Professional Documents
Culture Documents
com/row/document/university-of-karachi/operation-and-supply-chain-
management/other/mcqs-project-management-mcqs-pmp/2193955/view
Answer Option D
2. In the time-cost optimisation, using CPM method for network analysis, the crashing of the
activities along the critical path is done starting with the activity having
(A) Longest duration
(B) Highest cost slope
(C) Least cost slope
(D) Shortest duration
Answer Option C
3. The time with which direct cost does not reduce with the increase in time is known as
(A) Crash time
(B) Normal time
(C) Optimistic time
(D) Standard time
Answer Option B
4. The direct cost of a project with respect to normal time is
(A) Minimum
(B) Maximum
(C) Zero
(D) Infinite
Answer Option A
5. During the construction period, price variation clause in contracts caters to
(A) Increase in rates of only important materials
(B) Variation in cost in materials element, labour element and petrol-oil-lubricant element
(C) Variation in total cost of the project on an ad hoc basis
(D) Rate of inflation
Answer Option B
5. B
6. D
7. D
8. C
9. B
10. A