You are on page 1of 12

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/257774564

Uses of anti glare screen barrier in economic, financial analysis and


determination of optimal debt capacity ratio for a road project

Article  in  KSCE Journal of Civil Engineering · November 2012


DOI: 10.1007/s12205-012-1351-9

CITATIONS READS

3 284

2 authors:

Swapan Kumar Bagui Ambarish Ghosh


I CT (I)PVT LTD Indian Institute of Engineering Science and Technology, Shibpur
19 PUBLICATIONS   92 CITATIONS    65 PUBLICATIONS   1,068 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Near Surface Geophysical and Geotechnical Investigation for Site-specific Earthquake Hazard and Slope Stability studies in and around Gangtok vis-à-vis it’s
Vulnerability and Risk Implications View project

Performance evaluation of river Brahmaputra bed materials for use in construction of road embankment, subgrade and subbase View project

All content following this page was uploaded by Ambarish Ghosh on 12 September 2015.

The user has requested enhancement of the downloaded file.


KSCE Journal of Civil Engineering (2012) 16(7):1104-1114 Construction Management
DOI 10.1007/s12205-012-1351-9
www.springer.com/12205

Uses of Anti Glare Screen Barrier in Economic, Financial Analysis and


Determination of Optimal Debt Capacity Ratio for a Road Project
Swapan Kumar Bagui* and Ambarish Ghosh**
Received October 16, 2010/Revised 1st: May 4, 2011, 2nd: August 24, 2011, 3rd: December 14, 2011/Accepted February 13, 2012

···································································································································································································································

Abstract

Drivers of vehicles are facing problem to drive due to the glare of head light of the opposite vehicle. This reduces the speed of
vehicle during night driving for the case of not providing anti glare screen barrier on the median of the divided carriageway. This
speed can be increased by providing anti glare screen barrier on the median of divided carriageway. Different values of Vehicle
Operating Cost (VOC) have been found for both the cases. The values of VOC savings 40% and 15% are recommended as toll tariff
for commercial and passenger/bus vehicle respectively. Financial analysis has been carried out using toll rate calculated from VOC
savings. Toll revenue has been determined considering effects of local traffic, leakage of traffic and toll exempted traffic. These toll
rates are used to carry out financial analysis to determine optimal debt capacity ratio. This paper presents the development of a model
to determine the optimal debt equity ratio based on equal and variable repayment schedule as well as proposing equal and variable
depreciation and identify best model for using equity holder. The model is the combination of a financial model and a linear
programming model that incorporates an objective of maximizing the return of the project from the equity holder’s point of view and
identify best method of repayment schedule from promoter point of view. Equal installment schedule with Written Down Value i. e.,
variable Depreciation Method is the best method which maximizes return on equity. To show the versatility of the model, a real case
study has also been presented herein.
Keywords: BOT (Build Operate and Transfer), glare, glare screen height, model analysis, VOC (Vehicle Operating Cost), FIRR
(Financial Internal Rate of Return), NPV (Net Present Value)
···································································································································································································································

1. Introduction reduced and travel time cost will be saved. Suppose, a man
traveled 100 km road in one hour on a four lanes road with the
Glare is an important parameter in highway engineering during provision of glare screen and it takes 1.5 hour in case of without
traveling from one place to another place. Glare effect is max- provision of glare screen. His time saving for provision of glare
imum at night and driving speed is reduced due to the effect of screen on road is 0.5 hour. His time saving cost is Rs 30 per hour.
glare. So saving is Rs 15.
Glare can be controlled by installing anti glare screen barrier Vehicle operating cost is calculated from the sum of the
on the median of four/six lanes divided carriageway. Glare following components:
screen barrier has an important role in calculating economic and • Fuel and lubricating oil consumption
financial analysis of a road project. • Tire and spare parts
Vehicle speed has been reduced to 70-80 kmph for the case of • Vehicle crew wages
four/six lanes divided carriageways during night in the absence • Vehicle maintenance labor cost
of anti glare screen barrier. This reduction of speed increases • Vehicle depreciation and interest on capital
VOC and travel time cost savings. VOC savings both cases have Separate sets of equations are used for different vehicle types
been used to fix toll rate vehicle mode wise for a Build Operate specified by user. For each vehicle type, the models predict aver-
and Transfer (BOT) project. These toll rates are used for age speeds as function of road geometry and road condition. The
financial analysis to determine optimal debt equity ratio. above VOC components with exception of vehicle depreciation
Travel time costs are calculated from average travel speeds, and interest depend on largely roughness and road geometry.
distance travel and unit cost per hour of road users’ time. In case Major parameters like internal rate of return, net present value
of increasing speed for a fix distance travel, travel time will be depends on vehicle speed in base case and improved case.

*Ph.D. Student, Dept. of Civil Engineering, Bengal Engineering and Science University, Shibpur, Howrah - 711 103, India; Intercontinental Consultants and
Technocrats Pvt. Ltd, A-8, Geen Park, New Delhi, India (Corresponding Author, E-mail: swapanbagui@gmail.com)
**Professor, Dept. of Civil Engineering, Bengal Engineering and Science University, Shibpur, Howrah - 711 103, India (E-mail: ambarish@civil.becs.ac.in;
ghosh1968@yahoo.co.in)

− 1104 −
Uses of Anti Glare Screen Barrier in Economic, Financial Analysis and Determination of Optimal Debt Capacity Ratio for a Road Project

