Professional Documents
Culture Documents
PETRONAS Procedures and Guidelines For Upstream Activities (PPGUA 3.0)
PETRONAS Procedures and Guidelines For Upstream Activities (PPGUA 3.0)
Executive Summary 10
Contact Information 10
Definitions 11-13
Official Correspondence 14
Company Press Release 14
Section 1: Drilling Programme Approval 15
1.1 Notification 15
1.2 Wellsite Survey and Shallow Hazard Report 15
1.3 Well Positioning 15
1.3.1 Pre-survey Preparation 15
1.3.2 Positioning Operations 16
1.3.3 Post-positioning Works 16
1.4 Notice of Operations (NOOP) 16-17
1.5 Variations 17
Section 2: Recording and Reporting 18
2.1 Priority Reporting 18
2.2 Rig Arrival and Release Notice 18
2.3 Daily Drilling Report 18-19
2.4 Final Drilling and Completion Report 19-20
2.5 Supporting Reports 20
Section 3: Drilling Quality Assurance/Quality Control 21
3.1 Quality Plan 21
3.2 Quality Requirements 21
3.3 Quality Implementation and Continuous Improvement 21-22
Section 4: Drilling Unit Design, Manning and Logistics 23
4.1 Drilling Unit Design 23
4.1.1 Drilling Unit Inspection 23
4.1.2 General Arrangement Drawings 23-24
4.2 Blowout Preventer Equipment 24
4.3 Protection Against External Hazards 24
4.4 Personnel Safety and Welfare 24
4.4.1 Safety Guards and Exits 24
4.4.2 Derrick Escape 25
4.4.3 Rotary Tongs 25
4.4.4 Medical Facilities and Provisions 25
2 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
4.5 Fire Protection 25
4.5.1 Fire Fighting Equipment 25-26
4.5.2 Fire Alarm System 26
4.6 Gas Detection 26
4.7 Pollution Prevention 26
4.8 Helideck on Drilling Units 26-27
4.9 Pressure System 27
4.10 Electrical Installation 27
4.10.1 Equipment and Standards 27
4.10.2 Lighting 28
4.10.3 Emergency Electrical Power Supply 28
4.11 Forced Air System and Ventilation 28
4.11.1 Hazardous System 28
4.11.2 Ventilation 28
4.11.3 Engines and Motors 29
4.11.4 Exhaust Pipes 29
4.12 Weather Data Recording 29
4.13 Diving 29
4.14 Emergency Shutdown 29
4.15 Manning 29
4.16 Support Craft 30
Section 5: Well Design and Drilling Operations 31
5.1 Drilling Unit Moving and Positioning 31
5.1.1 General Provision 31
5.1.2 Anchor Testing for Drilling Unit 31
5.1.3 Bottom Supported Unit 31-32
5.1.4 Dynamically Positioned Units 32
5.1.5 Diving Operations 32
5.2 Casing and Cementing 32
5.2.1 Drive Pipe 33
5.2.2 Conductor Casing 33-34
5.2.3 Surface Casing 34
5.2.4 Intermediate Casing 34
5.2.5 Production Casing 34-35
5.2.6 Casing Pressure Test 35-36
5.2.7 Records 36
5.2.8 Cementation 36-37
PPGUA/3.0/042/2013 3
VOLUME 8
DRILLING AND WELL
OPERATIONS
5.2.9 Excess Cement Volume 37
5.2.10 Inadequate Cement Job 37
5.3 Well Directional Survey 37
5.3.1 Vertical Well 37
5.3.2 Directional Well 37-38
5.4 Well Control Equipment and Testing 38
5.4.1 BOP System 38
5.4.2 Auxiliary Equipment 38-39
5.4.3 Diverter System 39
5.4.4 Surface BOP Stack 39-40
5.4.5 Subsea BOP Stack 40-41
5.4.5.1 Subsea BOP Diversion 41
5.4.6 BOP Test 41
5.4.6.1 BOP Control System 41-42
5.4.6.2 Pressure Test 42
5.4.6.3 Function Test 42-43
5.4.7 Inspection and Maintenance 43
5.4.8 Personnel Competency 43-44
5.5 Drilling Fluid Programme 44
5.5.1 Primary Well Control 44-45
5.5.2 Drilling Fluid Test 45-46
5.5.3 Drilling Fluid Quantity 46
5.6 Formation Integrity Test 46
5.7 Lost Circulation 47
5.8 Detection of Overpressure 47
5.9 Suspension of Operations 47-48
5.10 Shallow Hazards and Hydrocarbons 48
5.11 Underbalanced Drilling 49
5.12 H2S Drilling Operations 49
5.12.1 Physical Properties and Toxicity 49-50
5.12.2 Breathing Equipment 50
5.12.3 H2S Gas Detection 50
5.12.4 Wind Direction Equipment 50
5.12.5 Ventilation 50
5.12.6 Personnel Training 51
5.12.7 Contingency Plan 51
5.12.8 Drilling Unit Equipment 51-52
4 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
5.12.8.1 Drill Pipe 52
5.12.8.2 Tubulars 52
5.12.8.3 BOP and Related Equipments 52
5.12.8.4 Flare System 52
5.12.9 Drilling Operations 52
5.12.9.1 Pipe Trips and Stripping 52
5.12.9.2 Well Control 53
5.12.9.3 Coring 53
5.12.9.4 Drilling Fluid 53
5.12.10 Well Testing Operations 53
5.13 HPHT Drilling Operations 54
5.13.1 Risk Management 54
5.13.2 Personnel Training 54
5.13.3 Preparation and Planning 54-55
5.13.4 Well Engineering and Design 55
5.13.5 Drilling Unit and Equipment 56
5.13.6 Contingency Plan 56
Section 6: Formation Evaluation 57
6.1 Drill Cutting Sampling 57
6.1.1 Sample Frequency 57
6.1.2 Sample Container 57
6.2 Coring 57
6.2.1 Conventional Cores 57
6.2.2 Side Wall Cores 57-58
6.3 Formation Evaluation Logging 58
6.4 Oil and Gas Flow Testing 58
Section 7: Completion Operations 59
7.1 General Provision 59
7.2 Wellhead Equipment 59
7.3 Tubing Requirements 59-60
7.4 Subsurface Safety Valve 60
7.4.1 Installation 60
7.4.2 Valve Specifications 60-61
7.4.3 Reinstalling, Testing and Maintenance 61
7.4.4 Tubing and Plug Testing 61
7.4.5 Additional Protective Equipment 61
7.4.6 Records 61-62
PPGUA/3.0/042/2013 5
VOLUME 8
DRILLING AND WELL
OPERATIONS
7.5 Packer Requirements 62
7.5.1 Cement Packer 62
7.5.2 Circulating Device 62
7.6 Separation of Zones 62
7.7 Landing Nipples 63
7.8 Completion Fluid 63
7.9 Packer Fluid 63
Section 8: Barriers and Well Integrity 64
8.1 Number of Well Barriers 64
8.2 Barrier Failure and Restoration 64
8.3 Barrier Material 64
8.3.1 Solidified Cement 64
8.3.2 Mechanical Barrier 64-65
8.3.3 Fluid Barrier 65
8.4 Well Integrity Management 65
Section 9: Plug and Abandonment of Wells 66
9.1 Responsibility to Abandon a Well 66
9.2 Application to Abandon a Well 66-67
9.3 Subsequent Report of Abandonment 67
9.4 Permanent Abandonment 67
9.4.1 Isolation of Zones in Open Hole 67-68
9.4.2 Isolation of Open Hole 68
9.4.3 Plugging or Isolation of Perforated Intervals 68-69
9.4.4 Plugging of Casing Stub 69
9.4.4.1 Stub Terminating Inside Casing String 69
9.4.4.2 Stub Terminating Below Casing String 69
9.4.4.3 Liner Top or Screen 69-70
9.4.4.4 Plugging of Annular Space 70
9.5 Surface Plug 70
9.6 Testing of Plugs 70
9.7 Abandonment Fluid 70-71
9.8 Clearance of Location 71
9.9 Well Suspension 71
9.10 Temporary Well Suspension 71
9.11 Suspended Well 71
6 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 10: Workover and Well Intervention Operations 72
10.1 General Requirement 72
10.1.1 Well Intervention 72-73
10.1.2 Workover 73
10.1.3 Operations 73
10.2 Workover Unit and Equipment 73
10.2.1 Workover Structure 73
10.2.2 Travelling Block Safety Device 73
10.2.3 Pumping Equipment 73-74
10.2.4 Pumping Operations 74
10.2.5 Hazardous Chemicals 74
10.3 Well Unloading Operations 74-75
10.4 Notification and Submittal Requirements – Workover 75
10.4.1 Notice of Workover Operations and Major Well Intervention 75
10.4.2 Workover Reports and Data Retention 76
10.4.3 Daily Workover Report 76
10.4.4 Final Workover Report 76-77
10.5 Major Well Intervention Operations 77
10.6 Notification and Submittal Requirements – Major Well Intervention 77
10.6.1 Well Intervention Activity Reports 77-78
10.7 Routine Well Intervention Operations 78
10.8 Well Control Equipment 78
10.8.1 Workover Pressure Control Equipment 78
10.8.2 Well Intervention Pressure Control Equipment 79
10.8.2.1 Coil Tubing Operations 79
10.8.2.2 Electric Line or Braided Line Operations 79
10.8.2.3 Slickline Operations 79
10.8.2.4 Snubbing Operations 79-80
10.8.3 Other Equipment 80
10.8.4 Well Control Fluids 80
10.8.5 Well Control 80
10.8.6 Pressure and Function Test 81
10.8.6.1 Pressure Test 81
10.8.6.2 Function Test 81
10.8.6.3 Lubricators 81
10.9 Emergency Shutdown (ESD) 81
10.10 Wireline Operations 82
PPGUA/3.0/042/2013 7
VOLUME 8
DRILLING AND WELL
OPERATIONS
10.10.1 General Requirements 82
10.10.2 Operations in Cased Hole 82
10.10.3 Operations in Open Hole 83
10.10.4 Swabbing Operations 83-84
10.11 Rigging Up or Down of Workover or Completion Equipment 84
Section 11: Onshore Drilling Operations 85
11.1 Drill Site and Camp Design 85
11.1.1 License and Permits 85
11.1.2 Risk Assessment 85-86
11.1.3 Access Road 86
11.1.4 Campsite 87
11.1.5 Water Pit and Drilling Fluid Pit 87-88
11.1.6 Flare Pit and Vent/Bleed-Off Line 88
11.1.7 Water Well and Water Source 88
11.1.8 Fencing and Well Security 88
11.2 Environment Protection and HSE 89
11.2.1 Emergency Response 89
11.2.2 Protection of Fresh Water Sands 89
11.2.3 Well Near Water Source 89
11.2.4 Drilling Liquid Waste, Contamination and Spills 89-90
11.2.5 Fire Prevention and Safety 90
11.2.5.1 Smoking 90
11.2.5.2 Engines Exhaust 90
11.2.5.3 Engines Intake 91
11.2.6 Restoration of Drill Site 91
11.3 Well Design and Drilling Operations 91
11.3.1 Reference for Well Depth 91
11.3.2 BOP System 91
11.3.3 Pressure and Function Test 91
11.3.4 Casing Programme 92
11.3.4.1 Stove Pipe 92
11.4 Plug and Abandonment of Well 92
Section 12: Onshore Completion, Workover and Intervention Operations 93
