the number of holes specified to be excavated using labour enhanced methods.
The tendered rates of items C11.4.5.1 and C11.4.5.2 shall include full compensation for supplying and installing additional posts complete as
specified, excavating the necessary holes, erecting the posts, and backfilling the holes.
The tendered rate of item C11.4.5.3 shall include full compensation for excavating the necessary holes using labour enhanced construction methods
and shall be paid as an extra over items C11.4.5.1 and C11.4.5.2.
Drilling and blasting will be paid for separately under item C11.4.11.
The unit of measurement for sub item C11.4.8.1 shall be the metre of single guardrail, whether straight or curved, or end units painted as specified,
the length of which shall be measured in accordance with the measurements of the guardrail elements after dismantling.
The unit of measurement for subitem C11.4.8.2 shall be the number of treated posts.
The tendered rates shall include full compensation for the work as specified in Clause A11.4.7.2b), surface preparation, applying all the coats of
paint, repairing any damaged surfaces, and all materials and construction plant necessary for completing the work including the loading,
transporting to and from the workshops, off- loading and storing of the material.
C11.4.9.3 Extra over C11.4.9.1 and C11.4.9.2 for excavating holes of posts using labour enhanced metre (m)
methods
The unit of measurement of items C11.4.9.1 and C11.4.9.2 shall be the metre of single or double guardrail re-erected with used and/or new material
and measured between the points where they are joined to the end units.
The unit of measurement for item C11.4.9.3 shall be the metre of guardrail system erected with holes specified to be excavated using labour
enhanced methods.
The tendered rates of items C11.4.9.1 and C11.4.9.2 shall include full compensation for re-erecting the guardrails as specified in Clause
A11.4.7.3c), including the loading, transporting between any two points on the site and off-loading the material and providing new fixing material.
Payment shall be made separately for any new material required, including spacer blocks, but not for other fixing materials. Where sections are
made entirely from new material, payment therefore shall be made under the appropriate items for new guardrails.
The tendered rate of item C11.4.9.3 shall include full compensation for excavating the necessary holes using labour enhanced construction methods
C11.4.10.6 Extra over C11.4.10.4 and C11.4.10.5 for excavating holes of posts using labour enhanced number (No)
methods (soft and intermediate)
The unit of measurement shall be the number of end treatments installed with recovered and, in part, new material.
The tendered rates shall include full compensation for installing the end treatments and for all excavation and backfill, providing all anchors, fixing
materials and anchor blocks but excluding costs for steel and timber materials.
Apart from anchors, anchor blocks and fixing materials, payment will be made separately for all new materials. End treatments made completely
from new materials shall be paid for in accordance with the appropriate rates for new end treatments.
The tendered rate of item C11.4.10.6 shall include full compensation for excavating the necessary holes using labour enhanced construction
methods and shall be paid as an extra over items C11.4.10.4 and C11.4.10.5 per number of end treatments
C11.4.11 New material required for the re-erection guardrails with recovered materials:
C11.4.11.6 Splice bolt complete with nut and washer compliant to SANS 1350 number (No)
C11.4.11.7 Post bolt complete with nut and washer compliant to SANS 1350 number (No)
C11.4.12 Extra over items C11.4.1 and C11.4.2 for drilling and blasting holes for guardrail posts number (No)
The unit of measurement shall be the number of holes drilled and blasted with explosives in hard material, which cannot be excavated except by
drilling and blasting, or with the use of pneumatic tools or mechanical breakers.
The tendered rate shall include full compensation for additional work including amongst others all drilling, explosives, materials, labour and
equipment and all Incidentals required for making holes in hard materials by means of drilling and blasting.
C11.4.13 Steel base plates for guardrail posts on structures number (No)
The unit of measurement is the number of steel base plates installed complete as shown on the drawings or directed by the Engineer.
The tendered rate shall Include full compensation for supplying all labour, materials, equipment and transport required for manufacturing,
galvanizing and installing the base plates complete with cement mortar pad, for cutting the guardrail post to the required length, drilling an additional
C11.4.14 Nailing of gang nail plates on top of timber guardrail posts number (No)
The unit of measurement shall be the number of gang-nail plates supplied and fixed as specified.
The tendered rate shall include full compensation for supplying all materials and labour and for fixing to the top of the sealed guardrail post.
The unit of measurement shall be the metre of guardrail section, regardless of condition, disposed of, and the length shall be measured between
the terminals points of the sections removed. Item C11.4.15.1 shall include end wings, bull noses and bridge adapters but exclude the end
treatments.
The tendered rate may be positive or negative as assessed by the Contractor. The tendered rate shall include full compensation for the removal
from site and disposal of the guardrails, poles, spacer blocks, bolts and nuts as scrap including loading, transporting and off-loading. A full record
of the destination of guardrails disposed of shall be provided to the Engineer for control purposes.
Removal of the guardrails shall be measured and paid under item C11.4.7.
CONTENTS
D11.4.1 SCOPE
D11.4.2 GENERAL
D11.4.1 SCOPE
Refer to Clause A11.4.1 for performance based systems which comply to the EN 1317 and/or AASHTO MASH or NCHRP350 as alternative where
no MASH product is available.
D11.4.2 GENERAL
Reflective sheeting suppliers for reflector plates shall supply an official test report as per the requirements of SANS 1519-1.
CONTENTS
PART A: SPECIFICATIONS
A11.5.1 SCOPE
A11.5.2 DEFINITIONS
A11.5.3 GENERAL
A11.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.5.5 MATERIALS
A11.5.6 CONSTRUCTION EQUIPMENT
A11.5.7 EXECUTION OF THE WORKS
A11.5.8 WORKMANSHIP
A11.5 FENCING
PART A: SPECIFICATIONS
A11.5.1 SCOPE
This Section covers the erecting of new fences and associated works, the repair or improvement of existing fences and moving of existing fences
where necessary along the boundaries of the road reserve and elsewhere as indicated on the drawings or as specified by the Engineer. Also
included shall be the erection of temporary fences as well as the removal and stacking of fencing where specified by the Engineer.
Except when otherwise specified or approved, new or temporary fences shall be erected before construction on a particular section of the road is
commenced with, before other properties are occupied for construction related work, or before temporary bypasses are opened to traffic. The
requirement to ensure the safety of road users and protection of property and other rights of the public against access over property lines by
vehicles, pedestrians and animals shall be enhanced by functional fences installed and maintained at the appropriate time and position.
A11.5.2 DEFINITIONS
No specific definitions are applicable.
A11.5.3 GENERAL
The Engineer and Employer shall identify and point out any cadastral beacons to the Contractor prior to any clearing or digging of holes is
undertaken for fencing purposes. Any disturbed or removed cadastral beacons shall only be replaced by a registered Land Surveyor. Cadastral
beacons shall be clearly demarcated to avoid disturbance.
A11.5.5 MATERIALS
A11.5.5.1 General material specifications
The material specifications are the required specifications for the materials as placed and/or processed in its final position within the road reserve.
It is the Contractor’s responsibility to ensure that the materials delivered to the road shall meet these specified requirements and that proof of
compliance is retained.
Materials removed under this Section from existing works, except where excavated materials are specified to be reused or disposed of, or except
where provision has been made in Part C for their reuse or specific disposal.
A11.5.5.4 Wire
Barbed wire shall comply with the requirements of SANS 675 for class A zinc coating, and shall be one or more of the following types:
High-tensile-grade steel single-strand 3,15 mm x 2,50 mm oval-shaped zinc-coated wire, with a 2,82 mm equivalent diameter and with a 1,8 mm
diameter barb
High-tensile-grade steel single strand 2,80 mm x 1,90 mm oval-shaped zinc-coated wire, with a 2,31 mm equivalent diameter and with a 1,6 mm
diameter barb. This shall not be used below 500 mm above ground where there is risk of veld fire such as where the dry grass density exceeds
1,0 kg per square metre.
Mild-steel-grade zinc-coated double-strand uni-directional-twist wire, each strand 2,50 mm in diameter with a 1,8 mm diameter barb, for use at any
height above ground.
Barbs shall be spaced at a maximum of 150 mm apart.
Smooth wire shall comply with the requirements of SANS 675 for class A zinc coating and shall be of the types specified below:
Straining wire high-tensile-grade steel 4,0 mm diameter zinc-coated wire for use at any height above ground.
Fencing wire high-tensile-grade steel 2,24 mm diameter zinc-coated wire for use above 500 mm above ground where there is a risk of veld fire.
Tying wire shall comply with the requirements of SANS 675 for class A zinc coating and shall be 2,50 mm diameter mild-steel zinc-coated wire for
tying fencing wire to standards and droppers and 1,6 mm mild-steel zinc-coated wire for tying netting and mesh wire to the fencing wire.
The actual diameter of wire supplied shall equal the specified diameter subject to the appropriate tolerance given in SANS 675.
A11.5.5.8 Gates
Gates shall be manufactured to the dimensions and details shown on the drawings.
Gates shall be complete in every respect, including hinges, washers, bolts and locking chains attached to the gate.
Gates shall be zinc-coated as specified in SANS 121, or painted as specified in Section A13.10 of Chapter 13, or as indicated on the drawings.
A11.5.5.11 Concrete
All concrete work shall be carried out in accordance with the requirements of Section A13.4 of Chapter 13, read together with the provisions of
Clause A11.1.5.4.
A11.5.8 WORKMANSHIP
The completed fence shall be plumb, taut, true to line and ground contour, with all posts, standards and stays firmly set. The height of the lower
fencing wire above the ground at posts and standards shall not deviate by more than 25 mm from that shown on the drawings. Other fencing wires
shall not deviate by more than 10 mm from their prescribed vertical positions.
The Contractor shall, on completion of each section of fence, remove all off-cuts and other loose wire or netting, poles and concrete so as to not
create a hazard to grazing animals or a nuisance to the owners or occupiers of the properties.
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular layer for which it will be used.
The Engineer may, at his discretion, elect to use the Contractor’s test results if he is satisfied that the Contractor has complied with the process
control requirements.
Any work or materials which do not comply with the specified requirements, shall be removed and replaced with work or materials which comply
with the requirements or, if the Engineer so agrees, shall be repaired so that it shall comply with the specified requirements after having been
repaired.
CONTENTS
B11.5.1 SCOPE
B11.5.2 DEFINITIONS
B11.5.3 GENERAL
B11.5.5 MATERIALS
B11.5.1 SCOPE
This Section covers the erecting of new fences, the repair or improvement of existing fences and moving of existing fences where necessary along
the boundaries of the road reserve and elsewhere as indicated on the drawings or as specified by the Engineer. It shall also include the erection
of temporary fences as well as the removal of fencing where specified by the Engineer.
The construction and removal of fencing shall be deemed to be a labour enhanced construction process.
This Section therefore includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A.
B11.5.2 DEFINITIONS
The provisions of Part A shall apply.
B11.5.3 GENERAL
The provisions of Part A shall apply.
B11.5.5 MATERIALS
The provisions of Part A shall apply.
B11.5.8 WORKMANSHIP
The provisions of Part A shall apply.
C11.5.1.2 Zinc-coated smooth wire (grade and size Indicated) kilometre (km)
C11.5.1.7 Standards (material, protection, length, diameter and type indicated) number (No)
C11.5.1.8 Droppers (material, protection, length, diameter and type indicated) number (No)
(a) Vertical
(i) Steel straining posts (type, size and length and whether galvanized or painted indicated) number (No)
(ii) Timber straining posts (protection, length and diameter indicated) number (No)
(b) Inclined
(i) Steel stays and anchors (protection, length, diameter and wall thickness indicated) number (No)
(ii) Timber stays and anchors (protection, length and diameter indicated) number (No)
(iii) Wire stays and anchors (diameter and type indicated) number (No)
(c) Horizontal
(i) Steel stays and anchors (protection, length, diameter and wall thickness indicated) number (No)
(ii) Timber stays and anchors (protection, length and diameter indicated) number (No)
(iii) Wire stays and anchors (diameter and type indicated) number (No)
C11.5.1.10 Extra over items C11.5.1.3; C11.5.1.4 and C11.5.1.6 for stone packing metre (m)
C11.5.1.11 Extra over items C11.5.1.3; C11.5.1.4 and C11.5.1.6 for trenching metre (m)
The quantity of material used shall be determined by measuring the quantities of individual Items of material used in the completed fence. The
linear measurement of the completed fence shall not apply.
The appropriate units of measurement are as follows:
• Straining posts
The unit of measurement shall be the number of posts, vertical; inclined or horizontal, as follows:
All straining posts erected in accordance with the maximum specified spacing or such lesser spacing as authorised by the Engineer, all corner
posts and posts at bends authorised by the Engineer, and all end posts. Wire cross bracing between vertical posts shall not be measured separately
and the cost thereof be deemed to be included in the rate for the posts.
• Standards and droppers
The unit of measurement shall be the number of standards and droppers erected to the maximum specified spacing or such lesser spacing as
authorised by the Engineer.
• Fencing wire (items C11.5.1.1 and C11.5.1.2)
The unit of measurement shall be the kilometre of each type of fencing wire measured between end posts. Tying wire and wire used for anchoring
the posts shall not be measured for payment.
• Diamond mesh, wire netting and hinge joint mesh (items C11.5.1.3; C11.5.1.4 and C11.5.1.6)
The unit of measurement shall be the square metre of diamond mesh, wire netting or hinge joint mesh, the quantity of which shall be calculated
C11.5.3.1 Fences:
C11.5.4.1 Fences:
C11.5.7 Drilling and blasting holes for posts and anchors number (No)
The unit of measurement shall be the number of holes for posts and anchors made by drilling where excavation by hand or by pneumatic tools
cannot be done economically.
The tendered rate shall include full compensation for drilling and blasting the holes and for all other expenses in connection with providing, storing,
transporting and using explosives.
C11.5.8.2 Mild steel pipes (diameter and wall thickness indicated) metre (m)
The unit of measurement shall be the metre of post of each type installed.
The tendered rate shall include full compensation for procuring, furnishing and fixing the posts, complete as specified and as shown on the drawings.
CONTENTS
D11.5.1 SCOPE
D11.5.2 GENERAL
CONTENTS
PART A: SPECIFICATIONS
A11.6.1 SCOPE
A11.6.2 DEFINITIONS
A11.6.3 GENERAL
A11.6.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.6.5 MATERIALS
A11.6.6 CONSTRUCTION EQUIPMENT
A11.6.7 EXECUTION OF THE WORKS
A11.6.8 WORKMANSHIP
A11.6.2 DEFINITIONS
No specific definitions.
A11.6.3 GENERAL
No general specifications.
A11.6.5 MATERIALS
A11.6.5.1 General material specifications
The material specifications are the required specifications for the materials as placed and/or processed in its final position within the road reserve.
A11.6.5.2 Materials
a) Structural steel
Structural steel shall comply with the requirements of BS 4360 for the type of steel specified or shown on the drawings. Unless otherwise specified,
channels, square tubes, angle irons and other steel members on the reverse side of the signboards and steel tubes for sign supports shall be
coated In accordance with Clause A11.6.7.2a).
Where specified, all structural steel, including tubes shall be galvanized in accordance with the requirements of SANS 121
Steel tubes shall comply with the requirements of SANS 657.
b) Bolts, nuts and rivets
Steel bolts and nuts shall comply with SANS 135 or SANS 1143. Aluminium bolts and nuts shall be manufactured from alloy B51S or D65S.
Stainless steel bolts, nuts and fasteners shall comply with SANS 1700-5-8, SANS 1700-5-9 or SANS 1700-5-10.
All steel bolts, nuts and washers shall have a hot-dip (galvanized) zinc coating, which complies with the requirements of SANS 121.
Blind rivets used for fixing road signboards to square tubing framework shall be 4,8 mm diameter rivets of sufficient length manufactured from or
coated with a material that prevent corrosion to the rivets or fastened members through electrolytic action. Hardened blind or aluminium rivets shall
be used for attaching aluminium sections.
c) Steel plate and steel profiles
• Steel plate
Steel plate for road signs, prior to the application of any reflective sheeting or painting, shall be 1,4 mm thick Z275 galvanized steel plate, which
has been treated on both sides to the paint system requirements specified inn Table A11.6.5-1.
Table A11.6.5-1: Steel plate paint system requirements
Property Test conditions Method Values
Resistance to UV Weathering QUV-A ASTM G154 After 2000 hrs:
(Colour Change) ISO 7724/1/2/3 ∆E < 2
Resistance to UV Weathering QUV-A ASTM G154 After 2000 hrs:
(Chalking ASTM D659-04 Rating No 8
Resistance to corrosion: Salt Spray ISO 7253 After 1000 hrs:
- Edge creep ASTM D1654 8 mm max
- Blister size ISO 4628/2 2-S2
Bending ASTM D4145 3T, No adhesion loss
Impact resistance ISO 6272 No adhesion loss
Pencil Hardness ASTM D3363 F–H
Scratch Hardness ISO 1518 25-40 N
Dry Film Thickness ISO 2808, 5B Top surface:
38 µm minimum
inclusive of primer
Bottom surface:
20 µm minimum
inclusive of primer
Specular Gloss at 60° At time of coating ISO 2813 25 – 35 %
The reverse side of a STOP sign R1 and all its derivatives shall be painted white. The reverse side of all other signs shall be dark grey.
Where a non-reflectorised road sign is required, its reverse side shall be painted with a dark grey prime coat and the face with only the specified
topcoat.
• Steel profiles
Standard sign profiles shall be 200 mm steel sections with a thickness, prior to the application of any reflective sheeting or painting, be 1,0 mm
thick Z275 galvanized steel plate, which has been treated on both sides to the paint system requirements specified in Table A11.6.5-1), and shall
comply with the details on the drawings.
d) Other plate material
Temporary roadworks delineators signs TW401 and TW402 shall be manufactured from a flexible material and shall comply with the requirements
of SANS 1555. These signs shall either bend or break under vehicular impact and cause minimal damage to vehicles on impact with them. Steel
shall not be used in either the signs or the footings.
Other plate material shall be as specified in the Contract Documentation.
e) Aluminium and aluminium composite
Aluminium flat plate shall be manufactured from grade 5251.H.3 alloy and shall comply with the requirements of BS 1470 and shall be 2,0 mm in
thickness.
Aluminium composite shall be a minimum of 3,0 mm thick composite flat plate, comprising a polyethylene core and two bonded aluminium cover
sheets (AlMg1, EN AW-5005 A alloy), each measuring 0,3 mm inn thickness, with a traffic grey modified polyester system lacquer coating, and
The use of materials from different manufactures or different batches for the same colour shall not be used on any one sign.
Materials from different manufacturers shall not be overlaid without specific approval of the Engineer and subject to such conditions as the Engineer
may impose.
The material shall be supplied with a pressure sensitive adhesive backing protected by a removable lining.
h) Timber posts for road sign supports
Timber posts for road sign supports shall conform to the requirements of SANS 754, shall be equal to or better than strength group B timber posts
and shall be affixed with the SABS mark. The posts shall be treated as specified in Clause A11.4.5.2b)(i). The exposed surface of any cut shall be
given two coats of the specified preservative. Any holes drilled in the timber posts after treatment with the preservative shall be re-treated.
i) Corrosion-protection tape
Corrosion-protection tape used between aluminium and steel shall be a black PVC tape not less than 0,25 mm in thickness, shall be resistant to
ultra-violet rays, and shall have an adhesive backing. The breaking strength of the material shall be more than 3,5 kN/m.
j) Silkscreening and digital printing
Silkscreen or digital printed materials shall comply with the requirements of SANS 1519-1 and the screening or printing of road signs shall only be
acceptable after verification of endorsement by the manufacturer of the retro-reflective material to provide an equal or better service life to the
specified retro-reflective material
k) Black vinyl
Black vinyl material shall provide an equivalent warranty as the lowest class of retro reflective material used on a road sign. Black vinyl shall comply
with the requirements for non-reflective sheeting in SANS 1519-1.
l) Concrete
All concrete work shall be carried out in accordance with the requirements of Section A13.4 of Chapter 13, read together with the provisions of
Clause A11.1.5.4.
m) Alternative materials
Alternative materials for road signage elements may be specified in the Contract Documentation.
A11.6.8 WORKMANSHIP
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular layer for which it will be used.
A copy of the process control test results shall be submitted to the Engineer for comments.
CONTENTS
B11.6.1 SCOPE
B11.6.2 DEFINITIONS
B11.6.3 GENERAL
B11.6.5 MATERIALS
B11.6.8 WORKMANSHIP
B11.6.1 SCOPE
This Section covers the supply of permanent and temporary road signs and the erection of permanent traffic signs alongside and over the
carriageway, ramps and crossroads at intersections, and interchanges, and at the locations indicated on the drawings or as directed by the Engineer.
The construction of road signs shall be deemed to be a labour enhanced construction process.
This Section therefore includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A.
B11.6.2 DEFINITIONS
The provisions of Part A shall apply.
B11.6.3 GENERAL
The provisions of Part A shall apply.
B11.6.5 MATERIALS
The provisions of Part A shall apply.
B11.6.8 WORKMANSHIP
The provisions of Part A shall apply.
(b) Area exceeding 0,5 m2 but not 2,0 m2 square metre (m2)
(a) Area 0 to 0,5 m2 (indicate plate thickness, 2,0 or 3,0 mm) square metre (m2)
(b) Area exceeding 0,5 m2 but not 2,0 m2 (indicate plate thickness, 2,0 or 3,0 mm) square metre (m2)
(c) Area exceeding 2,0 m2 but not 10 m2 (3,0 mm plate thickness) square metre (m2)
(b) Area exceeding 0,5 m2 but not 2,0 m2 square metre (m2)
(b) Area exceeding 0,5 m2 but not 2,0 m2 square metre (m2)
(b) Area exceeding 0,5 m2 but not 2,0 m2 square metre (m2)
(a) 600 mm diameter (signboard material, background and symbol retro-reflective class indicated) number (No)
(b) 900 mm diameter (signboard material, background and symbol retro-reflective class indicated) number (No)
1200 mm diameter (signboard material, background and symbol retro-reflective class
(c) number (No)
indicated)
(a) 600 mm diameter (signboard material, background and symbol retro-reflective class indicated) number (No)
(b) 900 mm diameter (signboard material, background and symbol retro-reflective class indicated) number (No)
1200 mm diameter (signboard material, background and symbol retro-reflective class
(c) number (No)
indicated)
C11.6.1.9 Warning signs, permanent
(a) 600 mm size (signboard material, background and symbol retro-reflective class indicated) number (No)
(b) 900 mm size (signboard material, background and symbol retro-reflective class indicated) number (No)
(c) 1200 mm size (signboard material, background and symbol retro-reflective class l indicated) number (No)
(d) 1500 mm size (signboard material, background and symbol retro-reflective class l indicated) number (No)
(a) 600 mm size (signboard material, background and symbol retro-reflective class indicated) number (No)
(b) 900 mm size (signboard material, background and symbol retro-reflective class indicated) number (No)
(c) 1200 mm size (signboard material, background and symbol retro-reflective class indicated) number (No)
(d) 1500 mm size (signboard material, background and symbol retro-reflective class indicated) number (No)
C11.6.1.11 Supplementary plates to permanent regulatory or warning signs (signboard material, square metre (m2)
background and symbol retro-reflective class indicated)
C11.6.1.12 Supplementary plates to temporary regulatory or warning signs (signboard material, square metre (m2)
background and symbol retro-reflective class indicated)
The unit of measurement for items C11.6.1.1 to 5 and C11.6.1.11 and C11.6.1.12 shall be the square metre of completed road signboard.
The unit of measurement for items C11.6.1.7 to C11.6.1.10 shall be the number of regulatory or warning road signs provided and installed as
specified.
The tendered rate for items C11.6.1.1 to C11.6.1.5 and items C11.6.1.7 to C11.6.1.12 shall include full compensation for procuring and furnishing
all the materials, and for manufacturing and supplying the completed road signboard, including amongst others the supporting framework,
reinforcement, cross bracing, struts, fixing brackets, angle-irons, channel profiles, galvanizing (if specified), painting, retro-reflective or semi-matt
black lettering, symbols, numbers, arrows, emblems and borders, for attaching the road signboard to a road sign support structure and for all
materials, equipment, labour, supervision, nuts, bolts, transport, handling, etc necessary for the manufacture, completion, delivery, installation of
the road sign board complete as specified, and the removal and disposal of all vegetation obstructing the motorists’ view of the new or replaced
sign board. Payment for road sign supports shall be made under item C11.6.3, except for temporary road sign removal and re-erection which is
paid for under traffic accommodation items.
Payment shall distinguish between road signboards made from the various sign board materials specified.
The tendered rate for item C11.6.1.6 shall include full compensation for all additional costs for working at height over trafficked or un-trafficked road
lanes in attaching road signboards to overhead gantry structures or bridges.
C11.6.2.2 Lettering, symbols, numbers, arrows, emblems and borders of retro-reflective material:
C11.6.3.1 Steel tubing (diameter and wall thickness indicated) ton (t)
Timber supporting structures will not be paid for until the break-away holes have been drilled and treated as specified.
C11.6.4.1 Kilometre markers on posts (type and post indicated and reference to drawings) number (No)
C11.6.4.2 Replace marker boards on existing kilometre posts square metre (m2)
The unit of measurement for item C11.6.4.1 shall be the number of kilometre markers on posts provided and erected in accordance with the
drawings. Excluded from this item shall be concrete kilometre marker posts measured under item C11.3.2 and C11.3.3. Markerboards shall be
assembled by the supplier prior to delivering on site.
The tendered rate shall include full compensation for all the labour and material, painting, lettering, posts, excavation, backfilling with soil or concrete,
etc, as may be necessary for completing the work in accordance with the details shown on the drawings.
The unit of measurement for item C11.6.4.2 shall be the number of reference marker boards provided and attached to existing kilometre posts in
accordance with the drawings.
The tendered rate shall include full compensation for the manufacturing and supplying of the completed marker boards, for attaching the marker
board to existing posts along the route and for all materials equipment, labour, nuts and bolts necessary for attaching the marker board as specified.
C11.6.5.2 Excavating soft or intermediate material and backfilling using labour enhanced construction cubic metre (m3)
methods
C11.6.5.3 Extra over item C11.6.5.1 and 2 for cement-treated soil backfill cubic metre (m3)
C11.6.5.4 Extra over item C11.6.5.1 for hard material excavation cubic metre (m3)
C11.6.5.5 Imported backfill material from commercial sources cubic metre (m3)
The unit of measurement for items C11.6.5.1 and C11.6.5.2 shall be the cubic metre of excavation measured in place according to the neat
dimensions of the footings or excavations as shown on the drawings or directed by the Engineer. In the case of timber posts not in concrete, the
plan area of the excavated hole shall be taken as 0,36 m2, irrespective of the actual size of the excavated hole.
Excavation shall be done using conventional construction methods and/or labour enhanced construction methods as specified and measured.
The tendered rate shall include full compensation for excavating, backfilling and compacting the backfill material, for the disposal of all surplus
excavated material, and for providing the backfill material.
The unit of measurement for item C11.6.5.3 shall be the cubic metre of excavation backfilled with cement-treated soil, measured as specified for
item C11.6.5.1 and C11.6.5.2.
The tendered rate shall include full compensation for the additional cost of providing and mixing in cement in the backfill material.
The unit of measurement for item C11.6.5.4 shall be the in situ cubic metre of hard material excavated within the excavation limits specified in item
C11.6.5.1
C11.6.6 Dismantling, storing and re-erecting road signs with a surface area of:
C11.6.6.2 Area exceeding 0,5 m2 but not 2,0 m2 square metre (m2)
C11.6.7.1 Dismantling and storing of road signs with a surface area of:
(b) Area exceeding 0,5 m2 but not 2,0 m2 square metre (m2)
C11.6.7.2 Dismantling and storing of overhead signs with a surface area of:
C11.6.8.1 Size 150 x 600 mm (state post type and reflective material) number (No)
C11.6.8.2 Size 200 x 800 mm (state post type and reflective material) number (No)
C11.6.8.3 Size 300 x 1200 mm (state post type and reflective material) number (No)
The unit of measurement shall be the number of danger plates provided and erected in accordance with the drawings in the Contract Documentation.
The tendered rate shall include full compensation for all labour and material, painting, specified posts, excavation, backfilling with soil etc., as may
be necessary for completing the work in accordance with the details shown on the drawings.
C11.6.9.2 Handling cost, profit and all other charges of sub item C11.6.9.1 Percentage (%)
Payment under item C11.6.9.1 for the provision specialist installation of traffic signals shall be made in accordance with the provisions of Chapter
1 and the General Conditions of Contract applicable to Prime Cost Sums.
The tendered percentage under sub-item C11.6.9.2. shall be a percentage of the actual amount spent under sub-item C11.6.9.1 and shall include full
compensation for handling costs, profit and any other costs associated with the specialist installation of traffic signals on site.
C11.6.10.2 Area exceeding 0,5 m2 but not 2,0 m2 square metre (m2)
Note:
Concrete, formwork and reinforcing steel for road sign gantry footings shall be measured and paid for in accordance with the provisions of Section
A13.4 of Chapter 13, but such payment items shall appear under this Section in the schedule of quantities.
CONTENTS
D11.6.1 SCOPE
D11.6.2 GENERAL
D11.6.1 SCOPE
As per Clause A11.6.1.
D11.6.2 GENERAL
The Engineer must ensure that the necessary compliance certificates are provided by the Contractor.
Compliance certification required:
• Affiliation of road sign manufacturer to a recognised traffic sign manufacturer association or being a permit holder under SANS 1519-2.
• Compliance of materials used in road signs to SANS 1519-1.
CONTENTS
PART A: SPECIFICATIONS
A11.7.1 SCOPE
A11.7.2 DEFINITIONS
A11.7.3 GENERAL
A11.7.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.7.5 MATERIALS
A11.7.6 CONSTRUCTION EQUIPMENT
A11.7.7 EXECUTION OF THE WORKS
A11.7.8 WORKMANSHIP
A11.7.2 DEFINITIONS
No specific definitions.
A11.7.3 GENERAL
No general specifications.
A11.7.5 MATERIALS
A11.7.5.1 General material specifications
The material specifications are the required specifications for the materials as placed and/or processed in its final position within the road reserve.
It is the Contractor’s responsibility to ensure that the materials delivered to the road shall meet these specified requirements.
Materials removed under this Section from existing works, except where provision has been made in Part C for their reuse or specific disposal,
shall be deemed to be the property of the Contractor.
A11.7.5.2 Materials
a) Marking materials
The responsibility for the selection of the appropriate road marking materials for road markings to ensure conformance with the requirements of
this specification rests with the Contractor. The road marking materials shall provide the characteristics for retro-reflectivity, luminance, skid
resistance and durability as required in the material specifications.
Where thermoplastic, also known as hot melt plastic, or Methyl Methacrylate (MMA), also known as cold plastic, is used, the Contractor shall obtain
approved certification, from the manufacturer, that the product complies with the specification and submit this certification to the Engineer.
(i) Road marking paint (solvent borne and water borne)
Road marking paint shall be Type 1 as specified in SANS 731-1 for solvent borne paints and SANS 731-2 for water borne paints.
Only paint, manufactured in a SANS approved and accredited facility shall be accepted. The no-pick-up time of road marking paint
shall comply with the Class 1 requirement in accordance with SANS 731-1 and -2.
The paint shall be delivered at the site in sealed containers marked in accordance with the requirements of SANS 731-1 and -2.
The viscosity of the paint shall be such that it can be applied according to the manufacturers recommended guidelines for optimum
performance.
(ii) Retro-reflective road marking
Retro-reflective road marking paint shall comply with the requirements of road marking paint in A11.7.5.2a)(i) above with retro
reflective drop on beads complying with SANS 51423. Unless otherwise specified by the Engineer or in the Contract Documents,
the Contractor may select either solvent or water borne paint.
Determination of coefficient of retro-reflected luminance by means of portable retro-reflectometer shall be carried out using
SANS 6261.
(iii) Thermoplastic road marking material
Thermoplastic road marking material shall comply with the requirements of EN 1436, and SANS 51423 for drop-on glass beads for
road marking and anti-skid aggregates and mixtures thereof. Blending of thermoplastic road marking material and glass beads shall
comply with SANS 51424.
The binder shall be a plasticised synthetic resin and the material shall be reflectorised by mixing in a minimum of 20 % by mass
Class A glass beads in accordance with SANS 51424. An additional topping of drop on glass beads shall be applied to the hot
surface of the material for immediate retro-reflectivity.
The white road marking material shall contain 6,0 % by mass minimum titanium dioxide content and shall have a skid resistance of
45 S.R.T. – units or higher. SABS Method 1248 shall be used for determination of traffic wear index; indication of durability.
The following minimum lumination values are required for the completed road marking for performance based application:
250mcd/m2.lux and 120mcd/m2/lux for white & yellow lines respectively, at 30 days after application.
200mcd/m2.lux and 100mcd/m2/lux for white & yellow lines respectively, at 6 months after application.
Determination of coefficient of retro-reflected luminance by means of portable retro-reflectometer shall be carried out using
SANS 6261. The timing for the application of thermoplastic road marking over previously applied marking during the contract period
shall be carried out as specified in the Contract Documentation.
(iv) Methyl Metacrylate (MMA) Cold Plastic Marking Material
Screed applied cold plastic road marking material shall be used for symbols, arrows and letters (hand painted markings) when
specified by the Engineer and shall consist of a solvent-free two component reactive acrylic resin, stuffing, beads and pigment to
Circular Cats-
Description Bi-directional Bi-directional Bi-directional
Eye
Height above
Road H2-H3 H2-H3 H1 H1
Road stud type and use is classified for the following areas of application:
Road Stud Application 1 (RSA-1): High trafficked center line of narrow roads less than 3,5 m lane width, yellow shoulder line application on single
carriageway roads (1 lane in each direction) where paved shoulder width is wider than 1,5 m.
Road Stud Application 2 (RSA-2): Low to high trafficked centre line application on single carriageway roads (1 lane of at least 3,5 m width in each
direction), and undivided dual carriageways (2 or more lanes in each direction). Low trafficked yellow and all white shoulder line applications on
• The spacing of the road studs will be determined by the road geometry, at least 3-4 road studs should be visible at a time
A11.7.7.6 Protection
After the road marking has been applied, the markings shall be protected against damage by traffic or other causes. The Contractor shall be
responsible for erecting, placing and removing all warning boards, flags, cones, barricades and other protective measures which may be necessary
in terms of any statutory provisions and/or as may be recommended in the SADC and South African Road Traffic Signs Manual.
A11.7.7.8 General
In broken lines the length of segments and the gap between segments shall be as indicated on the drawings. If these lengths are altered by the
Engineer, the ratio of the lengths of the painted section to the length of the gap between painted sections shall remain the same. Lines shall not be
painted more than 3 months prior to the road being opened to public traffic. Where there are risks of previously applied lines wearing through thin
surfacing such as slurries, the new lines shall be applied to match the old lines accurately.
Lines on curves, whether broken or unbroken, shall not consist of chords but shall follow the correct radius. Particularly on curves in the road, and
where roads are widened such as at climbing or passing lanes, the lines shall form continuous single curves without kinks.
The Contractor shall provide a warranty for the road marking, as specified in the Contract Documentation.
Where indicated by the Engineer, the Contractor shall remove existing painted markings from the existing surfaces by means of sand blasting or
as specified by the Engineer. Suitable precautions shall be taken to avoid damage to nearby vehicles or other property during the sand blasting
process.
The use of black paint or chemical paint remover to obliterate existing markings will not be permitted, except where it is specified by the Engineer
as a temporary measure. Where black paint is used, it shall be matt.
A11.7.8 WORKMANSHIP
A11.7.8.1 Faulty workmanship or materials
If any material which does not comply with the requirements is delivered to the site, or is used in the works, or if any work of an unacceptable
quality is carried out, such material or work shall be removed, replaced or repaired as specified by the Engineer at the Contractor's own cost.
Rejected road studs, road markings and paint which has been splashed or dripped onto the pavement, kerbs, structures or other such surfaces,
shall be removed by the Contractor at his own cost, in an approved manner so that the markings or spilt paint will not show up at all.
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of work produced will meet the specified requirements for the particular purpose for which it will be used.
A11.7.8.2 Tolerances
Temporary road marking is generally non removable on final road surfaces and may be over-painted with final road marking of the specified type,
which requires their positioning and spacing to be sufficiently accurate to allow over-painting to meet the required tolerances
Road markings shall be constructed to accuracy within the tolerances given below:
a) Width
The width of lines and other markings shall not be less than the specified width, nor shall they exceed the specified width by more than 10 mm.
b) Position
The position of lines, letters, figures, arrows, retro-reflective road studs and other markings shall not deviate from the true position by more than
100 mm in the longitudinal and 20 mm in the transverse direction.
c) Alignment of markings
The alignment of the edges of longitudinal lines shall not deviate from the true alignment by more than 10 mm in 15 m.
When an unbroken line and a broken line are painted alongside each other, the beginning and the end of the unbroken line shall coincide with the
beginning of one broken line and the end of another broken line. When existing lines are repainted, the new markings shall not deviate more than
100 mm in the longitudinal direction nor 10 mm in the transverse direction from the existing marking.
The alignment of the road studs shall not deviate from the true alignment by more than 10 mm and shall be positioned so that the reflective faces
are within 5 of a right angle to the centre line of the road
d) Broken lines
The length of segments of broken longitudinal lines shall not deviate by more than 150 mm from the specified length.
e) Testing of plant and equipment
Before applying any final road markings, the Contractor shall satisfy himself and the Engineer, by painting test lines on a section of pavement other
than the section required to be marked:
that the painting machine is in good working order and properly adjusted;
that the operator is fully experienced; and
that the machine sprays at the specified rate of paint application.
The Contractor shall bear the cost of all materials and workmanship required for the above plant tests.
In addition, the Contractor shall conduct random paint thickness tests and dip/spread tests as specified by the Engineer.
While work is in progress, tests shall be carried out on materials and/or the quality of work to ensure compliance with the specified requirements.
The sampling methods are specified in SANS 731-1. The sampling methods described in TMH5 shall be followed where applicable.
CONTENTS
B11.7.1 SCOPE
B11.7.2 DEFINITIONS
B11.7.3 GENERAL
B11.7.5 MATERIALS
B11.7.1 SCOPE
This Section covers the marking of the road surface with painted lines and symbols and the supply and fixing of retro-reflective road studs as
indicated on the drawings. This section also covers the removal of existing road studs, and the supply and fixing of temporary road studs as
specified by the Engineer, and the removal of existing road markings. Also included is the painting by hand of kerbs to the colours specified.
This Section therefore includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A.
B11.7.2 DEFINITIONS
The provisions of Part A shall apply.
B11.7.3 GENERAL
The provisions of Part A shall apply.
B11.7.5 MATERIALS
B11.7.5.1 Road marking paint (solvent borne and water borne)
The provisions of Part A shall apply.
B11.7.8 WORKMANSHIP
The provisions of Part A shall apply.
C11.7.1.1 White lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.1.2 Yellow lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.1.3 Red lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.1.4 White lettering and symbols (paint type indicated) square metre (m2)
C11.7.1.5 Yellow lettering and symbols (paint type indicated) square metre (m2)
C11.7.1.6 Red lettering and symbols (paint type indicated) square metre (m2)
C11.7.1.7 Transverse lines, painted island and arrestor bed markings (any colour) (paint type indicated) square metre (m2)
C11.7.1.8 Labour enhanced hand painted white lines broken or unbroken (paint type and width of line square metre (m2)
indicated)
C11.7.1.9 Labour enhanced hand painted yellow lines broken or unbroken (paint type and width of line square metre (m2)
indicated)
C11.7.1.10 Labour enhanced hand painted red lines broken or unbroken (paint type and width of line kilometre (km)
indicated)
C11.7.1.12 Labour enhanced hand painted yellow lettering and symbols (paint type indicated) square metre (m2)
C11.7.1.13 Labour enhanced hand painted transverse lines, painted island and arrestor bed markings square metre (m2)
(any colour) (paint type indicated)
C11.7.1.14 Labour enhanced hand painted kerb markings (any colour) (paint type indicated) square metre (m2)
C11.7.1.15 Labour enhanced hand operated pressure applied machine white lines broken or unbroken kilometre (km)
(paint type and width of line indicated)
C11.7.1.16 Labour enhanced hand operated pressure applied machine yellow lines broken or unbroken kilometre (km)
(paint type and width of line indicated)
C11.7.1.17 Labour enhanced hand operated pressure applied machine red lines broken or unbroken kilometre (km)
(paint type and width of line indicated)
C11.7.1.18 Labour enhanced hand operated pressure applied machine white lettering and symbols square metre (m2)
(paint type indicated)
C11.7.1.19 Labour enhanced hand operated pressure applied machine yellow lettering and symbols (paint square metre (m2)
type indicated)
C11.7.1.20 Labour enhanced hand operated pressure applied machine transverse lines, painted island square metre (m2)
and arrestor bed markings (any colour) (paint type indicated)
Item Description Unit
C11.7.2.1 White lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.2.2 Yellow lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.2.3 Red lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.2.4 White lettering and symbols (paint type indicated) square metre (m2)
C11.7.2.5 Yellow lettering and symbols (paint type indicated) square metre (m2)
C11.7.2.6 Red lettering and symbols (paint type indicated) square metre (m2)
C11.7.2.7 Transverse lines, painted island and arrestor bed markings (any colour) (paint type indicated) square metre (m2)
C11.7.2.8 Hand painted white lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.2.9 Hand painted yellow lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.2.10 Hand painted red lines broken or unbroken (paint type and width of line indicated) kilometre (km)
C11.7.2.11 Hand painted white lettering and symbols (paint type indicated) square metre (m2)
C11.7.2.12 Hand painted yellow lettering and symbols (paint type indicated) square metre (m2)
C11.7.2.13 Hand painted transverse lines, painted island and arrestor bed markings (any colour) (paint square metre (m2)
type indicated)
C11.7.2.14 Hand operated pressure applied machine white lines broken or unbroken (paint type and kilometre (km)
width of line indicated)
C11.7.2.15 Hand operated pressure applied machine yellow lines broken or unbroken (paint type and kilometre (km)
width of line indicated)
C11.7.2.16 Hand operated pressure applied machine red lines broken or unbroken (paint type and width kilometre (km)
of line indicated)
C11.7.2.17 Hand operated pressure applied machine white lettering and symbols (paint type indicated) square metre (m2)
C11.7.2.18 Hand operated pressure applied machine yellow lettering and symbols (paint type indicated) square metre (m2)
The unit of measurement for painting the lines shall be a kilometre of each specified colour and width of line and the quantity paid for shall be the
actual length of line painted in accordance with the instructions of the Engineer, excluding the length of gaps in broken lines.
The unit of measurement for painting the lettering, symbols, transverse lines or painted island and arrestor bed markings per required colour shall
be a square metre, and the quantity to be paid for shall be the actual surface area of lettering. Symbols or transverse lines, painted island and
arrestor bed markings completed in accordance with the drawings and Contract Documentation.
The tendered rate per kilometre or per square metre as the case may be for painting the road markings shall include full compensation for
establishing specialist teams and equipment, and for procuring and furnishing all labour and material, including the retro-reflective beads In the
case of retro- reflective paint, and the necessary equipment, and for painting, protecting and maintenance as specified, including the setting-out of
lettering, symbols and transverse lines, painted island and arrestor bed markings, but excluding setting out and premarking the lines. Separate
rates for different types of application are applicable.
C11.7.3.1 Thermoplastic road marking, broken or unbroken (colour and width of line indicated): kilometre (km)
C11.7.3.2 Performance based thermoplastic road marking, broken or unbroken (colour and width of line kilometre (km)
indicated):
C11.7.3.3 Reduced payment for thermoplastic road marking, white lines, broken or unbroken (width of kilometre (km)
line indicated):
C11.7.3.4 Reduced payment for thermoplastic road marking, yellow lines, broken or unbroken (width of kilometre (km)
line indicated):
The unit of measurement for painting the lines shall be a kilometre of each specified width of line and the quantity paid or deducted shall be the
actual length of line painted in accordance with the instructions of the Engineer, excluding the length of gaps in broken lines.
Full payment of the tendered rate will be applicable upon approved completion of the application of the thermoplastic road marking for items
C11.7.3.1 and C11.7.3.2. The tendered rate per kilometre for the road markings shall include full compensation for establishing specialist teams
and equipment, and for procuring and furnishing all material, including the retro-reflective beads and the necessary labour and equipment, and for
marking, protecting and maintenance as specified, including the setting-out of lettering, symbols and transverse lines, painted island and arrestor
bed markings, but excluding setting out and premarking the lines.
Should the coefficient of retro-reflected luminance fall below the required minimum levels as specified in Clause A11.7.5.2a)(iii), payment will be
deducted against item C11.7.3.2 on the following sliding scale under items C11.7.3.3 and C11.7.3 4. No contract price adjustment will be applicable
to any reduced payment.
White lines:
Below 250mcd /m2.lux at 30 days: minus 10 % of the tendered rate; which shall then be termed the reduced rate.
Below 200 down to 180mcd /m2.lux at 6 months: minus 10 % of the reduced rate
2
Below 180 down to 160mcd/m .lux at 6 months: minus 20 % of the reduced rate
2
Below 160 down to 140mcd/m .lux at 6 months: minus 30 % of the reduced rate
2
Below 140mcd/m .lux: repainting at Contractor’s expense
Yellow lines:
Below 120 down to 100mcd /m2 at 30 days: minus 20 % of the tendered rate; which shall then be termed the reduced rate.
2
Below 100 down to 80mcd/m .lux at 6 months: minus 20 % of the reduced rate
Below 80mcd/m2.lux: repainting at Contractor’s expense
The reduction in the tendered rate applicable for failing to meet the specified minimum luminance level at the 30 days and 6 months measurement
dates shall be applied accumulative in the certificate immediately following the date of measurement
C11.7.4.4 Transverse lines, painted island and arrestor bed markings (any colour) square metre (m2)
The unit of measurement for applying the roadmarking material for the lettering, symbols, transverse lines, islands and arrestor bed markings shall
DRAFT STANDARD (DS) OCTOBER 2020 11-78
be the square metre, and the quantity to be paid for shall be the actual surface area of the lettering, symbols, transverse lines, islands and arrestor
bed markings, completed in accordance with the specifications and on instructions of the Engineer.
The tendered rate per square metre for applying the road marking material shall include full compensation for establishing specialist teams and
equipment, and for procuring and furnishing all material, including the retro-reflective beads and all necessary equipment, and for applying,
protecting and maintenance as specified, including the setting out of lettering, symbols, transverse lines, islands and arrestor bed markings.
The unit of measurement will be for the supply and installation of the pre formed road marking tape on asphalt or concrete surfaces as
specified in Clause A11.7.5.2a)(vi).
Item Description Unit
C11.7.7.1 Permanent road studs compliant to SANS 1442 (type & colours stated) number (No)
C11.7.7.2 Permanent road studs compliant to SANS 1463 (classification & colours stated) number (No)
C11.7.7.3 Temporary road studs compliant to SANS 1442 or 1463 (type/classification & colours stated) number (No)
C11.7.7.4 Solar powered road studs (No of LED’s & colours stated) number (No)
Provisional sum
C11.7.7.5 Provision of temporary and permanent road studs
(Prov Sum)
C11.7.7.6 Handling cost, profit and all other charges of sub item C11.7.7.5 percentage (%)
C11.7.7.7 Installation only of surface bonded road studs with anchor shanks number (No)
C11.7.7.8 Installation only of surface bonded road studs without anchor shanks number (No)
C11.7.7.10 Installation only of temporary stick on road studs (including removal) number (No)
The unit of measurement for installed road studs shall be the actual number of approved road studs placed in terms of the specifications.
The tendered rate for items C11.7.7.1 to C11.7.7.4 shall include full compensation for establishing specialist teams and equipment, and for
procuring and furnishing all the necessary material, labour and equipment, and for fixing and maintenance as specified. Distinction shall be made
between various types of road studs. Payment under item C11.7.7.5 for the provision on site of approved road studs shall be made in accordance
with the provisions of Section C1.5 of Chapter 1 and the General Conditions of Contract applicable to Provisional Sums.
The tendered percentage under item C11.7.7.6 shall be a percentage of the actual amount spent under item C11.7.7.5 and shall include full
compensation for handling costs, profit and any other costs associated with providing the road studs on site.
The unit of measurement for setting out lines shall be the kilometre of lines set out and marked. Where two or three lines are to be premarked for
painted next to each other, and where the centre-to-centre distance between adjacent lines does not exceed 500 mm, the setting-out of all these
lines shall be measured only once.
The tendered rate shall include full compensation for establishing specialist teams and equipment, and for setting out and premarking the lines as
specified, including all necessary equipment, labour and materials.
The unit of measurement shall be the number of times the painting unit is re-established on site on instruction of the Engineer irrespective of the
number of times the road marking team is required to move within the site.
The tendered rate shall include full compensation for the re-establishment on the site and for later removing all painting and road marking units
including the traffic accommodation requirements and special equipment, personnel, etc, as may be required after instruction by the Engineer. The
Contractor will be paid at tender rates for repainting the road markings. Contract price adjustment at the full index values will apply for this item, if
the work is executed after the issue of the Certificate of Completion.
The establishment and re-establishment of road marking teams and equipment on site during the construction period shall not be paid for under
this iitem, and allowance therefore shall be made by the Contractor in his programme and his rates for painting or other general obligation rates.
The rate shall include for any preliminary and general costs applicable after the issue of the Certificate of Completion.
CONTENTS
D11.7.1 SCOPE
D11.7.2 GENERAL
D11.7.1 SCOPE
Refer to Clause A11.7.1.
D11.7.2 GENERAL
a) Prior to applying any road marking on the road, the Contractor needs to provide the following approved certification from the manufacturer:
SANS 731-1 for solvent borne road marking paints
SANS 731-2 for water borne road marking paints
SANS 51423 for drop on beads
EN 1436 for thermoplastic road marking material
SANS 51424 for Class A glass beads
SANS 731-1 or SANS 731-2 for white paint
b) The Contractor shall provide the road stud manufacturer / supplier's installation specifications for all application adhesives to the Engineer,
prior to installation.
CONTENTS
PART A: SPECIFICATIONS
A11.8.1 SCOPE
A11.8.2 DEFINITIONS
A11.8.3 GENERAL
A11.8.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.8.5 MATERIALS
A11.8.6 CONSTRUCTION EQUIPMENT
A11.8.7 EXECUTION OF THE WORKS
A11.8.8 WORKMANSHIP
A11.8.2 DEFINITIONS
A11.8.2.1 Weeds
Any declared weeds or alien invader plants (as listed in the Conservation of Agricultural Resources Act), including any tree, shrub, herb, water
plant or any other plant which, on the instruction of the Engineer, poses any problems in specified areas (such as the road reserve, haul roads,
borrow pits, camp sites, stockpile sites, drainage elements, etc.) at certain times or conditions.
A11.8.3 GENERAL
No general specifications.
A11.8.5 MATERIALS
A11.8.5.1 General material specifications
The material specifications are the required specifications for the materials as placed and/or processed in its final position within the road reserve.
It is the Contractor’s responsibility to ensure that the materials delivered to the road shall meet these specified requirements.
Materials removed under this Section from existing works, except where excavated materials are specified to be reused or disposed of, or except
where provision has been made in Part C for their reuse or specific disposal, shall be deemed to be the property of the Contractor.
• Grass sods
Grass sods shall be either nursery-grown or veld sods as described below. Both types shall be harvested, delivered, planted and watered within
36 hours unless otherwise specified by the Engineer. The grass sods shall be free from weeds and diseases. Sods delivered to the site shall be
moist and shall have at least 30 mm soil thickness for nursery-grown sods and 50 mm soil thickness for veldsods, at the location of planting or
placement. Sods shall also measure a minimum of 400 mm in width and 500 mm in length and shall retain the minimum dimensions once placed
for planting.
• Nursery-grown sods
These sods shall be of the variety of grass specified in the Contract Documentation. The grass shall have been grown specifically for sod purposes,
mown regularly and cared for to provide an approved uniformity to the satisfaction of the Engineer. It shall be harvested by sod cutting machines
to ensure an even depth of cut with sufficient root material and soil.
The sods shall be free of weeds, weed seeds, insects and fungal diseases.
A11.8.7.3 Grassing
After preparing the areas for planting the method of establishing grass shall depend on the circumstances relating to each case, and the Engineer
shall decide which method is to be used.
a) Planting grass cuttings
The areas to be grassed by means of grass cuttings shall, unless already moist, be thoroughly watered before the cuttings are planted to ensure
that the soil will be uniformly moist to a depth of at least 150 mm when the planting is done. This method shall only be used on flat areas, such as
medians.
An approved variety of grass cuttings shall be evenly planted by hand or mechanically at a rate of at least 600 kg of cuttings per hectare and shall
have the root system of the grass cuttings thoroughly planted within the topsoil layer to ensure good growth. No part of the grass root system shall
be left protruding from the topsoil.
Only fresh cuttings shall be used but not any grass cuttings that have been allowed to dry out. Immediately after having been planted, the grass
cuttings shall be given a copious watering.
b) Sodding
Areas to be grassed by sodding shall be given a layer of topsoil of at least 50 mm in thickness unless, where suitable soil is present, the Engineer
orders the topsoil to be omitted. The areas to be sodded shall be thoroughly watered beforehand so that it will be moist to a depth of at least 150
mm during sodding. The surface shall be roughened slightly to ensure a good penetration of roots into the soil. Sods shall be protected against
drying out and kept moist from the time of harvesting until they are finally placed. The handling of the sods shall not result in the sods losing their
prescribed soil thickness.
The first row of sods shall, where possible, be laid in a straight line, and if on a slope, laying the sods shall start at the bottom of the slope. The
sods shall be butted tightly against each other, and care shall be taken not to stretch or overlap the sods. Where a good fit cannot be obtained, any
intervening spaces shall be filled with topsoil. The next row shall be similarly placed tightly against the bottom row with staggered joints, and so on
until the entire area has been covered with sods. Sods shall be laid in such a way that unnecessary trampling over areas previously laid is prevented.
To this end, a diagonal method of laying sods is preferred, moving up the slope and behind previously laid sods. On steep slopes the sods shall
be held in position by a sufficient number of wooden stakes approximately 300 mm long by 20 mm in thickness and these stakes shall be knocked
in to a depth of 100 mm into the subsoil.
Sods laid adjacent to concrete side drains shall be laid in such a manner that the sodding will be 20 mm higher than the concrete. The top surface
of sods laid adjacent to the road pavement shall be 50 mm lower than the road surface. When stripsodding is required, the sods shall be laid in
such a manner that the sods are proud of the surrounding ground level. During stripsodding the areas in between shall be hydroseeded and
A11.8.7.7 General
a) Time for planting
Grass, trees and shrubs shall be planted as far as is practicable during periods of the year most likely to produce best growing results or dependent
on the germination requirements of the seed mixture. The Contractor shall make every effort to programme his operations in such a manner that
grass, trees and shrubs shall, as far as is possible, be planted during this period.
b) Traffic on grassed areas
The Contractor shall not plant any grass until all operations which may require road-building equipment to be taken over grassed areas have been
completed. No road-building equipment, trucks or water carts shall be allowed onto areas which have been grassed and only equipment required
for the preparations of areas, application of fertiliser and spreading of topsoil will be allowed to operate on areas to be grassed. All damaged areas
shall be reinstated by the Contractor at his own expense.
c) Erosion prevention
During construction the Contractor shall protect all areas susceptible to erosion by installing all the necessary temporary and permanent drainage
works as soon as possible and by taking such other measures as may be necessary to prevent the surface water from being concentrated in
streams and from scouring the slopes, banks or other areas.
Any runnels or erosion channels developing during the construction period shall be backfilled and compacted, and the areas restored to a proper
condition. The Contractor shall not allow erosion to develop on a large scale before effecting repairs and all erosion damage shall be repaired as
soon as possible within the contract period. All topsoil or other material accumulated in side drains shall be removed at the same time. Topsoil
washed away shall be replaced.
d) Proprietary brand materials used for erosion prevention
Certain proprietary brands of materials which may be necessary for erosion prevention to enable natural grass to become established shall, if
required, be specified in the Contract Documentation. The method according to which the material is to be applied, the surface preparation required,
the type of material to be provided and the method of payment shall be as specified in the Contract Documentation or in the suppliers specifications.
e) Responsibility for establishing an acceptable cover
Notwithstanding the fact that the Engineer will determine the method of grassing and that the type of seed or grass used and the rate of application
of the seed may be specified or agreed on by the Engineer and that the frequency of mowing will be as specified by him, the Contractor shall be
solely responsible for establishing an acceptable grass cover and for the cost of replanting grass or rehydroseeding where no acceptable cover
has been established. Where however, in the opinion of the Contractor it is doubtful from the outset if it will be possible to establish an acceptable
cover he may inform the Engineer of his reasons therefore, and the Engineer may, if he agrees, either adopt another method of grassing or agree
to accept whatever cover can be obtained, provided that all reasonable efforts shall be made to establish a good grass cover by the proposed
method. Any such agreement shall be valid only if given in writing by the Engineer beforehand.
In the case of grassing by topsoiling only the Contractor will not be held responsible for establishing an acceptable grass cover but will be held
responsible for the consequences of supplying workmanship, which does not conform to the specifications, or for lack of proper care.
f) Refertilising
Should it become necessary, the Engineer may instruct the Contractor to undertake a refertilising programme on grassed areas during the defects
liability period.
Payment for refertilising will be made under the relevant payment item.
g) Weeding
The Contractor shall maintain all areas affected by construction activities free of all weeds. They shall be removed before the seeding stage of
each species. Should the Contractor fail to remove the alien plant species before seeding he shall be held responsible for weed removal within the
affected area, for an additional period of one year, over and above the contractual one year defects liability period.
The method for the removal of weeds shall be either by hand, which shall include the removal of the complete root system, or by chemical means,
through the use of a registered selective herbicide. Only a registered, licensed pest control operator, licensed for the industrial application of
herbicides, shall administer the application of herbicides.
h) Establishment of vegetation within areas disturbed by construction activities
The Engineer shall assess any area within the construction boundaries that has been disturbed by construction activities, but which is not scheduled
A11.8.8 WORKMANSHIP
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced will meet the specified requirements for the particular layer for which it will be used.
The Engineer may, at his discretion, elect to use the Contractor’s test results if he is satisfied that the Contractor has complied with the process
control requirements.
Any work or materials which do not comply with the specified requirements, shall be removed and replaced with work or materials which comply
with the requirements or, if the Engineer so agrees, shall be repaired so that it shall comply with the specified requirements after having been
repaired.
CONTENTS
B11.8.1 SCOPE
B11.8.2 DEFINITIONS
B11.8.3 GENERAL
B11.8.5 MATERIALS
B11.8.8 WORKMANSHIP
B11.8.1 SCOPE
This Section includes all areas affected by construction activities but may also extend to other areas requiring landscaping and planting. It includes
landscaping, grassing, rehabilitation, erosion protections and planting trees and shrubs.
Landscaping and planting shall be deemed to be a labour enhanced construction process.
This Section therefore includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A.
B11.8.2 DEFINITIONS
The provisions of Part A shall apply.
B11.8.3 GENERAL
The provisions of Part A shall apply.
B11.8.5 MATERIALS
The provisions of Part A shall apply.
B11.8.8 WORKMANSHIP
The provisions of Part A shall apply.
C11.8.1 Trimming:
All bulk earth-moving operations as described under shaping in Clause A11.8.7.1a) of Part A shall be measured and paid for under Chapter 5.
The unit of measurement for trimming shall be the square metre of area trimmed on the instruction of the Engineer, including areas trimmed after
having been shaped. No trimming within the road prism including cut and fill slopes shall be measured for payment.
The tendered rates shall include full compensation for trimming the areas to the specified finishing requirements, including the moving of a small
quantity of material which would be inherent in this process and the removal of surplus material and stones. Payment shall distinguish between
machine trimming and hand trimming which shall be specified.
C11.8.2 Trimming using machines for trimming or shaping (alternative to subitem C11.8.1.1):
The unit of measurement shall be the hour actually worked by each machine in trimming or shaping areas, when so specified by the Engineer.
Standing time will not be measured. The tendered rates shall include full compensation for furnishing and using the machines, including the cost
of fuel, operators, maintenance, transporting the machine to and from the point where it is to be used, and for all other Incidentals necessary for
carrying out the work.