Changing these speed increases these parameters. reach project’s debt capacity level.
General principles suggested by one World Bank report (for The (D/E) ratio norms are specific to the country in which the
Viet Nam) indicate that (i) tolling is appropriate only when traffic investment is made and these largely depend on how keen the
levels exceed 4,000-5,000 vehicles per day; (ii) toll rate levels government is to stimulate private investment in infrastructure
should not result in excessive traffic diversion with an upper projects. In India, the admissible D/E ratio for road infrastructure
limit of acceptability considered to be in the range of 10-15 projects has recently been extended up to 70:30 as an incentive to
percent; and (iii) under certain conditions, toll rates can be set promote privatization. Studies have shown that financial perfor-
higher where there is no feasible alternative. mance indicators of a BOT project can be quite sensitive to the
Toll rates were set at levels considered adequate to avoid selected D/E ratio and decline rapidly as the project promoter
excessive traffic diversion. The toll levels established for the borrows more than the optimal amount in an attempt to reach the
various project links were set at levels consistent with existing project’s debt capacity level (Malini, 1997; Dias and Ioannau,
tolls in the rest of the Colombian network, i.e., at a level that 1996). The use of optimal capital structure merits significant atten-
would allow full recovery of routine and periodic maintenance tion during the project evaluation phase. Finally Mathematical
costs. The proposed tolls varied from 9 to 36 percent of user model to determine optimum debt capacity ratio was developed.
cost savings, with the lowest values corresponding to buses and Tiong (1995) observed from his comparative study of six BOT
the highest to medium trucks. projects from both developed and developing countries that D/E
Different approaches taken in Brazil, Chile, and (Bagui and ratio varied from 100:0 to 80:20.
Ghosh, 2009b) Mexico demonstrate the need for affordable toll The use of a fixed equity debt ratio of 15/85 or 20/80 (Ali
rates. Tolls in Brazil have also been kept at relatively low levels Şentürk et al., 2004) might not be suitable for all BOT projects.
by worldwide standards, usually about USD 0.04 per km, which In the world, there are examples of projects with an equity debt
has helped promote public acceptance of the program. ratio of 1/99. As the ratio of equity and debt increases, the
Another instructive example is that of Chile, which has tendency to finance the equity from the project also increases and
endeavored to keep tolls at levels that users are willing to pay toll this directly influences the cost of the investment. It is therefore,
for improved services (i.e., about USD 0.025-0.030 per vehicle- advised not to restrain the equity debt ratio in BOT projects, if the
km, linked to the consumer price index). optimum total investment cost is to be achieved. This is a matter to
The Indonesian toll road agency, undertakes to process such be considered by both the owners and the financing groups.
applications through the government regulatory and approval However, the programme of mobilization of debt capital
mechanism. Tariff rates are usually determined by comparing during the construction period can be regulated by the promoter
user cost savings on the toll road in question with the shortest subject to the limiting value of D/E ratio. Usually, the equity is
non-toll alternative; the maximum tariff cannot exceed 70 used up in the initial years of the project construction activity and
percent of the vehicle operating cost and travel time cost savings. debt is availed to cover the expenses later.
In a BOT project, the private promoter is wholly (Malini, The available studies about the uses of Anti Glare Screen
1997) responsible to raise the necessary finance, which is often a Barrier in Economic, Financial Analysis and to Determine
combination of debt and equity. Debt is provided by lending Optimal Debt Capacity Ratio for a Road Project are very rare.
institute and equity is subscribed by the promoting companies Bagui and Ghosh (2009a, 2009b) explicitly deal with the effect
and by participating shareholders who view the project as an of uses of antiglare screen barrier. The work also discusses how
attractive investment opportunity. The use of debt is essential as VOC varies with the uses of antiglare screen barrier and increases
the promoter may not have adequate financial resources for the the toll tariff vehicle mode wise. Glare screen barrier protects the
entire project cost and also avail the advantages associated with head light of oncoming vehicle. Glare from oncoming headlights
taxation. Again debt is a cheaper source of fund than equity. has some effect on speed and steering. Several field studies have
Equity holders demand higher rates of return for the additional been carried out and it has been found that night speeds reduce
risk they bear, given the uncertainty of their returns. As the costs than that of day speed. It has been found that travel time at night
of equity are usually higher than those of debt, higher proportion is more than that of day time. VOC directly depends on vehicle
of equity financing needs higher returns on equity which may speed, road geometry and road condition. HDM 4 analysis of
call for higher level of tolls or longer concession period. case studies show that VOC is higher at lower vehicle speed of
There is no norm for suggesting an ideal debt equity ratio for vehicle and vice versa.VOC of Base case analysis of real case
the success of a BOT project, as it differs from project to project study is more than that of improved case.VOC saving is com-
and from country to country. It is also dependent on how keen pared with base case value. VOC saving is defined as VOC of
the government is to stimulate private investment in the country base case – (minus)VOC of improved case.VOC saving provision
and state economy prevailing in the country. of anti glare screen is found more than that of VOC saving of
Dias and Iaonnou (1995) have shown that Net Present Value provision of without anti glare screen when both are compared
(NPV) and return on equity of a BOT project are sensitive to the with base case. Toll rate is considered some fixed percentage of
selected Debt/Equity (D/E) ratio and that decline rapidly as the VOC saving as mentioned in the literature review. Toll rate with
promoter borrows more than optimal amount in an attempt to provision of anti glare screen increases due to increase of speed.

