Block 23 Casing/Tubing REQUIREMENT - 2022 Work Programme

Weight IS Well QCN Well


SIZE Grade Connection
(ppf) (m) (m)
13-3/8" L-80 68 VAM Top / Premium 600 600
9-5/8" L-80 47 VAM Top / Premium 1660 1500
7" L-80 29 VAM Top / Premium 650 2150
4-1/2" L-80 12.6 VAM Top / Premium 0 0
3-1/2" L-80 9.2 VAM Top / Premium 2200 2150

Completion Equ QTY p/w


Reamer Shoe 1
3-1/2" SSD 3
3-1/2" x 6" Swell Packers 4
3-1/2" x 7" Liner Hanger 1 avaiable in our stock 4 1/2" x 7"

WEG 1
No Go 1
Landing Nipple 1
3-1/2" x 7" Production Pack 1
3-1/2" SSD 1
TRSV 1
Total inc. XS Reamer Bow Spring Ridgid
Float Shoe Float Collar
(m) Shoe Centralizer Centralizer
1230 2 0 2 30 0
3243 1 1 2 20 40
2833 2 x 9-5/8" x 7" Liner Hanger w float equipment & reamer shoe
0 TBD
4460 Completion Tubing