DAFTAR HARGA SATUAN BAHAN

SKPD :
NAMA PAKET :
LOKASI :
VOLUME :
PROP/KAB/KODYA :

NO KODE URAIAN SAT HARGA SATUAN


1 AA-002 Armature Dimming c/w lampu 150 W lengkap bh 3,050,000.00
2 AA-003 Armature Dimming c/w lampu 250 W decoratif lengkap bh 3,428,000.00
3 AE-001 Tiang Oktagonal 9 meter DO type baseplate btg 4,950,000.00
4 AE-002 Tiang Oktagonal 9 meter SO type baseplate btg 4,275,000.00
5 AE-003 Tiang Decoratic 9 meter SO type baseplate btg 6,400,000.00
6 AF-001 GPAS/ ELCB 25 A bh 430,000.00
7 AF-002 GPAS/ ELCB 40 A bh 500,000.00
8 AF-005 MCB 1P 2- 16 A bh 60,000.00
9 AF-016 Kontaktor 3P, 40 A bh 450,000.00
10 AF-019 Timer Switch type Analog/digital,24 jam 1P bh 500,000.00
11 AF-020 Selector Switch Auto/Manual bh 85,000.00
12 AF-022 KWH meter 1P 20/60 A bh 550,000.00
13 AF-023 KWH meter 3P 20/60 A bh 2,250,000.00
14 AF-024 OK meter 1 P bh 50,000.00
15 AF-025 OK meter 3 P bh 175,000.00
16 AF-026 Terminal keramik 4P 60 A bh 55,000.00
17 AG-003 Kabel Twisted 4x16 mm2 mtr 15,250.00
18 AG-007 Kabel NYY 2x1,5mm2 mtr 10,500.00
19 AG-008 Kabel NYY 4x6 mm2 rol 4,455,000.00
20 AG-005 Kabel NYFGbY 4x16mm2 mtr 122,500.00
21 AG-009 Kabel NYFGbY 4x10mm2 mtr 90,150.00
22 AG-013 Kabel NYAF 10 mm2 mtr 25,000.00
23 AG-014 Kabel NYAF 16 mm2 mtr 41,000.00
24 AG-015 Kabel NYMHYO 3x2.5 mm2 rol 1,800,000.00
25 AG-016 Kabel NYY 3x 2.5 mm2 mtr 13,500.00
26 AG-017 Kabel NYY 4x4 mm2 mtr 42,000.00
27 AG-018 Kabel NYFGbY 4x6 mm2 mtr 240,000.00
28 AH-001 Service Wedge Clamp bh 4,500.00
29 AH-002 Suspension Clamp bh 19,000.00
30 AH-003 Suspension Bracket bh 19,000.00
31 AH-004 Tension Bracket bh 22,000.00
32 AH-006 Line tap connector (CCS) 6/25 mm2 bh 13,000.00
33 AH-007 Line tap connector (CCS) 35/70 mm2 bh 27,000.00
34 AH-008 Jointing Konektor Bimetal AL/CU 16 - 6 + pengaman bh 6,000.00
35 AH-009 Konektor Tembus kedap air bh 12,000.00
36 AH-010 Stainless Steel Strip mtr 12,000.00
37 AH-011 Yokes/Stoping Buckle bh 2,350.00
38 AH-012 Link bh 2,000.00
39 AI-001 Panel Kontrol Distribusi PJU type APP-1P bh 4,338,300.00
40 AI-002 Box panel 60x40x25 cm bh 1,250,000.00
41 AI-004 Gembok bh 55,000.00
42 AI-005 Angkur Ø 22 mm bh 75,000.00
43 AI-006 Pipa PVC dia.2" mtr 16,000.00
44 AI-007 Pipa PVC dia.1 1/2" mtr 11,000.00
45 AI-008 Knee PVC dia.2" bh 10,000.00
46 AI-009 Sock PVC dia 2" bh 7,500.00
47 AI-010 Asesoris ls 450,000.00
48 AI-011 Kabel BC 16 mm2 mtr 23,500.00
49 AI-012 Grounding Rod 16 mm2 bh 225,000.00
50 AI-013 Kabel schoon 16 mm2 bh 3,500.00
51 AI-014 Pipa GIV. dia. 2" mtr 22,400.00
52 AI-016 Kabel BC 6 mm2 mtr 10,750.00
53 AI-017 Kabel schoon 6 mm2 bh 1,200.00
54 AJ-001 Aspal kg 10,200.00
55 AJ-002 Semen Portland(50 kg) zak 90,000.00
56 AJ-003 Pasir M3 120,000.00
57 AJ-004 Kerikil Saring M3 245,000.00
58 AJ-005 Sirtu M3 120,000.00
59 AJ-006 Papan cor m2 100,000.00
60 AJ-007 Besi beton tulangan kg 15,000.00
61 AJ-008 Kawat beton kg 20,000.00
62 AJ-009 Paku Campur kg 20,000.00
63 AJ-010 Kawat Duri m' 15,000.00
64 AJ-011 Pasir Urug m3 120,000.00
65 AJ-012 Batu Bata bh 600.00
66 DA-001 BP VA 775.00
67 DA-002 UJL VA 280.00
68 DA-003 Jaminan Instalasi & Konsuil VA 400.00
69 DA-004 SJI VA 500.00
70 DA-005 SLO LS 1,000,000.00
71 DA-006 Mutasi Data VA 75,000.00
DAFTAR HARGA SATUAN UPAH

