This document provides a bill of quantities and cost breakdown for constructing a temporary latrine under a humanitarian assistance program in Somalia. It lists the materials, labor, and costs associated with excavating the pit, constructing retaining walls, a concrete cover slab, floor, superstructure walls and roof made of iron sheeting and wood. It also includes doors, painting, and plastering. The total cost is calculated for building one latrine, as well as scaling up to construct twenty-four latrines.
This document provides a bill of quantities and cost breakdown for constructing a temporary latrine under a humanitarian assistance program in Somalia. It lists the materials, labor, and costs associated with excavating the pit, constructing retaining walls, a concrete cover slab, floor, superstructure walls and roof made of iron sheeting and wood. It also includes doors, painting, and plastering. The total cost is calculated for building one latrine, as well as scaling up to construct twenty-four latrines.
This document provides a bill of quantities and cost breakdown for constructing a temporary latrine under a humanitarian assistance program in Somalia. It lists the materials, labor, and costs associated with excavating the pit, constructing retaining walls, a concrete cover slab, floor, superstructure walls and roof made of iron sheeting and wood. It also includes doors, painting, and plastering. The total cost is calculated for building one latrine, as well as scaling up to construct twenty-four latrines.
40cm thick semi-dressed masonry with cement mortar of
1:3 ratio up to 300cm deep below the NGL for the M3 3 retaining wall
2.1
30 cm thick dressed masonry with cement mortar 1:3 ratio
2.2 M3 1 minimum 30cm above the NGL for foundation
3 Concrete work
150mm thick cover slab (reinforced concrete) construction
for the pit hole with concrete mix 1:2:3 minimum cement 3.1 content 360kg/m3(bar#12mm both ways spacing at M3 1 200mm c/c including cutting, shaping into required design and tying from work include scaffolding
80mm thick mass concrete or mix 1:2:3 ratio minimum
3.2 cement content 360 kg/m3 applied to the floor of the M3 1 latrine, a hole is left for fixing connecting PVC pipe
4 Supper structure
Supply and installation of gauge 28 iron sheet as walling
4.1 of the pit latrine constructed 10-12 cm diameter eucalypts ml 7 tree for vertical 1m for supports
5 Roof wok
Supplying and installation of G-28 galvanized metal sheet
roofing, 10-12 cm diameter eucalypts tree for vertical 1m, horizontal truss, 8 cm diameter eucalypts tree for diagonal 5.1 truss, 5X7 cm purlin and anti-termite (burned oil), the ml 5 price include fixing all roofing materials as per the drawing. (Slope =30%)
6 Doors
45mm thick match boarded timber single door, overall size
6.1 900x 2100mm high complete with a padbolt and tower Pcs 1 bolt
6.2 Stainless steel hinges pair 3
Install 110 mm diameter PVC vent pipe with fly trap on 6.3 Pc 1 top 7 Painting and plastering work
Plastering interior to a smooth finish ready for painting
7.1 ml 14 and cement screed, with a cement mortar of 1:3 mix
Paint inside and outside of wall with two coats of emulsion