Item Description Unit
C11.8.3.3 Topsoiling within the road reserve where the following materials are used:
(a) Topsoil obtained from within the road reserve or borrow areas cubic metre (m3)
(b) Topsoil obtained from commercial sources by the Contractor cubic metre (m3)
C11.8.3.4 Topsoiling of borrowpits by using topsoil obtained from borrow areas or from the road reserve cubic metre (m3)
C11.8.4 Grassing
C11.8.4.1 The planting of grass cuttings (type of grass indicated) hectare (ha)
C11.8.4.3 Hydroseeding:
C11.8.4.4 Planting grass seed with an approved grass-planting machine hectare (ha)
C11.8.5 Watering the grass when established by topsoiling only kilolitre (kℓ)
The unit of measurement for watering areas which have been topsoiled on the Instruction of the Engineer but which have not been hydroseeded
or planted with grass, shall be the kilolitre of water applied on the instructions of the Engineer and calculated from the number of tank loads applied,
multiplied by the capacity of the tank used in each case.
The tendered rate shall include full compensation for procuring, transporting and applying the water as specified.
C11.8.6 Watering the already planted grass, trees and shrubs during the growing season kilolitre (kℓ)
The unit of measurement for watering the grass, trees and shrubs shall be the kilolitre of water used.
The tendered rate shall include full compensation for obtaining, transporting and applying the water.
The Contractor shall keep a careful record of the quantity of water used by him for watering the grass, trees and shrubs planted and shall submit
such Information to the Engineer on a daily basis. When there are times during the normal growing season, as specified in the Contract
Documentation, when the monthly rainfall figure is less than 75 % of the monthly average, the Contractor will be compensated under this item for
the same percentage of the quantity of water used for watering as that for the monthly rainfall that fell short of the average rainfall.
Note:
The rainfall figures and minimum and maximum temperatures for the contract area are set out in the Contract Documentation.
The provisional sum allowed shall be expended at the discretion of the Engineer to cover the cost of work in addition to the scheduled items which
may be required in respect of shaping and trimming areas where plant is used at hourly rates, eg the cost of loading and transporting surplus
material, establishing grass by topsoiling only, repairing erosion damage after topsoil has been applied, or any other Items of work required for
which no pay Items have been provided.
Payment shall be made as specified in applicable the general conditions of contract.
The unit of measurement for weeding all grass-seeded areas and areas that have been topsoiled on the instruction of the Engineer (but have not
been hydroseeded or planted with grass), shall be the hectare.
The tendered rate shall include full compensation for weeding the prescribed areas in accordance with the specifications.
Note:
Measurement and payment for haul shall be as specified in Section C1.7 of Chapter 1, but no haul shall apply to topsoil paid for from commercial
sources.
The unit of measurement shall be the square metre measured within the road reserve and measured each time the Contractor has been instructed
by the Engineer to remove the undesirable vegetation under this pay item. This item shall not include areas of undesirable vegetation that have
occurred within areas affected by construction activities, and which are considered a contractual obligation
The tendered rate shall include full compensation for all plant, equipment, labour and consumables required to effectively remove the undesirable
vegetation, including the entire root system, and disposing by approved means.
CONTENTS
D11.8.1 SCOPE
D11.8.2 GENERAL
CONTENTS
PART A: SPECIFICATIONS
A11.9.1 SCOPE
A11.9.2 DEFINITIONS
A11.9.3 GENERAL
A11.9.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A11.9.5 MATERIALS
A11.9.6 CONSTRUCTION EQUIPMENT
A11.9.7 EXECUTION OF THE WORKS
A11.9.8 WORKMANSHIP
A1.9 FINISHING THE ROAD AND ROAD RESERVE AND TREATING OLD
ROADS
PART A: SPECIFICATIONS
A11.9.1 SCOPE
This Section covers the final finishing and cleaning up of the road and road reserve and all associated works on the site at the completion of
construction, including scarifying and treating old roads, temporary deviations and other temporary works.
Construction may be as new construction, as renewal construction or as a combination of both. When construction includes elements under
Section A1.6 of Chapter 1: Clearing and Grubbing, Chapter 4: Borrow Materials, and Mass Earthworks; and Section A11.8 of Chapter 11:
Landscaping and planting plants, then this Section does not cover the required finishing under those Chapters and Sections.
A11.9.2 DEFINITIONS
No specific definitions.
A11.9.3 GENERAL
No general requirements.
A11.9.5 MATERIALS
A11.9.5.1 General material specifications
There are no general materials specifications as finishing and cleaning results in the collection and removal of surplus and unwanted excess
material, vegetation and construction litter.
It is the Contractor’s responsibility to ensure that the materials vegetation and other litter collected are disposed of, to approved and authorised
waste disposal sites and not to contravene environmental legislative requirements.
A11.9.5.2 Materials
No specific materials required.
A11.9.8 WORKMANSHIP
No specific testing of materials is required.
CONTENTS
B11.9.1 SCOPE
B11.9.2 DEFINITIONS
B11.9.3 GENERAL
B11.9.5 MATERIALS
B11.9.1 SCOPE
This Section covers the final finishing and cleaning up of the road and road reserve after construction and scarifying and treating old roads and
temporary deviations.
This Section includes work with a large component of labour.
This Part B therefore only covers additional specifications for work to enhance the labour component of construction activities where specified in
Part A.
B11.9.2 DEFINITIONS
The provisions of Part A shall apply.
B11.9.3 GENERAL
The provisions of Part A shall apply.
B11.9.5 MATERIALS
The provisions of Part A shall apply.
B11.9.8 WORKMANSHIP
The provisions of Part A shall apply.
CONTENTS
D11.9.1 SCOPE
D11.9.2 GENERAL
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by COTO
on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and Bridge
Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 12: GEOTECHNICAL APPLICATIONS .............................................................................................. 12-1
12.1 PILING ........................................................................................................................................................ 12-1
PART A: SPECIFICATIONS ............................................................................................................................................................................ 12-1
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................. 12-22
PART C: MEASUREMENT AND PAYMENT ................................................................................................................................................. 12-23
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .................................................................................................................... 12-30
CONTENTS
PART A: SPECIFICATIONS
A12.1.1 SCOPE
A12.1.2 DEFINITIONS
A12.1.3 GENERAL
A12.1.5 MATERIALS
A12.1.8 WORKMANSHIP
A12.1 PILING
PART A: SPECIFICATIONS
A12.1.1 SCOPE
This Section covers specifications for design, construction and measurement and payment for various pile types for structures and bridges relating
to roads.
A12.1.2 DEFINITIONS
The following definitions shall apply to these specifications:
Auger bored piles - are those piles formed in holes bored with an auger drilling rig, with or without use of casing.
Continuous flight auger (CFA) piles - are constructed by drilling in a continuous operation, a CFA auger into the ground and, on reaching
required depth, pumping concrete or grout via a pressurised system, also in a continuous-motion, down the hollow stem as the ground-laden
auger is steadily withdrawn.
Full displacement auger piles - are piles constructed by drilling a displacement auger comprising a lower tapered augered portion of the flight,
a central displacement section and an upper auger section with reverse flighting and, on reaching required depth, pumping concrete or grout down
the hollow stem as the auger is steadily withdrawn.
Underslurry Piles - are piles excavated either by auger or grab-excavation (resulting in circular and rectangular cross-sections, termed barrettes)
under a head of bentonite/polymer slurry to prevent collapse of the pile excavation.
Screwed In Casing Auger Piles (SICAP) - are formed by screwing in a temporary casing and later removing internal material with an auger while
at all times maintaining a plug at the base to prevent water ingress. Twin rotary-drive systems may be used in which casings are installed in a
counter-clockwise direction with one drive head and clockwise-rotating augers with another.
Oscillator bored piles - are piles installed in holes bored by oscillating casings with hydraulic rams into the ground and removing spoil as progress
is made. Casings may be temporary or permanent.
Percussion bored piles - are formed by percussion driving segmental-coupled-casings and excavating soil inside the casing with a coring tool.
On attaining a suitable pile depth, a dry-cast bulbous base is formed. The pile may either be formed by filling the empty bore with high slump
concrete while withdrawing the temporary casing or dry mix concrete is pounded as the casing is withdrawn forming a series of bulbs along the
shaft.
Cast in situ piles (DCIS Piles) - are driven piles installed in holes formed by utilising a drop hammer acting on a sand/stone plug within a tube.
At founding level the plug is expelled from the secured tube. A bulbous base is formed by hammering measured quantities of inserted dry mix
concrete until the theoretically calculated energy required to ensure load capacity, is achieved.
Precast piles - are driven precast reinforced concrete piles generally top driven into the ground using hydraulic or drop hammers displacing in
situ soils. They are cast in any suitable cross-section such as square, hexagonal, rectangular or circular.
A12.1.3 GENERAL
A12.1.3.1 Method Statements
Where so indicated by the Engineer the Contractor shall prepare detailed method statements for each facet of the work describing key aspects
such as construction methodology, key plant, materials, personnel as well as any programme constraints of the envisaged construction process.
These method statements shall be prepared and submitted to the Engineer for approval prior to commencement of that activity, within time scales
specified. The onus lies with the Contractor to ensure that the information is obtained and that associated activities are completed expeditiously
to avoid any delays in the commencement, continuation and completion of the required works. Unless otherwise specified or provided for in the
Contract Documentation no permanent works shall be commenced until the Engineer’s approval of the relevant method statement. The Contractor
shall, however, remain responsible for all work-methods, materials, plant and equipment used, notwithstanding acceptance by the Engineer
Trials, if applicable, shall be conducted and based on outcomes thereof, may require that changes be made to the relevant method statements.
The Contractor shall be required to construct test or trial piles and the testing thereof as specified herein and shall make due allowance therefore
in his programme. Allowance shall also be made for allow for the Engineer’s assessment of constructed piles, procedures followed, and materials
and plant utilised and test data. Production anchoring shall not be permitted until it is shown and accepted by the Engineer that the Contractor
possesses the necessary experience, plant and equipment to carry out the works as specified in the Contract Documentation.
In the case of CFA piles, the following additional information shall be furnished in the Contractor’s method statement:
- Expertise of the design Engineer,
- Design methods used to predict serviceability and ultimate load capacity of the piles and load/deflection performance,
- Experience of site supervisors and operators in the form of CV’s and details of similar projects completed.
- Equipment for pile installation, including anticipated pressures at pump and auger toe and,
- Instrumentation for monitoring pile installation.
It should be noted that work shall only be performed by personnel listed by the Contractor. If personnel changes need to be made during the
project, works shall be suspended until replacement personnel are approved by the Engineer. Time lost due to incomplete submissions,
unacceptable submissions, or obtaining approval of replacement personnel will not be considered as cause for extension of time or delay claims.
All costs associated with incomplete, replacement, or unacceptable submissions shall be to the Contractor’s cost.
Once approved in writing by the Engineer, these shall become the method statements in accordance whereby the relevant portion of the works
shall henceforth be executed. Notwithstanding, the Engineer may require revision from time to time if circumstances during construction arise
which warrants change.
A12.1.4.1 Mix design for concrete/grout for piles 6 weeks prior to commencement of
placement
A12.1.7.1
A12.1.4.1 Grout / concrete mix design for CFA pile / micropile construction 6 weeks prior to commencement of
placement
A12.1.4.2
A12.1.7.1
Construction Approvals
A12.1.6.2 Contractor’s method statement for test piles 3 weeks prior to commencement of test
piles
Load testing of piles and review of results 5 weeks after test pile installation
A12.1.7.7b) Contractor’s approved method statement for piling prior to commencement of production
piling
A12.1.7.8a) Details of design and pile driving criteria for precast piles 3 weeks prior to commencement of
piling
A12.1.7.7a) Contractor to notify Engineer when obstructions are encountered Within 24 hours of stoppage
(i) Method 1
The Employer shall check alternative designs, calculate quantities and adjust rates as set out in paragraph 1 of Clause A12.1.3.5
c). The Employer will then pay for work in accordance with actually-measured quantities.
(ii) Method 2
The Employer may use the following formulae for calculating quantities under items C12.1.4 to C12.1.23 for payment:
Np = Nd
Lp = Nd . Ld + Nb(Lb-Ld)K for Nd Nb and
Lp = Nd . Ld + Nd(Lb-Ld)K for Nd Nb
K=Lb/Ld for Ld≥Lb and
K=Ld/Lb for Ld≤Lb
where:
p = paid, d = designed and b = built.
The term "units" means items of work measured and paid for under respective pay items such as piles, raking piles, casings,
under-reams, concrete, etc.
Np = number of "units" measured and finally paid for in a particular pile group.
Nd = number of "units" provided for in the tender for the alternative design in the same pile group.
Nb = number of approved and accepted "units" finally installed in the same pile group.
p = the length of the "units" measured and paid for or the length to be used in calculating quantities which are a direct function of
the length of the "units" for the same pile group.
Ld = the average length of the "units" provided for in the tender for the alternative design in the same pile group.
Lb = the average length of the Nb "units" actually installed in the same pile group.
Note: See the example below for application of formulas
The values Nd and Ld for each pile group for which an alternative design was offered shall be supplied with his tender by the
Contractor for the respective "units".
The values of Nd, Nb, Ld and Lb for each pile group for which are to be used in the formulae for determining the quantity for a
particular pay item shall relate only to the piles where the item is measured.
Nd Nb Lb Nd Nb
K = Ld for Ld > Lb
Np = Nd Np = Nd
Ld
K = Lb for Ld < Lb
Lp = Nd.Ld + Nb(Lb - Ld)K Lp = Nd.Ld + Nd(Lb - Ld)K
A12.1.5.3 Aggregate
Aggregates shall comply with SANS 1083.
A12.1.5.12 Casing
Temporary casings shall be sufficiently thick and rigid so as accommodate piling rig torque and to not deform under the collapse of adjacent soil
prior to concreting or while being extracted during concreting. Where casings may require jacking via hydraulic rams from depth, double wall
casings shall be used.
Permanent casings are usually corrugated steel galvanised liners or steel casings, 4,5 mm or thicker with a nominal ID as specified.
R4 Hard rock Point load tests on recovered borehole core shall be used for distinguishing 25 to 70
between these categories.
These results shall be verified by means of uniaxial/unconfined
R5 Very hard rock compressive-strength tests conducted on samples which have a diameter Greater than 70
of between 50mm and 150mm with lengths greater tan 100mm and which
meet the requirements set out in the Note below.
NOTE: The equipment used shall have a valid calibration certificate and the tests shall be carried out by an approved competent person. Sample
orientation in testing shall be similar to that in penetrating the tested material during piling. Standing time shall not be paid while the results of tests
are awaited.
* Classification after Core Logging Committee, South African Section, Association of Engineering Geologists:
" Guidelines for Soil and Rock Logging in South Africa, 2nd Impression 2002, eds. A.B.A. Brink and R.M.H. Bruin, Proceedings, Geoterminology
Workshop organised by AEG, SAICE and SAIEG, 1990.
A12.1.8 WORKMANSHIP
A12.1.8.1 Tolerances
Unless otherwise specified in Contract Documentation the tolerances given below shall be the maximum permissable deviations from the specified
dimensions, levels, alignment, positions, etc, shown on the drawings of the structures or structural members.
a) Piles:
Position ………………………………………………. 0,167 times the diameter of the pile, or 100 mm, whichever shall be the greater
External dimensions:
Prefabricated piles …………………………………………………………………………….……………………………….. 25 mm ± 5,0 mm
Cast in situ piles …………………………………………………………….………….. plus-tolerance not specified, minus-tolerance 0 mm
Pile head level: Average level
of trimmed /cut pile head …………………………………………………………………………………………….…………………. ± 25 mm
Verticality or rake …………………………………………………………………………………………………….………………………. 1,5 %
Straightness:
For precast piles the maximum deviation from straight is 5,0 mm for piles up to 3,0 m in length and 1,0 mm more for each additional metre of pile
length.
b) Self-drilling micropiles:
(i) Construction tolerances as per SANS 54199 shall be permitted unless otherwise specified in Contract Documentation.
(ii) Those geometrical deviations include the following as per SANS 54199 Section 8.2 and figure 5:
(iii) Plan location of vertical and inclined micropiles measured at working level: ≤ 0.10 m
(iv) The horizontal deflection at the top of the projected micropile cap under ultimate loading shall be limited to 5,0 mm
(v) Deviation from the theoretical axis:
1. Vertical micropiles: max 2 % of the length
2. Inclined micropiles: n ≥ 4, max 4 % of the length
3. Inclined micropiles: n < 4, max 6 % of the length
Any pile outside of these tolerances shall be subject to review by the Engineer and may be rejected or replaced at the Contractor’s expense. Any
re-design necessitated by non- compliance shall be carried out by the Engineer at the Contractor’s cost.
The method used in driving piles shall not subject the piles to excessive or undue abuse producing crushing and spalling of concrete, injurious
splitting, splintering, and brooming of the wood, or deformation of the steel. Misaligned piles shall not be forced into the proper position. Any pile
damaged during driving by reason of internal defects, or by improper driving, or driven out of its proper location, or driven below the designated
cut-off elevation, shall be corrected by the Contractor, without added compensation, by approved methods.
CONTENTS
B12.1.1 SCOPE
B12.1.2 DEFINITIONS
B12.1.3 GENERAL
B12.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.1.5 MATERIALS
B12.1.6 CONSTRUCTION EQUIPMENT
B12.1.7 EXECUTION OF THE WORKS
B12.1.8 WORKMANSHIP
B12.1.1 SCOPE
The provisions of Part A shall apply.
B12.1.2 DEFINITIONS
The provisions of Part A shall apply.
B12.1.3 GENERAL
The provisions of Part A shall apply.
B12.1.5 MATERIALS
The provisions of Part A shall apply.
B12.1.8 WORKMANSHIP
The provisions of Part A shall apply.
The work shall be carried out as instructed by the Engineer and shall be paid for in accordance with the provisions of the general conditions of
contract.
C12.1.3 Establishment on site for piling (piling locations indicated (type indicated) lump sum
The tendered lump sum shall include full compensation for establishment and subsequent removal of all special construction plant and equipment
for piling as specified, structural platforms, rafts as may be required, general levelling of the sites and for carrying out operations, the cost of which
does not vary with actual amount of piling undertaken on the indicated locations on the project.
The work will be paid by a lump sum, 50 % of which will become payable when all the equipment is on site and the first production pile installed.
The second instalment of 25 % of the lump sum will be payable after half the total number of piles are installed, and the final instalment of 25 %
after all the piles are completed and the equipment is removed from the site.
The unit of measurement shall be the number of positions to which installation equipment is moved and set up in position. The quantity measured
shall be the number of piles installed as instructed by the Engineer, including trial and test piles as specified or piles re-driven on the instruction
of the Engineer.
The tendered rate shall include full compensation for all costs involved in the moving and setting up of equipment.
C12.1.6.3 Rock formation (description and class of rock indicated) metre (m)
The unit of measurement shall be the metre of pile hole formed through identified materials, measured from depth at which the identified material
is first encountered to depth at which normal auger drilling or boring may be resumed or another type of identified material is encountered.
The tendered rates shall include full compensation for all additional work and incidentals required for forming pile holes through identified materials.
Notes:
Item C12.1.6.1: The matrix content indicated shall be percentage by volume of matrix in material containing coarse gravel. Where the maximum
percentage indicated is exceeded, payment for forming holes through such material shall be made under item C12.1.5. Unless otherwise specified,
the maximum percentage of matrix shall be 60 %.
Where materials other than those provided for in item C12.1.6 are identified, they shall be described on drawings and/or in Contract
Documentation. Provision therefore shall be made in the schedule of quantities under extensions to item C12.1.6.
C12.1.10 Provision for and maintenance of bentonite head for underslurry piles Lump Sum
The tendered lump sum shall include full compensation for supplying the bentonite, for all equipment for mixing pumping, de-sanding and all other
operations required to complete the task
The tendered rate shall include full compensation for supplying and installing permanent pile casing.
C12.1.13 Extra over items C12.1.5 and v C12.1.7 for raking of piles:
C12.1.13.1 Holes for piles of (diameter and rake indicated) metre (m)
metre (m)
C12.1.13.2 Temporary casing for driven displacement pile systems (diameter and rake indicated)
The tendered rates shall include full compensation for all additional work and incidentals for forming pile holes or for driving and later extracting
of temporary casing.
C12.1.14 Forming bulbous bases for piles of (diameter indicated) number (No)
The tendered rate shall include full compensation for all work conducted in forming the bulbous bases but shall exclude the concrete work.
C12.1.17 Extra over item C12.1.16 for concrete cast underwater cubic metre (m3)
The unit of measurement shall be the cubic metre of concrete cast under water, the quantity being calculated as for item C12.1.16.
The tendered rate shall include full compensation for all additional work, incidentals and extra cement required for placing the concrete under
water.
A provisional sum is allowed in the schedule of quantities for covering cost of this work. The method of payment for work authorised by the
Engineer shall be in accordance with provisions of the general conditions of contract.
The tendered rates shall include full compensation for all additional work and incidentals for installing prefabricated piles to specified rakes.
C12.1.23 Splicing/coupling prefabricated piles for lengthening (size of pile indicated) number (No)
The unit of measurement shall be number of splices/couplings in prefabricated piles for each size of pile.
The tendered rate shall include full compensation for all work required for splicing/coupling piles in accordance with the specifications.
C12.1.24 Stripping/cutting the pile heads (type and diameter/size of pile indicated) number (No)
The unit of measurement shall be the number of heads of each type and diameter/size of pile stripped/cut.
The tendered rate shall include full compensation for providing all tools and stripping/cutting pile heads.
C12.1.25 Establishment on site for the load testing of piles lump sum
The tendered lump sum shall include full compensation for the establishment on site and subsequent removing all special plant and equipment
required for conducting load tests on piles as specified. This cost does not vary with the number of load tests to be conducted. Payment for this
work shall be made by way of a lump sum, 100 % of which will be paid after testing assembly is completely assembled and the first load test
started. Standing time will not be paid in respect of piling activities and for pile installation equipment while pile testing is being carried out and the
results thereof are being assessed.
The unit of measurement shall be the number of load tests conducted on instruction of Engineer, for each specified working load. Test piles shall
be measured as specified above as for permanent piles. Anchor piles and anchors shall be deemed to form part of the testing equipment and
shall not be measured under this item.
The tendered rate shall include full compensation for installing anchor piles and anchors where necessary; conducting load tests, and the
processing and submitting of results.
C12.1.28 Moving equipment to and assembling at each location where cores are to be drilled number (No)
The unit of measurement shall be number of locations to which core-drilling equipment is moved and at which it is assembled.
The tendered rate shall include full compensation for cost of moving and assembling equipment.
The tendered rate shall include full compensation for all fixed costs for the pile-installation frame, which is not connected with its operation and
quantity of work done.
C12.1.31.2 Carrying out of Impact Frequency Response (IFR) measurements or Sonic Tapping tests number (No)
and interpretation of results (per pile diameter)
C12.1.31.3 Cross-Hole Sonic Logging tests and interpreted results (per pile diameter) metre (m)
The unit of measurement for C12.1.31.1 for the 85 mm nominal diameter mild steel tubes shall be the metre of approved 3,0 mm thick tubes provided
and installed into all designated piles of various diameters in accordance with the specification.
The tendered rate shall include full compensation for all materials, plant and equipment required or the installation of the tubes in the designated piles
as specified
The unit of measurement for C12.1.31.2, Impact Frequency Response tests shall be the number of designated piles tested by the IFR method
The tendered rate shall include full compensation for the establishment on site, procurement, preparation, conducting and supervising the tests and
full compensation for the proper evaluation and reporting of the results and findings of the IFR consultant to the Engineer,
The unit of measurement for C12.1.31.3, CSL tests, shall be the metre of pile shaft fully tested (for all designated piles) using the Cross-Hole Sonic
Logging method.
D12.1.1 SCOPE
The scope of this Section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
D12.1.2 GENERAL
The Contractor shall provide detailed specifications, test data, performance data and compliance certificates from independent reputable agencies
for all proprietary systems, processes and materials proposed for use. These shall demonstrate conformance with the performance requirements
specified in the Contract Documentation. Unless otherwise specified, all proprietary materials shall be used and placed in strict accordance with
the relevant manufacturer's current published instructions
CONTENTS
PART A: SPECIFICATIONS
A12.2.1 SCOPE
A12.2.2 DEFINITIONS
A12.2.3 GENERAL
A12.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A12.2.5 MATERIALS
A12.2.6 CONSTRUCTION EQUIPMENT
A12.2.7 EXECUTION OF THE WORKS
A12.2.8 WORKMANSHIP
A12.2.2 DEFINITIONS
The following definitions shall apply to these specifications:
Cable anchor - is a generic term covering all types of wire-strand cable ground anchors which are generally subdivided into rock anchors and
soil anchors. It is an installation which is capable of transmitting an applied tensile load to a stable load bearing stratum. The installation generally
consists of a stressing anchorage, a tendon with an uncoupled/free length and an anchored/ fixed length in the load bearing stratum.
Temporary anchor / Rockbolt / Soil nail / Dowel - installations used during the construction phase of a project to provide support for the period
until the permanent works are in place.
Test Anchor - is an anchor installed according to the Contractor’s proposed method statements whereby the Contractor shall demonstrate both
the suitability of the plant and equipment, the design of the anchors as well as their competency to install the anchors as designed and specified.
The term ‘test anchor’ shall include ‘proving’, ‘trial’ and ‘site suitability’ anchors as referred to elsewhere in this specification and other supporting
documents referred to.
Deadman Anchor - are anchors that have anchorages at both ends of the tendon or bar. One end of the anchor may be permanently fixed into
an anchor block which generally will be buried during construction or may be a retaining structure/element allowing tensioning to be carried out
from the other end. Other types have anchorages at both ends allowing tensioning from either end.
Permanent Anchor / Rockbolt / Soil Nail / Dowel - an installation required to ensure the stability and satisfactory performance of the permanent
works being supported.
Stressing Anchorage - is a component of a ground anchor capable of transferring the tensile load from the tendon to the surface of the ground
or structure requiring support:
- Normal type - An anchorage designed to permit the load in the anchor tendon to be raised or lowered within the entire range of operating
stress levels and measured when necessary to meet the requirements of acceptance testing. This is only possible during the initial stressing
phase as protruding tendons are cut making further measurement or adjustment impossible.
- Re-stressable type - An anchorage meeting all the requirements of the normal anchorage and permitting the load on the anchor tendon,
throughout the life of the support structure, to be measured by check lifting. It also allows small losses of up to 10 % of the working load to
be recovered.
- De-tensionable type - An anchorage meeting all the requirements of the re-stressable type and in addition permitting the anchor tendon to
be de-tensioned in a controlled manner at any time during the life of the anchor.
Fixed Anchor Length - is the designed length of the anchor over which the tensile load is transferred to stable load bearing strata.
Free Anchor Length - is the design length between the proximal end of the fixed anchor length and the stressing anchorage.
Proximal End - is nearest to the stressing anchorage or collar head.
Distal End - is furthest from the stressing anchorage or collar head.
A12.2.3 GENERAL
A12.2.3.1 Method Statements
Where so indicated by the Engineer the Contractor shall prepare detailed method statements for each facet of the work describing key aspects
such as construction methodology, key plant, materials, personnel as well as any programme constraints of the envisaged construction process.
These method statements shall be prepared and submitted to the Engineer for approval prior to commencement of that activity, within time scales
specified. The onus lies with the Contractor to ensure that the information is obtained and that associated activities are completed expeditiously
to avoid any delays in the commencement, continuation and completion of the required works. Unless otherwise specified or provided for in the
Contract Documentation no permanent works shall be commenced until the Engineer’s approval of the relevant method statement. The Contractor
shall, however, remain responsible for all work-methods, materials, plant and equipment used, notwithstanding acceptance by the Engineer.
The Contractor shall be required to construct test or trial anchors and the testing thereof as specified herein and shall make due allowance
therefore in his programme. Allowance shall also be made for allow for the Engineer’s assessment of constructed anchors, procedures followed,
The installation of working cable anchors, soil nails or rockbolts or mechanical earth anchors shall only commence when the Engineer has given
his written acceptance of the designs for which the Contractor is responsible in terms of the Contract Documentation, the Contractor’s method
statements, the proposed materials, the proposed drilling methods and of the Contractor’s successful installation and testing of the trial anchors/
soil nails/rockbolts.
The Contractor shall in carrying out his design obligations, familiarise himself with the available information and shall, at his own cost, carry out
whatever further investigations are required. This aspect must be catered for in the programme. In carrying out these obligations the Contractor
shall take note of the following:
- No cable anchor may be installed closer than 1,0 m from any point on the exterior of a known service, service duct or culvert.
- The anchors shall be designed such that the working stress in the tendons does not exceed 53% of the characteristic breaking stress for
permanent anchors and 64 % for temporary anchors.
- The Contractor shall assess the suitability of the bursting reinforcement in the concrete bearing pad to ensure that it is compatible with the
stressing system he intends using and will efficiently transfer and maintain the anchoring forces. Allowance shall be made by the Contractor
for any additional reinforcement required for the anchorage of his anchors. Payment for this additional reinforcement shall be deemed to be
included in the rates for the anchors.
- Test and/or site suitability anchors shall be carried out to the Engineer’s requirements and as specified in the Contract Documentation.
- The Contractor may not commence with the manufacture and installation of ground anchors until the Engineer has given written approval of
the Contractor's design.
A12.2.5 MATERIALS
All elements subject to hot dip galvanising shall be treated in accordance with SANS 121/ISO 1461 to a mean coating thickness of 85µm and
thereafter passivated using a non-toxic approved product.
A prototype shall be assembled where appropriate and the complete anchor system presented for inspection.
o) Grease
Grease shall comply with the requirements in Table A12.2.5-1 for rust-inhibiting properties.
Table A12.2.5-1: Properties for rust inhibiting grease
PROPERTY UNIT METHOD REQUIREMENTS
ASTM D127
Drop point (OC) 0
C ASTM D 566
65 min
ASTM2265/IP396
0 ASTM D92
Flash point C 150 min
ASTM D93
Penetration: un- worked
mm-1 ASTM D217 > 150
@ 25 0 C
p) Cement
The cement used in the manufacture of grout shall be CEM 1 42.5 N unless otherwise specified in the Contract Documentation.
- Broken wires which lead to other wires slipping past the broken wire as tensioning continues, leaving the end of the broken wire
protruding beyond the ends of the other wires;
- Wedges inadequately seated as evidenced by non-uniform embedment; and
- Wedges not adequately gripping strands, evidenced by disparate lengths of strands.
- Any deficiencies shall immediately be brought to the Engineer’s attention.
g) Routine acceptance tests for working anchors
Each working anchor shall be subjected to routine acceptance testing and checking of the free length as described in points 1 to 10
above. The 10-day lift-off test shall, however, not be required. Provided the apparent free length complies with (d), the anchor shall be deemed to
be acceptable if at 24 hours after lock-off, the loss of load does not exceed 6 % Tw and at 3 days after lock-off the loss of load does not exceed
7 % Tw. If at the 24-hour lift-off test or at the 3-day lift-off test the loss of prestress exceeds the allowable (6 %, 7 % Tw respectively), the anchor
shall again be locked off at 110 % and subjected to further tests at 24 hours and 3 days. If after either the second 24 hour or 3 day re-test, the
loss of prestress is still greater than the allowable, the anchor shall be regarded as a defective anchor and the anchors shall be condemned or
de-rated or otherwise dealt with as directed by the Engineer.
h) Protection
After the tensioning and testing have been completed and approved, the anchorages at the jacking end shall be filled with grease with particular
attention being paid to the annulus behind the anchor head. This shall be completely filled with the approved grease employing a suitable pump,
injecting the grease under pressure until it exudes between the wires of the individual strands. The anchor head shall then be thoroughly coated
with the grease before fitting and securing the partially grease filled permanent cover. Grease shall then be pumped through the lower grease
nipple until it exudes from the upper grease nipple hole.
The permanent covers shall then be cleaned and monitored for any loss of grease, externally or internally over the defects notification period.
Defective seals or gaskets shall be replaced and the covers refilled with grease all at the Contractor’s cost.
All anchor components shall be protected against damage or corrosion and shall be stored under cover until assembled / installation. Assembled
anchors shall be stored on trestles or similar approved installations and protected against ingress of water or other materials
All drilled holes shall be suitably sealed to prevent the ingress of water and foreign objects. Should the measures taken by the Contractor fail in
this regard the Engineer shall instruct the Contractor as to what measures shall be carried out to redress the situation. Holes lost due to the
Contractor’s negligence shall be re-drilled at his own cost. All other extra costs incurred thereby will be to the Contractor’s cost.
Installed but not yet tensioned anchors or not yet treated with rust inhibiting grease and permanent grease caps shall be suitably protected from
dust, water and other contaminants to the satisfaction of the Engineer. The works shall also be protected against vandalism by outsiders until all
the works have been completed and handed over.
A12.2.8 WORKMANSHIP
A12.2.8.1 Cable anchors
a) Cementitious grout
Immediately after mixing, and also during injection, the fluidity of the grout shall be tested at regular intervals in accordance with Clause
A20.1.5.6b)(iv) of Chapter 20. Viscosity tests may also be specified in the Contract Documentation.
During the course of grouting, 100 mm cubes shall be made, cured and tested in accordance with SANS 3001-CO11.
Six cubes per batch of anchorage grout shall be made, of which two shall be tested at 3 days, two at 7 days and two at 28 days. The testing shall
be carried out by an approved, SANAS accredited laboratory facility in terms of their accredited tests. The compressive strength of 100 mm cubes
made of the grout and cured in a moist atmosphere for the first 24 hours and thereafter in water at 20°C shall exceed 30 MPa at 7 days and 40
MPa at 28 days. The test results shall be reported within two days of the test date.
The fluidity and consistency of each grout batch mixed shall also be measured with a flow cone and, if specified, with a viscometer in accordance
with Clause A20.1.5.6b)(iv) of Chapter 20.
Grouting shall only be undertaken when the ambient air temperature is greater than 5C.
b) Concrete
All concrete for structural work associated with ground anchors and which is not covered elsewhere in the project documents shall comply with
the provisions of relevant Clauses of Chapter 13.
The Contractor shall bear the cost of all acceptance tests specified in the contract or prescribed by the Engineer and which are not listed in the
pricing schedule.
The results of tests on concrete shall be assessed according to Clause A20.1.7.5b) (ii) (Judgement Plan B) of Chapter 20.
c) Records
(i) Daily records
Daily records shall be kept in respect of each of the following phases of anchor construction:
- Drilling
- Anchor installation
- Anchor tensioning
(ii) Project records
• The project records to be prepared by the Contractor and submitted to the Engineer on completion of the anchoring shall include,
as a minimum, the following:
• Project details
• Anchoring details (numbers, positions, types, orientation, protection)
• per anchor, the following (as applicable):
o Anchor Number Anchor details (type, free length, fixed length, no of strands, design load)
o Date drilled
o Date installed
o Date grouted
o High pressure grouting details (dates, pressures, grout takes)
o Date tensioned, working load (Tw), proof load (1.5 Tw or 1.25 Tw) and lock-off load (1.1 Tw)
o Grout Test Data
CONTENTS
B12.2.1 SCOPE
B12.2.2 DEFINITIONS
B12.2.3 GENERAL
B12.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.2.5 MATERIALS
B12.2.6 CONSTRUCTION EQUIPMENT
B12.2.7 EXECUTION OF THE WORKS
B12.2.8 WORKMANSHIP
B12.2.1 SCOPE
The provisions of Part A shall apply.
B12.2.2 DEFINITIONS
The provisions of Part A shall apply.
B12.2.3 GENERAL
The provisions of Part A shall apply.
B12.2.5 MATERIALS
The provisions of Part A shall apply.
B12.2.8 WORKMANSHIP
The provisions of Part A shall apply.
C12.2.2 Re-establishment on site for additional work (type indicated) lump sum
The unit of measurement shall be the provision of access to the anchor positions as specified in the Contract Documentation.
The tendered rate shall include for all labour, plant and equipment required to provide access to the anchor positions as specified.
C12.2.4 Moving to, and setting up the equipment for drilling the holes at each position number (No)
The unit of measurement shall be the number of positions to which the drilling equipment has to be moved and set up in position to drill an anchor
hole. The quantity measured shall be the number of set ups at anchor positions as well as at site suitability /trial anchor positions or at positions
where the Engineer has ordered re-drilling of the holes.
The tendered rate shall include full compensation for all costs involved in moving and setting up any equipment.
C12.2.5 Drill holes with a diameter of (diameter indicated) to the specified depths and
metre (m)
inclinations
The unit of measurement shall be the metre of hole, including the depth of the bulbous base formed, as may be applicable. The depth of the
bulbous base shall be deemed to be equal to the diameter of a sphere, the volume of which shall be equal to the quantity of compacted concrete
in the bulbous base.
The tendered rate for forming augered holes shall include full compensation for augering and disposing of surplus material resulting from the hole
having been formed.
The tendered rate for forming bored holes shall include full compensation for boring, supplying, installing and extracting the driven temporary
casing as well as for disposing of surplus material resulting from the hole having been formed.
C12.2.6 Installation of permanent casing (size and length indicated) metre (m)
meganewton-metre
C12.2.9.1 Free anchor length
(MN-m)
meganewton-metre
C12.2.9.2 Fixed anchor length
(MN-m)
The unit of measurement shall be the meganewton-metre which is calculated as the product of the characteristic strength (in megapascals) of the
prestressing steel, the cross-sectional area of the tendon (in square metres) and the length of the tendon (in metres) between the outer faces of the
anchorages. In the case of fan and loop anchorages the "length of the tendon" shall include the length of tendon forming the loop or fan.
The unit of measurement shall be the meganewton which is calculated as the product of the characteristic strength in megapascals of the pre-stressing
steel and the cross-sectional area of the tendon in square metres, effectively anchored or coupled.
The tendered rates shall include full compensation for supplying, storing, handling, fabricating and protecting the complete anchorage or coupler
assembly, anchorage reinforcing, constructing the recesses for the anchorage or coupler, tensioning of the tendons, anchoring and/or coupling,
trimming the tendon ends, using all the equipment, as well as for all work and incidentals required for completing the work as specified. It shall also
include full compensation for testing the tendons to the specified test force in accordance with the prescribed methods.
The coupler shall include the complete assembly consisting of the anchorage built into the first-stage construction and the part coupled to it.
C12.2.11 Encasing the anchorages at the jacking end in concrete number (No)
The tendered lump sum shall include full compensation for establishment on site and subsequent removal of all the plant, equipment and
incidentals required for monitoring by means of lift – off tests and the re-tensioning of the anchors.
This work will be paid for as a lump sum, of which 75 % will become payable when all equipment is on site and the first anchor has been monitored
and the remaining 25 % will become payable after all anchors have been monitored and re-tensioned where required and the equipment has been
removed from site.
The unit of measurement for the lift-off tests shall be the number of anchors monitored or re-tensioned.
The tendered rate shall include for the supply and installation of all testing equipment, material, incidentals (including transport and
accommodation) as well as competent experienced personnel for the testing of the anchors as specified and for the preparation and submission
of tensioning records. The tendered lump sum shall also include for the removal and replacement of the grease cap, the refilling of the crease cap
with similar approved grease and ensuring a leak proof seal thereto. rockbolts, dowels, soil nails
C12.2.13 Establishment on the site for drilling of rockbolts, dowels, soil nails or mechanical lump sum
anchors (type indicated)
The tendered lump sum shall include full compensation for generally levelling the drilling site to the required post construction levels (where
applicable), establishing on site with and subsequent removal of all structural platforms, rafts and all special plant and equipment for drilling and
for carrying out operations, the cost of which does not vary with the actual amount of drilling done.
No additional payment will be made for the establishment of other or supplementary plant and ancillary equipment should that initially established
by the Contractor be incapable of penetrating the subsurface soil or rock formations, or achieving the desired hole formation without undue
disturbance of the surrounding material, or achieving the required production rate.
This work will be paid by lump sum: 50% payable when all equipment for the works is on site and the first hole has been drilled. The next 25% of
the lump sum will be payable after half the total number of holes have been drilled, and the final 25% after all the holes have been drilled and the
equipment has been removed from the site.
C12.2.14 Move to and set up at each rockbolt, dowel, soil nail or mechanical anchor position number (No)
The unit of measurement shall be the number of set ups as instructed and approved by the Engineer.
number (No)
C12.2.15 Install, grout and protect soil nails or rock bolts (lengths indicated)
The unit of measurement shall be the number of rock bolts / soil nails installed as specified and as approved by the Engineer.
C12.2.16 Extra over for tensioning soil nails or rockbolts number (No)
The unit of measurement shall be the number of rock bolts / soil nails tensioned in accordance with the Engineer’s instruction.
The tendered rate shall include full compensation for labour, plant, equipment, materials and all other incidentals required to complete the work in
accordance with the Contract Documentation and as instructed by the Engineer.
The unit of measurement shall be the number of rock bolt heads protected and / or camouflaged as instructed and approved by the Engineer.
The tendered rate shall include full compensation for the supply of all materials and work required to apply the protection and / or camouflage
layer.
C12.2.18 Move to and set up at each mechanical driven tipping anchor/ mechanical screw anchor number (No)
position (type indicated)
The unit of measurement shall be the number of set ups as instructed and approved by the Engineer.
The tendered rate shall include full compensation for access to the work face or position, dismantling, moving, erecting and commissioning all
plant, equipment and instruments required at anchoring location. The rate shall also include for undertaking the specified process control testing
and providing the Engineer with access to the work face. This item shall be paid for only after the entire anchoring operation has been completed
and approved by the Engineer.
C12.2.19 Install mechanically driven tipping anchors / mechanical screw anchors (type and
number (No)
lengths indicated)
The unit of measurement shall be the number of mechanical driven tipping plate soil anchors / installed to depths as instructed and approved by
the Engineer.
The tendered rate shall include full compensation for procurement of materials, corrosion protection, installation, and seating of anchors, load
locking, tensioning to the design working load and testing, as may be applicable. Installation shall include all ancillary face plates, washers and
nuts, protection of anchor ends and face plates, testing anchors as required, all labour, materials and all other incidentals required to complete
the work in accordance with the Contract Documentation and Engineer’s instructions. All pull out test requirements and costs are deemed to have
been included in this payment item and shall not be paid for separately.
D12.2.1 SCOPE
The scope of this Section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
D12.2.2 GENERAL
The Contractor shall provide detailed specifications, test data, performance data and compliance certificates from independent reputable agencies
for all proprietary systems, processes and materials proposed for use. These shall demonstrate conformance with the performance requirements
specified in the Contract Documentation.
Unless otherwise specified, all proprietary materials shall be used and placed in strict accordance with the relevant manufacturer's current
published instructions
CONTENTS
PART A: SPECIFICATIONS
A12.3.1 SCOPE
A12.3.2 DEFINITIONS
A12.3.3 GENERAL
A12.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A12.3.5 MATERIALS
A12.3.6 CONSTRUCTION EQUIPMENT
A12.3.7 EXECUTION OF THE WORKS
A12.3.8 WORKMANSHIP
A12.3.2 DEFINITIONS
Grout - is a cementitious, pumpable material injected into soil or rock, filling voids, stiffening, setting and effectively bonding with adjacent
materials.
Geotechnical Grouting - includes:
- Contact grouting - Contact grouting is the injection of grout under pressure into the interface between man-made structures and soil/rock.
- Fissure Grouting - Fissure grouting is injection of grout under pressure into fissures, joints, fractures and discontinuities, in rock.
- Gravity Grouting - Gravity grouting is grouting carried out with no applied pressure, sometimes referred to as tremie-grouting.
- Permeation Grouting - Permeation grouting is the replacement of interstitial water or air in a porous medium with grout at injection pressures
sufficiently low to prevent displacement.
- Jet Grouting - Jet grouting is a ground improvement technique whereby in situ materials are mixed with cementitious grout by eroding the
in situ material with a high velocity cementitious grout slurry, with or without compressed air/water, through an injection monitor attached to
the drill string to generate a mixture of soil and cement (soilcrete).
Single Jet Grouting - is the jet grouting technique where a single fluid, typically neat cementitious grout, is used.
Double Jet Grouting - is the jet grouting technique where one fluid, typically neat cement grout, is injected at high velocity assisted by air.
Triple Jet Grouting - is the jet grouting technique where one fluid, typically water, is injected at high velocity through horizontal radial nozzle(s)
and is assisted by a second “fluid”, typically air delivered through a coaxial nozzle(s), to erode the in-situ soil, while a separate nozzle placed lower
on the monitor delivers a third fluid, typically neat cement grout, at lower velocity to simultaneously fill the soil zone eroded by the cutting fluids
(air and water).
Jet Grouted Soilcrete Columns - are formed by simultaneously rotating and lifting the monitor at predetermined rates, while injecting cementitious
grout slurry (and air/water) creating a soilcrete mix with the eroded materials to form columns.
Monitor - the monitor transmits jet grouting fluids to the injection point/s, at high velocities. The monitor is attached to the bottom of the drill string.
Jet Grouting Drill String - are multi-conduit drilling rods for the separate conveyance of jet grouting fluid(s) to the monitor and drill bit.
Drill Bit - is an attachment at the bottom of the drill string to form a pilot hole for the required jet grouted column. These may be claw or drag bits
or any other bits that can produce the desired hole without unduly disturbing the surrounding materials.
Soil Return - includes all surplus materials exuded from the cavity/ hole during the jet grouting process and typically includes liquids, soil and soil
cement slurries as well as solids from the in-situ materials.
Grout Hydrometer - is an instrument used to measure the specific gravity (or relative density) of cementitious grouts and drilling fluids.
Drilling Aid - is a material mixed with drilling water to aid the drilling process and particularly the flushing of drill cuttings from the hole. Cement is
typically used.
A12.3.3 GENERAL
A12.3.3.1 Method Statements
Where so indicated by the Engineer the Contractor shall prepare detailed method statements for each facet of the work describing key aspects
such as construction methodology, key plant, materials, personnel as well as any programme constraints of the envisaged construction process.
These method statements shall be prepared and submitted to the Engineer for approval prior to commencement of that activity, within time scales
specified. The onus lies with the Contractor to ensure that the information is obtained and that associated activities are completed expeditiously
to avoid any delays in the commencement, continuation and completion of the required works. Unless otherwise specified or provided for in the
Contract Documentation no permanent works shall be commenced until the Engineer’s approval of the relevant method statement. The Contractor
shall, however, remain responsible for all work-methods, materials, plant and equipment used, notwithstanding acceptance by the Engineer.
Trials, if applicable, shall be conducted and based on outcomes thereof, may require that changes be made to the relevant method statements.
Due allowance shall therefore be made in his programme. Allowance shall also be made for allow for the Engineer’s assessment of the trials,
procedures followed, and materials and plant utilised and of the test data. Production work shall not be permitted until it is shown and accepted
by the Engineer that the Contractor possesses the necessary experience, plant and equipment to carry out the works as specified in the Contract
Documentation.
It should be noted that work shall only be performed by personnel listed by the Contractor. If personnel changes need to be made during the
project, works shall be suspended until replacement personnel are approved by the Engineer. Time lost due to incomplete submissions,
unacceptable submissions, or obtaining approval of replacement personnel will not be considered as cause for extension of time or delay claims.
All costs associated with incomplete, replacement, or unacceptable submissions shall be to the Contractor’s cost.
Once approved in writing by the Engineer, these shall become the method statements in accordance whereby the relevant portion of the works
shall henceforth be executed. Notwithstanding, the Engineer may require revision from time to time if circumstances during construction arise
which warrants change.
MA for Geotechnical Grouting, Jet Grouting, Compaction Grouting, 2 weeks before programmed use
Dynamic/Replacement Compaction, Rapid Impact Compaction, in permanent works
A12.3.6
Vibration Compaction/Vibroflotation, Underpinning, Preloading and
Basal reinforcement
Contact grouting is done to fill the cavities/voids between concrete and rock mass on account of shrinkage of concrete and uneven over
breaks. Consolidation grouting is done to strengthen the surrounding rock mass by filling up the open joints, fissures, cracks etc. Curtain grouting
involves the construction of a narrow excavation and filling it with concrete or by the creation of a thin grout curtain by pressure grouting holes at
closely spaced intervals, each grout pillar intersecting the adjacent grout pillar.
A12.3.3.9 Underpinning
Underpinning is the process of staunching settlement of a structure post-construction. Underpinning may be accomplished by extending existing
foundations in depth or in area to more supportive substratum or distributing load across a greater area, supplementing the support by providing
additional piles or micro-piles or by ground improvement beneath existing footings.
Underpinning may be necessary when:
- Original foundations have insufficient bearing capacity/stability. Properties of material supporting the foundation may have changed (possibly
through seepage or soil particle distribution or pore water dissipation),
- Geotechnical characteristics misdiagnosed during investigation/design,
- Construction of nearby/adjacent structures necessitates excavation of existing foundations,
- To increase depth or load capacity of the structure It is more economical to upgrade the present structure's foundation than to construct a new
one,
- Earthquake, flood, drought or other natural causes have caused the structure to move, thereby requiring additional work in the form of
underpinning.
A12.3.4.8 Underpinning
The Contractor shall be responsible for the design of all construction items necessary for the underpinning including, but not restricted to:
- Suitable cement mix design
- Excavation techniques and shoring
- Micropile type and installation techniques
- Grout and / or resin mix design and injection system.
A12.3.4.9 Preloading
The Contractor, where so specified, shall prepare a detailed construction method statement detailing all plant, equipment and materials to be
employed in meeting the preload monitoring objectives and performance requirements detailed in the Contract Documentation.
A12.3.5 MATERIALS
A12.3.5.1 Geotechnical grouting
The Contractor is responsible for the design of the grout. Typical grout types are listed below.
a) Cement/water grouts
Cement used in grout shall be CEM I or CEM II (SANS 50197-1) or such other cements as specified in the Contract Documentation. Depending
on the grouting method employed, the Engineer may allow or specify use of certain additives such as bentonite to reduce bleeding, improve
penetration, to vary viscosity or to improve pumpability of the grout. Where large cavities are to be filled, the Engineer may allow or specify use
of fillers, sands or gravels provided specified performance criteria are met. These shall be free of deleterious materials and meet criteria for use
as aggregates in concrete (SANS 1083).
Water for grout shall comply with SANS 241.
b) Bentonite/blended cement grouts
Bentonite grouts, either neat, or blended with cement, are finer than pure cement grouts but do not develop the same strengths.
c) Chemical grouts
Chemical grouts enable better penetration than cement or bentonite-based grouts.
These include:
- Sodium Silicate,
- Acrylamides,
- Ligno-sulphonates,
- Phenoplasts,
- Aminoplasts.
d) Speciality grouts
Specialised grouts such as epoxy resins, polyurethanes and resin silicates may be used in specialist applications and shall be detailed in Contract
Documentation.
All grout materials shall be stored under roof and protected from weather and contamination.
Dump rock for stone columns shall be obtained from a suitable source, approved by the Engineer. It shall be un-weathered, sound and durable.
Mudrock, shales and other rapid weathering rock types shall not be used.
A12.3.5.7 Underpinning
Materials for underpinning shall consist of:
a) Concrete
All concrete used for underpinning purposes shall comply with the requirements given in Section A13.4 of Chapter 13 unless otherwise specified
in the Contract Documentation. Water used for batching of grout shall comply with SANS 241 and water for concrete shall comply with SANS
51008.
b) Chemical grouts
Chemical grouts may include but not be limited to:
- Sodium Silicate,
- Acrylamides,
- Ligno-sulphonates,
- Phenoplasts,
- Aminoplasts
c) Speciality grouts
Specialised grouts such as epoxy resins, polyurethanes and resin silicates may be used in specialist applications as detailed in the Contract
Documentation.
Selection of pounder and drop height depends on site conditions and required compaction depths.
A12.3.6.7 Underpinning
The Contractor shall in his method statements provide comprehensive details of all plant and equipment, appropriate to the specified works before
construction commences. Such equipment shall cover demolition and/ or removal of existing materials or infrastructure, provision of temporary
support as well as any other activities whether temporary or permanent that may be required to facilitate the works to be carried out in terms of
Contract Documentation.
A12.3.6.8 Preloading
a) Settlement monitoring by survey methods
Survey equipment for monitoring of embankment fill by precise levelling shall be calibrated and in good working order.
Settlement plates to be installed shall comprise 20 mm thick metal discs with diameter greater than 1,0 m and have perpendicularly-attached
extendable 1,0 m long steel rods greater than 25 mm, or pipes, Targets painted at rod tops shall provide for accurate survey. Steel rods/pipes are
extended with couplings as filling of embankments progresses .
b) Settlement monitoring by magnetic extensometers
Magnetic extensometers provide a means of measuring settlement or heave at a point or series of points in the subsurface. Extendable access
tubes are installed in predrilled holes. A datum ring magnet is installed about 2,0 m from the lower end of the tube. Spider magnets, temporarily
held in place along the tube, are used within the subsoil. Plate magnets within the fill can be placed during construction. Once in position the
spider magnets are released. The hole is backfilled with a bentonite: cement mix of strength equivalent to surrounding material.
Readout devices shall consist of a nickel-plated brass probe containing a reed switch encapsulated in silicone rubber. Probes shall be connected
via a nylon coated steel tape to a reel buzzer. Instruments and all ancillary equipment shall be approved by the Engineer before being used.
Combined inclinometers and magnetic extensometers which provide means for measuring both vertical settlement and horizontal displacement
at a series of points below the ground surface may be considered by the Engineer.
c) Slope stability monitoring
(i) Inclinometers
Measurement of lateral movement at selected depths at a position on the embankment is conducted by means of sending an
inclinometer torpedo down inclinometer tubing installed in a borehole or placed horizontally across the embankment during
construction. This torpedo has an electronic accelerometer capable of measuring deflection of the torpedo (and tubing) which is
coupled via an electric cable to a remote readout unit. The instrument shall be approved prior to use by the Engineer and shall have
1 1
Tamper 18.2 Mg
1 1
4.6m
E = 6.66MJ /m2
A12.3.7.7 Underpinning
a) General
Underpinning, as directed by the Engineer, shall be undertaken as specified or instructed in the Contract Documentation. Underpinning support
may be provided by:
- Provision of temporary support to an existing structure,
- Removing existing footings and replacement thereof with new footings of greater bearing capacity, followed by removal of the temporary
support,
- Excavation beneath sections of existing foundations; constructing new footings of greater bearing capacity and ensuring load transfer to new
footings, with or without preloading of the new construction,
- Excavation under existing foundations, jacking in piles and ensuring load transfer to new piles, with or without preloading,
- Installing piles alongside existing foundations and casting new sections of footings keyed into existing foundations,
- Constructing new foundations adjacent to existing, with or without piles, and transferring load to these foundations by means of additional
columns or similar structural members or other unification measures.
- Installing piles through existing foundations and keying pile heads into existing foundation,
- Drilling small diameter holes (150–250 mm in diameter) through existing foundations and constructing micropiles beneath these foundations,
- Drilling small diameter holes (approx. 250 mm diameter) through existing foundations and installing jet grouted columns beneath existing
foundations,
- Drilling micro-holes (less than 30 mm diameter) through existing foundations and pumping under high pressures quick setting resins; silica’s
or other chemicals, or,
- Jet grouting or Compaction grouting through existing foundations as detailed in these specifications.
b) Process
Underpinning methods shall be specified in Contract Documentation and relevant specifications in various sections of this document shall be
applicable unless otherwise indicated.
c) Monitoring and Records
Monitoring and logging of all excavation, demolition, foundation compaction, reinforced concrete construction (all facets), drilling, piling and all
other activities carried out in executing underpinning shall be carried out by the Contractor. These shall include:
- Daily records of all underpinning activities,
- Positions,
- Depths of treatment,
- Start and stop times,
- Details of all stoppages, breakdowns and volume of grout injected at each position,
- Results of process control tests on materials,
- Details of any works not completed due to mechanical breakdowns, inadequacy of materials, grout, air or water supply or any other reason
and proposed remedy/remedies
Records shall be submitted to the Engineer before noon the following working day.
A12.3.8 WORKMANSHIP
A12.3.8.1 General
The Engineer will conduct routine inspections and tests to determine whether the workmanship provided complies with the requirements of this
section. The Engineer shall assess compliance with the requirements specified in the Contract Documentation.
The Contractor, however, shall carry out all necessary process control measures required in terms of Clause A1.2.8.1 in Chapter 1 as indicated
in the approved Quality Assurance Plan and as may be specified in the Contract Documentation.
The characteristic strength of the grout shall be as specified in the Contract Documentation. Results of strength tests on grout will be assessed
for acceptance if the average strength exceeds the specified strengths with no single test less than 95% of the specified strength. If these criteria
are not obtained, the Engineer may instruct that additional grouting shall be undertaken until compliance with is achieved.
A12.3.8.7 Underpinning
Requirements under the various methods used for underpinning of structures as specified in relevant Chapters and Sections of these specifications
shall apply.
CONTENTS
B12.3.1 SCOPE
B12.3.2 DEFINITIONS
B12.3.3 GENERAL
B12.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.3.5 MATERIALS
B12.3.6 CONSTRUCTION EQUIPMENT
B12.3.7 EXECUTION OF THE WORKS
B12.3.8 WORKMANSHIP
B12.3.1 SCOPE
The provisions of Part A shall apply.
B12.3.2 DEFINITIONS
The provisions of Part A shall apply.
B12.3.3 GENERAL
The provisions of Part A shall apply.
B12.3.5 MATERIALS
The provisions of Part A shall apply.
B12.3.8 WORKMANSHIP
The provisions of Part A shall apply.
The tendered lump sum for site establishment for items C12.3.1.1 to C12.3.1.9 above shall include full compensation for establishing all necessary
plant, equipment and services on site to carry out the works as specified including all work in preparing the works area for construction activities
and subsequent removal from site of all such plant and equipment including all temporary works such as access roads, staging, platforms and
such like. The tendered rate for preload monitoring shall include for the establishing on site of all the necessary equipment and material as
specified required for the installation of the specified monitoring instruments and for the removal thereof on completion of the works. The provision
of boreholes in which instruments are to be installed, and the supply of the specified instruments and accessories as may be required, shall be
paid for separately.
The work will be paid for by way of a lump sum, 50 % of which shall be payable when all major necessary equipment is on site, trials (if any) are
completed and the first production work started. The second instalment of 25 % is payable after half the specified work is complete. The final
instalment shall be payable after all work is complete, all equipment has been removed and the site restored as specified in the Contract
Documentation.
The unit of measurement shall be the number of positions to which equipment is moved and set up in position to execute the works as described
in the Contract Documentation. The quantity measured shall be the number of set ups at designated works positions inclusive of approved trial
works positions as well as any additional positions as may be instructed by the Engineer.
The tendered rates shall include full compensation for all costs involved in moving to and setting up required equipment at each works position.
Multiple setups at the same hole shall only be measured and paid for once. Tendered rates shall also include all costs in setting-up equipment
and subsequent decommissioning thereof
The unit of measurement shall be the number of positions set out by a registered surveyor as per Contract Documentation or as instructed by the
Engineer. Payment will not be made for re-setting out of treatment positions lost for whatever reason.
The tendered rate shall include for all labour, plant, equipment, materials and all incidentals required.
The unit of measurement shall be kilograms (kg) of cement actually utilised for grouting as specified and approved by the Engineer.
The tendered rates shall include for all labour, plant, equipment, materials, delivery, storing, mixing, pumping, injection and all incidentals required.
No payment will be made for any wastage or for rejected batches. Only verified quantities will be accepted for measurement and payment.
The rate shall include quality control measures, testing of materials, monitoring and supervision of the works, daily records of all items specified
in the Contract Documentation.
The unit of measurement shall be the kilograms (kg) of filler/additive actually utilised for grouting as specified and approved by the Engineer.
Tendered rates shall include for all labour, plant, equipment, materials, delivery, storing, mixing, pumping, injection and all incidentals required.
No payment will be made for any wastage or for rejected batches. Only verified quantities will be accepted for measurement and payment.
The rate shall include quality control measures, testing of materials, monitoring and supervision of the works, daily records of all items specified
in the Contract Documentation.
C12.3.6 Drilling of holes for geotechnical /compaction grouting (diameter and inclination metre (m)
indicated)
The unit of measurement shall be the metre of hole actually drilled and re-drilled. No differentiation will be made for different drilling methods (e.g.
rotary, percussion, rotary percussion or vibratory drilling), unless otherwise specified.
The tendered rate shall include full compensation for drilling holes of appropriate diameter including, drilling aids, drilling materials and disposal
of all waste products on completion thereof. Casings/sleeves shall be measured and paid for separately.
C12.3.7 Extra over for drilling through reinforced concrete metre (m)
The unit of measurement shall be the metre of drilling through reinforced concrete.
The tendered rate shall include for all labour, plant, equipment and materials to carry out the drilling as required.
C12.3.8 Drilling holes for jet grouting to specified depths (depth ranges and inclinations to be metre (m)
specified)
The unit of measurement shall be the metre of hole drilled of specified diameter and as specified in all materials.
The tendered rate for forming holes shall include full compensation for drilling and disposing of surplus material resulting from the hole being
formed. No differentiation will be made for different drilling methods (e.g. rotary, percussion, rotary percussion or vibratory drilling) unless otherwise
specified.
The unit of measurement shall be the cubic metre of grout actually injected into the fissure/cavity/void/material.
The tendered rate shall include full compensation for the mixing, storing, pumping and placement of the approved grout and shall include for all
labour, materials (other than for which provision for payment has been made in the Contract Documentation), quality control measures, the testing
of materials, monitoring and supervision of the works the daily recording of results, injection parameters, production and other record keeping and
reporting all as specified in the Contract Documentation.
C12.3.12 Extra-over items 12.3.4 and 12.3.5 for stage grouting (specify up-or downstage) number (No)
The unit of measurement shall be the number stages grouted to required pressures.
The tendered rate shall include full compensation for all additional costs of managing each stage.
C12.3.13 Extra-over items 12.3.4 and 12.3.5 for jet grouting of widened sections or mushroom number (No)
heads (position and width to be specified)
The unit of measurement shall be the number of widened sections or mushroom heads constructed as specified.
The tendered rate shall include full compensation for all additional cost for this operation.
The unit of measurement shall be the number of columns exposed for inspection, measurement and testing.
The tendered rate shall include for all plant, excavating the material around the column and trimming of the column as well as backfilling of
excavations with suitable material in 150mm layers compacted to required density.
The unit of measurement shall be per set up over a completed, cured column as instructed by the Engineer.
The unit of measurement for drilling and recovery of core samples using appropriate methods and equipment of size indicated.
cubic metre-
C12.3.16 Removal of jetting and drilling spoil
kilometre (m3-km)
The unit of measurement shall be the cubic metre of spoil hauled over the distance covered.
The tendered rate shall include for the loading, transport and all other costs in hauling the spoil material to the approved spoil site.
C12.3.17 Performing dynamic compaction over (specify distance) utilising a (indicate mass) tonne
pounder
The unit of measurement will be the number of blows imparted at a compaction point. Differentiation is made between primary phase, secondary
phase and ironing phase works.
The tendered rate will include full compensation for carrying out the specified dynamic compaction in full compliance with the specifications at
designated compaction points including the ongoing vibration measurement and monitoring as specified and for the placement of dumprock during
the construction of stone columns. Separate payment shall be made for the procuring of dump rock.
The unit of measurement in respect of increase or decrease in the number of blows imparted in the execution of dynamic compaction at designated
compaction points as instructed or approved by the Engineer.
Differentiation is made between primary phase, secondary phase and ironing phase works.
Payment for variations shall be made as specified in Clause C1.1.4
C12.3.19 Importing G7quality material from approved sources cubic metre (m3)
The unit of measure shall be the cubic metre of imported G7 quality material.
The tendered rate shall include full compensation for procuring, stockpiling, watering to compaction moisture content for processing as backfill in
craters formed by dynamic compaction or for the construction of capping layer or for general layerworks, levelling and finishing of compacted
areas. The quantity shall be taken as 70 % of the volume transported to site as measured in trucks. Only full, struck-off loads arriving on site shall
be paid for.
C12.3.20 Importing dump rock for forming stone columns by dynamic compaction from cubic metre (m3)
approved sources
The unit of measure shall be the cubic metre of dump rock as specified for forming of stone columns by dynamic compaction.
The tendered rate shall include full compensation for the procuring, stockpiling and placement during the construction process. The quantity shall
be taken as 70 % of the volume transported to site as measured in trucks.
C12.3.21 Importing crushed rock for vibratory replacement from approved sources cubic metre (m3)
The unit of measure shall be the cubic metre of imported G7 crushed rock for vibratory replacement as specified from approved sources.
The tendered rate shall include full compensation for the procuring, stockpiling, and for the placement in craters formed by vibrocompaction/
vibroflotation.
The quantity shall be taken as 70 % of the volume transported to site as measured in trucks. Only full, struck-off loads arriving on site shall be
paid for.
The unit of measurement shall be the number of tests carried out as instructed by the Engineer in accordance with the Contract Documentation.
The tendered rate shall include full compensation for establishing approved equipment on site and all costs incurred in carrying out the tests by
competent persons plus record keeping and reporting.
The unit of measurement shall be the number of plate load tests carried out as specified on the instruction of the Engineer.
The tendered rate shall include full compensation for the provision of the testing equipment on site for the duration of the works, for the carrying
out of the tests by competent persons and for the provision of the test data as specified in Contract Documentation.
The tendered lump sum for dynamic compaction shall include full compensation for the establishment and removal from site of all the plant and
equipment required to carry out the testing as specified inclusive of all preparatory work that may be required and all operations for which the cost
does not vary with actual amount of testing carried out.
The lump sum rate shall include full compensation for the provision of all the resources inclusive of water and electrical power for carrying out the
tests as specified.
This work will be paid for by way of a lump sum, 50 % of which will become payable when all the equipment is on site, trials (if any) are completed
and the first tests successfully conducted. The second instalment of 25 % of the lump sum will be payable after half the total number of tests are
completed and the final instalment of 25 % after all the testing work is complete, the results accepted by the Engineer and the equipment has
been removed from site.
The unit of measurement shall be the number of tests carried out as specified on the instruction of the Engineer.
The tendered rate shall include full compensation for the setting up of the equipment at each designated testing point, the execution of the tests
by competent persons as specified as well as the provision other the test results in an approved format within 24 hours of testing.
The unit of measurement shall be the number of tests carried out on the instruction of the Engineer.
The tendered rate shall include full compensation for the provision of the testing equipment on site for the carrying out of the tests by competent
persons and for the provision of the test data, all as specified.
The unit of measurement shall be the period over which the Contractor shall have in his employ a suitably-qualified and experienced surveyor
equipped with all the necessary survey equipment to carry out the monitoring as specified.
The tendered rate shall include for all labour, materials, calibrations and other items required to complete the works as specified.
The unit of measurement shall be the number of rod settlement gauges supplied and installed.
The tendered rate shall include for the supply and installation of the base plates and extension rods (number indicated) as specified, the marking
and protection thereof. The tendered rate shall also include for all the labour, materials, periodic installation of extension rods required as well as
for the recording and reporting of settlement results.
The unit of measurement shall be number of standpipe piezometers supplied and installed.
The tendered rate shall include for supply and installation of standpipe piezometers as specified as well as the labelling, survey and the protection
thereof. The tendered rate shall also include for all labour, materials, reading equipment and all incidentals required for the measurement of water
levels, the recording and for the reporting of the results as specified, Boreholes in which piezometers are installed shall be measured separately.
C12.3.30 Supply and install pneumatic piezometers (lengths indicated) number (No)
The unit of measurement shall be number of pneumatic piezometers supplied and installed.
The tendered rate shall include for supply and installation of pneumatic piezometers as specified, labelling, survey and protection thereof. The
tendered rate shall also include for all labour, materials, tubing, cabling, couplings, manifolds, readout and recording, unit cabinets and incidentals
required for measurement of water levels, recording, processing and for reporting of results as specified. Boreholes in which piezometers are
installed shall be measured separately.
C12.3.31 Supply and install inclinometer monitoring systems (lengths indicated) metre (m)
C12.3.32 Supply and install pressure measuring loadcells (type and make specified) number (No)
The unit of measurement shall be the number of loadcells of the specified type installed in the earthworks during construction.
C12.3.33 Supply and install geosynthetic for basal reinforcements square metre (m2)
The unit of measurement shall be the square metre (m2) of geosynthetic placed as specified.
The tendered rate shall include for the procurement, transport, storage and placement of the specified geosynthetic, measured in place inclusive
of all labour, incidentals and materials.
C12.3.34 Supply and placement of 125 mm protection layer cubic metre (m3)
D12.3.1 SCOPE
The scope of this Section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
D12.3.2 GENERAL
The Contractor shall provide detailed specifications, test data, performance data and compliance certificates from independent reputable agencies
for all proprietary systems, processes and materials proposed for use. These shall demonstrate conformance with the performance requirements
specified in the Contract Documentation.
Unless otherwise specified, all proprietary materials shall be used and placed in strict accordance with the relevant manufacturer's current
published instructions
CONTENTS
PART A: SPECIFICATIONS
A12.4.1 SCOPE
A12.4.2 DEFINITIONS
A12.4.3 GENERAL
A12.4.5 MATERIALS
A12.4.8 WORKMANSHIP
A12.4.2 DEFINITIONS
The following definitions shall apply to these specifications:
Embedded wall - is a structural wall, partially or fully embedded in subsoils. Embedment may be achieved by driving the structure or elements of the
structure into the subsoils or by placement into preformed holes or trenches. The structural wall is designed either as a cantilever to provide the primary
support, or to act as a support system against which braced or tie-back forces are mobilised. Embedded walls may comprise:
- Steel sheet piles
- Precast concrete sheet piles
- Steel soldiers
- Concrete soldier piles
- Contiguous and secant pile walls
- Diaphragm walls
Sheet pile wall - is an embedded wall comprising individual steel or precast concrete sheet piles linked together and driven into the ground to provide
lateral support and/ or an impermeable barrier. Steel sheet piles are more common than precast concrete.
Steel sheet piles - are Z- and U-shaped hot rolled steel sheet pile elements (manufactured and imported from Europe or the UK).
Pile threader - is a mechanical device used to interlock sheet piles into panels for grouped installation.
Slinging Hole - is a lifting hole located near individual pile sheets approximately 32 mm in diameter usually located 150 mm from the sheet ends.
Interlock - sheet pile interlock is preformed through coupling edges allowing individual steel piles to lock onto one another thereby providing a tight
high-strength bond.
Crimping - is spot pressure indentation which permanently locks one sheet pile to another in order to increase resistance against bending, and thereby
allowing faster pile installation.
Tie rods - are anchors used in sheet piling to retain sheet pile walls to remote deadman anchorages. They may comprise stand- alone steel elements
suitable protected against corrosion or reinforced concrete beams.
A12.4.3 GENERAL
A12.4.3.1 Method Statements
Where so indicated by the Engineer the Contractor shall prepare detailed method statements for each facet of the work describing key aspects
such as construction methodology, key plant, materials, personnel as well as any programme constraints of the envisaged construction process.
These method statements shall be prepared and submitted to the Engineer for approval prior to commencement of that activity, within time scales
specified. The onus lies with the Contractor to ensure that the information is obtained and that associated activities are completed expeditiously
to avoid any delays in the commencement, continuation and completion of the required works. Unless otherwise specified or provided for in the
Contract Documentation no permanent works shall be commenced until the Engineer’s approval of the relevant method statement. The Contractor
shall, however, remain responsible for all work-methods, materials, plant and equipment used, notwithstanding acceptance by the Engineer.
The Contractor shall be required to construct trials and the testing thereof as specified herein and shall make due allowance therefore in his
programme. Allowance shall also be made for allow for the Engineer’s assessment of constructed works, procedures followed, and materials and
plant utilised and test data. Production work shall not be permitted until it is shown and accepted by the Engineer that the Contractor possesses
the necessary experience, plant and equipment to carry out the works as specified in the Contract Documentation.
It should be noted that work shall only be performed by personnel listed by the Contractor. If personnel changes need to be made during the
project, works shall be suspended until replacement personnel are approved by the Engineer. Time lost due to incomplete submissions,
unacceptable submissions, or obtaining approval of replacement personnel will not be considered as cause for extension of time or delay claims.
All costs associated with incomplete, replacement, or unacceptable submissions shall be to the Contractor’s cost.
Once approved in writing by the Engineer, these shall become the method statements in accordance whereby the relevant portion of the works
shall henceforth be executed. Notwithstanding, the Engineer may require revision from time to time if circumstances during construction arise
which warrants change.
A12.4.4.3 Concrete mix design for Diaphragm walls 6 weeks before placement
Materials Approvals
- In very unstable soil profiles beneath the water table where continuous support and watertight joints are required to prevent mudflows, piping
and erosion of soils
- Where time is limited and the construction of a diaphragm wall to provide support and/or water retention allows earlier subsurface excavations.
In conditions where deeper than normal cantilever support may be required, for example, where the wall acts as cantilever only, or where a
very deep initial excavation is required before the first braced or tie-back support can be installed.
Diaphragm walls require a large site area. They are not suited to small or shallow basement excavations.
Wall widths from 600 mm to 1500 mm can be formed using diaphragm walls, to depths greater than 60 m. The resultant structural wall forms an
integral part of deep lateral support and is designed either as a cantilever to provide primary support or water retention/dewatering, or to act as a
support system against which braced or tie-back forces are mobilised. Cantilever is generally effective between 4,0 and 6,0 m; bracing up to 10
m, and anchored walls to 25 m and higher.
Commencement of production shall only start when the Engineer has given written acceptance of designs for which the Contractor is responsible
for in terms of the Contract Documentation, the Contractor’s method statements, and approval of plant and equipment.
The Contractor shall provide a quality management plan indicating his proposed quality assurance testing program which shall allow, if necessary,
testing at each treatment position as required. Testing methods to be employed shall be as specified in the Contract Documentation.
Sheet pile design shall be carried out by competent personnel following on from relevant approved/ specified design requirements.
Engineer approval of the Contractor’s method statement shall not be unduly withheld with acceptance lead time as per Table A12.4.3-1.
Planning and construction of diaphragm walls shall be carried out by competent and experience construction personnel following on from relevant
approved/ specified design requirements.
Engineer approval of the Contractor’s method statement shall not be unduly withheld with acceptance lead time as per Table A12.4.3-1.
The Contractor shall be responsible for the design of a suitable cementitious concrete mix and bentonite slurry for construction of the diaphragm
wall which shall be presented by for approval by the Engineer with due consideration of the following:
Availability of cementitious products in the quantities required for production
The achievement of the specified characteristic strength in the mix
Workability of the concrete during displacement of the bentonite slurry
The following procedure shall be applicable:
Concrete mix design shall be carried out by competent personnel following the relevant approved/ specified mix design procedures and SANS
Methods for the sampling, curing and testing procedures. The relative density as well as the fluidity of the various mixes shall be determined to
provide a basis for ongoing quality assurance during diaphragm wall construction.
The Contractor shall submit his proposed mix design for the concrete accompanied by all relevant information to the Engineer for approval. A lead
time, as per Table A12.4.3-1, is required for this information. Construction shall only proceed once the Engineer is satisfied that the mix meets the
minimum performance criteria specified including the 28 day characteristic strength of the concrete as specified in the Contract Documentation.
Any changes to the mix after the Engineer’s approval has been obtained shall only be permitted if approved in writing by the Engineer.
A12.4.5 MATERIALS
A12.4.5.1 Sheet piling
Sheet pile sections are available in ordered lengths. Recommended maximum lengths, as dictated mainly by handling and driving requirements
are as follows:
Table A12.4.5-1: Recommended sheet pile lengths
Moment of Inertia of Section cm4 Maximum recommended Typical wall thickness Typical section half
per metre width length in metres (mm) depth (mm)
4110 6
13513 14
Sheet pile lengths may be successfully extended by specialist welding of sections or shortened by cutting. Length changes must ensure no
damage or distortion occurs to adjacent piles.
Steel sheet pile sections are manufactured from various grades of steel in accordance with EN10249-1-1995 as per Table A12.4.5-2 below for
cold-formed U and Z sections:
Table A12.4.5-2: Steel grades
Minimum yield strength Tensile strength Rm
Grade of steel Former UK reference
ReH (MPa) (MPa)
In hard driving conditions it may be necessary to increase the pile section size to achieve the required penetration and/ or adopt a higher grade
of steel. The Engineer’s approval shall be obtained before orders for any sheet pile sections are placed.
Piles shall be stacked on site in accordance with the manufacturer’s recommendations. The Contractor shall ensure that operations involving
loading, transporting, offloading, handling, stacking and pitching the piles, are carried out in a manner that shall prevent damage to them or their
coatings. The Engineer shall be immediately informed of any damage and the Contractor shall the submit proposals for remedial measures, the
cost of which shall be borne by the Contractor. Lifting holes shall not be burned or drilled through sheet pile without prior approval by the Engineer
and shall be made good after use. The same pile sections; lengths and steel grades shall be stored in different stacks clearly marked or colour-
coded to avoid placement errors.
Driving caps for diesel hammers shall be manufactured from cast steel and have an arrangement of guiding grooves for the different sheet pile
sections on its lower side. A wooden or plastic/composite dolly (cushion) shall be fitted into recesses on top of the driving cap.
Walers, tie-rods and ground anchors shall be as specified in the Contract Documentation.
Coarse aggregate shall comprise of clean, durable, hard rock aggregate as per SANS 1083 or as specified in the Contract Documentation.
f) Steel
Steel for the reinforced cage shall be as indicated in the Contract Documentation and as per the requirements of this document.
b) Process
(i) Set-up
Sheet piles shall be lifted up one at a time and threaded one end into the other interlocking piles prior to driving. A crane shall be used
for this purpose and a pile threader/ guide frame/ or scaffold platform constructed to provide support for assembled sheets readied
for driving.
(ii) Driving
Sheet piles shall be installed by driving or vibrating into the ground. Driving can be achieved by the use of vibratory hammers; drop
hammers; or diesel, hydraulic or air hammers. Driving shall be by ‘Pitch and Pile’ where each pile or pile pair shall be driven to finished
level before repeating the operation – a method suited to relatively short piles in softer ground where obstructions are unlikely.
Alternatively, y ‘Panel Driving’, which is the more common method can be used. Once guide frames have been positioned for panel
driving the first pair of piles shall be carefully pitched, plumbed and partly driven to form a guide for adjacent piles. The remaining
panel of piles (usually 10 – 20 m run of wall panel) is then pitched and interlocked. The last pair of piles shall then be partially driven
followed by partial driving of the rest of the panel working back to the first pair in the panel. There shall be no departure from the
vertical. The top guide wailings can at this stage be removed and then all but the last pair of piles in the panel driven to level. The last
pair shall be left partially upstanding to form the guide pair for commencement of the next panel. It is essential, to ensure verticality,
and to make sure the pile driving hammer orientation is lined up with the pile axis.
Driving caps (also termed ‘helmets’) provide protection of the sheet pile head during driving. The cap shall be close fitting and rigid to
provide even energy distribution from a hammer blow. Buckling of steel sheet pile heads or damage to the heads of concrete piles
can otherwise occur in driving through very hard ground. In vibratory hammers a driving cap is unnecessary since the hammer clamps
the sheet pile hydraulically.
All changes to the initially approved method statements shall be approved in writing by the Engineer and all production work shall be
in strict accordance with the approved methodology and specifications.
(iii) Obstructions
When obstructions are encountered the remainder of the panel shall be completed so that the piles obstructed have support from
adjacent piles during attempts to drive through the obstruction. If unsuccessful, driving can continue whilst the obstruction is removed
thereby minimising construction delays. Sheet pile toes can be damaged when driving through cobble or boulder layers. Measures to
limit risk of damage include the use of sheet piles made from high tensile steel; reinforcement of the sheet pile toe by welding on
additional strengthening plates; and reducing hammer energy blow.
Pile toes shall, if necessary, be secured into underlying rock using steel pins. These may be required where it is not feasible to drive
piles to required penetration, or where there is concern piles may slide down a sloping rock surface. Pins shall be welded onto piles
before driving or installed via tubes attached to and driven with the piles. For the latter holes are drilled into rock and pins grouted into
position.
(iv) Ground pre-treatment
It may be cost effective to consider pre-treatment of ground to allow lighter section installation where piling is dominated by driving
rather than moment capacity. This could include:
Pre-auguring to weaken or replace hard ground
Driving a heavier section than required; extraction of the heavy unit followed by driving of working pile sheets in the same ground
Controlled blasting to reduce very dense soil or obstructions to granular material: without displacement.
(v) Water tightness
The only possibility of water infiltrating through a sheet pile is by flowing through the interlock. The interlock shape naturally provides
high resistance to seepage where sealing systems are unnecessary for applications such as temporary retaining walls where
moderate rates of seepage are acceptable. If medium to high seepage resistance is required double sheet piles or welding of joints
shall be required. Alternatively, elastic sealants such as silane modified polymers (MS-Polymers) shall be considered. Typically, the
d) Water tightness
Water tightness shall be ensured through care in ensuring formation of the required recess through stop-end retrieval. A water stop shall be
considered when an impermeable condition is sought.
e) Anchors
Where ground anchors are required these shall be specified in the Contract Documentation and the requirements given in Section A12.2: Ground
Anchors and shall be installed at the specified locations .
f) Obstructions
Obstructions encountered during construction shall be dealt with as per the Contractor’s plan methodology presented and agreed as in Clause
A12.4.4.3.
A12.4.8 WORKMANSHIP
A12.4.8.1 General
The Engineer shall undertake routine inspections and conduct routine tests to determine whether the quality of materials and workmanship
provided comply with the requirements of this section. Test results and measurements will be assessed by the Engineer for compliance with the
requirements specified in the Contract Documentation. The Contractor shall carry out the necessary process control measures required in terms
of Clause A1.2.8.1 of Chapter 1, as indicated in the approved Quality Assurance Plan and as may be specified in the Contract Documentation.
- UCS Testing of 100 mm diameter, 200-250 mm long drilled cores from constructed panels
- Coring the centre of constructed panels and UCS testing of selected cores
- Indicative compressive strength tests on 100 mm cubes made from concrete mix
- Any other tests as may be prescribed in the Contract Documentation
(ii) Concrete
- Consistency - The consistency and workability of each batch of concrete shall be tested for consistency with the Slump Cone.
The slump shall be more than 150 mm and less than 200 mm. Ranges in values shall be determined as works proceed and any
significant variation from running average shall be immediately investigated and brought to the attention of the Engineer.
- Concrete Cube Strength Testing - 150 mm cubes shall be made, cured and tested in accordance with SANS 3001-CO11 at
frequencies specified in the Contract Documentation. Three cubes per test shall be required. The results of strength tests on the
concrete shall be assessed according to Clause A20.1.7.5d) (Judgement Plan B) of Chapter 20.
c) Bentonite slurry
A minimum of 2 samples of bentonite slurry shall be sampled daily. One 0,3 m below the panel surface and a second one at panel mid-depth for
process control testing by the Contractor. Important parameters for testing are:
- Measure of rheology to ensure slurry is appropriately fluid
- Slurry density prior to concreting to ensure satisfactory displacement
- Sand content to determine re-use
The Engineer shall generally request testing to determine the density; viscosity (Marsh Cone); Fluid loss; pH, and sand content to verify uniformity
and compliance with the parameters established in the mix design and that listed in Table A12.4.8-1: Acceptance criteria below.
d) Acceptance criteria
Acceptance or rejection shall be based on the Contractor’s ability to achieve the specified criteria which may include:
(i) For concrete
- Required consistency and workability
- Attainment of 28 day specified characteristic strength of concrete cubes,
- Attainment of specified UCS results on cores,
(ii) For bentonite powder**:
- Yield Point/ Plastic Viscosity Ratio of maximum 6
- Plastic viscosity greater than 10
- Moisture contentless than 15 %
- Less than 2,5 % remaining on a 75 micron sieve
- A 6,4 % suspension of bentonite in distilled water, aged for 24 hours, should have a minimum viscometer dial reading of 30 at 600
rpm (American Petroleum Institute (API)RP13B).
**FEDERATION OF PILING SPECIALISTS BENTONITE SUPPORT FLUIDS IN CIVIL ENGINEERING January 2006
(iii) For bentonite slurry:
The following table (API) provides acceptance criteria:
Table A12.4.8-1: Acceptance criteria
Stages
Property Units Fresh Ready for re-use Before Test equipment
concreting
CONTENTS
B12.4.1 SCOPE
B12.4.2 DEFINITIONS
B12.4.3 GENERAL
B12.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.4.5 MATERIALS
B12.4.6 CONSTRUCTION EQUIPMENT
B12.4.7 EXECUTION OF THE WORKS
B12.4.8 WORKMANSHIP
B12.4.1 SCOPE
The provisions of Part A shall apply.
B12.4.2 DEFINITIONS
The provisions of Part A shall apply.
B12.4.3 GENERAL
The provisions of Part A shall apply.
B12.4.5 MATERIALS
The provisions of Part A shall apply.
B12.4.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be the number of positions to which equipment is moved and set up in position to execute the works as described in
the Contract Documentation. The quantity measured shall be the number of set ups at designated works positions (individual pile position, or panel
section of steel sheet piles, or diaphragm panel, as specified) inclusive of approved trial works positions as well as any additional positions as may be
instructed by the Engineer.
The tendered rates shall include full compensation for all costs involved in moving to and setting up required equipment at each works position.
Tendered rates shall include all costs in setting-up equipment and subsequent decommissioning.
C12.4.3 Setting out of works at sheet piling or diaphragm panel positions metre (m)
The unit of measurement shall be metres in length set out by a registered surveyor as per the Contract Documentation or as instructed by the Engineer.
The tendered rate shall include for all costs incurred in setting out the works inclusive of transport, labour and all incidentals required to carry out the
work as specified. Payment will not be made for the re-setting out of positions lost for whatever reason.
C12.4.4 Sheet pile driving (individual sheet pile type or sheet panel extent specified) square metre (m2)
The unit of measurement shall be the net square metre of sheet piles installed.
The tendered rate shall include full compensation for supply of sheet piles to site; correct handling and storage of sheet pile elements, driven
installation and for all labour, plant and equipment required for installation to depths as required by the Contract Documentation, or as instructed
by the Engineer.
The unit of measurement shall be the number of props or anchors or tie-bars (including designed deadman anchorages).
The tendered rate shall include full compensation for installation to Contract Documentation detail, including all labour, plant, materials and
equipment required.
The unit of measurement shall be the kilograms (kg) of chemical or cement actually utilised for grouting as specified and approved by the Engineer.
The tendered rates shall include for all labour, plant, equipment, materials, delivery, storing, mixing, pumping, drilling, injection and all incidentals
required. No payment will be made for any wastage or for rejected batches. Only verified quantities will be accepted for measurement and payment.
The rates shall include quality control measures, testing of materials, monitoring and supervision of the works and the provision of daily records for all
items specified in the Contract Documentation.
C12.4.8 Concrete placed by tremie under slurry in diaphragm walls (class of concrete indicated) cubic metre (m3)
The unit of measurement shall be the cubic metre (m3) of concrete placed by tremie under bentonite slurry for the construction of diaphragm walls.
The tendered rate shall include full compensation for supplying and storing all material, providing all plant, mixing, transporting and placing the concrete
by tremie methods
The unit of measurement shall be the cubic metre (m3) of material excavated for inspections and testing adjacent to panels and removed to stockpile
for backfilling operations or to spoil.
The tendered rate shall include full compensation for the excavation to expose the panels and shall include for the backfilling thereof as specified.
The rate shall include for all labour, plant and equipment required for such removal and backfilling as required by the Contract Documentation, or
as instructed by the Engineer. No overbreak shall be paid for excavation beyond the theoretical excavation boundaries.
The unit of measurement shall be the kilogram of materials actually utilised for diaphragm wall construction as specified and approved by the Engineer.
The tendered rates shall include for all labour, plant, equipment, materials, delivery, storing, mixing, pumping, placement and all incidentals required.
No payment will be made for wastage or rejected batches. Only verified quantities will be accepted for measurement and payment.
The rates shall include quality control measures, testing of materials, monitoring and supervision of the works, daily records of all items specified in
the Contract Documentation.
The unit of measurement shall be the volume of bentonite slurry pumped for re-use.
The tendered rate for re-used bentonite slurry shall be for full compensation of pumping from completed panels to storage; cleaning and removal
of sand from used slurry to design standards; storage and pumping to new panel positions. Rates shall include for all plant; labour and equipment
necessary for this process. All activities associated with bentonite slurry re-use shall be to the requirements of the Contract Documentation, or as
instructed by the Engineer.
The unit of measure for steel bars shall be the ton of reinforcing steel in place in accordance with the drawings or as authorised.
The tendered rate shall be for full compensation in procuring the steel, bending, cage reinforcement construction, pitching and installation and
shall include for all plant required for reinforcement cage installation; labour and equipment necessary
The unit of measurement shall be the number of concrete panel tops exposed for inspection, measurement and testing.
The tendered rate shall include for all plant, excavating the material around selected panels as well as backfilling of excavations with suitable approved
material in 150mm layers compacted to the required density.
CONTENTS
D12.4.1 SCOPE
D12.4.2 GENERAL
D12.4.3 PERFORMANCE GUARANTEE REQUIREMENTS
D12.4.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D12.4.5 VISUALLY ASSESSED PROPERTIES
D12.4.6 INSTRUMENTALLY ASSESSED PROPERTIES
D12.4.7 EVALUATION FOR ACCEPTANCE
D12.4.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D12.4.9 NOTIFICATION OF REMEDIAL WORK
D12.4.10 REMEDIAL WORKS
CONTENTS
PART A: SPECIFICATIONS
A12.5.1 SCOPE
A12.5.2 DEFINITIONS
A12.5.3 GENERAL
A12.5.5 MATERIALS
A12.5.8 WORKMANSHIP
A12.5 SHOTCRETE
PART A: SPECIFICATIONS
A12.5.1 SCOPE
This Section covers supply and application of shotcrete to rock and soil cut faces, soil nail faces, slope stabilisation and slope remediation, and
other areas as directed by the Engineer. It includes supply and application of shotcrete by either dry or wet-mix methods and for reinforcement
included in shotcrete layers. Sprayed concrete applied onto concrete faces is covered in Section A14.6 of Chapter 14: Rehabilitation of Structures.
A12.5.2 DEFINITIONS
Dry-mix shotcrete - constituent materials, comprising of a mixture of cementitious binder and aggregates, are mixed and delivered to the application
nozzle in dry form. Water and admixtures are added at the application nozzle under high pressure while being sprayed onto the receiving surface.
Shotcrete - means mortar or concrete which can be pneumatically projected at high velocity onto a surface.
Dental Shotcrete - is shotcrete applied to fill/cover or repair of a specific area/feature.
Shotcreting - is the process whereby mortar or concrete is pneumatically projected at high velocity onto a surface. It can comprise of dry-mix or wet-
mix shotcreting.
Wet-mix shotcrete - constituent materials, comprising of a mixture of cementitious binder, aggregates, water and admixtures, are premixed and
delivered to the application nozzle as a wet-mix before being sprayed onto the receiving surface.
A12.5.3 GENERAL
A12.5.3.1 Method Statements
Where so indicated by the Engineer the Contractor shall prepare detailed method statements for each facet of the work describing key aspects
such as construction methodology, key plant, materials, personnel as well as any programme constraints of the envisaged construction process.
These method statements shall be prepared and submitted to the Engineer for approval prior to commencement of that activity, within time scales
specified. The onus lies with the Contractor to ensure that the information is obtained and that associated activities are completed expeditiously
to avoid any delays in the commencement, continuation and completion of the required works. Unless otherwise specified or provided for in the
Contract Documentation no permanent works shall be commenced until the Engineer’s approval of the relevant method statement. The Contractor
shall, however, remain responsible for all work-methods, materials, plant and equipment used, notwithstanding acceptance by the Engineer.
The Contractor shall be required to construct trials and the testing thereof as specified herein and shall make due allowance therefore in his
programme. Allowance shall also be made for allow for the Engineer’s assessment of constructed works, procedures followed, and materials and
plant utilised and test data. Production work shall not be permitted until it is shown and accepted by the Engineer that the Contractor possesses
the necessary experience, plant and equipment to carry out the works as specified in the Contract Documentation.
It should be noted that work shall only be performed by personnel listed by the Contractor. If personnel changes need to be made during the
project, works shall be suspended until replacement personnel are approved by the Engineer. Time lost due to incomplete submissions,
Materials Approvals
A12.5.5.4 Admixtures 1 week prior to use
A12.5.5.11 Curing compounds 1 week prior to use
A12.5.5.4 Test panels 6 weeks before
construction
Note that the above design shall be carried out by competent personnel following the relevant approved/ specified mix design procedures. Slump
of various mixes shall be determined to provide a basis for ongoing quality assurance during production shotcreting.
The Contractor shall submit his proposed cementitious shotcrete mix design for shotcreting accompanied by all relevant information for approval
by the Engineer. Lead time as per Table A12.5.3-1 is required for this information. It should be noted that shotcreting will only permitted to proceed
if the Engineer is satisfied that the mix meets the minimum performance criteria specified including 28 day characteristic strength of the shotcrete
as specified in the Contract Documentation.
Any changes to the mix after the Engineer’s approval shall only be permitted if approved in writing by the Engineer.
A12.5.5 MATERIALS
A12.5.5.1 Cementitious binder
Refer to Clause A14.4.5.2a) of Chapter 14.
a) Cement
Cement shall be CEM I or CEM II with a strength class of 42,5 or greater. Where site blends are proposed, they shall conform to the particular
requirements of SANS 50197 - 1. (As per Clause A14.4.5.2a) of Chapter 14).
b) Supplementary cementitious materials
Refer to Clause A13.4.5.1b) of Chapter 13.
A12.5.5.2 Aggregates
Aggregate shall conform to the requirements of Clause A13.4.5.7 of Chapter 13 and SANS 1083.
A12.5.5.3 Water
Water used for batching of shotcrete hall be potable, complying with SANS 51008.
The supply of water to the mixing nozzle shall be such that a pressure of at least 400 kPa can be maintained.
A12.5.5.4 Admixtures
Shotcrete admixtures shall comply with SANS 50934 and shall be submitted to the Engineer together with the proposed mix design for approval
prior to commencement of work. Admixtures shall have no deleterious effects on reinforcement or shotcrete, and shall not contain any chlorides,
nitrates, sulphides or sulphites. Where more than one admixture is included in the shotcrete mixture, they shall be chemically compatible. Approval
of the shotcrete admixture shall be subject to satisfactory demonstration of suitability of the proposed shotcrete mixture through the construction
of trial panels and acceptable quality assessments conducted on a minimum of three test panels representing three independently batched
shotcrete mixes.
A12.5.5.7 Fibres
Fibres shall conform to the requirements of Clause A14.6.5.7 of Chapter 14.
A12.5.5.8 Reinforcement
All reinforcement shall comply with Section A13.3 of Chapter 13. Reinforcement type and description shall be welded steel fabric mesh reference
number 395 (SANS 1024) unless otherwise specified in the drawings or Contract Documentation.
Water collection geopipes shall be perforated or slotted U-PVC pipes that comply with SANS 791.The size of perforations in perforated pipes shall
in all cases be 8,0 mm in diameter plus or minus 1,5 mm, and the number of perforations per metre shall not be fewer than twenty-six for 100 mm
pipes and fifty-two for 150 mm pipes. Perforations shall be spaced in two rows for 100 mm pipes and in four rows for 150 mm pipes. Slotted pipes
shall have a slot width of 8,0 mm with a tolerance of 1,5 mm. Arrangement of slots shall be subject to approval by the Engineer, but the total slot
area shall not be less than that specified for perforations. Installed pipes shall protrude 20 mm beyond the surface of final shotcrete layer and
have their inner slotted section end wrapped with a single layer of approved geosynthetic.
Pipes without slots or perforations required for transporting water from the drainage system to point of discharge shall be U-PVC.
Geocomposite/geosynthetic drains shall be of type specified in the Contract Documentation and shown on the drawings. Strip or band drains
generally 150mm wide geosynthetic which discharge into weepholes installed through shotcrete lining are commonly specified. Such shall be
detailed on the drawings where these drain types are specified.
These materials shall be protected against sunlight and mechanical damage during storage and installation. Geosynthetics shall be non-woven,
spun or thermic-bonded filament consisting of more than 85 % by mass of polypropylene, polyester or other approved material and manufactured
for civil-Engineering applications by a recognised manufacturer.
In special applications requiring particular drainage measures, shotcrete may require application over vegetation, matting or other bonded open-
structured geosynthetic. Geosynthetic requirements shall be specified in the Contract Documentation and shown on drawings.
A12.5.7.4 Formwork
Formwork and shooting strips for shotcrete shall be employed to ensure square corners, straight lines and a plane surface of shotcrete, except
as otherwise permitted by the drawings or the Engineer’s approval. Formwork and shooting strips shall be designed and placed to avoid pockets
of rebound.
A12.5.7.8 Delivery
a) Dry-mix process
Shotcrete shall be applied as dry as practicable to prevent shrinkage cracking, while ensuring a compacted dense homogeneous mass.
Appropriate measures shall be taken to ensure that fresh concrete remains sufficiently workable until end of spraying.
Dry mix compositions with moist aggregate shall normally be applied within 60 minutes after mixing and shall be discarded after such elapsed
period. If more than 60 minutes is required until the end of spraying of a batch, open time provided by the chosen measures shall be demonstrated
and verified in advance to the Engineer’s satisfaction.
Dry mix composition with oven or kiln dried aggregate may be stored for a limited time but shall be applied immediately after mixing with water.
Oven or kiln dried material should be pre-dampened before the nozzle or before it is loaded in the spraying machine. When adverse weather
conditions require use of quickset cement, procedures shall be adjusted to allow for limited open time of the mix.
Detrimental changes in the dry mix, such as segregation, or other changes shall be minimized during loading, transporting and unloading as well
as during conveying on site. Plant shall be chosen, screened off and suitably controlled in a manner that prevents excessive cement dust
generation and aggregate separation.
b) Wet-mix process
Measures shall be taken to ensure that mixed constituents remain sufficiently workable until end of spraying. Normal workability time shall be
determined by pre-construction tests on test panels. If work requires longer workability times it shall be verified by additional tests. Wet mix
compositions shall be applied within 60 minutes after mixing and shall be discarded after such elapsed period. Detrimental changes to the base
mix, such as segregation, bleeding, paste loss, or other changes shall be minimized during loading, transporting and unloading as well as when
being conveyed on site.
A12.5.7.10 Finishing
The finished surface shall generally follow the contours of the roughly trimmed face such that it mimics the natural rock faces. It shall, however,
be free from rebound pockets or other defects. The inclusion of fibres may affect the finish obtained. The types of finish shall be designated on
the drawings by the following:
- SU: Undisturbed nozzle finish
- ST: Trowelled finish
- STB: Trowelled and brushed
- STF: Trowelled and flash-coated
- STW: Trowelled and wood floated.
The general procedure for achieving required finishes shall be:
Undisturbed nozzle finish (SU)
- The sprayed surface shall be brushed with a soft plasterer’s brush approximately one hour after placement to remove adhering rebound
dust and to prevent surface crazing.
Trowelled finish (ST)
- The surface shall be trowelled when the shotcrete exhibits initial set to obtain a uniform curved or plain surface true to line and shall then
be finished with one of the following treatments if so specified:
Brush-coated (STB)
- Coating of the trowelled surface with a cement mortar slurry using a soft broom or brush to give a soft “brushed effect”
Flash-coated (STF)
- Coating the trowelled surface with a thin uniform layer approximately 3,0 mm thick of shotcrete at least four hours after trowelling but not
later than eight hours.
Wood-floated (STW)
- Floating the trowelled surface with a wood float to produce a smooth even surface free from trowel marks
A12.5.8 WORKMANSHIP
A12.5.8.1 Tolerances
The tolerances provided below shall be maximum permissible deviations from specified dimensions, levels, alignment, positions, etc., as shown
on drawings.
- Position: the lesser of 100 mm or the specified position of the total shotcrete member.
- Thickness - Arithmetic mean value per lot: minimum 100 % of specified layer thickness, maximum thickness not specified.
- Individual depth at any measurement point: minimum 80 % of specified layer thickness, maximum thickness not specified.
- Surface regularity (where applicable): maximum value of any individual irregularity, measured with a custom template that ensures specified layer
thickness is achieved and is less than 25 mm.
CONTENTS
B12.5.1 SCOPE
B12.5.2 DEFINITIONS
B12.5.3 GENERAL
B12.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.5.5 MATERIALS
B12.5.6 CONSTRUCTION EQUIPMENT
B12.5.7 EXECUTION OF THE WORKS
B12.5.8 WORKMANSHIP
B12.5.1 SCOPE
The provisions of Part A shall apply.
B12.5.2 DEFINITIONS
The provisions of Part A shall apply.
B12.5.3 GENERAL
The provisions of Part A shall apply.
B12.5.5 MATERIALS
The provisions of Part A shall apply.
B12.5.8 WORKMANSHIP
The provisions of Part A shall apply.
The tendered lump sum shall include full compensation for establishing on site all plant and equipment, scaffolding, platforms, materials and
personnel necessary to carry out the specified work and for the removal from site of all such plant and equipment including all temporary works
such as access roads, staging, platforms and such like on completion of the works.
Work shall be paid as Lump Sum, 50 % of which will be due when all equipment is on site, trials (if any) are completed, and the first production
shotcrete has been applied to full thickness as specified. A second instalment of 25 % shall be payable after half the shotcreting has been
completed and final 25 % after all the shotcrete has been applied - and accepted - and all equipment and plant removed from site
The unit of measurement shall be the square metre of face/slope cleared of all loose or unwanted material, including indicated vegetation, and
manually trimmed to designed lines and levels as specified.
C12.5.3.1 Welded steel mesh fabric (Ref. 395) square metre (m2)
The unit of measurement for steel mesh shall be the net square metre of reinforcement actually incorporated into shotcrete. Measurement shall
be based on square metre of soil and or rock slope covered with mesh and measured on the plane of the slope. No overlaps of mesh and or
reinforcement system shall be measured.
The unit of measure for fibre shall be the mass in kilograms of fibre actually used, as determined by the kilogram of fibre per cubic metre of
shotcrete specified.
The tendered rate shall include full compensation for supply and installation, including all equipment, plant, materials, labour and incidentals
necessary to carry out the specified work and including specifically supply and installation of pins, earth spikes, soil nails/ rockbolts, wire ties, gun
nails and any other approved fastenings for the completion of the work as specified.
C12.5.4.2 Intermediate coat/s (specify thickness and number of layers) square metre (m2)
C12.5.4.3 Final coat (specify thickness, pigmentation and finish square metre (m2)
The unit of measurement shall be the net square metre of face measured in the plane of the cutting face, which is protected by shotcrete of
specified nominal thickness, installed as specified. No separate allowance shall be made for an uneven surface when measuring the area over
which shotcrete is applied.
The unit of measurement for dental shotcrete shall be the cubic metre of shotcrete of measured batch volume, agreed with the Engineer and
installed in accordance with the specifications.
The tendered rate shall include for everything necessary to carry out specified work as specified. and shall include safe access for the Engineer
to any portion of the cut face or slope.
C12.5.5 Removal to spoil of material trimmed from slope cubic metre - km (m3.km)
The unit of measurement shall be the cubic metre - kilometre which is calculated as the product of the quantity of material cleared, temporarily
stockpiled, loaded, transported in excess of 1.0 kilometre and disposed at approved spoil site, in accordance with the requirements multiplied by
the applicable haul distance which shall be calculated as defined in Clause A1.7.3.1 of Chapter 1.
The tendered rate shall include full compensation for trimming all material, and for all equipment, labour and other incidentals necessary to
complete specified work. Haul distance shall be measured from mass-centre to mass-centre.
The volume of such material shall be taken to be equal to 70 % of the loose struck volume measured in the truck.
The unit of measurement shall be the linear metre of perimeter where shotcrete is required to be finished off as detailed in the drawings, all as
specified.
The tendered rate shall include full compensation for excavation and spoiling of material from trenches, bending of mesh or reinforcement,
application of shotcrete irrespective of volume involved as well as all equipment, labour, transport and other incidentals necessary to complete
the specified work.
C12.5.7.1 50 mm diameter U-PVC weephole piping (specify length and class) number (No)
C12.5.7.2 Geopipe collectors (specify type, diameter and class) metre (m)
C12.5.7.3 Other piping (specify type, diameter and class metre (m)
The unit of measurement shall be the linear metre of geocomposite drain installed as specified at spacings or positions specified or as indicated
on the drawings.
The tendered rate shall include full compensation for supply, installation, protection during spraying, plant, equipment, labour and all other
incidentals necessary to complete the specified work.
D12.5.1 SCOPE
The scope of this Section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
D12.5.2 GENERAL
The Contractor shall provide detailed specifications, test data, performance data and compliance certificates from independent reputable agencies
for all proprietary systems, processes and materials proposed for use. These shall demonstrate conformance with the performance requirements
specified in the Contract Documentation.
Unless otherwise specified, all proprietary materials shall be used and placed in strict accordance with the relevant manufacturer's current
published instructions.
CONTENTS
PART A: SPECIFICATIONS
A12.6.1 SCOPE
A12.6.2 DEFINITIONS
A12.6.3 GENERAL
A12.6.5 MATERIALS
A12.6.8 WORKMANSHIP
A12.6.2 DEFINITIONS
Anchored earth - is a form of reinforced soil which uses anchors embedded within the soil mass to provide stability/resistance to pull-out
by passive action of the anchor and friction along the anchor shaft or loop.
Axially-flexible reinforcement - is reinforcement that can absorb tensile loads only.
Axially-stiff reinforcement - is reinforcement that can absorb tensile, shear and bending loads.
Extensible reinforcement - is reinforcement that sustains design loads at strains greater than 1 %.
Geogrids - are polymeric, planar structures consisting of an open network of connected tensile elements used in geotechnical and civil
Engineering applications.
Geotextile - are permeable, polymeric materials, which can be woven, non-woven or knitted, used in geotechnical and civil Engineering
applications.
Inextensible reinforcement - is reinforcement that sustains design loads at strains less than or equal to 1 %.
Partial factors - partial factors are specific design parameters to account for uncertainty.
Polymeric reinforcement - is a generic term that encompasses geosynthetic materials used as soil reinforcement in geotechnical
Engineering such as geotextiles, geogrids and geostrips.
Reinforced soil - is a general term which refers to use of imported or in situ soil or other material in which tensile reinforcements act through
interface friction, bearing or other means to improve stability.
Reinforced soil segmental block structure - is a reinforced soil structure with a facing comprising dry stacked blocks with a fixed
connection, without compressible joints between blocks and without joint fillers/covers.
Reinforcement base strength - is the un-factored strength of reinforcement at end of its design life.
Reinforcement design strength - is the factored strength of reinforcement at end of its selected design life; it is the reinforcement base
strength divided by the appropriate partial material factor.
Gabion boxes - are made from double twisted steel mesh and are subdivided into 1,0 m wide cells by diaphragms at 1,0 m intervals.
Gabions are filled with selected rock material providing pervious, semiflexible building blocks for slope and channel stabilisation.
Gabion mattresses - are made from steel mesh and are subdivided into 0,6 or 1,0 m metre wide cells by diaphragms. The mattresses are
filled with selected rock material providing pervious, channel linings, revetments and other anti-erosion and containment structures.
A12.6.3 GENERAL
A12.6.3.1 Design of Mechanically Stabilised Earth (MSE)
Table A12.6.3-1 below illustrates design considerations for vertical MSE’ walls illustrating typical design height limitations and uses. All geogrid or
strip reinforcement shall have a positive mechanical structural connection when used to retain a road pavement (surfacing, structural layers, kerbs,
etc) or a structure. The structural adequacy and pullout capacity of the connections shall be demonstrated by test data from pullout tests. Durability
and deflection of welded wire or gabion facings shall be crucial in assessing if the system can be used in the specific application.
Table A12.6.3-1: Design Considerations for Vertical MSE height limitations:
Type Description Typical Requirements Comments
Height
Limitations
(m)
Precast Concrete Discrete panels with 0 -18 m
Panel System compressible
bearing pads placed
between joints
Closed block Positively reinforced 0 -12 m ASTM D6638 and ASTM D6915 test results These systems
Segmental Block concrete segmental must be provided for acceptance of the shall have a
Retaining Walls I block retaining walls system. “positive”
connection to the
facing when
retaining road-
pavements or
structures.
MSE Wire-Faced Welded steel 0 -10 m Durability must be assessed in accordance to Not recommended
facings EN ISO 9223 and 9224 and the working life for bridge
provided. The expected deflection of the abutments
facing should be assessed and commented
on in the design.
Gabion Faced Reinforced Gabion 0 -10 m Durability must be assessed in accordance to Not recommended
faced wall EN ISO 9223 and 9224 and the working life for bridge
provided. The expected deflection of the abutments
facing should be assessed and commented
on in the design.
Materials Approvals
A12.6.5.1a) Materials for MSE wall elements, gabions 2 weeks prior to use
A12.6.5.2a) Reinforcement for MSE walls 2 weeks prior to use
A12.6.5.12 Testing of joints 2 weeks post construction
- Contractor shall provide a quality management plan indicating his proposed quality assurance testing programme which shall allow, if necessary,
testing at each treatment position as required. Testing methods to be employed shall be as specified in Contract Documentation.
A12.6.5 MATERIALS
A12.6.5.1 Materials for MSE walls
a) General
All materials used in constructing MSE walls, shall comply with Table B.1 of. SANS 54475 and be subject to approval by the Engineer. When
requested by the Engineer, the Contractor shall submit test certificates from an approved independent testing authority to show that materials
comply with specified requirements, or where applicable certificates from patent holders or licensees certifying that manufactured items comply in
all respects with relevant product specifications. All facings, soil reinforcement and fastener materials shall be designed and sourced from a single
MSE supplier to ensure compatibility.
b) Concrete facings
Concrete facings shall be manufactured from materials which comply with relevant requirements of Sections A13.2, A13.3 and A13.4 of Chapter
13 and have a 28-day cube strength of 30 MPa unless otherwise detailed in the Contract Documentation.
c) Concrete block facings
Concrete block facings used in MSE walls shall be manufactured and tested according to SANS 508. These shall have a positive connection to
reinforcement.
Pigments used for colouration of concrete blocks shall conform to BS EN 12878.
d) Concrete bases and foundations for earth retaining systems
All materials for concrete bases and foundations for earth retaining systems shall comply with relevant requirements of Sections A13.3 and A13.4
of Chapter 13.
e) Metallic soil reinforcements
Metallic soil reinforcement shall be manufactured from corrosion-resistant materials designed to ensure adequate performance when buried for
the design life of the structure. This metallic reinforcement may take the form of sheets, grids, meshes, strips, bars, rods, ladders etc. and shall
comply with section 3.2.1 of BS 8006-1:2010.
Galvanizing shall comply with the requirements of SANS 121 for bars and SANS 675 for wire up to 5,0 mm in diameter.
f) All facing units and their applications shall conform to SANS 54475 Fasteners between facing and reinforcing elements
Fasteners or joints (either metallic or polymeric) between facing and reinforcing elements shall comply with Section 3.4 of SANS 8006-1). Facings
shall have a positive connection to reinforcing elements. Galvanising shall comply with SANS 121.
g) Joint filler materials on facings
Fillers shall be durable, flexible, and resistant to effects of air pollution, and water that might be contaminated with de-icing salt.
h) Bedding material
Selection of bedding material depends upon structural behaviour of the facing assumed in design of the wall. Cement mortar or a durable gasket
material such as resin bonded cork, bitumen bonded cork, rubber or ethylene propylene diene monomer (EPDM) may be used.
i) Sealing material
Filling of joints other than bedding joints may be done either with closed cell polyethylene foam, closed cell polyurethane foam strips in the joint, or
geotextile strips over the rear face of joint as approved by the Engineer.
Any accessory proprietary products, elements or fittings necessary for construction of MSE structures shall comply with appropriate, accepted
standards or specifications.
j) Polymeric materials
All polymeric materials delivered to a site shall be identified in accordance with BS EN ISO 10320 and SATR 20432.
Joints shall be formed to have high mechanical and durability efficiency, compared to the performance characteristics of the parent
materials. Test methods used to assess joints shall correspond closely to those procedures employed when determining properties of the
parent materials. All joints used in permanent structures designed to carry loads shall be tested in accordance with BS EN ISO 10321
and results presented to the Engineer for approval.
(ii) Overlaps
In situations where relatively small tensions develop, overlapping may be employed utilising coarse sand-filled 20 mm thick joints (Sand
as per Table A3.1.5-1 of Chapter 3.
Such joints are sometimes used in secondary tensile directions but shall not be employed in primary tensile directions in reinforced soil
structures. Overlapping may also be used for jointing under water where amount of overlap depends on design considerations and
construction conditions.
(iii) Stapling
This method may be used with geotextiles to make temporary joints. Stapling shall never be used for structural jointing.
(iv) Other jointing methods
Other jointing methods may be adopted. However, general recommendations as set out above still apply.
m) Fasteners and connections between facing and reinforcing elements
(i) General
Fasteners are used to make a connection between the reinforcement and the facing and take the form of dowels, rods, hexagon headed
screws and nuts and bolts, and shall consist of either steel or polymers.
The choice of material used to form the fastener shall be compatible with design life of structure. Materials for fasteners and
connections shall conform to criteria described in BS EN 14475
(ii) Steel coatings
These may be divided into two groups:
- metallic coatings, including galvanizing in accordance with BS EN ISO 1461/SANS121 and aluminium-zinc coatings in accordance
with BS 2569; and,
- organic coatings, including bitumen in accordance with BS 3416 and BS 4147, coal tar products in accordance with BS 4164, polyvinyl
chloride (PVC), liquid and powder epoxies and liquid polyurethanes.
The application rates of coating to the base metal of the fastener are given in the Contract Documentation.
c) Wire
All wire used and dimensions for manufacturing the gabions and for tying during the construction of the gabions shall comply with the requirements
of SANS 675 for class A heavy galvanized mild-steel wire.
e) Galvanizing
All wire used in the making of gabions shall comply with SANS 1580 (zinc) or SANS 10244-2 table 2 (Zn95Al5).
f) Wire mesh
Wire mesh shall comply with the requirements of SANS 1580.
Boxes:
Length: 1, 2, 3 or 4 m
Width: 1,0 m
Depth: 0,5 m and 1,0 m
Diaphragm spacing: 1,0 m
Mattresses
Length: 2, 3 or 6 m
Width: 2,0 m
Depth: 0,17 m, 0,23 m and 0,3 m
Diaphragm spacing: 1,0 m
Other gabion sizes may be supplied, subject to the Engineer's prior approval.
i) Alternative materials
Alternative materials required, their property requirements, construction, measurement and payment shall be specified in the Contract
Documentation.
- Geosynthetic/polymer reinforcement shall either be fixed to the panels providing positive connection in an approved manner or
clamped between the panels where specified. Special care shall be taken to ensure the edges on facing panels are not sharp
or jagged such that thereinforcement may be damaged.
- The geosynthetic layer shall be uniformly laid taut over its specified length and held in place by approved means. The Engineer’s
approval of such tensioning shall be obtained prior to any placement of backfill. There shall be no loss of tension during
backfilling operations. Damaged reinforcements shall be removed and replaced at the Contractor’s cost.
- Fill material behind the facing panels shall be placed and compacted in accordance with Chapter 4 to greater than 95 % of the
Maximum Dry Density as per SANS 3001 at a moisture content of 0 to plus 2 % of the optimum moisture content, except that
the layer thickness may vary slightly to suit the position of soil reinforcement.
- Deposition, spreading, levelling and compaction of fill shall generally be carried out in a direction parallel to the facings, and
shall be executed in stages to alternate with placing and fixing of the reinforcing elements and the facing.
- Fill shall be deposited, spread, levelled and compacted in horizontal layers of appropriate/specified thickness. Spreading and
compaction shall be carried out so that all layers of the soil reinforcing elements are fixed at the specified levels on top of the
compacted fill.
- Fill shall be placed such that it slopes away from the face at 2 % to ensure water ponding at the soil/facing element interface
does not occur.
- Fill shall not be placed right up to the cladding panels before the underlying reinforcing is covered, with compacted fill materials
to anchor the reinforcement adequately to maintain the facing panel in position. Fill shall be placed from the end of the
reinforcement to the cladding panels.
- Metallic reinforcement shall be placed on compacted fill and in intimate contact with the ground, which shall have a nominal fall
of 2 % away from the facing.
- If inspection of elements prior to or during placement reveals bends or kinks with a radius less than twice the reinforcement
thickness, these shall be rejected.
- Small areas of galvanized coating damaged during handling shall be repaired in accordance with BS EN ISO 1461.
- Most sheet products exhibit preferential strength direction and therefore placing of reinforcement shall be consistent with the
direction of major stresses. Details shall be indicated on the drawings and Contract Documentation.
- Ideally strips shall be laid in the major load bearing direction, i.e. transverse to the embankment centreline. However,
construction is facilitated and sewing time minimized if geosynthetics are laid in centreline direction. This is not recommended
but may be allowed if joint-integrity is assured and the design takes account of likely transverse-direction-reduced-strength.
- Geotextiles and geogrids are generally supplied in rolls of specific width. Rolls shall not be cut along their width to fit a smaller
area and overlapping between adjacent rolls shall be adopted, this to avoid ravelling after cutting.
A12.6.7.2 GABIONS
a) Classification of materials
All excavations for gabions shall be excavated in the position indicated on the drawings and to the required dimensions. Overbreak in width or
depth shall be reinstated to the original condition as approved by the Engineer at the Contractor’s cost.
All excavations under this Section shall be classified as specified under Clause A11.1.7.1 of Chapter 11.
b) Constructing gabion boxes and mattresses
(i) General
Gabion boxes and mattresses shall be manufactured from wire mesh of the size and type and selvedge as specified below.
Boxes are generally used for the construction of gabion walls: The boxes are subdivided into cells by diaphragms spaced at 1,0 m
intervals. No diaphragms are required for boxes where the length does not exceed 1,5 m.
Mattresses are generally used as single-layer aprons in revetments, channel linings, etc, which the maximum width of units shall be
2,0 m, and the maximum depth 0,3 m. Mattresses shall be subdivided by diaphragms into cells with a width of 1000 mm. Mattress
shall be installed with diaphragm spaced at 1,0 m in the direction of the flow, unless otherwise specified by the Engineer.
(ii) Selvedges
The cut edges of all mesh used in the construction of gabions, except the bottom edges of diaphragms and end panels, shall be
selvedged with wire with a diameter as specified in SANS 1580.
Where the selvedge is not woven integrally with the mesh but has to be tied to the cut ends of the mesh, it shall be attached by tying
the cut ends of the mesh to the selvedge, so that a force of more than 8,5kN applied on the selvedge in the same plane as the mesh
of a mesh sample of 1,0 m in length will be required to separate it from the mesh.
(iii) Diaphragms and end-panels
The diaphragms and end-panels shall be selvedged on the top and vertical sides only. The end-panels shall be attached by the cut
ends of the mesh wires at the bottom of the panel being twisted around the selvedge on the base of the gabion. Similarly, the
diaphragms shall be attached by the cut ends of the mesh being twisted to the twisted joints of the mesh in the base of the gabion. In
each case the force required to separate the panels from the base shall not be less than 6kN/m.
(iv) Binding and connecting wire
Sufficient binding and connecting wire for all the tying to be done during construction of the gabions as specified in Clause A11.2.7.3
of Chapter 11 shall be supplied with the gabion boxes. The binding wire shall have the same properties as the gabion or mattress
mesh wire.
c) Constructing gabions
(i) Preparing the foundation and surface
The foundation surface on which the gabion boxes are to be installed prior to their being filled with rock shall be levelled to the line
and level shown on the drawings or as directed by the Engineer so as to present an even surface. If necessary, cavities between rock
protrusions shall be filled with appropriately sized material (See Clause A12.6.5.2). Where required, a foundation trench along the toe
of the revetment or wall shall be excavated to the dimensions specified and/or shown on the drawings.
(ii) Geotextile
One layer of geotextile shall be placed where indicated on the drawings or as specified. The geotextile shall be placed, in strips with
a minimum overlap of 300 mm at the joints and shall be properly fastened to prevent any movement or slipping while the gabions are
being placed.
(iii) Assembly
The methods of constructing, stretching, placing in position, wiring and filling the gabions with rock shall generally be in accordance
with the manufacturer's instructions subject to the approval of the Engineer, but nevertheless sufficient connecting wires shall be
tensioned between the vertical sides of all the outer visible cells and a sturdy frame shall be used to prevent the deformation of boxes
as they are being filled with stone. Joints between boxes shall be wired together along all 4 joining edges.