SKPD :
NAMA PAKET :
LOKASI :
VOLUME :
PROP/KAB/KODYA :

NO KODE URAIAN SAT HARGA SATUAN

1 BA-001 Mandor/Tenaga Ahli Listrik oh 75,000.00

2 BA-002 Mandor/Tenaga Ahli konstruksi oh 75,000.00

3 BA-003 Operator Truck Crane bucket oh 75,000.00

4 BA-004 Operator Truck Crane kapasitas 2,5 ton oh 75,000.00

5 BA-005 Operator Truck kapasitas 7 ton oh 65,000.00

6 BA-006 Operator Truck Tangga 12 meter oh 65,000.00

7 BA-007 Tukang Listrik oh 65,000.00

8 BA-008 Tukang Konstruksi oh 65,000.00

9 BA-009 Pembantu Tukang Listrik oh 55,000.00

10 BA-010 Pembantu Tukang Konstruksi oh 55,000.00

11 BA-011 Mandor Tenaga Ahli Sipil oh 75,000.00

12 BA-012 Tukang Batu oh 65,000.00

13 BA-013 Pembantu Tukang Batu oh 55,000.00

14 BA-014 Sopir oh 75,000.00

15 BA-015 Tukang Gali Tanah oh 55,000.00


DAFTAR HARGA SATUAN SEWA ALAT

SKPD :
NAMA PAKET :
LOKASI :
VOLUME :
PROP/KAB/KODYA :

NO KODE URAIAN SAT. HARGA SATUAN

1 CA-001 Sewa Truck Crane Bucket hari 1,650,000.00

2 CA-002 Sewa Truck Crane kapasitas 2,5 ton hari 1,650,000.00

3 CA-003 Sewa Truck kapasitas 7 ton hari 1,500,000.00

4 CA-004 Sewa Truck tangga 12 meter hari 1,500,000.00

5 CA-005 Tangga 7 meter hari 75,000.00

6 CA-006 Alat bantu hari 120,000.00

7 CA-007 Katrol pengangkat tiang hari 220,000.00

8 CA-008 Beton molen hari 250,000.00

9 CA-009 Penggetar beton/ Vibrator hari 250,000.00

10 CA-010 Stamper hari 250,000.00

11 CA-011 Jack Hammer hari 450,000.00

12 CA-012 Mobil Pickup hari 450,000.00


DAFTAR ANALISA HARGA SATUAN

SKPD :
NAMA PAKET :
LOKASI :
VOLUME :
PROP/KAB/KODYA :