12.1 General 93
12.2 Subsurface Safety Valve 93
12.3 Well Stimulation 93
12.4 Disposal of Produced Fluids 93-94
8 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
12.5 Onshore Wellhead Valve Assembly 94
12.6 Wells on Pump 94
Section 13: Waste Material Handling and Disposal 95
13.1 Material Handling 95
13.1.1 Bulk Material 95
13.1.2 Other Material 95
13.2 Disposal of Material 96
13.2.1 Drilling Fluid 96-97
13.2.2 Solid Waste 97
13.2.3 Liquid Waste 97-98
13.2.4 Sewage 98
13.3 Pollution Prevention 98
13.3.1 Offshore Pollution 98
13.3.2 Blowout Contingency Plan 98-99
13.3.3 Onshore Pollution 99-100
Abbreviations 101-103
Appendix 1 104-106
Acknowledgements 107
PPGUA/3.0/042/2013 9
VOLUME 8
DRILLING AND WELL
OPERATIONS
Executive Summary
This volume provides procedures for conducting offshore and onshore well
drilling, completion, testing, workover, intervention and servicing activities in
Malaysia. These procedures may be added to or amended from time to time upon
written notice by PETRONAS and provided such additions or amendments are
consistent with the provisions of the Contract. In adding to or amending the
procedures, PETRONAS shall consider the incremental expenditures which may be
incurred by Contractor in complying with the amended procedures.
PETRONAS shall have the right to be actively involved in all phases of Contractor’s
well drilling, completion, testing, workover, intervention and servicing activities
planning, preparation and execution.
Contact Information
All correspondence related to this volume shall be addressed to:
General Manager
Drilling
Petroleum Operations Management
Petroleum Management Unit
10 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Definitions
In this procedure, terms and expressions not specifically defined below shall have
the sense and meaning commonly attributed to them in the oil and gas exploration
and production industry unless the context requires otherwise:
TERM DEFINITION
Autoshear System A safety system that is designed to automatically
shut-in the wellbore in the event of a disconnect of the
Lower Marine Riser Package (LMRP). When the autoshear is
armed, a disconnect of the LMRP closes the shear rams.
Coiled-Tubing Operations Operations using spooled non-jointed pipe through the
wellhead and well tubing.
Conductor Casing The second casing string set in the order of normal
installation based on the relevant engineering and/or
geological factors (including the presence or absence of
hydrocarbons, potential hazards and water depth). The
Conductor Casing may also be first casing string set in lieu
of Drive Pipe or Structural Casing to support unconsolidated
deposits and to provide hole stability for initial drilling operations.
Deadman System A safety system that when armed is designed to automatically
close the wellbore in the event of a simultaneous absence of
hydraulic supply and signal transmission capacity in both subsea
control pods.
Deepwater Generally described as water depth beyond 300 metres.
Diverter A device for the purpose of diverting the uncontrolled flow
of fluid from the well bore.
Drill Stem Test A test that is performed by allowing formation fluids to
flow to the surface through the drill pipe or test string. It
is normally used for determination of well productivity.
Drilling Programme The programme for the drilling of one specific well.
Drilling Sequence A programme for the drilling of one or more wells as
presented in the annual Work Programme & Budget (WPB) and
its subsequent revisions.
Drilling Unit A drill ship, submersible, semi-submersible, barge, jack-up, land
rig or other vessels used in a drilling programme and includes
a drilling rig and other related facilities installed on a vessel.
PPGUA/3.0/042/2013 11
VOLUME 8
DRILLING AND WELL
OPERATIONS
TERM DEFINITION
Drive pipe or Structural The first casing string set in the order of normal installation
Casing by driving, jetting or drilling to a competent bed as means to
provide support to unconsolidated deposits and to provide
hole stability for initial drilling operation.
Emergency Disconnect A system that when activated initiates a pre-programmed
System (EDS) sequence of well securing Blowout Preventer (BOP) functions in
a minimum amount of time prior to disconnection of the LMRP.
External Hazard Environmental conditions occurring on the drilling unit or
drilling base which threaten the safety of the operation.
High Pressure High A well generally described as having an undisturbed
Temperature (HPHT) Bottom Hole Temperature (BHT) greater than 300°F (149°C) and
maximum pore pressure exceeding 0.8 psi/ft or requiring
pressure control equipment with a rated working pressure in
excess of 10,000 psi.
Intermediate Casing The string or strings of casing set after the surface casing in
the order of normal installation to protect against anticipated
pressures, mud weight, sediment, and other well conditions.
The setting depth for this casing is normally based on the
pressure test of the exposed formation below the surface
casing shoe or any other previous intermediate casing shoe and
anticipated formation pressure of the hole section to be drilled.
Kick Influx of wellbore fluid into the wellbore and possible loss
of primary control of the well which shall be controlled by
secondary control (BOP).
Liner A string of casing installed inside a casing string or
another liner and lapped back inside the previous casing or liner
for at least 30 metres. A liner may be used as a drilling liner
or production liner. A liner may also be tied back to surface if
required in which it will be regarded as a production string.
Lubricator Assembly A setup consisting of wireline BOP, a riser assembly with a bleed
valve and a wireline pack off.
Non-FDP wells Wells that are not included in the original approved Field
Development Plan (FDP) and require additional approval from
PETRONAS. A minimum of fourtteen (14) days notice shall
be given prior to spudding the well.
Offshore Well A well drilled from offshore drilling unit.
12 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
TERM DEFINITION
Oil Spill Any unexpected loss of crude oil, condensate or hydrocarbon
containment that reaches the environment, for example,
water or land irrespective of quantity recovered.
Open Hole A well bore or portion of a wellbore that is not protected by
casing.
Production Casing A string of casing which is set for the purpose of completing the
well for production.
Shooting Nipple Assembly Wireline packoff and a riser assembly held in place by BOP.
Small-Tubing Operations Operations using jointed pipes through the wellhead and well
tubing.
Snubbing Operations Operations using jointed tubing or drill pipe and a snubbing unit
under pressure conditions, either through the wellhead valve
assembly and well tubing of a completed well or through the
BOP and wellbore of a conventional operation.
Spud The initial penetration of the ground or sea floor for the purpose
of drilling a well.
Stripping Operations Operations that require manipulation of the drill string or work
string through BOP, under low or moderate pressure, without
the use of a snubbing unit.
Surface Casing The casing string set after the Conductor Casing in the order
of normal installation in a competent bed based upon relevant
engineering and/or geological factors, including the presence
or absence of hydrocarbons, potential hazards, and water
depths. The Surface Casing shall be set in order for the next hole
section to be drilled with BOP.
Waste Material Refuse, non-biodegradable garbage or any other useless
material generated during drilling and related operations
excluding fluid and drill cuttings.
Well Intervention Remedial operations performed with the christmas tree not
Operations removed.
Well Material Any formation or reservoir material obtained from a well and
includes cuttings, cores or fluids.
Well Suspension The temporary cessation of drilling/completion activities
(waiting for final completion or abandonment).
Workover Operations Remedial operations performed with the christmas tree
removed and BOP installed.
PPGUA/3.0/042/2013 13
VOLUME 8
DRILLING AND WELL
OPERATIONS
Official Correspondence
Refer to Appendix 1 of this volume.
14 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 1: Drilling Programme Approval
1.1 Notification
Contractor shall notify PETRONAS in the Work Programme & Budget (WPB)
and subsequent revisions of its intention to undertake any particular
Drilling Campaign.
For deepwater operations, hazards such as shallow gas, shallow water flow,
hydrates and expulsion features should be evaluated. 3D seismic or other
imaging methods may be used in lieu of conventional shallow seismic, as
appropriate.
