TESTS
SAN JOSE ENVIRONMENTAL INNOVATION CENTER
Revised 08082014
1.1 Objectives
What is
The purpose of commissioning this project is to
Commissioning?
provide the Owners and facility operators with a high
level of assurance that the mechanical, electrical, and
Building commissioning temperature control systems are installed in the
provides documented appropriate manner that is in compliance with the
confirmation that building design intent. This process is not to diminish the
systems function according to responsibility of the system designers or installers, nor
criteria set forth in the project is it intended to be a redundant testing or inspection
documents to satisfy the function.
owner’s operational needs. [1]
Commissioning is performed to complement the efforts of the designers, installers, contractors and
the construction manager, enhancing the quality of the systems and aiding in their orderly transfer to
the Owner. Commissioning tests the operation of the building equipment and systems to ensure they
operate as intended; and can satisfactorily meet the needs of the building throughout the entire range
of operating conditions.
The anticipated benefits of successfully commissioning this project are that the
Owner/Operator will receive systems that perform at or above the expected level, with reduced
operation and maintenance costs and increased overall facility performance.
For more information
about the
commissioning
process, please refer
to the
Commissioning Plan
See the Section titled “Basic Testing Terminology” for definitions of these terms.
Commissioning Authority
develops plan, checklists and
Functional Test Procedures
(FTPs)
Modifications as
necessary
Owner’s representative,
designer, and contractors review
documentation
Commissioning Authority
reviews and supplements
contractors’ pre-functional &
start-up documents
Commissioning team
Commissioning Authority
troubleshoots systems not
finalizes functional test schedule
complying
Contractors / Commissioning
GC / CM issues
Authority perform functional
Notice of Readiness
testing
PFTs are typically performed by the contractor/subcontractor and verified by the CxA via
spot-sampling. A 10% sampling rate is typically used, and if a high rate of failure occurs, a
second 10% sampling occurs. If there is a continued high rate of failure, 100% sampling occurs,
usually at additional cost to the contractor/subcontractor.
The completion of this phase of testing is one of the pre-requisites for Functional Testing.
B. Functional Test Procedures (FTPs) also referred to as Functional Performance Tests (FPTs) -
tests that verify that the various installed components/elements work together as a cohesive
system. This phase tests system performance as well as the sequences of operations (SOO).
C. Integrated Testing signifies the testing of various systems, relative to each other. For example,
does the fire alarm system provide a cross-system signal to shut down the air handler during a
fire emergency? While sometimes included as a separately labeled set of tests, Integrated
Testing is often a built-in component of Functional Testing.
D. Pull-the-Plug Testing indicates a test or series of tests that verify performance of various
systems during a power failure, during emergency power mode, and during a restoration-to-
normal power mode. Typically performed in critical applications or on critical systems.
E. Pass/Fail (P/F) - test results are typically evaluated based on a simple Pass or Fail system. Notes
and comments regarding either failures or other relevant information are recorded in the
comments section of the test procedures. OPEN issues are typically transferred to and
tracked in the Commissioning Issues Log.
B. Contingency Plan – When performing critical tests, develop a back-up plan if something goes
wrong, and distribute to all team members, for review, prior to beginning the test.
C. Communication – Verify that all team members understand their role, where they are to be
stationed, and that each critical person/team leader can properly communicate (walkie-talkies,
cell phone, need a reliable signal). Provide written instructions, as needed.
D. Red Flag – Depending on the critical nature or size of the test, designate a senior team
member exclusively authorized to alarm or ‘red flag’ the test to immediately cease.
E. Trending – Trend all tests and print to PDFs. Capture graphic screen shots as needed.
D. Testing, Adjusting and Balancing (TAB) is complete, and draft or final reports of the applicable
systems have been submitted to the design engineer and the Commissioning Authority
E. Start-up Reports, System Verification Checklists, Input/Output Checkouts, etc., have been
submitted to the design engineer and the Commissioning Authority
The applicable prerequisites apply to ALL commissioned systems (HVAC, BMS, lighting, domestic hot
water, etc.). In other words, these prerequisites would typically apply to the BMS contractor, but in
the case of lighting controls, trending might not be possible, while other prerequisites would be
possible (such as item E.).
Test %
Participant Phase Needed
Commissioning Authority All 100%
Building Automation System Technician BMS/Mech 100%
Mechanical Sub-contractor Mech 100%
Electrical Sub-contractor Lighting 100%
Testing, Adjusting, Balancing (TAB) Sub-contractor
– sampling only TAB 10-20%
Owner's Representative (O&M staff) All [1]
[1] Owner Representative not required, but recommend at least partial presence during Cx.
Other: ______________________________________________________________________
Fill in the test instrumentation utilized during testing. Continue on rear of sheet, if necessary.
Meter Manufacturer
Model Number
Serial Number
Contractor Providing It
Date Calibrated
Meter Manufacturer
Model Number
Serial Number
Contractor Providing It
Date Calibrated
Meter Manufacturer
Model Number
Serial Number
Contractor Providing It
Date Calibrated
Meter Manufacturer
Model Number
Serial Number
Contractor Providing It
Date Calibrated
Meter Manufacturer
Model Number
Serial Number
Contractor Providing It
Date Calibrated
Meter Manufacturer
Model Number
Serial Number
Contractor Providing It
Date Calibrated
Meter Manufacturer
Model Number
Serial Number
Contractor Providing It
Date Calibrated
Use reverse side of page if needed
This chart provides a list of commissioned equipment, along with a very brief outline version of
equipment descriptions, control “triggers,” and interlocks.
Indicate tag/ID (AHU-1), along with description. Indicate the area that the unit/system serves. Indicate
what triggers it to start (time clock, OAT > 65, any FCU = ON, etc.). If the unit is interlocked with
something else, indicate the tag/ID of the interlocked device (RF-1, EF-3, etc.).
A comparison of correct and incorrect result examples are shown below. The Commissioning
Authority or commissioning technician may, as an option, highlight the incorrect results in
yellow or red, as indicated below. Note how the actual result is listed following the “/”.
Illustration 1.13.D, Expected and Unexpected Results
Then, Sequence of Operation tests shall be performed on a random sampling of at least 10%
of the equipment, which shall be chosen by the Commissioning Authority. Verifying other or
similar equipment utilizing programming comparison techniques is permissible. In other words, if
one unit is thoroughly tested, and other identical units have the same programming, then it
can be assumed the other units will function similar to the tested unit.
In the test procedure comment area there is a column heading called “Attn.” This area
indicates the person/entity that the CxA considers the most appropriate to respond to the
issue. It may get changed as the issue matures.
Within the test procedure itself, there is generally a column titled “Notes.” An example of a
note reference is the symbol [1] or [2]. These symbols refer to a corresponding comment
number which can be found in the note/comment section immediately following the test
procedure. See the illustration below for an example of three (3) notes or comments. Issues
are classified as either “Open” or “Closed,” and in some cases “Closed, Need Verification.”
Enter the earliest time that the system can start, in advance of the normal ON
time shown above. Similarly, if there is an advanced stop/coast down feature in
the afternoon or evening, enter that time. Enter the night setback and setup
values. Enter the duration of time (in minutes) the system will run when in either
Enhanced night setback/setup. Once values are entered, verify that they function by
Scheduling entering Pass/Fail (P/F). Rows C & D are Pass/Fail for rows A & B. Indicate if
Features features do not exist.
Earliest After
Coast Night Night Timed
Occupancy Optimum Hours Notes
Down Setback Setup Override
ON Overrides
A. ON Time or Stpt 55 85 120 min 120 min [1]
B. OFF Time or
n/a n/a
Stpt/DB
C. Verify Row A
F P P P P [2] [3]
(above)
D. Verify Row B
F n/a n/a n/a n/a
(above)
COMMISSIONING COMMENTS & ISSUES
Notes Issue Attn:
The zone sensor button can be programmed, in 1 to 8 hour intervals, to
Note 1 bring on after hours HVAC. It’s default is120 minutes/2 hours. Owner
Note 2 Optimum start is not programmed. BMS
Note 3 Coast down was not specified. Does the Owner want this feature? Owner
G. Helpful Hints
1. First things first - Getting certain things verified first makes subsequent testing more
efficient, because information is now known to be reliable. As a result, there is less
running around. Generally, verify the following items first (in no particular order):
i. Inputs/Outputs – do start/stops work, valves stroke, dampers function, VFDs
ramp?
ii. Calibrations – doing certain things in groups can be faster
iii. Termination paths (does AHU-1 output turn on AHU-2?) or is AHU-1fan
status on the graphics really AHU-2 fan status?
iv. Interlocks – does the return fan start when the supply fan starts?
v. Setpoints – are the specified setpoints, timer delays, deadbands, etc. present?
vi. Schedules – are the systems all on their required schedules? Are energy-
saving features, such as optimum start, programmed?
vii. Enables – does the exhaust fan start based on a local thermostat setpoint? Is
the thermostat even installed and mounted? Do thermostat overrides work?
viii. Are alarms programmed and functioning?
2. If current switches (CTs) are used for fan status, verify that they are calibrated in a
manner that can distinguish the difference between a fan being ON and running
correctly, and a fan being ON and running with a broken fan belt.
3. When verifying setpoint control, overshooting/droop should not occur more than 2
times. Fast acting PID loops will typically settle out in less than 5 minutes, while slow
acting PID loops may take as long as 20 minutes to settle out.
4. If possible, trend during testing. Trending provides clear proof of testing and its
results. Collect the trends as PDFs and include in the Commissioning Final Report.
It is a requirement of the Commissioning Authority that the design team and the installing contractors
and/or subcontractors review all tests prior to their implementation, to ensure that the tests are fair
and safe. Appropriate designated representatives shall sign-off, in advance of any testing, regarding this
compliance (see below). If one or more of the manufacturers, designers, contractors, subcontractors
or designated representatives do not sign off, it shall be assumed that they have reviewed the tests
and accept responsibility as indicated in the Safety and Fairness Compliance Statement (see below).
Prior to each test, the testing team (which shall include the Commissioning Authority and/or
commissioning technician, representatives from the appropriate contracting/subcontracting teams,
and/or owner and/or design team members), shall meet to coordinate the safe administration of the
tests, and to verify that any operational critical systems remain robust and satisfactorily functional.
Use the reverse side of this page to add the names of additional parties.
Data shall be entered either by hand or electronically. Hand-entered data shall be in ink.
Participants must initial test forms and/or sign with their full name and the name of their company.
Signatures must be legible or accompanied by a legible printed name. Dates must accompany all
initialed or signed documents. Verified digital signatures are acceptable, as are facsimile signatures if
they are accompanied by a written authorization from the applicable party. An alternative method is
the use of a Tablet-PC which features handwriting recognition.
Guarantee: The Commissioning Authority does not guarantee the operation or efficiency of any
equipment or systems. Equipment guarantees are covered by the contractor’s or manufacturer’s
warranties. Issues concerning efficiency and expected performance are the responsibility of the system
designers and/or Owner Operations and Maintenance (O&M) team. The Commissioning Authority
makes no claims or warranties, stated or implied, concerning performance, operation or safety.
The Commissioning Authority reserves the right to perform Opposite Season testing.
The Owner may want to consider the benefits of including re-commissioning as part of their on-going
O&M program. Any re-commissioning efforts should refer to the original executed test procedures as
a baseline standard, as well as a reference guide for how to fill out the test forms.
[1] “Procedural Standards for Whole Building Systems Commissioning of New Construction,” 2009 Third Edition, National Environmental
Balancing Bureau, Page 40.
Respectfully Submitted,
GENERAL DESCRIPTION:
SINGLE ZONE VAV SYSTEM WITH ECONOMIZER DAMPERS, HW COIL, AND CHW
COIL, MODULATE DAMPERS, FAN SPEED, HEATING AND COOLING CONTROL
VALVES TO MAINTAIN SPACE TEMPERATURE. MODULATE DAMPERS TO PROVIDE
VENTILATION AIR.
1. RUN CONDITIONS:
THE UNIT SHALL RUN DURING OCCUPIED HOURS, DETERMINED BY OWNER
DURING SYSTEM PROGRAMMING AND USER ADJUSTABLE. THE UNIT SHALL.
RUN FOR 2 HOURS BASED ON A PUSH BUTTON OVERRIDE SIGNAL FROM A
SPACE TEMPERATURE SENSOR. MULTIPLE OVERRIDE BUTTON PUSHES SHALL
NOT ACCUMULATE RUN TIME BEYOND 4 HOURS WHEN UNIT IS NOT
RUNNING. FULLY SHUT OFF FAN, AND CLOSE ALL VALVES AND
DAMPERS.
2. STATUS INDICATION:
STATUS OF THE FAN SHALL BE MONITORED AND AN ALARM SHALL BE
PROVIDED IF THE STATUS IS DIFFERENT THAN THE COMMANDED ON/OFF
SIGNAL.