NO KODE U R A I AN SAT. HARGA SATUAN

1 EA-001 Pemasangan armatur/gearbox di top tiang/stang ornament titik 44,431.00


2 EA-002 Setting dan aiming armatur titik 35,573.00
3 EA-003 Pemasang Box MCB dan koneksi MCB 1 Phasa titik 18,833.00
4 EA-007 Tarikan kabel twist m' 2,935.00
5 EA-009 Gelar kabel tanah, perapian dan instalasi jaringan kabel tanah m' 22,911.00
6 EA-011 Galian pondasi tanah keras titik 133,000.00
7 EA-012 Galian Tanah Aspal dan Perapian Kembali m' 199,574.00
8 EA-013 Galian Tanah keras dan perapian kembali m' 109,500.00
9 EA-014 Panel kontrol distribusi type APP-1P set 4,338,300.00
10 EA-015 Pemasangan Grounding Panel Kontrol PJU titik 444,900.00
11 EA-016 Pemasangan Panel Kontrol PJU titik 199,331.00
12 EA-018 Pondasi Tiang PJU Oktagonal titik 917,479.00
13 EA-020 Finishing pondasi tiang PJU Oktagonal titik 74,299.00
14 EA-034 Crossing Kabel pada Jembatan m' 97,795.00
15 EA-035 Crossing Kabel pada Jalan m' 34,825.00
16 EA-026 Ereksion PJU Oktagonal titik 468,125.00
17 EA-033 Pemasangan grounding pada Tiang LPJU titik 263,575.00

Page 4 of 13
ANALISA HARGA SATUAN

SKPD :
NAMA PAKET :
LOKASI :
VOLUME :
PROP/KAB :

Jumlah Harga
No Kode Uraian Pekerjaan Koefisien Sat. Harga Satuan Satuan

I EA-001 Pemasangan armatur titik 44,431.00


1 BA-001 Mandor/Tenaga Ahli Listrik 0.0100 oh 75,000.00 750.00
2 BA-003 Operator Truck Crane bucket 0.0199 oh 75,000.00 1,492.50
3 BA-007 Tukang Listrik 0.0398 oh 65,000.00 2,587.00
4 BA-009 Pembantu Tukang Listrik 0.0796 oh 55,000.00 4,378.00
5 CA-001 Sewa Truck Crane Bucket 0.0199 hari 1,650,000.00 32,835.00
6 CA-006 Alat bantu 0.0199 hari 120,000.00 2,388.00
Jumlah 44,430.50
Pembulatan 44,431.00

II EA-002 Setting dan aiming armatur 1.0000 titik 35,573.00


1 BA-001 Mandor/Tenaga Ahli Listrik 0.0050 oh 75,000.00 375.00
2 BA-003 Operator Truck Crane bucket 0.0100 oh 75,000.00 750.00
3 BA-007 Tukang Listrik 0.0200 oh 65,000.00 1,300.00
4 BA-009 Pembantu Tukang Listrik 0.0395 oh 55,000.00 2,172.50
5 CA-001 Sewa Truck Crane Bucket 0.0175 hari 1,650,000.00 28,875.00
6 CA-006 Alat bantu 0.0175 hari 120,000.00 2,100.00
Jumlah 35,572.50
Pembulatan 35,573.00

III EA-003 Pemasang dan koneksi MCB 1 Phasa 1.0000 titik 18,833.00
1 BA-007 Tukang Listrik 0.0333 oh 65,000.00 2,166.67
2 BA-009 Pembantu Tukang Listrik 0.0667 oh 55,000.00 3,666.67
3 CA-005 Tangga 7 meter 0.0667 hari 75,000.00 5,000.00
4 CA-006 Alat bantu 0.0667 hari 120,000.00 8,000.00
Jumlah 18,833.33
Pembulatan 18,833.00

IV EA-007 Tarikan kabel twisted 1.0000 m' 2,935.00 2,935.00


1 BA-001 Mandor/Tenaga Ahli Listrik 0.0010 oh 75,000.00 75.00
2 BA-007 Tukang Listrik 0.0040 oh 65,000.00 260.00
3 BA-009 Pembantu Tukang Listrik 0.0080 oh 55,000.00 440.00
4 BA-014 Sopir 0.0030 oh 75,000.00 225.00
5 CA-005 Tangga 7 meter 0.0030 hari 75,000.00 225.00
6 CA-006 Alat bantu 0.0030 hari 120,000.00 360.00
7 CA-012 Mobil Pickup 0.0030 hari 450,000.00 1,350.00
Jumlah 2,935.00
Pembulatan 2,935.00

