Professional Documents
Culture Documents
1. Introduction
• Shallow excavating
• Pushing scraper
• Ditching
1
• Opening up pilot road
• Backfilling trenches
• Ripping
2
2. Type of Bulldozer
3. Blades (bilah)
3.1 Introduction
3
Basic earth-moving blade:
• Cutting edge: replaceable hard steel plate bolted along the bottom length
4. Blade-tractor performance
This indicates the ability of the blade to penetrate and obtain a load.
• Horsepower per loose cubic metre of material retained in front of the blade.
A higher ratio means that the bulldozer can push a load at a greater speed.
4
5. Type of Blades
Straight “S”
• For excavation work
• No curvature in it length
• Heavy duty – can penetrate into hard material
• Can be tilted and pitched
Angle “A”
• Wider than S blade
• Can be operated straight or angled up to 25o
• Cannot be pitched, designed for side-casting
material
Universal “U”
• Wider than S blade
• Edges are canted – to reduce spillage
• Efficient for moving loads over long distances
• hp/m ratio is lower than S
• hp/lm3 ratio is lower than S – best suited for
lighter material
Cushion “C”
• Mounted on large tractors for pushing loading
scrapers
• Rubber cushions and springs mounted on the
blade
• C blade is shorter than S – to avoid pushing the
blade into the rear tyres of the scraper;
facilitates manoeuvring behind scrapers
5
o Blade type
o HP
o Type and condition of material
o Cycle time
o Field measurements
6
6.3.1. Manufacturer’s blade ratings
Vs = 0.8WH2
Vu = Vs + ZH(W − Z)tanx o
Where:
o Stop the dozer’s forward motion. Create a symmetrical pile of the blade
content
7
• Measurement:
• Computation:
The blade load in loose cubic metre (lcm) can be calculated using the following
formula:
Example 1
1.49 + 1.58
H= = 1.54
2
2.10 + 2.13
W= = 2.11
2
• Cycle time is a complete dozer cycle = sum of the time required to push,
backtrack and manoeuvre into position
8
o Dozing is generally performed at slow speed 2-3 km/h, even slower for
heavy cohesive soil
Formula to calculate dozer production in loose cubic metre per 60 min hour:
Assume that the blade load of a 200 HP tracked tractor, with power shift, equals the
value calculated in Example 1. The tractor will be used to push a silty sand material.
The average push distance is 27 m. What production can be expected in loose cubic
metre?
27 1
Push Time = × x60 = 0.81 min
1000 2
9
Return time: assume 2nd gear because less than 30 m, maximum speed 6 km/h
27 1
Return Time = × x60 = 0.27 min
1000 6
Tractor must accelerate to attain 6 km/h speed, because the change in speed is very
small, an allowance of 0.05 min is made for acceleration
60 min× 4.68lcm
= 238 lm3/hr
0.81min+ 0.32min+ 0.05min
Actual production cannot be based on an ideal condition - 60 min hour; difficulty of the
work will affect job efficiency. Normally we use 50-min to calculate production.
Example 3
Assume a percent swell of 0.25 for the silty sand of Example 2 and job efficiency will
equal a 50-min hour. What is the actual production that can be expected in bank cubic
metre?
Production (bm3/hr):
238lcm 50 min
= ×
1.25 60 min
= 159bm3 / hr
……the final step is to compute the unit cost for pushing the material
Example 4
The machine in Example 3 has an owing and operating cost RM35.00 per hour.
Operators in the area were the proposed work will be performed are making RM9.50
per hour. What is the unit cost for pushing the silty sand?
10
RM35 per hour + RM9.50 per hour
Unit cost =
159bcm / hr
o Machine cuts for 15 m, then drift blade load to dump over a high wall
o Coefficient of traction:
11
Figure 1
Figure 2
Example 5
12
in bank state and is estimated to swell 12% in the loose state. Job efficiency is
assumed to be equivalent to a 50-min hour. Calculate the direct cost of the proposed
earth-moving operation in RM per bm3. Assume that the owing and operating cost is
RM 45 per hour and the operator’s wage is RM 10 per hour.
Solution:
Swell is 12%;
17
∴ loose cubic metre = = 15.2 kN/lm3
1.12
13.5
∴ material weight correction = = 0.89
15.2
Production factors:
Production:
13
Cost:
RM55 per hr
Production cost =
80 bm3 /hr
= RM0.688 per bm3
Table 1
Figure 3
14
Coefficient of traction:
15