3. PRE-FILTER MAINTENANCE:
WHEN PRESSURE DROP ACROSS THE PRE-FILTER HOUSING RAISES ABOVE
SCHEDULED DIRTY PRESSURE DROP (USER ADJUSTABLE) PROVIDE AN ALARM
AT THE BAS MONITORING STATION.
4. FINAL - FILTER MAINTENANCE:
WHEN PRESSURE DROP ACROSS THE FINAL-FILTER HOUSING RAISES ABOVE
SCHEDULED DIRTY PRESSURE DROP, PROVIDE AN ALARM AT THE BAS
MONITORING STATION.
5. SUPPLY TEMPERATURE, FAN SPEED, AND ECONOMIZER CONTROL SEQUENCE:
MODULATE FAN SPEED, DAMPER POSITIONS, AND COILS CONTROL VALVE
POSITIONS IN A SMOOTH, LINEAR MANNER ACCORDING TO PERCENTAGE OF
PROPORTIONAL - INTEGRAL CONTROL LOOP OUTPUT DESCRIBED BELOW.
TRANSITIONAL STAGES IN CONTROL LOOP OUTPUT ARE DESCRIBED BELOW,
BUT TRANSITIONS BETWEEN STAGES SHALL BE LINEAR AND SMOOTH.
HEATING:
ENABLE HEATING WHEN THE SYSTEM IS ON, WHEN CHW COOLING AND
ECONOMIZER COOLING IS NOT ACTIVE, AND WHEN OUTSIDE AIR
TEMPERATURE IS LESS THAN 65 DEG. F (USER ADJUSTABLE).
STAGE 3 HEATING:
SET FAN SPEED TO MAXIMUM. MODULATE HOT WATER CONTROL VALVE TO
CONTROL THE SPACE TEMPERATURE.
AT SYSTEM BALANCE, SET THE RA DAMPER TO FULL OPEN AND FAN SPEED
TO FULL, WITH CLEAN FILTERS. DETERMINE THE OSA DAMPER POSITION TO
DELIVER MINIMUM AND MAXIMUM VENTILATION AIRFLOW, AND MEASURE
THE DIFFERENTIAL PRESSURE AS THE SETPOINT FOR MINIMUM VENTILATION
AIR CONTROL. WHEN THE ECONOMIZER IS LOCKED OUT DUE TO WARM
WEATHER, MODULATE RA DAMPER POSITION TO MAINTAIN DIFFERENTIAL
PRESSURE SETPOINT.
8. FREEZE PROTECTION::
IF OSA TEMPERATURE DROPS BELOW 34 DEG. F FOR 30 MINUTES AT ANY
TIME, THE HOT WATER COIL VALVE SHALL BE COMMANDED TO 10% OPEN
AND AN ALARM GENERATED STATING, "POSSIBLE FREEZING CONDITIONS
DETECTED"
9. NIGHT PURGE:
IF OUTSIDE TEMPERATURE RISES ABOVE 75 DEG F DURING THE PREVIOUS 24
HRS, VENTILATION SYSTEM TO OPERATE CONTINUOUSLY DURING
UNOCCUPIED PERIODS WHEN OUTDOOR AIR TEMPERATURE ARE LESS
THAN 68 DEG. F (ADJUSTABLE) AND MAINTAIN A SPACE TEMPERATURE OF 70
DEG. F (ADJUSTABLE)
11. ALARMS:
AN ALARM SHALL BE GENERATED UPON FAN MOTOR FAILURE. IF
MAXIMUM FAN CAPACITY REACHED - CHECK FOR AIRFLOW
OBSTRUCTION, EXCESSIVE LOAD ETC. WARNING SHALL BE GENERATED
UPON OPERATION OF THE FAN AT 100% SPEED FOR GREATER THAN 4
HOURS.
GENERAL DESCRIPTION:
MULTIPLE ZONE VAV SYSTEM WITH ECONOMIZER DAMPERS, CHW COIL, ZONE
HW COILS, VAV DIFFUSERS AND CONSTANT VOLUME DIFFUSERS MODULATE
DAMPERS, HEATING AND COOLING CONTROL VALVES TO CONTROL
TEMPERATURE IN THE ZONES WITH TEMPERATURE SENSORS. TEMPERATURE
CONTROL FOR ZONES WITHOUT TEMPERATURE SENSORS IS PERFORMED WITH
VAV DIFFUSERS WHICH REQUIRE NO CONTROL POINT OR SEQUENCE.
MODULATE DAMPERS TO CONTROLVENTILATION AIR.
1. RUN CONDITIONS:
THE UNIT SHALL RUN DURING OCCUPIED HOURS, DETERMINED BY
OWNER DURING SYSTEM PROGRAMMING AND USER ADJUSTABLE. THE
UNIT SHALL RUN FOR 2 HOURS BASED ON A PUSH BUTTON OVERRIDE
SIGNAL FROM A SPACE TEMPERATURE SENSOR. MULTIPLE OVERRIDE
BUTTON PUSHES SHALL NOT ACCUMULATE RUN TIME BEYOND 4 HOURS
WHEN UNIT IS NOT RUNNING. FULLY SHUT OFF FAN, AND CLOSE ALL
VALVES AND DAMPERS.
2. STATUS INDICATION:
STATUS OF THE FAN SHALL BE MONITORED AND AN ALARM SHALL BE
PROVIDED IF THE STATUS IS DIFFERENT THAN THE COMMANDED ON/OFF
SIGNAL.
3. PRE-FILTER MAINTENANCE:
WHEN PRESSURE DROP ACROSS THE PRE-FILTER HOUSING RAISES
ABOVE SCHEDULED DIRTY PRESSURE DROP (USER ADJUSTABLE)
PROVIDE AN ALARM AT THE BAS MONITORING STATION.
HEATING:
FOR EACH HEATING COIL, ENABLE ZONE HEATING WHEN THE SYSTEM IS ON,
WHEN OUTSIDE AIR TEMPERATURE LESS THAN 65 DEG. F (USER ADJUSTABLE)
. ZONE HEATING AND COOLING MAY BE ENABLED AT THE SAME TIME. IF ALL
ZONES ARE IN HEATING, LOCK OUT COOLING. FOR EACH ZONE HOT WATER
CONTROL VALVE (TYPICAL):
LOBBY:
THE CONTROLLER SHALL MODULATE VIA PROPORTIONAL - ONLY CONTROL
THE LOBBY BRANCH CONTROL DAMPER TO MAINTAIN A SETPOINT OF 900 PPM
(USER ADJUSTABLE). IF THE LOBBY BRANCH CONTROL DAMPER HAS BEEN
FULLY OPEN FOR 10 MINUTES OR LONGER AND CO2 LEVELS ARE STILL HIGHER
THAN THE SETPOINT, MODULATE VIA PROPORTIONAL - ONLY CONTROL THE
RETURN AIR DAMPER (AND OUTSIDE AIR DAMPER IF NECESSARY) TO DELIVER
NO GREATER THAN THE MAXIMUM SCHEDULED DEMAND CONTROLLED
VENTILATION RATE (USER ADJUSTABLE).
13. ALARMS:
AN ALARM SHALL BE GENERATED UPON FAN MOTOR FAILURE. IF
MAXIMUM FAN CAPACITY REACHED - CHECK FOR AIRFLOW
OBSTRUCTION, EXCESSIVE LOAD ETC. WARNING SHALL BE
GENERATED UPON OPERATION OF THE FAN AT 100% SPEED
FOR GREATER THAN 4 HOURS.
GENERAL DESCRIPTION:
MULTIPLE ZONE VAV SYSTEM WITH ECONOMIZER DAMPERS, CHW COIL, TWO
HW COILS, ZONE VAV DIFFUSERS, AND CONSTANT VOLUME ZONE DIFFUSERS,
MODULATE DAMPERS, HEATING AND COOLING COIL VALVES TO CONTROL
TEMPERATURE IN THE ZONES WITH TEMPERATURE SENSORS. TEMPERATURE
CONTROL FOR ZONES WITHOUT TEMPERATURE SENSORS IS PERFORMED WITH
VAV DIFFUSERS WHICH REQUIRE NO CONTROL POINT OR SEQUENCE.
MODULATE DAMPERS TO CONTROL VENTILATION AIR.
1. RUN CONDITIONS:
THE UNIT SHALL RUN DURING OCCUPIED HOURS, DETERMINED BY
OWNER DURING SYSTEM PROGRAMMING AND USER ADJUSTABLE.
THE UNIT SHALL RUN FOR 2 HOURS BASED ON A PUSH BUTTON
OVERRIDE SIGNAL FROM A SPACE TEMPERATURE SENSOR. MULTIPLE
OVERRIDE BUTTON PUSHES SHALL NOT ACCUMULATE RUN TIME
BEYOND 4 HOURS WHEN UNIT IS NOT RUNNING. FULLY SHUT OFF FAN,
AND CLOSE ALL VALVES AND DAMPERS.
2. STATUS INDICATION:
STATUS OF THE FAN SHALL BE MONITORED AND AN ALARM SHALL BE
PROVIDED IF THE STATUS IS DIFFERENT THAN THE COMMANDED ON/OFF
SIGNAL.
3. PRE-FILTER MAINTENANCE:
WHEN PRESSURE DROP ACROSS THE PRE-FILTER HOUSING RAISES
ABOVE SCHEDULED DIRTY PRESSURE DROP (USER ADJUSTABLE)
PROVIDE AN ALARM AT THE BAS MONITORING STATION.
CDTC:
THE CONTROLLER SHALL MODULATE VIA PROPORTIONAL - ONLY CONTROL
THE LOBBY BRANCH CONTROL DAMPER TO MAINTAIN A SETPOINT OF 900 PPM
(PER ADJUSTABLE). IF THE LOBBY BRANCH CONTROL DAMPER HAS BEEN
FULLY OPEN FOR 10 MINUTES OR LONGER AND CO2 LEVELS ARE STILL HIGHER
THAN THE SETPOINT, MODULATE VIA PROPORTIONAL-ONLY CONTROL THE
RETURN AIR DAMPER (AND OUTSIDE AIR DAMPER IF NECESSARY) TO DELIVER
NO GREATER THAN THE MAXIMUM SCHEDULED DEMAND CONTROLLED
VENTILATION RATE (USERADJUSTABLE).
HEATING:
FOR EACH HEATING COIL, ENABLE ZONE HEATING WHEN THE SYSTEM IS ON
AND WHEN OUTSIDE AIR TEMPERATURE IS LESS THAN 65 DEG F (USER
ADJUSTABLE). ZONE HEATING AND COOLING MAY ENABLED AT THE SAME
TIME. HOWEVER, IF ALL ZONES ARE IN HEATING, LOCKOUT COOLING. FOR
EACH ZONE HOT WATER CONTROL VALVE (TYPICAL)
13. ALARMS:
AN ALARM SHALL BE GENERATED UPON FAN MOTOR FAILURE. IF
MAXIMUM FAN CAPACITY REACHED - CHECK FOR AIRFLOW
OBSTRUCTION, EXCESSIVE LOAD ETC. WARNING SHALL BE
GENERATED UPON OPERATION OF THE FAN AT 100% SPEED
FOR GREATER THAN 4 HOURS. RA DAMPER POSITION
CO2 S.OFFICE SENSOR
1. RUN CONDITIONS:
THE COOLING TOWER SYSTEM CONTROL SHALL BE INTEGRATED WITH
CHILLER FACTORY CONTROLS EXCEPT AS OTHERWISE NOTED IN BELOW
SEQUENCE. THE COOLING TOWER START-UP AND SHUTDOWN
SEQUENCES SHALL BE COORDINATED WITH CHILLER START-UPAND
SHUTDOWN REQUIREMENTS UNLESS OTHERWISE REQUIRED BY THE
CHILLER FACTORY CONTROLS, THE COOLING TOWER SHALL BE
ENABLED UPON DEMAND FOR COOLING FROM THE ZONES AND IF THE
OUTSIDE AIR TEMPERATURE IS BELOW 55 DEG F (ADJUSTABLE) TO
PREVENT SHORT CYCLING. THE COOLING TOWER SHALL RUN FOR AND
BE OFF FOR MINIMUM ADJUSTABLE TIMES (BOTH USER DEFINABLE),
UNLESS SHUTDOWN AN SAFETIES OR OUTSIDE AIR CONDITIONS.
STAGE 1:
LOW - CHILLER -LIFT AVOIDANCE:
NATURAL DRAFT, MINIMUM FLOW.
IF TOWER WATER TEMPERATURE IS LESS THAN 72 DEG. F (ADJ.) OR THE
MINIMUM CHILLER LIFT AS RECOMMENDED BY CHILLER MANUFACTURER,
DECREASE THE PUMP VFD SPEED TO MAINTAIN THE MAXIMUM OF
STAGE 2:
NORMAL OPERATION, NATURAL DRAFT.
LEAD CONDENSER WATER PUMP IS ON, PUMP SPEED AT VFD DELIVERS DESIGN
CONDENSER WATER FLOWRATE TO TOWER. COOLING TOWER FAN IS OFF.