Vol. 16, No. 7 / November 2012 − 1105 −


Swapan Kumar Bagui and Ambarish Ghosh

Aged drivers have the tendency to drive at lower speed at night negative and positive after few years of operation period.
but young drivers drive with higher speed at night. In India in 2. A loan is available from one source or from multiple sources
over all cases day and night travel time are not same because of with the same term of annual equal installment and variable
heavy vehicles are allowed to travel night only in major urban installment.
places. It is found from field studies that vehicle speed reduces at 3. Linear and non linear depreciation methodologies are consid-
night if anti glare screen is not installed on the median of divided ered.
carriageways. Presently anti glare screens are installed on several 4. Land acquisition cost is borne by the Government .
four/six lanes roads in India. VOC are lower at higher speed and 5. The cash flows during construction are predestinated.
vice versa. VOC saving is defined as VOC base case (Existing 6. The toll rate vehicle mode wise is fixed using VOC savings
two upgraded to two lanes providing overlay, pot hole repair etc.) obtained from economic analysis results.
- VOC of improved case (up gradation and improvement of two 7. Complete depreciation of the Total Project Cost (TPC) is
lanes two four lanes).Toll rate is fixed by certain percentage of allowed during the operation period.
VOC saving. It is found from economic analysis using HDM 4
VOC. With higher speed VOC is lesser but IRR, NPV are higher. 4. Theoretical Framework
Thus toll rate increases.
Based on present need of research work, the following points Ranasinghe (1996) has developed a simplified model to
are highlighted in this paper: calculate TPC for infrastructure projects in developing countries,
• Selection of appropriate percentage of VOC savings to which is the starting point of the (Bakatjan et al., 2003) financial
determine toll tariff vehicle mode wise for financial analysis analysis and the equation has been modified considering mainte-
• Development of theoretical framework for repayment sched- nance cost during construction and presented in the following
ule for various methods (equal and variable repayment sched- Eq. (1):
ules) with different depreciation methods (Straight line and
TPC = BC + EDC + IDC + MCDC (1)
Written Down Value Methods)
• Development of model to maximize NPV based on some Where,
financial constraints like minimum proportion of equity, FIIR BC: The base cost or constant value cost of the project
>Discount rate etc. estimated at market prices of a predetermined year
• Selection of the best method of repayment schedule which EDC: The cost escalation during construction
maximizes the profit of the concessionaire for a project IDC: The interest rate during construction
A real case study has been considered for economic and MCDC: Maintenance cost during construction
financial analysis.
After the completion of construction, revenue is generated
from toll during the operation period, which is fixed based on
2. Formulation of Financial Model
technical viability of the project. The net annual cash available in
current value is given by NCAi, can be estimated as:
A financial model is a mathematical expression of relation-
ships among financial components. It is used to support decision NCAi = PBITi − TAXi + DEPi − Di for i = 1, 2, ···, m (2)
making in project evaluation. The project viability is analyzed
Where,
from the equity holders’ perspective in the project. The first step
DEPi: Depreciation
in any investment evaluation is to gather the appropriate informa-
Di: Annual Debt Installment for ith year
tion on the project costs and calculate the cash flows generated by
PBITi: Profit Before Interest and Tax
that project. In the simplest terms, the cash flow is the difference
TAXi: Tax
between the money coming in and the money going out of the
investment project. ‘‘Every investment opportunity can be fully TAXi = (PBITi − INTi). TAXi = Tax Rate for i = 1,2, ···, m (3)
described by the cash flow that it generates’’ (Marshall and
Where,
Bansal, 1992). The certainty of cash flow determines risk associ-
INTi: interest to be paid in the ith year
ated with the investment opportunity. In order to calculate the
value of a project over a number of years, after the estimation of Debt is assumed to be repaid in two methods as mentioned
the cash flows, one needs to take into account the time value of below to find out best one.
money. It is a basic principle of finance that money has time value. • Equal Installment (Variable repayment of debt principal)
• Variable Installment (Fixed debt principal repayment system)
3. Assumptions and Theoretical Framework Repayment schedule has been computed in excel sheet.
Repayment − Equal Installment
The following assumptions have been made for the model:
1. The financing of a project is raised by a combination of equity Let r be the interest rate of debt and P be the debt amount.
and debt. The net cash flow during the construction period is Repayment schedule is shown in Table 1.

− 1106 − KSCE Journal of Civil Engineering


Uses of Anti Glare Screen Barrier in Economic, Financial Analysis and Determination of Optimal Debt Capacity Ratio for a Road Project

Table 1. Repayment Schedule for Equal Installment


Year Capital/Outstanding Interest Debt Amount
1 P Pr D-Pr
2 P(1+r)-D [P(1+r)-D]r D-[P(1+r)-D]r=(D-pr)(1+r)
3 P(1+r)2-D(1+r)-D [P(1+r)2-D(1+r)-D]r D-[P(1+r)2-D(1+r)-D]r=(D-Pr)(1+r)2
4 P(1+r)3-D(1+r)2-D(1+r)-D [P(1+r)3-D(1+r)2-D(1+r)-D]r D-[P(1+r)3-D(1+r)2-D(1+r)-D]r=(D-Pr)(1+r)3
# # # #
n P(1+r)n-D(1+r)n-1 ··· D(1+r)-D [P(1+r)n-D(1+r)n-1 ··· D(1+r)-D]r D-[P(1+r)n-D(1+r)n-1 ··· D(1+r)-D]r=(D-pr)(1+r)n-1

Table 2. Repayment Schedule for Unequal Installment (Equal Debt Repayment)


Year Capital/Outstanding Interest Debt Principal Total Installment
1 P Pr P/n P(1/n +r)
2 P- P/n (P- P/n)r P/n P(1/n +r-r/n)
3 P- 2(P/n) [P- 2(P/n)]r P/n P[(1/n +r-2(r/n)]
# # # # #
j P-j(P/n) [P-j(P/n)]r P/n P[(1/n +r- (r-1)/n]