It is essential that the corners of gabion boxes be securely wired together to provide a uniform surface and ensure that the structure
does not resemble a series of blocks or panels. The layout and the tolerances for the layout of the boxes shall be as shown on the
drawings or as specified in the Contract Documentation.
(iv) Rock filling
1. Boxes in gabions
Particular care shall be taken in packing the visible faces of gabion boxes, where only selected stone of the specified size shall
be used so as to obtain an even-faced finish. The boxes shall be filled in layers to prevent deformation and bulging. Boxes shall
be wire braced and filled to just below the level of the internal wire braces, after which the braces shall be twisted to provide
tension. Care must be taken to ensure that consecutive layers of boxes are filled evenly to a level surface ready to receive the
next course.
Filling of gabion boxes by dumping rock shall not be permitted and packing shall be done by means of hand labour.
A12.6.8 WORKMANSHIP
A12.6.8.1 MSE Walls
a) Facing foundations
Facing foundations shall at all times be level or stepped in facing panel size benches to ensure subsequent panels are always placed level even
if on sloping surfaces. In cases where the Contract Documentation prescribes ground improvement or drainage works to be carried out prior to
commencement of MSE’s, such work shall be undertaken as specified in other sections of Chapter 12, as may be specified.
b) Concrete facings
Concrete quality shall be tested to ensure compliance with 28 day strength, W standards as regards oxygen permeability, water sorptivity and
chloride conductivity as detailed in Clause A20.1.7.5c)(ii) of Chapter 20 and/or as specified in Contract Documentation.
c) Concrete blocks
1. Tolerances
Blocks shall comply with category D2 of BS EN 771-3 and Appendix A1. The width of a block is the distance from the front face
to the soil face and shall be as defined in BS EN 771-3:2003+A1. In some instances the exposed face is often a textured face or
else is a rough face created by splitting a double-width block which may be outside the specified width. The location of any nibs or
voids is critical and the method statement shall provide details of the specific blocks used and the associated operation-sequence.
2. Shear strength
The shear strength between blocks and connection strength between block and reinforcing element shall be determined. Concrete
block facings used in MSE walls shall be manufactured and tested according to SANS 508.
The test methods in ASTM D6916 and ASTM D6638 for measuring block-to-block shear strength and block-to-soil reinforcement
connection strength for blocks with plane-faced bedding surfaces shall be used where required by Engineer.
A12.6.8.2 Gabions
a) General
The Contractor shall determine the required frequency of testing and conduct sufficient tests on the sourced material for each type of material, in
order to ensure that the quality of materials produced meets the specified requirements. Similarly, the Contractor shall conduct sufficient checks
and controls during construction of the elements to ensure that the required lines, levels and finishes are achieved.
Any work or materials which do not comply with the specified requirements, shall be removed and replaced with work or materials which comply
with the requirements or, if the Engineer so permits, shall be repaired so that it shall comply with the specified requirements after having been
repaired.
b) Tolerances
Tolerances for gabion and mattress materials and dimensions shall conform to the requirements of EN 10223-3.
Both the vertical and horizontal tolerances for gabions facing and mattresses surfaces shall not deviate more than 20 mm over 1,0 m as well as
not more than 50 mm over 3,0 m sections.
CONTENTS
B12.6.1 SCOPE
B12.6.2 DEFINITIONS
B12.6.3 GENERAL
B12.6.5 MATERIALS
B12.6.1 SCOPE
For MSE the provisions of Part A shall apply.
The construction of segmental block walls shall be deemed to be a labour enhanced construction process and this Section therefore includes
work with a large component of labour. This work is included in Part A of this specification. This Part therefore only covers additional specifications
for work to enhance the labour component of construction activities where specified.
The construction of gabions shall be deemed to be a labour enhanced construction process and this Section therefore includes work with a large
component of labour. This work is included in Part A of this specification. This Part therefore only covers additional specifications for work to
enhance the labour component of construction activities where specified.
B12.6.2 DEFINITIONS
The provisions of Part A shall apply.
B12.6.3 GENERAL
The provisions of Part A shall apply.
B12.6.5 MATERIALS
The provisions of Part A shall apply.
Material which can be excavated efficiently by means of a suitable shovel with or without the use of a pick
Soft
or other hand-swung tool.
Material which is difficult to excavate by hand even with the aid of a crowbar and requires the assistance of
Intermediate
pneumatic tools for economic removal.
*1 Only applicable to materials comprising not more than 10 % gravel of size less than 10 mm and materials containing no cobbles or
isolated small boulders.
B12.6.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be a lump sum. The tendered lump sum for MSE shall include full compensation for establishing all necessary
plant and equipment on site to carry out the works and for the removal from site of all such plant and equipment including all temporary works
such as access roads, staging, platforms and such like on completion of the works.
Work shall be paid as a lump sum, 50 % of which shall be due when all the equipment is on site, trials (if any) are completed and 25 % of the
first production wall is installed to full height as specified. The second instalment of 25 % shall be payable after 50 % of the walls are installed
and final 25 % instalment after the specified walls are installed, accepted and in service and all equipment is removed from site.
The tendered lump sum shall include full compensation for all post-construction requirements as specified. No extra payment shall be made for
the establishment of additional plant should the established plant not be capable of achieving desired objectives.
The tendered rate shall include for all labour, plant and equipment required for the operation.
The unit of measurement shall be the cubic metre of required strength concrete.
The tendered rate shall include full compensation for all labour, plant and equipment required for the operation as well as shuttering if necessary.
The unit of measurement shall be the ton (t) of steel required for the operation.
The tendered rate shall include for all fixing wire, cover blocks and all other labour, plant and equipment required for the operation.
C12.6.5 Preparation of surface for laying metallic strips or geosynthetic square metre (m2)
The unit of measurement shall be the square metre of base surface prepared for the initial (first layer) strips or geosynthetic only. Subsequent
layer preparation costs are deemed to be included in the unit cost for backfill.
The tendered rate shall include full compensation for all materials, labour, plant and equipment required for the operation.
The unit of measurement shall be the metre of metallic strips of required section installed.
The tendered rate shall include full compensation for the supplying of all the materials, labour, plant and equipment required for the operation.
C12.6.7 Metallic reinforcing mesh (section dimension indicated) square metre (m2)
The unit of measurement shall be the square metre of metallic mesh of required section installed.
The tendered rate shall include full compensation for the supplying of all the materials, labour, plant and equipment required for the operation.
C12.6.8 Polymer/ Geosynthetic reinforcing strips (section dimension indicated) metre (m)
The unit of measurement shall be the metre of geosynthetic strips of required section installed.
The tendered rate shall include full compensation for the supplying of all the materials, labour, plant and equipment required for the operation.
The unit of measurement shall be the square metre of geosynthetic reinforcing sheet installed.
The tendered rate shall include full compensation for the supplying of all the materials, labour, plant and equipment required for the operation.
The unit of measurement shall be the number for C12.6.10.1 (strips) and by the metre for C12.6.10 (sheets).
The tendered rate shall include full compensation for the supplying of all the materials, labour, plant and equipment required for the
installation operation.
C12.6.11 Backfill (material type and compaction requirements indicated) cubic metre (m3)
The unit of measurement shall be the cubic metre of the required material grade compacted to the required standard.
The tendered rate shall include full compensation for the supplying of all the materials, labour, plant and equipment required for the operation.
The unit of measurement shall be the square metre of panel of the indicated size and thickness.
The tendered rate shall include full compensation for the manufacture, supply, labour, plant and equipment required for the installation as
well as for the sealing of the panel to prevent material egress through panel joints.
The unit of measurement shall be the number of drains installed either on excavation face, behind selected backfill or through facing panels.
The tendered rate shall include full compensation for the supplying of all the material, labour, plant and equipment required for the operation.
C12.6.14.1 Excavating all material situated within the following depth ranges below the surface level
C12.6.14.2 Extra over sub-item C11.2.1.1 for excavation in hard material, irrespective of depth cubic metre (m3)
C12.6.14.3 Excavating soft material within 1,5 m below the surface level using labour enhancement cubic metre (m3)
construction methods:
C12.6.14.4 Excavating intermediate material within 1,5 m below the surface level using labour cubic metre (m3)
enhancement construction methods:
Irrespective of the total depth of the excavation, the quantity of material in each depth range shall be measured and paid for separately.
Excavation shall be done using conventional construction methods and/or labour enhancement construction methods as specified and measured.
The tendered rates shall include full compensation for the excavation of the material to the required dimensions, lines, levels and grades, temporary
timbering, shoring and strutting, including unavoidable overbreak, the trimming of the trenches and compacting the trench inverts, backfilling of
over excavation and compacting the backfill, keeping excavations safe, dealing with any surface or subsurface water and the loading and disposal
of the excess material as directed. The tendered rates shall also include full compensation for any other operations necessary for completing the
work as specified but excluding surface preparation for bedding the gabions.
Loading and hauling, where applicable, including haul of 1,0 km, shall be measured and paid as specified in Section C1.7 of Chapter 1. Where
the excavation of material is specified by means of labour enhancement construction methods, the tendered rates shall include loading and
transport by wheelbarrow if the material is disposed of or utilised within a radius of 50 m, alternatively loading by hand onto transport vehicles for
such disposal or utilisation elsewhere, within a haul distance of 1,0 km.
For payment purposes a distinction shall be made between materials as classified above under Classification of Materials.
C12.6.15 Surface preparation for bedding the gabions square metre (m2)
The unit of measurement for levelling and preparing surfaces for receiving the gabions shall be the square metre to the neat dimensions of
revetments, aprons or wall foundations.
The tendered rate shall include full compensation for excavating, filling any cavities with rock, and levelling the ground surface to be ready for
receiving the gabion boxes tor retaining walls, aprons and revetments.
C12.6.16.2 Polymer coated gabion boxes (dimensions of box) cubic metre (m3)
C12.6.16.4 Polymer coated gabion mattresses (dimensions of mattress) cubic metre (m3)
The unit of measurement shall be the cubic metre of the rock-filled boxes or mattresses and the quantity shall be calculated from the dimensions
of the gabions indicated on the drawings irrespective of any accepted deformation or bulging of the completed gabions. Gabions boxes and
mattresses shall be measured to the nearest specified size.
The tendered rates shall include full compensation for supplying all the materials, including rock fill, wire-mesh boxes, galvanizing, PVC-coating,
tying and connecting wires, loading, transporting and off-loading, the assembling and filling of the boxes, disposal of waste, and any other work
necessary for constructing the gabions.
Placing of rock by dumping shall not be allowed and the tendered rates shall also include full compensation for placing rock by means of hand
labour.
The tendered rate shall include full compensation for supplying the geotextile, cutting, waste, placing, joining, overlapping, and securing the
material in position.
D12.6.1 SCOPE
The scope of this Section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
D12.6.1 GENERAL
The Contractor shall provide detailed specifications, test data, performance data and compliance certificates from independent reputable agencies
for all proprietary systems, processes and materials proposed for use. These shall demonstrate conformance with the performance requirements
specified in the Contract Documentation.
Unless otherwise specified, all proprietary materials shall be used and placed in strict accordance with the relevant manufacturer's current
published instructions
For gabions wire used for manufacturing gabions and for tying during construction of the gabions shall comply with SANS 675. Gabion boxes shall
comply with SANS 1580.
CONTENTS
PART A: SPECIFICATIONS
A12.7.1 SCOPE
A12.7.2 DEFINITIONS
A12.7.3 GENERAL
A12.7.5 MATERIALS
A12.7.8 WORKMANSHIP
A12.7.2 DEFINITIONS
Trenchless Methods - are methods of installing various forms of underground conduit without the excavation of trenches over the installed length
of conduit. These methods include Pipe Jacking, Directional Drilling, Pipe Ramming and Micro-Tunnelling.
Pipe Jacking - is a method for installing a conduit/pipe that serves as initial construction lining and support, installed for stability and safety during
construction, and finally as the service pipe. The pipe is forced forward, or jacked, to advance the conduit.
Micro-tunnelling - is a method of installing a conduit by jacking a pipe behind a micro-tunnel boring machine, generally precluding man entry.
Pipe Ramming - is a method by which a cylindrical tool uses air pressure to pound its way through the ground underneath an obstruction,
simultaneously installing a conduit.
Horizontal directional drilling (HDD) - is a steerable drilling method of installing a small diameter underground services conduit.
Micro-tunnel Boring Machine - is a mechanized excavating machine that is remotely-controlled, steerable, guided and articulated, connected to
and shoved forward by the pipe being installed, usually precluding man entry.
Zone of Active Excavation - the zone of active excavation is the area located within a radial distance about a surface point immediately above
the face of excavation equal to depth to bottom of excavation.
Critical Structure - is an existing service, any building, structure, bridge, pier, or similar construction partially or entirely located within a zone of
active excavation.
Inlet and outlet structures - may be entry and exit points for some applications to especially designed jacking pits in others. Names used in this
text include, entrance/entry and exit, jacking and receiving. These may be circular or rectangular shafts.
A12.7.3 GENERAL
A12.7.3.1 Services and obstructions
A geotechnical investigation shall have been carried out to select the route least affected by known services and which is free of apparent
obstructions. Details of known services and other objects which may constitute an obstruction on site shall be detailed in the Contract
Documentation. Notwithstanding this, unidentified obstructions/services may be encountered.
Materials Approvals
Details and product certificates for materials for
A12.7.5.1 Pipe jacking, Horizontal directional drilling, Pipe 2 weeks before ordering or delivery
ramming or Micro-Tunnelling
The following shall normally be specified (where applicable) by the Engineer and reflected in the Contract Documentation:
Calculations shall include clear statements of criteria used for design as described below:
- The Contractor is responsible for the selection of appropriate pipe and pipe joints to withstand jacking forces, pulling or other forces and any or
other construction loads in combination with overburden, earth and hydrostatic loads. Design of any pipe indicated on the drawings considers
in-place loads only and does not take into account any construction loads. Criteria for the longitudinal loading (jacking forces) on pipe and joints
shall be determined by the Contractor, based on the selected method of construction.
- Jacked pipe shall be designed to withstand the thrust or pulling forces of Pipe jacking, Pipe ramming, Micro-Tunnelling, shield or pipe advance,
without damage or distortion. Propulsion jacks shall be configured so that the thrust is uniformly distributed and will not damage or distort the
pipe.
- Loads from handling and storing shall be taken into account.
- The criteria contained in TMH 7 parts 1 and 2 are to be used.
- The Contractor shall provide pipes of diameter shown on the drawings. Substitution of the pipe/s with larger diameters to suit Pipe Ramming,
Pipe jacking, Horizontal Directional Drilling or Micro-tunnel boring machine equipment availability will only be permitted if the Contractor
demonstrates that design flows and velocities can be achieved.
A12.7.5 MATERIALS
A12.7.5.1 General
All materials used in the works described hereunder shall meet the appropriate standards given below and/or specified in the Contract Documentation
and shall be subject to the approval of the Engineer. The Contractor shall submit details and product certificates where appropriate to the Engineer
two weeks before ordering and delivery to site.
AWWA C200API 2B
Steel
ASTM A139 Grade BAPI 2B (Non-pressure)
Steel
Pipe Jacking (PJ) Jacking
Reinforced concrete pipes (SC type, D100)
Fibreglass Reinforced Polymer Mortar (FRPM) ASTM D 3262 ASTM D3517AWWA C950
The equipment shall be in good working order. Should the type of rig and/or equipment prove inappropriate for the requirements or conditions on
site, these shall be replaced by suitable equipment at the Contractor’s cost.
b) Locating and tracking
The Contractor shall provide details of his proposed method of locating and tracking the drill head during pilot boring. Walkover, wire line, and
wire line with surface grid verification as approved by the Engineer, shall be accepted methods of tracking directional bores. Locating and tracking
systems shall be capable of ensuring the intended installation is achieved. If an area of radio signal interference is expected to exceed 2,0 m, the
Contractor shall provide a suitable alternative tracking system. Locating and tracking systems shall provide information on:
- Clock and pitch,
- Depth,
- Transmitter temperature,
- Battery status,
- Position (x and y),
- Azimuth, where direct overhead readings (walkover) are not possible (i.e. subaqueous or limited access) transportation facility,
- Proper calibration of equipment,
- Alignment readings or plot points shall be taken and recorded every 2,0 m.
c) Monitoring/survey
All facilities shall be installed in such a way that their location can be readily determined by electronic designation after installation. For non-
conductive installations this shall be accomplished by attachment of a continuous conductive material either externally, internally, or integrally with
casing/sleeve. Either a copper wire line or a coated conductive tape for this material may be used. Any break in conductor must be connected by
an electrical clamp of brass or solder and coated with a rubber or plastic insulator to maintain the integrity of connection from corrosion.
Micro-tunnel boring machines shall conform to the tunnel shape with a uniform perimeter that is free of projections that could produce over-
excavation or voids. An appropriately sized overcutting bead may be provided to facilitate steering. In addition it shall be:
- Operation of the system without need for personnel to enter the tunnel. A display available to the operator, at a remote operation console,
showing the shield position in relation to a design reference together with other information such as face pressure, roll, pitch, steering attitude,
valve positions, thrust force, and cutter head torque; the rate of advance and the installed length,
- An integrated system of excavation and removal of spoil and its simultaneous replacement by conduit.
e) Active direction control
Micro-tunnel boring machines shall have the following features:
- Line and grade control by a guidance system that relates actual position of the micro-tunnel boring machine to a design reference, e.g. by a
laser beam transmitted from the jacking shaft along pipe to a shield-mounted target,
- Active steering information which shall be monitored and transmitted to operating console,
f) Jacking system
The jacking system shall have the capability of pushing the micro-tunnel boring machine and pipe through the ground in a controlled manner
compatible with the anticipated jacking loads and pipe capacity.
g) Spoil transportation systems
Where any of the above techniques use a spoil-transportation system, this shall balance soil and ground water pressures using a slurry or earth
pressure balance system, capable of adjustments required to maintain the face stability for the particular soil condition and shall monitor and
continuously balance the soil and ground water pressure to prevent loss of slurry or uncontrolled soil and ground water inflow.
- Provide pressure at the excavation face using slurry pumps, pressure control valves, and a flow meter.
- Include a slurry bypass unit to allow the direction of flow to be changed and isolated, as necessary.
- Include a separation process. The design shall provide adequate separation of the spoil from the slurry so that slurry with sediment content
within limits required for successful micro-tunnelling can be returned to the cutting face for reuse.
- Appropriately contain spoil on site prior to disposal.
- Use a type of separation process suited to the size of tunnel being constructed, the soil type being excavated, and the workspace available
at each work area for the operating plant.
- Allow composition of slurry to be monitored to maintain slurry density and viscosity limits required.
- It shall be capable of adjustments required to maintain the face stability for the particular soil conditions encountered.
- It shall monitor and continuously balance the soil and ground water pressure to prevent loss of soil or uncontrolled ground water inflow. Using
this system, pressure at the excavation face is managed by controlling the volume of spoil removed with respect to the advance rate.
- Speed of rotation of the auger flight, and the addition of water shall be monitored.
The Contractor shall identify suitable sources of fresh water for mixing drilling mud. Approvals and permits are required. Methods for operations
shall be used that will minimize ground settlement. The method shall control flow of water and prevent loss of soil into tunnel and provide stability
of face under anticipated conditions.
Power distribution systems shall be identified under the contract or permit provisions. Noise constraints shall be identified.
The Contractor shall establish and maintain construction control points, reference lines and grades for locating bore tip and detect movement of
ground surface and adjacent structures, in any of the Pipe jacking, Horizontal directional drilling, Pipe ramming or Micro-Tunnelling operations.
The control points shall be sufficiently far from work so as not to be affected by activities on site.
If settlement of ground surface occurs during boring which disturbs temporary benchmarks, the Contractor shall re-establish these.
Installation of instrumentation shall not preclude the Engineer, through an independent Contractor or consultant, from installing instrumentation
in, on, near, or adjacent to construction work. Access shall be provided to works for such independent installations.
Spoil shall be removed so as not to create a hindrance to other activities in the area.
Entry, recovery pits, slurry sump pits, or any other excavation which contain drilling fluids shall be restored and cleaned of all excess slurry left
on/in the ground after installation of casing/sleeve. Removal and final disposal of excess slurry or spoils as casing/sleeve is introduced shall be
the Contractor’s responsibility. The cost of restoring damaged pavement, kerbs, sidewalks, driveways, lawns, storm drains, landscape, and other
facilities shall be borne by the Contractor.
A12.7.7.4 Micro-tunnelling
a) General
For all installations, the Contractor shall provide detailed method statements indicating his proposed strategy.
A12.7.8 WORKMANSHIP
A12.7.8.1 Pipe jacking, directional drilling, pipe ramming and micro-tunnelling
On completion of any casing or non-casing carrier installation, the Engineer shall order pressure tests and any other testing as may be specified
in the Contract Documentation.
CONTENTS
B12.7.1 SCOPE
B12.7.2 DEFINITIONS
B12.7.3 GENERAL
B12.7.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.7.5 MATERIALS
B12.7.6 CONSTRUCTION EQUIPMENT
B12.7.7 EXECUTION OF THE WORKS
B12.7.8 WORKMANSHIP
B12.7.1 SCOPE
The provisions of Part A shall apply.
B12.7.2 DEFINITIONS
The provisions of Part A shall apply.
B12.7.3 GENERAL
The provisions of Part A shall apply.
B12.7.5 MATERIALS
The provisions of Part A shall apply.
B12.7.8 WORKMANSHIP
The provisions of Part A shall apply.
C12.7.1 Establishment on site for: (indicate type of operation: Pipe Jacking, Horizontal directional lump sum
drilling, Pipe Ramming, or Micro-tunnelling)
The unit of measurement shall be a lump sum. The tendered lump sum for above shall include full compensation for establishing all necessary
plant and equipment on site to carry out the works and for removal from site of all such plant and equipment including all temporary works such
as access roads, staging, platforms and such like on completion of the works.
Work shall be paid as a lump sum, 50 % of which shall be due when all the equipment is on site and trials (if any) are successfully completed to
the Engineer’s satisfaction. The second instalment of 25 % shall be payable after half-length is installed and the final 25% instalment after full-
length, in service, acceptable installation, and all equipment is removed from site.
The tendered lump sum shall include full compensation for all post-construction requirements as specified.
No extra payment shall be made for establishment of additional plant, should established plant not be capable of achieving desired objectives.
C12.7.2 Moving to and setting up equipment at each position for (indicate type of operation) number (No)
The unit of measurement shall be the number of positions to which equipment is moved and set up in position. The quantity measured shall be
number of set ups at positions as well as at trial positions or at positions where Engineer ordered re-setup.
The tendered rate shall include full compensation for all costs involved in moving and setting up any equipment.
C12.7.3 Installing holes (diameter, lining type indicated) to required length for (indicate type of metre (m)
operation)
The unit of measurement shall be the metre of hole installed to length required.
The tendered rate shall include full compensation for inlet and outlet structures, including dewatering sumps and operation of pumps to keep the
Works dry, supplying, installing and extracting temporary casing, installing permanent casing as well as for excavating and disposing of material
resulting from conduit formation.
D12.7.1 SCOPE
The scope of this Section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
D12.7.2 GENERAL
The Contractor shall provide detailed specifications, test data, performance data and compliance certificates from independent reputable agencies
for all proprietary systems, processes and materials proposed for use. These shall demonstrate conformance with the performance requirements
specified in the Contract Documentation.
CONTENTS
PART A: SPECIFICATIONS
A12.8.1 SCOPE
A12.8.2 DEFINITIONS
A12.8.3 GENERAL
A12.8.5 MATERIALS
A12.8.8 WORKMANSHIP
A12.8.2 DEFINITIONS
Wells - comprise preformed holes or trenches from which water is extracted by dewatering pumps to lower the water table /phreatic surface
thereby improving stability and/ or enabling excavation.
Horizontal drains - are sub horizontal drainage holes installed to intercept saturated material horizons in soil and rock slopes. Slotted collector
pipes or band drains, generally wrapped in a geosynthetic filter fabric or geotextile filter jacket to retain fine soil and rock particles, are inserted in
the drilled holes to drain collected moisture.
Vertical drains - are vertical drains comprising pre-manufactured long cylindrical formed geosynthetic filter socks that can be sand filled or have
cuspated cores wrapped in a geotextile filter jacket installed in a regular grid into soft compressible soils to provide preferred drainage paths to
accelerate consolidation settlement.
Sand drains - are vertical drains comprising columns (typically 150 mm to 250 mm in diameter) of highly permeable sand in holes formed in the
ground by either drilling or driving in a regular grid. These are used in stiff and dense soils which preclude the effective installation of band drains
Geosynthetic Drains - also referred to as Blanket drains comprises a geotextile filter fabric encapsulated/wrapped layer of drainage material
such as free draining sands or drainage stone constructed to intercept, collect or counteract moisture movements beneath structures such as
embankments and in roadbeds in cuttings.
Geocomposite drains - consist of drainage cores acting as a flow nets which are enclosed in a geotextile.
Construction Dewatering - is the removal or draining of groundwater from a riverbed, construction site or caisson by pumping or other means.
Dewatering may be implemented before subsurface excavation for foundations or shoring to lower the water table. (See Section A12.12)
A12.8.3 GENERAL
A12.8.3.1 Method Statements
Where so indicated by the Engineer the Contractor shall prepare detailed method statements for each facet of ground drainage describing key
aspects such as construction methodology, key plant, materials, personnel as well as any programme constraints of the envisaged construction
process.
Materials Approvals
A12.8.5.1a) Materials for Wells 2 weeks
A12.8.5.2a) Materials for Horizontal Drains 2 weeks
A12.8.5.3a) Materials for Vertical Drains 2 weeks
A12.8.5.4a) Materials for Geosynthetic / Blanket Drains 2 weeks
A12.8.3.3 Wells
Wells provide an effective means of drawing down water tables / phreatic surfaces in permeable to slightly permeable materials such as sandy
soils and gravels resulting in increased stability and excavatability of in situ materials with reduced risk of sidewall collapse.
Wells generally comprise drilled holes fitted with slotted pipes and filter elements from which collected water is withdrawn by pumping. Temporary
wells may be dewatered employing surface pumps while permanent systems shall have submersible pumps installed as instructed by the Engineer
Well systems may employ suction or positive displacement. For suction systems the maximum effective depth is about 6,0 m, for suction type
systems. Positive displacement systems do not have any limit as single and multiple stage pumps may be used
Installations may comprise individual single installations or multiple well points, sometimes linked to a base station/monitoring point.
The purpose of the wells shall be indicated in the Contract Documentation. Wells may be required for a fixed period such as during construction
or may be long term where ongoing phreatic level control is required for stability reasons (e.g. springs upstream of structures). Long term
installations will require a permanent source of electrical power to drive the pumps. Connection to the nearest local electricity network will be
required. Where so specified the Contractor shall obtain the necessary approvals for connection to such and have this work done by a competent
firm, to the local authority’s approval.
- Investigation data including subsurface geological information, hydrological data and geotechnical parameters
- Any test data, that may be available,
- Limitations including information on subsurface services,
A12.8.5.2 Wells
The anticipated depth of the wells shall be given in the Contract Documentation or shall be as determined on site during drilling operations.
Materials for wells shall be as specified below.
a) Drainage pipes
Unless otherwise specified the pipes shall be U-PVC conforming to SANS 966-1, Class 16, generally with a diameter of 125, 140 or 160 mm, to
match anticipated flow and pump capabilities.
The pipes shall be radially slotted with two rows of slots, at 60 degrees either side of the centreline at 5,0 mm intervals. The slot length measured
along the inner chord shall be 25 mm ± 5,0 mm and the slot width greater than 0,2 mm, less than 0,5 mm wide. Joins shall be sleeved and pop
riveted with non-corrodible rivets in addition to being glued with approved solvent cement. The distal end shall be fitted with an end cap, glued
and riveted in place.
b) Sand
The filter sand used to fill the void between the drilled hole sides and the slotted pipe shall be clean, siliceous sand from an approved source with
less than 5 % smaller than 0,425 mm and less than 5 % greater than 1,18 mm. The sand shall also comply with the requirements of SANS 1083.
c) Base station
A base station linking all well points designated as operational by the Engineer and which are fitted with permanent pumps shall be constructed
as per the Typical Drawing in the Contract Documentation. The Base station shall house the flow meter/s.
A12.8.8 WORKMANSHIP
For horizontal drains the maximum allowable deviation for any hole from the specified slope shall be 3 % of the actual length drilled with the
proviso that the minimum slope at any point in the drain shall be 1 % towards the outer end of the casing to ensure free draining is maintained.
All well points and drainage holes shall be checked for compliance with the specified positioning, hole inclinations and depths and any further
requirements that may be specified in the Contract Documentation. Any hole not meeting the specified is criteria or which does not reach the
specified depth may be rejected by the Engineer who may order that it be replaced by a correctly installed and aligned hole.
CONTENTS
B12.8.1 SCOPE
B12.8.2 DEFINITIONS
B12.8.3 GENERAL
B12.8.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.8.5 MATERIALS
B12.8.6 CONSTRUCTION EQUIPMENT
B12.8.7 EXECUTION OF THE WORKS
B12.8.8 WORKMANSHIP
B12.8.1 SCOPE
The provisions of Part A shall apply.
B12.8.2 DEFINITIONS
The provisions of Part A shall apply.
B12.8.3 GENERAL
The provisions of Part A shall apply.
B12.8.5 MATERIALS
The provisions of Part A shall apply.
B12.8.8 WORKMANSHIP
The provisions of Part A shall apply.
The tendered lump sum for ground drainage systems shall include full compensation for providing access and establishing all necessary plant
and equipment on site to carry out the works and for the removal from site of all such plant and equipment including all temporary works such as
access roads, staging, platforms and such like on completion of the works.
The unit of measurement shall be the provision of access to the drain positions as specified in the Contract Documentation.
The tendered rate shall include for all labour, plant and equipment required to provide access to the drain positions as specified.
C12.8.3 Moving to, and setting up the equipment for drilling the holes at each well /horizontal/ number (No)
sand drain position (type indicated)
The unit of measurement shall be the number of positions to which the drilling equipment has to be moved and set up in position to drill a drainage
hole. The quantity measured shall be the number of set ups at drain and/or trial drain positions or at positions where the Engineer has ordered
re-drilling of the holes.
The tendered rate shall include full compensation for all costs involved in moving and setting up any equipment.
C12.8.4 Moving to, and setting up the equipment for installing vertical drains at each drain number (No)
position (size and type of drain indicated)
The unit of measurement shall be the number of positions to which the installation rig, mandrel and other equipment required to install the specified
vertical drains is moved and set to install a vertical drainage hole. The quantity measured shall be the number of set ups at drain positions as
well as at trial drain positions or at positions where the Engineer has ordered re-installation of the drains.
The tendered rate shall include full compensation for all costs involved in moving and setting up any equipment.
C12.8.5 Drill holes for wells (diameter indicated) to the required depth metre (m)
The unit of measurement shall be the metre of hole drilled to the depth required.
The tendered rate for the drilling of holes for wells shall include full compensation for drilling as well as supplying, installing and extracting temporary
casing as well as for disposing of surplus material resulting from hole formation. Payment will only be made for holes where successful installations
have been accomplished.
C12.8.6 Drill holes for horizontal drains (inclination and diameter indicated) to the required depth metre (m)
The unit of measurement shall be the metre of hole drilled to the depth and inclination required.
The tendered rate for the drilling of holes shall include full compensation for supplying, installing and extracting the driven temporary casing as
well as for disposing of surplus material resulting from the hole having been formed. Payment will only be made for holes where successful
installations have been accomplished.
C12.8.7 Drill holes for vertical sand drains (diameter indicated) to the required depth metre (m)
The unit of measurement shall be the metre of hole drilled to the depth and inclination required.
The tendered rate for the drilling of holes shall include full compensation for supplying, installing and extracting the driven temporary casing as
well as for disposing of surplus material resulting from the hole having been formed.
C12.8.8 Pre- drilling of holes for vertical drains (diameter indicated) to the required depth metre (m)
The unit of measurement shall be the metre of hole drilled to the depth required.
The tendered rate for the pre-drilling of holes for vertical drains shall include full compensation for boring, supplying, installing and extracting the
temporary casing as well as for disposing of surplus material resulting from the hole formation. Payment will only be made for holes where
successful installations have been accomplished.
C12.8.9 Installation of slotted drainage pipes for wells (size indicated) metre (m)
The unit of measurement shall be the metre of slotted drainage pipes for well points installed as specified.
C12.8.10 Installation of slotted drainage pipes for horizontal drains (size indicated). metre (m)
The unit of measurement shall be the metre of slotted drainage pipes for horizontal drains installed as specified.
The tendered rate for installing slotted drainage pipes for horizontal drains shall include full compensation for the supply and installation of the
pipes as specified complete with synthetic filter fibre geosynthetic sock as specified including all labour and overhead costs. Payment will only be
made for successful installations where all the requirements have been met.
The unit of measurement shall be the metre of vertical drain installed as specified.
The tendered rate for installing vertical drains shall include full compensation for the supply and installation of the vertical drains as specified
utilising appropriate installation equipment, mandrels, etc including all labour, plant, equipment and overhead costs.
The tendered rate shall also include the costs of centering and filling the synthetic filter fibre geofabric socks with approved free draining sand
during installation where sand filled drains are specified. Payment will only be made for successful installations where all the requirements have
been met.
C12.8.12 Filter sand for wells (type/ size indicated) kilogram (kg)
The unit of measurement shall be the mass of approved filter sand utilised in the construction of the wells.
The tendered rate shall for the filter sand shall include full compensation for the supply of the specified filter sand on site. Payment will only be
made for the theoretical amount of sand utilised in filling the annulus between the drainage pipe and the surrounding soil which shall be taken as
the outside diameter of the temporary casing).
C12.8.13 River sand for vertical drains (source indicated) cubic metre (m3)
The unit of measurement shall be the volume of approved river sand utilised in the construction of the vertical drains.
The tendered rate for river sand shall include full compensation for the supply of the specified river sand on site from identified sources. Payment
shall only be made for the theoretical amount of sand utilised in filling the annulus between the drainage pipe and the surrounding soil which shall
be taken as the outside diameter of the temporary casing.
C12.8.14 Provision and installation of submersible borehole pumps in designated wells provisional sum
Pumping tests on installed wells as well as the number of wells where the yield warrants pump installation will determine the size/capacity of the
submersible borehole pumps to be installed.
The provisional sum is for the construction of a base station as per the typical drawing, sized to accommodate flow metres for each installed
borehole pump and as a distribution point for the electrical supply to each installed borehole pump. The costs of linking the pumps to the base
station shall also be covered by this provisional sum.
D12.8.1 SCOPE
The scope of this section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
D12.8.2 GENERAL
The Contractor shall provide detailed specifications, test data, performance data and compliance certificates from independent reputable agencies
for all proprietary systems, processes and materials proposed for use. These shall demonstrate conformance with the performance requirements
specified in the Contract Documentation.
CONTENTS
PART A: SPECIFICATIONS
A12.9.1 SCOPE
A12.9.2 DEFINITIONS
A12.9.3 GENERAL
A12.9.5 MATERIALS
A12.9.8 WORKMANSHIP
Where the foregoing geotechnical methods are specified as elements for the construction of the mitigation installations described hereunder the
specifications, measurement and payments Clauses for the relevant said geotechnical methods as described in Sections A12.2 (Ground Anchors),
A12.5 (Shotcrete), A12.6 (Mechanically Stabilised Earth) and A12.7 (Trenchless Methods) respectively, shall apply. In the event of a conflict
between the requirements of Section A12.9 and the specifications of the relevant aforementioned geotechnical methods referred to above, the
requirements of this Chapter shall take precedence.
A12.9.2 DEFINITIONS
The following definitions, terms, works or expressions shall be defined as assigned hereunder. It is to be noted that these are not exhaustive and
merely represent a selected few used in the field of mitigation measures specified. Accordingly, these do not in any way limit the scope of the
mitigation required or the required outcomes and objectives set out in these specifications.
Rockfall - occurs when a limited discrete number of rock blocks or wedges become detached at height and either free fall, bounce and/or translate
over ground with some speed and momentum.
Active Rockfall Mitigation Measures - are those where the rockfall hazard is either removed by excavation and disposal or stabilised to prevent
falls of ground. These would typically consist of either one or a combination of; barring down of loose rock; anchoring of individual loose blocks
or kinematically unstable wedges of rock; stabilisation of a relatively thin unstable surficial layer of rock by way of anchored rockfall netting or a
A12.9.3 GENERAL
A12.9.3.1 Objectives and requirements
Only specialised mitigation products, produced by reputable specialist manufacturers, with a proven and acceptable track record in the field of
design, manufacture and supply of these products, will be eligible for consideration as service providers for slope protection measures. Prototypes
of these products shall have been tested and certified by independent reputable agencies in accordance with the specified standard, as being
able to perform to the specifications and performance parameters claimed.
The installation of rockfall mitigation shall only be undertaken by suitably experienced and equipped specialist geotechnical Contractors with a
proven track record of having successfully undertaken anchoring of slopes and cuttings which shall include slope protection measures.
The works shall be managed and controlled on an on-going daily basis by a works manager with a proven track record. In the event that the
Contractor does not have the necessary experience he shall sub-contract this work to a suitably qualified, experienced and appropriately equipped
sub-Contractor with the required proven track record as specified above. The appointment of a suitable sub-Contractor shall be subject to the
approval of the Engineer.
Due allowance shall be made for obtaining materials, resubmissions and re-designs, all to the required/approved standards, methods and practices
in attending to these requirements. Particular attention shall be paid to the early submission of materials-, concrete- and grout mix designs where
parameters at various ages may be specified. No consideration for extension of the contract period will be entertained for delays incurred in
meeting these requirements.
The Contractor’s attention is drawn to the approvals required as indicated in Table A12.9.3-1 below regarding works carried out under this section
of the works:
Method statements
4 weeks prior to start of works on any
A12.9.7.1 Method statements for installation of various components
section
2 weeks prior to start of works on any
A12.9.7.1 Amended Method Statement
section
On site facilities for receiving, storing, assembling, inspection
A12.9.7.1 Prior to delivery, Verification on delivery
and verification of specialised materials and anchors
Materials
A12.9.7.1 Inspection, verification and approval of specialised materials 1 week before programmed installation
Process
A12.9.7.1 Traffic accommodation in place, works cordoned off 24hrs prior to inspections, setting out of the
works and/or testing
Proforma on the detail, format and frequency of the records that
A12.9.3.5 2 weeks prior to commencement of works
the Contractor shall submit to the Engineer.
A12.9.7.1
Barring down, making safe of work areas 1 day before initial setting out
Two weeks before programmed
A12.9.7.2 Initial setting out of the works, approval of adjustments
installation date
Inspection of Anchor assemblages, drilling of holes, anchor and Prior to insertion and grouting of anchors,
A12.9.7.2
post excavations, steel reinforcement pouring of concrete
A12.9.3.5 Records
The Contractor and the Engineer shall agree, at least two weeks prior to the commencement of any installation, on the detail, format and frequency
of the records that the Contractor shall submit to the Engineer. Work will not be allowed to commence prior to the requisite agreement on record
keeping being in place. Should the Contractor fail to produce the requisite agreed records timeously or to the required detail, the Engineer may
instruct that all work on the relevant section of the works be suspended until all the outstanding records have been submitted to the required level
and detail.
Alternative designs shall also include the design the barricades to intercept and safely attenuate the kinetic energy and the runout of falling rock
within the designated area(s) and constraints specified. These designs shall be undertaken by a suitably qualified and experienced specialist with
proven documented relevant experience in the design and construction of the required mitigation measures accepted by the Engineer. All designs
given shall be subject to the vetting and approval of the Engineer. All systems shall be assessed for compliance with the guidelines in ETAG 027.
Available information is presented in the Contract Documentation. It is the Contractor’s responsibility to obtain all the other information required
to enable him to meet his obligations in term of the Contract Documentation. The requirements given in Clause A12.9.3 shall be met and.
Notwithstanding the foregoing the Contractor shall in all instances undertake the design of all temporary measures required to protect the road
furniture, infrastructure and components of the work under construction or already complete, from the impacts of falling rock.
A12.9.5 MATERIALS
A12.9.5.1 Finalising the design and ordering of materials
The proprietary designed, developed and tested materials used in the slope protection works may need to be imported and/or are subject to
considerable lead time for manufacture and delivery. The Contractor shall take this into account in the planning and scheduling of the construction
of the works.
The Contractor shall furthermore undertake all the necessary site survey, setting out and measurements required to finalise the design and
dimensioning of the various elements of the installations timeously at the onset of construction so that the requisite orders for the manufacture
and/or delivery can be placed as soon as possible.
A12.9.7.2 Process
a) Rock Barring
This part of the specification covers the operations involved in the barring down and cleaning of loose rock from the faces of the various cuttings
and removing the material so produced to an approved disposal site. It also covers the inspections to be carried out prior to and after the
completion of barring down operations.
The Contractor shall make available equipment as required and approved by the Engineer together with a qualified operator to bring the Engineer’s
representative to within at least half a metre of any part of the surface of the cut face or slope requiring assessment. The Engineer’s representative
will undertake a detailed inspection of the rock surface before the barring down operations commence to determine to extent of barring required
and if necessary subsequent intermittent inspections to instruct the Contractor accordingly. All costs and delay incurred in providing this access
must be allowed for in the rates and programme for barring.
The Contractor shall have on site all the necessary equipment, plant materials and personnel required to gain access to and dislodge all rock
identified for barring down and to do so in compliance with all statutory and other requirements pertaining to matters regarding safety of personnel
and the general public.
All barring down shall be undertaken judiciously, in a controlled manner, and strictly as directed by the Engineer’s representative. It may therefore
be that in certain instances key blocks which are potentially unstable be instructed to be left in place and anchored back, or in the event of very
loose of friable ground, that no further removal takes place and that the ground instead be stabilised by a suitable revetment and/or bolts as part
of the mitigation works.
The Contractor will be required to traverse every square metre of the rock surface requiring stabilisation/treatment and attempt to bar down all
hollow sounding rock surfaces identified by tapping with a pinch bar or other approved method. The Contractor will continue with the barring down
to the satisfaction of the Engineer and he may be required to re-attempt to bar down sections of rock or specific rocks previously attempted as
may be required by the Engineer.
All loose material resulting from the barring down and cleaning operations shall be loaded and transported to the approved disposal site.
Once the mitigation measures are installed, the slopes in question shall be cleared of all loose fist size rock and greater by further scaling where
so required and then finally blowing it clean with the requisite number of passes of a high pressure jet of compressed air together with a high
pressure jet of water, if required.
Cleaning shall be undertaken from the top down to ensure that all loose rock and debris is systematically removed from the rock surfaces and
ledges and is not re-deposited on an adjacent section of rock surface previously cleaned. The Contractor shall remove any rock or debris so re-
deposited at no extra cost and all rock surfaces shall be cleaned to the satisfaction of the Engineer.
A final inspection and sign off by the Engineer’s Representative is required once the barring and cleaning is complete to confirm that the work has
been undertaken to the Engineers’ satisfaction and required standard.
b) Anchoring of slope protection installations
The anchoring required for the various slope protection installations shall be of the type, detail and at the locations provided in the relevant design
layout drawings and Contract Documentation or as might be modified and instructed by the Engineer for the wire mesh rockfall revetments, or in
accordance with the guidelines and requirements of the product and installation manuals in the case of catch fences, shallow landslide barriers
and debris flow barriers.
The Contractor shall initially set-out the design layout of the mitigation works which mainly entails the layout of the anchors of all the installations
as per the approved construction drawings, making use of approved survey methods specified and/or instructed by the Engineer. This setting out
will be inspected by the Engineer to confirm that the intended layout is to his satisfaction. The Engineer may require adjustments to the position
of certain elements of the installation or may decide that the alignment and location requires adjustment to better accommodate the topographical
or other physical constraints. The Contractor shall assist and co-operate with the Engineer in all respects in finalising the setting out and must
allow for this in his rates and construction programme.
Drilling and grouting of the anchors shall be undertaken in accordance with the requirements as specified for rock dowels in Section A12.2, to the
type, diameter, orientation and depth specified.
Holes shall be accurately set out and collared to within 75 mm of the required position for the wire mesh panel installations, and the upslope
support cables of the posts of catch fences, shallow landslide fences and debris flow fences, and the lateral anchors of the catch fences and
shallow landslide fences.
Accurate and relevant drilling templates, agreed to and approved by the Engineer, will be required for drilling the anchors of all post baseplates
as well as the anchors of the lateral support ropes of the debris flow fences. Collaring the holes is strictly dictated by the specific anchorage
arrangement(s) and no deviation from the template will be allowed. Holes that are found to have been collared and/or drilled deviant from the
template will be grouted and re-drilled once the grout reaches a minimum strength of 10MPa.
The Contractor shall control the drilling operations by the use of proper equipment and techniques to ensure that no holes deviate more than 2 %,
once collared, from the required orientation.
A12.9.8 WORKMANSHIP
A12.9.8.1 Acceptance of installations with proprietary supplied and designed products
All installations shall be finally inspected and signed off by a duly authorised representative of the approved specialist manufacturer of the
system(s) to verify that these have been installed in accordance with the requisite guidelines and standard(s) and will meet the performance
specifications of the system. Final payment for the installation(s) and the contract completion certificate shall not be issued if the completed
installation(s) have not been signed off as required in these specifications.
A12.9.8.2 Anchors
The quality control of the grouting of all anchors and load testing of the rock dowels and wire rope anchors shall be as per Section A12.2. All the
anchors supporting the top longitudinal wire rope cables of the drape mesh revetments and all wire rope anchors installed, for either catch fences,
shallow landslide fences or debris flow fences, shall be tested.
Where applicable, testing shall be undertaken prior to their possible encasement in concrete plinths.
The testing sequence and load limits shall be as for rock dowels/soil nails but using a specially adapted jack to accommodate the loop of the wire
rope anchor.
All tests shall be undertaken with the superintendence of the Engineer and the Contractor shall ensure that he adheres to the requisite hold points
specified in Table A12.9.3-1
The frequency of testing and applicable standards shall be as for Section A12.2.
CONTENTS
B12.9.1 SCOPE
B12.9.2 DEFINITIONS
B12.9.3 GENERAL
B12.9.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.9.5 MATERIALS
B12.9.6 CONSTRUCTION EQUIPMENT
B12.9.7 EXECUTION OF THE WORKS
B12.9.8 WORKMANSHIP
B12.9.1 SCOPE
The provisions of Part A shall apply.
B12.9.2 DEFINITIONS
The provisions of Part A shall apply.
B12.9.3 GENERAL
The provisions of Part A shall apply.
B12.9.5 MATERIALS
The provisions of Part A shall apply.
B12.9.8 WORKMANSHIP
The provisions of Part A shall apply.
C12.9.1 Barring down of rock surfaces within vertical height intervals (intervals stated) square metre (m2)
The unit of measurement shall be the square metre of rock barred down in accordance with the Engineer’s instruction. Heights shall be measured
from the outer edge of the road at the toe of the cutting. Barring down will be measured once only per area/section of the works instructed to be
treated irrespective of the number of times the Contractor is required to re-access the face of the cutting/slope to complete the work to achieve a
stable clean surface approved by the Engineer. The final measurement for payment will be made on the nett area of slope/cutting barred down.
The tendered rate shall include full compensation for access to the rock face, barring down of rock using suitable tools and equipment, adhering
to safety and other statutory precautionary measures, labour, plant (including specialised equipment), materials and all other necessary incidentals
to complete the works in accordance with the specifications and the Engineer’s instructions.
C12.9.2 Cleaning of rock surfaces by high pressure air and water jetting equipment within the square metre (m2)
vertical height intervals (categories stated)
The unit of measurement shall be the square metre of rock surface cleaned by high-pressure air and water jetting in accordance with the Engineer’s
instruction. Cleaning will be measured once only per area/section of the works instructed to be treated irrespective of the number of times the
Contractor is required to re-access the face of the cutting/slope to complete the work to achieve a stable clean surface approved by the
Engineer.The final measurement for payment will be made on the nett area of slope/cutting cleaned down.
The tendered rate shall include full compensation for access to the rock face, adhering to safety and other statutory precautionary measures,
labour, plant (including specialised equipment), materials and all other incidentals necessary to complete the works in accordance with the
specifications and Engineer’s instructions.
Heights shall be measured from the outer edge of the road at the toe of the cutting.
C12.9.4 Supply and install wire mesh rockfall netting within vertical height intervals (intervals square metre (m2)
stated), galvanic requirements, roll width, wire thickness, tensile strength, weave, aperture,
PVC coating and/or colouring indicated
The unit of measurement shall be the square metre of mesh wire mesh rockfall netting placed, secured and anchored in accordance with the
design layout drawings and the specifications of the approved specialist manufacturer of the system(s). The final measurement for payment will
be made on the nett area of mesh installed. The requisite overlaps and joints required to ensure full effective coverage of the slope/cutting shall
not be measured.
The tendered rate shall include full compensation for the procuring mesh, joining mesh rolls to create continuous netting and placing mesh on the
slopes and cutting, inclusive of all labour, materials, catch fence components including all clips, clamps and shackles and all other incidentals at
the locations required in accordance with the Engineer's instructions including the requisite process control testing, testing and sign off certificate
by the authorised representative of the approved specialist manufacturer of the system(s) if relevant. The tendered rate shall include full
compensation to the Contractor to assist and co-operate with the Engineer in all respects in finalising the setting out of the design layout, including
the individual elements of the installation.
Measurement and payment for all the anchoring of rock anchors, dowels and wire rope anchors shall made in Section A12.2.
C12.9.5 Supply and Installation/erection of catch fencing (galvanic requirements, type, height, metre (m)
length and energy rating in kJ and location of fences indicated)
The unit of measurement shall be the linear metre of catch fence supplied and erected in accordance with the design layout drawings and the
specifications of the approved specialist manufacturer of the system(s). Separate rates are required for each standard length class intervals,
namely, 0-10 m; >10 m – 20 m; >20 m- 30 m; >30 m – 40 m; >40 m – 50 m; >50 m – 60 m. The rates for each class length shall distinguish
between fence height and energy rating.
The tendered rate shall include full compensation for the procuring and erecting of the catch fence system, inclusive of all labour, materials, catch
fence components including all anchors, clips, clamps and shackles and all other incidentals at the locations required in accordance with the
Engineer's instructions including the requisite process control testing, testing and sign off certificate by the authorized representative of the
approved specialist manufacturer of the system(s).The tendered rate shall include full compensation to the Contractor to assist and co-operate
with the Engineer in all respects in finalising the setting out of the design layout, including the individual elements of the installation. The rate shall
make provision for a standard anchor length of 3,0 m for all threadbar and wire rope anchors.
C12.9.6 Supply and installation/erection of additional anchor lengths for catch fences metre (m)
(differentiate between threadbar and wire rope anchor for different diameters)
The unit of measurement shall be the linear metre of anchor length in addition to the standard 3m length of relevant anchor allowed for and priced
in item C12.9.5. The need for the additional anchor length shall be as required by the design to match the ground conditions and as instructed
and approved by the Engineer. In the event that the diameter and/or type of anchor provided for in the measurement item above does not match
that used for the fence offered by the Contractor, he shall indicate the requisite diameter and/or type of anchor(s).
The tendered rate shall be inclusive of all the additional compensation for the additional drilling, cleaning drill holes, procuring, corrosion protection,
installing and grouting, all labour, materials and all other incidentals required to complete the work in accordance with the Contract Documentation
and the Engineer’s instructions. All pull out test requirements and costs are deemed to be included in the tendered rate for this item and no extra
payment will be made in this regard.
C12.9.7 Gap filling under the catch fences (energy class stated) square metre (m2)
The unit of measurement shall be the square metre of fencing installed for gap filling as instructed by the Engineer.
The tendered rate must shall be inclusive of all the additional costs that will be incurred in the erection of the gap closures below the catch fences,
including anchors/pins required in accordance with the approved specialist manufacturer’s and the Engineer’s requirements.
C12.9.8 Supply and installation/erection of shallow landslide fencing (galvanic requirements, metre (m)
type, height, length and rating and fence length class interval
The unit of measurement shall be per linear metre of shallow landslide fencing supplied and erected in accordance with the design layout drawings
and the approved specialist manufacturer’s specifications. Separate rates are required for each standard class length intervals, namely, 0-10
m;>10 m – 20 m;>20 m- 30 m;>30 m – 40 m;>40 m – 50 m;>50 m – 60 m. The rates for each class length shall distinguish between fence height
and rating.
The tendered rate shall include full compensation for the procuring and erecting of the shallow landslide fence system, inclusive of all labour,
materials, catch fence components including all anchors, clips, clamps and shackles and all other incidentals at the locations required in
accordance with the Engineer's instructions including the requisite process control testing, testing and sign off certificate by the authorised
representative of the approved specialist manufacturer of the system(s). The tendered rate shall include full compensation to the Contractor to
assist and co-operate with the Engineer in all respects in finalising the setting out of the design layout, including the individual elements of the
installation. The rate shall make provision for a standard anchor length of 3,0 m for all threadbar and wire rope anchors.
C12.9.9 Supply and install additional anchor lengths for shallow landslide fences (differentiate metre (m)
between threadbar and wire rope anchor for different diameters
The unit of measurement shall be the linear metre of anchor length in addition to the standard 3,0 m length of relevant anchor allowed for and
priced in item C12.9.8. The need for the additional anchor length shall be as required by the design to match the ground conditions and as
instructed and approved by the Engineer. In the event that the diameter and/or type of anchor provided for in the measurement item above does
not match that used for the fence offered by the Tenderer, the Tender shall indicate the requisite diameter and/or type of anchor(s).
The tendered rate shall be inclusive of all the additional compensation for the additional drilling, cleaning drill holes, procuring, corrosion protection,
installing and grouting, all labour, materials and all other incidentals required to complete the work in accordance with the Contract Documentation
and the Engineer’s instructions. All pull out test requirements and costs are deemed to be included in the tendered rate for this item and no extra
payment will be made in this regard.
C12.9.10 Gap filling under the shallow landslide fences (fence rating indicated) square metre (m2)
The unit of measurement shall be the square metre of fencing installed for gap filling as instructed by the Engineer.
The tendered rate shall allow for all the additional costs that will be incurred in the erection of the gap closures below the shallow landslide fences,
including all anchors/pins required in accordance with the approved specialist manufacturer and the Engineer’s requirements.
C12.9.11 Supply and installation/erection of debris flow fencing (galvanic requirements, type, metre (m)
rating and location for each numbered fence indicated)
The unit of measurement shall be the running length in metres for each specific fence, measured for supply and delivery to site as required in
accordance with the design layout drawings and the approved specialist manufacturer’s specifications.
The tendered rate shall include full compensation for procuring, corrosion protection, all labour, materials, components including all anchors, clips,
clamps and shackles and all other incidentals required to provide the relevant Debris Flow Fence components at the locations requiredincluding
the requisite process control testing, testing and sign off certificate by the authorized representative of the approved specialist manufacturers of
the system(s). The tendered rate shall include full compensation to the Contractor to assist and co-operate with the Engineer in all respects in
finalising the setting out of the design layout, including the individual elements of the installation. The rate shall make provision for a standard
anchor length of 3,0 m for all threadbar and wire rope anchors.
C12.9.12 Supply and install additional anchor lengths for debris flow fences (differentiate metre (m)
between threadbar and wire rope anchor for different diameters)
The unit of measurement shall be the linear metre of anchor length in addition to the standard 3,0 m length of relevant anchor allowed for and
priced in item C12.9.11. The need for the additional anchor length shall be as required by the design to match the ground conditions and as
instructed and approved by the Engineer. In the event that the diameter and/or type of anchor provided for in the measurement item above does
not match that used for the fence offered by the Tenderer, the tender shall indicate the requisite diameter and/or type of anchor(s).
The tendered rate shall be inclusive of all the additional compensation for the additional drilling, cleaning drill holes, procuring, corrosion protection,
installing and grouting, all labour, materials and all other incidentals required to complete the work in accordance with the Contract Documentation
and the Engineer’s instructions. All pull out test requirements and costs are deemed to be included in the tendered rate for this item and no extra
payment will be made in this regard.
D12.9.1 SCOPE
The scope of this Section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for the following:
- Materials and Materials Design as per Clause A12.1.3.2
- Materials as per Clause A12.1 5
- Construction Equipment as per Clause A12.1.6
- Execution of the Works as per A12.1.7
D12.9.2 GENERAL
The Contractor shall provide detailed specifications, test data, performance data and compliance certificates from independent reputable agencies
for all proprietary systems, processes and materials proposed for use. These shall demonstrate conformance with the performance requirements
specified in the Contract Documentation. Unless otherwise specified, all proprietary materials shall be used and placed in strict accordance with
the relevant manufacturer's current published instructions.
CONTENTS
PART A: SPECIFICATIONS
A12.10.1 SCOPE
A12.10.2 DEFINITIONS
A12.10.3 GENERAL
A12.10.5 MATERIALS
A12.10.8 WORKMANSHIP
A12.10.2 DEFINITIONS
The following definitions, terms, works and expressions are applicable to this section. These are not exhaustive and merely represent a selection
used in the field of controlled rock blasting. Accordingly, these do not limit the scope of the blasting that may be required to meet the outcomes
and objectives set out in the Contract Documentation.
Controlled blasting - includes the use of special techniques, measures, procedures and for using explosives and ancillary materials specially
manufactured for this purpose in order to ensure that the required objectives are met without damage to person, property or the works.
Specified excavation or payment line - means the excavation profile given on the drawings or determined by the Engineer for the works, within
which no unexcavated or loose material shall occur after the excavation is complete except as allowed within the specified tolerances. It is also
the line to which payment for excavation will be measured and made. No additional payment will be made for any material excavated or removed
beyond this line unless the Contractor can demonstrate that the over excavation was not attributable to negligence or poor workmanship on his
part and was due to adverse ground conditions.
Pre-splitting - entails blasting utilising closely spaced, parallel drilled holes of appropriate diameter along the intended final excavation surface.
These holes may either be vertical or drilled at the inclination specified to establish the specified line in the Contract Documentation and/or shown
on the construction drawings. Pre-split holes are charged with a reduced amount of explosive than those for bulk blasting which is decoupled
from the wall of the blast hole and may include spacing the explosive charges along the length of the hole if required, i.e. deck charging. These
holes are detonated simultaneously, prior to the main bulk blast, to create a single, clean, continuous fracture plane in the rock along the line of
drilled holes, thereby creating the final permanent excavation surface with negligible or very limited damage.
Smooth blasting - entails drilling a line of closely spaced parallel holes along the intended final excavation surface, with a suitable burden/spacing
ratio and loading all the holes lightly with an appropriate amount of explosive, including decked charging if required. These charged holes are
detonated, as part of the main blast, but as the last row to be fired, thereby creating the final permanent excavation surface with negligible or very
limited damage.
Line Drilling - is a method of overbreak control which uses a series of closely spaced holes that are not charged to create a final excavated
surface with negligible damage.
Delay blasting - is the use of delay detonators or connectors to separate and delay the detonation of explosive charges in a single blast according
to a defined time sequence. This limits the amount of explosive detonated instantaneously and thereby limits the level of blast vibrations generated.
Detonation pressure - is the pressure created in the reaction zone of the detonating explosive.
Drill cuttings - are the fine chippings of rock material which are produced in percussion drilling of the blast holes and blown out as the hole
advances.
Explosives - are chemicals and chemical mixtures which, when properly initiated, are rapidly converted into gases at high temperature and
pressure as the detonation wave propagates through the explosive column. Unconfined, a litre of explosive will expand to around 1 000 litres in
milliseconds. Together with the shock wave of detonation, this results in extremely high breaking stresses in rock.
Free face - is any unconfined rock surface exposed to air – either natural or created by blasting, located some distance from the blast hole, which
reflects the compressional blast induced shock wave, turning it into a reflected tensional wave front which results in breakage and fragmentation
of the rock mass.
Flyrock - comprises rock fragments propelled through the air by the force of the explosion from a blast.
Fragmentation - is a measure to describe the particle (fragment) size distribution of the rock mass broken (fragmented) by the blast. It is normally
a measure of the extent to which the rock is broken into small pieces by a primary/bulk blast.
Ground vibration - is the ground movement caused by the stress waves emanating from a blast.