DETERMINE PUMP SPEED REQUIRED TO MAINTAIN DESIGN FLOW AT SYSTEM
BALANCE WITH DIRTY FILTER.
STAGE 3:
NORMAL OPERATION, FORCED DRAFT:
LEAD CONDENSER WATER PUMP RUNS. COOLING TOWER FAN SPEED
MODULATES FROM MINIMUM TO MAXIMUM SPEED TO MAINTAIN A MAXIMUM
TOWER LEAVING WATER TEMPERATURE SETPOINT OF 73.5 DEG. F (ADJ.)
VFD FAULT
2. PUMP CONTROL:
THE CHILLED WATER PUMP SHALL OPERATE IN LEAD / STANDBY
MANNER. UPON DEMAND FOR COOLING FROM THE ZONES, OR UPON A
CALL FOR CHILLER START-UP, ONE PUMP SHALL OPERATE. PUMPS
SHALL SWITCH LEAD/STANBY STATUS MONTHLY.
3. ALARMS:
A. AN ALARM SHALL BE GENERATED UPON PUMP MOTOR
FAILURE.
B. AM MAXIMUM PUMP CAPACITY REACHED - CHECK FOR
OBSTRUCTION, EXCESSIVE LOAD, ETC".
WARNING SHALL BE GENERATED UPON
OPERATION OF THE PUMP AT 100% SPEED FOR GREATER
THAN 4 HOURS.
5. ALARMS:
AT A MINIMUM, AN ALARM SHALL BE GENERATED FOR A FOLLOWING
CONDITIONS AND / OR EVENTS;
A. PUMP MOTOR FAILURE / FAULT
B FAILURE TO MAKE SETPOINT FOR 20 CONSECUTIVE
MINUTES
C. BYPASS AT OR ABOVE 30% OPEN FOR 6 CONSECUTIVE
HOURS
6. MONITORING:
AT A MINIMUM, TREND SUPPLY WATER TEMPERATURE, SUPPLY WATER
TEMPERATURE SETPOINT, RETURN WATER TEMPERATURE, CHILLER
ON/OFF, CHILLER RUN TIME, AND CHILLED WATER FLOW.
2. Upon detection of refrigerant above the specified code required levels, do all of the
following: Provide alarm to BMS. Turn on machinery room ventilation fan if not already on.
Activate audio and visual alarm inside and outside machinery room.
3. Emergency Operations of the refrigerant monitoring system shall comply with these
sequences and CMC Ch 11 RMR requirements.
Stop Control: If the break glass switch is activated, all electrically energized equipment is the
refrigerant machinery room shall be turn off. Hard wired electrical interlock shutdown (by
Electrical): CH-1, B-1, B-2, WT-1, CWF-1, Plug outlets, Transformers providing 24V power
to equipment in the RMR. BMS shutdown: BP-1, BP-2, HHWP-1 and VFD, HHWP-2 and
VFD, CHWP-1 and VFD, CHWP-2 and VFD. Provide alarm if the equipment is commanded
off but status is on
2. STAGING CONTROL:
BOILERS SHALL BE RUN IN PARALLEL WHENEVER LOAD IS HIGH
ENOUGH TO AVOID CYCLING. PARALLEL BOILER OPERATION SHALL
RESUME AS SOON AS BUILDING LOAD PERMITS OPERATION OF BOTH
BOILERS AT 20% OF THEIR RATED CAPACITY.WITH APPROVAL, BOILER
STAGING BY THE BOILER'S INTEGRATED ON BOARD CONTROL MAY
SUBSTITUTED.
1. SCHEDULING:
A. THE LEAD PUMP SHALL OPERATE UPON DEMAND
FROM THE SUPPLIED LOOP.
B. SUCH PUMP IS SIZED FOR THE FULL LOAD. ONLY ONE
PUMP SHALL RUN AT A TIME
3. ALARMS:
A. AN ALARM SHALL BE GENERATED UPON PUMP
MOTOR FAILURE.
B. AM MAXIMUM PUMP CAPACITY REACHED - CHECK
FOR OBSTRUCTION, EXCESSIVE LOAD,
ETC". WARNING SHALL BE GENERATED UPON
OPERATION OF THE PUMP AT 100% SPEED FOR
GREATER THAN 4 HOURS.
5. SETPOINT CONTROL:
THE HOT WATER SUPPLY SETPOINT SHALL BE RESET BASED ON OUTSIDE
AIR TEMPERATURE ACCORDING TO THE FOLLOWING SCHEDULE:
OUTSIDE AIR TEMPERATURE HWS TEMPERATURE
65 DEG. F 125 DEG. F
30 DEG. F 145 DEG. F
7. ALARMS:
AT A MINIMUM AN ALARM SHALL BE GENERATED FOR THE FOLLOWING
CONDITIONS AND/OR EVENTS:
A. BOILER FAILURE/FAULT
B. PUMP MOTOR FAILURE/FAULT
C. FAILURE TO MAKE SETPOINT FOR 20 CONSECUTIVE
MINUTES.
Exhaust fans - temperature controlled. All suggested setpoints and settings are to be adjustable.
1. Scheduling:
The exhaust fan shall be enabled based on a 24, 7-day occupancy schedule, user adjustable. Set
initial schedule to 24/7 operation.
2. The exhaust fan shall start when the space temperature rises above the space temperature
setpoint, and shall stop when the space temperature drops below the space temperature
setpoint.Use 4 Deg.F deadband.
1. Scheduling: the exhaust fan shall be enabled based on occupancy time scheduled, user
adjustable.
2. Start/Stop: The fan shall run during occupancy hours (user adjustable) and shall be turned
off otherwise.
Purpose:
Verify occupancy times, including that equipment and systems are grouped in the correct schedules. This
procedure assumes there is one (1) schedule. Add additional schedules, as required.
Prerequisite:
Front end computer/controller/server must be communicating for this test to be implemented. All BMS panels
and BMS-controlled equipment should be fully operational and in automatic mode.
Instruction:
Input the actual programmed start/stop times, by day of week (DOW). Enter time in military time (0800, 1730,
etc.). Enter TOD on/off data in rows A and B, and use rows C and D as the pass/fail rows for A and B
respectively. Verify that the schedules do, in fact, turn equipment on/off. List which equipment is grouped in
its respective schedule. The following schedule is assumed by the CxA.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that the following scheduling energy-saving features exist and are functional. Notate if they are not
specified, and carry the notation in the Commissioning Issues Log (this gives the designer and/or Owner the
opportunity to add the features).
Instructions:
Enter the earliest time (in minutes/hours) that the system can start, in advance of the normal ON time shown
above. Similarly, if there is an advanced stop/coast down feature in the afternoon or evening, then enter its
earliest enable time. Enter the night setback and setup temperature values (°F). In the After Hours column, enter
the duration of time (in minutes) that the system will run when enabled either in night setback/setup. Once
values are entered, verify that they function by entering Pass/Fail (P/F). Enter time data in row A, and use row B
as the pass/fail row for row A.
Enter the optimum start reset scale; enter the top and bottom end of the temperature scale, and enter the time
(in minutes) that correspond to the temperature scale. Verify it works by simulating the inputs. For example, if
heating optimum start were based solely on an outdoor temperature reset scale of 30-70°F, and if each degree
below 70° advance started the building by two minutes, then simulating a 60° outside temperature should yield a
20 minute advance start. Weight factor = the greater influence of OAT vs. ID temp. or vice versa.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
Use reverse side of page if needed
Purpose:
Verify that the BMS subcontractor and/or Owner have programmed the system for holiday scheduling.
Instructions:
List the holidays that are programmed. Add additional holidays as needed.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify the accuracy of the graphics. Graphical User Interface (GUI) must be functional prior to testing.
Prerequisite:
Front end computer/controller/server must be communicating for this test to be implemented. All BMS panels
and BMS-controlled equipment should be fully operational and in automatic mode. Graphics must be fully
installed and functional. A jump/thumb/USB drive will be needed to store screen shots.
Instruction:
Other tests verify that inputs/outputs are terminated correctly. For example, if a command to start AHU-1 is
given, AHU-1 should start, not AHU-2. However, are the graphics accurate? If AHU-1 fan status is viewed on
the graphics as being ON, has the coding been inadvertently switched, and the viewer is actually seeing the fan
status of AHU-2? This test samples various inputs and outputs, chosen at the Commissioning Authority’s
discretion. The sampled I/Os should be listed below, and should also indicate whether they Passed/Failed (P/F).
Also indicate with a Yes/No (Y/N) if a screen shot has been captured and will be attached to the test
procedures.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify that the content of the graphics are intuitive and suitably represent the installed systems, and that the
navigation links exist and work correctly. GUI must be functional prior to testing.
Prerequisite:
Front end computer/controller/server must be communicating for this test to be implemented. All BMS panels
and BMS-controlled equipment should be fully operational and in automatic mode. Graphics must be fully
installed and functional. A jump/thumb/USB drive will be needed to store screen shots.
Instruction:
A. Verify navigation (that clicking on a link takes you to that specific graphic or page).
B. Are the graphics informative, in the sense they provide the right balance of information?
C. Is the information being presented clear in what it is depicting? Well organized?
D. Is the graphic readable? Is the font a good size? Enough spacing, not all crammed together?
In steps A-D indicate either Pass/Fail (P/F). Also indicate with a Yes/No (Y/N) if a screen shot has been captured
and will be attached to the test procedures.
Commissioning Comments/Issues
Note Date Issue Attn:
1 Graphic should indicate why unit is ON: schedule, opt. start, after hours
o’ride
2 Graphics to show setpoints: Occ/Unoccup clg/htg, economizer changeover
3
4
5
Use reverse side of page if needed
Purpose:
Verify that trending is set-up. These trends are a critical diagnostic commissioning test.
Prerequisite:
Front end computer/controller/server must be communicating for this test to be implemented. All BMS panels
and BMS-controlled equipment should be fully operational and in automatic mode. Graphics must be fully
installed and functional. A jump/thumb/USB drive will be needed to store trend reports.
Recommended Trends:
Trend Title Monitoring Instructions
AHUs, FCUs: 1-Stable performance, stable loops, maintains steady temperatures & SPs
2-Economizer, heating/cooling – no simultaneous modes, stpts reset at
night
3-Triggering at correct setpoints; proper OA damper reactions, min OA
4-Scheduling: follows schedule, optimum start works, TOV works
Exhaust Fans 1-Triggering at correct setpoints; proper damper reactions
VAV Boxes 1-Stable performance, stable loops, maintains steady temperatures
2- Stpts reset at night; TOV works
3-Triggering at correct setpoints
Building Static Pressure 1-Stable performance, stable loop, maintains steady SP
Chiller Plant 1-Stable performance, stable loops, maintains steady temperatures
2- Lead/lag works (on main plant only); triggering at correct setpoints
3- Correct control of capacity
4 – Triggers on/off as specified (main plant only; other plant is 24/7)
HW Heating Plant 1-Stable performance, stable loops, maintains steady temperatures
2 – Triggers on/off as specified
Selection of trends is at the Commissioning Authority’s discretion. The above are simply recommendations. For
example, trend selection may be based on critical points. Examples: the CEO’s office, a server room, a critical
process, an exterior versus interior zone, a zone at the far end of a duct or H2O run, steady control of a PID
loop, shifting between heating and cooling cycles, occupancy scheduling, optimum start effectiveness, etc.
NOTE: As an alternative to filling out the following tables, screen shots can be printed and then marked up
(notating any issues and pass/fail), dated, initialed and scanned to become part of the commissioning record.
Make a note on this form if an alternative method of documentation is selected.
Instruction:*
A. Record System name or title (AHU-1, Pump 3, T’stat 202, etc.)
B. Record point being trended (SA temp, pump status, zone temp, etc.)
C. Record the trending time interval (15 min is typical) or if it is logging COS/COV
D. How many hours or days or weeks is the trend depicting?
Indicate with a Yes/No (Y/N) if a screen shot has been captured and will be attached to the test procedures.
System Name Point Being Trend Trend Pass/Fail Trend Date Notes
Trended Interval Duration Saved
Y/N
* As an alternative to filling out this table, screen shots can be printed and then marked up (notating any issues and pass/fail), dated, initialed
and scanned to become part of the commissioning record. Make a note on this form if this (or another) alternative method of
documentation is selected.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Instruction:*
A. Record System name or title (AHU-1, Pump 3, T’stat 202, etc.)
B. Record point being trended (SA temp, pump status, zone temp, etc.)
C. Record the trending time interval (15 min is typical) or if it is logging COS/COV
D. How many hours or days or weeks is the trend depicting?
Indicate with a Yes/No (Y/N) if a screen shot has been captured and will be attached to the test procedures.
System Name Point Being Trend Trend Pass/Fail Trend Date Notes
Trended Interval Duration Saved
Y/N
* As an alternative to filling out this table, screen shots can be printed and then marked up (notating any issues and pass/fail), dated, initialed
and scanned to become part of the commissioning record. Make a note on this form if this (or another) alternative method of
documentation is selected.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that alarms have been set-up and are functional.