Let n be the year for repayment of debt amount. income and provides an annual tax advantage equal to the
At n th year outstanding /Capital will be zero. Hence, product of depreciation and the (marginal) tax rate, but it does
not lead to a cash outflow from the company. The most common
P(1 + r)n − D(1 + r)n-1 − D(1+r)n-1 ··· D(1 + r) - D = 0 (4)
method for depreciation is straight-line depreciation. Under this
Or method, annual depreciation equals a constant proportion of the
n n–1 n–1 D ( 1 + r ) – 1-
n
initial investment. In this model, it is assumed that TPC can be
P(1 + r) = D (1 + r ) + D (1 – r) ··· + D (1 + r ) + D = ---------------------------
1+r–1 depreciable in its entirety. Thus,
(5)
TPC
Or DEPi = ----------- for i = 1, 2, 3 (10)
n m
D(1 + r) – 1
P(1 + r)n = ----------------------------- (6)
r Where, m is the operation period and DEPi is depreciation for
n each year
D[(1 + r) – 1]
Hence, Pr = ---------------------------------
n
(7)
(1 + r) 5.2 Written Down Value Method
Debt at the year j = (D - Pr)(1+r) j-1 (8) Under this method, depreciation is calculated in accordance
with the following equation (Chandra, 2008):
Putting the value of Pr, value of debt reduces to the form as
shown below: DEP1 = BV0 r0
(1 + r) – 1
n DEP2 = BV0 r0 ( 1 – r0 )
- ( 1 + r )j – 1
Dj = D 1 – ----------------------- (i – 1)
(1 + r)
n DEPi = BV0 ( 1 – r0 ) r0 (11)
–( n – j + 1 )
Dj = D ( 1 + r ) (9) Where,
BV: TPC
This is the basic equation of debt repayment schedule of a
DEP: Depreciation charge
project when equal installment shall be repaid by the conces-
r0: Depreciation
sionaire.
Both the above mentioned methods are used to find out the
Repayment - Equal Debt Principal i.e.,
best one.
Variable Installment Each Year
Let P be the principal and it will be repaid in n variable install- 5.3 Maintenance Cost during Construction
ments. Installment is variable due to constant debt repayment. Maintenance cost during construction includes repair of pothole,
Debt amount to be paid=P/n. Detail calculation is shown in patch, thin overlay, construction of diversion etc. These costs are
Table 2. included in the financial analysis.

5. Depreciation 5.4 Operation and Maintenance Cost


Operation and Maintenance (OM) cost includes personnel
5.1 Straight Line Method salaries, indirect costs, insurance cost, and OM of road cost. These
Depreciation is a noncash expense. It only reduces taxable costs are calculated separately and used in financial model.

Vol. 16, No. 7 / November 2012 − 1107 −


Swapan Kumar Bagui and Ambarish Ghosh

5.5 Formulation of Linear Programming Model entrusted with the development, maintenance and management
Linear Programming (LP) models are extensively used in of such of the highways as entrusted to it by Government, the
capital budgeting (Park and Sharpe-Bette, 1990). The objective Government have decided to convert some of the existing two
is to maximize NPV/IRR, ‘‘the best way to compute a rate of lanes highways into four lanes highways.
return for an investment.’’ (Marshall and Bansal, 1992). In this National Highway (NH) No. 4, running between Mumbai –
model, optimal capital structure is the mix of debt and equity that Pune – Satara – Kolhapur to Kagal – Maharashtra State Border is
maximizes NPV/IRR from the equity holder’s point of view, an important highway in western Maharashtra (NHAI 2000).
with the following constraints: The project road passes through three Districts viz. Satara,
1. Minimum equity amount allowed by legislation is 10-20%. It Sangli and Kolhapur in the State of Maharashtra. About 46 km
varies country to country depending on Government’s policy. (592-638 km) of project road is under Kolhapur district, 32 km
2. IRR must be greater than the discount rate. In other words, (638-670 km) is under Sangli district and remaining 55 km (670-
NPV must be positive. 725 km) is under Satara district. Some portion has been con-
3. PBIT should be always greater than zero, for financial viabil- sidered as a case study (605 to 616 km). Flow Chart 1 shows the
ity of the project. detail methodology.
4. Average DSCR should be at least equal to 1.5. DSCR in the
range of 1.10 to 1.25 is Bankable, 1.30 to 1.50 is satisfactory 6.2 Economic Analysis
and comfortable, and above 1.50 is preferable. Minimum A case study has been adopted considering following cases for
DSCR should be 1.0. economic analysis:
The view point of equity holders is focused on the project Case 1: Base Case-Maintain existing two lanes road to two
metrics, Financial Internal Rate of Return (FIRR) and NPV. The lanes providing do minimum. Vehicle speed of base case
FIRR and NPV are the most common and fundamental financial is taken 30 kmph
decision making parameters employed in practice (Lohmann, Case II: Widening of existing two lanes road to four lanes road
1988). without providing anti glare screen barrier. Vehicle speed
The objective is to maximize NPV. In this model, optimal of this improvement case is taken 80 kmph
capital structure is the mix of debt and equity that maximizes Case III:Widening of existing two lanes road to four lanes road
NPV from the equity holder’s point of view, with the following with providing anti glare screen barrier. Vehicle speed
constraints is proposed for the case study: of this improvement case is taken 100 kmph
1. Minimum equity amount allowed is 10%
2. FIRR must be greater than the discount rate 6.3 HDM Input Requirements
3. PBIT should be always greater than zero for financial viability The basic input files required to run HDM-4 (Kerali, 2000)
of the project software for economic analysis are:
4. Average Debt Service Coverage Ratio (DSCR) should be at • Road Network
least equal to 1.6 • Vehicles Fleet
5. Toll rate of vehicle mode wise is fixed based on VOC saving • Road Works
vehicle mode wise • HDM Configuration

5.6 The Linear Programming Model 6.3.1 Road Network


A real case study has been considered based on present experi- Following field data have been collected according to the
ence of a few ongoing BOT projects in India. Minimum equity is requirement of inputs for HDM-4 for project analysis.
10%, FIRR of concessionaire shall be greater than discount rate The road network input file has been prepared as a two lanes
and minimum average Debt Service Coverage Ratio is 1.6. road link with 7 m carriageway and 1.50 m earthen shoulder and
These values are used to formulate the following linear program- 11 km length. Road classification, speed flow pattern, surface
ming model. These values should be varied from project to type etc. were recorded.
project depending on the need of the project. Pavement data include Pavement Condition, Roughness,
Benkelman Beam Deflection, Axle loads, and the thickness of
Objective function: Maximize NPV=f(E)
pavement compositions. Average condition data of the entire
Subject to E≥0.10, IRR≥Discount Rate, NPV≥0, and Average
section has been carried out and used for economic analysis.
DSCR≥1.6.
Where f(E): Function of equity. 6.3.2 Vehicles Fleet
Information on classified Traffic Volume, speeds, growth rate
6. Case Study factors etc. have been collected from the field study. Average
Annual Daily Traffic (AADT) was 7500.
6.1 Project Background The basic details of motorized vehicles as well as economic
The National Highways Authority of India (NHAI) has been costs related to motorized vehicle fleet used in the analysis are