PPGUA/3.0/042/2013 15
VOLUME 8
DRILLING AND WELL
OPERATIONS
1.3.2 Positioning Operations
Contractor shall ensure the safety of pipelines and cables underlying
subsea and perform pre-spud and final post-spud verifications.
16 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
execution phase, if Contractor anticipates that there will be a potential cost
overrun of 10% from the approved well cost or Non-Productive Time (NPT)
more than fifty (50) consecutive hours, Contractor shall give written notice to
PETRONAS. In addition, if the above well has been completed, Contractor
shall submit and present the case to PETRONAS.
1.5 Variations
Contractor may implement variations or deviation to the approved NOOP as
deemed operationally necessary or desirable to achieve the agreed
objectives of the well in an efficient and safe manner, however prior
PETRONAS’ approval is required for significant deviations. The request for
approval submission shall include risk assessment and/or MOC documents.
Significant deviation refers to any changes that increase health, safety,
environmental or financial risk and/or well cost.
PETRONAS may require Contractor to show that specific equipment or
procedures are consistent with the interests of safe and efficient operations.
Contractor shall modify or replace any equipment or alter any procedure
that cannot be shown to be safe. Contractor shall install new equipment or
initiate new procedures if necessary to conduct safe operations.
Notwithstanding the above, during an emergency or contingency,
procedures or equipment may be altered without prior PETRONAS’ approval
and in such cases, PETRONAS shall be notified forthwith of the alterations
and the underlying circumstances within 24 hours.
PPGUA/3.0/042/2013 17
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 2: Recording and Reporting
18 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
e) Plan cost (USD or RM);
f ) Current cost (daily and cumulative);
g) Plan and actual days;
h) Days ahead/behind;
i ) The operations for last 24 hours;
j ) NPT description and duration (daily and cumulative NPT);
k) Set casing/liner size, properties and set depth;
l ) Wellbore/directional survey for last 24 hours progress;
m) Drilling fluid properties;
n) Bottom-Hole Assembly (BHA) and drilling bit description;
o) Number of Personnel on Board (POB); and
p) HSE incidents
PPGUA/3.0/042/2013 19
VOLUME 8
DRILLING AND WELL
OPERATIONS
p) Cement density, composition, volume of cement used and their
estimated top in annulus;
q) Depth-days chart, actual cost vs proposed;
r ) Operational-time breakdown;
s ) Summary of HSE incident and scheduled waste;
t ) Summary of NPT;
u) Directional drilling results and wellbore trajectory; and
v ) Final estimated well cost
20 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 3: Drilling Quality Assurance/Quality Control
Contractor shall have quality plans and procedures in place to ensure all drilling
and completion services and goods provided are in accordance with contractual
requirements (between Contractor and third party contractors) and able to perform
as per the stated performance.
PPGUA/3.0/042/2013 21
VOLUME 8
DRILLING AND WELL
OPERATIONS
QA is a continuous improvement process. Contractor shall periodically
review their performance (for example, non-productive time & cost,
non-compliance reports, etc.) to gauge the effectiveness of Contractor,
drilling rig and third party contractor’s QA/QC system. The process shall
incorporate a quality database and lessons learnt. Contractor drilling
management shall be responsible to ensure effectiveness of Contractor’s
QA/QC system.
22 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 4: Drilling Unit Design, Manning and Logistics
Drilling units, support craft, base office and warehouses used by Contractor
shall be ready with adequate fit-for-purpose equipment, detailed procedures,
competent personnel and support services to ensure operation objectives are met and
carried out with adherence to HSE concerns and regulations. As and when
requested by PETRONAS, copies of approval or certificates from recognised body
shall be submitted to demonstrate equipment reliability and operation safety.
In the event that weather forecasts indicate conditions during which normal
drilling operations could not continue, Contractor shall take necessary
actions to interrupt drilling operations in time, so that the safety of the well
and drilling unit shall not be jeopardised.
4.1.1 Drilling Unit Inspection
After obtaining PETRONAS’ approval to award, Contractor shall be
responsible for conducting full drilling unit inspection by an industry
recognised third party at an opportune time prior to contract award.
The aim of this inspection is to gain accurate assessment of the state
of maintenance and working conditions of the equipment and
systems on the drilling unit in accordance with the drilling unit’s
contractual requirements. The objectives are to limit downtime and
improve reliability and safety. All critical actions from the inspection
shall be duly closed out prior to spudding of the first well. The
inspection report shall be made available upon request by
PETRONAS.
PPGUA/3.0/042/2013 23
VOLUME 8
DRILLING AND WELL
OPERATIONS
areas and their associated equipment;
b) arrangements of mud tanks, high and low pressure mud and
cement slurry systems and bulk transfer system;
c) arrangement of all surface and subsea well control systems
including arrangement of choke manifold, testing and flaring
systems;
d) arrangement of other pressure systems; and
e) position and type of all life-saving appliances, fire extinguishing
and protection systems, fire stations and appliances,
navigational safety appliances and alarm systems
A red aircraft warning light of at least fifty (50) candelas shall be mounted
at the top of the derrick so as to be visible from all directions.
Drilling units and support craft shall have navigational safety and marine aids
which shall meet as a minimum, the requirements of the classification
bureau; and for aircraft, the civil aviation regulatory authority.
24 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
4.4.2 Derrick Escape
When a person is required to work in the derrick as part of normal
drilling operations, an escape device acceptable by general industry
practices shall be provided from the working platform in the derrick.
Persons required to work on the derrick or at a height of 2 metres or
higher, shall wear safety belts complete with tail rope having
adequate length and strength. Contractor shall ensure that such
safety belts are provided at all times on the derrick.
PPGUA/3.0/042/2013 25
VOLUME 8
DRILLING AND WELL
OPERATIONS
b) Have readily accessible:
• at least two (2) proximity firefighting suits;
• four (4) self-contained portable breathing devices; and
• a suitable water supply source of sufficient capacity to
assure adequate water supply
26 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
a) of adequate size and structural strength to accommodate the sizes and
types of helicopters to be used;
b) located so as to provide an approach/departure sector of at least 180
degrees or higher free of obstruction;
c) equipped with operable lights commonly used on heliports;
d) equipped with a non-skid deck surface and safety nets around the
perimeter;
e) provided with access gangways;
f ) provided with a coaming which shall contain any fuel spill from a leak in
the helicopter fuel tanks if such tanks are installed above decks and with
a drainage system which shall conduct such a spill away from the drilling
unit; and
g) equipped with a helicopter crash box located at the access to the
helicopter deck
PPGUA/3.0/042/2013 27
VOLUME 8
DRILLING AND WELL
OPERATIONS
4.10.2 Lighting
Adequate lighting shall be provided in all working areas inside and
outside of the drilling rig and emergency lighting shall be provided
for the proper illumination of vital areas such as control stations, well
control equipment, stairways, exits, machinery areas, emergency
generator area; and in the case of an offshore drilling unit; boat
stations, passage ways and navigation control area.
4.10.3 Emergency Electrical Power Supply
An independent emergency electrical power supply system capable
of supplying sufficient power in the event of failure in the primary
power supply shall be available to the drilling rig:
a) to secure well; and
b) for the operation of warning, lighting (in areas identified in
Section 4.10.2), alarm, communication and fire extinguishing
systems
4.11.2 Ventilation
Enclosed areas in the vicinity of the BOP stack and mud tanks and all
enclosed working and living areas on the drilling base or drilling unit
shall be properly ventilated and pressurized.
28 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
4.11.3 Engines and Motors
Engines, generators and motors located within any area as
designated in Section 4.11.1 shall have their air intakes located in a
non-hazardous area or the intakes shall be equipped with device to
automatically or manually shutdown the diesel engine in the event of
run away.
All fans and blowers located inside rooms containing engines,
boilers, mud pumps or mud tanks and all fans used for ventilating
such rooms shall be equipped with remote shut-off switches. Air
intakes and exhausts for machinery spaces shall be capable of being
closed.
4.11.4 Exhaust Pipes
Exhaust pipes from internal combustion engines and gas turbine
plants shall be provided with proper flame and/or spark arrestors and
shall be equipped with water cooled exhaust manifold or be insulated
to prevent ignition of combustible gases and be safely vented to the
atmosphere in a non-hazardous area.
4.13 Diving
An offshore drilling unit if required shall be equipped with diving apparatus
suitable for the working depths, whenever it is anticipated that the drilling
operations shall require assistance by divers based on the rig and in
accordance with Volume 3: Health, Safety & Environment.
4.15 Manning
Contractor shall require that a crew of sufficient number as determined by
general industry manning levels and with adequate training is available for
the operation of all equipment prior to activation of that equipment and that
all crew members have or are receiving training relevant to their duties.
PPGUA/3.0/042/2013 29
VOLUME 8
DRILLING AND WELL
OPERATIONS
4.16 Support Craft
Service, supply and survey craft participating in a drilling programme,
including vehicles, aircraft, standby craft and vessels, shall be designed and
constructed to operate safely and to provide safe and efficient support for all
drilling and related operations for which the craft are engaged, and
Contractor shall, upon request, demonstrate to the satisfaction of
PETRONAS, that support crafts are capable of safely operating in the
environmental conditions prevailing in the area of drilling operations.
(Contractor shall make reference to its own internal guideline with respect to
the technical specification).
30 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 5: Well Design and Drilling Operations
Wells shall be designed to ensure the well and/or development objectives are met;
safely and cost effectively. Casing, primary cementing and drilling fluid programmes
shall be engineered to withstand anticipated stresses and should compensate
prediction uncertainties. Drilling operations shall be carried out to ensure the
well objectives are met with As Low As Reasonably Practicable (ALARP) risk and
project/well costs containment. Contractor shall ensure that good oil field drilling
practices and continuous improvement are implemented in well design/planning
and throughout the drilling operations. Process shall be in place to manage
deviations or changes with adequate review, risk assessment and Contractor’s
authority’s approval. All wells drilled under the provisions of these procedures
shall have been included in the original WPB or its subsequent revision.