Prerequisite:
Front end computer/controller/server must be communicating for this test to be implemented. All BMS panels
and BMS-controlled equipment should be fully operational and in automatic mode. Graphics must be fully
installed and functional. Alarms must be programmed, including notification functions.
Recommended Alarms:
Listed below are typical kinds of alarms that should be verified. Keep in mind that some input points have more
than one alarm. For example, a temperature sensor is going to typically provide a “too hot,” “too cold” and a
“sensor fail” alarm.
Alarm Title Monitoring Instructions
High/low temperatures – Air Supply, mixed, return and zone temperatures
High/low temperatures – H2O Supply and return temperatures
High/low pressures Duct, filter, building SP, EF SP setpoint
Failure to start – Air systems Supply/return(exhaust) fans, cooling/heating/economizer mode
Failure to start – CHW/Htg Chillers, boilers, pumps, cooling towers
High CO2 High is if CO2 >1000 PPM +/- 100 PPM
Sensor failure Any temperature sensor. Be certain to test the OAT sensor
Sensor failure Any pressure sensor. Be certain to test building SP and any H20 DPs
Instruction:
A. Record Alarm name or title (AHU-1, Pump 3, T’stat 202, etc.)
B. Record point being alarmed (SA temp, pump failure, zone temp, etc.)
C. Record the alarm trigger/setpoint, i.e., what creates the alarm event?
D. Record any programmed delay (in minutes or seconds – indicate which: Ex- 5min/ or 30sec/ )
E. Trigger the alarm (simulations are okay); verify that it was initiated
F. Reset the alarm condition, and verify that it cleared
G. Return all overrides back to normal and/or automatic mode
Alarm Event Point Being Specified Trigger Alarm Initiated Cleared Normal Notes
Title Alarmed Alarm P/F Delay Y/N Y/N Y/N
Trigger ON
Main AHUs
AHU- SF status No fan
AHU- RF status No fan
AHU- SF VFD Alarm VFD
AHU- RF VFD Alarm VFD
AHU- SA Temp Hi 10 min
AHU- SA Temp Lo 10 min
AHU- Lo Min OA 10 min
flow
AHU- SF SP setpoint 5 min
AHU- Bldg SP 10 min
setpoint
Stairwell AHUs
AHU- SF status No fan
AHU- Gas furnace No heat
AHU- SA Temp Hi 10 min
AHU- SA Temp Lo 10 min
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Instruction:
A. Record Alarm name or title (AHU-1, Pump 3, T’stat 202, etc.)
B. Record point being alarmed (SA temp, pump failure, zone temp, etc.)
C. Record the alarm trigger/setpoint, i.e., what creates the alarm event?
D. Record any programmed delay (in minutes or seconds – indicate which: Ex- 5min/ or 30sec/ )
E. Trigger the alarm (simulations are okay); verify that it was initiated
F. Reset the alarm condition, and verify that it cleared
G. Return all overrides back to normal and/or automatic mode
Alarm Event Point Being Specified Trigger Alarm Initiated Cleared Normal Notes
Title Alarmed Alarm P/F Delay Y/N Y/N Y/N
Trigger ON
Fan Coil Units
FCU- SF status No fan
FCU- SA Temp Hi 10 min
FCU- SA Temp Lo 10 min
VAV Boxes
VAV- Zone Temp Hi 5 DegF
VAV- Zone Temp Lo 5 DegF
Exhaust Fans
EF- EF status No fan
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Instruction:
A. Record Alarm name or title (AHU-1, Pump 3, T’stat 202, etc.)
B. Record point being alarmed (SA temp, pump failure, zone temp, etc.)
C. Record the alarm trigger/setpoint, i.e., what creates the alarm event?
D. Record any programmed delay (in minutes or seconds – indicate which: Ex- 5min/ or 30sec/ )
E. Trigger the alarm (simulations are okay); verify that it was initiated
F. Reset the alarm condition, and verify that it cleared
G. Return all overrides back to normal and/or automatic mode
Alarm Event Point Being Specified Trigger Alarm Initiated Cleared Normal Notes
Title Alarmed Alarm P/F Delay Y/N Y/N Y/N
Trigger ON
Main CHW Plant
Chiller Status No start
CHW temp CHWS >50° 1 hour
CHW temp CHWS < 40° 1 hour
Prim Pump Status No start
Sec Pump Status No start
CW Pump Status No start
CTwr Fan Status No start
VFD Fault Internal Alarm Fail
CHW Iso Valve status Fail OP
CW Iso Valve status Fail CL
CW temp CWS > 95° 30 min
CW temp CWS < 64° 30 min
CW temp CWR > 95° 30 min
CW temp CWR < 64° 30 min
Diff Prssr DP>5 psi of 30 min
stpt
Diff Prssr DP<5 psi of 30 min
stpt
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
___________________________ ___________ _________ _________ [x] Initial Test
Commissioning Authority Date Date Date
___________________________ ___________ _________ _________ [ ] Retest
Controls Technician Date Date Date
___________________________ ___________ _________ _________
Other Witness/Attendee Date Date Date
Instruction:
A. Record Alarm name or title (AHU-1, Pump 3, T’stat 202, etc.)
B. Record point being alarmed (SA temp, pump failure, zone temp, etc.)
C. Record the alarm trigger/setpoint, i.e., what creates the alarm event?
D. Record any programmed delay (in minutes or seconds – indicate which: Ex- 5min/ or 30sec/ )
E. Trigger the alarm (simulations are okay); verify that it was initiated
F. Reset the alarm condition, and verify that it cleared
G. Return all overrides back to normal and/or automatic mode
Alarm Event Point Being Specified Trigger Alarm Initiated Cleared Normal Notes
Title Alarmed Alarm P/F Delay Y/N Y/N Y/N
Trigger ON
FCU CHW Plant
Chiller Status No start
CHW temp CHWS >50° 1 hour
CHW temp CHWS < 40° 1 hour
CHW Pump Status No start
CW Pump Status No start
Fluid Cooler Status No start
VFD Fault Internal Alarm Fail
CHW Iso Valve status Fail OP
CW Iso Valve status Fail CL
CW temp CWS > 95° 30 min
CW temp CWS < 64° 30 min
CW temp CWR > 95° 30 min
CW temp CWR < 64° 30 min
Runtime Pump Hours
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Instruction:
A. Record Alarm name or title (AHU-1, Pump 3, T’stat 202, etc.)
B. Record point being alarmed (SA temp, pump failure, zone temp, etc.)
C. Record the alarm trigger/setpoint, i.e., what creates the alarm event?
D. Record any programmed delay (in minutes or seconds – indicate which: Ex- 5min/ or 30sec/ )
E. Trigger the alarm (simulations are okay); verify that it was initiated
F. Reset the alarm condition, and verify that it cleared
G. Return all overrides back to normal and/or automatic mode
Alarm Event Point Being Specified Trigger Alarm Initiated Cleared Normal Notes
Title Alarmed Alarm P/F Delay Y/N Y/N Y/N
Trigger ON
Heating HW Plant
Boiler Status No start
HW Pump Status No start
Hi ∆P 5psi out/range Stpt
Lo ∆P 5psi out/range Stpt
HW temp 20° > stpt [1]
HW temp 20° < stpt [1]
VFD Fault Internal Alarm Fail
Runtime Pump Hours
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that the specified inputs/outputs exist on the BMS system. This sheet is for sampling and/or verifying the
contractor’s completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout
sheets.)
Prerequisite:
BMS panel is powered and fully terminated. All I/Os are visible via a laptop or workstation. All wiring and
terminations are labeled. All end devices (sensors, actuators, valves, relays, etc.) are terminated and functional.
The BMS subcontractor has submitted the completed I/O checkout forms, including submitting a copy to the
Commissioning Authority. A VOM meter may be needed for troubleshooting and/or verification.
Instruction:
I/Os may be spread among different panels. This is not a test to determine which panel a point is terminated in.
It is simply a back check to verify that the specified points exist.
A. Name the input/output point, and if it is an AO, AI, DO, DI.
B. Indicate if the point is terminated and if the point can be viewed on the BMS laptop or workstation.
I/O Point Type of Terminated Viewable Comments Notes
Name I/O P/F P/F
OAT AI Global point – only check one time
Bldg SP AI Global point - only check one time
MinOA AFMS AI
SF AFMS AI
RF AFMS AI
MA Temp AI
RA Temp AI
SA Temp AI
Filter DPS DI
SF Status DI
RF Status DI
SF VFD Speed AO
RF VFD Speed AO
Economizer AO
Clg Valve AO
Htg Valve AO
SF start/stop DO
RF start/stop DO
Purpose:
Verify the calibrations and/or functionality of the digital inputs. This sheet is for sampling and/or verifying the
contractor’s completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout
sheets.)
Prerequisite:
Same prerequisites as test 5.1.
Instruction:
Sample all digital inputs. If a current transformer (CT) or current switch (CS) is being used to monitor device
on/off status, make sure the CT/CS is calibrated in a manner that allows it distinguish the difference between a
fan (that has a belt drive) being ON and working correctly, and a fan that is ON but the belt is broken. This
would be the setting indicated below as the “Actual Trip Point.” The “Specified Setpoint” establishes the exact
setpoint that a device is supposed to trip, alarm or signal.
Purpose:
Verify the functionality of the analog inputs.
Prerequisite:
Same as test 5.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority.
Instruction:
Sample all analog inputs. Verify that inputs are not crossed. For example, make sure that Sensor 1 is not showing
up on the BMS as Sensor 2. Methods used to perform this verification may include taking a wire loose, moving a
setpoint, performing TOV, or changing a condition (example, creating more CO2 on a CO2 sensor). Verify that
the Timed Override (TOV) works, where applicable
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that the end devices start/stop from the BMS. This sheet is for sampling and/or verifying the contractor’s
completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same prerequisites as test 5.1.
Instruction:
Sample all digital outputs. Turn each output point on and off as indicated. Verify that outputs aren’t switched, i.e.,
that output point 1 is turning on device 1 not device 2.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that the end devices modulate from the BMS. This sheet is for sampling and/or verifying the contractor’s
completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same prerequisites as test 5.1.
Instruction:
Sample all analog outputs. Command each output point as indicated. Visually verify that the stroke position is
basically equivalent to the command.
Commissioning Comments/Issues
Note Date Issue Attn:
1 These percentages are typically 15hz, 35.5hz and 60 hz
2 Verify that OA/RA/Relief dampers move in proportion to each other
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify the calibration of the analog inputs. This sheet is for sampling and/or verifying the contractor’s completed
I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same as test 5.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority, Certified temperature meters and
magnehelics/manometers are required (verify resolutions). The same meter used by the BMS contractor to
perform initial calibration should be used for this back check.
Instruction:
Sample all analog inputs. First enter the BMS displayed data, and then enter the meter data in the next column.
Temperature readings should be within +/- 1°F. All other readings should be within +/-3%.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify a side-by-side comparison of sensors mounted in the same unit.
Prerequisite:
Same as test 5.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority, Certified temperature meters and
magnehelics/manometers are required (verify resolutions). The same meter used by the BMS contractor to
perform initial calibration should be used for this back check.
Instruction:
A. Disable heating and cooling on units to be tested by overriding outputs to 0.
B. Pose units to be tested to full recirculation by overriding damper signals on RTUs. OA damper and
minimum damper to be fully closed. All zone reheat coils to be fully closed.
C. Start unit running in full recirculation.
D. Wait at least 20 minutes for temperatures in system to blend and stabilize.
E. Verify that the zone, return, mixed and discharge temperatures are within 3°F of each other (5°F for
high ceiling spaces such as a Gym).
F. Record data in space provided.
G. Release all overrides at the end of the test.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
Use reverse side of page if needed
Purpose:
Verify that the specified setpoints have been programmed.
Prerequisite:
Same as test 5.1
Instruction:
Compare actual setpoint with specified setpoint. Indicate Pass/Fail. Note that a deviation from the specified
setpoint doesn’t necessarily indicate a failure. For example, the Owner may have a setpoint standard that differs
from the specified standard. Notate any deviations.
Setpoint Name Specified Actual Pass/Fail Notes
ZONE SETPOINTS, VAV BOXES
Setpoint °F °F
Heating/cooling offset °F °F
Unoccupied night setup °F °F
Unoccupied night setback °F °F
User t’stat override °F °F The amount a user can adjust +/-
setpoint
After hours override 120 mins User pushes t’stat override button
AHU SETPOINTS
Cooling enable, OAT 60°F °F Locks out if OAT < SAT
Cooling setpoint °F Reset based on OAT
Economizer enable >60°F °F Enables based on OA temperature
Economizer SA setpoint °F
Building SP
MA low limit Closes OA dampers below this temp
VFD minimum speed % Typically 15-20 hz [3]
VFD maximum speed %
Min OA damper CFM CFM Given to BMS by TAB
SF VFD setpoint
RF VFD setpoint
Commissioning Comments/Issues
Note Date Issue Attn:
1 VFD min/max’s are set within the unit on the ABB drive. MC to verify.
2
3
4
Use reverse side of page, if necessary
Purpose:
Verify the position of unit-related components when the unit is OFF, and when it is ON.
