You are on page 1of 2

PROJECT TITLE : PROPOSED RETAINING WALL

PROJECT LOCATION :
SUBJECT : REBAR CUT AND BEND SCHEDULE
DATE REVISED :

R E B A R C U T & B E N D S CH E D U L E
2 40 L99 Z T9 B
S U
C
A A A E
B A E C B D
A C A B F B D
B E
A C
D

QUANTITY SIZE OF BAR DIMENSION (OUT TO OUT), mm LENGTH OF BAR TOTAL LENGTH UNIT WT. TOTAL WT. COMMERCIAL P.O. WASTAGE PER PCS. PRODUCED WASTAGE
STRUCTURE LOCATION BAR MARK SHAPE CODE
(Ø,mm) A B C D E F G (m) (m) (Kg/m) (Kg) SIZE (m) (PCS.) BAR (m) PER BAR (kg)

Footing Transverse bottom bar 1 2 28 16 300 1200 300 1.80 50.40 1.578 79.54 6 9 0.6 3 8.84
RW-1

Vertical bar 8 L99 8 16 400 1600 2.00 16.00 1.578 25.25 6 3 0 3 -


PEDESTAL
Ties 9 L99 30 10 80 200 200 200 200 80 0.96 28.80 0.617 17.76 6 5 0.24 6 0.74

TOTAL 147.06 11.49

TOTAL 269.61 21.07


cutt

SUMMARY DIAM LENGTH QTY UNIT


6 pcs
9 pcs
10 10.5 pcs
12 pcs
6 #REF! pcs
9 #REF! pcs
12
10.5 #REF! pcs
12 pcs
6 pcs
7.5 #REF! pcs
16
10.5 pcs
12 pcs
6 pcs
7.5 #REF! pcs
20 9 #REF! pcs
10.5 pcs
12 pcs PREPARED BY: APPROVED BY
6 pcs
7.5 pcs
25 9 #REF! pcs
10.5 #REF! pcs
12 pcs
RO GONDRA HRD ENGINEER
PROJECT : PROPOSED ROOF REPAIR AT COMPRESSOR AREA TL-1
LOCATION : PLANT 1
OWNER : TONGLUNG, EZSET
SUBJECT : COST PROPOSAL FOR GENERAL CONSTRUCTION WORKS

Material Labor/Others
ITEM NO ITEM DESCRIPTION Qty. UNIT Unit TOTAL UNIT COST TOTAL COST
Unit Cost
Cost

I General Requirements

Mobilization 1.00 lot 8,000.00 8,000.00 8,000.00


Demobilization 1.00 lot 8,000.00 8,000.00 8,000.00
Supervision 1.00 lot 20,000.00 20,000.00 20,000.00
Others 1.00 lot -
- Safety and Health / PPEs 1.00 lot 10,000.00 5,000.00 15,000.00 15,000.00
Clearing works 1.00 lot 8,000.00 8,000.00 8,000.00
Consumables 1.00 lot 20,000.00 20,000.00 20,000.00

TOTAL FOR GENERAL REQUIREMENTS 79,000.00

II DISMANTLING WORKS

Dismantling of Existing Roof sheets including all existing tinsmithry 152.00 m² 200.00 200.00 30,400.00
Installation of safety supports 1.00 lot 10,000.00 8,000.00 18,000.00 18,000.00
Hauling of all dismantled sheets and debris 1.00 lot 15,000.00 15,000.00 15,000.00

RE-ROOFING WORKS
Thermoplastic UPVC Roof Sheet@ 1.0mm thk 180.00 L.m. 750.00 250.00 1,000.00 180,000.00
Tinsmithry works: Outside and Inside Gutter, ridgeroll and flashings 1.00 all 40,000.00 24,000.00 64,000.00 64,000.00
Downspouts 100.00mm dia. 1.00 all 15,000.00 7,000.00 22,000.00 22,000.00

ROOF FRAMING EXTENSION


Extension of Roof Framing at right side using ibeamw 8x15 5.00 sets 5,000.00 1,500.00 6,500.00 32,500.00
Additional Rafter B1 w 8 x 15 3.00 sets 28,000.00 8,400.00 36,400.00 109,200.00
Additional Girder w 12 x 30 26.60 l.m. 4,023.00 1,206.90 5,229.90 139,115.34
VTUB1 RHS 100mm x 100mm x 15mm 8.00 sets 2,000.00 800.00 2,800.00 22,400.00
C1, stiffiners & doublers 5mm thk 1.00 all 28,000.00 12,000.00 40,000.00 40,000.00
Installation of Rafter and Girders 1.00 all 50,000.00 50,000.00 50,000.00
TOTAL FOR REHABILITATION OF ROOF 722,615.34

Total Cost 801,615.34

Submitted By:

ELMER M. MARQUEZ
PRESIDENT / CEO

N5M DEVELOPER AND MAINTENANCE CORP.

You might also like