PPGUA/3.0/042/2013 31
VOLUME 8
DRILLING AND WELL
OPERATIONS
When the drilling unit is bottom-supported, the unit shall not be
raised or lowered, if weather or sea conditions exceed those allowed
in the drilling unit’s Marine Operations Manual to prevent undue risk
to the safety of the personnel, operations and drilling unit.
32 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
5.2.1 Drive Pipe
This casing shall be set in a competent bed, with the objective of
supporting unconsolidated formation and obtaining drilling fluid
returns to surface. Normally driven to refusal or set at depth
sufficient for its objective.
PPGUA/3.0/042/2013 33
VOLUME 8
DRILLING AND WELL
OPERATIONS
For deepwater operations, conductor casing may be eliminated if
geological factors, shallow hazards, and well structural integrity are
maintained.
34 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
A calculated volume of cement sufficient to fill the annular space at
least 150 metres above the uppermost hydrocarbon zone or
one-third of production casing length, whichever is greater, shall be
used. When a liner is used as production string, it shall be lapped a
minimum of 30 metres into the previous casing string, and the seal
between the liner top and the next larger string shall be tested.
PPGUA/3.0/042/2013 35
VOLUME 8
DRILLING AND WELL
OPERATIONS
Prior to any operations that put a well in an underbalanced mode or
removal of hydrostatic barrier (such as switching to lighter fluid), a
negative pressure or inflow test at a pressure below the lowest
planned hydrostatic pressure shall be performed on casing and/or
liner exposed to negative pressure and also mechanical barriers such
as formation isolation valves, retrievable packers/plugs, etc.
Contractor shall provide test procedures and criteria for a successful
test in the NOOP or at an appropriate time prior to conducting the
test.
5.2.8 Cementation
Cement and materials for well cementing shall conform to latest API
Specification 10A. Well cement test shall conform to API RP10B-2/
ISO 10426-2 and deepwater well cement test shall conform to API
RP 10B-3/ISO 10426-3.
The cementation of surface casing, intermediate casing, production
casing and liner shall be performed by conventional displacement
method. In addition to cement slurry, preflush and spacer design,
pipe centralisation to achieve optimum standoff and pipe movement
shall be considered to improve drilling fluid removal and cement
placement quality. A cement placement, centralizer placement,
Equivalent Circulating Density (ECD), fluid displacement and
applicable stress-analysis engineering software simulation shall be
performed to support cementing design. Cementation design
reports, post-job data and cement bond evaluation log result if any
for all individual casing primary cementing operations shall be
submitted to PETRONAS upon request.
Other industry acceptable methods may be used such as inner string
cementing or simply cementing without the use of wiper plugs where
deemed appropriate without compromising primary cementation
quality.
36 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
(U-tubing) of cement during cementing shall be incorporated into a
casing string with thread locking compound. For conventional
displacement method, a float collar shall be inserted in the casing
string above one or two joints of casing above a float shoe. The float
equipment performance criteria shall correspond to the anticipated
service requirements per latest API RP 10F.
PPGUA/3.0/042/2013 37
VOLUME 8
DRILLING AND WELL
OPERATIONS
metres during the normal course of drilling, i.e. tangent sections. Two
successive directional survey readings shall not exceed 30 metres in
all planned angle and/or directional change portions of the hole.
Anti-collision shall be taken into consideration. PETRONAS may
require Contractor to submit the anti-collision report upon request.
Copies of directional surveys report shall be submitted to PETRONAS.
The reports shall include but not limited to the tabulation of the
accumulative drift angles, direction, TVD, vertical section and the
rectangular coordinates of each shot point.
In calculating all surveys, a correction from true north to Universal
Transverse Mercator Grid North shall be made after making the
magnetic to true north correction.
38 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
are being conducted with crossovers if necessary; and
b) A safety valve and circulating head shall be available on the rig
floor, assembled with the proper connection to fit the casing
that is being run in the hole at the time
a) A set of pipe rams to fit the smaller string of drill pipe installed in
PPGUA/3.0/042/2013 39
VOLUME 8
DRILLING AND WELL
OPERATIONS
the existing BOP stack; or
b) Variable bore rams may be fitted in place of one or both sets of
pipe rams; or
c) An additional set of BOP equipped with a set of pipe rams to fit
the smaller string of drill pipe
40 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
a) Autoshear
b) Deadman
c) Emergency Disconnect system (EDS)
Autoshear, deadman and EDS are optional for moored drilling units.
Floating drilling units operating with Surface BOP (SBOP) system with
drilling riser designed to contain wellbore pressure shall be equipped
with a Seabed Isolation Device (SID).
Prior to the removal of marine riser, the riser shall be displaced with
sea water after successful negative test. Contractor shall ensure that
sufficient hydrostatic head exists within the well bore to compensate
for the reduction in head and maintain a safe well condition, where
possible.
PPGUA/3.0/042/2013 41
VOLUME 8
DRILLING AND WELL
OPERATIONS
operations of hydraulic BOPs. The control panel shall
be fitted with alarms for low accumulator pressure as well as
for low level in the control fluid reservoir.
42 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
the hole, after stack is nippled up, once each trip but
not more than once each day (except for subsea BOP);
c) Tapered drill string pipe rams: Actuated weekly, and
after nippling up;
d) Annular-type preventer: Actuated on the drill pipe, in
connection with the pressure test, once each week;
e) Actuation of control station shall be alternating
between primary and remote BOP control stations;
f ) Subsea BOPs shall be actuated at least on weekly basis.
Shear rams shall be function tested prior to drilling out
each set casing; and
g) Auto shear, deadman and ROV intervention operating
systems shall be function tested during subsea BOP
stump test.
5.4.7 Inspection and Maintenance
BOP system shall undergo an assessment by an industry recognised
third party well control equipment and system authority when a
drilling unit initially comes under contract. All critical actions from the
assessment shall be closed out prior to drilling. Shearing capability of
shear rams shall be verified either by testing or review of previously
conducted test data. The report shall be made available upon request
by PETRONAS.
All BOP systems and marine risers and associated equipment shall be
inspected and maintained in accordance with the manufacturer’s
recommended maintenance procedures. Inspection of subsea
installations shall be accomplished by the use of ROV, rig camera or
divers. This requirement will be waived for a period not to exceed 4
days in the event of a ROV or rig camera breakdown.
All BOP tests, maintenance and inspection shall be recorded on the
Driller’s log.
PPGUA/3.0/042/2013 43
VOLUME 8
DRILLING AND WELL
OPERATIONS
personnel to achieve the acceptable response.
When the drilling fluid in the hole is circulated, the Driller’s log shall
be monitored. When coming out of the hole with the drill pipe, the
annulus shall be filled with drilling fluid to ensure sufficient over
balance (at least 0.3 ppg or 100 psi) whichever is less is maintained at
all time.
For operations where narrow margins prevent a 0.3 ppg or 100 psi
overbalance, other methods, such as pumping out of hole, reduced
tripping speeds and increased frequency of flow checks should be
employed to maintain well control.
A device for measuring the amount of drilling fluid to fill the hole
shall be used. If there is at any time an indication of swabbing or
influx of formation fluids, the necessary safety devices and action
shall be employed to control the well.
The drilling fluid in the hole shall be circulated or reverse circulated
prior to pulling drill-stem test tools from the hole.
44 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
b) The number of barrels and pump strokes required to fill the hole
for the designated number of stands of drill pipe and drill collars;
c) For each casing string, the maximum pressure that can be
contained under the BOPs before controlled bleeding off excess
pressure through the choke. Drill pipe pressure shall be
monitored when bleeding off pressure for well control; and
d) Where continuous fill trip tank equipment is used, only the
number of barrels required to fill the hole per stand of drill pipe
or drill collars and the maximum allowable casing pressure need
be posted
If any variant of MPD method is used for more precise control of well
annular pressure profile, Contractor shall ensure that MPD
procedures are in place as well as risk assessment/Hazard and
Operability (HAZOP) analysis and personnel familiarisation training
are completed. Contractor shall select the MPD method that best
addresses drilling problems cost effectively.
PPGUA/3.0/042/2013 45
VOLUME 8
DRILLING AND WELL
OPERATIONS
d) Gas-detecting equipment to monitor the drilling fluid returns
When the drilling fluid quantity required exceeds the storage capacity
of the drilling unit, the Contractor shall demonstrate that the
drilling fluid inventories on hand are sufficient to maintain well
control until additional quantities can be delivered to the well site.
46 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
5.7 Lost Circulation
During all normal drilling operations below the conductor, drilling shall cease
immediately whenever the drilling fluid pumped down the drill pipe is not
returning to the surface and drilling shall not be continued until adequate
circulation has been established.
In case of known areas or zones of loss circulation, it may be permissible to
drill ahead with continuing losses guided by operational and contingency
procedures. Contractor shall exercise prudent drilling practices to ensure
well integrity and safety of the operations.
