Professional Documents
Culture Documents
Construction Contract
Construction Contract
Elisa Velazquez
Assistant Commissioner
Agency Chief
Contracting Officer
Volume 2 of 2
Contract Terms and Specifications
(with separate Bid Booklets)
December 2017
CITY OF NEW YORK
DEPARTMENT OF ENVIRONMENTAL PROTECTION
BUREAU OF ENGINEERING DESIGN & CONSTRUCTION
TABLE OF CONTENTS
Page No.
GENERAL CONDITIONS
1353
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
GENERAL SPECIFICATIONS
DIVISION 3 - CONCRETE
03100 Concrete Formwork ....................................................................................465
03210 Reinforcing Steel ........................................................................................479
03290 Joints in Concrete ........................................................................................498
03300 Cast-in-Place Concrete................................................................................511
03350 Concrete Finishes .......................................................................................593
03600 Grout ...........................................................................................................603
03931 Concrete Rehabilitation ..............................................................................611
DIVISION 4 - MASONRY
04051 Mortar and Masonry Grout .........................................................................623
04200 Unit Masonry ..............................................................................................631
DIVISION 5 - METALS
05061 Stainless Steel Work ...................................................................................649
05081 Galvanizing .................................................................................................661
05091 Welding .......................................................................................................669
05092 Metal Fastening ...........................................................................................679
05120 Structural Steel ............................................................................................689
ii
1354
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
DIVISION 9 - FINISHES
09740 Concrete Toppings ......................................................................................819
09900 Painting .......................................................................................................841
DIVISION 10 - SPECIALTIES
10200 Louvers .......................................................................................................865
10400 Identifying Devices .....................................................................................871
10521 Fire Extinguishers .......................................................................................883
DIVISION 15 - MECHANICAL
15060 Hanger and Supports .................................................................................1033
15076 Piping and Equipment Identification .......................................................1049
15081 Piping Insulation .......................................................................................1073
15720 Heating and Ventilation Units ..................................................................1087
15761 Heaters, Electric ........................................................................................1103
15810 Ductwork and Duct Accessories ...............................................................1117
15815 Duct Insulation ..........................................................................................1137
15830 Fans ...........................................................................................................1145
15951 Testing, Adjusting and Balancing .............................................................1163
iii
1355
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
DIVISION 16 - ELECTRICAL
16010 General Electrical Requirements ..............................................................1165
16020 Temporary Electrical Systems ..................................................................1171
16035 Demolition, Electrical ...............................................................................1179
16061 Grounding .................................................................................................1185
16071 Supporting Devices ...................................................................................1189
16076 Labeling and Identification .......................................................................1195
16121 Electric Wires and Cables .........................................................................1199
16131 Electric Conduit System ...........................................................................1217
16133 Underground Ducts - Ducts in Concrete ...................................................1239
16134 Electric Manholes .....................................................................................1245
16211 Electrical Service Entrance ......................................................................1251
16221 Electric Motors..........................................................................................1259
16231 Standby Power ..........................................................................................1279
16271 Dry Type Transformers.............................................................................1281
16281 Power Filters and Conditioners .................................................................1287
16292 Power Distribution System Coordination .................................................1297
16430 Low Voltage Switchgear...........................................................................1305
16441 Panelboards ...............................................................................................1319
16442 Electrical Control Equipment - Low Voltage A.C. Motors and
Devices ......................................................................................................1325
16491 Fuses .........................................................................................................1333
16511 Lighting Fixtures and Devices ..................................................................1337
- END OF VOLUME I -
iv
1356
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
DETAILED SPECIFICATIONS
1357
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
DETAILED SPECIFICATIONS
CONTRACT DEL-260G GENERAL
DIVISION 3 - CONCRETE
03100G Concrete Formwork ..................................................................................1769
03210G Reinforcing Steel ......................................................................................1771
03290G Joints in Concrete ......................................................................................1773
03300G Cast-in-Place Concrete..............................................................................1775
03350G Concrete Finishes .....................................................................................1781
03600G Grout .........................................................................................................1785
03931G Concrete Rehabilitation ............................................................................1787
DIVISION 4 - MASONRY
04051G Mortar and Masonry Grout .......................................................................1789
04200G Unit Masonry ............................................................................................1793
DIVISION 5 - METALS
05061G Stainless Steel Work .................................................................................1795
05081G Galvanizing ...............................................................................................1797
05091G Welding .....................................................................................................1799
05092G Metal Fastening .........................................................................................1801
05120G Structural Steel ..........................................................................................1803
05501G Metal Fabrications ....................................................................................1805
05524G Aluminum Pipe Railing ............................................................................1807
05533G Aluminum Floor Gratings and Checkered Plates .....................................1809
05561G Miscellaneous Metal Castings ..................................................................1811
vi
1358
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
DIVISION 9 - FINISHES
09740G Concrete Toppings ....................................................................................1823
09900G Painting .....................................................................................................1825
DIVISION 10 - SPECIALTIES
10200G Louvers .....................................................................................................1829
10400G Identifying Devices ...................................................................................1831
10521G Fire Extinguisher .......................................................................................1833
vii
1359
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
DETAILED SPECIFICATIONS
CONTRACT DEL-260H HVAC
DIVISION 3 - CONCRETE
03600H Grout .........................................................................................................1845
DIVISION 4 - MASONRY
04051H Mortar and Masonry Grout .......................................................................1847
04200H Unit Masonry ............................................................................................1851
DIVISION 5 - METALS
05081H Galvanizing ...............................................................................................1853
05091H Welding .....................................................................................................1855
05092H Metal Fastening .........................................................................................1857
05501H Metal Fabrications ....................................................................................1867
DIVISION 9 - FINISHES
09900H Painting .....................................................................................................1871
DIVISION 10 - SPECIALTIES
10200H Louvers .....................................................................................................1875
DIVISION 15 - MECHANICAL
15060H Hanger and Supports .................................................................................1901
15076H Piping and Equipment Identification .......................................................1913
15081H Piping Insulation .......................................................................................1923
15185 Hydronic Pumps........................................................................................1931
15515 Piping, Valves and Accessories ................................................................1939
15720H Heating and Ventilation Units ..................................................................1969
15761H Heaters, Electric ........................................................................................1981
15810H Ductwork and Duct Accessories ...............................................................1987
15815H Duct Insulation ..........................................................................................2001
viii
1360
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
DIVISION 16 - ELECTRICAL
16010H General Electrical Requirements ..............................................................2065
16076H Labeling and Identification .......................................................................2067
16121H Electric Wires and Cables .........................................................................2069
16131H Electric Conduit System ...........................................................................2073
16221H Electric Motors..........................................................................................2077
ix
1361
SHAFT 18 DA KENSICO ELECTRICAL AND HV UPGRADES
TABLE OF CONTENTS
DETAILED SPECIFICATIONS
CONTRACT DEL-260E ELECTRICAL
DIVISION 16 - ELECTRICAL
16010E General Electrical Requirements ..............................................................2089
16020E Temporary Electrical Systems ..................................................................2091
16035E Demolition, Electrical ...............................................................................2093
16061E Grounding .................................................................................................2095
16071E Supporting Devices ...................................................................................2097
16076E Labeling and Identification .......................................................................2099
16121E Electric Wires and Cables .........................................................................2101
16131E Electric Conduit System ...........................................................................2105
16133E Underground Ducts - Ducts in Concrete ...................................................2109
16134E Electric Manholes .....................................................................................2113
16211E Electrical Service Entrance ......................................................................2115
16221E Electric Motors..........................................................................................2121
16231E Standby Power ..........................................................................................2123
16271E Dry Type Transformers.............................................................................2149
16281E Power Filters and Conditioners .................................................................2153
16285 Surge Protective Devices (SPD) ...............................................................2155
16292E Power Distribution System Coordination .................................................2167
16361 Medium Voltage Load Interrupter Switchgear .........................................2173
16430E Low Voltage Switchgear...........................................................................2183
16441E Panelboards ...............................................................................................2189
16442E Electrical Control Equipment - Low Voltage A.C. Motors and
Devices ......................................................................................................2191
16482 Motor Control Center................................................................................2193
16491E Fuses .........................................................................................................2207
16496 Automatic Transfer Switches ....................................................................2209
16511E Lighting Fixtures and Devices ..................................................................2225
- END OF VOLUME II -
1362
DETAILED SPECIFICATION 01120 – MULTIPLE CONTRACT SUMMARY
CONTRACT DEL-260 G, H, E
SECTION 01120
Multiple Contract Summary
PART 1 GENERAL
1.01 NOTICE
The Contractors are advised that the Detailed Specifications of Division 1 – General
Requirements are applicable to all Contracts. Wherever the words “the Contractor” are
used, it shall be taken to mean “each Contractor”. Where an individual Contractor is
responsible for a particular item of Work, the Specifications shall specifically name that
Contractor.
A. Location of Work
F. Datum plane
1.03 DEFINITIONS
A. When specified in the Contract Documents, the term “General Contract”, “Electrical
Contract”, and “HVAC Contract” shall refer to the Contract for DEL-260G, DEL-260E
and DEL-260H, respectively.
A. Work under this Contract will be performed at the Shaft 18 Delaware Aqueduct (DA)
Site (Shaft 18). Shaft 18 is located in the Town of Mount Pleasant, Westchester
County, NY on City-owned property. Refer to the Contract Drawings for the Site
location map.
B. No activity or access of any kind shall be permitted to the Contractors beyond the limits
of Work shown on the Contract Drawings, except as directed by the Engineer.
01120-1 11/2017
1363
DETAILED SPECIFICATION 01120 – MULTIPLE CONTRACT SUMMARY
CONTRACT DEL-260 G, H, E
A. The following is general description of the principal Work items, and shall not be
construed as a complete description of the Work to be performed.
1. Installation of concrete pads for outdoor natural gas generator and switchgear
equipment.
2. Improvements to the existing electrical room allowing for required fire rated walls
and barriers.
A. The following is general description of the principal Work items, and shall not be
construed as a complete description of the Work to be performed.
1. Upgrade of the ventilation system for the chlorine storage room and the
chlorination room at Shaft 18 including air handling unit, fans, louvers, ductwork,
chlorine detectors, conduit and wiring.
A. The following is general description of the principal Work items, and shall not be
construed as a complete description of the Work to be performed.
01120-2 11/2017
1364
DETAILED SPECIFICATION 01120 – MULTIPLE CONTRACT SUMMARY
CONTRACT DEL-260 G, H, E
A. It is recommended that the prospective bidders visit the Site before bidding. Bidders
shall obtain all necessary information, and make its own determinations of any and all
conditions which may affect in any way the performance of its Work and its bid prices
under its Contract. All pertinent data and dimensions with regard to existing
construction shall be verified by the Contractor. Access to the Site for inspection
purposes prior to bidding will only be on the date advertised for the pre-bid tour.
A. All elevations, indicated or specified for refer to North American Vertical Datum 1988
(NAVD-88), unless otherwise noted.
A. Compliance with the latest versions of DEP EHS Policies, Procedures and Guidelines
is required on all DEP Contract Work.
END OF SECTION
01120-3 11/2017
1365
DETAILED SPECIFICATION 01120 – MULTIPLE CONTRACT SUMMARY
CONTRACT DEL-260 G, H, E
01120-4 11/2017
1366
DETAILED SPECIFICATION 01140 - WORK RESTRICTIONS
CONTRACT DEL-260 G, H, E
SECTION 01140
Work Restrictions
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any Work required under this
Section and the Contractor shall include all costs thereof in its lump sum price
bid for the Contract.
01140-1 11/2017
DEP 5/26/16
1367
DETAILED SPECIFICATION 01140 - WORK RESTRICTIONS
CONTRACT DEL-260 G, H, E
B. Contractor shall provide, erect and maintain catch platforms, lights, barriers,
weather protection, warning signs and other items as required for proper protection
of the public, occupants of the building, work persons engaged in operations and
adjacent construction.
C. Contractor shall provide and maintain weather protection at exterior openings so as
to fully protect the interior premises against damage from the elements until such
openings are closed by new construction.
D. Contractor shall provide and maintain temporary protection of the existing structure
designated to remain where new work is being done, connections made, materials
handled or equipment moved. Contractor shall be responsible for any damage to
the existing structure or contents by reason of providing insufficient protection.
E. Contractor shall take necessary precautions to control dust. Dust shall be prevented
from rising by wetting masonry, concrete, plaster and similar debris. Unaltered
portions of the existing buildings affected by the operations under this Section shall
be protected by dustproof partitions and other adequate means.
F. Contractor shall provide adequate fire protection in accordance with local Fire
Department requirements.
G. Contractor shall carry out all operations so as to avoid interference with operations
and work in the existing facilities and the work under other contracts. Refer to
Article 1.10 and 1.11 for additional facility requirements.
H. Contractor shall be solely responsible for making all necessary arrangements and
for performing all necessary work involving the discontinuance or interruption of
all utilities or services. Refer to Article 1.10 and 1.11 for additional facility
requirements.
I. Any equipment, piping and appurtenances disconnected without proper
authorization, and that are necessary for the operations of the existing or expanded
facilities, shall immediately be replaced to the satisfaction of the Engineer at no
cost to the City.
J. Closing or obstructing of roadways, sidewalks, and passageways adjacent to the
Work by the placement or storage of materials will not be permitted, and all
operations shall be conducted with minimum interference to traffic.
K. Contractor shall repair damage caused by his operations to facilities to remain, or
to any property belonging to the City or occupants of the facilities.
L. The Work shall comply with 29 CFR Part 1926 -- Safety and Health Regulations
for Construction, applicable provisions and recommendations of ANSI/ASSE A10
-- Construction and Demolition Safety Standards, all governing codes and rules,
and as specified herein or in the Detailed Specifications.
M. Contractor shall make such investigations, explorations and probes as are necessary
to ascertain any required protective measures before proceeding with Work.
01140-3 11/2017
DEP 5/26/16
1369
DETAILED SPECIFICATION 01140 - WORK RESTRICTIONS
CONTRACT DEL-260 G, H, E
N. Contractor shall be required to test for and mitigate hazardous materials impacted
in Work areas included in this Contract. Demolition and removal of hazardous
materials shall be in accordance with applicable Federal, State and Local
regulations.
01140-4 11/2017
DEP 5/26/16
1370
DETAILED SPECIFICATION 01140 - WORK RESTRICTIONS
CONTRACT DEL-260 G, H, E
E. Equipment, tools, and vehicles shall be prohibited from use until the City or
Resident Engineer is satisfied that the requirements of Articles 1.11.C and
1.11.Dabove have been met.
F. Comply with Rules and Regulations for the Protection from Contamination,
Degradation and Pollution of the New York City Water Supply and its Sources.
This document and documents incorporated by reference are available for
inspection and copying at the Department of Environmental Protection, Bureau of
Water Supply and Wastewater Collection, Division of Drinking Water Quality
Control, 465 Columbus Avenue, Valhalla, New York, 10595.
01140-5 11/2017
DEP 5/26/16
1371
DETAILED SPECIFICATION 01140 - WORK RESTRICTIONS
CONTRACT DEL-260 G, H, E
G. The Contractor shall have sufficient forms, shoring and other construction
materials; labor; permanent materials; equipment; tools and supervision available
to support a second shift and/or scheduled overtime.
H. When work is scheduled to be performed beyond the Normal Project Working
Hours, a second shift, at night or during weekends, the Engineer shall be informed
a minimum of 5 business days or other reasonable length of time specified by the
Engineer in advance of the beginning of such work. The Contractor shall adhere to
any local laws or ordinances that may govern or restrict the performance of such
work. Requirements for the provision and use of temporary light and power outside
Normal Project Working Hours are included in Section 01513 – Temporary
Electrical System.
01140-6 11/2017
DEP 5/26/16
1372
DETAILED SPECIFICATION 01140 - WORK RESTRICTIONS
CONTRACT DEL-260 G, H, E
1.15 ATTACHMENTS
A. Exhibit A - Local Law 77: DEP Monthly Reporting Forms
B. Exhibit B - Quality Assurance For Design and Construction of New and
Modified Risk Management Programs – Regulated Chlorine Processes
C. Exhibit C – Contractor Site Security Guidelines Water Supply Sites
END OF SECTION
01140-7 11/2017
DEP 5/26/16
1373
DETAILED SPECIFICATION 01140 - WORK RESTRICTIONS
CONTRACT DEL-260 G, H, E
01140-8 11/2017
DEP 5/26/16
1374
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
PAGE 1 OF 42 11/2017
DEP 5/26/16
1375
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
PAGE 2 OF 42 11/2017
DEP 5/26/16
1376
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
EXHIBIT B
PAGE 3 OF 42
1377 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
1. PURPOSE
This procedure establishes specific quality assurance (QA) requirements that shall be completed
during the execution of new construction projects on processes covered by EPA Risk
Management Programs (RMP) or equivalent OSHA Process Safety Management (PSM)
regulations. It outlines DEP’s approach to meet the regulatory requirements and ensure the
quality checks and inspections established by the contract specifications and drawings conform
to the applicable regulatory, code and other recognized standards for the type of work. It is
consistent with, but provides more detail than, the Mechanical Integrity section of the Process
Safety Management / Risk Management Program. These checks and inspections must be
completed, documented and placed into the Process Safety Information and Mechanical Integrity
Quality Assurance permanent records for the regulated facility. This procedure specifically
addresses 40 CFR 68.73(f)(1) and (2) of the following EPA RMP regulations (and equivalent
OSHA PSM regulations found at 29 CFR 1910.119(j)):
2. SCOPE
This procedure applies to all new construction or major modifications of RMP/PSM regulated
chlorination processes (e.g., replacement of all chlorinators/evaporators or installation of any
new chlorinators/evaporators that is not a replacement-in-kind) and addresses applicable
regulatory requirements, governing codes (Federal, State and Local) and other recognized
standards for the type of work (e.g., National Electric Code (NEC), Uniform Building Code
(UBC), National Fire Protection Agency (NFPA), American National Standards Institute
(ANSI), and Chlorine Institute (CI)). Existing construction projects (where design and
PAGE 4 OF 42
1378 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
construction specifications have already been issued for bids) must also meet the regulatory
requirements, but these projects may use alternative methods.
All modifications are reviewed under the Management of Change procedure and receipt
inspection is performed under the Mechanical Integrity program for maintenance materials, spare
parts and equipment for RMP/PSM regulated chlorine processes to address the requirements of
40 CFR 68.73(f)(3) above.
3. PROCEDURE
Fabrication and construction Quality Assurance requirements for specific chlorination process
equipment are summarized in Attachment A along with the primary codes and standards used as
the basis for design and Quality Assurance. Simpler checklists are also provided that may be
used by the design/construction project managers (Attachment B), the Bureau which owns and
operates the process (Attachment C) and the Contractor (Attachment D, E and F). The
following sections describe steps to be taken during design and construction and identify specific
roles and responsibilities.
Wherever this procedure refers to DEP Design Project Manager or DEP construction Contract
Supervisor, these individuals may delegate the execution of these responsibilities to other staff or
consultants who may be an “RMP QA Specialist” or otherwise have the necessary QA
experience. They may choose to select a single individual who will oversee the DEP RMP
project efforts through design and construction or to select different individuals for different
phases of the project.
The DEP Design Project Manager (or his/her designee) is responsible for ensuring that all
design phase requirements are actually implemented during the design phase and may use
Attachment E to , or equivalent, to track incorporation of minimum equipment QA
requirements into the design.
PAGE 5 OF 42
1379 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
implementation record. Preparing the QA Plan will generally be part of the Design contract. The
QA Plan must be submitted to the operating Bureau RMP Manager and DEP Design Project
Manager for review and approval and will then be integrated into the construction contract
requirements.
For design projects initiated before the effective date of this procedure, the DEP Contract
Supervisor will achieve compliance in other ways (e.g., assigning RMP QA responsibilities to
DEP or construction management staff and using the attached checklists).
Construction contracts would require that the contractor establish, implement and maintain their
own effective project Contractor Quality Program to meet the QA Plan (to be submitted and
approved by DEP) to manage, control, document and assure that their work complies with the
requirements of the contract documents and QA Plan.
The Contractor Quality Program shall include procedures, responsibilities and a clearly assigned
organization necessary to assure adequate control (inspection) and assure quality for materials,
workmanship, fabrication and operations covering both off-site fabrication and on-site
construction work. Contractors must assign a person whose function is to manage all quality
matters relating to the project and to audit the performance of other individuals who may be
doing inspection and testing and to ensure that they are performed in compliance with all
applicable standards and the contract documents. The Contractor would be required to have
personnel on site performing QA whenever QA activities are required by the QA Plan or
specifications during chlorination equipment and piping installation work.
PAGE 6 OF 42
1380 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
The Contractor would be required to identify those responsible for the various types of
inspections and tests they are required to perform under the QA Plan. The quality assurance
personnel of a fabricator are permitted to be inspectors if they are qualified for the tasks they
perform (e.g., for code vessel certification by the authority having jurisdiction).
Verification of construction against the approved design documents is performed throughout the
construction phase. Personnel and Consultants assigned to the construction of chlorine processes
will perform oversight of construction activities, and assure, on a day-to-day basis, that the
contractor is in compliance with construction documents, including quality and safety
requirements. This oversight takes the form of: checking contractor supplied documentation;
witnessing contractor operations, inspections and tests; performing independent inspections and
tests to verify contractor results; or any combination of these activities.
PAGE 7 OF 42
1381 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
For construction management projects initiated after the effective date of this procedure, the DEP
Contract Supervisor (or designee) will include all requisite construction RMP/PSM process QA
oversight requirements into the Construction Management contract including a requirement to
submit a final Quality Assurance Report to obtain a consolidated implementation record.
4.0 RECORDKEEPING
The Construction Manager/Resident Engineer, under direction of the Contract Supervisor, has
the responsibility to maintain a comprehensive record of the QA activities during the work. At
completion of construction, the Construction Manager/Resident Engineer, under direction of
the Contract Supervisor, shall submit a complete copy of the final Quality Assurance
documentation to the operating Bureau’s RMP Manager, including at a minimum:
The above may be in the form of a comprehensive QA Report, if it was included in project
design and/or construction specifications. The operating Bureau’s RMP Manager shall retain
these records for the life of the operating equipment.
PAGE 8 OF 42
1382 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT A
DESIGN AND CONSTRUCTION QA REQUIRED BY COMPONENT
Note: In addition to the codes/standards based installation QA, all projects will require Equipment Receipt QA documentation (verify equipment received meets specs and route QA documentation to
project QA files) and installation QA documentation (verification of manufacturer required & functional tests before startup and requirements below).
Type of Typical Rated Applicable Primary Ref’d Source in Design QA Requirement Construction QA Requirement
Chlorine Pressure/ Size Code/Standard/ Current Code/Std (for Specifications After the Effective Date of This
Process Temperature Range Guideline Defining QA Procedure)
Equipment Rqmt.
All Equipment NA NA Chlorine Institute None > Contractor shall provide manufacturer’s > Review/approve Contractor’s QA Plan (if provided)
below governed Pamphlet 6, Edition Certificate of Conformance for all chlorination and check that the Table specifies the correct
by Chlorine 15 equipment expected to normally be in contact Manufacturer’s O&M Manual Installation Instructions
Institute with chlorine (not ancillaries, ducts, etc.) per CI and route to Quality Assurance (QA) records.
Pamphlet 6 and Pamphlet 6 – Section 2.2: “Manufacturers or
overall process. suppliers must certify to their end user, when > Verify receipt of manufacturer’s Certificates of
requested, that their product is suitable for Conformance on Suitability for Chlorine Service for
chlorine in the specified service. all chlorination equipment expected to normally be in
contact with chlorine (not ancillaries, ducts, etc.) and
> Installation and fabrication QA shall be route to QA Records.
performed in accordance with manufacturer’s
installation instructions and Chlorine Institute > Review/approve Contractor submittal of written
requirements. Receipt Inspection QA and Installation QA
documentation prior to turnover for startup that is
Note: Items in gray > Contractor shall submit a chlorination complete for all chlorination process equipment and
are to be performed equipment QA Plan describing how receipt confirms all equipment meets specs and installation
independent of the inspection and installation QA will be performed QA successfully performed. This must include test of
contractor. They for all chlorination system equipment, including each switch/detector/alarm, overall process
must be conducted a Table listing and referencing manufacturers instrumentation functionality checks, & installed
by the Contract and standards requirements prior to installation. system pressure tests.
Supervisor’s It shall also include system-wide cleaning,
designee (e.g., RE) hydrostatic pressure tests, drying, and inert gas > DEP Contract Supervisor (CS) will ensure
and may be pressure tests upon completion of each phase independent on-site:
independently in preparation for startup in accordance with CI • Receipt Inspection QA of Major Equipment
checked by DEP Pamphlet 6 – Section 11. (chlorinators and evaporators).
QAS. • Observation of Contractor installation QA of Major
> Contractor shall submit written documentation Equipment.
of Receipt Inspection, Fabrication QA and • Observation of Contractor process instrument
Installation Inspection prior to turnover for functionality tests
startup. • Observation of Contractor system
cleaning/degreasing, hydrostatic pressure tests,
drying, and inert gas pressure tests upon
completion of each phase in preparation for
startup.
Page 1 of 7
PAGE 9 OF 42
1383 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT A
DESIGN AND CONSTRUCTION QA REQUIRED BY COMPONENT
Type of Typical Rated Applicable Primary Ref’d Source in Design QA Requirement Construction QA Requirement
Chlorine Pressure/ Size Code/Standard/ Current Code/Std (for Specifications After the Effective Date of This
Process Temperature Range Guideline Defining QA Procedure)
Equipment Rqmt.
Chlorinator To Full All Sizes Chlorine Institute None > All items required under “All Equipment > All items required under “All Equipment governed by
Vacuum Pamphlet 6, Edition governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
15 > DEP CS will ensure independent:
• Receipt Inspection QA.
• Observation of Contractor installation QA in
accordance with O&M/Installation Manual.
Chlorine Various Various Chlorine Institute ASME Boiler & > All items required under “All Equipment > All items required under “All Equipment governed by
Evaporator Pamphlet 9, Edition Pressure Vessel governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
6 Code, Section VIII, > Materials shall meet the requirements of CI > Materials shall meet the requirements of CI Pamphlet
Division I, Part Pamphlet 9. 9.
UW-2 > Provide code cert. of compliance (Form U-1A) > Verify stamp and route certificate to records.
& ASME Code "L" stamp on vaporizer vessel to > DEP CS will ensure independent:
demonstrate it meets the following: • Receipt Inspection QA.
• W-L: welding meets lethal gas requirements • Observation of Contractor installation QA in
• S-L: fabricated using seamless pipe for lethal accordance with O&M/Installation Manual.
gas
• HT: whole vessel post weld heat-treated
• RT-1: complete vessel satisfies the full
radiography requirements (100%) of all
welded joints for lethal substances or design
pressures exceeding 50 psi.
Rupture Disks Various Various Chlorine Institute None > All items required under “All Equipment > All items required under “All Equipment governed by
Pamphlet 6, Ed. 15; governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
ASME Boiler & > Rupture disks shall meet the requirements of CI > Verify Materials and trim meets the requirements of
Pressure Vessel Pamphlet 6 - Sections 5.1 and 5.2. CI Pamphlet 6 - Sections 5.1 and 5.2.
Code, Section VIII,
Div. I, Part UG-127
Pressure Safety Per Vaporizer Various Chlorine Institute ASME Boiler & > All items required under “All Equipment > All items required under “All Equipment governed by
Relief Valves Manufacturer Pamphlet 6, Edition Pressure Vessel governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
(PSV) 15 Code, Section VIII, > Relief valves shall meet the requirements of CI > Verify Materials and trim meets the requirements of
Division I, Part Pamphlet 6 - Section 5.2. CI Pamphlet 6 - Section 5.2.
UW-2 and UG-126 > Store in a vertical position per API 576.
Pressure Various NA Chlorine Institute NEMA 4X > All items required under “All Equipment > All items required under “All Equipment governed by
Switches Pamphlet 6, Ed. 15; governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Chlorine Institute > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
Pamphlet 165, Ed. 1 Pamphlet 165. Pamphlet 165.
Other Various NA Chlorine Institute NEMA 4X > All items required under “All Equipment > All items required under “All Equipment governed by
Detectors, Pamphlet 6, Ed. 15; governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Switches and Chlorine Institute > Instrumentation and controls shall meet the > Verify instrumentation and controls meets the
Controls (e.g., Pamphlet 165, Ed. 1 requirements of CI Pamphlet 6 - Section 6. requirements of CI Pamphlet 6 - Section 6.
level, temp.) > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
Pamphlet 165. Pamphlet 165.
Page 2 of 7
PAGE 10 OF 42
1384 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT A
DESIGN AND CONSTRUCTION QA REQUIRED BY COMPONENT
Type of Typical Rated Applicable Primary Ref’d Source in Design QA Requirement Construction QA Requirement
Chlorine Pressure/ Size Code/Standard/ Current Code/Std (for Specifications After the Effective Date of This
Process Temperature Range Guideline Defining QA Procedure)
Equipment Rqmt.
Electrical Various NA Chlorine Institute NEMA 4X, > Electrical controls shall meet the requirements > Verify electrical controls meet the requirements of CI
Enclosures Pamphlet 6, Ed. 15; Fiberglass of CI Pamphlet 6 - Section 6. Pamphlet 6 - Section 6 and NEMA 250.
NEMA Stds Pub. Reinforced
250, “Enclosures for Polyester (FRP)
Electrical Equipment
(1000 V Maximum)
Chlorine Up to 800psi Chlorine Institute General Industry > All items required under “All Equipment > All items required under “All Equipment governed by
Pressure (diaphragm) Pamphlet 6, Ed. 15; Practice governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Gauge (Liquid Chlorine Institute > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
Cl2) Pamphlet 165, Ed. 1 Pamphlet 6 and Pamphlet 165. Pamphlet 6 and Pamphlet 165.
Chlorine Up to 800psi Chlorine Institute General Industry > All items required under “All Equipment > All items required under “All Equipment governed by
Pressure (diaphragm) Pamphlet 6, Ed. 15; Practice governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Gauge (Vapor Chlorine Institute > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
Cl2) Pamphlet 165, Ed. 1 Pamphlet 6 - Section 6 and Pamphlet 165. Pamphlet 6 - Section 6 and Pamphlet 165.
Misc. Various NA Chlorine Institute None > Provide manufacturer’s Certificate of > Verify receipt of manufacturer’s Certificates of
Appurtenances: Pamphlet 6, Ed. 15 Conformance per CI Pamphlet 6 – Section 2.2 Conformance on Suitability for Chlorine Service and
> Basket route to Quality Assurance (QA) Records.
Strainer
Pressure Various Various Chlorine Institute None > All items required under “All Equipment > All items required under “All Equipment governed by
Regulating Pamphlet 6, Ed. 15 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Valves
Vacuum Various Various Chlorine Institute None > All items required under “All Equipment > All items required under “All Equipment governed by
Regulating Pamphlet 6, Ed. 15 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Valves
Liquid ≥ 560 PSI (per 20% pipe Chlorine Institute 1. ASME Boiler & > All items required under “All Equipment > All items required under “All Equipment governed by
Expansion DEP volume Pamphlet 6, Ed. 15 Pressure Vessel governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Chambers requirement) –Section 5.5, Code, Section VIII, > Chambers shall meet the requirements of CI > Verify Materials meet the requirements of CI Drawing
Section 10.6, and Division I, Part Drawing 136 (either ASME Pressure Vessel, 136.
Drawing 136 UW-2 DOT Cylinder or Pipe options). > For ASME vessel, verify stamp and route certificate
or > If ASME, provide code certificate of compliance to records.
2. DOT Cylinder (Form U-1A) and ASME Code "L" stamp on > For DOT Cylinder, verify stamp and document for
Specifications (49 vessel to demonstrate it meets the following records.
CFR 178) code certifications: > For Pipe, verify materials meet the requirements of
or • W-L: welding meets lethal gas requirements CI Pamphlet 6.
3. Pipe and • S-L: fabricated using seamless pipe for lethal > DEP CS will ensure independent:
Fittings per gas • Receipt Inspection QA.
Chlorine Institute • HT: whole vessel post weld heat-treated • Observation of Contractor installation QA in
Pamphlet 6- • RT-1: complete vessel satisfies the full accordance with O&M/Installation Manual.
Section 3 radiography requirements (100%) of all
welded joints for lethal substances or design
pressures exceeding 50 psi.
> If DOT, provide code req. DOT cylinder stamp.
> If Pipe, materials shall meet the requirements of
CI Pamphlet 6. Page 3 of 7
PAGE 11 OF 42
1385 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT A
DESIGN AND CONSTRUCTION QA REQUIRED BY COMPONENT
Type of Typical Rated Applicable Primary Ref’d Source in Design QA Requirement Construction QA Requirement
Chlorine Pressure/ Size Code/Standard/ Current Code/Std (for Specifications After the Effective Date of This
Process Temperature Range Guideline Defining QA Procedure)
Equipment Rqmt.
Pipe – Vacuum Vacuum to 6 Through Chlorine Institute ASTM D3915, > All items required under “All Equipment > All items required under “All Equipment governed by
PSIG 1–½” Pamphlet 6, Ed. 15 Sch. 80 PVC with governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
o
212 F Screwed Joints (CI > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
Pamphlet 6 refs Pamphlet 6 - Section 9. Pamphlet 6 - Section 9.
D1784, but this is
superceded by
D3915)
Pipe - Pressure Class IV- Through Chlorine Institute ASTM A106, > All items required under “All Equipment > All items required under “All Equipment governed by
Gas/Liquid, 1–½” Pamphlet 6, Ed. 15 Sch.80 Carbon governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
300 psig, Steel Seamless > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
o o
-20 F to 300 F ASME/ANSI Pamphlet 6 - Section 3. Pamphlet 6 - Section 3.
B36.10; ASME/ > Verify maximum spacing and integrity of pipe and
ANSI B31.3 large valves hangers and supports.
Fittings Class IV- Through Chlorine Institute ASTM A105 > All items required under “All Equipment > All items required under “All Equipment governed by
Gas/Liquid, 1–½” Pamphlet 6, Ed. 15 Class 3000 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
300 psig, Forged Steel > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
o o
-20 F to 300 F ASME/ ANSI Pamphlet 6 - Section 3. Pamphlet 6 - Section 3.
B16.11
Flanges Class IV- Through Chlorine Institute ASTM A105 > All items required under “All Equipment > All items required under “All Equipment governed by
Gas/Liquid, 1–½” Pamphlet 6, Ed. 15 Class 300 Forged governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
300 psig, Steel, > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
o o
-20 F to 300 F ASME/ANSI B16.5 Pamphlet 6 - Section 3. Pamphlet 6 - Section 3.
Ammonia-Type 1000psi (per 1” Chlorine Institute ASTM A105 > All items required under “All Equipment > All items required under “All Equipment governed by
Union (2-bolt F&P Chem Fd Pamphlet 6, Ed. 15 Class 300 Forged governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Flanged Union) Eq 70-9001 Steel, ASME/ANSI> Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
Rev 2) B16.5 Pamphlet 6 – Section 3 (See Note 4 for Table Pamphlet 6 – Section 3 (See Note 4 for Table 3-1).
3-1).
Unions Class IV- Through Chlorine Institute ASTM A105 > All items required under “All Equipment > All items required under “All Equipment governed by
Gas/Liquid, 1–½” Pamphlet 6, Ed. 15 Class 300 Forged governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
300 psig, Steel, > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
o o
-20 F to 300 F ASME/ANSI B16.5 Pamphlet 6 - Section 3. Pamphlet 6 - Section 3.
Bolts Class IV- All Sizes Chlorine Institute ASTM A193, > All items required under “All Equipment > All items required under “All Equipment governed by
Gas/Liquid, Pamphlet 6, Ed. 15 Grade B7 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
300 psig, > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 - Section 3. Pamphlet 6 - Section 3.
Nuts Class IV- All Sizes Chlorine Institute ASTM A194, > All items required under “All Equipment > All items required under “All Equipment governed by
Gas/Liquid, Pamphlet 6, Ed. 15 Grade 2H governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
300 psig, > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 - Section 3. Pamphlet 6 - Section 3.
Gaskets Class IV- All Sizes Chlorine Institute General Industry > All items required under “All Equipment > All items required under “All Equipment governed by
Gas/Liquid, Pamphlet 95 Practice governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
300 psig, > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
o o
-20 F to 300 F Pamphlet 95 Pamphlet 95
PAGE 12 OF 42 Page 4 of 7
1386 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT A
DESIGN AND CONSTRUCTION QA REQUIRED BY COMPONENT
Type of Typical Rated Applicable Primary Ref’d Source in Design QA Requirement Construction QA Requirement
Chlorine Pressure/ Size Code/Standard/ Current Code/Std (for Specifications After the Effective Date of This
Process Temperature Range Guideline Defining QA Procedure)
Equipment Rqmt.
Chlorine 560psi, 140F 1” Chlorine Institute General Industry > All items required under “All Equipment > All items required under “All Equipment governed by
Auxiliary Pamphlet 6, Ed. 15 Practice governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Valves, > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
Chlorine Pamphlet 6 and Drawing 113. Pamphlet 6 and Drawing 113.
Manifold Valves
Globe Valves- Class IV- Through Chlorine Institute Forged API Class > All items required under “All Equipment > All items required under “All Equipment governed by
Threaded or Gas/Liquid, 1–½” Pamphlet 6, Ed. 15 800 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Socket Welded 300 psig, > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 - Section 4. Pamphlet 6 - Section 4.
Globe Valves- Class IV- All Sizes Chlorine Institute Forged or Cast > All items required under “All Equipment > All items required under “All Equipment governed by
Flanged or Butt- Gas/Liquid, Pamphlet 6, Ed. 15 ANSI Classes 150 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Welded 300 psig, or 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 - Section 4. Pamphlet 6 - Section 4.
Unlined Ball Class IV- Through Chlorine Institute Forged or Cast > All items required under “All Equipment > All items required under “All Equipment governed by
Valves - Gas/Liquid, 1–½” Pamphlet 6, Ed. 15 ANSI Classes 150 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Threaded 300 psig, or 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 - Section 4. Pamphlet 6 - Section 4.
Unlined Ball Class IV- All Sizes Chlorine Institute Forged or Cast > All items required under “All Equipment > All items required under “All Equipment governed by
Valves – Gas/Liquid, Pamphlet 6, Ed. 15 ANSI Classes 150 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Flanged 300 psig, or 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 - Section 4. Pamphlet 6 - Section 4.
Unlined Plug Class IV- Through Chlorine Institute Forged or Cast > All items required under “All Equipment > All items required under “All Equipment governed by
Valves - Gas/Liquid, 1–½” Pamphlet 6, Ed. 15 ANSI Classes 150 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Threaded 300 psig, or 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 - Section 4. Pamphlet 6 - Section 4.
Unlined Plug Class IV- All Sizes Chlorine Institute Cast ANSI > All items required under “All Equipment > All items required under “All Equipment governed by
Valves – Gas/Liquid, Pamphlet 6, Ed. 15 Classes 150 or governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Flanged 300 psig, 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 - Section 4. Pamphlet 6 - Section 4.
High Class IV- All Sizes Chlorine Institute Plate or Cast ANSI > All items required under “All Equipment > All items required under “All Equipment governed by
Performance Gas/Liquid, Pamphlet 6, Ed. 15 Classes 150 or governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Butterfly Valves 300 psig, 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
(Unlined) – -20 F to 300 F Pamphlet 6 - Section 4. Pamphlet 6 - Section 4.
Wafer or
Lugged
High- Class IV- All Sizes Chlorine Institute Cast ANSI > All items required under “All Equipment > All items required under “All Equipment governed by
Performance Gas/Liquid, Pamphlet 6, Ed. 15 Classes 150 or governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Butterfly Valves 300 psig, 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
(unlined) – -20 F to 300 F Pamphlet 6 – Section 4. Pamphlet 6 – Section 4.
Flanged
Single-Seated Class IV- All Sizes Chlorine Institute Cast ANSI > All items required under “All Equipment > All items required under “All Equipment governed by
Segmented Ball Gas/Liquid, Pamphlet 6, Ed. 15 Classes 150 or governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Valves - Wafer 300 psig, 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
-20 F to 300 F Pamphlet 6 – Section 4. Pamphlet 6 – Section 4.
Page 5 of 7
PAGE 13 OF 42
1387 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT A
DESIGN AND CONSTRUCTION QA REQUIRED BY COMPONENT
Type of Typical Rated Applicable Primary Ref’d Source in Design QA Requirement Construction QA Requirement
Chlorine Pressure/ Size Code/Standard/ Current Code/Std (for Specifications After the Effective Date of This
Process Temperature Range Guideline Defining QA Procedure)
Equipment Rqmt.
Single-Seated Class IV- All Sizes Chlorine Institute Forged or Cast > All items required under “All Equipment > All items required under “All Equipment governed by
Segmented Ball Gas/Liquid, Pamphlet 6, Ed. 15 ANSI Classes 150 governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Valves - 300 psig, or 300 > Materials shall meet the requirements of CI > Verify materials and trim meet the requirements of CI
o o
Flanged -20 F to 300 F Pamphlet 6 – Section 4. Pamphlet 6 – Section 4.
Chlorine 560psig per Standard – Chlorine Institute ASTM B165, Cold > All items required under “All Equipment > All items required under “All Equipment governed by
Flexible Lines DEP Monel Pamphlet 6, Ed. 15 Drawn, annealed governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
requirements > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
Pamphlet 6 - Section 7. Pamphlet 6 - Section 7.
Chlorine N/A Standard – Chlorine Institute ASTM B88, > All items required under “All Equipment > All items required under “All Equipment governed by
Flexible Lines Copper Pamphlet 6, Ed. 15 Seamless, Type K, governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
or heavier, > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
[NOTE: Not annealed Pamphlet 6 - Section 7. Pamphlet 6 - Section 7.
used by DEP]
Chlorine N/A Local Building Code General Industry > All items required under “All Equipment > All items required under “All Equipment governed by
Emergency (and generally Int’l Practice governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Shutoff Valves Fire Code 2003 or > Performance shall meet the requirements of > Verify proper installation per manufacturer’s
latest ed., Section IFC (2003 or latest edition) Section instructions and controls meet requirements of IFC
3704.2.2.10.3) 3704.2.2.10.3. (2003 or latest edition) Section 3704.2.2.10.3.
Chlorine N/A Local Building Code General Industry > Design Engineer shall verify that ventilation > Verify receipt of Manufacturer certification of
Emergency (and generally Practice flow pattern optimally sweeps incidental conformance with IFC Section 3704.2.2.7.1
Scrubber International Fire releases from the working area around performance requirements or more stringent DEP
Code 2003 or latest containers. specifications.
edition, Section > Manufacturer certifies the design conforms > DEP CS will ensure independent:
3704, or Uniform with IFC Section 3704.2.2.7.1 or UFC Article • Fabrication and installation QA in accordance with
Fire Code Article 80 performance requirements (1 ton to < ½ DEP Inspection and Testing Plan for the
80), Chlorine IDLH in 30 min.) or more stringent DEP specs Fabrication of Emergency FRP Venturi Chlorine
Institute Pamphlet (i.e., worst-case release of 2 tons). Scrubber and manufacturer’s requirements.
89, Ed. 3 > Contractor shall comply with the DEP • Observation of Contractor installation QA in
Inspection and Testing Plan for the Fabrication accordance with O&M/Installation Manual.
of Emergency FRP Venturi Chlorine Scrubber. • Observation of contractor flow verification testing
> Contractor shall perform flow pattern and air and receipt of written report.
flow rate performance verification testing.
Top Running, N/A OSHA 29 CFR Regulatory > Conduct load test in accordance with ASME > DEP CS will ensure independent:
Double Beam 1910.179 Requirements standards and provide load test report. • Observation of Contractor installation QA in
Crane ASME B30.17c accordance with O&M/Installation Manual
• Observation of Contractor Load Test.
> Verify receipt of load test report.
SCBA N/A NIOSH Regulatory > Contractor shall provide manufacturer’s > Verify receipt of manufacturer’s Certificates of
MSHA Requirements Certificate of Conformance. Conformance and route to Quality Assurance (QA)
Records.
Page 6 of 7
PAGE 14 OF 42
1388 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT A
DESIGN AND CONSTRUCTION QA REQUIRED BY COMPONENT
Type of Typical Rated Applicable Primary Ref’d Source in Design QA Requirement Construction QA Requirement
Chlorine Pressure/ Size Code/Standard/ Current Code/Std (for Specifications After the Effective Date of This
Process Temperature Range Guideline Defining QA Procedure)
Equipment Rqmt.
Chlorine N/A Chlorine Institute General Industry > Contractor shall provide manufacturer’s > Verify receipt of manufacturer’s Certificates of
Emergency Kit Pamphlet 1, Edition Practice Certificate of Conformance. Conformance and route to Quality Assurance (QA)
6 Records.
> Verify appropriate emergency kit for container size,
e.g. Emergency Kit B for Chlorine Ton containers.
Chlorine Scales N/A Manufacturer’s Manufacturer’s > Contractor shall provide Calibration Certificates. > Verify receipt of Calibration Certificates and route to
Specifications Only Specifications Quality Assurance (QA) Records.
Ventilation Fan N/A Applicable NEMA Regulatory > All items required under “All Equipment > All items required under “All Equipment governed by
(Cl2 Storage Codes Requirements governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Room)
Ventilation Fan N/A Applicable NEMA Regulatory > All items required under “All Equipment > All items required under “All Equipment governed by
(Chlorination Codes Requirements governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
Room)
Ejector (New ejectors Manufacturer’s Manufacturer’s > All items required under “All Equipment > All items required under “All Equipment governed by
rated @ 300psi Specifications Only Specifications governed by CI Pamphlet 6” above. CI Pamphlet 6” above.
@ 90F)
Windsock N/A Manufacturer’s General Industry > None > None
Specifications Only Practice
Employee N/A Manufacturer’s Manufacturer’s > None > Functional test and audibility in all areas in and
Evacuation Specifications Only Specifications around the chlorination process area confirmed.
Alarm
Atmospheric NA NA Chlorine Institute General Industry > Materials shall meet the requirements of CI > Verify materials meet the requirements of CI
Monitoring Pamphlet 73, Ed. 7 Standard Pamphlet 73. Pamphlet 73.
Equipment for
Chlorine
Page 7 of 7
PAGE 15 OF 42
1389 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT B
Quality Assurance (QA) Checklist
for Design/Construction Project Management
Have summary / listing of all specs, procedures and plans governing fabrication,
receipt and installation QA prepared and the documents are available to support
construction QA?
Confirmed contractors performing/documenting receipt inspection QA:
> Shipping/packing documents and items themselves checked against Pos/specs
to verify the proper material/equipment was received.
> All items clearly marked/ID’d, including useful life.
> Periodic checks on items in storage subject to deterioration.
> All items controlled from the point of receipt through installation.
> All items maintained, properly stored and used per manufacturer’s
storage/handling requirements to prevent damage, loss, deterioration.
Performed/documented independent receipt QA on major chlorination equipment
Construction
1
Refer to Attachment A of the DEP procedure Quality Assurance for Design and Construction of New and Modified
RMP/PSM Regulated Chlorine Processes for specific guidance for all items on this list.
2
This document is intended to be used in conjunction with the Owner Bureau QA and Contractor QA Checklists in
implementing DEP’s above cited procedure.
PAGE 16 OF 42
1390 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
________________________________________________________________________________________
ATTACHMENT B
Quality Assurance (QA) Checklist
for Design/Construction Project Management
PAGE 17 OF 42
1391 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
________________________________________________________________________________________
ATTACHMENT C
Owning Bureau Role
in BEDC Quality Assurance (QA) Checklist Obligations
Note: The following is a summary of suggested involvement of the Owning Bureau RMP staff in the BEDC QA
Checklist obligations. Note that on some projects, the Owning Bureau may take a more active role.
1, 2 Owning Delegated Compl.
Phase / Task Description
Bureau Role To (sign &
date)
Design plans/specs integrate requirements of Att. A of Design and Review and
Construction of New and Modified RMP/PSM Regulated Chlorine Processes verify
under the “Design QA Requirement” column?
D e s i g n
Updated list of codes and standards provided with a summary of changes to Review and
the list predating the design? verify
Owning Bureau engineering and/or operations management review and Participate,
approval of the preliminary (60%) and final (100%) designs? comment,
approve
Obtained documentation to complete PHA and MOC, including all QA Review and
documentation and as built drawings. verify
QA Plan submitted (when specified, or see next item below). Review and
verify
Pre
Have summary / listing of all specs, procedures and plans governing Review and
fabrication, receipt and installation QA prepared and the documents available verify
to support construction QA.
Confirmed contractors performing/documenting receipt inspection QA: At Bureau’s
> Shipping/packing documents and items themselves checked against option, audit
Pos/specs to verify the proper material/equipment was received. execution on
> All items clearly marked/ID’d, including useful life. selected
> Periodic checks on items in storage subject to deterioration. equipment
> All items controlled from the point of receipt through installation.
> All items maintained, properly stored and used per manufacturer’s
storage/handling requirements to prevent damage, loss, deterioration.
Construction
1
Refer to Attachment A of the DEP procedure Quality Assurance for Design and Construction of New and Modified
RMP/PSM Regulated Chlorine Processes for specific guidance for all items on this list.
2
This document is intended to be used in conjunction with Quality Assurance Checklist for Project Management
and the Contractor Quality Assurance Checklists in implementing DEP’s above cited procedure.
PAGE 18 OF 42
1392 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT C
Owning Bureau Role
in BEDC Quality Assurance (QA) Checklist Obligations
1, 2 Owning Delegated Compl.
Phase / Task Description
Bureau Role To (sign &
date)
Verified completion of all other QA specified in Chlorine Equipment Quality Same as above
Assurance Checklist and the comprehensive Quality Assurance Plan (when
specified)?
All Non-Conforming Reports (NCR) submitted for approval of the Disposition Same as above
Plans? All Disposition Plans completed?
Managed the QA submittals and records during the project? Same as above
Involved a representative of the Owner Bureau’s management in substantial Participate,
completion inspections? comment,
approve
Received Contractor and Consultant QA final certifications w/all Verify receipt
inspection/testing documentation (e.g., receipt QA, Certificates of
Conformance on Suitability for Chlorine Service for all chlorination
equipment, NCR corrective actions completed per NCR Disposition Plans,
ASME Code vessel submittals, pressure tests, calibration tests, other
installation testing, etc.) covering all construction work and indicating
constructed substantially in compliance with specs?
Transmitted final QA documentation (e.g., Quality Assurance Report, if Verify receipt
specified) and other RMP/PSM requirements for startup to the Bureau
operations (e.g., maintenance and operating procedures and PSI) for final
acceptance?
PAGE 19 OF 42
1393 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT D
Contractor Quality Assurance (QA) Checklist
fully assembled system and all equipment and appliances are properly installed
consistent with design specifications and the manufacturer's instructions and are
free from defects.
1
Refer to Attachment A of the DEP procedure Quality Assurance for Design and Construction of New and Modified
RMP/PSM Regulated Chlorine Processes for specific guidance for all items on this list.
2
This document is intended to be used in conjunction with Quality Assurance Checklist for Project Management
and the Owner Bureau QA Checklists in implementing DEP’s above cited procedure.
PAGE 20 OF 42
1394 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________________
ATTACHMENT D
Contractor Quality Assurance (QA) Checklist
1, 2 Responsible Delegated Compl.
Phase / Task Description
Person To (sign &
date)
All Non-Conforming Reports (NCR) submitted for approval of the Disposition
Plans? All Disposition Plans completed?
QA documentation shall include all required activities and demonstrate that the
test results meet any relevant standards (e.g., pressure loss on leak test).
Drawings of constructed or fabricated items shall reflect conditions during
construction and at final completion of the project.
Upon completion of the work, a final QA documentation submittal covering all
construction work and indicating constructed substantially in compliance with
specs. Includes all receipt inspection QA, Certificates of Conformance on
Suitability for Chlorine Service for all chlorination equipment, NCR corrective
actions completed per NCR Disposition Plans, ASME Code vessel submittals,
pressure tests, calibration tests, other fabrication and construction installation
testing and QA, as-built and other records of Risk Management Programs
documentation required by the specs (e.g., as-built drawings, operating and
maintenance procedures, etc.) shall be submitted for approval to the Engineer
and the facility representative (including, when specified, a final consolidated
Construction QA Report demonstrating completion of all QA specified in
Chlorine Equipment QA Checklist and the QA Plan).
Transmitted other final RMP/PSM requirements for startup (e.g., maintenance
and operating procedures and PSI) for final acceptance, when required.
PAGE 21 OF 42
1395 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
__________1_______________________________________________________________________________________
ATTACHMENT E
Equipment Quality Assurance (QA) Checklist
of Minimum Applicable Standards and Certificates
Note: Must be used by the Design Engineer to verify that the requirements are in the specifications and by the
construction QA personnel to verify that documentation is received. Verify at minimum that equipment meets the
primary standards listed applicable to construction QA. “Certificates Required” are Certificates of Conformance on
Suitability for Chlorine Service for all chlorination equipment expected to normally be in contact with chlorine (not
ancillaries, ducts, etc.).
Equipment Primary Standards/Requirements Applicable to QA Certificate Required? In Spec? Rec’d?
Chlorinator ; Meets Chlorine Institute (CI) Pamphlet 6, Edition 15. ; Yes
Chlorine ; Meets the requirements of CI Pamphlet 9, Edition 6. ; Yes
Evaporator ; Certificate of compliance Form U-1A provided and has
ASME “L” stamp per ASME Boiler & Pressure Vessel
Code, Section VII, Division 1, Part UW-2.
Rupture Disks ; Meets CI Pamphlet 6, Ed. 15, Sections 5.1 and 5.2. ; Yes
; ASME Boiler & Pressure Vessel Code, Section VIII,
Div. I, Part UG-127.
Pressure Safety ; Meets CI Pamphlet 6, Ed. 15 - Section 5.2. ; Yes
Relief Valves ; Stored in a vertical position per API 576.
(PSV)
Pressure ; Meets CI Pamphlet 6, Ed. 15 ; Yes (if regular Cl2
Switches ; Meets CI Pamphlet 165, Ed. 1. contact)
Other Detectors, ; Meets CI Pamphlet 6, Ed. 15 - Section 6. ; Yes (if reg. Cl2
Switches and ; Meets CI Pamphlet 165, Ed. 1. contact; may be
Controls (e.g., covered in package
level, temp.) system cert.)
Electrical ; Meets CI Pamphlet 6, Ed. 15 - Section 6.
Enclosures ; Meets NEMA Pub. 250, “Enclosures for Electrical
Equipment (1000 V Maximum).
Chlorine ; Rated to 800 psi. ; Yes
Pressure Gauge ; Meets CI Pamphlet 6, Ed. 15.
(Liquid Cl2) ; Meets CI Pamphlet 165, Ed. 1.
Chlorine ; Meets CI Pamphlet 6, Ed. 15. ; Yes
Pressure Gauge ; Meets CI Pamphlet 165, Ed. 1.
(Vapor Cl2)
Misc. ; Meets CI Pamphlet 6, Ed. 15. ; Yes (if regular Cl2
Appurtenances: contact)
> Basket Strainer
Pressure ; Meets CI Pamphlet 6, Ed. 15. ; Yes (if regular Cl2
Regulating contact)
Valves
Vacuum ; Meets CI Pamphlet 6, Ed. 15. ; Yes (if regular Cl2
Regulating contact)
Valves
PAGE 22 OF 42
1396 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
__________________________________________________________________________________________
2
ATTACHMENT E
Equipment Quality Assurance (QA) Checklist
of Minimum Applicable Standards and Certificates
Equipment Primary Standards/Requirements Applicable to QA Certificate Required? In Spec? Rec’d?
Liquid ; Meets CI Pamphlet 6, Ed. 15 – Section 5.5, Section ; Yes
Expansion 10.6.
Chambers ; Meets CI Drawing 136.
; If using ASME Boiler & Pressure Vessel Code Section
VIII, Division I Part UW-2, certificate of compliance
(Form U-2) provided and has ASME “L” stamp.
• W-L: welding meets lethal gas requirements
• S-L: fabricated using seamless pipe for lethal gas
• HT: whole vessel post weld heat-treated
• RT-1: complete vessel satisfies the full radiography
requirements (100%) of all welded joints for lethal
substances or design pressures exceeding 50 psi.
; For DOT Cylinder, verify stamp meeting 49 CFR 178.
; For Pipe, meets CI Pamphlet 6.
Pipe – Vacuum ; Meets CI Pamphlet 6, Ed. 15 - Section 9.
(to 1–½”) ; ASTM D3915, Sch. 80 PVC with Screwed Joints (CI
Pamphlet 6 refs D1784, but this is superseded by
D3915)
Pipe – Pressure ; Meets CI Pamphlet 6, Ed. 15 - Section 3.
(Class IV, to ; Meets ASTM A106, Sch.80 Carbon Steel Seamless
1–½”) ASME/ANSI B36.10; ASME/ ANSI B31.31
; Verify maximum spacing and integrity of pipe and
large valves hangers and supports.
Fittings ; Meets CI Pamphlet 6, Ed. 15 - Section 3.
(Class IV, to ; Meets ASTM A105 Class 3000 Forged Steel; ASME/
1–½”) ANSI B16.11
Flanges ; Meets CI Pamphlet 6, Ed. 15 - Section 3.
(Class IV, to ; Meets ASTM A105 Class 300 Forged Steel; ASME/
1–½”) ANSI B16.5
Ammonia-Type ; Meets CI Pamphlet 6, Ed. 15 - Section 3 (see Note 4,
Union (1000 psi; Table 3-1).
2-bolt Flanged ; Meets ASTM A105 Class 300 Forged Steel; ASME/
Union) ANSI B16.5
Unions ; Meets CI Pamphlet 6, Ed. 15 - Section 3.
(Class IV, to ; Meets ASTM A105 Class 300 Forged Steel; ASME/
1–½”) ANSI B16.5
Bolts ; Meets CI Pamphlet 6, Ed. 15 - Section 3.
(Class IV) ; Meets ASTM A193, Grade B7.
Nuts ; Meets CI Pamphlet 6, Ed. 15 - Section 3.
(Class IV) ; Meets ASTM A194, Grade 2H.
Gaskets ; Meets CI Pamphlet 95. ; Yes (if regular Cl2
(Class IV) contact)
Chlorine ; Meets CI Pamphlet 6, Ed. 15” above. ; Yes (if regular Cl2
Auxiliary ; Meets CI Pamphlet Drawing 113. contact)
Valves, Chlorine
Manifold Valves
PAGE 23 OF 42
1397 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
__________3_______________________________________________________________________________________
ATTACHMENT E
Equipment Quality Assurance (QA) Checklist
of Minimum Applicable Standards and Certificates
Equipment Primary Standards/Requirements Applicable to QA Certificate Required? In Spec? Rec’d?
Globe Valves- ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Threaded or ; Meets Forged API Class 800. contact)
Socket Welded
(Class IV; to 1 -
1/2”)
Globe Valves- ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Flanged or Butt- ; Meets Forged ANSI Classes 150 or 300. contact)
Welded (Class
IV)
Unlined Ball ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Valves – ; Meets Forged ANSI Classes 150 or 300. contact)
Threaded (Class
IV; to 1 – ½“)
Unlined Ball ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Valves – Flanged ; Meets Forged ANSI Classes 150 or 300. contact)
(Class IV)
Unlined Plug ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Valves - ; Meets Forged ANSI Classes 150 or 300. contact)
Threaded (Class
IV; to 1 – ½“
Unlined Plug ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Valves – Flanged ; Meets Forged ANSI Classes 150 or 300. contact)
(Class IV)
High ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Performance ; Meets Forged ANSI Classes 150 or 300. contact)
Butterfly Valves
(Class IV;
Unlined) –
Wafer or Lugged
High- ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Performance ; Meets Forged ANSI Classes 150 or 300. contact)
Butterfly Valves
(Class IV;
unlined) –
Flanged
Single-Seated ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Segmented Ball ; Meets Forged ANSI Classes 150 or 300. contact)
Valves – Wafer
(Class IV)
Single-Seated ; Meets CI Pamphlet 6, Ed. 15 - Section 4. ; Yes (if regular Cl2
Segmented Ball ; Meets Forged ANSI Classes 150 or 300. contact)
Valves – Flanged
(Class IV)
Chlorine ; Meets CI Pamphlet 6, Ed. 15 - Section 7. ; Yes
Flexible Lines - ; Meets ASTM B165, Cold Drawn, annealed.
Monel
Chlorine ; Installation per manufacturer’s instructions. ; Yes
Emergency ; Controls meet Local Building Code (and generally Int’l
Shutoff Valves Fire Code 2003 or latest ed., Section 3704.2.2.10.3).
PAGE 24 OF 42
1398 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
___________________________________________________________________________________________
4
ATTACHMENT E
Equipment Quality Assurance (QA) Checklist
of Minimum Applicable Standards and Certificates
Equipment Primary Standards/Requirements Applicable to QA Certificate Required? In Spec? Rec’d?
Chlorine ; Chlorine Institute Pamphlet 89, Ed. 3. ; Yes
Emergency ; Local Building Code (and generally International Fire
Scrubber Code 2003 or latest edition, Section 3704, or Uniform
Fire Code Article 80)
; Manufacturer certification of conformance with IFC
Section 3704.2.2.7.1 performance requirements or
more stringent DEP specifications.
Top Running, ; Installation QA in accordance with OSHA 29 CFR
Double Beam 1910.179, ASME B30.17c, manufacturer
Crane O&M/Installation Manual.
; Load Test performed and report provided.
SCBA ; Manufacturer’s Certificates of Conformance
w/NIOSH/MSHA.
Chlorine ; Meets CI Pamphlet 1, Ed. 6. ; Yes
Emergency Kit ; Appropriate emergency kit for container size, e.g.
Emergency Kit B for Chlorine Ton containers.
Chlorine Scales ; Manufacturer’s Specifications Only
Ventilation Fan ; Applicable NEMA Codes.
(Cl2 Storage
Room)
Ventilation Fan ; Applicable NEMA Codes.
(Chlorination
Room)
Ejector ; Manufacturer’s Specifications Only. ; Yes (may be a part
of Chlorinator
system certificate)
Windsock ; Manufacturer’s Specifications Only.
Employee ; Functional test and audibility in all areas in and around
Evacuation the chlorination process area confirmed.
Alarm ; Manufacturer’s Specifications Only
Atmospheric ; Meets CI Pamphlet 73, Ed. 7.
Monitoring
Equipment for
Cl2
PAGE 25 OF 42
1399 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
_________________________________________________________________________________________
________
ATTACHMENT F
RECEIPT QA INSPECTION CHECKLIST
Name of Contractor/Subcontractor:
Contractor PO Number:
Relevant Specification:
Description of Equipment or Materials Received (attach work summary from contract):
Yes No Verified that all items are clearly marked and identified.
Yes No Checked shipping and packing documents and the items themselves against POs and relevant
specifications and verified that the proper material/equipment was received.
Yes No Verified that the items are not damaged.
Yes No Verified that the useful-life of limited-life items are indicated on the product packaging.
Yes No Confirmed that access to these items is controlled from the point of receipt through storage and
installation.
Yes No Identified the equipment as major chlorination equipment and notified the Resident Engineer to
conduct independent quality assurance inspection.
Yes No Confirmed the receipt of Certificate of Conformance on Suitability for Chlorine Service for
chlorination and provided a copy to the Resident Engineer.
Yes No Determined if the item is subject to environmental deterioration in storage and, if yes:
Identified the following storage inspection frequency:
Identified the following storage requirements are met:
Special Storage and Handling Requirements.
Inspection Certification:
I certify that I conducted the required receipt inspection of the equipment and relevant documentation and that
the information presented on this inspection form is accurate and complete.
PAGE 26 OF 42
1400 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
________________________________________________________________________________________
ATTACHMENT G
SAMPLE DESIGN / RE CONTRACT QA REQUIREMENTS
PAGE 27 OF 42
1401 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
________________________________________________________________________________________
ATTACHMENT G
SAMPLE DESIGN / RE CONTRACT QA REQUIREMENTS
procedure Quality Assurance for Design and Construction of New and Modified RMP
Regulated Chlorine Processes.
The Construction Manager/Resident Engineer shall verify that the Contractors meet all other
QA and other RMP obligations and submit requisite documentation (see next section).
The Construction Manager/Resident Engineer shall involve a representative of the operating
Bureau’s management in substantial completion inspections and in verifying completion of
all required RMP items (MoC and PHA action item completion, turnover of QA information,
as-built drawings, etc.) and obtain their approval prior to substantial completion.
The Construction Manager/Resident Engineer shall manage the QA submittals and records
during the project, shall provide requisite copies to the DEP Contract Supervisor and DEP
operating Bureau RMP staff on request.
Prior to final acceptance and startup, the Construction Manager/Resident Engineer shall
submit a Quality Assurance Report to DEP summarizing the QA work and confirming that
all inspected work was completed substantially in compliance with the approved construction
documents. The report shall include a complete copy of all fabrication/construction QA
certifications and other QA inspection and testing documentation completed by all
Contractors, DEP personnel and Consultants performing QA functions during the
construction and startup. The Construction Manager/Resident Engineer shall address DEP’s
comments and resubmit the plan within 60 days of receiving DEP comments, until approved
by the DEP the Contract Supervisor and facility RMP Manager.
PAGE 28 OF 42
1402 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
________________________________________________________________________________________
ATTACHMENT H
SAMPLE CONSTRUCTION CONTRACT QA REQUIREMENTS
PAGE 29 OF 42
1403 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
________________________________________________________________________________________
ATTACHMENT H
SAMPLE CONSTRUCTION CONTRACT QA REQUIREMENTS
and the manufacturer's instructions, meet their operating cycles and are free from defects
such as overheating, overloading and undue vibration. The Contractor shall make all
necessary changes, adjustments and replacements at his own expense in preparation for
placing the equipment into service.
Final Field Testing: Upon completion of the work and prior to final payment, all equipment
and appliances will be subject to final field tests, witnessed by the Engineer, to prove that the
fully assembled system and all equipment and appliances are properly installed consistent
with design specifications and the manufacturer's instructions and are free from defects.
Final Fabrication, As-Built and Installation QA Documents: Upon completion of the work
and prior to final payment, all fabrication and construction QA, as-built and other records of
Risk Management Programs documentation required by the specifications (e.g., as-built
drawings, operating procedures, maintenance procedures, etc.) shall be submitted for
approval to the Engineer and the facility representative. Drawings of constructed or
fabricated items shall reflect conditions during construction and at final completion of the
project. QA documentation shall include all required activities and demonstrate that the test
results meet any relevant standards (e.g., pressure loss on leak test).
PAGE 30 OF 42
1404 11/2017
ATTACHMENTS - DETAILED SPECIFICATION
01140 CONTRACT DEL-260 G, H, E
Attachment I
Non-Conformance Report
NCR – _____ – ___
Contract: Specification Section & Sub-section: DEP Assignment Code: P.O. to Vendor (Issue Date): Initial Issue Date:
Sub-vendor (If Applicable): Vendor NCR No. (If Applicable): See Also DJ:
Disposition to be proposed by Vendor and submitted to their Customer with this non-conformance Notice. Vendor to indicate item, condition and cause
of non-conformance, proposed disposition with technical justification, recommended re-inspection items, measure to avoid recurrence, and impact on
shipping schedule. Vendor is advised that this material or equipment may be subject to rejection and any work performed prior to resolution of the
non-conformance is at the Vendor’s own risk.
YES PAGES
Release for Non-Conformance and Verification: ATTACHMENT:
NO
1405
PAGE 31 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, H, E
________________________________________________________________________________________
PAGE 32 OF 42
1406 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
EXHIBIT C
1407
PAGE 33 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
Overview
This document details security guidelines that are often in addition to the Security Scope
of Work detailed in the contract. They are intended for DEP Project Manager, Resident
Engineer, and Contractor Personnel who work primarily at Water Supply Sites and
selected BWS Sites such as Hillview Reservoir, Jerome Park Reservoir, and Croton
Water Treatment Plant. Additional locations may fall under these guidelines at the
discretion of the Deputy Commissioner, Bureau of Police & Security (BPS) and/or his or
her authorized representative. Site Security Guidelines are subject to adjustment based on
changes in operations or increased threat levels.
Table of Contents
1408
PAGE 34 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
Contractor each must appoint a Security Point of Contact (SPOC) to liaise with
DEP Police and Security Systems Engineering Division on all security-related
matters.
1.1.1. An alternate SPOC (ASPOC) must also be appointed by the Prime
Contractor and CM in the case of SPOC absence or unavailability.
1.1.2. On contracts with multiple prime contractors, the G-Contractor will
appoint the designated SPOC and ASPOC.
1.2. The SPOC’s responsibilities extend to all subcontractors, consultants, and sub-
consultants of the Prime Contractor and CM.
1.3. DEP Project Manager must notify the DEP Detective Bureau and appropriate
DEP Police Precinct Command Center based on location the names and contact
information of SPOC and ASPOC and expected contract duration. Updates must
be made of any changes. Subject line must include contract number and work
location(s)
1.4. All persons working under a DEP Contract or on DEP Property must pass a
security clearance by the DEP Police Detective Bureau.
1.5. No less than 10 days prior to the commencement of work, SPOC must submit a
Security Clearance Form (available from DEP Project Manager) to
SecurityClearance@dep.nyc.gov.
1.5.1. On the email subject line, list the contract number and main project
location, ex. CAT 210E – Eastview UV
1.6. Clearance Forms must either be typed or printed clearly and legibly.
1.6.1. Incomplete or illegible forms will not be processed.
1.7. Submissions to the Detective Bureau are to be from the SPOC, ASPOC, or the
DEP Project Manager only. Individual submissions will not be accepted.
1.7.1. The DEP Project Manager must be copied on all transmissions.
1.8. The DEP Detective Bureau will notify the SPOC and DEP Project Manager of all
workers who have been cleared. SPOC or DEP Project Manager will contact
DEP Detective Bureau to set up an appointment for the issuance of DEP Non-
Employee Identification Cards. Contact information for appointments are in
Security Clearance Information.
1.8.1. Workers who are not cleared will not be permitted on DEP Property.
1.8.2. Any additional or replacement workers must be submitted for security
clearance and issued DEP Non-Employee Identification Cards using the
same procedures set forth above.
1.8.3. Security Clearances are valid for one year from the date of issuance.
1.9. Identification Cards must be visibly worn while on site or at any other DEP
Facility.
1.9.1. Identification cards are valid for one year from the date of issuance.
1.9.2. Renewal of ID cards must be coordinated with the Detective Bureau after
passing a successful security re-clearance
1410
PAGE 36 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
2.0 Construction:
2.1. Nothing contained herein shall diminish in any way the responsibility of any
Contractor for safeguarding and protecting his own work, materials, tools and
equipment.
2.2. All security measures must be completed to the satisfaction of BPS SSE prior to
the start of work.
2.3. The contractor is required to report all suspicious, unusual, or dangerous
activities to DEP Police without delay to:
o Eastview Precinct (If Work Location is East of Hudson) at
1-914-593-7500 or 1-888-426-7433
o Ashokan Precinct (If Work Location is West of Hudson) at
1-845-657-8433
2.4. Emergencies must be reported immediately to:
o 911 and
o Eastview Precinct (If Work Location is East of Hudson) at
1-914-593-7500 or 1-888-426-7433
o Ashokan Precinct (If Work Location is West of Hudson) at
1-845-657-8433 or 1-845-657-6965
o Central number at location if site is at an existing facility.
2.5. If an unusual occurrence happens within the area of the construction site such as
theft, vandalism, civil disturbance, larceny, riots or terrorism or any crime within
the Penal Law of the State of New York, the contractor and / or its
representatives agree to inform without delay all official authorities including
DEP Police Eastview Precinct at 1-914-593-7500 or 1-888-426-7433 and to
cooperate fully in any official investigation.
2.6. If an accident, spill, or unusual hazard occurs within the area of the construction
site, the contractor and / or its representatives shall immediately inform DEP
Police Eastview Precinct at 1-914-593-7500 or 1-888-426-7433 and all official
authorities as required by law and to cooperate fully in any investigation.
2.7. The contractor, its representatives, and all subcontractors agree to cooperate with
the New York City Department of Investigation and the DEP Inspector General
in all matters within their jurisdiction and in accordance with Mayoral Order
16/78.
1411
PAGE 37 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
3.1. SPOC will be responsible for ensuring compliance with all DEP Police and
Security Directives and related facility policies by all contractor personnel. Non-
compliance on the part of contractor personnel may result in denial of future access
to the site, or a stop work order.
3.2. SPOC must submit the following project related information to DEP Police
Eastview Precinct (if work location is East of Hudson) or Ashokan Precinct (if
work location is West of Hudson) or by email prior to the first day of work.
Submissions must include the following:
a. Contract Number and Project Name
b. Name and contact information of Construction Security Point of
Contact and emergency contact list
c. Work Schedule
d. List of personnel accessing the site and company (include Security
Clearance Number)
e. List of all vehicles parked at site including make, color, model,
license #, and registered owner (include Security Clearance
Number)
3.3. SPOC should update list immediately to reflect any changes in personnel.
3.4. Identification Cards
3.4.1. All expired identification cards and/or those belonging to personnel who
no longer work at the site must be collected by SPOC and surrendered to
DEP Detective Bureau. This must be done even if ID Cards are not expired.
3.4.2. The SPOC will be responsible for ensuring compliance.
3.4.3. Names of those with outstanding ID Cards must be reported to the DEP
Police Detective Bureau.
3.5. Provide to related security booths, DEP Project Manager, and DEP Police
Eastview Precinct (if work location is East of Hudson) or Ashokan Precinct (if
work location is West of Hudson) weekly lists of all personnel working at the
site. List should remain current to reflect any changes to staff.
3.6. Keys – A list of all those who have keys to contractor entrance gates must be
provided to DEP Project Manager and kept current to reflect any changes. The
SPOC is responsible for collecting keys from all personnel who no longer work
at the site.
3.7. Deliveries - provide the following information to via email or fax DEP Police
Eastview Precinct (if work location is East of Hudson) or Ashokan Precinct (if
work location is West of Hudson) a Delivery Notification Form (available on
website or from BPS) at least a day in advance.
3.7.1. Prime Contractor SPOC is responsible for escorting deliveries and
coordinating with site security and DEP Police.
1412
PAGE 38 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
1413
PAGE 39 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
5.0 Other:
5.1. No firearms are permitted on DEP Property even with legal permit.
5.1.1. No firearms are to be stored during working hours in vehicles belonging to
those working at DEP Sites.
5.2. If construction site is located on the property of an existing operating facility,
construction and contractor personnel must comply with current facility policies.
This includes, but is not limited to the areas of security, health & safety,
evacuations, participation in all drills, and other requirements.
5.3. Press Inquiries / Requests for Information – Do not speak to any news/media/ or
press person or any inquisitive citizen regarding any matter, including any matter
of security pertaining to DEP: Instead:
5.3.1. Refer to DEP Press Office at (718) 595-7867
5.3.2. Notify DEP Police Eastview Precinct (if EOH) or Ashokan Precinct (if
WOH)
1414
PAGE 40 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
6.3. Visitors
6.3.1. Not permitted on DEP sites without prior permission from the
Commissioner or his/her appointed designee.
6.3.2. Requires advance submission of a Day Tour Form (available from DEP
Project Manager) to the appropriate DEP Police Command Center based
on location – submission of forms must come from the DEP Project
Manager of record
6.3.3. Subject line must list contract number and work location(s)
1415
PAGE 41 OF 42 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01140
CONTRACT DEL-260 G, E, H
Revised 08-16-16
1416
PAGE 42 OF 42 11/2017
DETAILED SPECIFICATION 01241 VALUE ENGINEERING PROPOSALS
CONTRACT DEL-260 G, H, E
SECTION 01241
Value Engineering Proposals
PART 1 GENERAL
1.01 SUMMARY
A. The Contractor is encouraged to and is authorized to develop, prepare and
submit to the Agency Chief Contracting Officer or his/her designee (the
“ACCO”), in writing, Value Engineering Proposals (VEPs) for modifying the
plans, Specifications or other requirements of the Contract for the sole purpose
of reducing the net cost of construction.
B. VEPs have true economic merit for a project when a net cost savings to the City
is realized after consideration of the City’s review and implementation costs,
plus related costs of other construction contracts that are impacted by the
Contractor’s VEP. VEPs shall not impair, in any manner, the essential functions
or characteristics of the project, including but not limited to service life,
economy of operation and ease of maintenance, desired appearance, design, and
safety standards.
01241-1 11/2017
DEP 9/24/2015
1417
DETAILED SPECIFICATION 01241 VALUE ENGINEERING PROPOSALS
CONTRACT DEL-260 G, H, E
2. The City’s cost to review, design and implement the VEP shall be
determined by the ACCO and fifty (50%) percent of such cost shall be
deducted from the total Contract price as part of a VEP change order.
3. Payment for an accepted VEP shall be reflected in the adjusted total
Contract price per the following:
a. original Contract price for the Work;
b. less fifty (50%) percent of Net Cost Savings;
c. less fifty (50%) percent of the City’s Cost.
1.10 SUBMITTALS
A. The Contractor’s VEP submittal shall include the following in order to be
considered for approval by the ACCO:
1. Cover letter proposing the VEP and written description.
2. Complete description of the difference between the existing Contract
requirements and those proposed, listing of advantages and
disadvantages associated with the VEP, and effect, if any, the VEP has
on the performance of the Work included in the Contract Documents.
3. Preliminary sketches.
4. List and analysis of the Contract requirements that must be changed if
the VEP is accepted, including proposed Specification requirements.
5. A separate, detailed cost estimate showing the affected portions of the
existing Contract requirements and the cost savings associated with the
VEP. The VEP cost estimate shall include an itemization of the
Contractor’s development and implementation costs along with all costs
attributable to Subcontractors. This cost estimate shall be correlated,
where required, with the original Detailed Estimate Breakdown
submitted by the Contractor.
6. Description and estimate of the costs the City may incur implementing
the VEP.
01241-3 11/2017
DEP 9/24/2015
1419
DETAILED SPECIFICATION 01241 VALUE ENGINEERING PROPOSALS
CONTRACT DEL-260 G, H, E
7. Prediction of effect the VEP will have on the City’s Operations and
Maintenance (O&M) costs should the VEP be accepted.
8. Statement of time by which a change order must be issued to achieve
maximum value and cost reduction, noting any time impact on Contract
milestones and completion date. This statement shall be correlated with
where required, with the baseline construction schedule in use for
monitoring progress.
9. If the ACCO notifies the Contractor that additional information is
required to evaluate the VEP, such information must be provided in a
timely manner; otherwise, the VEP will be rejected.
B. The VEP shall be submitted to the ACCO for review and processing.
C. VEPs may be submitted at any time following the construction Contract Notice
to Proceed and up to 90 days prior to the latest accepted schedule date for
Substantial Completion.
1.11 CONDITIONS
A. The following conditions shall apply to any VEP accepted by the ACCO:
1. Bid prices may not be based on the anticipated approval of a VEP, and
if a VEP is rejected, the Contractor will be required to complete the
Contract in accordance with the plans and Specifications at the prices
bid.
2. Where a VEP has been approved and implemented by change order,
but subsequent modifications to the VEP are necessary in order to adjust
to unanticipated field or other conditions, any further change order(s) to
implement those subsequent modifications will provide for payment for
any additional Work at prices no higher than those in the Contractor’s
bid, as if such Work was being done in accordance with the original
Contract requirements.
3. In the event that the Engineer determines that unsatisfactory results are
being obtained as a result of Work performed pursuant to an
implemented VEP, he/she may reject all or any portion of such Work
and direct its removal, and require the Contractor to proceed in
accordance with the original Contract requirements. The change order
required to “reverse” the VEP shall not entitle the Contractor to
compensation for any Work performed under the failed VEP or for its
removal. Such rejection or limitation of reimbursement shall not
constitute the basis of any claim against the City
4. All terms and conditions of the Contract, including quality of the Work
and inspection shall apply to a VEP accepted by the ACCO, as if the
VEP was included originally.
01241-4 11/2017
DEP 9/24/2015
1420
DETAILED SPECIFICATION 01241 VALUE ENGINEERING PROPOSALS
CONTRACT DEL-260 G, H, E
5. The Contractor shall have no claim against the City due to or arising
from the ACCO’s rejection of a VEP.
END OF SECTION
01241-5 11/2017
DEP 9/24/2015
1421
DETAILED SPECIFICATION 01241 VALUE ENGINEERING PROPOSALS
CONTRACT DEL-260 G, H, E
01241-6 11/2017
DEP 9/24/2015
1422
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
SECTION 01270
Measurement and Payment
PART I GENERAL
PART 2 PRODUCTS
1.02 PAYMENT
A. The total bid price shall include, as applicable, the following items in the bid
schedule of prices for each Contract.
B. Excluding allowances and unit price items, no separate payment will be made for
the Work specified in the Standard Construction Contract, General Conditions, and
Division 1 – General Requirements. The cost thereof shall be included in the lump
sum bid prices Items No. G-LS-1, E-LS-1 and H-LS-1 for Contracts DEL-260G
01270-1 11/2017
1423
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
PART 2 PRODUCTS
A. Lump sum contract items have been provided on the Schedule of Prices for the
Contracts as follows:
B. Payment under the respective Contract Item No. G-LS-1, E-LS-1 or H-LS-1 will
constitute full compensation for all Work and costs as shown in the Contract
Documents to complete the Project, with the exception of Allowances and Unit
Prices.
C. Where the Detailed Specifications are silent on Payment for Work specified under
an individual specification Section, it is understood that Payment will be made as
part of the respective lump sum price bid under Contract Item No. G-LS-1, E-LS-1
or H-LS-1.
2.02 ALLOWANCES
A. The following Allowances are to be included in the total bid for each of the
respective Contracts. Descriptions of each Allowance are included in the sections
referenced. Payment for Work performed under these Allowance items shall be
made in accordance with Article 26 of the Standard Construction Contract. The
Contractor will be reimbursed for the amount paid from the Allowances, with no
provision for overhead and profit.
01270-2 11/2017
1424
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
c. Payment for overruns and extra Work performed under this Allowance
item shall be made in accordance with Article 26 of the Standard
Construction Contract.
d. The Allowance shall also be used for the testing, remediation and
disposal of unforeseen existing hazardous/contaminated materials
encountered in the course of excavation, as specified in Detailed
Specification 02316G – Excavation.
1425
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
c. Payment for overruns and extra Work performed under this Allowance
item shall be made in accordance with Article 26 of the Standard
Construction Contract.
1426
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
a. Description:
1) Under Contract Item E-A-3, the Contractor shall include the cost
for furnishing all labor, materials, tools, equipment and
incidentals required for cleaning and maintenance of the
Resident Engineer’s parking lot, Resident Engineer’s trailer and
movable equipment, temporary services, temporary water and
sanitary, consumable supplies, and garbage disposal.
c. Payment:
1) Payment for Work performed under this Allowance item shall
be made in accordance with Article 26 of the Standard
Construction Contract.
c. Payment for Work performed under this Allowance item shall be made in
accordance with Article 26 of the Standard Construction Contract.
1427
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
c. Payment for Work performed under this Allowance item shall be made in
accordance with Article 26 of the Standard Construction Contract.
c. Payment for overruns and extra Work performed under this Allowance
item shall be made in accordance with Article 26 of the Standard
Construction Contract.
