Professional Documents
Culture Documents
CM&CD Works On Canals and Design of Lift Irrigation Schemes
CM&CD Works On Canals and Design of Lift Irrigation Schemes
Irrigation Schemes
4
CANALS
MAJOR MINOR
MAIN CANAL BRANCH CANAL
DISTRIBUTORY DISTRIBUTORY
FIELD CHANNEL
5
CANAL STRUCTURES
Head Regulator Cross Regulator Drops Bridges, Roads & Foot Bridges for
Escapes Measuring Devices OT Sluices
Railways Men & Cattle
CROSS DRAINAGE WORKS
To Pass Irrigation Canal Over the To Pass Drain Over the Irrigation Canal
By means of SP/ Canal Syphon To Pass Drain through Irrigation Canal
Drainage by means of Aqueduct/ UT/
By means of Inlet & Outlet/ Level
Viaduct / Syphon Aqueduct
Crossing
6
Types of CM& CD Works
Types:
• 1. Falls: Vertical Fall, Sarda type fall and straight glacis fall.
• 2. Regulators: Head and cross regulators; design principles
• 3. Cross-drainage works: Aqueduct, Syphon aqueduct, and Super passage.
• 4. Outlets: Types Viz., proportionality, sensitivity and flexibility
Crest level
• For cross regulator- crest level is same as upstream bed level of anal
• For head regulator- crest level is kept 0.3-1m higher than the crest level of the cross regulator
Waterway: The discharge equation for drowned weir is used to find waterway
• Q =Q1+Q2= 2/3
• Where,Cd1 =0.577; Cd2= 0.80
• B= clear water way required
• h = difference of water levels U/S & D/S of crest
• D/S water level in the channel above the crest= head due to velocity of approach, which is
small and often ignored.
• conditions of flow for design
• The design is made for the worst of the following two conditions
• Full supply discharge is passing down both the channels with all gates of cross and head
regulator open
• The discharge in the parent channel is low but the off take channel is running at full with fully
supply level main maintained in branch channel
• Quite often the 1st condition governs the design.
• D/S floor level or cistern level
• Level of D/S floor = D/s FSL- Ef2 , taking hv=0
• Where,Ef2 = specific energy in the D/S of the section
• Ef2 ..is formed from the hydraulic jump equation
• length of D/s floor: generally it is = 5(y2-y1) where y1 and y2 are depths before
and after jump also it is governed by the safe exit gradient allowable for the site
conditions
• cut-offs
• Depth of U/S cutoff =Yu/3+0.6, where Yu = upstream water depth in canal
• Depth of D/S cutoff = Yd/3+0.6, where Yd = downstream water depth in canal
• total floor length: based on exit gradient consideration.
• uplift pressures and floor thickness: based on khoslas theory
• on U/S side: minimum thickness of 0.3-0.5 m is provided
• protection works: based on scour depth,
D which is Yu/3+0.6 on upstream side and Yd/3+0.6 on downstream side
• Cement concrete blocks are provided for length of 1.5 D on U/S & D/S side
• Quantity of slope =2.25D m3/m length.
Cross-Drainage work
(Aqueduct, Syphon aqueduct and Super passage)
• A cross drainage work is a structure constructed at the crossing of a canal and
a natural drain such that there is no interruption to the flow in the canal
when the drain receives water, due to rain fall or otherwise in the catchment.
The drainage water (of the drain) can be disposed of in one of the following
ways
• By passing the canal over the drainage through an aqueduct or siphon
aqueduct.
• By passing the canal below the drainage through a super passage or a canal
siphon
• By letting the drain water into the canal and then disposing it off through a
level crossing or inlets & outlets.
• Aqueduct: In this structure, the canal bed is above the highest flood level
(HFL) of the drain. Flow in the drain is at atm. Pressure.
• Syphon aqueduct: The drain bed is depressed and provided with a pucca
floor. The HFL of drain is above the bottom level of canal bed and as such flow
in the drain is under pressure and not at atmospheric pressure
Super passage and Canal Syphon.
