IWP INSTALLATION WORK PACKAGE 030


AUXILIARY TRAILER SETUP
Effectivity: TM2500+ / Gen VI & VII

PURPOSE & SCOPE:


This work package provides instructions for on‐site setup of the Auxiliary Trailer, including
positioning, elevation, and leveling; and installing ground connections.

DURATION:
1 day (based on 10 hour days)
* Number of personnel and duration may vary with skill level, productivity, and site conditions.

RECOMMENDED PERSONNEL:
• GE Mechanical TA • 2 Mechanics
• Truck Driver • 2 Helpers

RECOMMENDED TOOLS, MATERIALS, & EQUIPMENT:


• Air‐Ride Trailer Truck • Mechanical Hand Tools (US & Metric)
• Transit & Level • Standard Grease (NLGI Grade II)

REFERENCE DOCUMENTS:
751200 – General Arrangement, Main Trailer 751202 – Plot Plan, Trailer Mount
751218 – General Arrangement, Aux. Trailer 751294 – Interface Drawing, Main Trailer
751295 – Interface Drawing, Auxiliary Trailer TP1000 – Trailer Transport Instruction

©2014, GE Power & Water – Distributed Power – Aero Energy. All Rights Reserved.
This document is the proprietary property of GE Aero Energy, and is loaned in strict confidence, with the understanding that it will not be
reproduced, nor used for any purpose except that for which it is intended. It shall be immediately returned on demand, and is subject to all
other terms and conditions of any written agreement or purchase order which incorporates or relates to this document.
IWP030 TM2500+ Installation
Auxiliary Trailer Setup & Commissioning Manual

Main
Trailer

Auxiliary
Trailer

Figure 1: Auxiliary Trailer Layout

Fin/Fan Cooler

Control House
Generator
Exhaust
Silencer

Auxiliary
Skid CO2 System

Figure 2: Auxiliary Trailer Equipment

NOTE:
LANDING GEAR SUPPORT BLOCKS
It is recommended that a support block 8” to 10” thick be placed under each landing gear to minimize
travel. Minimal extension of the landing gear improves their support strength.
If the landing gear support blocks are not supplied by GE, they must be fabricated in accordance with GE
specifications.

IWP030_Rev.1.0 Page 2 of 4
IWP030 TM2500+ Installation
Auxiliary Trailer Setup & Commissioning Manual

A TRAILER SETUP Initials / Date


Refer to drawing 751202 – Plot Plan, Trailer Mount for additional details.
Move the Auxiliary Trailer into position on the foundation.
1 The centerline to centerline distance should measure roughly 12’ 6’.
Raise or lower the trailer with the airbags until rough level.
Verify the landing gear assemblies are aligned with their respective
2
landing gear pads.
Lower the landing gear and level the trailer to within ± ½” corner to
3
corner.
NOTE: The auxiliary trailer landing gear are inboard‐mounted. Handles rotate and engage in
the opposite direction vs. the main trailer (outboard‐mounted).

Figure 4: Landing Gear Support Locations (On‐Site Positioning)

B INSTALL GROUNDS Initials / Date


Install grounding connections. Reference drawing:
1
‐ 751218 – General Arrangement, Auxiliary Trailer

IWP030_Rev.1.0 Page 3 of 4
IWP030 TM2500+ Installation
Auxiliary Trailer Setup & Commissioning Manual

NOTE:
RECEIVING & INSPECTION
MISSING OR DAMAGED ITEMS MUST BE IDENTIFIED EARLY SO THEY CAN BE ORDERED AND POSSIBLE
PROJECT DELAYS ARE AVOIDED.
FAILURE TO SUBMIT THE OSD&D REPORT AND ANY WARRANTY CLAIMS MAY CAUSE DELAYS IN RECEIPT
OF REPLACEMENT COMPONENTS AND MAY IMPACT THE PROJECT SCHEDULE.

C PUNCH LIST UPDATE Initials / Date


1 Record any Punch List items identified during this work package.
WORK PACKAGE COMPLETION
Comments:

Project Name Unit Number

Start Date Completion Date

Contractor Representative Customer Representative GE Representative


Printed Name: Printed Name: Printed Name:

Printed Title: Printed Title: Printed Title:

Initials/Date: Initials/Date: Initials/Date:

Signature: Signature: Signature:

IWP030_Rev.1.0 Page 4 of 4

You might also like