V EA-009 Gelar kabel tanah, perapian dan instalasi 1.0000 m' 22,911.00 22,911.00
jaringan kabel tanah
Tenaga Kerja
1 BA-001 Mandor/Tenaga Ahli Listrik 0.0050 oh 75,000.00 375.00
2 BA-007 Tukang Listrik 0.0100 oh 65,000.00 650.00
3 BA-009 Pembantu Tukang Listrik 0.0200 oh 55,000.00 1,100.00
4 BA-014 Sopir 0.0200 oh 75,000.00 1,500.00
5 CA-012 Mobil Pickup 0.0200 hari 450,000.00 9,000.00
6 CA-006 Alat bantu 0.0200 hari 120,000.00 2,400.00
Jumlah Upah 15,025.00
Bahan
1 AJ-011 Pasir Urug 0.0300 m3 120,000.00 3,600.00
2 AJ-012 Batu Bata 7.1429 bh 600.00 4,285.71
Jumlah Bahan 7,885.71
Jumlah Upah+Bahan 22,910.71
Pembulatan 22,911.00
Jumlah Harga
No Kode Uraian Pekerjaan Koefisien Sat. Harga Satuan Satuan

VI EA-011 Galian pondasi tanah keras 1.0000 titik 133,000.00 133,000.00


1 BA-001 Mandor/Tenaga Ahli Listrik 0.2000 oh 75,000.00 15,000.00
2 BA-012 Tukang Batu 0.4000 oh 65,000.00 26,000.00
3 BA-015 Tukang Gali Tanah 0.8000 oh 55,000.00 44,000.00
4 CA-006 Alat bantu 0.4000 hari 120,000.00 48,000.00
Jumlah 133,000.00
Pembulatan 133,000.00

VII EA-012 Galian Tanah Aspal dan Perapian Kembali 199,574.00


Tenaga Kerja
1 BA-011 Mandor Tenaga Ahli Sipil 0.1000 oh 75,000.00 7,500.00
2 BA-012 Tukang Batu 0.2000 oh 65,000.00 13,000.00
3 BA-013 Pembantu Tukang Batu 0.6000 oh 55,000.00 33,000.00
4 CA-006 Alat bantu 0.6000 hari 120,000.00 72,000.00
Jumlah 125,500.00
Bahan
1 AJ-001 Aspal 1.8000 kg 10,200.00 18,360.00
2 AJ-004 Kerikil Saring 0.1000 M3 245,000.00 24,500.00
3 AJ-005 Sirtu 0.1000 M3 120,000.00 12,000.00
4 AJ-003 Pasir 0.0500 M3 120,000.00 6,000.00
5 CA-010 Stamper 0.0357 hari 250,000.00 8,928.57
6 CA-006 Alat bantu 0.0357 hari 120,000.00 4,285.71
Jumlah 74,074.29
Jumlah Tenaga Kerja dan Bahan 199,574.29
Pembulatan 199,574.00

VIII EA-013 Galian Tanah keras dan perapian kembali 1.0000 109,500.00 109,500.00
1 BA-011 Mandor Tenaga Ahli Sipil 0.1000 oh 75,000.00 7,500.00
2 BA-012 Tukang Batu 0.2000 oh 65,000.00 13,000.00
2 BA-013 Pembantu Tukang Batu 0.6000 oh 55,000.00 33,000.00
3 CA-010 Stamper 0.2000 hari 250,000.00 50,000.00
4 CA-006 Alat bantu 0.0500 hari 120,000.00 6,000.00
Jumlah 109,500.00
Pembulatan 109,500.00