Super Passage,Canal Syphon,& Inlet-outlets
• Super passage: the canal full supply level (FSL) is much below the bottom level of the drain.
Flow in canal is by gravity and water surface everywhere is exposed to atmosphere.
• Canal siphon: The bed of the canal is lowest and flow in canal is under pressure. The FSL of
the canal (on the u/s side) is above the bed level of drain. Thus flow in canal is syphonic in
action.
• Level crossing: A level crossing is a cross drainage structure constructed when the canal and
drain flows meet at the same level. (see fig.) Cross regulators across drain and canal
(outgoing) are required to control the flows in drain and canal respectively. Sometimes a
regulator across incoming canal is also provided.
These structures become necessary where high discharge is carried by canal and
intermittent floods of high magnitude occur in the drain and when they meet at the same
level.
• Inlets and outlets:
• An inlet is a structure constructed across the drain and the drain water is admitted into the
canal to augment canal discharge. It is done when drain discharge is small and canal water
level is maintained close to FSL or slightly higher. It is also necessary that too much silt does
not enter the canal through the drain discharge.If the drain discharge is high, then an outlet
may also be constructed d/s of function to dispose of the drain flood
General Design considerations for cross drainage works
• Max-Flood discharge of drain: Arrived at by empirical/rational
formula for small drains; and by hydrograph analysis for large
grains.
• Waterway required for aqueducts and siphon aqueducts:
Waterway of drain (P) = 4.75 (Laceys’s equations). Effective clear
waterway will be less then P due to the thickness of pipes. It
should not be less than 0.8P.
• Size of barrel: highest level of drain barrel: In case of aqueduct,
the HFL of drain is much below the bottom level of canal tough. In
Siphon aqueduct it depends on the velocity allowable in barrel,
which is of the order of 2-3 m/s.
• Afflux and Head loss through siphon barrels: Due to the reduction
in the width of the drain, afflux occurs or the u/s side of drain
barrel.
• The head loss through siphon barrel is found from Unwin’s formula. It is
also known as afflux.
• R=(1+f1+f2+L/R)V2/2g-Va2/2g
Where
• L = length of barrel
• R = Hyd. Mean Radius of barrel
• V = Velocity of flow through barrel
• Velocity of approach (negligible)
• f1 = Coefficient of head loss at entry = 0.505 for unshaped entry;
• = 0.08 for belt mouth entry
• f2 = Coefficient of function such that head loss through barrel due to
surface functions is given by formula f2*L*V2/2gR;
• =a(1+b/R)
• Value of a,b are given in Table in next slide.
• Taking D/s HFL of Drain same;
• U/s HFL=D/s HFL+h
Material a b
Smooth iron pipe 0.00497 0.025
Smooth pipe 0.00996 0.025
Ashlar or Brickwork 0.00316 0.030
Rubble Masonry/Stone 0.0057 0.250
pitching
Canal outlet:
• A canal outlet is a small structure, which admits water to a field channel (water course) from
a distributing (branch) canal. It is used to deliver the required water into the field channel,
which is turn, is used to irrigate the land under its command. Field channel is maintained by
the farmer.
• Outlets are classified under three hands:
• Non-modular outlet: A non modular outlet is the one in which the discharge (let out into the
field channel) is based on the difference in water levels in the distributary and the field
channel. E.g. submerged pipe outlet, masonry sluices and orifices, wooden shoots.
• Semi-module or flexible outlet:
• In this type, the discharge is affected by the water level in the distributary only. Fluctuations
in the water level of the field channel do not affect the discharge.
• E.g.: Kennedy’s gauge outlet crump’s open flume outlet, pipe – cum-open flume outlet.