Half barrel - is the rounded intact rock surface of the blast hole formed by the drilling process which remains sculpted behind on the blast-created
rock surface.
Initiation - is the act of detonating explosives by appropriate means.
Maximum Instantaneous Charge - is the mass of explosive detonated simultaneously, within a single delay interval, as part of a blast.
Overbreak - is the amount of rock broken and removed by blasting, and/or subsequent scaling, beyond the specified excavation limit/payment
line.
Peak Particle velocity (PPV) - is the maximum speed of movement in a given direction of a rock or soil mass recorded as mm/s.
Secondary blasting - is blasting undertaken to further breakdown excessively large rocks produced by a blast or re-blasting a portion of the rock
mass which did not breakout as required and which remained behind.
Spacing of blast holes - is the centre to centre distance between adjacent drill holes in the same row.
Stemming - is the portion of the blast hole packed with inert material above the charge so as to confine and retain gasses generated by the
explosion during detonation, thus improving the fragmentation process. Inert material used in the stemmed section of the blast hole is also referred
to as stemming.
Toes - occur at the lower part of the blast near the base of the blast holes and represent a mass of rock that is not broken out by blast. Toes may
be caused by misfires, cut-offs or an excessive toe burden. Toes generally require secondary blasting for removal.
Due allowance shall be made for obtaining such information, resubmissions and re-designs, all to the required/approved standards, methods and
practices in attending to these requirements. No consideration for extension of the contract period will be entertained for delays incurred in
meeting these requirements.
Table A12.10.3-1: Approval requirements
A12.10.7.3 b) - Mark-up and setting of blast holes One day before drilling.
A12.10.7.3 b) - Perimeter Blast hole orientation survey One day prior to charging.
A12.10.7.3 c) - Depth, spacing and approval of drilled holes ready for charging One day prior to charging.
A12.10.7.2 c) Engineer approval that equipment for vibration and over No charging up or blasting pending
pressure monitoring equipment is in place and in working order approval.
Prior to continuing with drilling and
A12.10.7.3 f) Post blast Inspection and approval by the Engineer blasting
Prior to drilling and blasting for next
Assessment of preparatory works rock support bench
Disputes/variations
A12.10.8.1 Engineer/Contractor disagreement on an outcome of any blast Works stopped pending receipt of
independent specialist’ report
A12.10.7.3 f) Submission of a revised blast pattern when variation in ground Engineer’s approval required before
conditions is encountered further drilling and blasting
A12.10.7.3g) Contractor to submit Required Records timeously Drilling and Blasting shall only
commence receipt of the required
records
The Contractor shall comply with the above requirements and shall furthermore give the Engineer at least 24hrs written notification in respect of
requests for required inspection(s).
A12.10.5 MATERIALS
A12.10.5.1 Explosives
All explosives proposed to be used by the Contractor are subject to acceptance by the Engineer. The explosives shall be of such quality and
power and shall be used in such locations as will achieve the desired result. The firing systems of blasts shall be controlled using reliable approved
delay detonators with the requisite degree of accuracy as per submitted design.
The Contractor shall submit comprehensive product data, specification and performance sheets produced and certified by the manufacturer and
relevant testing authority as might apply.
a) Controlled perimeter blasting
Only cartridge explosives, prepared specifically for pre-splitting and smooth blasting, packaged by explosive manufacturing firms and accepted
by the Engineer, will be permitted for use in controlled perimeter blasting. Appropriately spaced charges will be used in the case of presplitting.
No bulk explosives (such as ANFO) or pumped emulsions shall be used in pre-split, smooth and buffer blast holes.
Maximum diameter of explosives used in pre-split holes shall be less than half the diameter of the pre-split hole unless otherwise approved by the
Engineer.
Use of detonating cord may be used in certain applications for pre-splitting and smooth blasting if proven to be successful during trial blasts and
provided there are no environmental constraints on its use.
b) Controlled bulk blasting
Only standard cartridge explosives prepared and packaged by explosive manufacturing firms and accepted by the Engineer shall be permitted for
use in controlled bulk blasting.
No bulk explosives such as ANFO or pumped emulsions shall be used in controlled bulk blast holes.
A12.10.5.3 Stemming
Stemming may only be used with the explicit written approval of the Engineer and the materials used shall be subject to the approval of the
Engineer. As a guideline, when in soft to hard rock, stemming shall consist of drill cuttings sourced from the drilling operation. In hard to extremely
Steel pipelines 50
Private property 10
Note: The onset of damage is a function of the frequency of the vibrations, namely the lower the frequency the lower the limit will be for the onset
of damage. The higher frequencies from the blast are first to be attenuated as the vibrations propagate from the source of the blast and are
therefore the lowest frequencies that propagate the furthest. The onset of damage is also dependant on the resonant frequency of the
structures/infrastructure under consideration. The limits presented in Table A12.10.8-2 are typically for the higher frequency limits, greater than
50 Hz. No more than 5 % of the results shall exceed these limits. The final thresholds for the various elements of the contract will be established
from the trial blasts.
No measurements at any residential or sensitive structures should exceed this limit. 134
Less than 10% of blasts shall be allowed to produce an air blast pressure of more than 128dB at the closest identified sensitive location, and no
blast shall generate air blast pressures greater than 134dB.
At the onset of the blasting trials, estimates of air blast at any distance D in metres for the weight E in kg of explosive detonated instantaneously
may be made from Equation 2, namely:
D b
PPV = a−b log ( ) ………………………..(2)
√E
Where a and b are site specific constants. Log is log to base 10.
The initial values of a = 165 ±2 0 for confined blasts and a = 195 for unconfined blasts. The decay factor b ≈24. These values of a and b are
common practice in South Africa shall be used for initial trials until such time as the site-specific constants are established.
The Contractor shall monitor blast induced ground vibration and air blast levels for each blast. The Contractor shall have sufficient measuring
equipment (triaxial seismographs) permanently deployed on site, at the requisite strategic locations, for the duration of drilling and blasting
operations to record ground vibrations, air blast and fly rock for all blasts. The equipment shall be correctly set up to capture the full event without
exceeding respective sensitivity ranges. The Contractor shall confirm in writing that the equipment is fully operational and appropriately set up
24hrs before commencing to charge any blast and then again immediately prior to detonating the charge.
(iii) Fly Rock
The Contractor is required to establish a fly rock risk zone defining the area where fly rock may extend to. This zone shall be cleared
before each blast. As fly rock is conservatively considered to be a function of mean predicted blast fragment size and drill hole
diameter, fly rock risk zones need to be established for the various blast configurations from the trial blast. Mean predicted blast
fragment size is typically determined by way of the KuzrRam model of Cunningham as part of the blast design, see reference 1.
At the onset of blasting trials, minimum estimates of throw distance L which must be cleared, shall obtained from estimated the graphs
for throw distance L in metres for various mean fragment sizes and blast hole diameters presented in Fig 1 below.
Should the Contractor fail to submit this information as required, the Engineer may instruct that no further drilling or blasting be undertaken until
such time as the required information has been received. Any ensuing delay or disruption to the Contractor’s programme will be for his own
account.
The supply of any information to the Engineer in respect of controlled blasting techniques does not relieve the Contractor of his responsibilities
under the Contract.
h) Use of non-detonating explosives
Blasting shall not be carried out within 10 m of any works, infrastructure or structure, unless otherwise agreed to in writing by the Engineer.
Furthermore, whenever, in the opinion of the Engineer, there is careless or inappropriate use of explosives or where the Engineer considers that
further blasting might damage the rock, use of detonating explosives shall be discontinued. In the event of the foregoing the excavation shall be
undertaken/completed by either one of the following, namely, propellants, swelling agents, hydraulic wedging or mechanical breakers. In these
circumstances, and unless the said conditions and quality of the rock could not have been foreseen, the Contractor shall not be entitled to any
additional compensation or extension of time and he shall be reimbursed at the rates tendered for the work as though it had been undertaken by
means of detonating explosives.
i) Restrictions
In addition to the normal statutory restrictions and regulations, blasting shall not be permitted:
- When there is low dense cloud cover of more than 50 %
- When the wind velocity is greater than 10 km/h towards the area of concern
- Before 09h00 and after 16h00
- On Sundays and public holidays
- Unless timeous notifications have been issued to the appropriate parties as per Clause A12.10.3.4.
CONTENTS
B12.10.1 SCOPE
B12.10.2 DEFINITIONS
B12.10.3 GENERAL
B12.10.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.10.5 MATERIALS
B12.10.6 CONSTRUCTION EQUIPMENT
B12.10.7 EXECUTION OF THE WORKS
B12.10.8 WORKMANSHIP
B12.10.1 SCOPE
The provisions of Part A shall apply.
B12.10.2 DEFINITIONS
The provisions of Part A shall apply.
B12.10.3 GENERAL
The provisions of Part A shall apply.
B12.10.5 MATERIALS
The provisions of Part A shall apply.
B12.10.8 WORKMANSHIP
The provisions of Part A shall apply.
C12.10.1 Excavation in hard rock using controlled blasting techniques cubic metre (m3)
The unit of measurement shall be the cubic metre of rock excavated employing controlled blasting techniques in cuts, borrow pits and quarries.
The volume measured for payment shall be shall be the volume of the compacted earthworks or layerworks calculated using the authorised
dimensions for those works given in the Contract Documentation. The tendered rate shall include
-
all costs in employing controlled drilling and blasting techniques in hard rock limiting the mass of explosive to be detonated simultaneously
to ensure that the required and specified limits of PPV are not exceeded and ensuring that all other conditions and constraints as specified
are satisfied.
- for any additional drilling, setting out, setting-up drilling equipment, special techniques, explosives or special explosives and any other
incidentals necessary to complete the blasting without any fly-rock and with minimal possible damage to the remaining rock.
- all additional costs and disruption to the Contractor’s programme resulting from carrying out the required trial blasts and test sections.
No separate payment will be made for cushion blasting. The cost of using cushion blasting techniques shall be included in the rates for excavation.
No separate payment shall be made for oversize material excavated to spoil.
C12.10.2 Pre-splitting - base rate for holes @ 750 mm c/c square metre (m2)
The unit of measurement shall be the square metre of net fracture surface created that is measured on the payment cut slope line. Measurement
will only be made for pre-splitting carried out in accordance with approved pre-splitting specified in the Contract Documentation and drawings, or
as ordered in writing by the Engineer. The base rate covers all the activities and requirements specified below, for creating a pre-spilt, with holes
strictly drilled at 750 mm centre to centre.
The base rate tendered shall include for pre-splitting blasting trials, for drilling and charging the holes, any additional works such as but not limited
to moving all plant and equipment to the respective drilling site and moving between holes, setting-up drilling equipment, any additional setting
out and control measures, limited spacing and diameters of pre-split holes, any additional explosives and any other incidentals necessary to
complete the pre-splitting work as specified.
The unit of measurement shall be the metre length of pre-split hole drilled and charged over and above the total length required for the base case,
where charged holes are spaced at 750 mm c/c. Only those additional holes as instructed and approved by the Engineer in writing prior to blasting
will be paid for.
The rate tendered shall include for drilling and charging the additional holes, for moving all plant and equipment to the drill site and moving between
holes, for setting-up drilling equipment, any additional setting out and control measures, limited spacing and diameters of drilled holes, and any
other incidentals necessary to complete the additional drilling work as required.
C12.10.4 Smooth blasting - base rate for holes @ 1500 mm c/c square metre (m2)
The unit of measurement shall be the square metre of net fracture surface created that is measured on the payment cut slope line. Measurement
will only be made for work carried out in accordance with approved smooth blasting techniques specified in the Contract Documentation and
drawings, or as ordered in writing by the Engineer. The base rate includes all the activities and requirements specified below, for creating a smooth
blast, with holes strictly drilled at 1500 mm centre to centre.
The base rate tendered shall include for all smooth blasting trials, for drilling and charging the holes, any additional works such as but not limited
to moving all plant and equipment to the respective drilling site and moving between holes, setting-up drilling equipment any additional setting out
and control measures, limited spacing and diameters of smooth blast holes, any additional explosives and any other incidentals necessary to
complete the smooth blasting work as specified.
The unit of measurement shall be the metre length of smooth blast hole drilled and charged over and above the total length required for the base
case, where charged holes are spaced at 1500 mm c/c. Only those additional holes as instructed and approved by the Engineer in writing prior to
blasting will be paid for.
The rate tendered shall include for drilling and charging the additional holes, for moving all plant and equipment to the drill site and moving between
holes, for setting-up drilling equipment, any additional setting out and control measures, limited spacing and diameters of drilled holes, and any
other incidentals necessary to complete the additional drilling work as required.
C12.10.6 Line Drilling - base rate for holes @ 300 mm c/c square metre (m2)
The unit of measurement shall be the square metre of net cut slope that is measured on the payment cut slope line. Measurement will only be
made for line drilling carried out in accordance with approved line drilling specified in the Contract Documentation and drawings, or as ordered in
writing by the Engineer. The base rate includes for all the activities and requirements specified below, for creating a drill, with holes strictly drilled
at 300 mm centre to centre.
The rate tendered shall include for all line drilling trials, any additional works of moving all plant and equipment to the drilling site and between
holes, any additional works of setting-up drilling equipment, any additional setting out and control measures, limited spacing and diameters of line
drilled holes, and any other incidentals necessary to complete line drilling work as specified.
The unit of measurement shall be the metre length of uncharged hole drilled over and above the total length of uncharged holes required for the
base case, where uncharged drill holes are spaced at 300 mm c/c. Only those additional holes as instructed and approved by the Engineer in
writing prior to blasting will be paid for.
The rate tendered shall include for drilling the additional holes, for moving all plant and equipment to the drill site and moving between holes, for
setting-up drilling equipment, any additional setting out and control measures, limited spacing and diameters of drilled holes, and any other
incidentals necessary to complete the additional drilling work as required.
D12.10.1 SCOPE
The scope of this Section covers the following:
- Guarantees and compliance certificates
- Product conformance specifications
D12.10.2 GENERAL
The Contractor shall submit comprehensive product data, specification, performance data and compliance certificates certified by the manufacturer
and relevant testing authority as might apply for all explosives, detonators and initiation systems within 28 days of entering into the contract with
the Employer.
CONTENTS
PART A: SPECIFICATIONS
A12.11.1 SCOPE
A12.11.2 DEFINITIONS
A12.11.3 GENERAL
A12.11.5 MATERIALS
A12.11.8 WORKMANSHIP
A12.11 GEOSYNTHETICS
PART A: SPECIFICATIONS
A12.11.1 SCOPE
This Section details only material specifications and uses of geosynthetics including their application as barriers, containment, drainage
(transmission), filtration, protection, reinforcement, separation, erosion control or as frictional interlayer systems. This Section does not contain
any Measurement and Payment items.
A12.11.2 DEFINITIONS
Geosynthetic Materials - collective term for geogrids, geotextiles and geocells made from a synthetic or natural polymer, in the form of a sheet,
a strip or a three-dimensional structure, used in contact with soil and/or other materials in geotechnical and civil engineering applications
Geotextiles - are planar soil and polymeric (synthetic or natural) textile material, which may be nonwoven, knitted, woven knitted or
stitch-bonded fibres or yarns, used in contact with /or other materials in geotechnical and civil engineering applications.
Geogrids - are planar, polymeric structures consisting of a regular open network of integrally connected, tensile elements, which may be linked
by extrusion, bonding or interlacing, whose openings are larger than the constituents.
Geonets - are a geosynthetic consisting of parallel sets of ribs overlying and integrally connected with similar sets at various angles.
Geomembranes - are continuous flexible sheets or rolls manufactured from one or more synthetic materials. They are relatively impermeable
and are used as liners for fluid or gas containment and as vapour barriers.
Geocomposites - are geosynthetics made from a combination of two or more geosynthetic types. Examples include geotextile-geonet;
geotextile-geogrid; geonet- geomembrane; or a geosynthetic clay liner (GCL). Prefabricated geocomposite drains or prefabricated vertical drains
(PVDs) are formed by a plastic drainage core surrounded by a geotextile filter.
Geosynthetic clay liners (GCLs) - are geocomposites, prefabricated with a bentonite clay layer typically incorporated between a top and
bottom geotextile layer or geotextile bonded to a geomembrane or single layer of geotextile. Geotextile-encased GCLs are often stitched or
needle- punched through the bentonite core to increase internal shear resistance. When hydrated, they are effective as a barrier for liquid or
gas and are commonly used in landfill liner applications often in conjunction with a geomembrane.
Geopipes - are perforated, slotted or solid-wall polymeric pipes used for drainage of liquids or gas (including leachate or gas collection in landfill
applications). In some cases the perforated or slotted pipe is wrapped with a geotextile filter.
Geocells - are three-dimensional, permeable, polymeric (synthetic or natural) honeycomb or similar cellular structure, made of linked strips of
geosynthetics. Strips are joined together to form interconnected cells that are in-filled with soil and sometimes concrete. In some cases 0,5 to
1,0 m wide strips of polyolefin geogrids are linked together with vertical polymeric rods used to form deep geocell layers called geomattresses.
Geofoam - blocks or slabs are created by expansion of polystyrene foam to form a low-density network of closed, gas-filled cells. Geofoam is
used for thermal insulation, as a lightweight fill or as a compressible vertical layer to reduce earth pressures against rigid walls.
Geosynthetic Cementitious Composite Mats (GCCMs) - is a flexible, concrete impregnated fabric that hardens on hydration to form a thin,
durable waterproof and fire resistant concrete layer. It is used in concrete channel lining, slope protection, bund lining, remediation of existing
concrete structures and culvert lining.
A12.11.5 MATERIALS
A12.11.5.1 General
The Contractor shall, within 28 days of entering into the contract with the Employer, provide conformance documentation obtained from his supplier
confirming the compliance with the specified properties before establishing such materials on site. Where so specified samples of the materials
shall be tested by an approved testing facility to ensure compliance with the specified requirements employing the appropriate test methods. Such
shall include geotextile qualities regarding soil retention; permeability; clogging; durability, strength and any other specified performance criteria.
A12.11.5.3 Durability
Geotextile shall comply with the following durability specifications:
A12.11.8 WORKMANSHIP
To ensure quality of materials testing may be specified to verify compliance with the specified requirements. This includes geotextile qualities
regarding soil retention; permeability; clogging; durability and strength. Table A12.11.8-1 details various test methods that may be used to verify
compliance with specified properties.
Table A12.11.8-1: Generic specification tests
CONTENTS
B12.11.1 SCOPE
B12.11.2 DEFINITIONS
B12.11.3 GENERAL
B12.11.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.11.5 MATERIALS
B12.11.6 CONSTRUCTION EQUIPMENT
B12.11.7 EXECUTION OF THE WORKS
B12.11.8 WORKMANSHIP
B12.11.1 SCOPE
The provisions of Part A shall apply.
B12.11.2 DEFINITIONS
The provisions of Part A shall apply.
B12.11.3 GENERAL
The provisions of Part A shall apply.
B12.11.5 MATERIALS
The provisions of Part A shall apply.
B12.11.8 WORKMANSHIP
The provisions of Part A shall apply.
Measurement and Payment will be covered under the Chapters where applicable.
D12.11.1 SCOPE
No specific items in this Section.
D12.11.2 GENERAL
No specific items in this Section.
CONTENTS
PART A: SPECIFICATIONS
A12.12.1 SCOPE
A12.12.2 DEFINITIONS
A12.12.3 GENERAL
A12.12.5 MATERIALS
A 12.12.8 WORKMANSHIP
A12.12.2 DEFINITIONS
Sump pumping - is the simplest method of dewatering excavations and is usually undertaken within the excavation. A sump is created by
excavating a hole which may either be left open unlined, open but supported by boarding and/or backfilled partially or wholly with a suitably graded
filter material. It is most effective in clean gravels and coarse sands and is generally unsuitable in materials containing a lot of fines because of
the danger of internal erosion and loss of fines unless special measures are taken.
Pumping may either be by way of sludge/submersible pumps placed in the sump or by way of a suction hose connected to a discharge pump
placed remotely at a convenient place in the dry.
Sumps are usually sited along the inner perimeter of excavations, below the invert level, and made big enough to hold sufficient water to match
the pumping capacity to keeping the excavation floor drained for the duration of the construction. A pump is provided for each sump and connected
to a discharge pipe, which conveys and disposes the pumped ground water to an approved destination.
Well point systems - are small well screens about 50 mm diameter, between 0,5 m to 1,0 m long, connected to the bottom of a small diameter
riser pipe which is usually water jetted down into the water bearing stratum with a lance to the required depth, generally not deeper than about
7,0 m. They are typically used in sandy gravels, sands and down to fine sand. With additional measures and augmentation they can also be
used to drain fine silty sands.
Well points are installed as a series of small wells along the perimeter of an excavation and are each connected directly through the riser pipe to
a common header pipe from which the water is pumped by a vacuum assisted centrifugal pump to an approved discharge point. The connection
between the riser pipe and common header pipe may either be directly, or more commonly by a short flexible pipe also referred as a swing joint.
Each connection between the riser pipe and header is fitted with a gate valve.
The effective depth of drawdown is limited to between 5,0 m to 6,0 m depending on the permeability and soil structure. Air-leaks/efficiency of the
system lines and connections may result in further reducing the depth of drawdown. Multistage systems are necessary for greater drawdown
depths.
Water jet eductor well systems - are similar to well point systems except that the riser pipe consists of a two part configuration, namely a
supply/feeder line and return line. Ground water is sucked through a well screen, into an eductor fitted to the base of the feeder pipe by a vacuum
formed when a high pressure jet of water fed from a surface high pressure ring main is forced through the venturi within it. The jetting water
together with the groundwater is then forced up through the return line of the riser pipe, to the return header ring main and discharges into a
collector/settling/holding tank. Part of the return water is drawn off and re-used by the supply water header pump to feed the high pressure ring
main, whilst the balance overflows and is discharged to waste. Typically, the input flow is about 1,5 to 2,5 times the induced flow, resulting in a
very low efficiency and slow extraction rates.
A12.12.3 GENERAL
A12.12.3.1 General
Groundwater conditions and/ or construction requirements may necessitate the design and application of site specific dewatering system/s to
ensure that safety is not compromised or the integrity of the founding and surrounding materials is not adversely affected by poor methodology or
equipment failure. Dewatering shall be conducted in such a manner to ensure that within the potential zone of influence of the dewatering activities,
no unacceptable ground subsidence, damage to any property, structures or facilities will occur and that it does not pose a threat to the public
health or create any hazard.
This may require that construction dewatering be undertaken by a specialist Contractor or sub-Contractor. The Contractor shall design the
dewatering strategy and layout plan(s). The supply, install, and operate all pumps, pipes, appliances, and equipment of sufficient capability to
maintain the requisite minimum lowered groundwater levels for all excavations requiring dewatering until they are backfilled to the required
specification.
The groundwater level shall normally be lowered and maintained at an absolute minimum of 1,0 m below the lowest excavation invert level, or to
such levels as may be specified in the Contract Documentation or instructed in writing by the Engineer.
The scope of the works shall also encompass the requirements of Clause A2.1.3.2 of Chapter 2.
Where necessary diversion ditches and dikes/earthen bunds shall be used, to prevent surface water from entering any excavation(s).
Unless specifically reflected in the pricing schedule, or where provision for such has been made in the Contract Documentation, the requirements
stipulated shall be deemed to be included in the rates for the works.
Method Statements
A12.12.7.1a) Method statements for dewatering each work area. 2 weeks prior to construction
Process
Prior to commencement of
Permits and wayleaves to dispose of removed water where
A12.12.7.1c) dewatering
required
All or some of the information listed above may be available and presented in the Contract Documentation, failing which it will be the Contractor’s
responsibility to obtain the further requisite minimum information he considers necessary.
A12.12.5 MATERIALS
Where so specified the Contractor shall submit samples and the requisite technical details and specifications of all the main components of the
dewatering system proposed, for acceptance by the Engineer, at least 2 weeks before the approved programmed trial/construction activity. Where
appropriate a prototype of the proposed system shall be assembled and presented to the Engineer for inspection.
A12.12.6.2 Maintenance
All equipment shall be inspected, serviced and calibrated at regular requisite intervals and tested to ensure system functionality, efficiency and
accuracy.
At the commencement of the work the Contractor shall supply the Engineer, for all key plant to be used, the requisite maintenance plans and
schedules as required by the manufacturer, to keep them in the requisite working order. The Contractor shall for the duration of the contract,
submit monthly returns summarising all maintenance and repair work undertaken on the key equipment.
The Engineer may suspend the further use of the item of equipment plant in question if such is shown to be unsafe or ineffective. In this event the
Contractor shall replace that equipment to ensure that there is no interruption to any active dewatering programme.
The Contractor shall have fully functional and operational standby pumps with all accessories on site to cope with at least two simultaneous and/or
two successive breakdowns. The Contractor shall be so equipped and staffed so as to install and commission the requisite standby equipment
within 3hrs from the breakdown.
A12.12.7.2 Process
a) Operational requirements
The system shall be in place and fully operational and ground water lowering proven to have achieved the specified reduced levels, 24 hrs prior
to commencing with any excavation or other construction activity. If required the system shall be operated continuously 24 hours a day, 7 days a
week once excavation/ construction has commenced, irrespective of whether construction activities are interrupted or temporarily halted, and fully
operational until such time as construction activities are completed and the excavations have been completely backfilled, which backfilling shall
have been tested for compliance with the specification and approval by the Engineer.
Generally dewatering by sump creation and pumping is an ongoing activity as excavation proceeds. Unless specifically provided for and instructed
by the Engineer to address sudden and unforeseen surges of water inflow into excavation separate payment will not be made therefore.
The Contractor shall at all times have, on the work site, sufficient dewatering equipment for immediate use, including standby pumps and
generators for use in case any of these items of plant breakdown and require replacement.
If the dewatering system shuts down or if pumping is suspended, for any reason whatsoever the Contractor shall withdraw from the excavation
before water levels start to rise. On resumption of dewatering, the groundwater levels will need to be re-lowered to the specified level before
continuing any construction, including excavation or backfilling.
Any in-situ material /backfill that is subjected to groundwater and wetted shall be tested as directed by the Engineer, to confirm that the condition
thereof is stable and acceptable prior to placement of further backfill and/or other construction activities. The Contractor shall remove and replace
adversely affected material with suitable material approved by the Engineer at his own expense.
Due care shall be taken when turning off the dewatering system to prevent upsurge in ground water which may weaken the subgrade of the
completed excavation.
Surface runoff shall be diverted away from excavations by site grading to promote drainage away from any excavation. Surface water shall be
collected in shallow trenches around the perimeter of the excavation, drained to sumps, and pumped or drained by gravity to maintain an
excavation free from ponding water. In the case of multistage dewatering, this would require a perimeter drain to be in place at the toe of each
excavated stage and for the collected water to pumped back to surface into the water discharge system.
Adequate control shall be maintained by the Contractor to ensure that the stability of excavated slopes are not adversely affected by water, that
erosion is controlled and that flooding of excavation or damage to structures does not occur. The Contractor is solely responsible for site
excavation safety and compliance with OHS regulations.
If the planned groundwater reduction levels are reached, but notwithstanding unstable conditions and/or unacceptable excavation invert conditions
are present, the Contractor shall either increase dewatering pumping rates and/or to install additional wells to lower the groundwater to a revised
requisite level. The Contractor should achieve the revised groundwater level lowering and stable and acceptable invert conditions before
continuing with construction.
Buoyant ground conditions shall be prevented by the Contractor by maintaining a positive and continuous removal of water. The Contractor shall
be fully responsible for all damages which may result from failure to adequately keep excavations dewatered.
A12.12.7.5 Records
The Contractor shall submit daily returns indicating activities completed on each working day. The Contractor shall also, for each completed hole/
well point provide a record, in a format agreed with the Engineer prior to the commencement of the work. Where such records are of an ongoing
nature the Contractor shall regularly produce reports summarising criteria and recording trends, as may be required by the Engineer.
A12.12.8 WORKMANSHIP
All dewatering systems shall be checked for compliance with the specifications. Any system, or element(s) of a system, not meeting the specified
criteria, or which does not reach the specified depth may be rejected by the Engineer who may order that it be amended to conform or be replaced
if so required, to conform to the requirements.
CONTENTS
B12.12.1 SCOPE
B12.12.2 DEFINITIONS
B12.12.3 GENERAL
B12.12.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B12.12.5 MATERIALS
B12.12.6 CONSTRUCTION EQUIPMENT
B12.12.7 EXECUTION OF THE WORKS
B12.12.8 WORKMANSHIP
B12.12.1 SCOPE
The provisions of Part A shall apply.
B12.12.2 DEFINITIONS
The provisions of Part A shall apply.
B12.12.3 GENERAL
The provisions of Part A shall apply.
B12.12.5 MATERIALS
The provisions of Part A shall apply.
B12.12.8 WORKMANSHIP
The provisions of Part A shall apply.
C12.12.2 Installing and commissioning all requisite plant and equipment to undertake dewatering number (No)
by well system offered (type of well system to be nominated by tenderer)
The unit of measurement shall be a standard length section of header pipe with all the requisite number of wells at the dewatering location, all
fittings, materials and dewatering pump(s).
The quantity measured shall be the number of standard pipe lengths installed and commissioned in compliance with best practice and the
requirements of these specifications.
The tendered rate shall include full compensation for all costs involved in installing all equipment, pre-drilling, drilling, jetting or any other means
necessary and approved for installing all wells required at the dewatering location to achieve the required level of drawdown, complete with the
requisite filters, screens and casings in all materials and their subsequent extraction, or abandonment if approved by the Engineer, on completion
of dewatering. The tendered rate shall furthermore include for the supply and installation of all caps, riser pipes, flexible swing joints, stop valves,
couplings, well take-off points, flow meters, header pipes and dewatering pumps fully equipped with motors. Where electric motors are used to
drive the motors, the tendered rate shall include for all costs of establishing the requisite electrical supply, either from mains or by way of
generators. The rate shall also include the provision of all requisite standby equipment and the installation of all requisite, monitoring wells/points
and survey monitoring beacons as specified.
C12.12.3 Operate and maintain well system (type of well system to be nominated by tenderer) (pumped) hours) (hrs)
C12.12.4 Supply Install and remove discharge pipeline to the required depth (diameter and class metre (m)
indicated)
The unit of measurement shall be the metre of pipeline installed.
The quantity measured shall be the actual length of discharge pipe installed from the position of the dewatering pump to the approved disposal
site(s) along the approved route.
The tendered rate shall include for the supply and installation of all pipe together with stop valves, couplings, and flow meters if required. The
rate shall also include for the protection and securing the discharge pipeline in, on and over all terrain as well the cost of securing the discharge
end, including the requisite scour protection resulting from the water discharge.
The tendered rate shall include for all costs to operate and maintain the discharge pipeline, including 24hr/7 days per week requisite supervision
and operators, all repairs and maintenance, replacement of al damaged pipe.
C12.12.5 Install ground observation wells to the required depth (diameter and class indicated) metre (m)
The tendered lump sum shall include full compensation for monitoring the groundwater levels as specified.
The tendered lump sum shall include full compensation for the monitoring of settlements as specified.
The tendered lump sum shall include full compensation for the monitoring of the quality of groundwater as specified
The Contractor shall provide detailed specifications and certificates from independent reputable agencies for all proprietary casing/sleeves and
materials proposed for use. These shall demonstrate conformance with the performance requirements stipulated in the Contract Documentation.
CONTENTS
D12.12.1 SCOPE
D12.12.2 GENERAL
D12.12.3 PERFORMANCE GUARANTEE REQUIREMENTS
D12.12.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D12.12.5 VISUALLY ASSESSED PROPERTIES
D12.12.6 INSTRUMENTALLY ASSESSED PROPERTIES
D12.12.7 EVALUATION FOR ACCEPTANCE
D12.12.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D12.12.9 NOTIFICATION OF REMEDIAL WORK
D12.12.10 REMEDIAL WORKS
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by
COTO on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and
Bridge Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 13: STRUCTURES............................................................................................................................... 13-1
13.1 FOUNDATIONS ............................................................................................................................................. 13-1
PART A: SPECIFICATIONS ............................................................................................................................................................................ 13-1
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................. 13-12
PART C: MEASUREMENT AND PAYMENT ................................................................................................................................................. 13-15
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES .................................................................................................................... 13-22
CONTENTS
PART A: SPECIFICATIONS
A13.1.1 SCOPE
A13.1.2 DEFINITIONS
A13.1.3 GENERAL
A13.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.1.5 MATERIALS
A13.1.6 CONSTRUCTION EQUIPMENT
A13.1.7 EXECUTION OF THE WORKS
A13.1.8 WORKMANSHIP
A13.1 FOUNDATIONS
PART A: SPECIFICATIONS
A13.1.1 SCOPE
This Section covers foundation and foundation related work which, for the purposes of these specifications, shall comprise amongst others those
elements of construction below the level of the bottom surface of conventional spread footings, pile-capping slabs or caisson cover slabs,
collectively hereinafter referred to as base or bases, and it covers all the associated permanent and temporary works. Piling is dealt with in
Chapter 12. Foundations for prefabricated culverts are not included but are specified in Chapter 3.
A13.1.2 DEFINITIONS
Artificial islands - temporary platforms constructed in rivers and streams to allow access for construction activities.
Banks - a stream bank or river bank is the terrain alongside the bed of a river.
Watercourse - a watercourse means a river or spring; a natural channel in which water flows regularly or intermittently; a wetland lake or dam,
into which or from which water flows; and any collection of water that may be declared to be a watercourse in terms of relevant legislation.
Caissons - a watertight retaining structure used, to facilitate founding of bridge structures as an alternative to piling.
Cofferdams - a cofferdam is a temporary enclosure built within a body of water, in waterways, on waterlogged areas or on unsuitable ground
and is constructed to allow the enclosed area to be pumped out, creating a dry work environment for the construction of permanent works to
proceed.
DWS - Department of Water and Sanitation.
Contractor’s Competent Person (CCP) - the Contractor’s Competent Person is appointed in writing to administer, inspect and verify the
adequacy of temporary work such as excavations and sub-structure work must be registered and competent in relation to the services rendered
in terms of the ECSA Engineering Professions Act and construction regulations as contained in the OHS.
A13.1.3 GENERAL
A13.1.3.1 Subsurface data
The Contractor shall take due cognizance of available information regarding site geotechnical conditions and related stability and safety of the
excavations. Provision for specialised support systems shall be included in appropriate payment items. If such separate items are not provided
they shall be deemed to be included in rates for excavation items.
The provisions of the General Conditions of Contract shall apply with regard to any information supplied regarding any subsurface conditions
likely to be encountered.
A13.1.4.3 Cofferdams
The design and construction of cofferdams other than those comprising earth embankments, shall comply with the requirements of BS 8004.
Before starting with construction, the Contractor shall submit drawings to the Engineer, which show details of cofferdams and method of
construction, for his information. All risks related to such cofferdams, including the risk of flooding, shall remain exclusively with the Contractor.
A13.1.5.6 Grouting
a) Cementitious grout
Cementitious binder for grout shall meet the appropriate requirements of Clause A13.5.5.7.
b) Proprietary-brand, and chemical, grouts
Proprietary-brand, and chemical, grouts shall be prepared and used strictly in accordance with the manufacturer’s instructions and as specified
in the applicable Sections of Chapter 14.
A13.1.7.2 Excavation
a) General
This work shall include excavations not provided for elsewhere in these specifications, which are required for founding the structures as well as
for excavation required in respect of demolition, extension or modification of existing bridges and culverts.
Excavation in the vicinity of existing structures and road formations shall be performed with due care and diligence. The Contractor shall take
special care not to disturb the founding material of any existing foundations and road formations. The excavation profile must strictly be as
approved by the Engineer and as shown on drawings.
b) Agreed excavation surface level and profiles
Prior to commencing with any excavation, artificial islands, cofferdams, temporary banks or any other works covered by this specification, the
Contractor shall notify the Engineer in good time to ensure that levels be taken of the undisturbed ground surface for determining a ground
surface from where excavation shall be measured, and this ground surface shall be agreed on by Engineer and Contractor.
In addition, the proposed excavation profile, with due consideration of stability of material, existing structures and existing road formations shall
be agreed prior to commencement of excavation. Details of lateral support systems, if any, shall be provided and approved in accordance with
all the requirements for temporary works and site designs.
The final foundation depth and suitability of the foundation material shall be approved by the Engineer in consultation with a suitably–qualified,
ECSA–Professional Registered Geotechnical Engineer.
c) Excavation
In stable or hard material the Engineer may approve that the excavated surfaces can act as forms for casting of the concrete and the
excavations shall then be carried out and trimmed to neat dimensions of the concrete members shown on the drawings. To prevent moisture
loss in the concrete where excavated surfaces act as forms, a foundation lining shall be installed as specified in Clause A13.1.7.9. As an
alternative, provided that sufficient space is made available during excavation, an additional 50 mm of concrete cover, over and above that
specified may also be provided if approved by the Engineer. Excavations in soft material in excess of the authorised dimensions (over-
excavation) or overbreak in hard material shall be backfilled with the same class of concrete as that in the base.
A13.1.7.3 Founding
Variations during construction in anticipated founding conditions may necessitate changes to dimensions and founding levels specified or shown
on the drawings.
The Engineer has full and absolute power in terms of the contract to order such variations and to specify actual founding level for each
foundation fill, base or caisson during construction.
The Contractor shall not be entitled to any additional payment in consequence of any such variation in dimensions or founding depths over and
above that provided in Clause A13.1.3.1 irrespective of stage of construction at which the instruction to alter the dimensions or founding depths
is given.
No bases or caissons shall be founded unless authorised by the Engineer. Each founding level shall be accurately measured, recorded and
agreed.
The term "founding level" used in these specifications shall be have the following meanings in respect of:
a) Foundation fill
Surface of in situ material that was prepared to receive foundation fill.
b) Bases
Underside of base, or conversely, top of the concrete screed.
c) Piled Foundations
Underside of pile cap.
d) Caissons
Underside of cutting edge.
A13.1.7.10 Caissons
a) General
Caissons, as contemplated in these specifications, shall be hollow concrete vessels which are wholly or partly constructed at a higher level and
lowered by internal excavation or ballast to desired founding level to form structural bearing members. Caissons may be of circular, rectangular
or any other shape and may contain one or more excavation compartments, all as detailed on the drawings.
Unless otherwise specified hereafter, provisions of BS 8004 shall apply in regard to construction of caissons.
b) Construction and sinking
A firm horizontal base shall be prepared on which the cutting edge of caisson shall be laid horizontally. The level of base shall be determined
and shall be agreed by the Engineer and Contractor and shall serve as the ground surface from which the excavation inside the caisson is
measured.
Successive stages of the caisson shall be of convenient height, or as directed by the Engineer, and shall be lined accurately with preceding
stages.
If specified, all precast elements shall have adequately constructed joints in accordance with drawings to ensure a snug fit.
For in situ phase construction, all construction joints in walls shall be reinforced and joints shall be made as specified in Section A13.4.
The lowest element of every caisson, which contains cutting edges, shall be cured for at least 7 days or shall reach the specified characteristic
compressive strength before sinking is commenced. Subsequent elements shall be cast in sufficient time to ensure adequate strength for safely
resisting applied forces.
During constructing and sinking, caissons shall be maintained vertically and kept in correct positions.
Position and inclination of each caisson shall be determined accurately by measurement every 2,0 m of sinking, or after sinking through depth of
one element, whichever distance is smaller.
To eliminate excess friction, the Contractor may use bentonite or similar lubricant, or a water-jet system.
Excavation inside caisson compartments shall, unless otherwise specified herein, comply with provisions of Clause A13.1.7.2.
In multi-compartmented caissons excavation in any one compartment shall not be taken deeper than 0,6 m below that in any other
compartment, except where necessary for correcting deviations.
Cutting edges shall be frequently inspected or probed to locate obstacles, which shall immediately be removed.
The Contractor shall supply all grabs, pumps, diving gear and other plant required for sinking and founding all caissons and shall allow the
Engineer to use a diving suit and related equipment for inspection purposes, if required.
A13.1.8 WORKMANSHIP
At commencement of construction the Contractor shall provide detailed process quality assurance procedures with regards to backfill, foundation
fill and grouting
A13.1.8.1 Definitions
Except where otherwise specified, the following aspects of construction, to which tolerances apply, shall have meanings attributed to them as
detailed below:
Position - the position of a structure or structural member shall be the horizontal position of its centre line(s) or centre point(s) in relation
to the overall layout of the works as shown on the drawings.
A13.1.8.2 Tolerances
For the assessment of acceptance and compliance the tolerances given below shall be the maximum permissible deviations from the
specified dimensions, levels, alignment, positions, etc., shown on drawings of the structures or structural members.
a) Foundations
Caissons:
Position of top of caisson ............................................................... 10 % of smallest outer dimension of caisson, measured in plan.
Verticality....................................................................................................................................................................................... 1,5°
Dimensions:
Wall thickness ........................................................................................................................................................ + 25 mm – 5,0 mm
Outer dimension of circular, rectangular or square cross-section ............................................................................................ ± 25 mm
Level: Upper level of trimmed/cut caisson head:
Maximum deviation of average level ....................................................................................................................................... ± 25 mm
Maximum deviation of any individual level .............................................................................................................................. ± 50 mm
Foundation fill:
Average level of top of foundation fill ...................................................................................................................................... ± 25 mm
b) Footings, pile capping slabs, caisson cover slabs, etc.
Position ..................................................................................................................................................................................... 15 mm
Alignment:
Alignment of individual member ........................................................................................................................................................ 5°
Alignment of members as they collectively determine
alignment of structure as a whole ........................................................................................................................................... 1 minute
Dimensions: Leading dimension in plan ................................................................................................................................. ± 25 mm
Thickness ................................................................................................................................................................ + 25 mm – 15 mm
Levels: Average level of slabs, footings, etc............................................................................................................................ ± 25 mm
CONTENTS
B13.1.1 SCOPE
B13.1.2 DEFINITIONS
B13.1.3 GENERAL
B13.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.1.5 MATERIALS
B13.1.6 CONSTRUCTION EQUIPMENT
B13.1.7 EXECUTION OF THE WORKS
B13.1.8 WORKMANSHIP
B13.1.1 SCOPE
This Section covers foundation and foundation related work and relates to the additional specification Clauses for the labour enhanced
excavation and backfilling of foundations.
B13.1.2 DEFINITIONS
Definitions as provided in A13.1.2 shall apply.
B13.1.3 GENERAL
Any activity specified in Part A, where hand work is envisaged, shall be executed in such a way as to maximise labour enhancement.
B13.1.5 MATERIALS
The provisions of Part A shall apply.
• Excavation plant may be used for excavations under water. All excavations in the dry shall be done using labour.
• Drilling equipment
B13.1.7.2 Excavation
a) General
The labour enhanced work shall include excavations not provided for elsewhere in these specifications, which are required for founding the
structures as well as for excavating required in respect of demolition, extension or modification of existing bridges and culverts.
Excavation in the vicinity of existing structures and road formations shall be performed with due care and diligence. The Contractor shall take
special care not to disturb the founding material of any existing foundations and road formations. The excavation profile must strictly be as
approved by the Engineer and as shown on drawings.
Transportation of all materials shall be done with wheelbarrows up to the haul distance of 50 m. For haulage that is longer than 50 m,
transportation for the full distance shall be done by hand-loaded dumpers, flat-bed trucks, tractor-trailer combinations or by other approved
means.
b) Agreed excavation surface level and profiles
The provisions of Clause A13.1.7.2b) shall apply.
c) Excavation
All excavations in the dry shall be done by using labour. Excavations under water shall be undertaken with suitable plant.
In stable or hard material the Engineer may approve that the excavated surfaces can act as forms for casting of the concrete and the
excavations shall then be carried out and trimmed to neat dimensions of the concrete members shown on the drawings. To prevent moisture
loss in the concrete where excavated surfaces act as forms, a foundation lining shall be installed as specified in Clause A13.1.7.9. As an
alternative, provided that sufficient space is made available during excavation, an additional 50 mm of concrete cover, over and above that
specified may also be provided if approved by the Engineer. Excavations in soft material in excess of the authorised dimensions (over-
excavation) or overbreak in hard material shall be backfilled with the same class of concrete as that in the base.
In the case where excavations are made to neat dimensions of the concrete members (no formwork), compensation for the backfill of over-
break in hard material shall be measured and paid for under pay item C13.1.9 but the cost of backfilling of over-excavation in soft material shall
be at the Contractor’s own expense. Where additional excavation width is required for the erection of formwork, no additional compensation for
over-excavation or overbreak will be made except as provided for the applicable payment items.
The labour enhanced Contractor is not permitted to undertake blasting. Where blasting is required, the Contractor shall complete the entire
foundation excavation before commencing with the construction of any permanent concrete work, unless otherwise approved by the Engineer.
Boulders, logs or any other unsuitable material excavated shall be spoiled.
When material suitable for founding is encountered at the founding level, it shall be cut and trimmed to a firm surface, either level, stepped or
serrated, as may be required.
Where, in the opinion of the Engineer, unsuitable material is encountered at founding level, such material shall be removed and replaced with
foundation fill in accordance with Clause A13.1.7.6 and as directed by the Engineer.
d) Labour Enhancement Classification of Excavated Material
The Engineer shall classify excavated materials as soft or intermediate.
The Contractor shall notify the Engineer of the presence of what he considers to be rock or intermediate material immediately upon discovery
thereof. The Engineer will inspect the material and decide whether the material shall indeed be classified as suggested by the Contractor or not.
The decision of the Engineer shall be final and binding, subject to the provisions of the Contract.
(i) Intermediate
Intermediate excavation shall include rock banks breakable by conventional means (jack hammers using pneumatic or hydraulic
means), and in situ materials containing more than 40 % of any material (by volume) consisting of boulders each not exceeding
0,03 m3 in size.
(ii) Soft
Soft excavation shall be excavation in normal soft and hard soil containing less than 40 % (by volume) boulders each not
exceeding 0,03 m3.
(iii) Blasting
Blasting will not be permitted.
B13.1.7.3 Founding
All specifications under this sub-heading in the various sections of Clause A13.1.7.3, shall apply.
B13.1.7.10 Caissons
Not suitable for labour intensive work.
B13.1.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be the lump sum and shall be paid in two payments; 50% on submission of the temporary work designs and the
second 50 % on complete removal of all the temporary works.
The tendered rates shall include full compensation for procuring and provision of all drawings of the temporary works, designs by an ECSA-
registered Professional Engineer or Technologist or Geotechnical Engineer, including all labour, material, travelling and incidentals, time delays
and submission of all the certificates as specified.
C13.1.2.1 Provisional sum allowed for additional foundation investigations provisional sum
C13.1.2.2 Handling costs and profit in respect of item C13.1.2.1 percentage (%)
The provisional sum allowed under subitem (a) shall only be expended on submission of actual costs of the appointed sub-Contractor for the
additional foundation investigation.
The tendered percentage of subitem (b) is a percentage of the amount actually spent under subitem (a) and shall include full compensation for
all charges and incidental costs of the Contractor, profit and overheads.
C13.1.3 Excavation:
C13.1.3.1 Excavating soft material situated within the following successive depth ranges:
C13.1.3.2 Extra over subitem C13.1.3.1 for excavation in hard material irrespective of depth cubic metre (m3)
C13.1.3.3 Extra over subitem C13.1.3.1 for additional excavation required by the Engineer after cubic metre (m3)
excavation is complete
C13.1.3.4 Extra over subitem C13.1.3.1 for excavation by hand cubic metre (m3)
C13.1.3.5 Extra over subitem C13.1.3.1 for excavation in restricted areas cubic metre (m3)
C13.1.4.1 Excavate in soft material situated within the following successive depth ranges:
C13.1.4.2 Extra over item C13.1.3.1(a) for excavation in intermediate material cubic metre (m³)
C13.1.4.3 Extra over item C13.1.3.1(a) for additional excavation required by the Engineer after cubic metre (m³)
excavation is complete
Limits for successive depth ranges shall be measured vertically down from surface levels agreed (Clause A13.1.7.2b)) to founding level (Clause
A13.1.7.3) agreed.
In the case of excavations required for diverting, channelization or widening streams, successive depth ranges for those portions of excavations
that are within 5,0 m of a concrete structure shall be measured from surface levels agreed to invert level of channel or stream.
Unit of measurement shall be the cubic metre of material, measured in original position before excavation. Quantity of excavation for each depth
range shall be calculated from neat outlines of base or floor and depth of excavation completed within each range.
Excavation required for diverting, channelling or widening streams within 5,0 m of concrete structures shall be measured and paid for under item
C13.1.3. Excavations beyond this 5,0 m limit shall be measured and paid under the appropriate items in Chapters 3 and 4 unless otherwise
provided for in the Contract Documentation.
C13.1.5 Mass excavation within a restricted area (extra over item C13.1.3) cubic metre (m³)
Unit of measurement shall be the cubic metre and quantities shall be taken as total volume of material within the restricted area as defined in
Clause A13.1.7.5. The quantity shall not include volume of excavation which is measured and paid for under item C13.1.3 above.
Tendered rate shall include full compensation for all additional work necessitated by working in restricted areas.
The unit of measurement shall be the cubic metre of backfill material measured in the excavation. The quantity measured shall be calculated
from within the neat outlines defined for excavation under item C13.1.3 and height to which the backfilling is constructed. The volume occupied
by the structure shall be subtracted when calculating volume of backfilling.
The height shall be determined by the upper surface of the road prism or reference ground surface (Clause A13.1.7.2b)), whichever is the lower.
The tendered rates shall include full compensation for furnishing and placing all materials within the entire excavation, transporting the material
within haul distance of 1,0 km, and in the case of labour enhanced methods a haul distance of 100 m, and preparing, processing, shaping,
watering, mixing and compacting the material to the specified densities.
C13.1.9 Fill within a restricted area (extra over item C5.2.2) cubic metre (m3)
The unit of measurement shall be the cubic metre and the quantity shall be taken as total volume of material within the restricted area as defined
in Clause A13.1.7.5 d). This quantity shall not include the volume of backfill measured and paid for under items C13.1.7 and C13.1.8.
The tendered rate shall include full compensation for all additional work necessitated by working in restricted areas and for increased density
required in restricted areas.
Haul shall be measured and paid for as specified in Section C1.7 of Chapter 1 and shall apply only to that portion of the material qualifying for
payment under items C13.1.3, C13.1.4, C13.1.7.2, C13.1.8.2, C13.1.10, C13.1.11, C13.1.14.1, C13.1.14.2, C13.1.14.3, C13.1.15.1, C13.1.15.2,
C13.1.15.3, C13.1.30 & C13.1.31
Haul shall not apply to concrete used in foundation fill.
The unit of measurement shall be the square metre of surface area of the vertical outer faces of the base where excavations are made to “neat”
dimensions of the base.
The tendered rate shall include full compensation for the overbreak material removed from the excavation in hard material, for the concrete fill in
accordance with Clause A13.1.7.6, and any additional screeding concrete required.
C13.1.14.5 Concrete blinding (thickness and class of concrete indicated) cubic metre (m3)
C13.1.15.5 Concrete blinding (thickness and class of concrete indicated) cubic metre (m³)
The unit of measurement shall be the cubic metre of approved material placed and compacted below the bases as specified or where directed
by the Engineer.
The quantity of foundation fill to be measured for payment shall be the material contained within the prism specified in Clause A13.1.7.6 or shall
otherwise be the quantity to the outlines shown on the drawings or as directed by the Engineer.
The tendered rates shall include full compensation for procuring, furnishing, transporting for a haul distance of 1,0 km (subitems (a) to (c) only),
placing and compacting material and in the case of labour enhanced methods, a haul distance of 50 m.
Item Description Unit
C13.1.16 Establishment on site for drilling of holes and grouting of rock fissures (type of drilling lump sum
indicated):
The tendered lump sum shall include full compensation for establishment on the site and the subsequent removal of all special equipment and
plant for drilling the holes, grouting of rock fissures and any additional plant for carrying out operations, the cost of which does not vary with the
actual amount of work to be done.
This work will be paid for by way of a lump sum, 75 % of which will become payable when all equipment is on the site and the first hole has been
grouted. The remaining 25 % will become payable after all holes have been grouted and equipment removed from site.
C13.1.17 Moving to and setting up equipment at each hole to be drilled for grouting: number (No)
The unit of measurement shall be number of positions to which the equipment has to be moved and set up for drilling and grouting rock fissures.
The number to be measured shall equal number of holes drilled as instructed by the Engineer.
Tendered rate shall include full compensation for all the costs involved in moving and setting up the equipment.
C13.1.18 Drilling of holes for grouting (diameter and type of drilling indicated): metre (m)
The unit of measurement shall be the metre of hole drilled.
The tendered rate shall include full compensation for drilling and clearing the holes as specified.
C13.1.19 Grouting of rock fissures (type of grout and for which purpose it is required indicated): kilogram (kg)
The unit measurement for grouting shall be the kilogram of cementious binder or proprietary grout as may be applicable used in the grouting
operation.
The tendered rates shall include full compensation for providing the equipment and all material and mixing and pumping the grout into the
prepared holes in accordance with instructions of the Engineer, and also for the water-pressure tests.
C13.1.20.1 Drilling and preparation of holes (diameter and length indicated) metre (m)
(type, diameter, length, corrosion protection, together with type of grout, indicated) kilogram (kg)
The unit of measurement for drilling and preparation of holes in rock shall be the metre of holes drilled while unit of measurement for dowel bars
shall be the kilogram of bars provided and secured in position.
The tendered rates shall include full compensation for drilling holes, preparing holes for grouting i.e. saturating and cleaning, supplying all the
material and positioning and grouting the dowel bars as specified.
C13.1.21 Foundation lining (type of material and thickness indicated): square metre (m2)
The unit of measurement for foundation lining shall be the square metre of concrete surface lined.
The tendered rates shall include full compensation for procuring, furnishing and placing all material and incidentals required for completing the
work as specified.
The unit of measurement for foundation lining shall be the square metre of concrete surface lined.
The tendered rates shall include full compensation for procuring, furnishing and placing all material, labour and incidentals required for
completing the work as specified.
C13.1.25 Formwork for caissons (class of finish indicated) square metre (m2)
The unit of measurement shall be square metre of formwork, and only area of formwork in contact with finished faces of concrete shall be
measured. Formwork for construction joints shall be measured for payment under class F1 surface finish but shall be measured only for the
construction joints shown on drawings or as prescribed by the Engineer.
The tendered rate shall include full compensation for supplying all materials, erecting falsework and formwork, constructing forms, forming
grooves, fillets, chamfers, stop ends for construction joints, treating forms, all accessories, and stripping and removing the formwork after
completion of the work. Payment for the formwork shall be made only after the formwork is stripped and surface finish approved.
C13.1.27 Cast in situ concrete in caissons and concrete seals (class of concrete indicated) cubic metre (m3)
The unit of measurement for cast in situ concrete shall be the cubic metre of concrete in place. Concrete quantities in caissons shall be
calculated from dimensions shown on drawings or authorised by the Engineer, and length of caisson from founding level to specified cut-off
C13.1.28 Cutting edge for (diameter/ size indicated) caissons number (No)
The unit of measurement shall be number of caissons provided with cutting edges, irrespective of constructed material.
The tendered rate shall include full compensation for manufacturing, supplying, delivering and installing the complete cutting edge as well as for
joining cutting edge to caisson unit. Where cutting edge is of concrete and forms part of the bottom element, tendered rates shall include full
compensation for all additional work required for completing the element.
C13.1.30.1 Excavating soft material situated within the following successive depth ranges:
C13.1.30.2 Extra over subitem C13.1.24.1 for excavation in hard material irrespective of depth cubic metre (m3)
Limits for successive depth ranges shall be measured from the firm horizontal base (Clause A13.1.7.10b)) to excavated level inside the caisson.
The unit of measurement shall be the cubic metre of material, measured in original position before excavation. Quantity of excavation for each
depth range shall be calculated from the gross area of caisson in plan and depth of excavation completed within each depth range.
Irrespective of total depth of excavation, quantity of material within each depth range shall be measured and paid for separately.
The tendered rates shall include full compensation for excavation in the classified material, spoiling or stockpiling material, hauling excavated
material for haul distance of 1,0 km, trimming bottom of excavation, dewatering, pumping and removing material leaking into the caisson before
sealing.
CONTENTS
D13.1.1 SCOPE
D13.1.2 GENERAL
D13.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.1.5 VISUALLY ASSESSED PROPERTIES
D13.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.1.7 EVALUATION FOR ACCEPTANCE
D13.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.1.9 NOTIFICATION OF REMEDIAL WORK
D13.1.10 REMEDIAL WORK
CONTENTS
PART A: SPECIFICATIONS
A13.2.1 SCOPE
A13.2.2 DEFINITIONS
A13.2.3 GENERAL
A13.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.2.5 MATERIALS
A13.2.6 CONSTRUCTION EQUIPMENT
A13.2.7 EXECUTION OF THE WORKS
A13.2.8 WORKMANSHIP
A13.2.2 DEFINITIONS
Falsework - is any temporary construction used to support the loads for a structure until it becomes self-supporting.
Formwork - is the temporary structure, mould or form used to retain plastic or fluid concrete in its designated shape until it hardens.
Formed Surfaces - there are 3 classes of struck off the form surface finishes.
Unformed Surfaces - there are 3 classes of surface finish.
A13.2.3 GENERAL
Notwithstanding approval given by the Engineer for the design and drawings prepared by the Contractor for the falsework and formwork and the
acceptance of the falsework and formwork as constructed, the Contractor shall be solely responsible for the safety and adequacy of the
falsework and formwork and shall indemnify and keep indemnified the Employer and Engineer against any losses, claims or damage to persons
or property whatsoever which may arise out of or in consequence of the design, construction, use and maintenance of the falsework and
formwork and against all claims, demands, proceedings, damages, costs, charges and expenses and risks whatsoever in respect thereof or in
relation thereto.
For works on, over, under or adjacent to any railway line, walkway, existing road or any other facility which is controlled by a statutory authority,
the Contractor shall comply, inter alia, with the requirements for the preparation and submission of drawings for falsework and formwork, and the
submission of certificates for the proper construction thereof, all in accordance with the official specifications of such authority.
After having constructed the falsework and formwork, and prior to placing the reinforcing steel and/or the concrete, the Contractor shall inspect
the falsework and formwork. Dimensions shall be checked, unevenness of surface shall be corrected, and special attention paid to the
adequacy and tightness of all bolts, ties and bracings as well as to the soundness of the foundations.
The Contractor shall give the Engineer at least 24 hours' notice of his intention to place the concrete to enable the Engineer to inspect all
aspects of the completed work. However, before notifying the Engineer, the Contractor shall satisfy himself that the work complies in all
respects with the specifications.
Concrete sections with dimension of smaller than 200 mm shall not be formed with sliding formwork unless authorised by the Engineer.
Where no provision has been made in the schedule of quantities for sliding formwork, the Contractor may, in a covering letter to the tender,
submit a lump sum which reflects a saving in the cost for the use of sliding formwork in lieu of conventional formwork. The tendered lump sum
quoted shall be accompanied by rates for pay items C13.2.7, C13.2.8, C13.2.9 and C13.3.3 all in accordance with the measurement and
payment Clauses. Such submission shall be regarded as an alternative tender for the purposes of tender evaluation, and shall in every respect
comply with the provisions of Clause A13.2.4.
The Contractor shall at all times during the supply and erection of falsework and formwork assure that safety standards and requirements as
prescribed in the Regulations are adhered to.
A13.2.4.2 Falsework
The Contractor shall submit his design criteria and detailed drawings of the falsework to the Engineer. The design, signing of the drawings and
inspection of the falsework prior to construction of the permanent works shall be undertaken by the Contractor’s ECSA Registered Professional
Engineer or Technologist falsework designer.
The Contractor shall make his own assessment of the allowable bearing pressure on the foundation material and shall design the footings and
falsework to prevent overloading, differential settlement and unacceptable overall settlement and safety. In assessing the allowable bearing
pressure, due account shall be taken of the effect of wetting on the foundation material.
The Contractor’s falsework designer shall take account of the location of the structure and the possible ingress of water from sources such as
watercourses, water table and saturation due to rainfall and assess the resulting effects on bearing capacity
In designing the falsework, cognizance shall also be taken of the redistribution of load which may occur on account of the effect of temperature,
wind force, the prestressing of curved and skewed structures, stage construction, flooding and debris.