IX EA-014 Panel kontrol distribusi type APP-1P 1.0000 set 4,338,300.00 4,338,300.00
Tenaga Kerja
22 BA-001 Mandor/Tenaga Ahli Listrik 0.0500 oh 75,000.00 3,750.00
23 BA-007 Tukang Listrik 0.1000 oh 65,000.00 6,500.00
24 BA-009 Pembantu Tukang Listrik 0.2000 oh 55,000.00 11,000.00
Jumlah Tenaga Kerja 21,250.00
Bahan
1 AI-002 Box panel 60x40x25 cm 1.0000 bh 1,250,000.00 1,250,000.00
2 AI-005 Angkur Ø 22 mm 2.0000 bh 75,000.00 150,000.00
3 AF-005 MCB 1P 2- 16 A 2.0000 bh 60,000.00 120,000.00
5 AF-016 Kontaktor 3P, 40 A 1.0000 bh 450,000.00 450,000.00
6 AF-019 Timer Switch type Analog/digital,24 jam 1P 1.0000 bh 500,000.00 500,000.00
7 AF-020 Selector Switch Auto/Manual 1.0000 bh 85,000.00 85,000.00
9 AF-022 KWH meter 1P 20/60 A 1.0000 bh 550,000.00 550,000.00
10 AG-014 Kabel NYAF 16 mm2 5.0000 mtr 41,000.00 205,000.00
11 AF-024 OK meter 1 P 1.0000 bh 50,000.00 50,000.00
11 AF-026 Terminal keramik 4P 60 A 1.0000 bh 55,000.00 55,000.00
12 AH-001 Service Wedge Clamp 2.0000 bh 4,500.00 9,000.00
12 AH-004 Tension Bracket 1.0000 bh 22,000.00 22,000.00
13 AH-007 Line tap connector (CCS) 35/70 mm2 4.0000 bh 27,000.00 108,000.00
14 AI-006 Pipa PVC dia.2" 8.0000 mtr 16,000.00 128,000.00
15 AI-008 Knee PVC dia.2" 6.0000 bh 10,000.00 60,000.00
16 AI-009 Sock PVC dia 2" 2.0000 bh 7,500.00 15,000.00
17 AH-010 Stainless Steel Strip 3.0000 mtr 12,000.00 36,000.00
18 AH-011 Yokes/Stoping Buckle 3.0000 bh 2,350.00 7,050.00
19 AH-012 Link 6.0000 bh 2,000.00 12,000.00
20 AI-004 Gembok 1.0000 bh 55,000.00 55,000.00
21 AI-010 Asesoris 1.0000 ls 450,000.00 450,000.00
Jumlah Bahan 4,317,050.00
Jumlah Tenaga Kerja dan Bahan 4,338,300.00
Dibulatkan 4,338,300.00
Jumlah Harga
No Kode Uraian Pekerjaan Koefisien Sat. Harga Satuan Satuan

X EA-015 Pemasangan Grounding Panel Kontrol PJU 1.0000 titik 444,900.00 444,900.00
Tenaga Kerja
1 BA-001 Mandor/Tenaga Ahli Listrik 0.1000 oh 75,000.00 7,500.00
2 BA-007 Tukang Listrik 0.2000 oh 65,000.00 13,000.00
3 BA-009 Pembantu Tukang Listrik 0.4000 oh 55,000.00 22,000.00
Jumlah 42,500.00
Bahan
1 AI-011 Kabel BC 16 mm2 3.0000 mtr 23,500.00 70,500.00
2 AI-012 Grounding Rod 16 mm2 1.0000 bh 225,000.00 225,000.00
3 AI-013 Kabel schoon 16 mm2 2.0000 bh 3,500.00 7,000.00
4 AI-014 Pipa GIV. dia. 2" 3.0000 mtr 22,400.00 67,200.00
5 AH-010 Stainless Steel Strip 2.0000 mtr 12,000.00 24,000.00
5 AH-011 Yokes/Stoping Buckle 2.0000 bh 2,350.00 4,700.00
6 AH-012 Link 2.0000 bh 2,000.00 4,000.00
Jumlah 402,400.00
Jumlah Tenaga Kerja dan Bahan 444,900.00
Dibulatkan 444,900.00

XI EA-016 Pemasangan Panel Kontrol PJU 1.0000 titik 199,331.00 199,331.00


1 BA-001 Mandor/Tenaga Ahli Listrik 0.1832 oh 75,000.00 13,740.00
2 BA-007 Tukang Listrik 0.7326 oh 65,000.00 47,619.00
3 BA-009 Pembantu Tukang Listrik 0.7326 oh 55,000.00 40,293.00
4 BA-014 Sopir 0.0500 oh 75,000.00 3,750.00
5 CA-012 Mobil Pickup 0.0500 hari 450,000.00 22,500.00
4 CA-005 Tangga 7 meter 0.3663 hari 75,000.00 27,472.50
5 CA-006 Alat bantu 0.3663 hari 120,000.00 43,956.00
Jumlah 199,330.50
Dibulatkan 199,331.00