• Rigid module: In this type, constant discharge is admitted to field channel even when there
are fluctuations in water levels of both distributary and field channel. E.g. Gibbs Module
III) Hydro-Mechanical
V
9250
BEAM B6
V
BEAM B7
+ 356.75
20 t E.O.T. CRANE
provisions
BEAM B5 + 353.75 V
MANUALLY OPERATED V
225 Th BRICK WALL
CRANE ( 3 t CAPACITY )
+ 351.50 REFLUX VALVE 4000 Ø MANIFOLD
( TENTATIVE )
SLUICE VALVE
+ 349.00
W 1300 Ø DELIVERY PIPE + 348.15
SLAB S1
+ 346.50 + 347.00 + 346.50
CBL + 340.50 150 Th C.C. IN M15 GRADE BEAM B3 1000 Th R.C.C. STEINING WALL
STOPLOG GROOVE
+ 338.00
250 Th C.C. IN M10 GRADE + 338.50
+ 337.50
1000 Th R.C.C. RAFT
500 13500
house
IRREGULARITIES IN FOUNDATION TO BE
FILLED WITH C.C. M20 GRADE WITH MSA 40
Intake/Sump/Forebay/Surge pool
2
Sub structure / sump
9250
C1 W C1
+ 346.50
C3 C3
+ 346.50
5000
+ 347.00
W RS1
REPAIR BAY
26000 5000
+ 338.50
+ 338.00
BEAM B1
W
500
Th + 346.50
500 C1 BEAM B2 C1
4000
+ 338.00
TRASHRACK GROOVE W 1300 Ø DELIVERY PIPE
REFLUX VALVE
4000 Ø MANIFOLD
2.0 m WIDE
SILT TRAP
6 x 4.00 + 5 x 1.00 = 29.00 m
+ 338.50
W
BEAM B1
2500
10000
5000
FLOW APPROACH BED C1 BEAM B2 C1
LEVEL + 340.50
4000
+ 338.00
W
STOPLOG GROOVE
+ 338.50
+ 347.00
+ 338.00
W 1300 Ø DELIVERY PIPE
Delivery Cistern
C1 1000 Th PIER C1
5500
1000
+ 338.50
+ 347.00
+ 338.00
W 1300 Ø DELIVERY PIPE
4000
3 C1 C3 C3 C1
+ 375.00
10000
4750
W
4750
W
C3 C3
C2 RS2 C2
2
works on delivery side IEI, HYDERABAD
6 October 2017
PLAN OF THE JACKWELL CUM PUMP HOUSE
35
II) Electro
Mechanical 9250
SLAB S2 BEAM B6 BEAM B7
BEAM B5 + 353.75 V
MANUALLY OPERATED V
225 Th BRICK WALL
CRANE ( 3 t CAPACITY )
+ 351.50 REFLUX VALVE 4000 Ø MANIFOLD
( TENTATIVE )
SLUICE VALVE
Control Panels
+ 349.00
W 1300 Ø DELIVERY PIPE + 348.15
SLAB S1
+ 346.50 + 347.00 + 346.50
CBL + 340.50 150 Th C.C. IN M15 GRADE BEAM B3 1000 Th R.C.C. STEINING WALL
STOPLOG GROOVE
SCADA
+ 338.00
250 Th C.C. IN M10 GRADE + 338.50
+ 337.50
1000 Th R.C.C. RAFT
500 13500
IRREGULARITIES IN FOUNDATION TO BE
FILLED WITH C.C. M20 GRADE WITH MSA 40
Dewatering Pumps
CROSS SECTIONAL ELEVATION OF JACKWELL CUM PUMP HOUSE
( SECTION 1 - 1 )
2
9250
C1 W C1
+ 346.50
C3 C3
5000
+ 347.00
W RS1
REPAIR BAY
26000 5000
500 3000
+ 338.50
+ 338.00
BEAM B1
W
Pumps
500
Th + 346.50
500 C1 BEAM B2 C1
4000
+ 338.00
TRASHRACK GROOVE W 1300 Ø DELIVERY PIPE
REFLUX VALVE
HOPDV / NRV /
C1 1000 Th PIER C1
1 SLUICE VALVE
4000 Ø MANIFOLD
2.0 m WIDE
SILT TRAP
6 x 4.00 + 5 x 1.00 = 29.00 m
+ 338.50
W
BEAM B1
2500
10000
5000
FLOW APPROACH BED C1 BEAM B2 C1
LEVEL + 340.50
4000
EOPDV etc within
+ 338.00
W
STOPLOG GROOVE
+ 338.50
+ 347.00
+ 338.00
W 1300 Ø DELIVERY PIPE
0
550
1000
+ 338.50
+ 347.00
+ 338.00
W 1300 Ø DELIVERY PIPE