Prerequisite:
Programming is complete. All inputs/outputs are fully functional.
Instruction:
Begin with unit OFF. Verify that the various components are in states that are normal for them to be in when
the unit is OFF. Turn the unit ON. Verify that the various components are then in states that are normal for
them to be in when the unit is ON. Note that in this application, the term ‘enable’ or ‘modulating’ doesn’t
necessarily imply that something is actually ON or active, but rather that it is EITHER active or it has the
potential to become active. For example, when an AHU is ON, depending on conditions it can either go into
heating or cooling mode – that can happen anytime it is running. Or, when a damper is enabled, it may be
modulating, or it could be fully open or closed.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify the unit goes OFF when a fire/life safety event occurs. Only qualified, authorized personnel should
initiate a fire/life safety event.
Prerequisite:
Programming is complete. All inputs/outputs are fully functional.
Instruction:
Demonstrate that all supply, exhaust, return and relief fans:
A. System should be in Occupied Mode when testing begins
B. System should shutdown when the DDC receives a contact closure from the fire alarm panel
C. System should resume normal operation when the contact closure from the fire alarm panel clears.
D. Verify that the BMS receives and alarm, and also that the BMS alarm clears when the actual alarm
condition clears
It may be necessary to jumper the input to the DDC from the fire alarm panel. Make sure the dial-out to
the fire department is disabled and/or that the fire department is aware of testing. If this is an
occupied building, ensure that occupants are aware of testing.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify that manual and automatic starting/stopping and ramping of the AHU, via the VFD and via the BMS, works
correctly.
Prerequisite:
VFD and AHU have been started, checked out and programmed. Manufacturer’s and/or contractor’s start-up
reports are completed and have been submitted, including a copy to the Commissioning Authority.
Instruction:
A. Place the BMS and VFD in various states of either automatic or manual modes, as indicated.
B. In the second section of the test, note any hard-wired interlocks that exist. Briefly describe what
happens (EF starts when SF starts, or Smoke Detector shuts down AHU, etc.). Next, indicate the ID/tag
of the device or system that is interlocking (Example: EF-1 or SD-1) with the main equipment. Finally,
indicate if the interlock works (Pass/Fail).
VFD Mode Test Instructions SF Response Pass/Fail Notes
Manual BMS Auto command is OFF; turn VFD OFF in manual Off/
Manual Turn VFD ON in manual On/
Manual Ramp VFD to 5 hz; should go to minimum of 10 hz 10 hz/ [2]
Manual Ramp VFD to 95 hz; should go to maximum of 91 hz 91hz/ [2]
Auto BMS Auto command remains OFF Off/
Auto BMS Auto command is placed to ON On/
Auto BMS commands VFD to 5 hz; should go to min. of 10 hz 10hz/ [2]
Auto BMS commands VFD to 95 hz; should go to max. of 91 91hz/ [2]
hz
Auto Release BMS to full Auto Mod/
Manual BMS in Auto; turn VFD manual switch to OFF Off/
Manual BMS in Auto; turn VFD switch back to Auto On/
Auto Place all devices/overrides back into Automatic Mode Auto/
Interlocks Description of Interlock I’lock Pass/Fail Notes
Tag/ID
Interlock 1 Return fan starts when SF starts RF-
Interlock 2 EF starts with AH EF-
Interlock 3 SF manual reset high limit switch for duct static SP HiLim [3] [4]
pressure
Commissioning Comments/Issues
Note Date Issue Attn:
1 Note any programmed skip frequencies here: ____hz
2 VFDs should have on-board min/max speed settings
3 SP HiLim switch should be manual reset. Should shut-off BOTH the SF & RF.
4 SP HiLim - Set: 4” SP – Indicate setpoint P/F: ___
Use reverse side of page if needed
___________________________ ___________ _________ _________ [x] Initial Test
Commissioning Authority Date Date Date
___________________________ ___________ _________ _________ [ ] Retest
Controls Technician Date Date Date
___________________________ ___________ _________ _________
Other Witness/Attendee Date Date Date
Purpose:
Verify that the specified default setpoints have been programmed into the BMS. Monitor control of the setpoints
as they are changed from one value to another value.
Prerequisite:
Programming is complete. Proportional/Integral/Derivative (PID) loops are tuned (and are typically minimally set
up as PI loops). A stop watch might be useful if the monitoring of loop timing is necessary.
Instruction:
A. Verify that default setpoints are programmed, as indicated.
B. Sensors have displays, and include aTOV button.
C. Test setpoint control. Begin in steady state. Each time the setpoint is either raised or lowered, monitor
for smooth transitions to the new setpoint, along with arriving at the new setpoint within a reasonable
time. Transitions should have no more than two (2) cycles of slight-to-moderate overshoot/droop.
Faster reacting loops should stabilize within 2-5 minutes. Slow reacting loops (CHW, HW) may take as
long as 15 or more minutes. If necessary, manually place system into various modes (heating, cooling,
etc.) to perform this test. Also, simulate input values as needed to perform this test. It is permissible to
change the test’s setpoints. Notate, however, if specified default setpoints have been modified.
Setpoint Name Default Defaults Steady Lower Raise the Return Release all Not
Setpoint Pgrmd? State the Setpoint to O’rides es
Value Setpoint Setpoint Normal
EF/RF Bldg SP __” (adj) P/ y/
SF VFD speed P/ y/
RF VFD speed P/ y/
Clg SA __˚F P/ __/ __/ __/ __/ y/
Econ SA __˚F P/ __/ __/ __/ __/ y/
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose/Sequences:
This test verifies that the BMS will correctly switch the unit between cooling and economizer modes.
During occupied mode, the supply air temperature setpoint of __°F will be maintained by modulating the
economizer air dampers and the chilled water valve in sequence. If the outside air temperature drops below
economizer switchover setpoint of 60°F (adj.) the return damper is 100% closed the exhaust & outside air
dampers are 100% open.
The chilled water valve shall be opened and modulated to maintain the SA temperature setpoint. As the OA
temperature falls below the SA temperature setpoint the chilled water valve shall be closed and the economizer
dampers shall modulate to maintain the SA temperature setpoint. If the outside air temperature exceeds the
economizer switchover setpoint. The economizer mode will be disabled. The return air damper will open and
the exhaust air damper will close. Minimum OA volume shown on the equipment schedule shall be maintained
by modulating the OA damper with an integral airflow station.
Prerequisite:
Programming is complete. Unit is fully functional.
Instruction:
A. Mechanical cooling only: begin with the OA temperature simulated to be above 60°F. Only the
minimum OA damper should be open (not the full economizer).
B. Add in economizer: simulate OA temperature at 60°F. Make sure the supply air temperature is greater
than the simulated OA temperature. Economizer and mechanical cooling are both running.
C. Drop out mechanical cooling: simulate the OA temperature below the SA temperature setpoint. Only
economizer is running.
D. Drop out the economizer: Simulate the outside air temperature being above the economizer
switchover setpoint of 60°F
Test Instruction Mech Clg Economizer Min OA
Damper
Place into mechanical cooling, as described above On/ Cl/ Op/
Add in economizer, as described above On/ Op/ Op/
Drop out mechanical cooling, as described above Off/ Op/ Op/
Drop out economizer, as described above Off/ Cl/ Op/
Economizer stage 1
Economizer stage 2
Economizer stage 3
Economizer stage 4
Economizer stage 5
Heating stage 1
Heating stage 2
Heating stage 3
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
Purpose:
Verify that the specified default setpoints have been programmed into the BMS. Monitor control of the setpoints
as they are changed from one value to another value.
Prerequisite:
Programming is complete. Proportional/Integral/Derivative (PID) loops are tuned (and are typically minimally set
up as PI loops). A stop watch might be useful if the monitoring of loop timing is necessary.
Instruction:
A. Verify that default setpoints are programmed, as indicated.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify that the specified inputs/outputs exist on the BMS system. This sheet is for sampling and/or verifying the
contractor’s completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout
sheets.)
Prerequisite:
BMS panel is powered and fully terminated. All I/Os are visible via a laptop or workstation. All wiring and
terminations are labeled. All end devices (sensors, actuators, valves, relays, etc.) are terminated and functional.
The BMS subcontractor has submitted the completed I/O checkout forms, including submitting a copy to the
Commissioning Authority. A VOM meter may be needed for troubleshooting and/or verification.
Instruction:
I/Os may be spread among different panels. This is not a test to determine which panel a point is terminated in.
It is simply a back check to verify that the specified points exist.
A. Name the input/output point, and if it is an AO, AI, DO, DI.
B. Indicate if the point is terminated and if the point can be viewed on the BMS laptop or workstation.
I/O Point Type of Terminated Viewable Comments Notes
Name I/O P/F P/F
Room Temp AI
SA Temp AI
SF Status DI
Clg Valve AO
SF start/stop DO
FC-1 FC-2
Purpose:
Verify the calibrations and/or functionality of the digital inputs. This sheet is for sampling and/or verifying the
contractor’s completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout
sheets.)
Prerequisite:
Same prerequisites as test 6.1.
Instruction:
Sample all digital inputs. If a current transformer (CT) or current switch (CS) is being used to monitor device
on/off status, make sure the CT/CS is calibrated in a manner that allows it distinguish the difference between a
fan (that has a belt drive) being ON and working correctly, and a fan that is ON but the belt is broken. This
would be the setting indicated below as the “Actual Trip Point.” The “Specified Setpoint” establishes the exact
setpoint that a device is supposed to trip, alarm or signal.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify the functionality of the analog inputs.
Prerequisite:
Same as test 6.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority.
Instruction:
Sample all analog inputs. Verify that inputs are not crossed. For example, make sure that Sensor 1 is not showing
up on the BMS as Sensor 2. Methods used to perform this verification may include taking a wire loose, moving a
setpoint, performing TOV, or changing a condition (example, creating more CO2 on a CO2 sensor). Verify that
the Timed Override (TOV) works, where applicable
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify that the end devices start/stop from the BMS. This sheet is for sampling and/or verifying the contractor’s
completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same prerequisites as test 6.1.
Instruction:
Sample all digital outputs. Turn each output point on and off as indicated. Verify that outputs aren’t switched, i.e.,
that output point 1 is turning on device 1 not device 2.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify that the end devices modulate from the BMS. This sheet is for sampling and/or verifying the contractor’s
completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same prerequisites as test 6.1.
Instruction:
Sample all analog outputs. Command each output point as indicated. Visually verify that the stroke position is
basically equivalent to the command.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify the calibration of the analog inputs. This sheet is for sampling and/or verifying the contractor’s completed
I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same as test 6.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority, Certified temperature meters and
magnehelics/manometers are required (verify resolutions). The same meter used by the BMS contractor to
perform initial calibration should be used for this back check.
Instruction:
Sample all analog inputs. First enter the BMS displayed data, and then enter the meter data in the next column.
Temperature readings should be within +/- 1°F. All other readings should be within +/-3%.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify that the specified setpoints have been programmed.
Prerequisite:
Same as test 6.1
Instruction:
Compare actual setpoint with specified setpoint. Indicate Pass/Fail. Note that a deviation from the specified
setpoint doesn’t necessarily indicate a failure. For example, the Owner may have a setpoint standard that differs
from the specified standard. Notate any deviations.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page, if necessary
FC-1 FC-2
Purpose:
Verify the position of unit-related components when the unit is OFF, and when it is ON.
Prerequisite:
Programming is complete. All inputs/outputs are fully functional.
Instruction:
Begin with unit OFF. Verify that the various components are in states that are normal for them to be in when
the unit is OFF. Turn the unit ON. Verify that the various components are then in states that are normal for
them to be in when the unit is ON. Note that in this application, the term ‘enable’ or ‘modulating’ doesn’t
necessarily imply that something is actually ON or active, but rather that it is EITHER active or it has the
potential to become active. For example, when an AHU is ON, depending on conditions it can either go into
heating or cooling mode – that can happen anytime it is running. Or, when a damper is enabled, it may be
modulating, or it could be fully open or closed.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify that manual and automatic starting/stopping the AHU, via the Hand/Off/Auto (HOA) switch and via the
BMS, works correctly.
Prerequisite:
FCU has been started, checked out and programmed. Manufacturer’s and/or contractor’s start-up reports are
completed and have been submitted, including a copy to the Commissioning Authority.
Instruction:
A. Place the BMS and HOA in various states of either automatic or manual modes, as indicated.
B. In the second section of the test, note any hard-wired interlocks that exist. Briefly describe what
happens (EF starts when SF starts, or Smoke Detector shuts down AHU, etc.). Next, indicate the ID/tag
of the device or system that is interlocking (Example: EF-1 or SD-1) with the main equipment. Finally,
indicate if the interlock works (Pass/Fail).
