EXERCISE 1

SKAU 4112
PENGATURAN KONTRAK DAN TAKSIRAN

NAMA AHLI KUMPULAN :

1. MURNI FAHIRAH BINTI MAHMUD (A17PP0055)


2. NUR AZLIN IDAYU BINTI MD ADAM @ MOHD ADNAN
(A17PP0072)
3. NOR AQIRA BINTI ROSLI (A17PP0067)
4. SITI NUR MADEEHAH BINTI ISMAWI (A17PP0093)
1. You are required to analyse and calculate cost of an excavator. Provide cost of

operating the excavator in 1 hour.

– Cost of excavator RM 350,000

– Estimated plant maintenance cost RM 35,000/5yr

– Duration of use 5 yr

– Yearly interest rate 10%

– Usage rate in a year 275 days

– Operator cost RM 40/day

– Diesel (daily) RM 50

– Grease (daily) RM 5

Cost of excavator = RM 350 000

Maintenance cost (5 years) = RM 35 000

Interest rate (1/10 x 5 x RM 350 000) = RM 175 000

Operation Cost

Operator cost = RM 40

Diesel = RM 50

Grease = RM 5

Total Operation Cost/daily = RM 95 x 275 days x 5 years = RM 130 625

TOTAL OPERATION COST FOR 5 YEARS (RM 350 000 + RM 35 000 + RM 175 000 +
RM 130 625)

= RM 690 625

Daily Cost [RM 690 625/5yrs x 275days] = RM 502.27

Hourly Cost (RM 502.27/8hrs) = RM62.78


2. You are required to do an excavation work as part of site clearing activity. The

excavation should not exceed 300mm depth (average depth is 150mm) for a 900 m2

field area. Type of soil is sand, and all excavation works to be done manually. If gross

profit required is 15%, how much cost for the site clearing is needed.

Given information:

Labour constant

– Excavation not more than 300mm (average 150mm) - 0.58hr/m2

– Levelling the excavated level 0.12hr/m2

– Discarding excavated materials 1.2hr/m3

– Daily labour rate 40.00

Excavation not more than 300mm (average 150mm) - 0.58hr/m2

Levelling the excavated level 0.12hr/m2

Discarding excavated materials 1.2hr/m3

Total = 1.9hrs

Hourly labour rate (RM 40/8hrs) = RM 5/hr

Therefore, 1.9hr x RM 5 = RM 9.50

15% Profit = RM 1.43

>> Rate of 1 cubic meter = RM10.93

RM 10.93 x 900 m2 = RM 9 837.00