4000
3
4750
W
CONTROL PANEL
+ 346.50 C2 C2
+ 346.50
+ 347.00
4750
W
station C2
C3
RS2
C3
C2
2
PLAN OF THE JACKWELL CUM PUMP HOUSE
6 October 2017 IEI, HYDERABAD 36
III) Hydro – Mechanical
Pressure mains with design dia SLAB S2
9250
BEAM B6
V
BEAM B7
+ 356.75
V
CRANE GIRDER 20 t E.O.T. CRANE
and thickness
BEAM B5 + 353.75 V
MANUALLY OPERATED V
225 Th BRICK WALL
CRANE ( 3 t CAPACITY )
+ 351.50 REFLUX VALVE 4000 Ø MANIFOLD
( TENTATIVE )
SLUICE VALVE
+ 349.00
W 1300 Ø DELIVERY PIPE + 348.15
SLAB S1
+ 346.50 + 347.00 + 346.50
CBL + 340.50 150 Th C.C. IN M15 GRADE BEAM B3 1000 Th R.C.C. STEINING WALL
STOPLOG GROOVE
+ 338.00
250 Th C.C. IN M10 GRADE + 338.50
+ 337.50
1000 Th R.C.C. RAFT
500 13500
regular intervals
2
Stoplogs & trashracks
9250
C1 W C1
+ 346.50
C3 C3
+ 346.50
5000
+ 347.00
W RS1
REPAIR BAY
26000 5000
Manifold connecting
500 3000
+ 338.50
+ 338.00
BEAM B1
W
500
Th + 346.50
500 C1 BEAM B2 C1
4000
+ 338.00
TRASHRACK GROOVE W 1300 Ø DELIVERY PIPE
SLUICE VALVE
4000 Ø MANIFOLD
2.0 m WIDE
SILT TRAP
6 x 4.00 + 5 x 1.00 = 29.00 m
+ 338.50
W
BEAM B1
2500
10000
5000
FLOW APPROACH BED C1 BEAM B2 C1
pressure mains
LEVEL + 340.50
4000
+ 338.00
W
STOPLOG GROOVE
+ 338.50
+ 347.00
+ 338.00
Semi Portal crane for
W 1300 Ø DELIVERY PIPE
C1 1000 Th PIER C1
0
550
1000
+ 338.50
+ 347.00
+ 338.00
W 1300 Ø DELIVERY PIPE
4000
3 C1 C3 C3 C1
+ 375.00
4750
W
CONTROL PANEL
+ 346.50 C2 C2
+ 346.50
+ 347.00
4750
W
C3 C3
C2 RS2 C2
2
PLAN OF THE JACKWELL CUM PUMP HOUSE
6 October 2017 IEI, HYDERABAD 37
Planning & Design Of LIS Comprises
1. Hydrology
2. Finalisation of Alignment
- Length of Gravity Canals
- Length of Pressuremains
- Number of Lifts
- Balancing Reservoirs Utilization/Introduction
- Pump Houses Location
3. Hydraulic Particulars
- Discharge
- Pumping Head
4. Design of Pumps
- Type of Pumps
- Number of Pumps
- Capacity of Pumps Cont..
6 October 2017 IEI, HYDERABAD 38
5. Design of Pump House
- Approach Canal / Tunnel
- Intake / sump / Forebay
- Sub Structure
- Super Structure
6. Design of Pressure mains
- Type / Material
- Diameter of Pipes and
- Number of rows
- Pipe Laying & Compaction of refill
- Surge Analysis And Protection System
- CM & CD Works for Pipe crossings
7. Delivery Cistern / Out fall structure
8. SCADA
6 October 20179. Canal networking system
IEI, HYDERABAD 39
1)
HYDROLOGY
Water Required to be assessed based on
- Ayacut to be served
- Type of Crops
- Quantity of water
- Period of operation
Water Availability at source
- Net Quantity
- Period / Duration
The water requirement shall match with the water
available at the source duly considering the allocated or under
utilization quantity for the already existing needs, if any.
