PT.

GRAND SURYA PONDASI


PROYEK PEMBANGUNAN PELABUHAN BIAS MUNJUL
NUSA CENINGAN‐BALI

PILE DRIVING RECORD

Date : 1-Nov-21 Page:

Structure Dudukan Movable Bridge Driving Data

Pile Position Vertical/Batter Pile Blow Pile Blow Pile Blow Pile Blow

SPP Marking Count Marking Count Marking Count Marking Count


Pile Type
Diameter: 609 mm 0.50 0 15.50 177 30.50 440 45.50 778

Lower 1A Marking 12m 1.00 0 16.00 185 31.00 447 46.00 799

Middle 1B Marking 12m 1.50 0 16.50 194 31.50 455 46.10


Pile Code
Middle 1C Marking 12m 2.00 0 17.00 205 32.00 465 46.20

Upper 1D Marking 11m 2.50 0 17.50 213 32.50 476 46.30

X 330476.55 3.00 0 18.00 226 33.00 484 46.40


Coordinate Design
Y 9039280.5 3.50 0 18.50 236 33.50 490 46.50

Design Cut Off Level +1.300 4.00 0 19.00 247 34.00 498 46.60

Hammer Type DD65 4.50 1 19.50 259 34.50 505 46.70


H Data

Weight of Piston 6.5 Ton 5.00 2 20.00 267 35.00 512 46.80

Lower Middle 1 Middle 2 Upper 5.50 4 20.50 275 35.50 519 46.90

Date: 1-Nov-21 1-Nov-21 1-Nov-21 1-Nov-21 6.00 7 21.00 282 36.00 533 47.00
Driving Data (Time Cycle)

Launching & Start 8:24 8:50 9:49 10:27 6.50 16 21.50 288 36.50 545
Handling Finish 8:30 8:57 9:52 10:32 7.00 27 22.00 294 37.00 555

Start 8:30 8:57 9:52 10:32 7.50 31 22.50 303 37.50 563
Positioning
Finish 8:41 9:19 9:59 10:42 8.00 35 23.00 311 38.00 570

Start 8:41 9:40 10:21 10:57 8.50 40 23.50 320 38.50 576
Driving
Finish 8:50 9:48 10:27 11:09 9.00 45 24.00 334 39.00 584

Total Time 0:26 0:37 0:16 0:27 9.50 56 24.50 350 39.50 595

Material Number 1B 1C 1D 10.00 67 25.00 361 40.00 607

Segment L-M1 M1-M2 M2-U 10.50 78 25.50 369 40.50 621


Welding

Start Time 9:19 9:59 10:42 11.00 90 26.00 375 41.00 636

Finish Time 9:40 10:21 10:57 11.50 101 26.50 381 41.50 647

Total Time 0:21 0:22 0:15 12.00 113 27.00 388 42.00 667

Survey Point 12.50 129 27.50 394 42.50 678

Sea Bed Elevation -4.00 LAT 13.00 140 28.00 401 43.00 691
Driving Result

Top Pile Elevation +2.653 LAT 13.50 150 28.50 410 43.50 714

Bottom Pile Elevation -44.35 LAT 14.00 155 29.00 419 44.00 738

Total Blow 799 Blows 14.50 163 29.50 426 44.50 752

Final Penetration 23.81 mm/blow 15.00 170 30.00 432 45.00 772

Remarks: Survey's Result

Coordinate Actual Difference

X 330476.584 0.034

Y 9039280.469 -0.031

Mengetahui Disetujui oleh : Dibuat oleh


Staff Teknis Kegiatan LLASDP PT. Parigraha Konsultan PT. Nindya Karya (Persero)
Name

Signature

Date