− 1108 − KSCE Journal of Civil Engineering


Uses of Anti Glare Screen Barrier in Economic, Financial Analysis and Determination of Optimal Debt Capacity Ratio for a Road Project

Table 3. Preliminary Project Cost Case – 3 Improvements Option


Improvement Option
Economic Cost Widening of existing two lanes road to four lanes road along
(Rs Million) per km with routine maintenance-annually, functional overlay – every
Two lanes to Four Lanes fifth year and structural overlay -every tenth year with providing
a) Without anti glare screen barrier 46 anti glare screen barrier.
a) With anti glare screen barrier 47
6.3.3.5 Speed
recommended by Central Road Research Institute (CRRI) HDM Speeds of vehicles are considered 100 km/hr for day time.
Training manual, 2000. Night speed is taken 80 and 100 km/hr for without anti glare
screen barrier and with anti glare screen barrier on the median
6.3.3 Road Works respectively. Base case speed was found 30 km/hr from field
6.3.3.1 Costing investigation.
Preliminary project cost has been determined based on
pavement design, widening of the road from two lanes to four 6.3.4 HDM Configuration Files
lanes with and without providing anti glare screen barrier and To represent the actual field condition, traffic flow pattern,
shown in Table 3. Rate analysis of each item has been calculated Climatic and Speed flow type configuration files are prepared.
based on standard data book, 2000. Traffic flow pattern file created by deriving 24 hours traffic
volume to represent the peak and off-peak hour traffic flow
6.3.3.2 Maintenance and Rehabilitation Alternative pattern.
The various routine and schedule maintenance are considered
which consist of annual maintenances, functional and structural 6.3.5 Economic Analysis Results
overlay. Economic analysis has been carried out using HDM 4 software
and results are shown in Table 4.
6.3.3.3 Project Analysis
An economic analysis is conducted with a discount rate of 12 6.4 Financial Analysis
percent as recommended by World Bank. The financial analysis has been carried out to evaluate the
financial strength of the project from an investor's point of view.
6.3.3.4 Pavement Management at Project Level Obviously, the exercise presumes that the 4-lane highway is an
Project level pavement management analysis is carried out for economically viable option. In this exercise, all the costs and the
the following cases: benefits are based on the market prices.

Case – 1 – Base Option – Do Minimum 6.5 Costs


This case consists of routine maintenance-annually, functional The costs to be considered for commercial viability analysis
overlay – every fifth year and structural overlay every -tenth consist of:
year. • Cost of construction
• Annual and periodic repair and maintenance cost
Case – 2 Improvements Option • Toll administration cost
Widening of existing two lanes road to four lanes road along
with routine maintenance-annually, functional overlay – every 6.5.1 Construction Cost
fifth year and structural overlay every - tenth year without The construction costs ( Widening of two lanes to four lanes
providing anti glare screen barrier. road of 11 km length) for the road is calculated and base cost

Table 4. Results of Economic Analysis


Transportation costs and Savings (Rs/km)
Toll Rate
3 Axle Truck Bus 2 axle LCV* Multiaxle Car
Base Case VOC Cost 14.18 18 9.5 7 20 5.9
Without Anti Glare Screen Barrier VOC Cost 10.5 7.55 5.15 4.5 13.53 2.33
With Anti Glare Screen Barrier VOC Cost 10.3 6 4.9 4.3 10.3 2.7
VOC Saving for Without Anti Glare Screen Barrier 3.5 10.45 4.35 2.5 6.47 3.57
VOC Saving for With Anti Glare Screen Barrier 3.7 12 4.60 2.70 7.1 3.80
Toll charge as approximate percentage of saving 40 % 15% 40% 40% 40% 15%
Toll rate- Without Anti Glare Screen Barrier (Rs/km) 1.4 1.6 1.6 1.0 2.5 0.50
Toll rate- With Anti Glare Screen Barrier (Rs/km) 1.5 1.8 1.80 1.1 2.85 0.55
Note :* LCV:Light Commercial Vehicle

Vol. 16, No. 7 / November 2012 − 1109 −


Swapan Kumar Bagui and Ambarish Ghosh

with the provision of anti glare screen barrier found Rs. 47


million per km. Total cost of bypass=11×47=Rs 517 million
(USD 1=Rs 40).

6.5.2 Maintenance Cost


This cost is taken as Rs 0.23 million per km based standard
Maintenance Norm (Government of India). So total annual main-
tenance cost Rs 11×0.23 million =Rs 2.53 million.

6.5.3 Periodic Maintenance


Functional overly in the form of 40 mm bituminous concrete Fig. 1. TPC as Function of Equity for Equal Repayment Schedule
to be provide every 5th year. Approximate cost=17×1000×0.04
×4175= Rs 2.84 million.
Total periodic strengthening overlay cost Rs 2.84×11=Rs. 31.2
million.

