You are on page 1of 10

BUILDING NAME: CCTV HEADQUARTERS

LOCATION: BEIJING, CHINA


ARCHITECT: REM KOOLHAAS
ENGINEER: ARUP
MAIN CONTRACTOR: CHINA STATE CONSTRUCTION
AND ENGINEERING CORPORATION
DEVELOPER/OWNER: CHINA CENTRAL TELEVISION
CONSTRUCTION STARTED: 2004
COMPLETION DATE: MAY 16, 2012
FLOOR COUNT: 51 (3 BELOW GROUND)
FLOOR AREA: 389079 SQUARE METERS
HEIGHT: 234m (768ft)
Design Issues:

Instability due form: The building


form: the continuous loop, sloping
tower and cantilever overhang add the
complexity of structure

Instability dude to weight: dead load DESIGN CONCEPT


caused by steel structure

Site Issues:

• Beijing is an earthquake zone


• Shallow subsoil condition
• High Settlement risk
• Large amount underground water
Advantages:
• Structurally very strong
• Less material required (~20%
reduction in steel as opposed to
typical moment frame method)
• Aesthetically Pleasing – Blends in
together with façade
• Floor plan becomes open and free –
more internal space
• Most forms can be created with a
triangulated form– architectural
freedom
• Self-reliant structure, simple in
shape
• Simple Construction Technique
• Skyscraper Structural Failure
minimized by diagrid construction
• Better ability to redistribute loads
than a moment frame (Failure of one
portion does not mean complete
structural failure)
EXTERNAL STRUCTURE SYSTEM
DIAGRID SYSTEM

• Triangles connected at Nodes and


Rings intersect the nodes.
• Triangulate structure with
diagonal support beams.
• Combines a hollow tube with a
truss.
• Loads follow diagonals, gravity
and lateral loads can be transferred
by the system to the ground.
• Steel is typical because of high
tensile and compressive strengths.
• Essentially marrying columns,
diagonals and bracings into one
INTERNAL STRUCTURE SYSTEM
Columns
• The Columns mean to transfer load from
the top to the foundation level.
• Types: SRC Columns and Steel Columns
• Challenge: columns on the inside faces of the
Towers; huge amount of dead load from the
• Overhang Solution: corner columns and brace
elements directly below the Overhang were
left out until the end of construction
forcing the dead loads to travel along the
VERTICAL CORE
diagonals down the adjacent columns; enabling
the full capacity of the corner elements to
be available for wind and seismic loads.

• Make each floor a specific spatial


configuration
• Making stability of overall system
STRUCTURAL CONCEPT
• 3 story basement, 9 story base, 2 towers, 9-
13 story overhang (36 stories above ground)
joined as a ‘continuous tube’
• Towers slope in 6 degrees each direction
• External diagrid solution for high seismic
area as well as solution to connect full loop
• Transparency of structure expressed through
façade.
TRANSFER STRUCTURES
• Due to slope of towers, internal
vertical columns cannot be continuous
• Select plant floors house two story deep
trusses to transfer loads
• Connect to internal cores and external
columns at singular pin-joint locations
to prevent outrigging
• Also located in overhang to support
internal columns
• Forces in truss diagonals carried only
by the flanges at connections
• Webs stop short of the chords to
simplify construction.
FOUNDATION PILED-RAFT
• Towers are supported on separate piled
raft foundations 370 reinforced concrete
bored piles beneath each tower
• 1242 piles were installed
• Centre of the raft is close to the centre
of the load at the bottom of each tower
for no permanent tension in the piles
• Certain piles were designed for tension
especially designed for severe
earthquakes

TESTING PRACTICES
Butterfly plate - 1:5 scale model of
joint for performance in cyclical
loading and confirmation of yield
location
Composite column - 1:5 model for
concerns that high steel ratio would
result in ductility
Shake table - 1:35 full model under
various seismic events
DIAGRID SYSTEM CONNECTION DETAILS
The meeting of vertical columns, diagonal members& perimeter
beams at nodes
• Butterfly plates will be welded to bring all these 3
members together
• Enabling the vertical and horizontal elements to remain
comparatively unstressed in an earthquake

Critical Members in the Structural System


• Must ensure a “strong joint-weak member” system
• Must resist maximum probable load from braces with minimum
yielding and stress concentration.
• Butterfly plates used to assist smooth load transfer.
• Finite Element Analysis of Connection.

Node construction
• In-place steel shop welding
• Lifting up piece by piece
• Trial shop assembly of parts with high
strength bolts
• In-place welding
• High strength bolts assembly
• Setting up perimeter girders
HVAC FOUNDATION
SYSTEM DESIGN

P
R
O
G
R
A
M
CONSTRUCTION SEQUENCING In addition to regular gravity and lateral
forces acting on the structure, there are
significant additional construction stage
forces due to the fact that the building
comprises two separate leaning Towers with
cantilever up until the point at which
they are joined to become one structure.
• First method is to construct a temporary
tower the full 162m height to the
underside of the Overhang, providing a
working platform to build the Overhang
connection.

• Second method is to construct the


lower part of the Overhang at ground
level and strand jack the assembly into
position
• Third method is to construct
incremental cantilevers from each Tower
until the two met and connected at the
center of the Overhang.

You might also like