Professional Documents
Culture Documents
relatively new wells (drilled in 1995). Details and findings of Well HD07
the investigative efforts are as follow: ¾ The ultrasonic log indicated that the 7” liner
predominantly suffered external corrosion
1. Location – A review of the geographical location across the leak area (see Fig. 4). The
relative to other cathodically protected facilities and observed corrosion occurred over the
to formation exposures of the wells with casing leaks interval where total losses were experienced
did not reveal any enlightening patterns when while drilling.
compared to wells without casing leaks.
Well HD11
2. Cross-section – The review of the casing cross- ¾ Similar to well HD07, the ultrasonic log
sections of the affected wells, compared to other showed that the liner had external corrosion
wells without leaks, did not reveal any enlightening across the leak area. The observed corrosion
patterns. In all wells, the corrosion worked its way occurred over the interval where total losses
through both the 9-5/8” and the 7” casings. were experienced while drilling.
3. Injection history – The three Haradh wells were on Well HD01 Integrated Corrosion Logs
continuous injection since completion in 1995. No Though the information from HD05, HD07 and HD11
major shutdowns took place. Again, no enlightening provided significant insight into the problem (poor cement),
information was noted when compared to wells the principle question of why the external corrosion had
without corrosion failures. occurred despite the application of adequate cathodic
protection was still not answered. To try to answer this
4. Cementing quality – The wells that suffered from question, an integrated corrosion logging program was run in
external corrosion failures did not have good quality well HD01. Ultrasonic, electromagnetic, and cathodic
cement behind pipe, and the leaks took place in lost protection evaluation logs were run in the well.
circulation zones.
The HD01 well was in the same area and drilled during the
5. Cathodic protection history – The ICCP installation same year (in 1995) as the other three Haradh wells that
timing was reviewed, and it was found that the ICCP experienced casing leaks. Well HD01 is also the only offset
systems were commissioned approximately 10 vertical well with no major downhole operations since drilling.
months after well completion (acceptable However, this well did not suffer from lost circulation and
commissioning time per Saudi Aramco standards is poor cementing to the extent that the other three wells did.
within 6 months). However, other wells that have not
failed were also noted to have been without ICCP for Corrosion logs with dynamic ICCP operating conditions were
10 months or more following completion. completed to attempt to understand the effect of interference
between wells under CP protection and to confirm the
6. The ICCP operating history was reviewed, and it was company’s standards related to the magnitude of CP
found that the output currents of the Haradh wells requirement in the Haradh area.
were 50% to 100% or higher than the recommended
output current of 12 amperes, refer to Fig. 3. Results of the logs for HD01 provided the following
information:
7. Review of the cathodic protection evaluation and the
corrosion logs that were run on HD05, HD07 and 1. The ultrasonic log indicated that the 7-inch liner was
HD11 provided the following information: in excellent condition both internally and externally
through the areas the investigation was focusing on.
Well HD05
¾ The ultrasonic log verified that failure of the 2. The concentric pipes analysis using the ultrasonic and
7-inch casing was caused by external electromagnetic measurements indicated that the
corrosion and indicated additional external general condition of the 9-5/8” casing was very good.
corrosion in the nearby vicinity of the leak.
¾ A second ultrasonic log indicated that the 7” 3. The ultrasonic log illustrated that the cement in the
x 9-5/8” casing-casing annulus was poorly annulus behind the 7” liner through the Shu’aiba
cemented over the corroded interval. formation was of relatively low density, but well
¾ The cathodic protection evaluation log bonded to the casing. However, if the 9-5/8” casing
indicated that cathodic protection under were to corrode, the low density casing/casing
normal operation was effective through and annulus cement would rapidly saturate with
below the area where the corrosion was formation fluid. Consequent chemical reactions on
noted. the steel/cement interface would likely result in rapid
disruption of the bond quality.
SPE 93184 3
4. The ultrasonic log also showed that the cement on the casing below the 9-5/8” shoe.
formation side of the 9-5/8” casing through the
Shu’aiba formation was not ideal. It displayed a It is evident here that interference can occur in
gas/dry micro-annulus behind the casing, suggesting the field if certain conditions are present.
that the Shu’aiba formation at this well site was dry. Protection shown across the Shu’aiba formation
If the Shu’aiba formation had been wet at this in HD01 is believed to be aided by the cement on
location, saturation of the cement and permeation of the formation side of the 9-5/8” and the absence
formation fluids into the micro-annulus would likely of fluids in the formation through this area.
have occurred. This would support galvanic coupling
to other formations with resulting corrosion of the CP Evaluation Log – Second Pass (Fig. 6)
casing. In a formation fluid containing acid gasses, a The second pass of the cathodic evaluation log
reduction in pH of the cement caused by CO2 or H2S was run from 6,460 feet to 3,960 feet. During
would also facilitate eventual corrosion of the casing. this pass, a number of operating conditions were
However, timely application of cathodic protection altered to judge the effects on the well casing.
