Professional Documents
Culture Documents
BY
KHALID KAMESHKI
STUDENT NO : 00610289
TABLE OF CONTENTS
INTRODUCTION:
MAINBODY:
According to yellow form clause 35a (i) the employer and contractor have account called
‘Guarantee account’ in the bank mentioned in the appendix. The employer has to pay 2 months
of average amount (i.e. €120,000 Contract value/12 months completion period = €10,000x2 =
€20,000/-) in the guarantee account.
The amount in the Guarantee account will be paid to the contractor upon final certificate or any
unpaid interim certificate pursuant to clause 34(b).
And also the employer’s bank will issue a certificate confirms that the employer having
sufficient fund for the project to meet the uninterrupted cash flow.
Interim payment:
The contractor has to submit their valuation based on the work progress with detailed supporting
documents for architects approval. The architect would check and certify the same and send their
recommendation to the employer for payment. The employer should pay to the contractor within
5 working or days or as mentioned in the appendix. This amount inclusive of sub-contractor and
nominated subcontractor works also. If certified amount differs from submitted amount by the
contractor, the Architects shall give detailed explanation to the contractor about deduction or
addition of amount submitted by them.
Materials at Site: The contractor entitled to claim for material at site in their interim valuation as
mentioned in the appendix. The contractor cannot claim 100% of value of material in their
valuation.( Normally up to 80%).
Material at site will be approved by architects with following conditions:
Materials or goods planned for the particular project.
Materials or goods stored by the contractor, the employer, sub-contractor or Nominated
sub-contractor.
Classification of works( i.e. Aluminium, Wooden doors)
Retention Fund:
The amount to be retained by the employer in every interim as agreed in the appendix. The total
amount shall not exceed as mentioned in the appendix as limit of retention amount.
This retention amount will be released against retention bond issued by contractor to employer
after the issue of practical completion certificate. Or else the 50% of retention amount released to
contractor upon the practical completion certificate and balance 50% will be released after the
defects liability period.