1428
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
c. Payment for overruns and extra Work performed under this Allowance
shall be made in accordance with Article 26 of the Standard Construction
Contract.
A. The following unit price Contract Items shall be included in the total bid of the
Contract. The Contractor shall write the proposed unit costs for each item and
calculate the bid price based on the estimated quantity included in the Schedule of
Prices.
c. Payment:
1) Payment for additional conduit, ordered in writing, will be made at
the Contract unit price bid per linear foot for Contract Items No. E-
UP-1a through E-UP-1h as follows:
a) E-UP-1a - Actual linear footage ¾-inch PVC coated rigid steel
conduit.
b) E-UP-1b - Actual linear footage 1-inch PVC coated rigid steel
conduit.
01270-7 11/2017
1429
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
c. Payment:
1) Payment for additional wire and cable, ordered in writing, will be
made at the Contract unit price bid per linear foot for Contract Items
E-UP-2a thru E-UP-2k as follows:
a) E-UP-2a- Actual linear footage of 2/C #16 TSP cable.
b) E-UP-2b- Actual linear footage of #14 AWG wire.
c) E-UP-2c- Actual linear footage of #12 AWG wire.
d) E-UP-2d- Actual linear footage of #10 AWG wire.
e) E-UP-2e- Actual linear footage of #8 AWG wire.
f) E-UP-2f- Actual linear footage of #6 AWG wire.
g) E-UP-2g- Actual linear footage of #4 AWG wire.
h) E-UP-2h- Actual linear footage #1/0 AWG wire.
i) E-UP-2i- Actual linear footage of #4/0 AWG wire.
j) E-UP-2j- Actual linear footage of 500 KCMIL wire.
k) E-UP-2k- Actual linear footage of 600 KCMIL wire.
01270-8 11/2017
1430
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
END OF SECTION
01270-9 11/2017
1431
DETAILED SPECIFICATION 01270 – MEASUREMENT AND PAYMENT
CONTRACT DEL-260 G, H, E
01270-10 11/2017
1432
DETAILED SPECIFICATION 01291 – DETAILED ESTIMATE BREAKDOWN
CONTRACT DEL-260 G, H, E
SECTION 01291
Detailed Estimate Breakdown
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any work required under this
Section and each Contractor shall include all costs thereof in its lump sum price
bid for the Contract.
1.04 DEFINITIONS
A. Detailed Estimate Breakdown: A breakdown of the (Contractor’s) lump sum
bid price for the Contract, or of lump sums bid for items of the Contract,
showing the various operations to be performed under the Contract and the
value of each of such operations, the total of such items to equal the lump sum
price bid. The Contractor shall also submit such other information relating to
the bid breakdown as directed by the Resident Engineer.
B. Logic and Duration Schedule: See Detailed Specification 01321 – Progress
Schedule for a definition of the term.
C. Work Result: Permanent or temporary aspect of a construction project achieved
in the production stage or by subsequent alteration, maintenance or demolition
processes, through the application of a particular skill or trade to construction
resources. (CSI, Section Format 2009)
1.05 DESCRIPTION
A. This Section describes the process whereby the Detailed Estimate Breakdown
(DEB) shall be developed in parallel and in coordination with the development
of the Logic and Duration Schedule in accordance with the requirements of
Section 01321 – Progress Schedule
01291-1 11/2017
DEP 3/23/2016
1433
DETAILED SPECIFICATION 01291 – DETAILED ESTIMATE BREAKDOWN
CONTRACT DEL-260 G, H, E
01291-2 11/2017
DEP 3/23/2016
1434
DETAILED SPECIFICATION 01291 – DETAILED ESTIMATE BREAKDOWN
CONTRACT DEL-260 G, H, E
1. To assist in the correlation of the DEB and the Logic and Duration
Schedule, the Contractor shall provide a cross reference listing which
shall be furnished in two (2) parts. The first part shall list each
scheduled activity with the breakdown of the respective valued items
making up the total cost of the activity. The second part shall list the
valued item with the respective scheduled activity or activities that make
up the total cost indicated. These listings shall be updated and submitted
in conjunction with the Logic and Duration Schedule monthly
submittals as specified in Section 01321 – Progress Schedule.
F. Changes to the Detailed Estimate Breakdown
1. Changes to the Logic and Duration Schedule which add activities not
included in the original schedule, but included in the original scope of
Work (schedule omissions or errors) shall have values assigned in the
DEB as approved by the Engineer. Necessary revisions will incorporate
the Cross Reference Listing.
1.06 ATTACHMENTS
A. Table 1 – Preliminary Detailed Estimate Breakdown (Major Work Results)
B. Table 2 – Final Detailed Estimate Breakdown (Minimum Detail Required)
END OF SECTION
01291-3 11/2017
DEP 3/23/2016
1435
DETAILED SPECIFICATION 01291 – DETAILED ESTIMATE BREAKDOWN
CONTRACT DEL-260 G, H, E
01291-4 11/2017
DEP 3/23/2016
1436
ATTACHMENTS DETAILED SPECIFICATION 01291
CONTRACT DEL-260 G, H, E
TABLE 1
PRELIMINARY DETAILED ESTIMATE BREAKDOWN
(Major Work Results)
1. Area/ Process/Location
1. Area/ Process/Location
1. Area/ Process/Location
*********
PAGE 1 OF 4 11/2017
DEP 3/23/2016
1437
ATTACHMENTS DETAILED SPECIFICATION 01291
CONTRACT DEL-260 G, H, E
PAGE 2 OF 4 11/2017
DEP 3/23/2016
1438
ATTACHMENTS – DETAILED SPECIFICATION 01291
CONTRACT DEL-260 G, H, E
TABLE 2
FINAL DETAILED ESTIMATE BREAKDOWN
(Minimum Detail Required for Contracts DEL-260-G, H, E)
1. GENERAL REQUIREMENTS
1. AREA/PROCESS/LOCATION
a. Site Construction....................................................................Div. 02
i. Earthwork
ii. Site Demolition & Removals
iii. Plantings
iv. Site Barriers & Fencing
v. Selective Demolition
b. Concrete .................................................................................Div. 03
i. CIP Concrete
c. Masonry .................................................................................Div. 04
ii. Unit Masonry
d. Thermal & Moisture Protection .............................................Div. 07
i. Firestopping
e. Specialties ..............................................................................Div. 10
i. Fire Protection Specialties
1. AREA/PROCESS/LOCATION
a. Mechanical .............................................................................Div. 15
i. HVAC
1. AREA/PROCESS/LOCATION
PAGE 3 OF 4 11/2017
DEP 3/23/2016
1439
ATTACHMENTS – DETAILED SPECIFICATION 01291
CONTRACT DEL-260 G, H, E
*********
PAGE 4 OF 4 11/2017
DEP 3/23/2016
1440
DETAILED SPECIFICATION 01310 – PROJECT COORDINATION
CONTRACT DEL-260 G, H, E
SECTION 01310
Project Coordination
PART 1 GENERAL
A. Related Specifications
B. Contractor Cooperation
A. The Contractors shall allow the City, the Engineer and other contractors or their
agents, to enter upon the Site for the purpose of constructing, maintaining,
removing, repairing, altering or replacing such equipment, materials, structures
which may be required to be installed at or in the Work. The Contractors shall
cooperate with all the aforesaid parties and shall allow reasonable provisions for the
prosecution of any other Work by the City, or others, to be done in connection with
the Work, or in connection with normal use of the facilities.
B. The Contractors shall cooperate fully with the City, the Engineer, and any other
Contractors employed on the Work or otherwise working at the Site, to effect proper
coordination and progress.
C. The Contractors are advised that, other construction contracts near or at the project
Site may be in progress on the starting date of this Contract or will be started while
this Contract is in progress. The Contractors shall cooperate with the contractors for
these other contracts as outlined in Article 18 of the General Conditions to ensure
that the Work under these other contracts is not impeded or interfered with. Any
disagreements with these other contractors shall be brought to the immediate
attention of the Engineer, whose judgment as to the resolution of the disagreement
shall be final, binding, and conclusive.
D. The Contractors are advised that they shall have shared use of Site and interior
access roads.
01310-1 11/2017
1441
DETAILED SPECIFICATION 01310 – PROJECT COORDINATION
CONTRACT DEL-260 G, H, E
E. The Contractors shall coordinate its Work installed under this Contract and other
contracts for the satisfactory installation and operation of the facility.
F. The Contractors shall review installation procedures under other section and
Contracts and coordinate them with their Work specified in the Contract.
G. Each Contractor shall notify the other Prime Contractor in advance of the
installation of the Work included to provide them with sufficient time for
installation and coordination of interrelated items that are included in their
Contracts and that must be installed in conjunction with their Work.
END OF SECTION
01310-2 11/2017
1442
DETAILED SPECIFICATION 01311 - PROJECT PARTNERING
CONTRACTS DEL-260 G, H, E
SECTION 01311
Project Partnering
PART 1 GENERAL
1.01 SUMMARY
A. The Contractors shall participate in "project partnering" along with DEP and its
consultants (Engineer/ Construction Manager) for this project. Each Contractor
should also include its major subcontractors and suppliers in partnering so that
these participants may "buy-in" to the concept and work cooperatively with
other parties on the project.
B. Partnering is considered important to the overall success of this project by DEP,
its Engineer, and its construction manager. It is also important to this project
that the Contractors be equally concerned with quality, performance, budget,
and schedule and that they will endorse and adopt Partnering as an effective
tool for achieving these objectives.
C. Partnering will be effective only if all parties willingly and enthusiastically
enter into this cooperative arrangement which is supported by each entity at the
highest level in their organizations.
D. Section Includes:
1. Project partnering and goals;
2. Initial workshop and follow-up;
3. Partnering Facilitator and project charter.
1.02 PAYMENT
A. No separate payment will be made for performing any Work required under this
Section and the Contractors shall include all costs thereof in their lump sum
price bids for the Contracts.
1.03 DEFINITIONS
1. "Partnering" refers to the team-building required to create mutual trust
among the prime Contractors, Subcontractors, representatives of DEP
and its consulting firms, and other stakeholders in a construction project,
and respect for one another’s roles in the project and recognition of the
risks inherent in those roles, so that all members of the team
(participants) become partners in executing and completing the Work.
a. Unless otherwise specified, the Bureau of Engineering Design
& Construction (BEDC) will represent DEP in construction
projects.
01311-1 11/2017
DEP 3/15/2016
1443
DETAILED SPECIFICATION 01311 - PROJECT PARTNERING
CONTRACTS DEL-260 G, H, E
01311-2 11/2017
DEP 3/15/2016
1444
DETAILED SPECIFICATION 01311 - PROJECT PARTNERING
CONTRACTS DEL-260 G, H, E
01311-3 11/2017
DEP 3/15/2016
1445
DETAILED SPECIFICATION 01311 - PROJECT PARTNERING
CONTRACTS DEL-260 G, H, E
1.08 SUBMITTALS
A. Within 30 days after the NTP, the Contractor for Contract DEL-260E -
Electrical shall provide the candidates’ full names and contact information and
the following information:
1. Resume showing certification or training;
2. Resume showing experience and qualifications;
3. Resume showing past facilitation participation.
01311-4 11/2017
DEP 3/15/2016
1446
DETAILED SPECIFICATION 01311 - PROJECT PARTNERING
CONTRACTS DEL-260 G, H, E
END OF SECTION
01311-5 11/2017
DEP 3/15/2016
1447
DETAILED SPECIFICATION 01311 - PROJECT PARTNERING
CONTRACTS DEL-260 G, H, E
01311-6 11/2017
1448 DEP 3/15/2016
DETAILED SPECIFICATION 01312 – WEB-BASED PROJECT MANAGEMENT
INFORMATION SYSTEM
CONTRACT DEL-260 G, H, E
SECTION 01312
Web-based Project Management Information System
PART 1 GENERAL
1.01 SUMMARY
A. This Section describes the requirements for the Contractor’s use of the DEP’s
enterprise web-based Project Management Information System (“PMIS” or
“the System”) to manage all project communications, workflows and document
submittals.
1.02 PAYMENT
A. No separate payment will be made for performing any Work of the Section and
the Contractor shall include all costs thereof in the lump sum price bid for the
Contract.
B. There will be no licensing cost incurred by the Contractor. The DEP will
determine and provide the appropriate number of user registrations to the
Contractor to access and utilize the System.
1.04 DESCRIPTION
A. Use and Operation of the System:
1. The Contractor shall utilize the DEP’s web-based PMIS for electronic
submittal of all data and documents throughout the duration of the
Contract.
2. The System is required for use by all participants in the project including
DEP, the construction manager, Engineer, Contractor, and all other
users authorized by the DEP.
3. The System will operate primarily on an e-Builder, Inc. (www.e-
builder.net) platform that will be administered by DEP and the
construction manager. The joint use of this System will facilitate
electronic exchange of information, automation of key processes, and
overall management of the Contract.
01312-1 11/2017
DEP 3/15/2016
1449
DETAILED SPECIFICATION 01312 – WEB-BASED PROJECT MANAGEMENT
INFORMATION SYSTEM
CONTRACT DEL-260 G, H, E
01312-2 11/2017
DEP 3/15/2016
1450
DETAILED SPECIFICATION 01312 – WEB-BASED PROJECT MANAGEMENT
INFORMATION SYSTEM
CONTRACT DEL-260 G, H, E
01312-3 11/2017
DEP 3/15/2016
1451
DETAILED SPECIFICATION 01312 – WEB-BASED PROJECT MANAGEMENT
INFORMATION SYSTEM
CONTRACT DEL-260 G, H, E
2. DEP owns the PMIS, and will provide initial training and rollout
services after Contract award. DEP will provide overall System
administration during the Contract period. The construction manager
will have a System administrator for the project with limited System
administration support responsibilities including ongoing training of the
Contractor team.
3. The Contractor shall provide a list of its key personnel designated for
access to the System for the City’s approval. The Contractor is
responsible for timely notifying the City and the Engineer of any
changes in personnel that require adding or removing authorized users
from the System. DEP reserves the right to perform a security check on
all potential users. The Contractor may be given the rights to provide
System access to additional personnel or Subcontractors. .
4. The System user license fees will be paid by DEP.
F. Connectivity
1. PMIS is a web-based environment and therefore subject to the inherent
speed and connectivity problems of the internet. The Contractor is
responsible for its own connectivity to the Internet. The System’s
response time is dependent on the equipment used to access it, including
processor speed, internet access speed, etc. and current traffic on the
internet. The City will not be liable for damages resulting from any
delays associated with the use of the System including, but not limited
to: slow response time, downtime periods, connectivity problems, or
loss of information. Moreover, such delay shall not be deemed a
sufficient basis for a time extension of or cost adjustment to the
Contract.
G. Training
1. DEP, through the System vendor or the System vendor’s qualified
representative, will provide on-site training in the use and functionality
of the System. Training sessions will be provided for employees of the
construction manager, Engineer, the City, and the Contractor. Each
training session will be for eight (8) hours duration. The Contractor shall
have two (2) qualified persons attend the training. One (1) refresher
training session will be provided upon request.
1.06 SUBMITTALS
A. Within thirty days of issuance of the Notice to Proceed, the Contractor shall
submit for approval by the Engineer, a list of the Contractor's and its
Subcontractor’s key personnel who have been designated to have access to the
System. The list shall include descriptions of the designated individual’s roles
and responsibilities for this Project. The Contractor should also identify its
organization’s System administrator on the list.
B. The Contractor shall submit the name and qualifications of its designated
Document Control Specialist. Any change in the individual serving as
Document Control Specialist shall be submitted to and coordinated with the
construction manager.
PART 3 EXECUTION
01312-5 11/2017
DEP 3/15/2016
1453
DETAILED SPECIFICATION 01312 – WEB-BASED PROJECT MANAGEMENT
INFORMATION SYSTEM
CONTRACT DEL-260 G, H, E
the original, searchable PDF files from the manufacturer and not scanned files
which are not searchable. Examples of product data include, but are not limited
to:
1. Manufacturers’ printed literature;
2. Preprinted product specification data and installation instructions.
E. All correspondence and pre-construction administrative submittals shall be
submitted using the System. Examples of administrative submittals include, but
are not limited to:
1. Digging permits and notices for excavation;
2. Requests for Deviation (RFDs) for product substitutions;
3. List of contact personnel;
4. Notices for roadway interruption, Work outside regular hours, and
utility cut overs;
5. Requests for Information (RFIs);
6. Network Analysis Schedules and associated reports and updates;
7. Each schedule submittal specified in Detailed Specification 01321 –
Progress Schedule shall be submitted as a native backed-up file (.PRX
or XER) of the scheduling program being used. The schedule will also
be posted as a PDF file in the format specified in Detailed Specification
01321 – Progress Schedule.
8. Plans for safety, demolition, environmental protection, and similar
activities;
9. Quality control plan(s), testing plan and log, quality control reports,
production reports, quality control specialist reports, preparatory phase
checklist, initial phase checklist, field test reports, summary reports,
rework items list, etc.;
10. Meeting minutes for quality control meetings, progress meetings, pre-
installation meetings, etc;
11. Any general correspondence submitted.
F. Compliance submittals such as test reports, certificates, and manufacturer’s
field report submittals shall be submitted through the System as PDF
attachments. Examples of compliance submittals include, but are not limited to:
1. Field test reports;
2. Quality control certifications;
3. Manufacturers’ documentation and certifications for quality of products
and materials provided.
01312-6 11/2017
DEP 3/15/2016
1454
DETAILED SPECIFICATION 01312 – WEB-BASED PROJECT MANAGEMENT
INFORMATION SYSTEM
CONTRACT DEL-260 G, H, E
END OF SECTION
01312-7 11/2017
DEP 3/15/2016
1455
DETAILED SPECIFICATION 01312 – WEB-BASED PROJECT MANAGEMENT
INFORMATION SYSTEM
CONTRACT DEL-260 G, H, E
01312-8 11/2017
DEP 3/15/2016
1456
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
SECTION 01321
Progress Schedule
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes
1. CPM and Project Schedule Software
2. Work Breakdown Structure (WBS)
3. Activities and Activity Code Structure
4. Sequence and Interdependence of Work Activities
5. Project Calendars
6. Activity Labor and Resource Data
7. CPM Progress Meeting and Reports
8. Remedial Measures and Recovery Schedule
B. Wherever the words “the Contractor” are used, it shall be taken to mean “each
Contractor”. Where an individual Contractor is responsible for a particular item
of work, the Specifications shall specifically name that Contractor.
C. For convenience, an index of this Section is presented below:
1.02 PAYMENT
A. The Contractor shall include the cost for furnishing the construction scheduling
services as described herein in its lump sum price bid for the Contract. The
Contractor for Contract DEL-260E must supply adequate funding to procure a
qualified CPM scheduling consultant for the duration of the Contract.
1.03 DEFINITIONS
Term Definition
Activity A representation of a discrete portion of the overall
scope of Work or an event through Duration and
description.
Baseline Construction The planned, detailed Critical Path Method (CPM)
Schedule schedule of activities, including all Logic, Durations,
Resource and Cost Loading, and showing the entire
scope of Work, which has been accepted by DEP.
Critical Path Method (CPM) A management technique used to plan and control a
project which combines all relevant information into a
single plan defining the sequence and Duration of
operations, and depicting the interrelationship of the
Work elements required to complete the project. The
critical path is defined as the longest sequence of
activities in a network which establishes the minimum
length of time for accomplishment of the end event of
the project.
Current Construction The most recently updated schedule that captures
Schedule progress to date and forecasts the Early Start/Early
Finish for each Activity and the remaining cash flow,
depicted with the open bar chart activity line with
corresponding schedule dates shown.
Data Date The date used as a starting point for scheduling
calculations. The Data Date is changed to the current
end of period date when a schedule is updated for
progress.
01321-2 11/2017
DEP 1/13/2017
1458
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
Term Definition
Duration The amount of time, in workdays, an Activity will take
to perform once begun and continuously performed
until complete.
Early Finish The earliest estimated date an Activity is calculated to
be complete, based on the estimated performance of all
prior Activities to which the Activity is logically
connected in a progressive relationship.
Early Start The earliest estimated date an Activity is calculated to
begin, based on the estimated performance of all prior
Activities to which the Activity is logically connected
in a progressive relationship.
Float The calculated amount of time that the estimated start
or finish of an Activity can be delayed without
impacting the start or finish of other downstream
Activities logically connected in a progressive
relationship.
Fragnet Fragmentary network: a portion of the project schedule
detailing impacts of an event on specific activities in
the broader schedule.
Late Finish An estimate of the latest plausible date an Activity’s
completion can be postponed until without rendering
as unachievable the required completion of any
downstream milestones to which the Activity is
Logically connected to in a progressive relationship.
Late Start An estimate of the latest plausible date an Activity’s
start can be postponed until without rendering as
unachievable the required completion of any
downstream milestones to which the Activity is
Logically connected to in a progressive relationship.
Logic A direct progressive relationship between Activities
where one Activity’s performance restricts the
performance of another Activity
Original Duration The estimated amount of time, in workdays, an
Activity is expected to take to complete at the
beginning of a project as anticipated by the Contractor
based on its planned means and methods at time of bid
and documented in the baseline.
01321-3 11/2017
DEP 1/13/2017
1459
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
Term Definition
Percent Complete The percentage of the scope of Work represented by an
Activity completed as of the Data Date calculated by
dividing the progress earned by the budgeted value.
Remaining Duration The amount of time, in workdays, the remaining scope
of Work represented by an Activity is expected to take
to complete at the current Data Date
Resource and Cost Loading Values assigned for estimated manpower, equipment
and/or materials necessary to complete the scope of
Work represented by a specific Activity.
Total Float The amount of time the start or finish of an Activity
can be delayed without affecting the project
completion date.
Work Breakdown Structure WBS is a deliverable-oriented decomposition of a
(WBS) project into smaller components. A WBS also
provides the necessary framework for detailed cost
estimating and control along with providing guidance
for schedule development and control.
01321-4 11/2017
DEP 1/13/2017
1460
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
1.06 ACTIVITIES
A. Activities included in the CPM schedule shall be of sufficient detail to assure
adequate planning and execution of the Work, such that, in the judgment of the
Engineer, it provides an appropriate basis for forecasting, monitoring and
evaluating the progress of the Work.
1. Activities shall conform to the following requirements:
a. Subdivide the total scope of Contract Work into Activities of
Duration no longer than twenty working days each, except as
to non-construction activities (such as purchase of materials,
delivery of materials, delivery of equipment and concrete
curing) and any other Activities for which the Engineer may
approve longer Duration. The Duration of the Activities
representing the Engineer’s approval of items such as Shop
Drawing submittals, drawing submittals, requests for
manufacturer approval, requests for Subcontractor approval,
etc. shall not be less than twenty calendar days but may be
longer if the detail and complexity of the submittal warrant.
b. The construction time as determined by the CPM schedule
from Early Start to Late Finish for any sub-phase, phase or the
entire project shall not exceed the Contract time specified or
shown in the Contract Documents.
c. One day shall be the smallest time unit shown unless otherwise
directed by the Engineer.
d. Activity descriptions shall contain consistent terminology such
that the scope of Work represented is readily identifiable for
assessment of completion.
e. Activities labeled "start," "continue," or "complete," will not be
allowed. Lead and lags will be acceptable only if the
description accurately identifies such a restraint and if they are
realistic with respect to the scheduling and sequencing of the
Work and overall control of the project.
f. Show the following on each Activity, as directed by the
Engineer:
01321-5 11/2017
DEP 1/13/2017
1461
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
01321-6 11/2017
DEP 1/13/2017
1462
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
01321-8 11/2017
DEP 1/13/2017
1464
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
C. All resource loading shall be coded to the Contract identifier under a “root.”
Since resource loading cannot be project-specific, this root heading is needed
to keep the database segregated.
01321-10 11/2017
DEP 1/13/2017
1466
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
1.12 SUBMITTALS
A. The qualifications of the CPM consultant shall be submitted to the Engineer for
approval within seven (7) calendar days after the NTP. The Engineer will
respond to the submittal within seven (7) calendar days of submittal receipt.
B. The preliminary CPM Schedule shall be submitted fifteen (15) calendar days
after NTP in accordance with Article 9 in the Standard Construction Contract
and this Section. The preliminary CPM Schedule shall include:
1. All critical mobilization, project set-up, procurement, and construction
activities in each of the major Work areas required during the first 180
calendar days of Contract time after the NTP, including submittals and
permitting;
2. The balance of the Work depicted in summary activities by MLS
(milestone), AREA (area), SYS (system) and RESP (responsibility).
(See Activity Code Structures for MLS, AREA, SYS and RESP in
Exhibit A of this Section);
01321-11 11/2017
DEP 1/13/2017
1467
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
3. All submittal and procurement activities for long lead items necessary
to meet all project milestones;
4. The project’s overall critical path and each milestone’s critical path.
5. An electronic copy of the schedule in Primavera Project Planner (.xer)
format.
C. Within fourteen (14) calendar days after submittal of the preliminary CPM
Schedule, the Engineer will notify the Electrical Contractor of the acceptance,
rejection, or acceptance with comments of the preliminary CPM Schedule. If
the preliminary CPM Schedule has been rejected, or accepted with comments,
the Contractor shall address all comments and re-submit within 14 calendar
days for review. The submittal process shall continue until the Engineer accepts
the preliminary CPM schedule with no comments.
D. The final, complete and detailed CPM Schedule required for submittal under
this Section shall be composed of two parts, with each part due as follows:
1. Part 1 -- Logic and Duration Schedule is due within sixty (60) calendar
days after NTP.
a. Submit an electronic copy of the schedule in Primavera Project
Planner (.xer) format, schedule reports, and the narrative report
as specified within this Section.
b. This schedule is at the final level of detail for each Activity,
containing the required relationships completely identified and
the Duration of each Activity correctly depicted and coded in
accordance with this Section.
c. This Baseline Construction Schedule shall identify all Contract
milestones.
i. If the schedule reflects completion of a milestone or
completion of Contract Work earlier than specified in the
General Conditions, this in no way revises or voids the
dates set forth in the Contract. The dates specified in the
Contract govern.
ii. Where the schedule reflects such an early completion
date, the schedule may be accepted by the Engineer with
the Contractor’s understanding that no claim for
additional Contract time or an increase in the Contract
price shall be made by the Contractor as the result of
failure to complete the Work by the earlier date shown on
the schedule.
d. This schedule shall show the overall schedule requirements as
set forth in Schedule “A” of the General Conditions being met.
01321-12 11/2017
DEP 1/13/2017
1468
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
01321-13 11/2017
DEP 1/13/2017
1469
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
H. The Contractor shall have no claim for damages by reason of the failure of the
Engineer to give timely acceptance or comments on any progress schedule
under this Section.
I. The monthly update schedule submittal to the Engineer shall include the
following:
1. An electronic copy of the schedule in Primavera Project Planner (.xer)
format, Data Date and monthly period clearly marked.
2. Electronic (.pdf) format copy of the CPM computer printouts in bar
chart form, including:
a. A comparison of the Baseline Schedule activities against
current update activities organized and summarized by
milestone, AREA, and DIV according to the requirements for
Activity codes in this Section, or as otherwise directed by the
Engineer. Each Activity shall have two bars with different
colors (one showing the current schedule and one showing the
Baseline Schedule).
b. A comparison of current activities against the prior month’s
activities organized and summarized by milestone, AREA, and
DIV according to the requirements for Activity codes in this
Section, or as otherwise directed by the Engineer. Each
Activity summary shall have two bars with different colors
(one showing the current schedule and one showing the prior
month’s update schedule).
c. A clear presentation of the specific detailed Activities making
up the critical path(s) for the project and for each milestone.
3. Electronic (.pdf) format copy of the Narrative Report as outlined in this
Section.
J. Comments made by the Engineer on the initial and monthly updated Current
Construction Schedule will not relieve the Contractor from compliance with the
requirements of the Contract Documents. This review is only for general
conformance with the schedule concept of the project and general compliance
with the information given in the Contract Documents.
update/revise the schedule (plan) of the Work for the balance of the project. The
updated schedule and draft narrative report shall be furnished to the Engineer
at least 48 hours prior to the meeting and be distributed by the Electrical
Contractor in hard copy at the meeting for review.
To update the CPM schedule, the Contractor shall:
1. Enter actual start and completion dates for those activities started and/or
completed during the previous reporting period;
2. For activities in progress, indicate the Remaining Duration correlating
to an accurate forecasted completion date and physical percentage
complete to date (Percent Complete is to reflect the actual quantity of
Work completed, and is separate from any actual or Remaining
Duration calculation). Review, and revise as necessary, the network
logic for the Remaining Duration of the Work from the update to the
estimated completion date;
3. For activities not yet started, review, and revise as required, the
necessary Logic, the Durations of Work and the estimated start and
completion dates;
4. Enter, for each applicable Activity, actual installed quantities
information;
5. For identified construction change requests, Extra Work or change
orders, add the appropriate detailed schedule Activities upon submittal
of Form 1 for changes in the Work. The change order review and
registration Fragnet will be provided by the Engineer and shall include
the following Activities in sequence:
a. Submittal of Form 1 on the actual date submitted;
b. Contractor pricing of the identified change subsequent to
submittal of Form 1;
c. Pricing negotiations;
d. Comptroller review and registration; followed by;
e. Detailed submittal and construction Activities with correct
Activity coding as specified within this Section.
C. The total Duration to be initially added to any schedule update reflecting the
Activities from submittal of Form 1 to the registration of any specific change
order, shall be in accordance with the Fragnet provided by the Engineer and
shall be incorporated into the monthly schedule update following the submittal
of Form 1 for the change in Work. The forecasted construction Activities shall
be logically tied to the appropriate predecessor and successor base Contract
Activities and contain all of the required Logic, Duration, and Resource
Loading specified for the detailed CPM schedule Activities.
01321-17 11/2017
DEP 1/13/2017
1473
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
D. In the event the Contractor begins performance in the field of identified Extra
Work during the update period, the monthly progress schedule update shall
reflect the actual start date of the Work, and any predecessor Logic ties or
restraints shall be broken in order to accurately forecast completion of the
identified Extra Work Activity. This will allow for accurate forecasting of the
successor Work Activities and completion milestones.
1. Annotate updated status information on the CPM schedule update in a
manner that will graphically depict the current status of the Work;
2. Should discrepancies regarding data/information accuracy be noted
during the review meeting or other discussions, the Engineer may direct
the Contractor to adjust the percentage completion, Remaining Duration
and actual dates to selected activities and re-issue the updated schedule
and reports.
E. Default progress data provided from the scheduling system shall not be allowed.
Actual start and finish dates and Remaining Durations of Activities shall not be
automatically updated by default mechanisms that may be included in CPM
scheduling software systems. Actual start and finish dates on the CPM schedule
shall match those dates provided from the Contractor’s Daily Quality Control
Reports. Failure of the Contractor to document the actual start and finish dates
on the Contractor Daily Quality Control Report for every in-progress or
completed Activity, and to ensure that the data contained on the Contractor
Daily Quality Control Reports is the sole basis for schedule updating, shall
result in the disapproval of the Contractor's submittal.
F. Activities that have reported progress without predecessor Activities being
completed (out-of-sequence progress) will not be allowed except on a case-by-
case basis with the approval of the Engineer. A written explanation for each
instance shall be included in the monthly submittal.
G. The Contractor shall not constrain the schedule with artificial Logic ties and or
constraint dates and or any other scheduling techniques that may distort the
Activity Float and Total Float associated with the critical path Activities and
the schedule in general.
H. In addition to the requirements of the General Conditions, the Contractor shall
submit monthly the proposed correlated sequence and estimated dates for
submission, approval and final submission activities for the following:
1. Working drawings submittals;
2. Equipment operation and maintenance manuals submittals;
3. Witness shop tests;
4. Delivery of materials and equipment to Site;
5. Final field tests;
6. Special tools and lubricant deliveries;
01321-18 11/2017
DEP 1/13/2017
1474
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
01321-19 11/2017
DEP 1/13/2017
1475
DETAILED SPECIFICATION 01321 – PROGRESS SCHEDULE
CONTRACTS DEL-260 G, H, E
4. Submit to the Engineer for review a written statement of the steps the
Contractor intends to take to remove or arrest the delay to the schedule.
The Contractor shall promptly provide the necessary level of effort to
bring the Work back on schedule.
B. The Engineer may require the Contractor to add to its equipment and materials
or construction forces, as well as increase the working hours, if operations for
critical, less critical or non-critical activities fall behind the Contractor's
Baseline Schedule at any time during the construction period.
C. The Engineer may require the Contractor, at any time during the project and at
no additional cost to the City, to develop a more detailed schedule/Fragnet than
depicted in the detailed Baseline Schedule to provide a clearer understanding
of the effort needed to complete a specific area of Work or task.
D. Should the Contractor fall behind schedule, the Engineer may require the
Contractor to prepare a recovery schedule for Engineer review and acceptance.
The recovery schedule shall propose alternative methods, overtime, and other
means available to the Contractor to recover the schedule slippage incurred to
date.
1.16 ATTACHMENTS
A. Exhibit 1 - Work Breakdown Structure
B. Exhibit 2 - Activity ID Format
C. Exhibit 3 – Schedule Milestones
D. Exhibit 4 – Proposed Activity Codes
E. Exhibit 5 – Project Calendars
END OF SECTION
01321-20 11/2017
DEP 1/13/2017
1476
ATTACHMENTS –DETAILED SPECIFICATION 01321
CONTRACTS DEL-260 G, H, E
PAGE 1 OF 8 11/2017
DEP 4/25/2016
1477
ATTACHMENTS –DETAILED SPECIFICATION 01321
CONTRACTS DEL-260 G, H, E
*********
1. Activity ID format: Activity ID’s shall be preceded by the Contract identifier: DEL-
260G-…, DEL-260H - … , DEL-260E-…
2. Do not use the letters X or Z within the activity ID as these are reserved for DEP
use
3. For Activities added to the schedule during the project representing Contract
change order execution and Extra Work, the Contractor shall insert “CO” after the
Contract identifier and use the succeeding numbers to identify the change order
number.
*********
*********
PAGE 3 OF 8 11/2017
DEP 4/25/2016
1479
ATTACHMENTS –DETAILED SPECIFICATION 01321
CONTRACTS DEL-260 G, H, E
M2 2 Exterior Complete
M3 3 Interior Complete
M4 4 Substantial Completion
BASM 3 Basement
PAGE 4 OF 8 11/2017
DEP 4/25/2016
1480
ATTACHMENTS –DETAILED SPECIFICATION 01321
CONTRACTS DEL-260 G, H, E
MEZZ 7 Mezzanine
01 1 General Requirements
02 2 Site Clearing
03 3 Site Earthwork
04 4 Utilities
05 5 Access Roads
06 6 Temp Facilities
07 7 Erosion Control
08 8 Concrete
09 9 Landscape
10 10 Drainage
11 11 Temp Power
12 12 Lighting
13 13 Dewatering
PAGE 5 OF 8 11/2017
DEP 4/25/2016
1481
ATTACHMENTS –DETAILED SPECIFICATION 01321
CONTRACTS DEL-260 G, H, E
14 14 Masonry
15 15 Metals
19 19 Finishes
20 20 Specialties
21 21 Equipment
22 22 Furnishings
23 23 Special Construction
24 24 Conveying Systems
25 25 Mechanical
26 26 Electrical
28 28 Site Restoration
29 29 Piping modifications
30 30 Electrical modifications
31 31 Maintenance Activities
PAGE 6 OF 8 11/2017
DEP 4/25/2016
1482
ATTACHMENTS –DETAILED SPECIFICATION 01321
CONTRACTS DEL-260 G, H, E
8. DEL-260 _Point of Contact DEP Accountable Manager. This Activity Code field
should be defined as being seven digits in length.
TBD 1 TBD
13. In addition to the required Activity coding outlined above, the Engineer may direct
the Contractor to provide additional Activity coding, at no additional cost to the City,
in order to facilitate the management of the project and schedule. Additional Activity
coding may include:
a. SUBC – Code designating major subcontractors or vendors;
b. SYST – Code designating process or functional system;
c. TYPE – Code designating general type of Work;
PAGE 7 OF 8 11/2017
DEP 4/25/2016
1483
ATTACHMENTS –DETAILED SPECIFICATION 01321
CONTRACTS DEL-260 G, H, E
*********
*********
PAGE 8 OF 8 11/2017
DEP 4/25/2016
1484
DETAILED SPECIFICATION 01323 - JOB PHOTOGRAPHS AND VIDEOS
CONTRACT DEL-260 G, H, E
SECTION 01323
Job Photographs and Videos
PART 1 GENERAL
1.02 PAYMENT
A. The cost of furnishing the goods and services described herein shall be included
in the lump sum price bid for Contract DEL-260E Electrical item E-LS-1.
B. In the event that fewer than the specified number of photographs is required,
the Contractor shall credit the City twenty dollars ($20.00) for each photograph
under the specified number.
C. Should more than the specified number of photographs be required, the
Contractor will be paid twenty dollars ($20.00) for each photograph provided
over the specified number requested in writing by the Engineer.
D. The Engineer reserves the right to reject any photograph that is not clear or
definitive. Any photograph so rejected shall be subtracted from the total
exposures before computations for payment or credit under this Section.
01323-1 11/2017
DEP 3/15/2016
1485
DETAILED SPECIFICATION 01323 - JOB PHOTOGRAPHS AND VIDEOS
CONTRACT DEL-260 G, H, E
1.05 DEFINITIONS
A. For the purposes of this Section, “Photograph” shall be defined as one (1)
camera exposure, which is approved by the Engineer for development into the
products specified herein. Photographs shall be understood as including prints
and DVDs as specified.
1.06 DESCRIPTION
A. Unless specifically noted otherwise, all work of this Section shall be performed
by the Electrical Contractor.
B. The Contractor shall engage the services of experienced professional
photographers and/or video recording firms, approved by the Engineer, to
document the progress of Work by taking color job Photographs, and videos.
The photographer shall take Photographs, and videos of the project before start
of construction work, during ongoing construction, and after completion of
construction as directed by the Engineer.
C. A designee of the Engineer will accompany the photographer for the taking of
all Photographs and videos.
D. Pre-Construction Photographs and Videos
1. The photographer, when directed by the Engineer, shall visit the site
prior to start of construction to take a total of 45 photographs and make
a 25 minute video showing existing conditions of the entire project site
and any adjacent areas which could possibly be disturbed during
construction.
E. Construction Photographs and Videos
1. The photographer, when directed by the Engineer, shall visit the site
during construction on a monthly basis unless the Engineer requests
different frequencies of the visits, to take a total of 100 photographs for
the project and to visit the site when directed by the Engineer to tape a
total of 2 hours of videos. Photographs taken and video minutes taped
shall be distributed evenly among the visits and visits shall be
distributed evenly over the course of the project, all subject to the
direction of the Engineer.
F. Post-Construction Photographs and Videos
1. The photographer, when directed by the Engineer, shall visit the site at
the completion of construction to take a total of 50 photographs and
make a 25 minute video showing the completed work, the entire project
site and any adjacent areas which were disturbed during construction.
G. Informational Video
01323-2 11/2017
DEP 3/15/2016
1486
DETAILED SPECIFICATION 01323 - JOB PHOTOGRAPHS AND VIDEOS
CONTRACT DEL-260 G, H, E
1.08 SUBMITTALS
A. Submittals shall include, but not be limited to, the following:
1. Resume of the professional photographer proposed for this work;
2. Resume and experience of the professional video recording firm
proposed for preparing the informational video;
3. Plot plans indicating the location and photo numbers of all Photographs.
4. One (1) set of all Photographs taken for the Engineer’s review and
approval for processing further.
5. The Contractor shall provide the Engineer with updated images on a
monthly basis.
PART 2 PRODUCTS
2.01 PHOTOGRAPHS
A. The file format for digital photographs shall be Tagged Image File Format
(TIFF).
B. Digital cameras shall produce records with true optical resolution. Images shall
not be resized or interpolated to a higher resolution from a lower resolution.
C. Photographic images shall be provided as 8 bit per channel RGB color images.
01323-3 11/2017
DEP 3/15/2016
1487
DETAILED SPECIFICATION 01323 - JOB PHOTOGRAPHS AND VIDEOS
CONTRACT DEL-260 G, H, E
01323-4 11/2017
DEP 3/15/2016
1488
DETAILED SPECIFICATION 01323 - JOB PHOTOGRAPHS AND VIDEOS
CONTRACT DEL-260 G, H, E
2.02 VIDEOS
A. Video recordings shall be ASTC format, 1080P (1920 x 1080) using MPEG-4
Program Stream encoding (ISO-IEC 14496-14 “Coding of audio-visual objects
-- Part 14: MP4 File Format”), delivered on flash drive or portable hard drive,
using professional video cameras with clear and succinct narrative. The
narrative material shall be developed in conjunction with the Construction
Manager, construction contractor, and Engineer.
1. All video recordings shall begin with a chapter index listing the contents
in detail and providing direct access to each chapter.
2. All video recordings must include on parallel tracks metadata (catalogue
information) to include the date and time of recording, the name of the
area being documented, the project name, direction of travel, the
viewing side, project number, project name, Contract number and
description, name of photographer and Department of Environmental
Protection witness. The date and time shall be on a track separate from
the rest of the metadata and, when displayed, shall appear in the upper
left hand corner of the picture. Time and date shall use the following
format:
Time: 08:35:15 (using 24-hour clock time)
Date: 09/18/2002 (date format MM/DD/YYYY)
3. The project number, project name, Contract number and description,
name of photographer and Department of Environmental Protection
witness, when displayed, shall appear on the lower half.
B. Video output from camera used must be capable of producing full HD
resolution (1920 x 1080). Geometric distortion should not exceed two (2)
percent of picture height at any point in picture area.
C. All recording shall be done with adequate lighting. Written authorization by the
Engineer to proceed with video documentation at any areas must be done with
consideration of existing environmental conditions. The designee of the
Engineer will accompany the photographer during all taping sessions.
D. During the recording period, all records shall be turned over to the Engineer for
review of the content and quality. Any portion of the recording deemed
unacceptable by the Engineer shall be re- recorded by the Contractor at no
additional expense to the City.
E. One copy of all acceptable recordings (flash drive or hard drive) shall be
furnished and shall be properly identified by container number, equipment,
location and project name. A record of the contents of each recording shall be
provided on a run sheet, identifying each chapter segment of the recording. The
run sheet shall be provided in paper copy as well as on the flash dive or hard
drive.
01323-5 11/2017
DEP 3/15/2016
1489
DETAILED SPECIFICATION 01323 - JOB PHOTOGRAPHS AND VIDEOS
CONTRACT DEL-260 G, H, E
PART 3 EXECUTION
END OF SECTION
01323-6 11/2017
DEP 3/15/2016
1490
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
SECTION 01330
Submittal Procedures
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any work required under this
Section and the Contractor shall include all costs thereof in its lump sum price
bid for the Contract.
1.05 DEFINITIONS
A. Submittals includes all types of drawings and other documents required to be
prepared or assembled and submitted to the Engineer by the Contractor before,
during, or after construction, such as, but not limited to, the following
“submittal categories”:
1. Certifications;
2. Construction Progress Photos and Videos;
3. Detailed Estimate Breakdowns;
01330-1 11/2017
DEP 4/21/2016
1491
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
1.06 DESCRIPTION
A. General:
1. All Submittals including, but not limited to, Shop Drawings and
inquiries pertaining to engineering features or Specification and
Drawing interpretations, shall conform to the General Conditions and
the requirements of this Section and Section 01312 – Web-based Project
Management Information System.
2. Within 30 days from the work commencement date specified in the
Notice to Proceed (NTP), the Contractor shall prepare and submit for
the Engineer’s approval a Schedule of Submittals which it proposes to
follow, listing Section references, names of Submittals required, and the
dates on which the Contractor proposes to make the Submittals. No
other Submittals will be considered for review until the Schedule of
Submittals is received and approved by the Engineer.
3. Submittal shall be made as directed by the Engineer. All submittals shall
be in the English language with U.S. customary units of measurement
being used in all drawings and data.
4. The Contractor shall use the project web-based document management
system as directed by the Engineer and as described in Section 01312 –
01330-2 11/2017
DEP 4/21/2016
1492
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
01330-3 11/2017
DEP 4/21/2016
1493
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
01330-4 11/2017
DEP 4/21/2016
1494
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
01330-5 11/2017
DEP 4/21/2016
1495
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
10. Engineer's assumed design data. All structural steel, concrete and
reinforcement indicated or specified to fully or partially support
equipment or appurtenances and the areas immediately adjacent thereto,
have been designed from data based on assumed average anticipated
clearances and loadings. The final structural design in these locations
will be based on definite data available only after the Engineer approves
the equipment and appurtenances to be installed. Therefore, no Shop
Drawings pertaining to such supporting steel or concrete structures shall
be submitted until the Contractor is furnished with full data relative to
the approved equipment and appurtenances.
11. Necessary major changes in framing will be covering by supplementary
or revised drawings which will be furnished to the Contractor. All
changes indicated or necessary to accommodate the equipment and
appurtenances shall be incorporated into the Shop Drawings submitted
for approval.
12. Shop Drawings for the work in paragraphs 9, 10, and 11 above shall be
prepared by or under the direction of a qualified licensed Professional
Engineer, currently registered in the State of New York, and shall bear
the imprint of their seal and signature.
E. Shop Drawings Approval
1. Shop Drawing submittals to the Engineer shall contain complete data on
the Work and full information on related matters.
2. In submitting Shop Drawings for approval, all associated drawings
relating to a complete assembly of various parts necessary for a unit
shall not be submitted until the assembly of drawings is complete so that
they may be checked in relation to the assembly proposed. Where errors,
deviations and/or omissions are discovered later, they shall be made
good by the Contractor irrespective of any approval by the Engineer.
3. With Submittals, the Contractor shall notify the Engineer of all
departures from the Drawings and Specifications; otherwise, approval
of such Submittals will not constitute approval of the departure.
Approval of a Submittal will constitute approval of the subject matter
thereof only and not of any other structure, material or apparatus shown
or indicated.
4. Materials or equipment shall not be ordered nor shall any Work be done
by the Contractor before the materials, the equipment and the Shop
Drawings as herein required have been approved by the Engineer.
5. After the Engineer completes their review, the submittal will be marked
with one of the following notations:
• Furnish as Submitted;
• Furnish as Corrected;
01330-6 11/2017
DEP 4/21/2016
1496
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
01330-7 11/2017
DEP 4/21/2016
1497
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
1.08 SUBMITTALS
A. All Submittals shall have identifying titles and bear the stamp of approval and
signature of the Contractor as evidence that they have been reviewed and
approved by the Contractor and that they conform to the requirements of the
Contract Documents. Submittals without this stamp of approval will not be
reviewed by the Engineer and will be returned to the Contractor. The stamp
shall contain the following minimum information completed in ink:
01330-8 11/2017
DEP 4/21/2016
1498
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
Project Name:
Contract No.: _________________________________________
Contractor's Name:
Date:
Item:
Specification Section No.: ___ Section Title: ____________________
Page Nos.: __ ___ __Article No.:_______ Paragraph No.:__________
Contract Drawing No.: _________________ of
Location:
Submittal No.: ______________ Review Cycle No.:
Shop Drawing Reference No.:
Source company name:
Approved By:
B. Submittal Identification and Tracking: In order to identify and track each
submittal as a separate and unique item, the Contractor shall utilize a submittal
numbering system as follows:
1. Submittal Number: The Submittal Number shall be a separate and
unique number correlating to each individual Submittal that needs to be
tracked as a separate and unique item. The Submittal Number shall be a
two-part, eight-character, alpha/numeric number assigned by the
Contractor in the following manner:
a. The first part of the Submittal Number shall consist of six (6)
characters that pertain to the applicable specification section
(without spaces after ever two (2) numerical characters).
b. The second part of the Submittal Number shall consist of three
digits (the numbers 001 to 999) to number each separate and
unique submitted under each Section.
c. A dash shall separate the two parts of the Submittal Number.
d. As an example, the Submittal Number for the third submittal
under Section 09900 – Painting and Coating, would be
09900-003.
C. Review Cycle: The review cycle shall be identified by a three-digit number
indicating whether a Submittal is the initial submission (“000”) or a
resubmission of an earlier Submittal. The first resubmission, for example, will
be assigned “001”; the second resubmission will be assigned “002”; etc.
Liquidated damages will be assessed upon rejection of any Submittal identified
as “003” in the review cycle.
D. Submittals shall include appropriate references to Drawings and Specifications.
E. In submitting Shop Drawings for approval, all associated drawings relating to
a complete assembly of various parts necessary for a unit shall be included.
01330-9 11/2017
DEP 4/21/2016
1499
DETAILED SPECIFICATION 01330 –SUBMITTAL PROCEDURES
CONTRACT DEL-260 G, H, E
Shop Drawings shall not be submitted until the full set of associated drawings
is complete, so that they may be checked in relation to the assembly proposed.
F. All items of electrical equipment constituting an operating system and any
mechanical units involved therein or necessary for the functioning of such
system shall be submitted at the same time and shall include clear diagrams
showing circuit functioning and necessary details for field construction.
G. Partial, incomplete, or illegible submissions will be marked “Rejected” and
returned to the Contractor without review, for resubmission.
H. Final Copy -- Shop Drawings: The Contractor shall furnish all “Final Copy
Shop Drawings” to the DEP as a condition precedent to obtaining the final
certificate under Article 45 of the Standard Construction Contract. Final Copy
Shop Drawings shall be submitted in accordance with Section 01332 – Final
Record Documents.
END OF SECTION
01330-10 11/2017
DEP 4/21/2016
1500
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
SECTION 01332
Final Record Documents
PART 1 GENERAL
1.01 SUMMARY
A. This Section describes the requirements for all final record documents.
1.02 PAYMENT
A. No separate payment will be made for performing any work required under this
Section and the Contractor shall include all costs thereof in its lump sum price
bid for the Contract.
1.04 DEFINITIONS
A. Archive: In this Section, to Archive shall mean to furnish as a final record
document.
B. As-Built Drawings. The “As-Built Drawings” reflect the “as constructed” final
product. These drawings shall use the same title blocks and sheet numbers as
the original “Bid Set Drawings”, with the exception that an “AB” is prefixed
onto the original drawing number.
C. Final Copy Shop Drawing (FCSD): The Final Copy Shop Drawing means the
approved copy [Furnish as Submitted (FAS) or Furnish as Corrected (FAC)] of
the shop drawing as described in Section 01330 - Submittal Procedures,
corrected to reflect any deviations made for the installed condition showing the
actual construction.
D. Conformed Drawings: The Conformed Drawings are the original Bid Set
Contract Drawings modified to incorporate the changes made by addenda to the
Invitation for Bids issued during the bid period.
01332-1 11/2017
DEP 4/26/2016 (NO CM)
1501
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
E. Conformed Set Contract: The Conformed Set of the Contract is the original
Bid Set Contract modified to incorporate the changes made by addenda to the
Invitation for Bids issued during the bid period.
F. Bid Set Drawings (aka Design Drawings): The Bid Set Drawings shall consist
of the original Contract Drawings issued by DEP with the solicitation for
Contract bids.
G. Bid Set Contract (including Addenda): The Bid Set Contract shall be the text of
the original Contract (excluding Drawings) issued by DEP with the solicitation
for Contract bids, including any Addenda issued during the bid period.
H. Change Orders: The Change Orders shall include registered change order forms
and the complete sets of attached text and/or drawings for all design and field
Change Orders.
I. Operations and Maintenance Manuals: When specified, Operations and
Maintenance Manuals (“O&M Manuals”) shall be prepared by the Contractor
in conformance with Detailed Specification 01831 - Operation and
Maintenance Manuals. Final copies of the O&M Manuals shall be submitted in
accordance with the requirements of this Section.
J. Key Documents: For purposes of this Section, Key Documents shall include,
but not be limited to, to the following items:
1. Signed copy of the Standard Construction Contract;
2. The Contractor’s bonds;
3. Signed and submitted Bid Schedule of Prices;
4. DEP Award Folder contents;
5. Contract Notice of Award letter;
6. Notice to Proceed Letter;
7. Approved Detailed Estimate Breakdown as described in Detailed
Specification 01291 – Detailed Estimate Breakdown;
8. Article 44 (Standard Construction Contract) Substantial Completion
Certificate;
9. Final evaluation;
10. Final extension of time (if applicable);
11. Claim settlements (if applicable);
12. Certificate of Occupancy;
13. Warranties;
14. Structure Survey (per Article 9 of the General Conditions);
15. Regulatory Transition Plan (where applicable).
01332-2 11/2017
DEP 4/26/2016 (NO CM)
1502
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
1.05 DESCRIPTION
A. The Contractor shall submit the following final record documents in paper,
microfilm, and electronic formats according to the requirements of Table 1 –
Summary of Final Record Documents to be Furnished attached at the end of
this Section, and as defined above and specified below:
1. As-Built Drawings
2. Final Copy Shop Drawings;
3. Bid Set Drawings (aka Design Drawings);
4. Conformed Drawings;
5. Bid Set Contract (including Addenda);
6. Conformed Set Contract
7. Key Documents;
8. Change Orders (text and drawings);
9. O&M Manuals;
10. Additional Documents;
11. Job Photographs and Videos.
B. Submittal of these documents shall be a condition precedent to obtaining the
final certificate under Article 45 of the Standard Construction Contract.
01332-3 11/2017
DEP 4/26/2016 (NO CM)
1503
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
1.07 SUBMITTALS
A. As-Built Drawings
1. The Contractor is to create an As-Built Drawing Set by revising the
Conformed set of contract drawings electronically using AutoCAD. If
no Conformed set was created, then he shall use the original set of
Contract Drawings. When using the Conformed Set of Drawings, the
Contractor shall independently confirm that the changes made by the
Addenda to the original Bid Set of Drawings were correctly reflected in
the Conformed Set of Drawings. Files submitted in AutoCAD format
will be bound to include all related matter (e.g. base files, font files and
shapes). Each file shall be viewable and printable in its entirety without
recourse to external files.
2. The Contractor shall use the information compiled during construction
to create an As-Built Drawing Set. The Contractor shall document any
deviations, changes, etc. from the configurations shown on the original
Contract Drawings or revised drawings issued during the course of
executing the work including Change Orders, Design During
Construction (DSDC) memorandums, Requests for Information (RFIs),
Requests for Clarification (RFCs), etc. These deviations, changes, etc.
shall generally relate to topographic features, relocation of structures, or
locations of underground items such as pipelines, duct banks, manholes
or footings. Survey distances, coordinates and/or elevations shall be
included to accurately locate all such items. All deviations, changes, etc.
shown shall be field verified.
3. Contractor should have the electronic files of the contract drawings.
However, should the Contractor require an additional copy, the
Engineer will supply the Contract Drawings AutoCAD electronic files
on DVD-Rs upon written request, if such copies are available. The
AutoCAD files will consist of a bound set of drawings.
4. Drawing Size – The As-Built drawings are to be the same size as the
full size Contract Drawings (22-inches by 34-inches).
5. Generate the new As-Built drawing number as per the following steps:
a. The As-Built drawing number is the original contract drawing
number prefixed by an “AB” for As-Built.
i. Example: If the drawing number for a contract drawing is
36G-02S-14, the As-Built drawing number will be “AB-
36G-02S-14”.
b. If a new drawing is produced, its number can be added to the
end of the series. (i.e., if 14 is the last drawing in the series,
then the first new drawing becomes 15; the second new one
becomes 16, etc.)
01332-4 11/2017
DEP 4/26/2016 (NO CM)
1504
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
01332-5 11/2017
DEP 4/26/2016 (NO CM)
1505
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
01332-6 11/2017
DEP 4/26/2016 (NO CM)
1506
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
01332-7 11/2017
DEP 4/26/2016 (NO CM)
1507
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
F. Conformed Drawings
1. The Conformed Drawings shall be Archived. If the Contractor does not
have a complete set of the Conformed Drawings in the AutoCAD
format, it may request a set from the Engineer. If possible, the
Conformed Drawings will be provided to the Contractor in AutoCAD
format, bound with their respective data sets.
G. Change Orders
1. All change orders (both field and design) produced during the
construction of the project shall be Archived.
H. Operations and Maintenance (O&M) Manuals
1. O&M Manuals should have been submitted and reviewed as part of the
shop drawings submission and review process in accordance with
Detailed Specification 01831 - Operations and Maintenance Manuals.
2. Final, approved copies of the O&M Manuals shall be furnished during
the progress of the work in accordance with Detailed Specification
01831 - Operations and Maintenance Manuals. Additional electronic
copies of each manual shall be submitted as part of the Final Record
Documents.
I. Key Documents
1. Key Documents produced during the construction of the project shall be
Archived. They shall consist generally of the items defined above.
J. Additional Documents
1. Any Additional Documents such as Soil Classification Reports,
Environmental Impact Statements, Site Assessments, Geotechnical
Reports, permits, RFI's. etc., shall also be Archived when directed by
DEP. If the Contractor does not have copies of any documents, they will
be provided by the Engineer, when possible, in electronic or paper
format.
K. Job Photographs and Videos
1. Job Photographs and Videos produced during the performance of the
Work shall be Archived.
L. Quantities
1. The quantities and formats to be furnished for each Final Record Document
shall be as shown in Table 1.
1.08 ATTACHMENTS
A. Table 1 – Summary of Final Record Documents to be Furnished
01332-8 11/2017
DEP 4/26/2016 (NO CM)
1508
DETAILED SPECIFICATION 01332 -FINAL RECORD DOCUMENTS
CONTRACT DEL-260 G, H, E
END OF SECTION
01332-9 11/2017
DEP 4/26/2016 (NO CM)
1509
ATTACHMENTS – DETAILED SPECIFICATION 01332
CONTRACT DEL-260 G, H, E
Table 1
Summary of Final Record Documents To Be Furnished
Microfilm
Microfilm Microfilm Microfilm
(35mm
(35mm (16mm first (16mm
Final Record Electronic first
Paper second generation second
Document Type (DVD-R sets) generation
generation silver- generation
silver-
diazo) gelatin) diazo)
gelatin)
6 sets (PDF/A)*
O&M Manuals 4 sets * 2 compilation NA NA NA NA
sets*
* Each paper copy of an O&M manual shall have a DVD-R copy of the Manual in a fitted
sleeve attached on the inside of the front cover of the binder for the Manual. These shall be
furnished to the Operating Bureau in accordance with the requirements Detailed Specification
01831 - Operation and Maintenance during the progress of the work. Two extra DVD-R's of
each manual or two compilation DVD-R be furnished as part of the Final Record Documents.
END OF SECTION
PAGE 1 OF 1 11/2017
DEP 4/26/2016 (NO CM)
1510
DETAILED SPECIFICATION 01333 – RECORDS IN PAPER FORMATS
CONTRACT DEL-260 G, H, E
SECTION 01333
Records in Paper Formats
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any work required under
this Section and the Contractor shall include all costs thereof in its lump sum
price bid for the Contract.
1.05 DEFINITIONS
1. Small-Format Documents: 11 by 17 inches or smaller
2. Large-Format Documents: larger than 11 by 17 inches
01333-1 11/2017
DEP 9/24/2015
1511
DETAILED SPECIFICATION 01333 – RECORDS IN PAPER FORMATS
CONTRACT DEL-260 G, H, E
1.06 DESCRIPTION
A. Final Record Documents
1. For the Final Record Documents specified in Detailed Specification
01332 - Final Record Documents, the following directions shall apply.
a. Drawings
i. As specified in Detailed Specification 01332 - Final
Record Documents, provide full size, paper copies of the
Final Copy Shop Drawings and As-Built Drawings (if
required).
(a) Bid Set and Conformed Drawings are not required to
be furnished as paper copies but shall be furnished as part
of the electronic archives and microfilm.
ii. Paper copies are to be produced from the electronic
copies.
b. Bid Set - Contract
i. A single set of the Bid Contract in paper format shall be
provided by the Contractor, and it shall be identical to the
copy distributed for bid. They shall be furnished as bound
volumes.
ii. All Addenda shall be produced in paper format by the
Contractor. Each Addendum shall be bound separately
and include all attachments including sketches and
drawings. Drawings shall be attached using half-size
drawings (11” x 17”).
c. O&M Manuals
i. As required in Detailed Specification 01831 - Operation
and Maintenance Manuals, submit hard-bound copies and
electronic copies of each O&M Manual during the
progress of the work.
ii. No additional paper copies are required to be submitted
as part of the Final record Documents.
d. Key Documents
i. Key Documents, as defined in Detailed Specification
01332 - Final Record Documents, are not required to be
produced in paper format.
e. Change Orders
i. Change orders are not required to be produced in paper
format.
f. Job Photographs
01333-2 11/2017
DEP 9/24/2015
1512
DETAILED SPECIFICATION 01333 – RECORDS IN PAPER FORMATS
CONTRACT DEL-260 G, H, E
1.08 SUBMITTALS
A. Paper Certification: All documents covered by this Section shall be
accompanied by a certification from the manufacturer of the paper that it
complies with ANSI/NISO Z39.48.
B. Printing Test Certification: The organization that operates the printing
processes and materials used to produce the documents covered by this
Section shall submit the following documentation as proof that the tests have
been carried out:
1. An affidavit, signed by the supervisor responsible for the production
area, certifying that the tests have been performed in accordance with
the procedures described in the National Archives and Records
Administration Technical Information Paper No. 5, Tape Pull Test.
2. All of the Peel Test Targets actually used to perform the tests.
END OF SECTION
01333-4 11/2017
DEP 9/24/2015
1514
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
SECTION 01334
Records in Microfilm Formats
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any work required under this
Section and the Contractor shall include all costs thereof in its lump sum price
bid for the Contract.
01334-1 11/2017
DEP 4/22/2016
1515
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
01334-2 11/2017
DEP 4/22/2016
1516
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
1.05 DEFINITIONS
1. Archive: In this Section, to "Archive" shall mean to furnish as a final
record document.
2. “Small-Format” Records: Office files, manuals, etc. equal to or less than
11” x 17” for one page) to be filmed on 16mm roll microfilm.
3. “Large-Format” Records: Mostly architectural and engineering
drawings larger than 11” x 17” per sheet to be filmed on 35mm roll
microfilm.
1.06 DESCRIPTION
A. Design Requirements
1. The microfilm shall be produced by “computer-output microfilm”
(COM) recorders using digital files as the source of the records. As of
the issue date of this Specification, the typical COM device used to
produce 16mm roll microfilm is the Digital Archive Writer
manufactured by the Eastman Kodak Company (Rochester, NY). The
typical COM device used to produce 35mm roll microfilm is the line of
Electron Beam Recorders produced by Image Graphics Inc. (Shelton,
CT).
B. Records and Microfilm Pick-Up And Delivery
1. When required, the records to be microfilmed shall be picked-up from
the premises of DEP, the Contractor or the construction manager for the
project. The driver of the delivery vehicle, or other accredited
representative of the microfilming Subcontractor, will sign a document
acknowledging receipt of the records outlined in the transmittal list of
the shipment;
2. After filming, all copies of the records shall be returned to the premises
of DEP and the Contractor or construction manager. The microfilming
Subcontractor is not permitted to retain any copies of the records, in any
format;
3. The recipient (DEP, or the Contractor, or construction manager) shall
be notified, by phone, of pick-up or delivery at least 24 hours
beforehand;
4. Records transport shall be provided by the Subcontractor, using an
insured delivery vehicle. All pick-ups and deliveries shall be “Inside
Delivery”.
01334-3 11/2017
DEP 4/22/2016
1517
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
1.08 SUBMITTALS
A. Information Letter: Upon DEP’s request, the Contractor shall submit an
information letter containing a list of the microfilming Subcontractor’s hardware,
software, and supplies. The letter will be considered valid for two calendar years,
and may be extended for a third year with a follow-up (update) letter of facility
configuration and/or staff changes. As a minimum, the letter shall include the
following information.
1. Hardware (number, manufacturer & model)
a. COM recorder(s);
b. Microfilm processor(s), silver gelatin;
c. Chemical stability test method;
d. Inspection equipment;
e. Duplicating equipment.
2. Supplies (manufacturer & product identification)
a. Microfilm stock;
b. Developer;
01334-5 11/2017
DEP 4/22/2016
1519
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
c. Fixer (hypo);
d. Duplicating film.
B. Sample Microfilm
1. The microfilming Subcontractor may be required to produce a test
microform (roll film) of COM and duplicate film, in accordance with
the requirements of this Section, using records supplied by DEP, or the
Contractor, or DEP’s Construction Manager. The Contractor must
submit this sample to the Chief - BEDC Specifications Section for
inspection and approval;
2. If the test film is unacceptable, the microfilming Subcontractor is
required to produce one or more test films until the microfilming
Subcontractor produces a sample acceptable to DEP;
3. If the microfilming Subcontractor fails to produce an acceptable roll of
microfilm within five business days after receipt of DEP’s initial
request, DEP may require the Contractor to propose another
microfilming Subcontractor.
C. Activity Reports: The Contractor shall submit a written report of the activities
of its microfilming Subcontractor, on a monthly basis, to DEP, or the Resident
Engineer. The activity report shall consist of a summary list of projects
completed, showing for each project:
1. Project Description;
2. Final Record Type(s);
3. Number of images;
4. Number of rolls;
5. List of retakes and rolls of film re-filmed, showing for each roll the
record type, roll number, and nature of remedy (retake or re-film);
6. Number of diazo duplicate rolls;
7. Number of indexing keystrokes (when applicable);
8. Date all microfilm (first-generation and all duplicates) and records
returned to DEP, or the Contractor, or the Construction Manager.
PART 2 PRODUCTS
01334-6 11/2017
DEP 4/22/2016
1520
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
2. In general, the Contractor shall use the records in its possession. When
required, records will be supplied by DEP, or the construction manager;
3. The specific condition, format, and number of records is established by
a survey of samples of the records. The microfilming Subcontractor will
be offered the opportunity to inspect each record series prior to
microfilming;
4. Small-format records typically consist of reports, various sorts of
Contract records (such as Requests for Information, Bid and
Specifications, Addenda, Change Orders, Drawing Log, Contract
Notices, Permits, Warranties, Bid Tabulations, Completed Bid Sheets,
Forms of Bonds, and Advertising Notices);
5. Large-Format records typically consist of architectural, engineering,
and topographical drawings (building and machinery plans, maps, etc.);
6. Electronic records will normally be produced in one of three file
formats: PDF for text records (with or without raster images), and
AutoCAD and PDF for drawings and uncompressed TIFF 6.0 for digital
photographs;
7. Files in formats other than TIFF will have to be converted to that format
for output to COM. This conversion may be performed by DEP, by the
Contractors by the Construction Manager, or by the microfilming
Subcontractor, in accordance with the terms and conditions of the
Contract;
8. The microfilming Subcontractor and DEP, or the Contractor, or the
Construction Manager will establish, before the start of each
microfilming project, the acceptable file transfer medium or media.
B. Ownership of Records and Microfilm
1. The original records, and all microfilm produced, shall remain the
property of DEP;
2. If an entire roll of microfilm is determined defective and re-filming is
required, the original (defective) roll of film and all duplicates shall be
returned, to DEP;
3. Unless specifically requested in writing by DEP, no records shall be
destroyed by the microfilming Subcontractor.
C. Record Order
1. Records shall be maintained in existing logical record order before,
during and after filming;
2. The only exception to this requirement is when corrections are made to
record order to conform to the requirements of the indexing system.
Such corrections shall be made only with written permission from DEP.
01334-7 11/2017
DEP 4/22/2016
1521
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
D. Records’ Condition
1. Potential problems with digital records include corrupt files, damaged
storage media, incorrect metadata, and invalid or obsolete file formats;
2. In record series covering long spans of time, the indexing system may
have changed repeatedly (it is not uncommon for drawings to include
multiple indexing systems).
2.03 MICROFILMING
A. Final Format
1. Small-Format Records: 16mm roll microfilm, with a minimum of one
diazo duplicate of each roll;
2. Large-Format Records: 35mm roll microfilm, with a minimum of one
diazo duplicate of each roll.
B. COM Film
1. Small-Format Records: 16mm x 100ft, 5-mil thick, non-perforated
polyester, high contrast (gamma 3.0 to 4.0) panchromatic film in
accordance with ANSI/NAPM IT9.1;
2. Large-Format Records: 35mm x 100ft, 5-mil thick, non-perforated
polyester, high contrast (gamma 3.0 to 4.0) panchromatic film in
accordance with ANSI/NAPM IT9.1.
C. Reduction Ratio shall be in accordance with the following schedule:
01334-8 11/2017
DEP 4/22/2016
1522
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
01334-9 11/2017
DEP 4/22/2016
1523
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
01334-10 11/2017
DEP 4/22/2016
1524
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
01334-11 11/2017
DEP 4/22/2016
1525
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
2.05 SPLICING
A. Splices shall be in accordance with ANSI/AIIM MS18. Under no circumstances
shall a roll of film contain more than three splices.
B. Splicing shall not be used to insert technical targets (resolution or residual
thiosulfate test certificate) which have been omitted.
C. Only ultrasonic-weld splices shall be used; pressure-sensitive tape, cements
using acetic acid, and/or other chemicals injurious to the permanent-record
qualities of microfilm, shall not be used.
2.06 RETAKES
A. Retakes shall be filmed with full documentation (as though they were separate
rolls of film), and spliced into the film leader, leaving at least 50cm (20 inches)
of blank film before the original START target.
B. Defective images shall not be removed from the roll.
C. When any frame of a roll-shaped drawing (such as a map of an aqueduct right-
of-way) or any portion of a multi-sheet drawing is rejected, the entire drawing
shall be re-microfilmed.
D. The microfilming Subcontractor is cautioned to carefully check record integrity
before filming retakes, to ensure proper record order.
2.07 DUPLICATES
A. Number of duplicates shall be as specified in Table 1 of Section 01 78 39-
Project Record Documents.
B. Type: Diazo (silver, if required); see Exhibit C - Sample Diazo Film Table,
attached at the end of this Section.
C. Base: Polyester.
D. Size: 16mm (Small-Format records) or 35mm (Large-Format records) x 100ft,
4-mil thick.
E. Bar-Gamma Range: 1.10 to 1.49 (see Diazo Film Table, column 3).
F. Dmax Range: 1.50 to 1.80 (see Diazo Film Table, column 4).
G. Dmin Range: Burn-out density, plus 0.05 to 0.09. For example, a typical burn-
out density (see Diazo Film Table, column 9) of 0.05 should result in a Dmin
of 0.10 to 0.14.
H. Background Density, Visual Diffuse Transmission
1. Negative-appearing images: 1.10 (+0.20);
2. Positive-appearing images: 0.04 (+0.20).
01334-12 11/2017
DEP 4/22/2016
1526
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
2.09 PACKAGING
A. Silver-gelatin microfilm, both first-generation and any duplicates, shall be on
spools, in accordance with ANSI PH1.33. The spools shall be in closed plastic
containers, in accordance with ANSI/NAPM IT9.2, and shall fit into boxes
loosely, without binding or pressure.
B. Diazo Duplicate Microfilm
1. Reels: ANSI/AIIM MS34 (Figure 2, Style 1¾square/round spindle
hole, solid flange) in closed plastic containers. Film trailer shall be
secured to the reel hub with a Kodak/Recordak trailer holder (Kodak
catalogue number 149-1703), or equal.
C. Package marking will be prescribed by DEP, the Contractor, or the Construction
Manager for each microfilming project. See Exhibit B - Sample Label Layout,
attached at the end of this Section.
01334-14 11/2017
DEP 4/22/2016
1528
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
PART 3 EXECUTION
01334-15 11/2017
DEP 4/22/2016
1529
DETAILED SPECIFICATION 01334 – RECORDS IN MICROFILM FORMATS
CONTRACT DEL-260 G, H, E
3.02 ATTACHMENTS
A. Exhibit A – Sample Information / Certification Target
B. Exhibit B – Sample Label Layout
C. Exhibit C – Sample Diazo Film Table
END OF SECTION
01334-16 11/2017
DEP 4/22/2016
1530
ATTACHMENTS – STANDARDIZED DETAILED SPECIFICATION 01334 –
CONTRACT DEL-260 G, H, E
EXHIBIT A
This is to certify that the microphotographic images appearing on this roll of microfilm
are accurate reproductions of the above-named Department of Environmental
Protection (DEP) records, and were microfilmed from the best available records, in the
course of regular operations, following established DEP policy and procedures (the
Specification governing the microfilming of this record series is included at the
beginning of the first roll of each calendar year of the series).
OPERATOR INFORMATION
COM operator: ________________ starting date: ________________
COM operator: ________________ starting date: ________________
COM operator: ________________ starting date: ________________
COM operator: ________________ starting date: ________________
ending date: ________________
FILM INFORMATION
manufacturer: _______________________type: ________________________
emulsion number: _____________________expiration date: ________________
PAGE 1 OF 4 11/2017
DEP 4/22/2016
1531
ATTACHMENTS – STANDARDIZED DETAILED SPECIFICATION 01334 –
CONTRACT DEL-260 G, H, E
EXHIBIT B
CONTRACT ####
AS- BUILT DRAWINGS
Roll 1 of 3 (Silver Original)
CONTRACT #####
Label contents are based on standard courier typeface, at 10 characters per inch
(monospaced), and labels 3-1/2 inches long. Microfilming Subcontractor may use a
proportional sans-serif typeface of equivalent legibility, in ten-point, eleven-point, or
twelve-point type sizes.
PAGE 2 OF 4 11/2017
DEP 4/22/2016
1532
ATTACHMENTS – STANDARDIZED DETAILED SPECIFICATION 01334 – CONTRACT DEL-260 G, H, E
EXHIBIT C
SAMPLE DIAZO FILM TABLE
(in bar-gamma order)
This table is not part of the Specification and is provided for information purposes only. The information shown herein is, without exception, compiled from the manufacturers'
specification sheets. A dash indicates that the manufacturer’s specification sheet does not provide the data. Diazo suppliers may change product characteristics without notice.
1 2 3 4 5 6 7 8 9 10
COMPANY PRODUCT BAR D COLOR PAPER DIAZO CONTRAST BURNOUT SEE
NUMBER GAMMA MAX PRINT DUPLICATE D NOTE
MEDIUM-LOW CONTRAST
REXAM 2724 1.0 1.25 BLACK — — — 0.04
REXAM 2751 1.30 BLUE — YES LOW
XIDEX/ANACOMP DHCF2 1.0 1.45 BLUE — — LOW 0.05
NOVAMEDIA BK2 1.1 1.50 BLACK — — MEDIUM 0.05 2
REXAM 2754 1.2 1.60 BLACK YES YES MEDIUM 0.05 3
FR CHEMICALS 2754 1.2 1.60 BLACK YES YES MEDIUM 0.05
REXAM 2758 1.1 1.70 BLUE-BLACK YES — MEDIUM 0.05 3
FR CHEMICALS 2758 1.1 1.70 BLUE-BLACK YES — MEDIUM 0.05
NOVAMEDIA BE8 1.2 1.70 BLUE — — HIGH 0.05 2
MEDIUM CONTRAST
REXAM 2753 1.40 1.85 BLUE YES YES HIGH 0.05 3
FR CHEMICALS 2753 1.40 1.85 BLUE YES YES HIGH 0.05
XIDEX/ANACOMP DMC 1.40 1.60 BLUE-BLACK YES — MEDIUM 0.05
XIDEX/ANACOMP DEM 2 1.40 1.60 BLACK YES YES MEDIUM 0.05
BELL & HOWELL BLACK 1.40 1.60 BLACK YES YES MEDIUM 0.05
BELL & HOWELL BLUE 1.40 1.60 BLUE YES — MEDIUM 0.05
XIDEX/ANACOMP DEM 1.40 1.70 BLACK YES — — 0.05
NOVAMEDIA BN4 1.45 1.60 BLUE-BLACK YES — MEDIUM 0.07 2
XIDEX/ANACOMP DBA 1.45 1.70 — YES YES — 0.05
HIGH CONTRAST
3M NRX1 1.70 1.80 BLUE-BLACK — — HIGH 0.1 1
XIDEX/ANACOMP DATAGARD 1.70 1.80 — YES NO — 0.05
XIDEX/ANACOMP DHCF 1.70 1.80 BLUE — — HIGH 0.05
XIDEX/ANACOMP DHC 1.70 1.90 BLUE-BLACK YES — HIGH 0.05
XIDEX/ANACOMP DEHF 1.70 1.90 BLACK YES YES HIGH 0.05
XIDEX/ANACOMP DEH 1.80 2.00 BLACK YES NO HIGH 0.05
NOTES (ref.: column 10): 1. 3M Company product NRZ-1 is a dry, heat-processed diazo film.
2. Meets ANSI IT9.5 for long-term preservation.
3. Rexam Graphics, formerly Graphics Technology International, formerly James River Graphics.
PAGE 3 OF 4 11/2017
DEP 4/22/2016
1533
ATTACHMENTS – STANDARDIZED DETAILED SPECIFICATION 01334 –
CONTRACT DEL-260 G, H, E
PAGE 4 OF 4 11/2017
DEP 4/22/2016
1534
DETAILED SPECIFICATION 01335 – RECORDS IN ELECTRONIC FORMATS
CONTRACT DEL-260 G, H, E
SECTION 01335
Records in Electronic Formats
PART 1 GENERAL
1.01 SUMMARY
A. This Specification describes the requirements for the electronic records for the
items specified in Detailed Specification 01332 - Final Record Documents.
B. This Specification does not cover digital objects which include a time base
correction code (e.g., analogue or digital video recordings, analogue or digital
audio recordings, instrumentation data feeds, etc.), or geo-coded objects
(produced by Geographic Information Systems-GIS).
1.02 PAYMENT
A. No separate payment will be made for performing any work required under this
Section and the Contractor shall include all costs thereof in its lump sum price
bid for the Contract.
01335-1 11/2017
DEP - 3/28/2016
1535
DETAILED SPECIFICATION 01335 – RECORDS IN ELECTRONIC FORMATS
CONTRACT DEL-260 G, H, E
1.05 DEFINITIONS
A. Archive: In this Section, to Archive shall mean to furnish as a final record
document.
B. Metadata: Metadata is commonly defined as “data about data.” For the purposes
of this Section, Metadata refers to the “descriptive metadata” that describes the
content and form of the construction records known as Final Record Documents
(i.e. contract name, document date, construction phase, engineer of record, etc.)
and supports the discovery (searching) and identification of the resources.
C. Portable Document Format-Archival (PDF/A): A standard that identifies a
"profile" for electronic documents that ensures the documents can be
reproduced the exact same way in years to come. A key element to this
reproducibility is the requirement for PDF/A documents to be 100% self-
contained. All of the information necessary for displaying the document in the
same manner every time is embedded in the file. This includes, but is not limited
to, all content (text, raster images and vector graphics), fonts, and color
information. A PDF/A document is not permitted to be reliant on information
from external sources (e.g. font programs and hyperlinks).
1.06 DESCRIPTION
A. Source of Electronic Records
1. In preparing the electronic records, the Contractor shall make every
reasonable effort to obtain from the originator (e.g., the manufacturer)
documents in their original electronic format and incorporate these in
the records. Subject to the approval of the Engineer, electronic records
may be scanned from a paper version only when the Contractor cannot
obtain the electronic version from the originator (e.g., the
manufacturer).
B. Metadata
1. For each type of Final Record Document, a Metadata table shall be
prepared in Excel which will furnish the specified data for that
document. The data elements shall be furnished to the Contractor by
DEP prior to production of the Final Record Documents DVD-Rs.
C. File Compression, File Formats, and Quality Control
1. File compression is not permitted for any of the files in any format;
2. File formats acceptable to DEP are ISO 15009-1 Portable Document
Format-Archival (PDF/A); Tagged Image File Format (TIFF), version
6.0 (“II” format); AutoCAD. All files shall be delivered to DEP with
file names that use the default file extension for each of the above
formats.
3. Portable Document Format-Archival (PDF/A)
01335-2 11/2017
DEP - 3/28/2016
1536
DETAILED SPECIFICATION 01335 – RECORDS IN ELECTRONIC FORMATS
CONTRACT DEL-260 G, H, E
01335-3 11/2017
DEP - 3/28/2016
1537
DETAILED SPECIFICATION 01335 – RECORDS IN ELECTRONIC FORMATS
CONTRACT DEL-260 G, H, E
01335-4 11/2017
DEP - 3/28/2016
1538
DETAILED SPECIFICATION 01335 – RECORDS IN ELECTRONIC FORMATS
CONTRACT DEL-260 G, H, E
7. Digital Photographs
a. The file format for digital photographs is Tagged Image File
Format (TIF);
b. Photographic (raster) images shall may be produced directly by
digital cameras;
c. Digital cameras shall produce records with true optical
resolution. Images shall not be resized or interpolated to a higher
resolution from a lower resolution;
d. Photographic images shall be provided as continuous-tone (8-
bit) gray scale or color (24-bit or 48-bit RGB) raster images;
e. Digital camera files shall be captured as specified in Detailed
Specification 01323 - Job Photographs and Videos.
PART 2 PRODUCTS
3.01 GENERAL.
A. When creating DVD-Rs, the Contractor should organize the information in
separate DVD-R's as presented below. For each final record document, use as
many disks as needed to accommodate the materials. The multiple disks will be
further labeled to read “1 of x”. So, if three DVD-Rs are needed to
accommodate the material for a specific final record document, the DVD-Rs
will be labeled Disk 1 of 3, etc.
In general, separate DVD-R's shall be prepared for the following items:
1. As-Builts (when required);
2. Final Copy Shop Drawings;
3. Bid Set Drawings (aka Design Drawings);
4. Bid Set - Contract (including Addenda);
5. Conformed Drawings;
6. Conformed Contract;
7. Key Documents;
01335-5 11/2017
DEP - 3/28/2016
1539
DETAILED SPECIFICATION 01335 – RECORDS IN ELECTRONIC FORMATS
CONTRACT DEL-260 G, H, E
8. Change Orders;
9. O&M Manuals;
10. Job Photographs;
11. Job Videos
12. Additional Documents.
For projects with smaller amount of Final Record Document files, some of the
above volumes can be combined.
B. The DVD-R label shall include:
1. The Project by number, facility, and description;
2. Contract Number and Title;
3. Description of the final record documents(s) included on the disc;
4. The total number of DVD-Rs for the final record document(s);
5. The date (month and year) of when the materials were archived;
6. The preparer of the final record document (i.e. Contractor or Consultant
CM);
7. For O&M Manuals, include the Equipment Item, the Manufacturer, and
the related Specification Section number;
An example of a DVD-R label is provided for guidance in Exhibit B, attached
at the end of this Section.
C. Files submitted in AutoCAD format shall be bound to include all related matter
(e.g. base files, font files and shapes) so that each file is viewable and printable
in its entirety without recourse to external files.
D. PDF files shall be 1200 dpi print quality.
3.02 METADATA
A. The Metadata Excel Table shall be included in the DVD of each Final Record
Document type and shall serve as an index for the files for of the record in the
DVD. Each file indexed in the Metadata Table shall be hyperlinked so that
clicking on the file name opens that file. The filenames given on the Metadata
Table must exactly match the files on the DVD to which they are hyperlinked.
B. The Metadata Excel tables shall be utilized as the Final Document Log.
Templates for the Metadata Excel table for each Final Record Document will
be provided by the DEP.