6.5.4 Structural Maintenance


Structural overly in the form of 40 mm bituminous concrete
and 50 mm Dense Bituminous Macadam to be provide every
10th year. Approximate cost=17×1000×0.04×4175+17×1000×
3700=Rs 5.93 million.
Total periodic strengthening overlay cost Rs 5.93×11=Rs. 66.84
Fig. 2. FIRR (Promoter) as Function of Equity for Equal Repay-
million.
ment Schedule

6.5.5 Toll Administrative Cost


Toll administrative cost consists of salary of toll collectors,
security guards, labour, accountants, toll manager, bill of
electricity, expenses of generator. This cost has been found Rs 3
million per year.
An annual inflation has been calculated based on Consumer
Price Index (CPI).
Toll rates have been calculated based on economic analysis
and shown in Table 4. Fig. 3. NPV as Function of Equity for Equal Repayment Schedule

6.6 Financial Analysis


6.6.1 Mathematical Calculation for Cash Flows
Financial analysis has been carried out taking various percent-
ages of equities. TPC, NPV, IRR and DSCR are calculated and
presented in the graphical forms with best fit linear equation and
shown in Figs. 1 to 4 for equal installment schedule with linear
depreciation of construction cost. Similar figures are developed
for calculation of NPV, IRR and DSCR for variable installment
schedule i.e., repayment of fixed debt with linear depreciation.
Linear programming equations for both cases are as follows: Fig. 4. Average DSCR as Function of Equity for Equal Repayment
Schedule
6.6.2 Case 1: Equal Installment Schedule
Maximize
Based on these conditions, linear programming-Simplex Method
NPV = -5.2285 E + 664.86 (12) has been applied (Kapoor 1999). Detail calculation is shown in
Appendix 1. Final values are reported as:
Subject to:
Equity = 8.85% and maximum NPV = Rs 568.3 Million.
E ≥ 10%, DSCR ≥ 1.6, NPV ≥ 0
FIRR = −0.1223E + 32.862 (13) 6.6.3 Case 2: Unequal Installment Schedule
DSCR = 0.0357E + 0.9273 (14) Maximize

− 1110 − KSCE Journal of Civil Engineering


Uses of Anti Glare Screen Barrier in Economic, Financial Analysis and Determination of Optimal Debt Capacity Ratio for a Road Project

NPV = -9.01E + 670.4 (15) NPV = − 8.07E + 682.1 (22)


AVDSCR = − 0.0029E + 1.5644 (23)
Subject to: E ≥ 10%, DSCR ≥ 1.6, NPV ≥ 0
NPV is maximized and equity percentage is found out 12.3%,
FIRR = − 0.15323E + 29.899 (16)
NPV is Rs 582.84 million and FIRR value is 29.48%. Optimal
DSCR = 0.0029E + 1.5644 (17)
debt equity is=7.13.
By Simplex Method, E = 12.5%
DSCR = 0.0029 × 12.5 + 1.5644 = 1.60066 7. Mathematical Calculation for Cash Flows with-
NPV = 557.78 out Use of Anti Glare Screen Barrier
FIRR = −0.15323E + 29.899 = − 0.15323 × 12.5 + 29.899
= 27.984. In the similar manner financial analysis has been carried out
Discount Rate = 15 × (1 − .125) + 20×0.125 = 13.43,Hence ok. for various methods and shown in Table 5 for comparisons.
Optimal debt equity ratio = (1 − 0.125)/0.125=7. From Table 5, it is found that equal installment with Written
Down Depreciation Method i.e., case 3 is the best suitable
6.7 Equal Repayment Installment with Written Down Value method from equity point of view. So Case 3 is the best method
Depreciation Method from equity holder point view. So case 3 i.e., equal installment
Financial analysis is carried out taking variable depreciation with Written Down Depreciation Value is recommended for
and summary of the results are shown in the form of linear consideration.
equation as follows: Typical Cash flow diagrams are prepared at optimum equity

FIRR = − 0.141E + 37.2 (18)


NPV = − 4.845E + 722.6 (19)
DSCR = 0.0408E + 0.8947 (20)
NPV is maximized and equity percentage is found out 17.3%,
NPV is Rs. 638.78 million and FIRR value is 34.8%. Optimal
debt equity ratio is 4.78.

6.8 Unequal Repayment Installment with Written Down


Value Depreciation Method
Following equations have been developed:
Fig. 5. Revenue/Cash Flow/Maintenance Cost vs. Concession Period
FIRR = −0.1503E + 31.33 (21) (Equal Installment & Linear Depreciation)

Table 5. Summary of the Financial Results


With Anti Glare Screen Barrier Without Anti Glare Screen Barrier
Cases
Equation Remarks Equation Remarks
FIRR=30.56% FIRR=28.82%
Case1 –Equal installment FIRR=-0.1223E+32.862 NPV=568.3 FIRR=-0.1021E+30.966 NPV=541.59
with linear depreciation of NPV=-5.2285EE+664.6 DSCR=1.6002 NPV=-5.01 E+645.8 DSCR=1.6005
cost DSCR=0.0357E+ 0.927 E=18.85% DSCR=0.034E+ 0.8933 E=20.8%
D/E=4.30 D/E= 3.81
FIRR=27.98% FIRR=23.4%
Case2 –Unequal installment FIRR=- 0.1532E+29.9 NPV=557.8 FIRR=- 0.1474E+28.84 NPV=269
with linear depreciation of NPV=-9.01 E+670.4 DSCR=1.600 NPV=-9.03E+602.8 DSCR=1.6008
cost DSCR=0.0029E+ 1.56 E=12.5% DSCR=0.0028E+ 1.4972 E=36.9%
D/E=7.0 D/E=1.7
FIRR=34.8% FIRR=33.1%
FIRR=-0.141E+37.2 NPV=638.78 FIRR=-0.1294E+35.586 NPV=567.26
Case 3 –Equal installment
NPV==-4.845E+722.6 DSCR=1.6005 NPV=-4.33E+649.53 DSCR=1.601
with Variable depreciation
DSCR=0.0408E+0.8947 E=17.27% DSCR=0.039E+0.86 E=18.9%
D/E=4.78 D/E=4.26
FIRR=29.48% FIRR=26.8%
FIRR=-0.1503E+31.33 NPV=582.84 FIRR=-0.151E+30.24 NPV=443.27
Case 4 –Unequal installment
NPV=-8.07E+682.1 DSCR=1.6003 NPV=-7.79E+622.46 DSCR=1.602
with Variable depreciation
DSCR=-0.0029E+1.564 E=12.29% DSCR=0.0035E+1.5211 E=22.97%
D/E=7.13 D/E=3.35
Note: Value of NPV in Rs million