PPGUA/3.0/042/2013 47
VOLUME 8
DRILLING AND WELL
OPERATIONS
safely. Conditions under which drilling shall be suspended in the case of a
drilling unit:
a) Inability to maintain primary well control;
b) Problems are experienced with critical BOP system component or
control system;
c) Failure of wellhead, casing or drilling fluid system;
d) Uncontrolled fire at the drilling site;
e) Failure of a significant portion of the primary power source;
f ) Inability to maintain adequate stability and buoyancy of the drilling unit;
g) Inability to satisfactorily maintain the position of the drilling unit over the
well;
h) Excessive motions of the drilling unit caused by sea-state or weather
conditions;
i ) While diving operations are being conducted at or near any part of the
subsea drilling system
For drilling operations with a bottom supported drilling unit and/or drilling
from a fixed structure where presence of shallow hazards or hydrocarbons
are possible, a small diameter initial pilot hole of 8-1/2 inch or smaller size
from the bottom of the conductor casing to the proposed surface casing
seat shall be drilled and logged to aid in determining the presence or
absence of these hazards.
For drilling operations with floating drilling unit (not from a fixed structure),
systems and procedures shall be in place to continuously monitor the
operation for indications of a shallow hazard, and to ensure the safe and
swift move of the drilling unit to a position that is sufficiently remote from
the area of possible hazard or disturbance caused by any uncontrolled flow
of formation fluids.
48 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
5.11 Underbalanced Drilling
Underbalanced drilling is defined as deliberately drilling where the pore
pressure of the formation being drilled is greater than the hydrostatic
pressure exerted by column of drilling fluid and formation fluids are allowed
to flow into wellbore. In this respect, balanced pressure drilling is a
subcategory of underbalanced drilling because the annular pressure is
expected to fall below the formation pressure during pipe movement. In
general, underbalanced drilling is aimed at improving drilling rate, limiting
lost circulation and protecting reservoir formation.
Underbalanced drilling shall be conducted only when the requirements
below are satisfied and subject to further discussion and approval by
PETRONAS prior to execution:
a) Assessment of risk and benefit of underbalanced drilling (economic and
technical justification to change from conventional drilling);
b) Assessment of fluid type to be used (gas, mist, foam, gasified liquid
and liquid);
c) Identification and assessment of equipment to be used that covers both
surface and sub-surface (gas compression, gas generation, separation,
foam, pressure control, downhole tools, BOP stack, rotating head, etc.);
d) Preparation of detailed underbalanced design programme (fluid design,
expected Rate of Penetration (ROP), wellbore model, fluid velocity,
cutting transport, cost analysis, etc.) and contingency plans; and
e) Environmental and safety concerns associated with underbalanced
drilling shall be addressed and documented. A primary consideration of
environmental protection shall include handling of returning fluid from
wellbore.
PPGUA/3.0/042/2013 49
VOLUME 8
DRILLING AND WELL
OPERATIONS
a continuous eight hours exposure of personnel is 10 parts per
million (ppm) in air, which is 0.001% by volume.
50 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
5.12.6 Personnel Training
All personnel shall be informed as to the hazards of H2S. They shall
be trained in the use of H2S safety equipment, informed of H2S
detectors and alarms, ventilation equipment, prevailing winds,
briefing areas, warning systems and evacuation procedures.
All crew members shall be familiar with basic first-aid procedure
applicable to victims of H2S exposure. Emphasis shall be placed
upon rescue and first aid for H2S victims.
PPGUA/3.0/042/2013 51
VOLUME 8
DRILLING AND WELL
OPERATIONS
failure due to SSC.
52 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
encountered, the BOP shall be closed while maintaining
drilling fluid circulation through the choke line to the
mud-gas separator. The mud-gas separator shall be
connected into the flare system. The degasser shall be used
until the drilling fluid is free of entrained gas.
5.12.9.3 Coring
When coming out of the hole with a core barrel under
suspected H2S condition, the drilling crew shall wear
breathing mask before pulling the last twenty stands or at
any time H2S is detected at surface. “Mask on” shall
continue while opening the core barrel and examining the
cores. Cores to be transported shall be sealed and marked
for the presence of H2S.
5.12.9.4 Drilling Fluid
Suitable water or oil base drilling fluid should be used in
drilling formations containing H2S gas. A pH of 10.0
and above shall be maintained in a water base mud to
control corrosion and prevent SSC. Consideration shall also
be given the use of H2S scavengers in both water and oil
base drilling fluid systems. Sufficient quantities of additives
shall be maintained at well site for addition to neutralise H2S
picked up by the drilling fluid system. Drilling fluid
containing H2S shall be degassed and the gases removed
shall be burned with the flare system and shall be
continuously monitored for H2S concentration.
5.12.10 Well Testing Operations
During well test, the level of H2S concentration shall be
monitored at first hydrocarbon to surface and at regular
intervals subsequent to first hydrocarbon. All produced
gases shall be burned with the flare system if the gases are
flammable.
All well test equipment, well head equipment and tubular
goods shall meet the H2S service requirement. Drill pipe
shall not be used for testing well with H2S. The water
cushion shall be inhibited in order to prevent H2S corrosion.
The test equipment shall be flushed with treated fluid for the
same purpose at the end of the test.
PPGUA/3.0/042/2013 53
VOLUME 8
DRILLING AND WELL
OPERATIONS
5.13 HPHT Drilling Operations
Wells having an undisturbed bottom hole temperature (BHT) greater than
300 °F (149 °C) and maximum pore pressure exceeding 0.8 psi/ft or requiring
pressure control equipment with a rated working pressure in excess of
10,000 psi shall adhere to the following procedures. Contractor should
consider the following procedures for high pressure (HP) wells.
54 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
necessary data needed to engineer and plan the potential HPHT
development wells.
PPGUA/3.0/042/2013 55
VOLUME 8
DRILLING AND WELL
OPERATIONS
5.13.5 Drilling Unit and Equipment
Drilling units proposed for HPHT operations shall be audited for
HPHT technical fitness for purpose and readiness by an industry
recognised third party authority in HPHT drilling rig auditing. All
critical actions from the audit shall be duly closed out prior to drilling
any HPHT hole sections. The report shall be made available upon
request by PETRONAS.
56 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 6: Formation Evaluation
Contractor shall obtain sufficient well data and samples during operation to permit
geological and reservoir evaluation of the well and to achieve all well objectives
while ensuring operation safety and wellbore integrity. The applicable formation
evaluation data and reports shall be made available to PETRONAS in a proper and
timely manner.
6.2 Coring
Proposals for coring shall be indicated in the NOOP to include but not
limited to the depth interval of coring, objectives and reservoirs to be cored.
PPGUA/3.0/042/2013 57
VOLUME 8
DRILLING AND WELL
OPERATIONS
durably labelled with the name of the well and the depth of the core.
58 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 7: Completion Operations
PPGUA/3.0/042/2013 59
VOLUME 8
DRILLING AND WELL
OPERATIONS
and connections that are internally coated shall be suitable for the
temperature and well fluid characteristic.
7.4 Subsurface Safety Valve
All tubing installations open to a hydrocarbon bearing zone shall be
equipped with a Surface Controlled Subsurface Safety Valve (SCSSV) located
at least 30 metres below the sea floor. An injection valve capable of
preventing backflow may be installed in lieu of a SCSSV in an injection well
with PETRONAS’ approval. Such valve shall be located at least 30 metres
below the sea floor. Any other method/replacement of subsurface safety
valve (SSSV) requires PETRONAS’ approval.
The prime purpose of the SSSV is to protect people, property and the
environment against uncontrolled production while safeguarding the
hydrocarbon resource asset.
A risk analysis shall be conducted to address all the possible failure modes,
their likelihood of occurring and identify mitigation steps to reduce the
likelihood and/or limit the consequences.
7.4.1 Installation
All tubing installation in wells shall be equipped with a functioning
SCSSV.
Notwithstanding the above, during emergency, alternative safety
devices (for example, subsurface control devices) may be
temporarily installed without prior consent of PETRONAS. PETRONAS
shall be notified of the situation and circumstances.
7.4.2 Valve Specifications
Contractor shall use subsurface safety devices that comply with the
minimum standards set forth in the latest API Specification for
60 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
quality assurance including design, material and functional test
requirements and for verification of independent party’s performance
testing and manufacturer’s functional testing of such valves.
7.4.3 Reinstalling, Testing and Maintenance
Contractor shall install, test and maintain the SSSV systems based on
their operating and inspection maintenance philosophy.
7.4.4 Tubing and Plug Testing
A shut-in well equipped with a tubing plug or other device shall be
inspected for leakage of not less than once in six (6) months. If leakage
is detected, the plug shall be removed, repaired and reinstalled, or an
additional tubing plug may be installed in lieu of removal and repair.
7.4.5 Additional Protective Equipment
All tubing installations in which a wireline or pumpdown retrievable
subsurface safety device is to be installed shall be equipped with
a landing nipple which comes with flow couplings or other protective
equipment above the landing nipple to provide for sitting of the
subsurface safety devices.
7.4.6 Records
Contractor shall maintain records which include design
PPGUA/3.0/042/2013 61
VOLUME 8
DRILLING AND WELL
OPERATIONS
specifications, verification of assembly and setting depth, removal
date, reason for removal, reinstallation date and all mechanical
failures or malfunctions with notations as to the cause. Such records
shall be made available upon request by PETRONAS.
62 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
7.7 Landing Nipples
Tubing hanger(s) shall be equipped with landing nipples or plug bushings to
receive pump-through tubing plugs or back pressure valves.
Requirements for landing nipples shall be considered at completion design
stage. Contractor shall ensure that the landing nipples are properly chosen
considering flow path area, pressure rating, etc.
PPGUA/3.0/042/2013 63
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 8: Barriers and Well Integrity
There shall be one well barrier in place during all well activities and operations,
including suspended or abandoned wells, to prevent uncontrolled cross flow
in the wellbore between formation zones.