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify that the specified default setpoints have been programmed into the BMS. Monitor control of the setpoints
as they are changed from one value to another value.
Prerequisite:
Programming is complete. Proportional/Integral/Derivative (PID) loops are tuned (and are typically minimally set
up as PI loops). A stop watch might be useful if the monitoring of loop timing is necessary.
Instruction:
A. Verify that default setpoints are programmed, as indicated.
B. Sensors have displays, and include a TOV button.
C. Test setpoint control. Begin in steady state. Each time the setpoint is either raised or lowered, monitor
for smooth transitions to the new setpoint, along with arriving at the new setpoint within a reasonable
time. Transitions should have no more than two (2) cycles of slight-to-moderate overshoot/droop.
Faster reacting loops should stabilize within 2-5 minutes. Slow reacting loops (CHW, HW) may take as
long as 15 or more minutes. If necessary, manually place system into various modes (heating, cooling,
etc.) to perform this test. Also, simulate input values as needed to perform this test. It is permissible to
change the test’s setpoints. Notate, however, if specified default setpoints have been modified.
Setpoint Name Default Defaults Steady Change Change Return Release all Notes
Setpoint Pgrmd? State Setpoint Setpoint to O’rides
Value Setpoint Normal
Cooling __˚F P/ __/ __/ __/ __/ y/
Commissioning Comments/Issues
Note Date Issue Attn:
1 Zone temperature changes may take a while.
2
3
4
5
Use reverse side of page if needed
FC-1 FC-2
Purpose:
Verify the operation of any fan coil unit’s condensate pump. While any of the FCU’s may have a condensate
pump, only one unit is known to have been designed with one: FC-3103
Prerequisite:
FCUs and condensate drains are fully operational.
Instruction:
A. Verify that the pump works and that it drains correctly.
B. Indicate Pass/Fail (P/F) as applicable.
Commissioning Comments/Issues
Note Date Issue Attn:
1 Zone temperature changes may take a while.
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify the position of unit-related components when the unit is OFF, and when it is ON. Perform a minimum of
a 10% sample.
Prerequisite:
Programming is complete. All inputs/outputs are fully functional.
Instruction:
A. Make sure the VAV/CAV box being verified is being associated with the correct AHU.
B. Begin with unit OFF. Verify that the various components are in states that are normal for them to be in
when the unit is OFF.
C. Turn the unit ON. Verify that the various components are then in states that are normal for them to be
in when the unit is ON.
D. Note that in this application, the term ‘enable’ or ‘modulating’ doesn’t necessarily imply that something
is actually ON or active, but rather that it is EITHER active or it has the potential to become active. For
example, when an AHU is ON, depending on conditions it can either go into heating or cooling mode –
that can happen anytime it is running. Or, when a damper is enabled, it may be modulating, or it could
be fully open or closed.
Commissioning Comments/Issues
Note Date Issue Attn:
1 May not be applicable
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that the specified default setpoints have been programmed into the BMS. Monitor control of the setpoints
as they are changed from one value to another value. Sample at least 10%.
Prerequisite:
Programming is complete. Proportional/Integral/Derivative (PID) loops are tuned (and are typically minimally set
up as PI loops). A stop watch might be useful if the monitoring of loop timing is necessary.
Instruction:
A. Verify that default setpoints are programmed, as indicated.
B. Sensors have displays, and include a TOV button.
C. Test setpoint control. Begin in steady state. Each time the setpoint is either raised or lowered, monitor
for smooth transitions to the new setpoint, along with arriving at the new setpoint within a reasonable
time. Transitions should have no more than two (2) cycles of slight-to-moderate overshoot/droop.
Faster reacting loops should stabilize within 2-5 minutes. Slow reacting loops (CHW, HW) may take as
long as 15 or more minutes. If necessary, manually place system into various modes (heating, cooling,
etc.) to perform this test. Also, simulate input values as needed to perform this test. It is permissible to
change the test’s setpoints. Notate, however, if specified default setpoints have been modified.
Setpoint Name Default Defaults Steady Lower Raise the Return Release all Notes
Setpoint Pgrmd? State the Setpoint to O’rides
Value Setpoint Setpoint Normal
Rm Heating __ DegF P/ __/ __/ __/ __/ y/ [1]
Rm Cooling __ DegF P/ __/ __/ __/ __/ y/
Commissioning Comments/Issues
Note Date Issue Attn:
1 Heating/Cooling zone temperature changes may take a while.
2
3
4
5
Use reverse side of page if needed
EF-1 EF-15
EF-2 EF-17
EF-11 EF-18
EF-13 EF-19
Purpose:
Verify that manual and automatic starting/stopping and ramping of the fan, via the local HOA switch and/or
thermostat, works correctly.
Prerequisite:
The fan has been started, checked out and controls are done. Manufacturer’s and/or contractor’s start-up
reports are completed and have been submitted, including a copy to the Commissioning Authority.
Instruction:
A. Place the thermostat and HOA switch in various states of either automatic or manual modes, as
indicated.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
This fan runs 24/7 to serve the Refrigerant Monitoring System. Verify the 24/7 operation schedule and alarm
point if the fan fails.
Prerequisite:
Refer to Test 8.1.
Instruction:
A. Follow test instructions, as indicated
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
EF-2 EF-19
Purpose:
This fan runs based off of the building occupancy schedule. Verify the occupancy schedule programming and
alarm point if fan fails.
Prerequisite:
Refer to Test 8.1.
Instruction:
B. Follow test instructions, as indicated
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
EF-3105 EF-3106
Purpose:
This fan starts/stops based on space temperature. When the space temperature rises above setpoint the fan
becomes energized. When the space temperature falls below setpoint the fan will De-energize. A 4 degree F
deadband shall keep the fan from short cycling.
Prerequisite:
Refer to Test 11.1.
Instruction:
A. Follow test instructions, as indicated
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that the specified inputs/outputs exist on the BMS system. This sheet is for sampling and/or verifying the
contractor’s completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout
sheets.)
Prerequisite:
BMS panel is powered and fully terminated. All I/Os are visible via a laptop or workstation. All wiring and
terminations are labeled. All end devices (sensors, actuators, valves, relays, etc.) are terminated and functional.
The BMS subcontractor has submitted the completed I/O checkout forms, including submitting a copy to the
Commissioning Authority. A VOM meter may be needed for troubleshooting and/or verification.
Instruction:
I/Os may be spread among different panels. This is not a test to determine which panel a point is terminated in.
It is simply a back check to verify that the specified points exist.
A. Name the input/output point, and if it is an AO, AI, DO, DI.
B. Indicate if the point is terminated and if the point can be viewed on the BMS laptop or workstation.
I/O Point Type of Terminated Viewable Comments Notes
Name I/O P/F P/F
CHWS temp AI Common temp to entire system
CHWR temp AI Common temp to entire system
CHWS temp AI For individual chiller
CHWR temp AI For individual chiller
CWS temp AI Common temp to entire system
CWR temp AI Common temp to entire system
CWS temp AI For individual chiller
CWR temp AI For individual chiller
DPT sensor AI Across individual evaporator
DPT sensor AI Across individual condenser
CTwr flow AI Flow meter
CHW DPT AI CHW static pressure
Purpose:
Verify the calibrations and/or functionality of the digital inputs. This sheet is for sampling and/or verifying the
contractor’s completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout
sheets.)
Prerequisite:
Same prerequisites as test 9.1
Instruction:
Sample all digital inputs. If a current transformer (CT) or current switch (CS) is being used to monitor device
on/off status, make sure the CT/CS is calibrated in a manner that allows it distinguish the difference between a
fan (that has a belt drive) being ON and working correctly, and a fan that is ON but the belt is broken. This
would be the setting indicated below as the “Actual Trip Point.” The “Specified Setpoint” establishes the exact
setpoint that a device is supposed to trip, alarm or signal.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify the functionality of the analog inputs.
Prerequisite:
Same as test 9.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority.
Instruction:
Sample all analog inputs. Verify that inputs are not crossed. For example, make sure that Sensor 1 is not showing
up on the BMS as Sensor 2. Methods used to perform this verification may include taking a wire loose, moving a
setpoint, performing TOV, or changing a condition (example, creating more CO2 on a CO2 sensor). Verify that
the Timed Override (TOV) works, where applicable
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
Use reverse side of page if needed
Purpose:
Verify that the end devices start/stop from the BMS. This sheet is for sampling and/or verifying the contractor’s
completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same prerequisites as test 9.1
Instruction:
Sample all digital outputs. Turn each output point on and off as indicated. Verify that outputs aren’t switched, i.e.,
that output point 1 is turning on device 1 not device 2.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that the end devices modulate from the BMS. This sheet is for sampling and/or verifying the contractor’s
completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same prerequisites as test 9.1
Instruction:
Sample all analog outputs. Command each output point as indicated. Visually verify that the stroke position is
basically equivalent to the command.
Commissioning Comments/Issues
Note Date Issue Attn:
1 These percentages are typically 15hz, 35.5hz and 60 hz
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify the calibration of the analog inputs. This sheet is for sampling and/or verifying the contractor’s completed
I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same as test 9.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority, Certified temperature meters and
magnehelics/manometers are required (verify resolutions). The same meter used by the BMS contractor to
perform initial calibration should be used for this back check.
Instruction:
Sample all analog inputs. First enter the BMS displayed data, and then enter the meter data in the next column.
Temperature readings should be within +/- 1°F. All other readings should be within +/-3%.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
Use reverse side of page if needed
Purpose:
Verify a side-by-side comparison of sensors mounted in the same unit/system.
Prerequisite:
Same as test 9.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority, Certified temperature meters and/or
magnehelics/manometers are required (verify resolutions). The same meter used by the BMS contractor to
perform initial calibration should be used for this back check.
Instruction:
A. Disable cooling on units to be tested by overriding outputs to 0.
B. Pose units to be tested to full recirculation by circulating CHW and CW without the chiller being ON,
and without the cooling tower fans running.
C. Start unit running in full recirculation.
D. Wait at least 20 minutes for temperatures in system to blend and stabilize.
E. Verify that the CHW/CW supply/return sensors, throughout the system, are within 3°F of each other.
F. Record data in space provided.
G. Release all overrides at the end of the test.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
Use reverse side of page if needed
Purpose:
Verify that the specified setpoints have been programmed.
Prerequisite:
Same as test 9.1
Instruction:
Compare actual setpoint with specified setpoint. Indicate Pass/Fail. Note that a deviation from the specified
setpoint doesn’t necessarily indicate a failure. For example, the Owner may have a setpoint standard that differs
from the specified standard. Notate any deviations.
Setpoint Name Specified Actual Pass/Fail Notes
CHWS setpoint Reset on Chiller setpoint
OAT
Cooling ON demand Any zone calls for cooling
OAT enable 55 DegF Enable plant above this temperature
Prim pumps Delay OFF 10 min Pumps shut OFF after chiller goes OFF
Lead/lag switch CHWS Monthly Pumps switch positions monthly
Lead/lag switch CWS Monthly Pumps switch positions monthly
Lead pump CWS lock Lead pump always on when CHWS on
CTwr VFD CWS stpt From Condenser water setpoint
CHWS
Enable CTwr bypass valve If CWS temp drops to this temp for X
Enable CTwr bypass valve minutes, start opening bypass to maintain
this new setpoint
CTwr lockout 55 DegF OAT that locks out CWS
CTwr fan min timer adj To prevent short cycling
CTwr stage 1 >72 DegF Natural draft; min flow
CTwr stage 2 <72 DegF Normal operation; Natural draft
but >73.5
DegF
CTwr stage 3 <73.5 DegF Normal operation; Forced draft
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
Use reverse side of page, if necessary
Purpose:
Verify the position of unit-related components when the unit is OFF, and when it is ON.
Prerequisite:
Programming is complete. All inputs/outputs are fully functional.
Instruction:
Begin with unit OFF. Verify that the various components are in states that are normal for them to be in when
the unit is OFF. Turn the unit ON. Verify that the various components are then in states that are normal for
them to be in when the unit is ON. Note that in this application, the term ‘enable’ or ‘modulating’ doesn’t
necessarily imply that something is actually ON or active, but rather that it is EITHER active or it has the
potential to become active. For example, when an AHU is ON, depending on conditions it can either go into
heating or cooling mode – that can happen anytime it is running. Or, when a damper is enabled, it may be
modulating, or it could be fully open or closed.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify that breaking or interrupting hard-wired safety interlocks will shut down the chiller.
Prerequisite:
Chiller plant programming is complete, and plant is fully operational.
Instruction:
The chiller plant should be operational for each of these tests (chiller should be ON or at least be simulated as
ON). Each section of the following set of tests assumes that the chiller is ON.