Vol. 16, No. 7 / November 2012 − 1111 −


Swapan Kumar Bagui and Ambarish Ghosh

Fig. 6. Revenue/Cash Flow/Maintenance Cost vs. Concession


Period (Equal Installment & Written Down Depriciation)

Flow Chart 1 Economic and Financial Analysis for Case Study


Fig. 7. Revenue/Cash Flow/Maintenance Cost vs. Concession
Period (Unequal Installment & Linear Depreciation) a divided carriageway to reduce glare and reduce economic
loss.
• Provision of anti glare screen barrier is economically and
financially viable so it can be installed to protect glare.

On Financial Analysis
• Total project cost is a function of equity with negative slope.
It varies Rs 828 million to Rs 686 million.
• Financial internal rate of return decreases with increase of
equity percentage. It varies 23.4 % to 34.8 %.
• An average debt service coverage ratio increase with
percentage increase of equity. It varies from 1.600 to 1.062.
Fig. 8. Revenue/Cash Flow/Maintenance Cost vs. Concession • Optimum debt equity ratio can be determined using present
Period (Unequal Installment & Written Down Depriciation) proposed model. It varies from 1.7 o 7.13.
• Net present value has negative slope for equal installment
for various repayment schedule and illustrated in Fig. 5 to Fig. 8. payment and unequal payment schedule. It Varies from Rs
269 million to Rs 638.8 million.
8. Conclusions • Repayment schedule can be compared with equal and
unequal repayment schedule.
Following conclusions may be drawn from the analysis and • Concessionaire maximizes his profits based on repayment
discussion presented in this paper: schedule as calculated.
On Economic Analysis • Linear Programming model can be prepared taking real
• Night speed has been decreased (80 kmph) due to absence of values of equity, financial internal rate of return, net present
anti glare screen barrier. This decreases vehicle operating value and average debt service coverage ratio.
cost saving and reduces chargeable toll rate. • Maximum financial internal rate of return is found for the
• Toll rates are found different with and without provision of case of equal repayment schedule with Written Down Value
anti glare screen barrier cases. This values are reported in depreciation method for the present case study. Maximum
table 4. It varies Rs 1.4 to Rs 1.5 for 3 axle vehicle. NPV and FIIR are found Rs 638.8 million and 34.8%
• Anti glare screen barrier should be provided on the median of • Concessionaire maximizes his profits based on repayment

− 1112 − KSCE Journal of Civil Engineering


Uses of Anti Glare Screen Barrier in Economic, Financial Analysis and Determination of Optimal Debt Capacity Ratio for a Road Project

