Gantt Chart

DURATION (WEEKS)

Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
(ACTIVITIES)
A. Development of
Ideas about Industrial
Process
B. Create Description
of the machine
C. Planning and
Designing of the
machine
D. Inquiring for the
components of the
machine
E. Developed marketing
analysis or the budget
F. Assembly and
Installation of the
Vitamin Syrup Filling
Machine
G. Design and
Evaluation of the
Software
H. Finalized
Installation
I. Test Operation
J. Troubleshooting and
Correction
K. Commissioning
L. Documentation
Activities Description Predecessor Duration (Weeks)
Development of Ideas about Industrial
A Process - 4

B Create Description of the machine - 4

C Planning and Designing of the machine A 5

D Inquiring for the components of the machine C 4

E Developed marketing analysis or the budget D 4


Assembly and Installation of the Vitamin
F Syrup Filling Machine E 7

G Design and Evaluation of the Software F 5

H Finalized Installation G 4

I Test Operation H 3

J Troubleshooting and Correction I 4

K Commissioning - 5

L Documentation K, J 5