1. OBJECTIVE
The purpose of this document is to cover the minimum technical requirement for Metal
Enclosed Gas Insulated Switchgear 13.8 kV, required for Anaco Project-Operaciones
Centralizadas Campo San Joaquin.
2. SCOPE
The document is based the Engineering specification “Metal Enclosed Gas Insulated
Switchgear up to 34.5 kV, according to PDVSA N 280, rev 0. Which is the specification
shall be applied to this project.