schedules as calculated using four cases. simplex table is formed by writing down the coefficients and
constraints of linear programming problem in a systematic
References tabular form. The rule for the construction of the initial simplex
is same in both the maximization and minimization problems.
Ali Şentürk, H., Yazici, G., and Burçin Kaplanoğlu, S. (2004). “Case Minimization problem has been discussed herein.
study: Izmit domestic and industrial water supply build-operate-
transfer project.” Journal of Constr. Engrg. and Mgmt., ASCE, Vol. Consider the general linear programming problem:
130, No. 3, pp. 225-234.
Minimize Z=c1x1+c2x2+ ··· +cnxn (24)
Bagui, S. K. and Ghosh, A. (2009a). “Financial analysis for providing
anti glare screen and selection of future widening scheme to avoid Subject to the constraints
glare.” Seminar on Public Private Partnership in Highway Sector a11x1+a12x2+ ··· a1nxn≥b1
28-29 August 2009, Organised by Indian Roads Congress, New a21x1+a212x2+ ··· a21nxn≥b2
Delhi.
Bagui, S. K. and Ghosh, A. (2009b). “Selection of toll tariff, debt equity #
ratio and concession period for a BOT project.” Seminar on Public am1x1+am2x2+ ··· amnxn≥bm
Private Partnership in Highway Sector 28-29 August 2009, Organized and x1,x2, ··· xn≥0
by Indian Roads Congress, New Delhi.
To convert inequalities into the equations, we subtract surplus
Bakatjan, S. A. M., Arikan, M., and Tiong, R. L. K. (2003). “Optimal
capital structure model for BOT power projects in Turkey.” Journal of
variables and the above problem reduces to the form:
Construction Engineering and Management, ASCE, Vol. 129, No. Minimize Z=c1x1+c2x2+ ··· +cnxn+0s1+0s2+ ··· +0sn (25)
1, pp. 89-97.
Chandra, P. (2008). Financial management, theory and practice 7e. Subject to the constraints
CFM-Mc graw –Hill professional series in Finance, Published by a11x1+a12x2+ ··· a1nxn-s1=b1
Tata McGraw –Hill Publishing Company Limited. a21x1+a212x2+ ··· a21nxn-s2=b2
Dias, A. and Ioannou, P. G. (1995). ‘‘Debt capacity and optimal capital #
structure for privately financed infrastructure projects.’’ J. Constr.
am1x1+am2x2+ ··· amnxn-sn=bm
Engrg. and Mgmt., ASCE, Vol. 121, No. 4, pp. 404-414.
Dias, A. and Ioannou, P. G. (1996). ‘‘Company and project evaluation and xj ≥ 0(j=1,2 ··· n);sj≥0(j=1,2 ··· m)
model for privately promoted infrastructure projects.’’ J. Constr. An initial basic solution is obtained by setting:x1=x2 ··· xn=0.
Engrg. and Mgmt., ASCE, Vol. 122, No. 1, pp. 71-82.
Thus, it can be found
Kapoor, V. K. (1999). Operation research, Sultan Chand & Sons
Educational Publisher, New Delhi. s1=-b1, s2=-b2, ··· sm=-bm.
Kerali, H. R. (2000). Highway development and management (HDM-4),
Vol. 1-Over View of HDM 4, World Bank, pp. 2-25. Which is not feasible because it violates the non-negativity
Lohman, J. R. (1988). “The IRR, NPV and the fallacy of the reinvest- restrictions (i.e., si≥0). Therefore slight modifications are required
ment rate assumption.” Egg. Econ., Vol. 33, No. 4, pp. 303-330. in Simplex Algorithim. Introducing now into the system of con-
Malini, E. (1997). ‘‘Evaluation of fnancial viability of BOT transport straints (**), m new variables A1, A2, ··· Am, known as artificial
infrastructure projects.’’ J. Indian Road Congress, Vol. 58, No. 1, pp. variables one to each equation. The resulting system of the
87-123.
equations can be written as follows:
Marshall, J. F. and Bansal, V. K. (1992). Valuation relationships and
applications, Financial Engineering, Institute of Finance, Allyn and a11x1+a12x2+ ··· a1nxn-s1+A1=b1
Bacon Inc., New York. a21x1+a212x2+ ··· a21nxn-s2+A2=b2 (26)
NHAI (2000). Feasibility study and detailed engineering for satra kagal #
section of NH 4 from km 592.240 to km 725.000, Government of
am1x1+am2x2+ ··· amnxn-sn+Am=bm
India, New Delhi.
Park. C. S. and Sharp-Bette, G. P. (1990). Advance engineering economy, and xj≥0(j=1,2 ··· n); sj≥0(j=1,2 ··· m), Aj≥0(j=1,2 ··· m)
Wiley, New York. Thus the standard linear programming problem has reduced to
Ranasinghe, M. (1996). “Total project cost: A simplified model for
a system of m equations in n+m+m(n decision variables surplus
decision makers.” Journal of Construction Management Econom.
Vol. 14, No. 5, pp. 497-505.
variables artificial variables).An initial basic feasible solution
Tiong, R. L. K. (1995). “Competitive advantage of equity in BOT can now be obtained by setting n+2m-m variables equal to zero
project.” Journal of Construction Engineering and Management, which is given by :A:=b1, A2=b2, ··· Am=bm.
ASCE, Vol. 121, No. 3, pp. 282-289. This however, does not constitute a solution to the original
system of equations because two systems of equations are not
Appendix 1. Simplex Method equivalent. Therefore, to derive the artificial variables out of the
solution a very large value (M) id assigned to each of the
Computational procedures in the simplex method require the artificial variables and a zero value to each of the surplus
construction of simplex table which can be done different ways, variables are the coefficient value in the objective function.
all of which, however, led to the same optimum solution. Initial Therefore, the problem can now be written as follows:

Vol. 16, No. 7 / November 2012 − 1113 −


Swapan Kumar Bagui and Ambarish Ghosh

Minimize Z=c1x1+c2x2+ ··· +cnxn+0s1+0s2+ ··· +0sn+MA1 Maximize:


+MA2+ ··· +MAm (27) 666.86-5.2285E
Subject to the constraints Alternatively,
a11x1+a12x2+ ··· a1nxn-s1+A1=b1
Minimize:
a21x1+a212x2+ ··· a21nxn-s2+A2=b2
5.2285E
#
am1x1+am2x2+ ··· -amnxn-sn+An=bm Subject to:
and xj ≥ 0(j=1,2 ··· -n); sj≥0(j=1,2 ··· m), Aj≥0(j=1,2 ··· m) E ≥ 10
E-S1+A1=10 (28)
The modified simplex method for solving a L.P. problem,
666.86-5.2285E ≥ 0
when a high penalty cost or profit M has been assigned to the
5.2286+S2=666.86 (29)
artificial variables is sometimes known as the Big M Method or
0.0357E+0.9273≥1.6
Penalty Method.
0.0357E-S3+A2=0.6727 (30)
Simplex Method has been used to solve the problem.

Based on this Simplex Tables are developed and mentioned below :


Cj Basic Solution 5.2285 0 0 0 M M Minimum
CB Variable Variable x1 S1 S2 S3 A1 A2 Ratio
M A1 10 1 -1 0 0 1 0 10
M A2 666.86 5.2285 0 1 0 0 0 127.5433
0 S2 0.6727 0.0357 0 0 -1 0 1 18.84314
Zj 5.332M -M M 0 M 0
Z= Cj- Zj 5.332M-5.2285 M -M 0 -M 0

Cj Basic Solution 5.2285 0 0 0 M M Minimum


CB Variable Variable x1 S1 S2 S3 A1 A2 Ratio
5.2285 x1 10 1 -1 0 0 1 0 -10
M A2 614.575 0 5.23 1 0 -5.2285 0 117.54
0 S2 0.3157 0 0.04 0 -1 -0.0357 1 8.84
Zj 5.2285 5.2285M-.5.2285 M 0 .1223-4.33M 0
Z= Cj- Zj 0 .1223-4.334M -M 0 3.33M-.1223 M

Cj Basic Solution 5.2285 0 0 0 M M Minimum


CB Variable Variable x1 S1 S2 S3 A1 A2 Ratio
5.2285 x1 18.85 1 0 0 -28.01 0 28.01
0 S1 568.34 0 0 1 146.46 0 -146.46
0 S2 8.85 0 1 0 -28.01 -1 28.01
Zj 5.2285 0 0 -146.46 0 146.46
Z= Cj- Zj 0 0 0 146.46 M M-166.45

− 1114 − KSCE Journal of Civil Engineering

View publication stats

You might also like