C. A sample Metadata Table will be provided by DEP.
01335-6 11/2017
DEP - 3/28/2016
1540
DETAILED SPECIFICATION 01335 – RECORDS IN ELECTRONIC FORMATS
CONTRACT DEL-260 G, H, E
3.03 ATTACHMENTS
A. Exhibit A – DVD-R Folder Structure
B. Exhibit B - Sampled DVD-R Label
END OF SECTION
01335-7 11/2017
DEP - 3/28/2016
1541
DETAILED SPECIFICATION 01335 – RECORDS IN ELECTRONIC FORMATS
CONTRACT DEL-260 G, H, E
01335-8 11/2017
DEP - 3/28/2016
1542
ATTACHMENTS – STANDARDIZED DETAILED SPECIFICATION 01335 –
CONTRACT DEL-260 G, H, E
EXHIBIT A
1. The DVD-R shall have a folder structure similar to the ones shown below.
a. For a DVD-R with one set of Final Record Documents
“ Contract #### – Bid Drawings (PDF Files)
(a) Metadata Table- Contract ##### – As-Built
Drawings - PDF.xls”
b. For a DVD-R with more than one set of Final Record Documents:
“ Contract #### – Bid Drawings (PDF)
(a) Contract ##### – Bid Drawings (PDF Files)
(b) Metadata Table- Contract ##### – As-Built
Drawings - PDF.xls”
“ Contract #### – Bid Drawings (AutoCAD)
(a) Contract #### – Bid Drawings (AutoCAD Files)
(b) Metadata Table- Contract ##### – As-Built
Drawings - AutoCAD.xls”
PAGE 1 OF 2 11/2017
DEP - 3/28/2016
1543
ATTACHMENTS – STANDARDIZED DETAILED SPECIFICATION 01335 –
CONTRACT DEL-260 G, H, E
EXHIBIT B
ProjectTitle
Project Title
CONTRACT
CONTRACT ##########
(Insert
(Insert Contract
Contract Title
Title and
and Description
Description
asasShown
Show onon Contract
Contract Book
Book Covers)
Covers)
Prepared by:
(Insert Contractor
ID or CM/DE ID)
Disk 1 of 1
PAGE 2 OF 2 11/2017
DEP - 3/28/2016
1544
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
SECTION 01355
Hazardous Materials Control
PART 1 GENERAL
1.02 PAYMENT
A. Payment for unforeseen hazardous material remediation and the related
costs of hazardous waste management and regulatory compliance will
be made from the allowance(s) as specified in Detailed Specification
01270 – Measurement and Payment.
B. Except for the allowance specified herein, no separate payment will be
made for performing any other Work required under this Section and the
Contractor shall include all costs thereof in its lump sum price bid for
the Contract.
01355-1 11/2017
DEP – 6/16/2017
1545
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
1.05 DEFINITIONS
A. Competent Person: One who is capable of identifying existing and
predictable hazards in the work area or unsanitary, hazardous, or dangerous
working conditions, and who has authority to take prompt corrective
measures (29 CFR 1926.32(f)).
B. Large Quantity Generator (LQG): A facility that generates (in a calendar
month) ≥1,000 kg of total hazardous waste or >1 kg of acute hazardous
waste or >100 kg of acute hazardous waste spill residue or soil, or at any
time stores hazardous and acute hazardous wastes in greater quantities
than 6,000 kg of hazardous waste, 1 kg acute hazardous waste, or 100
kg of acute hazardous waste spill residue or soil.
1.06 DESCRIPTION
A. Known Hazardous Materials
1. There are materials present within the designated work areas that
will require special handling and other safeguard measures in
order to minimize chemical exposure hazards to site workers and
to prevent environmental impacts to offsite areas. As applicable
to its Work, the Contractor shall incorporate these minimum
requirements into its Environmental, Health and Safety Plan
(EHASP) or other applicable submittal to ensure a safe and
healthful working environment. The Health and Safety Plan shall
be designed in accordance with Detailed Specification 01356 –
Environmental, Health and Safety Requirements.
a. Upon completion of any additional material sampling at
the project/work site(s), the Contractor’s EHASP shall
be updated as needed to incorporate new data generated
by analysis of the samples.
b. Each Contractor should shall share new data on
material’s analysis with other primer contractors under
this Contract.
2. The following are known hazardous materials in the work area
and are to be included in the Lump Sum Bid Items:
a. Asbestos was identified in the caulk around the door
frame(s) in the mezzanine. Although there was no
asbestos identified in the insulation around the door
frame, due to its proximity to the caulk, it is likely to be
impacted during the upgrades, therefore it is
recommended that this be handled as ACM.
b. Lead Containing Paint was identified within the red
paint in the generator room at 3.7% by weight as well as
in the light gray paint in the main room at 2.1% by
weight.
01355-2 11/2017
DEP – 6/16/2017
1546
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
01355-3 11/2017
DEP – 6/16/2017
1547
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
01355-4 11/2017
DEP – 6/16/2017
1548
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
01355-5 11/2017
DEP – 6/16/2017
1549
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
01355-6 11/2017
DEP – 6/16/2017
1550
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
01355-7 11/2017
DEP – 6/16/2017
1551
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
1.08 SUBMITTALS
A. Following items shall be submitted as described above for the
Engineer’s approval:
1. Site Inspection Report
2. Coordination Plan for Known Hazardous Materials. Also for
Unknown Hazardous Materials, when required.
3. Remediation Plan for Unforeseen Hazardous Materials, when
required.
01355-8 11/2017
DEP – 6/16/2017
1552
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
1.09 ATTACHMENTS
A. Exhibit A – Standard Operating Procedure for Entry – Cone Valve
Chamber
END OF SECTION
01355-9 11/2017
DEP – 6/16/2017
1553
DETAILED SPECIFICATION 01355 - HAZARDOUS MATERIALS CONTROL
CONTRACT DEL-260 G, H, E
01355-10 11/2017
DEP – 6/16/2017
1554
ATTACHMENTS - DETAILED SPECIFICATION 01355
________________________________________________________________________________________
CONTRACT DEL-260 G, H, E
Bureau of Water Supply – Eastern Operations Directorate
NYC Department of Environmental Protection
EXHIBIT A
SOP No. 8.6.2015
Contact Terence Murphy, Regional Manager, at the above numbers and EHS Facility
Compliance representative for information regarding this facility.
1. Before entry is made, air monitoring (4-gas meter, PCM and Jerome Meter) shall be used.
Air monitoring shall be continuous while work is being performed in the chamber. A report
of contaminants found in the chamber indicate that surfaces within the chamber have
detectable levels of Aroclors (PCB’s) and heavy metals such as lead, mercury, cadmium and
chromium. If the work performed disturbs surfaces or dust that may contain these
containments, then wet method shall be used to control dust prior to commencement of work.
2. Disposable protective (Tyvek) coveralls, safety glasses, disposable booties, disposable gloves
(nitrile or latex) and a hard hat shall be worn at all times. A negative pressure respirator with
appropriate cartridges shall be carried with entrant in case elevated readings of mercury are
detected in which case the respirator shall be donned as per (3) below). Used PPE shall be
discarded in the “Used PPE” barrel located in the waste storage area of the SH18 building.
1|Page
1555
PAGE 1 OF 2 11/2017
ATTACHMENTS - DETAILED SPECIFICATION 01355
____________________________________________________________________________________
CONTRACT DEL-260 G, H, E
Bureau of Water Supply – Eastern Operations Directorate
NYC Department of Environmental Protection
SOP No. 8.6.2015
3. Where Jerome Meter readings indicate that the mercury vapor levels are at or above the DEP
Permissible Exposure Limit (PEL) (TWA) of 0.050 mg/m3, but below 0.10 mg/m3:
Where Jerome Meter readings indicate that the mercury vapor levels exceed 0.10 mg/m3:
All personnel must immediately evacuate the area until levels return below the ceiling
level of 0.10 mg/m3.
2|Page
1556
PAGE 2 OF 2 11/2017
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
SECTION 01356
Environmental Health and Safety (EHS) Requirements
PART 1 GENERAL
A. Requirements for the Contractor to provide its employees and those of its
subcontractors a safe and healthful work environment and for performing all
Work in compliance with all applicable environmental health and safety laws,
rules, and regulations.
01356-
01356-1 11/2017
DEP 3/15/2016
1557
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
1.04 Definitions........................................................................................3
PART 2 PRODUCTS...................................................................................13
1.02 PAYMENT
A. No separate payment will be made for performing any work of this Section. The
Contractor shall include all costs for this work in its lump sum price bid for the
Contract.
A. The Contractor shall comply with all current federal, state, city and local EHS
laws, rules, and regulations, including all those that become effective during the
01356-2 11/2017
DEP 3/15/2016
1558
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
term of the Contract, related to ensuring health and safety of employees and to
the protection of property and the environment.
1.04 DEFINITIONS
B. “EHS Resources” shall mean the Contractor’s EHS Professional(s) and its EHS
Site Representative (EHS Rep), as approved by the BEDC EHS unit. This
definition shall also apply to the subcontractors’ EHS Resources, where
required. This definition also includes any consultant or other EHS personnel
associated with the project. Such EHS personnel are subject to evaluation and
approval by BEDC EHS as set forth in this Section.
C. “Environmental Health & Safety Plan (EHASP)” shall mean the plan developed
in accordance with all applicable EHS rules and regulations and these
Specifications to identify and set forth policies and procedures to control the
health and safety concerns and environmental impacts known and unknown at
the site. This plan is not to be confused with the Health and Safety Plan that
may be required under 29 CFR 1910.120 for Hazardous Waste Operations and
Emergency Response (HAZWOPER).
01356-3 11/2017
DEP 3/15/2016
1559
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
D. “Job Hazard Analysis” shall mean a tool used to document a process by which
the steps required to accomplish a work activity are outlined, the actual or
potential hazards for each step are identified, and measures for the elimination
or control of those hazards are developed.
E. “Incident” shall mean an event in which a person or persons are injured or made
ill, property or equipment is damaged, the environment is harmed, or an
environmental release occurs.
1.05 DESCRIPTION
A. In performing the Work of this Contract, the Contractor shall at all times be in
compliance with all federal, state, City and local environmental, health and
safety laws, rules, and regulations.
B. The Contractor shall be responsible for the health and safety of its employees,
subcontractors, the public and all other persons at or around the work site. The
Contractor shall be solely responsible for the adequacy of all construction
methods, materials, equipment and the safe and environmentally compliant
prosecution of the Work. Where possible, the Contractor shall implement Best
Management Practices to reduce injuries, accidents and environmental impacts.
D. The Contractor shall perform and document its due diligence in determining
whether the subcontractors they hire to perform work under the Contract are
capable of performing to the EHS standards set forth in this Section. At a
minimum, the Contractor is required to perform an EHS evaluation of
01356-4 11/2017
DEP 3/15/2016
1560
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
subcontractors prior to submitting them for DEP approval. The Contractor must
have a subcontractor EHS evaluation program that is at least as stringent as the
DEP Contractor Selection and Management Policy available in the BEDC web-
based PMIS. Poorly performing subcontractors will affect the Contractor’s
performance evaluations and ability to obtain future contracts with DEP.
E. DEP requires a drug and alcohol free, healthful, safe and secure work
environment. Contractor employees will report to work in an appropriate
mental and physical condition for work. DEP reserves the right to require any
Contractor or subcontractor employee to submit to drug testing when cause for
reasonable suspicion of a violation of this policy exists. Drug testing may occur
when: a) there is reasonable suspicion that an employee is under the influence
of alcohol or illegal drugs, or b) an employee has been in involved in an
Incident, or involved in an unsafe practice, or c) as required by BEDC EHS
Standards. The Contractor must prohibit any employee from being under the
influence of any illegal drug or alcohol while at work, on duty, or operating a
vehicle or construction equipment.
G. The Contractor shall ensure that its EHS Resources have appropriate authority
to execute their duties and responsibilities as set forth in this Section and under
the Contractor’s EHS Management Program.
2. For all contracts that employ 100 or less employees on site at any time,
the Contractor shall have at least one full-time site EHS Rep. The
Contractor may submit a request in writing to the Engineer to waive the
requirement of a separate EHS Rep at each site and permit other
01356-5 11/2017
DEP 3/15/2016
1561
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
3. For all contracts that employ over 100 employees on site at any time,
the Contractor shall have at least two full time EHS Reps. These EHS
Reps shall have no other duties except those related to EHS on the
Contract, and shall not be project managers, engineers, superintendents
or have any other title or project role other than EHS Rep.
6. If the Contract has more than one location, each location shall be treated
as a separate contract for purposes of determining the number(s) of
necessary EHS Reps in accordance with paragraphs 2 through 4 above.
J. All site workers have the right to refuse unsafe work which is reasonably
believed to present imminent danger to their own safety or the safety of others,
the public or the environment, or to City property, without adverse
consequences.
K. The Contractor and its subcontractors shall stop work and initiate immediate
corrective action whenever a work procedure or a condition at the work site is
deemed unsafe by the EHS staff, DEP, Competent Persons, or the Engineer.
01356-6 11/2017
DEP 3/15/2016
1562
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
All Contractor and subcontractor employees working on site shall report any
unsafe or noncompliant work condition(s) immediately to the EHS staff,
Competent Persons, or Engineer. If a stop work order is issued to the Contractor
by the Engineer for unsatisfactory EHS performance, the Contractor shall not
make any claim against the City for any losses associated with the stop work
order.
L. The Contractor and all subcontractors are responsible for daily cleanup of their
immediate work areas per BEDC’s Housekeeping Standard. Construction scrap
and debris shall be removed daily during the course of construction, alterations
and repairs. Contractor refuse shall not be allowed to accumulate creating trip
hazards and blocking access routes and pathways. The Contractor shall
implement procedures to ensure a high standard of housekeeping. All waste
shall be disposed of in accordance with the appropriate regulations and
applicable Specifications.
M. The Contractor shall ensure that any sand, soil, plaster, cement, mortar or the
like is not deposited or washed into any drain or sewer unless specifically
authorized under required permits.
A. The Contractor shall have a written EHASP prepared and signed by the EHS
Professional in accordance with the BEDC EHASP Standard. The EHASP
must be signed by a principal or senior manager of the company and project
management staff. The EHASP shall be submitted to BEDC for review and
approval prior to the start of any work. Job Hazard Analyses (JHAs) will be
developed as the work progresses, in accordance with the BEDC JHA Standard,
and will supplement the Contractor’s EHASP.
A. The Contractor shall work with the Construction Manager and other
Contractors to develop a single cohesive construction EAP in accordance with
BEDC’s EAP Standard.
01356-7 11/2017
DEP 3/15/2016
1563
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
A. The Contractor shall establish a Spill Prevention Program (SPP) for the
prevention of releases of petroleum, hazardous substances or other pollutants.
The SPP shall be included in the EHASP, and include awareness training for all
personnel on measures designed to reduce, minimize and eliminate the potential
for releases.
B. The Contractor shall establish sound work practices and implement appropriate
measures to achieve release prevention and control of releases when they do
occur.
C. At a minimum, the Contractor shall include within the SPP the following:
D. The Contractor shall bear sole responsibility for all costs and delays resulting
from any releases on the project which occur as a result of the work activities.
01356-8 11/2017
DEP 3/15/2016
1564
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
A. Qualifications
1. The Contractor shall ensure that, at all times, its employees and those of
its Subcontractors working on this Contract have received OSHA 10-
Hour Construction training or OSHA 30-Hour training within the last
five years.
01356-9 11/2017
DEP 3/15/2016
1565
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
01356-10 11/2017
DEP 3/15/2016
1566
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
6. The EHS Professional and EHS Rep shall have extensive experience
with hazard identification, evaluation and controls, and be
knowledgeable of all applicable EHS requirements set forth by
governing laws, rules and regulations as well as Best Management
Practices. Where gaps in the training or experience are identified, DEP
may require additional experience or training for approval.
1.10 SUBMITTALS
A. The Contractor shall submit the EHASP to the draft Engineer for review and
approval within thirty business days from issuance of the Notice to Proceed. In
no case shall Work be allowed to commence without an approved EHASP.
1. Initial submission of the EHASP shall be provided as one hard copy and
one electronic copy (either Word or Acrobat format) to the Engineer.
3. Upon receipt of final approval, the Contractor shall provide one hard
copy and one electronic copy (either Word or Acrobat format) of the
EHASP to the Engineer.
C. Review, acceptance and/or approval of the EHASP will not impose on any other
party responsibility for the EHASP, nor will it relieve the Contractor from any
of its EHS responsibilities.
D. The Contractor shall submit to BEDC EHS for approval, the names of the EHS
Professional and EHS Rep(s) to be employed. BEDC EHS may request and
conduct an interview of the candidates prior to approval. The Contractor shall
submit the resumes, copies of certifications, a signed certification of employee
training, along with other qualifications of the EHS Professional and EHS Rep.
The resumes shall include items such as: experience, education, EHS courses
completed, safety and environmental conferences attended, and certifications
achieved. Documentation and/or personal references confirming the
qualifications may also be required. The NYCDEP may reject persons
proposed as EHS Professionals or EHS Reps for failure to have adequate
01356-11 11/2017
DEP 3/15/2016
1567
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
qualifications or for other cause at any point prior to and during the contract
period, as determined by the Engineer.
E. The Contractor shall adhere to the requirements of BEDC Incident and Near
Miss Reporting and Investigation Standard and shall immediately notify the
Engineer of all incidents involving employee injury and illness, and any other
work-related incidents or near misses, damage to equipment and structures, and
any releases or adverse impacts to the environment.
F. The Contractor must notify the Engineer and BEDC EHS immediately of any
regulatory inspections, notices of citations and penalties, Notices of Violation
(NOVs), or any other outside agency violations. In addition, the Contractor
shall furnish to the Engineer a copy of all correspondence from OSHA,
NYSDEC, DOB or any other government regulatory agency, within one day of
receipt, which may include employee complaints, notices of citations and
penalties, environmental NOVs, etc. The Contractor must close out all NOVs
and provide documentation to the Engineer that the NOV is closed/corrected or
final payment will not be provided.
G. The Contractor will forward to the Engineer any risk control reports generated
by their insurance carrier or broker within one day or receipt.
1. The Contractor shall submit, on or before the 10th day of the month, a
summary report of EHS activity for the prior month, including, but not
limited to:
01356-12 11/2017
DEP 3/15/2016
1568
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
2. The Engineer shall review the report to verify that the Contractor is
effectively managing the EHS requirements under the contract. If the
Contractor has no, or limited work in a given month, they shall inform
the Engineer that no work was performed or submit the required
documentation for those days that work was performed.
I. Performance Evaluations
3. Any EHS Professional or EHS Rep who knowingly falsifies any data,
result, audit, document, etc. will be removed from the project and
precluded from further DEP Work.
PART 2 PRODUCTS
A. The Contractor shall provide the proper EHS and rescue equipment for all
employees, adequately maintained and readily available, for any foreseeable
contingency or situation under the Contract during the performance of the
Work.
B. All equipment shall be stored in protected areas and maintained and calibrated
as per the manufacturer’s recommendations and as specified in the EHASP.
Where equipment is required to be inspected and or calibrated, documentation
shall be maintained and available for review.
All personnel employed by the Contractor and any visitors entering the job site
shall be required to wear appropriate personal protective equipment (PPE)
01356-13 11/2017
DEP 3/15/2016
1569
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
required as specified in the EHASP and the BEDC EHS PPE Standard. The
Contractor shall continuously provide and maintain adequate PPE.
PART 3 EXECUTION
A. The Contractor’s EHS staff is responsible for overseeing and managing the
Contractor’s safe and environmentally compliant performance of all Work.
D. The EHS Professional shall visit the site prior to developing the Contractor’s
EHASP. The EHS Professional will arrange a visit with the Engineer and
perform an inspection of the site to understand the full scope of Work to be
performed under the Contract. Contract Documents relevant to writing the
EHASP can be reviewed and obtained at this time. Facility/site specific
information must be provided, reviewed, and documented in accordance with
the BEDC EHS Site Orientation Standard.
E. The EHS Professional shall visit all work areas as frequently as necessary, but
no less frequently than monthly, to verify that EHS compliance is being
achieved. The EHS Professional shall review hazards, JHAs, and the foremen’s
and superintendent’s preparation and communication of JHAs to workers. The
EHS Professional shall review the project team’s compliance with and
adherence to EHS requirements, as well as their proactive approach and
planning for EHS.
01356-14 11/2017
DEP 3/15/2016
1570
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
site, but shall also mentor and direct the EHS Rep. During the inspection, the
EHS Professional will evaluate the Contractor and each subcontractor working
under the Contract and clearly identify findings and who they are assigned to,
using the EHS Professional checklist provided in the EHASP. Any findings that
cannot be resolved immediately will be assigned to the EHS Rep for follow-up.
The EHS Professional is expected to communicate with the EHS Rep to ensure
all identified findings are closed out. The EHS Professional’s inspection shall
include programmatic issues such as adhering to the Contractor’s EHS
program, including, but not limited to, preparing and communicating JHAs and
proactively minimizing EHS risks.
H. The EHS Rep will coordinate with the EHS Professional when questions arise
requiring EHS Professional expertise. After each visit, the EHS Professional
shall prepare a report, including photographs (where necessary), acceptable to
the Engineer and BEDC EHS, detailing the findings. The report shall include
those hazards and violations discovered during the site visit and when and how
they were or will be closed out. Any EHS items not covered or documented by
the inspection checklist will be noted in the comments section of the checklist.
The report shall be submitted to the Engineer within one business day of the
site visit.
I. The EHS Rep shall be at the job site full time whenever work is in progress
during all shifts.
2. The EHS Rep must review JHAs to verify that the work activity’s EHS
issues and hazards are accurately identified, addressed, and
communicated. JHAs shall be regularly communicated to affected
employees and must be made available in the areas where the affected
employees are working. The EHS Professional is responsible for
periodically reviewing JHAs to verify that they adequately reflect the
recognized hazards and controls of the tasks being performed. JHAs
shall be provided to the Engineer or BEDC EHS when requested.
01356-15 11/2017
DEP 3/15/2016
1571
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
3. Both shall schedule and conduct EHS meetings and training programs
as required. A specific schedule of these meetings and an outline of
topics to be covered shall be provided with the EHASP. The Engineer
shall be advised in advance of the time and place of such meetings, and
DEP personnel shall be invited to attend the meetings.
10. The EHS Rep is to conduct EHS inspections a minimum of twice a shift
to ensure that all machines, tools and equipment are in a safe operating
condition, and that all work areas are free of safety and environmental
hazards. Take necessary and immediate corrective actions, where
feasible, to eliminate all unsafe acts and/or conditions, and submit to the
Engineer each day a copy of their findings on the inspection check list
report forms established in the EHASP. Detailed checklists will be
01356-16 11/2017
DEP 3/15/2016
1572
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
tailored to the EHS hazards and conditions on the site, and will include
a comments section to include findings not specifically listed on the
checklist.
11. Whenever DEP and its agents perform both announced and
unannounced inspections of the Contractor’s EHS performance, a
member of the Contractor’s on-site EHS team will make themselves
available during inspections performed by DEP or its representatives.
The EHS Professional will coordinate inspections with the Engineer and
DEP inspectors upon request. The Contractor shall take immediate
corrective action, where feasible, to eliminate of hazards identified by
the Engineer, DEP inspectors, or any other entity. The Contractor, if
requested, shall develop and implement a plan detailing corrective
actions necessary to mitigate the presence of noncompliant conditions
and actions following Incidents, citations, NOVs, or identification of
patterns of noncompliant conditions and acts.
12. Notify the Engineer and BEDC EHS immediately of all inspections by
regulatory agencies, and submit to the Engineer and BEDC EHS copies
of all EHS reports, citations, and NOVs from regulatory agencies and
insurance companies within one workday of receipt.
13. Implement an effective fire protection and prevention program at the job
site throughout all phases of the construction Work in accordance with
BEDC’s Fire Prevention Standard. The Contractor will ensure the
availability of fire protection and suppression equipment adequate to
control the degree of fire hazard encountered during construction.
01356-17 11/2017
DEP 3/15/2016
1573
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
B. The Contractor shall prepare and provide to the Engineer, a Right to Know
(RTK)/Emergency Planning and Community Right to Know Act (EPCRA)
Annual Chemical Inventory Form for all hazardous and extremely hazardous
substances that the Contractor used or stored that exceeded legal thresholds
during the previous calendar year. This shall be provided by February 1st of
each year.
C. The Contractor shall bear sole responsibility for complying with annual
reporting requirements. For facilities within the five boroughs, the New York
City Community RTK Law requires annual reporting of hazardous and
extremely hazardous substances from all facilities that stored or used hazardous
substances that met the applicable law’s thresholds. For facilities outside the
five boroughs of New York City, the Federal EPCRA requires annual reporting
of hazardous and extremely hazardous substances from all facilities that stored
or used hazardous substances that met the applicable law’s thresholds.
1. The Contractor is the “facility” during the construction phase and must
report on its hazardous substances if the applicable law’s thresholds are
met.
3. In NYC, the Contractor must file using the NYC Facility Inventory
Form. Filing instructions can be found on the website
www.nyc.gov/dep/tier2filing. Within NYC there is a Right to Know
filing fee.
4. Outside of New York City, the Contractor must use the SARA Tier II
forms. Information for filing outside of NYC is found on the website
www.semo.state.ny.us/programs/SERC/tier2.cfm.
D. The Contractor must satisfy all EPCRA reporting requirements for the final year
of the Contract before completion will be accepted by DEP.
E. The Contractor must provide a copy of the filed annual report to the Engineer.
3.03 VISITORS
A. Allowing visitors and members of the public to tour an active construction site
is discouraged due to the potential exposures to hazardous conditions and
materials associated with construction work. However, where necessary,
approved and authorized visitors of the Contractor, subcontractors, or any other
01356-18 11/2017
DEP 3/15/2016
1574
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
3.04 ATTACHMENTS
END OF SECTION
01356-19 11/2017
DEP 3/15/2016
1575
DETAILED SPECIFICATION 01356 - ENVIRONMENTAL, HEALTH AND
SAFETY REQUIREMENTS
CONTRACT DEL-260 G, H, E
01356-20 11/2017
DEP 3/15/2016
1576
ATTACHMENTS 01356 - ENVIRONMENTAL, HEALTH AND SAFETY
REQUIREMENTS
CONTRACT DEL-260 G, H, E
EXHIBIT A
PAGE 1 OF 6 11/2017
DEP 3/15/2016
1577
ATTACHMENTS 01356 - ENVIRONMENTAL, HEALTH AND SAFETY
REQUIREMENTS
CONTRACT DEL-260 G, H, E
PAGE 2 OF 6 11/2017
DEP 3/15/2016
1578
ATTACHMENTS - DETAILED SPECIFICATION 01356
CONTRACT DEL-260 G, H, E
Revision: 1
Volume III Contractor Selection & Management Effective Date: 11/3/08
1.1 Scope
The Department of Environmental Protection (NYCDEP) has developed procedures to
ensure that contractors’ environmental, health and safety (EHS) records and programs
are evaluated when NYCDEP is selecting a contractor or approving a subcontractor.
These procedures also require that the contractors are properly prepared and trained to
safely complete the work and to adhere to all EHS laws, rules and regulations.
NYCDEP facilities are subject to requirements regarding qualification, supervision and
activities of contractors.
The intent of this section is to advise the Contractor of the EHS training and Contract
Award requirements for performing work at NYCDEP facilities as well as special
procedures applicable to locations where hazardous materials are stored and used.
Revision: 1
Volume III Contractor Selection & Management Effective Date: 11/3/08
1.3.3 For Joint Ventures the above information must be provided and will be
reviewed for both the Joint Venture and the individual Joint Venture partners.
PAGE 4 OF 6 11/2017
DEP 3/15/2016
1580
ATTACHMENTS - DETAILED SPECIFICATION 01356
CONTRACT DEL-260 G, H, E
Revision: 1
Volume III Contractor Selection & Management Effective Date: 11/3/08
1.3.4 The subcontractor approval process requires an information submittal that includes the
subcontractor EMR, program descriptions and certifications similar to those
required for the Contractor. The above review criteria may also apply to the
acceptance of Subcontractors performing a significant volume or aspect of the
project.
PAGE 5 OF 6 11/2017
DEP 3/15/2016
1581
ATTACHMENTS - DETAILED SPECIFICATION 01356
CONTRACT DEL-260 G, H, E
Revision: 1
Volume III Contractor Selection & Management Effective Date: 11/3/08
1.5.2 The Contractor and subcontractors and all of their employees shall, upon
request, produce certificates, licenses and other documentation that laws or
regulations require them to obtain in order to conduct activities they are
performing (e.g., Asbestos Worker Certificate, FDNY Certificate of Fitness in
New York City).
1.5.3 The Contractor shall, at all times when working at the facilities, exercise all
necessary precautions to avoid interaction with the hazardous material feeds
and/or storage systems and conform to all directions and instructions provided
by the NYCDEP.
1.5.4 Contractor and subcontractor employees are restricted from entering all high-
hazard process areas, unless access is required to perform their work. In
coordination with the Contract Supervisor, the Contractor or subcontractor
employees entering such process areas must obtain permission from the on-duty
operator/Supervisor in person or by the telephone before entering and must
inform the on-duty operator/Supervisor in person or by telephone upon leaving
and follow all other facility access control procedures.
1.5.5 Any worker who fails to abide by the EHS requirements presented in the
hazardous material and safe work practices information package and/or at the
orientation shall, at the sole discretion of the NYCDEP, be denied access to the
facilities and shall be replaced by the Contractor, as directed by the NYCDEP.
1.5.6 The Contractor shall immediately inform the NYCDEP Contract Supervisor
and the facility’s Responsible Individual of all chemical or petroleum product
spills or releases, of any contract employee OSHA-reportable work place
injuries or illnesses, and of any notices of violation resulting from work
performed. Initial written reports shall be submitted by the next day. Refer to
other safety specifications for additional investigation and reporting
requirements.
1.5.7 NYCDEP will perform periodic evaluations of the contractor’s performance to
ensure compliance with all EHS laws and regulations and NYCDEP and facility
EHS requirements. The Contractor must correct non-compliance with any
applicable laws, regulations and NYCDEP and facility EHS requirements when
such non-compliance is communicated to it by NYCDEP. Failure to correct
such non-compliance in a timely manner or repeated violation of any EHS law,
regulation or NYCDEP/facility requirement, especially a violation about which
it received a prior notification, is grounds for stopping work until corrective
actions are completed. Such failures will also be considered when evaluating
the Contractor’s submittals for future work proposals.
PAGE 6 OF 6 11/2017
DEP 3/15/2016
1582
DETAILED SPECIFICATION 01410 – REGULATORY REQUIREMENTS
CONTRACT DEL-260 G, H, E
SECTION 01410
Regulatory Requirements
PART 1 GENERAL
B. Work permits
D. Existing utilities
E. Drainage
H. No Advertising Sign
I. Non- Compliance
1.02 PAYMENT
A. No separate payment will be made for performing any Work of this Section. The
Contractor shall include all costs for this Work in its lump sum price bid for the
Contract.
A. The Contractor shall provide proper facilities for inspection and access to the work at
all times, whenever it is in preparation and progress, for authorized representatives of
the City, local, State and Federal Governments, the latter three in the presence of the
Engineer.
A. Unless otherwise specified in the Detailed Specifications, the Contractor shall obtain,
pay for, and comply with all necessary permits, licenses, approvals, certificates of
inspection, and controlled inspection reports, and shall give all notices and pay all legal
01410-1 11/2017
1583
DETAILED SPECIFICATION 01410 – REGULATORY REQUIREMENTS
CONTRACT DEL-260 G, H, E
fees to the City and local Departments in connection with the Work of this Contract.
B. All Work performed under the Contract shall conform to the rules and regulations of
the Bureau of Electrical Control, Department of Business Services, Department of
Buildings; the Building Laws of the City of New York and all other City, local, State
and Federal Departments having jurisdiction.
C. The Contractor is advised that all activities associated with this Work are to be
conducted in accordance with the permits for this project, including, but not limited to:
the New York State Department of Environmental Conservation (NYSDEC) SPDES
Permit for Discharge of Stormwater from Construction Activities. The Contractor shall
comply in all respects with the requirements of these permits.
D. Upon completion of the various stages of construction, the Contractor shall schedule
inspections and obtain certificates of approval and/or acceptance from the various
agencies and Departments having jurisdiction and shall deliver these certificates to the
Engineer.
E. The necessary permits to be obtained by the Contractor include, but are not limited to,
the following:
F. The Contractor shall comply with the conditions and regulations of the permits that are
obtained by the City or its Engineer. These permits include, but are not limited to, the
following:
01410-2 11/2017
1584
DETAILED SPECIFICATION 01410 – REGULATORY REQUIREMENTS
CONTRACT DEL-260 G, H, E
B. After completion of his Work, the Contractor shall notify the local office of the Town
of Mount Pleasant Building Department and Department of Buildings, by letter,
requesting that a final inspection be made.
C. Prior to final payment, there must be filed in the Office of the Comptroller of the City a
Certificate of Inspection signed by the Superintendent of the Town of Mount Pleasant
Building Department shall certify that:
1. All material and workmanship comply in every respect with the rules and
regulations of the Town of Mount Pleasant Building Department and the New
York City Electrical Code.
2. All materials and workmanship comply in every respect with the Contract
Documents approved by the Town of Mount Pleasant Building Department and
fulfill the intent thereof.
A. All subsurface utility and structure information shown on the Contract Drawings were
obtained from various plans and maps and field investigations, however they are not
guaranteed to be complete or accurate. It shall be the Contractor's responsibility to
locate all such necessary utilities or structures by digging test pits prior to the starting
construction. No separate payment will be made for test pits.
B. During progress of the Work, the Contractor shall protect from damage any existing
utilities or services within the work areas until, they have been re-routed, disconnected
or capped off.
1.07 DRAINAGE
A. The Contractor shall, as approved by the Engineer, provide and construct flumes,
berms, dams and all incidental and related facilities necessary to divert groundwater
and surface drainage, and to prevent any sediment from being conveyed into the
reservoir or water courses.
01410-3 11/2017
1585
DETAILED SPECIFICATION 01410 – REGULATORY REQUIREMENTS
CONTRACT DEL-260 G, H, E
A. The Contractor's attention is directed to requirements of the Industrial Code of the State
of New York, Department of Labor, Board of Standard and Appeals, latest edition and
amendments or supplements thereto. All mechanical equipment with respect to
manufacture, fabrication, and safety devices for protection of personnel from electrical
parts and mechanically moving parts such as belts, shafts, couplings, and other
apparatus, appliances or equipment, all floors, stair surfaces, ladders, equipment, access
stairs and platforms, all exit enclosures, vertical openings and stairs, shall comply with
this code; and all provisions therein shall be deemed included in and required by these
Specifications and shall be detailed for approval and furnished without additional cost;
the price thereof considered to be included in the applicable prices bid for the various
Contract Items in the Contracts.
A. All Work under this Contract shall conform to the current applicable requirements of
the NYS Department of Transportation, the NYS Uniform Fire Prevention and Building
Code, the National Electrical Code (NFPA 70), ANSI, ASTM, IEEE, NEMA, OSHA,
UL, the Contract Documents and the documents specified elsewhere in the Detailed
Specifications.
1. The State of New York codes shall be followed in case of conflict. Latest edition
of all codes shall apply.
2. Petroleum storage shall conform to applicable state, county and local codes (Parts
612 through 614 in Title VI of the New York Code of Rules and Regulations;
Schoharie County Sanitary Code; Town of Gilboa Code).
3. Lifting operations and requirements for submittals for lifting plans shall conform
to Section 585-3.02 of the New York Standard Specifications, latest edition.
B. In case of conflict, the more stringent requirements of the latest edition of the codes
shall apply.
C. All materials and equipment submitted for approval by the Contractor shall have, at the
time of their submittal, a current Report of Material and Equipment Acceptance from
the New York City Department of Buildings, Materials and Equipment Acceptance
Division, indicating acceptance of the item submitted for approval for its specified use.
A. Contractor shall not display any advertising signs on or about the Site of the Work other
than those specified, without the written permission of the Engineer.
01410-4 11/2017
1586
DETAILED SPECIFICATION 01410 – REGULATORY REQUIREMENTS
CONTRACT DEL-260 G, H, E
1.11 NON-COMPLIANCE
A. All fees/penalties incurred by the Contractor, City, County, Town of Mount Pleasant,
Engineer or other such entity, resulting from non-compliance by the Contractor with
permits or approvals obtained by the Contractor, permits obtained by the City or
Engineer, conformance to the Industrial Code or conformance to other codes or
standards governing the performance of this Contract will be paid for by the Contractor
and deducted from the final payment.
END OF SECTION
01410-5 11/2017
1587
DETAILED SPECIFICATION 01410 – REGULATORY REQUIREMENTS
CONTRACT DEL-260 G, H, E
01410-6 11/2017
1588
DETAILED SPECIFICATION 01415 – MISCELLANEOUS PROJECT
REQUIREMENTS
CONTRACT DEL-260 G, H, E
SECTION 01415
Miscellaneous Project Requirements
PART 1 GENERAL
B. Diagrammatic drawings.
C. Ratings approximate.
G. Uniform finishes.
H. ANSI/NSF 61 Certification.
1. "Concealed" piping and ducts shall mean piping and ducts hidden from sight
in masonry or other construction, in floor fill, trenches, partitions, hung
ceilings, furred spaces, pipe shafts and in service tunnels not used for passage.
Where piping and ducts run in areas that have hung ceilings, such piping and
ducts shall be installed above the hung ceilings.
2. The Contract Drawings are in part diagrammatic and show the general
arrangement of the equipment, ducts and piping included in the Contract and
the approximate size and locations of the equipment. The Contractor shall
follow these Contract Drawings in laying out the Work and shall consult the
Contract Drawings of the other Contracts to familiarize himself with all
conditions affecting his Work and to verify the spaces in which it will be
installed.
01415-1 11/2017
1589
DETAILED SPECIFICATION 01415 – MISCELLANEOUS PROJECT
REQUIREMENTS
CONTRACT DEL-260 G, H, E
B. All gravity and pressure pipelines and appurtenant structures shall be field tested for
leakage after installation in accordance with the requirements contained in the
applicable General Specifications as supplemented by the Detailed Specifications.
A. Various pipelines are shown on the Drawings in diagram form. Where such
pipelines are shown in diagram form, they shall be arranged clear of other pipelines,
equipment and walking areas, and shall be accessible for maintenance. Such
pipelines shall be fitted and installed in a neat and workmanlike manner in
accordance with approved Shop Drawings. An adequate number of unions shall be
provided in main pipe and branch pipe runs to facilitate dismantling or removal of
pipeline sections without disturbing adjacent branch or connecting lines.
B. The final locations of valves, fittings and other such appurtenances included as a
part of diagrammed pipelines shall be as shown on approved Shop Drawings or as
determined in the field by the Engineer.
D. In the vicinity of overhead roll-up doors and truck ways all pipe, conduit and
appurtenances shall be installed a minimum of 14'-0" above the finished grade or
floor elevation, and a minimum of 8'-0" above the finished grade or floor elevation
in all walking areas.
E. Electrical conduits and wiring are in part diagrammatic and show the general
arrangement and routing of conduits and wiring and the approximate size and
location of devices included in the Contract. The Contractor shall follow the intent
of these Contract Drawings in laying out the Work. The Contractor shall verify the
spaces allocated in which his Work will be installed.
A. The ratings of the devices shown on the Contract Drawings are approximate only
and are merely indicative of the probable power requirements insofar as they can be
determined in advance of the purchase of devices. The ratings of the devices
01415-2 11/2017
1590
DETAILED SPECIFICATION 01415 – MISCELLANEOUS PROJECT
REQUIREMENTS
CONTRACT DEL-260 G, H, E
B. The Contractor shall verify the exact rating of each device before performing the
Work required under his Contract and modify the size of conduit, wiring and control
equipment accordingly.
A. The following systems will be available for operation of motor driven equipment
and electrical devices furnished under the Contract:
1. 480 Volts, 3 Phase, 3 Wire power for all equipment, motor control centers,
power panels and lighting transformers, except as listed hereinafter.
2. 208Y/120V, 3 Phase, 4 Wire, grounded neutral power for single phase, 120
Volt operation of motors 1/3 horsepower or smaller, alarm circuits, and
various low power devices and control circuits and receptacle circuits.
A. All electrical equipment and devices manufactured and furnished under the Contract
shall be of a type that have been in satisfactory operation for not less than three
years, except as provided in Article 5 of the General Conditions. Whenever similar
devices or appliances are furnished, they shall be of one manufacturer and
interchangeable within their ratings. If this is not feasible, the Contractor shall
submit a statement for each manufacturer supplying devices, certifying the
following:
1. That they recommends the use of the device or devices for the specific
function to be performed;
2. That they fully guarantees the satisfactory operation of the device or devices in
conjunction with the other elements of the equipment.
1591
DETAILED SPECIFICATION 01415 – MISCELLANEOUS PROJECT
REQUIREMENTS
CONTRACT DEL-260 G, H, E
fulfill the specified conditions, they shall be modified or special devices shall be
furnished. All electrical devices furnished under the Contract shall be housed in
metal enclosures with provisions for threaded conduit connections. The enclosures
shall be designed to protect all electrical parts from local conditions.
C. The ratings of motors and devices given in various Detailed Specifications are
approximate only and merely indicate the probable power requirements insofar as
they can be determined in advance of the purchase of the equipment specified. The
ratings of the motors and other devices furnished may be either increased or
decreased according to the requirements of the equipment furnished and the
Contractor shall verify the exact rating of each item of equipment before performing
the Work required under this Contract.
D. Float switches, limit switches and other mechanically actuated electrical devices
shall consist of an approved electrical system housed in rugged metal enclosures.
They shall be adjustable without disturbing conduit connections. The switch
actuating mechanism shall be mechanically and structurally correct for the required
service and shall not subject the electrical parts to unnecessary stress or mechanical
shock. Operating shafts shall be bushed and stuffed in dust-tight cases. Switches
containing mercury shall not be permitted.
E. The Contractor shall, unless otherwise directed, furnish and assemble all special
lamps, indicating lamps, annunciator lamps and pilot lamps with all accessories.
F. Electrical equipment rated greater than 1,000 watts and lighting equipment greater
than 15 watts with an inductive reactance load component, shall have a power factor
of not less than 85 percent under rated load conditions. Electrical equipment with a
power factor less than 85 percent shall be corrected to at least 85 percent under
rated load conditions. Installed power factor corrective devices shall be switched
with utilization equipment.
G. Nameplates and warning signs shall be provided. Nameplates shall be 1/16 inch
thick laminated plastic, white with a black core for black engraved lettering, and
shall have beveled edges. They shall be provided for all controls on all power
control panels and cabinets, lighting cabinets and operating devices, marked and
positioned on the front panel as approved by the Engineer. Mounting shall be by
stainless steel screws through predrilled nameplate holes, one at each end of the
plate. The Contractor shall provide, as required or as directed, all warning signs
required for the safe operation of the equipment. Such warning signs shall be of
substantial material, porcelain enameled, of suitable thickness and as approved by
the Engineer. All components within electrical control panels, switchgear and
assemblies shall be identified with engraved stainless steel tags rigidly mounted at
or near the respective device.
1592
DETAILED SPECIFICATION 01415 – MISCELLANEOUS PROJECT
REQUIREMENTS
CONTRACT DEL-260 G, H, E
control panels, alarm boards, and motor control equipment shall consist of cup
terminals, pronged washers, compression type solderless connectors or pressure
type terminals furnished on devices.
I. All control and indication wires within switchboards, control centers and other
panels and cabinets shall be terminated on terminal blocks provided with marking
strips for wire designation. The manufacturer shall identify all wires on the marking
strips. All field wires will be terminated and identified by the Contractor.
J. Provision shall be made for wire and cables installed at the plant site to be
terminated by the Contractor with approved solderless copper alloy lugs. Lugs may
be of the compression type, clamp type or screw type with internal pressure bar, or
may be pressure-tool applied solderless connectors. Pressure tool applied solderless
connectors for wires 250 MCM or larger shall have long barrels to allow double
indentation. Where clamp type or screw type lugs are installed on wires 1/0 AWG
and larger, wire ends shall be filled with solder, contact surfaces of lugs shall be
tinned and heat shall be applied when the lugs are tightened.
L. All electrical equipment and Work shall be in accordance with the Electrical Code
of the City of New York. The Contractor shall submit proof to the Engineer of
application for an electrical inspection certificate for equipment furnished under this
Contract in accordance with Article 12 of the General Conditions.
A. A uniform finish shall be used for all hardware, metallic nameplates and similar
exposed metal parts used on any equipment or group of equipment and, as far as
possible, the same finish shall be used for all such equipment items.
A. Materials that come in contact with drinking water, drinking water treatment
chemicals, or both, shall be ANSI/NSF 61 Certified. Materials include, but are not
necessarily limited to, the following:
1. Pipe and related products including fittings, couplings, flexible and rigid
tubing, riser tubing, dip tubes, hoses, wall casings, drop pipes, screens, and
pipe related coatings.
01415-5 11/2017
1593
DETAILED SPECIFICATION 01415 – MISCELLANEOUS PROJECT
REQUIREMENTS
CONTRACT DEL-260 G, H, E
4. Process media including, but not necessarily limited to, those used for ion
exchange, adsorption, oxidation, aeration and filtration
A. The Contractor shall establish designated smoking areas outdoors which are at least
thirty feet from construction activities and all flammable and combustible material.
The locations will be subject to the approval of the City and Engineer. These areas
must be clearly delineated with signage, equipped with fire extinguishers and
appropriate waste receptacles, and maintained. The areas will be relocated as needed
due to changes in construction activities.
There will be zero tolerance for any personnel found smoking outside of these
designated areas, and the Contractor shall remove any worker found smoking outside
of these designated areas. This shall be in a progressive disciplinary policy: first
offense, removal for the day; second offense, removal from the project. This policy
shall be included in the site specific Health and Safety Plan and communicated to all
Subcontractors and their personnel. Communication of this policy shall be
documented in a written tailboard talk, meeting minutes, or other communication.
All personnel must sign to indicate that they have read and understood the policy.
In those cases where evidence of discarded cigarette butts and other smoking
paraphernalia is found, the Engineer or City will issue findings against the Contractor
or Contractors working in that area. If Contractors do not clean up their areas daily,
01415-6 11/2017
1594
DETAILED SPECIFICATION 01415 – MISCELLANEOUS PROJECT
REQUIREMENTS
CONTRACT DEL-260 G, H, E
or there is a dispute about ownership, the Engineer will have the area immediately
cleaned and all Contractors will be charged accordingly.
END OF SECTION
01415-7 11/2017
1595
DETAILED SPECIFICATION 01415 – MISCELLANEOUS PROJECT
REQUIREMENTS
CONTRACT DEL-260 G, H, E
01415-8 11/2017
1596
DETAILED SPECIFICATION 01420 -- REFERENCE STANDARDS
CONTRACT DEL-260 G, H, E
SECTION 01420
Reference Standards
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any work of this Section and
the Contractor shall include all costs thereof in its lump sum price bid for the
Contract.
1.05 DESCRIPTION
A. Use of Reference Standards:
1. Products or workmanship specified by the referenced standards shall
comply with the requirements of those standards, except where
requirements that are more rigid are specified or required by applicable
codes.
2. Referenced standards shall be current as of the time of bidding the
Contract Documents, unless otherwise specified.
3. The Contractor shall obtain copies of the referenced standards when
required by the Contract Documents.
B. Schedule of References
1. Whenever reference is made to the furnishing of materials or testing
thereof to conform to the standards of any technical society,
organization or body, it shall be construed to mean the latest standard,
01420 - 1 11/2017
DEP 3/15/2016
1597
DETAILED SPECIFICATION 01420 -- REFERENCE STANDARDS
CONTRACT DEL-260 G, H, E
1.07 ATTACHMENTS
A. Table 1 – Standards Developing Organizations / Publications
END OF SECTION
01420 - 2 11/2017
DEP 3/15/2016
1598
ATTACHMENTS - DETAILED SPECIFICATION 01420
CONTRACT DEL-260 G, H, E
TABLE 1
Standards Developing Organizations / Publications
PAGE 1 OF 8 11/2017
DEP 3/15/2016
1599
ATTACHMENTS - DETAILED SPECIFICATION 01420
CONTRACT DEL-260 G, H, E
1500 King Street, Suite 201 One East Wacker Drive, Suite 3100
Alexandria, Virginia 22314-2730 Chicago, Illinois 60601-2001
Phone: 703-684-0211 Phone: 312-670-2400 or 800-644-2400
Fax: 703-684-0242 Fax: 312-670-2400
Internet: www.agma.org Internet: www.aiscweb.com
PAGE 2 OF 8 11/2017
DEP 3/15/2016
1600
ATTACHMENTS - DETAILED SPECIFICATION 01420
CONTRACT DEL-260 G, H, E
PAGE 3 OF 8 11/2017
DEP 3/15/2016
1601
ATTACHMENTS - DETAILED SPECIFICATION 01420
CONTRACT DEL-260 G, H, E
PAGE 4 OF 8 11/2017
DEP 3/15/2016
1602
ATTACHMENTS - DETAILED SPECIFICATION 01420
CONTRACT DEL-260 G, H, E
PAGE 5 OF 8 11/2017
DEP 3/15/2016
1603
ATTACHMENTS - DETAILED SPECIFICATION 01420
CONTRACT DEL-260 G, H, E
NEW YORK CITY BUILDING CODE NEW YORK CITY ELECTRICAL CODE
(NYCBC) (NYCEC)
NYC Department of Buildings NYC Department of Buildings
280 Broadway 280 Broadway
New York, NY 10007 New York, NY 10007
Phone: 212-566-5000 Phone: 212-566-5000
PAGE 6 OF 8 11/2017
DEP 3/15/2016
1604
ATTACHMENTS - DETAILED SPECIFICATION 01420
CONTRACT DEL-260 G, H, E
PAGE 7 OF 8 11/2017
DEP 3/15/2016
1605
ATTACHMENTS - DETAILED SPECIFICATION 01420
CONTRACT DEL-260 G, H, E
PAGE 8 OF 8 11/2017
1606 DEP 3/15/2016
DETAILED SPECIFICATION 01430
APPROVAL OF PRODUCT MANUFACTURERS – NAMED OR EQUAL
CONTRACTS DEL-260 G, H, E
SECTION 01430
Approval of Product Manufacturers – Named or Equal
PART 1 GENERAL
1.01 SUMMARY
A. This Section describes the requirements for the use of named Manufacturers of
materials and equipment and the requirements for the use of equivalent
materials and equipment.
1.02 PAYMENT
A. No separate payment will be made for performing any Work required under this
Section and the Contractor shall include all costs thereof in its lump sum price
bid for the Contract.
1.03 DEFINITIONS
A. “Manufacturer” shall mean a company that manufactures, fabricates,
assembles, and/or integrates materials, fixtures, equipment, appliances, or other
fittings. Manufacturer shall not mean a distributor, sales representative, and/or
supplier.
B. “Named Manufacturer” shall mean any Manufacturer cited by company name
in the Specification Sections.
1.04 DESCRIPTION
A. Approval of Manufacturers
1. All transactions with Manufacturers shall be through the Contractor.
2. Similar materials and equipment of one and the same kind, type or
classification that are used for identical purposes shall be made by the
same Manufacturer, except that multiple Manufacturers may be
approved for commodity items including, but not limited to, such items
as concrete, conduit and cable, at the discretion of the Engineer.
3. Approval of a proposed Manufacturer is conditional upon compliance
with the Specifications and Drawings as determined by the Engineer
during the subsequent review of the Contractor’s submitted Shop
Drawings.
4. Unless otherwise approved by the Engineer, the Contractor shall be
granted approval for one Manufacturer per item.
5. For items of significant import or requiring specialized manufacturing,
the Engineer may deny approval based on a determination that the
proposed Manufacturer:
01430-1 11/2017
DEP 12/16/2016
1607
DETAILED SPECIFICATION 01430
APPROVAL OF PRODUCT MANUFACTURERS – NAMED OR EQUAL
CONTRACTS DEL-260 G, H, E
01430-2 11/2017
DEP 12/16/2016
1608
DETAILED SPECIFICATION 01430
APPROVAL OF PRODUCT MANUFACTURERS – NAMED OR EQUAL
CONTRACTS DEL-260 G, H, E
01430-4 11/2017
DEP 12/16/2016
1610
DETAILED SPECIFICATION 01430
APPROVAL OF PRODUCT MANUFACTURERS – NAMED OR EQUAL
CONTRACTS DEL-260 G, H, E
END OF SECTION
01430-5 11/2017
DEP 12/16/2016
1611
DETAILED SPECIFICATION 01430
APPROVAL OF PRODUCT MANUFACTURERS – NAMED OR EQUAL
CONTRACTS DEL-260 G, H, E
01430-6 11/2017
DEP 12/16/2016
1612
DETAILED SPECIFICATION 01432 – CONTRACTOR’S WORK QUALITY
CONTRACT DEL-260 G, H, E
SECTION 01432
Contractor’s Work Quality
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any work of this Section
and all costs thereof shall be included in the lump sum price bid for the
Contract, unless otherwise specified in the Detailed Specifications.
1.03 DESCRIPTION
A. Experience and Qualifications of Supply and Service Companies: The
Contractor shall not enter into any subcontracts or agreements for the
furnishing of supplies or services without DEP approval as required under the
Standard Construction Contract.
B. Quality of Materials, Equipment and Work
1. All materials, fixtures, fittings, supplies, and equipment furnished
under this Contract shall be new, of standard first grade quality, of the
best workmanship, correctly designed, and be intended for the use for
which they are offered. Materials or equipment which, in the opinion
of the Engineer, are inferior or of a lower grade than indicated,
specified or required, or are obsolete, will not be accepted.
2. All Work of assembly, installation, and construction shall be done in a
neat, first class, and workmanlike manner. If the quality of the
material, fixtures, fittings, supplies, equipment or work required by the
Drawings does not agree with that required by the Specifications, the
01432-1 11/2017
DEP 9/24/2015
1613
DETAILED SPECIFICATION 01432 – CONTRACTOR’S WORK QUALITY
CONTRACT DEL-260 G, H, E
01432-2 11/2017
DEP 9/24/2015
1614
DETAILED SPECIFICATION 01432 – CONTRACTOR’S WORK QUALITY
CONTRACT DEL-260 G, H, E
Engineer and approved for payment. The Contractor shall repair such
defect, without compensation, in a manner satisfactory to the Engineer.
2. Unsuitable materials and equipment may be rejected, notwithstanding
that such defective Work, materials and equipment may have been
previously overlooked by the Engineer and accepted or approved for
payment.
3. If any workmanship, materials or equipment shall be rejected by the
Engineer as unsuitable or not in conformity with the Specifications or
Drawings, the Contractor shall promptly replace such materials and
equipment with acceptable materials and equipment at no additional
cost to the City. Equipment or materials rejected by the Engineer shall
be tagged as such and shall be immediately removed from the site.
4. The Engineer may order tests of imperfect or damaged Work
equipment, or materials to determine the required functional capability
for possible acceptance, if there is no other reason for rejection. The
cost of such tests shall be borne by the Contractor, and the nature,
tester, extent and supervision of the tests will be as determined by the
Engineer. If the results of the tests indicate that the required functional
capability of the Work, equipment, or material was not impaired, the
Work, equipment or materials may be deemed acceptable, in the
discretion of the Engineer. If the results of such tests reveal that the
required functional capability of the questionable Work, equipment or
materials has been impaired, then such Work, equipment or materials
shall be deemed imperfect and shall be replaced. The Contractor may
elect to replace the imperfect Work, equipment or material in lieu of
performing the tests.
5. If, in the making of any test, it is ascertained by the Commissioner that
the material or equipment does not comply with the Contract, the
Contractor will be notified thereof, and it will be directed to refrain
from delivering said material or equipment, or to promptly remove it
from the site or from the Work and replace it with acceptable material
without cost to the City. Upon rejection of any material or equipment
submitted as the equivalent of that specifically named in the Contract,
the Contractor shall immediately proceed to furnish the named
material or equipment.
D. Welding Certification and Welding Inspection
1. For work performed within NYC limits, all field welding required
under this Contract shall be performed by New York City certified
welders in accordance with the latest rules of the New York Board of
Standards and Appeals (BS & A) and the current provisions of the
New York Building Code. Additional certification requirements are as
follows:
01432-3 11/2017
DEP 9/24/2015
1615
DETAILED SPECIFICATION 01432 – CONTRACTOR’S WORK QUALITY
CONTRACT DEL-260 G, H, E
d. On full penetration welds, both the root pass and the final
weldment shall be inspected by means of MT or PT as
applicable;
e. Unless otherwise approved, inspection of welds shall be
conducted by an inspection agency approved by DEP;
f. Unless waived by the City, all full penetration welds shall be
inspected by Radiographic Examination (RT) in accordance
with ASME Code, Section VIII, Division I, Paragraph UW-51;
g. The Division of Design Services of the DEP Bureau of
Engineering Design and Construction may elect to witness any
or all of the welding inspection. Notice shall be given to the
Bureau not less than five (5) business days prior to any welding
and inspection of those items specifically designated by the
Engineer. All costs associated with the welding inspection by
the DEP inspectors and any additional testing required by DEP
shall be borne by the City.
E. Inspection and Testing of Concrete
1. Inspection and testing of concrete shall be in accordance with the
relevant work-specific requirements in the Contract.
F. Leakage Tests
1. All new pipelines and appurtenant structures and all new liquid
containing structures shall be field tested for leakage after installation
in accordance with the relevant work-specific requirements in the
Contract.
G. Contractor's Surveyor
1. The General Contractor shall retain the services of a licensed land
surveyor, registered in the State of New York, to perform survey work
including but not limited to establishing line and grade, in advance of
the construction; and to perform other surveying services for the work
included under the Contract. . The surveyor shall be subject to the
approval of the Commissioner. Survey drawings shall be submitted to
the Engineer for approval.
2. The Contractor shall erect, install and maintain survey platforms,
targets, benchmarks and similar facilities to be used by the Engineer in
the performance of its inspection services; shall perform all survey
work required before, during and after construction; and shall comply
with the requirements specified under Article 9 - Surveys, of the
General Conditions.
H. Field Measurements
01432-5 11/2017
DEP 9/24/2015
1617
DETAILED SPECIFICATION 01432 – CONTRACTOR’S WORK QUALITY
CONTRACT DEL-260 G, H, E
1.05 SUBMITTALS
A. Within 15 days after the commence work date given in the Notice to Proceed
(NTP), the Contractor shall provide its QA/QC plan to the Engineer for
approval. At a minimum, the plan should consist of the following quality
elements:
1. Responsibilities
2. Management and Production Instructions
3. Material Control
4. Marking and Material Identification
5. Set-Up and Operational Procedures
6. Non-Conformances
7. Painting
B. Additionally, when required by the Engineer, the Contractor shall submit the
following information prior to his entering into a supply or service
subcontracts:
1. Contract number, supplies or services to be provided and a general
description of the proposed item(s), such as trade name, type, etc.
2. The name and address of the manufacturer or service company and the
location of the plant at which supplies will be manufactured and tested
as required, or at which the services will be performed.
3. Experimental and test data required to support the claimed
performance of the supplies.
01432-6 11/2017
DEP 9/24/2015
1618
DETAILED SPECIFICATION 01432 – CONTRACTOR’S WORK QUALITY
CONTRACT DEL-260 G, H, E
END OF SECTION
01432-7 11/2017
DEP 9/24/2015
1619
DETAILED SPECIFICATION 01432 – CONTRACTOR’S WORK QUALITY
CONTRACT DEL-260 G, H, E
01432-8 11/2017
DEP 9/24/2015
1620
DETAILED SPECIFICATION 01433 – WITNESS SHOP TESTING AND QUALITY
ASSURANCE INSPECTION
CONTRACT DEL-260 G, H, E
SECTION 01433
Witness Shop Testing and Quality Assurance Inspection
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any work of this Section and
all costs thereof shall be included in the lump sum price bid for the Contract.
1.04 DESCRIPTION
A. Witness Shop Tests
1. See Table 1 - List of Equipment Scheduled for Witness Shop Testing,
attached at the end of this Section.
2. Witness Shop Testing Procedures: Witness shop testing of equipment
shall be performed in accordance with the procedures described in
Article 12 of the General Conditions and in the Specifications for the
equipment listed in Table 1.
3. Advance Notice for Witness Shop Testing: The Contractor shall notify
the Engineer at least forty-five (45) calendar days in advance of all
scheduled witness shop tests, whether conducted within or outside the
continental United States.
4. City’s Right to Witness Shop Testing of Additional Items: In
accordance with General Conditions Article 12, the City reserves the
right to require witness shop tests for items that have not been
designated as such in the Contract Documents.
5. Contractor’s Presence during Witness Shop Testing: The Contractor
shall be present by a duly authorized representative at the manufacturing
and testing facilities during times of witness shop testing.
B. Quality Assurance (QA) Inspection
1. City’s Right to QA Inspection of Contract Items
01433- 1 11/2017
DEP 3/15/2016
1621
DETAILED SPECIFICATION 01433 – WITNESS SHOP TESTING AND QUALITY
ASSURANCE INSPECTION
CONTRACT DEL-260 G, H, E
01433- 3 11/2017
DEP 3/15/2016
1623
DETAILED SPECIFICATION 01433 – WITNESS SHOP TESTING AND QUALITY
ASSURANCE INSPECTION
CONTRACT DEL-260 G, H, E
01433- 4 11/2017
DEP 3/15/2016
1624
DETAILED SPECIFICATION 01433 – WITNESS SHOP TESTING AND QUALITY
ASSURANCE INSPECTION
CONTRACT DEL-260 G, H, E
f. Testing Compliance
i. Contractor’s testing personnel shall make the necessary
inspections and tests. The reports thereof shall be in such
form as will facilitate checking to determine compliance
with the Specifications and shall indicate all the analyses
and/or test data and interpreted results thereof.
g. Contractor to Provide Engineer with Advance Notice of
Sampling and Testing
i. The Engineer shall be informed in advance of all times of
sampling and testing, and shall witness these operations if
the Engineer so desires.
h. Testing Performed in Engineer’s Presence
i. When requested or specified, testing and examinations of
all kinds and any weighing required under Contract shall
be done in the presence of the Engineer during the normal
eight hour shift, unless otherwise approved, and adequate
advance notice of intent to schedule tests shall be given to
the Engineer.
i. Submittal of Samples of Materials for Testing
i. When required or requested by the Engineer, specified
samples of materials, equipment, and appliances,
identified in a manner acceptable to the Engineer shall be
submitted by the Contractor for approval by the Engineer.
The samples shall be submitted sufficiently in advance of
the time when the materials are to be used so that
rejections thereof will not delay the approved
construction schedules. Approved samples will be labeled
and dated.
ii. As directed and specified below, the Contractor shall be
required to furnish and deliver to the DEP Bureau of
Engineering Design and Construction Quality Assurance
Chemical Laboratory located at 96-05 Horace Harding
Expressway, Corona, New York 11368-5107, or any
other designated location, samples of metals from
vendors plants engaged in the manufacture of mechanical
equipment and structural components.
iii. A minimum of two (2) unmachined material samples of
sufficient size shall be supplied from each material heat
lot for the components identified as requiring samples for
independent verification of both chemical and physical
test results. Material samples shall be provided in
accordance with the applicable material specifications
01433- 5 11/2017
DEP 3/15/2016
1625
DETAILED SPECIFICATION 01433 – WITNESS SHOP TESTING AND QUALITY
ASSURANCE INSPECTION
CONTRACT DEL-260 G, H, E
01433- 6 11/2017
DEP 3/15/2016
1626
DETAILED SPECIFICATION 01433 – WITNESS SHOP TESTING AND QUALITY
ASSURANCE INSPECTION
CONTRACT DEL-260 G, H, E
01433- 7 11/2017
DEP 3/15/2016
1627
DETAILED SPECIFICATION 01433 – WITNESS SHOP TESTING AND QUALITY
ASSURANCE INSPECTION
CONTRACT DEL-260 G, H, E
1.05 ATTACHMENTS
A. Table 1 – List of Equipment Scheduled for Witness Shop Testing
END OF SECTION
01433- 8 11/2017
DEP 3/15/2016
1628
ATTACHMENTS - DETAILED SPECIFICATION 01433
CONTRACT DEL-260 G, H, E
TABLE 1
DEL-260E ELECTRICAL
LIST OF EQUIPMENT SCHEDULED FOR WITNESS SHOP TESTING
PAGE 1 OF 2 11/2017
DEP 3/15/2016
1629
ATTACHMENTS - DETAILED SPECIFICATION 01433
CONTRACT DEL-260 G, H, E
PAGE 2 OF 2 11/2017
DEP 3/15/2016
1630
DETAILED SPECIFICATION 01511 - TEMPORARY WATER AND SANITARY
SERVICES
CONTRACT DEL-260 G, H, E
SECTION 01511
Temporary Water and Sanitary Services
PART 1 GENERAL
1.02 PAYMENT
A. All costs associated with the work of this Section shall be included in the
Contract Allowance item E-A-3, as described in Detailed Specification 01270
– Measurement and Payment.
1.03 DESCRIPTION
A. The Electrical Contractor (the “Contractor”) shall provide and maintain
temporary water and sanitary services for the use of Engineer’s and
Contractor’s personnel on the site. In addition, the Contractor shall provide all
water required to perform the Work of this Contract.
B. The Contractor shall provide and maintain all temporary water and sanitary
services at the site during construction in compliance with all applicable State,
City and local regulations.
C. The temporary sanitary services electrical power should be fed from the
Resident Engineer’s trailer power panel.
D. The Contractor shall remove temporary services at the completion of the Work.
01511-1 11/2017
DEP 10/5/2016
1631
DETAILED SPECIFICATION 01511
TEMPORARY WATER AND SANITARY SERVICES
CONTRACT DEL-260 G, H, E
END OF SECTION
01511-2 11/2017
DEP 10/5/2016
1632
DETAILED SPECIFICATION 01513 – TEMPORARY ELECTRICAL SYSTEM
CONTRACT DEL-260 G, H, E
SECTION 01513
Temporary Electrical System
PART 1 GENERAL
1.02 PAYMENT
A. Payment for electrical energy charges for the temporary power for the
Engineer’s field office trailer and restroom trailer shall be made under
Allowance E-A-3 of the Electrical Contract, as specified in Section 01270 –
Measurement and Payment.
B. Except for the Allowance specified herein, all costs for the work under this
Section shall be included in the Lump Sum price bid for the Contract E-LS-1
of the Electrical Contract, as specified in Section 01270 – Measurement and
Payment, except as otherwise specified. However, any Contractor requiring the
use of the temporary electrical facilities before 7:00 A.M. or after 3:30 P.M.,
from Monday through Friday or at any time on Saturdays, Sundays or holidays
shall bear the cost of energizing and/or de-energizing the system, and if more
than one Contractor uses the system during such periods, prorate the costs
accordingly.
C. The service shall have provisions for meter connections for each Contractor on
the worksite and the Engineer’s field office. The service shall be branched and
metered using circuit breakers or fused switches and meters.
1. The distribution from each meter to the Contractor’s field office and
shops at the site shall be the responsibility of each Contractor.
2. The distribution from one (1) meter to Engineer’s field office shall be
the responsibility of the Electrical Contractor.
3. The distribution from one (1) meter to the construction temporary light,
power, and security system shall be the responsibility of the Electrical
Contractor.
D. Each Contractor shall be responsible for making arrangements with the Utility
to have a sealed meter installed and for payment of same.
E. The energy charges for each Contractor’s field office and shop usage shall be
the responsibility of each Contractor.
F. Energy charges associated with the work areas power and lighting and the
security site lighting shall be the responsibility of the Electrical Contractor.
Energy charges associated with the Engineer’s field office and restroom trailer
shall be the responsibility of the Electrical Contractor.
G. Each Contractor requiring additional temporary power and light, beyond that
provided under by the Electrical Contractor as specified herein, shall arrange
with the utility for such additional temporary power and light and shall bear the
costs of all material and ancillary equipment necessary. Removal of such
additional temporary power and light shall be at the expense of each Contractor.
01513-3 11/2017
DEP 5/4/2016
1635
DETAILED SPECIFICATION 01513 – TEMPORARY ELECTRICAL SYSTEM
CONTRACT DEL-260 G, H, E
1.07 SUBMITTALS
A. Electrical Contractor shall submit shop drawings, shop drawings and material
specifications for the approval of the Engineer and the utility in accordance with
the requirements of Section 01330 – Submittal Procedures.
B. Shop Drawings:
1. One line diagram representing the power distribution for the temporary
system.
2. Location plan indicating the major distribution equipment.
3. Manufacturer’s catalog cuts for the products proposed for use.
4. Panel loading, voltage drop, short circuit and other calculations, as
required.
5. Security lighting layout.
01513-4 11/2017
DEP 5/4/2016
1636
DETAILED SPECIFICATION 01513 – TEMPORARY ELECTRICAL SYSTEM
CONTRACT DEL-260 G, H, E
PART 2 PRODUCTS
E. Poles shall have a class suitable for the installation in accordance with the
National Electrical Safety Code and the utility and shall be thirty feet length
minimum. Poles shall be guyed at angle or corner runs and when eccentrically
loaded.
2.04 GROUNDING
A. The temporary systems shall be grounded in accordance with the requirements
of General Specification 16061 - Grounding.
PART 3 EXECUTION
3.01 INSTALLATION
A. Temporary wiring systems shall be installed without interfering with the work
of other contractors.
B. The ground grid cable shall be installed in loop fashion completely around and
outside the service point fence. The fence and distribution equipment shall be
connected to the grid at a minimum of two locations.
C. The temporary lighting system shall be installed progressively in structures as
the designated areas are enclosed or as lighting becomes necessary because of
partial enclosure. Lamps shall be installed to provide an even distribution of
illumination over the work areas.
D. Receptacles shall be installed in such a manner so as to reach any point in the
work areas with an extension cord not to exceed 40 feet in length.
E. Security lighting shall be installed on poles to illuminate the staging and parking
areas.
F. Aerial conductors shall be installed at a minimum height of 14 feet above
finished grade. When conductors cannot be routed at the proper height or where
it will interfere with plant operations or construction activities, conductors shall
be provided in rigid steel conduit and installed underground.
01513-6 11/2017
DEP 5/4/2016
1638
DETAILED SPECIFICATION 01513 – TEMPORARY ELECTRICAL SYSTEM
CONTRACT DEL-260 G, H, E
3.02 OPERATION
A. The Electrical Contractor shall keep the temporary power and lighting system
operational each working day from 7:00 A.M. to 3:30 P.M., from Monday to
Friday inclusive for the duration of the Contract. This requirement includes
provision of one electrician available on-call at all times for incidental
modifications of the temporary electrical system as directed by the Engineer or
to maintain the electrical equipment and power distribution systems at the Site.
Areas of the Work designated by the Engineer as requiring the use of the
temporary electrical system to function outside of the above hours shall be
energized continuously or as directed by the Engineer. These areas include
security lighting and the Engineer’s trailer complex.
3.03 MAINTENANCE
A. The temporary electrical system shall be maintained and repaired until it is no
longer required.
B. Lamps, fuses and other equipment shall be repaired and/or replaced, as
required.
3.04 REMOVAL
A. At the conclusion of the work, when directed by the Engineer, the temporary
system shall be removed by the Electrical Contractor in its entirety. The ground
surfaces and structures disturbed by the work shall be restored to their original
condition.
END OF SECTION
01513-7 11/2017
DEP 5/4/2016
1639
DETAILED SPECIFICATION 01513 – TEMPORARY ELECTRICAL SYSTEM
CONTRACT DEL-260 G, H, E
01513-8 11/2017
DEP 5/4/2016
1640
DETAILED SPECIFICATION 01520 - TEMPORARY CONSTRUCTION
FACILITIES
CONTRACT DEL-260 G, H, E
SECTION 01520
Temporary Construction Facilities
PART 1 GENERAL
1.04 SUBMITTALS
A. Floor plan, square footage, location, and amenities of Engineer’s field trailer.
B. Data sheets for all electronic devices, movable equipment to be provided under
this section.
01520-1 11/2017
1641
DETAILED SPECIFICATION 01520 - TEMPORARY CONSTRUCTION
FACILITIES
CONTRACT DEL-260 G, H, E
1. The Electrical Contractor shall obtain and pay for any necessary permits
for the office.
2. Services for the office shall be as hereinafter specified.
B. The office shall be at minimum 800 square feet of open space.
C. Materials
1. Exterior metal fully insulated walls and roof with a minimum of R-25
insulation.
2. Interior walls insulated with R-11 insulation for sound attenuation.
3. Ceiling height shall be 8’.
4. Completely weatherproofed and insulated.
5. Floor systems designed for 40 psf in addition to dead load.
6. Roof system designed for 35 psf in addition to dead load.
7. Exterior doors fully insulated (whole-unit U-factor less than 0.32,
greater than R-3.0) metal type with, aluminum thresholds, heavy duty
closers and vandal-proof locksets with keys meeting building code
requirements.
8. Low VOC Paints and sealants and floor coverings
9. Exterior walls and roof finished with a high SRI material, minimum
reflectivity of 0.65.
10. Interior doors solid wood with lock sets.
11. High-Performance Windows with a whole-unit U-factor less than 0.32
(greater than R-3.0)
12. Windows provided with adjustable blinds, operable sashes, screens,
storm sashes and all hardware such as that required for security.
13. Underside of trailers completely sealed and insulated with minimum of
R-19 insulation.
14. Resilient floor coverings with a minimum 20% recycled material
content.
15. Passive solar window awnings on South-facing and West-facing
windows.
D. HVAC
1. Ducted system with ducts concealed above the finish ceiling.
2. Sized to maintain the temperature in each room at 70 degrees Fahrenheit
(F) when the outside temperature is 0 degrees F and 75 degrees F when
the outside temperature is 100 degrees F.
3. Wall mounted heat/cool programmable thermostat.
01520-2 11/2017
1642
DETAILED SPECIFICATION 01520 - TEMPORARY CONSTRUCTION
FACILITIES
CONTRACT DEL-260 G, H, E
01520-3 11/2017
1643
DETAILED SPECIFICATION 01520 - TEMPORARY CONSTRUCTION
FACILITIES
CONTRACT DEL-260 G, H, E
01520-4 11/2017
1644
DETAILED SPECIFICATION 01520 - TEMPORARY CONSTRUCTION
FACILITIES
CONTRACT DEL-260 G, H, E
metal filing cabinets with lock, four drawer legal size, Style No. 314CP
or No. 1904 respectively.
2. Five (5) waste paper baskets 15-1/4 inches x 11-1/4 inches x 20 inches
as manufactured by Rubbermaid, Model No. K6-2957-BK, or by
Lustrow, Division of Borden, Columbus, OH, Model No. B-W44, or
approved equal.
3. One (1) drafting table, 37-1/2 inches x 60 inches as manufactured by
Plan Hold, 17621 Von Karman Ave., Irvine, CA, Model No. 350T-60,
or by Anco Wood Specialties, Inc., 71-02 80th Street, New York, NY,
No. 602F, or approved equal.
4. Two (2) dry chemical fire extinguishers, UL listed 1A-10BC as
manufactured by Walter Kidde & Co., Inc., Belleville, NJ, Model No.
2-5/8 TPS-2, or by J.L. Industries, 4450 West 78th Street, Bloomington,
MN, Model No. Cosmic 2-1/2E, or approved equal.
5. Electric water cooler with water filter. Filter must be changed per
manufacturer’s recommendations.
6. One (1) all in one color LED Laser printer as manufactured by Xerox
Corp., Model No.6027/NI, or equal. The Electrical Contractor shall
maintain the machine for the duration of the Contract, providing all
ancillary supplies including Xerox quality paper.
7. One minimum 1,000W with turntable microwave oven from Sears or
equal
8. Specifications for Personal Laptop and Associated Software. Under this
Section, the Electrical Contractor shall supply one (1) complete laptop
system, with consumable supplies and software as specified below. The
computer systems shall be delivered to Field Office as determined by
the Bureau of Engineering Design & Construction (BEDC). At the
conclusion of the Contract, the computer system shall remain the
property of the Electrical Contractor. The Computer System shall be as
follows:
a. Intel Core i7-6600U Dual Core 2.6 GHz Processor, or
equivalent as approved by the Engineer with the following
features:
i. 16 GB (2x8GB) DDR4 2133 MHz RAM.
ii. 512 GB M.2 SATA Solid State Drive.
iii. LCD 23 inch color monitor
iv. Integrated Intel HD Graphics 53.
v. 14.0”—4-Cell Battery with 65 Watt Adapter
vi. Dell DW316 UltraSlim USB DVD/RW
vii. Dell E/Port Plus Advanced Replicator
01520-6 11/2017
1646
DETAILED SPECIFICATION 01520 - TEMPORARY CONSTRUCTION
FACILITIES
CONTRACT DEL-260 G, H, E
01520-7 11/2017
1647
DETAILED SPECIFICATION 01520 - TEMPORARY CONSTRUCTION
FACILITIES
CONTRACT DEL-260 G, H, E
for a period of thirty (30) days after the Contract is completed as evidenced by
the issuance of the Final Certificate.
D. The Contractor’s field offices shall present a clean and neat exterior appearance
and shall be in a state of good repair. Temporary construction facilities, which,
in the opinion of the Engineer, require exterior painting or maintenance, shall
be repaired or replaced at the Engineer’s direction.
END OF SECTION
01520-9 11/2017
1649
DETAILED SPECIFICATION 01520 - TEMPORARY CONSTRUCTION
FACILITIES
CONTRACT DEL-260 G, H, E
01520-10 11/2017
1650
DETAILED SPECIFICATION 01550 – VEHICULAR ACCESS AND PARKING
CONTRACT DEL-260 G, H, E
SECTION 01550
Vehicular Access and Parking
PART 1 GENERAL
01550-1 11/2017
1651
DETAILED SPECIFICATION 01550 – VEHICULAR ACCESS AND PARKING
CONTRACT DEL-260 G, H, E
requirement that the Contractor implement and enforce this policy, and that
Contractor take any necessary or appropriate actions to ensure compliance with
such parking policy by it and its Subcontractors’ employees. The Contractor
agrees to make appropriate efforts to encourage the use of public transportation
and the practice of car pooling by all such employees.
B. The Contractor shall issue parking badges or stickers to such employees for their
personal vehicles, in such form and with such associated documentation as the
Resident Engineer may approve, require or modify.
C. The parking badges or stickers shall be displayed in a prominent location upon
each employee’s vehicle, as may be approved, required or modified by the
Engineer.
D. The Contractor Employees Parking Area(s) shall be of a size and situated in
location(s) acceptable to the Engineer.
E. The Contractor shall be responsible for the safe and efficient movement of
employees between the Contractor Employees Parking Area and the Contractor’s
work area.
END OF SECTION
01550-2 11/2017
1652
DETAILED SPECIFICATION 01560 - TEMPORARY BARRIERS
AND ENCLOSURES
CONTRACT DEL-260 G, H, E
SECTION 01560
Temporary Barriers and Enclosures
PART 1 GENERAL
A. Payment
B. Barricades
B. Fencing
C. Pollution control
1.02 PAYMENT
A. No separate payment will be made for performing any Work of this Section. The
Contractor shall include all costs for this Work in its lump sum price bid for the
Contract.
1.03 BARRICADES
1. The Contractor shall provide, erect and maintain as necessary for his work, strong
and suitable barricades, danger signs and warning lights along all roads, parking
areas and sidewalks, accessible to the public or City personnel.
B. Excavations:
01560-1 11/2017
1653
DETAILED SPECIFICATION 01560 - TEMPORARY BARRIERS
AND ENCLOSURES
CONTRACT DEL-260 G, H, E
2. The Contractor shall, at his own expense, provide suitable and safe bridges and
other crossings for accommodating travel by pedestrians and workmen. Bridges
provided for access during construction shall be removed when no longer
required.
4. The Contractor shall take precautions to prevent injury to the public or City
personnel due to open trenches. All trenches, excavated material, equipment, or
other obstacles which could be dangerous to the public or City personnel shall be
well lighted from sunset to sunrise.
C. The Contractor's responsibility for the maintenance of barricades, signs and lights shall
continue until the City accepts the Work. The Contractor shall provide and maintain
other warning signs and barricades in other areas and around their respective work as
may be required for the safety of all those employed in the work, plant operating
personnel, or those visiting the Site.
1.04 FENCING
1. The Contractor shall provide and erect, when required or shown on the Contract
Drawings or directed by the Engineer, temporary project safety fencing at the
work site.
2. The safety fencing shall be a high visibility, orange colored, high density
polyethylene grid or approved equal, a minimum of 4 feet high, supported and
tightly secured to steel posts located on maximum 6-feet centers.
B. Fencing shall be maintained by the Contractor during the life of the Contract and, upon
completion and acceptance of the Work, shall become the property of the Contractor
and shall be removed from the work site.
01560-2 11/2017
1654
DETAILED SPECIFICATION 01560 - TEMPORARY BARRIERS
AND ENCLOSURES
CONTRACT DEL-260 G, H, E
A. The Contractor shall provide the methods, means and facilities required to prevent
contamination of soil, water or atmosphere by the discharge of noxious substances
from construction operations.
C. Special measures shall be taken by the Contractor to prevent harmful substances from
entering public waters, and to prevent disposal of wastes, effluents, chemicals, or other
such substances to adjacent waterways or to sanitary or storm sewers.
D. The Contractor shall provide systems for control of atmospheric pollutants to prevent
toxic concentrations of chemicals and to prevent harmful dispersal of pollutants into
the atmosphere. See Detailed Specification 01140 – Work Restrictions for additional
emissions and fuel requirements.
E. All chemicals used during project construction or furnished for project operation,
whether herbicide, pesticide, disinfectant, polymer, or reactant of other classification,
must show approval of the EPA and other recognized certifying agencies. Use of all
such chemicals and disposal of residues shall be in strict conformance with regulatory
requirements.
F. All Contractor equipment used during construction shall conform to all current federal,
state and local laws and regulations.
G. In the event that any type of fuel, lubricant, or any other material is spilled on board a
piece of on water equipment, or spilled in the reservoir, all Work must immediately
cease and the Engineer must be notified. All Work will remain ceased until the spill is
cleaned to the satisfaction of the Resident Engineer and City. The Contractor is
responsible for disposing of all contaminated materials at no additional cost. The
Contractor must provide documentation to the Resident Engineer proving that the
contaminated materials were disposed of in a proper manner.
A. During the progress of the Work and up to the date of final payment, the Contractor
shall be solely responsible for the care and protection of all Work, personnel,
equipment and materials covered by the Contract.
01560-3 11/2017
1655
DETAILED SPECIFICATION 01560 - TEMPORARY BARRIERS
AND ENCLOSURES
CONTRACT DEL-260 G, H, E
B. In order to prevent damage, injury or loss, actions taken by the Contractor shall include,
but not be limited to, the following:
2. Provide suitable storage facilities for all materials that are subject to injury by
exposure to weather, theft or breakage. Remove on water equipment from the
reservoir in the event of a major storm.
3. Place upon the Work or any part thereof only such loads as are consistent with the
safety of that portion of the Work.
4. Clean up frequently all refuse, rubbish, scrap materials, and debris caused by his
operations, to the end that at all times the site of the Work shall present a safe,
orderly and workmanlike appearance.
C. The Contractor shall protect the existing work and material from damage by his
workmen and shall be responsible for repairing any such damage at no additional cost
to the City.
END OF SECTION
01560-4 11/2017
1656
DETAILED SPECIFICATION 01570 – TEMPORARY CONTROLS
CONTRACT DEL-260 G, H, E
SECTION 01570
Temporary Controls
PART 1 GENERAL
A. Related Specifications
B. Related Documents
C. Payment
D. General Requirements
E. Submittals
G. Stockpiling of materials
I. Noise Control
J. Particulates
K. Notification of Non-Compliance
01570-1 11/2017
1657
DETAILED SPECIFICATION 01570 – TEMPORARY CONTROLS
CONTRACT DEL-260 G, H, E
1.04 PAYMENT
A. No separate payment will be made for performing any Work of this Section. The G
Contractor shall include all costs for this Work in its lump sum price bid G-LS-1
unless otherwise noted.
A. The Contractor shall furnish all labor, materials, equipment and incidentals required
to assure adequate environmental protection including implementation of all erosion
and sediment control measures shown in the Contract Drawings, the Stormwater
Pollution Prevention Plan, as directed by the Engineer, and specified herein.
B. In the performance of the Contract, the Contractor shall comply with all applicable
Federal, State and Local laws and regulations and all permits related to the Work
concerning environmental protection, restoration and erosion and sediment control.
1.06 SUBMITTALS
1. Dumping or wasting of spoil material, silt-laden water, trees, bush and other
debris into the reservoir or any stream corridor, any surface waters or at
unspecified locations adjacent to the work area or at locations not approved by
the Engineer.
01570-2 11/2017
1658
DETAILED SPECIFICATION 01570 – TEMPORARY CONTROLS
CONTRACT DEL-260 G, H, E
PART 2 PRODUCTS
A. The cover fabric for temporary stockpiles of non-hazardous excavated soil shall be a
composite material of woven polyethylene fabric and 1.5 mils of polyethylene film
laminated on both sides to form a monolithic sheet. The fabric shall be inert to
biological degradation and naturally encountered chemicals, alkalies, and acids. Its
permeability coefficient shall be less than 10-3 cm/sec. The terminal edges of the
fabric panels shall be secured to prevent uplift by wind.
B. These stockpiles shall be placed on a liner of 30 mil polyvinyl chloride (PVC) and
covered with a minimum 20 mil reinforced PVC liner at all times except during the
time the stockpile is being filled, emptied or sampled.
PART 3 EXECUTION
A. Staging and stockpile areas shall be as designated on the Contract Drawings. The
choice of alternate or additional stockpile areas shall be subject to the approval of the
Engineer.
B. The Contractor shall cover all temporary stockpiles of non-hazardous excavated soil
with an impermeable, woven polyethylene fabric, as specified in Article 2.01 of this
Detailed Specification.
A. The Contractor shall use necessary methods to prevent demolition waste from
contaminating stormwater runoff. Methods of preventing contamination shall
include construction of berms and dikes to direct stormwater runoff around the
work areas to the local drainage system.
01570-3 11/2017
1659
DETAILED SPECIFICATION 01570 – TEMPORARY CONTROLS
CONTRACT DEL-260 G, H, E
B. All catch basins and other stormwater inlets within or downhill of the project area
shall be surrounded by stone and block to filter the stormwater runoff.
C. The Contractor shall perform the Work under this Contract in compliance with
Appendices D and E from the New York State Department of Environmental
Conservation (NYSDEC), Division of Water, General Permit for Construction
Activities.
1. The Contractor shall comply with SPDES permit from the NYSDEC in
accordance with Detailed Specification 01410 - Regulatory Requirements.
The Contractor shall implement the procedures, technologies and methods
described in the Appendices to ensure compliance with the terms and
conditions of the permit.
A. All sound attenuation measures shall comply with local noise code regulations and
the following City noise code regulations. Compliance with the noise level
requirements specified herein above shall be understood as a material requirement of
this Contract.
2. Ambient Noise Quality: The Building Code of the City of New York, Title
24, Chapter 2, Subchapter 6, concerns ambient noise quality criteria and
standards which indicates the maximum outdoor sound levels in specific
ambient noise quality zones for day-time and night-time standards.
3. Where specific noise attenuation methods and/or systems are specified, these
shall be considered minimum requirements, and the Contractor shall provide all
additional noise attenuation methods and/or systems necessary to comply with
the specified levels, regulations and standards, all at no additional cost to the
City. No separate payment will be made for said items, as costs for these shall
be understood as included in the lump sum price bid for Bid Item No. 1, G-LS-
1.
5. Where operations by the Contractor are determined by the City to fail to comply
with the specified noise levels, regulations or standards, the Contractor shall
discontinue said operations immediately. Operations will be permitted to
resume only after the Contractor has submitted for the approval of the Engineer
a revised procedure for the performance of said operations in a manner that will
ensure compliance. All repairs shall be made at no increase to the Contract
price. In addition, the Contractor will have no claim for additional
compensation or Contract time if the Resident Engineer ceases operations due
to non-compliance with the specified noise levels.
6 The Contractor shall include in his Health and Safety Plan (HASP), to be
prepared as specified in Detailed Specification Section 01356 - Environmental
Health and Safety Requirements, the control measures he will employ to ensure
compliance with all specified noise requirements.
D. The Contractor shall submit Shop Drawings in accordance with the requirements of
Article 5 of the General Conditions and Detailed Specification 01330 - Submittal
Procedures. Shop Drawings shall include, but not be limited to:
1. Structural calculations verifying and certifying that all noise attenuation system
components comply with the requirements of the New York City Building
Code. The calculations shall be prepared, stamped and sealed by a Professional
Engineer registered in the State of New York.
2. Noise attenuation calculations demonstrating that the system satisfies the noise
attenuation requirements of the Contract.
E. Noise attenuation system materials may be made of concrete, wood or any suitable
materials, all as selected by the Contractor, which satisfy the Contract requirements.
01570-5 11/2017
1661
DETAILED SPECIFICATION 01570 – TEMPORARY CONTROLS
CONTRACT DEL-260 G, H, E
3.04 PARTICULATES
A. The Contractor shall perform the Work required in this Contract without causing
the concentrations of the particulate matters to exceed the following levels:
C. The Contractor shall implement measures to comply with all applicable OSHA
requirements. Additional and related requirements include:
D. The beds of dump trucks and trucks removing soil, rock, or material of any kind
from the work site or delivering raw materials to the work site shall be covered
with tarpaulins when loaded. The cover shall be secured to the truck so that no
contents of the bed may be seen when the bed is viewed from above. Bed of the
trucks shall be lined with a noise attenuation mat. Delivery vehicles are not
required to have noise attenuation mats.
E. Construction roads and, as needed, other areas within the limit of disturbance shall
be washed down with water as needed, but no less frequently than once daily, to
prevent the accumulation of and to suppress dust.
F. Soil and other potentially hazardous materials shall be removed from vehicles and
equipment leaving the work area, as specified in Detailed Specification 02371G -
Dust, Soil Erosion and Sedimentation Control.
01570-6 11/2017
1662
DETAILED SPECIFICATION 01570 – TEMPORARY CONTROLS
CONTRACT DEL-260 G, H, E
G. The Contractor shall take all additional measures needed to control objectionable
dust caused by his operations and the moving of his vehicles and equipment. The
use of chemicals for dust control, including calcium chloride, will not be
permitted.
H. The Contractor shall include in the Health and Safety Plan (HASP), to be prepared
by him as specified in Detailed Specification 01356 – Environmental Health and
Safety Requirements, the control measures he will employ to ensure compliance
with all specified particulate requirements.
A. The Engineer will notify the Contractor in writing of any non-compliance with the
provisions of this Section and the action to be taken. The Contractor shall, after
receipt of such notice, immediately take corrective action. Such notice, when
delivered to the Contractor or his authorized representative at the site of the work,
shall be deemed sufficient for the purpose.
2. No part of the time lost due to any such stop orders shall be made the subject of
a claim for extension of time or for excess costs or damages by the Contractor,
unless it is later determined that the Contractor was in compliance with the
provisions of this Section.
A. The Electrical Contractor shall furnish all labor, equipment, and materials necessary
to implement a Rodent and Insect Control Program for the following areas
specifically requested and authorized in writing by the Engineer:
1. Resident Engineers Trailer: On and around the Resident Engineer’s field office
complex and the Resident Engineer’s parking area.
B. All Work shall be performed by an exterminator licensed in the State of New York
and shall comply with all New York City, New York State Department of Health, and
local requirements for rodent and insect control. The exterminator shall only use
products approved by the USEPA for rodent and insect control.
01570-7 11/2017
1663
DETAILED SPECIFICATION 01570 – TEMPORARY CONTROLS
CONTRACT DEL-260 G, H, E
C. The Electrical Contractor shall perform one (1) full round of rodent and insect control
on and around the areas specified in Article 3.06.A above once every two months
from October through May and once every month from June through September, or
more frequently as directed by the Engineer..
A. The Contractor shall employ such measures as are needed to protect from damage
trees and plants located in or adjacent to any areas of work. Trees shall be protected
as specified in the New York City Department of Parks and Recreation “Horticulture
I” Recommendations and Specifications (June 1986 or most recent version) and in
accordance with Department of Parks and Recreation instructions.
END OF SECTION
01570-8 11/2017
1664
DETAILED SPECIFICATION 01583 – CONSTRUCTION SITE SIGNS
CONTRACT DEL-260 G, H, E
SECTION 01583
Construction Site Signs
PART 1 GENERAL
1.01 SUMMARY
A. This Section includes the requirements of the New York City Department of
Buildings (DOB) for uniform display of project and safety contact information
in the signage posted along construction fences and sidewalk sheds at
government-owned or government-funded project sites. Under Local Law
47/13, all miscellaneous construction signs – including City, Contractor and
311 contact information are consolidated in one simplified project information
panel. No other signage or permits, unless otherwise required by law, may be
posted.
1.02 PAYMENT
A. No separate payment will be made for performing any work required under this
Section and the Electrical Contractor shall include all costs thereof in its lump
sum price bid E-LS-1.
B. No extra payment will be made for any update of contact information, including
the changes of names and offices on the project information panel, necessitated
by administrative changes during the course of the Project.
1.03 REFERENCES
A. New York City Local Law 47/13
B. Rules of the City of New York 3301-01 (RCNY 3301-01)
1.04 DESCRIPTION
A. The Electrical Contractor shall procure and erect a project information panel at
the project site identifying the project. The panel shall be erected within
twenty-one (21) days from the date the Contractor is ordered to Commence
Work and shall be in accordance with the specifications and details included in
this Section.
1.05 SUBMITTALS
A. Submit the following for approval prior to fabrication of the project information
panel:
1. Detailed sketch showing all lettering, dimensions and colors
2. Detailed bill of materials indicating materials of construction for all
project sign components.
01583-1 11/2017
DEP 9/26/2016
1665
DETAILED SPECIFICATION 01583 – CONSTRUCTION SITE SIGNS
CONTRACT DEL-260 G, H, E
PART 2 PRODUCTS
01583-2 11/2017
DEP 9/26/2016
1666
DETAILED SPECIFICATION 01583 – CONSTRUCTION SITE SIGNS
CONTRACT DEL-260 G, H, E
2.02 MANUFACTURERS
A. The project information panel shall be manufactured by one of the following:
1. Mineola Signs, Mineola, New York; http://mineolasigns.com/
2. Or approved equal
PART 3 EXECUTION
3.01 INSTALLATION
A. Location: The project information panel shall be located in a prominent
position as determined by the Engineer.
B. Panel Supports: Adequate supports for the project information panel, including
the positioning and alignment of the sign, as determined by the Engineer, shall
be provided by the Contractor.
C. Maintenance: The project information panel shall be maintained by the
Contractor in good condition at all times for the duration of the Contract.
D. Removal of project information panel from Project Site: The Contractor shall
remove the project information panel and supports from the site when ordered
by the Engineer.
3.02 ATTACHMENTS
A. The following sketches are attached to this Section:
1. Figure 1 – Project Information Panel Layout (For Projects with Street
Frontage of 60 Feet or Greater)
2. Figure 2 – Project Information Panel Layout (For Projects with Street
Frontage of Less than 60 Feet)
END OF SECTION
01583-3 11/2017
DEP 9/26/2016
1667
DETAILED SPECIFICATION 01583 – CONSTRUCTION SITE SIGNS
CONTRACT DEL-260 G, H, E
01583-4 11/2017
DEP 9/26/2016
1668
ATTACHMENTS – DETAILED SPECIFICATION 01583
CONTRACT DEL-260 G, E, H
FIGURE 1
2’-4” 3’-8”
4’
PAGE 1 OF 2 11/2017
DEP 9/26/2016
1669
ATTACHMENTS – DETAILED SPECIFICATION 01583
CONTRACT DEL-260 G, H, E
PAGE 2 OF 2 11/2017
DEP 9/26/2016
1670
DETAILED SPECIFICATION 01651 - TRANSPORTATION AND HANDLING
OF MATERIALS AND EQUIPMENT
CONTRACT DEL-260 G, H, E
SECTION 01651
Transportation and Handling of Materials and Equipment
PART 1 GENERAL
A. Payment
B. General Requirements
C. Delivery of Products
D. Handling of Products
E. Inspection of Items
1.02 PAYMENT
A. No separate payment will be made for performing any Work of this Section. The
Contractor shall include all costs for this Work in its lump sum price bid for the
Contract.
A. Contractor shall make all arrangements for transportation, delivery and handling of
equipment and materials required for prosecution and completion of the Work.
B. Working space within the facilities is limited. Equipment shall not be delivered to the
Site until it can be moved directly to its concrete foundation pad and placed thereon, or
to the area where it will be utilized.
01651-1 11/2017
1671
DETAILED SPECIFICATION 01651 - TRANSPORTATION AND HANDLING
OF MATERIALS AND EQUIPMENT
CONTRACT DEL-260 G, H, E
B. Coordinate deliveries to avoid conflict with Work and conditions at the site and to
accommodate the following:
1. Work of other Contractors.
2. Limitations of storage space.
3. Availability of equipment and personnel for handling products.
C. Products shall not be delivered to the Site until related Shop Drawings, including the
manufacturer's recommended storage instructions, have been approved by the Engineer.
D. Products shall not be delivered to the Site until required storage facilities have been
provided.
A. The Contractor shall provide equipment and personnel necessary to handle products by
methods to prevent soiling or damage to products or packaging.
F. Materials and equipment shall at all times be handled in a safe manner and as
recommended by manufacturer or supplier so that no damage will occur to them. Do
01651-2 11/2017
1672
DETAILED SPECIFICATION 01651 - TRANSPORTATION AND HANDLING
OF MATERIALS AND EQUIPMENT
CONTRACT DEL-260 G, H, E
not drop, roll or skid products off delivery vehicles. Hand carry or use suitable
materials handling equipment.
A. The Contractor shall inspect all items, including all boxes, crates and packages,
containing equipment and materials for damage that may have occurred during
shipment prior to its removal from the truck or other conveyance. Any damage shall be
reported immediately to the Engineer.
B. The Contractor shall then carefully remove the equipment and materials from the truck
or trucks on which it is shipped. The equipment and materials shall then be transported
to the place of installation at the site. The Contractor shall be liable for loss or damage
to the equipment and materials that may occur while being unloaded, transported,
stored or installed.
C. All equipment that arrives at the Site during normal working hours shall be unloaded as
soon as practicable.
A. The Contractor shall, in all cases where heavy loads are to be temporarily imposed on
existing slabs, assure himself of the slab's load-sustaining ability. Whenever heavy
loads are to be stored or temporarily imposed on slabs, the Contractor shall submit for
approval by the Engineer a plan of procedure prepared by a licensed Professional
Engineer, indicating a structural analysis of the slabs and methods of distributing loads,
and providing auxiliary support so that slabs and beams are not loaded in excess of
their design loadings.
A. Existing cranes in the Shaft 18 Facility are property of the City and are available for the
Contractor's use. The Contractor shall perform an inspection of the hoisting equipment
prior and after the use of such, any necessary repairs will be the responsibility of the
Contractor
END OF SECTION
01651-3 11/2017
1673
DETAILED SPECIFICATION 01651 - TRANSPORTATION AND HANDLING
OF MATERIALS AND EQUIPMENT
CONTRACT DEL-260 G, H, E
01651-4 11/2017
1674
DETAILED SPECIFICATION 01661 – PROTECTION OF MATERIALS AND
EQUIPMENT
CONTRACTS DEL-260 G, H, E
SECTION 01661
Protection of Materials and Equipment
PART 1 GENERAL
A. Related Specifications.
B. Payment.
B. Storage of product.
1.03 PAYMENT
A. No separate payment will be made for performing any Work of this Section. The
Contractor shall include all costs for this Work in its lump sum price bid for the
Contract.
B. Handle and lift products only at designated lift points and by methods to avoid
soiling, disfigurement, bending, overstressing and damage.
C. Store products on shelves, in bins, or in neat groups of like items, with seals and
labels intact and legible, and in a manner to provide access for maintenance and
inspection.
D. Store loose granular materials on clean, solid, flat surfaces and prevent mixing with
foreign matter. Store fabricated products supported above the ground on skids or
blocking. Provide surface drainage to prevent erosion and ponding of water.
01661-1 11/2017
1675
DETAILED SPECIFICATION 01661 – PROTECTION OF MATERIALS AND
EQUIPMENT
CONTRACTS DEL-260 G, H, E
F. Store and protect products, which are subject to damage by the elements, in
weathertight, climate controlled enclosures and according to manufacturer's
instructions. Maintain temperature, ventilation, and humidity within ranges stated in
manufacturer's instructions.
I. Record inspection, maintenance and services performed and keep log available for
review by the City and Engineer.
A. The Contractor shall make every effort to minimize extended storage periods of
materials and equipment at the Site by judiciously scheduling deliveries to coincide
with construction needs.
C. All mechanical and electrical equipment shall be coated, wrapped and otherwise
protected from snow, rain, drippings of any sort, dust, mud and condensed water
vapor, during shipment, storage, and installation and until placed in service.
D. All storage areas for motors and control panels shall be heated. Space heaters shall
be supplied, as needed or required, in all enclosures being utilized for storage of
motors. Motors equipped with space heaters shall be properly wired and the heaters
activated while the motors are in storage.
F. Materials may be stored out of doors if supported above ground surface on wood
runners and protected with approved, effective and durable weathertight covers.
G. Provide separate, safe and suitable storage for hazardous and flammable materials.
H. All storage and protection of materials and equipment at the Site shall be subject to
the approval of the Engineer.
01661-2 11/2017
1676
DETAILED SPECIFICATION 01661 – PROTECTION OF MATERIALS AND
EQUIPMENT
CONTRACTS DEL-260 G, H, E
I. The Contractor is responsible for managing and protecting any and all materials and
equipment that the Contractor stores within the Site and must be able to move such
materials and equipment during a City-Ordered Demobilization. The Contractor
shall have no claim for additional compensation or Contract time due to the
Contractor’s failure to protect and move materials and equipment during a City-
Ordered Demobilization.
END OF SECTION
01661-3 11/2017
1677
DETAILED SPECIFICATION 01661 – PROTECTION OF MATERIALS AND
EQUIPMENT
CONTRACTS DEL-260 G, H, E
01661-4 11/2017
1678
DETAILED SPECIFICATION 01711 – MAINTENANCE OF OPERATIONS
AND CONSTRUCTION STAGING
CONTRACT DEL-260 G, H, E
SECTION 01711
Maintenance of Operations and Construction Staging
PART 1 GENERAL
A. Related Specifications
B. Payment
E. Construction Staging.
1.03 PAYMENT
A. No separate payment will be made for performing any Work of this Section. The
Contractor shall include all costs for this Work in its lump sum price bid for the
Contract.
A. It is required as a part of this Contract that the Contractor conducts their Work in
a manner such that the City can keep Shaft 18 in continuous dependable operation
during construction.
B. Any temporary Work that may be required to maintain the existing facilities in
operation shall be furnished by the Contractor at the direction of the Engineer at
no extra cost to the City.
C. The Contractor shall keep the City and the Engineer informed of any Work which
has the potential to interfere with the operation of the existing facilities.
01711-1 11/2017
1679
DETAILED SPECIFICATION 01711 – MAINTENANCE OF OPERATIONS
AND CONSTRUCTION STAGING
CONTRACT DEL-260 G, H, E
E. The Contractor shall be responsible for the operation and maintenance of its own
equipment. Operation of Contractor-owned equipment connected to the City
water supply system will be subject to approval by the City.
F. The Engineer and City must receive sixty (60) days prior written notice of the
Contractor's intended schedule for Work which will interfere with the operation of
the existing facilities. The Critical Path Method schedule shall not serve as prior
notice.
A. The following general criteria and restrictions shall apply except where otherwise
noted:
2. The Chlorine Storage and the Chlorination Rooms are used by the City on
a daily basis. The City receives routine deliveries of chlorine gas
containers that must be unloaded and stored in the Chlorine Storage
Room. In addition, the City has to perform numerous chlorine gas
container replacements in the Chlorine Storage room and process
motoring activities in the Chlorination Room on a daily basis. The
Contractor shall perform the Work under this Contract without interfering
with the daily activities that the City performs in the work areas.
A. The Contractor shall perform the Work as shown on the Contract Drawings and
specified herein to meet the requirements of this Detailed Specification regarding
time of completion and maintenance of operations.
C. The Contractor shall coordinate with DEP Operations on the allowable time per
phasing stage. Equipment shall only be out of service for the minimum amount of
time needed to move the loads from the existing panels to the new panels.
END OF SECTION
01711-3 11/2017
1681
DETAILED SPECIFICATION 01711 – MAINTENANCE OF OPERATIONS
AND CONSTRUCTION STAGING
CONTRACT DEL-260 G, H, E
01711-4 11/2017
1682
DETAILED SPECIFICATION 01721 - PROTECTION AND RESTORATION OF
STRUCTURES
CONTRACT DEL-260 G, H, E
SECTION 01721
Protection and Restoration of Structures
PART 1 GENERAL
A. Related Specifications
B. Payment
C. General Requirements
E. Underground Structures
F. Surface Structures
G. Underwater Structures
1.03 PAYMENT
A. No separate payment will be made for performing any work of this Section. The
Contractor shall include all costs for this work in its lump sum price bid for the
Contract.
A. The Contractor shall execute the Work to prevent damage or injury to the existing
Structures and occupants thereof, which might result from work or other causes, and so
as not to interfere with the use and free and safe passage to and from Shaft 18 uptake
building.
01721-1 11/2017
1683
DETAILED SPECIFICATION 01721 - PROTECTION AND RESTORATION OF
STRUCTURES
CONTRACT DEL-260 G, H, E
B. The Contractor shall erect and maintain barriers, lights, fences, and other required
protective devices in accordance with the Contract Documents and the NYC Building
Code, local codes and NYS Department of Transportation.
C. The Contractor shall be responsible for taking all precautions, providing all programs,
and taking all actions necessary to protect the Work and all public and private property
and facilities from damage, injury, loss or vandalism.
D. The Contractor shall assume full responsibility for the preservation of all public and
private property or facilities on or adjacent to the Site. If any direct or indirect damage
is done by or on account of any act, omission, neglect or misconduct in the execution of
the Work by the Contractor, it shall be restored by the Contractor, at their expense, to a
condition equal to that existing before the damage was done. Where necessary to
protect the Work or materials from damage, the Contractor shall at their expense
provide suitable drainage and erect such temporary structures as are necessary to
protect the Work or materials from damage. The suspension of the Work or the
granting of an extension of time from any cause whatever shall not relieve the
Contractor of their responsibility for the Work and materials.
E. All structures and appurtenances shall be adequately supported and safeguarded against
all damage or injury in performance of Work under this Contract. Work under this
Contract includes, but is not limited to, excavation, backfilling, trucking and other
activities. The Contractor will be held responsible for any such damage or injury
resulting from their operations and shall repair such damage immediately and to the
satisfaction of the Engineer.
F. The Contractor shall ascertain the location of underground pipelines, conduits and other
subsurface structures in those locations where the operation of their heavy construction
equipment might damage such structures. The Contractor shall either avoid such
locations or provide the necessary safeguards and repair any damage quickly at their
own expense.
G. The Contractor shall comply promptly with such safety regulations as may be
prescribed by the Engineer or the local authorities having jurisdiction and shall, when
so directed, properly correct any unsafe conditions created by, or unsafe practices on
the part of their employees. In the event of the Contractor's failure to comply, the
Engineer may take the necessary measures to correct the conditions or practices
complained of, and all costs thereof will be deducted from any monies due the
Contractor. Failure of the Engineer to direct the correction of unsafe conditions or
practices shall not relieve the Contractor of their responsibility hereunder.
H. In the event of any claims for damage or alleged damage to property as a result of Work
under this Contract, the Contractor shall be responsible for all costs in connection with
the settlement of or defense against such claims.
01721-2 11/2017
1684
DETAILED SPECIFICATION 01721 - PROTECTION AND RESTORATION OF
STRUCTURES
CONTRACT DEL-260 G, H, E
I. Prior to commencement of Work in the vicinity of property adjacent to the work site,
the Contractor, at their own expense, shall take such surveys as may be necessary to
establish the existing condition of the property. Before final payment can be made, the
Contractor shall furnish satisfactory evidence that all claims for damage have been
legally settled or sufficient funds to cover such claims have been placed in escrow, or
that an adequate bond to cover such claims has been obtained.
1. Location of damage.
2. Nature of damage.
3. Extent of damage.
A. The term existing utilities shall be deemed to refer to both publicly-owned and
privately-owned utilities such as, but not limited to electric power and lighting,
telephone, water, gas, storm drains, process lines, sanitary sewers and all appurtenant
structures.
B. Where existing utilities and structures are indicated on the Contract Drawings, it shall
be understood that all of the existing utilities and structures affecting the work may not
be shown and that the locations of those shown are approximate only. It shall be the
responsibility of the Contractor to ascertain the actual extent and exact location of
existing utilities and structures. In every instance, the Contractor shall notify the proper
authority having jurisdiction and obtain all necessary directions and approvals before
performing any work in the vicinity of existing utilities.
C. The Work shall be carried out in a manner to prevent disruption of existing services and
to avoid damage to the existing utilities. Temporary connections shall be provided, as
required, to insure no interruption of existing services. Any damage resulting from the
Work of this Contract shall be promptly repaired by the Contractor at their own
expense in a manner approved by the Engineer and further subject to the requirements
of any authority having jurisdiction. Where it is required by the authority having
jurisdiction that they perform their own repairs or have them done by others, the
Contractor shall be responsible for all costs thereof.
01721-3 11/2017
1685
DETAILED SPECIFICATION 01721 - PROTECTION AND RESTORATION OF
STRUCTURES
CONTRACT DEL-260 G, H, E
D. Where excavations by the Contractor require any utility lines or appurtenant structures
to be temporarily supported and otherwise protected during the construction Work,
such support and protection shall be provided by the Contractor. All such Work shall
be performed in a manner satisfactory to the Engineer and the respective authority
having jurisdiction over such Work. In the event the Contractor fails to provide proper
support or protection to any existing utility, the Engineer may, at this discretion, have
the respective authority to provide such support or protection as may be necessary to
ensure the safety of such utility, and the costs of such measures shall be paid by the
Contractor.
E. During the progress of the Work, the Contractor shall protect from injury any existing
utilities or services within the work area until, if required, they have been re-routed,
disconnected or capped off. Protection and re-routing shall conform to standards
established by the utilities, agencies and governing codes.
A. Underground structures are defined to include, but not be limited to, all sewer, water,
gas, and other piping, and manholes, chambers, electrical and signal conduits, tunnels
and other existing subsurface infrastructure located within or adjacent to the limits of
the Work.
B. Underground structures known to the Engineer are shown for the assistance of the
Contractor in accordance with the best information available, but is not guaranteed to
be correct or complete.
C. The Contractor shall explore ahead of their trenching and excavation Work and shall
uncover all obstructing underground structures sufficiently to determine their location,
to prevent damage to them and to prevent interruption to the services which such
structures provide. If the Contractor damages an underground structure, they shall
quickly restore it to original condition at their own expense.
D. Necessary changes in the location of the Work may be made by the Engineer, to avoid
unanticipated underground structures.
E. If the Contractor discovers utility facilities not identified in the Contract Documents or
in a position different from that shown in the Contract Documents, they shall
immediately notify the Engineer and the owner of the utility facility, in writing.
01721-4 11/2017
1686
DETAILED SPECIFICATION 01721 - PROTECTION AND RESTORATION OF
STRUCTURES
CONTRACT DEL-260 G, H, E
A. Surface structures are defined as all existing buildings, structures and other facilities
above the ground surface. Included with such structures are their foundations or any
extension below the surface.
B. Surface structures include, but are not limited to, buildings, tanks, walls, bridges, roads,
dams, channels, open drainage, piping, poles, wires, posts, signs, markers, curbs, walks
and all other facilities that are visible above the ground surface.
A. Underwater structures are defined as all structures below the water surface.
A. The Contractor shall sustain in their places and protect from direct or indirect injury all
underground, surface, and underwater structures located within or adjacent to the limits
of the Work. Such sustaining and supporting shall be done carefully and as required by
the party owning or controlling such structure. Before proceeding with the Work of
sustaining and supporting such structure, the Contractor shall satisfy the Engineer that
the methods and procedures to be used have been approved by the party owning same.
B. The Contractor shall assume all risks attending the presence or proximity of all
underground and surface structures within or adjacent to the limits of the Work. The
Contractor shall be responsible for all damage and expense for direct or indirect injury
caused by their Work to any structure. The Contractor shall repair immediately all
damage caused by their Work, to the satisfaction of the owner of the damaged structure.
C. The fact that any structure or facility is not shown on the Contract Drawings shall not
relieve the Contractor of their responsibility of protecting and preserving the structure
or facility.
D. All other existing surface facilities, including but not limited to, guard rails, posts,
guard cables signs, poles, markers, and curbs which are temporarily removed to
facilitate installation of the Work shall be replaced and restored to their original
condition after the protective and relocation work is no longer needed at the
Contractor's expense.
1687
DETAILED SPECIFICATION 01721 - PROTECTION AND RESTORATION OF
STRUCTURES
CONTRACT DEL-260 G, H, E
D. Cover projections, wall corners, jambs, sills, soffits in areas used for traffic and passage
in subsequent work.
E. Provide protection of existing trees and landscaping to prevent damage from all
construction operations. No trees or shrubs shall be cut, felled or removed from the Site
except as designated in the Contract Documents. Remove protection facilities when no
longer needed, prior to completion of Work.
F. Prohibit traffic of any kind across planted lawn and landscaped areas. Protect
landscaped areas and seeded areas from birds and animals.
END OF SECTION
01721-6 11/2017
1688
DETAILED SPECIFICATION 01732 - INSTALLATION OF EQUIPMENT
CONTRACT DEL-260 G, H, E
SECTION 01732
Installation of Equipment
PART 1 GENERAL
1.02 PAYMENT
A. There will be no separate payment for performing any work required under this
Section and the Contractor shall include all costs thereof in the lump sum price
bid for the Contract.
1.03 DESCRIPTION
A. GENERAL
1. The Contractor shall have adequate resources on site, including labor,
materials, construction tools and equipment, to perform the Work of this
Section.
2. The Contractor shall be responsible for locating, aligning and leveling
all equipment and shall employ a licensed surveyor to set all lines and
levels of equipment to the accuracy required.
3. Complete manufacturer's installation instructions, including permissible
tolerances, shall be furnished in duplicate with each unit of equipment
or set of identical units.
4. All equipment shall be installed in accordance with the approved shop
drawings; inclusive of manufacturer's specifications, drawings and
tolerances; under the direct supervision of the required manufacturer's
01732-1 11/2017
DEP 6/30/2016
1689
DETAILED SPECIFICATION 01732 - INSTALLATION OF EQUIPMENT
CONTRACT DEL-260 G, H, E
PART 2 PRODUCTS
2.01 GROUT
A. Grout bed shall be a non-shrink grout, "Euco-N-S" by the Euclid Chemical
Company or "Masterflow 713" by Master Builders, or approved equal.
PART 3 EXECUTION
01732-3 11/2017
DEP 6/30/2016
1691
DETAILED SPECIFICATION 01732 - INSTALLATION OF EQUIPMENT
CONTRACT DEL-260 G, H, E
necessary to bring parts to proper bearing after erection shall be done at the
expense of the Contractor.
E. Each piece of equipment or supporting base, bearing on concrete foundations,
shall be bedded in grout. The Contractor shall provide a minimum of 1-1/2 inch
thick grouting under the entire base plate supporting each pump, motor drive
unit and other equipment.
F. When motors are shipped separately from driven equipment, the motors shall
be received, stored, meggered once a month, and the reports submitted to the
Engineer. Space heaters shall be supplied in all enclosures being utilized for
storage of motors. After driven equipment is set, the motors shall be set,
mounted, shimmed, mill righted, coupled and connected complete.
G. Moving parts shall be rotated a minimum of once weekly before and after
installation to ensure proper lubrication and to avoid metal-to-metal welding
and to prevent "flat-spotting" of bearings.
H. Anchor and expansion bolts shall be furnished by the Contractor as specified
and required by this Contract Documents.
I. At threaded connections, a molybdenum disulphide anti-seize compound shall
be applied to all threads in mechanical connections such as bolts, studs, cap
screws, tubing, etc., unless otherwise indicated.
3.03 WORKMANSHIP
A. The following erection specifications are not intended to be all-inclusive, but
only to cover some of the important practices. In all cases, only the best
methods known to the trades are to be employed.
B. Only those mechanics skilled in the handling, setting, alignment, leveling and
adjustment of the type of equipment supplied shall be employed in the work.
C. An oil bath heater shall always be used to expand couplings, gears, etc. They
shall not be forced or driven on equipment shafts, nor shall they be subjected to
an open flame or torch.
D. Wedging will not be permitted. Only the least number of flat shims are to be
used in leveling equipment (shims are to be clean and free of slag). All shims,
filling pieces, keys packing, red or white lead grout, or other materials necessary
to properly align, level and secure apparatus in place shall be furnished by the
Contractor. All parts intended to be plumb or level must be proven exactly so.
Any grinding necessary to bring parts to proper bearing after erection shall be
done at the expense of the Contractor.
E. Proper tools shall be used in the assembly of equipment and materials to prevent
marring the surface of shafts, nuts or other parts.
01732-5 11/2017
DEP 6/30/2016
1693
DETAILED SPECIFICATION 01732 - INSTALLATION OF EQUIPMENT
CONTRACT DEL-260 G, H, E
01732-6 11/2017
DEP 6/30/2016
1694
DETAILED SPECIFICATION 01732 - INSTALLATION OF EQUIPMENT
CONTRACT DEL-260 G, H, E
3.07 LUBRICATION
A. All lubrication shall be performed by the Contractor in accordance with the
lubricant specifications and directions furnished by the manufacturer. The
Contractor shall furnish the lubricants for the equipment until it is accepted.
B. Lubricants shall be changed upon completion of installation and as frequently
as required thereafter during the period between installation and acceptance.
New lubricants shall be put into the equipment at the time of acceptance.
01732-7 11/2017
DEP 6/30/2016
1695
DETAILED SPECIFICATION 01732 - INSTALLATION OF EQUIPMENT
CONTRACT DEL-260 G, H, E
END OF SECTION
01732-8 11/2017
DEP 6/30/2016
1696
DETAILED SPECIFICATION 01733 - CONSTRUCTION WASTE
MANAGEMENT
CONTRACT DEL-260 G, H, E
SECTION 01733
Construction Waste Management
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any work required under
this Section and the Contractor shall include all costs thereof in its lump
sum price bid for the Contract.
1.05 DEFINITIONS
A. Hazardous Waste - A solid, liquid or gaseous waste that meets any of the
following criteria, unless excluded by 6 NYCRR 370 or 371:
1. Exhibits one or more hazardous waste characteristics listed in 6
NYCRR 371.3 (i.e., corrosivity, ignitability, reactivity and toxicity);
2. Is listed in 6 NYCRR 371.4 as a hazardous waste;
3. Is a mixture of a solid waste and a hazardous waste unless the
hazardous waste is listed in 6 NYCRR 371.4 solely because it
exhibits one or more of the characteristics of hazardous waste
identified in section 371.3 and the resultant mixture no longer
exhibits any characteristic of hazardous waste identified in section
371.3 (6 NYCRR371.1(d)(1)(ii)(‘c’)). Mixing may require a 6
NYCRR 373 permit.
B. Universal Waste as defined by:
1. 40 CFR Part 273: Standards for Universal Waste Management;
2. 6 NYCRR Subpart 374-3: Standards for Universal Waste;
01733-1 11/2017
DEP 6/17/2017
1697
DETAILED SPECIFICATION 01733 - CONSTRUCTION WASTE
MANAGEMENT
CONTRACT DEL-260 G, H, E
1.06 DESCRIPTION
1. Construction Waste Materials: The list of construction waste
materials shall include, but not be limited to, the following
materials:
a. Cardboard
b. Clean dimensional wood
c. Demolition debris
d. Concrete
e. Bricks
f. Concrete masonry units (CMU)
g. Asphalt
h. Metals from rebar, sheetrock studs, framing, etc.
i. Steel sheet piling
j. Steel pipe piles
01733-2 11/2017
DEP 6/17/2017
1698
DETAILED SPECIFICATION 01733 - CONSTRUCTION WASTE
MANAGEMENT
CONTRACT DEL-260 G, H, E
k. Structural steel
l. Paints, solvents, and other hazardous fluids
m. Glass
n. Roofing
o. Wood pallets
p. Fencing materials
q. Mercury containing light bulbs from the Contractor’s office
r. Recyclable office wastes such as paper and toner and ink
cartridges that should be recycled.
B. Construction Waste Management
1. Each Contractor shall use construction and demolition methods and
processes to ensure the generation of as little waste as possible due
to error, poor planning, breakage, mishandling, contamination, or
other factors. Where feasible, as many of the materials from the
generated waste shall be salvaged, reused, or recycled.
2. When encountered as part of its Work for sites within New York
City, the Contractor shall dispose of construction waste by recycling
methods in accordance with the NYC Recycling Law: Local Law 19
(1989) and Local Law 87 (1992), and NYC’s Commercial
Recycling Regulations: Rules Governing the Recycling of Private
Carter-Collected Waste (September 1993). Under these laws and
rules, waste materials to be recycled shall include concrete, metals,
and rock. In addition, the Contractor shall also arrange for recycling
of untreated wood (scrap wood, pallets, etc.), green wood (stumps
and tree parts), asphalt, brick and concrete block. All material to be
recycled shall be separated from normal refuse, per New York City
Department of Sanitation (DOS) Rules. Normal refuse and material
not required to be recycled shall be disposed of by the Contractor as
specified and in accordance with all applicable federal, state and
local laws, rules and regulations.
3. When encountered as part of its work for sites outside New York
City, the Contractor shall dispose of construction and demolition
waste by recycling methods in accordance with all relevant State,
County and local codes, laws and regulations.
4. All hazardous waste, universal waste, and used oil must be separated
and stored in their own dedicated storage areas and managed in
compliance with NYSDEC Hazardous Waste, Universal Waste and
Used Oil Regulations, USDOT Hazardous Material Transportation
Regulations found in Title 49 of the Code of Federal Regulations,
and in accordance with NYCDEP Hazardous Waste Management,
01733-3 11/2017
DEP 6/17/2017
1699
DETAILED SPECIFICATION 01733 - CONSTRUCTION WASTE
MANAGEMENT
CONTRACT DEL-260 G, H, E
1.08 SUBMITTALS
A. The Electrical Contractor shall prepare and submit a Construction Waste
Management Plan for review and approval by the Resident Engineer within
15 days after receipt of Notice to Proceed and prior to the removal of any
construction waste or demolition materials from the Project site.
B. The Construction Waste Management Plan shall contain the following:
1. Analysis of the proposed construction waste to be generated,
including types and quantities of each, during prosecution of the
Work.
2. A description of the means by which any construction waste
materials listed above will be appropriately segregated and not
mixed in order to prevent cross-contamination as well as a
description of the means to be employed in recycling the above
materials consistent with requirements of the New York City
Department of Sanitation.
3. A list of waste transporters, transfer stations, disposal facilities and
recyclers with addresses, phone numbers, and permits which the
Contractor intends to utilize during the Project for the purpose of
complying with the Construction Waste Management Plan. The
Construction Waste Management Plan shall list where the non-
recyclable materials will be disposed.
4. A description of the means of transportation of the recyclable and
non-recyclable materials (whether materials will be site-separated
and self-hauled to designated centers, or whether mixed materials
01733-4 11/2017
DEP 6/17/2017
1700
DETAILED SPECIFICATION 01733 - CONSTRUCTION WASTE
MANAGEMENT
CONTRACT DEL-260 G, H, E
01733-5 11/2017
DEP 6/17/2017
1701
DETAILED SPECIFICATION 01733 - CONSTRUCTION WASTE
MANAGEMENT
CONTRACT DEL-260 G, H, E
END OF SECTION
01733-6 11/2017
DEP 6/17/2017
1702
DETAILED SPECIFICATION 01740 CLEANING AND SITE MAINTENANCE
CONTRACTS DEL-260 G, H, E
SECTION 01740
Cleaning and Site Maintenance
PART 1 GENERAL
1.03 PAYMENT
A. Payment for electrical energy charges for the temporary power for the
Engineer’s field office trailer and restroom trailer shall be made under
Allowance E-A-3 of the Electrical Contract, as specified in Section 01270 –
Measurement and Payment.
B. Allowance for the Collection and Disposal of Debris and Rubbish and for
Maintenance of the Site.
1. The Electrical Contractor shall provide all labor, expendable materials
and/or supplies, and equipment to collect and dispose of all debris and
rubbish generated by all Contractors in the work area, not including
each Contractor’s staging and storage areas. The Engineer may require
additional site cleaning services beyond what is described herein. Such
cleaning shall be performed by the Electrical Contractor when ordered
in writing by the Resident Engineer.
01740-1 11/2017
DEP 9/24/2015
MULTIPLE CONTRACTS
1703
DETAILED SPECIFICATION 01740 CLEANING AND SITE MAINTENANCE
CONTRACTS DEL-260 G, H, E
2. Payment for the Work performed under this Allowance item shall be
made as specified in Detailed Specification 01270 – Measurement and
Payment.
3. The Electrical Contractor shall include this Allowance in his bid as
specified in Detailed Specification 01270 -- Measurement and
Payment, for this work.
4. No separate payment will be made to the Contractors for the Final
Cleaning work called for herein under Article 3.04; the costs thereof
shall be included in the lump sum bid price for each Contract.
C. Allowance for Snow and Ice Removal
1. The Electrical Contractor shall include an Allowance in his bid, as
specified in Detailed Specification 01270 -- Measurement and
Payment, for Snow and Ice Removal work. Payment for the Work
performed under this Allowance item shall be made as specified in
Section 01270 – Measurement and Payment.
01740-2 11/2017
DEP 9/24/2015
MULTIPLE CONTRACTS
1704
DETAILED SPECIFICATION 01740 CLEANING AND SITE MAINTENANCE
CONTRACTS DEL-260 G, H, E
B. The Contractors shall comply with all federal, state and local anti-pollution
laws, ordinances, codes and regulations when disposing of waste materials,
debris, rubbish, snow and ice.
01740-3 11/2017
DEP 9/24/2015
MULTIPLE CONTRACTS
1705
DETAILED SPECIFICATION 01740 CLEANING AND SITE MAINTENANCE
CONTRACTS DEL-260 G, H, E
1. The sidewalks and parking areas associated with the Engineers field
office.
2. All construction access roads.
3. Any Plant walkways which cannot be accessed by the Plant's snow
removal equipment due to construction activities.
4. Any additional areas designated by the Engineer.
5. Snow and ice removal shall be before 7:00 AM whenever there is a
snowfall storm and before 7:00 AM on the day following the
termination of the snowfall storm.
6. In addition, when directed by the Engineer, snow and/or ice removal
shall be started immediately (within one (1) hour of directive to
proceed) by the Contractor.
7. The Electrical Contractor shall haul the removed snow and ice for
disposal as per the applicable local requirements.
8. Spreading of Salt and Sand
a. The Electrical Contractor shall furnish all labor, tools,
equipment, and materials necessary to provide the following
services specifically requested and authorized in writing by the
Engineer:
b. Spread calcium chloride over all areas of the Resident
Engineer’s parking lot and spread sand on the steps and
platforms at the entrances to the Resident Engineer’s field
office.
c. Salt and sand shall be spread prior to a snowstorm.
d. Upon termination of a snowstorm, the Electrical Contractor
shall remove all sand from the steps and platforms at the
entrances to the Engineer’s field office.
e. Disposal of sand shall be the responsibility of the Electrical
Contractor.
END OF SECTION
01740-5 11/2017
DEP 9/24/2015
MULTIPLE CONTRACTS
1707
DETAILED SPECIFICATION 01740 CLEANING AND SITE MAINTENANCE
CONTRACTS DEL-260 G, H, E
01740-6 11/2017
DEP 9/24/2015
MULTIPLE CONTRACTS
1708
DETAILED SPECIFICATION 01750 - SPARE PARTS AND MAINTENANCE
MATERIALS
CONTRACTS DEL-260 G, H, E
SECTION 01750
Spare Parts and Maintenance Materials
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any Work of this Section and
the Contractor shall include all costs thereof in its Lump Sum price bid for the
Contract.
1.04 DESCRIPTION
A. Furnish spare parts and maintenance materials as specified in the individual
Detailed Specifications of each Contract.
B. Provide data for each distinct part in paper and electronic format.
C. Attach bar-code tag (sticker), transmitted by the Engineer, to each distinct part.
D. All parts and materials required under the Detailed Specifications of this
contract shall be turned over to the City in as-new condition and shall be
furnished in manufacturers' unopened cartons, boxes, crates or other protective
covering suitable for preventing corrosion or deterioration for the maximum
length of storage which may be normally anticipated. They shall be clearly
marked and identified
E. Schedule delivery of all parts from this contract over a reasonable period of
time in coordination with City Plant personnel and the Engineer. Parts and
materials shall be delivered to the City upon Substantial Completion of the
Work or when the City assumes beneficial occupancy or as directed by the City
or the Engineer. Contractor shall then place them in permanent storage rooms
or areas approved by the City.
F. Provide a letter of transmittal for each parts shipment for all contracts including
the following:
1. Date of letter and transfer of parts and materials.
01750-1 11/2017
DEP 3/15/2016
MULTIPLE CONTRACTS
1709
DETAILED SPECIFICATION 01750 - SPARE PARTS AND MAINTENANCE
MATERIALS
CONTRACTS DEL-260 G, H, E
1.05 SUBMITTALS
A. The DEL- 260 G, H and E Contractors shall prepare a list of all spare parts and
requisite data to be inventoried and stored under Paragraph 3.01 of this
Specification in a format provided by the Engineer. The spare parts data shall
be submitted in paper and electronic format. The electronic format shall be a
spreadsheet that allows data to be uploaded into a commercial database system
owned by the City.
B. The spare parts data shall be submitted to the Engineer at least 120 days prior
to delivery of spare parts to the storage location.
PART 3 EXECUTION
3.02 ATTACHMENTS
A. Spare Parts Schedule Form.
END OF SECTION
01750-3 11/2017
DEP 3/15/2016
MULTIPLE CONTRACTS
1711
ATTACHMENTS - DETAILED SPECIFICATION 01750 - CONTRACTS DEL-260 G, H, E
PAGE 1 OF 1 11/2017
DEP 3/15/2016
MULTIPLE CONTRACTS
1712
DETAILED SPECIFICATION 01781 - PROJECT CLOSEOUT
CONTRACT DEL-260 G, H, E
SECTION 01781
Project Closeout
PART 1 GENERAL
A. Related Sections
B. Payment
C. Items To Be Completed
1.03 PAYMENT
A. No separate payment will be made for performing any Work of this Section. The
Contractor shall include all costs for this Work in its lump sum price bid for the
Contract.
A. As construction of the project enters the final stages of completion, the Contractor
shall, in concert with accomplishing the requirements set forth in the Contract
Documents, attend to or have already completed the following items as they apply to
his Contract:
2. Attend to any other items listed herein or brought to the Contractor's attention by
the Engineer.
01781-1 11/2017
1713
DETAILED SPECIFICATION 01781 - PROJECT CLOSEOUT
CONTRACT DEL-260 G, H, E
C. In addition, and before the Certificate of Substantial Completion will be issued, the
Contractor shall submit to the Engineer certain records, certifications, etc., which are
specified elsewhere in the Contract Documents. A partial list of such items appears
below, but it shall be the Contractor's responsibility to submit all items which are
required by the Contract Documents:
2. One set of neatly marked-up Record Drawings showing as-built changes and
additions to the Work under his Contract.
D. The Contractor's attention is directed to the fact that required certificates and
information under Article 1.03C., above, must actually be submitted earlier in
accordance with other Sections of the Specifications.
A. Upon completion of the Work and as a condition precedent to final acceptance, the
Contractor shall provide all labor and material required to furnish Final Record
Documents in accordance with the requirements of Detailed Specification 01332 –
Final Record Documents. The submittal must be approved by the Engineer. If the
Contractor chooses to use a Consultant to perform this Work, the choice of Consultant
shall be submitted to the Engineer for approval.
B. Failure to perform this Work as specified above and in Detailed Specification 01332 –
Final Record Documents will result in a deduction from the final payment to the
Contractor. The amount of the deduction will be equal to the actual cost incurred by
the City to perform this Work.
A. Special tools and appliances which may be needed to adjust, operate, maintain or repair
the Work furnished under this Contract shall be provided in accordance with Article 12
of the General Conditions, applicable General Specifications and the Detailed
Specifications.
B. The Contractor shall submit a complete list of special tools and appliances to be
furnished, for approval by the Engineer, as a part of the Shop Drawing submittal.
01781-2 11/2017
1714
DETAILED SPECIFICATION 01781 - PROJECT CLOSEOUT
CONTRACT DEL-260 G, H, E
C. Special tools and appliances shall be furnished in approved painted steel cases, properly
labeled and equipped with good grade cylinder locks and duplicate keys.
A. The Contractor must promptly repair, replace, restore or rebuild, as the Commissioner
may determine, any Work provided under this Contract in which defects of equipment,
materials or workmanship may appear or to which damage may occur because of such
defects, during the 1-year maintenance and guaranty period subsequent to the date of
final acceptance, except where longer periods of maintenance and guaranty are
provided for in the Detailed Specifications.
END OF SECTION
01781-3 11/2017
1715
DETAILED SPECIFICATION 01781 - PROJECT CLOSEOUT
CONTRACT DEL-260 G, H, E
01781-4 11/2017
1716
DETAILED SPECIFICATION 01811 – PRELIMINARY AND FINAL FIELD TESTS
CONTRACT DEL-260 G, H, E
SECTION 01811
Preliminary and Final Field Tests
PART 1 GENERAL
1.02 PAYMENT
A. No separate payment will be made for performing any Work required under this
Section and the Contractor shall include all costs thereof in the lump sum price
bid for the Contract.
1.04 DEFINITIONS
A. “System”: A System for purposes of testing is defined as consisting of the
component equipment, valves, piping, instrumentation, controls, ducts,
accessories, etc., which are required for the proper functioning of each piece of
equipment and the System as a whole. The purpose of the System testing is to
demonstrate the capability of the equipment, interconnections and accessories
to perform as specified.
1.05 DESCRIPTION
A. All field tests, including equipment and Systems tests, shall be performed in
accordance with the requirements of the Specifications and this Section. The
requirements contained herein shall apply, whether or not this Section is
specifically referenced elsewhere in the Detailed Specifications.
B. Field tests shall include preliminary and final field tests of equipment and
Systems.
01811-1 11/2017
DEP 4/26/16
1717
DETAILED SPECIFICATION 01811 – PRELIMINARY AND FINAL FIELD TESTS
CONTRACT DEL-260 G, H, E
01811-2 11/2017
DEP 4/26/16
1718
DETAILED SPECIFICATION 01811 – PRELIMINARY AND FINAL FIELD TESTS
CONTRACT DEL-260 G, H, E
2. For final field tests of equipment and Systems, the Contractor shall
furnish all labor, lubricants, materials, fuel, power, materials,
instruments and equipment required for the tests.
3. All testing shall be performed by the Contractor and witnessed by the
Engineer, DEP Operations personnel and, when applicable,
representatives of the Town of Mount Pleasant. Preliminary field
testing of equipment and Systems and final field testing of equipment
and Systems shall be performed within the time periods designated in
the preliminary construction schedule (CPM) during regular weekday
daytime working hours.
F. Coordination
1. The Electrical Contractor shall coordinate the field testing activities
with the HVAC and General Contractors in order to ensure the
availability of their equipment for field tests. A Contractor furnishing
equipment under one Contract that is required for testing in a System
furnished by another Contractor shall coordinate with the other
Contractor to ensure that its equipment is available for testing with the
System. All such requirements for coordination shall be indicated in the
preliminary and final field activity schedules specified herein.
2. The Contractor for the equipment to be tested (General or HVAC) shall
be responsible for coordinating with the Electrical Contractor for
furnishing power required to perform its field tests.
3. Each Contractor shall study the requirements of these Contracts insofar
as they affect its work, or insofar as its work may affect that of the
related Contractors. Coordination with the other Contractors will be
required in order to perform the field tests. Any Contractor having
equipment installed under its Contract and tested as part of a System
furnished by another Contractor shall assist in the testing procedure.
1.07 SUBMITTALS
A. The Contractor shall submit a preliminary and final field test schedule to the
Engineer within 120 days after the date for commencing work in the Notice to
01811-3 11/2017
DEP 4/26/16
1719
DETAILED SPECIFICATION 01811 – PRELIMINARY AND FINAL FIELD TESTS
CONTRACT DEL-260 G, H, E
PART 3 EXECUTION
01811-4 11/2017
DEP 4/26/16
1720
DETAILED SPECIFICATION 01811 – PRELIMINARY AND FINAL FIELD TESTS
CONTRACT DEL-260 G, H, E
3.04 SYSTEMS
A. The following equipment groupings shall be tested together as Systems, in
accordance with the General and Detailed Specifications:
1. Electrical Systems:
a. Electric wires & cables, MV load interrupter switch, MV
transformer, MV sectionalizing cabinet, Dry type transformers,
Standby generator, Low voltage switchgear, Panelboards,
Electrical control equipment, Motor control center and
Automatic transfer switch.
2. HVAC Systems:
a. HVAC Monitoring and Control System (HMCS): The HMCS
shall be tested together with all equipment that is being
controlled by the HMCS. Also included in the System testing
is all equipment that is interlocked with the HMCS.
b. Chlorine Storage Room and Chlorinator Room Ventilation
System: This System is comprised of HV-1, EF-1, EF-2,
ventilation System chlorine detection panel, associated
dampers, valves, ductwork, piping and controls.
c. Electric Service Room Heating and Ventilation System: This
System is comprised of SF-1, EF-3, EUH-1, associated
dampers, ductwork and controls.
d. Electric Room 2 Heating and Ventilation System: This System
is comprised of EF-4, EUH-2, associated dampers, and
controls.
e. Hydronic System (provides heating hot water to HV-1): This
System is comprised of HWP-1, HV-1 hot water coil,
associated piping, valves and controls. Existing gas fired hot
water boiler and existing zone pumps shall be included in the
System testing to confirm that work associated with draining,
refilling, and air purging have not affected the operation of the
System and that hot water is restored through each zone
without air binding.
01811-6 11/2017
DEP 4/26/16
1722
DETAILED SPECIFICATION 01811 – PRELIMINARY AND FINAL FIELD TESTS
CONTRACT DEL-260 G, H, E
END OF SECTION
01811-7 11/2017
DEP 4/26/16
1723
DETAILED SPECIFICATION 01811 – PRELIMINARY AND FINAL FIELD TESTS
CONTRACT DEL-260 G, H, E
01811-8 11/2017
DEP 4/26/16
1724
DETAILED SPECIFICATION 01821 – EQUIPMENT START-UP AND TRAINING
CONTRACT DEL-260 G, H, E
SECTION 01821
Equipment Start-Up and Training
PART 1 GENERAL
A. Related Specifications
B. Payment
C. General Requirements
E. Training of Personnel
F. Videorecording of Training
G. Lesson Plans
H. Training Aids
1.03 PAYMENT
A. No separate payment will be made for performing any Work of this Section. The
Contractor shall include all costs for this Work in its lump sum price bid for the
Contract.
01821-1 11/2017
1725
DETAILED SPECIFICATION 01821 – EQUIPMENT START-UP AND TRAINING
CONTRACT DEL-260 G, H, E
A. The Contractor shall include, in the price bid, the cost to provide the services of a
factory trained and certified manufacturer’s representatives of all the equipment
furnished under its Contract, who shall provide the following services, at a
minimum:
4. Supervise the preliminary and final equipment and system field test work
as specified herein. Additional testing supervision resulting from the
failure to meet the specified performance requirements shall be at the
Contractor's expense.
C. Each Contractor shall provide the services of a factory trained and certified
manufacturer’s representatives for the training of an adequate number of City
operation and maintenance personnel. This service shall consist of the training or
the amount of training time recommended by the manufacturer or the training
indicated in Schedule 01821-2, whichever is greater, for each type of equipment.
One (1) day of training is defined to be a minimum of eight (8) hours on-site.
Any additional time required to achieve a satisfactory level of training shall be at
the Contractor’s expense.
D. The Contractor shall coordinate all equipment start-up services and training with
the City, the Engineer and the manufacturer.
01821-2 11/2017
1726
DETAILED SPECIFICATION 01821 – EQUIPMENT START-UP AND TRAINING
CONTRACT DEL-260 G, H, E
A. Equipment start-up and initial operating period shall begin after satisfactory
completion of the preliminary and final field tests of equipment and preliminary
field test of systems, during each stage of construction and prior to completion of
construction. Equipment start-up and initial operating period shall be completed
when the manufacturer and Engineer have mutually agreed that the equipment is
in suitable condition for continuous operation.
B. The Contractor shall furnish the services of factory trained and certified
manufacturer’s representatives to assist in the start-up and initial operation of the
equipment. The manufacturer’s representatives shall devote, at a minimum, the
full time specified under the Detailed Specifications for start-up and initial
operation. Any additional time required to achieve successful operation shall be
at the expense of the Contractor. One day of assistance by a manufacturer’s
representative shall be defined as a minimum of eight (8) hours on-site.
A. The City shall identify and make available the applicable personnel to be trained
in the operation and maintenance of the equipment. The City's personnel shall
operate all equipment.
B. The training shall consist of classroom and field instructions and shall follow the
approved lesson plans as described herein. Field instructions shall include
“Hands On” demonstration of the equipment operation and maintenance as
covered in the classroom instructions and in the operation and maintenance
manuals. Field instructions shall also identify all items required for equipment
operation and maintenance. All tools and spare parts required for hands on
demonstrations shall be supplied by each Contractor.
C. All training shall take place at the work site at a place specified by the City and
shall be conducted by factory trained and certified manufacturer’s representatives.
E. The Contractor shall deliver all training material to the Engineer and the City with
a minimum of fourteen (14) days prior to the scheduled training.
for each item of equipment specified unless otherwise specified in the Detailed
Specifications, to prepare training scripts and to participate in video recording of
training.
B. The Contractor shall submit to the Engineer, for approval, the training scripts for
video recording. After final approval by the Engineer, the Contractor with the
certified manufacturer’s representative shall conduct video recording of the
classroom and field training sessions. The Contractor shall edit the videorecorded
material to remove dead air time, conversations, remarks and non-pertinent
material to the training. The Contractor shall then submit, for approval by the
Engineer, the unedited and edited videorecorded training sessions to ensure no
important material is lost.
C. Videorecorded training sessions shall include title of the session, date, location,
trainer name, equipment covered and manufacturer, and shall incorporate any
visuals (i.e. drawings, slides, etc.) and/or other training aids used during personnel
training.
D. The Contractor shall provide the City with one (1) unedited and one (1) edited
copy of the videorecorded training in a mini-DV digital format. In addition, the
Contractor shall provide four (4) copies of the edited material in DVD format.
The Contractor shall deliver the copies within six weeks after the scheduled
training session. The City shall have the right to permanent ownership and use of
the copies.
E. The videorecorded training shall be considered “work made for hire” under
applicable provisions of the Copyright Act, and the City shall be the copyright
owner thereof and of all aspects, elements and components thereof in which
copyright protection might subsist. To the extent that such materials do not
qualify as “work made for hire”, the Contractor hereby irrevocably transfers,
assigns and conveys exclusive copyright ownership in and to such materials to the
City, free and clear of any liens, claims or other encumbrances. The agreement
between the Contractor and the person video recording shall contain a provision
containing these requirements.
01821-4 11/2017
1728
DETAILED SPECIFICATION 01821 – EQUIPMENT START-UP AND TRAINING
CONTRACT DEL-260 G, H, E
A. The Contractor shall submit the equipment manufacturer's lesson plans, which
shall include specific information about each item of equipment. Lesson plans
shall include but not be limited to the following information and meet the
following requirements:
1. The Contractor shall submit for approval by the Engineer, the equipment
manufacturer's lesson plans in no less than sixty (60) days prior to the date
that the training is to take place. Lesson plans shall be approved before
scheduling the training.
2. Lesson plans shall indicate the training audience that the instruction is to
address and estimated duration of each segment of the training. The
training audience refers to City’s operation and maintenance personnel.
3. Lesson plans shall indicate when training aids are used or referred to
during the course of instruction.
5. Lesson plans shall include but not be limited to the following topic areas:
Training Session Overview, Detailed Equipment Description, Equipment
Operation, Equipment Monitoring, Troubleshooting, Safety and
Housekeeping, O&M Manual Use, Preventive Maintenance Requirements,
Maintenance Inspection Program, Maintenance Troubleshooting,
Equipment Disassembly and Assembly, Equipment Calibration, and an
Assessment of Training Effectiveness.
3. Determine what information the personnel being trained would like to take
away from the session.
01821-5 11/2017
1729
DETAILED SPECIFICATION 01821 – EQUIPMENT START-UP AND TRAINING
CONTRACT DEL-260 G, H, E
G. Safety and Housekeeping: Training for the Safety and Housekeeping shall include
the following:
2. Safe practices.
4. Housekeeping practices.
3. Inspection procedures.
4. Problem identification.
01821-8 11/2017
1732
DETAILED SPECIFICATION 01821 – EQUIPMENT START-UP AND TRAINING
CONTRACT DEL-260 G, H, E
A. Training aids shall be used as an integral part of the training program. Training
aids shall include text and/or pictorial handouts specific to the equipment
supplied. Handouts shall be legible and printed on good quality stock. Handouts
shall be submitted when lesson plans are submitted.
B. Additional training aids shall be used for maximum training effectiveness and
shall include the following as appropriate:
2. Models and samples, for example, cutaways, spare parts, tools, miniature
models, equipment assemblies, and damaged parts.
C. The use of additional training aids shall be identified in the lesson plans, and a
description of the additional training aids shall be given.
A. The Contractor shall submit the qualifications of their proposed factory trained
and certified manufacturer’s representatives for approval by the Engineer sixty
(60) days prior to the date of proposed training. The documentation shall include
the experience of the manufacturer’s representative in operation and maintenance
of the equipment and a summary of training experience.
01821-9 11/2017
1733
DETAILED SPECIFICATION 01821 – EQUIPMENT START-UP AND TRAINING
CONTRACT DEL-260 G, H, E
1.11 ATTACHMENTS
END OF SECTION
01821-10 11/2017
1734
ATTACHMENTS - DETAILED SPECIFICATION 01821 CONTRACT DEL-260 G, H, E
Schedule 01821-1 – Minimum Installation, Inspection, Testing and Initial Operation Manufacturer Services
Type of Service
Equipment Installation & Preliminary and/or Final Startup & Initial
Total # of
Spec # Equipment Inspection Field Tests* Operating Period
Days
# of Duration Total # of Duration Total # of Duration Total
Visits (days) Days Visits (days) Days Visits (days) Days
13862H Non-Metallic Ductwork 1 1 1 1 1 1 0 0 0 2
15060H Hangers and Supports 1 1 1 2 2 4 0 0 0 5
15185H Hydronic Pumps 1 1 1 1 1 1 0 0 0 2
15515H Piping and Motorized Valve 1 1 1 1 1 1 0 0 0 2
Heating and Ventilating
15720H 1 1 1 1 1 1 1 1 1 3
Units
15761H Electric Heaters 1 1 1 1 1 1 0 0 0 2
Ductwork and Duct
15810H 1 1 1 1 1 1 0 0 0 2
Accessories
15830H Fans 1 1 1 1 1 1 1 1 1 3
HVAC Monitoring and
15950H 1 5 5 5 1 5 2 1 2 12
Control System
16061E Grounding 0 0 0 4 1 4 0 0 0 4
16121E Electrical Wires and Cables 0 0 0 4 1 4 0 0 0 4
16131E Electrical Conduit System 0 0 0 4 1 4 0 0 0 4
16221E Electrical Motors 2 2 4 2 2 4 2 1 2 10
16221G Electrical Motors 2 2 4 2 2 4 2 1 2 10
16231E Standby Power 2 2 4 2 2 4 2 1 2 10
16271E Dry Type Transformer 0 0 0 4 1 4 2 1 2 6
Power Distribution System
16292E 0 0 0 4 1 4 0 0 0 4
Coordination
Medium Voltage Load
16361E 0 0 0 4 1 4 0 0 0 4
Interrupter Switch
16430E Low Voltage Switchgear 2 2 4 2 2 4 2 2 4 12
16442E Electric Control Equipment 0 0 0 4 1 4 0 0 0 4
16482E Motor Control center 4 1 4 2 2 4 2 1 2 10
Lighting Fixtures and
16511E 0 0 0 4 1 4 0 0 0 4
Devices
16496E Automatic Transfer 1 3 3 1 2 2 1 1 1 6
PAGE 1 OF 4 11/2017
1735
ATTACHMENTS - DETAILED SPECIFICATION 01821 CONTRACT DEL-260 G, H, E
Schedule 01821-1 – Minimum Installation, Inspection, Testing and Initial Operation Manufacturer Services
Type of Service
Equipment Installation & Preliminary and/or Final Startup & Initial
Total # of
Spec # Equipment Inspection Field Tests* Operating Period
Days
# of Duration Total # of Duration Total # of Duration Total
Visits (days) Days Visits (days) Days Visits (days) Days
Switches
TOTALS 36 70 15 121
PAGE 2 OF 4 11/2017
1736
ATTACHMENTS - DETAILED SPECIFICATION 01821 –
CONTRACT DEL-260 G, H, E
Type of Service
Training
Spec # Equipment
Duration
# of Visits Total Days
(days)
13862H Non-Metallic Ductwork 1 1 1
15185H Hydronic Pumps 1 1 1
15515H Motorized Valves 1 1 1
15720H Heating and Ventilating Units 1 1 1
15761H Electric Heaters 1 1 1
15810H Ductwork and Duct Accessories 1 1 1
15830H Fans 1 1 1
HVAC Monitoring and Control
15950H 1 2 2
System
16231E Standby Power System 1 1 1
16430E Low Voltage Switchgear 1 2 2
Medium Voltage Load Interrupter
16444E 1 2 2
Switch
16482E Motor Control center 1 2 2
16496E Automatic Transfer Switches 1 2 2
16511E Lighting Fixtures and Devices 1 1 1
TOTAL 19
PAGE 3 OF 4 11/2017
1737
ATTACHMENTS - DETAILED SPECIFICATION 01821 –
CONTRACT DEL-260 G, H, E
PAGE 4 OF 4 11/2017
1738
DETAILED SPECIFICATION 01831 - OPERATION AND MAINTENANCE
MANUALS
CONTRACT DEL-260 G, H, E
SECTION 01831
Operation and Maintenance Manuals
PART 1 GENERAL
C. Submittals
A. The Contractor shall prepare, submit and obtain the Engineer’s approval, as designated
by “Furnish as Submitted” of an Manual for each item of equipment supplied under
this Contract. Approval is a prerequisite for continuing payments for equipment
furnished by the Contractor, providing instructional services and equipment start-up.
B. Each Manual shall be prepared especially for each installation and shall include all
pertinent and legible instructions, technical bulletins and other printed matter required
to provide fully accurate and comprehensive information for the safe and proper
operation, maintenance and repair of the equipment item.
A. The O&M Manuals shall include, but not be limited to the following:
3. On a separate page, list names, addresses and telephone numbers of the three (3)
nearest suppliers and manufacturers, including local source (if applicable), of
supplies and replacement parts.
01831-1 11/2017
1739
DETAILED SPECIFICATION 01831 - OPERATION AND MAINTENANCE
MANUALS
CONTRACT DEL-260 G, H, E
6. Drawings, diagrams and illustrations shall be black on white, and clearly legible.
Up to 11” x 17” shall be bound into the manual. Larger size documents shall be
folded and inserted into clear plastic pockets or envelops bound into the manual
and marked as to contents.
C. Equipment parts shall be identified by manufacturer’s part number and located with
relation to other components of the equipment utilizing “exploded” type drawings for
clarity, if required. Complete parts lists shall be included, which indicate the part
number, the part description, applicable serial and model numbers, current unit prices
and the name, address and telephone number of the nearest equipment manufacturer’s
representative and nearest service and spare parts warehouse. Complete instructions for
the ordering of all replaceable parts shall be noted in this section of the Manual.
Recommendations as to spare parts and spare inventory levels shall be made. Where
pertinent, lead time and shelf life values and preservation, packaging and labeling
methods shall be also recommended.
D. All copyrighted material used in the Manual or in any operation required in the
performance of the Contract will be preceded by the Contractor obtaining the copyright
holder’s written permission to use such material. The Contractor shall hold the City
and the Engineer free of any legal responsibility for its use.
A. The Contractor shall provide each O&M Manual in paper and electronic form.
B. For the paper form each O&M Manual shall meet the following requirements:
1. The O&M Manual shall be bound in a durable, permanent, hard cover binder of
one (1) (more if required) volume. Binders shall be of the three-ring type or three
post type and shall not be overfilled. Covers shall be oil, moisture and wear
resistant. The content of the manual shall be printed on 8-1/2 by 11 inches 30
pound (minimum) paper and biding holes shall be reinforced with plastic, cloth or
01831-2 11/2017
1740
DETAILED SPECIFICATION 01831 - OPERATION AND MAINTENANCE
MANUALS
CONTRACT DEL-260 G, H, E
metal.
2. All contents shall be original quality copies. That is, the material shall either be
original manufacturer printed or typed materials or xerographic copies that are
indistinguishable from the original. O&M Manuals that contain copies that are not
clear, not completely legible, off-center, skewed, or where text or drawings are cut
by the binding holes shall be subjected to disapproval. Pages that contain approval
or date stamps, comments, or other markings that cover any portion of text or
drawing are unacceptable. Electronically transmitted facsimile (fax) copies are also
unacceptable.
3. Each volume shall have a complete index of the O&M Manual's contents
organized into sections or categories of information such as operating instructions,
preventive maintenance, drawings, and parts list. Dividers and indexes tabs shall
be used to separate sections. The index shall indicate the title of each section and a
complete listing of the contents of each section in order of presentation within the
section. Applicable equipment item numbers, as shown in the Contract
Documents shall be prominently included at their appropriate location in the index.
The title of the Manual shall be securely affixed to the binder in two places: the
front cover and the binder back edge. The title shall identify the Project by number
and name, location of the Site, state the volume is an O&M Manual, generally
classify the equipment and state the manufacturer's name and equipment model
number.
C. For the electronic form each O&M Manual shall be scanned into separate Adobe
Acrobat “PDF” files using a minimum scan resolution of 300 dpi (dots per inch) not to
exceed 400 dpi. The file name of each scanned O&M Manual file shall be the
corresponding equipment number with a pdf extension. Each O&M Manual shall
consist of multiple files arranged as per the index with search capability and shall
include all the information, drawings and content of the Manual paper form.
D. Intermediate submittals, for approval by the Engineer, of the paper form of the Manual
need not be hard bound.
E. After an O&M Manual submittal receives final approval status, signified by the
annotation “Furnish as Submitted”, the Contractor shall furnish five (5) paper copies and
six (6) electronic copies of the Manual on a CD-ROM in Adobe PDF format to the
Engineer. In preparing the electronic copies of the O&M Manuals, the Contractor shall
make every reasonable effort to obtain from the originator (i.e., manufacturer) the
documents in their original electronic format and incorporate these in the Manuals.
Subject to the approval of the Engineer, documents shall be scanned from a paper
version only when the Contractor cannot obtain the electronic version from the
originator (i.e., manufacturer).
01831-3 11/2017
1741
DETAILED SPECIFICATION 01831 - OPERATION AND MAINTENANCE
MANUALS
CONTRACT DEL-260 G, H, E
G. The City shall have the right to permanent ownership and unlimited license to reproduce
and use, for internal purposes, the approved O&M Manual.
1.05 SUBMITTALS
A. The Contractor’s submittal to the Engineer for approval shall consist of three (3)
complete sets of each O&M Manual and three (3) copies of an itemized listing providing
cross reference identification between the Specification sections of the Contract
Documents, the approved Shop Drawings, and the O&M Manual submittal.
B. A transmittal will be returned to the Contractor indicating the status of the Manual and
will include a tabulation of any pages being returned with review comments and noting
any extra pages required to clarify or amplify the comments. Copies of only the pages
containing comments and any additional pages needed to clarify or amplify the
comments will be attached to the transmittal. The status of the Manual will be noted on
the front page of the Manual, which will also be attached to the transmittal, and will be
stamped either, “Furnish as Submitted”; “Furnish as Corrected”, when the Manual
submittal substantially conforms to the requirements of this Section and requires minor
corrections; or “Revise and Resubmit”, when the Manual submittal is considered
inadequate, inaccurate or lacking essential information.
C. The Contractor shall rectify all submittals annotated “Furnish as Corrected” or “Revise
and Resubmit” within 15 days of receipt of such notice by replacing pages or adding
additional data, as required. The Manual's Index of Contents and the itemized, cross-
referenced listing shall be revised to reflect all revisions or additions made. Then, three
copies of the revised material shall be resubmitted to the Engineer for approval.
D. When the status of the Manual is stamped “Rejected”, a transmittal to the Contractor
will return the copies of the Manual intact with the reason for the rejection stated. The
Manual will be stamped "Rejected" when the submittal is considered illegible, or does
not contain a complete index of contents and/or an itemized list of cross references, or is
so incomplete and lacking in required documentation as to preclude a meaningful review
by the Engineer. Within fifteen (15) days of receipt of such notice the Contractor shall
revise the Manual and resubmit to the Engineer for approval.
E. After the O&M Manual receives final approval the Contractor shall submit, for approval
by the Engineer, the electronic form which will be reviewed for conformation to the
requirements of this Section. A transmittal with review comments and stamped either,
“Furnish as Submitted”; “Furnish as Corrected” or “Revise and Resubmit” will be
returned to the Contractor. The Contractor shall rectify all submittals annotated “Furnish
as Corrected” or “Revise and Resubmit” within fifteen (15) days of receipt of such
notice. The revised material shall be resubmitted to the Engineer for approval.
01831-4 11/2017
1742
DETAILED SPECIFICATION 01831 - OPERATION AND MAINTENANCE
MANUALS
CONTRACT DEL-260 G, H, E
END OF SECTION
01831-5 11/2017
1743
DETAILED SPECIFICATION 01831 - OPERATION AND MAINTENANCE
MANUALS
CONTRACT DEL-260 G, H, E
01831-6 11/2017
1744
DETAILED SPECIFICATION 02105G – SOIL SAMPLING AND ANALYSIS
CONTRACT DEL-260G
SECTION 02105G
Soil Sampling and Analysis
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02105 – Soil Sampling and Analysis except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
Replace Paragraph 1.02.A with the following:
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
D. Soil samples were taken in the proposed work area on March 24 and 25, 2016.
Laboratory analytical results for these soil samples indicated that there were no
results identified with concentrations that exceed RCRA and NYSDEC regulatory
standards.
END OF SECTION
02105G-1 11/2017
1745
DETAILED SPECIFICATION 02105 – SOIL SAMPLING AND ANALYSIS
CONTRACT DEL-260G
02105G-2 10/2017
1746
DETAILED SPECIFICATION 02222G – DEMOLITION AND REMOVALS
CONTRACT DEL-260 G
SECTION 02222G
Demolition and Removals
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02222 - Demolition and Removals except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
02222G-1 11/2017
1747
DETAILED SPECIFICATION 02222G – DEMOLITION AND REMOVALS
CONTRACT DEL-260 G
02222G-2 11/2017
1748
DETAILED SPECIFICATION 02230G – SITE CLEARING
CONTRACT DEL-260 G
SECTION 02230G
Site Clearing
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02230 – Site Clearing except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
02230G-1 11/2017
1749
DETAILED SPECIFICATION 02230G – SITE CLEARING
CONTRACT DEL-260 G
02230G-2 11/2017
1750
DETAILED SPECIFICATION 02316G – EXCAVATION
CONTRACT DEL-260G
SECTION 02316G
Excavation
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02316 - Excavation except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.05 DEFINITIONS
Replace Paragraph 1.05.D with the following:
D. Excavated Material: All material regardless of its nature, except rock or boulders that
have been excavated.
PART 3 EXECUTION
02316G-1 11/2017
1751
DETAILED SPECIFICATION 02316G – EXCAVATION
CONTRACT DEL-260G
END OF SECTION
02316G-2 11/2017
1752
DETAILED SPECIFICATION 02317G – BACKFILLING
CONTRACT DEL-260 G
SECTION 02317G
Backfilling
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02317 - Backfilling except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
02317G-1 11/2017
1753
DETAILED SPECIFICATION 02317G – BACKFILLING
CONTRACT DEL-260 G
02317G-2 11/2017
1754
DETAILED SPECIFICATION 02371G – DUST, SOIL EROSION AND
SEDIMENTATION CONTROL
CONTRACT DEL-260 G
SECTION 02371G
Dust, Soil Erosion and Sedimentation Control
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02371 – Dust, Soil Erosion and Sedimentation Control except as
modified herein.
PART 1 GENERAL
Delete 1.02.C and renumber 1.02.D with 1.02.C, and 1.02.E with 1.02.D
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
02371G-1 11/2017
1755
DETAILED SPECIFICATION 02371G – DUST, SOIL EROSION AND
SEDIMENTATION CONTROL
CONTRACT DEL-260 G
02371G-2 11/2017
1756
DETAILED SPECIFICATION 02481G – FOOTINGS, FOUNDATION PIERS AND
FOUNDATION WALLS
CONTRACT DEL-260 G
SECTION 02481G
Footings, Foundation Piers and Foundation Walls
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02481 – Footings, Foundation Piers and Foundation Walls except as
modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 3 EXECUTION
02481G-1 11/2017
1757
DETAILED SPECIFICATION 02481G – FOOTINGS, FOUNDATION PIERS AND
FOUNDATION WALLS
CONTRACT DEL-260 G
END OF SECTION
02481G-2 11/2017
1758
DETAILED SPECIFICATION 02505G - LEAKAGE TESTS
CONTRACT DEL-260 G
SECTION 02505G
Leakage Tests
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02505 – Leakage Tests except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
Replace Paragraph 1.02.A with the following:
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
02505G-1 11/2017
1759
DETAILED SPECIFICATION 02505G - LEAKAGE TESTS
CONTRACT DEL-260 G
02505G-2 11/2017
1760
DETAILED SPECIFICATION 02741G - ASPHALTIC CONCRETE PAVEMENTS
CONTRACT DEL-260 G
SECTION 02741G
Asphaltic Concrete Pavements
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02741 – Asphaltic Concrete Pavements except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
02741G-1 11/2017
1761
DETAILED SPECIFICATION 02741G - ASPHALTIC CONCRETE PAVEMENTS
CONTRACT DEL-260 G
02741G-2 11/2017
1762
DETAILED SPECIFICATION 02771G – CONCRETE CURBS, HEADERS AND
SIDEWALKS
CONTRACT DEL-260 G
SECTION 02771G
Concrete Curbs, Headers and Sidewalks
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02771 – Concrete Curbs, Headers and Sidewalks except as modified
herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
02771G-1 11/2017
1763
DETAILED SPECIFICATION 02771G – CONCRETE CURBS, HEADERS AND
SIDEWALKS
CONTRACT DEL-260 G
02771G-2 11/2017
1764
DETAILED SPECIFICATION 02910G – PLANTING
CONTRACT DEL-260G
SECTION 02910G
Planting
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02910 – Planting except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
02910G-1 11/2017
1765
DETAILED SPECIFICATION 02910G – PLANTING
CONTRACT DEL-260G
02910G-2 11/2017
1766
DETAILED SPECIFICATION 02920G – SOIL MIXES
CONTRACT DEL-260G
SECTION 02920G
Soil Mixes
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02920 – Soil Mixes except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
02920G-1 11/2017
1767
DETAILED SPECIFICATION 02920G – SOIL MIXES
CONTRACT DEL-260G
02920G-2 11/2017
1768
DETAILED SPECIFICATION 03100G – CONCRETE FORMWORK
CONTRACT DEL-260G
SECTION 03100G
Concrete Formwork
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 03100 – Concrete Formwork except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.04 REFERENCES
K. Southern Pine Inspection Bureau (SPIB): Standard Grading Rules for Southern Pine.
PART 2 PRODUCTS
2.02 LUMBER
C. Provide lumber free of material defects that would deform the finished concrete
product.
2.03 PLYWOOD
1769
DETAILED SPECIFICATION 03100G – CONCRETE FORMWORK
CONTRACT DEL-260G
G. Provide snap-off metal ties with ends that break at least 1-1/2-inches from the face of
the wall.
H. Removable ties that leave holes larger than 7/8-inches are not permitted.
I. Form ties fabricated on the Site and wire ties or flat bands are not acceptable.
PART 3 EXECUTION
3.01 PREPARATION
B. Earth cuts shall not be used as forms for vertical surfaces, unless shown on the
Contract Drawings.
S. Fabricate forms for easy removal without hammering or prying against concrete
surfaces.
END OF SECTION
03100G-2 11/2017
1770
DETAILED SPECIFICATION 03210G – REINFORCING STEEL
CONTRACT DEL-260G
SECTION 03210G
Reinforcing Steel
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 03210 – Reinforcing Steel except as modified herein.
PART 1 GENERAL
2. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract G-LS-1, as described in Detailed
Specification 01270 - Measurement and Payment.
1.07 SUBMITTALS
6. Two copies of test results conducted in accordance with the American Society for
Testing and Materials Specifications. Testing requirements may be waived,
based upon certified copies of mill test reports.
G. Protection: Protect in-place reinforcing from excessive construction traffic and other
work.
PART 3 EXECUTION
1771
DETAILED SPECIFICATION 03210G – REINFORCING STEEL
CONTRACT DEL-260G
END OF SECTION
03210G-2 11/2017
1772
DETAILED SPECIFICATION 03290G – JOINTS IN CONCRETE
CONTRACT DEL-260G
SECTION 03290G
Joints in Concrete
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 03290 – Joints In Concrete except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 - Measurement and Payment.
PART 2 PRODUCTS
Type IV only shall be used unless otherwise noted herein or on Contract Drawings.
END OF SECTION
03290G-1 11/2017
1773
DETAILED SPECIFICATION 03290G – JOINTS IN CONCRETE
CONTRACT DEL-260G
03290G-2 11/2017
1774
DETAILED SPECIFICATION 03300G – CAST-IN-PLACE CONCRETE
CONTRACT DEL-260G
SECTION 03300G
Cast-In-Place Concrete
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 03300 – Cast-in-Place Concrete except as modified herein.
PART 1 GENERAL
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.04 REFERENCES
37. ASTM C 156 - Test Method for Water Retention by Concrete Curing Materials.
38. ASTM C 1751 - Specification for Preformed Expansion Joint Filler for Concrete
Paving and Structural Construction (Non-extruding and Resilient Bituminous
Types.)
7. Where concrete strengths are specified in Contract Drawings, use those values in
lieu of strengths shown in Table 1.
1.07 SUBMITTALS
03300G-1 11/2017
1775
DETAILED SPECIFICATION 03300G – CAST-IN-PLACE CONCRETE
CONTRACT DEL-260G
G. Design Mix: Prior to production of concrete, submit for approval proposed mix
designs for each concrete class, including lightweight concrete, cellular concrete,
concrete for Consolidated Edison structures, and for each change of ingredients and
ingredient sources and admixtures. Mix designs shall be based on requirements of
ACI 318, ACI 301 and other relevant ACI standards. Make adjustments to the
proposed mix designs as directed by the Engineer. Such adjustments shall be at no
additional cost to the City.
H. Certificates for Concrete: Furnish to the Engineer and local authorities requiring same,
certificates originated by the batch mixing plant certifying ready mixed concrete, as
manufactured and delivered, to be in conformance with ASTM C 94.
I. Certificates for Aggregate: Furnish to the Engineer a certificate obtained from the
aggregate producer certifying that the entire quantity of aggregate shipped for this
project is in conformance with the requirements of NYSDOT Standard Specifications.
J. Delivery Tickets: A delivery ticket shall accompany each load of concrete from the
patch plant.
PART 2 PRODUCTS
1. Portland Cement: ASTM C 150, Type II; or blended hydraulic cement, ASTM C
595, Type 1P (MS); or Type I, Normal. Only one brand and manufacturer of
approved cement shall be used for concrete.
K. Air Entraining: Air-entrain all concrete. Total air content of concrete shall be as
follows:
03300G-2 11/2017
1776
DETAILED SPECIFICATION 03300G – CAST-IN-PLACE CONCRETE
CONTRACT DEL-260G
L.
Maximum-size coarse Air content
Aggregate, In. Percent by volume
1-1/2 5 +/- 1
3/4 or 1 6 +/- 1
3/8 or 1/2 7-1/2 +/- 1
G. Unit weight of lightweight concrete shall not exceed 115 pounds per cubic foot.
10. All concrete mix designs shall be based on New York City Building Code
Method II, unless noted otherwise in Contract Documents.
PART 3 EXECUTION
d. Increase the slump of concrete entering the pump as required to maintain the
specified slump at the point of placement. The change in slump shall be
achieved by the following requirements of Article 3.02.F of General
Specifications and this Detailed Specification.
2. In general, conduct concrete placement work in accordance with ACI 304 and
such additional requirements as specified herein.
3. Handle concrete from mixer to final deposit rapidly by methods which will
prevent segregation or loss of ingredients to maintain required quality of
concrete.
5. Do not place concrete by pumps or other similar devices without prior written
approval of Engineer.
I. Preparation:
1. Prepare formwork in advance and remove snow, ice, water and debris from
within forms. Formwork as specified in Detailed Specification 03100 – Concrete
Formwork.
2. Pre-position reinforcement in advance of concrete pours. Provide concrete
reinforcement as specified in Detailed Specification 03210G – Reinforcing Steel.
3. Do not place concrete on frozen surfaces.
J. Consolidation:
03300G-4 11/2017
1778
DETAILED SPECIFICATION 03300G – CAST-IN-PLACE CONCRETE
CONTRACT DEL-260G
D. Concrete Quality
1. The Contractor shall use Class A – 4,000 psi concrete for all concrete work
2. Selection of Proportions for NORMAL WEIGHT Concrete: ACI 211.1.
3. Proportions of Ingredients: Establish proportions, including water cement ratio on
the basis of field experience, with the materials specified herein.
4. Water-Cement Ratio: Maximum water cement ration of 0.50.
5. Classes of Concrete:
a. Class A: 4,000 psi minimum compressive strength at 28 days; 564 pounds
per cubic yard minimum cement content.
F. Form Tie Repairs: Following form removal repair holes vacated by removable
components of form ties in accordance with the following:
1. Hammer-pack holes with stiff mortar of same mix and ingredients as used in
surrounding concrete. Prepare mortar no more than 30 minutes prior to use.
2. Render mortar patch work inconspicuous. Keep mortar patches damp and cure in
accordance with requirements for curing and protection.
END OF SECTION
03300G-5 11/2017
1779
DETAILED SPECIFICATION 03300G – CAST-IN-PLACE CONCRETE
CONTRACT DEL-260G
03300G-6 11/2017
1780
DETAILED SPECIFICATION 03350G – CONCRETE FINISHES
CONTRACT DEL-260G
SECTION 03350G
Concrete Finishes
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 03350 – Concrete Finishes except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
B. The mock-up wall panel shall be structural lightweight concrete, 12 inches thick.
Reinforcing shall be stainless bars, #4@12” on center (o.c.), each way, each face.
PART 3 EXECUTION
A. After removal of forms, the finishes described below shall be applied in accordance
with Article 3.05 - Concrete Finish Schedule. All surfaces shall receive at least a
Type I finish. The Engineer shall be the sole judge of acceptability of all concrete
finish work.
1. Type I - Rough or Board Form Finish: All fins, burrs and other projections left by
the forms shall be removed. All holes left by removal of ties, and all other holes,
depressions, or voids shall be filled solid with cement grout after first being
thoroughly wetted. Honeycombs shall be chipped back to solid concrete as
directed, prior to patching with cement grout. Holes shall be filled with a small
tool that will permit packing the hole solidly with cement grout. Cement grout
shall consist of one part cement to three parts sand, and the amount of mixing
water shall be as little as consistent with the requirements of handling and
placing. Color of cement grout shall match the adjacent wall surface. The
03350G-1 11/2017
1781
DETAILED SPECIFICATION 03350G – CONCRETE FINISHES
CONTRACT DEL-260G
1782
DETAILED SPECIFICATION 03350G – CONCRETE FINISHES
CONTRACT DEL-260G
mortar is removed and the aggregate is uniformly exposed. Then rinse the
surface with clear water. If portions of the surface have become too hard to
permit uniform aggregate exposure, use dilute hydrochloric acid (one part
commercial muriatic acid diluted with 4 to 10 parts water) to remove the
excess surface mortar after the concrete is at least 2 weeks old. Remove the
acid from the finished surface with clean water within 15 minutes after
application.
b. For a blast finish, sandblast or waterblast the concrete surface to a degree
sufficient to expose fine aggregates with occasional exposure of coarse
aggregate, and to produce a uniform color with a maximum reveal of 1/16
inch unless specified otherwise in the Contract Documents. All surfaces
with the same specified blast finish shall be done at approximately the same
time after placing co concrete. Use stainless steel or plastic reinforcement
supports and spacers near concrete surfaces to be blasted. Protect adjacent
materials and inserts during blasting operations.
c. For a tooled finish, dress the thoroughly cured concrete surface with electric,
air, or hand tools to a uniform texture removing surface mortar as specified
in the Contract Documents. Then provide the surface with a hand tooled,
rough or fine pointed, crandalled, or bush-hammered surface texture, as
specified by Contract Documents.
8. Type VIII - Applied: When finishes of stucco, cementitious coatings, or similar
troweled materials are required or permitted, prepare the surface of the concrete
to ensure permanent adhesion of the finish. If the concrete is less than 24 hours
old, roughen it with a heavy wire brush or scoring too. If the concrete is older,
roughen the surface mechanically or by acid etching. After roughening, wash the
surface free of all dust, acid, chemical retarder, and other foreign material before
any final finish is applied.
END OF SECTION
03350G-3 11/2017
1783
DETAILED SPECIFICATION 03350G – CONCRETE FINISHES
CONTRACT DEL-260G
03350G-4 11/2017
1784
DETAILED SPECIFICATION 03600G – GROUT
CONTRACT DEL-260G
SECTION 03600G
Grout
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 03600 – Grout except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
03600G-1 11/2017
1785
DETAILED SPECIFICATION 03600G – GROUT
CONTRACT DEL-260G
03600G-2 11/2017
1786
DETAILED SPECIFICATION 03931G – CONCRETE REHABILITATION
CONTRACT DEL-260G
SECTION 03931G
Concrete Rehabilitation
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 03931 – Concrete Rehabilitation except as modified herein.
PART 1 GENERAL
3. Concrete rehabilitation work for this project shall include concrete structural crack
repair and concrete spall repair.
B. Payment:
1. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 3 EXECUTION
A. Repair areas shall be saw-cut to a 1” depth around the perimeter of each repair area
prior to the removal of deteriorated concrete.
B. All loose and disintegrated concrete shall be removed from areas to be repaired in such
a manner and to such an extent as to expose a sound concrete surface. Once sound
concrete (concrete beneath the deteriorated concrete) is reached, Contractor shall also
remove a minimum of ¼ inch of the sound, non-deteriorated concrete. Remaining
concrete shall be brush cleaned and roughened by sandblasting.. The work shall be
done in such a manner as not to damage the concrete that is to remain.
C. Only pneumatic or hand tools shall be used in the removal of the disintegrated material
and in preparation and shaping the areas to be repaired. The weight of the tools used
for concrete removal shall not exceed 30 pounds.
03931G-1 11/2017
1787
DETAILED SPECIFICATION 03931G – CONCRETE REHABILITATION
CONTRACT DEL-260G
E. Where corroded reinforcing bars are uncovered, those bars shall be cleaned by
sandblasting, waterblasting, or wire brushing. Where the bond between existing
concrete and reinforcing steel has been destroyed, or where the steel is exposed, the
concrete adjacent to the bar shall be removed to provide ½” clearance around the bar.
END OF SECTION
03931G-2 11/2017
1788
DETAILED SPECIFICATION 04051G – MORTAR AND MASONRY GROUT
CONTRACT DEL-260G
SECTION 04051G
Mortar and Masonry Grout
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 04051 – Mortar and Masonry Grout except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Acceptable manufacturers
1. Lehigh Cement Co., Irving, TX
2. The Sakrete Co., Calverton, NY
3. Or approved equal.
2.03 MIXES
A. Mortar: Provide mortar that conforms to the requirements of ASTM C270, except
as modified herein, and of the type and color to match existing adjacent wall.
1. Provide a cement-lime mortar. Masonry cement mortars are not acceptable.
2. Calcium chlorides are not permitted.
3. Admixtures shall not be used unless specifically directed.
4. Masonry Pointing, provide mortar that conforms to the requirements of
ASTM C270, and of the type and color to match existing condition.
04051G-1 11/2017
1789
DETAILED SPECIFICATION 04051G – MORTAR AND MASONRY GROUT
CONTRACT DEL-260G
B. Grout:
1. Fine Grout: Fine grout shall be used for filling spaces with
openings less than 2 inches.
2. Coarse Grout: Course grout shall be used for filling spaces with
openings greater than 2 inches.
C. Fire-Resistant Mortar:
04051G-2 11/2017
1790
DETAILED SPECIFICATION 04051G – MORTAR AND MASONRY GROUT
CONTRACT DEL-260G
2. Use 1 part Portland cement, 3 parts clean sand, and 15 percent hydrated
lime (by cement volume).
D. Mortar for All Locations. Comply with ASTM C270, Table 2, except limit
materials to those specified herein. Do not substitute ASTM C91 masonry cement
for ASTM C150 portland cement without an approved Shop Drawing and a
complete chemical analysis of the material and its properties. Limit cement-to-
lime ratio by volume as follows:
1. Type M:
a. Provide the following proportions by volume:
b. Properties:
2. Type S:
a. Provide the following proportions by volume:
b. Properties:
1791
DETAILED SPECIFICATION 04051G – MORTAR AND MASONRY GROUT
CONTRACT DEL-260G
3. Type N:
a. Provide the following proportions by volume:
1) Portland Cement: 1 part.
2) Hydrated Lime or Lime Putty: Over 1/2 to 1 1/4
maximum.
3) Aggregate Ratio (measured in damp loose condition):
Not less than 2-1/4 and not more than 3 times the sum of
the volumes of cementitious materials.
b. Properties:
1) Average Compressive Strength, ASTM C270: 750 pounds
per square inch.
2.04 MIXING
END OF SECTION
04051G-4 11/2017
1792
DETAILED SPECIFICATION 04200G – UNIT MASONRY
CONTRACT DEL-260G
SECTION 04200G
Unit Masonry
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 04200 – Unit Masonry except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
I. Brick size, texture, color and bond run will match adjacent wall. Mortar joint size,
finish, color and strike type will match adjacent wall. This includes all masonry
repair and new walls.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Acceptable Manufacturers
1. Belden Brick Co., Canton, OH
2. Old Castle, Red Bank, NJ
3. Approved equal.
2.02 MATERIALS
B. Structural Glazed Brick: Structural glazed brick shall meet the requirements of
ASTM C126 for finish properties and shall conform to ASTM C216 Grade SW
Type FBX for durability. Structural glazed brick shall meet UL requirements for
04200G-1 11/2017
1793
DETAILED SPECIFICATION 04200G – UNIT MASONRY
CONTRACT DEL-260G
zero flame spread and zero smoke developed. Face dimensions and custom colors
shall match existing adjacent material.
D. Glazed Structural Tile: Glazed structural facing tile shall be of Selected Size
Quality (Grade SS ground ends) in size to match existing, and shall conform to
the requirements of ASTM C126, Type I. Glazed structural tile walls and
partitions shall be provided with bullnose shapes for external corners, sills, and
jambs, and shall have coved base courses.
N. Weep Vents: Weep vents shall be provided where shown, and shall be an offset
T-shaped vent injection molded from flexible polyvinyl chloride. The vents shall
be provided in a custom size and color to match existing brick and mortar.
PART 3 EXECUTION
3.01 INSTALLATION
1. Bond: New brickwork should be laid the same way as existing brickwork on the
adjacent wall.
END OF SECTION
04200G-2 11/2017
1794
DETAILED SPECIFICATION 05061G- STAINLESS STEEL WORK
CONTRACT DEL-260G
SECTION 05061G
Stainless Steel Work
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05061 – Stainless Steel Work except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
05061G-1 11/2017
1795
DETAILED SPECIFICATION 05061G- STAINLESS STEEL WORK
CONTRACT DEL-260G
05061G-2 11/2017
1796
DETAILED SPECIFICATION 05081G– GALVANIZING
CONTRACT DEL-260 G
SECTION 05081G
Galvanizing
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05081-Galvanizing except as modified herein.
1.02 PAYMENT
Replace paragraph 1.02.A with the following:
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
05081G-1 11/2017
1797
DETAILED SPECIFICATION 05081G– GALVANIZING
CONTRACT DEL-260 G
05081G-2 11/2017
1798
DETAILED SPECIFICATION 05091G- WELDING
CONTRACT DEL-260G
SECTION 05091G
Welding
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05091-Welding except as modified herein.
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
05091G-1 11/2017
1799
DETAILED SPECIFICATION 05091G- WELDING
CONTRACT DEL-260G
05091G-2 11/2017
1800
DETAILED SPECIFICATION 05092G – METAL FASTENING
CONTRACT DEL-260G
SECTION 05092G
Metal Fastening
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05092 - Metal Fastening except as modified herein.
Add the following after paragraph 1.06 – DELIVERY, STORAGE AND HANDLING:
1.07 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
05092G-1 11/2017
1801
DETAILED SPECIFICATION 05092G – METAL FASTENING
CONTRACT DEL-260G
05092G-2 11/2017
1802
DETAILED SPECIFICATION 05120G- STRUCTURAL STEEL
CONTRACT DEL-260G
SECTION 05120G
Structural Steel
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05120-Structural Steel except as modified herein.
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
05120G-1 11/2017
1803
DETAILED SPECIFICATION 05120G- STRUCTURAL STEEL
CONTRACT DEL-260G
05120G-2 11/2017
1804
DETAILED SPECIFICATION 05501G- METAL FABRICATIONS
CONTRACT DEL-260G
SECTION 05501G
Metal Fabrications
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05501-Metal Fabrications except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
END OF SECTION
05501G-1 11/2017
1805
DETAILED SPECIFICATION 05501G- METAL FABRICATIONS
CONTRACT DEL-260G
05501G-2 11/2017
1806
DETAILED SPECIFICATION 05524G- ALUMINUM PIPE RAILING
CONTRACT DEL-260G
SECTION 05524G
Aluminum Pipe Railing
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05524-Aluminum Pipe Railing except as modified herein.
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
05524G-1 11/2017
1807
DETAILED SPECIFICATION 05524G- ALUMINUM PIPE RAILING
CONTRACT DEL-260G
05524G-2 11/2017
1808
DETAILED SPECIFICATION 05533G -ALUMINUM FLOOR GRATINGS
AND CHECKERED PLATES
CONTRACT DEL-260G
SECTION 05533G
Aluminum Floor Gratings and Checkered Plates
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05533-Aluminum Floor Gratings and Checkered Plates except as
modified herein.
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
05533G-1 11/2017
1809
DETAILED SPECIFICATION 05533G -ALUMINUM FLOOR GRATINGS
AND CHECKERED PLATES
CONTRACT DEL-260G
05533G-2 11/2017
1810
DETAILED SPECIFICATION 05561G – MISCELLANEOUS METAL CASTINGS
CONTRACT DEL-260G
SECTION 05561
Miscellaneous Metal Castings
NOTE: All work for this Section shall be in accordance with the requirements of General
Specification 05561-Miscellaneous Metal Castings except as modified herein.
1.03 PAYMENT
A. There shall be no separate payment for the work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
05561-1 11/2017
1811
DETAILED SPECIFICATION 05561G – MISCELLANEOUS METAL CASTINGS
CONTRACT DEL-260G
05561-2 11/2017
1812
DETAILED SPECIFICATION 06100G – ROUGH CARPENTRY
CONTRACT DEL-260G
SECTION 06100G
Rough Carpentry
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 06100 – Rough Carpentry except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
06100G-1 11/2017
1813
DETAILED SPECIFICATION 06100G – ROUGH CARPENTRY
CONTRACT DEL-260G
06100G-2 11/2017
1814
DETAILED SPECIFICATION 07811G – CEMENTITIOUS FIREPROOFING
CONTRACT DEL-260G
SECTION 07811G
Cementitious Fireproofing
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 07811 – Cementitious Fireproofing except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
PART 3 EXECUTION
END OF SECTION
07811G-1 11/2017
1815
DETAILED SPECIFICATION 07811G – CEMENTITIOUS FIREPROOFING
CONTRACT DEL-260G
07811G-2 11/2017
1816
DETAILED SPECIFICATION 07900G – CAULKING AND SEALANTS
CONTRACT DEL-260G
SECTION 07900G
Caulking and Sealants
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 07900 – Caulking and Sealants except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
07900G-1 11/2017
1817
DETAILED SPECIFICATION 07900G – CAULKING AND SEALANTS
CONTRACT DEL-260G
07900G-2 11/2017
1818
DETAILED SPECIFICATION 08110G – STEEL DOORS AND FRAMES
CONTRACT DEL-260G
SECTION 08110G
Steel Doors and Frames
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 08110 – Steel Doors and Frames except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
7. Louvers in doors
a. Louvers in fireproof doors shall be constructed of No. 18 gauge stainless
steel and shall be equipped with a fusible link and automatic mechanism
as approved by the New York City Building Department Bureau of
Standards and Appeals and finished to match face of door.
END OF SECTION
08110G-1 11/2017
1819
DETAILED SPECIFICATION 08110G – STEEL DOORS AND FRAMES
CONTRACT DEL-260G
08110G-2 11/2017
1820
DETAILED SPECIFICATION 08710G – FINISH HARDWARE
CONTRACT DEL-260G
SECTION 08710G
Finish Hardware
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 08710 – Finish Hardware except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.02 MATERIALS
PART 3 EXECUTION
3.06 SCHEDULES
08710G-1 11/2017
1821
DETAILED SPECIFICATION 08710G – FINISH HARDWARE
CONTRACT DEL-260G
END OF SECTION
08710G-2 11/2017
1822
DETAILED SPECIFICATION 09740G – CONCRETE TOPPING
CONTRACT DEL-260 G
SECTION 09740G
Concrete Topping
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 09740 – Concrete Topping except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
2. All material provided under this Section shall comply with the General
Specifications.
END OF SECTION
09740G-1 11/2017
1823
DETAILED SPECIFICATION 09740G – CONCRETE TOPPING
CONTRACT DEL-260 G
09740G-2 11/2017
1824
DETAILED SPECIFICATION 09900G – PAINTING
CONTRACT DEL-260G
SECTION 09900G
Painting
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 09900 – Painting except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
B. Manufacturer's Standard Finished Items: The following items shall be furnished with
the manufacturer's standard prime and finish coats applied in the shop: pumps,
motors, gears, gear housings, air compressors, wall fans, temperature control and
instrument panels, process air blowers, engines, filters, strainers, air dryers, meters,
gas boosters, gas turbines, generators, panelboards, transformers, boilers, condensing
units, water chillers, cooling towers, condensers, heat exchangers, humidifiers, air
handling units, sound attenuators, air conditioning and dehumidification units,
convector cabinets, unit heaters, enclosures for finned tube radiators, cabinet heaters,
boilers, wood seats, lockers, metal toilet partitions, metal urinal screens, aluminum
fascia, motor control centers, aluminum light standards, and hoisting equipment.
Steel reinforcing bars for concrete shall be coated in accordance with the Contract
Drawings. When powder coatings are required by the Contract Drawings, the
powder coatings shall be in accordance with the requirements of the manufacturer of
the item.
PART 2 PRODUCTS
2.03 MATERIALS
09900G-1 11/2017
1825
DETAILED SPECIFICATION 09900G – PAINTING
CONTRACT DEL-260G
CLASSIFICATION OF PAINTS
Dry Film
Paint Volume
Product Name and Number Thickness
Group Solids %
Mils per Coat
Sherwin Williams (Cleveland, OH): FIRETEX
69% 40.0*
FX5120
O
Carboline (St. Louis, MO): A/D Firefilm III 65% 30.0*
* Required DFT for specific fire rating is dependent on steel section and size. Consult
Representative.
09900G-1 11/2017
1826
DETAILED SPECIFICATION 09900G – PAINTING
CONTRACT DEL-260G
PART 3 EXECUTION
* Refer to UL N636 Beam Design for application thickness. Consult Sherwin-Williams Representative.
END OF SECTION
09900G-3 11/2017
1827
DETAILED SPECIFICATION 09900G – PAINTING
CONTRACT DEL-260G
09900G-4 11/2017
1828
DETAILED SPECIFICATION 10200G – LOUVERS
CONTRACT DEL-260G
SECTION 10200G
Louvers
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 10200 – Louvers except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
Replace paragraph 1.03.A with the following:
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.02 MATERIALS
Replace paragraph 2.02 with the following:
10200G-1 11/2017
1829
DETAILED SPECIFICATION 10200G – LOUVERS
CONTRACT DEL-260G
2. Manufacturer to submit test data on 4 feet x 4 feet louver units. Test data
shall show the following results at 948 fpm free area velocity.
B. Fixed Louver
1. Individual louver shall be Airolite, Penn Ventolator or approved equal, type
6096; fixed 43 degree, 6" deep stationary blade of the following
characteristics:
a. Frames and blades shall be stainless steel 316 alloy .064" thick.
b. Fasteners: Of same basic metal and alloy as fastened metal, unless
otherwise indicated. Do not use metals which are corrosive or
incompatible with materials joined.
1) Use types, gages and lengths to suit unit installation
conditions.
2) Use Philips flat-head machine screws for exposed fasteners
unless otherwise indicated.
c. Anchors and inserts of type, size and material required for type of
loading and installation indicated. Use Type 316 stainless steel
anchors and inserts for exterior installation and elsewhere as required
for corrosion resistance.
d. Bituminous Paint: SSPC-Paint 12 (cold-applied asphalt mastic).
2. Manufacturer to submit test data on 4 feet x 4 feet louver units. Test data
shall show the following results at 896 fpm free area velocity.
END OF SECTION
10200G-2 11/2017
1830
DETAILED SPECIFICATION 10400G– IDENTIFYING DEVICES
CONTRACT DEL-260G
SECTION 10400G
Identifying Devices
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 10400 – Identifying Devices except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
Replace paragraph 1.02.A with the following:
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.01 MANUFACTURERS
Add the following after paragraph 2.01.3.a
b. Or approved equal
2.02 MATERIALS
Replace paragraph 2.02.I with the following:
PART 3 EXECUTION
A. Identifying devices shall be installed where shown on the Contract Drawings and
where directed by DEP.
END OF SECTION
10400G-2 11/2017
1832
DETAILED SPECIFICATION 10521G – FIRE EXTINGUISHER
CONTRACT DEL-260G
SECTION 10521G
Fire Extinguisher
NOTE: All Work for this Section shall be in accordance with the requirements of
General Specification 10521 – Fire Extinguisher except as modified herein.
PART 1 GENERAL
1.04 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item G-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
END OF SECTION
10521G-1 11/2017
1833
DETAILED SPECIFICATION 10521G – FIRE EXTINGUISHER
CONTRACT DEL-260G
10521G-2 11/2017
1834
DETAILED SPECIFICATION 13281G – ASBESTOS MANAGEMENT
CONTRACT DEL-260G
SECTION 13281G
ASBESTOS MANAGEMENT
NOTE: All work for this Section shall be in accordance with the requirements of General
Specification 13281 – Asbestos Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. Except for abatement of unforeseen ACM and related Work payable under the
allowance, as described in Section 01355– Hazardous Materials Control, no
separate payment will be made for performing any Work required under this
Section and the Contractor shall include all costs thereof in its lump sum price bid
for Contract Item G-LS-1, as described in Detailed Specification 01270 –
Measurement and Payment.
END OF SECTION
13281G-1 11/2017
1835
DETAILED SPECIFICATION 13281G – ASBESTOS MANAGEMENT
CONTRACT DEL-260G
13281G-2 11/2017
1836
DETAILED SPECIFICATION 13282G – MERCURY MANAGEMENT
CONTRACT DEL-260G
SECTION 13282G
Mercury Management
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 13282 – Mercury Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
END OF SECTION
13282G-1 11/2017
1837
DETAILED SPECIFICATION 13282G – MERCURY MANAGEMENT
CONTRACT DEL-260G
13282G-2 11/2017
1838
DETAILED SPECIFICATION 13283G - LEAD MANAGEMENT
CONTRACT DEL-260G
SECTION 13283G
Lead Management
NOTE: All work for this Section shall be in accordance with the requirements of General
Specification 13283 – Lead Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. A.Except for unforeseen lead-containing materials and related work eligible for
payment under allowance, as described in Section 01355– Hazardous Materials
Control, no separate payment will be made for performing any work required
under this Section and the Contractor shall include all costs thereof in its lump
sum price bid for Contract Item G-LS-1, as described in Detailed Specification
01270 – Measurement and Payment.
END OF SECTION
13283G-1 11/2017
1839
DETAILED SPECIFICATION 13283G - LEAD MANAGEMENT
CONTRACT DEL-260G
13283G-2 11/2017
1840
DETAILED SPECIFICATION 13284G - PCB MANAGEMENT
CONTRACT DEL-260G
SECTION 13284G
PCB Management
NOTE: All work for this Section shall be in accordance with the requirements of General
Specification 13284 – PCB Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. Except for unforeseen PCB-containing materials and related work eligible for
payment under allowance, as described in Section 01355 – Hazardous Materials
Controls, no separate payment will be made for performing any work of this
Section and the Contractor shall include all costs thereof in its lump sum price bid
for Contract Item G-LS-1, as described in Detailed Specification 01270 –
Measurement and Payment.
END OF SECTION
13284G-1 11/2017
1841
DETAILED SPECIFICATION 13284G - PCB MANAGEMENT
CONTRACT DEL-260G
13284G-2 11/2017
1842
DETAILED SPECIFICATION 02222H – DEMOLITION AND REMOVALS
CONTRACT DEL-260H
SECTION 02222H
Demolition and Removals
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 02222 - Demolition and Removals except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
B. Permits: Obtain all permits from all appropriate regulatory agencies required for
closing or obstructing streets and sidewalks. Obtain all air permits as required for
demolition including a Demolition Permit from the Department of Buildings and a
DEP Registration for Demolition from the Department of Environmental Protection,
Bureau of Environmental Compliance.
02222H-1 11/2017
1843
DETAILED SPECIFICATION 02222H – DEMOLITION AND REMOVALS
CONTRACT DEL-260H
PART 3 EXECUTION
3.01 GENERAL
A. Pollution Controls: Use water sprinkling, temporary enclosures, and other suitable
methods to limit the amount of dust and dirt rising and scattering in the air to the
lowest practical level. Comply with all governing regulations pertaining to
environmental protection.
1. Do not use water when it may create hazardous or objectionable conditions
such as ice, flooding, and pollution.
2. Clean adjacent structures, facilities, and improvements of dust, dirt, and
debris caused by demolition operations. Return adjacent areas to conditions
existing prior to the start of the Work.
3. The use of calcium chloride for dust control will not be allowed.
P Dust Control: The Contractor is responsible for controlling visible dust caused by
demolition activities.
END OF SECTION
02222H-2 11/2017
1844
DETAILED SPECIFICATION 03600H – GROUT
CONTRACT DEL-260H
SECTION 03600H
Grout
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 03600 – Grout except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
Replace Paragraph 1.03.A with the following:
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the Allowance price bid for Contract Item H-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
A. Curing material for cement grout shall be as recommended by the manufacturer for
prepackaged grouts.
PART 3 EXECUTION
B. New concrete surfaces to receive cement grout shall be cleaned of all dirt and
grease and oil-like films.
1. Existing concrete surfaces shall likewise be cleaned of all similar
contamination and debris, for protection of cement grout.
END OF SECTION
03600H-1 11/2017
1845
DETAILED SPECIFICATION 03600H – GROUT
CONTRACT DEL-260H
03600H-2 11/2017
1846
DETAILED SPECIFICATION 04051H – MORTAR AND MASONRY GROUT
CONTRACT DEL-260H
SECTION 04051H
Mortar and Masonry Grout
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 04051 – Mortar and Masonry Grout except as modified herein.
PART 1 GENERAL
1.01 SUMMARY
B. The Contractor shall provide all labor, materials, equipment and incidentals, as shown,
specified and required to complete all Work as shown on the Contract Drawings or
specified herein. .
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Acceptable Manufacturers
1. Lehigh Cement Company, Allentown, PA.
2. The Sakrete Company, Cincinnati, OH.
3. Or approved equal.
2.03 MIXES
A. Mortar: Provide mortar that conforms to the requirements of ASTM C270, except
as modified herein, and of the type and color to match existing adjacent wall.
1. Provide a cement-lime mortar; masonry cement mortars are not acceptable.
04051H-1 11/2017
1847
DETAILED SPECIFICATION 04051H – MORTAR AND MASONRY GROUT
CONTRACT DEL-260H
B. Grout:
1. Fine Grout: Fine grout shall be used for filling spaces with openings
less than 2 inches.
2. Coarse Grout: Course grout shall be used for filling spaces with
openings greater than 2 inches.
C. Fire-Resistant Mortar:
2. Use 1 part Portland cement, 3 parts clean sand, and 15 percent hydrated
lime (by cement volume).
D. Mortar for All Locations. Comply with ASTM C270, Table 2, except limit
materials to those specified herein. Do not substitute ASTM C91 masonry cement
for ASTM C150 Portland cement without an approved Working Drawing and a
complete chemical analysis of the material and its properties. Limit cement-to-
lime ratio by volume as follows:
1. Type M:
a. Provide the following proportions by volume:
b. Properties:
2. Type S:
a. Provide the following proportions by volume:
04051H-3 11/2017
1849
DETAILED SPECIFICATION 04051H – MORTAR AND MASONRY GROUT
CONTRACT DEL-260H
b. Properties:
3. Type N:
a. Provide the following proportions by volume:
1) Portland Cement: 1 part.
2) Hydrated Lime or Lime Putty: Over 1/2 to 1 1/4 part
maximum.
3) Aggregate Ratio (measured in damp loose condition):
Not less than 2-1/4 and not more than 3 times the sum of
the volumes of cementitious materials.
b. Properties:
1) Average Compressive Strength, ASTM C270: 750 pounds
per square inch.
2.04 MIXING
END OF SECTION
04051H-4 11/2017
1850
DETAILED SPECIFICATION 04200H – UNIT MASONRY
CONTRACT DEL-260H
SECTION 04200H
Unit Masonry
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 04200 – Unit Masonry except as modified herein.
PART 1 GENERAL
1.01 SUMMARY
B. The Contractor shall provide all labor, materials, equipment and incidentals, as
shown, specified and required to complete all Work as shown on the Contract
Drawings or specified herein.
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
I. Brick size, texture, color and bond run will match adjacent wall. Mortar joint size,
finish, color and strike type will match adjacent wall. This includes all masonry
repair and new walls.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Acceptable Manufacturers
04200H-1 11/2017
1851
DETAILED SPECIFICATION 04200H – UNIT MASONRY
CONTRACT DEL-260H
2.02 MATERIALS
B. Structural Glazed Brick: Structural glazed brick shall meet the requirements of
ASTM C126 for finish properties and shall conform to ASTM C216 Grade SW
Type FBX for durability. Structural glazed brick shall meet UL requirements for
zero flame spread and zero smoke developed. Face dimensions and custom colors
to match exist adjacent material.
D. Glazed Structural Tile: Glazed structural facing tile shall be of Selected Size
Quality (Grade SS ground ends) in size to match existing, and shall conform to
the requirements of ASTM C126, Type I. Glazed structural tile walls and
partitions shall be provided with bullnose shapes for external corners, sills, and
jambs, and shall have coved base courses.
N. Weep Vents: Weep vents shall be provided where shown, and shall be an offset
T-shaped vent injection molded from flexible polyvinyl chloride. The vents shall
be provided in a custom size and color to match brick and mortar to match
existing.
PART 3 EXECUTION
3.01 INSTALLATION
END OF SECTION
04200H-2 11/2017
1852
DETAILED SPECIFICATION 05081H- GALVANIZING
CONTRACT DEL-260H
SECTION 05081H
Galvanizing
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05081-Galvanizing except as modified herein.
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
05081H-1 11/2017
1853
DETAILED SPECIFICATION 05081H- GALVANIZING
CONTRACT DEL-260H
05081H-2 11/2017
1854
DETAILED SPECIFICATION 05091H- WELDING
CONTRACT DEL-260H
SECTION 05091H
Welding
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05091-Welding except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
1.04 REFERENCES
PART 3 EXECUTION
END OF SECTION
05091H-1 11/2017
1855
DETAILED SPECIFICATION 05091H- WELDING
CONTRACT DEL-260H
05091H-2 11/2017
1856
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
SECTION 05092H
Metal Fastening
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall furnish all materials, labor, and equipment required to provide
all metal fastening in accordance with the Contract Drawings and these
Specifications.
B. The following index of this Section is included for convenience:
05092H-1 11/2017
1857
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
05092H-2 03/2017
1858
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 ANCHOR BOLTS
A. Anchor bolts for miscellaneous framing and architectural elements attachments
shall conform to ASTM A36 or ASTM A307 Grade A except where stainless steel
or other approved anchor bolts are shown on the Contract Drawings. Anchor bolts
05092H-3 11/2017
1859
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
shall be of the size and configuration shown on the Contract Drawings and shall be
supplied with hexagonal nuts meeting the requirements of ASTM A563 Grade A.
B. Anchor bolts for equipment attachment shall be of stainless steel Type 316 with
nitronic 60 stainless steel nuts and locknuts.
C. Where anchor bolts are used to anchor galvanized steel or are otherwise specified
to be galvanized, they shall be hot-dip galvanized in accordance with ASTM A307
and General Specification 05081 - Galvanizing.
D. Pipe sleeves around anchor bolts shall be of the size and configuration shown on
the Contract Drawings.
E. Material for anchor bolts submerged in salt water or corrosive liquids for which
stainless steel Type 316 is not suitable shall be as indicated in the specification
herein.
2.02 BOLTS
A. Bolts, nuts and washers for miscellaneous framing and for attachment of
architectural elements shall conform to ASTM A325.
B. Where bolts are used to connect galvanized steel or are otherwise specified to be
galvanized, bolts, nuts, and washers shall be hot-dip galvanized in accordance with
General Specification 05081 - Galvanizing.
2.03 STAINLESS STEEL BOLTS
A. Stainless steel bolts shall conform to ASTM F593. Unless otherwise specified,
fasteners for aluminum members shall be Type 304 stainless steel. Fasteners for
stainless steel members shall be of matching grade.
B. Stainless steel bolts shall have hexagonal heads with a raised letter or symbol on
the bolts indicating the manufacturer, and shall be supplied with hexagonal nuts
meeting the requirements of ASTM F594. Nuts shall be of the same alloy as the
bolts and shall have a raised letter or symbol indicating the manufacturer.
C. Nuts for stainless steel bolts for elements which are indicated on the Contract
Drawings to be removable shall be made of nitronic 60 alloy.
D. Material for bolts submerged in salt water or corrosive liquids for which stainless
steel Type 316 is not suitable shall be as indicated in the specification herein.
2.04 CONCRETE ANCHORS
A. Concrete anchors shall be one of the types listed below as indicated on the Contract
Drawings. Unless otherwise noted, all concrete anchors which are submerged, or
which are subject to vibration from equipment such as pumps and generators, shall
be injected, adhesive anchors. The determination of anchors equivalent to those
listed below shall be on the basis of test data performed by a commercial testing
laboratory. There are two categories used:
1. Expansion anchors shall be wedge, sleeve, or drop-in mechanical anchors.
05092H-4 03/2017
1860
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
05092H-5 11/2017
1861
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
Table 1
Allowable Tensile Capacity (Kips) for Standard Manufacturer
Embedment
Concrete Anchors
Concrete Anchors with Injection
Size Wedge Type Adhesive System
3/8" 1.3 2.1
1/2" 2.4 3.8
5/8" 3.3 5.9
3/4" 4.8 8.4
7/8" 5.6 11.0
1" 7.1 15.0
Table 2
Allowable Tensile Masonry (lbs) in Hollow Concrete Block
Masonry Anchors with Injection
Size Adhesive System
1/4" 255
5/16" 370
3/8" 525
1/2" 525
2.07 WELDS
A. Electrodes for welding carbon steel shall comply with ASTM A36.
B. Electrodes for welding aluminum shall comply with the Aluminum Association
Specifications and AWS D1.2.
C. Electrodes for welding stainless steel and other metals shall comply with AWS
A5.4.
2.08 EYEBOLTS
A. Eyebolts shall be of the size indicated on the Contract Drawings and shall conform
to ASTM A489 unless noted otherwise.
B. Carbon steel eyebolts shall be galvanized in accordance with General Specification
05081 - Galvanizing.
05092H-7 11/2017
1863
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
PART 3 EXECUTION
3.01 EXAMINATION
A. The Contractor shall field verify all dimensions and condition of the materials to be
connected, review the Drawings and report any discrepancies to the Engineer for
clarification prior to starting fabrication.
3.02 INSTALLATION
A. Anchor Bolts and Concrete Anchors:
1. Anchor bolts shall be installed in accordance with AISC "Code of Standard
Practice" by setting in concrete while it is being placed and positioned by
means of a rigidly held template.
2. The installation of concrete anchors shall be done in strict conformance with
the manufacturer's field demonstration and recommendations.
3. The holes drilled for adhesive anchors shall be cleaned by use of a fiber
bristle brush and dry compressed air. The anchors shall be supported in the
correct position until the adhesive sets and gains enough strength to prevent
any dislocation. Adhesive anchors shall not be tightened or loaded until the
adhesive has fully cured as recommended by the manufacturer.
4. No concrete anchor shall be installed before base concrete has attained
specified 28-day strength.
5. Concrete anchors shall not be used in place of anchor bolts without
Engineer's approval.
B. Bolts:
1. All steel bolts shall be installed in conformance with ASTM A325.
05092H-8 03/2017
1864
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
END OF SECTION
05092H-9 11/2017
1865
DETAILED SPECIFICATION 05092H – METAL FASTENING
CONTRACT DEL-260H
05092H-10 03/2017
1866
DETAILED SPECIFICATION 05501H – METAL FABRICATIONS
CONTRACT DEL-260H
SECTION 05501H
Metal Fabrications
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 05501-Metal Fabrications except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.01 MATERIALS
A. Structural steel shapes shall be fabricated in accordance with the details shown on
the Contract Drawings and shall conform to the requirements of ASTM A36
unless otherwise indicated. All steel shall be galvanized in accordance with the
requirements of General Specification 05081 - Galvanizing, and shop painted in
accordance with General Specification 09900 - Painting.
C. Stainless steel shapes and plate shall be Type 316 stainless steel for bolted
constructions and 316L for welded construction as detailed on the Contract
Drawings. Shapes shall conform to ASTM A276. Stainless steel plates shall
conform to ASTM A480 and ASTM A666.
Delete 2.02 ACCESS STAIRS, SHIP LADDERS AND PLATFORMS in its entirety and
replace with N/A.
05501H-1 11/2017
1867
DETAILED SPECIFICATION 05501H – METAL FABRICATIONS
CONTRACT DEL-260H
Delete 2.03 FLOOR ACCESS HATCHES in its entirety and replace with N/A.
B. Materials and fabrication shall conform with ASTM A36. All galvanizing shall
be done after fabrication and shall conform to the requirements of General
Specification 05081 - Galvanizing.
END OF SECTION
05501H-2 11/2017
1868
DETAILED SPECIFICATION 07900H – CAULKING AND SEALANTS
CONTRACT DEL-260H
SECTION 07900
Caulking and Sealants
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 07900 – Caulking and Sealants except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.02 MATERIALS
Add 2.02E:
b. Sealant:
1) 3M, Inc., St. Paul, MN, 3M Fire Barrier Silicone Sealant 2000
2) Specified Technologies Inc., Somerville, NJ, SIL300 Silicone
Firestop Sealant
3) RectorSeal, Houston, TX, Metacaulk 835+ Silicone
Firestopping Sealant
4) Or approved equal.
END OF SECTION
07900H-2 11/2017
1870
DETAILED SPECIFICATION 09900H – PAINTING
CONTRACT DEL-260H
SECTION 09900H
Painting
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 09900 – Painting except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
B. Manufacturer's Standard Finished Items: The following items shall be furnished with
the manufacturer's standard prime and finish coats applied in the shop: pumps,
motors, gears, gear housings, air compressors, wall fans, temperature control and
instrument panels, process air blowers, engines, filters, strainers, air dryers, meters,
gas boosters, gas turbines, generators, panelboards, transformers, boilers, condensing
units, water chillers, cooling towers, condensers, heat exchangers, humidifiers, air
handling units, sound attenuators, air conditioning and dehumidification units,
convector cabinets, unit heaters, enclosures for finned tube radiators, cabinet heaters,
boilers, wood seats, lockers, metal toilet partitions, metal urinal screens, aluminum
fascia, motor control centers, aluminum light standards, and hoisting equipment.
Steel reinforcing bars for concrete shall be coated in accordance with the Contract
Drawings. When powder coatings are required by the specification herein, the
powder coatings shall be in accordance with the requirements of the manufacturer of
the item.
09900H-1 11/2017
1871
DETAILED SPECIFICATION 09900H – PAINTING
CONTRACT DEL-260H
PART 2 PRODUCTS
2.03 MATERIALS
CLASSIFICATION OF PAINTS
Dry Film
Paint Volume Thickness
Product Name and Number
Group Solids % Mils per
Coat
Sherwin Williams (Cleveland, OH): FIRETEX
69% 40.0*
FX5120
O
Carboline (St. Louis, MO): A/D Firefilm III 65% 30.0*
* Required DFT for specific fire rating is dependent on steel section and size. Consult
Representative.
09900H-2 11/2017
1872
DETAILED SPECIFICATION 09900H – PAINTING
CONTRACT DEL-260H
PART 3 EXECUTION
* Refer to UL N636 Beam Design for application thickness. Consult Sherwin-Williams Representative.
END OF SECTION
09900H-3 11/2017
1873
DETAILED SPECIFICATION 09900H – PAINTING
CONTRACT DEL-260H
09900H-4 11/2017
1874
DETAILED SPECIFICATION 10200H – LOUVERS
CONTRACT DEL-260H
SECTION 10200H
Louvers
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 10200 – Louvers except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
Replace paragraph 1.03.A with the following:
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.02 MATERIALS
Replace paragraph 2.02 with the following:
10200H-1 11/2017
1875
DETAILED SPECIFICATION 10200H – LOUVERS
CONTRACT DEL-260H
2. Manufacturer to submit test data on 4 feet x 4 feet louver units. Test data
shall show the following results at 948 fpm free area velocity.
B. Fixed Louver
1. Individual louver shall be Airolite (Schofield, WI) louver type 6096; fixed 43
degree, 6" deep stationary blade of the following characteristics:
a. Frames and blades shall be stainless steel 316 alloy .064" thick.
b. Fasteners: Of same basic metal and alloy as fastened metal, unless
otherwise indicated. Do not use metals which are corrosive or
incompatible with materials joined.
1) Use types, gages and lengths to suit unit installation
conditions.
2) Use Philips flat-head machine screws for exposed fasteners
unless otherwise indicated.
c. Anchors and inserts of type, size and material required for type of
loading and installation indicated. Use Type 316 stainless steel
anchors and inserts for exterior installation and elsewhere as required
for corrosion resistance.
d. Bituminous Paint: SSPC-Paint 12 (cold-applied asphalt mastic).
2. Manufacturer to submit test data on 4 feet x 4 feet louver units. Test data
shall show the following results at 896 fpm free area velocity.
END OF SECTION
10200H-2 11/2017
1876
DETAILED SPECIFICATION 13281H – ASBESTOS MANAGEMENT
CONTRACT DEL-260H
SECTION 13281H
ASBESTOS MANAGEMENT
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 13281 – Asbestos Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
END OF SECTION
13281H-1 11/2017
1877
DETAILED SPECIFICATION 13281H – ASBESTOS MANAGEMENT
CONTRACT DEL-260H
13281H-2 11/2017
1878
DETAILED SPECIFICATION 13282H – MERCURY MANAGEMENT
CONTRACT DEL-260H
SECTION 13282H
Mercury Management
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 13282 – Mercury Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the Allowance price bid for Contract Item H-A-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
13282H-1 11/2017
1879
DETAILED SPECIFICATION 13282H – MERCURY MANAGEMENT
CONTRACT DEL-260H
13282H-2 11/2017
1880
DETAILED SPECIFICATION 13283H - LEAD MANAGEMENT
CONTRACT DEL-260H
SECTION 13283H
Lead Management
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 13283 – Lead Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the Allowance price bid for Contract Item H-A-1, as described in
Detailed Specification 01270 – Measurement and Payment.
END OF SECTION
13283H-1 11/2017
1881
DETAILED SPECIFICATION 13283H - LEAD MANAGEMENT
CONTRACT DEL-260H
13283H-2 11/2017
1882
DETAILED SPECIFICATION 13284H - PCB MANAGEMENT
CONTRACT DEL-260H
SECTION 13284H
PCB Management
NOTE: All work for this Section shall be in accordance with the requirements of General
Specification 13284 – PCB Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. Except for unforeseen PCB-containing materials and related work eligible for
payment under allowance, as described in Section 01355 – Hazardous Materials
Controls, no separate payment will be made for performing any work of this
Section and the Contractor shall include all costs thereof in its lump sum price bid
for Contract Item H-LS-1, as described in Detailed Specification 01270 –
Measurement and Payment.
END OF SECTION
13284H-1 11/2017
1883
DETAILED SPECIFICATION 13284H - PCB MANAGEMENT
CONTRACT DEL-260H
13284H-2 11/2017
1884
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
SECTION 13862H
Non-Metallic Ductwork
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall provide all labor, materials, equipment and incidentals as
shown, specified and required to furnish and install all non-metallic ductwork
complete with auxiliary equipment and accessories as shown, specified and/or
required for proper operation.
B. The following index of this Section is presented for convenience.
B. Contractor shall provide certification that all stainless steel accessories including
screws, hangers, supports, etc. for FRP ductwork are Type 316 stainless steel.
C. Field Measurements: Take field measurements where required prior to installation
to ensure proper fitting of Work.
D. Where reference is made to one of the above standards, the version in effect at the
time of bid opening shall apply.
1.05 SUBMITTALS
A. Contractor shall submit Shop Drawings, and material Specifications for the
approval of the Engineer. Submittals shall be provided, but not be limited to:
1. 1/4-inch scale duct layouts.
2. Dimensions.
3. Details of construction.
4. Details of installation, hanger details and spacing.
5. Manufacturer's literature, illustrations, Specifications and engineering data
including, but not limited to:
a. Ductwork.
b. Registers, grilles and diffusers.
c. Fire Dampers (UL Listed):
1) Closing mechanisms.
2) Fusible link operating temperature.
3) Installation details.
4) Access Doors.
d. Flexible connections.
e. Duct sealants.
6. Air outlet schedule indicating room name and location of each outlet. Cross
reference contract designation and manufacturer's model number or name.
7. Specifications for FRP resins and reinforcing material used.
8. Specifications for fire-retardant epoxy FRP ductwork coating and
reinforcing material used.
9. Specification of FRP ductwork laminate construction including schedule of
duct sizes indicating weight per foot, wall thickness and all other data
required for indicating conformance to FRP round duct schedule. Submit
procedures for hand layup of duct joints.
10. Submit FRP rectangular duct schedule with sizes, thickness, vacuum
pressure, weight per foot pressure, spans, joint type, and flange data.
13862H-3 11/2017
1887
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
11. Other technical data related to the specified material and equipment as
requested by Engineer.
B. Test Reports: Submit the following test reports for approval where required.
1. UL Label, Fire Dampers.
2. Volume Damper leakage tests from an AMCA approved testing laboratory.
C. Submit a letter stating that the proposed resins proposed in the fabrication of the
FRP ductwork will give satisfactory performance under the specified service
conditions or a corrosion resistance chart indicating same.
D. Manufacturer's certified literature indicating compliance with proposed pressure
and vacuum classification and wheel loading classification indicated below.
E. Tabulation in check list forms to indicate compliance with ASTM D 2563 Table I,
Level II visual acceptance levels.
1.06 QUALITY ASSURANCE
A. Manufacturer Qualifications:
1. Contractor shall engage a single firm, with undivided responsibility for
performance and other requirements and components of the ductwork. The
firm will show successful experience in the fabrication of ductwork systems
of scope and type similar to the required Work.
B. Installer Qualifications:
1. Contractor shall have at least five (5) years’ experience in the installation of
the Work specified. He shall employ only tradesmen with specific skills
and experience in this type of Work.
2. Contractor shall have undivided responsibility as a single firm for
performance and other requirements for the installation of the Work
specified herein.
C. The Contractor shall comply with applicable provisions of regulatory agencies
below and any others having jurisdiction and shall obtain and pay for all required
permits, fees and inspections.
1. Underwriters Laboratories, Incorporated.
2. National Fire Protection Association.
3. National Electrical Code.
4. Local and State Building Codes and Ordinances.
a. Building Code of the City of New York.
b. Code of New York State.
13862H-4 11/2017
1888
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 MATERIALS
A. Non-Metallic Ductwork:
13862H-5 11/2017
1889
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
13862H-6 11/2017
1890
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
trioxide and nexus veil reinforcement. Exterior surfaces located outdoors shall be
factory-painted in accordance with Article 2.05.
D. Laminates shall consist of a 10 to 20 mil chemical resistant liner with a synthetic
surfacing veil embedded in a resin rich surface. The corrosion barrier shall be a
minimum of 100 mils and include no less than two (2) layers of 1-1/2 ounce mat
with 25% glass and 75% resin content. The structural layer shall be of sufficient
thickness to meet the minimum thickness requirements specified. The exterior
surface layer shall be resin rich apertured nexus veil not less than 20 mils thick.
Outside finish shall have a paraffinated pigmented gel coat finish with an ultra
violet inhibitor. The composition specified for the inner surface and interior layer
is intended to achieve optimum chemical resistance.
E. Resins used in the laminate shall be premium corrosion resistant and fire retardant
brominated bispenol-A vinylester resins as manufactured by:
1. Dow Chemical Company, Derakane – Midland, MI.
2. Reichhold Chemicals, Dion 9300 FR – Research Triangle Park, NC.
3. Ashland Chemical Company, Hetron FR992 – Lexington, KY.
4. AOC Vipel K022, Collierville, TN
5. Or approved equal.
13862H-7 11/2017
1891
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
2. Surface Preparation: All mold release agents and other foreign matter shall
be completely removed. All glossy surfaces shall be brush-blasted or
sanded and cleaned.
3. Manufacturer: Provide products as manufactured by one of the following:
a. Flame Control Coatings, Incorporated, Flame Control No. 46081
Thermal Insulating (Intumescent) Epoxy Paint, Niagara Falls, NY.
b. Or approved equal.
4. Laminate must be fully cured before application of fire-retardant coating.
5. Apply first coating minimum 8-10 mil (wet) over duct.
6. Immediately apply one layer of C-Veil onto wet coating. Brush or roll C-
Veil to remove any creases and to completely wet C-Veil.
7. Apply second layer of intumescent coating at 8-10 mil (wet) minimum
thickness. Dry thickness of two coats plus C-Veil shall be not less than 10
mils.
8. Apply additional coats as required to ensure that C-Veil is completely
immersed in the epoxy coating and completely wetted and that the total dry
thickness will be greater than 10 mils. There shall be no exposed or dry C-
Veil.
9. The flame spread rating of the fire-retardant coating shall not exceed 25 and
the smoke developed rating shall not exceed 50. The manufacturer shall
submit test data indicating that the fire retardant system does not exceed
listed ratings and has been tested by Factory Mutual Research Corporation.
10. Color shall be light gray.
J. Fittings and Joints: All fittings such as elbows, laterals, tees, and reducers shall be
of the same resin, equal or superior in strength to the adjacent duct section and shall
have the same internal diameter as the adjacent duct. Round duct joints shall be
butt-wrapped or bell and spigot joints as shown or required. Bell and spigot joints
shall be sealed with a standard butt joint overlay as per PS 15-69. All interior
surfaces of joint to be coated with a paraffinated resin-rich gel coat.
K. Total width of overlay for butt-wrap joints shall be not less than 6 inches for
diameters between 8 and 30 inches and not less than 10 inches for diameters 31
inches and larger.
L. Standard Elbows:
1. Standard elbow centerline radius shall be equal to 1-1/2 times the diameter.
2. Standard elbows up to 24-inch diameter shall be smooth radius molded
elbows. Standard elbows 25-inch diameter and greater may be mitered
sections as specified below.
3. 0° to 44° elbows shall contain one (1) mitered joint and two (2) sections.
45° to 80° elbows shall have a minimum of two (2) mitered joints and three
13862H-8 11/2017
1892
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
(3) sections. Elbows greater than 80° shall have a minimum of four (4)
mitered joints and five (5) sections.
4. All square elbows shall have FRP or Type 316 stainless steel single
thickness turning valves with streamlined leading edges.
M. Maximum allowable deflection for any size ductwork shall be 1/2-inch between
supports and for any side of duct under worst case operating conditions.
N. Tolerances:
1. Out-of-roundness of duct shall be limited to ±1/8-inch or ±1 percent of duct
inside diameter, whichever is greater for duct sizes 8-inch diameter and
greater.
2. Length of all flange pipe sections shall not vary more than ±1/8-inch at 70
F.
3. All unflanged ducts shall be square on the ends in relation to the pipe axis
and ±1/8-inch up to and including 24-inch diameter and ±3/16-inch for all
diameters greater than 24-inch.
4. Fittings: The tolerance on angles of all fittings shall be ±1 degree, up to and
including 24-inch diameter and ±1/2 degree for 30-inch diameter and above.
5. Flanges:
a. Flange faces shall be perpendicular to the axis of the duct within 1/2
degree.
b. Flange faces shall be flat to within ± 1/32-inch, up to and including
18-inch diameter and flat within ± 1/16-inch for 20-inch diameter
and larger.
c. Provide custom filler pieces as required to mate flanges squarely.
O. Contractor shall submit wall thickness calculations for review. Calculations shall
include the following:
1. Wall thickness determination shall be based on the structural fiberglass
reinforced wall only.
2. Wall thickness shall have a safety factor of 4 to 1 for pressure and vacuum
service.
3. Wall thickness shall be suitable for use up to 120 F in pressure service and
vacuum service.
4. Wall thickness shall be based on a 0.50-inch maximum deflection between
supports and for any side of duct under worst case operating conditions.
5. Where ductwork is located outdoors, wall thickness shall be based on the
following occurring simultaneously:
a. Wind Load: 25 pounds per square foot.
13862H-9 11/2017
1893
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
13862H-11 11/2017
1895
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
j. Angles: FRP.
k. Ends: Flanged with bolt holes drilled. Flange thickness shall not
vary more than 1/16 inch.
l. Blade, Shaft and Jamb Seals: EPDM suitable for use in a hydrogen
sulfide atmosphere.
4. Dimensions: As shown on the Drawings.
5. Leakage test and performance data from an AMCA approved testing
laboratory shall be submitted.
6. Manufacturers: Provide products as manufactured by one of the following:
a. Swartwout, Phillips Industries, Model 1108AF, Kansas City, MO
b. Or approved equal.
V. Sleeves shall be Type 316 stainless steel. Install round duct sleeves and mechanical
link seals for round duct as required.
W. Conform to General Specification 15810 - Ductwork and Duct Accessories (in
Type 316 stainless steel construction) for fire dampers, bird screen and other
accessories.
2.03 REGISTERS, GRILLES AND DIFFUSERS
A. As specified in General Specification 15810 - Ductwork and Duct Accessories (in
Type 316 stainless steel construction).
2.04 MOTORIZED DAMPERS
A. Furnish and install, where indicated on the Drawings, motorized spring return FRP
dampers.
B. Motorized dampers shall be as specified above for rectangular dampers except that
a factory installed motorized actuator shall be provided in lieu of a hand operator.
C. Motorized actuator shall be factory mounted and tested at the damper manufacturer.
Actuator torque shall be verified with the damper manufacturer.
D. Electric motor actuators shall be provided for all electrically operated dampers and
shall be furnished complete with accessories as specified.
E. Actuators shall be rated for NEMA 4X.
F. Each electric motor operator shall be capable of providing not less than 1.5 times
the required operator torque for opening and closing of the damper. Responsibility
for correct actuator sizing shall be that of the damper manufacturer.
G. Motor operation cycle time from full open to full close shall be set for 15 seconds.
H. The operator shall be furnished with a hand wheel for manual operation.
I. The operator gear reducer shall be provided with four limit switches and two torque
switches. Two limit switches shall indicate full open and two shall indicate full
closed positions. Limit switches shall be field adjustable. Switches shall be
13862H-12 11/2017
1896
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
equipped with SPDT contacts. Limit switches and torque switches shall be supplied
in the enclosure furnished and mounted on the operators.
J. The electric motor shall be designed for actuator service, Class B insulation,
squirrel cage construction, with thermal overloads, and suitable for operation on
120 volt, 1 phase, 60 Hz power.
K. Circuitry and devices shall be furnished with the operator to provide damper
position and indication for remote control and monitoring through the automatic
temperature control system. Terminal strips shall accept #12 gauge wire size.
Provide additional terminal strips for remote signals.
L. Provide limit switches and position indicators for interlocking and monitoring.
1. Provide position indicating signals as follows:
a. Damper completely opened.
b. Damper completely closed.
c. Damper stopped at any intermediate position.
M. The actuator gearing shall be heat treated alloy steel and designed to withstand the
stall torque developed by the actuator.
N. All external fasteners shall be type 316 stainless steel.
O. The actuator shall be lubricated at the time of manufacture and not require any field
lubrication.
P. Manufacturer: Provide motorized dampers of one of the following:
1. Raymond Control Systems (RCS), Houston, TX.
2. Rotork, Milwaukee, WI.
3. Limitorque, Irving, TX.
4. Or approved equal.
PART 3 EXECUTION
3.01 INSTALLATION
A. Turning vanes shall be installed in all miter elbows to permit air to make the abrupt
turns with a minimum of turbulence. The turning vanes shall be quiet and free from
vibration when the system is in operation. Turning vanes shall be single thickness
type. Vanes shall be installed in all short radius elbows in accordance with
SMACNA standards and Industrial Duct Construction standards. Duct clean out
doors shall be provided at each elbow with turning vanes.
B. Manual volume dampers larger than 11 inches in any dimension shall be opposed
blade type. The damper blades shall be operated by a lockable dial regulator and
may be set in any position. The dial regulators shall be marked so that the "open"
and "shut" positions are clearly identified. The dial regulators on insulated
13862H-13 11/2017
1897
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
ductwork shall be mounted on an elevated platform which will finish flush with the
surface of the insulation. Manual volume dampers shall be located at accessible
points and wherever possible some distance from a duct transition or fitting. Care
shall be taken during installation to make certain that sheet metal fasteners do not
protrude into the duct and interfere with damper operation. Dampers shall be
provided in each branch duct take off and in both ducts downstream of each trunk
duct split. Manual volume dampers shall be FRP construction. Splitter type
dampers shall not be installed.
C. Duct access doors shall be provided within working distance of, and on the fusible
link side of all fire dampers, adjacent to volume dampers, on the linkage side of
automatic dampers and at all other apparatus requiring service or inspection in the
duct system. The doors shall be rigid and airtight, and provided with EPDM
gaskets, hinges and sash locks. Whenever space requirements are such that a
hinged access door is impractical, a screw fastened lift-out door shall be provided
instead.
D. Test openings shall be installed in the ductwork to facilitate air testing, adjusting
and balancing where directed by the Contractor. The openings shall be sealed by a
screw cap and gasket.
E. Flexible connectors for preventing the transmission of vibrations through the
ductwork to the structure shall be installed between the ductwork and all air moving
equipment and at the building joints. Flexible connectors shall be neoprene-
impregnated fabric collars with cemented seams fastened with straps and bolts of
the same material as the ductwork. Flexible connectors shall not be painted or used
to correct misalignment.
F. The fire damper shall be secured to a stainless steel collar with 1/4" diameter
stainless steel nuts and bolts with maximum spacing of 12 inches on center and a
minimum of two fastenings per side beginning two inches from the corners of the
collar. The collars shall be at least the same gauge as the ductwork to which it is
attached. Regardless of the duct gauge, collars shall not be lighter than 24 gauge
316 stainless steel. Retaining angles shall be installed on four sides of the collar
and on both sides of the protected opening with a minimum of one inch overlap on
the wall or floor. The 316 stainless steel angles shall be a minimum of 1 1/2" x 1
1/2" x 1/8" and shall be fastened to the collar only; do not fasten angles to the wall
or floor.
G. The angles shall be fastened to the collar with 1/4" diameter stainless steel nuts and
bolts with a maximum spacing of 6 inches on center and a minimum of two
fastenings per side beginning two inches from the corners of the collar. Where gas
tight seals are required, the angles shall be fastened to the collar with a continuous
weld and a sealant shall be installed between the angle and the wall or floor.
Collars, angles and hardware used with stainless steel fire dampers shall be Type
316 stainless steel. Clearance for expansion is required between the collar and the
opening on the top and on each vertical side. The clearance shall be 1/8 inch per
lineal foot of sleeve with clearance on the sides distributed equally and all vertical
clearance on the top. The retaining angles shall be increased in size to provide the
13862H-14 11/2017
1898
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
minimum overlap of one inch on the wall or floor. The ductwork shall be connected
to the collar sides of the collar. The distance from the wall or floor to the breakaway
connection shall not exceed 6 inches.
H. Contractor shall furnish and install sleeves for registers, grilles, and dampers
mounted in the masonry, concrete plenums or shafts. Sleeves shall be 16 gage Type
316 stainless steel.
I. After the installation is completed, the Contractor shall seal all joints air tight.
Sealants and tape shall have a flame spread not greater than 25 and a smoke
developed rating of not over 50.
J. All screens shall be Type 316 stainless steel. Bird screen shall conform to ASTM
E2016, Type 1, Class 1, 2 x 2 mesh (0.031 inch diameter stainless steel wires).
Frame shall be removable Type 316 stainless steel construction.
K. All ductwork shall conform accurately to the dimensions shown, the ducts shall be
straight and smooth inside with joints neatly finished; ductwork shall be installed
so as to preclude the possibility of vibration under all operating conditions.
L. Elbows shall have a minimum centerline radius of 1-1/2 times the width of the duct.
Turning vanes shall be provided at all square elbows. Turning vanes shall be double
wall and shall be quiet and free from vibration when the system is in operation.
M. Provide flexible connectors at inlet and discharge of air handling equipment.
N. Provide volume dampers where indicated on the Drawings and as required to
facilitate accurate volume control. The duct of the damper shall be reinforced to
prevent vibration. Volume dampers specified with air devices shall be installed in
addition to those shown on the Drawings.
O. Fire dampers shall be provided and installed where indicated on the Drawings and
where required by U.L. and authorities having jurisdiction, and shall be approved
by local building codes and in accordance with the requirements of the NFPA.
P. Provide access doors for all dampers for inspection and maintenance.
Q. Install all ductwork and accessories to provide a system free from buckling,
warping, breathing or vibration.
R. All expansion joints in ducts at building expansion joints shall be suitably supported
at each end by support guides within 12 inches of joint.
S. All ducts at flexible connectors with air handling equipment, and fans shall be
supported at free end within 12 inches of flexible connector.
T. Provisions shall be made for supporting all ductwork, dampers, and other ductwork
accessories, where necessary.
U. All ductwork shall arrive on site fully fabricated, not in two halves for field
fabricated.
3.02 FIELD TESTING
A. Preliminary and final field test shall be performed for all equipment provided under
13862H-15 11/2017
1899
DETAILED SPECIFICATION 13862H – NON-METALLIC DUCTWORK
CONTRACT DEL-260H
END OF SECTION
13862H-16 11/2017
1900
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
SECTION 15060H
Hangers and Supports
NOTE: This Detailed Specification 15060H – Hangers and Supports replaces General
Specification 15060 – Hangers and Supports in its entirety. All Work for this Section shall
fully conform to the requirements specified herein.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Contractor shall provide all hangers, supporting devices and appurtenances shown,
specified or required for pipes, fittings, valves and other in-line equipment.
B. Included in this classification are rod hangers; clevis hangers, spring hangers; stanchion,
roller and pipe pole supports and saddle stands; supports of structural steel; concrete
saddles, concrete anchor blocks and bases, and all necessary guides, restraints, fastening
devices, anchor bolts, pipe anchors and appurtenances.
C. Contractor shall provide all temporary pipe supports required during construction.
D. Contractor shall design all piping support systems in accordance with the requirements of
this Section unless otherwise shown or specified.
E. The following index of this Section is included for convenience:
15060H-1 11/2017
1901
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
15060H-2 11/2017
1902
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
15060H-4 11/2017
1904
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
13. All points of adjustment for pipe and duct hanger rods shall be locked securely in
place using double-nutting. Double-nutting means two nuts torqued directly
against each other under each point of adjustment in addition to a third nut on top
of the bracket. Damaging threads or tack welding as a method of locking
adjustment is not permitted.
14. All threaded assemblies shall be double nutted or provided with pinned nuts.
Alternately, tack welding of bolted assemblies may be acceptable unless provisions
for vertical adjustment is required.
15. At all flexible couplings, supports shall be placed on each side and as close to the
coupling as possible. Supports shall be the guide type which prevent axial
movement from resulting in pipe deflection and misalignment.
1.06 SUBMITTALS
A. Contractor shall submit the Shop Drawings for approval of the Engineer. Submittals shall
include, but not be limited to:
1. Name and qualifications of the support and hanger engineer.
2. Detailed Shop Drawings showing all hangers and supports for each piping system.
Shop Drawings shall show location, installation, material, loads, forces, stresses
and deflections of all hangers and supports. Reaction forces imparted to structures
to which hangers and supports are attached shall be shown.
3. Manufacturer's catalogs and engineering data on all hangers and supports.
4. Load ratings.
5. Materials.
6. Installation details.
7. All drawings and specified or required design calculations, signed and sealed by a
New York State registered professional engineer.
B. Contractor shall provide detailed drawings of each pipe support. Each drawing shall
contain enough information to verify the pipe support design and to allow the manufacture
of the device. At a minimum, the Contractor shall submit:
1. Scaled details of the device with dimensions.
2. A table of applied forces and moments.
3. A complete bill of materials.
4. An isometric showing the applied forces and moments.
5. Detailed connections to existing structure.
6. Shop and field welds.
C. Each submittal shall have the following:
1. A unique identification number and revision level.
15060H-5 11/2017
1905
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Manufacturer: Provide products of one of the following:
1. T&L Metal Fabricators, Inc – IL.
2. Carpenter and Paterson – Woburn, MA.
3. Or approved equal.
B. Each type of hanger and support shall be the product of a single manufacturer.
2.02 MATERIALS
A. Materials for hangers and supports of metallic construction shall conform to ASME B31.1
and to the following standards:
1. Structural Steel, ASTM A 36 and A 283.
2. Iron Castings, ASTM A 48 (Class No. 35).
3. Stainless Steel, ASTM A 276.
a. Type 316 stainless steel for non-welded items.
b. Type 316L stainless steel for welded or fabricated items.
c. Tensile Strength 70,000 psi minimum.
d. Yield Strength 25,000 psi minimum.
e. Elongation in 2 inches 35%.
f. Reduction of area 45%.
4. Stainless Steel Pipe and Tube, ASTM A 778, Type 316L stainless steel.
B. Pipe supports, hangers, brackets, guides, restraints, rods, bolts and shall be Type 316
stainless steel in Corrosive Areas and galvanized steel in non-corrosive areas. Concrete
inserts shall be of malleable iron with galvanized finish. Where steel is used herein, it shall
refer to Type 316 stainless steel for corrosive areas and galvanized steel for non-corrosive
areas.
15060H-6 11/2017
1906
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
C. Pipe rolls, including stands and bases, shall be of cast iron, hot-dipped galvanized
conforming to ASTM A123 for non-corrosive areas and Type 316 stainless steel for
corrosive areas.
D. Only new materials shall be provided.
E. Hangers and supports shall conform to MSS-SP-58, Table 2.
F. Expansion anchors for use in existing concrete structure shall be made of Type 316
stainless steel.
2.03 HANGERS AND SUPPORTS
A. Hangers and supports where shown shall be in accordance with the Contract Drawings.
Hangers and supports not shown shall comply with MSS SP-58.
B. All hangers and supports shall allow minimum 3-inches of vertical adjustment.
C. Hangers and Supports shall be of the following types:
1. Hangers for Single Pipes:
a. Single pipes shall be supported by hangers suspended by rods from
structural steel members, inserts in concrete ceilings and beams, bottom of
trapeze hangers and wall mounted steel angle brackets. The strength of the
rod shall be based on its root diameter.
b. Except for piping subject to thermal expansion and contraction or as
otherwise specified in the Detailed Specifications, pipe hangers shall be
adjustable clevis type MSS SP-58 Type-1.
c. Piping subject to thermal expansion and contraction shall be supported on
rollers.
2. Hangers or Supports for Multiple Pipes:
a. Multiple pipes, running parallel in the same horizontal plane, and adjacent
to each other, shall be suspended by trapeze type hangers or supported on
wall brackets. Trapeze hangers shall consist of channel sections supported
from threaded rods or attached to concrete walls, columns or structural steel
support members.
b. Except as otherwise specified herein, pipe anchors used for attaching pipe
to trapeze or multiple pipe wall brackets, shall be anchor or pipe chains as
required.
3. Supports for Single Pipe:
a. Single pipes located in a horizontal plane close to the floor shall be
supported by one of the methods specified herein or as shown on the
Contract Drawings.
b. Pipes shall be supported by adjustable stanchions, pipe saddle or roll
supports with "U" bolts. Stanchions shall provide at least 4-inches
adjustment and be flanged-mounted to floor.
15060H-7 11/2017
1907
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
15060H-8 11/2017
1908
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
* Single rods may be used only if approved by the Engineer. If not approved,
double rods shall be used.
a. Hanger loads shall be calculated based on the weight of pipe filled with
water plus 50 pounds per foot of dead load.
B. Concrete Inserts, Attachment Plates and Clamps:
1. Hanger rods up to 7/8-inch diameter shall be attached to new concrete structures
using concrete inserts MSS SP-58, Type 18. Inserts shall be malleable iron with
galvanized finish. The use of steel inserts is prohibited. Design of the inserts shall
permit the rods to be adjusted laterally in one plane and to lock the rod nut or head
to the body. The inserts shall be provided with openings or recesses to receive
reinforcing rods. To facilitate installation, slots shall be provided in the exposed
flanges of the insert. Inserts shall be rated to safely carry the maximum load which
can be supported by the hanger rod.
2. Hanger rods shall be attached to existing concrete structures using stainless steel
expansion anchors as specified in General Specification 05501 - Metal
Fabrications.
15060H-9 11/2017
1909
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
3. Steel beam clamps shall be malleable iron and conform to MSS SP-58 Type 28 or
29 for wide flange or I-beams, and Type 20 for channel sections or where it is
necessary to locate the hanger rod off the beam centerline.
4. Steel U-shape beam attachments welded to the underside of beams, and welded
steel brackets fastened to structural steel columns, shall be subject to specific
approval of the Structural Steel and Pipe Supports Shop Drawings.
2.05 PIPE INSULATION PROTECTION
A. Contractor shall furnish steel protection saddles on all supports for insulated pipe.
1. For pipe sizes less than 12 inches in diameter, provide saddles of No. 14 U.S. gauge
stainless steel curved 180 degrees for use with roller hangers or structural trapeze
hangers and of No. 16 U.S. gauge stainless steel curved 120 degrees for use in clevis
hangers. Saddles shall be at least 12-inches long. Saddle gripping side edges shall
be turned up at least to the thickness of insulation.
B. Before placing the saddles, saddles shall be filled with either insulating cement or high
density insulation cut to fit. For vapor barrier insulation, the barrier must be maintained;
contact between hanger and support and bare pipe will not be permitted.
2.06 PIPE ANCHORS AND BRACES
A. Anchors and sway braces shall be provided when required to hold the pipelines and
equipment in position or alignment. Pipe anchors and braces for rigid fastening to the
structures shall be attached to steel anchor plates and Type 316 stainless steel anchor bolts
set into the forms when placing concrete of new structures. Brackets and braces shall be
attached to existing concrete structures with through bolts or expansion anchors.
B. Anchors, guides and restraints shall be provided for the proper operation of pipeline
expansion joints.
C. Anchors shall be provided with steel straps on piping, except where anchors form an
integral part of pipe fittings and couplings or where an anchor of special design is required
or shown on the Contract Drawings.
D. All pipe anchors, guides and restraints shall be designed to conform to ASME B31.1.
2.07 INSPECTION
A. The City may elect to conduct shop inspections. The inspections may include but not be
limited to: mechanical and chemical testing, material sampling, material certifications,
traceability of parts, blasting and painting, visual and dimensional inspection, and free iron
contamination check on stainless steel parts.
2.08 GALVANIZING
A. Galvanizing shall conform to General Specification 05081 - Galvanizing, except that
malleable iron and concrete inserts shall be galvanized in conformance with the
manufacturer's specifications.
15060H-10 11/2017
1910
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
PART 3 EXECUTION
3.01 GENERAL
A. Hangers, supports, and accessories shall be located within maximum span lengths specified
to support continuous pipeline runs unaffected by concentrated loadings.
B. Hangers or supports shall be provided at all locations where piping changes direction.
C. Hangers and supports shall be located to prevent vibration or swaying and to provide for
expansion and contraction.
D. Hangers’ rods shall be straight and vertical. Chain, wire, strap or perforated bar hangers
shall not be used. Hangers shall not be suspended from piping.
E. Concrete embedded items shall be installed before concrete placement.
F. Embedded items shall be fastened securely to prevent movement during concrete
placement.
G. Hanger and support units shall be installed in accordance with manufacturer's
recommendations.
H. Hangers and supports shall be adjusted and grout placed as specified in General
Specification 03600 – Grout to bring pipelines to specified elevations.
3.02 SPACING OF HANGERS AND SUPPORTS
A. Supports and Hangers for Horizontal Pipes:
1. Supports and hangers for all piping shall be placed no farther apart than described
below, unless otherwise shown or specified:
a. Ductile Iron, Steel and Stainless Steel Pipe:
1) Maximum spacing in accordance with Table 3 of MSS-SP-69. The
designer should check the capacity of the steel or building structure
to which the hanger or support is attached, and adjust the maximum
spacing accordingly.
2) In addition, ductile iron pipe shall have a minimum of two supports
per length and shall have a hanger or support adjacent to each end.
b. Tubing less than 1-inch diameter: In accordance with best piping practice
and ASME B31.1 and as approved by the Engineer.
2. Additional supports shall be placed immediately adjacent to any change in piping
direction, at equipment, and on both sides of valves, expansion joints and couplings.
B. Supports for Vertical Piping:
1. Riser clamp shall be placed under hub, fitting or coupling with approved solid
bearing on steel sleeve.
2. Where riser clamps are used with plastic piping they shall be modified so as not to
exert any compressive forces on the pipe.
15060H-11 11/2017
1911
DETAILED SPECIFICATION 15060H – HANGERS AND SUPPORTS
CONTRACT DEL-260H
3. Vertical piping shall be supported at each floor and between floors by stays or
braces to prevent rattling and vibration. Maximum spacing shall not exceed 25 feet.
4. Base elbows or welded equivalent shall be provided at vertical piping bases.
5. Top support shall have a horizontal connection, and provide for pipe expansion.
3.03 PAINTING AND COATING
A. Surfaces of hangers and supports in contact with aluminum, brass, plastic and copper
pipelines or pipeline equipment shall be protected with an approved plastic coating to
prevent abrasion. Touch-up shall be provided in the field, as required. Coating shall be
applied in accordance with the manufacturer's recommendations, and shall be free from
spots and brush marks, to the satisfaction of the Engineer.
3.04 TESTING
A. Preliminary and final field test shall be performed for all equipment provided under this
Specification, as specified in Article 13 of the General Conditions and Detailed
Specification 01811 – Preliminary and Final Field Tests.
B. All pipe support and restraining systems shall be installed and secured prior to the testing
or activation of the pipeline on which they are installed.
C. All pipe support systems shall be tested. After installation, each pipe support system shall
be tested in conjunction with the respective piping pressure tests. Tests shall include
cycling the piping system to duplicate operating conditions. If any part of the pipe support
system proves to be defective or inadequate, as evidenced by vibration or excessive
movement, it shall be repaired or augmented at no additional cost to the City.
END OF SECTION
15060H-12 11/2017
1912
DETAILED SPECIFICATION 15076H – PIPING AND EQUIPMENT
IDENTIFICATION
CONTRACT DEL-260H
SECTION 15076H
Piping and Equipment Identification
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Furnish and install all components of the system for identification of piping,
ductwork and equipment. The system includes the placing of identification
signs and direction-of-flow arrows on all visible piping and ductwork, and the
placing of nameplates on equipment as shown on the Contractor's Shop
Drawings submitted under the related Sections for equipment, piping and
valves, and ductwork as required for a complete job.
B. The following index of this Section is included for convenience:
PART 2 PRODUCTS
2.01 MATERIALS
A. Construct fiberglass reinforced plastic identification signs and nameplates of 70
mils thick fiberglass reinforced plastic conforming to ASTM D709.
B. Provide fiberglass reinforced plastic process with a blemish free, low gloss
surface of superior permanence and durability in the colors selected. Provide
each identification sign and nameplate in two colors and with the legend
specified. Provide the backside of the sign in black or some other uniform
color.
C. Provide lettering made by permanent embedment of subsurface printed
graphics in the material so as to produce a clear, legible sign. Do not place
lettering, symbols or markings containing the name of the manufacturer on the
signs. The contract number and year of the Contract as given on the Contract
Drawings may be placed in small lettering on the front of the sign, if approved
by the Engineer.
D. Provide signs for piping and valve identification with two 3/8 inch diameter
grommet-protected holes located on the long side center line, the center of the
hole to be ½ inch from the edge. Provide nameplates for equipment with four
3/8 inch diameter grommet-protected holes, the center of the hole located ½
inch away from the edges. Provide all holes with suitable brass or stainless
steel grommets.
E. Construct all signs and nameplates in conformity with ASTM D523, D638,
D646, D790, D792 and D5420.
2.02 DIMENSIONS OF SIGNS AND TAGS
A. Provide identification signs and nameplates rectangular in shape and of the
dimensions specified below. A dimensioned tolerance of plus or minus 1/16
inch is permissible.
15076-3 11/2017
1915
DETAILED SPECIFICATION 15076H – PIPING AND EQUIPMENT
IDENTIFICATION
CONTRACT DEL-260H
Sign Dimensions
TYPE OF SIGN (Width x Length)
PIPE IDENTIFICATION -
1. Outside diameter of pipe
(including pipe insulation):
a. 4 inches and larger
3-1/2 X 12 INCHES
b. less than 4 inches 1-1/2 x 7 inches
VALVE IDENTIFICATION -
1. Valve tags 2 inches diameter
2. Operating stands for valves 1-1/2 x 7 inches
NAMEPLATES -
1. Equipment and Ductwork 3-1/2 x 12 inches
15076-4 11/2017
1916
DETAILED SPECIFICATION 15076H – PIPING AND EQUIPMENT
IDENTIFICATION
CONTRACT DEL-260H
8. Heptane
9. Kerosene
10. Ethyl alcohol
11. Ethyl acetate
12. Transformer oil
13. Heavy duty detergents
14. Water
B. Submit certification on acid resistance to the Engineer prior to installation.
2.05 COLORS
A. Code pipeline signs, equipment and ductwork in basic colors.
B. Provide brilliant colors, distinctive shades matching as closely as possible
(without custom color blending) the following basic colors as specified by the
Munsell Color System (MN):
15076-5 11/2017
1917
DETAILED SPECIFICATION 15076H – PIPING AND EQUIPMENT
IDENTIFICATION
CONTRACT DEL-260H
COLORS
Service Line Letters Background
22. HEATING, VENTILATING
AND CONDITIONING AIR Green Charcoal
(Equipment And Ductwork)
system. Provide identification code for each valve, damper and control without
duplication. Provide lettering on identification tags not less than 5/16 inch high
and limited to two lines. Lettering in correct color combination; stenciled or
painted numbers and lettering will not be accepted.
2.08 ARROWS
A. Make direction-of-flow arrows for attachment to pipe and ductwork
identification signs from No. 16 U.S. gauge Type 316L stainless steel, the full
width of the sign. Make the arrow head with a tapered point, about 90 degrees
at the apex, extending one half of the sign width from the sign edge and one
half of the sign width extending under the sign. Finish all edges of the arrow.
Make point with a radius of 1/4 inch for the 3-1/2 inch wide sign and a radius
of 3/16 inch for the 1-1/2 inch wide sign. Punch detents on the arrows to prevent
twisting of the point. Drill one hole in the arrow in alignment with the hole in
the pipe identification sign so that both sign and arrow can be mounted with the
same screw and bracket.
B. Submit sample direction-of-flow arrows for both sizes of pipe identification
signs to the Engineer for approval before installation.
2.09 NAMEPLATES
A. Provide nameplates for equipment in the same color combination as the medium
they service. Legends for nameplates must follow the terminology shown.
Provide numbering system as described in the Operation and Maintenance
Manual.
B. The following is a representative list, not necessarily complete, of nameplate
legends with appropriate color combinations to which the equipment
identification number must be added:
NAMEPLATES
Legend Color Code
First Line (1) Second Line (2) Lettering Background
AIR HANDLING UNIT UNIT ** White Charcoal
EXHAUST FAN ** White Charcoal
SUPPLY FAN ** White Charcoal
PUMP – HEATING HW ** White Charcoal
(1)
Nominal limit of 18 letters, numerals and spaces.
(2)
Nominal limit of 17 letters, numerals and spaces.
15076-7 11/2017
1919
DETAILED SPECIFICATION 15076H – PIPING AND EQUIPMENT
IDENTIFICATION
CONTRACT DEL-260H
NAMEPLATES
Legend Color Code
First Line (1) Second Line (2) Lettering Background
*Where equipment is mounted on roofs or where exposed to the public view, such as in lobby or
office areas, the color will be selected by the Architect.
**The legend on these nameplates also includes the appropriate six-digit numeral
and letter designation for such equipment and structures as specified
by the Operation and Maintenance Manual.
Pipeline Identification
ABBR. Process/Service Line Fed. Std. 595B Color
HWR Hot Water Return (heating) Orange 12215
HWS Hot Water Supply (heating) Orange 11400
HVACEX HVAC Exhaust Gray 14158
HVACS HVAC Supply Gray 14056
PART 3 EXECUTION
3.01 LOCATION
A. Locate identification signs for piping and ductwork along straight line runs at
intervals of not more than 30 feet, near valves, branches and junction points and
where pipes and ductwork pass through walls or ceilings. Place direction-of-
flow arrows as shown or required. Place all identification signs so as to be
easily visible from operating locations. Locate nameplates on equipment at
readily visible levels in such positions relative to the equipment so as to prevent
damage to the nameplate.
15076-8 11/2017
1920
DETAILED SPECIFICATION 15076H – PIPING AND EQUIPMENT
IDENTIFICATION
CONTRACT DEL-260H
3.02 MOUNTING
A. Mount identification signs and arrows parallel and tangent to the pipe and
ductwork by fastening with screws, plastic or fiber washers, threaded brackets
and banding straps and seals. Provide screws and brackets of stainless steel
with 5/16 - 18 American Standard Coarse Threads; provide No. 25 U.S. gauge
Type 316 stainless steel, 3/4 inch wide bands.
B. Where pipe and ductwork is insulated, use care in mounting the signs so to
prevent the banding straps from crushing the insulation.
C. Provide mounting assembly "Steelbinder" strapping unit as manufactured by:
1. A.J. Gerrard & Co., Des Plaines, Illinois,
2. Independent Metal Strap Co., Inc., Roslyn, N.Y.
3. Or approved equal.
D. Mount nameplates in a manner specifically approved by the Engineer after the
installation of equipment. Submit details of the method of fastening to the
Engineer for approval. Provide fastening of Type 316 stainless steel
construction.
E. Mount valve and damper identification signs with approved stainless steel
brackets or approved stainless steel strapping in such a fashion that sharp
corners or edges on signs, brackets, bolts, chain or strapping will not constitute
a hazard to personnel operating the valves. Since it is impractical to detail each
means of attachment in the Detailed Specifications or on the Contract
Drawings, each type of attachment shall be approved on a case-by-case basis.
Submit for approval sketches of each type proposed.
F. Do not attach identification tags or signs to handwheels. Use of flange bolts or
bonnet bolts as a means of attachment of brackets will receive consideration.
Provide all attachment devices and bolting of Type 304 stainless steel.
END OF SECTION
15076-9 11/2017
1921
DETAILED SPECIFICATION 15076H – PIPING AND EQUIPMENT
IDENTIFICATION
CONTRACT DEL-260H
15076-10 11/2017
1922
DETAILED SPECIFICATION 15081H - PIPING INSULATION
CONTRACT DEL-260H
SECTION 15081H
Piping Insulation
PART 1 GENERAL
1.01 SECTION INCLUDES
A. This Section includes insulation and jacketing requirements for piping systems,
including piping, valves and accessories. The Contractor shall provide all labor,
materials, equipment and incidentals as shown, specified or required to furnish and
install the piping insulation work.
B. The following index of this Section is included for convenience.
15081H-1 11/2017
1923
DETAILED SPECIFICATION 15081H - PIPING INSULATION
CONTRACT DEL-260H
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the Lump Sum price bid for Contract Item H-LS-1, as specified in
Section 01270 – Measurement and Payment.
1.04 REFERENCES
A. ASTM C 195 - Standard Specification for Mineral Fiber Thermal
Insulating Cement
B. ASTM C 240 - Standard Test Methods of Testing Cellular Glass
Insulation Block
C. ASTM C 411 - Standard Test Method for Hot-Surface Performance of
High-Temperature Thermal Insulation
D. ASTM C 534 - Standard Specification for Preformed Flexible
Elastomeric Cellular Thermal Insulation in Sheet and Tubular Form
E. ASTM C 552 - Standard Specification for Cellular Glass Thermal
Insulation
F. ASTM C 547 - Standard Specification for Mineral Fiber Pipe Insulation
G. ASTM C 1136 - Standard Specification for Flexible, Low Permeance
Vapor Retarders for Thermal Insulation.
H. ASTM D 1056 - Standard Specification for Flexible Cellular Materials -
Sponge or Expanded Rubber
I. ASTM E 84 - Standard Test Method for Surface Burning
Characteristics of Building Materials
J. ASTM E 96 - Standard Test Method for Water Vapor Transmission of
Materials
K. Building Code of the City of New York
L. Energy Conservation Construction Code of New York State
M. NFPA 255 - Surface Burning Characteristics of Building Materials
1.05 SUBMITTALS
A. General: The Contractor shall submit Shop Drawings and all submittals for the
approval of the Engineer. Submittals shall include, but not be limited, to:
1. Product Data: insulation and related materials. Submit the manufacturer’s
technical product data, insulation materials, densities, fire ratings, flame-
spread ratings, smoke-developed ratings material safety data sheets and
installation instructions for each type of piping insulation and related
materials. Submit a schedule showing the manufacturer’s product number,
k-value, thickness, and furnished accessories for each piping system
requiring insulation.
15081H-2 11/2017
1924
DETAILED SPECIFICATION 15081H - PIPING INSULATION
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. The insulations used may be as manufactured by:
1. Style A Insulation:
a. Owens Corning
b. Johns Manville
c. Or approved equal.
2. Stainless Steel Jacketing:
a. Childers Product Company.
b. RPR Products, Inc.
c. Or approved equal.
3. Thermal Hanger Shields:
a. Pipe Shields Inc.
b. Buckaroos Inc.
c. Or approved equal.
15081H-3 11/2017
1925
DETAILED SPECIFICATION 15081H - PIPING INSULATION
CONTRACT DEL-260H
moisture barrier. Adjacent sections shall butt together and shall be secured
with a weather-proof butt strap. Jacketing shall be secured with 3/4-inch
wide, 0.015-inch thick stainless steel bands at a maximum spacing of twelve
inches. All edges of strapping shall be factory deburred. All insulated
fittings shall be finished in the same manner, using 0.024-inch thick type
316 stainless steel preformed fitting covers and fabricated covers made from
the same material for valves, flanges, tees, in-line accessories, and other
pipeline appurtenances. Type 316 stainless steel end caps shall be provided
at the ends of the pipelines.
C. Accessories
1. Provide staples, bands, wires and cement as recommended by the insulation
manufacturer and approved by the Engineer for the applications indicated.
2. Provide adhesives, sealers, and protective finishes as recommended by the
insulation manufacturer and approved by the Engineer for the applications
indicated.
D. Thermal Hanger Shields
1. Provide insulated pipe protectors consisting of a 360-degree high density,
100 psi, waterproofed calcium silicate inserts encased in 360-degree sheet
metal.
2. Provide the thickness of the insulation insert to be the same as the adjoining
pipe insulation, and sheet metal gauge in accordance with the
manufacturer’s recommendations.
3. Pipe hangers and supports provided in conjunction with the thermal hanger
shields shall meet the requirements of General Specification 15060 -
Hangers and Supports.
PART 3 EXECUTION
3.01 INSPECTION
A. General: Examine areas and conditions under which piping insulation is to be
installed. Do not proceed with Work until unsatisfactory conditions have been
corrected in manner acceptable for insulation installation, as determined by the
Engineer.
3.02 INSTALLATION
A. General: Install piping insulation products in accordance with the manufacturer’s
recommendations and approved Shop Drawings, and as specified in Contract
Documents. Install piping insulation products in accordance with the Building
Code of New York State. Install all products in accordance with the recognized
industry practices so that insulation serves its intended purpose. Insulated thermal
hangers shields shall be installed at all support points, except where otherwise
indicated.
B. Piping Insulation:
15081H-5 11/2017
1927
DETAILED SPECIFICATION 15081H - PIPING INSULATION
CONTRACT DEL-260H
15081H-6 11/2017
1928
DETAILED SPECIFICATION 15081H - PIPING INSULATION
CONTRACT DEL-260H
D. All jacket openings - such as at overlaps of jackets with thermal hanger shields,
around valve stems and similar projections - shall be sealed with nonhardening,
waterproof, clear or white sealing compound so that upon completion the insulation
is essentially watertight.
3.03 EXISTING INSULATION REPAIR
A. Repair sections of existing piping insulation that are damaged during construction.
Use insulation of same thickness as the existing insulation. Install a new jacket
lapping and sealer over the existing insulation. If existing insulation is painted,
paint new insulation to match the existing surface color. If existing insulation is
jacketed, replace damaged jacketing with new jacket.
3.04 PROTECTION AND REPLACEMENT
A. Protection: Insulation shall be protected against dirt, water, chemical or mechanical
damage before, during and after installation. Follow methods which are required
for protection of the insulation work during the remainder of construction period,
to avoid damage and deterioration.
B. Replacement: Any insulation or covering damaged prior to final acceptance of the
Work shall be satisfactorily repaired or replaced, including units with vapor barrier
damage and moisture saturated units.
3.05 PAINTING AND CLEANING
A. Piping insulation shall not be painted except where otherwise noted for existing
insulation repair.
B. The Contractor shall remove all debris, waste materials and loose foreign matter
resulting from installation.
3.06 PIPING SYSTEM INSULATION SCHEDULE
A. Hot Water Piping Systems (to 250 Degrees F)
1. Style:
a. Insulation shall be Style A for pipe sizes up to and including 30-
inch.
2. Jacketing:
a. Stainless Steel.
3. Thickness: The Contractor shall provide the following minimum
thicknesses for the purpose of reducing heat loss and preventing injury to
workers:
a. Insulation shall be 1-1/2-inches thick for pipe sizes up to and
including 1-1/2-inches.
b. Insulation shall be 2-inch thick for pipe sizes larger than 1-1/2-
inches.
15081H-7 11/2017
1929
DETAILED SPECIFICATION 15081H - PIPING INSULATION
CONTRACT DEL-260H
END OF SECTION
15081H-8 11/2017
1930
DETAILED SPECIFICATION 15185 – HYDRONIC PUMPS
CONTRACT DEL-260H
SECTION 15185
Hydronic Pumps
NOTE: This Detailed Specification 15185 – Hydronic Pumps has been prepared
specifically for the Work of this Contract. There is no corresponding General
Specifications 15185 – Hydronic Pumps.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Contractor shall furnish, install, test and place in satisfactory operation Hydronic
Pumps.
15185-1 11/2017
1931
DETAILED SPECIFICATION 15185 – HYDRONIC PUMPS
CONTRACT DEL-260H
15185-2 11/2017
1932
DETAILED SPECIFICATION 15185 – HYDRONIC PUMPS
CONTRACT DEL-260H
15185-3 11/2017
1933
DETAILED SPECIFICATION 15185 – HYDRONIC PUMPS
CONTRACT DEL-260H
necessary for the proper operation of the equipment provided under this
Specification, as specified in Detailed Specification 01781 – Project Closeout.
1. The oil, grease, and special lubricants furnished shall be sufficient for the
required operation of the equipment prior to its final acceptance, and for the
operation of the equipment during the maintenance and guaranty period
specified in Article 24 of the Standard Construction Contract.
2. The oil, grease, and special lubricants furnished under this Specification
shall, wherever possible, be standardized and consolidated with those
furnished other Specifications, as specified in Detailed Specification 01781 –
Project Closeout.
1.10 ANCHOR BOLTS
A. Type 316 stainless steel anchor bolts (and related hardware, including, but not limited
to, nuts and washers) shall be included in the supply of the equipment provided under
this Specification, and shall be installed by the Contractor in accordance with the
equipment manufacturer’s instructions.
1.11 EQUIPMENT IDENTIFICATION
A. The Contractor shall provide corrosion-resistant nameplates, securely affixed in a
conspicuous place, on each item of equipment. Nameplates shall conform to the
requirements of Detailed Specification 15076 – Piping and Equipment Identification,
and shall bear the manufacturer’s name or trademark and such other information as is
specified or deemed necessary by the manufacturer to complete the identification.
Nameplate numbering shall be as specified or shown on the Contract Drawings. The
Engineer may change or supplement such numbering at the time of or at any time
before the approval of Shop Drawings.
1.12 MANUFACTURER’S REPRESENTATIVE
A. The Contractor shall provide the services of a qualified manufacturer’s representative
to: assist in the installation of the equipment; check the installation before the
equipment is placed into operation; assist in the performance of field tests; assist in
the start-up of the equipment; and train the maintenance staff in the care, operation,
and maintenance of the equipment. The services provided shall be in accordance
with the requirements of Article 12 of the General Conditions and Detailed
Specification 01732 – Installation of Equipment, Detailed Specification 01811 –
Preliminary and Final Field Tests, and Detailed Specification 01821 – Equipment
Start-Up and Training.
B. The Engineer reserves the right to require that any unused person-days from any visit
be applied to any other specified visit.
C. Person-days shall be understood only as days spent on site, not in transit.
D. Unless otherwise authorized by the Engineer, the manufacturer’s representative shall
15185-5 11/2017
1935
DETAILED SPECIFICATION 15185 – HYDRONIC PUMPS
CONTRACT DEL-260H
be a direct employee of the equipment manufacturer, with at least three (3) years’
experience in the installation, testing, and start-up of equipment of the type provided
under this Specification. The manufacturer’s sales and marketing personnel will not
be accepted as manufacturer’s representatives.
E. The manufacturer’s representative shall sign in and out at the office of the Engineer
each day they are at the Site.
F. Reports: The Contractor shall submit a report from the manufacturer for each visit to
the Site of the manufacturer’s representative. The report shall provide complete
information regarding the visit, including, but not limited to, dates, times, subject
equipment, tasks performed, persons contacted, problems corrected, test results,
training provided, and other pertinent information.
G. In addition to the above, the Contractor shall provide the services of person(s)
authorized by the manufacturer to witness the unloading at the Site of the equipment
provided under this Specification, and to ascertain the condition of said equipment.
Manufacturers’ sales and marketing personnel may be accepted as authorized
person(s) to perform these specific tasks. The Contractor shall submit to the
Engineer a report, completed by the authorized person(s) and certified by the
equipment manufacturer, documenting the findings of the authorized person(s).
1.13 PAINTING
A. Factory painted with the manufacturer’s standard painting system.
1.14 DELIVERY, STORAGE, AND HANDLING
A. The Contractor shall deliver, store, and handle the equipment and materials provided
under this Specification as specified in Detailed Specification 01651 – Transportation
and Handling of Materials and Equipment and Detailed Specification 01661 –
Protection of Materials and Equipment.
1.15 SHOP TESTS
A. In addition to Preliminary and Final Field Tests required in Detailed Specification
01811 – Preliminary and Final Field Tests, the Contractor shall provide the following
tests:
1. No additional tests required.
PART 2 PRODUCTS
2.01 PUMP MANUFACTURERS
A. Equipment/Materials provided under this Specification shall be manufactured
(including all standard equipment, unless otherwise specified) by:
1. Bell & Gossett, Division of ITT, Morton Grove, IL - Series 60
15185-6 11/2017
1936
DETAILED SPECIFICATION 15185 – HYDRONIC PUMPS
CONTRACT DEL-260H
PART 3 EXECUTION
3.01 INSTALLATION
A. Examine equipment at time of delivery for damaged or missing components.
B. Do not install defective components, Contractor shall not proceed with installation
until all items found defective have been corrected or replaced.
C. Install equipment in accordance with the manufacturer's instructions and
recommendations.
D. Install equipment so that sufficient access and working space is provided for safe
operation and maintenance.
3.02 FIELD TESTING
A. Preliminary and final field test shall be performed for all equipment provided under
this Specification, as specified in Article 13 of the General Conditions and Detailed
Specification 01811 – Preliminary and Final Field Tests.
3.03 START-UP AND ADJUSTMENT
A. Check all controls, interlocks and power connections.
B. Demonstrate equipment performance.
3.04 CLEANING
A. Cleaning and site maintenance shall be performed for all equipment provided under
this Specification, as specified in Detailed Specification 01740 - Cleaning and Site
Maintenance.
B. Clean dirt and marks and other debris from equipment.
C. Remove debris and waste material resulting from installation.
END OF SECTION
15185-8 11/2017
1938
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
SECTION 15515
Piping, Valves and Accessories
NOTE: This Detailed Specification 15515 – Piping, Valves and Accessories has been
prepared specifically for the Work of this Contract. There is no corresponding
General Specifications 15515 – Piping, Valves and Accessories.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Contractor shall furnish, install, test and place in satisfactory operation piping, valves
and accessories for HVAC systems.
B. Coordination:
1. Review installation procedures under this and other Sections and coordinate the
installation of items that must be installed concurrent with or before the
installation of piping, valves and accessories pursuant to this Section.
15515-2 11/2017
1940
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
15515-3 11/2017
1941
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
1.06 SUBMITTALS
B. Contractor shall submit the Shop Drawings for the approval of the Engineer.
Submittals shall include, but not be limited to the following:
1. Working Drawings.
2. Operation and Maintenance Manuals.
3. List of Spare Parts, Special Tools and Supplies.
4. Reports of Certified and Witnessed Shop Tests.
5. Reports and Field Tests.
6. Reports of Manufacturer’s Representative Site Visits.
C. Working Drawings shall include, but not be limited to, the following:
1. Equipment specifications and data sheets, with identification of all materials
used and methods of fabrication.
2. Complete assembly, layout, installation and Shop Drawings, with clearly
marked dimensions.
3. Equipment cross-section drawings.
4. Manufacturer’s deliver, storage, and handling requirements.
5. Manufacturer’s installation instructions and recommendations.
6. Weights of equipment component parts, assembled weights of equipment,
and total shipping weight. As applicable, include dynamic loads and weight
when full.
7. Comprehensive schematic diagrams showing the wiring for each electrical or
electro-mechanical equipment item, as well as interconnecting and point-to-
point field wiring diagrams. Point-to point field wiring diagrams shall
comply with Article 2.01 of Detailed Specification 16010 – General
Electrical Requirements.
8. Certification of manufacturing facility.
9. Certification of welders, pipefitters, and other workmen.
10. Painting details.
11. Equipment nameplate data.
12. Document for instrumentation and control equipment as specified herein.
13. Submittals specified in Detailed Specification 16221 – Electric Motors.
15515-4 11/2017
1942
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
2. The oil, grease, and special lubricants furnished under this Specification
shall, wherever possible, be standardized and consolidated with those
furnished other Specifications, as specified in Detailed Specification 01781 –
Project Closeout.
1.09 ANCHOR BOLTS
A. Type 316 stainless steel anchor bolts (and related hardware, including, but not limited
to, nuts and washers) shall be included in the supply of the equipment provided under
this Specification, and shall be installed by the Contractor in accordance with the
equipment manufacturer’s instructions.
1.10 EQUIPMENT IDENTIFICATION
A. The Contractor shall provide corrosion-resistant nameplates, securely affixed in a
conspicuous place, on each item of equipment. Nameplates shall conform to the
requirements of Detailed Specification 15076 – Piping and Equipment Identification,
and shall bear the manufacturer’s name or trademark and such other information as is
specified or deemed necessary by the manufacturer to complete the identification.
Nameplate numbering shall be as specified or shown on the Drawings: the Engineer
may change or supplement such numbering at the time of or at any time before the
approval of Shop Drawings.
1.11 MANUFACTURER’S REPRESENTATIVE
A. The Contractor shall provide the services of a qualified manufacturer’s representative
to: assist in the installation of the equipment; check the installation before the
equipment is placed into operation; assist in the performance of field tests; assist in
the start-up of the equipment; and train the maintenance staff in the care, operation,
and maintenance of the equipment.
B. The services provided shall be in accordance with the requirements of Article 12 of
the General Conditions and Detailed Specification 01732 – Installation of
Equipment, Detailed Specification 01811 – Preliminary and Final Field Tests, and
Detailed Specification 01821 – Equipment Start-up and Training.
1.12 PAINTING
A. Equipment shall be factory painted with the manufacturer’s standard painting system
except where otherwise noted below.
1.13 DELIVERY, STORAGE, AND HANDLING
A. The Contractor shall deliver, store, and handle the equipment and materials provided
under this Specification as specified in Detailed Specification 01651 – Transportation
and Handling of Materials and Equipment and Detailed Specification 01661 –
Protection of Materials and Equipment.
15515-7 11/2017
1945
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 GENERAL
A. The Contract Documents show the general arrangement and extent of the Work to be
completed. The exact location and arrangement of all parts shall be determined as
the Work progresses. The exact location of all parts of the Work must be governed
by the general building plans and the actual building conditions.
B. The Contract Drawings show an indication of the arrangement of equipment and
piping and is as nearly correct as can be determined in advance of the actual
construction of the Work. Equipment, piping and appurtenances found to interfere
with the construction of the building, plumbing apparatus and piping, electrical
wiring or other obstructions, etc., must be changed in location to clear such
obstructions.
C. The connections shown to the various units are intended as an indication only. The
actual connections at the time of installation to be made and arranged to suit the
requirements of each case and adequately provide for expansion and circulation and
minimize the amount of space required for the same.
D. The Drawings show the general arrangement of all systems. Should local conditions
necessitate rearrangement of one (1) or more of the systems, the Contractor, before
proceeding with the Work, shall prepare and submit complete drawings showing all
details of the proposed rearrangement for written approval.
E. The Contract Drawings do not necessarily show all the offsets, fittings, accessories
and details which may be required. Contractor shall examine and be familiar with all
Contract Drawings and the specifications of the E and G DEL-260 contracts which
may affect the installation of the Work under this Contract. The Contractor shall
furnish all items or perform all work required to complete the systems/HVAC Work
if not explicitly provided or performed under the other DEL-260 contracts.
15515-8 11/2017
1946
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
2.02 PIPING
A. Copper Tube:
1. Tube:
a. Reference: ASTM B88.
b. Aboveground:
1) Type: K.
2) Temper: Hard drawn.
c. Below ground:
1) Type: K.
2) Temper: Hard drawn.
2. Fittings:
a. Solder:
b. Type:
1) Cast copper alloy conforming to the requirements of
ASME/ANSI 16.18.
2) Wrought copper or copper alloy conforming to the
requirements of ASME/ANSI 16.22.
c. Flanged:
1) Reference: ANSI B16.24, 150 lb. class.
2) Type: Cast copper alloy.
3) Gaskets:
a) Reference: ASTM D 1330, Grade 1.
b) Type: Non-asbestos, compressed carbon fiber
gasketing with SBR binder, 1/8-inch thick
manufactured by Garlock Gasket Co., Series HTC
9800, or equal.
3. Joints:
a. Soldered using alloys containing less than 0.2 percent lead (Pb) as
listed in ASTM B32. Soldering flux shall conform to the
requirements of ASTM B 813. Joint preparation and operations shall
be in accordance with the requirements of ASTM B 828.
15515-9 11/2017
1947
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
B. Steel Pipe:
1. Pipe:
a. Reference, ANSI B36.10 and ASTM A 53/A 53M.
b. Type: Seamless steel pipe.
c. Weight: Schedule 40.
d. Finish: Black.
e. End Finish: Plain.
2. Fittings:
a. Threaded:
1) Reference: ANSI B16.3.
2) Type: Malleable iron.
b. Flanged:
1) Reference: ANSI B16.1, Class 125 or ANSI B16.5,
Class 150.
2) Gaskets:
a) Reference: ASTM D 1330, Grade 1.
b) Type: Non-asbestos, compressed carbon fiber
gasketing with SBR binder, 1/8-inch thick
manufactured by Garlock Gasket Co., Series HTC
9800, or equal.
c. Welded:
1) Reference: ANSI B16.9.
2) Type: Butt welded.
C. Unions:
1. Copper Tube:
a. Manufacturers: Provide products of one (1) of the following:
1) Mueller Industries, Inc.
2) Nibco, Inc.
3) Or approved equal.
15515-10 11/2017
1948
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
material is specified.
8. Operation of levers and gates shall be designed so that the effort required to
operate the handwheel, lever or chain shall not exceed forty (40) pounds
applied at the extremity of the wheel or lever. The handwheels on valves
fourteen (14) inches and smaller shall not be less than eight (8) inches in
diameter.
9. Except where noted otherwise, all interior and exposed valves shall be
handwheel or lever operated.
10. All operators shall turn counter clockwise to open. Operators shall have the
open direction clearly and permanently marked. All valve operators shall be
provided with the valve by the valve manufacturer. Contractor, through the
valve manufacturer, shall be solely responsible for the selection of the proper
operator to confirm to the operating conditions specified herein. Field
calibration and testing of the operators and valves to ensure a proper
installation and an operating system shall be the responsibility of Contractor.
11. All raised face flanges, in conformance with ANSI B16.5, Class 150, shall be
milled flat.
B. Manufacturers: Provide products of one (1) of the following, except where indicated
otherwise:
1. Stockham Valves and Fitting Company, Cullman, AL.
2. Lunkenheimer Company, Cincinnati, OH.
3. Crane, Stamford, CT.
4. Or approved equal.
C. Bronze Body Ball Valves:
1. Reference: ASTM B 283.
2. Type: Two-piece body with standard port opening.
3. Construction:
a. Body: Brass.
b. Ball: Brass with hard chrome plated finish.
c. Stem: Brass.
d. Stem Packing: PTFE.
e. O-Rings: Viton.
f. Seats: PTFE.
15515-12 11/2017
1950
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
4. Screens:
a. Sizes 2-inch and smaller: 20-mesh, stainless steel with 0.031-inch
diameter openings.
b. Sizes 2-1/2-inch: Perforated stainless steel with 0.063-inch diameter
openings.
5. Pressure Rating: Class 125, 200 psi WOG.
G. Iron Body Gate Valves:
1. Reference: ANSI B16.1, ANSI B16.10, ASTM A 126 Class B, MSS P 70,
Type 1.
2. Type: Outside screw and yoke, rising stem.
3. Construction:
a. Body: Iron.
b. Disc: Bronze.
c. Bonnet: Bolt-on type.
d. Seat: Renewable bronze seat ring.
e. Packing: Acrylic and novaloid fibers Teflon impregnated, non-
asbestos.
4. Pressure Rating: Class 125, 200 psi WOG.
H. Iron Body Butterfly Valves:
1. Reference: ASTM A 126 Class B, MSS SP 67.
2. Type: Wafer body, lever operated, bubble tight shutoff.
3. Construction:
a. Body: Cast-Iron.
b. Disc: Ductile Iron.
c. Handle: Malleable iron.
d. Seat Sleeve: Viton.
4. Lever shall have a ten position indicator plate.
5. Pressure Rating: Class 125, 200 psi WOG.
I. Iron Body Globe Valves:
15515-14 11/2017
1952
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
1. Reference: ANSI B16.1, ANSI B16.10, ASTM A 126 Class B, MSS SP 85,
Type 1, Military Specification MIL-V-18826.
2. Type: Outside screw and yoke, rising stem.
3. Construction:
a. Body: Iron.
b. Disc: Renewable bronze disc.
c. Bonnet: Bolt-on type.
d. Seat: Renewable bronze seat ring.
e. Packing: Acrylic and novaloid fibers with Teflon, non-asbestos.
4. Pressure Rating: Class 125, 200 psi WOG.
J. Iron Body Check Valves:
1. Reference: ANSI B16.1, ANSI B16.10, ASTM A 126 Class B, MSS SP 71,
Type 1, Military Specification MIL-V-18436.
2. Type: Horizontal swing.
3. Construction:
a. Body: Iron.
b. Disc, Seat Ring: Bronze.
c. Cap: Bolt-on type.
4. Rating: Class 125, 200 psi WOG.
K. Cast-Iron Strainers:
1. Manufacturers: Provide products of one (1) of the following:
a. Mueller Steam Specialties, St. Paul, NC.
b. Armstrong Machine Works, Three Rivers, MI.
c. Or approved equal.
2. Type: Wye self-cleaning strainer.
3. Construction:
a. Body: Iron body with tapered seats in both the body and cover flange
for secure screen retention.
b. Cap: Bolted cap with gasket.
15515-15 11/2017
1953
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
1. Materials:
a. Body: Cast-Iron.
b. Diaphragm and Seat: EPDM.
c. Internal Wetted Parts: Brass.
d. Maximum Operating Pressure: 125 psig.
e. Maximum Operating Temperature: 250 degrees F.
f. ASME labeled for relieving pressure.
g. Low blow down differential.
h. Fluid shall not be permitted to discharge into the spring chamber.
i. Manufacturers: Provide products of one (1) of the following:
1) Bell & Gosset, Division of ITT, Morton Grove, IL
2) Or approved equal.
C. Thermometers:
1. Manufacturers: Provide products of one (1) of the following:
a. H.O. Trerice Company.
b. Weksler Instrument Company.
c. Or approved equal.
2. Range:
a. 30 degrees F to 240 degrees F temperature range in maximum
increments of 2 degrees F for hot water systems.
3. Type: Adjustable Angle Column Type Thermometer.
a. Construction:
1) Case: Nine-inch smooth die cast aluminum.
2) Window: Clear acrylic plastic or glass held in place with
stainless steel cap.
3) Tube: Lens front red appearing mercury tubing.
4) Scale: White background with black figures and markings.
5) Stem: Brass with union connections.
15515-20 11/2017
1958
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
15515-21 11/2017
1959
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
15515-23 11/2017
1961
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
A. All bolts, nuts, washers and other fastening hardware shall be Type 304 stainless steel
construction.
B. Hardware shall be provided in accordance with the manufacturer’s recommendations
for type and size.
2.08 MATERIAL SCHEDULES
A. Piping:
1. Use types of pipe and fittings as specified below, unless otherwise specified
or shown.
2. All piping 2-1/2-inches and smaller run within the interior and exterior of a
building shall be copper.
3. All piping 3-inches and larger run within the interior and exterior of a
building shall be welded steel.
4. Use “wrought copper” fittings for copper tubing.
5. Use “butt welded” fittings for welded steel pipe connections.
B. Valves:
1. All valves for copper tubing shall be bronze or brass bodied, unless otherwise
specified.
2. All valves for steel piping shall be iron bodied, unless otherwise specified.
3. All valves 2-1/2-inches and smaller shall be of the sweat or screwed end type.
Adaptors for screwed or sweat connections shall be provided as required.
4. All valves 3-inches and larger shall be of the flanged end type.
PART 3 EXECUTION
3.01 INSTALLATION
A. General:
1. Examine equipment at time of delivery for damaged or missing components.
2. Do not proceed with installation of equipment until all items found defective
upon examination have been corrected.
3. Install equipment in accordance with the manufacturer's instructions and
recommendations.
4. Install equipment so that sufficient access and working space is provided for
safe operation and maintenance.
15515-24 11/2017
1962
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
5. Contractor shall provide all labor, tools, materials, and equipment necessary
for installation of the piping system. All piping shall be installed in
accordance with the Contract Documents in a neat workmanlike manner and
shall be set for accurate line and elevation. All piping shall be thoroughly
cleaned before installation, and care shall be taken to keep the piping clean
throughout the installation.
6. Before setting wall sleeves, pipes, castings and pipes to be cast-in-place,
Contractor shall coordinate with the Contract Drawings and Figures, which
may have a direct bearing on the pipe locations. Contractor shall be
responsible for coordinating the proper location of the pipes and
appurtenances during the construction with all trades.
7. Piping shall be attached to pumps, valves, equipment, etc., in accordance with
the respective manufacturer’s recommendations.
8. For piping assembled with threaded, solvent cemented, welded or soldered
joints, liberal use of unions shall be made. Unions shall be provided close to
main pieces of equipment and in branch lines to allow dismantling of piping
without disturbing main pipe lines or adjacent branch lines. A minimum of
one union per straight run of pipe between fittings and/or valves with
multiple lengths of pipe shall be used. Unions shall be placed downstream of
the shutoff or isolating valves. Where flanges are installed, unions shall be
omitted.
9. All changes in directions or elevations shall be made with fittings.
10. Piping shall not run above motor control centers, control panels or other
electrical equipment, unless directed by the Engineer, in writing. Piping
which must run above electrical equipment shall be provided with suitable
drip pans.
11. Piping shall be installed free of traps and with sufficient slope so that all of
the various piping systems may be drained to one or several points. In the
event that it is impossible to drain to a common point due to structural
obstructions and finished ceiling heights, furnish and install all additional
drain valves that may be required to completely drain piping systems.
Location of all drain valves shall be approved by Engineer prior to
installation.
12. Install all items as shown, specified, and as recommended by the
manufacturer.
13. Request instructions from Engineer, in writing, when there is a conflict
between the manufacturer's recommendations and the Contract Documents.
14. Present conflicts between piping systems or equipment or structures to
Engineer who shall determine corrective measures to be taken.
15515-25 11/2017
1963
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
15515-26 11/2017
1964
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
2. Install the valves so that they can be conveniently operated. Do not place
operators at angles other than parallel to the floors or walls.
3. Valves shall be supported as integral components of the piping systems.
4. Valve supports shall anchor the valves against an unbalanced force in either
direction. The magnitude of the force shall be based on a pressure equal to
twice the maximum working pressure with a maximum allowable stress of
1/2 of the support's yield strength.
F. Piping Layout in Building:
1. Slope piping up in direction of flow.
2. Water shall circulate freely with no evidence of trapping or air binding.
3. Runouts to units above the main shall be taken off top of main and pitch up to
units.
4. Runouts to units below the main shall be taken off bottom of main and pitch
to units.
5. Low points of piping shall have ball drain valves.
6. Threaded end unions or bolted end flange connections shall be provided for
removal of each piece of equipment or device without major dismantling.
7. Allow clearances for expansion and contraction of piping.
8. Provide flexible connectors for each pipe passing through building expansion
joints.
9. Do not block openings or passageways with piping.
10. Field Measurements: Take field measurements prior to installation to ensure
proper fitting of the Work.
11. Install straight runs true to building line.
12. Install vertical pipe truly plumb in all directions.
13. Install piping parallel or perpendicular to building walls. Piping at odd angles
and 45 degrees runs across corners will not be accepted.
14. Unless otherwise approved by Engineer, provide temporary caps or plugs
over all pipe openings at the end of each day, or when otherwise required or
directed by the Engineer to prevent foreign material from entering the piping
systems.
G. Pressure gage ranges shall be selected for proper sensitivity, so that the dial indicator
points to the approximate center of the dial in normal operation.
15515-27 11/2017
1965
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
H. Provide automatic air vents at all high points of water lines and where shown.
I. Provide nipple, 3/4-inch ball valve and short nipple with capped hose connection for
each hydronic strainer blow down.
J. Install fine mesh start-up screens in all strainers and replace with final stainless steel
screens after 30 days of pump operation.
K. Provide all supporting steel, brackets, etc. as required to support all equipment in an
approved manner.
L. Hard pipe all drain lines, relief valve drain lines, and air vents to nearest floor drain.
M. All thermometers shall be legible from a standing position on the floor.
N. Escutcheon plates shall be provided for all exposed piping penetrations.
O. Provide sleeves and mechanical seals where pipes pass through wall, roof and floor
slabs.
P. All connections between ferrous and non-ferrous piping materials shall be made with
dielectric couplings.
Q. Care shall be taken so as not to leave tool marks or abrasions on plated, polished or
soft metal piping.
R. Wherever changes in sizes of piping occur, changes shall be made with concentric
reducing fittings. The use of bushings is not permitted, unless otherwise shown.
S. Provide shutoff valves to each piece of equipment furnished.
3.02 FIELD TESTING
A. Preliminary and final field tests shall be performed for all equipment provided under
this Specification, as specified in Article 13 of the General Conditions and Detailed
Specification 01811 – Preliminary and Final Field Tests.
B. Field Tests:
1. Contractor shall provide all necessary labor and equipment required for the
field tests specified below including, but not limited to, air compressor,
gauges, conduit caps, temporary pipe and connections. Contractor shall
provide water for all testing and may use only water from an approved
source. Contractor shall also furnish and install all means and apparatus
required for getting the water into the pipeline and testing; including pumps,
gauges, and meters, plugs, caps, temporary blow-off piping and bypass
piping, etc., complete with any necessary reaction blocking to prevent pipe
movement during the testing. All pipelines shall be flushed clean and tested
in such lengths or sections as agreed upon between the Engineer and
Contractor. Contractor shall provide the Engineer reasonable notice of the
15515-28 11/2017
1966
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
time when he intends to test portions of the pipelines. The Engineer reserves
the right to request additional testing of any section or portion of a pipeline.
2. After flushing, all pipelines shall be hydrostatically tested to one and one half
times the maximum system design pressure, but not less than 50 psi.
Equipment not capable of being tested at the indicated pressure shall be
isolated and protected.
3. The piping shall be filled with water for a period of not less than eight hours,
then subject to the indicated test pressure. During the pressure test, there
shall be no leakage. All air shall be purged from the line before pressure
testing. The duration of the hydrostatic test shall be eight hours.
4. Any leaks or defective pipe disclosed by the hydrostatic test shall be
corrected by Contractor and the test repeated until passed.
C. Inspection:
1. Examine areas to receive piping and accessories for:
2. Defects that adversely affect execution and quality of the Work.
3. Deviations beyond allowable tolerances.
4. Start the Work only when conditions are satisfactory.
5. The Engineer reserves the right to reject or authorize replacement of piping
and accessories found to be defective or deviated from allowable tolerances.
3.03 START-UP AND ADJUSTMENT
A. Check all controls, interlocks and power connections.
B. Demonstrate equipment performance.
C. While system is operable, balance all equipment and valves to achieve design
conditions.
3.04 CLEANING
A. Cleaning and Site maintenance shall be performed for all equipment provided under
this Specification, as specified in Detailed Specification 01740 - Cleaning and Site
Maintenance.
B. Contractor shall provide all necessary labor and equipment required for flushing and
cleaning. Contractor shall provide water for all flushing and may use only water
from an approved source. Contractor shall also furnish and install all means and
apparatus necessary for getting the water into the pipeline and flushing including
pumps, gauges, meters, temporary blow off piping, bypass piping, etc., complete with
all required reaction blocking to prevent pipe movement during the procedure.
15515-29 11/2017
1967
DETAILED SPECIFICATION 15515 - PIPING, VALVES AND ACCESSORIES
CONTRACT DEL-260H
C. Before placing the hydronic piping system into service, Contractor shall thoroughly
clean all piping systems by thoroughly flushing with water and chemical cleaner. All
debris which may have entered the pipe during the construction period shall be
removed. If obstructions remain after cleaning, Contractor shall correct to the
satisfaction of the Engineer. Pipelines shall be flushed at a rate of at least 2.5 feet per
second for duration suitable to the Engineer.
D. Cleaning methods and procedures shall be as recommended by the manufacturer of
the cleaning agents and chemicals used. Chemical cleaning agents shall be as
manufactured by Oakite, Nalco, Dearborn, or approved equal.
E. After the cleaning period, empty all dirt pockets and clean all strainers.
F. Remove all dirt, rust, dust and any other obsturciton from hydronic piping systems
after installation.
G. Remove and dispose of all debris and waste from the Site resulting from installation.
3.05 PROTECTION OF EXECUTED WORK
A. Water Treatment:
1. The Contractor shall engage a suitable water treatment consultant such as
Drew Water Services, Nalco Chemical, or Betz or approved equal, to provide
a supervised water treatment program for a period of one year from the date
of initial treatment. Services shall include the following:
a. Provide all equipment and chemicals such as corrosion inhibitor,
descaler, and propylene glycol for freeze protection required for the
water treatment program.
b. Conduct test analysis of the system water.
c. Furnish trained personnel to supervise initial fill and instruct
designated Owner’s personnel in maintaining proper concentration
through water analysis and chemical dosage.
2. The water treatment consultant shall provide monthly visits to the facilities
for the purpose of running tests on samples of treated water, review the
performance of the treatment program and make written recommendations for
any changes in chemical dosages that may be needed. The consultant shall
submit a full written report describing the initial condition of the water and
the recommended corrective action taken after each monthly facility visit.
The report shall be submitted within a week of testing.
END OF SECTION
15515-30 11/2017
1968
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
SECTION 15720H
Heating and Ventilating Units
NOTE: This Detailed Specification 15720H – Heating and Ventilating Units replaces
General Specification 15720 – Heating and Ventilating Units in its entirety. All
Work for this Section shall fully conform to the requirements specified herein.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall provide all labor, materials, equipment and incidentals to
furnish and install all heating and ventilating units with the requirements specified
herein and as shown on the Contract Drawings or specified herein.
B. The equipment shall be furnished complete with all accessories, special tools, spare
parts, base attachments, mountings, anchor bolts and other appurtenances as
specified or as may be required for a satisfactory installation.
C. All heating and ventilating units shall be furnished in accordance with the schedule
shown on the Contract Drawings.
D. The following index of this Section is presented for convenience:
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section, all costs shall be
included in the Lump Sum price bid for Contract Item H-LS-1, as specified in
Section 01270 – Measurement and Payment.
1.04 REFERENCES
A. Equipment shall comply with the latest applicable provisions and recommendations
of the following, except as otherwise shown or specified.
1. American Society of Mechanical Engineers (ASME)
2. American Society of Testing Materials (ASTM)
3. Air Movement and Control Association (AMCA)
4. Air Conditioning and Refrigeration Institute (ACRI)
5. National Fire Protection Association (NFPA)
6. National Electrical Code (NEC)
7. American Society of Heating, Refrigeration and Air Conditioning
Engineers (ASHRAE)
8. Applicable Federal, State and local laws and/or ordinances
B. Where conflict arises between the requirements of the local codes and the
requirements of the above reference standards, the more stringent requirements
shall prevail.
1.05 SUBMITTALS
A. Contractor shall submit the Shop Drawings for the approval of the Engineer.
Submittals shall include, but not be limited to the following:
1. Preliminary Operation and Maintenance (O&M) Manuals.
2. Final Operation and Maintenance (O&M) Manuals.
3. Spare Parts List.
4. Special Tools List.
5. Reports of Certified Shop Tests.
B. Each submittal shall be identified by the applicable Equipment Identification
Number and Specification section.
C. Shop Drawings
1. Shop Drawings shall include but not be limited to:
a. Equipment specifications and data sheets identifying all materials
used and methods of fabrication.
b. Complete assembly, layout, installation and foundation drawings
with clearly marked dimensions.
15720H-2 11/2017
1970
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
practices of the trade, and shall operate satisfactorily when installed as shown on
the Contract Drawings.
B. All components of the Heating and Ventilating System be provided by one
manufacturer who shall match all components and provide equipment which
functions together as a system.
1.07 SPARE PARTS AND SUPPLIES
A. Furnish all special tools necessary to dissemble, service, repair and adjust the
equipment.
B. The following spare parts shall be furnished with each unit:
1. Two (2) sets of belts.
2. Two (2) sets of complete change of filters.
3. One (1) quart of touch-up paint.
C. Furnish all additional spare parts as recommended by the equipment manufacturers.
D. Spare parts lists, included with the shop drawing submittal shall indicate specific
sizes, quantities, and part numbers of the items to be furnished. Terms such as "1
lot of packing material" are not acceptable.
E. Parts shall be completely identified with a numerical system to facilitate parts
inventory control and stocking. Each part shall be properly identified by a separate
number.
PART 2 PRODUCTS
2.01 HEATING AND VENTILATING UNIT
A. General:
1. Heating and ventilating unit shall be industrial-grade custom equipment
conforming to the requirements and conditions listed under this Section.
Commercial grade units are not acceptable.
2. Heating and ventilating unit shall be specifically designed for the
performance and service conditions specified in these Detailed
Specifications.
3. Heating and ventilating unit shall be anchored to the building structure.
B. Manufacturers:
1. Engineered Air, De Soto, KS
2. Temtrol Inc, Okarche, OK.
3. Govenair, Oklahoma City, OK.
4. Or approved equal.
C. Material and Construction:
15720H-4 11/2017
1972
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
1. Units shall be complete with inlet damper, angled filters, horizontal tube
integral face and bypass heating coils, fan section and discharge module as
required. All parts of the equipment herein shall be amply proportioned for
all stresses that may occur during fabrication, shipment, erection and
continuous operation. All corresponding parts shall be interchangeable and
all parts subject to wear shall be standard pattern and easily replaceable.
Adequate lubrication shall be provided for bearings and lubrication points
shall be readily accessible.
2. Casing:
a. Unit casing shall be of minimum 16 gauge satin coat galvanized
sheet metal. All surfaces shall be cleaned with a degreasing solvent
to remove oil and metal oxides and finished with one coat of a two
component epoxy primer. Exterior surfaces shall also include a
polyurethane top coat.
b. All walls, roofs and floors shall be of formed construction, with at
least two breaks at each joint. Joints shall be secured by sheet metal
screws or pop rivets. Wall and floor joints shall be broken in for
rigidity. All joints shall be caulked with a water resistant sealant.
c. The following components shall be provided with a 22 gauge solid
galvanized metal liner over insulated areas:
1) Fan Sections
2) Coil Sections
3) Filter Sections
4) Access Sections
5) Underside of Unit (where visible)
d. Units shall be provided with access doors to the following
components: fans and motors; filters; dampers and operators; access
plenums. Access doors shall be large enough for easy access.
Contractor shall use hinged access doors when maintenance of
internal components is needed. Removing screwed wall panels for
access is not feasible and is not permitted under this contract.
e. Provide hinged access doors in welded steel frames. Doors shall be
fully lined with closed cell bulb gasket and Leverlok handles,
operable from both sides.
f. Casings shall be supported on structural channel supports, designed
and welded for low deflections. Integral lifting lugs shall be
provided for hoisting.
g. All units shall be internally insulated with 2-inch thick nominal 3
lb./cu.ft. density acoustic insulation.
15720H-5 11/2017
1973
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
3. Coils:
a. Coils shall be 5/8" O.D. constructed of copper tube, aluminum fin,
and copper headers with Schedule 40 steel pipe connectors.
b. Fins constructed of aluminum or copper shall be rippled for
maximum heat transfer and shall be mechanically bonded to the
tubes by mechanical expansion of the tubes. The coils shall have a
galvanized steel casing. All coils shall be factory tested with air at
300 psig while immersed in an illuminated water tank.
c. Headers with Schedule 40 steel pipe connections utilize male
National Pipe Thread (N.P.T.) up to 4-inch connections.
d. Provide an insulated header cover to conceal exposed headers.
e. Provide integral face and bypass coil-damper units arranged with
vertical tubes. The units shall consist of alternate vertical coil and
bypass sections in galvanized steel casings of not less than 18 ga.
Coil and bypass sections shall be balanced to provide equal air
pressure drop at each extreme of operation. Maximum header length
of a single section shall be 64 inches.
f. Multiple row coils shall be of staggered tube design circuited to
optimize capacity with minimum pressure drop.
g. Opposed blade dampers shall be provided on both face and bypass
channels on the entering airside. In addition, provide a single blade
damper on the leaving airside of the coil channel to eliminate coil
wiping. Blades shall be heavy gauge galvanized steel welded to
steel damper rods operating in oil impregnated bronze bushings.
Bushings shall be installed at no more than 48-inches on center.
Opposed blade dampers shall interlock on closing and require no
sealing gaskets. Damper linkage shall be non-adjustable to prevent
slippage and subsequent air leakage.
15720H-6 11/2017
1974
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
15720H-7 11/2017
1975
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
15720H-8 11/2017
1976
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
2.02 MOTORS
A. Motors shall be of the totally enclosed fan cooled type.
15720H-10 11/2017
1978
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
B. All motors shall be of the high premium energy efficient type. Motors rated greater
than 1,000 watts shall meet or exceed ASHRAE 90-75 requirements for a power
factor not less than 95 percent.
C. Motors shall be selected so that the maximum break horsepower required at any
point on the performance curve does not exceed the nominal motor horsepower;
operation in the service factor is not acceptable. Motors shall be mounted
externally on an adjustable base.
D. The drive shall be of the static-resistant, V-belt type with adjustable sheave.
E. For motors less than or equal to 10 Hp, the belts shall be selected for 120 percent
of the rated load at design conditions. For motors greater than 10 Hp the belts shall
be selected for 150 percent of the rated load at design conditions.
F. A removable belt guard with openings to allow for tachometer readings at both
drive and fan shafts shall be provided.
G. Motors shall comply with the requirements of Detailed Specification 16221 -
Electric Motors.
PART 3 EXECUTION
3.01 INSTALLATION
A. Heating and ventilation units shall be installed, connected and placed in satisfactory
working order in accordance with the manufacturer's instructions and details,
approved Shop Drawings, and the Contract Drawings.
3.02 IDENTIFICATION
A. Each unit of equipment shall be identified with the equipment item numbers given
on the Contract Drawings. A corrosion-resistant tag or nameplate, securely affixed
in a conspicuous place on each unit shall give the equipment item number,
manufacturer's name or trademark and such other information as the manufacturer
may consider necessary, or as specified, to complete identification.
3.03 TESTING
A. Preliminary and final field tests shall be performed for all equipment provided
under this Specification, as specified in Article 13 of the General Conditions and
Detailed Specification 01811 – Preliminary and Final Field Tests.
B. All tests shall be performed in accordance with the requirements of this Contract.
C. Motor tests in accordance with Detailed Specification 16221 - Electric Motors.
Field tests shall be performed in accordance with General Specification 15951 -
Testing, Adjusting and Balancing.
3.04 MANUFACTURER'S REPRESENTATIVE
A. The Contractor shall provide the services of a qualified manufacturer's technical
representative who shall adequately supervise the installation and testing of all
15720H-11 11/2017
1979
DETAILED SPECIFICATION 15720H – HEATING AND VENTILATING UNITS
CONTRACT DEL-260H
END OF SECTION
15720H-12 11/2017
1980
DETAILED SPECIFICATION 15761H – HEATERS, ELECTRIC
CONTRACT DEL-260H
SECTION 15761H
Heaters, Electric
NOTE: This Detailed Specification 15761H – Heaters, Electric replaces General Specifi-
cation 15761 – Heaters, Electric in its entirety. All Work for this Section shall fully
conform to the requirements specified herein.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall provide all labor, materials, equipment and incidentals as
shown, specified and required to furnish and install all electric heaters complete
with auxiliary equipment and accessories as shown, specified and/or required for
proper operation.
B. Schedule: Units shall be furnished in accordance with the equipment data schedules
as shown on the Contract Drawings.
C. The following index of this Section is presented for convenience:
15761H-1 11/2017
1981
DETAILED SPECIFICATION 15761H – HEATERS, ELECTRIC
CONTRACT DEL-260H
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section, all costs shall be
included in the Lump Sum price bid for Contract Item H-LS-1, as specified in
Section 01270 – Measurement and Payment.
1.04 REFERENCES
A. Reference Standards: Comply with applicable provisions and recommendations of
the following, except as otherwise shown or specified. General requirements of
this Contract shall supersede the Standards in case of conflict:
1. Air Moving and Conditioning Association (AMCA)
2. American Society of Heating, Refrigerating, and Air Conditioning
Engineers (ASHRAE)
3. National Electrical Manufacturers' Association (NEMA)
B. Where reference is made to one of the above standards, the revision in effect at the
time of bid opening shall apply.
1.05 SUBMITTALS
A. Contractor shall submit Shop Drawings and material specifications for the approval
of the Engineer. Submittals shall include, but not be limited, to the following:
1. Dimensions.
2. Capacities.
3. Materials of construction.
4. Finishes, standard and custom color chart for Engineer's approval.
5. Manufacturer's literature, illustrations, Specifications and engineering data.
6. Documentation from the factory substantiating painting systems in
accordance with the Specifications. Include types applied and dry film
thicknesses.
B. Operations and Maintenance (O&M) Manuals:
1. The Contractor shall submit O&M manuals in accordance with the
procedures and requirements of this Contract.
2. Two copies of a preliminary O&M manual shall be included in the Shop
Drawings submittal. Without inclusion of these manuals, the submittal will
be considered incomplete and will be returned without review.
1.06 QUALITY ASSURANCE
A. Manufacturer Qualifications:
B. Contractor’s Qualifications:
15761H-2 11/2017
1982
DETAILED SPECIFICATION 15761H – HEATERS, ELECTRIC
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 UNIT HEATERS
A. Manufacturers:
1. Products and Manufacturers: Provide one of the following:
a. Chromalox, Pittsburgh, PA - Type LUH.
b. Industrial Engineering and Equipment Company (INDEECO), St.
Louis, MO - Series IUH.
c. Or approved equal.
B. Details or Construction:
1. Casing:
a. Material: Minimum 18-gauge steel.
b. Finish: Phosphate undercoated and finished with polyester powder
coat.
2. Louvers: Individually adjustable louvers for up, down and perpendicular
air flow.
15761H-3 11/2017
1983
DETAILED SPECIFICATION 15761H – HEATERS, ELECTRIC
CONTRACT DEL-260H
PART 3 EXECUTION
3.01 INSPECTION
A. Inspect units for damage prior to installation and correct as necessary.
3.02 FIELD TESTING
A. Preliminary and final field tests shall be performed for all equipment provided un-
der this Specification, as specified in Article 13 of the General Conditions and De-
tailed Specification 01811 – Preliminary and Final Field Tests.
3.03 INSTALLATION
A. Unit heaters shall be installed, connected and placed in satisfactory working order
in accordance with the manufacturer’s instructions and details, and the Contract
Drawings.
B. Each unit of equipment shall be identified with the equipment item numbers given
on the Contract Drawings. A corrosion resistant tag or nameplate, securely affixed
in a conspicuous place on each unit shall give the equipment item number,
manufacturer’s name or trademark and such other information as the manufacturer
may consider necessary, or as specified, to complete identification.
C. Install cabinets level and plumb.
D. Install units in accordance with details on the Contract Drawings and approved
Shop Drawings.
E. Coordinate with ceiling grid for ceiling recessed units installation.
3.04 CLEANING
A. Clean tar, cement or other dirt from units.
B. Remove debris and other waste material resulting from installation.
3.05 ADJUSTMENTS
A. Conform to requirements of Detailed Specification 15951 - Testing, Adjusting and
Balancing.
B. Set air deflectors for proper air delivery.
C. Check room thermostat and wiring connections to heater.
END OF SECTION
15761H-5 11/2017
1985
DETAILED SPECIFICATION 15761H – HEATERS, ELECTRIC
CONTRACT DEL-260H
15761H-6 11/2017
1986
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
SECTION 15810H
Ductwork and Duct Accessories
NOTE: This Detailed Specification 15810H – Ductwork and Duct Accessories replaces
General Specification 15810 – Ductwork and Duct Accessories in its entirety. All
Work for this Section shall fully conform to the requirements specified herein.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall provide all labor, materials, equipment and incidentals as
shown, specified and required to furnish and install all ductwork complete with
auxiliary equipment and accessories as shown, specified and/or required for proper
operation.
B. The following index of this Section is presented for convenience:
15810H-1 11/2017
1987
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section, all costs shall be
included in the Lump Sum price bid for Contract Item H-LS-1, as specified in
Section 01270 – Measurement and Payment.
1.04 REFERENCES
A. Reference Standards: Comply with applicable provisions and recommendations of
the following, except as otherwise shown or specified. General requirements of
this Contract shall supersede the standards in case of conflict:
1. American Society of Heating, Refrigerating and Air Conditioning
Engineers (ASHRAE).
2. Sheet Metal and Air Conditioning Contractors National Association
(SMACNA).
a. HVAC Duct Construction Standards.
b. Seismic Restraint Manual - Guidelines for Mechanical Systems.
3. ASTM A 774 - As-Welded Wrought Austenitic Stainless Steel
Fittings for General Corrosive Service at Low and Moderate Temperatures.
4. ASTM A 778 - Welded, Unannealed Austenitic Stainless Steel
Tubular Products.
5. NFPA 91 - Blowers and Exhaust Systems for Dust, Stock and Vapor
Removal or Conveying.
6. UL 555 - Fire Dampers.
7. UL 181 - Factory Made Air Ducts and Connectors.
8. UL 214 - Tests for Flame Propagation of Fabrics and Films.
9. NFPA 90A - Installation of Air Conditioning and Ventilation
Systems.
B. Contractor shall provide certification that all stainless steel accessories including
screws, hangers, supports, etc. for stainless steel are Type 316 stainless steel.
C. Field Measurements: Take field measurements where required prior to installation
to ensure proper fitting of Work.
D. Where reference is made to one of the above standards, the revision in effect at the
time of bid opening shall apply.
15810H-2 11/2017
1988
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
1.05 SUBMITTALS
A. Contractor shall submit Shop Drawings and material specifications for the approval
of the Engineer. Submittals shall include, but not be limited to:
1. 1/4-inch scale duct layouts.
2. Dimensions.
3. Details of construction.
4. Details of installation, hanger details and spacing.
5. Manufacturer's literature, illustrations, specifications and Engineering data.
6. Registers, grilles and diffusers.
7. Fire Dampers (UL Listed):
a. Closing mechanisms.
b. Fusible link operating temperature.
c. Installation details.
d. Access Doors.
8. Flexible connections.
9. Other technical data related to the specified material and equipment as
requested by Engineer.
10. Duct sealants.
11. Air outlet schedule indicating room name and location of each outlet. Cross
reference Contract designation and manufacturer's model number or name.
B. Test Reports: Submit the following test reports for approval where required.
1. UL Label, Fire Dampers.
2. Volume Damper leakage tests from an AMCA approved testing laboratory.
PART 2 PRODUCTS
2.01 MATERIALS
A. Metal Ductwork:
1. Galvanized Steel (G90 Coating): Only where specified herein or indicated
on Contract Drawings.
a. Air devices for galvanized ductwork shall be aluminum.
15810H-4 11/2017
1990
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
15810H-7 11/2017
1993
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
PART 3 EXECUTION
3.01 INSTALLATION
A. Turning vanes shall be installed in all miter elbows to permit air to make the abrupt
turns with a minimum of turbulence. The turning vanes shall be quiet and free from
vibration when the system is in operation. Turning vanes shall be single thickness
type. Vanes shall be installed in all short radius elbows in accordance with
SMACNA standards and Industrial Duct Construction standards. Manual volume
dampers larger than 11" in any dimension shall be opposed blade type. The damper
blades shall be operated by a lockable dial regulator and may be set in any position.
The dial regulators shall be marked so that the "open" and "shut" positions are
clearly identified. The dial regulators on insulated ductwork shall be mounted on
an elevated platform which will finish flush with the surface of the insulation.
Manual volume dampers shall be located at accessible points and wherever possible
some distance from a duct transition or fitting. The Contractor shall take care that
sheet metal fasteners do not protrude into the duct and interfere with damper
operation when securing it to ductwork. Dampers shall be provided in each branch
duct take off and in both ducts downstream of each trunk duct split. Manual volume
dampers material of construction shall be the same as the ductwork.
B. Splitter type dampers shall not be installed.
C. Duct access doors shall be provided within working distance of, and on the fusible
link side of all fire dampers, adjacent to volume dampers, on the linkage side of
automatic dampers and at all other apparatus requiring service or inspection in the
duct system. The doors shall be rigid and airtight, and provided with neoprene
gaskets, hinges and sash locks. Whenever space requirements are such that a
15810H-9 11/2017
1995
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
hinged access door is impractical, a screw fastened lift-out door shall be provided
instead.
D. Access doors in finished work such as walls, plaster, wood paneling and in
suspended ceilings which do not have removable panels, shall be provided for all
concealed valves, controls, test openings, duct access doors, and at all other
locations requiring service, inspection or adjustment of a concealed item. The
Contractor shall submit details of construction and material to the Engineer for
review. In general, the access doors shall match the appearance of the finished
work in which they are installed and shall be of sufficient size to permit service,
inspection or adjustment of the concealed item.
E. Flexible connections for preventing the transmission of vibrations through the
ductwork to the structure shall be installed between the ductwork and all air moving
equipment and at the building joints. Flexible connections shall be neoprene-
impregnated fabric collars with cemented seams fastened with straps and bolts of
the same material as the ductwork. Flexible connections shall not be painted or
used to correct misalignment.
F. The fire damper shall be secured to a stainless steel collar with ¼" diameter stainless
steel nuts and bolts with maximum spacing of 12 inches on center and a minimum
of two fastenings per side beginning two inches from the corners of the collar. The
collars shall be at least the same gauge as the ductwork to which it is attached,
except that regardless of the duct gauge, collars shall not be lighter than 24 gauge
galvanized steel.
G. Retaining angles shall be installed on four sides of the collar and on both sides of
the protected opening with a minimum of one inch overlap on the wall or floor.
The galvanized steel angles shall be a minimum of 1½" x 1½" x 1/8" and shall be
fastened to the collar only. In no case shall angles be fastened to the wall or floor.
H. The angles shall be fastened to the collar with ¼" diameter stainless steel nuts and
bolts with a maximum spacing of 6 inches on center and a minimum of two
fastenings per side beginning two inches from the corners of the collar. Where gas
tight seals are required, the angles shall be fastened to the collar with a continuous
weld and a sealant shall be installed between the angle and the wall or floor.
Collars, angles and hardware used with stainless steel fire dampers shall be Type
316 stainless steel. Clearance for expansion is required between the collar and the
opening on the top and on each vertical side. The clearance shall be 1/8 inch per
lineal foot of sleeve with clearance on the sides distributed equally and all vertical
clearance on the top. The retaining angles shall be increased in size to provide the
minimum overlap of one inch on the wall or floor. The ductwork shall be connected
to the collar on each side of the wall or floor with a breakaway connection on all
four sides of the collar. The distance from the wall or floor to the breakaway
connection shall not exceed 6 inches.
I. Contractor shall furnish and install sleeves for registers, grilles, and dampers
mounted in the masonry, concrete plenums or shafts. Sleeves shall be 16 gage
galvanized steel.
15810H-10 11/2017
1996
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
J. After the installation is completed, the Contractor shall seal all joints air tight.
Sealants and tape shall have a flame spread not greater than 25 and a smoke
developed rating of not over 50.
K. Safing shall be provided to seal off remaining portions of shafts and louvers which
are not covered by the plenums or equipment attached to the shaft or louver. Safing
shall consist of a two inch thick rigid fiberglass board type insulation sandwiched
between two 16 gauge minimum sheets. Insulation shall be secured to the sheets
with adhesive. All edges of the panels shall be provided with a 16 gauge minimum
channel secured in place with sheet metal screws six inches on centers. Insulated
sandwich panels shall be removable type with maximum space of 18 inches, and
supported on 3 x 3 x ¼" angle. Provide intermediate supports. The sheets, channels
and hardware used for the safing shall be 316 stainless steel. The Contractor shall
submit details of construction to the Engineer for review.
L. All ductwork shall conform accurately to the dimensions shown, the ducts shall be
straight and smooth inside with joints neatly finished; ductwork shall be installed
so as to preclude the possibility of vibration under all operating conditions.
M. Seal all joints as per SMACNA Standards.
N. Elbows shall have a minimum centerline radius of 1-1/2 times the width of the duct.
Turning vanes shall be provided at all square elbows. Turning vanes shall be single
wall and shall be quiet and free from vibration when the system is in operation.
O. Provide flexible connections at inlet and discharge of air handling equipment.
P. Provide volume dampers where indicated on the Contract Drawings and as required
to facilitate accurate volume control. The duct of the damper shall be reinforced to
prevent vibration. Volume dampers specified with air devices shall be installed in
addition to those shown on the Contract Drawings.
Q. Fire dampers shall be provided and installed where indicated on the Contract
Drawings and where required by UL and authorities having jurisdiction, and shall
be approved by local building codes and in accordance with the requirements of the
NFPA.
R. Provide access doors for all dampers for inspection and maintenance.
S. Install all ductwork and accessories to provide a system free from buckling,
warping, breathing or vibration.
T. All expansion joints in ducts at building expansion joints shall be suitably supported
at each end by support guides within 12 inches of joint.
U. All ducts at flexible connections with air handling equipment, and fans shall be
supported at free end within 12 inches of flexible connection.
V. Provisions shall be made for supporting all ductwork, dampers, and other ductwork
accessories, where necessary.
W. Coordinate all air outlets for compatibility with ceiling system.
15810H-11 11/2017
1997
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
X. All ductwork shall arrive on Site fully fabricated, not in two halves for field
fabricated.
3.03 ADJUSTMENT
A. Set volume control devices for approximate positions in preparation for final testing
and balancing.
B. Install fusible links in fire dampers and verify that dampers are in open position.
C. Start fan system and check for excessive leaks and vibration and correct.
3.04 BALANCING
A. Systems shall be completely tested, adjusted and balanced by a qualified engineer.
A complete balancing procedure shall be submitted for approval. All equipment
and connections required to balance the systems shall be provided.
B. All duct systems shall be balanced as specified in General Specification 15951 -
Testing, Adjusting and Balancing.
3.05 CLEANING
A. Remove all loose materials and obstructions from interior of ducts.
B. Remove debris and waste materials resulting from installation.
1. Notes:
a. All accessories, including but not limited to, turning vanes, air
turning devices, manual volume dampers, motor operated control
dampers, fire dampers, access doors, supports, angles, clamps,
hangers and hardware, shall be suitable for the pressure
classification given above.
C. Ductwork Material Schedule:
1. As shown on the Contract Drawings.
END OF SECTION
15810H-13 11/2017
1999
DETAILED SPECIFICATION 15810H – DUCTWORK AND DUCT ACCESSORIES
CONTRACT DEL-260H
15810H-14 11/2017
2000
DETAILED SPECIFICATION 15815H – DUCT INSULATION
CONTRACT DEL-260H
SECTION 15815H
DUCT INSULATION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall provide all labor, materials, equipment and incidentals as
shown, specified and required to furnish and install all duct insulation complete
with auxiliary equipment and accessories as shown, specified and/or required for
proper operation.
B. The following index of this Section is presented for convenience:
15815H-1 11/2017
2001
DETAILED SPECIFICATION 15815H – DUCT INSULATION
CONTRACT DEL-260H
1.04 REFERENCES
A. Reference Standards: Comply with applicable provisions and recommendations of
the following, except as otherwise shown or specified. General Requirements of
this Contract shall supersede the standards in case of conflict:
1. American Society of Heating, Refrigerating and Air Conditioning
Engineers (ASHRAE)
2. ASTM E 84 - Surface Burning Characteristics of Building
Materials
3. NFPA 255 - Surface Burning Characteristics of Building
Materials
4. UL 723 - Test for Surface Burning Characteristics of
Building Materials
5. NFPA 90A - Installation of Air Conditioning and Ventilating
Systems
6. ASTM C 449 - Mineral Fiber Hydraulic-Setting Thermal
Insulating and Finishing Cement
7. ASTM C 534 - Preformed Flexible Elastomeric Cellular
Thermal Insulation in Sheet and Tubular Form
8. ASTM C 547 - Mineral Fiber Pipe Insulation
9. ASTM C 552 - Cellular Glass Thermal Insulation
10. ASTM C 553 - Mineral Fiber Blanket Thermal Insulation for
Commercial and Industrial Applications
11. ASTM C 612 - Mineral Fiber Block and Board Thermal
Insulation
12. ASTM C 647 - Properties and Tests of Mastics and Coating
Finishes for Thermal Insulation
13. ASTM C 916 - Adhesives for Duct Thermal Insulation
14. ASTM C 920 - Elastomeric Joint Sealants
15. ASTM C 1126 - Specification for Faced or Unfaced Rigid
Cellular Phenolic Thermal Insulation
B. Field Measurements: Take field measurements where required prior to installation
to ensure proper fitting of Work.
C. Where reference is made to one of the above standards, the revision in effect at the
time of bid opening shall apply.
1.05 SUBMITTALS
A. Contractor shall submit Shop Drawings and material specifications for the approval
of the Engineer. Submittals shall include, but not be limited, to:
15815H-2 11/2017
2002
DETAILED SPECIFICATION 15815H – DUCT INSULATION
CONTRACT DEL-260H
15815H-3 11/2017
2003
DETAILED SPECIFICATION 15815H – DUCT INSULATION
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 MATERIALS
A. Manufacturer: Provide insulation of one of the following:
1. Owens Corning, Toledo, OH.
2. CertainTeed Corporation, Valley Forge, PA.
3. Schuller International, Inc. (Johns-Manville), Denver, CO.
4. Or approved equal.
B. Exposed Ductwork Insulation (Rigid): All exposed ductwork as listed under
Paragraph 3.05 - Schedules, shall be insulated with glass fiber board having a
density of not less than 3.0 lbs./cu.ft., and a thermal conductivity of not more than
0.23 BTU-inch/hour square feet °F at 75°F mean temperature. The insulation shall
be:
1. Johns-Manville No. 814 Spin.
2. Certain Teed Corporation Industrial Board
3. Or approved equal.
C. The insulation shall be impaled over pins welded to the duct surface on 12" centers.
The pins shall be coated with vapor barrier adhesive, and the insulation shall then
be secured with caps over the pins. All joints and breaks in the vapor barrier shall
be sealed with 3" wide strips of the vapor barrier facing. All insulation shall be
reinforced with corner bead. The facing shall be AP consisting of white kraft paper
bonded to aluminum foil and reinforced with fiberglass yarn.
D. Adhesives and Accessories:
1. Lagging Adhesive: Lagging adhesives shall be nonflammable and fire-
resistant and shall have flame spread and smoke developed ratings of 25/50
when measured in accordance with ASTM E 84.
2. Contact Adhesive: Adhesive may be dispersed in a nonhalogenated organic
solvent with a low flash point (flash pint less than minus 25°F when tested
15815H-4 11/2017
2004
DETAILED SPECIFICATION 15815H – DUCT INSULATION
CONTRACT DEL-260H
PART 3 EXECUTION
3.01 INSPECTION
A. Ensure that all surfaces are clean and dry before applying insulation.
3.02 PREPARATION
A. Ensure that ductwork has been inspected and released for application of insulation.
3.03 INSTALLATION
A. Install insulation so as to make surfaces smooth, even and substantially flush with
adjacent duct insulation.
B. Follow manufacturer's application instructions for all materials used.
C. Thickness of rigid insulation shall be greater than the seams or angles of ductwork
to which it is applied.
D. Duct insulation shall be continuous through sleeves and prepared openings.
E. Insulation shall terminate at fire dampers and flexible connections.
F. Field Painting shall comply with the requirements of Detailed Specification 09900
- Painting.
G. Identification markers and labels shall be in conformance with Detailed
Specification 15076 - Piping and Equipment Identification.
3.04 CLEANING
A. Remove all debris, waste materials and loose foreign matter resulting from
installation.
3.05 SCHEDULES
A. Thermal Insulation - Rigid:
1. All ductwork connected to HV-1 including the outside air intake plenum as
shown on the Contract Drawings.
2. All ductwork connected to SF-1 including the outside air intake plenum as
shown on the Contract Drawings.
15815H-5 11/2017
2005
DETAILED SPECIFICATION 15815H – DUCT INSULATION
CONTRACT DEL-260H
END OF SECTION
15815H-6 11/2017
2006
DETAILED SPECIFICATION 15830H - FANS
CONTRACT DEL-260H
SECTION 15830H
Fans
NOTE: This Detailed Specification 15830H - Fans replaces General Specification 15830 –
Fans in its entirety. All Work for this Section shall fully conform to the
requirements specified herein.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall provide all labor, materials, equipment and incidentals to
furnish and install all fans in accordance with the requirements specified herein as
shown on the Contract Drawings or specified herein.
B. The equipment shall be furnished complete with all accessories, special tools, spare
parts, base attachments, mountings, anchor bolts and other appurtenances as
specified or as may be required for a satisfactory installation.
C. All fans shall be furnished in accordance with the schedule shown on the Contract
Drawings.
D. The following index of this Section is presented for convenience:
15830H-1 11/2017
2007
DETAILED SPECIFICATION 15830H - FANS
CONTRACT DEL-260H
15830H-2 11/2017
2008
DETAILED SPECIFICATION 15830H - FANS
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 FANS - CONDITION OF SERVICE AND DESIGN DATA
A. Fans shall be as specified below and shown on the Contract Drawings. The
Contractor shall include, as part of this Work, all supports required. The fans shall
be installed where indicated on the Contract Drawings.
B. Performance data for all fans shall be based on tests conducted in accordance with
the "Standard Test Code for Centrifugal and Axial Fans" as adopted by the Air
Movement and Control Association (AMCA) and shall be licensed to bear the
AMCA certified rating seal for both sound and air performance. All fans shall be
selected from performance curves and not from rating tables. A copy of the curve,
indicating the operating point, shall be submitted for each proposed fan.
C. Unless otherwise indicated, motors shall be of the totally enclosed premium
efficiency type. Motors shall not be selected for operation in the service factor
range/zone. The maximum brake horsepower required at any point on the
performance curve shall not exceed the rated horsepower of the motor.
D. Motors 1/3 HP and less shall be suitable for use with 115V, single phase, 60 Hz
electric service. Motors 1/2 HP or larger shall be for use with 460V, three phase,
60 Hz electric service, unless otherwise indicated. Two-speed motors shall be two
winding type. Motors shall comply with the requirements of General Specification
16221 - Electric Motors.
E. All fans and damper operators shall each be provided with individual externally
mounted disconnect switches. All enclosures shall be NEMA 4X-stainless steel
unless otherwise specified.
F. All fans shall be statically and dynamically balanced at the speed at which the unit
is scheduled to operate. Fans with corrosion resistant coatings shall be balanced
after being coated.
G. The fans shall be either direct connected or V-belt drive as indicated on the
schedule. For motors less than or equal to 10 HP, the V-belt drive shall be selected
for 120 percent of rated capacity. For motors larger than 10 HP, the V-belt drive
shall be selected for 150 percent of rated capacity. All V-belt drives shall be
provided with adjustable sheaves. Exposed V-belt drives shall have removable belt
guards with openings to allow for tachometer readings at both drive and fan shafts.
Guards shall be so constructed as to allow visual inspection of the belts without
removing the guard.
H. All fan bearings shall be selected for a minimum L-50 life of 100,000 hours at
maximum operating speed.
15830H-4 11/2017
2010
DETAILED SPECIFICATION 15830H - FANS
CONTRACT DEL-260H
I. All fan motors shall be provided with high premium energy efficient totally
enclosed fan cooled type. All shafts shall be sized so the first critical speed is at
least 20 percent over the maximum operating speed. Close tolerance shall be
maintained along the length of the shaft.
J. Each fan shall bear a permanently affixed manufacturer’s nameplate containing the
model number and individual serial number for future identification.
K. Fan manufacturer shall provide sound power ratings in the eight octave bands.
Sound power levels shall be based on AMCA Standard 301. Sound power ratings
shall be in decibels, referenced to 10-12 watts.
15830H-5 11/2017
2011
DETAILED SPECIFICATION 15830H - FANS
CONTRACT DEL-260H
10 HP and belts sized for continuous service. Fans shall be designed for
mounting in any position from horizontal to vertical.
5. The fan assembly shall be dynamically balanced at the factory prior to
shipping. Fans shall be balanced to the American National Standards
Institute, Std. S2.19-1989 “Balance Quality of Rotating Rigid Bodies”,
Grade G6.3. Fans shall be manufactured in accordance with the fan
manufacturer's standard quality assurance procedures. Fan performance
shall be based on tests conducted in an AMCA accredited test laboratory
and in accordance with AMCA Standard 210 for air performance and
AMCA Standard 300 for sound. Fans shall be licensed to bear the AMCA
Certified Air Performance Rating Seal.
C. Accessories:
1. FRP Mounting feet
2. Companion flanges
3. Lifting lugs
4. Motor cover and belt guard
5. Access Door - For inspection of the propeller and fan bearings
propeller. Bearings shall be heavy duty, self aligning, ball or roller type;
depending on fan size, motor horsepower and performance. Bearings shall
have extended lube tubes and be able to be repeatedly lubricated for
continuous service. Variable pitch drive sheaves shall be standard on fans
up through and including 10 HP. Belts shall be "V" type, heat, oil, and static
resistant and sized for continuous service.
5. The fan assembly shall be dynamically balanced at the factory prior to
shipping. Fans shall be balanced to the American National Standards
Institute, Std. S2.19-1989 “Balance Quality of Rotating Rigid Bodies”,
Grade G6.3. Fans shall be manufactured in accordance with the fan
manufacturer’s standard quality assurance procedures. Fan performance
shall be based on tests conducted in an AMCA accredited test laboratory in
accordance with the latest revision of AMCA Standard 210 for air
performance and AMCA Standard 300 for sound. Fans shall be licensed to
bear the AMCA Certified Air Performance Rating Seal.
C. Accessories:
1. Mounting feet
2. Companion flanges
3. Lifting lugs
4. Motor cover and belt guard
5. Access Door - For inspection of the propeller and fan bearings.
15830H-7 11/2017
2013
DETAILED SPECIFICATION 15830H - FANS
CONTRACT DEL-260H
4. The propeller shall be mounted in a high efficiency air seal fan orifice with
smaller diameter of the ring overlapping the propeller tips.
5. The fan assembly shall be dynamically balanced at the factory prior to
shipping. Fans shall be balanced to the American National Standards
Institute, Std. S2.19-1989 “Balance Quality of Rotating Rigid Bodies”,
Grade G6.3. Fans shall be manufactured in accordance with the fan
manufacturer’s standard quality assurance procedures. Fan performance
shall be based on tests conducted in an AMCA accredited test laboratory in
accordance with the latest revision of AMCA Standard 210 for air
performance and AMCA Standard 300 for sound. Fans shall be licensed to
bear the AMCA Certified Air Performance Rating Seal.
C. Accessories:
1. Inlet guard.
2. Mounting angle flange.
PART 3 EXECUTION
3.01 INSTALLATION
A. The fans shall be installed, connected and placed in proper working order in
accordance with the manufacturer's instructions and details and the Contract
Drawings.
3.02 IDENTIFICATION
A. Each unit of equipment shall be identified with the equipment item numbers given
on the Contract Drawings or as directed by the Engineer. A corrosion resistant tag
or nameplate, securely affixed in a conspicuous place on each unit shall give the
equipment item number, manufacturer’s name or trademark and such other
information as the manufacturer may consider necessary, or as specified, for
complete identification.
3.03 TESTING
A. Preliminary and final field tests shall be performed for all equipment provided
under this Specification, as specified in Article 13 of the General Conditions and
Detailed Specification 01811 – Preliminary and Final Field Tests.
B. All tests shall be performed in accordance with the requirements of the Contract
Documents. Motor tests in accordance with General Specification 16221 -
Electrical Motors.
C. Field tests shall be performed in accordance with General Specification 15951 -
Testing, Adjusting and Balancing.
3.04 MANUFACTURER’S REPRESENTATIVE
A. The Contractor shall provide the services of a qualified manufacturer's technical
representative who shall adequately supervise the installation and testing of all
15830H-8 11/2017
2014
DETAILED SPECIFICATION 15830H - FANS
CONTRACT DEL-260H
END OF SECTION
15830H-9 11/2017
2015
DETAILED SPECIFICATION 15830H - FANS
CONTRACT DEL-260H
15830H-10 11/2017
2016
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
SECTION 15950
HVAC Monitoring and Control
NOTE: This Detailed Specification 15950 – HVAC Monitoring and Control has been
prepared specifically for the Work of this Contract. There is no corresponding
General Specifications 15950 – HVAC Monitoring and Control.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Contractor shall furnish, install, test and place in satisfactory operation an open
architecture HVAC monitoring and control system (HMCS as specified herein.
B. Contractor is required to load, configure, develop, test, document and place into
satisfactory operation all software associated with the HMCS and all its ancillary
devices as described herein, required by other Specifications as shown and as
necessary to provide a properly operating and integrated system.
C. The system configuration shall be as specified herein and as described in the
Sequence of Operations in Part 3, below. Some variations in the configuration may
be permitted as long as functional constraints as intended for the various components
of the system are met. Hardware requirements are specified in this Specification.
Software requirements for the HMCS and for interfacing with the plant control
system and other microprocessor based equipment are specified herein.
D. The Contract Documents illustrate and describe the overall functional and operational
requirements. Contractor is responsible for tagging, integrating, and verifying the
functionality of all system components.
E. The Work also includes:
1. Automatic Temperature Control Panels (ATC).
2. Power and control wiring and conduit: The wiring and conduit to be
provided under this Specification shall include the following:
a. All wiring and conduit from the ATC panel to sensors, controllers,
switches, dampers, valves, HVAC equipment panels, ventilation
system chlorine detection panel and alarm station.
b. All wiring and conduit from the ventilation system chlorine detection
panel to chlorine gas sensors.
c. All wiring and conduit between HVAC equipment panels and
associated field devices.
d. Any other HVAC device requiring control.
e. Conduit layouts for these wiring requirements are not shown.
15950-1 11/2017
2017
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
consist of equipment models, which are currently in production. All equipment shall
be of modular construction and capable of field expansion through the installation of
plug-in circuit cards and additional cabinets, as necessary. Design all logic and
control loops to be fail safe.
G. All components shall be designed to return automatically to accurate measurement
within fifteen (15) seconds upon restoration of power after a power failure or when
transferred to standby power supply.
H. Surge protection shall be provided for all instruments and all other control system
components, which could be damaged by electrical surges.
I. All relays with interconnections to field devices shall be wired through terminal
blocks. Terminals as part of the relay base are not an acceptable alternative.
J. All panel mounted instruments, switches, and other devices shall be selected and
grouped for functionality and arranged to present a neat coordinated appearance.
Similar type front of panel mounted devices shall be of the same manufacturer and
model line.
K. All components furnished, including field and panel instruments, shall be tagged with
the item number and nomenclature indicated as shown and/or approved Shop
Drawings.
L. Ranges and scales shall be coordinated to suit equipment actually furnished.
M. Field-mounted devices shall be protected from exposure to freezing temperatures.
1.07 SUBMITTALS
A. Contractor shall submit the Shop Drawings for the approval of the Engineer.
Submittals shall include, but not be limited to the following:
1. Working Drawings.
2. Operation and Maintenance (O&M) Manuals.
3. List of Spare Parts, Special Tools and Supplies.
4. Reports of Certified and Witnessed Shop Tests.
5. Reports and Field Tests.
6. Reports of Manufacturer’s Representative Site Visits.
B. Working Drawings shall include, but not be limited to, the following:
1. Equipment specifications and data sheets, with identification of all materials
used and methods of fabrication.
2. Complete assembly, layout, installation and Shop Drawings, with clearly
15950-5 11/2017
2021
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
marked dimensions.
3. Equipment cross-section drawings.
4. Manufacturer’s deliver, storage, and handling requirements.
5. Manufacturer’s installation instructions and recommendations.
6. Weights of equipment component parts, assembled weights of equipment,
and total shipping weight. As applicable, include dynamic loads and weight
when full.
7. Comprehensive schematic diagrams showing the wiring for each electrical or
electro-mechanical equipment item, as well as interconnecting and point-to-
point field wiring diagrams. Point-to point field wiring diagrams shall
comply with Article 2.01 of Detailed Specification 16010 – General
Electrical Requirements.
8. Equipment nameplate data.
9. Submittals specified in Detailed Specification 16221 – Electric Motors.
10. Evidence of manufacturer experience and of the successful operation in other
facilities of equipment similar to that proposed for this project, as specified
herein and in Article 5 of the General Conditions.
C. Operation and maintenance manuals shall conform to the requirements of Detailed
Specification 01831 – Operation and Maintenance Manuals.
D. Spare parts lists shall indicate sizes, quantities and part number of the items to be
furnished. Terms such as “1 lot of packing material” shall not be acceptable.
E. Reports of field tests shall be submitted as specified herein and in accordance with
Article 13 of the General Conditions and Detailed Specification 01811 – Preliminary
and Final Field Tests.
1. Prior notification of field tests shall be submitted as specified herein and in
accordance with Article 13 of the General Conditions and Detailed
Specification 01811 – Preliminary and Final Field Tests.
F. Reports of manufacturer’s representative Site visits shall be submitted as specified
herein and in applicable provisions of Division 1 – General Requirements.
G. Other applicable information, as required elsewhere in the Contract Documents.
H. Additional information as summarized below:
1. Sequence of Operations, as described in Section 3.05.
2. Record Drawings and Documentation:
15950-6 11/2017
2022
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
15950-8 11/2017
2024
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
C. The Contractor shall furnish such oil, grease, and any special lubricants as are
necessary for the proper operation of the equipment provided under this
Specification, as specified in Detailed Specification 01781 – Project Closeout.
1. The oil, grease, and special lubricants furnished shall be sufficient for the
required operation of the equipment prior to its final acceptance, and for the
operation of the equipment during the maintenance and guaranty period
specified in Article 24 of the Standard Construction Contract.
2. The oil, grease, and special lubricants furnished under this Specification
shall, wherever possible, be standardized and consolidated with those
furnished other Specifications, as specified in Detailed Specification 01781 –
Project Closeout.
1.10 ANCHOR BOLTS
A. Type 316 stainless steel anchor bolts (and related hardware, including, but not limited
to, nuts and washers) shall be included in the supply of the equipment provided under
this Specification, and shall be installed by the Contractor in accordance with the
equipment manufacturer’s instructions.
1.11 EQUIPMENT IDENTIFICATION
A. The Contractor shall provide corrosion-resistant nameplates, securely affixed in a
conspicuous place, on each item of equipment. Nameplates shall conform to the
requirements of Detailed Specification 16076 – Labeling and Identification and shall
bear the manufacturer’s name or trademark and such other information as is specified
or deemed necessary by the manufacturer to complete the identification. Nameplate
numbering shall be as specified or shown on the Drawings: the Engineer may change
or supplement such numbering at the time of or at any time before the approval of
Shop Drawings.
1.12 MANUFACTURER’S REPRESENTATIVE
A. The Contractor shall provide the services of a qualified manufacturer’s representative
to: assist in the installation of the equipment; check the installation before the
equipment is placed into operation; assist in the performance of field tests; assist in
the start-up of the equipment; and train the maintenance staff in the care, operation,
and maintenance of the equipment.
B. The services provided shall be in accordance with the requirements of Article 12 of
the General Conditions and Detailed Specification 01732 – Installation of
Equipment, Detailed Specification 01811 – Preliminary and Final Field Tests, and
Detailed Specification 01821 – Equipment Start-up and Training.
C. The Contractor shall provide the services of the manufacturer’s representative at such
times and for such durations of time as needed to perform the required tasks, as
specified in the Detailed Specifications listed in this Article. At a minimum, the
15950-9 11/2017
2025
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Unless otherwise specified, equipment and materials provided under this
Specification shall be manufactured by:
1. Schneider Electric, IA Series
2. Siemens, Washington D.C.
3. Johnson Controls, Milwaukee, WI
4. Or approved equal.
2.02 SYSTEM PERFORMANCE
A. General:
1. Descriptions contained hereinafter are for guidance and to explain the
functions desired. They do not describe or specify all components required to
interface equipment. All parts and equipment necessary to meet functional
and operational requirements shall be provided.
2. All components of the ATC system shall be rugged industrial grade and
installed within NEMA 4X enclosures:
3. Components located in corrosive areas shall be provided with enclosures
constructed of materials suitable chlorine atmospheres. Suitable exposed
materials shall be epoxy or Teflon coated aluminum or other similar materials
approved by the Engineer. Uncoated steel and galvanized steel are not
suitable materials for exposure in corrosive areas.
4. Commercial sensors and field devices shall not be acceptable.
B. Power Supplies:
1. All electrically powered monitoring equipment, control equipment and
devices shall be suitable for operation on 115 volt ±10 percent, 60 Hz ±2 Hz
power. The Contractor shall provide a suitable regulator or transformer if a
different voltage or closer regulation is required.
15950-12 11/2017
2028
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
15950-14 11/2017
2030
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
15950-15 11/2017
2031
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
g. Support for all mandatory and optional LonMark SNVT for their
LonMark profile as documented by the LonMark Interoperability
Association.
h. Internal customizable safeties and limits to prevent third party
LonMark tools from providing improper and unrealistic inputs to
ASC.
i. Local operator interfaces port located on ASC and ASC sensor for
download from or upload to portable workstation. All Lon bus
devices shall be accessible from either port.
j. Communication: ASC shall communicate with the system at a baud
rate of not less than 78.8K baud using LonTalk communications
protocol (EIA 709.1).
k. ASC units monitor or control each input/output point, process
information, and provide a minimum of fifty (50) expressions for
customized HVAC control including mathematical equations,
Boolean logic, PID control loops with anti-windup, sequencers,
timers, interlocks, thermostats, counters, interlocks, compare, limit,
and alarms.
l. ASC unit setpoints shall be digital display with dual setpoint limits
(integral hard limits, which the user cannot exceed above and below,
and independent soft limits, which are hidden from the user). All
digital setpoints shall be network retentive after power outages and
after replacement of sensor.
K. Performance
1. The system shall conform to the following performance standards:
a. Object Command: The maximum time between the command of a
binary object by the operator and the reaction by the device shall be
less than five (5) seconds. Analog objects should start to adjust
within five (5) seconds.
b. Object Scan: All changes of state and change of analog values will be
transmitted over the high-speed network such that any data used or
displayed at a controller or HMI will have been current within
previous sixty (60) seconds.
c. Alarm Response Time: The maximum time from when an object
goes into alarm to when it is annunciated at the HMI shall not exceed
twenty (20) seconds.
d. Program Execution Frequency: Custom and standard applications
shall be capable of running as often as once every five (5) seconds.
15950-16 11/2017
2032
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
15950-17 11/2017
2033
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
Note 1: (10 percent to 100 percent of scale) (cannot read accurately below 10 percent).
Note 2: For both absolute and differential pressure.
Note 3: Not including utility-supplied meters.
15950-18 11/2017
2034
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
15950-19 11/2017
2035
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
10. Actuator shall be provided with sufficient torque to open and close the
device. Provide a minimum torque of 133-in-lb.
11. 120VAC or 24VDC.
12. NEMA Type 2 housing.
13. Accessories:
a. Linkage kit.
b. Mounting bracket.
c. Auxiliary switches for monitoring damper position.
d. NEMA Type 4X enclosure.
14. Manufacturers: Provide products of one (1) of the following:
a. Belimo, Danbury, CT.
b. Or approved equal.
2.05 MOTORIZED DAMPERS
A. Refer to Detailed Specification 13862 - Non-Metallic Ductwork for fiberglass
reinforced plastic motorized dampers.
B. Refer to Detailed Specification 15810 - Ductwork and Accessories for metal
motorized dampers.
2.06 MOTORIZED VALVES
A. Refer to Detailed Specification 15515 - Piping, Valves and Accessories for
motorized valves.
2.07 PANELS AND ENCLOSURES
A. General Construction Requirements
1. Contractor shall provide all electrical components and devices, support
hardware, fasteners, and interconnecting wiring required to make the control
panels and/or enclosures complete and operational.
2. Contractor shall locate and install all devices and components so that
connections can be easily made and that there is ample room for servicing
each item.
3. Components for installation on panel exterior shall be submitted for approval.
4. Contractor shall adequately support and restrain all devices and components
mounted on or within the panel to prevent any movement.
15950-20 11/2017
2036
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
5. All wiring to panel connections from field instruments, devices, and other
panels shall be terminated at master numbered terminal strips, unless
otherwise specified.
6. Contractor shall provide copper grounding studs for all panel equipment.
7. Contractor shall provide the following convenience accessories inside of each
control panel:
a. One (1) 120 VAC, 20A duplex, grounding type receptacle.
8. No device shall be mounted less than thirty-six (36) inches above the
operating floor level, unless otherwise specified.
B. Identification:
1. Contractor shall provide laminated plastic nameplates for identification of
panels and components mounted thereon as follows:
a. Nameplates shall be of 3/32-inch thick laminated phenolic type with
white matte finish surface and black letter engraving.
b. Panel identification nameplates to have 1/2-inch high letter
engravings.
c. Panel mounted component (e.g., control devices, indicating lights,
selector switches, etc.) identification nameplates to have 1/4-inch
high letter engravings.
d. Nameplates shall be attached to the panel face with two (2) stainless
steel self-tapping screws.
e. Nameplate engravings shall include the instrument or equipment tag
number and descriptive title.
f. Tag all internally mounted instruments in accordance with the
following requirements:
1) The identifying tag number shall be permanently etched or
embossed onto a stainless steel tag which shall be fastened to
the device housing with stainless steel rivets or self-tapping
screws of appropriate size.
2) Where neither of the above fastenings can be accomplished,
tags shall be permanently attached to the device by a circlet of
1/16-inch diameter stainless steel wire rope.
3) Identification tag shall be installed so that the numbers are
easily visible to service personnel.
4) Front of panel mounted instruments shall have the tag
15950-21 11/2017
2037
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
15950-23 11/2017
2039
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
a. Control of Environment:
1) Panels shall be furnished with adequately sized, automatically
controlled 120 VAC strip heaters to maintain temperature 10
degrees F above ambient temperature for condensation
prevention inside panels.
2) Panels shall be provided with automatically controlled closed
loop ventilation fans or closed loop air conditioners with
filtered air louvers if required to maintain temperature inside
each enclosure below the maximum operating temperature
rating of the components inside the enclosure.
b. Internal Power Distribution:
1) Panels shall be provided with an internal 120 VAC power
distribution panel with number of circuits and separate circuit
breakers sized as required to distribute power to the panel
components. Distribution panel shall contain two spare
breakers minimum.
c. Wiring:
1) Internal wiring shall be Type MTW stranded copper wire with
thermoplastic insulation rated for 600 V at 85 degrees C for
single conductors, color coded and labeled with wire
identification.
2) For DC panel signal wiring, use No. 18 minimum AWG
shielded.
3) For AC power wiring, use No. 12 minimum AWG. For AC
signal and control wiring, use No. 16 minimum AWG. For
wiring carrying more than 15 Amps, use sizes required by
NEC and NFPA 79 Standards.
4) Low voltage signal wiring and shielded wiring shall be
separated from power and control wiring by a minimum of six
(6) inches.
5) Parallel runs of wire shall be grouped or bundled using
covered troughs. Maximum bundle size to be one (1) inch.
Troughs shall have forty (40) percent spare capacity.
6) Wire troughs along horizontal or vertical routes shall be
installed to present a neat appearance. Angled runs are not
acceptable.
7) Contractor shall adequately support and restrain all wiring
15950-24 11/2017
2040
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
flashed contacts rated not less than three amperes resistive at 120 VAC or 28
VDC continuous shall be provided.
D. Relays to have clear plastic dust cover.
E. Relays to be UL recognized.
F. Manufacturers: Provide products of one (1) of the following:
1. IDEC, Sunnyvale, CA.
2. Potter & Brumfield, Princeton, IN.
3. Allen-Bradley, Milwaukee, WI.
4. Or approved equal.
2.09 SELECTOR SWITCHES, PUSHBUTTONS AND INDICATING LIGHTS
A. General:
1. Selector switches, pushbuttons and indicating lights shall all be provided by
Allen-Bradley or approved equal and shall be of the same series or model
type.
2. Type: Heavy-duty, oil-tight.
3. Provide legend plate for indication of switch, pushbutton or light function
(e.g. “OPEN/CLOSED”, “HAND/OFF/AUTOMATIC”).
4. Mounting: Contractor shall mount flush on control panel front, unless
otherwise noted.
5. NEMA rated to match panel in which mounted.
B. Selector Switches:
1. Type: Provide selector switches with number of positions as required to
perform intended functions, as shown on the Contract Drawings and specified
in the sequence of operation in section 3.05.
2. Contacts:
a. Provide number and arrangement of contacts as required to perform
intended functions specified but not less than one single pole, double
throw contact.
b. Type: Double break, silver contacts with movable contact blade
providing scrubbing action.
c. Rating: Selector switches shall be compatible with other devices and
the type of power, AC or DC current, that are simultaneously
15950-27 11/2017
2043
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
operated by the switch contacts, but not less than ten (10) amperes
resistive at 120 VAC or DC continuous.
d. Switch Operator: Standard black knob.
C. Pushbuttons:
1. Type: Provide momentary, dual type pushbuttons as required to perform
intended functions specified and shown.
2. Contacts: Comply with the requirements specified above for selector
switches.
D. Indicating Lights:
1. Type: Compact, integral transformer type.
2. Lamps: Six-volt, long life (20,000 hours minimum).
3. Indicating lights shall be provided with labeled escutcheon plates identifying
the light function (e.g. “RUN”, “STOP”, “ALARM”, “POWER”).
E. Button and Lens Colors:
1. Green for indication of closed, off (ready), stopped.
2. Red for indication of open, on, running.
3. Amber for indication of equipment malfunction, trouble and alarms (e.g.
motor overload, etc.).
4. Blue for indication of electrical control power on.
F. Rotary Cam Switches:
1. Provide rotary cam switches with number of positions and poles as required
to perform the required signal switching function as shown on the Contract
Drawings and as specified in Section 3.05.
2. Contacts:
a. Gold-flashed contacts housed in mechanical contact blocks with
number and arrangement of contacts as required to perform intended
functions.
b. Contact Rating: Compatible with AC or DC through-put current of
signals and devices simultaneously operated by the switch contacts,
but not less than twenty (20) amperes at 600 VAC or 250 VDC
continuous.
c. Switch Operator: Standard black knob.
15950-28 11/2017
2044
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
1. Each of the four alarm module output contacts shall be wired together and
any of the alarm outputs will trigger a common chlorine sensor contact used
to interface with the ATC system.
2. Each of the alarm module output contacts shall be adjusted to be non-latching
to allow the system to automatically reset upon gas detection levels dropping
below the detection setpoint.
3. Audible alarming shall be provided external to the panel as described in the
ventilation alarm panel sequence of operations in Section 3.05, below.
2.12 CONDUIT AND WIRE
A. Electric wires and cables shall be provided under this Specification in accordance
with the requirements of Detailed Specification 16121 – Electric Wires and Cables
except where otherwise noted.
B. Electric conduit shall be provided under this Specification in accordance with the
requirements of Detailed Specification 16131 – Electric Conduit System except
where otherwise noted.
2.13 LABELING
A. Labeling of equipment shall be provided under this Specification in accordance with
the requirements of Detailed Specification 16076 – Labeling and Identification.
2.14 MISCELLANEOUS
A. Provide any additional controls and appurtenances as required to provide proper
equipment control.
B. Provide all mounting accessories, as required.
C. Tubing, static pressure tips, mounting hardware, fasteners, and appurtenances shall
be constructed of Type 304 stainless steel.
PART 3 EXECUTION
3.01 INSTALLATION
A. Contractor shall examine equipment at time of delivery for damaged or missing
components.
B. Do not proceed with installation of equipment until all damaged items found have
been replaced or missing items have been provided.
C. Install equipment in accordance with the manufacturer's instructions and
recommendations.
D. Install equipment so that sufficient access and working space is provided for safe
operation and maintenance.
15950-31 11/2017
2047
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
E. Wall sensors shall be installed at least five (5) feet above the finished floor. Wall
plates and mounting hardware shall be provided as required for a complete
installation.
F. Where sensors are located on exterior walls, Contractor shall provide an insulated
mounting sub-base.
G. Where sensors are located outdoors, Contractor shall provide sunshield enclosures.
H. Furnish and install all mounting accessories, junction boxes, wall boxes and wall
plates as required for installation of all devices.
I. All Work described in this Specification shall be installed, wired, circuit tested and
calibrated by electricians, technicians and mechanics qualified for the Work.
J. Contractor shall be responsible for the proper operation and installation of all control
systems herein specified. Contractor shall be responsible for coordination of all
interfaces with other equipment and contractors to achieve the required control
operation.
3.02 FIELD TESTING
A. Preliminary and final field tests shall be performed for all equipment provided under
this Specification, as specified in Article 13 of the General Conditions and Detailed
Specification 01811 – Preliminary and Final Field Tests.
B. Additional requirements for the final field testing of the equipment provided under
this Specification are as follows:
1. Integrated System Field Test:
a. Following checkout of the HMCS, Contractor, under the supervision
of the HMCS Supplier, shall perform an integrated system test to
verify that all components and programmed software are operating
properly as a fully integrated system and that the intended monitoring
and control functions are fully implemented and operational.
b. Contractor shall perform all Sequence of Operations in the presence
of the Engineer.
c. The HMCS, including all field sensors/transducers and instruments,
shall be fully operational and shall run trouble-free for a successful
test. Any defects or problems found during the integrated system test
shall be immediately corrected by Contractor and the system retested
to demonstrate proper operation.
3.03 START-UP AND ADJUSTMENT
A. Contractor, under the supervision of the HMCS supplier, and other component
suppliers, as applicable, shall perform the following:
15950-32 11/2017
2048
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
1. Check and approve the installation of all HMCS components and all cable
and wiring connections between the system components prior to placing the
system into operation.
2. Conduct a complete system checkout and adjustment, including calibration of
all instruments, tuning of control loops, checking operation functions, and
testing of final control actions. When there are future operational functions
included in the Work, they should be included in the system checkout. All
problems encountered shall be promptly corrected to prevent any delays in
start-up of the system.
B. Contractor and the HMCS supplier shall be responsible for initial operation of the
HCMS and shall make all necessary modifications or replacements to ensure that the
HMCS functions in the manner intended by these Specifications.
C. Contractor shall submit to the Engineer certified calibration reports for field
instruments and devices and panel mounted devices upon completion of calibration.
D. Contractor shall submit to the Engineer an installation inspection report certifying
that all system components have been installed correctly and are operating in the
manner intended. The report shall be signed by authorized representatives of
Contractor and the HMCS supplier.
3.04 CLEANING
A. The Contractor shall perform cleaning and site maintenance for all equipment
provided under this Specification, as specified in Detailed Specification 01740 -
Cleaning and Site Maintenance.
B. Clean dirt and marks and other debris from equipment.
C. Remove debris and waste material resulting from installation.
3.05 SEQUENCE OF OPERATIONS
A. General:
1. ON/OFF/AUTOMATIC” (O-O-A) selector switches shall start the unit when
in the “ON” position, stop the unit when in the “OFF” position, and perform
a specified operation through the direct digital controls (DDC) when in the
“AUTOMATIC” position.
2. Safety devices shall be hardwired, interlocked to operate in “ON” and
“AUTOMATIC” positions.
3. Safety sequences shall override other automatic control sequences.
4. Reset schedules and set points shown in Sequence of Operations are for
initial programming and start-up, during system check out the reset schedules
and set points shall be fine-tuned to obtain desired comfort and energy
15950-33 11/2017
2049
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
savings results. The Engineer reserves the right to make set point changes
based on installed operating conditions, at no additional cost to the City.
5. Automatic control functions that switch equipment on and off must be
programmed with dead bands or time delays to prevent short cycling of
equipment.
6. Hardwire relay logic shown on the drawings for the “ON” position is
provided so that units can provide fan control if the DDC microprocessors
should fail. In order to operate the fan in this mode, motorized dampers are
required to be positioned accordingly before the fan can be energized to
prevent dead-heading the fan. The hardwire relay logic shown on the
Contract Drawings is generic and may need to be modified accordingly
depending on number of dampers and damper logic requirements. Where
additional damper logic descriptions are required to convey hardwire
requirements, “ON” position logic may be included within the sequence of
operations and is understood to be hardwired without the use of DDC
microprocessors.
7. ATC Panels:
a. All controllers, relays, and other devices required to provide the
Sequence of Operations shall be housed within the ATC panel, except
where otherwise noted.
b. O-O-A selector switches and indicating lights shall be mounted on
the panel face.
c. Indicating lights shall be provided for each piece of equipment
controlled from the ATC panel and include the following, where
applicable:
1) Run.
2) Stop.
3) Motor Overload Alarm.
4) Low Temperature Alarm.
5) Dirty Filter.
6) Fail
a) Equipment indexed to run that has not been energized.
b) Broken belt drive
7) Ventilation System On.
8) Ventilation System Off.
15950-34 11/2017
2050
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
15. Provide discrete alarm contacts in the ATC panel for future connection for
the following:
a. Common alarm (any alarm condition except those alarms described
below)
b. Chlorine gas alarm (Chlorine Storage Room ventilation exhaust)
c. Chlorine gas alarm (Chlorinator Room ventilation exhaust)
d. Chlorine scrubber system activated
B. Equipment Operating Descriptions:
1. Heating and Ventilating Unit (HV-1) (Chlorine Storage and Chlorinator
Rooms):
a. HV-1 shall be indexed ON/OFF by a START/STOP pushbutton at the
ATC panel. HV-1 supply fan shall be energized to provide
continuous ventilation to the space.
b. When HV-1 is indexed to START, MD-HV1-1, MD-HV1-2, MD-
EF1-1, and MD-EF2-1 shall open and then the unit supply fan shall
be energized. When HV-1 is indexed to STOP, the unit supply fan
shall be de-energized and the dampers shall close.
c. The unit manufacturer shall wire following to the factory installed
unit control panel or remote interface, monitoring and control by the
ATC system:
1) Fan start.
2) Fan stop.
3) Fan status (energized or de-energized).
4) Fan motor overload.
5) Face and bypass damper control (modulating).
6) Intake damper control (two position).
7) Damper status (opened, closed).
8) Dirty filter.
15950-37 11/2017
2053
DETAILED SPECIFICATION 15950 – HVAC MONITORING AND CONTROL
CONTRACT DEL-260H
ATC panel. In the AUTO position, the fan shall be energized and de-
energized through a software interlock with SF-1.
b. When EF-3 is indexed to operate, MD-EF3-1 shall open and then the
fan shall be energized. When EF-3 is indexed to stop, the fan shall be
de-energized then the dampers shall close.
c. A current sensing relay shall monitor the motor current and provide a
broken drive belt alarm at the ATC panel when a no-load motor
current is detected.
7. Exhaust Fan EF-4 (Electric Room 2):
a. EF-4 shall be indexed ON/OFF/AUTO by an O-O-A switch at the
ATC panel. In the AUTO position, the fan shall be energized and de-
energized based on the relative temperature of the space and outdoor
air temperature.
b. The HMCS system shall compare the space temperature and outdoor
air temperature through the space temperature sensor and the outdoor
air temperature sensor and do the following when the outdoor air
temperature is 80°F or greater:
c. When the space temperature is greater than 5°F above the outdoor
temperature, the fan shall be indexed ON.
1) When the space temperature is 100°F, the fan shall be indexed
ON.
d. When EF-4 is indexed to operate, MD-EF4-1 shall open and then the
fan shall be energized. When EF-4 is indexed to stop, the fan shall be
de-energized and the dampers shall close.
8. Hot Water Pump (HWP-1) (Basement):
a. HWP-1 shall be indexed ON/OFF/AUTO by an O-O-A switch at the
ATC panel. In the AUTO position, the pump shall be energized and
de-energized through the outdoor air temperature sensor at 65°F.
b. A current sensing relay shall monitor the motor current and provide
run indication on the ATC panel.
9. Electric Unit Heaters (EUH):
a. EUH shall be energized and de-energized through its associated space
thermostat set at 55° F.
END OF SECTION
15950-40 11/2017
2056
DETAILED SPECIFICATION 15951H – TESTING ADJUSTING AND BALANCING
CONTRACT DEL-260H
SECTION 15951H
Testing, Adjusting and Balancing
NOTE: This Detailed Specification 15951H – Testing, Adjusting and Balancing replaces
General Specification 15951 – Testing, Adjusting and Balancing in its entirety. All
Work for this Section shall fully conform to the requirements specified herein.
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall provide all labor, materials, equipment and incidentals as
shown, specified and required to perform testing, adjusting and balancing of all
Heating, Ventilation and Air Conditioning Systems as specified or required for
proper operation.
1. All new equipment.
2. Existing zone flow and return header balancing valve differential pressure
data prior to beginning piping work associated with the existing boiler.
3. Final flow and return header balancing valve differential pressure data after
completing piping work associated with the existing boiler.
B. The following index of this Section is presented for convenience:
15951H-1 11/2017
2057
DETAILED SPECIFICATION 15951H – TESTING ADJUSTING AND BALANCING
CONTRACT DEL-260H
PART 2 PRODUCTS
2.01 INSTRUMENTS: GENERAL
A. Contractor shall provide all necessary instrumentation, tools, ladders, etc. to
complete all air and hydronic balancing tests and adjustments.
B. Instrumentation shall be in accordance with NEBB, AABC, or SMACNA
requirements and shall be calibrated to the accuracy standards demanded by these
organizations.
C. Flow-measuring hoods (manufactured, not fabricated) shall be acceptable for
measurement of ceiling diffuser performance only.
D. Contractor shall assume full responsibility for safe keeping of all instrumentation
during the course of work.
15951H-3 11/2017
2059
DETAILED SPECIFICATION 15951H – TESTING ADJUSTING AND BALANCING
CONTRACT DEL-260H
PART 3 EXECUTION
3.01 GENERAL
A. All testing, adjusting, and balancing of air and hydronic systems shall be performed
in compliance with the standard procedure manual published by the testing,
adjusting, and balancing organization affiliated with the Contractor. Contractor
shall submit one copy of the standard procedure manual to the Engineer for his
records.
B. Contractor shall be solely responsible for the protection and safeguarding of his
work and shall provide every protection against accidents, injury, and damage to
persons and property.
C. Contractor shall keep dust, dirt, and debris to an absolute minimum and reinstall all
removed ceiling components to their original positions at the end of each day.
D. Contractor shall be fully responsible for removal and reinstallation of ceiling
system and replacement of any component damaged.
E. Contractor shall install additional access panels at no extra cost to the City, as is
required to gain access to equipment concealed above ceilings, behind walls, or any
other concealed space.
F. Air systems shall be tested, adjusted, and balanced with clean filters.
G. Hydronic systems shall be tested, adjusted, and balanced with clean strainers.
3.02 INSPECTION
A. The Contractor shall conform to the requirements of this Contract Equipment
Check:
15951H-4 11/2017
2060
DETAILED SPECIFICATION 15951H – TESTING ADJUSTING AND BALANCING
CONTRACT DEL-260H
15951H-5 11/2017
2061
DETAILED SPECIFICATION 15951H – TESTING ADJUSTING AND BALANCING
CONTRACT DEL-260H
start-up or shutdown of equipment, etc. The change in the state of the controlled
device or equipment shall be shown to result in a corrective action on the controlled
parameter. Upsets include, but are not limited to, any condition which should cause
annunciation of an alarm, safety shutdown of equipment, startup of standby
equipment, closing of fusible-link devices, lifting of relief valves, etc. The
Contractor shall immediately restore to its original state any safety device, the state
of which has been changed by its having been tested.
E. The Contractor shall immediately correct any system deficiency that should come
to light during testing.
F. After the overall system testing has been completed, and after all final adjustments
have been made, the Contractor shall operate and maintain all new systems and
equipment, site-wide, associated therewith, for a period of thirty consecutive days.
During this period all normal maintenance (filter replacements, strainer cleaning,
periodic checks of safety devices, datalogging, etc.) shall be performed by the
Contractor. If, during this period, any work beyond routine maintenance of
equipment and materials installed under this Contract, should be required to
maintain proper operation of the overall system, the elapsed time shall be forfeited,
and a new thirty (30)-day period shall commence following the completion of the
corrective action.
3.04 BALANCING AND ADJUSTING
A. In addition to any other reference to balancing and adjusting specified elsewhere in
these Section, the Contractor shall be bound by this portion of the Section to
balance, adjust and leave in good working order all systems and accessories covered
under this Contract.
B. The Contractor shall procure the services of an independent balancing and testing
agency which specializes in the balancing and testing of heating, ventilating and air
conditioning systems to balance, test and adjust all systems installed under this
Section.
C. The Contractor shall advise the Engineer at least two weeks in advance of the date
scheduled for balancing to commence; at the Engineer's discretion, the balancing
shall be conducted in the Engineer's presence.
D. At least three (3) months prior to the commencement of balancing, the Contractor
shall forward a detailed explanation of the balancing procedure to the Engineer for
review. In general, the method shall conform to those specified by the NEBB,
AABC or SMACNA.
E. All piping systems shall be balanced under this Section to provide the flows
indicted on the Contract Drawings or in this Section.
F. Before beginning to balance the air systems the Contractor shall check, in the
presence of the Engineer, all filters and coils for cleanliness, dampers (automatic,
volume and fire) for correct position, all fans for proper rotation, and temperature
controls for minimum completeness to allow for proper balancing. If any of the
above or other conditions are found which would not allow for proper balancing
15951H-6 11/2017
2062
DETAILED SPECIFICATION 15951H – TESTING ADJUSTING AND BALANCING
CONTRACT DEL-260H
the Contractor shall take the necessary corrective actions, at his own expense,
before balancing begins.
G. All heating, ventilating, and air conditioning systems shall be balanced by the
Contractor by adjustment of dampers, fan sheaves, apparatus and air outlets to
provide the air quantities indicated on the Contract Drawings. If necessary,
adjustments of air outlets shall be made to eliminate drafts.
H. Balancing for all air systems shall be accomplished in a manner to first minimize
throttling losses, then fan speed shall be adjusted to meet design conditions. All air
outlets and fans shall be balanced within 5 percent of the design capacity.
I. Balancing for all hydronic systems shall be accomplished in a manner that results
in the balancing having a minimum pressure required to provide an accurate flow
measurement and not excessively high. (Inadequate pressure drop renders flow
readings inaccurate; excessive pressure drop imposes needless additional head on
the pumps). Balancing for all hydronic systems shall be accomplished in a manner
to first minimize throttling losses.
J. Pump flows shall be balanced within 5 percent of the specified capacity.
K. After the systems have been balanced, the Contractor shall submit and certify to the
City, a list containing the following minimum equipment:
1. Room served.
2. Size, quantity and model of air outlet or equipment.
3. Type of air outlet or equipment.
4. Air flow indicated on Contract Drawings.
5. Air flow measured.
6. GPM indicated on Contract Drawings.
7. GPM measured.
8. Coil entering and leaving water temperatures.
9. Fan cfm indicated on the Contract Drawings.
10. Fan cfm measured.
11. Fan motor running amps.
12. Coil entering and leaving water pressure.
13. Filter differential pressure.
14. Boiler entering and leaving water temperature.
15. Existing heating zone entering and leaving water temperature as measured
at the supply and return header.
16. Static pressure profile of all air handling unit sections.
17. Pump entering and leaving water pressure.
15951H-7 11/2017
2063
DETAILED SPECIFICATION 15951H – TESTING ADJUSTING AND BALANCING
CONTRACT DEL-260H
END OF SECTION
15951H-8 11/2017
2064
DETAILED SPECIFICATION 16010H – GENERAL ELECTRICAL
REQUIREMENTS
CONTRACT DEL-260H
SECTION 16010H
General Electrical Requirements
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16010 – General Electrical Requirements except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
16010H-1 11/2017
2065
DETAILED SPECIFICATION 16010H – GENERAL ELECTRICAL
REQUIREMENTS
CONTRACT DEL-260H
16010H-2 11/2017
2066
DETAILED SPECIFICATION 16076H – LABELING AND IDENTIFICATION
CONTRACT DEL-260H
SECTION 16076H
Labeling and Identification
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16076 – Labeling and Identification except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
16076H-1 11/2017
2067
DETAILED SPECIFICATION 16076H – LABELING AND IDENTIFICATION
CONTRACT DEL-260H
16076H-2 11/2017
2068
DETAILED SPECIFICATION 16121H – ELECTRIC WIRES AND CABLES
CONTRACT DEL-260H
SECTION 16121H
Electric Wires and Cables
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16121 – Electric Wire and Cables except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item H-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.03 REFERENCES
A. Electric wires and cables shall comply with the latest applicable provisions and
recommendations of the following:
1. Electrical Code of the City of New York.
2. NFPA 70 – National Electrical Code.
3. National Electrical Safety Code.
4. ASTM B5 – High Conductivity Tough-Pitch Copper Refinery Shapes.
5. ASTM B8 – Concentric-Lay-Stranded Copper Conductors, Hard, Medium-hard
or Soft.
6. ASTM D69 – Test Methods for Friction Tape
7. ICEA - Insulated Cable Engineers Association, Inc.
8. UL Standard No. 44 – Wires and Cables, Rubber-Insulated. (Standard for
Thermoset-Insulated Wires and Cables)
9. UL Standard No. 83 – Wires and Cables, Thermoplastic-Insulated.
10. UL Standard 486A – Wire Connectors and Soldering Lugs for Use with Copper
Conductors.UL 1072 – Medium Voltage Power Cables.
11. AEIC CS6-96 – Ethylene-Propylene-Rubber-Insulated Shielded Power Cable.
12. NETA – International Electrical Testing Association.
13. IEEE 48 – Test Procedures and Requirements for High Voltage Alternating-
Current Cable Terminations.
14. Consolidated Edison Company for electric wires and cables.
16121H-1 11/2017
2069
DETAILED SPECIFICATION 16121H – ELECTRIC WIRES AND CABLES
CONTRACT DEL-260H
PART 2 PRODUCTS
1. Conductors shall be stranded, tinned coated copper conforming to ASTM B8, No.
12 AWG minimum size.
E. Stress Cones: Provide a Class 3 indoor stress cone conforming to IEEE Std. 48 for
15kV, designed to accept cable insulation diameters from .495-inches to 1.875-
inches with cable shield device and grounding devices for a No. 2 copper ground
wire.
.
F. SECTIONALIZING CABINET
1. Provide 15kV sectionalizing cabinet with 200A 15kV junctions. Cabinet shall be
manufactured with min 12 gauge steel and stainless steel hardware.
2. Furnish 200A 15kV deadbreak elbow connectors fully shielded and insulated
plug-in termination type molded using high quality peroxide-cured EPDM
16121H-2 11/2017
2070
DETAILED SPECIFICATION 16121H – ELECTRIC WIRES AND CABLES
CONTRACT DEL-260H
H. FEEDTHROUGH INSERTS
1. Provide 200A 15kV rotatable feedthrough inserts to provide dual bushing from
single bushing well. Feedthrough insert shall comply with IEEE 386 standards.
2. Furnish Feedthrough insert by Cooper Industries, Houston, TX, or approved
equal.
B. The fire and arc proofing tape shall consist of a flexible conformable unsupported
intumescent elastomer. The tape shall be not less than .030 inches thick and be
capable of over 100 percent elongation. The tape shall be non-corrosive to metallic
cable sheaths and compatible with synthetic cable jackets (i.e. semi-conducting URD
type, polyethylene, P.V.C., etc.). It shall be self-extinguishing and shall not support
combustion. The tape shall not deteriorate when subjected to water, salt water, gases
and sewage.
C. The wrapped tape shall be secured by a band, consisting of two layers (the second
wrapped directly over the first) of glass cloth electrical tape. The completed
installation of single half-lapped layer of arc and fireproofing tape shall be capable of
withstanding a high current (60 Hz) fault arc temperature of 13,000 degrees K for 70
cycles.
D. Fire and arc proofing tape shall conform to Scotch 77, as manufactured by the 3M
Company, St. Paul, MN or approved equal
E. Glass cloth electrical tape shall conform to Scotch 69, as manufactured by the 3M
Company, St. Paul, MN.
2071
DETAILED SPECIFICATION 16121H – ELECTRIC WIRES AND CABLES
CONTRACT DEL-260H
END OF SECTION
16121H-4 11/2017
2072
DETAILED SPECIFICATION 16131H – ELECTRIC CONDUIT SYSTEM
CONTRACT DEL-260H
SECTION 16131H
Electric Conduit System
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16131 – Electric Conduit System except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
B. The electric conduit system shall be designed, constructed and installed suitable for
earthquake regulations in accordance with the seismic requirements of the City of
New York Building Code, the Uniform Building Code for Zone 2A application and
local and state building codes.
C. Flexible conduit used in all areas shall include a steel core with a liquid-tight,
polyvinyl chloride cover and shall include a built-in copper ground for sizes 3/4-inch
through 1-1/4 inch.
B. For all areas, conduit fittings and outlet bodies shall be cast gray iron alloy, cast
malleable iron bodies and covers. All units shall be gasketed, watertight, and threaded
with five full threads and shall have rust-proofing in accordance with the requirements
16131H-1 11/2017
2073
DETAILED SPECIFICATION 16131H – ELECTRIC CONDUIT SYSTEM
CONTRACT DEL-260H
of Paragraph 2.06. Fittings and bodies installed on PVC coated conduits shall also
include interior and exterior coatings equivalent to the conduit.
D. For concealed areas, pressed steel boxes of the proper size and depths for the
application shall be provided. Boxes shall be rated NEMA 12, not less than No. 14
U.S. Standard Gauge (0.078 inch). The conduit openings shall be provided with oil
resistant gaskets. Conduits shall be fastened to these boxes with grounding bushings
and hub. All unused outlets or holes shall be left sealed.
F. For all conduit runs, connections to boxes and fittings shall be made through threaded
holes. Where necessary, unions may be used. Unions in hazardous locations shall be
Crouse Hinds type UNF, UNL, UNY conduit fittings or equal to be approved by the
Engineer. Unions in non-hazardous areas shall be Universal or Erickson conduit
couplings or equal to be approved by the Engineer.
H. All boxes installed for concealed conduit, shall be provided with extension rings or
plaster rings and covers as required. For finished areas stainless 302/304. satin
beveled steel cover and device plates for surface mounted boxes shall be used. For
other areas galvanized ferrous and galvanized cast ferrous metal cover and device
plates with neoprene gaskets shall be used.
1. Conduit hubs shall be threaded, insulated throat type with bonding screw
grounding bushing.
F. Conduit Bushings:
16131H-2 11/2017
2074
DETAILED SPECIFICATION 16131H – ELECTRIC CONDUIT SYSTEM
CONTRACT DEL-260H
1. For corrosive locations boxes shall be corrosion resistant, NEMA Type 4X.
Except for chlorine areas, boxes shall be constructed of 316 stainless steel
material with sealed seams. Boxes in chlorine areas shall be constructed of non-
metallic FRP materials and shall be explosion proof NEMA Type 7.
2. Refer to the NEMA room designations on contract drawings for additional detail
on box and accessory ratings.
PART 3 EXECUTION
3.01 GENERAL
O. Where conduit enter or leave equipment located within electrical, control, chlorine,
scrubber or other corrosive areas and rooms, the conduit shall be sealed and packed
with duct seal compound.
END OF SECTION
16131H-3 11/2017
2075
DETAILED SPECIFICATION 16131H – ELECTRIC CONDUIT SYSTEM
CONTRACT DEL-260H
16131H-4 11/2017
2076
DETAILED SPECIFICATION 16221H – ELECTRIC MOTORS
CONTRACT DEL-260H
SECTION 16221H
Electric Motors
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16221 – Electric Motors except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
END OF SECTION
16221H-1 11/2017
2077
DETAILED SPECIFICATION 16221H – ELECTRIC MOTORS
CONTRACT DEL-260H
16221H-2 11/2017
2078
DETAILED SPECIFICATION 07140E – FLUID-APPLIED WATERPROOFING
CONTRACT DEL-260E
SECTION 07140E
Fluid-Applied Waterproofing
NOTE: All Work for this Section shall be in accordance with the requirements of
General Specification 07140 – Fluid-Applied Waterproofing except as modified
herein.
PART 1 GENERAL
A. None
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the Allowance bid for Contract Item E-A-5, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
07140E-1 11/2017
2079
DETAILED SPECIFICATION 07140E – FLUID-APPLIED WATERPROOFING
CONTRACT DEL-260E
07140E-2 11/2017
2080
DETAILED SPECIFICATION 13281E – ASBESTOS MANAGEMENT
CONTRACT DEL-260E
SECTION 13281E
ASBESTOS MANAGEMENT
NOTE: All work for this Section shall be in accordance with the requirements of General
Specification 13281 – Asbestos Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. Except for abatement of unforeseen ACM and related Work payable under the
allowance, as described in Section 01355– Hazardous Materials Control, no
separate payment will be made for performing any Work required under this
Section and the Contractor shall include all costs thereof in its lump sum price bid
for Contract Item E-LS-1, as described in Detail Specification 01270 –
Measurement and Payment.
END OF SECTION
13281E-1 11/2017
2081
DETAILED SPECIFICATION 13281E – ASBESTOS MANAGEMENT
CONTRACT DEL-260E
13281E-2 11/2017
2082
DETAILED SPECIFICATION 13282E – MERCURY MANAGEMENT
CONTRACT DEL-260E
SECTION 13282E
Mercury Management
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 13282 – Mercury Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
END OF SECTION
13282E-1 11/2017
2083
DETAILED SPECIFICATION 13282E – MERCURY MANAGEMENT
CONTRACT DEL-260E
13282E-2 11/2017
2084
DETAILED SPECIFICATION 13283E - LEAD MANAGEMENT
CONTRACT DEL-260E
SECTION 13283G
Lead Management
NOTE: All work for this Section shall be in accordance with the requirements of General
Specification 13283 – Lead Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. A.Except for unforeseen lead-containing materials and related work eligible for
payment under allowance, as described in Section 01355– Hazardous Materials
Control, no separate payment will be made for performing any work required
under this Section and the Contractor shall include all costs thereof in its lump
sum price bid for Contract Item E-LS-1, as described in Detailed Specification
01270 – Measurement and Payment.
END OF SECTION
13283E-1 11/2017
2085
DETAILED SPECIFICATION 13283E - LEAD MANAGEMENT
CONTRACT DEL-260E
13283E-2 11/2017
2086
DETAILED SPECIFICATION 13284E - PCB MANAGEMENT
CONTRACT DEL-260E
SECTION 13284E
PCB Management
NOTE: All work for this Section shall be in accordance with the requirements of General
Specification 13284 – PCB Management except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. Except for unforeseen PCB-containing materials and related work eligible for
payment under allowance, as described in Section 01355 – Hazardous Materials
Controls, no separate payment will be made for performing any work of this
Section and the Contractor shall include all costs thereof in its lump sum price bid
for Contract Item E-LS-1, as described in Detailed Specification 01270 –
Measurement and Payment.
END OF SECTION
13284E-1 11/2017
2087
DETAILED SPECIFICATION 13284E - PCB MANAGEMENT
CONTRACT DEL-260E
13284E-2 11/2017
2088
DETAILED SPECIFICATION 16010E – GENERAL ELECTRICAL
REQUIREMENTS
CONTRACT DEL-260E
SECTION 16010E
General Electrical Requirements
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16010 – General Electrical Requirements except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
16010E-1 11/2017
2089
DETAILED SPECIFICATION 16010E – GENERAL ELECTRICAL
REQUIREMENTS
CONTRACT DEL-260E
16010E-2 11/2017
2090
DETAILED SPECIFICATION 16020E – TEMPORARY ELECTRICAL SYSTEM
CONTRACT DEL-260E
SECTION 16020E
Temporary Electrical System
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16020 – Temporary Electrical System except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
8. The Contractor shall provide all portable cables necessary to connect portable
generator to existing distribution equipment.
9. The Contractor shall provide a start signal circuit from the existing ATS to
portable generator.
10. The Contractor shall provide a 120V branch circuit for generator
jacket heater.
2091
DETAILED SPECIFICATION 16020E – TEMPORARY ELECTRICAL SYSTEM
CONTRACT DEL-260E
END OF SECTION
16020E-2 11/2017
2092
DETAILED SPECIFICATION 16035E – DEMOLITION ELECTRICAL
CONTRACT DEL-260E
SECTION 16035E
Demolition, Electrical
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16035 – Demolition Electrical except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
16035E-1 11/2017
2093
DETAILED SPECIFICATION 16035E – DEMOLITION ELECTRICAL
CONTRACT DEL-260E
16035E-2 11/2017
2094
DETAILED SPECIFICATION 16061E – GROUNDING
CONTRACT DEL-260E
SECTION 16061E
Grounding
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16061 – Grounding except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
D. Provide UL Listed Steel, H-20 rated Heavy Duty High Traffic Area Test/Inspection
Wells at all ground rod locations.
END OF SECTION
16061E-1 11/2017
2095
DETAILED SPECIFICATION 16061E – GROUNDING
CONTRACT DEL-260E
16061E-2 11/2017
2096
DETAILED SPECIFICATION 16071E – SUPPORTING DEVICES
CONTRACT DEL-260E
SECTION 16071E
Supporting Devices
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16071 – Supporting Devices except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
E. All channels, fittings, brackets and related hardware shall be steel and have a hot-dip
galvanized finish according to ASTM A123.
16071E-1 011/2017
2097
DETAILED SPECIFICATION 16071E – SUPPORTING DEVICES
CONTRACT DEL-260E
PART 3 EXECUTION
3.01 INSTALLATION
END OF SECTION
16071E-2 011/2017
2098
DETAILED SPECIFICATION 16076E – LABELING AND IDENTIFICATION
CONTRACT DEL-260E
SECTION 16076E
Labeling and Identification
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16076 – Labeling and Identification except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
END OF SECTION
16076E-1 11/2017
2099
DETAILED SPECIFICATION 16076E – LABELING AND IDENTIFICATION
CONTRACT DEL-260E
16076E-2 11/2017
2100
DETAILED SPECIFICATION 16121E – ELECTRIC WIRES AND CABLES
CONTRACT DEL-260E
SECTION 16121E
Electric Wires and Cables
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16121 – Electric Wire and Cables except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.03 REFERENCES
A. Electric wires and cables shall comply with the latest applicable provisions and
recommendations of the following:
1. Electrical Code of the City of New York.
2. NFPA 70 – National Electrical Code.
3. National Electrical Safety Code.
4. ASTM B5 – High Conductivity Tough-Pitch Copper Refinery Shapes.
5. ASTM B8 – Concentric-Lay-Stranded Copper Conductors, Hard, Medium-hard
or Soft.
6. ASTM D69 – Test Methods for Friction Tape
7. ICEA - Insulated Cable Engineers Association, Inc.
8. Underwriter’ Laboratories, Inc. (UL):
a. UL Standard No. 44 – Wires and Cables, Rubber-Insulated. (Standard for
Thermoset-Insulated Wires and Cables)
b. UL Standard No. 83 – Wires and Cables, Thermoplastic-Insulated.
c. UL Standard 486A – Wire Connectors and Soldering Lugs for Use with
Copper Conductors
d. UL 510 - Insulating Tapes
e. UL 1072 – Medium Voltage Power Cables
2101
DETAILED SPECIFICATION 16121E – ELECTRIC WIRES AND CABLES
CONTRACT DEL-260E
PART 2 PRODUCTS
1. Conductors shall be stranded, tinned coated copper conforming to ASTM B8, No.
12 AWG minimum size.
E. STRESS CONES
1. Provide a Class 3 indoor stress cone conforming to IEEE Std. 48 for 15kV,
designed to accept cable insulation diameters from .495-inches to 1.875- inches
with cable shield device and grounding devices for a No. 2 copper ground wire.
. F. SECTIONALIZING CABINET
1. Provide 15kV sectionalizing cabinet with 200A 15k V junctions. Cabinet shall be
manufacturer with min 12 gauge steel and stainless steel hardware.
2102
DETAILED SPECIFICATION 16121E – ELECTRIC WIRES AND CABLES
CONTRACT DEL-260E
2. Furnish 200A 15kV deadbreak elbow connectors fully shielded and insulated
plug-in termination type molded using high quality peroxide-cured EPDM
insulation as manufactured by Cooper Industries, Houston, TX or approved
equal.
H. FEEDTHRU INSERTS
1. Provide 200A 15kV rotatable feedthrough inserts to provide dual bushing from
single bushing well. Feedthru insert shall comply with IEEE 386 standards.
2. Furnish Feedthrough insert by Cooper Industries, Houston, TX or approved
equal.
B. The fire and arc proofing tape shall consist of a flexible conformable unsupported
intumescent elastomer. The tape shall be not less than .030 inches thick and be
capable of over 100 percent elongation. The tape shall be non-corrosive to metallic
cable sheaths and compatible with synthetic cable jackets (i.e. semi-conducting URD
type, polyethylene, P.V.C., etc.). It shall be self-extinguishing and shall not support
combustion. The tape shall not deteriorate when subjected to water, salt water, gases
and sewage.
C. The wrapped tape shall be secured by a band, consisting of two layers (the second
wrapped directly over the first) of glass cloth electrical tape. The completed
installation of single half-lapped layer of arc and fireproofing tape shall be capable of
withstanding a high current (60 Hz) fault arc temperature of 13,000 degrees K for 70
cycles.
D. Fire and arc proofing tape shall conform to Scotch 77 as manufactured by the 3M
Company, Maplewood, MN or approved equal. Glass cloth electrical tape shall
conform to Scotch 69 as manufactured by the 3M Company, Maplewood, MN or
approved equal
16121E-3 11/2017
2103
DETAILED SPECIFICATION 16121E – ELECTRIC WIRES AND CABLES
CONTRACT DEL-260E
END OF SECTION
16121E-4 11/2017
2104
DETAILED SPECIFICATION 16131E – ELECTRIC CONDUIT SYSTEM
CONTRACT DEL-260E
SECTION 16131E
Electric Conduit System
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16131 – Electric Conduit System except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
D. Conduits, elbows and coupling shall include a PVC coating for all areas. Refer to the
NEMA room designations on Contract Drawings for use of non PVC RGS coated
conduit.
B. The electric conduit system shall be designed, constructed and installed suitable for
earthquake regulations in accordance with the seismic requirements of the City of
New York Building Code, the Uniform Building Code for Zone 2A application and
local and state building codes.
B. Flexible conduit used in all areas shall include a steel core with a liquid-tight,
polyvinyl chloride cover and shall include a built-in copper ground for sizes 3/4-inch
through 1-1/4 inch.
16131E-1 11/2017
2105
DETAILED SPECIFICATION 16131E – ELECTRIC CONDUIT SYSTEM
CONTRACT DEL-260E
B. For all areas, conduit fittings and outlet bodies shall be cast gray iron alloy, cast
malleable iron bodies and covers. All units shall be gasketed, watertight, and threaded
with five full threads and shall have rust-proofing in accordance with the requirements
of Article 2.06. Fittings and bodies installed on PVC coated conduits shall also
include interior and exterior coatings equivalent to the conduit.
D. For concealed areas, pressed steel boxes of the proper size and depths for the
application shall be provided. Boxes shall be rated NEMA 12, not less than No. 14
U.S. Standard Gauge (0.078 inch). The conduit openings shall be provided with oil
resistant gaskets. Conduits shall be fastened to these boxes with grounding bushings
and hub. All unused outlets or holes shall be left sealed.
F. For all conduit runs, connections to boxes and fittings shall be made through threaded
holes. Where necessary, unions may be used. Unions in hazardous locations shall be
by Crouse Hinds, or approved equal, type UNF, UNL, UNY conduit fittings or equal
to be approved by the Engineer.
H. All boxes installed for concealed conduit, shall be provided with extension rings or
plaster rings and covers as required. For finished areas stainless 302/304 satin
beveled steel cover and device plates for surface mounted boxes shall be used. For
other areas galvanized ferrous and galvanized cast ferrous metal cover and device
plates with neoprene gaskets shall be used.
1. Conduit hubs shall be threaded, insulated throat type with bonding screw
grounding bushing.
F. Conduit Bushings:
1. For corrosive locations boxes shall be corrosion resistant, NEMA Type 4X.
Except for chlorine areas, boxes shall be constructed of 316 stainless steel
material with sealed seams. Boxes in chlorine areas shall be constructed of non-
metallic FRP materials and shall be explosion proof NEMA Type 7.
2. Refer to the NEMA room designations on Contract Drawings for additional detail
on box and accessory ratings.
PART 3 EXECUTION
3.01 GENERAL
O. Where conduit enter or leave equipment located within electrical, control, chlorine,
scrubber or other corrosive areas and rooms, the conduit shall be sealed and packed
with duct seal compound.
16131E-3 11/2017
2107
DETAILED SPECIFICATION 16131E – ELECTRIC CONDUIT SYSTEM
CONTRACT DEL-260E
END OF SECTION
16131E-4 11/2017
2108
DETAILED SPECIFICATION 16133E – UNDERGROUND DUCTS, DUCTS IN
CONCRETE
CONTRACT DEL-260E
SECTION 16133E
Underground Ducts, Ducts in Concrete
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16133 – Underground Ducts, Ducts in Concrete except as modified
herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.05 SUBMITTALS
A. All electrical work to be performed under this Section shall be accomplished using
personnel trained and skilled in the craft. All electrical work shall be performed by
personnel licensed in the authority having jurisdiction.
PART 2 PRODUCTS
16133E-1 11/2017
2109
DETAILED SPECIFICATION 16133E – UNDERGROUND DUCTS, DUCTS IN
CONCRETE
CONTRACT DEL-260E
A. Steel conduit for ducts shall be in accordance with the requirements of General
Specification 16131 - Electric Conduit System, except PVC coating of conduit is not
required. Rigid steel conduit shall be used for all systems throughout the underground
system. The use of non-metallic conduit and fittings as specified in Article 2.02 shall
not be permitted.
B. Refer to Contract Drawings for additional detail on reinforcing the concrete for duct
banks.
A. Expansion and deflection fittings shall be provided at the structural joints of the
underground duct system.
A. Conduit Grounding bushings shall be provided for the termination of conduits at each
manhole.
PART 3 EXECUTION
3.01 INSTALLATION
I. Terminate the duct bank conduits at building and manhole walls using insulated
grounding bushings in accordance with the details shown on the Contract Drawings.
Where duct banks turn upward for continuation above grade, a transition shall be
16133E-2 11/2017
2110
DETAILED SPECIFICATION 16133E – UNDERGROUND DUCTS, DUCTS IN
CONCRETE
CONTRACT DEL-260E
made from rigid steel conduit to PVC coated rigid steel conduits if required for the
area.
N. Provide field testing of the duct bank system. The testing shall include conduit
cleaning and ground testing. The field testing shall be in accordance with the General
Specification 16131 - Electric Conduit System.
Q. Install an expansion and deflection fitting on each conduit at each of the structural
expansion joints. Joints shall be located as defined by the criteria noted on the
Contract Drawings.
END OF SECTION
16133E-3 11/2017
2111
DETAILED SPECIFICATION 16133E – UNDERGROUND DUCTS, DUCTS IN
CONCRETE
CONTRACT DEL-260E
16133E-4 11/2017
2112
DETAILED SPECIFICATION 16134E – ELECTRIC MANHOLES
CONTRACT DEL-260E
SECTION 16134E
Electric Manholes
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16134 – Electric Manholes except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
A. All electrical work to be performed under this Section shall be accomplished using
personnel trained and skilled in the craft. All electrical work shall be performed by
personnel licensed in Westchester County, New York.
H. All electrical work to be performed under this Section shall be accomplished using
personnel trained and skilled in the craft. All electrical work shall be performed by
personnel licensed in the Town of Mount Pleasant, New York.
END OF SECTION
16134E-1 11/2017
2113
DETAILED SPECIFICATION 16134E – ELECTRIC MANHOLES
CONTRACT DEL-260E
16134E-2 11/2017
2114
DETAILED SPECIFICATION 16211E – ELECTRICAL SERVICE ENTRANCE
CONTRACT DEL-260E
SECTION 16211E
Electrical Service Entrance
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16121 – Electrical Service Entrance except as modified herein.
PART 1 GENERAL
B. The electrical service entrance equipment required under this section shall
include overhead and underground primary service, outdoor pad mounted
cast coil transformers and low voltage type service equipment suitable for
delivering electric energy from the Consolidated Edison Company (Con
Edison) to the wiring system of the Shaft 18 facility.
C. The electrical service entrance equipment required under this section shall also
include coordination with Con Edison, installation of primary service
overhead and underground facilities, poles, medium and low voltage
terminations and appurtenances indicated on the Contract Drawings.
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
B. The Contractor shall pay to Con Edison all costs associated with the service.
16211E-1 11/2017
2115
DETAILED SPECIFICATION 16211E – ELECTRICAL SERVICE ENTRANCE
CONTRACT DEL-260E
1.04 REFERENCES
3. The service entrance equipment shall be designed and built in accordance with
the latest applicable editions of ANSI/IEEE, NEMA, UL, the Electrical Code of
the City of New York and the latest applicable requirements of Con Edison.
7. Permits: Obtain all permits required to commence Work and, upon completion of
the Work, obtain and deliver to Engineer a Certificate of Inspection and approval
from the State Board of Fire Underwriters or other authority having jurisdiction.
3. The costs of all necessary arrangements and coordination with Con Edison shall
be included for payment in the lump sum price bid for the Work under this
Contract.
16211E-2 11/2017
2116
DETAILED SPECIFICATION 16211E – ELECTRICAL SERVICE ENTRANCE
CONTRACT DEL-260E
A. The service entrance equipment shall be designed, constructed and installed suitable
for earthquake regulations in accordance with the seismic requirements of the City of
New York Building Code, the Uniform Building Code for Zone 2A application and
local and state building codes.
A. Service entrance equipment shall be delivered, stored and handled in accordance with
the Detailed Specifications, the manufacturer’s instructions and the following:
1. Equipment shall be inspected for shipping damage or loose parts when received.
Evidence of water which may have entered equipment during transit shall be
checked.
A. Existing Conditions:
1. The Contractor shall examine the Site and existing facilities in order to compare
them with the Contract Drawings and Specifications with respect to the
conditions of the premises, location of and connection to existing facilities and
any obstructions which may be encountered.
16211E-3 11/2017
2117
DETAILED SPECIFICATION 16211E – ELECTRICAL SERVICE ENTRANCE
CONTRACT DEL-260E
2. The Contractor is cautioned to perform their Work with due regard to safety and
in a manner that will not interfere with existing equipment or in any way cause
interruption of any of the functions of the facility.
PART 2 PRODUCTS
1. The service entrance equipment bus bars shall be tin-plated copper, supported
with high impact, non-tracking insulating material. The bus joints shall be
secured with Belleville type washers and shall be braced for the mechanical
forces exerted during short circuit conditions. Bus bar sizes shall be based upon a
maximum temperature rise of 65 degrees C over a 40 degrees C ambient in
accordance with UL and NEMA standards.
2. The service entrance equipment shall be adequately braced for the maximum
available short circuit current fault condition.
1. The main service disconnects shall be circuit breaker molded case type.
3. The service entrance main service disconnects shall include microprocessor type
bus metering in accordance with the requirements of General
Specification 16430 - Low Voltage Switchgear.
16211E-4 11/2017
2118
DETAILED SPECIFICATION 16211E – ELECTRICAL SERVICE ENTRANCE
CONTRACT DEL-260E
4. Transformer shop tests shall be witnessed by the Engineer and the City
representative and include the following:
a. Resistance measurements of all windings shall be performed on the rated
voltage connection.
b. Ratio test on the rated voltage connection and on all tap connections shall be
performed.
c. Polarity and phase relation tests on the rated voltage connection shall be
performed.
d. No load loss at rated voltage on the rated voltage connection shall be
performed.
e. Excitation current at rated voltage on the rated voltage connection shall be
performed.
f. Impedance and load loss at rated current on the rated voltage connection
shall be performed.
g. Applied potential tests shall be performed.
h. Induced potential test shall be performed.
i. High potential test shall be performed.
j. Temperature rise test at Ambien Air (AA) rating shall be performed.
PART 3 EXECUTION
A. The Contractor shall coordinate with the utility for shut down of the service. Dewater
and clean existing manholes prior testing the service conductors. Submit detailed
schedule noting duration for utility shutdown, dewatering and cleaning manholes and
inspecting and testing service conductors to the City and Engineer 45 days prior
commencing with actual Work.
16211E-5 11/2017
2119
DETAILED SPECIFICATION 16211E – ELECTRICAL SERVICE ENTRANCE
CONTRACT DEL-260E
B. Inspect and test existing medium voltage service conductors in all the existing
manholes from Columbus Avenue up to Shaft-18 facility building. Testing shall be
performed in accordance ANSI/NETA MTS-2015 Maintenance Testing Specification.
All tests and values for wire and cable shall be in accordance with the manufacturer's
recommendations and NETA, MTS Maintenance Testing Specification. The
Contractor shall provide a testing report. The report shall be in accordance with
NETA, MTS Maintenance Testing Specification.
C. Existing manholes shall be dewatered and cleaned prior to testing service conductors.
D. Submit detailed assessment report to the City and Engineer for approval.
E. The Contractor shall notify the City two (2) weeks prior to the date Work to be
performed.
END OF SECTION
16211E-6 11/2017
2120
DETAILED SPECIFICATION 16221E – ELECTRIC MOTORS
CONTRACT DEL-260 E
SECTION 16221E
Electric Motors
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16221 – Electric Motors except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
END OF SECTION
16221E-1 11/2017
2121
DETAILED SPECIFICATION 16221 – ELECTRIC MOTORS
CONTRACT DEL-260 E
16221-2 11/2017
2122
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
SECTION 16231E
Standby Power
PART 1 GENERAL
A. The Contractor shall provide, install and acceptance test a complete and operable
Gas-Fueled Electric Generator Set, including all labor, materials, equipment and
incidentals as shown, specified and required to furnish and install standby power.
Equipment shall be new, factory tested and delivered ready for installation.
B. Standby power required under this section shall be from natural gas-fueled
generator set. The generator set shall include all appurtenances for a complete
functioning standby power generating system. The Contractor and the generator
supplier shall coordinate with the G Contractor and Con Edison for a complete
and operable system.
PART 2 PRODUCTS...........................................................................................8
2.01 Manufacturers ........................................................................................8
2.02 Generator Set .........................................................................................8
2.03 Engine ....................................................................................................9
2.04 Alternator .............................................................................................11
16231E-1 11/2017
2123
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
16231E-2 11/2017
2124
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
1.04 REFERENCES
A. Standby power shall comply with the latest applicable provisions and
recommendations of the following:
1. Electrical Code of the City of New York.
2. NFPA 30 - Flammable and Combustible Liquids Code.
3. NFPA 37 - Standard for Installation and use of Stationary
Combustible Engine and Gas Turbines.
4. NFPA 70 - National Electrical Code.
5. NFPA 110 - Standard for Emergency and Standby Power
Systems.
6. NEMA MG1 - Motors and Generators.
7. NEMA MG2 - Safety Standard for Construction and
Guide for
Selection, Installation and Use of Motors and
Generators.
8. NEMA AB1 - Molded Case Circuit Breakers
9. ISO STD 8528 - Reciprocating Internal Combustion Engines
10. ISO STD 3046 - Performance Standard for Reciprocating
Internal Combustion Engines.
11. UL 142 - Steel Aboveground Tanks for Flammable and
Combustible Liquids.
12. UL 508 - Industrial Control Equipment.
13. EGSA - Electrical Generating Systems
Association
14. NFPA 54 - National Fuel Gas Code
15. UL 2200 - Stationary Engine Generator Assemblies
16. UL 1236 - Battery Chargers
A. The generator sets shall be designed, built and tested in accordance with the latest
applicable editions of NFPA, NEMA and NGSA.
16231E-3 11/2017
2125
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
B. The generator sets shall operate at 1800 rpm, 60 hertz from natural gas and be
equipped with all necessary accessories.
C. The generator sets shall be rated for continuous 24-hour per day operation for the
duration of any normal utility outage up to a maximum of 30 days.
D. The generator sets telephone influence factor shall be less than 50 in accordance
with NEMA MG1-22.43.
E. The KW, KVA, power factor, voltage and number of phases of the Standby
generator shall be as specified.
F. The generator sets shall have suitable motor starting capability to limit the voltage
dip to less than 20 percent when starting operational facility process and lighting
loads.
G. The generator sets shall have identifying nameplates in accordance with the
requirements of General Specification 16076 - Labeling and Identification.
Alternator nameplates shall also be in accordance with NEMA MG1.
H. The generator sets shall be designed for outdoor installations.
I. The generator shall comply with the applicable requirements of 40 CFR 60
Subpart JJJJ – Standards of Performance for Stationary Spark-Ignition Internal
Combustion Engines.
1.06 SUBMITTALS
A. Contractor shall submit Shop Drawings and material specifications for the
approval of the Engineer. Submittals shall include, but not be limited to:
1. Manufacturer's technical information which shall include:
a. Standard published curves of standby generator rating. Special or
maximum ratings are not acceptable.
b. Calculations confirming motor starting capability.
c. Published data of the generator line and machine constants.
d. Published data of fuel and oil consumption estimates, based on
engine manufacturer's data.
e. Published manufacturer’s estimated data of cooling and
combustion air flow requirements, plus heat rejection of the engine
and generator when operating at full load.
f. Proof of compliance with all local, federal as well as EPA codes
with respect to noise control and exhaust emissions.
16231E-4 11/2017
2126
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
A. General:
1. Each generator set shall be of current manufacture from a firm regularly
engaged in the production of such equipment. The firm shall have
experience in designing, supplying and supporting standby generators sets.
2. Each generator set shall be factory assembled and tested to determine that
it is free from electrical or mechanical defects and to assure that it meets
design specifications.
3. Each generator set shall be adequately guarded both physically and
electrically for protection of operating personnel.
16231E-5 11/2017
2127
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
4. All materials, equipment and parts comprising each generator set shall be
new, of current manufacturer and of the highest grade. All components
shall be covered by the manufacturer’s standard warranty on new
machines.
5. The generator set manufacturer shall have complete parts and service
facilities and ensure the availability of a manufacturer-trained technicians
on a 24-hour basis. Services shall be readily available so to avoid long
periods of interruption or require extensive spare parts inventory.
6. The generator set manufacturer shall use a shop test facility that has
recently calibrated testing apparatus and qualified, experienced
technicians, for all factory tests. Calibration of testing apparatus shall be
within one year.
7. All test equipment and instrument calibration shall be in accordance with
the latest edition of the accuracy standard of the U.S. National Institute of
Standards and Technology and the NETA maintenance testing
specification.
B. Field Tests:
1. The generator set shall be field tested. Field testing shall be performed in
accordance with the requirements specified under Article 3.02.
2. The services of the generator set manufacturer shall be retained for field
service. Field service shall be in accordance with the requirements
specified under Article 3.03.
3. Retain the service of an independent testing firm who shall perform field
acceptance testing of the generator set. The testing firm shall have
experience in the inspection and testing of the equipment and shall be a
member company of NETA. Acceptance testing shall be in accordance
with the requirements specified under Article 3.04.
A. Generators shall be delivered, stored and handled in accordance with the Detailed
Specifications 01651 – Transportation and Handling of Materials, the generator
manufacturer’s instructions and the following:
1. Generators shall be inspected for shipping damage when received.
2. All sleeve or oil lubricated bearings generators shall be identified and the
bearing reservoirs filled to normal level.
3. Generators shall be handled using base lifting lugs. Avoid pounding or
bumping of generator which may damage unit. A hoist and spreader bar
arrangement shall be used to avoid damage.
16231E-6 11/2017
2128
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
A. The generator set manufacturer guaranty shall include all equipment furnished
under this Section against defects in workmanship and material for a period of
twenty-four (24) months from the date of final acceptance of the equipment.
B. All costs for labor, transportation, freight and replacement parts required to
satisfactorily repair any piece of equipment as a result of equipment malfunction
during the guarantee period shall be considered to have been included in the lump
sum price bid for providing the generator sets.
C. The Service and Maintenance Agreement shall cover maintenance as well as
emergency repairs. The agreement shall at a minimum include the following:
1. All maintenance recommended by the manufacturer including checkout,
inspection and maintenance of all furnished components and wiring once
per year.
2. All parts, labor, and other expenses associated with providing emergency
(within forty-eight (48) hours) on-site repairs, regardless of the reason for
failure excepting misuse or vandalism.
3. A report shall be submitted after each site visit describing the problem,
solution, all work performed and parts replaced.
A. The Contractor shall furnish and deliver to the Engineer, at that part of the site
and at such time as the Engineer may direct, spare parts for the generator sets in
accordance with the Detailed Specifications 01750 – Spare Parts & Maintenance
Materials.
B. The spare parts shall be listed in an index and packed in containers suitable for
long term storage, bearing labels clearly designating the manufacturer's part
number with complete information for use and reordering.
C. Spare parts shall be furnished in accordance with the manufacturer's
recommendations for the generator size and type. Spare parts shall include at a
minimum the following:
16231E-7 11/2017
2129
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
1. One complete set of air, oil and fuel filters shall be provided of each type
and size used.
2. One complete set of belts and hoses shall be provided of each type and
size used.
3. Two sets of control power fuses shall be provided of each type and size
used.
4. Two per ten pilot lights shall be provided of each size and type used.
D. The Contractor shall furnish as part of the bulk lubricant order the quantity of
lubricants required to operate and maintain the generators furnished under this
section for a period of one year after acceptance. As a minimum, there shall be
provided sufficient oil and grease to make a least one lubricant change. Replace
all lubricants used during startup and testing prior to acceptance of equipment.
Furnish this replacement lubricant in addition to the lubricants included in the
bulk order.
PART 2 PRODUCTS
2.01 MANUFACTURERS
16231E-8 11/2017
2130
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
2.03 ENGINE
A. Generator set shall include an engine. The engine shall be configured for
generator set service and be of the internal combustion-natural gas. The engine
shall be equipped to operate on natural gas fuel and include radiator cooling, with
engine driven water pump, expansion tank and temperature control modulating
valve.
B. The rated net horsepower of the engine at the generator synchronous speed, with
all accessories, shall not be less than that required to produce 1000 kW.
C. The engine shall be capable of producing the specified kW, without overload, for
the duration of the power outage, at the altitude of 365 feet, with ambient
temperatures up to 122 degrees F.
D. The engine shall be constructed with cast iron cylinder heads and steel backed
bearings. Pistons shall be aluminum alloy with chrome faced rings. The engine
crank case shall be reinforced cast iron. The crank case shaft shall be forged alloy
steel with hardened journals, finished and dynamically balanced.
E. The engine shall be equipped with a solid state electronic governor, isochronous
type to maintain frequency within 1/4 percent of its mean value for constant loads
from no load to full load. The engine shall have a 3 seconds maximum transient
recovery time for one-step load acceptance and an 8 percent maximum transient
frequency dip on one-step application of a 0.8 power factor load at 80 percent of
unit full load rating.
16231E-9 11/2017
2131
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
F. Engine cooling system shall consist of an engine mounted radiator with blower
type fan, sized to maintain safe operation. The cooling system shall be filled with
a 50 percent solution of ethylene glycol and be equipped with the following
accessories:
1. High engine temperature shutdown
2. Loss of coolant shutdown
3. Cooling water temperature gage
4. Fan guard
5. Radiator face duct connection
G. The engine shall be equipped with jacket water heaters. Heaters shall be in
accordance with the following:
1. Thermostatically controlled, of sufficient capacity to keep the jacket water
at a suitable temperature for trouble-free starting at an ambient
temperature up to 122 degrees F.
2. Heater shall be provided with a suitable contactor to automatically
disconnect the heater when the engine is started. Heater shall operate
single phase with a voltage of 120 VAC.
H. Engine lubrication system shall be equipped with the following accessories:
1. Lube oil temperature gage.
2. Lube oil pressure gage.
3. Oil level indicator.
4. Low oil pressure shutdown.
I. Engine accessories and features shall include:
1. Skid mounted radiator and cooling system rated for full load operation in
122 degrees F (50 degrees C) ambient as measured at the generator air
inlet. The cooling system shall be filled with 50/50 ethylene glycol/water
mixture by the equipment supplier. Rotating parts shall be guarded
against accidental contact per OSHA requirements.
2. An electric starter(s) capable of three complete cranking cycles without
overheating.
3. Positive displacement, mechanical, full pressure, lubrication oil pump.
4. Full flow lubrication oil filters with replaceable spin on canister elements
and dipstick oil level indicator.
5. Replaceable dry element air cleaner with restriction indicator.
6. Flexible fuel supply lines and with fuel shutoff solenoid.
16231E-10 11/2017
2132
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
2.04 ALTERNATOR
A. Each generator set shall be provided with an alternator. The alternator shall be
engine-driven, single or two bearing type, synchronous, four pole, 2/3 pitch,
revolving field with brushless excitation and drip-proof, guarded construction,
single prelubricated sealed bearing, air cooled by a direct drive centrifugal blower
fan, and directly connected to the engine with flexible drive disc. The alternator
shall be coupling connected to the engine flywheel housing to ensure permanent
alignment.
B. All insulation system components shall meet NEMA MG1 temperature limits for
Class H insulation system. Actual temperature rise measured by resistance
method at full load shall not exceed 105 degrees Centigrade over 40 degrees C
ambient.
C. The rotor shall be dynamically balanced and include amortisseur windings to
minimize voltage deviations and heating effects under unbalanced load
conditions.
D. The alternator shall be equipped with a static electronic voltage regulator to
maintain voltage within plus or minus 1/2 percent under load, from no load to 100
percent load. The regulator shall also maintain the random voltage variation for
constant loads within plus or minus 1/2 percent under load, from no load to 100
percent load.
E. The alternator shall be equipped with an excitation support system. The system
shall consist of a permanent magnet exciter to provide a dedicated source of
power for the exciter field. The permanent magnet exciter shall isolate the
excitation system and sustain 300 percent short circuit current, under any short
circuit condition, for up to 10 seconds.
F. The Alternator shall be equipped with anti-condensation heaters of sufficient
wattage to maintain the temperature approximately 5 degrees above ambient when
16231E-11 11/2017
2133
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
A. Each generator set shall be provided with an air supply/exhaust system. The air
supply/exhaust system shall consist of a heavy duty air cleaner, silencer and
exhaust piping of suitable size, configuration and material in accordance with
engine manufacturer's recommendations and shall comply with NFPA 37.
B. Silencer: Critical type, constructed of double plate sheet with condensate drain
ports, sized as recommended by engine manufacturer. Measured sound level at a
distance of 10 feet from exhaust discharge, shall be 85 dBA or less. If local codes
are more stringent, they shall apply. Similar to Hapco – complete with flanges.
C. Exhaust piping shall be welded schedule 40 stainless steel with standard bend
radius and stainless steel flexible exhaust fittings. All indoor exhaust piping shall
be insulated to maintain a surface temperature not to exceed 50 degrees C.
D. The engine exhaust stack shall have two, perpendicular sampling ports that meet
USEPA Method 1 criteria.
E. Oxidation Catalyst: The oxidation catalyst shall be a precious metal type catalyst.
The catalyst body shall be fabricated from stainless steel. The catalyst exhaust
inlet and outlet connections shall be Carbon steel with 150# R.F. Flanges. The
Oxidation Catalytic Converter shall be equipped with a flanged access portal for
easy access to the catalyst to facilitate servicing. The catalyst element shall be
mounted and sealed with gasket material into a frame which is inserted into a
16231E-12 11/2017
2134
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
presized slot inside the catalyst housing. The arrangement must prevent exhaust
gas from bypassing the catalyst. The catalyst shall be properly supported to
prevent damage from mechanical vibration and thermal stress. Couplings rated at
3000 lbs shall be supplied in sufficient number to provide ports for monitoring
temperature upstream and downstream of the catalyst along with environmental
testing. Catalyst housing should also be provided with lifting brackets. The
catalytic converter shall be sized to treat the gas engine’s exhaust at rated capacity
to ensure complete compliance with all local, state, and federal environmental
regulations and emission standards.
F. Furnish and install an exhaust silencer. The silencer shall be insulated using a
calcium silicate material covered by a brushed aluminum skin or shall be
uninsulated with a brushed stainless steel skin. The silencer system shall be
designed, furnished, and installed to prevent moisture and condensation from
corroding the silencer. The work shall result in a long-term, aesthetically pleasing
installation.
G. Connect the silencer to the engine exhaust manifold with a high corrosion and
temperature resistant stainless steel flexible convoluted exhaust pipe. Use flange-
type connections. Provide a taper-cut tail pipe complete with rain cap to exhaust
the gases to the atmosphere.
H. All indoor exhaust piping shall be insulated to maintain a surface temperature not
to exceed 50° C. The exhaust piping and expansion fittings, shall be completely
covered with an insulation blanket in order to protect operating personnel and to
reduce noise. Insulation shall be composite fiberglass and stainless steel
construction capable of withstanding 1200° F continuously. The insulation
blankets shall be tailored and custom fabricated to fit the contours of the exhaust
system. Average weight of the insulating blanket shall be 1.5 psf. Insulation
shall conform to MIL-1-16411D, Type II and shall be custom fabricated to fit the
contours of the exhaust system.
1. Insulation shall be Hitco Blanket Armco, Hitco Blanket Insulation system,
or approved equal.
A. The generator set shall be provided with a battery system. The battery system
shall consist of batteries, cables and a battery charger.
B. Batteries shall be heavy duty lead acid type, with number of cells, voltage and
rating in accordance with requirements of the engine manufacturer. The batteries
shall be sized for a minimum of four crank cycles of the specified engine and
have sufficient current available for break-away of the particular engine at worst
case temperature.
16231E-13 11/2017
2135
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
C. Battery cables and connectors shall connect the starting motor and the generator
control panel to the battery supply.
D. Battery charger shall be automatic float type, current limited with 120 volts, 60
Hertz input. The battery charger shall be capable of recharging a discharged
battery in 12 hours while carrying normal loads. The battery charger shall be
equipped with the following additional features and accessories:
1. Equalizing switch and equalizing timer.
2. DC ammeter.
3. DC voltmeter.
4. DC cranking disconnect relay.
5. Low-high DC voltage alarm relay.
6. Current failure relay.
E. The battery system shall be provided with a suitable rack for mounting batteries
and battery charger.
A. Each generator set shall be provided with a unit-mounted control panel. The
control panel shall include the necessary controls, instruments and lights to
manually and automatically start, stop and monitor the generator unit.
B. The control shall be UL 508 listed. The panel control shall be microprocessor
based with programmable adjustments and shall provide monitoring, metering and
control of the system based upon the manufacturer's standard arrangement.
Control power to the panel shall be DC supplied from the starting battery system.
C. The panel controls shall include the following:
16231E-14 11/2017
2136
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
1. Automatic engine starting control from a single pole contact which closes
for engine run and opens for engine stop.
2. Automatic cranking controls to disconnect engine while running.
3. Four (4) 7 seconds minimum, cranking cycles with cranking attempts
separated by appropriate rest periods.
4. Cranking controls shall be locked out, requiring manual reset, if engine
fails to start at the completion of the starting program.
5. Overspeed shutdown.
6. Overcrank shutdown.
7. 30 minute adjustable timer for cool down after transfer to utility power.
8. Three Position Selector Switch: Manual Start-Off-Auto Start, and Start-
stop Pushbuttons.
9. Voltage adjusting rheostat.
10. Auxiliary contacts for controlling generator space heaters.
D. The panel malfunction protection, status and alarm indicators and accessories
shall include the following:
1. Shutdown and alarm annunciation:
a. Engine high water temperature.
b. Engine low oil pressure.
c. Engine overspeed.
d. Engine overcrank.
e. Low coolant level.
2. Alarm annunciation without shutdown:
a. Engine low water temperature.
b. Engine high water temperature pre-alarm.
c. Engine low oil pressure pre-alarm.
d. Battery charger malfunction.
3. Normally open contact, common for all alarm conditions, for remotely
indicating generator malfunction.
4. Generator Run Relay with a minimum of two (2) normally open and two
(2) normally closed contacts for remotely indicating generator run.
5. Wattmeter and power factor meter.
6. Elapsed time meter.
7. Ammeter, voltmeter and phase selector switches.
16231E-15 11/2017
2137
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
8. Frequency meter.
9. Oil pressure and temperature gauges, coolant temperature gauge and
battery voltmeter.
10. Normally open contact for remotely indicating generator selector switch in
Auto Start position.
E. The unit mounted control panel shall be completely pre-wired. All instruments,
controls and indicating lights shall be suitably mounted and properly identified.
All wires and terminals shall be individually identified.
F. The panel controls shall be arranged to accept a stop signal from a remote stop
station. Station shall provide emergency shutdown of the generator set.
G. REMOTE ANNUNCIATOR PANEL
1. The generator set shall be equipped with two (2) remote annunciator
panels. Remote annunciator panel shall be installed as shown on the
Contract Drawing.
2. The remote annunciator panels shall be from the same manufacturer that
supplies the generator set.
3. The remote annunciator panels shall provide visual and audible indication
20 separate alarm or status conditions based on discrete relay inputs or
network inputs.
4. Each remote annunciator panel shall be equipped to display with the
following statuses:
a. Customer Fault 1 (programmable)
b. Customer Fault 2 (programmable)
c. Customer Fault 3 (programmable)
d. Genset Supplying Load
e. Charger AC Failure
f. Low Coolant Level
g. Check Genset
h. Not In Auto
i. Genset Running
j. High Battery Voltage
k. Low Battery Voltage
l. Weak Battery
16231E-16 11/2017
2138
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
m. Fail to Start
n. Low Coolant Temp
o. Pre-High Engine Temp
p. High Engine Temp
q. Pre-Low Oil Pressure
r. Low Oil Pressure
s. Overspeed
t. Custom Relay 1
u. Custom Relay 2
v. Custom Relay 3
w. Custom Relay 4
5. The remote annunciator panel shall be provided with a sealed membrane
panel design and with an enclosure for wall surface mounting.
H. GENERATOR REMOTE SHUTDOWN BREAK GLASS STATION
1. Provide quantity three (3) Emergency Generator Stop break glass stations
Pilla Model ST120SN3R or approved equal.
2. Break glass station shall be painted red and labeled “EMERGENCY
GENERATOR STOP”.
3. Each break glass switch shall be equipped with a minimum of one contact
block with one normally open switch with contacts rated for 10A at 600V
AC.
4. Provide one spare glass disc for each break glass station provided.
5. Each break glass switch shall be equipped with a normally open switch
with contacts rated for 10A at 600V AC.
6. Break glass switch shall be provided with an NEMA 3R enclosure.
A. The generator set shall be provided with unit mounted main circuit breaker and
exciter circuit breaker, sized for protecting the unit.
B. Circuit breakers shall be in accordance with the requirements of General
Specification 16442 - Electric Control Equipment - Low Voltage A.C. Motors and
Devices.
16231E-17 11/2017
2139
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
2.10 PAINTING
A. All ferrous metal surfaces to be cleaned and painted with a rust inhibiting primer.
All exterior surfaces shall be given three coats of manufacturer's standard finish
paint. Finish paint shall be suitable for the operating temperature.
B. Finish paint shall be manufacturer's standard color.
C. Generator enclosure shall be primed with two coats of zinc-chromate. The
enclosure exterior shall be finished painted with three coats of enamel. Color of
finish paint to be selected by the City from manufacturer's standard color chart.
2.11 ENCLOSURE
16231E-18 11/2017
2140
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
16231E-19 11/2017
2141
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
4. The test may include the manufacturer's standard test procedure, but, at a
minimum, shall include the following:
a. Verify generator set assembly, prior to operation, including all
mechanical and electrical connections.
b. Verify fuel and lubrication systems are clean and filled with proper
grades of fuel and lubricants.
c. Make adjustments as required to governor and voltage regulator
controls.
d. Inspect operation of all gauges, switches and meters. Verify
generator set monitoring meters against calibrated load bank
meters.
e. Verify operation of all safeties and alarms.
f. Maintain records of unit operation, at 15 minute intervals, for
duration of test. Records at a minimum shall include, water
temperature, oil pressure, ambient air temperature, voltage, current,
frequency, kilowatts and power factor.
B. Witnessed Shop Tests:
1. The Contractor shall perform witnessed shop tests.
2. Generators shall be witness tested in accordance with the procedures
specified under paragraph 2.12. Generators shall be given a complete test
two weeks before and then retested in the presence of the witness. The
Contractor shall include in his bid the cost of satisfactory and suitable
means for air travel, transportation, incidentals, meals and lodging for both
the Engineer and the City’s representatives to attend witness testing at the
factory.
3. The Contractor shall provide all labor, materials, equipment and
incidentals as shown, specified and required to perform shop testing,
before shipment, at the manufacturer’s facility to verify that the generators
are functioning properly and that they meet the functional and
performance requirements of the Contract Documents.
4. The Contractor shall submit shop testing procedures to verify testing
meets the requirements specified herein. Submittal shall be made at least
two months in advance of any scheduled testing and shall include dates of
scheduled tests.
5. The Contractor shall notify the Engineer in writing at least four weeks
before expected initiation of tests. The City and Engineer may elect to be
present at manufacturer’s facilities during pre-witness test. Presence of the
City and Engineer during this test shall not imply acceptance of the
equipment.
16231E-20 11/2017
2142
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
PART 3 EXECUTION
3.01 INSTALLATION
16231E-21 11/2017
2143
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
A. After installation, generator sets shall be field tested for operation and
conformance. The Contractor shall perform field tests as specified in this Article.
The field tests shall be witnessed by the Engineer and certified by the Contractor.
B. Generator set testing shall be performed by the manufacturer's representative,
prior to energizing equipment. Equipment shall not be energized without the
permission of the Engineer. The testing shall be in accordance with the
recommendations of the manufacturer's representative and, at a minimum, shall
ensure the following:
1. That the entire installation has been made in accordance with the approved
manufacturer's drawings, and that the unit and all auxiliaries are ready for
operation.
2. That fuel and lubrication systems are complete, clean and filled with the
proper grades of fuel and lubricants.
3. That the units and all subsystems start, operate, and shutdown in
accordance with manufacturer's recommendations.
4. That all safeties, alarms and shut-downs function at the correct set point
and sequence.
5. That the unit accepts load, governs speed and regulates voltage.
A. The Contractor shall provide acceptance testing of the generator sets. All
acceptance testing shall be performed by the testing firm, after the completion of
the field tests specified under Article 3.02. The acceptance testing shall be
witnessed by the Engineer and certified by the Contractor.
B. Acceptance testing shall be performed on each generator set. Each set shall be
tested for a period of four hours, using portable resistance type load banks or plant
loads or combination of the two. Testing shall include the following:
1. Perform functionally tests to verify generator set shutdown features
operate as required.
2. Perform vibration base line test.
3. Unit shall be operated for a simulated power failure test. Tests shall be
initiated by simulating a failure of the normal supply. Tests shall end by
returning normal supply.
16231E-23 11/2017
2145
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
4. Apply the actual plant loads available plus load banks necessary to total
full load. Unit shall be load tested, 30 minutes at 25 percent load, 30
minutes at 50 percent load and three hours at 100 percent load.
5. Records shall be maintained, at 30 minute intervals, for duration of test.
Records at a minimum shall include fuel consumption, water temperature,
oil pressure, ambient air temperature, voltage, current, frequency,
kilowatts and power factor.
6. That the unit is EPA emissions compliant as operated with oxidation
catalyst installed.
C. Acceptance electrical testing shall be performed on each alternator. Testing shall
include the following:
1. Insulation-resistance tests shall be performed on each alternator winding
with respect to ground. Determine polarization index.
D. All tests and values shall be in accordance with the manufacturer's
recommendations and NETA, ATS Acceptance Testing Specification.
E. The Contractor shall provide an acceptance testing report. The report shall be in
accordance with NETA, ATS Acceptance Testing Specification.
3.06 TRAINING
A. The Contractor shall provide a training session for up to five (5) owner’s
representatives for one (1) normal workday at jobsite location determined by the
Owner.
B. The training session shall be conducted by a manufacturer’s qualified
representative. The training program shall consist of the instruction on the
operation of the assembly, circuit breakers and major components within the
assembly.
3.07 WARRANTY
16231E-24 11/2017
2146
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
END OF SECTION
16231E-25 11/2017
2147
DETAILED SPECIFICATION 16231 – STANDBY POWER
CONTRACT DEL-260E
16231E-26 11/2017
2148
DETAILED SPECIFICATION 16271E- DRY TYPE TRANSFORMERS
CONTRACT DEL-260E
SECTION 16271E
Dry Type Transformers
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16271 – Dry Type Transformers except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.01 MANUFACTURER
B. Transformer KVA capacity and primary voltage shall be as shown on the Contract
Drawings. Transformers shall be rated 60 KV BIL for 15 KV connected primaries.
Transformer secondaries shall be rated 10 KV BIL.
16271E-1 11/2017
2149
DETAILED SPECIFICATION 16271E- DRY TYPE TRANSFORMERS
CONTRACT DEL-260E
1. Epoxy resin shall be rated 185 degrees C used throughout the construction.
Winding temperature rise shall not exceed 80 degrees C above 40 degrees C
ambient.
2. Cores shall be silicon steel construction assembled and rigidly clasped to ensure
mechanical strength and to reduce vibration. Core shall be grounded to the frame
with a flexible grounding strap.
3. Windings shall be copper and have high dielectric and mechanical strength
insulation. Coils shall be sized, insulated and supported for short circuit forces
and be impervious to moisture. The windings shall withstand impulse, induced
and dielectric test voltage and short circuit testing without damage.
4. The high voltage primary windings shall be disc wound for enhanced voltage
stress distribution and to facilitate complete epoxy penetration. The high voltage
primary windows shall be completely impregnated and cast in epoxy resin under
vacuum in molds and be over cured.
5. The low voltage secondary winding shall be resin encapsulated by winding epoxy
impregnated insulation. All exposed surfaces shall be covered and sealed with
epoxy. The entire winding shall be oven cured.
D. Transformers shall be equipped with six 2 ½ percent fully rated taps. Taps shall
include two 2 ½ percent primary taps above normal and four 2 ½ percent primary taps
below normal. Easily accessible bolted tap links in the high-voltage windings shall be
changed when the transformer is de-energized.
E. Transformer enclosure shall be grounded heavy gauge sheet steel. The transformer
enclosure shall include ventilation louvers, removable panels for access to taps, and
vibration isolating pads. Each enclosure shall be equipped with a diagrammatic
nameplate.
F. Transformer shall be equipped with provisions for future forced air cooling
equipment. Transformer components shall be suitable for the forced air rating
H. The transformer enclosure shall have high voltage signs in accordance with the
requirements of General Specification 16076 - Labeling and Identification.
16271E-2 11/2017
2150
DETAILED SPECIFICATION 16271E- DRY TYPE TRANSFORMERS
CONTRACT DEL-260E
I. Manufacturers
1. Cast coil transformers shall be manufactured by Square D, Palatine, IL, ABB,
Cary, NC or approved equal.
A. The following standard factory tests shall be performed on all equipment provided
under this section. All tests shall be in accordance with the latest version of ANSI and
NEMA standards.
1. Resistance measurements of all windings on the rated voltage connection of each
unit and at the tap extremes of one unit only of a given rating on this project
2. Ratio tests on the rated voltage connection and on all tap connections
3. Polarity and phase-relation tests on the rated voltage connections
4. No-load loss at rated voltage on the rated voltage connection
5. Exciting current at rated voltage on the rated voltage connection
6. Impedance and load loss at rated current on the rated voltage connection of each
unit and on the tap extremes of one unit only of a given rating on this project
7. Applied potential test
8. Induced potential tests
9. For dry-type and cast-coil units, the manufacturer shall perform additional 100%
quality control impulse test on the primary windings of each unit
B. The manufacturer shall provide three (3) certified copies of factory test reports.
1. One (1) 1500kVA Delta Wye Pad Mounted Cast Coil Transformer 13.8kV
Primary, 480Y/277V Secondary;
a. This shall also include all the necessary accessories, components and lugs
provided with the transformer that is to be installed to provide a complete
working system.
END OF SECTION
16271E-3 11/2017
2151
DETAILED SPECIFICATION 16271E- DRY TYPE TRANSFORMERS
CONTRACT DEL-260E
16271E-4 11/2017
2152
DETAILED SPECIFICATION 16281E – POWER FILTERS AND CONDITIONERS
CONTRACT DEL-260E
SECTION 16281E
Power Filters and Conditioners
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16281 – Power Filters and Conditioners except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.04 REFERENCES
1.05 SUBMITTALS
PART 2 PRODUCTS
2.01 MANUFACTURERS
16281E-1 11/2017
2153
DETAILED SPECIFICATION 16281E – POWER FILTERS AND CONDITIONERS
CONTRACT DEL-260E
Replace “suppressor”, “suppression device” and “suppressor device” with “protective device”
for all instances in this Article.
3. The maximum UL 1449 voltage protection rating for the protective device shall
be rated for Type 1 locations shall not exceed the following:
a. For 208Y/120 volt systems, 700 volts line-neutral, 700V line-ground and
700V neutral-ground. 1200 volts line-line.
b. For 480Y/277 volt systems, 1200 volts line-neutral, 1200V line-ground and
1200V neutral-ground. 2000 volts line-line.
6. The minimum total surge current that the suppression device shall be capable of
withstanding shall be as follows:
a. For service entrance equipment, category C (Type 1) locations, 320 KA per
phase, 160 KA per mode.
b. For distribution panelboards, category B (Type 2) locations, 160 KA per
phase, 80 KA per mode.
c. For branch panelboards, category A (Type 3) locations, 80 KA per phase, 40
KA per mode.
B. The Contractor shall provide power filter start-up services and training.
END OF SECTION
16281E-2 11/2017
2154
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
SECTION 16285
Surge Protective Devices (SPD)
NOTE: This Detailed Specification 16285 – Surge Protective Devices (SPD) has been
prepared specifically for the Work of this Contract. There is no corresponding
General Specifications 16285 – Surge Protective Devices (SPD).
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes: The Work specified in this Section consists of materials for furnishing,
installing, connecting, energizing, testing, cleaning and protecting enclosed surge
protective devices (SPD).
B. Related Sections:
1. The following Sections are related to the Work described in this Section. This list of
Related Sections is provided for convenience only and is not intended to excuse or
otherwise diminish the duty of the Contractor to see that the completed Work
complies accurately with the Contract Documents.
1.02 REFERENCES
16285-1 11/2017
2155
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.04 SUBMITTALS
A. Submit to the Engineer for approval in accordance with Detailed Specification 01330 –
Submittal Procedures, Shop Drawings, factory test reports, product data, certified letters
of compliance and information required to establish compliance with this section.
B. Testing Agency/Quality Verification: Provide with all product data evidence of testing
agency/quality verification, listing, and labeling either by printed mark on the data or by a
separate listing card. Provide from product manufacturers a written statement indicating
why an item does not have a quality assurance verification. Such statements are subject to
the approval of the Owner and the Engineer.
C. Product Data and Catalog Cuts: Provide product data within 60 days of Contract award
for all products provided.
D. Shop Drawings: Submit Shop Drawings for all Surge Protective Devices.
F. Project Record Documents: Record actual installed elevation and locations of equipment
and wiring on record Contract and Shop Drawings as specified in Detailed Specification
16010E- General Electrical Requirements.
G. Include Record Drawings, Shop Drawings and product data with Operation and
Maintenance Manuals and submit at project closeout in accordance with Detailed
Specification 01831 – Operation and Maintenance Manuals.
A. Conform all quality control work to Detailed Specification 01432 – Contractor’s Work
Quality.
B. Provide products that are listed and labeled by Underwriters Laboratory, approved by
Factory Mutual or certified as meeting the standards of United Laboratories by the
16285-2 11/2017
2156
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
Electrical Testing Laboratory for the location installed in and the application intended
unless products meeting the requirements of these testing laboratories are not available or
unless standards do not exist for the products.
C. Unless products meeting the requirements of nationally recognized testing laboratories are
not readily available for a category of products, provide products that are:
1. Listed and labeled by Underwriters Laboratory.
2. Approved by Factory Mutual.
3. Certified as meeting the standards of Underwriters Laboratory by the Electrical
Testing Laboratory.
D. Conform all Work to regulatory requirements of all state, local, and national governing
codes and requirements, NFPA 70, National Electrical Code, and the requirements of
Detailed Specification 16010E – General Electrical Requirements.
A. Protect items from damage during delivery, storage and handling in accordance with
Detailed Specification 01651 – Transportation and Handling of Materials and as detailed
below.
1.07 WARRANTY
A. SPD shall have a ten-year warranty. Warranty shall be the responsibility of the electrical
distribution equipment manufacturer and shall be supported by their respective field
service division.
PART 2 PRODUCTS
A. General Requirements:
1. Provide only products satisfying the applicable requirements for testing and reporting
as established herein. Devices proposed for use on this project shall be tested in
accordance with ANSI/UL 1449 Third Edition, as prescribed by ANSI/IEEE C62.45.
The residual or "clamping" voltages shall be recorded for all applicable mode of
operation and for each of the test standard waveforms referenced. The results of
16285-3 11/2017
2157
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
these tests shall be submitted to the Engineer with the product data sheets as outlined
under in this Section.
2. Products furnished for use on this project are to incorporate protective elements in all
applicable modes, unless specifically indicated otherwise.
3. Install SPD equipment where so indicated on the Contract Drawings. Voltage class
and type of unit to be compatible with distribution voltage being protected.
16285-4 11/2017
2158
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
AND/OR
240/120 700V 700V 700V 1200V
16285-5 11/2017
2159
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
3. SPD shall be installed by and shipped directly from the manufacturer of the electrical
distribution equipment.
4. SPD shall be modular in design. Each protection element shall be a user replaceable
surge current diversion module (MOV based). Each surge current diversion module
shall be fused with 200 kAIC rated fuses. Each surge current diversion module shall
include solid state status indicator lights.
5. SPD shall provide redundant surge current diversion modules for each mode of
Protection. Modes of Protection shall be L-N, L-G, N-G in WYE systems, and L-L,
L-G in DELTA systems.
6. SPD shall incorporate copper bus bars for the surge current path. Small gauge round
wiring or plug-in connections shall not be used in the path for surge current
diversion. Surge current diversion modules shall use bolted connections to the bus
bars for reliable low impedance connections.
7. Nominal Discharge Current (In) –SPD applied to the distribution system shall have a
20kA In rating.
8. 120 kA SPDs shall be tested and demonstrate suitability for application within
ANSI/IEEE C62.41 Category B (Type 2) environments. Select this for 120kA per
phase device
9. 250 kA SPDs shall be tested and demonstrate suitability for application within
ANSI/IEEE C62.41 Category C (Type 1) environments.
10. SPD shall meet or exceed the following criteria:
a. Minimum surge current rating per mode shall be:
L-N 120 kA
L-G 120 kA
N-G 120 kA
Per phase 250 Ka
1) UL 1449 Third Edition component recognized voltage protection ratings
shall not exceed the following:
VOLTAGE L-N L-G N-G L-L
480 DELTA XXX 1800V XXX 1800V
AND/OR
480Y/277 1200V 1200V 1200V 2000V
AND/OR
208Y/120 700V 700V 700V 1200V
AND/OR
240/120 700V 700V 700V 1200V
16285-6 11/2017
2160
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
audible alarm. This alarm shall activate upon a fault condition. An alarm on/off
switch shall be provided to silence the alarm. An alarm push to test switch shall be
provided. The SPD diagnostic monitoring devices shall be mounted on the front of
the Distribution/Switchboard, Motor Control Center, and Panelboard enclosure. The
diagnostic monitoring circuits shall continually monitor the operational status of the
surge current diversion modules. No other test equipment shall be required for SPD
monitoring or testing before or after installation.
13. SPD shall have a response time no greater than 1 nanosecond for any of the
individual Protection modes.
14. SPD shall be mounted external to the distribution equipment and connected to the
power bus through a dedicated circuit breaker or disconnect.
15. SPD shall be mounted in a NEMA enclosure rated to match the rooms NEMA
designation.
16. SPD shall include Form C dry contacts to monitor the performance of each phase and
provide a summary alarm.
17. SPD shall include an event surge counter. The counter shall be equipped with a
manual reset and a battery or flash memory to retain memory upon loss of AC
power. The surge counter display and reset switch shall be mounted on the front of
the Distribution/Switchboard, Motor Control Center, and Panelboard enclosure.
18. Acceptable Manufacturers:
a. Eaton Electric, Cleveland, OH
b. Square D Company, Palatine, IL
c. General Electric, Fairfield, CT
d. Siemens, Washington, D.C.
e. Advanced Protection Technologies Inc., Clearwater, FL.
f. LEA International, Hayden, Idaho
g. Or approved equal.
.
16285-7 11/2017
2161
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
diversion. Surge current diversion modules shall use bolted connections to the bus
bars for reliable low impedance connections.
5. Nominal Discharge Current (In) –SPD applied to the distribution system shall have a
20kA In rating.
6. SPDs shall be tested and demonstrate suitability for application within ANSI/IEEE
C62.41 Category C (Type 1) environments.
7. SPD shall meet or exceed the following criteria:
a. Minimum surge current rating per mode shall be:
L-N 120 kA
L-G 120 kA
N-G 120 kA
Per phase 250 kA
b. ANSI/UL 1449 Third Edition component recognized voltage protection ratings
shall not exceed the following:
VOLTAGE L-N L-G N-G L-L
480 DELTA XXX 1800V XXX 1800V
AND/OR
480Y/277 1200V 1200V 1200V 2000V
AND/OR
208Y/120 700V 700V 700V 1200V
AND/OR
240/120 700V 700V 700V 1200V
16285-8 11/2017
2162
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
The surge counter display and reset switch shall be mounted on the front cover of the
enclosure.
14. Acceptable Manufacturers:
a. Eaton Electric, Cleveland, OH
b. Square D Company, Palatine, IL.
c. General Electric, Fairfield, CT.
d. Siemens, Washington, D.C.
e. Advanced Protection Technologies Inc Clearwater, FL.
f. LEA International, Hayden, Idaho
g. Or approved equal.
16285-9 11/2017
2163
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
2. Unit shall be two-piece, consisting of a base and plug. The base shall be DIN rail-
mountable.
3. Technical specifications:
a. Nominal operating voltage 24 VDC
b. Maximum continuous operating voltage 26.4 VDC
c. Nominal current 2A
d. Nominal discharge current (8/20) 10 kA
e. Peak clamping voltage (tested at 1 kV
per microsecond rate of rise)
Normal Mode < 40 VAC
Common Mode < 650 V
f. Resistance per line neglible
4. Acceptable Manufacturers:
a. Phoenix Contact, Middletown, PA catalog number PT 4-24DC-ST plug and PT
4+F-BE base element.
b. LEA International DRDC, Hayden, Idaho
c. Or approved equal.
A. Direct Wire Protective Unit: Provide in-line (series) connected for module rated for a
nominal operating voltage of 25 volts and a maximum operating current of 160 milliamps.
Units shall be wired for terminal connect of line and load side wiring.
B. Acceptable Manufacturers:
1. Telephone Protective Unit:
a. MCG Electronics Inc., Deer Park, NY, DLP Series
b. LEA, Hayden, Idaho, TE-PS Series
c. Or approved equal
2. Data-Line Protective Unit:
a. MCG Electronics Inc., Deer Park, NY, DLP Series
b. LEA, Hayden, Idaho, TE-DB25 Series
c. Or approved equal.
A. Direct Wire Protective Unit: Provide in-line (series) connected module for branch circuit
equipment Protection rated for 120 VAC 20 amp (min), 60 hertz. Units shall be wired for
terminal connect of line and load side wiring.
1. Acceptable Manufacturers:
a. Leviton, Melville, NY, No. 51020-WM.
b. MCG Electronics Inc., Deer Park, NY
c. LEA, Hayden, Idaho
d. Or approved equal
16285-10 11/2017
2164
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
B. Plug-in Protective Unit: 6 outlet plug-in strip type protective unit rated 120 VAC, 15
amperes, sine wave tracking.
1. Acceptable Manufacturers:
a. Leviton, Melville, NY, No. 5200PS.
b. MCG Electronics Inc., Deer Park, NY
c. LEA, Hayden, Idaho, DPS series
d. Or approved equal
2.05 MATERIALS
PART 3 EXECUTION
3.01 PREPARATION
A. Painted surfaces, which will be covered by items of this Section, shall have a prime and
finish coat of paint per General Specification 09900 - Painting.
B. Ensure that all indoor areas are enclosed from the weather.
3.02 INSTALLATION
A. Space enclosures out from surfaces mounted on 1/4-inch spacers or u-channel supports.
Provide supports as specified in Detailed Specification 16071E – Supporting Devices.
B. Install all Surge Protective Devices in accordance with the manufacturer’s instructions.
C. Ground all Surge Protective Devices in accordance with Detailed Specification 16061E -
Grounding, and the manufacturer’s instructions using wire as specified in Detailed
Specification 16121E – Electric Wires and Cables, of size No. 6 AWG or larger if
otherwise indicated, recommended, or specified.
D. Connect all Surge Protective Devices in accordance with Detailed Specification 16121E –
Electric Wires and Cables and the manufacturer’s instructions. For service, Surge
Protective Devices use No. 4 AWG or larger if otherwise indicated or recommended. For
16285-11 11/2017
2165
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
branch circuit Surge Protective Devices use No. 6 AWG or larger if otherwise indicated
on the Contract Drawings, recommended, or specified. For instrument, communication,
and data and telephone unit protectors use wire sized the same as the circuit, data-line that
the Surge Protective Devices is connected to or larger if otherwise indicated,
recommended, or specified.
F. Set enclosure top 6-feet 6-inches above finished floor or grade unless otherwise indicated
or specified. If other equipment is installed in an area, the top of the units may be set
lower then 6-feet 6-inches but in no case set the bottom of the enclosure lower than 12-
inches above the finish floor or grade.
H. In all areas except dry areas install conduit drain-fitting in punched hole in bottom of
enclosure, conduit breather fitting in top of enclosure.
A. Site Testing:
1. Visually and mechanically inspect the SPD unit and connections.
2. Use an AC voltmeter to check all voltages and ensure that normal operating voltages
of the power system match the voltage rating on the SPD nameplate.
3. Check LED status indicators on the display panels and suppression modules to
confirm normal status.
4. Press the alarm test button to confirm the audible alarm and LED.
5. Operate the alarm silence switch to confirm proper operation.
3.04 PROTECTION
A. During painting mask all nameplates, all plastic parts, pushbuttons, operating shafts and
all items not to be painted.
16285-12 11/2017
2166
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
B. Protect all items during Work of other trades including welding and cutting.
C. Protect Surge Protective Devices against short circuits and improper operation.
END OF SECTION
16285-13 11/2017
2167
DETAILED SPECIFICATION 16285 – SURGE PROTECTIVE DEVICES (SPD)
CONTRACT DEL-260E
16285-14 11/2017
2168
DETAILED SPECIFICATION 16292E – POWER DISTRIBUTION SYSTEM
CONTRACT DEL-260E
SECTION 16292E
Power Distribution System
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16292 – Power Distribution System Coordination except as modified
herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
2. The Contractor shall retain the services of an independent testing firm who shall
perform field testing of the power distribution system. The testing firm shall
have experience in the inspection and testing of the system equipment, shall be a
member company of NETA, and shall provide proof of the certification, or
demonstrate that the standards and experience required for certification are
possessed.
PART 2 PRODUCTS
E. Provide an arc flash hazard study for the electrical distribution system shown on the
one line drawings. The intent of the arc flash hazard study is to determine hazards
that exist at each major piece of electrical equipment shown on the one line drawing.
This includes new and existing 480V & 120/208V equipment such as switchgear,
switchboards, panelboards, motor control centers, PDUs, UPS, ATSs, transformers,
control panels & safety disconnect switches. The study will include creation of arc
flash hazard warning labels. These labels serve as a guide to assist technicians and
others in the selection of proper Personal Protective Equipment when working around
exposed and energized conductors. The Electrical Contractor will install the labels.
16292E-1 11/2017
2169
DETAILED SPECIFICATION 16292E – POWER DISTRIBUTION SYSTEM
CONTRACT DEL-260E
1. The arc flash hazard study shall include the electrical distribution system
equipment shown on the one line drawing. If an existing up-to-date current short-
circuit and protective device coordination study is not available, perform a short
circuit and protective device coordination study for the electrical distribution
system before performing the arc flash hazard study. The arc flash hazard study
shall consider operation during normal conditions alternate operations,
emergency power conditions, and any other operations, which could result in
maximum arc flash hazard.
2. Qualifications
The Contractor shall have the study prepared by qualified engineers of an independent
consultant. The consultant shall be a Registered Professional
a. Electrical Engineer (licensed in the state where the project is completed)
who has at least five (5) years of experience and specializes in performing
power system studies.
b. The arc flash hazard study shall be performed using computer software
package such as DesignBase 5.0 or approved equal.
3. Submittals
a. The Contractor shall submit the arc flash hazard study and arc flash warning
labels at least 45 days prior to energizing the electrical equipment. The arc
16292E-2 11/2017
2170
DETAILED SPECIFICATION 16292E – POWER DISTRIBUTION SYSTEM
CONTRACT DEL-260E
flash hazard study and arc flash warning labels shall be approved by the
Engineer on record prior energizing the equipment.
b. Submit three (3) copies of the power systems study and (1) set of warning
labels. Submit one (1) copy of study saved in the native electronic format of
the software used to prepare study.
B. The results of the arc flash study shall be summarized in a final typewritten report.
The report shall include the following:
2. The study shall be in accordance with applicable NFPA 70E, OSHA 29-CFR,
Part 1910 Sub part S and IEEE 1584 Standards.
4. Produce an Arc Flash Warning label listing items 3.a through 3.g above. Also
include the bus name and voltage. Labels shall be printed in color and be printed
on adhesive backed Avery labels. See example above.
5. Produce Bus Detail sheets that lists the items 3.a through 3.g from above and the
following additional items:
a. Bus Name
b. Upstream Protective Device Name, Type and Settings
c. Bus Line to Line Voltage
6. Produce Arc Flash Evaluation Summary Sheet listing the following additional
items:
a. Bus Name
b. Upstream Protective Device Name, Type and Settings
c. Bus Line to Line Voltage
16292E-3 11/2017
2171
DETAILED SPECIFICATION 16292E – POWER DISTRIBUTION SYSTEM
CONTRACT DEL-260E
7. Analyze the short circuit, protective device coordination, and arc flash
calculations and highlight any equipment that is determined to be underrated or
causes an abnormally high incident energy calculation. Propose approaches to
reduce the energy levels. Proposed major corrective modifications will be taken
under advisement by the Engineer, and the Contractor will be given further
instructions.
8. The results of the power system study shall be summarized in a final report. The
report shall include the following sections.
a. Introduction, executive summary and recommendations, assumptions,
reduced copy of the one line drawing.
b. Arc Flash Evaluations Summary Spreadsheet
c. Bus Detail Sheets
d. Arc Flash Hazard Warning Labels printed in color on adhesive backed
labels.
END OF SECTION
16292E-4 11/2017
2172
DETAILED SPECIFICATION 16361 – MEDIUM VOLTAGE
LOAD INTERRUPTER SWITCHGEAR
CONTRACT DEL-260E
SECTION 16361
Medium Voltage Load Interrupter Switchgear
NOTE: This Detailed Specification 16361 – Medium Voltage Load Interrupter Switchgear
has been prepared specifically for the Work of this Contract. There is no
corresponding General Specifications 16361 – Medium Voltage Load Interrupter
Switchgear.
PART 1 GENERAL
1.01 SCOPE
A. The Contractor shall furnish and install the medium voltage load interrupter
switchgear as specified herein and as shown on the Contract Drawings.
3.5 INSTALLATION..........................................................................................10
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be included
in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 - Measurement and Payment.
1.04 REFERENCES
A. The medium voltage load interrupter switchgear and all components shall be designed,
manufactured and tested in accordance with the latest applicable standards as follows:
1. ANSI/IEEE C37.20.3
2. ANSI/IEEE C37.20.4
3. ANSI C37.22
4. ANSI C37.57, C37.58
5. NEMA SG5
6. EEMAC G8-3.3
16361-2 11/2017
2174
DETAILED SPECIFICATION 16361 – MEDIUM VOLTAGE
LOAD INTERRUPTER SWITCHGEAR
CONTRACT DEL-260E
a. Voltage
b. Continuous current
c. Interrupting ratings
11. Cable terminal sizes
B. Where applicable or required by the Engineer the following additional information shall be
submitted to the Engineer:
1. Final as-built drawings and information for items listed in Paragraph 1.05, and
shall incorporate all changes made during the manufacturing process
2. Wiring diagrams
3. Certified production test reports
4. Installation information including equipment anchorage provisions
5. Seismic certification as specified
1.07 QUALIFICATIONS
B. For the equipment specified herein, the manufacturer shall be ISO 9001 or 9002
certified.
1. The equipment and major components shall be suitable for and certified to meet
all applicable seismic requirements of the International Building Code (IBC) for
zone 4 application. Guidelines for the installation consistent with these
requirements shall be provided by the switchgear manufacturer and be based
upon testing of representative equipment. The test response spectrum shall be
based upon a 5% minimum damping factor, IBC: a peak of 2.45g's (3.2-11 Hz),
and a ZPA of 0.98g's applied at the base of the equipment. The tests shall fully
envelop this response spectrum for all equipment natural frequencies up to at
least 35 Hz.
B. Each switchgear assembly shall be split into shipping groups for handling as
indicated on the Contract Drawings or per the manufacturer's recommendations.
Shipping groups shall be designed to be shipped by truck, rail or ship. Shipping
groups shall be bolted to skids. Accessories shall be packaged and shipped
separately. Each switchgear shipping group shall be equipped with lifting eyes for
handling solely by crane.
16361-4 11/2017
2176
DETAILED SPECIFICATION 16361 – MEDIUM VOLTAGE
LOAD INTERRUPTER SWITCHGEAR
CONTRACT DEL-260E
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Square D, Palatine, IL
B. Eaton / Cutler-Hammer products, Cleveland, OH
C. Or Approved equal
The listing of specific manufacturers above does not imply acceptance of their
products that do not meet the specified ratings, features and functions. Contractor is not
relieved from providing a product that meets these specifications. Products in compliance
with the specification and manufactured by others not named will be considered only if
pre-approved by the Engineer ten (10) days prior to bid date.
2.02 RATINGS
B. The following features shall be supplied on every vertical section containing a three-
pole, two-position open-closed switch:
1. A minimum 8-inch x 16-inch high-impact viewing window that permits full view
of the position of all three switch blades through the closed door. The window
shall not be more than 58-inches above the switch pad level to allow ease of
inspection
3. A hinged grounded metal barrier that is bolted closed in front of every switch to
prevent inadvertent contact with any live part, yet allows for a full-view
inspection of the switch blade position
5. Green OPEN, Red CLOSED switch position indicators with the words "Open"
and "Closed".
6. A hinged cover with rustproof quarter turn nylon latches over the switch operating
mechanism to discourage casual tampering
7. The switch shall be removable from the structure as a complete operational
component
C. Vertical section construction shall be of the universal frame type using die- formed and
bolted parts. All enclosing covers and doors shall be fabricated from steel with
thickness equal to or greater than that specified in ANSI/IEEE C37.20.3. No owner
removable hardware for covers or doors shall be thread- forming type. To facilitate
installation and maintenance of cables and bus in each vertical section, a split removable
top cover and padlockable hinged rear door held closed by bolts shall be provided. A
G90 grade galvanized base shall isolate equipment from contact with the concrete pad
providing protection from rust. Heavy-duty hot dipped galvanized anchor clips shall be
provided to anchor the switchgear to the concrete pad.
D. Each vertical section containing a switch shall have a single, full-length, flanged front
door and shall be equipped with two (2) rotary latch-type padlockable handles. Provision
shall be made for operating the switch and storing the removable handle without
opening the full length door.
3. The speed of opening and closing the switch shall be independent of the operator,
and it shall be impossible to tease the switch into any intermediate position under
normal operation
4. Separate main and break contacts to provide maximum endurance for fault close and
load interrupting duty
16361-6 11/2017
2178
DETAILED SPECIFICATION 16361 – MEDIUM VOLTAGE
LOAD INTERRUPTER SWITCHGEAR
CONTRACT DEL-260E
5. Insulating barriers between each phase and between the outer phases and the
enclosure
6. A maintenance provision for slow closing the switch to check switch blade
engagement and slow opening the switch to check operation of the arc interrupting
contacts.
F. Provide a grounding switch on the load side of the fuses to discharge any capacitive voltage
in the feeder cable prior to gaining access to the fuse compartment. Switch shall be
mechanically interlocked with the main grounding switch of the load interrupter switch.
G. Provide line and load side live line indicators as standard on the mechanism compartment.
The live line indicator assembly shall be mounted in the mechanism compartment and shall
be an easily removable module containing three neon indicators powered from voltage
dividers within the 3 standoff insulators.
2.04 BUS
C. A neutral bus shall be provided only when indicated on the Contract Drawings. It shall
be insulated for 1000 Vac to ground. The current rating of the neutral bus shall be
600 amperes.
A. All bus shall be supported utilizing a high strength and high creep support providing
10.5-inch of creep distance between phases and ground. The molded fins shall be
constructed of high track resistant.
B. All standoff insulators on switches and fuse mountings shall be glass polyester or
cycloaliphatic epoxy Wiring/Terminations
C. One (1) terminal pad per phase shall be provided for attaching contractor-supplied cable
terminal lugs for a maximum of two (2) conductors per phase of the sizes indicated
on the Contract Drawings. Sufficient space shall be allowed for Contractor- supplied
electrical stress relief termination devices.
D. Small wiring, fuse blocks and terminal blocks within the vertical section shall be
furnished as indicated on the Contract Drawings. Each control wire shall be labeled with
wire markers. Terminal blocks shall be provided for owner's connections to other
16361-7 11/2017
2179
DETAILED SPECIFICATION 16361 – MEDIUM VOLTAGE
LOAD INTERRUPTER SWITCHGEAR
CONTRACT DEL-260E
apparatus.
2.06 FUSES
A. Fault protection shall be provided by fuses with continuous ratings as shown in the
C ontract Documents. Any fuse/switch integrated momentary and fault close ratings
specified shall have been verified by test and UL and CSA certified.
2.07 ENCLOSURES
B. Each vertical section shall have a sloped weatherproof roof with labyrinth shaped
joints. Use of gasket or caulking to make roof joints weatherproof shall not be
permitted. All exterior openings shall be covered with screens to prevent the entrance
of small animals and barriered to inhibit the entrance of snow, sand, etc. A minimum
of one (1) 250-watt, 120-volt space heater shall be provided in each vertical section.
Power for the space heater(s) shall be furnished by a control power transformer mounted
in the switchgear. The design of the enclosure shall be non-walk-in type.
C. Enclosure shall be dust resistant. All ventilated openings shall be filtered to inhibit the
ingress of dust. The ventilated covers shall be externally removable to allow safe
maintenance of the filter media without providing access to live parts. All external
doors and covers shall be gasketed.
2.08 NAMEPLATES
A. A nameplate shall be mounted on the front door of each switch vertical section in
accordance with the Contract Drawings.
2.09 FINISH
A. Prior to assembly, all enclosing steel shall be thoroughly cleaned and phosphatized. A
powder coating shall be applied electrostatically, then fused-on by baking in an oven.
The coating shall have a thickness of not less than 1.5 mils. The finish shall have the
following properties: Impact resistance (ASTM D-2794); 60 direct/60 indirect Pencil
hardness (ASTM D-3363); H Flexibility (ASTM D-522) Pass 1/8- inch mandrel bend
test; Salt spray (ASTM B117-85 [20]) 600 hours; Color ANSI 61 gray
PART 3 EXECUTION
A. Standard factory tests shall be performed on the equipment under this section. All tests
shall be in accordance with the latest version of ANSI and NEMA standards.
1. The manufacturer shall notify the owner two (2) weeks prior to the date the
tests are to be performed
2. The Contractor shall include in his bid the cost of satisfactory and suitable means
for air travel, transportation, incidentals, meals and lodging for the Engineer and
the City’s representatives to attend witness testing at the factory.
3. The manufacturer shall provide three (3) certified copies of factory test reports.
B. The Contractor shall provide three (3) copies of the manufacturer's field startup
report.
B. The Contractor shall provide three (3) copies of the manufacturer's representative's
certification.
3.04 TRAINING
A. The Contractor shall provide a two-day training session for up to five (5) Owner's
representatives at a location determined by the Owner.
16361-9 11/2017
2181
DETAILED SPECIFICATION 16361 – MEDIUM VOLTAGE
LOAD INTERRUPTER SWITCHGEAR
CONTRACT DEL-260E
3.05 INSTALLATION
A. The Contractor shall install all equipment per the manufacturer's recommendations and
the Contract Drawings.
B. All necessary hardware to secure the assembly in place shall be provided by the
Contractor.
END OF SECTION
16361-10 11/2017
2182
DETAILED SPECIFICATION 16430E – LOW VOLTAGE SWITCHGEAR
CONTRACT DEL-260E
SECTION 16430E
Low Voltage Switchgear
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16430 – Low Voltage Switchgear except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
2.01 MANUFACTURERS
2.02 SWITCHGEAR
A. The low voltage switchgear shall consist of individually mounted molded case circuit
breakers in fixed mounting construction and auxiliary transition compartments.
2183
DETAILED SPECIFICATION 16430E – LOW VOLTAGE SWITCHGEAR
CONTRACT DEL-260E
5. Where the highest continuous current trip setting for which the actual overcurrent
device is installed in a circuit breaker is rated or can be adjusted is 1200A or
higher provide energy reducing active arc flash mitigation system or energy
reducing maintenance switching with local status indicator.
E. The switchgear shall include low voltage molded case circuit breakers, 3 pole fixed
mounting type and shall include an electronic microprocessor based trip system.
Breaker frame size and sensor rating shall be as indicated on the Contract Drawings.
Switchgear breakers shall be in accordance with the following:
1. Each circuit breaker shall be UL listed for 100 percent continuous ampere rating
when operating within the switchgear compartment
2. Each circuit breaker shall be fully rated. Each Circuit breaker shall have a
minimum short circuit rating of 65KAIC. The breakers shall have a short circuit
interrupting rating greater than the maximum available short circuit current at the
breaker line side terminals.
3. Each circuit breaker shall be fully rated. The breakers shall have a short circuit
interrupting greater than the maximum available short circuit current at the
breaker line side terminals.
4. The electronic trip system shall include a plug-in protection programmer, a flux
shift trip device and current sensor package. The programmer, sensor and flux-
shifting trip device shall be constructed as integral elements of the breaker,
requiring no externally mounted assemblies for proper operation.
5. A neutral current sensor shall be provided for each circuit breaker when used in
the 4 wire circuits shown on the Contract Drawings.
2184
DETAILED SPECIFICATION 16430E – LOW VOLTAGE SWITCHGEAR
CONTRACT DEL-260E
7. Where on the Contract Drawings circuit breaker is rated 1200A or higher provide
arc energy reduction in accordance with the following:
a. Auxiliary contacts for remote indication of circuit breaker’s open and close
status.
b. Indicators for overload, short circuit and ground trip indication.
c. Hand-held programmer for accessing, displaying, configuring and testing
each breaker trip unit.
16430E-3 11/2017
2185
DETAILED SPECIFICATION 16430E – LOW VOLTAGE SWITCHGEAR
CONTRACT DEL-260E
1. The switchgear shall include microprocessor type bus metering. The bus
metering shall consist of three current transformers, ampere ratio as shown on the
Contract Drawings and a microprocessor based meter device. The meter device
shall include self-contained potential transformers and internal fuses, and shall
include the following direct reading metered values:
a. AC amperes, each phase.
b. AC voltage, phase to phase and phase to neutral.
c. Watts, VARS and VA.
d. Watt-hours, VAR-hours and VA-hours.
e. Power factor.
f. Frequency.
g. Percent THD.
h. Watt, VAR, VA and Ampere Demand.
i. Individual Ampere and Voltage Harmonics.
j. Trend Analysis.
k. Event Logging and Recording.
2. The switchgear shall include an electronic interface module. The module shall
permit central monitoring and display of each circuit breaker programmer
parameter. The module shall also communicate information from the protective
and energy monitoring type programmers over a monitoring data network to a
microcomputer. The module shall permit configuration, display and testing
features and shall include the following displayed parameters:
a. Phase and average demand current.
b. Present and peak demand watts.
c. Energy.
d. Trip information.
e. Percent THD.
f. Percent harmonic content.
4. Each low voltage switchgear shall be provided with bus surge protection. The
bus surge protection shall consist of a three phase secondary type arrester and
capacitor suitable for applications at 600 volts and below.
16430E-4 11/2017
2186
DETAILED SPECIFICATION 16430E – LOW VOLTAGE SWITCHGEAR
CONTRACT DEL-260E
G. Protective relays
1. The switchgear manufacturer shall furnish and install in the switchgear the phase
loss relay and capacitor trip device. Phase loss relay shall provide phase
loss/unbalance phase detection, low voltage detection and overvoltage detection
features. Provide voltage and current transformer for protective relay.
Manufacture shall provide adequate quantity, type and ratings of relays and
associated equipment. Protective relays and associated equipment ratings shall be
coordinated with arc-flash and short circuit coordination study.
2. Phase loss relay type PND-LV-O by Taylor Electronic Inc. or approved equal.
3. The Contractor shall notify the owner two (2) weeks prior to the date the tests are
to be performed.
4. The Contractor shall include in his bid the cost of satisfactory and suitable means
for air travel, transportation, incidentals, meals and lodging for the Engineer and
the City’s representatives to attend witness testing at the factory.
PART 3 EXECUTION
END OF SECTION
16430E-5 11/2017
2187
DETAILED SPECIFICATION 16430E – LOW VOLTAGE SWITCHGEAR
CONTRACT DEL-260E
16430E-6 11/2017
2188
DETAILED SPECIFICATION 16441E – PANELBOARDS
CONTRACT DEL-260E
SECTION 16441E
Panelboards
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16441 – Panelboards except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There is shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
B. The panelboards shall be designed, constructed and installed suitable for earthquake
regulations in accordance with the seismic requirements of the City of New York
Building Code and the Uniform Building Code for Zone 2A applications and in
accordance with local and state building codes.
PART 2 PRODUCTS
2.02 PANELBOARDS
8. Where required to meet the interrupting ratings shown on the Contract Drawings,
the main circuit breaker design shall include a current limiting feature for proper
performance of the circuit breaker during short circuit conditions.
END OF SECTION
16441E-1 11/2017
2189
DETAILED SPECIFICATION 16441E – PANELBOARDS
CONTRACT DEL-260E
16441E-2 11/2017
2190
DETAILED SPECIFICATION 16442E – ELECTRICAL CONTROL EQUIPMENT-
LOW VOLTAGE AC MOTORS AND DEVICES
CONTRACT DEL-260E
SECTION 16442
Electrical Control Equipment- Low Voltage AC Motors and Devices
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16442 – Electrical Control Equipment – Low Voltage AC Motors and
Devices except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
1. Circuit breakers shall be the molded case type with number of poles, voltage and
current ratings as shown on the Contract Drawings. Circuit breakers shall have a
minimum short circuit rating of 65KAIC.
H. Pilot devices shall be heavy duty type, rated 10 amp continuous, minimum.
Pushbuttons, selector switches, indicating lights and other devices shall be located on
the starter enclosure. Indicating lights shall be push-to-test, LED transformer type.
Lens color shall be as shown on the Contract Drawings.
D. Pilot devices shall be heavy duty type, rated 10 amp continuous, minimum.
Pushbuttons, selector switches, indicating lights and other devices shall be located on
the starter enclosure. Indicating lights shall be push-to-test, LED transformer type.
Lens color shall be as shown on the Contract Drawings.
16442E-1 11/2017
2191
DETAILED SPECIFICATION 16442E – ELECTRICAL CONTROL EQUIPMENT-
LOW VOLTAGE AC MOTORS AND DEVICES
CONTRACT DEL-260E
2.05 ENCLOSURES
A. Enclosures shall be provided for the electric control equipment. Unless otherwise
indicated on the Contract Drawings, enclosures shall meet the following requirements:
1. For all locations enclosures shall be corrosion resistant, NEMA Type 4X. Except
for chlorine areas, boxes shall be constructed of 316 stainless steel material with
sealed seams. Enclosures in chlorine areas shall be constructed of non-metallic
FRP materials.
2. For enclosures located in the Electrical Service Room and on the Mezzanine
Floor enclosures shall meet NEMA 12 requirements.
END OF SECTION
16442E-2 11/2017
2192
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
SECTION 16482
Motor Control Centers
NOTE: This Detailed Specification 16482 – Motor Control Centers has been prepared
specifically for the Work of this Contract. There is no corresponding General
Specifications 16482 – Motor Control Centers.
PART 1 GENERAL
A. The Contractor shall provide all labor, materials, equipment and incidentals as shown,
specified and required to furnish and install motor control centers complete and
operational.
PART 1 GENERAL
1.01 Section Includes .........................................................................1
1.02 Related Specifications ................................................................2
1.03 Payment………………………………………………………..2
1.04 References ..................................................................................2
1.05 Submittals ..................................................................................2
1.06 Quality Assurance ......................................................................3
1.07 Delivery, Storage and Handling .................................................4
1.08 Spare Parts .................................................................................4
PART 2 PRODUCTS
PART 3 EXECUTION
16482-1 11/2017
2193
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
3.01 Installation.................................................................................12
3.02 Field Tests .................................................................................12
3.03 Manufacturer’s Field Services ..................................................12
3.04 Acceptance Testing ...................................................................13
1.04 REFERENCES
A. The motor control centers shall comply with the latest applicable provisions and
recommendations of the following.
1. Electrical Code of the City of New York.
2. NFPA 70, National Electrical Code.
3. NEMA ICS 2, Industrial Control and Systems.
4. NEMA ICS 2.3, Instruction for Handling, Installation, Operation and
Maintenance.
5. UL No. 845, Standard for Motor Control Centers.
6. NETA, International Electrical Testing Association.
1.05 SUBMITTALS
B. Working Drawings:
1. Prior to equipment submission, submit the proposed manufacturer.
2. Manufacturer’s specifications and other data required to demonstrate
compliance with the specific requirements. Data shall be submitted for each
component to be provided. Data shall include type, ratings, settings and other
technical information.
3. A completed materials list with outline and summary sheets and schedule of
equipment in each unit.
4. Unit control schematics and wiring diagrams showing numbered terminal
points and all interconnections. A separate diagram shall be provided for each
compartment. The diagram shall also include the equipment name, number and
the motor control center designation.
16482-2 11/2017
2194
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
5. Description of shop and field testing methods, procedures and apparatus with
calibration dates shall be submitted. Testing methods and procedures shall be
submitted at least 45 days in advance prior to conformation of witness testing
dates and actual testing.
6. Qualifications of proposed testing firm to perform acceptance testing shall be
submitted. Submit firm experience records at least 45 days in advance to
actual testing, five recent references with phone numbers shall be submitted.
C. Certificate of Compliance:
1. The Contractor shall submit seismic qualification certification from the
manufacturer including mounting recommendations.
2. All data and results of witness tests shall be accompanied by a certificate of
authenticity sworn to before a notary public by an officer of the manufacturing
company. Upon approval, release for shipment to the Site shall proceed.
D. Reports:
1. Shop test and field test reports shall be submitted.
2. Manufacturer’s Site visit and acceptance testing reports shall be submitted.
A. General:
1. Motor control centers shall be designed, built and tested in accordance with
the latest applicable requirements of NEMA, UL, NFPA and the Electrical
Code of the City of New York.
2. The Contractor shall obtain motor nameplate data on the actual equipment
being furnished of all Contracts for properly sizing circuit breakers, starters
and overloads. The settings of all devices shall be based upon the actual
motors furnished.
3. The motor control center manufacturer shall use a shop test facility that has
recently calibrated testing apparatus and qualified, experienced technicians, for
all factory tests. Calibration of testing apparatus shall be within one year.
4. All test equipment and instrument calibration shall be in accordance with the
latest edition of the accuracy standard of the U.S. National Institute of
Standards and Technology and the NETA acceptance testing specification.
5. Shop Tests and Inspection: The Motor Control Centers specified in this
Division and shown on the Contract Drawings shall be witness shop tested and
inspected in accordance with the equipment manufacturer’s standard
procedures. The testing and inspection procedures shall be approved by the
Engineer. At least 45 days’ notice shall be given to the Engineer prior to such
tests and inspection dates. The test(s) shall be witnessed by the Engineer and
one Engineer form the DEP. The NYCDEP Engineer’s travel room and board
16482-3 11/2017
2195
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
C. Field Tests:
1. The motor control centers shall be field tested. Field testing shall be performed
in accordance with the requirements specified under Article 3.02.
2. The services of the motor control center manufacturer shall be retained for
field service. Field service shall be in accordance with the requirements
specified under Article 3.03.
3. Retain the service of an independent testing firm who shall perform field
acceptance testing of the motor control centers. The testing firm shall have
experience in the inspection and testing of the equipment and shall be a
member company of NETA. Acceptance testing shall be in accordance with
the requirements specified under Article 3.04.
Field testing(contractor), field services (contractor), and field acceptance (independent
contractor)
1.07 DELIVERY, STORAGE AND HANDLING
A. The Contractor shall furnish and deliver spare parts for the motor control centers to
the Engineer, at the time and location specified by the Engineer.
B. The spare parts shall be listed in an index and packed in containers suitable for long
term storage, bearing labels clearly designating the manufacturer’s part number with
complete information for use and reordering.
C. Spare parts for each motor control center shall include at a minimum the following:
16482-4 11/2017
2196
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
1. One (1) starter and one (1) circuit breaker or MCP per each of six (6) starters
or circuit breakers or MCP’s of a type/size, but not less than a minimum of
one(1) spare starter or circuit breaker or MCP shall be provided.
2. Twelve (12) fuses shall be provided, for each type and size used.
3. Four (4) control relays and timers shall be provided, for each type and size
used.
4. Four (4) control power transformers shall be provided, for each type and size
used.
5. Twelve (12) indicating lamp assemblies with lamps shall be provided, for each
type and size used.
6. Twelve (12) control station assemblies shall be provided, for each type and
size used.
7. Two (2) interlock system keys shall be provided.
PART 2 PRODUCTS
2.01 MANUFACTURERS
2.02 RATINGS
A. The motor control centers shall be 600 volt class suitable for operation on a three
phase, 60 hertz system. The system operating voltage, number of wires, bus
ampacity and short circuit withstand capability shall be as shown on the Contract
Drawings.
B. The circuit breakers and combination motor circuit protectors, motor starters shall
have a short circuit interrupting rating of 65KAIC.
C. Motor control center wiring shall be rated NEMA Class II, Type B. All motor
starters shall be NEMA rated, NEMA size 1 minimum.
2.03 STRUCTURE
B. The structure shall consist of vertical sections of heavy gauge steel bolted together
forming a rigid unit assembly. Removable lifting angles or tabs shall be mounted on
16482-5 11/2017
2197
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
top of each section. Removable bottom channel sills shall be mounted front and rear
of vertical section and shall extend full width of line-up.
D. Each vertical section shall contain a top and bottom horizontal wireway for
incoming lines and wiring between sections. A vertical wireway shall be adjacent to
each vertical unit and shall be covered by a hinged door. Vertical wireways shall
contain cable tie supports. Each individual device compartment shall have a side
barrier to permit pulling wire from vertical wireway without disturbing adjacent
device compartments.
E. Compartments for mounting units shall be incrementally arranged such that not
more than six NEMA Size 1 starters can be mounted within any vertical structure.
Guide rails shall be provided.
F. Construction for mounting units shall be back to back. Back to back construction
shall permit the mounting of units within the front and rear of a single section.
G. The structure and each compartment within shall have identifying nameplates in
accordance with the requirements of General Specification 16076 - Labeling and
Identification. Each spare and space compartments shall be labeled as such.
A. Each motor control center shall contain a main horizontal and vertical tin-plated
copper bus. Vertical buses feeding unit compartments shall be 800 ampere
minimum, and main horizontal bus shall be 800 ampere. Vertical bussing shall be
securely bolted to the horizontal main bus. All joints shall be front accessible for
ease of maintenance. Two independent front and rear vertical buses shall be
provided within each section arranged for back to back construction. The current
density of the busses shall not exceed 1000A/in2.
B. Main bus shall be isolated from wireways, starters and other areas by insulated
barriers. Bus bars shall be supported on white polyester reinforced insulators.
C. Vertical buses shall be completely isolated and insulated. Small openings in bus
sandwich shall permit unit stabs to plug into vertical bus bars, rather onto them.
Shutter mechanism shall be furnished to completely isolate vertical bus, including
stab area opening, when plug-in device is removed.
D. Neutral buses shall be tin-plated copper and extend the entire length of the
equipment. The neutral bus shall have a capacity equal to one half the capacity of
the main power bus.
16482-6 11/2017
2198
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
E. Each motor control center shall contain a tin-plated copper horizontal ground bus
which extends the full width of the structure. The horizontal ground bus shall be
rated 300 ampere. Pressure type ground lugs shall be mounted on the ground bus in
the incoming line sections.
F. A vertical plug-in ground bus shall be tin-plated copper and linked to the horizontal
ground bus. The vertical plug-in ground bus shall be rated 150 ampere. This tin-
plated copper vertical plug-in ground bus, in combination with the unit ground bus
stab, shall establish unit insert grounding before the plug-in power stabs engage the
power bus, and conversely, as the unit is withdrawn, grounding is maintained until
after the plug-in power stabs are disengaged.
G. A vertical load ground bus shall be tin-plated copper and linked to the horizontal
ground bus. The vertical load ground bus shall be rated 150 ampere. The bus
assembly shall provide a termination point for the load ground cable at the unit. The
fixed connection shall not require removal, when the unit is withdrawn.
A. General:
1. Each unit compartment shall be provided with an individual front door.
Plug-in units shall be supported and guided by a removable support pan, so
that unit rearrangement is easily accomplished.
2. The rearrangement of the unit support pan from one location to the other shall
be accomplished without use of tools. After insertion, each plug-in unit shall
be held in place by at least two multi-turn latches, located on the front of the
unit. At least one latch shall be located at the top of the unit and one at the
bottom, for front accessibility and inspection convenience.
3. Unit compartments shall contain circuit breakers, combination motor starters,
and related control equipment as required and shown on the Contract
Drawings.
4. Full voltage starter units through NEMA Size 5 shall be of the draw-out type.
Draw-out provisions shall include a positive guide rail system and stab
shrouds to absolutely ensure alignment of stabs with the vertical bus. Draw-out
units shall have a stab assembly for connection to the vertical bus. Cables shall
be connected to stabs with maintenance free crimp connectors. No wiring to
these stabs shall extend into the bus compartment.
5. All units shall be isolated from one another, above and below, by unit support
pans or steel barriers which can remain in place when the units are withdrawn.
6. Incoming line compartments shall be isolated from horizontal and vertical
wireways by steel barriers.
7. All spare compartments shall be fully equipped with mounting rails and
accessories and all miscellaneous hardware. Spare starters shall also include
terminal blocks and pilot devices in accordance with starter types shown on
the Contract Drawings.
16482-7 11/2017
2199
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
8. All space compartments shall be fully equipped with mounting rails and
accessories and all miscellaneous hardware required for the future installation
of a breaker or starter.
B. Operating Mechanisms:
1. An operating mechanism shall be mounted on the primary disconnect of each
feeder or starter unit. It shall be mechanically interlocked with the unit
door to prevent access unless the disconnect is in the OFF position. A defeater
shall be provided to bypass this interlock.
2. With the door open, an interlock shall be provided to prevent inadvertent
closing of the disconnect. A second interlock shall be provided to prevent
removal or re-insertion of the unit while in the ON position.
3. Padlocking facilities shall be provided to positively lock the disconnect in the
OFF position with from one to three padlocks with the door open or closed. In
addition, means shall be provided to padlock the unit in a partially withdrawn
position with the stabs free of the vertical bus.
16482-8 11/2017
2200
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
1&2 200
3 300
4&5 500
8. Control power transformers be epoxy encapsulated, core and coil units
designed for machine tool applications. Insulation temperature classes shall be
185 degrees C, 115 degrees C rise. Maximum surface temperature shall be 65
degrees C.
9. Control power transformers shall be provided with one secondary lead
furnished with a Class H control fuse and clip, and the other secondary lead
grounded. Both primary leads shall be provided with Class CC control fuses
and clips.
10. Control relays and pilot devices shall be provided as required for the control
operation, shown on the Contract Drawings.
11. Control relays shall be machine tool type, rated 600 volt with contacts rated 10
ampere continuous, and shall be capable of making 7200VA and breaking
720VA. Contacts shall be bifurcated and convertible, coil voltage shall be 120
volt, 60 Hertz unless otherwise shown Contract Drawings.
12. Relays shall be standard, latching type, pneumatic or solid state time delay
type. Each relay shall be furnished with the number of contacts required and
contain a minimum of two normally open and two normally closed contacts.
16482-9 11/2017
2201
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
13. Pushbuttons, selector switches, indicating lights and other pilot devices shall
be provided with a door mounted control station. The control station shall be
removable for the purpose of mounting and wiring the pilot devices, and shall
be held in place with mounting screws. Contact blocks of the pilot devices
shall be mounted in a recessed control station housing to minimize the hazard
of accidental contact when the unit door is opened.
14. The pilot devices shall be heavy duty, machine-tool service type. Pilot
devices shall be rated 600 volt with contacts rated 10 ampere continuous, and
shall be capable of making 7200VA and breaking 720VA. Pilot lights shall
be LED push-to-test, transformer type.
15. Terminal blocks shall be pull-apart type on plug-in units for easy removal of
the unit from the structure. Terminal blocks on non plug-in units shall be the
fixed type. Terminal blocks shall be mounted on the right side or bottom of the
unit compartment for easy accessibility. Control terminal blocks shall be rated
20 ampere, 600 volt minimum.
16. Power pull-apart blocks shall be 3-pole rated 60 ampere at 600 volts and shall
be supplied through NEMA Size 2 starters. A non-pull-apart block rated 195
amps, 600 volts shall be supplied for NEMA Size 3 starters.
A. The motor control centers shall include a bus metering system. The system shall
permit central monitoring and display of each main bus.
B. The bus metering system shall consist of three current transformers, ampere ratio as
indicated on the Contract Drawings, a pull fuse disconnect and a microprocessor
based meter device.
D. Current transformers shall be window type, designed for 600 volt indoor service.
Transformers shall be metering class, 1 percent accuracy suitable for operating the
meters.
16482-10 11/2017
2202
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
2.07 WIRING
A. Control and power wiring shall be flame-retardant, VW-1 moisture, heat and oil
resistant thermoplastic insulation rated 600 volt, 90 degree C, with stranded copper
conductors, types MTW and THW.
B. Control wires shall be colored red. Power phase wires shall be colored black, with
neutral wires white. Ground wires shall be colored green.
C. Control wire size shall be No.14 AWG minimum. Power wire size shall be No.12
AWG minimum.
E. All wiring shall be labeled in accordance with the wiring numbers shown the wiring
diagrams. Wire numbers shall not repeat.
2.08 PAINTING
A. All metal surfaces of the motor control centers shall be thoroughly cleaned and
given one coat of zinc chromate primer. All interior surfaces shall then be given one
shop finishing coat of a nitro- cellulose lacquer enamel.
B. All exterior surfaces shall be given three coats of the same lacquer. The color of the
finishing coats shall be light gray ANSI No. 61.
16482-11 11/2017
2203
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
d. High potential tests shall be performed on the power and control circuits.
Power circuits shall be tested phase to phase and phase to ground at 2200
volt for one minute or 2700 volt for one second. Control circuits shall be
tested at 1500 volt for one minute or 1800 volt for one second.
2. Each new motor control center shall be witnessed shop tested in accordance
with the procedures specified under paragraph 2.09(A). The Contractor shall
include in his bid the reasonable cost of air travel, transportation, incidentals,
meals and lodging for the Engineer and the City’s representatives to attend
witness testing at the factory.
PART 3 EXECUTION
3.01 INSTALLATION
B. Motor control centers shall be installed so that sufficient access and working space
is provided for ready and safe operation.
C. Motor control centers shall be installed on concrete pads at locations shown on the
Contract Drawings. Steel channels shall be provided for support of equipment,
which shall be securely mounted to surface with anchor bolts. Anchor motor control
centers to satisfy the specified seismic requirements in accordance with the
anchorage details.
D. All circuits within motor control centers shall be wired together and identified with
durable tag secured to cabling twine.
E. All motor control center protection and control devices shall be properly adjusted
such that the circuits operate correctly and safely.
A. After installation, the motor control centers shall be field tested for operation and
conformance. The Contractor shall perform field testing in accordance with
Detailed Specification 01811 – Preliminary and Final Field Tests. The field tests
shall be witnessed by the Engineer and certified by the Contractor.
16482-12 11/2017
2204
DETAILED SPECIFICATION 16482 – MOTOR CONTROL CENTERS
CONTRACT DEL-260E
C. The Contractor shall provide a field report from the manufacturer’s representative
for each visit to the Site. The report shall include complete information on time,
schedule, tasks performed, persons contacted, problems corrected, tests results,
training instruction and all other pertinent information.
D. The service representative shall sign in with the Engineer on each day they are at
the Site.
A. The Contractor shall provide acceptance testing of the motor control centers. All
acceptance testing shall be performed by the testing firm, after the completion of the
field tests specified under Article 3.02. The acceptance testing shall be witnessed by
the Engineer and certified by the Contractor.
E. The Contractor shall provide an acceptance testing report. The report shall be in
accordance with NETA ATS Acceptance Testing Specifications.
END OF SECTION
16482-14 11/2017
2206
DETAILED SPECIFICATION 16491E – FUSES
CONTRACT DEL-260E
SECTION 16491E
Fuses
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16491 – Fuses except as modified herein.
PART 1 GENERAL
1.02 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
1.03 REFERENCES
PART 3 EXECUTION
3.01 INSTALLATION
END OF SECTION
16491E-1 11/2017
2207
DETAILED SPECIFICATION 16491E – FUSES
CONTRACT DEL-260E
16491E-2 11/2017
2208
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
SECTION 16496
Automatic Transfer Switches
NOTE: This Detailed Specification 16496 – Automatic Transfer Switches has been
prepared specifically for the Work of this Contract. There is no corresponding General
Specifications 16496 – Automatic Transfer Switches.
PART 1 GENERAL
A. The Contractor shall provide all labor, materials, equipment and incidentals as
shown, specified and required to furnish and install automatic transfer switches
(ATSs) complete and operational.
B. Furnish and install ATSs with number of poles, amperage and voltage, withstand
and close-on ratings as shown on the Contract Drawings. Each automatic transfer
shall consist of an inherently double-throw power transfer switch mechanism and a
microprocessor controller to provide automatic operation. All transfer switches
and controllers shall be the products of the same manufacturer.
C. The Contractor shall obtain motor nameplate data on the equipment being
furnished of all Contracts for properly sizing circuit breakers, starters and
overloads. The settings of all devices shall be based upon the actual motors
furnished.
1.02 REFERENCES
A. The automatic transfer switches and controls shall conform to the requirements of:
1. UL 1008 - Standard for Transfer Switch Equipment
2. IEC 60947-6-1 Low-voltage Switchgear and Control gear; Multifunction
equipment; Automatic Transfer Switching Equipment
3. NFPA 70 - National Electrical Code
4. NFPA 110 - Emergency and Standby Power Systems
5. IEEE Standard 446 - IEEE Recommended Practice for Emergency and
Standby Power Systems for Commercial and Industrial Applications
6. NEMA Standard ICS10-1993 (formerly ICS2-447) - AC Automatic Transfer
Switches
7. UL 508 Industrial Control Equipment
8. Electrical Code of the City of New York.
16496-1 11/2017
2209
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in
Detailed Specification 01270 – Measurement and Payment.
1.04 SUBMITTALS
A. Submit the following to the Engineer for approval in accordance with Detailed
Specification 01330 - Submittal Procedures: qualifications of proposed
manufacturer and testing agency; Shop Drawings; factory test reports; product
data; certificates of compliance; and all other information required to establish
compliance with this section.
C. Shop Drawings:
1. Manufacturer’s specifications and other data required to demonstrate
compliance with the specific requirements. Data shall be submitted for each
component to be provided. Data shall include type, ratings, settings and other
technical information.
2. A completed materials list with outline and summary sheets and schedule of
equipment in each unit.
3. Unit control schematics and wiring diagrams showing numbered terminal
points and all interconnections. A separate diagram shall be provided for each
compartment. The diagram shall also include the equipment name, number
and the ATS designation.
4. The Contractor shall submit a description of shop and field testing methods,
procedures and apparatus with calibration dates. Testing methods and
procedures shall be submitted at least 45 days in advance prior to
conformation of witness testing dates and actual testing.
D. Certificate of Compliance:
1. Seismic qualification certification from the manufacturer including mounting
recommendations.
2. Data and results of witness tests accompanied by a certificate of authenticity
sworn to before a notary public by an officer of the manufacturing company.
Upon approval, release for shipment to the Site shall proceed.
E. Reports:
1. Shop test and field test reports shall be submitted.
2. Manufacturer’s Site visit and acceptance testing reports shall be submitted.
16496-2 11/2017
2210
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
A. Manufacturer:
1. The ATS manufacturer shall maintain a national service organization of
company-employed personnel located throughout the contiguous United
States. The service center's personnel must be factory trained and must be on
call 24 hours a day, 365 days a year.
2. The ATS manufacturer shall be certified to ISO 9001 International Quality
Standard and the manufacturer shall have third party certification verifying
quality assurance in design/development, production, installation and
servicing in accordance with ISO 9001.
3. The manufacturer shall maintain records of each switch, by serial number, for
a minimum of 20 years.
C. Seismic Requirements:
16496-3 11/2017
2211
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
1. The ATS shall be designed, constructed and installed suitable for earthquake
regulations in accordance with the seismic requirements of the City of New
York Building Code and the Uniform Building Code for zone 2A application.
D. Field Tests:
1. The ATS shall be field tested. Field testing shall be performed in accordance
with the requirements specified under Article 3.03.
2. The services of the ATS manufacturer shall be retained for field service. Field
service shall be in accordance with the requirements specified under Article
3.06.
3. Retain the service of an independent testing firm who shall perform field
acceptance testing of the ATS. The testing firm shall have experience in the
inspection and testing of the equipment and shall be a member company of
NETA. Acceptance testing shall be in accordance with the requirements
specified under Article 3.03.
PART 2 PRODUCTS
A. The transfer switch shall be electrically operated and mechanically held. The
electrical operator shall be a momentarily energized, single-solenoid mechanism.
Main operators which include overcurrent disconnect devices, linear motors or
gears shall not be acceptable. The switch shall be mechanically interlocked to
ensure only two possible positions, normal or emergency.
1. Acceptable Manufacturers:
a. Automatic transfer switches shall be ASCO 7000 Series by ASCO,
Alexandria, VA
b. Or approved equal.
16496-4 11/2017
2212
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
B. All transfer switch sizes shall use only one type of main operator for ease of
maintenance and commonality of parts.
D. All main contacts shall be silver composition. Switches rated 800 amperes and
above shall have segmented, blow-on construction for high withstand and close-on
capability and be protected by separate arcing contacts.
E. Inspection of all contacts shall be possible from the front of the switch without
disassembly of operating linkages and without disconnection of power conductors.
Switches rated 600 amperes and higher shall have front removable and replaceable
contacts. All stationary and moveable contacts shall be replaceable without
removing power conductors and/or bus bars.
B. A single controller shall provide twelve selectable nominal voltages for maximum
application flexibility and minimal spare part requirements. Voltage sensing shall
be true RMS type and shall be accurate to ± 1% of nominal voltage. Frequency
sensing shall be accurate to ± 0.2%. The panel shall be capable of operating over a
temperature range of -20 to +60 degrees C and storage from -55 to +85 degrees C.
16496-5 11/2017
2213
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
2.03 ENCLOSURE
B. All standard and optional door-mounted switches and pilot lights shall be 16-mm
industrial grade type or equivalent for easy viewing & replacement. Door controls
shall be provided on a separate removable plate, which can be supplied loose for
open type units.
B. Power interconnections shall be silver-plated copper bus bar. The only field
installed power connections shall be at the service and load terminals of the
bypass-isolation switch. All control interwiring shall be provided with disconnect
plugs.
C. Separate bypass and isolation handles shall be utilized to provide clear distinction
between the functions. Handles shall be permanently affixed and operable without
opening the enclosure door. Designs requiring insertion of loose operating handles
or opening of the enclosure door to operate are not acceptable.
16496-6 11/2017
2214
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
E. The isolation handle shall provide three operating modes: "Closed," "Test," and
"Open."
1. The "Test" mode shall permit testing of the entire emergency power system,
including the automatic transfer switches with no interruption of power to the
load.
2. The "Open" mode shall completely isolate the automatic transfer switch from
all source and load power conductors. When in the "Open" mode, it shall be
possible to completely withdraw the automatic transfer switch for inspection
or maintenance to conform to code requirements without removal of power
conductors or the use of any tools.
3. When the isolation switch is in the "Test" or "Open" mode, the bypass switch
shall function as a manual transfer switch.
F. Designs requiring operation of key interlocks for bypass isolation or ATSs which
cannot be completely withdrawn when isolated are not acceptable.
A. A four line, 20 character LCD display and keypad shall be an integral part of the
controller for viewing all available data and setting desired operational parameters.
Operational parameters shall also be available for viewing and limited control
through the serial communications input port. The following parameters shall only
be adjustable via DIP switches on the controller:
1. Nominal line voltage and frequency
2. Single or three phase sensing
3. Operating parameter protection
4. Transfer operating mode configuration
a. (Open transition, Closed transition, or Delayed transition)
B. All instructions and controller settings shall be easily accessible, readable and
accomplished without the use of codes, calculations, or instruction manuals.
16496-7 11/2017
2215
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
A. Voltage and frequency on both the normal and emergency sources (as noted
below) shall be continuously monitored, with the following pickup, dropout, and
trip setting capabilities (values shown as % of nominal unless otherwise indicated):
D. The controller shall be capable (when activated by the keypad or through the serial
port) of sensing the phase rotation of both the normal and emergency sources. The
source shall be considered unacceptable if the phase rotation is not the preferred
rotation.
E. Source status screens shall be provided for both normal & emergency to pro-vide
digital readout of voltage on all 3 phases, frequency, and phase rotation.
F. The controller shall include a user selectable algorithm to prevent repeated transfer
cycling to a source on an installation which experiences primary side, single phase
failures on a Grounded Wye – Grounded Wye transformer which regenerates
voltage when unloaded. The algorithm shall also inhibit retransfer to the normal
(utility) source upon detection of a single phasing condition until a dedicated timer
expires, the alternate source fails, or the normal source fails completely and is
restored during this time delay period. The time delays associated with this feature
shall be adjustable by the user through the controller keypad and LCD.
16496-8 11/2017
2216
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
C. Two time delay modes (which are independently adjustable) shall be provided on
re-transfer to normal. One time delay shall be for actual normal power failures and
the other for the test mode function. The time delays shall be adjustable from 0 to
60 minutes. Time delay shall be automatically bypassed if the emergency source
fails and the normal source is acceptable.
D. Time delay shall be provided on shut down of engine generator for cool down,
adjustable from 0 to 60 minutes.
E. A time delay activated output signal shall also be provided to drive an external
relay(s) for selective load disconnect control. The controller shall have the ability
to activate an adjustable 0 to 5 minute time delay in any of the following modes:
1. Prior to transfer only.
2. Prior to and after transfer.
3. Normal to emergency only.
4. Emergency to normal only.
5. Normal to emergency and emergency to normal.
6. All transfer conditions or only when both sources are available.
F. The controller shall also include the following built-in time delays for optional
Closed Transition and Delayed Transition operation:
1. 1 to 5 minute time delay on failure to synchronize normal and emergency
sources prior to closed transition transfer.
2. 0.1 to 9.99 second time delay on an extended parallel condition of both power
sources during closed transition operation.
3. 0 to 5 minute time delay for the load disconnect position for delayed transition
operation.
G. All time delays shall be adjustable in 1 second increments, except the extended
parallel time, which shall be adjustable in .01 second increments.
H. All time delays shall be adjustable by using the LCD display and keypad or with a
remote device connected to the serial communications port.
A. A three position momentary-type test switch shall be provided for the test /
automatic / reset modes. The “test” position will simulate a normal source failure.
The “reset” position shall bypass the time delays on either transfer to emergency or
retransfer to normal.
B. A Single Pole Double Throw (SPDT) contact, rated 5 amps at 30 VDC, shall be
provided for a low-voltage engine start signal. The start signal shall prevent dry
cranking of the engine by requiring the generator set to reach proper output, and
run for the duration of the cool down setting, regardless of whether the normal
source restores before the load is transferred.
16496-9 11/2017
2217
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
C. Auxiliary contacts, rated 10 amps, 250 VAC shall be provided consisting of one
contact, closed when the ATS is connected to the normal source and one contact
closed, when the ATS is connected to the emergency source.
D. LED indicating lights (16 mm industrial grade, type 12) shall be provided
energized by controller outputs. The lights shall provide true source availability of
the normal and emergency sources, as determined by the voltage sensing trip and
reset settings for each source. Green shall indicate when the ATS is connected to
the normal source and red shall indicate when the ATS is connected to the
emergency source.
E. The following features shall be built-in to the controller, and must be capable of
activation through either keypad programming or the serial port as required y the
user:
1. Allow the user to select “commit/no commit to transfer” when determining if
the load should be transferred to the emergency generator if the normal source
restores before the generator is ready to accept the load.
2. An inphase monitor shall be provided in the controller. The monitor shall
control transfer so that motor load inrush currents do not exceed normal
starting currents, and shall not require external control of power sources. The
inphase monitor shall be specifically designed for and be the product of the
ATS manufacturer. The inphase monitor shall be equal to ASCO Feature 27
or approved equal.
3. The controller shall be capable of accepting a normally open contact that will
allow the transfer switch to function in a non-automatic mode using an
external control device.
F. Engine Exerciser - The controller shall provide an internal engine exerciser. The
engine exerciser shall allow the user to program up to seven different exercise
routines. For each routine, the user shall be able to:
1. Enable or disable the routine.
2. Enable or disable transfer of the load during routine.
3. Set the start time:
a. Time of day
b. Day of week
c. Week of month (1st, 2nd, 3rd, 4th, alternate or every)
4. Set the duration of the run.
5. At the end of the specified duration the switch shall transfer the load back to
normal and run the generator for the specified cool down period. A 10-year
life battery that supplies power to the real time clock in the event of a power
loss will maintain all time and date information.
G. The following feature shall be built into the controller, but capable of being
activated through keypad programming or the communications interface port.
Note: The transfer switch will operate in a non-automatic mode with this feature
activated.
16496-10 11/2017
2218
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
1. Terminals shall be provided for a remote contact which opens to signal the
ATS to transfer to emergency and for remote contacts which open to inhibit
transfer to emergency and/or retransfer to normal. Both of these inhibit
signals can be activated through the keypad or serial port.
H. System Status - The controller LCD display shall include a “System Status” screen
which shall be readily accessible from any point in the menu by depressing the
“ESC” key a maximum of two times. This screen shall display a clear description
of the active operating sequence and switch position. For example:
1. Normal Failed
2. Load on Normal
3. TD Normal to Emerg
4. 2min15s
J. Self-Diagnostics - The controller shall contain a diagnostic screen for the purpose
of detecting system errors. This screen shall provide information on the status
input signals to the controller which may be preventing load transfer commands
from being completed.
L. Data Logging – The controller shall have the ability to log data and to maintain the
last 99 events, even in the event of total power loss. The following events shall be
time and date stamped and maintained in a non-volatile memory:
1. Event Logging
a. Data and time and reason for transfer normal to emergency.
b. Data and time and reason for transfer emergency to normal.
c. Data and time and reason for engine start.
d. Data and time engine stopped.
e. Data and time emergency source available.
f. Data and time emergency source not available.
2. Statistical Data
a. Total number of transfers.
b. Total number of transfers due to source failure.
c. Total number of days controller is energized.
d. Total number of hours both normal and emergency sources are available.
16496-11 11/2017
2219
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
PART 3 EXECUTION
3.01 INSTALLATION
A. General:
1. Automatic transfer switches shall be fully assembled with all required devices,
wiring, nameplates, terminal blocks and enclosures.
2. Mount automatic transfer switches rigidly and securely to the building
structure or to supporting devices, which are rigidly and securely supported to
the building structure.
3. Automatic transfer switches shall be fastened with bolts and expansion shields
on concrete or brick, with toggle bolts or hollow masonry units, and with
machine screws or welded studs on steel work.
4. Mount automatic transfer switches with sides parallel or perpendicular to
walls or equipment, and such that the local control station is installed in a neat
and professional manner.
5. Install all automatic transfer switches such that door swing is not hampered.
16496-12 11/2017
2220
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
C. Grounding:
1. All automatic transfer switches shall be grounded in accordance with NEC
requirements.
2. The use of two (2) locknuts and a grounding bushing will be required at all
conduit terminations where hub type fittings are not required. Conduit
grounding bushings within automatic transfer switches shall be bonded
together with jumper cables where control station size or number of conduits
warrants their use per NEC requirements.
D. Terminal Blocks:
1. Terminal blocks shall be installed parallel or perpendicular to the automatic
transfer switch enclosure sides. Approximately 20 percent spare terminals
shall be provided (minimum of two (2)). Terminals shall be lettered or
numbered to conform to the wiring diagrams.
E. Wires:
1. The wires within automatic transfer switch shall be neatly harnessed to
prevent the door damaging the wires and to prevent the wires hampering the
door operation.
2. All wires shall have identification markers on each end. Marker numbers shall
match the terminal block numbers.
F. Identification:
1. All automatic transfer switches shall have a nameplate attached which
properly identifies the box. Nameplates shall be installed as specified in
Detailed Specification 16076 - Labeling and Identification.
A. The following standard factory tests shall be performed on the equipment provided
under this section. All tests shall be in accordance with the latest version of UL
and NEMA standards.
1. Insulation check to ensure the integrity of insulation and continuity of the
entire system
2. Visual inspection to ensure that the switch matches the Specification
requirements and to verify that the fit and finish meet quality standards
3. Mechanical tests to verify that the switch’s power sections are free of
mechanical hindrances
4. Electrical tests to verify the complete electrical operation of the switch and to
set up time delays and voltage sensing settings of the logic.
C. The manufacturer shall provide three (3) certified copies of factory test reports.
2. Automatic transfer switch shall be witness shop tested in accordance with the
procedures specified under paragraph 3.02. The Contractor shall include in his
bid cost of satisfactory and suitable means for air travel, transportation,
incidentals, meals and lodging for the Engineer and the City’s representatives
to attend witness testing at the factory.
D. The Contractor shall provide three (3) copies of the manufacturer’s field start-up
report.
3.05 TRAINING
A. The Contractor shall provide a training session for up to five (5) owner’s
representatives for 3 normal workday at a jobsite location determined by the
owner.
16496-14 11/2017
2222
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
operation of the assembly, circuit breakers and major components within the
assembly.
A. The manufacturer of the ATS shall also have a national service organization that is
available throughout the contiguous United States and is available on call 24 hours
a day, 365 days a year.
END OF SECTION
16496-15 11/2017
2223
DETAILED SPECIFICATION 16496 – AUTOMATIC TRANSFER SWITCHES
CONTRACT DEL-260E
16496-16 11/2017
2224
DETAILED SPECIFICATION 16511E – LIGHTING FIXTURES AND DEVICES
CONTRACT DEL-260E
SECTION 16511E
Lighting Fixtures and Devices
NOTE: All Work for this Section shall be in accordance with the requirements of General
Specification 16511- Lighting Fixtures and Devices except as modified herein.
PART 1 GENERAL
1.03 PAYMENT
A. There shall be no separate payment for the Work of this Section; all costs shall be
included in the lump sum price bid for Contract Item E-LS-1, as described in Detailed
Specification 01270 – Measurement and Payment.
PART 2 PRODUCTS
I. The fixture schedule exit sign catalog numbers list only the manufacturer’s name and
the series type. Exit sign catalog numbers are dependent on single face, double face,
mounting method and/or indicating arrows being used. Provide exit signs accordingly
suitable for the various arrangements shown on the Contract Drawings.
2.02 LAMPS
B. Fluorescent lamps shall be cool white, energy efficient rapid start type. Unless
specifically indicated otherwise, fluorescent lamps shall be 32 watt T8, suitable for
ambient operation above 50 degrees F. For operation outdoors, at 50 degrees and
below, standard lamps shall be provided. All fluorescent lamps shall be Toxicity
16511E-1 11/2017
2225
DETAILED SPECIFICATION 16511E – LIGHTING FIXTURES AND DEVICES
CONTRACT DEL-260E
B. The panel enclosures shall be steel, single door type. Enclosures shall be NEMA 4X
stainless steel where necessary according to the NEMA room designations shown on
the Contract Drawings, NEMA 4X non-metallic in chlorine storage, feed rooms and
scrubber room. Each enclosure shall be equipped with a control fuse with mounting
block and 600 volt screw terminals. All other panel enclosures shall meet the
requirements of its associated NEMA room designations shown on the Contract
Drawings.
2. Not Used.
3. Receptacles shall be marine duty, straight blade type, with heat resistant
melamine body. Special receptacles in NEMA 4X locations shall be Type 316
stainless steel.
1. Stainless steel plates shall be furnished for devices in finished or dry locations.
They shall have beveled edges and shall be made of 302/304 stainless steel.
3. For other locations, neoprene gasketed covers shall be used. Covers shall be
galvanized ferrous or cast ferrous metal. Covers shall be PVC-coated where
necessary according to the NEMA room designations shown on the Contract
16511E-2 11/2017
2226
DETAILED SPECIFICATION 16511E – LIGHTING FIXTURES AND DEVICES
CONTRACT DEL-260E
Drawings. Covers shall be equipped with gasketed spring doors for receptacles
and an external operating mechanism for switches. Receptacle cover shall
maintain wet location rating with plug inserted where necessary according to the
NEMA room designations.
PART 3 EXECUTION
END OF SECTION
16511E-3 11/2017
2227
DETAILED SPECIFICATION 16511E – LIGHTING FIXTURES AND DEVICES
CONTRACT DEL-260E
16511E-4 11/2017
2228
THE CITY OF NEW YORK
DEPARTMENT OF
ENVIRONMENTAL PROTECTION
DEL-260G – GENERAL
DEL-260H – HVAC
DEL-260E – ELECTRICAL
Volume 2 of 2
Contract Terms and Specifications
(with separate Bid Booklets)
December 2017