Cognizance shall also be taken of the lateral forces which may be induced by earth platforms, required for the support of falsework on the
substructures resulting in temporary or permanent stresses for which the sub-structures have not been designed.
Particular attention shall be given to providing transverse and diagonal bracing as well as rib stiffeners on cross bearers.
A13.2.4.3 Formwork
a) General
Formwork shall be so designed as to be sufficiently rigid to ensure that the specified dimensional tolerances can be achieved under the
combined action of self-weight, dead load and imposed loads as well as the additional loads resulting from the rate of concreting, the layer
thickness of the concrete cast in one operation and the method of placing and compaction.
b) Sliding formwork
The Contractor shall be responsible for the design of sliding formwork, if any is intended to be used. Prior to fabrication or bringing the sliding
formwork and any additional equipment to the site, the Contractor shall submit drawings of the complete sliding- formwork assembly to the
Engineer for approval. The drawings shall show full details of the forms, jacking frames, access ladders, hanging platforms, safety rails and
curing skirts as well as details of the jacks and jack layouts.
The Contractor shall be required to submit to the Engineer, before slide casting commences, an instruction manual in which the sliding
techniques, jacking procedure, methods of keeping the formwork level, the procedure to be adopted to prevent bonding of the concrete to the
forms and a method for releasing the forms in the event of bonding, the instrumentation and monitoring of the slide casting and correcting for
verticality, twisting and levelness are described in detail. The manual shall also include detail procedures for corrective actions to be
implemented in the event that any problem that might conceivably occur, actually manifests.
The formwork panels shall be inclined to give a small taper, the forms being slightly wider at the bottom than at the top.
The taper shall be so designed as to produce the specified concrete thickness at the mid-lift level of the form.
The spacing of the jacks with their jack rods shall be so designed that the dead load of the sliding-formwork assembly, the frictional load, and the
mass of materials, personnel and equipment will be evenly distributed and within the design capacity of the jacks used.
A13.2.5.2 Falsework
The timber, structural steel and scaffolding used shall be free from defects that may prejudice the stability of the falsework. The jacks, devices,
clamps and fittings shall all be in a good working order and of adequate design and strength.
A13.2.5.3 Formwork
a) Tongue-and-groove boarding
Tongue-and-groove boarding shall be of suitably dried timber which will not warp, distort or cause discolouration of the concrete. The widths of
the boards shall be as specified on the drawings or in the schedule of quantities or as prescribed by the Engineer. Boards shall be supplied in
lengths not shorter than 3,0 m.
b) Steel forms to exposed surfaces
For classes F2 and F3 surface finish the individual panels shall be assembled sufficiently rigidly and so clamped as not to deform or kick during
handling or under the pressure of the wet concrete.
The surfaces of forms which are to be in contact with the concrete shall be clean, free from deposits or adhering matter, ridges or spatter which
will impart irregularities and blemishes to the concrete surface, and shall also be free from indentations and warps.
The thickness of the steel forms shall be adequate to support the forces applied by the wet concrete but shall not be less than 2,5 mm.
c) Void formers
Void formers used in permanent work shall be subject to the approval of the Engineer.
Where void formers of a special design are required, details thereof shall be specified.
Void formers shall always be tied down to the falsework using mild steel anchor ties with minimum characteristic yield strength of 250 MPa.
Void formers shall be manufactured from material which will not leak, tear or be damaged during the course of construction and shall be of such
tight construction as to prevent undue loss of the mortar component of the concrete through leakage. The units shall be sufficiently rigid so as
not to deform during handling or under the pressure of the wet concrete.
For mild-steel spiral-lock-formed void formers, the metal thickness, unless otherwise specified shall be as follows:
(i) Unbraced void formers
1,0 mm for diameters of up to 600 mm
(ii) Braced void formers
1,2 mm for diameters from 600 mm to 1 000 mm
1,6 mm for diameters exceeding 1 000 mm.
The thickness specified for braced void formers shall apply to formers internally braced with timber or equivalent braces. The
braces shall be at spacings not exceeding 1,5 m and not further than 1,0 m from the end of each unit. Timber cross braces shall
consist of members with cross sectional dimensions of at least 50 mm x 50 mm. The cross bracing shall be vertical and horizontal
and have longitudinal walers attached to ends of the bracing of the same cross sectional dimensions.
All hollow void-former units shall be provided with a 12 mm diameter drainage hole at each end.
d) Chamfer and recess fillets
Timber fillets used for forming chamfers and recesses on exposed surfaces shall be made from new suitable material unless otherwise
approved by the Engineer.
e) Jack rods for sliding formwork
The jack rods, base plates and couplers shall be strong enough to carry the design load under all operating conditions without buckling,
distorting or causing damage to the concrete. Jack rods which are to remain permanently embedded in the concrete shall comply with the
requirements of Clauses A13.3.7 and A13.3.8. Under no circumstances shall bent rods be used in the work.
The jack rods used shall have a diameter of at least 25 mm.
A13.2.7.2 Formwork
a) General
The formwork for concrete work including bridge decks shall be erected to levels calculated from the information given on the drawings for
roadworks and bridges. The levels shall be adapted to make provision for the specified precamber as well as for the expected deflection and
settlement of the fully loaded falsework and formwork. The levels shall be set out and checked at intervals not exceeding 2,50 m, to assure
compliance with specified construction tolerances of the completed work.
For constructing the formwork, the Contractor may, subject to the provisions of Clause A13.2.5, use any material suitable for and compatible
with the class of surface finish and dimensional tolerances specified for the particular member (unless specific type of formwork has been
prescribed in the Contract Documentation).
Formwork shall be sufficiently rigid to maintain the forms in their correct position, shape and profile and shall be of such tight construction that
the concrete can be placed and compacted without undue loss or leakage of the mortar component of the concrete.
The joints between contiguous formwork elements shall be of a tight fit and, where necessary, the joints shall be caulked, taped or packed with a
sealing gasket, all at no extra payment if undue leakage occurs or can be expected. Paper, cloth or similar material shall not be used for this
purpose.
The formwork construction shall permit accurate erection and easy stripping without shock, disturbance or damage to the cast concrete. Where
necessary, the formwork assembly shall permit the removal or release of side forms Independently of the soffit forms.
Metal supports, ties, hangers and accessories embedded in the concrete shall be removed to a depth of not less than the cover specified for the
reinforcement. No wire ties shall be used.
All external corners shall be chamfered by fillet strips being fixed into the corners of the formwork to form 25 mm x 25 mm chamfers, or such
other dimensions as may be specified on the drawings. Re-entrant angles need not be chamfered unless specified.
Where polystyrene or similar material, susceptible to damage is used, it shall be lined with a hard surface on the side to be concreted. The hard
material shall be sufficiently resilient to ensure that the required quality of work can be achieved.
Where it is specified, all formwork ties shall be provided with recoverable truncated cones between sleeve ends and formwork faces to ensure
that sleeve ends are not exposed on concrete surfaces. The cones shall have a minimum depth of 50 mm.
All ferule and tie holes shall be filled using a mortar compatible with the concrete in strength and colour.
The formwork and boards shall be so arranged as to form a uniform and regular pattern in line with and perpendicular to the main axis of the
member, unless otherwise approved or directed by the Engineer.
Joints between contiguous members shall, after caulking, taping or sealing, be treated to prevent blemishes, stains and undue marks from being
imparted to the concrete surface.
Bolt and tie positions shall be neatly arranged so that they conform to the symmetry of the formwork panels or boards. Bolt and rivet heads
which will be in contact with the formed surface shall be of the countersunk type and shall be treated to prevent marks from forming on the
concrete surface.
The formwork at construction joints shall be braced to prevent steps from forming in the concrete surfaces at the joints between successive
stages of construction.
The formwork at construction joints shall have moulding strips 25 mm x 25 mm neatly butted and set at the position of the construction joint.
Where moulding or recess strips are specified, they shall be neatly butted or mitred.
(i) Protecting the surfaces
The Contractor shall ensure that permanently exposed concrete surfaces are protected from rust marks, spillage and stains of all
kinds and other damage during construction.
b) Formed surfaces: Classes of finish
(i) General
In addition to complying with the tolerances specified in Clause A13.2.8, the surface finish on formed concrete surfaces shall also
comply with the following requirements:
1. Class F1 surface finish
After repair work has been done to surface defects in accordance with Clause A13.2.7.4, no further treatment of the as-stripped finish will
be required. This finish is required on concealed formed surfaces.
2. Class F2 surface finish
This finish shall be equivalent to that obtained from the use of square-edged timber panels and boards wrought to the correct thickness, or
shutter boards or steel forms arranged in a regular pattern. This finish is intended to be left as struck but surface defects shall be remedied
in accordance with Clause A13.2.7.4. Although minor surface blemishes and slight discolourations will be permitted, large blemishes and
(ii) The stripping time for vertical formwork and unloaded columns shall be the greater of the values derived from consideration of the strength
required to:
1. withstand wind loading,
2. the stripping time to avoid early thermal contraction cracking,
3. a minimum in situ concrete strength of 4 MPa
(iii) The stripping time, or minimum strength requirements, for continuously reinforced concrete structures and in particular where a structure is
constructed in stages, for formwork and falsework removal shall be calculated from the last concrete pour and shall be specified on the
drawings and authorised by the Engineer.
(iv) The stripping time, or minimum strength requirements, for all prestressed concrete structures, for formwork and falsework removal shall be
calculated from the last concrete pour and shall only be considered after the full prestressing force relating to the particular stage of
construction has been applied and shall be, submitted to the Engineer for approval and verified by the Engineer as acceptable.
c) Strength estimation
The in situ concrete strength may be determined by the following methods:
(i) Compressive strength test on temperature-matched cubes,
(ii) Compressive strength test on cubes stored and cured under the same conditions as the structural member,
(iii) In situ maturity measurements in accordance with ASTM C1074.
Specialist literature such as the CIRIA Report 136 should be consulted where necessary.
A13.2.8 WORKMANSHIP
A13.2.8.1 Tolerances
For the assessment of acceptance and compliance the tolerances given below shall be the maximum permissible deviations from the
specified dimensions, levels, alignment, positions, etc., shown on the drawings of the structures or structural members.
Surface regularity:
d) Precast beams
The following tolerances shall apply to precast beams in addition to the requirements stated in Clause A13.2.8.1c) for the superstructure.
The width of the gap between contiguous beams shall not exceed twice the width of the specified nominal gap shown on the drawings or the
width of the nominal gap plus 40 mm, whichever is the lesser, and the overall width between the outermost beams of the bridge deck shall be
within 40 mm of the specified width.
Straightness or bow: The deviation from the prescribed line measured on the overall length of the beam shall not exceed the following:
(i) In the horizontal plane:
0,5 mm per metre length of the beam within the tolerance range of 6,0 mm to 15 mm.
(ii) In the vertical plane:
(1) I-beams: 2,0 mm per metre length of the beam within the tolerance range of 6, 0 mm t o 20 mm.
(2) Other beams: 1,0 mm per metre length of the beam within the tolerance range of 3,0 mm to 20 mm.
Camber: The soffits of adjacent beams when placed side by side on the bridge deck shall not at any place differ by more than 2,0 mm per
metre length of the beam within the tolerance range of 6,0 mm to 20 mm
The lengths of precast beams before stressing shall be ± 0 , 1 % o f the total length within the tolerance range of ± 5,0 mm to ± 20
mm.
Surfacing regularity................................................................................................................................................................... 3,0 mm
e) Miscellaneous
(i) Chamfers
Fillets used for forming chamfers shall be within a tolerance of 2,0 mm in cross-sectional dimensions, and the actual chamfer
on the concrete shall not vary by more than 3,0 mm from the specified dimensions.
(ii) Barriers, parapets, railings, footwalks, kerbs and copings etc.
The members shall be constructed within a tolerance ± 5,0 mm for all dimensions. The alignment shall not deviate from the true
alignment by more than 10 mm in any place, nor shall the alignment deviate by more than 5,0 mm from the true alignment over
any length of 5,0 m.
Notwithstanding the above the levels on the above elements shall be fitted to give a smooth, aesthetic vertical alignment.
CONTENTS
B13.2.1 SCOPE
B13.2.2 DEFINITIONS
B13.2.3 GENERAL
B13.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.2.5 MATERIALS
B13.2.6 CONSTRUCTION EQUIPMENT
B13.2.7 EXECUTION OF THE WORKS
B13.2.8 WORKMANSHIP
B13.2.1 SCOPE
This Section covers the design, supply and erection of all falsework and formwork used in the construction of permanent work. This Section also
describes the classes of surface finishes on formed and unformed concrete surfaces. Most of the activities are executed by labour at various
skill levels, therefore the specifications derived in Part A can be deemed suitable for labour enhanced work.
B13.2.2 DEFINITIONS
The provisions of Part A shall apply.
B13.2.3 GENERAL
The provisions of Part A shall apply.
B13.2.5 MATERIALS
The provisions of Part A shall apply.
B13.2.8 WORKMANSHIP
The provisions of Part A shall apply.
The unit of measurement shall be the square metre, and only the actual area of formwork in contact with the finished face of the concrete shall
be measured. Formwork for the different classes of finish shall be measured separately. Formwork for construction joints shall be measured for
payment under class F1 surface finish, but only formwork for mandatory construction joints shall be measured for payment.
The tendered rates shall include full compensation for procuring and furnishing all materials required, erecting the falsework and formwork,
constructing the forms, forming the grooves, fillets. chamfers up to 100 mm and stop-ends for construction joints, treating and preparing the
forms, all bolts, nuts, ties, struts and stays, stripping and removing the formwork after completion of the work, all labour, equipment and
incidentals, and rubbing and surface treatment. Payment of 80 % of the amount due for formwork will be made when the formwork has been
removed, and payment of the remaining 20 % will be made on approval of the concrete surface finish.
C13.2.5.2 Of (description of material and member to which applicable) square metre (m2)
The unit of measurement shall be the square metre of concrete area formed with permanent formwork.
The tendered rates shall include full compensation for procuring and furnishing all the materials required, installing the formwork, and labour,
equipment and incidentials.
The tendered rates shall include for the installation of permanent drainage holes within the void formers at the low points of each void.
C13.2.6 Formwork to form open joints (description of member to which applicable, and location) square metre (m2)
The unit of measurement shall be the square metre of concrete area formed
Surfaces formed prior to the construction of the final surface for completing the joint, shall be measured under Items C13.2.1, C13.2.2, C13.2.3
or C13.2.4, as may be applicable.
The tendered rate shall include full compensation for procuring and furnishing all the materials required, constructing the formwork and
subsequently removing all the material within the joint space, as well as labour, equipment and Incidentals. Payment for formwork to open joints
shall be made only after the forms and filler material have been completely removed and approval of the surface finish has been obtained.
C13.2.7 Establishment on the site for sliding formwork operations lump sum
The tendered lump sum shall include full compensation for the establishment on the site and the subsequent removal of the complete sliding-
formwork assembly, special plant and equipment, and incidentals for the sliding work, the cost of which does not vary with the actual amount of
sliding work done.
This work will be paid for by way of a lump sum, 75 % of which will become payable when the manual is approved, sliding-formwork assembly,
plant and equipment have been fully Installed and commissioned at the first structural member on the site, and the remaining 25 % will become
payable after all sliding work has been completed and the said items have been removed from the site.
The unit of measurement shall be the number of following similar structures to which the complete sliding-formwork assembly has to be
transported and re-erected in position ready to be commissioned, after successful completion of the first structure.
The tendered rate shall include full compensation for all costs involved in dismantling, transporting and re-erecting of the complete sliding-
formwork assembly.
The unit of measurement shall be the metre height of each structure formed by sliding formwork. The quantity measured shall be the actual
height of each structure formed by the sliding technique.
The tendered rate shall include full compensation for sliding, instrumentation and monitoring, the maintenance of the complete sliding-formwork
assembly, plant and equipment, supplying, installing and recovering the jack rods, floating, repairing and treating the concrete surfaces, forming
the emergency construction joints, and all labour, equipment and Incidentals.
C13.2.10 Provision of designs and drawings of falsework and formwork by an ECSA registered lump sum
Professional Engineer or Technologist (description of member to which applicable)
The unit of measurement shall be the lump sum and shall be paid in two payments of 50 % on submission of the falsework and formwork
designs and the second 50 % on complete removal of all the falsework.
The tendered rates shall include full compensation for procuring and provision of all drawings for the falsework and formwork designs by an
ECSA registered professional, including inspections, supervision where applicable, all labour, material, travelling and incidentals, and the signing
off on the erection of the falsework and formwork including submission of all certificates as specified.
CONTENTS
D13.2.1 SCOPE
D13.2.2 GENERAL
D13.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.1.5 VISUALLY ASSESSED PROPERTIES
D13.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.1.7 EVALUATION FOR ACCEPTANCE
D13.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.1.9 NOTIFICATION OF REMEDIAL WORK
D13.1.10 REMEDIAL WORK
D13.2.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part C only but includes all of the requirements in the
Contract Documentation.
D13.2.2 GENERAL
D13.2.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for the following, if required for the execution of the work as specified:
a. Steel falsework members.
b. Timber falsework members.
c. Jacks, devices, clamps and fittings.
d. Steel and Timber formwork.
e. Material in permanent Void formers.
A13.3.2 DEFINITIONS
Cover - shall mean the minimum thickness of concrete between the surface of the outermost reinforcement and the face of the concrete.
A13.3.3 GENERAL
A13.3.3.1 Method Statements
The method statements and typical drawings submitted by the Contractor with his tender submission, describing key facets such as method, key
plant, materials, personnel and programme constraints of the envisaged construction process, shall form the basis for the detailed method
statements required for the works to be executed on the project.
These method statements shall be prepared and submitted to the Engineer for approval for each facet of the work at the start of construction,
within time scales specified. The onus lies with the Contractor to ensure that the information is gathered and associated activities are completed
expeditiously so as to avoid any delays in the commencement, continuation and completion of the required works. Unless otherwise specified or
provided for in the Contract Documentation no permanent works shall be commenced until the Engineer’s approval has been obtained. Due
allowance shall be made for obtaining alternative materials, resubmissions and redesigns, all to the required/approved standards, methods and
practices in attending to these requirements. Particular attention shall be paid to the early submission of materials-, concrete- and grout mix
designs where parameters at various ages may be specified. No consideration for extension of the contract period will be entertained for delays
incurred in meeting these requirements.
Trials, if applicable, shall be conducted and based on outcomes thereof, may require that changes be made to the relevant method statements.
Once approved in writing by the Engineer, these shall become the method statements in accordance whereby the relevant portion of the works
shall henceforth be executed. Notwithstanding, the Engineer may require revision from time to time if circumstances during construction arise
which warrants change.
The Contractor shall, however, remain responsible for all work-methods, materials, plant and equipment used, notwithstanding acceptance by
the Engineer.
A13.3.5 MATERIALS
A13.3.5.1 Steel bars
Steel reinforcing bars shall comply with the requirements of SANS 920. For each consignment of steel reinforcement delivered on the site, the
Contractor shall submit a certificate issued by a recognised testing authority to confirm that the steel complies with the specified requirements.
Cold-worked reinforcing bars shall not be used.
The type of bar required shall be indicated on the drawings by the symbols R, Y or Z in accordance with SANS 282.
A13.3.8 WORKMANSHIP
A13.3.8.1 Surface condition
When the concrete is placed around the reinforcing steel, the reinforcing steel shall be clean, free from mud, oil, grease, paint, loose rust, loose
mill scale or any other substance which could have an adverse chemical effect on the steel or concrete, or which could reduce the bond.
A13.3.8.2 Welding
Reinforcement shall be welded only where shown on the drawings or as authorised.
All welding shall be done in a controlled environment.
Flash butt welding shall be done only with the combination of flashing, heating, upsetting and annealing to the satisfaction of the Engineer, and
only those machines which control this cycle of operations automatically shall be used.
Metal-arc welding of reinforcement shall be done in accordance with BS EN 1011, and with the recommendations of the reinforcement
manufacturers, subject to approval by the Engineer and the satisfactory performance of trial joints. Hot-rolled high-yield-stress steel shall be
preheated to between 240C and 280C and low-hydrogen electrodes only may be used.
Trial welding joints shall be made on the site in circumstances similar to those which will govern during the making of production welding joints
by the person who will be responsible for the production welding joints.
Other methods of welding e.g. resistance welding, may be used subject to approval by the Engineer and to their satisfactory performance in trial
joints.
Welded joints shall be full-strength welds and their strength shall be assessed by destruction tests on samples selected by the Engineer.
A13.3.8.4 Tolerances
In addition to the requirements given below, the reinforcing steel shall be neatly and accurately fixed in a manner which is consistent with proper
workmanship and the structural integrity of the structural member.
Specifically the following requirements shall apply:
a) Tension steel
The actual position of tension steel shall not deviate from the true position by a distance which would reduce the effective lever arm by more
than 2 % of the overall depth of the member, or 10 mm, whichever is the greater.
b) Concrete cover
The concrete cover on reinforcing steel shall nowhere be less than the specified cover, reduced by the tolerance given in Clause A13.4.8.1a)(iv).
c) Spacing between bars
The spacing between closely spaced parallel bars, especially in beams and columns, shall, unless otherwise specified, be not less than the
maximum size of the aggregate used in the concrete plus 5,0 mm.
CONTENTS
B13.3.1 SCOPE
B13.3.2 DEFINITIONS
B13.3.3 GENERAL
B13.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.3.5 MATERIALS
B13.3.6 CONSTRUCTION EQUIPMENT
B13.3.7 EXECUTION OF THE WORKS
B13.3.8 WORKMANSHIP
B13.3.1 SCOPE
This Section covers the furnishing and placing of reinforcing steel in concrete structures. This is deemed to be ideally suited for labour
enhanced work at varying skills level, therefore provisions provided in Part A, shall apply
B13.3.2 DEFINITIONS
The provisions of Part A shall apply.
B13.3.3 GENERAL
The provisions of Part A shall apply.
B13.3.5 MATERIALS
The provisions of Part A shall apply.
B13.3.8 WORKMANSHIP
The provisions of Part A shall apply.
C13.3.2 Mechanical couplers (type of coupler and diameter of bar indicated) number (No)
The unit of measurement shall be the number of mechanical couplers for each bar diameter installed.
The tendered rate shall include full compensation for supplying all the material, preparing and modifying the bar ends to be joined, and all tools,
equipment and labour required for completing the work.
C13.3.3 Spacer ladders for (description of part of structure to which applicable) ton (t)
The unit of measurement for spacer ladders shall be the ton of steel in place in accordance with the drawings or as authorised.
The tendered rate shall include full compensation for supplying, delivering, cutting, bending, welding, placing and fixing the ladders, including all tying
wire, spacers and waste.
C13.3.4 Extra-over item C13.3.1 (a), (b), etc. for galvanising of reinforcement ton (t)
The unit of measurement shall be the ton of reinforcing steel hot-dip galvanised with an 85 micrometre coating in accordance with the detail on the
drawings, SANS 121 and Clause A13.9.7.1m).
The tendered rate shall include full compensation for all materials, labour, tools and equipment required to galvanise the specific bars of
reinforcement as required as well as transporting and handling costs.
CONTENTS
D13.3.1 SCOPE
D13.3.2 GENERAL
D13.3.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.3.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.3.5 VISUALLY ASSESSED PROPERTIES
D13.3.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.3.7 EVALUATION FOR ACCEPTANCE
D13.3.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.3.9 NOTIFICATION OF REMEDIAL WORK
D13.3.10 REMEDIAL WORK
D13.3.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part C only but includes all of the requirements in the
Contract Documentation.
D13.3.2 GENERAL
D13.3.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for:
(a) Steel reinforcement: each type and batch;
(b) Galvanising of steel reinforcement
(c) Welding of reinforcement, where relevant; and
(d) Mechanical couplers.
(e) Stainless Steel.
(f) Other special materials.
CONTENTS
PART A: SPECIFICATIONS
A13.4.1 SCOPE
A13.4.2 DEFINITIONS
A13.4.3 GENERAL
A13.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.4.5 MATERIALS
A13.4.6 CONSTRUCTION EQUIPMENT
A13.4.7 EXECUTION OF THE WORKS
A13.4.8 WORKMANSHIP
A13.4 CONCRETE
PART A: SPECIFICATIONS
A13.4.1 SCOPE
This Section covers the supply and storage or stockpile of all materials, manufacture, transport, placing, finishing, curing, protection and testing
concrete in bridges, culverts and miscellaneous structures. The completed concrete elements shall conform to the lines, grades, and
dimensions shown on the drawings and as specified in Section A13.2. The work includes elements of structures constructed by cast-in-place
and precast methods using either plain (unreinforced), reinforced, or prestressed concrete or any combination thereof.
A13.4.2 DEFINITIONS
Characteristic strength - characteristic strength of concrete is the compressive cylinder or cube strength below which no more than 5 % of the
test results in a statistical population shall fall, tested as specified in Section A20.1 and applicable Clauses of Chapter 20.
Environment - the physical and chemical actions to which the concrete is exposed and which results in effects on the concrete or reinforcement
that are not considered as loads in structural design.
Fresh phase of concrete - concrete that has been fully mixed, that has not yet reached initial set and is still capable of being compacted by the
chosen method.
Hardened phase of concrete - concrete in a solid state and which has developed a certain amount of strength.
Normal-Weight Concrete - concrete in the oven –dry state having a density greater than 2000 kg per cubic metre but not exceeding 2600 kg
per cubic metre, determined in accordance with SANS 3001-C02-8.
Self-compacting concrete - concrete that is able to flow and compact under its own weight, fill the formwork with its reinforcement, ducts, etc.,
while remaining homogeneous.
Valid test result (Fcu) - a valid test result, for the purpose of evaluating compressive strength, shall comprise of the arithmetic mean of three
cube or cylinder specimens where the difference between the highest and lowest result does not exceed 15 % of the arithmetic mean of the
specimens.
Water: cementitious binder ratio - the ratio of the total water content to total cementitious binder content by mass in the mixed concrete.
A13.4.3 GENERAL
This section describes work that encompasses the design, production and placing of concrete conforming to the set of performance criteria in
both the fresh and hardened phases. Irrespective of the originating concrete supply and production source, for example commercially-sourced
ready mixed concrete or precast concrete, the Contractor shall ensure the full conformance to all aspects of this specification.
A13.4.5 MATERIALS
A13.4.5.1 Cementitious binder
The cementitious binder shall comprise either cement, complying with SANS 50197-1, or an approved site blend of such cement and
supplementary cementitious materials that take appropriate cognizance of environmental conditions, durability and strength requirements of the
structural member. The site blending of cement with supplementary cementitious materials shall only be conducted on the basis of an
acceptable quality assurance system approved by the Engineer. Further limitations of the cementitious binder for prestressed concrete
members or units shall be strictly enforced. The cementitious binder shall comprise the following:
a) Cement
Cement shall comply with SANS 50197-1 (EN 197-1) with a strength class of 32,5 or greater, and a rate of strength gain N or greater. Cement
shall hold valid certification in the form of a Letter of Authority issued as certified approval pursuant to the Compulsory Specification for cement
published by Government Notice R.544. Masonry cement shall not be used.
In order to promote resource sustainability principles, cement shall have a maximum average carbon dioxide emission value of 925 kg CO2e
per ton, determined in accordance with the World Business Council for Sustainable Development Greenhouse Gas Protocol.
b) Supplementary cementitious materials
Additional supplementary cementitious materials may be added at the batchplant and used to replace specific proportions of the cementitious
binder. The maximum supplementary cementitious material replacement values shall be cumulative, comprising proportions both pre-blended
into the cement and supplementary cementitious materials added at the batchplant. The further blending of cements that contain a factory-
blended proportion of supplementary cementitious materials exceeding 5 % by mass of cement, except in the particular case of limestone, with
supplementary cementitious materials of a different generic type or nature, e.g. site-based ternary blending, shall not be permitted. The site
blending of CEM III/B, CEM III/C, CEM IV/B and CEM V cements with supplementary cementitious materials shall not be permitted.
Supplementary cementitious materials added at the site batchplant shall be classified and conform to the following requirements:
(i) Ground granulated blastfurnace slag or ground granulated corex slag, conforming to SANS 55167-1, up to maximum cumulative
replacement value of 65 % by mass of cementitious binder;
(ii) Fly ash, conforming to SANS 50450-1, up to maximum cumulative replacement value of 40 % by mass of cementitious binder;
A13.4.5.2 Aggregates
All aggregates for concrete shall fully comply with the requirements of SANS 1083, subject to the following amendments and additional project
requirements:
a) Coarse aggregates
(i) The flakiness index of the coarse aggregate as determined by SANS 3001-AG4 shall not exceed 35;
(ii) The 10 % FACT value as determined by SANS 3001-AG10 shall be minimum 150 kN when tested dry or minimum 110 kN when tested
wet;
(iii) Alternatively to the 10 % FACT and if required by the Contract Documentation, the aggregate crushing value as determined by
SANS 3001-AG10 shall be maximum 25 % by mass; and
(iv) The soundness of mudrock, shale, basalt and dolomitic aggregates as determined in accordance with SANS 3001-AG13 shall have
maximum 15 % mass loss where magnesium sulfate is used.
b) Fine aggregates
(i) The fineness modulus of the fine aggregate as determined by SANS 3001-PR5 shall not vary by more than ± 0,2 from the approved
modulus;
(ii) The sand equivalent of the fine aggregate shall be determined in accordance with SANS 3001-AG5 and shall be minimum 65 %. The
sand equivalent shall be considered as an indicator test, together with the clay content and methylene blue absorption value, where
non-compliance may be established. However the satisfactory performance in concrete shall be evaluated by drying-shrinkage tests in
accordance with Clause A13.4.5.2c)(i); and
(iii) Tests for organic impurities in natural sands shall be determined in accordance with SANS 5832 and shall be not darker than the
reference solution.
c) Additional project requirements
(i) The drying-shrinkage of both the fine and coarse aggregate, when either is obtained from the Karoo Series or from newly developed
sources, shall be tested in accordance with SANS-AG-33 (SANS 5836) shall not exceed the following limits:
1. For use in prestressed concrete, concrete bridge decks and slender columns the shrinkage of both fine and coarse aggregate shall
not exceed 150 % of that of the reference aggregates;
2. For use in other reinforced concrete members the shrinkage of the fine aggregate shall not exceed 200 %, and of the coarse
aggregate 175 %, of that of the reference aggregates; and
3. For use in mass concrete substructures and unreinforced concrete head walls and wing walls, the shrinkage of both the fine and
coarse aggregate shall not exceed 235 % of that of the reference aggregates.
(ii) Aggregates shall not contain any deleterious amounts of organic materials such as grass, timber or similar materials, as assessed by
visual inspection;
(iii) Where instructed by the Engineer, aggregates shall be checked and shall be free of the following deleterious substances:
1. Tests for the presence of sugar shall be determined in accordance with SANS 3001-AG-30 (SANS 5833) and shall be free from the
presence of sugar;
2. Tests for soluble deleterious impurities shall be conducted in accordance with SANS 3001-AG-31 (SANS 5834) and shall have
minimum compressive strength of 85 % of the reference;
3. Test for the presence of material of low density shall be determined in accordance with SANS 5837 and shall have maximum 0,5
% by mass;
4. Tests for soluble salts shall be determined in accordance with SANS 3001-AG-40 (SANS 5849) and shall have maximum 0,5 % by
mass;
5. Tests for water soluble sulfates shall be determined in accordance with SANS 3001-AG-31 (SANS 5850-1) and shall have
maximum 0,2 % SO3 by mass; and
6. Tests for the presence of shell shall be determined in accordance with SANS 3001-AG-35 (SANS 5840) and shall be maximum
5 % by mass of unbroken shell, or maximum 25 % by mass of broken shell fragments, in the coarse aggregate.
(iv) Where there is any danger of a particular combination of aggregate and cementitious binder giving rise to a harmful alkali-aggregate
reaction, the particular combination shall be tested in accordance with SANS 6245 as described in Clause A13.4.7.2a), and where the
result points to such reaction, either the aggregate or the cementitious binder or both shall be replaced so that an acceptable
combination may be obtained; and
(v) Where aggregate size of larger than 28 mm is used in concrete, the aggregate shall be supplied in two nominal sizes, and the smaller
shall be either 20 mm or 14 mm. The relative proportions of larger and smaller nominal sized aggregate shall be determined by the mix
design.
A13.4.5.3 Water
The Contractor shall prove by way of laboratory tests that all water used for mixing and curing concrete complies with SANS 51008.
A13.4.5.4 Admixtures
The use of admixtures is encouraged to produce durable concrete and to achieve particular fresh phase properties of concrete. All admixtures
for concrete shall comply with the requirements of SANS 50934 (EN 934), ASTM C494 or AASHTO M194. Admixtures shall be of a brand
approved by the Engineer and type compatible with the exposure environment and cementitious binder composition. Admixtures shall have no
deleterious effects on the reinforcement, prestressing or concrete, and shall not contain any chlorides, nitrates, sulphides or sulphites, which
may be detrimental to the reinforcement. Admixtures shall generally be supplied in liquid form and accurately dispensed by a mechanical
dosing unit in a manner appropriate to the method batching e.g. dry versus wet batching. Unless extraordinary circumstances dictate
otherwise, under no circumstances shall a mixture be dispensed on to mix components. Where extraordinary circumstances do exist, other
methods of feeding into the concrete mixture shall be agreed with the Engineer. Where specified, air entraining agents may alternatively comply
with the requirements of SANS 50934 (EN 934), ASTM C260 or AASHTO M154.
Where combinations of two or more admixtures are utilised, they shall be tested for compatibility.
The total amount of admixtures shall not exceed the maximum dosage recommended by the admixture producer and also shall not exceed 5 %
by mass of the total cementitious binder, unless the influence of the higher dosage of admixture on the performance and durability of the
concrete is established and taken into account.
If the total quantity of liquid admixture equals or exceeds 3 litres per cubic metre of concrete, the admixture quantity shall be included in the
water content of the concrete mixture when calculating the water: cementitious binder ratio.
The alkali content (Na2O-equivalent) of all admixtures shall form part of the calculation of the alkali content of concrete in order to limit the
degree of reactivity as specified in Clause A13.4.7.2a).
A13.4.5.6 Fibres
Steel fibres for concrete shall comply with EN 14889-1 or ASTM A820 and polymer fibres shall comply with EN 14889-2 or ASTM D7508. Fibres
shall be submitted to the Engineer for approval prior to the commencement of work.
Specialist literature, such as BRE Special Digest 1: ‘Concrete in aggressive ground’, should be consulted where sulfate-bearing water,
aggressive groundwater, aggressive chemical environments or aggressive environments not classified in Table A13.4.7-2 are encountered.
Class D concrete mix shall meet the following criteria:
(i) the specified 28-day characteristic cylinder or cube compressive strength;
(ii) the specified 28-day nominal oxygen permeability index;
(iii) the specified 28-day nominal chloride conductivity value; or
(iv) a characteristic 28-day cylinder or cube compressive strength corresponding to the maximum water: cementitious binder ratio for
chloride (XS) environments.
Durable concrete for environments where corrosion induced by carbonation presents the governing risk, the desirable properties shall conform
to Table A13.4.7-3 for 100 year service life.
Table A13.4.7-3: Nominal Durability Index and cover values for 100 year service life in typical carbonating environments
Environmental Cover (mm), OPI (log
class as specified scale)
For 100 year service life
XC1a, and 40 9,15
XC1b 50 9,00
60 9,00
XC2 40 9,40
50 9,10
60 9,00
XC3 40 9,65
50 9,35
60 9,05
XC4 40 9,85
50 9,55
60 9,30
Where the degree of compaction is the desirable measure of consistence, the compacting factor shall be determined in accordance with
SANS 3001-CO1-5 (EN 12350-4).
Table A13.4.7-7: Degree of compaction classes and values
Compaction factor determined in
Consistence Class accordance with SANS 3001-CO1-5
(EN 12350-4)
ZA-C1 0,80 or less
ZA-C2 0,81 to 0,89
ZA-C3 0,90 or greater
Where slump may exceed 150 mm and flow is the desirable measure of consistence, flow shall be conducted in accordance with SANS 3001-
CO1-6.
Table A13.4.7-8: Flow classes and values
Flow diameter (mm) determined in
Consistence Class
accordance with SANS 3001-CO1-6
ZA-F1 500 to 545
ZA-F2 550 to 595
ZA-F3 600 to 650
Where high workability concrete is used and the slump flow is the desirable measure of consistence, slump flow shall be conducted in
accordance with SANS 3001-CO1-9 (EN 12350-8).
Table A13.4.7-9: Slump flow classes and values
Slump flow diameter (mm)
Consistence Classes determined in accordance with
SANS 3001-CO1-9 (EN 12350-8)
ZA-SF1 550 to 650
ZA-SF2 660 to 750
ZA-SF3 760 to 850
Passing resistance shall be assessed using either the L-box determined in accordance with SANS 3001-CO1-11 (EN 12350-10) or J-ring tests
determined in accordance with SANS 3001-CO1-13 (EN 12350-12).
Sieving segregation resistance shall be determined in accordance with SANS 3001-CO1-12 (EN 12350-11).
Table A13.4.7-14: Sieve segregation resistance classes and values
Segregation portion (percent)
Segregation Resistance Class determined in accordance with
SANS 3001-CO1-12 (EN 12350-11)
ZA-SR1 Maximum 20
ZA-SR2 Maximum 15
For particular uses, it may be necessary to specify the compressive strength at ages earlier or later than 28 days, for example massive structural
elements, or after storage under special conditions, for example heat treatment. In assessing the strength, other sizes of mould and other curing
regimes may be used provided the relationship to those standardised has been established and documented and subject to the approval of the
Engineer.
b) Tensile splitting strength
The tensile splitting strength shall be determined at 28 days in accordance with SANS 3001-CO2-6.
c) Flexural strength
The flexural strength shall be determined from beam specimens prepared in accordance with SANS 3001-CO2-3 and tested at 28 days in
accordance with SANS 3001-CO2-5.
d) Energy absorption capacity of fibre reinforced concrete
The minimum energy absorption capacity shall be specified on the drawings. The energy absorption capacity shall be determined from a slab
specimen, tested at 28 days in accordance with EN 14488-5, save that the fibre reinforced concrete shall be cast into the formwork using
conventional concreting techniques. The energy absorption capacity shall conform to the specified energy adsorption class defined in Table
A13.4.7-16.
Table A13.4.7-16: Energy absorption classes and values
Energy absorption class Energy adsorption for deflection
up to 25mm (J)
E500 500 to 690
E700 700 to 990
E1000 1000 and greater
Compressive strength, determined from 150 mm cube samples, shall be minimum 4,0 MPa at 28 days.
(iv) Batching and mixing
Cement shall be measured by mass or in full bags of 50 kg each and aggregate shall be measured by volumes in approved
measuring boxes or barrows.
The aggregate shall be moist or wetted before the cement is added.
The quantity of water added shall be just sufficient to form a smooth grout which will adhere to, and completely coat, every
particle of aggregate, and which is just wet enough to ensure that, at points of contact of aggregate, the grout will run together
to form a small fillet to bond the aggregate together. The mix shall contain no more than 20 litres of water for every 50 kg of
cement.
Mixing shall be done in an approved batch-type mechanical mixer, but small quantities may be hand mixed.
(v) Placing
No-fines concrete shall be placed in accordance with the procedure approved by the Engineer. If cast in situ, it shall be placed
in its final position, and if precast it shall be placed in the mould, within 30 minutes of mixing.
The no-fines concrete shall be worked sufficiently to ensure that it completely fills the space to be concreted and that adjacent
aggregate particles are in contact with one another. Excessive tamping or ramming shall be avoided and under no
circumstances may the no-fines concrete be vibrated. Due care must be taken to ensure that any geosynthetic filter fabric and
drainage provisions are not contaminated.
The Contractor shall be responsible to ensure the permeability of the no fines concrete. The Engineer may request to
Contractor to demonstrate the permeability of no fines concrete in place and any portion deemed to be of insufficient
permeability shall be broken out and replaced at the Contractor’s expense.
(vi) Curing and surface protection
All no-fines concrete shall be protected from the elements and loss of moisture. Protection against loss of moisture shall be
accomplished in one or more of the following ways:
1) retaining formwork in place;
2) covering exposed surfaces with sacking or other approved absorbent material kept continuously wet; or
3) covering exposed surfaces with plastic sheeting.
No fines placed during cold weather shall be adequately protected against frost for at least 3 days.
g) Construction joints
(i) General
Concreting shall be carried out continuously up to the construction joints shown on the working drawings or as approved by the
Engineer, except that if, because of an emergency, such as breakdown of the mixing plant or the occurrence of adverse
DRAFT STANDARD (DS) OCTOBER 2020 13-61
environmental conditions, concreting has to be interrupted, a construction joint shall be formed at the place of stoppage and in
the manner which will least impair the durability, appearance, and proper functioning of the concrete. If directed by the
Engineer, additional reinforcing steel dowels shall be placed across the emergency construction joint and the additional steel
shall be furnished and placed at the Contractor’s expense.
Unless otherwise shown on the drawings, the exact position of horizontal construction joints shall be marked on the formwork.
The external face, for the specified cover depth, of fresh concrete at horizontal construction joints shall be wood floated
sufficiently to thoroughly compact the surface and to form a neat regular straight line for aesthetic reasons. The remaining
surface of the horizontal construction joint can be rough floated to thoroughly compact the surface prior to preparing the
surfaces for structural bond.
Stub columns, stub walls, kickers and stays on footings shall be cast integrally with the footings and not afterwards, even where
another class of concrete is being used. This concrete shall be well-compacted and no roughening of the cast surface by rakes
or similar devices that disturb the surface while in the fresh phase shall be permitted.
(ii) Preparing the surfaces
When the concrete has set and while it is still green, the surface film and all loose material shall be removed, without disturbing
the aggregate, by means of a water jet assisted by light brushing to expose the aggregate and leave a sound, irregular surface.
Where this is not possible, the surface film shall be removed after the concrete has hardened, by mechanical means
appropriate to the degree of hardness of the concrete so as to expose the aggregate and leave a sound, irregular surface.
Controlled sand blasting or careful scabbling using light chipping hammers are favourable mechanical techniques. The
Contractor shall where sand blasting and or scabbling techniques are used, prepare a trial section for approval to make sure
the concrete joint is correctly formed. The Contractor shall ensure that the green concrete is not damaged or disturbed during
the preparation of the joint and that any water proofing systems, for example waterstops, are not damaged. The resultant
prepared concrete surfaces shall be entirely free of cracks, spalling, damage, laitance, loose debris, concrete slush and any
other form of contamination.
Acid etching techniques shall not be permitted as this may damage the bond line and compromise water tightness of the
structure. Surface retarding agents may be used only with the approval of the Engineer.
The roughened concrete surface shall be washed with clean water to remove all laitance, dirt and loose particles.
All exposed reinforcement shall be free from loose debris, concrete slush or any form of contamination that may affect its future
bond to concrete.
(iii) Placing fresh concrete at construction joints
Where fresh concrete is placed the same day as that on which the construction joint was formed, the fresh concrete shall be
cast directly against the face of the construction joint.
When concreting recommences a day or more after the construction joint has been formed, the following procedure shall be
followed:
1. The construction joint shall be kept constantly wet for a period of at least 4 hours before concreting restarts, but, the surface of
the concrete shall be in a saturated, surface- dry condition when concreting has to recommence;
2. Any dirt, excess water and loose particles shall be removed prior to reconcreting being started;
3. For horizontal construction joints a 150 to 250 mm thick concrete layer of the same grade of concrete made richer by reducing
the coarse aggregate content by 25 % shall be placed on the joint plane immediately before normal concreting;
4. For vertical construction joints the fresh concrete shall be placed against a surface prepared in accordance with
Clause A13.4.7.11g)(ii), and which is in a saturated, surface-dry; and
5. Where pumped concrete is utilised, the priming slush shall not be permitted to enter into any formwork or structural element to
be cast.
Epoxy resins shall not be used to bond fresh concrete to hardened concrete. For specialist construction methods, for example
precast segmental construction, the particular epoxy adhesive requirements shall be specified on the drawings.
(iv) Waterstops
Where required for water-tight structures or structural elements, waterstops for construction joints shall be as detailed on the
drawings.
Waterstops shall be of plasticised virgin, non-biodegradable polyvinyl chloride (PVC) material and sealing systems shall be of
modified, flexible Polyolefin material, of the type and details as specified on the drawings:
1. Flexible PVC waterstops shall comply with the requirements of CKS 389;
2. Modified, flexible Polyolefin sealing system shall have a minimum tape thickness of 2,0 mm and shall have resistance to diesel
and petrol fuels and oils; or
3. Special Engineered waterstops shall be specified on the drawings.
Each piece of premoulded waterstop or sealing system shall be of maximum practical length in order to keep the number of
end joints to a minimum. All joints in waterstops and sealing systems shall develop effective watertightness fully equal to that of
the continuous waterstop material, shall permanently develop at least 50 % of the mechanical strength of the parent section,
and shall permanently retain their flexibility. Precautions shall be taken so that the waterstops and sealing systems shall be
neither displaced nor damaged by construction operations or other means. All surfaces of the waterstops shall be kept free
from oil, grease, dried mortar, or any other foreign matter while the waterstop is being embedded in concrete. The Contractor
shall ensure that all portions of the waterstop designed for embedment shall be tightly enclosed by dense concrete, particularly
on the underside of horizontal waterstops.
h) Curing and surface protection
The protection of concrete before and during concrete placement, and hardened concrete susceptible to adverse environmental conditions is
described in Clause A13.4.7.10. All classes of hardened concrete shall be cured so as to prevent loss of water and to achieve specified levels
of curing efficiency. Curing shall commence immediately after the bleed water has left the surface and finishing operations are completed.
The method of curing adopted shall be subject to the Engineer's approval and shall not cause staining, contamination, or marring of the
surface of the concrete. Due care shall be exercised to ensure adherence to the recommended limits for thermal gradients in concrete.
The curing period, represented as either a prescribed minimum strength or curing efficiency, shall be stated on the drawings. Curing efficiency
shall be measured in accordance with the water sorptivity test (refer Clause A13.4.7.9e)). The minimum curing efficiency required shall be the
water sorptivity value determined from trial panels during the mix approval process as adjusted by the permissible deviation. When no such
minimum strength or curing efficiency data is prescribed, the minimum curing period shall be as shown in Table A13.4.7-18.
Table A13.4.7-18: Minimum duration of curing
Minimum daily Minimum curing period1, in days
surface concrete
temperature3, t, in °C Rate of concrete compressive strength development2,
r = (Fcu at 3 days / Fcu at 28 days)
r ≥ 0,55 𝑟 ≥ 0,50 r ≥ 0,45 r ≥ 0,25
t ≥ 25 5 7 10 15
25 > 𝑡 ≥ 15 6 8 11 16
15 > 𝑡 ≥ 5 7 10 15 21
Note: 1) Based on 70% of 28 day compressive cube or cylinder strength.
2) The rate of concrete compressive strength development is the ratio of the mean compressive strength after 3 days to the mean
compressive strength after 28 days determined from initial tests or based on known performance of concrete from site records.
3) Where the ambient relative humidity is below 85 % this value may be increased as directed by the Engineer.
Typically extend curing period by 0,5 days (12 hours) for every 5 %, or part thereof, reduction in ambient relative humidity. When the ambient
surface temperature of concrete falls below 5°C, the minimum curing periods shown in Table A13.4.7-18 shall be extended by the period during
which the temperature of the concrete was below 5°C.
The concrete shall be protected by means of a fog spray to keep it wet constantly for the periods stated above or until a curing compound is
applied. Wetting the concrete by spraying shall be by means of a fixed spraybar along the full length of the formwork. The spraybar shall be
connected to a suitable high-pressure water supply. Wetting shall be discontinued when the ambient air temperature drops below 5°C, and care
shall be taken by the Contractor to ensure that the water will not erode the surface of the fresh concrete.
When sliding formwork is used, the concrete shall be protected against the weather and rapid drying out by means of a 4,0 m wide skirt
attached to the tail of the formwork and if vertical, below the lowest working walkway, both internal and external. The skirt shall consist of two
layers of hessian in summer months but of one layer of canvas or other suitable material in winter. The skirt shall be weighted at the end to
prevent it flapping around in windy conditions.
i) Pipes, ferrules and conduits
No pipes and conduits other than those shown on the drawings shall be embedded in the concrete without the Engineer's approval. Pipes and
conduits shall be embedded in the structural element simultaneously with the casting of the element. The clear space between such pipes or
between such pipes and any reinforcing steel shall be at least 30 mm or the maximum size of the aggregate plus 10 mm, whichever is the
greater. The thickness of the concrete cover over pipes and fittings shall be specified on the drawings but shall be at least 40 mm.
The ends of ferrules used for bracing formwork shall be neatly finished off to the details shown on the drawings. Where no details are given
on the drawings, ferrules shall be cut back to a depth of at least the specified cover, and the holes shall be filled in with mortar and finished off
flush with the concrete surface.
j) Applied loading
(i) General
No load shall be applied to any part of a structure until the specified curing period has expired, the concrete has attained
sufficient strength and, when applicable, sufficient prestressing has been completed, so that damage will not occur. The
decision to permit applied loading to the structure shall rest with the Engineer. The Engineer's decision will be based on the
type of load to be applied, the age of the concrete, the magnitude of stress induced and the propping of the structure.
A13.4.8 WORKMANSHIP
A13.4.8.1 Tolerances
The tolerance shall be the maximum permissible deviations from the specified dimensions, properties, levels, alignment, positions, etc. shown
on the drawings of the structures or structural members or described in Sections A13.1 to A13.7 after completion of concrete construction. In
addition, the following tolerances and maximum permissible deviations are given below:
a) Concrete quality
(i) Compressive strength
1. Individual valid compressive strength test result:
Minus tolerance ..................................................... 3 MPa less than specified characteristic compressive strength at 28 days.
Plus tolerance ............................................................................................................................................................ unlimited
2. Arithmetic mean of any group of 3 to 29 successive valid compressive strength test results:
Minus tolerance ........................................ Tolerance value as stated in Table A13.4.8-1 greater than specified characteristic
DRAFT STANDARD (DS) OCTOBER 2020 13-65
compressive strength at 28 days.
Plus tolerance ............................................................................................................................................................ unlimited
Table A13.4.8-1: Allowable minimum tolerance for mean compressive strength tests
Minimum number of valid Tolerance (minimum)
compressive strength tests
3 +2,0 MPa
4 +3,0 MPa
5 +4,5 MPa
6 +5,0 MPa
10 +6,0 MPa
20 +7,0 MPa
CONTENTS
B13.4.1 SCOPE
B13.4.2 DEFINITIONS
B13.4.3 GENERAL
B13.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.4.5 MATERIALS
B13.4.6 CONSTRUCTION EQUIPMENT
B13.4.7 EXECUTION OF THE WORKS
B13.4.8 WORKMANSHIP
B13.4.1 SCOPE
This Section covers the labour enhanced work in minor bridges, culverts and miscellaneous structures.
This Section covers the supply and storage or stockpile of all materials, manufacture, transport, placing, finishing, curing, protection and testing
concrete in bridges, culverts and miscellaneous structures. The completed concrete elements shall conform to the lines, grades, and
dimensions shown on the drawings and as specified in Section A13.2. The work includes elements of structures constructed by cast-in-place
and precast methods using either plain (unreinforced), reinforced, or prestressed concrete or any combination thereof. This work is
appropriately suited for labour enhanced construction activities.
B13.4.2 DEFINITIONS
The provisions of Part A shall apply.
B13.4.3 GENERAL
The provisions of Part A shall apply.
B13.4.5 MATERIALS
The provisions of Part A shall apply.
B13.4.8 WORKMANSHIP
The provisions of Part A shall apply.
C13.4.1 Cast in situ concrete (Class of concrete and use or position in structure stated):
C13.4.4 Extra over item C13.4.2 for the protection of labour enhanced concrete from adverse
environmental conditions
C13.4.4.1 (Class of concrete and use or position in structure stated): cubic metre (m³)
The unit of measurement shall be the cubic metre of concrete placed in situ where any combination of means described in Clause A13.4.7.11
has been satisfactorily implemented in order to control the temperature of concrete within the specified limits and to adequately mitigate against
adverse environmental conditions.
The tendered rate shall include full compensation for the design, supply, procurement and implementation of the required means of protection
and environmental mitigation and applying it prior to casting and to the fresh concrete surface using approved method until the commencement
of the curing period.
Partial payment shall be applied in the event that the Engineer allows conditional acceptance.
C13.4.5.2 Etc for other parts of structure (Tenderer to specify method of curing) square metre (m2))
C13.4.6 Curing and surface protection of labour enhanced cast in situ concrete
C13.4.6.1 Structural element and surface to be stated (Tenderer to specify method of curing) square metre (m2)
The unit of measurement shall be the square metre of completed concrete element cured using an approved method as described in
Clause A13.4.7.12 of these specifications, if and where specifically required on the drawings or as ordered by the Engineer.
The tendered rate shall include full compensation for providing the curing means and applying it to the fresh concrete surface using approved
method(s) and, where applicable, in accordance with the product manufacturer’s specified nominal rates of application satisfying ASTM C309
as amended in Clause A13.4.5.8.
Should no curing method be specified at the time of tender then it will be assumed that wet fine mist spraying curing is to be done. Where
specified, curing shall be assessed by the sorptivity test. Partial payment shall be applied in the event that the Engineer allows conditional
acceptance.
(a) Indicate class of no-fines concrete and portion of structure or use cubic metre (m3)
(b) Etc for other classes of no-fines concrete and other portions of structures or uses cubic metre (m3)
C13.4.7.2 Precast:
(a) Indicate class of no-fines concrete and describe unit with reference to drawing: number (No)
(b) Etc for other classes of no-fines concrete and units of other types and sizes number (No)
The unit of measurement shall be the number of complete units of each size and type in position in the works.
The tendered rate for each precast unit shall include full compensation for providing all materials, labour, plant and formwork required for the
manufacturing of the unit, complete as shown on the drawings, and for curing, transporting, lifting and placing the unit in position.
C13.4.8.1 Cast in situ (class and portion of structure or use stated) cubic metre (m3)
The unit of measurement shall be the cubic metre of no-fines concrete in place. Quantities shall be calculated from the dimensions shown on
the drawings or authorised by the Engineer.
The tendered rates shall include full compensation for procuring, furnishing and storing the materials, providing all plant, mixing, transporting,
placing and working the concrete and for curing and protection of the surfaces described in Clause A13.4.7.11f) of the specification.
The unit of measurement shall be the number of complete members or elements of each type and size in position in the works.
The tendered rate for each precast member shall include full compensation for all concrete work, protection from adverse environmental
conditions, all formwork, curing and surface protection, safe guarding, and for all reinforcing steel and all the prestressing as required for
manufacturing the member complete, excluding only prestressing in connection with in situ concrete cast subsequent to the placing of the
precast members, for which prestressing separate payment is provided elsewhere in the schedule of quantities. Where required, the surfaces
shall be prepared for structural bonding with subsequent concrete to the satisfaction of the Engineer.
DRAFT STANDARD (DS) OCTOBER 2020 13-71
Item Description Unit
C13.4.11 Transporting and erecting precast concrete members (description of member and number (No)
approximate mass to be given)
Item Description Unit
C13.4.12 Labour enhanced transporting and erecting precast concrete members (Description of number (No)
member and approximate mass to be given)
The unit of measurement shall be the number of precast concrete members of each type and size placed into position
The tendered rate for each precast member shall include full compensation for all work, costs, access and equipment required for transporting,
stacking, lifting, erecting and installing the precast concrete member in its final position, complete as specified.
The tendered rate shall include full compensation for all labour, material, screening of the structure for safety and environment protective
measures, plant and equipment as well as for all work and incidentals required to partially demolish the concrete member. The tendered rate
shall also include the processing of the demolished product to ensure acceptance by the approved construction waste facility, loading, lifting,
transport and the disposal of the construction waste at the construction waste facility within a haul distance of 10 km. The tendered rate shall
also include full compensation for any necessary measures to ensure no debris falls into rivers and for any debris that has fallen into rivers to be
recovered.
CONTENTS
D13.4.1 SCOPE
D13.4.2 GENERAL
D13.4.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.4.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.4.5 VISUALLY ASSESSED PROPERTIES
D13.4.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.4.7 EVALUATION FOR ACCEPTANCE
D13.4.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.4.9 NOTIFICATION OF REMEDIAL WORK
D13.4.10 REMEDIAL WORK
D13.4.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Performance specifications
D13.4.2 GENERAL
D13.4.2.1 Product Conformance Specifications
The Contractor shall within 28 days of entering into the contract with the Employer submit to the Engineer conformance documentation related to
the specifications. All products used in the manufacture of concrete element shall be in compliance with the specifications continued in Section
A13.4.
Compliance documentation shall be provided for the following;
a) Cement (Clause A13.4.5.1)
b) Supplementary cementitious materials (Clause A13.4.5.1)
c) Aggregates (Clause A13.4.5.2)
d) Water (Clause A13.4.5.3)
e) Admixtures (Clause A13.4.5.4)
f) Integral permeability reducing technology (Clause A13.4.5.5)
g) Fibres (Clause A13.4.5.6)
h) Pigments and integral colouring agents (Clause A13.4.5.7)
i) Curing compounds (Clause A13.4.5.8)
j) Commercially-sourced concrete (Clause A13.4.6.2)
k) Testing necessary to prove the satisfactory execution of the works (Clause A13.4.7)
CONTENTS
PART A: SPECIFICATIONS
A13.5.1 SCOPE
A13.5.2 DEFINITIONS
A13.5.3 GENERAL
A13.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.5.5 MATERIALS
A13.5.6 CONSTRUCTION EQUIPMENT
A13.5.7 EXECUTION OF THE WORKS
A13.5.8 WORKMANSHIP
A13.5 PRESTRESSING
PART A: SPECIFICATIONS
A13.5.1 SCOPE
This Section covers the materials, equipment and work required for prestressing structural concrete members.
A13.5.2 DEFINITIONS
The following definitions shall apply to these specifications:
Anchorage - is the device comprising all the components and materials required for retaining the force in a tensioned tendon and to transmit
this force to the concrete of the structure.
Anchorage reinforcement - is the spiral and other reinforcement which forms part of the anchorage and is required for strengthening the
anchorage and/or assisting in transmitting the tendon force to the concrete.
Bursting reinforcement - is the reinforcing steel required in and adjacent to the anchorage zones to resist the tensile or splitting stresses induced
in the concrete by the anchorage(s).
Cable - is the tendon, together with the anchorage, sheathing and all fittings.
Characteristic strength - characteristic strength of prestressing steel is the manufacturer's guaranteed tensile strength below which no more than
5 % of the test results in a statistical population shall fall.
Duct - is the void formed in the structural element to house the tendon(s) and may be formed by coring, or by using sheaths or by way of extractable
cores.
Prestress - is the stress induced in concrete by tensioned tendons.
Prestressed concrete - is structural concrete in which effective internal stresses are induced by means of tensioned tendons.
Pre-tensioned concrete - is prestressed concrete where the tendon has been tensioned before the concrete is cast.
Post-tensioned concrete - is prestressed concrete where the tendon is tensioned after the concrete has hardened.
Pull-in - is the elastic shortening of the tendon caused by relative movement between the anchorage or coupler components on account of seating
and gripping action during or immediately after transfer.
Release - is the specified elastic shortening of the tendon at the anchorage achieved before or during transfer.
Sheath - is the tube or casing enclosing the tendon and which temporarily or permanently allows a relative movement between the tendon and
the surrounding concrete.
Tendon - is the prestressing steel consisting of the bar, wire or strand individually placed, or of bars, wires or strands placed in a duct, all of
which are tensioned to impart prestress to a concrete member.
Tensioning - is the action of inducing and regulating the force in a tendon by means of tensioning and measuring equipment.
A13.5.3 GENERAL
A13.5.5 MATERIALS
A13.5.5.1 General
All materials and prestressing systems used in the prestressing of structural concrete members shall be subject to approval by the Engineer.
A13.5.5.4 Sheaths
Sheaths shall be grout-tight and of such material and configuration that bond forces can be transferred from the grout to the surrounding
concrete. The properties of the sheath material shall be such that no corrosion attack of the prestressing steel will be induced. The sheath
shall be sufficiently flexible to accept the required curvature without kinking, and strong enough to retain its cross-section and alignment and to
resist damage on account of handling, transporting, tying and contact with vibrators during concreting. Unless otherwise approved by the
Engineer, the thickness of the metal of steel sheaths shall not be less than 0,4 mm.
