Professional Documents
Culture Documents
SBEC 4763
Material Management
FACILITATOR
ASSOC. PROF. SR. DR. WAN YUSOFF WAN MAHMOOD
Email: b-wyusof@utm.my
HP: +60 19 755 8088
Lecture Outline
• Introduction
• Definition Material and
Material Management
• Function of Material
Management
• Focus of Material
Management
Lecture Outline
• Objectives of Material
Management.
• Benefit of Material
Management
• Phases in Material
Management
• Challenges in Material
Management
1
30/11/2020
Lecture Outline
Introduction
Introduction
• Material is an important physical
resources to complete the construction
project.
• Hence, its need to be manage carefully
to avoid any disruption to construction
production.
• Delay in supply, shortage in quantity and
quality not according to specification will
disturb the project implementation.
2
30/11/2020
Introduction
Introduction
• Preventive measure to avoid
delay in material supply:
§ Material supply agreement
§ Confirmation of order
PROJECT
PROJECT RISK PROCUREMENT
COMMUNICATION
MANAGEMENT MANAGEMENT
MANAGEMENT
TECHNOLOGY AND
ENVIRONMENTAL
ENGINEERING PROJECT MARKETING
MANAGEMENT
MANAGEMENT
PLANT AND
MATERIALS HEALTH AND SAFETY
MACHINERY
MANAGEMENT MANAGEMENT
MANAGEMENT
3
30/11/2020
10
What is Materials?
• Materials are any
commodities used directly
or indirectly in producing a
product such as raw
materials, component
parts or assemblies.
11
12
4
30/11/2020
13
14
15
5
30/11/2020
16
17
18
6
30/11/2020
19
20
21
7
30/11/2020
• Purchasing power
• Material availability
• Transport availability
• Purchasing/selling conditions
22
23
24
8
30/11/2020
25
26
27
9
30/11/2020
Building Materials
• In construction, materials account for about 35-
40% of the cost of the project. It is a very
considerable portion of the total cost of the
project.
• What happen to the project cost, particularly
the profit margin of the contractor if there is a
savings of say 5% in the cost of materials?
• What happen if there is a waste of materials,
say 5%?
• Especially if the project is secured through
competitive tendering where the profit margin
in only about 5-10% of the total cost of the
project.
28
29
Profit
Material
Cost
30
10
30/11/2020
31
32
33
11
30/11/2020
34
35
36
12
30/11/2020
37
38
39
13
30/11/2020
Material Classification
• There are many factors to be considered
while classifying the materials
§ the usage rates
§ storage methods and location
§ shelf life of the materials
§ supply reliability and regularity
§ inventory cost
§ ease of identification
§ construction sequence (work
arrangement)
40
Material Classification
41
Material Classification
• In general construction materials may be
grouped or classified into any of the following
categories:
1. Bulky – one time purchase, repetitive use and
minor materials
2. Vital – essential and desirable materials
3. Indigenous and imported materials
4. High price, medium price and low price
materials
5. High usage value, medium usage value and
low usage value
42
14
30/11/2020
Material Classification
1. High value
2. Medium value
43
44
45
15
30/11/2020
46
47
48
16
30/11/2020
49
50
Definition of Waste
• Waste is defined as:
“The difference between the value of
those materials delivered and
accepted at site and those properly
used as specified and accurately
measured in the work, after deducting
the cost saving of substituted
materials and those transferred
elsewhere”.
51
17
30/11/2020
Causes of Waste
• Site stacking and storage
• Unloading, transporting and handling of
materials
• Work place waste, i.e. cutting, quality and
mishandling
• Theft and vandalism
• Non-delivery
• Misuse and damages by following trades
52
Causes of Waste
• Variations requested by the architect
• Training errors
• Rejected work
• Substitution –goods bought for one
purpose and use for another
• Production waste e.g. cutting to length of
joist
• Negligence waste e.g. over excavation
53
Causes of Waste
• Waste also occurs on site caused
by off site activities such as poor
design, poor project information,
unintelligent buying, etc.
54
18
30/11/2020
Output
55
56
57
19
30/11/2020
58
e) Site Management
• Currently site management given more
attention to:
§ Built up working relationship with other
personnel on the contract, and
§ Resolving labour problems.