64 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
means in a wellbore. Plugs, bridge plugs, cement retainer and packers
are acceptable as permanent barriers if used with cement. When
cement is used as a barrier during well construction together with
mechanical barriers, then the mechanical barriers are
complementary to a properly executed cementing operation.
PPGUA/3.0/042/2013 65
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 9: Plug and Abandonment of Wells
Contractor shall adhere to or exceed the minimum plug and abandonment (P&A)
requirements provided to ensure full and adequate isolation of formation fluids both
within the wellbore and from surface or seabed. Plugs shall be verified to ensure
correct depth placement with the required sealing capability. Well P&A programme
and suspension plans shall be submitted to PETRONAS for approval in a timely
manner.
66 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
reservoirs and estimated pressures; and
• Cement bond evaluation log result, if recorded
PETRONAS may request additional requirements where it deems necessary
or to enhance benefits.
PPGUA/3.0/042/2013 67
VOLUME 8
DRILLING AND WELL
OPERATIONS
through the perforations to cement the annulus between the fish and
the hole to isolate any open sands that are present. If any
hydrocarbon bearing sands are exposed below the fish, Contractor
shall consider taking remedial action to prevent cross flow between
them. Where this is not possible, a cement plug shall be positioned
that extends at least 30 metres above the fish to isolate the fish from
the open hole above the fish. The plug shall be tested in accordance
with Section 9.6.
In the event that any of the above fish carries a radioactive source,
Atomic Energy Licensing Board (AELB) under the Ministry of Science,
Technology and Innovation (MOSTI) approval shall be sought before
any decision is made to abandon the well and/or bore. A copy of
AELB approval letter shall be provided to PETRONAS when
requesting for approval to abandon. Where there is possible risk of
subsequent drilling into the source, coloured cement shall be used.
68 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
a) A cement retainer with effective back pressure control or a
permanent packer set not less than 15 metres and not more
than 30 metres above the top of the perforated interval with
a cement plug calculated to extend at least to the top of the
perforated interval and 15 metres above the retainer or packer.
The plug shall be tested in accordance with Section 9.6
b) A permanent bridge plug set not more than 45 metres
above the top of the perforated interval with 30 metres of
cement set on top of the plug. The plug shall be tested in
accordance with Section 9.6
PPGUA/3.0/042/2013 69
VOLUME 8
DRILLING AND WELL
OPERATIONS
plugged in accordance with Section 9.4.4.1.
a) Plug entirely in open hole shall be verified with weight test (unless
bottom supported by the well or a successfully tested plug);
b) Plug in cased hole shall be verified with both weight and pressure test; and
c) Plug (the first plug below surface plug) in deepwater wells where a
reduction of hydrostatic pressure will occur above the plug, shall be
verified by inflow test in addition to the above testing requirements
70 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
intervals between the plugs. In addition to the above, the hole shall be
circulated so that the drilling fluid is gas-free and of uniform fluid weight.
In all cases, wellhead valve assembly tree or wellhead cap or BOP shall be
employed to give pumping access to the well.
PPGUA/3.0/042/2013 71
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 10: Workover and Well Intervention Operations
Workover operations conducted on wells after initial completion for the purpose
of maintenance, restoration or increasing the productivity shall be conducted in a
safe and efficient manner. Workover programme or Notice of Workover Operations
(NOWOP) shall be prepared by Contractor and submitted to PETRONAS for approval
in a timely manner. Reporting and report contents requirement shall adhere to the
procedures in this section.
All activities shall be done under two verified barriers. Contractor shall have a
system in place to assure that personnel involved in these activities have
acquired necessary competencies to perform the jobs. All equipment shall
meet related industry recognised standards. All work shall be done under
approved written work programme. Where a contingency plan requires well
intervention activities, Contractor shall have procedures readily approved and
all required equipment and personnel prepared.
72 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Further discussion is required for any types of operation and/or
method that are not covered in this document and subject to approval
from PETRONAS.
10.1.2 Workover
Workover is a remedial operation conducted with equipment and
support facilities that includes requirement for workover rig over
well bore.
Further discussion is required for any types of operation and/or
method that are not covered in this document and subject to approval
from PETRONAS.
10.1.3 Operations
Workover and testing operations whereby rig assistance is required
shall not be undertaken, nor operations other than emergency well
control be conducted unless rig crews and supporting service units
are properly manned and supervised.
PPGUA/3.0/042/2013 73
VOLUME 8
DRILLING AND WELL
OPERATIONS
wellhead equipment or to the maximum anticipated well or pumping
pressure, whichever is less.
A lubricator assembly with the necessary shut-off valves, bleed
valves and pump connections to permit the safe installation and
removal of the pumpdown tools shall be connected to the flowlines
downstream of the pump manifold. Any polluting fluids bled from the
lubricator shall be properly contained.
Appropriate first aid kits, safety shower and eye washer shall be
available.
74 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
directions, the position of the platform and vessels presence in the vicinity.
PPGUA/3.0/042/2013 75
VOLUME 8
DRILLING AND WELL
OPERATIONS
10.4.2 Workover Reports and Data Retention
All activities performed at the well site shall be recorded consistently
in both reporting format and level of detail. The reporting
requirements described below are aimed at capturing records of
activities done, problems encountered, lessons learnt in order to
facilitate performance improvement and knowledge management:
All reports shall be retained for future reference and made available
to PETRONAS upon request.
76 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
d) Results of well test, before and after workover;
e) Detailed estimate against actual expenditure;
f ) Summary of workover operations and time break down;
g) Zonal isolation intervals and pumped cement volume; and
h) Lessons learnt and improvement initiative
MONTH OF …………………………………
Coiled Tubing Well Name Well Name Well Name Well Name
Job Description Job Description Job Description Job Description
Plan Cost Plan Cost Plan Cost Plan Cost
Plan Duration Plan Duration Plan Duration Plan Duration
Expected Gain Expected Gain Expected Gain Expected Gain
Electric Line Well Name Well Name Well Name Well Name
Job Description Job Description Job Description Job Description
Plan Cost Plan Cost Plan Cost Plan Cost
Plan Duration Plan Duration Plan Duration Plan Duration
Expected Gain Expected Gain Expected Gain Expected Gain
PPGUA/3.0/042/2013 77
VOLUME 8
DRILLING AND WELL
OPERATIONS
a) Well number;
b) Summary of operations for the last 24 hours including HSE report;
c) NPT-Hour (daily and cumulative NPT);
d) Look ahead plan and major concerns (if any); and
e) Fish or well problem encountered or left behind
However, prior to removing the wellhead valve assembly, well control shall
be maintained by well control fluids and by a downhole sealed off pressure
tested annulus and tubing. In this condition, wellhead repair may be carried
out involving removal of the wellhead valve assembly and tubing-casing
annulus pack-off.
78 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
10.8.2 Well Intervention Pressure Control Equipment
a) Stuffing box;
b) Lubricator with bleed off valve; and
c) Single or Dual rams BOP (if necessary)
PPGUA/3.0/042/2013 79
VOLUME 8
DRILLING AND WELL
OPERATIONS
b) 2 sets of stripper type pipe-rams BOPs, hydraulically
operated with spacer spool;
c) A pipe stripper assembly; and
d) Hydraulically operated, or in exceptional cases,
mechanically operated snubber slip and seal assembly;
if the surface pressure is above 5000 psi, hydraulically
operated blind rams shall be used
80 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
10.8.5 Well Control
Prior to pulling the production tubing from the well, tubing strings
and casing annulus shall be circulated with well control fluids. The
hole shall be filled by accurately measured volumes of well control
fluids; wells which will not maintain a full column of fluid shall
maintain the maximum fluid level. Fill-up operations shall be
monitored by use of a mechanical, volumetric or electronic device
during all trips in and out of the hole.
A back pressure valve or wireline type plug, shall be installed and
function tested if possible in each tubing string before removing BOP
or wellhead valve assembly. The work shall be organised to minimise
the time between the removal of the wellhead valve assembly and
the installation of the BOP.
The well shall be continuously monitored during workover or
completion operations and shall not be left unattended at any time
unless shut-in with assurance of complete well control.
10.8.6 Pressure and Function Test
10.8.6.1 Pressure Test
Each component of the BOP stack assembly and related
control equipment shall be individually tested in accordance
with Section 5.4.6.2.
10.8.6.3 Lubricators
Lubricator assemblies shall be pressure tested each time
they are installed to the maximum anticipated wellhead
pressure and at least annually to their rated working
pressure. The test date and test pressure of the former shall
be recorded on the daily log, and that of the latter shall be
indicated by a metal tag or band.
PPGUA/3.0/042/2013 81
VOLUME 8
DRILLING AND WELL
OPERATIONS
10.10 Wireline Operations
10.10.1 General Requirements
For the purpose of these requirements wireline operations include all
cased hole or open hole operations, utilising either a solid or
stranded line.
The wireline packoff shall be monitored and maintained during
wireline operations and the elements shall be replaced, when
necessary, to assure a proper seal under pressure conditions.
Operations under pressure conditions shall not allow fluids to flow
through the wireline packoff, other than minor leakage necessary to
permit free movement of the wireline. Minor leakage from packoff
assemblies shall be properly contained and disposed of.
Before commencing the wireline work, all equipment shall be
checked for compliance with all applicable safety standards,
including the use of explosion proof motors on all power equipment.
When operations are temporarily suspended, the well shall be
monitored or completely shut-in until operations resume. Wireline or
conductor line operations during hours of darkness shall only be
performed in the presence of a proper lighting.
10.10.2 Operations in Cased Hole
When perforating or logging in a cased hole without the wellhead
valve assembly installed and where communication exists from the
wellbore to the formation, well control shall be maintained by well
control fluid and the BOP. The well shall be monitored continuously
on the trip tank.