XII EA-018 Pondasi Tiang PJU Oktagonal 1.0000 titik 917,479.00 917,479.00
1 AJ-002 Semen Portland(50 kg) 2.3652 zak 90,000.00 212,868.00
2 AJ-003 Pasir 0.2160 M3 120,000.00 25,920.00
3 AJ-004 Kerikil Saring 0.1440 M3 245,000.00 35,280.00
4 AJ-007 Besi beton tulangan 19.3836 kg 15,000.00 290,754.00
5 AJ-006 Papan cor 1.9200 m2 100,000.00 192,000.00
6 AI-007 Pipa PVC dia.1 1/2" 2.0000 mtr 11,000.00 22,000.00
7 AJ-009 Paku Campur 0.0700 kg 20,000.00 1,400.00
8 AJ-008 Kawat beton 0.0200 kg 20,000.00 400.00
9 BA-011 Mandor Tenaga Ahli Sipil 0.0278 oh 75,000.00 2,085.00
10 BA-012 Tukang Batu 0.0556 oh 65,000.00 3,614.00
11 BA-013 Pembantu Tukang Batu 0.1667 oh 55,000.00 9,168.50
12 BA-014 Sopir 0.1667 oh 75,000.00 12,502.50
13 CA-012 Mobil Pickup 0.1667 hari 450,000.00 75,015.00
14 CA-008 Beton molen 0.0556 hari 250,000.00 13,900.00
15 CA-009 Penggetar beton/ Vibrator 0.0556 hari 250,000.00 13,900.00
16 CA-006 Alat bantu 0.0556 hari 120,000.00 6,672.00
Jumlah 917,479.00
Dibulatkan 917,479.00

XIII EA-020 Finishing pondasi tiang PJU Oktagonal 1.0000 titik 74,299.00 74,299.00
1 AJ-002 Semen Portland(50 kg) 0.1238 zak 90,000.00 11,137.50
2 AJ-003 Pasir 0.0240 M3 120,000.00 2,880.00
6 BA-011 Mandor Tenaga Ahli Sipil 0.1820 oh 75,000.00 13,650.00
7 BA-012 Tukang Batu 0.3636 oh 65,000.00 23,634.00
8 BA-013 Pembantu Tukang Batu 0.3636 oh 55,000.00 19,998.00
11 CA-006 Alat bantu 0.0250 hari 120,000.00 3,000.00
Jumlah 74,299.50
Dibulatkan 74,299.00
Jumlah Harga
No Kode Uraian Pekerjaan Koefisien Sat. Harga Satuan Satuan

XIV EA-026 Ereksion PJU Oktagonal 1.0000 titik 468,125.00 468,125.00


1 BA-002 Mandor/Tenaga Ahli konstruksi 0.0667 oh 75,000.00 5,000.00
2 BA-008 Tukang Konstruksi 0.2500 oh 65,000.00 16,250.00
3 BA-010 Pembantu Tukang Konstruksi 0.3750 oh 55,000.00 20,625.00
4 BA-004 Operator Truck Crane kapasitas 2,5 ton 0.1250 oh 75,000.00 9,375.00
5 BA-005 Operator Truck kapasitas 7 ton 0.1250 oh 65,000.00 8,125.00
6 CA-002 Sewa Truck Crane kapasitas 2,5 ton 0.1250 hari 1,650,000.00 206,250.00
7 CA-003 Sewa Truck kapasitas 7 ton 0.1250 hari 1,500,000.00 187,500.00
8 CA-006 Alat bantu 0.1250 hari 120,000.00 15,000.00
Jumlah 468,125.00
Dibulatkan 468,125.00

XV EA-033 Pemasangan grounding pada Tiang LPJU 1.0000 titik 263,575.00 263,575.00
Tenaga Kerja
1 BA-001 Mandor/Tenaga Ahli Listrik 0.0500 oh 75,000.00 3,750.00
2 BA-007 Tukang Listrik 0.1000 oh 65,000.00 6,500.00
3 BA-009 Pembantu Tukang Listrik 0.2000 oh 55,000.00 11,000.00
Jumlah 21,250.00
Bahan
1 AI-012 Grounding Rod 16 mm2 1.0000 bh 225,000.00 225,000.00
2 AI-016 Kabel BC 6 mm2 1.5000 mtr 10,750.00 16,125.00
3 AI-017 Kabel schoon 6 mm2 1.0000 bh 1,200.00 1,200.00
Jumlah 242,325.00
Jumlah Tenaga Kerja dan Bahan 263,575.00
Dibulatkan 263,575.00