Metal sheathing shall be delivered at the site suitably protected against damage and corrosion. At the time of incorporation into the structural
member, the sheathing shall be free from loose mill scale, loose rust, lubricants and harmful matter.
Galvanized sheathing shall not be used unless specified.
Plastic sheaths shall be formed using HDPE corrugated piping in accordance with ‘Corrugated Plastic Ducts for Internal Bonded Post-
tensioning’, Bulletin No. 7, International Federation for Structural Concrete (fib), January 2000.
Unless otherwise specified, the internal diameter of the sheath shall be at least 10 mm greater than the diameter of the tendon. For vertical
tendons and where tendons are to be drawn into cast-in sheaths, the cross-sectional duct area shall be at least three times the cross-sectional
area of the tendon.
A13.5.5.7 Grout
a) Materials
In addition to the requirements of Clause A13.4.5.3, water shall not contain more than 500 mg of Cl ions per litre of water.
Only CEM I or CEM II/A, with a strength class of 42.5 N or greater, which complies with the requirements of SANS 50197 shall be used. The
temperature of the cement shall be less than 40C, and the cement shall be stored in accordance with the requirements of Clause
A13.4.5.10b).
Fine aggregate shall consist of siliceous granules, finely ground limestone or very fine sand. The aggregate used shall pass through a
0,600 mm sieve. The use of fine aggregate shall be subject to the approval of the Engineer and shall be restricted to grout for ducts with a
diameter exceeding 150 mm. The aggregate content in the grout shall not exceed 30 % of the mass of the cement.
The use of admixtures shall be subject to tests having shown that their use improves the properties of the grout, e g by increasing workability,
reducing bleeding, entraining air, or expanding the grout. Admixtures shall be free from any product liable to damage the steel or the grout
itself, such as halides, nitrates, sulphides, sulfates, etc. The quantity of admixture to be used shall be in accordance with the manufacturer's
instructions.
b) Properties of the grout
The mixed grout shall have the following properties:
(i) The Cl ions content shall not exceed 750 mg per litre.
(ii) The viscosity of the grout measured in accordance with Clause A13.5.5.9(d) for horizontal cables shall be 500 to 2 500 cP and for vertical
cables 400 to 1 500 cP. The viscosity of the grout, 20 minutes after mixing, shall not exceed 2 500 cP and 1 500 cP for horizontal and
vertical cables respectively.
(iii) Bleeding at 20C measured in accordance with Clause A13.5.5.9d) shall not exceed 2 % by volume 3 hours after the grout has been
mixed, and the maximum bleeding shall not exceed 4 %. In addition, the separated (bleed) water must be reabsorbed after 24 hours.
(iv) The cube compressive strength of 100 mm cubes made of the grout and cured in a moist atmosphere for the first 24 hours and then in
water at 20C shall exceed 20 MPa at 7 days.
A13.5.5.9 Testing
a) General
Where so directed by the Engineer, the Contractor shall make arrangements for samples of the materials he intends to use in the works to be
tested by an independent testing authority. The cost of testing prestressing steel, anchorage assemblies and couplings shall be paid for as
specified in Section C20.1 of Chapter 20 on condition that the product complies with the requirements. Control tests on the viscosity and
bleeding of grout will be regarded as part of the Contractor's obligations under Chapter 1 for process control and will not be paid for separately.
Material represented by samples which do not comply with the specified requirements, shall be removed and replaced with suitable material.
b) Anchorages and couplers
Anchorages and couplers shall be tested in accordance with the requirements of Clause A13.5.5.3. The anchorages and couplers shall be
assembled in accordance with their practical application on the site where all the components necessary for anchoring shall be used, but
excluding the ducts.
c) Prestressing steel
Prestressing steel shall be tested in accordance with the requirements of Clause A13.5.5.2. Should any test piece fail to comply with the
requirements specified for the prestressing steel, the material represented by that sample shall not be used without further testing and shall be
replaced with materials conforming to the specifications, if further testing confirms that they do not comply with the specifications.
d) Grout
The fluidity of grout shall be measured with a flow cone, immersion apparatus or viscometer. The instrument shall be accurately calibrated in a
laboratory so that the specified viscosity of the grout can be controlled satisfactorily.
The procedure for conducting the flow-cone test for measuring the fluidity of grout shall be as follows:
Unless otherwise approved, the flow cone shall be as shown in Figure A13.5-1.
Immediately after the grout has been mixed, the pre-wetted flow cone, which is held firmly with its top rim in a level position, shall be filled with
grout to the level indicated by the pre-set pointer, whilst the bottom orifice is held closed with a finger.
As soon as the required volume of grout, (± 1 750 ml), is reached, the finger shall be released to allow the grout to flow out freely through the
bottom orifice. A stop watch shall be used to determine the flow time for emptying the cone, to the nearest second.
The readings obtained during grouting shall be compared with the times determined in the laboratory for grouts of the specified viscosities.
The bleeding of grout shall be measured in a metal or glass container with an internal diameter of approximately 100 mm and a height of
approximately 120 mm. The grout and water levels in the container shall be controlled with a metal bridge into which two adjustable studs A
and B are secured. See Figure A13.5-2 for details of the apparatus.
The procedure for determining the bleeding of grout shall be as follows:
Studs A and B in the metal bridge shall be adjusted and locked so that the distance from the lower tips of the studs to the bottom of the
container will be approximately 100 mm and 107 mm respectively. The volumes VA and VB for the container at the respective levels of the stud
settings shall then be determined to the nearest millilitre.
The container shall be filled with freshly mixed grout to a level where the grout will just touch the tip of stud A which points downwards. The
bridge shall then be removed and the container tightly sealed to prevent evaporation. The container shall then be stored at 20°C and kept free
from vibrations for the entire duration of the test.
Three hours after the grout has been mixed, the container shall be opened and the free (bleed) water poured off. The bridge shall be placed
over the container with the tip of stud B pointing downwards and water poured onto the grout with a measuring apparatus until the water level
touches the tip of stud B. The volume of water added shall be determined to the nearest millilitre and designated as ΔV.
The percentage of bleeding shall be calculated from the formula: [ 1 – ( VB – ΔV ) / VA ] x 100
A13.5.7.2 Pre-tensioning
During the period between tensioning and transfer, the force in the tendon shall be fully maintained by some positive means. At transfer,
detensioning shall take place slowly to minimise any shock which could adversely affect the transmission length of the tendon.
In the long-line method of pre-tensioning, sufficient locator plates shall be distributed through-out the length of the bed to ensure that the
straight tendons are maintained in their proper position during concreting. Where a number of units are manufactured in line, they shall be free
to slide in the direction of their length so as to permit transfer of the tendon force to the concrete along the entire line.
In the individual-mould system, the moulds shall be sufficiently rigid to provide the reaction to the tendon force without distortion.
Where possible, the mechanism for holding down or holding up deflected tendons shall ensure that the part in contact with the tendon will be
free to move in the line of the tendon so that friction losses are eliminated. If, however, a system is used which develops a frictional force, this
force shall be determined by test and due allowance made therefor.
For single tendons, the deflector in contact with the tendon shall have a radius of not less than 5 times the tendon diameter for wire, or 10 times
the tendon diameter for a strand, and the total angle of deflection shall not exceed 15.
Transfer of the tendon force to the concrete shall be effected in conjunction with the release of hold-down and hold-up forces in accordance with
an approved method.
A13.5.7.3 Post-tensioning
a) Storage, handling and protection
During storage, transit, construction and after installation, the sheaths, prestressing steel, anchorages and couplers shall be protected against
corrosion, damage or permanent deformation. The manner and extent of protection required will depend on the environmental factors and the
length of time before permanent corrosion protection is applied, and shall be to the satisfaction of the Engineer. Under severe corrosive
conditions in coastal, damp and wet areas and under aggressive conditions the materials shall be stored in weatherproof sheds. All materials
shall be stored clear of the ground and while in storage shall not be exposed to the weather.
When prestressing steel has been stored for a prolonged period and there is evidence of its deterioration, the Contractor may be called on to
prove by tests that the quality of the steel has not been significantly impaired and that the prestressing steel still complies with the provisions of
these specifications.
Suitable protection shall be provided to the threaded ends of bars.
After fabrication, the cable ends shall be covered with protective wrapping to prevent the ingress of moisture into the duct.
When the tendon is to be left untensioned for a prolonged period after installation, precautions shall be taken to protect the tendon against
corrosion. Corrosion inhibitors, soluble oils or similar materials used as lubrication or to provide temporary protection shall be such that they
can be completely removed before permanent protection is affected.
b) Fabrication
All cutting of prestressing steel shall be performed with a high-speed abrasive cutting wheel or by a method approved by the Engineer. Flame
cutting will not be permitted.
Care shall be taken to prevent the prestressing steel or anchorages from coming into contact with splashes from flame-cutting or welding
processes in the vicinity.
Where possible, all bars, wires or strands tensioned in one operation shall be taken from the same parcel of prestressing steel. The tendon or
cable shall be labelled to show the tendon or cable number, as well as identify from which parcel the steel has been taken.
Where bars, wires or strands in a tendon are not tensioned simultaneously, tendon spacers shall be used in accordance with the
recommendations for the prestressing system or, in the absence thereof, as directed by the Engineer.
Cables shall be fitted at both ends with pipes with a diameter of at least 10 mm for the injection of grout or protection agents. The ends of the
injection pipes shall be fitted with a clamp, valve or device capable of withstanding a pressure of at least 15 bars without loss of grout or
protection agent.
Vent pipes with a diameter of at least 25 mm shall be provided in the duct at every high point, low point, change of sheath cross-section and at
such intermediate positions as may be shown on the drawings or required by the Engineer. The vent pipes shall extend to at least 500 mm
above the concrete and shall comply with the requirements for injection pipes.
Connections to, and joints in sheaths shall be made grout-tight by using special sheathing couplings and taping. With bonded cables, the
length of taping shall not exceed six sheath diameters. Where oversleeves are used, equal overlaps shall be provided over each length of
sheathing. Joints in adjacent sheaths shall be spaced at least 300 mm apart.
c) Installation
The installation of tendons shall not commence until the requirements of Clause A13.5.4.5 have been complied with.
The cable, sheath or extractable core shall be accurately installed to the specified alignment and securely held in position both vertically and
horizontally at intervals appropriate to its rigidity and so as not to be displaced during concreting, either by the weight of the concrete or by
buoyancy. The spacing of the cable supports shall furthermore ensure that the tendon can be installed to a smooth alignment without kinks and
within the tolerance specified in Clause A13.5.8.1. Cable sheaths shall be supported and held in position by means of separate reinforcing
steel supports with a diameter of not less than 16 mm. The transverse bars must be welded to the vertical bars or must rest on lugs welded to
the vertical bars. The spacing of the vertical supports shall not exceed 1,0 m.
Extractable cores shall not be coated with release agent unless approved by the Engineer.
Unless otherwise shown on the drawings, the alignment of the tendon within a distance of 1,0 m from the live anchorage and/or coupler shall be
straight. The tendon axis shall be set perpendicular to the bearing surface of its anchorage and firmly secured in position so as not to move
during concreting. External anchorages shall be seated on a thin mortar bedding to bear evenly on the concrete bearing surface, and the
tendon axis shall be perpendicular to the bearing surface of the anchorage.
Unless otherwise shown on the drawings, the minimum concrete cover over the outside surface of the sheath or cable support shall comply with
the requirements of Clause A13.3.7.4, except that, for sheaths, the cover shall not be less than 50 mm.
The spacing of cables will depend on the size of the cable and shall be such that the concrete can be properly placed and compacted.
Immediately before concreting, the Contractor shall inspect the sheaths for grout-tightness and shall seal all damaged and suspect sections.
External tendons shall be installed to the same standards and accuracy specified herein for internal tendons. The tendons shall be temporarily
supported at regular intervals along the straight length between saddles. The supports shall consist of rigidly constructed frames secured to the
concrete face.
A13.5.7.5 Safety
Stressing operations shall be carried out under the direction of a competent person. Workers involved in prestressing shall be instructed in, and
follow safe work procedures. Appropriate eye protection shall be worn by all workers involved in grouting, stressing and cable trimming
operations.
During prestressing operations, workers shall be protected by guards or other suitable devices at the tensioning ends and anchoring points to
contain the flying strands and the strand wedges in the event of strand failure.
Welding, flame-torching or other similar operations shall not be permitted in the vicinity of prestressing strands unless proper care is taken to
protect the strands from sparks or other heat sources, and from stray electric currents.
Visual or audible signaling devices shall be provided and used in the area of tensioning operations to warn workers approaching the area.
Workers not directly involved in tensioning or de-tensioning operations shall be kept clear of the danger area and shall remain clear until
operations are completed and the visual or audible signals are turned off or removed.
Strand elongation and strand deflection shall be measured by a means which does not expose the workers to the risk of injury.
A13.5.8 WORKMANSHIP
The Contractor shall ensure that prestressing is done in accordance with the specifications and instructions of an ECSA Registered
Professional Engineer, and a copy of such information shall be available in the safety file on site while the work is being done.
A13.5.8.1 Tolerances
Sheaths for prestressing tendons shall be placed and maintained in position within the following tolerances:
In the direction of the width of the member:
DRAFT STANDARD (DS) OCTOBER 2020 13-85
• For members of up to 200 mm in width ...................................................................................................................... ± 10 mm
• For members exceeding 200 mm in width ................................................................................................................... ± 20 mm
In the direction of the depth of the member:
• For members of up to 200 mm in depth ........................................................................................................... ± 0,025 x depth
• For members exceeding 200 mm in depth ...................... ± 0,010 x depth within the tolerance range of ± 5,0 mm to ± 25 mm.
CONTENTS
B13.5.1 SCOPE
B13.5.2 DEFINITIONS
B13.5.3 GENERAL
B13.5.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.5.5 MATERIALS
B13.5.6 CONSTRUCTION EQUIPMENT
B13.5.7 EXECUTION OF THE WORKS
B13.5.8 WORKMANSHIP
B13.5.1 SCOPE
This Section covers the materials, equipment and work required for prestressing structural concrete members. Due to the specialised skills level
that is required for this activity, it is deemed not suitable for labour enhanced construction methods.
B13.5.2 DEFINITIONS
The provisions of Part A shall apply with no additional requirements.
B13.5.3 GENERAL
The provisions of Part A shall apply with no additional requirements.
B13.5.5 MATERIALS
The provisions of Part A shall apply with no additional requirements.
B13.5.8 WORKMANSHIP
The provisions of Part A shall apply with no additional requirements.
C13.5.3 Extra over item C13.5.2 for partially tensioning the tendons meganewton (MN)
The unit of measurement shall be the meganewton, which is calculated as for item C13.5.2.
The tendered rate shall include full compensation for the use of all equipment, as well as for all work and incidentals required for tensioning and
anchoring the tendons to the specified partial force.
CONTENTS
D13.5.1 SCOPE
D13.5.2 GENERAL
D13.5.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.5.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.5.5 VISUALLY ASSESSED PROPERTIES
D13.5.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.5.7 EVALUATION FOR ACCEPTANCE
D13.5.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.5.9 NOTIFICATION OF REMEDIAL WORK
D13.5.10 REMEDIAL WORK
D13.5.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part C only but includes all of the requirements in the
Contract Documentation.
D13.5.2 GENERAL
D13.5.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for:
a) Prestressing strand: each parcel or cheese
CONTENTS
PART A: SPECIFICATIONS
A13.6.1 SCOPE
A13.6.2 DEFINITIONS
A13.6.3 GENERAL
A13.6.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.6.5 MATERIALS
A13.6.6 CONSTRUCTION EQUIPMENT
A13.6.7 EXECUTION OF THE WORKS
A13.6.8 WORKMANSHIP
A13.6 BEARINGS
PART A: SPECIFICATIONS
A13.6.1 SCOPE
This Section covers various items of work associated with the construction, supply and installation of bearings for structures. All bearings shall
be designed, manufactured and installed in accordance with European Standard EN 1337: “Structural Bearings.”
A13.6.2 DEFINITIONS
The following definitions shall apply to this Section:
Polytetrafluoroethylene chemical compounds used for sliding surfaces of Bearings (PTFE).
The Hardness of rubber used in Bearing is defined as International Rubber Hardness Degree (IRHD).
Elastomer - natural or synthetic rubber which has both viscosity and elasticity.
Large Elastomeric Bearings - these are bearings which can be subjected to a maximum vertical load of 3000 kN at ultimate limit state
Micaceous Iron Oxide (MIO) points are used as part of the paint systems for Bearings
Shear Modulus (G) is the ratio of shear stress to shear strain
Polychloroprene Rubber (CR) and Natural Rubbers (NR) are used in bearings.
A13.6.3 GENERAL
The bearings in this Section include simple bearing strips of roofing felt and rubber, elastomeric bearings reinforced with steel plates and
precision manufactured steel pot type, spherical, uplift and line rocker proprietary bearings.
A13.6.5 MATERIALS
A13.6.5.1 Bearings in structures
a) General
Unless otherwise specified, all the materials used for manufacturing the bearings shall comply with the requirements of EN 1337: Structural
bearings.
b) Roofing felt
Roofing felt shall be 3-ply and comply with the requirements of SANS 92 for type 1 roofing felt.
c) Elastomer
(i) General
The elastomer used in the manufacture of Elastomeric Bearings should be specified in the project documentation as either natural
rubber (NR) or chloroprene rubber (CR) as the raw polymer. Blending with up to 5 % of another polymer, which may be added to
aid processing, is permitted. No reclaimed or ground vulcanized rubber shall be used.
NOTE: Natural rubber bearings can be protected by a cover of polychloroprene, both parts vulcanized simultaneously.
(ii) Physical and mechanical properties of elastomer
The physical and mechanical properties of the elastomer shall comply with the requirements given in Table A13.6.5-1, depending
upon the raw polymer used. In case of a natural rubber bearing having a polychloroprene cover, the natural rubber does not have
to be tested for ozone resistance.
The polychloroprene compound for the cover shall meet the requirements for polychloroprene and the core shall meet the
requirements for NR, except for ozone resistance.
The frequency of the tests given in Clause 8 of EN 1337 – 3.
The specifications are given for moulded test pieces or samples taken from complete finished bearings. In this case they shall be
taken from the top and bottom surfaces or first internal layer, and from the internal layer at the centre of the bearing.
(ii) On completion of the manufacture of the bearings, the Contractor shall submit bearings selected by the Engineer, or specially
manufactured bearings to serve as samples as authorised by the Engineer, to an independent testing authority for testing.
The testing facilities of the manufacturer or supplier may be used if so approved and on condition that the tests are conducted in the
presence of the Engineer.
The Engineer will determine which tests are to be conducted, and the tests shall comply with the appropriate requirements of Clause
A20.1.5.6a) of Chapter 20. Payment will be made under Section C20.1 of Chapter 20 for these tests, for bearings damaged, and for sample
bearings.
Copies of test results and certificates for the abovementioned tests shall be submitted by the Contractor to the Engineer in good time to
enable the Engineer to assess the information before the bearings are installed.
(iii) Before the bearings are dispatched to the site of the works, each bearing, with the exception of large bearings as defined in Clause
A13.6.2, shall be subjected simultaneously to a vertical load equal to 150 % of the maximum design load, and to a shear distortion equal to
150 % of the maximum design value. The bearings shall be visually inspected for defects by the Engineer or his nominee and shall not at
any stage under this test show any cracks visible to the naked eye or any other defects. The cost of this testing shall be included in the
rate tendered for under Section C20.1 of Chapter 20.
The Engineer may instruct that 1 or more bearings of each consignment shall be cut open with a view to a visual assessment of the
bonding and the thickness of the elastomeric layers. Payment for these bearings shall be paid for under payment item C13.6.1.
Large bearings shall also be tested by cutting them into halves or quarters in accordance with EN 1337-3. The test results shall then be
factored to ensure that the loads obtained meet the requirements of the design.
(b) Proprietary bearings
The Engineer may require tests to be conducted to verify compliance of the bearing with the EN 1337 specifications and/or its satisfactory
performance under the design loads. Payment for this testing will be made under Section C20.1 of Chapter 20.
Test certificates of all the tests conducted shall be submitted to the Engineer.
The Contractor shall give the Engineer at least 14 days' notice prior to final assembly of the bearings to enable the Engineer to inspect the
bearings at the factory.
Under no circumstances shall bearings be taken apart and reassembled on the site, except where it is an unavoidable feature of the installation
procedure, in which case the dismantling, installation and reassembly shall be under the supervision of qualified personnel.
Rehabilitation, modification and repair work to bearings shall be carried out only in the factory or in an Engineering works approved by the
Engineer.
CONTENTS
B13.6.1 SCOPE
B13.6.2 DEFINITIONS
B13.6.3 GENERAL
B13.6.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.6.5 MATERIALS
B13.6.6 CONSTRUCTION EQUIPMENT
B13.6.7 EXECUTION OF THE WORKS
B13.6.8 WORKMANSHIP
B13.6.1 SCOPE
This Section covers various items of work associated with the construction, supply and installation of bearings for structures. This Section is of a
specialist nature and is not suitable for labour enhanced work.
B13.6.2 DEFINITIONS
The provisions of Part A shall apply with no additional requirements.
B13.6.3 GENERAL
The provisions of Part A shall apply with no additional requirements.
B13.6.5 MATERIALS
The provisions of Part A shall apply with no additional requirements.
B13.6.8 WORKMANSHIP
The provisions of Part A shall apply with no additional requirements.
C13.6.1 Bearings:
The unit of measurement shall be the number of complete bearings of each type and class installed.
The tendered rate shall include full compensation for supplying all the materials, including anchor bolts and/or dowels, constructing the bedding,
manufacturing the bearings, transporting, handling and storing, and all labour, equipment and incidentals required for installing the bearings
complete as detailed. The tendered rate shall also include for the provision of Engineering drawings and certification after installation by an
ECSA Registered Professional Engineer or Technologist. Payment shall only be made for the Engineering drawings after the submission of the
construction record drawings of the bearings. Payment shall be made in 2 stages 50 % on submission and approval of the Bearings and 50 %
on the submission of the record drawings of Bearings.
C13.6.3 Bearing strips (description of the material and number of Layers) square metre (m2)
The unit of measurement shall be the square metre of bearing area lined with the specified material irrespective of the number of layers placed
The tendered rate shall include full compensation for supplying all the materials, transporting, handling and storing, and all labour and incidentals
required for installing the bearing strips complete as detailed.
C13.6.5.1 Prime cost sum allowed for purchasing and taking delivery of bearing prime cost sum
C13.6.5.2 Percentage on prime cost sum for charges and profit percentage (%)
Payment for purchasing and taking delivery of proprietary bearings, complete with anchor bolts and/or dowels, shall be in accordance with the
provisions of the general conditions of contract.
C13.6.6 Installing the proprietary bearings (description of each type, and state class) number (No)
The unit of measurement shall be the number of complete bearings of each type and class installed.
The tendered rate shall include full compensation for supplying all the materials not covered under item C13.6.5, constructing the bedding,
transporting, handling and storing, and all labour, equipment and incidentals required for installing the bearings complete as detailed.
The tendered rate shall be final and binding, irrespective of the type or make of bearing finally installed.
CONTENTS
D13.6.1 SCOPE
D13.6.2 GENERAL
D13.6.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.6.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.6.5 VISUALLY ASSESSED PROPERTIES
D13.6.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.6.7 EVALUATION FOR ACCEPTANCE
D13.6.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.6.9 NOTIFICATION OF REMEDIAL WORK
D13.6.10 REMEDIAL WORK
D13.6.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
D13.6.2 GENERAL
D13.6.2.1 Product conformance specifications
The Contractor shall within 28 days before manufacture of the Bearings submit to the Engineer conformance documentation related to the
specifications. All products used in the manufacture and installation of Bridge bearings shall be in compliance with the specifications contained in
Section A13.6 and EN 1337.
Compliance documentation shall be provided for:
a) Carbon Steel
b) Stainless Steel
c) Natural Rubber (NR)
d) Synthetic Rubber (Polychloroprene) (SR)
e) PTFE
f) Epoxy Adhesives
g) Epoxy Mortars
DESCRIPTION DETAILS
Bridge Number
Date of Manufacture
Date of Installation
Duration of Warranty
The Contractor, Manufacturer and Installer hereby warrant that the above bearings will perform satisfactorily in terms of workmanship and
durability, and that the bearings have been installed in accordance with the patent holders requirements and as set out in the specifications and
on the drawings for each particular bearing.
This warranty is for 25 years from the completion date of the Main Contract for the project.
In the event that the performance of the bearings is not in accordance with this warranty due to materials or workmanship defects, the
Contractor undertakes to rectify the bearings within 90 days of receiving the instruction to do so by the Employer.
The bearings shall be completely replaced including, supply and installation including all other costs associated thereto (i.e. Traffic
Accommodation, jacking, closure of the road and bridge as agreed to by the Employer) to the satisfaction of the Engineer.
SIGNED ON BEHALF OF CONTRACTOR: ____________________________________________________________________
SIGNED ON THIS THE ____________ DAY OF _______________________ IN THE YEAR ______________________________
on behalf of: _________________________________________________________________________________
Address: _________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Telephone No: _________________________________________________________________________________
SIGNED ON BEHALF OF MANUFACTURER: ___________________________________________________________________
SIGNED ON THIS THE ____________ DAY OF _______________________ IN THE YEAR ______________________________
on behalf of: _________________________________________________________________________________
Address: _________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Telephone No: _________________________________________________________________________________
DRAFT STANDARD (DS) OCTOBER 2020 13-102
SIGNED ON BEHALF OF INSTALLER: ____________________________________________________________________
SIGNED ON THIS THE ____________ DAY OF _______________________ IN THE YEAR ______________________________
on behalf of: _________________________________________________________________________________
Address: _________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Telephone No: _________________________________________________________________________________
WITNESS:
Signature: _________________________________________________________________________________
Name: _________________________________________________________________________________
Address: _________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Telephone No: _________________________________________________________________________________
CONTENTS
PART A: SPECIFICATIONS
A13.7.1. SCOPE
A13.7.2 DEFINITIONS
A13.7.3 GENERAL
A13.7.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.7.5 MATERIALS
A13.7.6 CONSTRUCTION EQUIPMENT
A13.7.7 EXECUTION OF THE WORKS
A13.7.8 WORKMANSHIP
A13.7 JOINTS
PART A: SPECIFICATIONS
A13.7.1 SCOPE
This Section covers the supply and installation of all permanent joints which will permit relative movement between contiguous structural
members.
A13.7.2 DEFINITIONS
The following definitions shall apply to this Section.
Joint Termination - shall consist of the end treatment of a joint at a barrier, wall, soffit, parapet or sidewalk kerb.
Thermoplastic sealants - thermoplastic material has a high concentration of polymers with amorphous structures and excellent elasticity.
These sealants can be either hot poured or cold applied.
International Rubber Hardness Degree - refer to Clause A13.6.2. The hardness of rubber used in joint glands is defined as international
Rubber Hardness Degree IRHD
Polyethelene Tape - polyethelenes are types of polymers which are thermoplastic in nature
Agrément South Africa - an objective, independent agency which evaluates the fitness-for-purpose of non-standard construction products.
A13.7.3 GENERAL
This Section covers all types of joints in structures including horizontal and vertical joints in walls and slabs and bridge deck expansion joints.
Cover plates at the termination of bridge joints shall always be provided.
Proprietary bridge joints shall have Agrément South Africa certification. The certification shall include the Roadway / Footwalk / Barrier interface
as part of the complete Joint System.
Joint terminations in Roadway Joints shall always be constructed as part of all expansion joints in the roadway.
A13.7.5 MATERIALS
A13.7.5.1 Joints in structures
a) General
All materials used in forming, constructing and sealing permanent joints as well as all proprietary or custom-built expansion-joint assemblies
shall be subject to the approval of the Engineer.
b) Joint filler
Joint filler shall consist of sheets or strips of the following materials complying with the requirements of the relevant specifications listed:
Bitumen-impregnated fibreboard and bitumen - impregnated corkboard – US Federal Specification HH- F-341F or AASHTO Specification M213.
Resin-impregnated corkboard U S Federal Specification HH-F-341F.
Flexible foams of expanded polyethylene, polyurethane, PVC or polypropylene AASHTO Specification.
A13.7.8 WORKMANSHIP
A13.7.8.1 Tolerances
The joint assemblies shall be constructed within a tolerance of ± 5,0 mm for all dimensions. The alignment shall not deviate from the true
alignment by more than 10 mm in any place, nor shall other alignment deviate by more than 5,0 mm from the true alignment over a length of 5,0
m.
CONTENTS
B13.7.1 SCOPE
B13.7.2 DEFINITIONS
B13.7.3 GENERAL
B13.7.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.7.5 MATERIALS
B13.7.6 CONSTRUCTION EQUIPMENT
B13.7.7 EXECUTION OF THE WORKS
B13.7.8 WORKMANSHIP
B13.7.1 SCOPE
This Section covers the supply and installation of all permanent joints which will permit relative movement between contiguous structural
members. Complex joints are deemed to be of a specialist nature and hence not suitable for labour enhanced work.
B13.7.2 DEFINITIONS
The provisions of Part A shall apply with no additional requirements.
B13.7.3 GENERAL
The provisions of Part A shall apply with no additional requirements.
B13.7.5 MATERIALS
The provisions of Part A shall apply with no additional requirements.
B13.7.8 WORKMANSHIP
The provisions of Part A shall apply with no additional requirements.
C13.7.2.1 (Description of joint and thickness of joint filler for joints measured per square metre) square metre (m²)
C13.7.2.2 (Description of joint and thickness of joint filler for joints measured per metre) metre (m)
The unit of measurement shall be the square metre of filled joint calculated from the surface area of the joint. Where the filled joint is 150 mm or
less in depth, the unit of measurement shall be the metre of filled joints measured along the joint centre line. Concrete surfaces formed prior to
the construction of the final surface for completing the filled joint shall be measured under item C13.2.1, C13.2.2, C13.2.3 or C13.2.4, as may be
applicable.
The tendered rates shall include full compensation for supplying and installing the joint filler and all materials not covered under item C13.7.4,
and for all labour and incidentals required for completing the filled joint as prescribed.
The tendered rate for items C13.7.2.1 and C13.7.2.2 shall also include for water test required to test the joint. The tendered rate shall include
full compensation for providing the pond of water and maintaining its depth of 150 mm for the full one hour period and clearing away the
ponding materials on completion.
C13.7.3.1 (Description of joint for joints measured per square metre) square metre (m²)
C13.7.3.2 (Description of joint for joints measured per linear metre) metre (m)
The unit of measurement shall be the square metre of unfilled joint, calculated in accordance with the joint area. Where, however, the depth of
the joint is 150 mm or less, the unit of measurement shall be the metre of unfilled Joint measured long the joint centre line. Concrete areas
formed before the final surface is constructed to complete the unfilled joint, shall be measured under items C13.2.1, C13.2.2, C13.2.3 or
C13.2.4, as may be applicable.
The tendered rates shall include full compensation for providing and applying the bond breaker and also for the labour and incidentals required
for completing the unfilled joint as prescribed.
C13.7.5 Supply and installation of Agrément South Africa certified proprietary expansion joints
(g) Extra over for variation in joint depth of asphaltic joints litre (lit)
C13.7.5.3 Provision of Engineering Drawings of proprietary joints and certification after installation by lump sum
an ECSA registered professional Engineer of technologist
The unit of measurement shall be the metre of complete joint inclusive of concrete or elastomeric nosings between the kerbs of each type
installed excluding the joint terminations and nonmetallic coverplates.
The tendered rates shall include full compensation for supplying all materials, transporting, handling and storing, and all labour, equipment,
shaping the recesses, and incidentals required for installing the expansion joint complete in accordance with instructions (see notes 1 and 2
below). The joint measured shall be the complete joint shown on the drawings excluding the joint termination details, recesses and cover plates
at the barriers, parapets and sidewalks. Payment for the Engineering drawings shall only be made after the submission of the construction
record drawings of the joints.
The tendered rate for all the sub items shall also include for water test required to prove the joint. The tendered rate shall include full
compensation for providing the pond of water and maintaining its depth of 150mm for the full one hour period and clearing away the ponding
materials on completion.
The tendered rate shall be final and binding, irrespective of the type or make of joint finally installed.
C13.7.8 Additional water tests for joints ordered by the Engineer number (No)
The unit of measurement shall be the number of additional water tests for proving the expansion joints, as ordered by the Engineer.
The tendered rate shall include full compensation for providing the pond of water and maintaining its minimum depth of 150mm for the full one
hour period, and clearing away the ponding materials on completion.
C13.7.9.1 Prime cost sum allowed for purchasing and taking delivery of expansion joints prime cost sum
C13.7.9.2 Percentage on prime cost sum for charges and profit percent (%)
Payment for purchasing and taking delivery of proprietary expansion joints shall be in accordance with the provisions of the general conditions
of contract (see note 2 below).
CONTENTS
D13.7.1 SCOPE
D13.7.2 GENERAL
D13.7.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.7.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.7.5 VISUALLY ASSESSED PROPERTIES
D13.7.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.7.7 EVALUATION FOR ACCEPTANCE
D13.7.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.7.9 NOTIFICATION OF REMEDIAL WORK
D13.7.10 REMEDIAL WORK
D13.7.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
D13.7.2 GENERAL
D13.7.2.1 Product conformance specifications
The Contractor shall within 28 days of entering into the contract with the Employer submit to the Engineer conformance documentation related to
the specifications. All products used in the manufacture and installation of Bridge joints shall be in compliance with the specifications contained
in Section A13.7.
Compliance documentation shall be provided for:
a) Carbon Steel
b) Stainless Steel
c) Elastomeric Glands
d) Asphaltic Plug joint material.
e) All sealants
f) Epoxy Adhesives
g) Epoxy Mortars
DESCRIPTION DETAILS
Name of Contact
Person
Name of Contact
Person
Name of Contact
Person
Date of Manufacture
Date of Installation
Duration of
Warranty
Start date of
Warranty
End date of
Warranty
The Contractor, Manufacturer and Installer hereby warrant that the above joints will perform satisfactorily in terms of workmanship and durability,
and that the joints have been installed in accordance with the patent holder’s requirements and as set out in the specifications and on the
drawings for each particular joints.
This warranty is for 25* or 15* years from the completion date of the Main Contract for the project. (*Delete whichever is not applicable).
In the event that the performance of the joints is not in accordance with this warranty due to materials or workmanship defects, the Contractor
undertakes to rectify the joints within 90 days of receiving the instruction to do so by the Employer.
The joints shall be completely replaced including, supply and installation including all other costs associated thereto (i.e. Traffic Accommodation,
Closure of the road and bridge as agreed to by the Employer) to the satisfaction of the Engineer.
SIGNED ON BEHALF OF MAIN CONTRACTOR: ________________________________________________________________
SIGNED ON THIS THE ____________ DAY OF _______________________ IN THE YEAR ______________________________
on behalf of: _________________________________________________________________________________
Address: _________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Telephone No: _________________________________________________________________________________
SIGNED ON BEHALF OF MANUFACTURER: ___________________________________________________________________
SIGNED ON THIS THE ____________ DAY OF _______________________ IN THE YEAR ______________________________
on behalf of: _________________________________________________________________________________
CONTENTS
PART A: SPECIFICATIONS
A13.8.1. SCOPE
A13.8.2 DEFINITIONS
A13.8.3 GENERAL
A13.8.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.8.5 MATERIALS
A13.8.6 CONSTRUCTION EQUIPMENT
A13.8.7 EXECUTION OF THE WORKS
A13.8.8 WORKMANSHIP
A13.8.2 DEFINITIONS
Concrete Barriers - a barrier is a concrete element which separates lanes of traffic (or pedestrians) in the same or opposing directions.
Parapets - a parapet is an element constructed on sides of bridges and other structures to prevent traffic from falling off where there is a vertical
drop.
Railings - railings manufactured from various materials are constructed along footwalks to prevent pedestrians from falling off where there is a
drop.
Transition Blocks - transition blocks are concrete members constructed between elements of different cross sections such as barriers, end
blocks, parapets, kerbs and channels etc.
Synthetic Fibre - is a geotextile fabric with a specific tensile strength and flow rate through the fabric to allow water to permeate through it but to
retain fine materials.
Copings - copings are concrete elements which are constructed on retaining walls, decks and footwalks as a finish to these members. Railings
in concrete or steel are cast into copings.
A13.8.3 GENERAL
The ancillary items for structures covered in this section consist of concrete elements constructed on site or elements which are precast
concrete, steel or other materials used for the construction or manufacture of the elements which are specified in this Chapter. All cast in situ
elements and manufactured items shall be constructed or manufactured as indicated on the drawings from materials as specified in of these
specifications or in other Chapter the relevant SANS, BS and EN specifications.
A13.8.5 MATERIALS
A13.8.5.1 Barriers, parapets, railings and sidewalks for structures.
a) Concrete
All concrete work shall be carried out in accordance with the requirements of Sections A13.2, A13.3 and A13.4.
b) Structural steel
Structural steel work shall comply with the provisions of Section A13.7.
c) Mortar
Mortar shall comply with the requirements of Clause A13.6.5.1g).
d) Painting
Painting shall comply with the requirement of Section A13.12.
The vertical posts and horizontal railing shall be cast on site or manufactured as detailed on the drawings and cast into the kerbs or footwalks of
DRAFT STANDARD (DS) OCTOBER 2020 13-118
the structure. Special attention shall be given to the top railing being erected to the line and level of the footwalks and railings as indicated on the
drawings. All the posts supporting the railings shall be vertical.
d) Numbers for structures
(i) Number plates
Number plates shall be fixed in the positions and according to the method of fixing shown on the drawings. Number plates shall be
cast from nonmetallic materials. The minimum overall thickness shall be 11 mm and a background plate with a minimum thickness
of 8,0 mm. The letter thickness shall not be less than 3,0 mm. Laminated PVC or other laminated materials shall not be permitted.
(ii) Painted numbers
The surface onto which the numbers are to be painted shall be prepared in accordance with the requirements of Section A13.12.
The background shall be of at least two coats of the prescribed paint. The letters and figures shall be in accordance with the
details given on the drawings and shall be written at the prescribed positions with a template.
(iii) Numbers shaped in concrete
Bridge numbers shall be placed and shaped in accordance with the requirements shown on the drawings. The minimum concrete
cover over the steel reinforcement behind the numbers shall not be less than the prescribed cover for the structural member in
question.
e) Concrete sidewalks
After completion of the prestressing and the removal of the formwork, the sidewalks and kerbing shall be constructed, but not before the bridge
deck has been accurately surveyed to establish final lines and levels after the falsework has been removed.
The previously cast bridge deck area shall be prepared as specified in Section A13.4 to receive the sidewalk concrete.
Forms shall be accurately set to the final lines and levels and shall be firmly held in position during the placing of the concrete. Stops at the
ends of sections shall be accurately placed to ensure that joints between adjacent sections will be truly perpendicular to the surface of the
concrete and at right angles to the edge of the road or to the skew angle of the deck at the expansion joint. All finishing chamfers shall be firmly
installed on formwork within final tolerance for completed concrete.
After removal of the forms, the exposed surfaces of the kerbs and copings shall be rubbed and finished in accordance with the requirements of
Clauses A13.2.7.4c) and (iii) and A13.2.7.2b). All edges shall be rounded to a radius of 20 mm unless otherwise shown on the drawings
f) Service Ducts in Sidewalks and Structures
When required, the Contractor shall construct service ducts for the easy installation and maintenance of existing, new and future services.
Service ducts shall be normal duty uPVC pipes in accordance with SANS 791. All pipes shall be joined with water tight couplings made of the
same material as the pipe. The couplings shall be adequate at expansions joints to provide for deck movements as detailed on the drawings.
All ducts shall be suitably fixed at 500 mm centres to prevent horizontal and vertical movement.
Duct ends shall be provided with suitable end caps to prevent material from entering the ducts.
Two stands 2,5 mm diameter galvanised steel wire shall be threaded through each duct and shall extend 3,0 m beyond each end.
g) Concrete surface finish requirements
All formed concrete surfaces shall have a class F3 surface finish as specified in Clause A13.2.7.2b) and all unformed concrete surfaces shall
have a class U3 surface finish in accordance with Clause A13.2.7.2c).
h) Transition blocks
Transition blocks shall be constructed in accordance with the details shown on the drawings.
A13.8.8 WORKMANSHIP
A13.8.8.1 Tolerances
The tolerances given below shall be the maximum permissible deviations from the specified dimensions, levels, alignment, positions, etc.,
shown on the drawings of the structures or structural members.
a) Chamfers
Fillets used for forming chamfers shall be within a tolerance of 1,0 mm in cross-sectional dimensions, and the actual chamfer on the concrete
shall not vary by more than 3,0 mm from the specified dimensions.
b) Barriers, parapets, railings, footwalks and kerbs.
The members shall be constructed within a tolerance ± 5,0 mm for all dimensions. The vertical and horizontal alignment shall not deviate from
the true alignment by more than 10 mm in any location, nor shall the alignment deviate by more than 5,0 mm from the true alignment over any
length of 5,0 m.
c) Service ducts
Service ducts shall be placed horizontally and vertically to a tolerance of 10 mm.
d) Brackets
Brackets shall be fixed to a horizontal tolerance of 20 mm.
e) Copings
Coping shall be constructed to an alignment tolerance of ± 10 mm and for level tolerance of ± 5,0 mm.
CONTENTS
B13.8.1 SCOPE
B13.8.2 DEFINITIONS
B13.8.3 GENERAL
B13.8.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.8.5 MATERIALS
B13.8.6 CONSTRUCTION EQUIPMENT
B13.8.7 EXECUTION OF THE WORKS
B13.8.8 WORKMANSHIP
B13.8.1 SCOPE
This Section covers:
a) The construction of barriers, parapets, railings and sidewalks on structures.
b) The construction and installation of drainage works such as weep holes, drainage pipes and gulley’s, no-fines concrete blocks, filter lining
and concrete channels; and.
c) The installation of bolt groups for electrification brackets.
d) The installation of service ducts
Part A is suitable for labour enhanced work.
B13.8.2 DEFINITIONS
The provisions contained in Part A shall apply.
B13.8.3 GENERAL
The provisions contained in Part A shall apply.
B13.8.5 MATERIALS
The provisions contained in Part A shall apply.
B13.8.8 WORKMANSHIP
The provisions contained in Part A shall apply.
The tendered rate for concrete parapets shall include full compensation for all concrete, formwork, service ducts, drawing wires and accessories.
The rates will exclude only the cost of reinforcing steel as this will be measured and paid for under another pay item.
The tendered rate shall also include for sealing of joints between barriers and parapet units as shown on the drawings.
The tendered rate shall include full compensation for all materials, labour, plant, and other incidentals required for constructing the end blocks
complete as specified excluding only reinforcing steel. The rate for end blocks shall also include all the attachment brackets, bolts and other
fixtures required to attach the steel traffic barriers to the end block. All barrier attachment brackets off the end block shall be measured under the
appropriate pay items in Chapter 4.
The tendered rate shall include full compensation for all labour, constructional plant, materials and all incidentals required for constructing the
transition blocks.
The tendered rate shall include full compensation for all labour, plant and materials (including reinforcing steel and prestressing requirements)
for the manufacture and erection of the precast concrete railings. The concrete railing shall include for fixing the concrete railing into the
sidewalk.
The tendered rate for steel railings shall include full compensation for all steelwork and corrosion protection, including fastenings, anchor bolts,
mortar bedding, etc, as may be required, and for erecting the steel railings, complete as specified.
The tendered rate shall include full compensation for procuring and installing service ducts, including, end caps, draw wires and complete
installation.
The tendered rates shall include full compensation for providing and installing either the number plates, or preparing the surface and painting
the numbers, or forming the numbers in concrete, and for all material, labour and equipment required in this connection.
C13.8.8 Cast in situ no-fines concrete (class of concrete indicated) cubic metre
The provisions of Clause A13.4.7.12f) and item C13.4.7.1 shall apply mutatis mutandis.
C13.8.9 Precast no-fines concrete units (class of concrete and description of unit) number (No)
The unit of measurement shall be the number of complete units of each size and type in position in the works.
The tendered rate for each precast concrete unit shall include full compensation for providing all the materials, labour, plant and formwork
required for manufacturing the unit complete as shown on the drawings and for transporting and placing the unit in position.
The tendered rates shall include full compensation for supplying all the materials, manufacturing and installing the pipes and making weep
holes.
The tendered rate shall include full compensation for providing all the material and manufacturing and installing the drainage inlets.
C13.8.12 Synthetic-fibre filter fabric (type indicated and description) square metre (m2)
The unit of measurement shall be the square metre of filter fabric installed as specified, including the specified overlap.
The tendered rate shall include full compensation for supplying, cutting and installing the filter fabric, and for waste material.
C13.8.13 Concrete channels adjoining structural works (size indicated) metre (m)
The unit of measurement shall be the metre of completed concrete channeling of each size constructed.
The tendered rate shall include full compensation for providing all the material, all labour, equipment and expenses required for completing the
work.
C13.8.14 Crushed stone in drainage strips (stone size indicated) cubic metre (m3)
The unit of measurement shall be the cubic metre of crushed stone placed in position as specified, in accordance with the details shown on the
drawings or instructed by the Engineer.
The tendered rate shall include full compensation for procuring, furnishing and placing the crushed stone, and for wrapping it in synthetic-fibre
geotextile as specified.
C13.8.15 Drainage strips (type, size and grade indicated) metre (m)
The unit of measurement shall be the linear metre of drainage strips placed at the structure / earth interfaces as shown on the drawing.
The tendered rate shall include full compensation for all material, labour, and equipment to supply and install the strips as shown.
The unit of measurement shall be the linear metre of perforated drainage pipes placed behind the earth faces as shown on the drawing.
The tendered rate shall include full compensation for all material, labour, and equipment to supply and install the perforated pipes as shown
including the 300 mm wide by 50 mm thick mortar bed under the core.
C13.8.17 Supplying and installing bolt groups complete with electrification brackets:
The tendered rates shall include full compensation for procuring and furnishing all materials, manufacturing, transporting and storing, and all
labour, constructional plant and materials required for installing the bolt groups as specified.
CONTENTS
D13.8.1 SCOPE
D13.8.2 GENERAL
D13.8.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.8.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.8.5 VISUALLY ASSESSED PROPERTIES
D13.8.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.8.7 EVALUATION FOR ACCEPTANCE
D13.8.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.8.9 NOTIFICATION OF REMEDIAL WORK
D13.8.10 REMEDIAL WORK
D13.8.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
D13.8.2 GENERAL
D13.8.2.1 Product conformance specifications
The Contractor shall within 28 days before manufacture submit to the Engineer conformance documentation related to the specifications. All
products used in the manufacture and installation of Ancillary Structural Elements shall be in compliance with the specifications contained in
Section A13.8.
Compliance documentation shall be provided for:
a) Concrete Pedestrian Railings.
b) Steel Pedestrian Railings.
c) PVC or Polyethylene Drainage Pipes.
d) Drainage Gullies
e) Synthetic-fibre filter fabric
f) Perforated PVC or Polyethylene pipes.
g) Bridge Number Plates.
CONTENTS
PART A: SPECIFICATIONS
A13.9.1 SCOPE
A13.9.2 DEFINITIONS
A13.9.3 GENERAL
A13.9.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.9.5 MATERIALS
A13.9.6 CONSTRUCTION EQUIPMENT
A13.9.7 EXECUTION OF THE WORKS
A13.9.8 WORKMANSHIP
A13.9.2 DEFINITIONS
A13.9.3 GENERAL
A13.9.5 MATERIALS
A13.9.5.1 Structural steel
Structural steel shall comply with the following requirements:
Mild steel: SANS 50025 (EN 10025) grade S275JR
High-yield stress steel: SANS 50025 (EN 10025) grade S355JR
The dimensions and properties of rolled steel sections shall comply with the prescriptions given in the structural steel tables issued by the SA
Institute of Steel Construction.
A13.9.5.4 Rivets
Mild-steel rivets shall comply with the requirements of SANS 1700-18. High-tensile rivets shall be so manufactured that they can be driven and
their heads formed satisfactorily without the physical properties of the steel being impaired.
A13.9.8 WORKMANSHIP
A13.9.8.1 Testing
a) Testing by the Engineer
The Engineer may nominate a testing authority to inspect the works and to conduct such tests as he may deem to be necessary to test
compliance with the specifications. Where required, test samples of welds shall be prepared by the Contractor, free of charge.
Payment for these tests shall be made under Section C20.1 of Chapter 20.
b) Process control
Welds shall be regularly inspected and tested by the Contractor in terms of his obligations in regard to process control, as described in Clause
A1.2.8.1 of Chapter 1. This shall include visual inspection of welds to ensure that no undercutting, uneven lengths, porosity, or evidence of
cracking occurs and that full fusion of the metals has been achieved. In doubtful areas, cores containing weld metal and adjacent parent
material shall, if so required by the Engineer, be cut out, polished and examined and the hole repaired.
At least 30 % of the welds shall be examined by ultrasonic or radiographic means. If more than 5 % of the examined welds show unsatisfactory
results, additional examinations covering all welds shall be performed. Certificates of the examination confirming that the steel plates and welds
comply with the requirements of SANS 15614 shall be submitted to the Engineer.
The cost of testing shall be deemed to be included in the rate tendered for item C13.9.1 Structural steel.
A13.9.8.2 Tolerances
The tolerances given below shall be the maximum permissible deviations from the specified dimensions, levels, alignment, positions, etc., shown
on the drawings of the structures or structural members.
a) General
The fabrication and assembly tolerances on all dimensions for structural steel shall be ± 2,0 mm. Holes for connections shall be drilled/punched
and aligned as specified in Clauses A13.9.7.1 d) and g) respectively.
b) Cross-section
The tolerances on cross-sectional dimensions of rolled sections shall be as specified in the Structural Steel Tables, published by the SA Institute
of Steel Construction.
CONTENTS
B13.9.1 SCOPE
B13.9.2 DEFINITIONS
B13.9.3 GENERAL
B13.9.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.9.5 MATERIALS
B13.9.6 CONSTRUCTION EQUIPMENT
B13.9.7 EXECUTION OF THE WORKS
B13.9.8 WORKMANSHIP
B13.9.1 SCOPE
This Section covers the manufacture, transport and erection of structural steelwork for minor structures, e.g. overhead road-sign structures. It
does not apply to major steel structures such as steel and composite steel bridges, which is covered in Section A13.12. Part A is suitable for
labour enhanced work at varying skill levels.
B13.9.2 DEFINITIONS
The provisions of Part A shall apply.
B13.9.3 GENERAL
The provisions of Part A shall apply.
B13.9.5 MATERIALS
The provisions of Part A shall apply.
B13.9.8 WORKMANSHIP
The provisions of Part A shall apply.
C13.9.2.1 (Description of each assembly, and grade/type of steel, diameter and length indicated) kilogram (kg)
C13.9.2.2 (Description of each assembly, and grade/type of steel, diameter and length indicated) number (No)
The unit of measurement shall be either the kilogram of installed anchor-bolt assemblies or the number of installed anchor-bolt assemblies.
The tendered rates shall include full compensation for the materials, fabrication, handling, transporting and installing the anchor-bolt assemblies,
including corrosion protection.
(a) (Type of metal and thickness or type symbol of coating indicated) ton (t)
(b) (Type of metal and thickness or type symbol of coating indicated) metre (m)
(c) (Type of metal and thickness or type symbol of coating indicated) number (No)
C13.9.3.2 Galvanising
The tendered rates shall be extra over the rates for item C13.9.1 and shall include full compensation for applying the specified corrosion
protection, including surface preparation, materials, labour, tools, equipment and all incidentals required.
Note:
CONTENTS
D13.9.1 SCOPE
D13.9.2 GENERAL
D13.9.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.9.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.9.5 VISUALLY ASSESSED PROPERTIES
D13.9.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.9.7 EVALUATION FOR ACCEPTANCE
D13.9.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.9.9 NOTIFICATION OF REMEDIAL WORK
D13.9.10 REMEDIAL WORK
D13.9.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part C only but includes all of the requirements in the
Contract Documentation.
D13.9.2 GENERAL
D13.9.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for:
a) Structural steel: each type and batch;
b) Other structural steel materials including bolts, nuts, washers, welding material, etc.;
c) Welding procedures; and
d) Certification of welders.
CONTENTS
PART A: SPECIFICATIONS
A13.10.1 SCOPE
A13.10.2 DEFINITIONS
A13.10.3 GENERAL
A13.10.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.10.5 MATERIALS
A13.10.6 CONSTRUCTION EQUIPMENT
A13.10.7 EXECUTION OF THE WORKS
A13.10.8 WORKMANSHIP
A13.10.2 DEFINITIONS
A13.10.3 GENERAL
A13.10.5 MATERIALS
Paints shall comply with the requirements of the following specifications:
A13.10.5.1 Primers
Wash primer (metal etch primer).......................................................................................................................................... SANS 723
Calcium-plumbate primer..................................................................................................................................................... SANS 912
Two-pack zinc-rich epoxy primer ......................................................................................................................................... SANS 926
A13.10.5.2 Undercoats
Undercoat ............................................................................................................................................................ SANS 681 (type II)
A13.10.5.4 Other
Epoxy-tar paints ...................................................................................................................................................... SANS 801 (type I)
Bonding liquid for concrete surfaces ...................................................................................................................................... CKS 564
Powder coating .................................................................................................................................................................. SANS 1274
Bituminous-emulsion paint shall consist of a stable bituminous emulsion with a minimum of 45 % of bitumen and about 5 % of approved fibre.
A13.10.8 WORKMANSHIP
A13.10.8.1 Measuring paint thicknesses
The dry-film thickness of paint shall be determined in accordance with SANS 2808.
At least 90 % of all thickness measurements shall comply with the minimum specified requirements. The thickness shall not in any case be less
than 70 % of the specified thickness.
In addition, painters shall be supplied with, and instructed to use, wet-film thickness gauges.
CONTENTS
B13.10.1 SCOPE
B13.10.2 DEFINITIONS
B13.10.3 GENERAL
B13.10.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.10.5 MATERIALS
B13.10.6 CONSTRUCTION EQUIPMENT
B13.10.7 EXECUTION OF THE WORKS
B13.10.8 WORKMANSHIP
B13.10.1 SCOPE
This Section covers the painting of structural steel to minor structures, guard rails, overhead road sign supports and other minor structures. Painting
of steel and composite steel bridges is covered in Section A13.12.
It excludes the corrosion protection of steel work exposed to aggressive or severe conditions.
This Section is suitable for labour enhanced construction activities and is subject to the Occupational, Health and Safety requirements,
particularly related to zinc chromate primers.
B13.10.2 DEFINITIONS
The provisions of Part A, shall apply, in addition to the following:
VOC = Volatile Organic Compounds
Low VOC paints contain < 50 g/litre of VOCs
B13.10.3 GENERAL
The provisions of Part A shall apply.
B13.10.5 MATERIALS
The provisions of Part A shall apply with the following amendments.
Paints shall comply with the requirements of the following specifications:
All primers, undercoats and paints shall contain low levels of Volatile Organic Compounds (VOC) and shall be non-toxic. Where toxicity or
absorption of the toxic element is low, such paints may be used provided that adequate precautions are taken during the application of the paints.
For labour enhanced work, Zinc-chromate primers for steel shall NOT be used. Alternatives such as zinc-phosphate primer shall be submitted
to the Engineer for approval.
An approved non-toxic primer shall be applied in accordance with the manufacturer’s instructions, for labour enhanced work.
C13.10.1 Painting:
The unit of measurement may also be the number of structures or articles painted, or a metre length of the structures or articles painted, or a ton of
the structures or articles painted, the quantities are calculated as specified in item C13.9.1.
The tendered rates shall include full compensation for surface preparation, applying all the coats of paint, repairing any damaged surfaces, and all
materials and construction plant necessary for completing the work.
CONTENTS
D13.10.1 SCOPE
D13.10.2 GENERAL
D13.10.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.10.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.10.5 VISUALLY ASSESSED PROPERTIES
D13.10.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.10.7 EVALUATION FOR ACCEPTANCE
D13.10.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.10.9 NOTIFICATION OF REMEDIAL WORK
D13.10.10 REMEDIAL WORK
D13.10.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part C only but includes all of the requirements in the
Contract Documentation.
D13.10.2 GENERAL
D13.10.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for:
a) Primers;
b) Undercoats; and
c) Finishing coats.
A13.11.2 DEFINITIONS
A13.11.3 GENERAL
The specification below in general refers to British and European Standards. Equivalent international standards will be accepted subject to the
Engineer’s approval.
A13.11.5 MATERIALS
A13.11.5.1 General
All steels shall comply with the requirements of EN 10025, EN 10113, EN 10137, EN 10155, EN 10210 or BS 7668 and cross referenced
Standards therein.
Compliance shall be demonstrated by satisfactory testing in accordance with the requirements of the above standards.
Rimming steel shall not be used.
All steels shall be manufactured to a process acceptable to the Engineer to give required material properties.
A13.11.5.5 Bolts
Unless noted otherwise on the Drawings all bolts incorporated in the permanent works shall be HSFG bolts and shall comply with BS 4395, AMD
1843 and BS 4604
As an alternative, equivalent bolts may be supplied in accordance with SANS 1282.
A13.11.8 WORKMANSHIP
A13.11.8.1 Welding
a) Weld procedures
Written weld procedures are required for all welds and shall be subject to approval by the Engineer.
The following items of information shall be provided as appropriate:
• Welding processes to be used in making the joint.
• Parent metal specification, thicknesses of plate, and geometry of proposed joint.
• Whether weld is to be performed on site or in the fabrication shop.
• Proposals for cleaning, inter-run cleaning.
• Details of type, size, classification, specification for electrodes and other consumables.
• For manual metal arc-welding details of electrode size, welding current, fillet weld leg length, number of runs and electrode run-out
length.
• For semi-automatic, automatic and mechanised welding, the size of electrode, welding current, arc voltage, travel speed, wire feed
speed, electrode extension or fillet weld leg length and number of runs, rate of flow of shedding gases, rates of consumption of other
process materials.
• The temperature and time adopted for drying and baking of welding consumables before use.
• Diagram to show edge preparation, fit-ups, approximate number and disposition of runs in multi-run welds.
• Jigging arrangements to hold respective pieces in the correct relationship.
• Tack welding.
• Backing strips, material, method of fixing.
• Welding positions.
• Welding sequence.
• Preheat temperature and interpass temperature range, methods of confirmation and maintenance of required temperatures.
• Back gouging.
• Post-weld heat treatment.
• Matters arising from restraint and effects on weld metal and parent plate.
• Matters in relation to fracture toughness of weld metal and heat affected zone.
• Procedures to avoid cracking of welds.
• Package of information from which welders will work which must be sufficiently comprehensive.
All weld procedures shall be carried out in accordance with EN 288 to the satisfaction of the Engineer to demonstrate that the Contractor can
produce satisfactory welds.
Before fabrication is commenced, welding trials shall be carried out using representative samples of materials to be used in the work, samples of
materials shall be subject to approval by the Engineer and have appropriate documentation.
Welding trials shall demonstrate to the satisfaction of the Engineer the procedures to be adopted in the fabrication of the work, and as a
minimum shall comply with the requirements of EN 1011 & EN 288
Where primers are to be applied to the work prior to fabrication, these shall be applied to the sample material before the procedure trials are
made. Where galvanising or other metal coating of the material is to be applied to a part which is to be subsequently welded in the shop or on
site, the same coating shall be applied to the sample material before the procedure trials are made.
DRAFT STANDARD (DS) OCTOBER 2020 13-152
b) Welder qualification and testing
The Contractor shall ensure that all welders he employs on the Works are competent and qualified to carry out welds in accordance with
approved welding procedures.
The Contractor shall ensure that welds will only be performed by welders qualified to each specific weld procedure.
Approval testing and certification of welders shall be in accordance with EN 287.
c) Identification of welds
The Contractor shall implement a system to enable welds to be traced to the welder by whom it was made.
Hard stamping of steel is not permitted.
d) Procedure trials
(i) Testing of welding for structural steels
Non-destructive and Destructive Testing
With the exception of all weld tensile tests, non-destructive and destructive testing of welding shall be carried out as specified in
EN 288. The root bend and face bend tests specified in EN 288 shall have the weld root and the weld face respectively in tension
as described in the transverse bend tests of EN 910. Additionally, hardness tests shall be carried out on weld metal, heat affected
zone and parent material of a macro section from each weld procedure test sample and the results recorded and submitted to the
Engineer.