will in most cases offset these types of corrosion The various changes to the operating conditions
mechanisms. involved: turning rectifiers off, connecting and
disconnecting the HD01 flowline, and finally
5. The ultrasonic and the electromagnetic measurements setting the conditions as close as possible to
logs indicated that there was no corrosion of the normal operating conditions and optimizing the
casings through the Shu’aiba formation. This rectifier outputs for HD01 and the two offset
suggests that the conditions that were present on the wells.
wells that had suffered full corrosion wall loss
through the 9-5/8” and the 7” casings were not The testing completed during the second pass
present at well HD01. revealed the following:
6. The cathodic protection evaluation log was run to ¾ Severe interference was generated under
determine if electrical interference could be the cause worst case conditions. However, the
of the corrosion on the failed casings. To emphasize damaging aspect of the interference did not
possible deficiencies, worst case conditions were set occur through the Shu’aiba formation as
up at well HD01 and allowed to work on the casing might have been expected.
for two weeks. Worst case conditions as set up were ¾ The interference generated with worst case
as follows: conditions was not spontaneously eliminated
by connecting HD01 well to its flowline and
a. The HD01 ICCP system was turned off. thereby generating electrical continuity with
b. The flowline from HD01 was disconnected the neighboring cathodic protection systems.
and the well was completely electrically Long-term effects of connecting the flowline
isolated from the cathodically protected were not measured due to practical
flowline system. constraints.
c. The nearest two well-casing cathodic ¾ The testing also revealed that complete
protection systems, one located 500 meters cathodic protection of the HD01 well casing
away, and the other located 2,000 meters was evident when its rectifier and the
away, were adjusted to near maximum neighboring rectifiers were adjusted to
output (44 amps each). This magnitude is slightly above their target outputs (12 amps)
more than triple the recommended output of and the HD01 flowline was connected.
12 amps each.
The significance of these findings emphasizes the benefits of a
CP Evaluation Log – First Pass (Fig. 5) quality cement job, and suggests that the initial corrosion that
The cathodic protection evaluation log was occurs over a 10-month period on poorly cemented casings
initially run from 7,600 feet to 3,005 feet. without ICCP significantly affects the long-term integrity of
During this pass, the nearest neighboring rectifier the wells. Based on the logs and testing completed on HD01,
was briefly shut off between 4,680 feet to 4,605 the findings also indicate that, under normal operating
feet. The log revealed severe interference; conditions, damaging interference effects would be unlikely,
however, it is quite evident by the log that the and complete cathodic protection would be expected through
deleterious aspect of the interference occurred the Shu’aiba formation.
below the 9-5/8” shoe. The area through the
Shu’aiba formation was actually an area on the
casing that was protected by the interference Conclusion
current. Surprisingly, the area of the casing Integrated corrosion logs were used to investigate the casing
through the Shu’aiba formation was protected corrosion problem in Haradh area. The logs showed that the
from corrosion at the expense of the area of the main cause of the casing leaks in the Haradh injectors was
4 SPE 93184
Acknowledgement
The authors wish to thank Saudi Aramco for permission to
publish this paper.
SPE 93184 5
Fig. 1 Fig. 2
Typical Injection Well Completion
9
8
Started Cathodic Protection
7
No. of Casing Leaks
4
Area M othballed
3
2
1
0
1976 1979 1982 1985 1988 1991 1994 1997 2000 2003
Year
Fig. 4
Well HD07 External Corrosion
3-D Visualization of the Corrosion Log
Fig. 3 at Interval 4,438’ – 4,434’
35
string
30
25
20
15
10
Recommended Output Current
5
0
1994 1995 1997 1998 1999 2001 2002 2004 2005 2006
Date
HD05 HD07 HD11 HD01
6 SPE 93184
Fig. 5
-500
Interference due to shutoff
Current (milliamps)
-2000
-2500
6' Interval Data
-3000
-3500
3000 3500 4000 4500 5000 5500 6000 6500 7000 7500
Depth (feet)
Well HD01 flowline was disconnected, rectifier is off. Offset wells rectifiers were set @ 44 amps,
At 4,605'-4,680’ one of the offset wells’ rectifier was set off.
SPE 93184 7
Fig. 6
Logging Setup
1 Offset wells’ rectifiers set @ 44 amps. Well HD01 flowline was disconnected.
2 Connected well HD01 flowline and drained 1.2 amps from Flowline.
3 Disconnected well HD01 flowline and reduced one of the offset well’s rectifier to 22 amps.
4 Offset wells’ rectifiers back to 44 amps. Well HD01 flowline was disconnected.
5 One of the offset well’s rectifier set to 0.0 amps.
6 Set the offset well’s rectifier back to 44 amps.
7 All rectifiers set to 15 amps, and well HD01 flowline was connected with 0.5 amps from well casing.
8 All rectifiers set to 10 amps, and the HD01 flowline was connected with 0.4 amps from well casing.