A. Condition 1: Stop the CHW pump at the HOA switch. The chiller should stop.
B. Condition2: Stop the CW pump at the HOA switch. The chiller should stop.
C. Condition 3: Remove the CHW flow interlock, mounted on the chiller. The chiller should stop.
D. Condition 4: Remove the CW flow interlock, mounted on the chiller. The chiller should stop.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
___________________________ ___________ _________ _________ [x] Initial Test
Commissioning Authority Date Date Date
___________________________ ___________ _________ _________ [ ] Retest
Controls Technician Date Date Date
___________________________ ___________ _________ _________
Other Witness/Attendee Date Date Date
Purpose:
Verify that the specified default setpoints have been programmed into the BMS. Monitor control of the setpoints
as they are changed from one value to another value.
Prerequisite:
Programming is complete. Proportional/Integral/Derivative (PID) loops are tuned (and are typically minimally set
up as PI loops). A stop watch might be useful if the monitoring of loop timing is necessary.
Instruction:
A. Verify that default setpoints are programmed, as indicated.
B. Test setpoint control. Begin in steady state. Each time the setpoint is either raised or lowered, monitor
for smooth transitions to the new setpoint, along with arriving at the new setpoint within a reasonable
time. Transitions should have no more than two (2) cycles of slight-to-moderate overshoot/droop.
Faster reacting loops should stabilize within 2-5 minutes. Slow reacting loops (CHW, HW) may take as
long as 15 or more minutes. If necessary, manually place system into various modes (heating, cooling,
etc.) to perform this test. Also, simulate input values as needed to perform this test. It is permissible to
change the test’s setpoints. Notate, however, if specified default setpoints have been modified.
Setpoint Name Default Defaults Steady Change Change Return Release all Notes
Setpoint Pgrmd? State the the to O’rides
Value Setpoint Setpoint Setpoint Normal
Chiller Reset on P/ y/
OAT
Cooling Tower From P/ y/
chiller
setpoint
CHW DP 12 psi P/ y/
CW Temp Min CW P/ y/
setpoint
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify that manual and automatic starting/stopping and ramping of the motor, via the VFD and via the BMS,
works correctly.
Prerequisite:
VFD and motors have been started, checked out and programmed. Manufacturer’s and/or contractor’s start-up
reports are completed and have been submitted, including a copy to the Commissioning Authority.
Instruction:
A. Place the BMS and VFD in various states of either automatic or manual modes, as indicated.
B. In the second section of the test, note any hard-wired interlocks that exist. Briefly describe what
happens (EF starts when SF starts, or Smoke Detector shuts down AHU, etc.). Next, indicate the ID/tag
of the device or system that is interlocking (Example: EF-1 or SD-1) with the main equipment. Finally,
indicate if the interlock works (Pass/Fail).
VFD Mode Test Instructions SF Response Pass/Fail Notes
Manual BMS Auto command is OFF; turn VFD OFF in manual Off/
Manual Turn VFD ON in manual On/
Manual Ramp VFD to 5 hz; should go to minimum of 10 hz 10 hz/
Manual Ramp VFD to 95 hz; should go to maximum of 91 hz 91hz/
Auto BMS Auto command remains OFF Off/
Auto BMS Auto command is placed to ON On/
Auto BMS commands VFD to 5 hz; should go to min. of 10 hz 10hz/
Auto BMS commands VFD to 95 hz; should go to max. of 91 91hz/
hz
Auto Release BMS to full Auto Mod/
Manual BMS in Auto; turn VFD manual switch to OFF Off/
Manual BMS in Auto; turn VFD switch back to Auto On/
Auto Place all devices/overrides back into Automatic Mode Auto/
Interlocks Description of Interlock I’lock Pass/Fail Notes
Tag/ID
Interlock 1
Interlock 2
Interlock 3
Commissioning Comments/Issues
Note Date Issue Attn:
1 Note any programmed skip frequencies here: ____hz
2 VFDs should have on-board min/max speed settings
3
4
Use reverse side of page if needed
___________________________ ___________ _________ _________ [x] Initial Test
Commissioning Authority Date Date Date
___________________________ ___________ _________ _________ [ ] Retest
Controls Technician Date Date Date
___________________________ ___________ _________ _________
Other Witness/Attendee Date Date Date
Purpose:
Verify that lead/lag switching works correctly. Two conditions cause the switch: lead pump failure, or a timed
interval has elapsed.
Prerequisite:
Chiller plant programming is complete, and plant is fully operational.
Instruction:
A. Condition 1: With the lead pump running, turn it OFF at the HOA switch. The lag pump should start.
B. Condition 2: With the lead pump running, trigger the software run timer. The lag pump should start.
C. In both of the above conditions, it is important to verify that IF the chiller is running during a transition
from one pump to the other pump that the chiller restarts.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
___________________________ ___________ _________ _________ [x] Initial Test
Commissioning Authority Date Date Date
___________________________ ___________ _________ _________ [ ] Retest
Controls Technician Date Date Date
___________________________ ___________ _________ _________
Other Witness/Attendee Date Date Date
Purpose:
The chiller plant will be locked out if the outside air temperature is below 55°F (adj.).
Prerequisite:
CHW plant programming is complete, and plant is fully operational.
Instruction:
A. Begin test with plant turned OFF, outside air temperature simulated as below 55°F.
B. Simulate raising the outside air temperature below 55°F.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Refrigerant Monitoring
System (RMS)
Purpose:
Verify that the Refrigerant Monitoring System is enabled to run 24/7
Prerequisite:
BMS panel is powered and fully terminated. All I/Os are visible via a laptop or workstation. All wiring and
terminations are labeled. All end devices (sensors, actuators, valves, relays, etc.) are terminated and functional.
The BMS subcontractor has submitted the completed I/O checkout forms, including submitting a copy to the
Commissioning Authority. A VOM meter may be needed for troubleshooting and/or verification.
Instruction:
A. Verify the schedule programming for the Refrigerant Monitoring System
Refrigerant Monitoring
System (RMS)
Purpose:
Verify the Refrigerant Monitoring System (RMS) responds correctly upon detection of refrigerant above code
accepted values.
Prerequisite:
Same prerequisites as test 10.1.
Instruction:
Simulate a rise in refrigerant levels above acceptable setpoint (this is to be determined via building safety code).
Verify that the following alarm measures are taken and that the electrical interlock (Break Glass Switch) is
functional for all applicable equipment:
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify that the specified inputs/outputs exist on the BMS system. This sheet is for sampling and/or verifying the
contractor’s completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout
sheets.)
Prerequisite:
BMS panel is powered and fully terminated. All I/Os are visible via a laptop or workstation. All wiring and
terminations are labeled. All end devices (sensors, actuators, valves, relays, etc.) are terminated and functional.
The BMS subcontractor has submitted the completed I/O checkout forms, including submitting a copy to the
Commissioning Authority. A VOM meter may be needed for troubleshooting and/or verification.
Instruction:
I/Os may be spread among different panels. This is not a test to determine which panel a point is terminated in.
It is simply a back check to verify that the specified points exist.
A. Name the input/output point, and if it is an AO, AI, DO, DI.
B. Indicate if the point is terminated and if the point can be viewed on the BMS laptop or workstation.
I/O Point Type of Terminated Viewable Comments Notes
Name I/O P/F P/F
HWS Temp AI
HWR Temp AI
System ∆P AI
HWP status DI
VFD alarm DI
HWP s/s DO
Boiler Enable DO
VFD speed AO
Purpose:
Verify the calibrations and/or functionality of the digital inputs. This sheet is for sampling and/or verifying the
contractor’s completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout
sheets.)
Prerequisite:
Same prerequisites as test 11.1.
Instruction:
Sample all digital inputs. If a current transformer (CT) or current switch (CS) is being used to monitor device
on/off status, make sure the CT/CS is calibrated in a manner that allows it distinguish the difference between a
fan (that has a belt drive) being ON and working correctly, and a fan that is ON but the belt is broken. This
would be the setting indicated below as the “Actual Trip Point.” The “Specified Setpoint” establishes the exact
setpoint that a device is supposed to trip, alarm or signal.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify the functionality of the analog inputs.
Prerequisite:
Same as test 11.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority.
Instruction:
Sample all analog inputs. Verify that inputs are not crossed. For example, make sure that Sensor 1 is not showing
up on the BMS as Sensor 2. Methods used to perform this verification may include taking a wire loose, moving a
setpoint, performing TOV, or changing a condition (example, creating more CO2 on a CO2 sensor). Verify that
the Timed Override (TOV) works, where applicable
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
___________________________ ___________ _________ _________ [x] Initial Test
Commissioning Authority Date Date Date
___________________________ ___________ _________ _________ [ ] Retest
Controls Technician Date Date Date
___________________________ ___________ _________ _________
Other Witness/Attendee Date Date Date
Purpose:
Verify that the end devices start/stop from the BMS. This sheet is for sampling and/or verifying the contractor’s
completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same prerequisites as test 11.1.
Instruction:
Sample all digital outputs. Turn each output point on and off as indicated. Verify that outputs aren’t switched, i.e.,
that output point 1 is turning on device 1 not device 2.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify that the end devices modulate from the BMS. This sheet is for sampling and/or verifying the contractor’s
completed I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same prerequisites as test 11.1.
Instruction:
Sample all analog outputs. Command each output point as indicated. Visually verify that the stroke position is
basically equivalent to the command.
Commissioning Comments/Issues
Note Date Issue Attn:
1 These percentages are typically 15hz, 35.5hz and 60 hz
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify the calibration of the analog inputs. This sheet is for sampling and/or verifying the contractor’s completed
I/O checkout forms. (It can also be used by the contractor in lieu of their own checkout sheets.)
Prerequisite:
Same as test 11.1, with the addition that all calibrations are complete, and the calibration report has been
submitted, with a copy given to the Commissioning Authority, Certified temperature meters and
magnehelics/manometers are required (verify resolutions). The same meter used by the BMS contractor to
perform initial calibration should be used for this back check.
Instruction:
Sample all analog inputs. First enter the BMS displayed data, and then enter the meter data in the next column.
Temperature readings should be within +/- 1°F. All other readings should be within +/-3%.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
___________________________ ___________ _________ _________ [x] Initial Test
Commissioning Authority Date Date Date
___________________________ ___________ _________ _________ [ ] Retest
Controls Technician Date Date Date
___________________________ ___________ _________ _________
Other Witness/Attendee Date Date Date
Purpose:
Verify that manual and automatic starting/stopping and ramping of the motor, via the VFD and via the BMS,
works correctly.
Prerequisite:
VFD and AHU have been started, checked out and programmed. Manufacturer’s and/or contractor’s start-up
reports are completed and have been submitted, including a copy to the Commissioning Authority.
Instruction:
A. Place the BMS and VFD in various states of either automatic or manual modes, as indicated.
B. In the second section of the test, note any hard-wired interlocks that exist. Briefly describe what
happens (EF starts when SF starts, or Smoke Detector shuts down AHU, etc.). Next, indicate the ID/tag
of the device or system that is interlocking (Example: EF-1 or SD-1) with the main equipment. Finally,
indicate if the interlock works (Pass/Fail).
Commissioning Comments/Issues
Note Date Issue Attn:
1 Note any programmed skip frequencies here:
2 VFDs should have on-board min/max speed settings
3
4
Use reverse side of page if needed
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
Use reverse side of page if needed
Purpose:
Verify that the specified default setpoints have been programmed into the BMS. Monitor control of the setpoints
as they are changed from one value to another value.
Prerequisite:
Programming is complete. Proportional/Integral/Derivative (PID) loops are tuned (and are typically minimally set
up as PI loops). A stop watch might be useful if the monitoring of loop timing is necessary.
Instruction:
A. Verify that default setpoints are programmed, as indicated.
B. Test setpoint control. Begin in steady state. Each time the setpoint is either raised or lowered, monitor
for smooth transitions to the new setpoint, along with arriving at the new setpoint within a reasonable
time. Transitions should have no more than two (2) cycles of slight-to-moderate overshoot/droop.
Faster reacting loops should stabilize within 2-5 minutes. Slow reacting loops (CHW, HW) may take as
long as 15 or more minutes. If necessary, manually place system into various modes (heating, cooling,
etc.) to perform this test. Also, simulate input values as needed to perform this test. It is permissible to
change the test’s setpoints. Notate, however, if specified default setpoints have been modified.
Setpoint Name Default Defaults Steady Lower Raise the Return Release all Notes
Setpoint Pgrmd? State the Setpoint to O’rides
Value Setpoint Setpoint Normal
Loop ∆P 12 psi P/ 12/ 14/ 10/ 12/ y/ [1]
HWS OAT 65 125 °F P/ 125/ 125/ 125/ 125/ [2]
HWS OAT 30 145 °F P/ 145/ 145/ 145/ 125/
HW Reset OAT P/
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
___________________________ ___________ _________ _________ [x] Initial Test
Commissioning Authority Date Date Date
___________________________ ___________ _________ _________ [ ] Retest
Controls Technician Date Date Date
___________________________ ___________ _________ _________
Other Witness/Attendee Date Date Date
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
The boiler plant will be locked out if the outside air temperature is above 65°F (adj.).