When logging in a cased hole without the wellhead valve assembly
installed, where no communication exists from the wellbore to the
formation, well control shall be maintained by the BOP or well
control fluids.
When running and perforating with tubing conveyed guns, well
control shall be maintained by well control fluids and the BOPs. If
the perforation assembly includes a packer above the guns, it is
permitted to displace the workstring to underbalanced fluids to
enable perforation under drawdown conditions.
82 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
10.10.3 Operations in Open Hole
Open hole operations such as induction-electrical, density and
acoustic logging that are performed without the wellhead valve
assembly installed shall maintained well control by the use of well
control fluids and BOP.
A lubricator assembly/or shooting nipple assembly shall also be used
if necessary in order to safely run and retrieve wireline tools.
All personnel not directly associated with the operations which utilise
explosive devices or hazardous radioactive materials shall vacate
the rig floor and substructure prior to device arming, entry and
retrieval from the wellbore. Competent personnel shall verify that all
explosive device systems, wireline units and BOPs are grounded to
the basic rig structure and that no unsafe electric potential exists (for
example, electric welding, exposed rig wiring near the cable etc.).
Contractor shall ensure that safe operating procedures and test are
used when handling any explosive devices.
All primary charges and secondary charges shall be stored and
transported exclusively in separated metal containers, marked with
internationally recognised explosives signs. This also applies to
defective detonators which have been removed from a misfired gun.
Transfer of loaded gun without detonators is only allowed if properly
identified and manifested with detonators stored in separate metal
containers.
Radio silence shall be observed just prior to arming any explosive
device and at all times while the device is at the surface or less than
60 metres down the hole. The observation of radio silence shall be
observed depending on the type of explosives and tools used.
Electrical welding machines and top drive system shall be isolated.
The impressed current cathodic protection equipment shall be
switched off on offshore platforms prior to arming any explosive
device and at all times, while the device is at the surface or less than
60 metres down the hole.
10.10.4 Swabbing Operations
The swabbing of wells shall be performed with a lubricator
assembly whether carried out with a small slickline or large braded
line. Flow rates shall be controlled by the use of choke restrictions in
the flowline. Swabbing of tubing strings capable of flowing
PPGUA/3.0/042/2013 83
VOLUME 8
DRILLING AND WELL
OPERATIONS
hydrocarbons shall not be performed during hours of darkness
unless approved by PETRONAS.
10.11 Rigging Up or Down of Workover or Completion Equipment
The movement of workover or completion rigs and related equipment on
and off an offshore facility, rigging up and rigging down, shall be conducted
during daylight hours only unless adequate lighting is provided. Those
wellheads, flowlines, production and other equipment which could be
damaged by heavy lifting operations shall be shut-in and bled down or
otherwise protected (well with tubing/casing annulus pressure which cannot
be bled down shall be killed) prior to commencing heavy lift.
SCSSV shall be closed or a tubing plug or back pressure valve shall be
installed and tested if possible in each tubing string of wells that are exposed
to possible damage in moving operations.
84 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 11: Onshore Drilling Operations
Contractor shall comply with the relevant regulations prior to constructing the well
location. This includes but not limited to license and permits, risk assessment,
protection of the environment and safety, culture and religious traditions in the area
of operations, Emergency Response Plan (ERP) and restoration of the well location
as per original condition.
PPGUA/3.0/042/2013 85
VOLUME 8
DRILLING AND WELL
OPERATIONS
a) Effects on the habitat of animals as a result of a change in the
natural drainage, surface water levels, aquifers;
b) Effects on fauna and potential hazards to the local population,
caused by excavations, filling, erosion, drainage and motorised
traffic;
c) Effects of increased accessibility for people by opening up tracks
into previously inaccessible areas;
d) Finding routes which are less utilised and therefore can be
opened again for traffic after completion of the operation
without causing resentment of interested communities; and
e) Direct impact by the survey team on the environment, including
minimising of vegetation cutting and controlling the survey crew
(for example, by preventing littering and poaching)
86 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
11.1.4 Campsite
The campsite should contain accommodation and personnel support
facilities such as bedrooms, kitchens, sanitary blocks, dining,
recreation, laundry rooms, power generation, radio room, etc.
The campsite shall be located at a safe distance from the rig. Prior
to determining the distance between the drill site and the campsite,
the following should be considered:
Any holes or tears in the liners shall be repaired. Life buoys shall be
provided in clearly visible and accessible positions around pits
containing water, liquid mud, etc. Rectangular roping shall be
provided around each such pit to assist egress from the pit. Ropes
shall be fixed, from corner to corner, around the perimeter and
kept taut at all times.
PPGUA/3.0/042/2013 87
VOLUME 8
DRILLING AND WELL
OPERATIONS
Upon completion of the drilling operations and once the liquids
contained within the water based mud cuttings pit have evaporated
and the pit has dried out, Contractor shall backfill over and around
the pit using locally obtained material and shall restore the area to its
original condition.
In any event, pits shall not be left open to the atmosphere (other than
while drying) and shall be left in such condition after remediation that
they shall not constitute a danger to the local population, domestic
animals or wildlife, etc.
Flare pit shall be located at least 50 metres away from the well, has
raised walls and excavated to contain any liquid that might be
bled-off without overflowing. Every effort shall be made to clear the
area around the flare pit to be free of grass, debris, logs and
flammable materials to reduce the hazards of fire. The flare pit on
cessation of operations shall be backfilled and compacted.
88 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
11.2 Environment Protection and HSE
PPGUA/3.0/042/2013 89
VOLUME 8
DRILLING AND WELL
OPERATIONS
disposed in a manner that shall not pollute any surface water or
underground source of potable water. Such liquids produced may be
stored in a properly lined earthen pit at the well site, provided that
such pit is excavated to a depth which shall contain all the waste fluid
and shall not collect natural run-off water.
Any drilling rig with a camp located within 50 metres of the well shall
be installed with an interconnected fire alarm system that is able of
sounding an alarm automatically and also indicate on a panel the
location of the fire.
11.2.5.1 Smoking
Smoking shall be permitted only within safe and designated
areas. Contractor shall ensure that proper signs and notices
prohibiting smoking are posted at all designated no smoking
areas at a drill site.
90 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
11.2.5.3 Engines Intake
Any fixed internal combustion engine that is located within
25 metres of a drilling well onshore shall be equipped with:
a) Air intake shut-off valve that can be activated by a
remote control device that is easily accessible from the
Driller’s location; and
b) A system of injecting inert gas into the cylinders or an
air duct that conveys air to the engine from a source
that is located 25 metres from the well
PPGUA/3.0/042/2013 91
VOLUME 8
DRILLING AND WELL
OPERATIONS
11.3.4 Casing Programme
Supplementary to the casing and cementing requirements in the
foregoing Section 5.2 and in lieu of drive pipe and/or conductor
casing, the casing to be installed in an onshore well is:
a) All casing shall be cut at least 1 metre below the natural ground level
with a minimum of 10 metres of cement plug placed in the innermost
casing; and
b) A steel plate of at least 7 millimetres thick shall be welded over the top of
the largest casing in a manner that completely closes the well bore and
the annulus between all strings of casing exposed at the cut point
92 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 12: Onshore Completion, Workover and Intervention Operations
Contractor shall design completion for onshore wells to withstand all expected loads
throughout different phases of well life. Completion operations shall be executed
in a safe and efficient manner. Well completion shall be done under an approved
written work programme only and all well completion activities shall be recorded
and made available to PETRONAS.
12.1 General
Supplementary to the foregoing Section 7 and Section 10, Contractor shall
comply with the following procedures in conducting onshore completion
and workover activities.
PPGUA/3.0/042/2013 93
VOLUME 8
DRILLING AND WELL
OPERATIONS
For any waste/hazardous material generated during operations shall be
disposed in accordance to Section 13 Waste Material Handling and Disposal
with reference to Volume 3, Section 1: Health, Safety and Environment.
When a well located near to the normal high water mark of a body of water
or a stream or a river is in such a situation that the oil spill or leak may reach
the water, Contractor shall ensure that when a well is not on pump, the
wellhead valve assembly shall contain a SSV that shall automatically shut-off
an uncontrolled flow of oil from the well in the event of a wellhead failure
or leak. Such valve shall be the second valve from bottom to top
arrangement.
94 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Section 13: Waste Material Handling and Disposal
All waste materials from drilling and related operations shall be handled and
disposed in a manner that does not create a hazard to safety, health and
environment and is in compliance with the applicable Malaysian laws.
PPGUA/3.0/042/2013 95
VOLUME 8
DRILLING AND WELL
OPERATIONS
13.2 Disposal of Material
Wastes generated during drilling operations including used oil based mud
including synthetic oil based mud and chemical residues/wastes resulting
from drilling shall be managed in an environmentally safe and prudent
manner in accordance with statutory and acceptable industrial practices.
Wastes are not allowed to be discharged into the sea and shall be brought to
shore for further handling if they cannot be properly processed and disposed
at the rig site.
Storage and disposal of these wastes including information on waste
generated, stored, treated or disposed at the rig and wastes
transported to shore base shall be recorded, tracked and in compliance with
the requirements of the Environmental Quality (Scheduled Wastes)
Regulations, 2005 or its amendment.