XVI EA-034 Crossing Kabel pada Jembatan 1.0000 m' 97,795.00 97,795.00
Tenaga Kerja
1 BA-001 Mandor/Tenaga Ahli Listrik 0.0050 oh 75,000.00 375.00
2 BA-007 Tukang Listrik 0.0100 oh 65,000.00 650.00
3 BA-009 Pembantu Tukang Listrik 0.0200 oh 55,000.00 1,100.00
4 CA-006 Alat bantu 0.0200 hari 120,000.00 2,400.00
Jumlah Upah 4,525.00
Bahan
1 AI-014 Pipa GIV. dia. 2" 1.0500 mtr 22,400.00 23,520.00
2 AI-005 Angkur Ø 22 mm 0.5000 bh 75,000.00 37,500.00
3 AJ-010 Kawat Duri 1.2500 m' 15,000.00 18,750.00
4 AI-010 Asesoris 0.0300 ls 450,000.00 13,500.00
Jumlah Bahan 93,270.00
Jumlah Upah+Bahan 97,795.00
Pembulatan 97,795.00

XVII EA-035 Crossing Kabel pada Jalan 1.0000 m' 34,825.00 34,825.00
Tenaga Kerja
1 BA-001 Mandor/Tenaga Ahli Listrik 0.0050 oh 75,000.00 375.00
2 BA-007 Tukang Listrik 0.0100 oh 65,000.00 650.00
3 BA-009 Pembantu Tukang Listrik 0.0200 oh 55,000.00 1,100.00
4 CA-006 Alat bantu 0.0200 hari 120,000.00 2,400.00
Jumlah Upah 4,525.00
Bahan
1 AI-006 Pipa PVC dia.2" 1.0500 mtr 16,000.00 16,800.00
2 AI-010 Asesoris 0.0300 ls 450,000.00 13,500.00
Jumlah Bahan 30,300.00
Jumlah Upah+Bahan 34,825.00
Pembulatan 34,825.00
DAFTAR KUANTITAS DAN HARGA

SKPD :
NAMA PAKET :
LOKASI :
VOLUME :
PROP/KAB/KODYA :

NO KODE URAIAN PEKERJAAN VOLUME SAT. HARGA JUMLAH

A PEKERJAAN PENDAHULUAN
1 Pekerjaan Papan Nama Proyek 1.00 Ls -
2 Mobilisasi dan Demobilisasi Peralatan 1.00 Ls -
Jumlah A -

B PENGADAAN DAN PEMASANGAN LAMPU ARMATUR


1 AA-003 Armature Dimming c/w lampu 250 W decoratif lengkap 15.00 bh 3,428,000.00 51,420,000.00
2 EA-001 Pemasangan armatur 15.00 titik 44,431.00 666,465.00
3 EA-033 Pemasangan grounding pada Tiang LPJU 15.00 titik 263,575.00 3,953,625.00
Jumlah B 56,040,090.00

C PENGADAAN DAN PEMASANGAN TIANG LAMPU


1 AE-001 Tiang Oktagonal 9 meter DO type baseplate 3.00 btg 4,950,000.00 14,850,000.00
2 AE-002 Tiang Oktagonal 9 meter SO type baseplate 8.00 btg 4,275,000.00 34,200,000.00
3 AF-005 MCB 1P 2- 16 A 15.00 bh 60,000.00 900,000.00
4 EA-003 Pemasang dan koneksi MCB 1 Phasa 15.00 titik 18,833.00 282,495.00
5 EA-011 Galian pondasi tanah keras 15.00 titik 133,000.00 1,995,000.00
6 EA-018 Pondasi Tiang PJU Oktagonal 15.00 titik 917,479.00 13,762,185.00
7 EA-020 Finishing pondasi tiang PJU Oktagonal 15.00 titik 74,299.00 1,114,485.00
8 EA-026 Ereksion PJU Oktagonal 15.00 titik 468,125.00 7,021,875.00
9 EA-002 Setting dan aiming armatur 15.00 titik 35,573.00 533,595.00
Jumlah C 74,659,635.00

D PENGADAAN DAN PEMASANGAN JARINGAN KABEL PJU


1 AG-016 Kabel NYMHYO 3x2.5 mm2 2.00 rol 1,800,000.00 3,600,000.00
2 AG-018 Kabel NYY 4x6 mm2 4.00 rol 4,455,000.00 17,820,000.00
3 AG-009 Kabel NYFGbY 4x10mm2 - mtr 90,150.00 -
5 EA-013 Galian Tanah keras dan perapian kembali - oh 109,500.00 -
6 EA-009 Gelar kabel tanah, perapian dan instalasi jaringan kabel tanah 716.10 m' 22,911.00 16,406,567.10
7 EA-035 Crossing Kabel pada Jalan - m' 34,825.00 -
8 EA-036 Galian Tanah Aspal dan Perapian Kembali m' 199,574.00
Jumlah D 37,826,567.10

