You are on page 1of 4

SHIELDED METAL ARC WELDING II

GRABSUM SCHOOL INC. / FEBRUARY 3 – MARCH 2, 2021


TRAINING ACTIVITY MATRIX

FACILITIES/ VENUE DATE


TRAINING
TRAINEE TOOLS AND WORKSTATION/ AND REMARKS
ACTIVITY/IES
EQUIPMENT AREA TIME

Perform root pass Equipment Demo/ Practical Feb 3 Group


Welding machine work area to Mar Discussion
 Root pass is AC or AC/DC
2
performed in Welding table or jig
accordance Portable grinder 7AM Demo with
with WPS Welding booth to Interview
and/or client Portable oven 4PM
specifications
Tools/Accessories
 Task is Welding mask
performed in Steel brush
accordance clear glass
with company Chipping hammer
or industry Dark glass
requirement Supplies/Materials
and safety Electrodes
procedure. Carbon Steel Pipes
Cutting grinding
 Weld is disk
visually
checked for Personal
defects and protective
repaired, as equipment
required Safety shoes
Apron
 Weld is Leggings
visually Safety goggles
acceptable in Gloves
accordance
with Training Materials
applicable Arc welding
codes and manuals
standards Welding
procedures
specifications
(WPS)
Welding standards

RENNEL S. ADOLFO / TRAINER


SHIELDED METAL ARC WELDING II
GRABSUM SCHOOL INC. / FEBRUARY 3 – MARCH 2, 2021
TRAINING ACTIVITY MATRIX

FACILITIES/ VENUE DATE


TRAINING
TRAINEE TOOLS AND WORKSTATION AND REMARKS
ACTIVITY/IES
EQUIPMENT / AREA TIME

Clean root pass Equipment Demo/ Practical Feb 3 Group


Welding machine work area to Discussion
 Root pass is AC or AC/DC
Mar 2
cleaned and Welding table or jig
free from Portable grinder 7AM Demo with
defects and Welding booth to Interview
discontinuitie Portable oven 4PM
s
Tools/Accessories
 Task is Welding mask
performed in Steel brush
accordance clear glass
with approved Chipping hammer
WPS Dark glass
Supplies/Materials
Electrodes
Carbon Steel Pipes
Cutting grinding
disk

Personal
protective
equipment
Safety shoes
Apron
Leggings
Safety goggles
Gloves

Training Materials
Arc welding
manuals
Welding
procedures
specifications
(WPS)
Welding standards

RENNEL S. ADOLFO / TRAINER


SHIELDED METAL ARC WELDING II
GRABSUM SCHOOL INC. / FEBRUARY 3 – MARCH 2, 2021
TRAINING ACTIVITY MATRIX

FACILITIES/ VENUE DATE


TRAINING
TRAINEE TOOLS AND WORKSTATION AND REMARKS
ACTIVITY/IES
EQUIPMENT / AREA TIME

Weld Equipment Demo/ Practical Feb 3 Group


subsequent/ Welding machine work area to Discussion
filling passes AC or AC/DC
Mar 2
Welding table or jig
 Subsequent/ Portable grinder 7AM Demo with
filling passes Welding booth to Interview
is performed Portable oven 4PM
in accordance
with approved Tools/Accessories
WPS Welding mask
Steel brush
 Weld is clear glass
visually Chipping hammer
checked for Dark glass
defects and Supplies/Materials
repaired, as Electrodes
required Carbon Steel Pipes
Cutting grinding
 Weld is disk
visually
acceptable in Personal
accordance protective
with equipment
applicable Safety shoes
codes and Apron
standards Leggings
Safety goggles
Gloves

Training Materials
Arc welding
manuals
Welding
procedures
specifications
(WPS)
Welding standards

SHIELDED METAL ARC WELDING II


RENNEL S. ADOLFO / TRAINER
GRABSUM SCHOOL INC. – FEBRUARY 3 / MARCH 2, 2021
TRAINING ACTIVITY MATRIX

FACILITIES/ VENUE DATE


TRAINING
TRAINEE TOOLS AND WORKSTATION/ AND REMARKS
ACTIVITY/IES
EQUIPMENT AREA TIME

Perform capping Equipment Demo/ Practical Feb 3 Group


Welding machine work area to Discussion
 Capping is AC or AC/DC
Mar 2
performed in Welding table or jig
accordance Portable grinder 7AM Demo with
with WPS Welding booth to Interview
and/or client Portable oven 4PM
specifications
Tools/Accessories
 Weld is Welding mask
visually Steel brush
checked for clear glass
defects and Chipping hammer
repaired, as Dark glass
required Supplies/Materials
Electrodes
 Weld is Carbon Steel Pipes
visually Cutting grinding
acceptable in disk
accordance
with Personal
applicable protective
codes and equipment
standards Safety shoes
Apron
Leggings
Safety goggles
Gloves

Training Materials
Arc welding
manuals
Welding
procedures
specifications
(WPS)
Welding standards

RENNEL S. ADOLFO / TRAINER