Professional Documents
Culture Documents
Finance Mini Case
Finance Mini Case
QUESTION (A)
What is capital
budgeting?
• Analysis of potential projects.
• Long-term decisions; involve
large expenditures.
• Very important to firm’s future.
• Evaluate & select long term
investment, align with the goal of
the firm, maximize s/holder
wealth.
QUESTION (B)
What is the difference
between independent
and mutually exclusive
projects?
Projects are:
Independent, if the cash flows of
one are unaffected by the
acceptance of the other.
Mutually exclusive, if the cash
flows of one can be adversely
impacted by the acceptance of the
other.
QUESTION C (1)
What is the payback
period? Find the paybacks
for Franchises L and S.
The payback period is the expected number of years required to
recover a project's cost. We calculate the payback by developing
the cumulative cash flows
Franchise L
0 1 2 3
| | | | Payback L: 2 + ($30/$80) = 2.4 years
-100 10 60 80
-90 -30 50
Franchise S
0 1 2 3
| | | |
Payback S: 1 + ($30/$50) = 1.6 years
-100 70 50 20
-30 20 40
QUESTION C (2)
What is the rational for the payback
method? According to the payback
criterion, which franchises should be
accepted if the firm’s maximum
acceptable payback is 2 years, and if
franchises L and S are independent? If
they are mutually exclusive?
• Payback represents a type of "breakeven"
analysis: the payback period tells us when the
project will break even in a cash flow sense.
• With a required payback of 2 years, franchise S
is acceptable, but franchise L is not.
• Whether the two projects are independent or
mutually exclusive makes no difference in this
case.
QUESTION C (3)
What is the difference
between the regular and
discounted payback
periods?
Payback period Discounted payback period
• A capital budgeting procedure • the payback period only measure
used to determine the profitability how long it take for the initial cash
of a project. outflow to be paid back, ignoring
• Provides the overall value of a the time value of money
project, a discounted payback
period gives the number of years it
takes to break even from
undertaking the initial expenditure.
QUESTION C (3)
What is the main disadvantage of
discounted payback? Is the
payback method of any real
usefulness in capital budgeting
decisions?
• Time value of money is not considered when you
If IRR = k : cash flows are just sufficient to provide investors with their
required rates of return.
If IRR < k : economic loss, or a project that will not earn enough to
cover its cost of capital.
0 1 2 3
(100) 70 50 20
55
84.7
TV = 159.7
MIRRL = 16.50%
Franchise S WACC = 10%
0 1 2 3
(100) 10 60 80
66
12.1
TV = 158.1
MIRRS = 16.89%
QUESTION H(2)
What are the MIRR’s
advantages and
disadvantages vis-a-
vis the regular IRR?
• MIRR assumes that cash flows from all the
firm’s projects are reinvested at the cost of
capital.
• MIRR is a better indicator of a project’s
true profitability.
• MIRR solves the multiple IRR problems, as a
set of cash flows can have but one MIRR.
What are the MIRR’s advantages and
disadvantages vis-a-vis the NPV?
0 ($0.8)
1 5.0
2 (5.0)
The project is estimated to be of average risk, so its cost of capital is 10 percent.
• Normal cash flows begin with a negative or a series of negative cash flows, switch
to positive cash flows and then remain positive and vice versa.
•They have only one change in sign.
•Non-normal cash flows have more than one sign change. For example, they may
start with negative cash flows, switch to positive, and then switch back to negative.
(2) What is project P’s NPV? What is its IRR? It’s MIRR?
Here is the time line for the cash flows, and the NPV;
0 10% 1 2
| | |
-800,000 -5,000,000 5,000,000
NPV = -$386,776.86.
We can find the NPV by entering the cash flows into the cash flow register, entering i=
10, and then pressing the NPV button. However, calculating the IRR presents a
problem. With the cash flows in the register, press the IRR button will give the
message "error-soln." This means that project P has multiple IRRs. As you are asked to
guess, if you guess 10%, the calculator will produce IRR = 25%. If you guess a high
number, such as 200%, it will produce the second IRR, 400%. The MIRR of project P =
5.6%, and is found by computing the discount rate that equates the terminal value
($5.5 million) to the present value of cost ($4.93 million).
i. (3) Does project P have normal or non-normal
cash flows? Should this project be accepted?
0 ($100,000) ($100,000)
1 60,000 33,500
2 60,000 33,500
3 -- 33,500
4 -- 33,500
Project L's common life NPV is its raw NPVL = $6,190 (since actual duration = 4 years)
However, project S would be replicated in year 2, and if we assume that the replicated
project's cash flows are identical to the first set of cash flows, then the replicated NPV
is also $4,132, but it "comes in" in year 2. We can put project S's cash flow situation
on
a time line:0 10% 1 2 3 4
| | | | |
4132 4132
3,415
7,547
7547
(3) Now assume that the cost to replicate project S in 2 years will increase
to $105,000 because of inflationary pressures. How should the
analysis be handled now, and which project should be chosen?
With this change, the common life NPV of project S is less than that for project
L, and hence project L should be chosen.
QUESTION K
You are also considering another project which has a physical life of 3 years; that is, the
machinery will be totally worn out after 3 years. However, if the project were terminated prior
to the end of 3 years, the machinery would have a positive salvage value. Here are the
project’s estimated cash flows:
Using the 10 percent cost of capital, what is the project’s NPV if it is operated for the full 3
years? Would the NPV change if the company planned to terminate the project at the end of
year 2, at the end of year 1? And what is the project’s optimal (economic) life?
Solution:
0 1 2 3
10%
Therefore, Net Present Value for no project termination is (NPV) = -$123.22/ -$123.
(i) With Termination After 2 Years
0 1 2
10%
Salvage ($2000)
Value
($4000)
Therefore, Net Present Value with project termination after 2 years is (NPV) = $214.88/
$215.
(i) With Termination After 1Years
0 1
10%
CF ($5000) ($2100)
Salvage ($3100)
Value ($4000)
Therefore, Net Present Value with project termination after 2 years is (NPV) = $-272.73/
-$273.
CONCLUSION:
Based on all NPV value from three different options
can be conclude that the optimal economic life is the
project should be terminate after years 2 where the
NPV value is positive ($215). Moreover, it also
indicated that a project engineering life does not
always equal to its economic life.
QUESTION L
Capital
Rationing
THANK YOU
Q & A SESSION