E PENGADAAN DAN PEMASANGAN PANEL


1 EA-014 Panel kontrol distribusi type APP-1P 2.00 set 4,338,300.00 8,676,600.00
2 EA-015 Pemasangan Grounding Panel Kontrol PJU 2.00 titik 444,900.00 889,800.00
3 EA-016 Pemasangan Panel Kontrol PJU 2.00 titik 199,331.00 398,662.00
4 AG-005 Kabel NYFGbY 4x16mm2 - mtr 122,500.00 -
5 DA-006 Mutasi Data 2.00 ls 75,000.00 150,000.00
Jumlah E 10,115,062.00

F BIAYA PENYAMBUNGAN LISTRIK


1 DA-001 BP 6,600.00 VA 775.00 5,115,000.00
2 DA-002 UJL 6,600.00 VA 172.00 1,135,200.00
3 DA-004 SJI 6,600.00 VA 500.00 3,300,000.00
4 DA-005 SLO 1.00 Ls 1,000,000.00 1.00
9,550,201.00
1 DA-001 BP 7,700.00 VA 775.00 5,967,500.00
2 DA-002 UJL 7,700.00 VA 172.00 1,324,400.00
3 DA-004 SJI 7,700.00 VA 500.00 3,850,000.00
4 DA-005 SLO 1.00 Ls 1,000,000.00 1,000,000.00
12,141,900.00
Jumlah F 13,542,100.00
REKAPITULASI
PERKIRAAN HARGA PEKERJAAN

SKPD :
NAMA PAKET :
LOKASI :
VOLUME :
PROP/KAB. :

Jumlah Harga
No. Divisi Uraian
(Rp)

A Pekerjaan Pendahuluan -
B Pekerjaan Pengadaan dan Pemasangan Lampu Armature 56,040,090.00
C Pekerjaan Pengadaan dan Pemasangan Tiang Lampu 74,659,635.00
D Pekerjaan Pengadaan dan Pemasangan Jaringan Kabel PJU 37,826,567.10
E Pekerjaan Pengadaan dan Pemasangan Panel 10,115,062.00
F Biaya Penyambungan Listrik 13,542,100.00
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 192,183,454.10
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 19,218,345.41
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 211,401,799.51
DIBULATKAN 211,400,000.00

Terbilang :

Kendari, Februari 2015


Diperiksa oleh, Dibuat Oleh,

Direktur

Mengetahui,
Penerangan Jalan Umum Dua Lengan

Jumlah Satuan Uraian Pekerjaan Harga Satuan Upah Pekerja


(Rp) (Rp)
0.0107 hari Mandor 75,000.00 802.50
0.0857 hari Pekerja 55,000.00 4,713.50
0.0321 hari Tukang Listrik 65,000.00 2,086.50
1 btg Tiang PJU H-11 1,750,000.00
1 Ls Pondasi 450,000.00
1 Bh Armature Dimming c/w lampu 150 W lengkap 3,050,000.00
13 m' Kabel Instalasi NYM 3 x 2.5 mm 18,000.00
35 m' Kabel Tanah NYY 4 x 6 mm 44,550.00
1 Ls Panel Penerangan 250,000.00
1 Ls Pelindung Kabel 45,000.00
1 Ls Ground Perlengkapan 125,000.00
35 m' Galian Tanah keras dan perapian kembali 45,000.00
1 Ls Peralatan Listrik 25,500.00
0.5 jam Lift Car 75,000.00

Total/Titik PJU = 7,602.50

(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan )


(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A)
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)

DIBULATKAN
Harga Alat/Bahan Jumlah
(Rp) (Rp)
802.50
4,713.50
2,086.50
1,750,000.00 1,750,000.00
450,000.00 450,000.00
3,050,000.00 3,050,000.00
234,000.00 234,000.00
1,559,250.00 1,559,250.00
250,000.00 250,000.00
45,000.00 45,000.00
125,000.00 125,000.00
1,575,000.00 1,575,000.00
25,500.00 25,500.00
37,500.00 37,500.00

9,101,250.00 9,108,852.50

= 182,177,050.00
= 18,217,705.00
= 200,394,755.00

= 200,390,000.00