Charpy V-Notch impact tests for butt welds and heat affected zones of butt welds shall be carried out as given below.
Weld Metal and Heat Affected Zone (HAZ) Charpy V-notch Impact Test Requirements for Tension Areas.
e) Butt welds including corner or T-Butt welds parallel or transverse to main tension stress.
The minimum Charpy energy absorption requirements and test temperature shall be the same as that specified for the parent material joined. In
the case of parent material on each side of the joint which have different specified Charpy requirements, the weld metal requirements shall be
those of the parent material with the lower test temperature or, in the event that the test temperatures are the same, the higher energy
absorption requirement.
f) Heat Affected Zone (HAZ)
The fusion boundary region of the HAZ of butt welds, including corner or T-butt welds, which are transverse to and carry the main tension stress
shall have the following notch ductility requirements:
Heat welding input up to and including 5 kJ/mm – no test requirement
Heat welding input over 5 kJ/mm – as per parent metal.
g) Location and orientation of specimens and orientation of notch.
For Charpy tests in the weld metal the length of specimen shall be taken transverse to the line of the weld and the specimens notched so that
the line of the notch root is perpendicular to the plate surface and is on the centre line of the weld joint.
For symmetrical and asymmetrical double V double J and double bevel joint preparations the specimen shall be cut so that one face is
substantially parallel to, and within 3,0 mm of, the surface of the weld.
Additionally, for the asymmetrical preparation the specimen shall be taken from the side with the smaller preparation.
For single V, singled and single level joint preparations the specimen shall be cut so that one face is substantially parallel to and within 3,0 mm
of the root surface of the weld.
For Charpy tests in the fusion boundary region of the HAZ, specimens shall be taken with their length transverse to the line of the weld and
notched so that the line of the notch root is perpendicular to the original plate surface.
As far as possible, the notch at mid-thickness of the specimen should lie on the fusion boundary of the HAZ of the weld under test. The
specimens shall be cut so that one face is substantially parallel to, and within 3,0 mm of, the original plate surface.
h) Number of specimens
Initially, three specimens for each weld or HAZ under consideration shall be taken and depending on the test results for these specimens, a
further three specimens may be taken from the same joint.
i) Testing and acceptance criteria
The initial three specimens shall be tested and if the average of the three impact test results is less than the specified minimum average values,
or if one individual result is less than 70 % of the specified minimum average value, or if two results are less than the specified minimum average
value, then three additional test pieces from the sample shall be tested and the results added to those previously obtained and a new average
value calculated.
The new average value shall not be less than the specified minimum average value.
Not more than three of the total of six results shall be less than the specified minimum average value, nor more than two results less than 70 %
of the specified minimum average value and no individual result shall be less than 50 % of the specified minimum average value.
If the results fail to comply with the above requirements, the procedures concerned shall be rejected.
The cause of failure shall be established and depending on the causes either the procedure shall be modified without necessitating a new
procedure test, as given in EN 288 or a new procedure shall be established and approved by the Engineer.
100% MPI
10% MPI
The fixing of studs after being welded in position shall be tested to the satisfaction of the Engineer by striking the side of the head of the stud
with a 2,0 kg hammer.
Any stud selected by the Engineer shall be capable of being bent by striking the side of the head of the stud with a 6,0 kg hammer until its head
is displaced approximately 0,25 times the height of the stud. The stud weld shall not show any signs of cracking or lack of fusion. Satisfactory
studs shall not be bent back. The Contractor shall ensure that the direction of the test does not interfere with the fixing of reinforcement.
Where studs fail the hammer ring test, the Contractor shall increase the number of shear studs on that element of steelwork by 10 % together
with replacing the faulty stud. The extra connectors shall be placed in positions agreed by the Engineer
A minimum of 1 % or 2 No, whichever is greater, of the studs attached to any one element of steelwork shall be tested.
Should a stud fail the bend test, 10 further studs shall be tested on the same item of steelwork. If any of the further studs fail the test, the
Contractor shall submit a revised weld procedure for approval and shall carry out weld procedure trial at his own cost.
Further to the requirements above, before the start of each day’s welding, three studs shall be welded to a plate of the same thickness as the
steelwork being worked on and tested in accordance with the above requirements. If any of these studs fail, a further set of three studs shall be
welded and tested until satisfactory results are obtained, before any studs are welded to the permanent steelwork.
n) Supervision
All welding shall be carried out under the control and supervision of appropriately qualified and experienced supervisory staff.
A13.11.8.2 Shopwork
a) Supervision
All fabrication and assembly shall be carried out under the supervision of suitably qualified and experienced staff with particular experience of
the type of fabrication and assembly required by this contract.
Proposals for supervision and management structure of the supervisory team shall be submitted to the Engineer for acceptance 6 weeks prior to
commencement of the fabrication process.
b) Dimension control
All measuring instruments shall be calibrated against reference standards acceptable to the Engineer.
The Contractor shall maintain a continuous record of calibration of each instrument; the Contractor shall submit for the Engineer's approval his
proposed method and programme for instrument servicing and control of calibration.
For each element a full record of dimensions, pre- and post fabrication shall be prepared by the Contractor and submitted to the Engineer.
These shall be provided for the Engineer's acceptance, and the Contractor shall provide full access and assistance to enable the Engineer to
check any dimensions as required.
The Contractor shall make due allowance in his programme for time required by the Engineer to check dimensions.
DRAFT STANDARD (DS) OCTOBER 2020 13-155
The accuracy of equipment for scanning imperfections shall be calibrated to 0,5 mm.
c) Fabrication Method Statement
The Contractor shall prepare a detailed method statement with explanatory diagrams to demonstrate his intended sequence of operations in
fabrication and assembly.
The method statement shall be submitted to the Engineer for approval, and shall be re-submitted if revisions are required by the Engineer.
The method statement shall be submitted at least six weeks prior to commencement of fabrication.
d) Traceability
The Contractor shall operate a full documentation and control system designed to ensure that all elements have full traceability from material
production through fabrication to final assembly, protective treatment, and erection.
Ingots, billets, slabs, plates, steel sections, bars and other products shall be clearly marked with identification marks to enable finished steel to
be traced to the cast from which it was made. Grades of steel shall be clearly identified.
The proposed system shall be subject to approval by the Engineer, and 6 weeks prior to commencement of work details of the proposed system,
including its supervision, shall be submitted.
The traceability system will be subject to independent audit by the Engineer.
Aspects covered by the traceability system shall be sufficient in extent to demonstrate adequate control.
The system shall embrace:
• production of steel plate
• marking of plate; control in stockyard
• sub-division of parent plate into sub-elements
• preparation
• dimensional control from material cutting through to final assembly, checking of dimensions at each stage
• welding process
• welder to weld identification
• electrode manufacture, storage and subsequent use
• Imperfections surveys
• Non-conformance controls and rectification
• Protective treatment
• Trial assembly
• Final assembly
• Erection
• All testing and inspection records
Further items as necessary are to be incorporated to ensure that all aspects of fabrication, assembly and erection are covered.
e) Inspection
The Contractor is responsible for preparation and implementation of an Inspection and Test Plan for the fabrication of all elements of the bridge.
The Inspection and Test Plan shall address all operations, stages involved, inspection and testing required at each stage, quantum of inspection
and testing to be carried out, the type of documentation record to be produced, hold points, and points for independent inspection and testing by
the Engineer.
The Inspection and Test Plan will be submitted to the Engineer for approval and identification of inspection and testing points required by the
Engineer 6 weeks prior to the commencement date of manufacturing.
CONTENTS
B13.11.1 SCOPE
B13.11.2 DEFINITIONS
B13.11.3 GENERAL
B13.11.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.11.5 MATERIALS
B13.11.6 CONSTRUCTION EQUIPMENT
B13.11.7 EXECUTION OF THE WORKS
B13.11.8 WORKMANSHIP
B13.11.1 SCOPE
This Section covers the manufacture, transport and erection of structural steelwork for major steel structures, e g steel bridge decks, composite
steel decks, and steel and composite steel cable-stay towers. It does not apply to minor steel structures such as sign gantries, which is covered
in Section A13.9. Due to the specialist nature of the activities associated with this work, it is deemed unsuitable for labour enhanced work.
B13.11.2 DEFINITIONS
The provisions of Part A shall apply with no additional requirements.
B13.11.3 GENERAL
The provisions of Part A shall apply with no additional requirements.
B13.11.5 MATERIALS
The provisions of Part A shall apply with no additional requirements.
B13.11.8 WORKMANSHIP
The provisions of Part A shall apply with no additional requirements.
CONTENTS
D13.11.1 SCOPE
D13.11.2 GENERAL
D13.11.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.11.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.11.5 VISUALLY ASSESSED PROPERTIES
D13.11.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.11.7 EVALUATION FOR ACCEPTANCE
D13.11.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.11.9 NOTIFICATION OF REMEDIAL WORK
D13.11.10 REMEDIAL WORK
D13.11.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part C only but includes all of the requirements in the
Contract Documentation.
D13.11.2 GENERAL
D13.11.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for:
(a) Structural steel: each type and batch;
(b) Other structural steel materials including shear studs, bolts, nuts, washers, welding material, etc.;
(c) Welding procedures; and
(d) Welder qualification and testing.
CONTENTS
PART A: SPECIFICATIONS
A13.12.1 SCOPE
A13.12.2 DEFINITIONS
A13.12.3 GENERAL
A13.12.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.12.5 MATERIALS
A13.12.6 CONSTRUCTION EQUIPMENT
A13.12.7 EXECUTION OF THE WORKS
A13.12.8 WORKMANSHIP
A13.12.2 DEFINITIONS
A13.12.3 GENERAL
The Specification below in general refers to European and British Standards. Equivalent international standards will be accepted subject to the
Engineer’s approval.
The Contractor shall establish implementation procedures which shall ensure the integrity of the protective treatment systems to be applied to
the various elements of the bridge. Both the supplier and applicator of the protective treatment shall have a quality system in accordance with
ISO 9001.
The Contractor shall prepare, for approval by the Engineer, method statements, procedures and Inspection and Test Plans covering each aspect
of protective treatment from paint manufacture (including paint manufacture quality control systems, testing and traceability), storage of paint,
paint system application procedure trials, the various stages of steel preparation, paint coat application, ambient conditions control, inspection,
testing, restoration and repair, compliance with all health and safety requirements and reporting of results.
Surface preparation and protection against corrosion of steelwork shall be carried out in accordance with the undernoted Clauses with due
account taken of the design and fabrication of the structure.
The Contractor shall establish measures to contain people, plant, materials, dust and debris during preparation and application of protective
coatings.
The particle size of metallic abrasive in plant or equipment shall not exceed the maximum of the relevant grade as specified above.
Before the start of blast cleaning and during blast cleaning the Contractor shall ensure that the abrasive is free from matter which could leave
detrimental contamination on the surfaces to be coated.
b) Surface preparation by abrading in the shops or on site
Any matter or paint which is difficult to remove by abrading alone shall be dislodged by scraping, by hand or power wire-brushing and shall be
completed before abrading the areas so affected.
Abrading shall be by use of abrasive paper or other material or a flexible abrasive disc mounted on a power driven flexible pad and may be used
to remove weld spatter. Wet abrading may be used for the preparation of finishes over sound undercoats, over unsound systems over
galvanising, or galvanising. Wet abrading shall not be allowed to come into contact with exposed thermally sprayed metal coatings.
All equipment, tools, abrasive sheets and discs and shall be suitable for the purpose. The use of hard grinding wheels for abrading shall not be
acceptable.
A burnished appearance caused by polishing in paint, rust or dirt shall not be accepted.
Corroded steel or unsound metal coatings which have been prepared by abrading to bright steel or bright metal coating, and blast cleaned,
where appropriate, shall be protected by the primer and next coat of the paint system prior to cleaning or preparation of adjacent surfaces.
c) Surface preparation by wet cleaning in the shops or on site
Wet cleaning shall be carried out by scrubbing with a stiff-bristled brush using water and an approved cleaning agent or a pressure washer and
immediately after cleaning, surfaces shall be thoroughly rinsed.
d) Surface preparation by dry cleaning in the shops or on site
Surfaces shall be cleaned by scrubbing with a dry stiff-bristled brush.
e) Surface preparation by dry blast cleaning on site
Metallic grit abrasives shall comply with section (a) of this Clause and shall be used for dry blast cleaning of small areas to be metal sprayed, as
at site welds, at areas prepared to clean steel or areas where a metal spray is to be restored, as indicated in Clause 13.12.7.4(b). The
Contractor shall ensure that the grade and particle shape of proposed non-metallic abrasives are adequate for the purpose intended: non-
metallic abrasives shall not be recycled.
f) Surface preparation by low or high pressure wet blast cleaning on site
Subject to the Engineer's approval an adjustable low pressure air/water/abrasive system shall be used with the air/water pressure at the nozzle
limited to 7,0 kgf/cm2 maximum and shall be fully adjustable. The quantity of non-metallic abrasive to be fed into the air/water mixture shall be
fully adjustable by remote control and the air, water abrasive mixture thoroughly mixed and projected by a single bore nozzle. Inhibitors shall not
be permitted.
Subject to the Engineer's approval an adjustable high pressure water system shall be used with the water pressure at the nozzle limited to 562
kgf/cm2 for high pressure or between 1750 and 2860 kgf/cm2 for ultra high pressure. The system shall incorporate a mechanical metering device
controlled by the operator at the nozzle, to regulate from zero to the maximum quantity of non-metallic abrasive being fed into the water.
g) Surface preparation by combined wet/dry blast cleaning on site
Wet blast cleaning using the low pressure air/water/abrasive system in compliance with the above Clauses shall be followed by dry blast
cleaning as specified above.
The specified standard of surface preparation shall be achieved by wet blast cleaning and washing; dry blast cleaning shall be used to remove
flash rusting or to restore surface preparation to the required standard.
A13.12.7.3 Workmanship standards for the surface preparation of steel by blast cleaning,
abrading, grinding and cleaning
The surface profile to be achieved by blast cleaning, either 'Fine', 'Medium' or 'Coarse', as appropriate, shall be within the limits set by the
Surface Profile Comparator for the Assessment of Abrasive Blast Cleaned Surfaces, conforming to EN ISO 8503: Part 1.
Blast cleaned surfaces shall be virtually free from sharp spikes of parent metal defined as 'rogue peaks' formed by the impact of abrasive
particles and which project above the blast cleaning profile. Any 'rogue peaks' which in the opinion of the Engineer would be detrimental to the
protective system shall be removed.
'Hackles' and inclusions caused by the rolling process, visible after blast cleaning, shall be removed. Affected surfaces shall be prepared by
grinding or abrading to bright steel in compliance with Clause A13.12.7.6 where appropriate. Sharp edges shall be rounded. If metal spray is to
be applied the surfaces shall then be blast cleaned.
Steel surfaces to be prepared by any of the methods described in the Contract shall be such that after surface preparation the surfaces are free
from detrimental contamination and conform to the following.
a) Visual cleanliness
Surface preparation by blast cleaning shall be to one or more of the following standards of visual cleanliness:
• 'Clean steel' SA3 to EN ISO 8501 – 1
Appearance: There shall be a blast cleaning pattern overall. The surface profile shall be free from mill scale, rust and foreign matter when
viewed through a X10 illuminated magnifying glass.
• 'Clean steel' SA2½ to EN ISO 8501 - 1
Appearance: There shall be a blast cleaning pattern overall. The surface profile shall be free from mill scale, rust and foreign matter when
viewed by normal vision.
• 'Bare Steel' (blast cleaned or abraded)
Appearance: The surface shall be free from all rust scale, loose rust and loose mill scale.
After surface preparation by blast cleaning to SA3 or SA2½ the surface profile shall be virtually free from embedded abrasive particles when
viewed through a 10X illuminated magnifying glass of a type approved by the Engineer. Surfaces assessed as unsatisfactory in this respect by
the Engineer shall be blast cleaned again with fresh abrasive. Another abrasive complying with the Specification may be used if necessary.
b) 'Harmful residues' or 'detrimental contamination':
Surfaces shall be deemed to be free from 'harmful residues' or 'detrimental contamination' after surface preparation when, in the opinion of the
Engineer, any such remaining matter will not reduce the required durability of the specified protective system.
c) 'Bright steel':
Surfaces free from defects or prepared to this standard by grinding or abrading shall have an overall bright appearance.
A13.12.7.4 Workmanship standards for the surface preparation of coated steelwork by blast
clearing, abrading, grinding and cleaning
a) Before overcoating
Before overcoating, surfaces shall be free from:
(i) any visible gloss which may, in the opinion of the Engineer, prevent adequate adhesion of the next coat
(ii) any unsound paint down to sound paint
(iii) any unsound paint down to clean steel
(iv) any unsound paint down to bright steel
(v) any unsound paint down to sound metal coating
(vi) any unsound paint down to bright metal coating
(vii) any unsound metal coating down to sound metal coating
(viii) any unsound metal coating down to bright metal coating
(ix) any unsound metal coating down to clean steel
(x) any unsound metal coating down to bright steel
(xi) detrimental contamination
Definitions of terms used in Clauses A13.12.7.5, A13.12.7.6 and A13.12.7.7 are as follows:
(i) 'Restored' coatings. When paint or similar coatings or metal spray coatings are to be restored, the standard of surface preparation and
coating material shall comply with the original standard. Damaged or failed paint systems over metal spray shall be restored using dry
blast cleaning. The thickness of any underlying metal spray or paint coating which may have been reduced in thickness during surface
preparation shall be brought up to specification.
(ii) 'Restored' surface preparation. The original standard shall be obtained. When further metal spray coating is to be applied, the surface
of the existing metal spray coating shall be restored by dry blast cleaning with metallic grit abrasive to sound metal coating.
(iii) 'Local failure'. An isolated breakdown of a protective coating or system due to extraneous causes excluding mechanical damage.
c) Permitted residual metal sprayed aluminium and zinc
When 'clean steel' is exposed through a metal spray coating during remedial surface preparation, remnants of sound aluminium metal spray
coating may, subject to the agreement of the Engineer, be retained in a blast cleaning profile; also, subject to the agreement of the Engineer, be
retained in a blast cleaning profile; also, subject to the agreement of the Engineer, traces of zinc metal may remain occluded within the surface
of a blast cleaning profile after the removal of a zinc metal spray coating.
A13.12.8 WORKMANSHIP
A13.12.8.1 Testing of metal spray coatings
At the start of the Works, and later at intervals specified by the Engineer (with the exception of coatings on steel in bearings, curved surfaces,
repairs to mechanical damage, local failure of metal spray at site joints or areas restored on site), the Contractor shall demonstrate by means of
a pull off test, of a type approved by the Engineer, that the minimum adhesion requirement is being attained. In the excepted areas the
Contractor shall demonstrate to the satisfaction of the Engineer that the adhesion is satisfactory when tested in accordance with EN 22063.
Areas affected by the tests shall be restored.
The pull off tests shall be carried out initially on panels 150 mm x 150 mm x 6,0 mm which are of the same grade of steel as the parent material
and which before blast cleaning had the same surface condition. The panels shall be blast cleaned and metal sprayed together with the parent
material to the same standard and using the same technique.
The Contractor shall make arrangements for the Engineer to witness the preparation of the panels and all testing. When instructed by the
Engineer, the Contractor shall carry out further tests on similarly prepared and metal sprayed panels.
If the adhesion requirement on any test panel is not met, the Contractor shall carry out a further test on the parent material adjacent to the panel
position. In the case of adhesion failure on the steelwork itself by either method of test, unsound metal spray coating shall be restored and the
tests repeated.
If more than two local areas of faulty adhesion occur on any one component, the whole of the metal spray coating on the component shall be
considered as having failed, and it shall be restored. Clause A13.12.7.4c) is not applicable in the case of adhesion failure.
6. DETAILS 1st Coat 2nd Coat 3rd Coat 4th Coat 5th Coat 6th Coat
Registered Description
Date Registered
Brand Name and Manftr's Ref No.
7. STRIPE COAT DESCRIPTION (including Item No and Colour) 8. PAINT MANUFACTURER'S OFFICIAL
STAMP:
Shop:
Site:
9. MINIMUM TOTAL DRY FILM THICKNESS OF PAINT SYSTEM (See Note) 10. APPROVED BY:
NOTE: The calculated sum of the mdft, neglecting the thickness of primers under 25 microns applied to blast cleaned steel, sealed or unsealed DATE:
aluminium metal spray, shall not be less than 84% of the minimum total dry film thickness of the paint system
CONTENTS
B13.12.1 SCOPE
B13.12.2 DEFINITIONS
B13.12.3 GENERAL
B13.12.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.12.5 MATERIALS
B13.12.6 CONSTRUCTION EQUIPMENT
B13.12.7 EXECUTION OF THE WORKS
B13.12.8 WORKMANSHIP
B13.12.1 SCOPE
This Section covers the protective treatment of structural steelwork for major steel structures, e g steel bridge decks, composite steel decks, and
steel and composite steel cable-stay towers. It does not apply to protective treatment of minor steel structures such as sign gantries, which is
covered in Section A13.10. Due to the specialised application and skill levels, Part A is not suitable for labour enhanced work.
B13.12.2 DEFINITIONS
The provisions of Part A shall apply with no additional requirements.
B13.12.3 GENERAL
The provisions of Part A shall apply with no additional requirements.
B13.12.5 MATERIALS
The provisions of Part A shall apply with no additional requirements.
B13.12.8 WORKMANSHIP
The provisions of Part A shall apply with no additional requirements.
CONTENTS
D13.12.1 SCOPE
D13.12.2 GENERAL
D13.12.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.12.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.12.5 VISUALLY ASSESSED PROPERTIES
D13.12.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.12.7 EVALUATION FOR ACCEPTANCE
D13.12.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.12.9 NOTIFICATION OF REMEDIAL WORK
D13.12.10 REMEDIAL WORK
D13.12.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part C only but includes all of the requirements in the
Contract Documentation.
D13.12.2 GENERAL
D13.12.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for:
Paint and similar protective coatings: each type and batch: Refer to the “Paint System Sheet”.
CONTENTS
PART A: SPECIFICATIONS
A13.13.1 SCOPE
A13.13.2 DEFINITIONS
A13.13.3 GENERAL
A13.13.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.13.5 MATERIALS
A13.13.6 CONSTRUCTION EQUIPMENT
A13.13.7 EXECUTION OF THE WORKS
A13.13.8 WORKMANSHIP
A13.13.2 DEFINITIONS
A13.13.3 GENERAL
A13.13.3.1 Method Statement and Procedural Manual
A detailed ‘Method Statement and Procedural Manual’ for the construction and launching of the deck shall be prepared and submitted to the
Engineer at least 56 calendar days before first segment is launched, for consideration and approval. It shall include, inter alia, a detailed
programme, details of the equipment and devices to be used including casting yard and launching anchors, anticipated maximum launching,
restraining and pull-back forces, launching girder design, details of the method to be used in measuring pier deflections, control measures,
monitoring systems and proposed emergency procedures.
A13.13.3.2 Superintendence
The Contractor’s representative shall be an ECSA registered Professional Engineer or Technologist, who is conversant with all aspects of the
incremental launching method of construction, in attendance for the full duration of construction up to completion of the expansion joint
installation.
An experienced surveyor, using precision survey equipment, shall be responsible for the setting out, level control of the temporary and
permanent work, and for controlling the launching alignment.
A13.13.3.4 Design
Details of the temporary work and, if required, supporting calculations, shall be submitted to the Engineer for consideration. Approval or
acceptance given by the Engineer for such designs and drawings will be subject to the provisions of Clause A1.2.4 of Chapter 1 of the Standard
Specifications.
A13.13.3.6 Programme
A programme for construction and launching of the deck, detailing the proposed construction cycle and the daily activities, the time and
sequence in which the concrete shall be placed and pre-stressed, and the curing period and method of curing to be used, shall be submitted to
the Engineer at least 56 days prior to commencement of the launched bridge construction.
A13.13.5 MATERIALS
The relevant Clauses of relevant Chapters of the Specifications shall be binding unless otherwise specified in this Section.
A13.13.6.3 Design
Sufficient jacking or restraining force for launching of the bridge deck shall be provided to overcome the most adverse combination of forces
arising from the frictional forces at the temporary bearings, the sliding resistance of the deck in the deck construction area, and the forces
associated with the gradient of the bridge deck, taking construction inaccuracies into account.
The launching, restraining or pull-back forces shall act directly on the deck through fail-safe mechanical means and shall not rely on friction.
The restraining capacity to be provided, shall have a factor of safety of 1,3 against uncontrolled sliding.
For design of the restraining or braking mechanism, the sliding friction coefficient shall be assumed to be zero.
A13.13.7.5 Platforms
At all of the supports, safe working platforms complete with access ladders and safety railings in compliance with current safety regulations and
OHS requirements shall be provided and maintained. The platforms shall not be removed before acceptance by the Engineer of the installation
of the permanent bearings and repair work to the supports.
Where necessary, access walkways to the platforms or direct access from the bridge deck shall be provided. If the platforms are damaged or
become unstable from any cause, they shall immediately be repaired at the Contractor’s expense.
If necessary, feeding trays for the elastomeric launching bearing pads shall be provided at each temporary bearing as part of the platform.
A13.13.7.7 Stays
Where shown on the drawings, high piers shall be stayed with staying cables symmetrically arranged around the centre of the pier. The stays
shall be positively anchored to the top of the pier in a position that will not interfere with the working platform and at the other end, to the
foundation of the adjacent pier. For each pier, the stays shall be simultaneously tensioned to a force that will limit the maximum pier deflection
under launching to within the specified value without overstressing the pier. If during launching the limiting deflections are exceeded, or if the
pier deflection is to be zeroed before installation of the permanent bearings, the stays shall be re-tensioned as directed by the Engineer.
A13.13.8 WORKMANSHIP
A13.13.8.1 Monitoring
In the context of this specification, monitoring shall include all those functions performed during the process of launching the deck, which inter
alia includes the jacking of the bridge deck, measuring of support deflections, communication facilities and safety measures to be applied.
A detailed description of the proposed monitoring, together with the system for recording the jacking or restraining forces, incremental launching
rate and the operation of the fail-safe systems, shall be submitted to the Engineer.
If the launching, restraining or pull-back force should vary disproportionately from the anticipated force at any instant, the jacking operation shall
be stopped immediately and the cause thereof ascertained and corrected before jacking is restarted.
A supervisor, who is fully conversant with the sliding operation, potential malfunctions, and concomitant risk, shall be stationed at each support
where sliding takes place. They shall be responsible for continuously monitoring the pier deflections during each launch, ensuring that the
monitoring system is functioning correctly, and must be in radio contact with the launch controller at all times during the launching operation. No
launch shall commence before radio contact has been established between the launch controller and each supervisor. In addition, a panic button
shall be installed at each bearing where sliding is taking place, which when activated will immobilise the jacking operation.
Monitoring data shall be submitted to the Engineer on a daily basis.
A13.13.8.2 Tolerances
It is in the Contractor’s interest to keep the tolerances as small as possible. This will reduce the loads and wear on the temporary works,
especially jacking forces and launching bearing pad wear.
a) Sliding surfaces in the deck casting area: These shall be checked and adjusted after each launch.
• Dimensions:
Width of the deck soffit on the plane of the side guides ................................................................................ ± 5,0 mm
Thickness of sliding formwork (Marineply) .................................................................................................... ± 1,0 mm
• Alignment:
Deviation of the centre line of the sliding surface from the specified line .... 1 in 1000 with maximum 5,0 mm deviation
• Levels:
Levels on a sliding surface ........................................................................................................................... ± 2,0 mm
Relative difference in level between two corresponding
DRAFT STANDARD (DS) OCTOBER 2020 13-185
points on two adjacent sliding surfaces ........................................................................................................... 1,0 mm
• Slope:
Slope in both directions on a sliding surface .................................................................................................. ± 0,1 %
b) Temporary bearings
• Position:
Transverse position of the side guides ......................................................................................................... ± 5,0 mm
Temporary bearings...................................................................................................................................... ± 5,0 mm
Elastomeric launching pads relative to deck soffit edge ................................................................................. ± 10 mm
• Levels:
Levels of bearings ........................................................................................................................................ ± 1,0 mm
Relative difference in level between the sliding surfaces
on corresponding bearings on consecutive piers, abutments or temporary supports ....................................... 4,0 mm
Relative difference in level between sliding surface on adjacent
bearings on the same pier, abutment or temporary support ............................................................................ 2,0 mm
• Slope:
Slope in both directions .................................................................................................................................. ± 0,1 %
• Dimensions:
Thickness of elastomeric launching bearing pads ........................................................................................ ± 1,0 mm
The thickness of the pads are to be accurately measured on site and similar thickness pads then used at each support.
Note: The cumulative effect of the tolerances listed in (1) and (2i) above shall not result in a relative difference of more than 5,0 mm in level
between two corresponding points on two adjacent sliding surfaces on the same pier, abutment or temporary support.
c) Jacks
Position: ............................................................................................................................................................... ± 25 mm
d) Launching girder nose
• Fabrication and assembly:
In accordance with Clause A13.11 of Chapter 13.
• Position:
Transverse position at deck connection ......................................................................................................... ± 10 mm
• Alignment:
Deviation of centre line of bottom flange from the specified line ... 3,0 mm over 12 m with maximum 5,0 mm deviation
Deviation of the front of the girder from the theoretical position during
launching, measured perpendicular and horizontally to the launching direction............................................ ± 100 mm
• Surface regularity:
Surface regularity of sliding surface ............................................................................................... 1,0 mm over 1,0 m
• Slope:
Slope in both directions on the sliding surface ................................................................................................ ± 0,1 %
CONTENTS
B13.13.1 SCOPE
B13.13.2 DEFINITIONS
B13.13.3 GENERAL
B13.13.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B13.13.5 MATERIALS
B13.13.6 CONSTRUCTION EQUIPMENT
B13.13.7 EXECUTION OF THE WORKS
B13.13.8 WORKMANSHIP
B13.13.1 SCOPE
This Section covers the requirements for the incremental launching method of construction for bridge decks, and includes temporary work (i.e.
all works temporary in nature and required for construction of the permanent works), launching of the deck segments and the permanent work
not covered elsewhere in the Standard Specifications. Although the labour component associated with the various construction activities is high,
it is deemed to be of a specialist nature and therefore not suitable for labour enhanced work.
B13.13.2 DEFINITIONS
The provisions of Part A shall apply with no additional requirements.
B13.13.3 GENERAL
The provisions of Part A shall apply with no additional requirements.
B13.13.5 MATERIALS
The provisions of Part A shall apply with no additional requirements.
B13.13.8 WORKMANSHIP
The provisions of Part A shall apply with no additional requirements.
The tendered lump sums shall include full compensation for the design, fabrication, supply and initial erection, for dismantling and re-assembly
and for the subsequent removal from site of the formwork assembly. The tendered amounts shall include the operation and maintenance of the
formwork assembly to achieve the required concrete finish. The internal and external formwork to the launched bridge deck shall not be
measured in other Sections: all formwork, concrete finish and curing costs shall be included in the pay items under Section A13.13, unless
measured elsewhere.
30 % of the rate will be paid when the formwork assembly is delivered to site, a further 60 % pro rata to physical progress with bridge deck
casting and the remaining 10 % when it is removed from site.
The tendered lump sums shall include full compensation for the design, supply and installation of the launching equipment, which includes
control and monitoring equipment, for dismantling and re-assembly and for the subsequent removal from site of the equipment.
50 % of the rate will be paid when the equipment is delivered to site, a further 40 % pro rata to successful bridge deck launching and the
remaining 10 % when it is removed from site.
The unit of measurement shall be the number of temporary supports. Note that a single temporary support as measured comprises both a
vertical and a horizontal temporary support component. At the permanent and temporary piers two temporary supports are generally required
per pier, and at least two sliding pads are required per temporary support.
The tendered amounts shall include full compensation for the design, fabrication, supply and installation of the temporary bearings and side
guides, for dismantling and re-erection and for the subsequent removal from site, and for the design, fabrication, supply and use of the launching
pads at each support, including the replacement of damaged launching pads.
C13.13.7 Platforms:
The unit of measurement shall be the number of access platforms and is equal to the number of permanent and temporary piers.
The tendered amounts shall include full compensation for the design, fabrication, supply and erection, for dismantling and re-erection, for the
DRAFT STANDARD (DS) OCTOBER 2020 13-189
subsequent dismantling and removal from site of the access platforms and for any repairs to holes and recesses in the piers required for the
support of the platforms.
80 % of the rate will be paid when the platforms are commissioned and the remaining 20 % when they are removed from site and the repairs to
the permanent works completed.
The unit of measurement shall be the number of piers/supports required to be stayed during the launching operation.
The tendered rate shall include full compensation for the supply, installation, tensioning, adjusting and subsequent removal of the stays, for the
anchorages and the anchorage reinforcing, for any temporary or permanent work required for the installation and for the subsequent repairs to
any holes and recesses.
80 % of the amount will be paid when the stay is satisfactorily installed. The remaining 20 % will be paid when the launching operation is
complete, the stay is disconnected, repairs completed to the pier and the stay moved to another position or removed from site.
The unit of measurement shall be the number of deck segments cast and launched regardless of the length of segment being launched.
The tendered rate shall include full compensation for the complete launching of the bridge deck segment, for the appropriate control measures,
measurement of pier deflections, the operation and maintenance of the equipment and instruments including the formwork assembly, for all
lubricants and any additional costs necessary for the execution of the work as well as for the management of the launching pads at the supports.
90 % of the amount will be paid when the segment is launched. The remaining 10 % will be paid when the concrete formed and unformed
surfaces has reached the required standard of finish.
The unit of measurement shall be the number of temporary piers provided. A temporary pier shall include all piles, pile cap, columns and bracing
required. Two columns are usually required per temporary pier.
The tendered rate for temporary piers shall include full compensation for all concrete, structural steel, formwork and reinforcement steel and for
all other materials, labour, plant and other incidentals required for constructing the temporary piers complete, and for demolition of the temporary
piers and temporary pilecaps after use. All works including concrete and reinforcement shall be removed to a minimum depth of 1,5 m below
ground level.
80 % of the amount will be paid once the temporary pier is constructed. The remaining 20 % will be paid once the temporary pier is removed.
CONTENTS
D13.13.1 SCOPE
D13.13.2 GENERAL
D13.13.3 PERFORMANCE GUARANTEE REQUIREMENTS
D13.13.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D13.13.5 VISUALLY ASSESSED PROPERTIES
D13.13.6 INSTRUMENTALLY ASSESSED PROPERTIES
D13.13.7 EVALUATION FOR ACCEPTANCE
D13.13.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D13.13.9 NOTIFICATION OF REMEDIAL WORK
D13.13.10 REMEDIAL WORK
D13.13.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part C only but includes all of the requirements in the
Contract Documentation.
D13.13.2 GENERAL
D13.13.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related
to the specifications.
Conformance documentation shall be provided for:
a) Structural steel launching girder
b) Temporary Bearings.
CONTENTS
PART A: SPECIFICATIONS
A13.14.1 SCOPE
A13.14.2 DEFINITIONS
A13.14.3 GENERAL
A13.14.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A13.14.5 MATERIALS
A13.14.6 CONSTRUCTION EQUIPMENT
A13.14.7 EXECUTION OF THE WORKS
A13.14.8 WORKMANSHIP
A13.14.2 DEFINITIONS
The following definitions shall apply to these specifications:
Jacked structures - includes all structures that are constructed either partially or completely and are then jacked into their final position into or
under road embankments.
Cable support systems for structures can range from minor cable support systems for bridges to major cable stayed bridges.
Other specialist bridges including balanced cantilever and other complicated structures.
A13.14.3 GENERAL
The construction of specialist structures shall be carried out in terms of world best practice for the construction of these structures and specialist
specifications shall be included in the Contract Documentation which shall replace this Section as applicable.
A13.14.5 MATERIALS
A13.14.8 WORKMANSHIP
COTO
Committee of Transport
Officials
Published by:
The South African National Roads Agency SOC Limited
PO Box 415, Pretoria, 0001
Disclaimer of liability:
The document with its Chapters is provided as a Draft Standard (DS) without any warranty of any kind, expressed or implied.
No warranty or representation is made, either expressed or implied, with respect to fitness of use and no responsibility will be
accepted by the Committee or the authors for any losses, damages or claims of any kind, including, without limitation, direct,
indirect, special, incidental, consequential or any other loss or damages that may arise from the use of the document.
Existing publication:
The new COTO Standard Specifications for Road and Bridge Works for South African Road Authorities was approved by
COTO on 18 August 2020 as a Draft Standard (DS) and will be replacing the COLTO Standard Specifications for Road and
Bridge Works for State Road Authorities (1998 Edition).
Existing contracts and tenders in the design phases based on the COLTO Standard Specifications (1998 Edition) will remain
unaffected but will be phased out during the next 6 months and the COTO Standard Specifications (2020 Edition) will be
mandatory for use in procurement documents advertised as from 1 March 2021.
Document versions:
Draft Standard (DS). The Draft Standard will be implemented in industry for a period of two (2) years, during which written
comments may be submitted to the COTO subcommittee. Draft Standards (DS) have full legal standing.
Final Standard (FS). After the two-year period, comments received are reviewed and where appropriate, incorporated by the
COTO subcommittee. The document is converted to a Final Standard (FS) and submitted by the Roads Coordinating Body
(RCB) to COTO for approval as a final standard. This Final Standard is implemented in industry for a period of five (5) years,
after which it may again be reviewed. Final Standards (FS) have full legal standing.
Comments:
Comments on the Draft Standard Chapters should be provided in writing on the Excel spreadsheet provided on the websites
mentioned below and e-mailed to cotorevision@nra.co.za .
Please note:
This document and its various Chapters will only be available in electronic format.
The Draft Standard (DS) Chapters will be made available for download on the South African National Roads Agency SOC Ltd
(SANRAL) and Department of Transport websites.
August 2020 version replaced with October 2020 version due to amendments to Chapters.
TABLE OF CONTENTS
CHAPTER 14: REPAIR AND REHABILITATION OF STRUCTURES ................................................................. 14-1
14.1 ACCESS FOR BRIDGE REHABILITATION .................................................................................................. 14-1
PART A: SPECIFICATIONS ............................................................................................................................................................................ 14-1
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................... 14-4
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................... 14-5
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ....................................................................................................................... 14-8
14.2 CORROSION SURVEY METHODS AND TESTING OF NEAR SURFACE CONCRETE PROPERTIES.... 14-9
PART A: SPECIFICATIONS ............................................................................................................................................................................ 14-9
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................. 14-13
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 14-14
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 14-16
14.3 DEMOLITION AND REMOVAL OF STRUCTURAL CONCRETE AND STEELWORK ............................. 14-17
PART A: SPECIFICATIONS .......................................................................................................................................................................... 14-17
PART B: LABOUR ENHANCEMENT ............................................................................................................................................................. 14-20
PART C: MEASUREMENT AND PAYMENT .................................................................................................................................................. 14-21
PART D: GUARANTEES AND COMPLIANCE CERTIFICATES ..................................................................................................................... 14-23
CONTENTS
PART A: SPECIFICATIONS
A14.1.1 SCOPE
A14.1.2 DEFINITIONS
A14.1.3 GENERAL
A14.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A14.1.5 MATERIALS
A14.1.6 CONSTRUCTION EQUIPMENT
A14.1.7 EXECUTION OF THE WORKS
A14.1.8 WORKMANSHIP
A14.1.2 DEFINITIONS
Temporary works - shall be necessary for access to the work area and includes all foundations, scaffolding and support structures, working
platforms, cradles, fixtures to existing structural members, etc. required for the safe access to and execution of the work.
Mobile access unit - consists of a vehicle-mounted access gantry and work platform, including mobile crane type units.
Location - means a specific structure as a whole where rehabilitation work has to be carried out.
Structural element - shall be that particular part or parts of a structure, bridge, culvert, retaining wall, traffic barrier, gantry or light mast as
specified or indicated on drawings.
• Bridge elements consist of abutments, piers, foundations, piles, decks, parapets, bearings and joints.
• Culvert elements consist of floors, walls and decks.
• Retaining wall elements consist of foundations and walls.
• Median barriers consist of foundations and barrier walls.
• Gantries consist of foundations, stub column and masts.
Setting up at each structural element shall include all movement required from point to point on a particular element.
Screening the work - suitable metallic or non-metallic grids, boarding or fabric membranes shall be used to screen the work area and to
prevent falling debris from endangering the persons in the work area.
A14.1.3 GENERAL
The Contractor shall provide and will be responsible for safe access structures and work platforms to all areas or structural elements requiring
remedial work. The access and temporary works shall be designed, constructed and maintained in accordance with the current relevant safety
regulations, all in compliance with the Occupational Health and Safety Act and its applicable Regulations, and shall remain in place until removal
is authorised by the Engineer. Appropriate allowances shall be made for screening of the work and other protective measures required by the
various work activities.
A14.1.4.2 Falsework
The Contractor shall make his own assessment of the allowable bearing pressure on the foundation material and shall design the footings and
falsework to prevent overloading, differential settlement and unacceptable overall settlement. In assessing the allowable bearing pressure, due
account shall be taken of the effect of wetting on the foundation material.
The Contractor’s falsework designer shall take account of the location of the structure and the possible ingress of water from sources such as
watercourses, water table and saturation due to rainfall and assess the resulting effects in bearing capacity.
In designing the falsework, cognizance shall also be taken of the redistribution of load which may occur on account of the effect of temperature,
wind force, flooding and debris.
Cognizance shall also be taken of the lateral forces which may be induced by earth platforms, required for the support of falsework on the
substructures resulting in temporary or permanent stresses for which the existing sub-structures have not been designed.
Particular attention shall be given to providing transverse and diagonal bracing as well as rib stiffeners on cross bearers.
A14.1.5 MATERIALS
All timber, structural steel and scaffolding used shall be free from defects that may prejudice the stability of the working platform(s) and access
structures. All materials used for temporary access shall be certified and approved by the designer and copied to the Engineer. The jacks,
devices, clamps and fittings shall all be in good working order and of adequate design and strength.
The type, grade and condition of the material shall be subject to the designer’s approval and submitted to the Engineer for the record.
A14.1.8 WORKMANSHIP
The Contractor shall, prior to dispatching the mobile access unit to the site, provide certification from the manufacturer or the operating authority
that the unit has been thoroughly inspected and serviced, that the unit is functioning properly and that it complies with the relevant safety
regulations and that the operator has been certified to operate the unit. After the erection for access purposes and before usage by the
workmen the works shall be certified by the designer in terms with compliance with the specifications and is suitable for its intended use. A copy
of the certification shall be delivered to the Engineer.
CONTENTS
B14.1.1 SCOPE
B14.1.2 DEFINITIONS
B14.1.3 GENERAL
B14.1.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B14.1.5 MATERIALS
B14.1.6 CONSTRUCTION EQUIPMENT
B14.1.7 EXECUTION OF THE WORKS
B14.1.8 WORKMANSHIP
B14.1.1 SCOPE
Access for bridge rehabilitation through mechanised means, is deemed to be specialised activity and generally not suitable for labour enhanced
work, however the traffic accommodation related to access requirements can be considered to be a labour enhanced activity and is covered
under Section B1.1 of Chapter 1. The temporary works associated with scaffolding and platform erection is executed by labour with the relevant
skills set and is deemed to be a labour enhanced activity.
B14.1.2 DEFINITIONS
The provisions of Part A shall apply.
B14.1.3 GENERAL
The provisions of Part A shall apply.
B14.1.5 MATERIALS
The provisions of Part A shall apply.
B14.1.8 WORKMANSHIP
The provisions of Part A shall apply.
C14.1.2.1 Establishment of mobile access unit on site (description of type of unit) lump sum
C14.1.2.2 Setting up of mobile access unit at each structure location and removal after completion number (No)
C14.1.2.3 Operation of mobile access unit during repair work at each location (structure) days
C14.1.2.4 Operation of mobile access unit during inspections by the Engineer hours (h)
C14.1.2.5 De-establishing and removal of mobile access unit from site after completion of work lump sum
The unit of measurement for each item shall be the lump sum, number, days or hours as indicated and shall be paid proportionately as the work
progresses.
The tendered amounts and rates shall include full compensation for all labour, plant and equipment required to procure, transport to site and to
establish the mobile access unit including all costs related to inspection, operation and maintenance of the unit on site.
The tendered rate for items C14.1.2.1 to C14.1.2.5 shall cover all costs necessary for establishing and de-establishing of the mobile access unit
on site.
The tendered rate for item C14.1.2.2 shall cover the cost for setting up of the mobile unit at each of the number of locations scheduled, and
removal after completion of the work at the location.
The tendered sum for item C14.1.2.3 shall cover all costs for operating the mobile access unit on location for the full time required to complete
the repairs.
The tendered rate for item C14.1.2.4 shall cover the cost of operation of the mobile access unit as required by the Engineer. No payment shall
be considered for this item if the Engineer requires the use of the mobile access unit while it is on location for the normal work to be done under
the contract and not specially re-established on the location for the purpose of inspection only.
Items C14.1.2.1 and C14.1.2.5 shall not apply to times when the mobile access unit is in operation on site for the repair works when it is possible
to be simultaneously also be used for inspection by the Engineer. The Contractor is to co-ordinate with the Engineer to ensure no unnecessary
establishment or de-establishments.
C14.1.3 Access at end of defects liability period (description of location) lump sum
The unit of measurement shall be the lump sum for access to each site or structural elements at the end of the Defects Liability Period as
ordered by the Engineer.
The tendered amount shall include full compensation for all labour, material, plant or equipment including plant operators required to provide
suitable and safe access for the Engineer to carry out the necessary inspections as measured in the pricing schedule.
A prime cost sum is provided in the pricing schedule to cover the cost of the attendance as required and approved by the Engineer.
Payment for obtaining this service shall be in accordance with the provisions of the General Conditions of Contract.
The unit of measurement shall be the lump sum for each complete safety gantry erected.
The tender amount shall include full compensation for design supply, fabrication, erection, dismantling and for all labour materials and plant or
equipment required fabricate, supply, erect and dismantle the safety gantry in its location as specified.
CONTENTS
D14.1.1 SCOPE
D14.1.2 GENERAL
D14.1.3 PERFORMANCE GUARANTEE REQUIREMENTS
D14.1.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D14.1.5 VISUALLY ASSESSED PROPERTIES
D14.1.6 INSTRUMENTALLY ASSESSED PROPERTIES
D14.1.7 EVALUATION FOR ACCEPTANCE
D14.1.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D14.1.9 NOTIFICATION OF REMEDIAL WORK
D14.1.10 REMEDIAL WORK
D14.1.1 SCOPE
The scope of this Section covers the following:
• Product conformance specifications
• Warranties for product or element design and installation of proprietary systems
• Performance specifications
Note that the requirements for performance specifications are not limited to that given in Part A only but includes all of the requirements in the
Contract Documentation.
D14.1.2 GENERAL
D14.1.2.1 Product conformance specifications
The Contractor shall, within 28 days of entering into the contract with the Employer, submit to the Engineer conformance documentation related to
the specifications.
Conformance documentation shall be provided for:
a. Scaffolding members.
b. Timber scaffolding members.
c. Jacks, devices, clamps and fitting.
d. Mobile Platform / Hanging Access Platform Certificates.
The Contractor shall accept full responsibility for the design, erection, usage and removal of the plant and equipment from site after completion.
CONTENTS
PART A: SPECIFICATIONS
A14.2.1 SCOPE
A14.2.2 DEFINITIONS
A14.2.3 GENERAL
A14.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A14.2.5 MATERIALS
A14.2.6 CONSTRUCTION EQUIPMENT
A14.2.7 EXECUTION OF THE WORKS
A14.2.8 WORKMANSHIP
A14.2.2 DEFINITIONS
A14.2.3 GENERAL
The Engineer will specify what provision must be made to inspect and survey exposed concrete surfaces via a sampling plan. The Contractor
shall carry out appropriate in situ or laboratory tests as stipulated in the sampling plan to determine appropriate remedial work. The Contractor
shall make allowance in his programme for the time required to carry out surveys, laboratory tests and the reporting of results prior to
commencing with repairs.
The Contractor shall provide suitable and safe access to enable the Engineer to carry out a close inspection of all specified concrete surfaces.
General access requirements shall be measured and paid for under Section A14.1.
A14.2.5 MATERIALS
All materials utilised to repair any survey or testing locations, shall comply with the requirements of Section A14.4 or as directed by the
Engineer.
The following chemicals shall be standards for testing concrete according to the standard methods presented in this Section:
A14.2.8 WORKMANSHIP
The Contractor shall prepare an agreed reference grid of lines on the concrete surface to be tested and the Engineer will supply the design
sampling plan. The location of each test, as amended by the Contractor, shall be recorded on an approved reference drawing along with the
processed test result. All substandard areas or areas of potential contamination or corrosion risk shall be agreed with the Engineer and marked
on the structure by the Contractor.
CONTENTS
B14.2.1 SCOPE
B14.2.2 DEFINITIONS
B14.2.3 GENERAL
B14.2.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B14.2.5 MATERIALS
B14.2.6 CONSTRUCTION EQUIPMENT
B14.2.7 EXECUTION OF THE WORKS
B14.2.8 WORKMANSHIP
B14.2.1 SCOPE
This Section covers the test methods and requirements to determine cover over reinforcement and to evaluate specific concrete properties. Due
to the specialised nature of the activities it is not suitable for labour enhanced work.
B14.2.2 DEFINITIONS
The provisions of Part A shall apply with no additional requirements.
B14.2.3 GENERAL
The provisions of Part A shall apply with no additional requirements.
B14.2.5 MATERIALS
The provisions of Part A shall apply with no additional requirements.
B14.2.8 WORKMANSHIP
The provisions of Part A shall apply with no additional requirements.
C14.2.1.3 using extracted core samples (description of location, core size and length) number (No.)
C14.2.1.4 using extracted core samples (description of location, core size and length) metre (m)
The unit of measurement shall be the square meter area of delamination tests carried out in accordance with Clause A14.2.7.1 or the number or
metre length of concrete core.
The tendered rate shall include full compensation for all labour, material and testing equipment, transport to a laboratory, preparation of the
sample and testing, data capturing and data processing required to execute the work and the recording and presentation of results, including
furnishing of record drawings, and the repair of all specimen and test locations.
C14.2.3.1 using extracted core samples (description of location, core size and length) number (No)
C14.2.3.2 using extracted core samples (description of location, core size and length) metre (m)
The unit of measurement shall be the number or metre length of concrete core, transport to a laboratory, preparation of the specimen and
testing, in accordance with Clause A14.2.7.3. The tendered rate shall include full compensation for all labour, material and testing equipment
required to execute the work, the recording and reporting of results, including furnishing of record drawings, and the repair of all specimen and
test locations.
Item Description Unit
C14.2.4.1 using extracted core samples or fragment removed for (description of location on structure) number (No)
The unit of measurement shall be the number of carbonation tests carried out in accordance with Clause A14.2.7.4a).
The tendered rate shall include full compensation for all labour, material and testing equipment required to execute the work, the recording of
results, including furnishing of record drawings, and the repair of all specimen and test locations.
C14.2.5.1 using extracted core samples or fragment removed for (description of location on structure) number (No)
The unit of measurement shall be the number of chloride tests carried out in accordance with Clause A14.2.7.4b).
The tendered rate shall include full compensation for all labour, material and equipment required to execute the work including all testing and
reporting by an approved laboratory, including furnishing of record drawings, and the repair of all specimen and test locations.
The unit of measurement shall be the square metre of concrete surface where corrosion rates are determined in accordance with Clause
A14.2.7.5c).
The tendered rate shall include full compensation for all labour, material and equipment required to execute the work including all connections to
the reinforcement, testing and reporting by an approved specialist or laboratory, including furnishing of record drawings, and the repair of all
specimen, reinforcement connections and test locations.
CONTENTS
D14.2.1 SCOPE
D14.2.2 GENERAL
D14.2.3 PERFORMANCE GUARANTEE REQUIREMENTS
D14.2.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D14.2.5 VISUALLY ASSESSED PROPERTIES
D14.2.6 INSTRUMENTALLY ASSESSED PROPERTIES
D14.2.7 EVALUATION FOR ACCEPTANCE
D14.2.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D14.2.9 NOTIFICATION OF REMEDIAL WORK
D14.2.10 REMEDIAL WORK
CONTENTS
PART A: SPECIFICATIONS
A14.3.1 SCOPE
A14.3.2 DEFINITIONS
A14.3.3 GENERAL
A14.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A14.3.5 MATERIALS
A14.3.6 CONSTRUCTION EQUIPMENT
A14.3.7 EXECUTION OF THE WORKS
A14.3.8 WORKMANSHIP
A14.3.2 DEFINITIONS
Concrete and steel members or elements:
a) All references to concrete members shall include mass concrete, un-reinforced, reinforced and prestressed concrete members.
b) References to steel members shall include all structural steel members in structures.
Demolition of concrete and steel members or elements:
Demolition means the breaking up and removal of an entire concrete member or portion of a member or demolition and removal of an entire
structural steel member or element.
Removal of concrete and steel members or elements:
a) Removal of concrete means cutting back into the surface or end of a concrete element and the removal of unsound, damaged or
contaminated concrete, or the partial removal of concrete sections, to expose a sound surface for bonding new material for the repair or
extension of the concrete element.
b) Removal of steel members or elements means the cutting out of a steel member or element out of a steel structure.
A14.3.3 GENERAL
A14.3.3.1 Concrete members and elements
The work is this chapter includes the demolition of concrete members or elements either completely or partially. Complete demolition is usually
carried out for the replacement of a member or element of a structure in its entirety and partial demolition of member or element is carried out for
alterations or extensions to a structure.
Removal of small areas of concrete in partial demolitions is carried out for repairs of concrete members or elements.
A14.3.5 MATERIALS
All materials used in the demolition and removal of concrete elements, shall be handled, stored and used strictly in accordance with the
manufacturer’s instructions and the current Occupation Health and Safety Act and its regulations.
A14.3.7.7 Preparation of exposed contact surfaces (for extension of existing concrete elements
or construction of new concrete members)
All loose and shattered concrete, as well as foreign material such as oil, paint, grease, etc. shall be removed from the contact surface of old
concrete before new concrete is placed. The aggregate must be exposed to provide a good bonding surface.
The mechanically prepared concrete surface shall be cleaned by means of grit blasting or water jetting.
The breaking out and preparation of damaged, spalled and/or cracked concrete surfaces is described and measured under Sections A14.3 and
A14.4.
A14.3.8 WORKMANSHIP
A14.3.8.1 Tolerances
The Contractor shall remove concrete to a planar, uniform surface with 25 mm maximum deviation from the level or dimension indicated on the
drawings unless otherwise approved by the Engineer. The outer edge of the contact surface shall consist of straight lines with maximum
deviation of 5,0 mm from straight, measured with a 1,0 m long straight edge, and shall be within 5,0 mm of the position indicated on the
drawings, or as instructed by the Engineer. Steel members to be removed shall be cut out and replaced to a tolerance of 2,0 mm and then be
welded or bolted into position.
A14.3.8.2 Trials
The Contractor shall carry out pre-construction trials with the proposed equipment to determine the suitability of the technique for the envisaged
application. The results shall be reported to the Engineer and shall be subject to the Engineer’s approval before the inclusion of such equipment
into the method statement for the execution of the works.
DRAFT STANDARD (DS) OCTOBER 2020 14-19
B14.3 DEMOLITION AND REMOVAL OF STRUCTURAL CONCRETE AND
STEELWORK
PART B: LABOUR ENHANCEMENT
CONTENTS
B14.3.1 SCOPE
B14.3.2 DEFINITIONS
B14.3.3 GENERAL
B14.3.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
B14.3.5 MATERIALS
B14.3.6 CONSTRUCTION EQUIPMENT
B14.3.7 EXECUTION OF THE WORKS
B14.3.8 WORKMANSHIP
B14.3.1 SCOPE
This Section covers the work in connection with the demolition of entire members of a concrete structure as well as cutting back concrete to
expose reinforcement and the initial preparation of the exposed surface. Surface and structural repair of concrete members is covered in
Section A14.4. This Section also covers the demolition and removal of steel structures and members. It is suitable for labour enhanced work.
This part covers additional specifications to optimise the labour component of construction activities.
The removal of concrete for labour enhanced activities is limited to a surface area of 2,0 m2.
B14.3.2 DEFINITIONS
The provisions of Part A shall apply.
B14.3.3 GENERAL
The provisions of Part A shall apply, in addition to the following:
All concrete shall conform to the requirements of Section A13.4 of Chapter 13.
The demolition of discrete structural elements shall employ techniques that do not damage adjacent structures or structural components, nor
contaminate the surrounding environment.
The Contractor shall ensure that any nuisance associated with his work activity is minimized by implementing appropriate precautions and
measures. Common nuisances associated with demolition and concrete removal include fumes, noise, dust, flying fragments, heat and
vibration.
Water jet removal of concrete is preferred wherever possible. Demolition using explosives is not permitted.
B14.3.5 MATERIALS
The provisions of Part A shall apply.
B14.3.8 WORKMANSHIP
The provisions of Part A shall apply.
C14.3.1.1 Full member or element (location and description) cubic metre (m³)
C14.3.1.2 Partial member or element (location and description) cubic metre (m³)
C14.3.2.1 Full member or element (location and description) cubic metre (m³)
C14.3.2.2 Partial member or element (location and description) cubic metre (m³)
The unit of measurement for items C14.3.1 and C14.3.2 is the cubic metre of concrete demolished, measured in its original position and shape
based on either full or partial demolition.
The tendered lump sum shall include full compensation for establishment on the site and the subsequent removal of all special equipment
and plant for the high pressure water demolition of defective concrete, the cost of which does not vary with the actual amount of work to be
done.
This work will be paid for by way of a lump sum, 75 % of which will become payable when all the equipment is on the site. The remaining 25
% will become payable after all the water demolition of concrete has been completed and the equipment has been removed from the site.
CONTENTS
D14.3.1 SCOPE
D14.3.2 GENERAL
D14.3.3 PERFORMANCE GUARANTEE REQUIREMENTS
D14.3.4 FUNCTIONAL PERFORMANCE ASSESSMENTS
D14.3.5 VISUALLY ASSESSED PROPERTIES
D14.3.6 INSTRUMENTALLY ASSESSED PROPERTIES
D14.3.7 EVALUATION FOR ACCEPTANCE
D14.3.8 ADDITIONAL PROCEDURES TO BE ADOPTED IN THE EVENT OF FAILURE
D14.3.9 NOTIFICATION OF REMEDIAL WORK
D14.3.10 REMEDIAL WORK
CONTENTS
PART A: SPECIFICATIONS
A14.4.1 SCOPE
A14.4.2 DEFINITIONS
A14.4.3 GENERAL
A14.4.4 DESIGN BY CONTRACTOR / PERFORMANCE BASED SYSTEMS
A14.4.5 MATERIALS
A14.4.6 CONSTRUCTION EQUIPMENT
A14.4.7 EXECUTION OF THE WORKS
A14.4.8 WORKMANSHIP
A14.4.2 DEFINITIONS
Bonding agent - the component of a repair system used to promote adhesion of a repair mortar or concrete to a concrete substrate for the
purpose of achieving a permanent bond, which is not affected by moisture and strong alkalis in service.
Cementitious repair products and systems - hydraulic or polymer mortars, concretes and grouts.
High flow mortar or concrete - a repair product formulated to exhibit extremely high flow characteristics, outside the limits of normal methods
of test, and which flows through narrow gaps and around areas of congested reinforcement, without bleeding or segregation.
Smoothening coat - a fine mortar coating applied to a surface to fill voids, cracks, and cavities or to level an uneven surface. The purpose is to
prepare the surface for the application of protection systems (refer Section A14.7).
A14.4.3 GENERAL
This Section includes all the work and materials required to carry out the surface and structural repair of concrete members. The proprietary
repair materials which are specified are based on the EN 1504-3 specification which shall be used in conjunction with this specification.
A14.4.5.3 Water
The Contractor shall prove by way of laboratory test that all water used for mixing and curing repair materials complies with SANS 51008.
In addition to the general occupation health and safety requirements of the works all the necessary health, safety and fire precautions stated by
the manufacturer shall be complied with.
Only material of which the shelf life has not expired shall be used.