6 October 2017 IEI, HYDERABAD 40
2) ALIGNMENT
+ 46.25
Delivery III
+41.30 FSL +40.00 LWL + 38.795
CBL +38.53
+ 22.60 Delivery II
FSL +18.00M
LWL + 16.715
+16.00M CBL +15.00M
LIFT II
+37.00
Pressure mains
+22.80
M.F.L +20.80 +22.80 FSL +18.00M
+16.00M CBL +15.00M
RIVER
Avg. G.L
+14.00 Bank Delivery I
LWL + 13.50 No. Disch LWL Platform Delivery Intake/Gravity Length Pipe Length
+8.00
+6.50 +8.00 BED LEVEL OF Lift I 6.56 cumecs + 13.00m + 22.80m + 23.60m 20.00m 200.0m
JACKWELL Lift II 6.56 cumecs + 16.715m + 22.60m + 41.30m 4540.0m 1350.0m
+2.75
+2.30 C.C M20 Lift III 6.06 cumecs + 38.795m + 46.25m + 60.60m 4080.0m 525.0m
GRADE
-1.00
- 3.0
LIFT I Fig 1 SCHEMATIC DIAGRAM SHOWING 3 - LIFTS OF CHAGALNADU L.I. SCHEME
6 October 2017 IEI, HYDERABAD 42
Approach Canal and
Gravity Canal
Shorter length of Approach canal
Off take point shall not be silt
accumulation region as it is the
gate way of the LIS
Reverse slope may be provided
in river intake
Approach Capacity 50% more
than required for river intake
Greater length of gravity canals
on delivery side shall be
explored minimizing pipe length
to achieve economy.
6 October 2017 IEI, HYDERABAD 43
Length of Pressure mains
• Shorter length of Pressure main shall be provided
since length has compounding impact on cost of the
•- Pipe thickness
+ 46.25
Delivery III
+41.30 FSL +40.00 LWL + 38.795
CBL +38.53
+ 22.60 Delivery II
FSL +18.00M
LWL + 16.715
+16.00M CBL +15.00M
LIFT II
+37.00
Pressure mains
+22.80
M.F.L +20.80 +22.80 FSL +18.00M
+16.00M CBL +15.00M
RIVER
Avg. G.L
+14.00 Bank Delivery I
LWL + 13.50 No. Disch LWL Platform Delivery Intake/Gravity Length Pipe Length
+8.00
+6.50 +8.00 BED LEVEL OF Lift I 6.56 cumecs + 13.00m + 22.80m + 23.60m 20.00m 200.0m
JACKWELL Lift II 6.56 cumecs + 16.715m + 22.60m + 41.30m 4540.0m 1350.0m
+2.75
+2.30 C.C M20 Lift III 6.06 cumecs + 38.795m + 46.25m + 60.60m 4080.0m 525.0m
GRADE
-1.00
- 3.0
LIFT I Fig 1 SCHEMATIC DIAGRAM SHOWING 3 - LIFTS OF CHAGALNADU L.I. SCHEME
6 October 2017 IEI, HYDERABAD 45
Utilization of Tanks / Balancing Reservoirs
rivers EL 294.00
CONTROL ROOM
EL 273.50
P.T & S.A CUBICLES, EXCITATION
EQUIPMENT 11 KV CUBICLES ETC.