Disposal of materials, wastes and equipment that are contaminated with
Technologically Enhanced Naturally Occurring Radioactive Material
(TENORM), shall comply with all applicable laws and regulations in Malaysia,
but not limited to the followings:
a) Atomic Energy Licensing Act, 1984;
b) Radiation Protection (Licensing) Regulations, 1986;
c) Radiation Protection (Basic Safety Standards) Regulations, 1988;
d) Radiation Protection (Transport) Regulations, 1989; and
e) LEM/TEK/30 SEM.2 , 1996- Guidelines on Radiological Monitoring for Oil
and Gas Facilities Operators Associated with TENORM
Any TENORM disposal proposal shall be submitted to the Malaysian AELB for
approval before license is applied and in general, a Radiological Impact
Assessment (RIA) study shall be performed first. Copy of RIA shall be made
available and submitted to PETRONAS for reference.
96 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
accordance to applicable Malaysian laws.
Cuttings drilled with low toxicity oil based mud and/or synthetic
based mud shall be properly washed and treated before disposing of
into the sea in accordance with the PETRONAS E&P Minimum
Environmental Specification (MES).
13.2.2 Solid Waste
Contractor shall not, unless licensed by Department of Environment
(DOE), burn or incinerate solid combustible waste on any premises
from such operation. All wastes, residues or ashes produced shall be
collected, recovered and transported back to shore for proper
disposal in accordance to the approval from the local authorities
or to a safe area designated for disposal in accordance to applicable
Malaysian laws.
Oil and gas produced while formation flow testing shall be properly
stored in suitable containers and either transferred to shore or flared
in a proper manner using an appropriate burner.
For offshore operations, waste engine lube oil, fuel oil, lubricants and
other fluid mixtures containing oil shall be collected in a closed drain
system labelled and transferred to shore for safe disposal or
recycling. If production facilities are available at the worksite, for
example when drilling in an existing field, arrangement with the
facility operator shall be sought to dispose of the fluid waste into the
effluent treatment sump.
PPGUA/3.0/042/2013 97
VOLUME 8
DRILLING AND WELL
OPERATIONS
Excess acids shall be collected and stored in suitable containers for
transportation to shore to be disposed of in a proper manner.
Surface discharge shall only be allowed with approval from local
authorities and pre-treatment for example, neutralisation is essential
prior to the disposal.
13.2.4 Sewage
Contractor shall not discharge or cause or permit the discharge of
any refuse, garbage into the Malaysian waters. Sanitary and galley
waste shall be disposed of in accordance with all applicable
Malaysian laws.
98 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
c) Well capping system technical specification;
d) Deployment strategies, containment system and logistical
support (aircraft, vessel, ROV and etc.); and
e) Personnel proficiency and preparedness
The BOCP for deepwater and HPHT wells shall include a plan for
suitably rated relief well which shall contain:
a) impermeable drains;
b) oil and mud traps;
c) waste pit;
d) holding basin (optional); and
e) septic tank and soak away
The waste pit should be located next to the shale shaker of the rig to
prevent double handling of the cuttings. They are sized to contain all
drilling cuttings and superfluous mud that will be produced during
the drilling operation. Waste water collected in a drain surrounding
the rig substructure, as well as waste water produced around mud
pumps, mixing tanks and chemical stores, shall also be discharged to
the mud and cuttings (waste) pits.
PPGUA/3.0/042/2013 99
VOLUME 8
DRILLING AND WELL
OPERATIONS
In tropical areas, with very high groundwater levels and high
precipitation, it is not always possible to contain all contaminated
liquids. In these conditions, excess water should be discharged into
the surroundings or into a holding basin for further retention or
treatment after passing a mud and oil retaining trap. The decision to
either discharge or to retain in a holding basin will depend on the
sensitivity of the environment.
100 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Abbreviations
TERM IN FULL
AELB Atomic Energy Licensing Board
AFE Authorisation for Expenditure
ALARP As Low As Reasonably Practicable
API American Petroleum Institute
BHA Bottom-Hole Assembly
BHT Bottom-Hole Temperature
BOCP Blowout Contingency Plan
BOP Blowout Preventer
BPV Back Pressure Valve
CIBHP Closed-In Bottom Hole Pressure
CITHP Closed-In Tubing Head Pressure
DDR Daily Drilling Report
DOE Department of Environment
DP Dynamic Positioning
DWR Daily Workover Report
ECD Equivalent Circulating Density
EDS Emergency Disconnect System
EIA Environmental Impact Assessment
ERP Emergency Response Plan
ESD Emergency Shutdown
FBHP Flowing Bottom Hole Pressure
FDCR Final Drilling and Completion Report
FDP Field Development Plan
FMEA Failure Mode and Effect Analysis
FTHP Flowing Tubing Head Pressure
FWR Final Workover Report
H2S Hydrogen Sulphide
HAZOP Hazard and Operability Analysis
HP High Pressure
HPHT High Pressure High Temperature
PPGUA/3.0/042/2013 101
VOLUME 8
DRILLING AND WELL
OPERATIONS
TERM IN FULL
HSE Health, Safety and Environment
IMCA International Marine Contractors Association
IMO International Maritime Organization
ISO International Organization for Standardization
LMRP Lower Marine Riser Package
MD Measured Depth
MEDEVAC Medical Evacuation
MES Minimum Environmental Specification
MOC Management Of Change
MOSTI Ministry of Science, Technology and Innovation
MPD Managed Pressure Drilling
MSDS Material Safety Data Sheet
NACE National Association of Corrosion Engineers
NOOP Notice of Operations
NOWOP Notice of Workover Operations
NPT Non-Productive Time
OEM Original Equipment Manufacturer
OOC Oil on Cuttings
P&A Plug and Abandonment
PETRONAS Petroliam Nasional Berhad
PGBOOM PETRONAS Guidelines for Barges Operating Offshore Malaysia
POB Personnel on Board
POM Petroleum Operations Management
ppm parts-per-million
PRD Petroleum Resource Development
PREX Petroleum Resource Exploration
PSC Production Sharing Contract
QA Quality Assurance
QC Quality Control
RIA Radiological Impact Assessment
102 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
TERM IN FULL
RM Ringgit Malaysia
ROP Rate of Penetration
ROV Remotely Operated Vehicle
RP Recommended Practices
RSC Risk Service Contract
SBOP Surface Blowout Preventer
SCP Sustained Casing Pressure
SCSSV Surface Controlled Subsurface Safety Valve
SID Seabed Isolation Device
SIPROD Simultaneous Production and Drilling Operations
SSC Sulphide Stress Cracking
SSSV Subsurface Safety Valve
SSV Surface Safety Valve
TD Total Depth
TENORM Technologically Enhanced Naturally Occurring Radioactive
Material
TVD True Vertical Depth
USD United States Dollar
WOC Wait-On-Cement
WIMS Well Integrity Management System
WPB Work Programme & Budget
PPGUA/3.0/042/2013 103
VOLUME 8
DRILLING AND WELL
OPERATIONS
Appendix 1
EXPLORATION STAGE
PLANNING EXECUTION
Note:
1. DDR – DAILY DRILLING REPORT
2. G&G – GEOLOGY AND GEOPHYSICS
3. NOOP – NOTICE OF OPERATIONS
4. FDCR – FINAL DRILLING AND COMPLETION REPORT
5. POM – PETROLEUM OPERATIONS MANAGEMENT
6. PREX – PETROLEUM RESOURCE EXPLORATION
7. P&A – PLUG & ABANDONMENT
*Please note that all approval request and information need to be submitted to PSC
Exploration Management group.
104 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
DEVELOPMENT STAGE
PLANNING EXECUTION
Note:
1. DDR – DAILY DRILLING REPORT
2. FDCR – FINAL DRILLING AND COMPLETION REPORT
3. FDP – FIELD DEVELOPMENT PLAN
4. G&G – GEOLOGY AND GEOPHYSICS
5. NOOP – NOTICE OF OPERATIONS
6. POM – PETROLEUM OPERATIONS MANAGEMENT
7. PRD – PETROLEUM RESOURCE DEVELOPMENT
8. P&A – PLUG & ABANDONMENT
*Please note that producing oil fields (revisit, infill, etc.) are under the Petroleum
Operations Management (POM) Department while oil & gas fields are under
Petroleum Resource Development (PRD) Department.
PPGUA/3.0/042/2013 105
VOLUME 8
DRILLING AND WELL
OPERATIONS
Note:
1. DDR – DAILY DRILLING REPORT
2. G&G – GEOLOGIST AND GEOPHYSIST
3. NOOP – NOTICE OF OPERATION
4. P&A – PLUG & ABANDON
5. POM – PETROLEUM OPERATIONS MANAGEMENT
6. PRD – PETROLEUM RESOURCE DEVELOPMENT
7. PREX – PETROLEUM RESOURCE EXPLORATION
106 PPGUA/3.0/042/2013
VOLUME 8
DRILLING AND WELL
OPERATIONS
Acknowledgements
NAME COMPANY
Malik Faisal Abdullah PMU (Team Leader)
Adrian Chesters KPOC
Adrin Shafil Ahmad Nasir BHPB
Alistair Gauld Newfield
Astyo Budi Ardi PMU
Benjamin Choo Murphy
Christian Baranthol TOTAL
Daniel Miessner PCSB
Fauzi Abbas Hess
George Jarvis EMEPMI
Gregoire Chabrol TOTAL
Ivan Tan Boon Kiat Shell
Jim Kelly Petrofac
Keith Stewart Talisman
Khairul Annuar Nordin PMU
M Zaidan Khalid PCSB
Neil Armstrong EMEPMI
Neil Hudson PCSB
Pankaj Jain PCSB
Patrick Brenan PCSB
Rifhan Zarif M Razali PMU
Rizal Awang Newfield
Rosli Hamzah PCSB
Sofiah Sharbudeen PMU
Vince Tilley Murphy
Zuka Row Shell
PPGUA/3.0/042/2013 107