• Hence, a little time allocated for
attending to the responsibility of
construction, control of workmanship and
management of materials on site.
59
60
20
30/11/2020
Process of Material
Management
61
62
63
21
30/11/2020
64
65
66
22
30/11/2020
67
68
69
23
30/11/2020
70
71
• Material samples
§ During construction, test sample of
materials to confirm the quality meets
the specification.
§ If the test not carried out properly, the
result will be open to question?
§ Some sample are submitted direct to
the selected laboratory for testing.
72
24
30/11/2020
73
74
75
25
30/11/2020
76
77
78
26
30/11/2020
79
80
81
27
30/11/2020
82
83
84
28
30/11/2020
85
86
87
29
30/11/2020
88
89
90
30
30/11/2020
91
92
93
31
30/11/2020
94
95
96
32
30/11/2020
97
98
99
33
30/11/2020
100
101
102
34
30/11/2020
103
104
105
35
30/11/2020
106
107
108
36
30/11/2020
109
110
111
37
30/11/2020
Just in Time
• JIT, or “Just-In-Time,” refers to the
timing of production flow;
• Goods are delivered to the
construction site just in time to be
used, just in the immediately
needed quantities, and just to the
production processes that need
them.
112
Just in Time
• The most important word in Just-In-
Time is the first word, “just.”
• Goods need to arrive within minutes,
not days or weeks, of their use on the
production line.
• Only then can we eliminate waste in
such forms as overproduction,
waiting for late deliveries, and excess
inventory.
113
• Maintaining continuity of
production without switching
from one operation to another
otherwise the planned flow of
materials will be interrupted.
114
38
30/11/2020
115
116
117
39
30/11/2020
118
ABC Analysis
Techniques
119
120
40
30/11/2020
121
122
123
41
30/11/2020
124
125
126
42
30/11/2020
127
128
129
43
30/11/2020
130
131
ABC Analysis
Techniques
• The graph shows the Pareto Analysis or ABC Analysis can be depicted
pictorially
• On the X-axis we have the cumulative percentage of items. On the Y-axis we
have the cumulative percentage of use by value
• As can we seen from the graph, a few items contribute to a high percentage
of usage by value and there are many items which are the ‘C’ class items
which contribute only to a small percentage of usage by value.
• The ABC analysis puts items into categories that show the amount of effort
worth spending on inventory control.
• 20% of inventory items need 80% of the attention, while the remaining 80% of
items need only 20% of the attention.
132
44
30/11/2020
133
Bills of Materials
• For the purpose of applying the
ABC Analysis in the planning and
control of materials, it necessary to
prepare Bills of Materials.
• It is very different from the Bills of
Quantities that you have seen or
know about it before this.
134
Bills of Materials
• Your work of preparing the BILL OF
MATERIALS is made easy if the contract is
based on BILL OF QUANTITIES. You can
estimate the quantities of the various
materials for the project by abstracting
the quantities of the different work items
in the bill of quantities using the material
constants and standard wastage.
135
45
30/11/2020
Bills of Quantities
No Description Unit Qty Rates Amount
1 In columns m3 15 220.00
Formwork as specified
TO COLLECTION
136
Bills of Quantities
No Description Unit Qty Rates Amount
TO COLLECTION
137
Bills of Quantities
No Description Unit Qty Rates Amount
TO COLLECTION
138
46
30/11/2020
Bills of Quantities
No Description Unit Qty Rates Amount
139
Bills of Quantities
Qty of Add Qty of
No Description Factor
item wastes materials
1 part cement
12mm Thick cement and sand 3 parts sand
1 (1:3) as specified screeded 35 m2 1 part lime
backing to receive wall tiles 1 part Plasticiser
2.5 %
12mm Thick cement and sand
(1:3) with approved plasticiser 1 part cement
2 plainface to walls trowelled 104m2 3 parts sand
smooth 1 part lime
1 part Plasticiser 2.5 %
105mm x 105mm x 6mm thick
white glazed wall tiles bedded
and jointed to wall on screeded
3 35m2
backing including filling joints with
white cement mortar
35 35.00
Prepare and apply two coats of
4 emulsion paint to plastered wall 104m2
104 9.00
140
141
47
30/11/2020
142
143
144
48
30/11/2020
145
146
147
49
30/11/2020
148
50