ID Task Task Name Duration Start Finish August 2021September 2021

October 2021
November 2021
December 2021
January 2022February 2022
March 2022 April 2022 May 2022 June 2022 July 2022 August 2022September 2022
October 2022
November 2
1 Contract Anthar Offshor / ARC 30 days Mon 20-9-21 Fri 29-10-21

2 Proposal Engineering, procurement and project 5 days Mon 20-9-21 Fri 24-9-21
management

3 Drafting Letter of Credit 24 days Mon 27-9-21 Thu 28-10-21

4 Engineering order ARC==>Anthar 1 day Fri 29-10-21 Fri 29-10-21

5 Contract Niron / ARC 6 days Mon 3-1-22 Mon 10-1-22

6 Drafting Letter of Credit 5 days Mon 3-1-22 Fri 7-1-22

7 Fabrication order Niron/ARC 1 day Mon 10-1-22 Mon 10-1-22

8 Anthar Offshore 116 days Mon 1-11-21 Mon 11-4-22

9 Basic design 31 days Mon 1-11-21 Mon 13-12-21

10 class approval of basic design 40 days Tue 14-12-21Mon 7-2-22

11 Engineering documents and Design 0 days Mon 7-2-22 Mon 7-2-22 7-2

12 Detailed Engineering 45 days Tue 8-2-22 Mon 11-4-22

13 Niron Staal 270 days Mon 20-9-21 Fri 30-9-22

14 Workshop drawings and cutting files 15 days Tue 12-4-22 Mon 2-5-22

15 Order materials 20 days Tue 3-5-22 Mon 30-5-22

16 Fabrication 30 days Tue 31-5-22 Mon 11-7-22

17 painting 15 days Tue 12-7-22 Mon 1-8-22

18 Delivery of bearings and produced swivel 0 days Mon 1-8-22 Mon 1-8-22 1-8

19 assembly 30 days Tue 2-8-22 Mon 12-9-22

20 Mechanical completion 0 days Mon 12-9-22 Mon 12-9-22 12-9

21 launch 1 day Tue 13-9-22 Tue 13-9-22

22 Ballasting and tuning 10 days Wed 14-9-22 Tue 27-9-22

23 final acceptance 1 day Wed 28-9-22 Wed 28-9-22

24 Factory acceptance and third party approval 0 days Mon 20-9-21 Mon 20-9-21 20-9

25 Data book 2 days Thu 29-9-22 Fri 30-9-22

26 Delivery to ARC ex works Niron 0 days Fri 30-9-22 Fri 30-9-22 30-9

Task Project Summary Manual Task Start-only Deadline

Project: ZOC calm buoy rev 02 Split Inactive Task Duration-only Finish-only Progress
Date: Wed 20-10-21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone