Name of Owner - အမွတ္(၅) ဓာတ္ေျမၾသဇာစက္ံ  (ကန္ၾကီးေထာင့္)

Name of Work -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")

SUMMARY OF COST

Material Cost Labour Cost Machine Total Cost


Item Cost
No. Particular QTY
( Kyats ) ( Kyats ) ( Kyats ) ( Kyats )

1 ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္း
လု ပ္င န္း 1 9,514,896 385,740 972,820 10,873,456

Total Cost 9,514,896 385,740 972,820 10,873,456


ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း

Abstract Of Cost, Bill Of Quantity


&
Builder's Estimate, Detail Of Measurement
Name of Owner - အမွတ္(၅) ဓာတ္ေျမၾသဇာစက္ံ  (ကန္ၾကီးေထာင့္)

Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")

Sr. No. Descriptions Amount (Kyat) Remark

1 Material Charges 9,514,896

2 Labour Charges 385,740

3 Machine Charges 972,820

Total Cost 10,873,456


Name of Owner - အမွတ္(၅) ဓာတ္ေျမၾသဇာစက္ံ  (ကန္ၾကီးေထာင့္)

Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")


BILLS OF QUANTITIES

Sr No Particular Unit Quantity Rate Amount Total

MATERIALS LIST
1 Earth Sud 162.00 10000 1620000.00
2 Crushed Rock (max.Size 1") Sud 20.45 85000 1738250.00
3 Sandy Soil Sud 13.64 10000 136400.00
4 River Shingle or Chaung Gravel(max.1") Sud 34.09 95000 3238550.00
5 Sand Sud 6.82 16000 109120.00
P.O.L forOperation
6 Diesel Gal 581.98 4200 2444316.00
7 Engine Oil Gal 8.73 20000 174600.00
8 Gear Oil Gal 1.31 16000 20960.00
9 Hydraulic Oil Gal 1.96 15000 29400.00
10 Grease Lb 1.65 2000 3300.00
Cost Of Materials 9514896.00 9514896

LABOUR LIST
1 Head Worker Nos 3.74 9500 35530.00
2 Worker Nos 12.34 7500 92550.00
3 Operator Nos 22.89 9500 217455.00
4 Helper Nos 7.31 5500 40205.00
Cost Of Labours 385740.00 385740

MACHINE LIST
1 Compactor Hr. 2.95 30000 88500.00
2 Grader Hr. 13.36 30000 400800.00
3 Smooth Wheel Roller (8-10 Ton) Hr. 9.56 35000 334600.00
4 Tipper Hr. 4.89 12000 58680.00
5 Water Bowzer Hr. 10.68 8000 85440.00
6 Water Pump Hr. 2.40 2000 4800.00
Cost Of Machine 972820.00 972820

Total Cost 10873456

4
Name of Owner - အမွတ္(၅) ဓာတ္ေျမၾသဇာစက္ံ  (ကန္ၾကီးေထာင့္)

Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")


BILLS OF QUANTITIES

Sr No Particular Unit Quantity Rate Amount Total

5
0.00

6
7
Name of Owner - အမွတ္(၅) ဓာတ္ေျမၾသဇာစက္ံ  (ကန္ၾကီးေထာင့္)

Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")


ABSTRACT OF COST

Sr.No Particulars Unit Quantity Rate Per Amount

1 Construction of Subgrade
Using Transported soil Cft 12000.00 214.96 Cft 2579493.00

2 Construction of 6"(compacted)Granular Base Course


Using Crushed Rock+Gravel+Sand+Soil(3:5:1:2) Cft 6000.00 1382.33 Cft 8293963.00

Total Of Cost 10873456.00

8
Name of Owner - အမွတ္(၅) ဓာတ္ေျမၾသဇာစက္ံ  (ကန္ၾကီးေထာင့္)
Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")

BUILDER'S ESTIMATE

Sr.No Particulars Quantity Unit Rate Per Amount Total

1 Construction of Subgrade
Using Transported soil 12000.00 Cft
Material
Earth 162.00 Sud 10000 Sud 1620000.00
P.O.L forOperation
Diesel 71.59 Gal 4200 Gal 300678.00
Engine Oil 1.07 Gal 20000 Gal 21400.00
Gear Oil 0.16 Gal 16000 Gal 2560.00
Hydraulic Oil 0.24 Gal 15000 Gal 3600.00
Grease 0.20 Lb 2000 Lb 400.00
1948638.00
Machine
Compactor 2.95 Hr. 30000 Hr. 88500.00
Grader 5.68 Hr. 30000 Hr. 170400.00
Smooth Wheel Roller (8-10 Ton) 4.77 Hr. 35000 Hr. 166950.00
Tipper 4.89 Hr. 12000 Hr. 58680.00
Water Bowzer 5.68 Hr. 8000 Hr. 45440.00
Water Pump 2.39 Hr. 2000 Hr. 4780.00
534750.00
Labour
Head Worker 1.14 Nos 9500 Nos 10830.00
Worker 4.55 Nos 7500 Nos 34125.00
Operator 3.41 Nos 9500 Nos 32395.00
Helper 3.41 Nos 5500 Nos 18755.00
96105.00 2579493.00

2 Construction of 6"(compacted)Granular Base Course


Using Crushed Rock+Gravel+Sand+Soil(3:5:1:2)
6000.00 Cft
Material
Crushed Rock (max.Size 1") 20.45 Sud 85000 Sud 1738250.00
River Shingle or Chaung Gravel(max.1") 34.09 Sud 95000 Sud 3238550.00
Sand 6.82 Sud 16000 Sud 109120.00
Sandy Soil 13.64 Sud 10000 Sud 136400.00

P.O.L forOperation

9
Name of Owner - အမွတ္(၅) ဓာတ္ေျမၾသဇာစက္ံ  (ကန္ၾကီးေထာင့္)
Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")

BUILDER'S ESTIMATE

Sr.No Particulars Quantity Unit Rate Per Amount Total

Diesel 510.39 Gal 4200 Gal 2143638.00


Engine Oil 7.66 Gal 20000 Gal 153200.00
Gear Oil 1.15 Gal 16000 Gal 18400.00
Hydraulic Oil 1.72 Gal 15000 Gal 25800.00
Grease 1.45 Lb 2000 Lb 2900.00
7566258.00
Machine
Smooth Wheel Roller (8-10 Ton) 4.79 Hr. 35000 Hr. 167650.00
Grader 7.68 Hr. 30000 Hr. 230400.00
Water Bowzer 5.00 Hr. 8000 Hr. 40000.00
Water Pump 0.01 Hr. 2000 Hr. 20.00
438070.00
Labour
Head Worker 2.60 Nos 9500 Nos 24700.00
Worker 7.79 Nos 7500 Nos 58425.00
Operator 19.48 Nos 9500 Nos 185060.00
Helper 3.90 Nos 5500 Nos 21450.00
289635.00 8293963.00

10873456

10
Name of Owner - အမွတ္(၅) ဓာတ္ေျမၾသဇာစက္ံ  (ကန္ၾကီးေထာင့္)
Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")
DETAIL MEASUREMENT

Measurement
No Particular No Dedu; Content Unit
L B H
1 Construction of Subgrade
Using Transported soil
Road 1 1 800'- 0'' 15'- 0'' 1'- 0'' 12000.00 Cft
12000.00 Cft

2 Construction of 6"(compacted)Granular Base Course


Using Crushed Rock+Gravel+Sand+Soil(3:5:1:2)
Road 1 1 800'- 0'' 15'- 0'' 0'- 6'' 6000.00 Cft
6000.00 Cft

11
Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")
DETAIL MEASUREMENT

Measurement
No Particular No Dedu; Content Unit
L B H

12
Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")
DETAIL MEASUREMENT

Measurement
No Particular No Dedu; Content Unit
L B H

13
Name of Project -ေက်ာက္ေရာေျမျဖင့္လမ္းခင္းျခင္းလု ပ္င န္း (800'x15'x6")
DETAIL MEASUREMENT

Measurement
No Particular No Dedu; Content Unit
L B H

14