Prerequisite:
Hot water heating plant programming is complete, and plant is fully operational.
Instruction:
C. Begin test with plant turned OFF, outside air temperature simulated as above 65°F.
D. Simulate lowering outside air temperature below 65°F.
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
Verify Testing, Adjusting and Balancing (TAB) of the system. Sampling is at the Commissioning Authority’s
discretion, and other verifications may be required.
Prerequisite:
The system is fully operational and balanced. The TAB subcontractor has submitted the draft and/or the final
TAB Report, and provided a copy to the Commissioning Authority.
Instruction:
A. Enter design TAB values
B. Enter TAB report values
C. Enter the verification/sampled values
D. Calculate the design versus actual/sampled values and enter in the +/- 10% column
E. A tolerance of +/- 10% is acceptable
F. Enter actual conditions on last row, as indicated
Supply Fan Design TAB Report Actual/Sample +/- 10% Pass/Fail Notes
SA CFM
OA CFM
RA CFM
MA CFM
Clg ∆T
Htg ∆T
SAT
SA SP
Ex/Ret Fan Design TAB Report Actual/Sample +/- 10% Pass/Fail Notes
EF/RF CFM
Bldg SP
Conditions OAT SAT RAT MAT Notes
Temps. °F °F °F °F
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
Use reverse side of page if needed
Purpose:
Verify Testing, Adjusting and Balancing (TAB) of the system. Sampling is at the Commissioning Authority’s
discretion, and other verifications may be required. This test can be used for either SA or RA diffusers/grilles.
Prerequisite:
The system is fully operational and balanced. The TAB subcontractor has submitted the draft and/or the final
TAB Report, and provided a copy to the Commissioning Authority.
Instruction:
A. Enter design TAB values
B. Enter TAB report values
C. Enter the verification/sampled values
D. Calculate the design versus actual/sampled values and enter in the +/- 10% column
E. A tolerance of +/- 10% is acceptable
F. Enter actual conditions on last row, as indicated
Purpose:
Verify Testing, Adjusting and Balancing (TAB) of the system. Sampling is at the Commissioning Authority’s
discretion, and other verifications may be required.
Prerequisite:
The system is fully operational and balanced. The TAB subcontractor has submitted the draft and/or the final
TAB Report, and provided a copy to the Commissioning Authority.
Instruction:
A. Enter design TAB values
B. Enter TAB report values
C. Enter the verification/sampled values
D. Calculate the design versus actual/sampled values and enter in the +/- 10% column
E. A tolerance of +/- 10% is acceptable
F. Enter actual conditions on last row, as indicated
Supply Fan Design TAB Report Actual/Sample +/- 10% Pass/Fail Notes
Min. CFM
Max. CFM
Ent. SP
Clg ∆T
Htg ∆T
HW ∆P
HW ∆T
Diffuser ID Design TAB Report Actual/Sample +/- 10% Pass/Fail Notes
Diffuser 1
Diffuser 2
Diffuser 3
Diffuser 4
Diffuser 5
Diffuser 6
Diffuser 7
Diffuser 8
Diffuser 9
Diffuser 10
TOTAL
Conditions OAT Ent. Temp Lvg. Temp BMS T’stat Act T’stat Notes
Temps. °F °F °F °F °F
Use reverse side of page if needed
Purpose:
Verify Testing, Adjusting and Balancing (TAB) of the system. Sampling is at the Commissioning Authority’s
discretion, and other verifications may be required.
Prerequisite:
The system is fully operational and balanced. The TAB subcontractor has submitted the draft and/or the final
TAB Report, and provided a copy to the Commissioning Authority.
Instruction:
A. Enter grille CFM design TAB values
B. Enter grille CFM TAB report values
C. Enter the grille CFM verification/sampled values
D. Calculate the design CFM versus actual/sampled CFM values and enter in the +/- 10% column
E. A tolerance of +/- 10% is acceptable
F. Enter actual conditions on last row, as indicated
Purpose:
Verify Testing, Adjusting and Balancing (TAB) of the system. Sampling is at the Commissioning Authority’s
discretion, and other verifications may be required.
Prerequisite:
The system is fully operational and balanced. The TAB subcontractor has submitted the draft and/or the final
TAB Report, and provided a copy to the Commissioning Authority.
Instruction:
A. Enter design TAB values
B. Enter TAB report values
C. Enter the verification/sampled values
D. Calculate the design versus actual/sampled values and enter in the +/- 10% column
E. A tolerance of +/- 10% is acceptable
F. Enter actual conditions on last row, as indicated
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose:
Verify Testing, Adjusting and Balancing (TAB) of the system. Sampling is at the Commissioning Authority’s
discretion, and other verifications may be required.
Prerequisite:
The system is fully operational and balanced. The TAB subcontractor has submitted the draft and/or the final
TAB Report, and provided a copy to the Commissioning Authority.
Instruction:
A. Enter design TAB values
B. Enter TAB report values
C. Enter the verification/sampled values
D. Calculate the design versus actual/sampled values and enter in the +/- 10% column
E. A tolerance of +/- 10% is acceptable
F. Enter actual conditions on last row, as indicated
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
Use reverse side of page if needed
Purpose
The CxA assumes BMS control of the domestic hot water system. Field modify the test procedures, if necessary.
Prerequisite:
The domestic hot water has been started, checked out and programmed. Manufacturer’s and/or contractor’s
start-up reports are completed and have been submitted, including a copy to the Commissioning Authority.
Instruction:
A. Verify the sequence of operation
B. Unoccupy the building BMS schedule, and verify that the system is turned OFF and can’t start.
C. Verify that when the water heater goes OFF, the pump remains on for 30 seconds (adj.).
Test Instructions HW Htr Pump Pass/Fail Notes
BMS unoccupied Off/ Off/
BMS occupied En/ Off/
Call for heat En/ On/
No call for heat En/ On/
30 seconds elapse En/ Off/
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
CxA assumes HW tank setpoint of 110°f (adj.). Verify the domestic hot water system is functional. This system
is enabled via TOD from the BMS. The circulating pump (HWCP-3101) runs if the water heater is ON, or if the
pipe temperature is below 105°F (adj.), as measured by a pipe-mounted Aquastat.
Prerequisite:
The domestic hot water heater is fully functional. The tank water temperature is at setpoint. The circulating
pump (HWCP-3101) is operational. Hot water is available at all janitor’s closets, sinks, lavatories, etc.
Instruction:
A. With an occupied building and an enabled water heater, verify the water heater thermostat setpoint
and compare to the actual temperature (+/- 5 degrees is acceptable)
B. Verify the pipe-mounted circulating pump thermostat setpoint. More readings are done in the next test;
this reading simply verifies that hot water is circulating.
Verify as Indicated Setpoint Actual Area Indicate Sample Reading Location Notes
WHtr internal t’stat setpoint °F °F n/a
Circ pump setpoint 105°F °F n/a
Sample reading, Dom Htr 1 110°F °F
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose/Sequence:
Verify that the domestic hot water heater is maintaining setpoint. There are also Cross-Connect checks.
Prerequisite:
The domestic hot water heater is fully functional. The tank water temperature is at setpoint. The circulating
pump is operational. Hot water is available at all janitor’s closets, sinks, lavatories and/or showers.
Instruction:
A. Verify the temperature at the water heater
B. Take sample readings at remote fixtures (+/- 5 degrees compared to water heater is acceptable)
C. Also, run cold water at various fixtures to make sure lines aren’t crossed
D. Flush toilets and shoot the entering water with I/R meter, to verify lines aren’t crossed
Test Location Room/Area HW CW Pass/Fail Indicate any Pass/Fail Notes
Temp Temp crossed lines
Dom HW Htr n/a
Lavatory 1
Lavatory 2
Lavatory 3
Lavatory 4
Lavatory 5
Lavatory 6
Toilet 1 n/a
Toilet 2 n/a
Toilet 3 n/a
Toilet 4 n/a
Toilet 5 n/a
Toilet 6 n/a
Janitor 1
Janitor 2
Commissioning Comments/Issues
Note Date Issue Attn:
1
2
3
4
5
6
7
Use reverse side of page if needed
Purpose:
The purpose of functional testing is to verify the normal operational qualities of the tested systems. Each system
is ‘put through its paces,’ and is monitored for proper performance. Often, other systems are being viewed
simultaneously. This testing verifies the more advanced aspects of the sequences of operations.
Prerequisite:
All systems must be fully operational, including mechanical, FUNCTIONAL TEST LOCATIONS
electrical, BMS and life safety. Note that some functional testing is
A. Start-up of all equipment is complete performed in other Sections of the test
B. Control programming is complete procedures. This is done to keep tests
C. BMS graphics are complete efficient.
D. BMS alarms are programmed and functional
E. BMS trends are programmed and active
F. Pre-Functional Testing is complete
G. All HVAC and BMS systems are in full automatic mode
H. All BMS panels are active and communicating
Participants:
A. Commissioning Authority
B. BMS contractor
C. Mechanical contractor – available or on call
D. Electrical contractor – available or on call
E. General contractor – available or on call
Contact List, Functional Testing Phase
Contact Name Company Phone Number Email
Test Description:
A. This test verifies the occupancy cycle of the entire building. Perform during daylight hours.
B. This test verifies the position of various systems, to make sure that systems are in their proper state
during occupied and unoccupied modes. Some equipment/systems remain enabled 24/7, as indicated.
Change modes via the BMS.
Commissioning Comments/Issues
Note Date Issue Attn:
1 Capture screen shots, and record trends. Get copies of both and attach.
2
3
4
Test Description:
A. This test verifies that when the building is in cooling mode, the entire system is stable.
B. Create conditions for cooling. Economizer and chiller plants should be in AUTO mode.
C. System should be running for at least 30-60 minutes prior to beginning this test.
D. Verify that appropriate systems are maintaining setpoint, as indicted.
E. Chiller plant is being verified, in addition to applicable air systems.
Commissioning Comments/Issues
Note Date Issue Attn:
1 Capture screen shots, and record trends. Get copies of both and attach.
2
3
4
5
6
Use reverse side of page if needed
Test Description:
A. This test verifies that when the building is in heating mode, the entire system is stable.
B. Create conditions for heating. Economizer and chiller plants should be in AUTO mode.
C. System should be running for at least 30-60 minutes prior to beginning this test.
D. Verify that appropriate systems are maintaining setpoint, as indicted.
Commissioning Comments/Issues
Note Date Issue Attn:
1 Capture screen shots, and record trends. Get copies of both and attach.
2
3
4
5
6
Use reverse side of page if needed
Test Description:
This test verifies building-wide optimum start. It verifies what does/does not start or operate during optimum
start conditions. The test begins with the building in unoccupied mode. Below sequence is assumed by CxA.
Optimum Start
The system shall use an optimal start algorithm for morning start-up. This algorithm shall minimize the
unoccupied warm-up or cool-down period while still achieving comfort conditions by the start of scheduled
occupied period. While under optimal start, the outside air damper shall remain completely closed until space is
satisfied. Outside air damper shall remain closed and not go to minimum position after optimal start period ends
while space temperature has not been satisfied.
VAV Box Optimum Start
The unit shall use an optimal start algorithm for morning start-up. This algorithm shall minimize the unoccupied
warm-up or cool-down period while still achieving comfort conditions by the start of scheduled occupied period.
Box shall modulate towards 100% closed under optimal start to maintain space temperature. Minimum setting
shall revert to normal operation once space is satisfied and space is occupied.
Test Description:
Enter the Optimum Start Reset Scale
A. Enter the top and bottom end of the temperature scale
B. Enter the time (in minutes) that correspond to the temperature scale.
C. Verify it works by simulating the inputs. For example, if heating optimum start were based solely on an
outdoor temperature reset scale of 30-70°F, and if each degree below 70° would advance started the
building by two minutes, then simulating a 60° outside temperature should yield a 20 minute advance
start.
D. The concept of “weight factor” needs to be noted. Weight factor = the greater influence of outside air
temperature vs. indoor air temperature, or vice versa. Is it 2:1, 3:1, 1.2:1, 1:2?
E. Enter the earliest optimum start time allowed prior to normal occupied start time. Ex: if normal start
time is 7:00 AM, what is the earliest time BEFORE 7:00 AM that optimum start is allowed to engage? In
addition, on Monday’s – after a weekend of being OFF – optimum start is typically given additional time
to advance start. Enter that time separately.
F. Verify which OA sensor is being used in the calculation, as well as which ID temperature sensors are
being used to establish a building average temperature.
Commissioning Comments/Issues
Note Date Issue Attn:
1 Capture screen shots, and record trends. Get copies of both and attach.
2 Trend logs should depict comfortable conditions by occupancy time.
3
4
5
6
Use reverse side of page if needed