EL 268.00
SURGE POOL SFC EQUIPMENT
L.T. BOARDS (415 V)
PUMP STARTING ISOLATORS
EL 262.50
15000
NE
LI
RY
500 20000 500
VE
LI
DE
11000 9000
UNIT
CONTROL
PANELS
FOR TENDER PURPOSE ONLY
EL 233.00
CPU
RECIVER
NGR
CUBICLES
5000
EL 225.00
GREASE
PUMP
OIL
LIFTPUMP
5000
OPU
SUMP
TANK
EL 223
NOTE:
1) DISCHARGE LINE (DELIVERY LINE) OUTLET IS AT EL 340M
Capacity of Pumps
Specific Speed
Type of pumps
V V
CRANE GIRDER
impeller. BEAM B5
V
+ 346.00
V
W
+ 341.25
SLAB S1
+ 324.50
(Generally it may be 6D)
Pumps shall be 4.5m (approx) away
+ 319.75
+ 317.75
+ 314.50
Approach Canal
+ 356.75
V V
CRANE GIRDER 20 t E.O.T. CRANE
BEAM B5 + 353.75 V
MANUALLY OPERATED V
225 Th BRICK WALL
CRANE ( 3 t CAPACITY )
+ 351.50 REFLUX VALVE 4000 Ø MANIFO
( TENTATIVE )
SLUICE VALVE
+ 349.00
W 1300 Ø DELIVERY PIPE + 348.15
SLAB S1
Intake/Sump/Forebay/Surge pool
+ 346.50 + 347.00 + 346.50
CBL + 340.50 150 Th C.C. IN M15 GRADE BEAM B3 1000 Th R.C.C. STEINING WALL
STOPLOG GROOVE
+ 338.00
250 Th C.C. IN M10 GRADE + 338.50
+ 337.50
2
Pumps & Motors + 346.50
C1
C3
9250
W
C3
C1
+ 346.50
5000
+ 347.00
W RS1
REPAIR BAY
26000 5000
500 3000
+ 338.50
+ 338.00
BEAM B1
W
500
Th + 346.50
500 C1 BEAM B2 C1
4000
+ 338.00
TRASHRACK GROOVE
REFLUX VALVE
C1 1000 Th PIER C1
1 SLUICE VALVE
4000 Ø MANIFOLD
2.0 m WIDE
SILT TRAP
6 x 4.00 + 5 x 1.00 = 29.00 m
+ 338.50
W
BEAM B1
2500
10000
5000
FLOW APPROACH BED C1 BEAM B2 C1
LEVEL + 340.50
4000
+ 338.00
W
STOPLOG GROOVE
+ 338.50
+ 347.00
+ 338.00
W 1300 Ø DELIVERY PIPE
0
550
1000
+ 338.50
+ 347.00
+ 338.00
W 1300 Ø DELIVERY PIPE
4000
3 C1 C3 C3 C1
+ 375.00
10000
4750
Dewatering Pumps
W
CONTROL PANEL
+ 346.50 C2 C2
+ 346.50
+ 347.00
4750
W
C3 C3
C2 RS2 C2
Fire
2
Water Pumps
6 October 2017 IEI, HYDERABAD
PLAN OF THE JACKWELL CUM PUMP HOUSE
83
PRESSURE MAINS / WATER
CONDUCTOR SYSTEM
Pressure mains function as nerves of LI scheme and they
consume lions share of the project cost whenever pipe
lengths are in Km.
length of pipe has direct bearing on pumping head
thereby on pump capacity & surge protection system.
MS pipes and PSC pipes are under more usage in LIS.
It is desirable to limit the velocity in MS pipes to 2.0 m/s
and 1.5 m/s in PSC pipes.
Velocity more than 2.0 m/s in MS pipes may be
considered for the schemes with shorter length of pipes
duly examining the impact on pump capacity.
Max Dia of 3.0m is under more usage
Radiography test
UV Test
Hydraulic Test – To be
performed above design
working pressure to determine
water tightness of joints
Hydraulic test may be 1.5
times design pr as per codal
provisions and 1.25 times as
per AWWA.
6 October 2017 IEI, HYDERABAD 116
TADIPUDI LIS
6 October 2017
08.12.2010 IEI, HYDERABAD 117
ONE WAY SUTGE TANK
126
6 October 2017 IEI, HYDERABAD 126