Cost summary for 125

SALES 750000
less(-)
Labour 225000
Material 62500
Overhead 318800

Profit (Rupees) 143700


ABC costing at Edgewood Cororation

Manufacturing OH
Selling and Admin OH

Therefore

Hence for 125 units

Assembly and Fitting Units(125 orders assembled)


Processing Orderfor materials (4 orders)
Customer support (1 customer )
Others
Total
gewood Cororation

Assembling and Fitting Processing Orders Customers Support


2,000,000 1,400,000 200,000
200,000 900,000 500,000
2,200,000 2,300,000 700,000

1000 units 250 orders 100 customers

for 1 unit of assembling and fitting 2,200


for 1 order processing 9,200
for 1 customers support 7,000

275,000
36,800
7,000

318,800
Other Total
400,000 4,000,000
400,000 2,000,000