Weekly Progress Report

(19.02.18 to 25.02.18)
Construction of Multimodal IWT Terminal
at Varanasi, U.P
Progress Photographs

Front View Berthing Structure


2
Progress Photographs

Erection of Fender column completed 2nd & 3rd layer for D2 to D11
3
Progress Photographs

In-situ shuttering for Fender column Installation of working platform for


completed In-situ shuttering of Fender column
in progress

4
Progress Photographs

Rebar tying for Deck slab in progress for A17-C17 to A18 to C18
5
Progress Photographs

Rebar tying, shuttering & concreting of Precast Long


beam for approach slab in progress

6
Progress Photographs

Fixing of shuttering & weep holes for Retaining wall in progress

7
Progress Photographs

Soling & PCC completed for Raft ( 25m) length of retaining wall
in berthing area
8
Progress Photographs

Rebar tying is in progress for Raft ( 25m) length of retaining


wall in berthing area
9
Progress Photographs

Excavation for Retaining wall works between grid 1 to 12 in progress


10
Progress Photographs

Mobile Harbour crane Parts received from Kolkata to IWT Terminal Varanasi on
24.02.18. Balance parts is in Transit
11
Progress Photographs

Mobile Harbour crane Parts received to IWT Terminal Varanasi on


24.02.18.
12
Progress Photographs

Mobile Harbour crane Parts received to IWT Terminal Varanasi on 24.02.18.

13
Progress Photographs

Mobile Harbour crane Parts received to IWT Terminal Varanasi on 24.02.18.

14
Progress Photographs

Mobile Harbour crane Parts received to IWT Terminal Varanasi on 24.02.18 unloading is
in progress
15
Progress Photographs

Storage of Mobile Harbour crane Parts in Stack yard

16
Progress Photographs

World Bank officials along with IWAI Sh. A. K. Mishra (Director, Patna), Sh. Shukla
(Member finance) visited site on 24.02.18.
17
Progress Photographs

World Bank officials along with IWAI Sh. A. K. Mishra (Director, Patna), Sh. Shukla
(Member finance) visited site on 24.02.18.

18
Progress Photographs

World Bank officials along with IWAI Sh. A. K. Mishra (Director, Patna), Sh. Shukla
(Member finance) inspected Worker’s Accommodation & mess facilities at site on
24.02.18.
19
Progress Photographs

World Bank officials along with IWAI Sh. A. K. Mishra (Director, Patna), Sh. Shukla
(Member finance) inspected Worker’s Accommodation & mess facilities at site on
24.02.18.

20
Activities completed/in-progress for the week
• Rebar tying & In-situ concreting Fender column 1st, 2nd & 3rd is in progress.

• Shifting & Installation of fender column grid- D is in progress.

• Rebar tying for in-situ deck slab is in progress for A17-C17 to A18-C18.

• Precast concrete for approach slab long beam completed 2 nos & rebar tying is in progress.

• Removal of excess earth & Slope profiling for bank protection between grid A14-A16 to B14-B16 is in progress.

• Laying of stones for bank protection between grid A11-A13 is in progress.

• Procurement of stones for bank protection works is in progress.

• Excavation for Retaining wall completed up to Grid 12.

• Rubble soiling & PCC for retaining wall raft completed for 25m length (up to 50m).

• Rebar tying & RCC for retaining wall raft is in progress for 25m length. (up to 50m).

• Rebar tying for wall is in progress for retaining wall.

• Mobile harbour cranes dispatched from Kolkata port & 2nd & 3rd lot received at site on 19.02.18,20.02.18 & 24.02.18 with crane
cabin (77% crane parts received at site).

 World Bank officials along with IWAI Sh. A. K. Mishra (Director, Patna), Sh. Shukla (Member finance) visited site on 24.02.18.

21
Plan Vs Achieved for the week
Progress
Sr. Plan for week Week’s Progress Cumulative achieved Project
Description of activity UOM achieved for Scope
No. (19.02.18 to 25.02.18) (%) up to date Progress (%)
the week
1 Berthing Structure
1.1 Installation of Precast Beams Nos 0 0 182 100 55%
1.2 Installation of Precast Slab Nos 0 0 288 144 50%
Installation of Precast Fender
1.3 Nos 6 9 150% 54 49 91%
Column
1.4 In-situ Concrete Muff Cum 0 Completed 50 50.01 100%
1.5 In-situ concrete beams Cum 0 0 1612 979.5 61%
1.6 In-situ concrete slab Cum 0 0 1050 399 38%
1.7 In-situ concrete Fender Column Cum 120 120 100% 594 447 75%
Electrical Substation Building Drawing revision in
2 0 0
(ESS) progress
Drawing revision in
3 Worker's Amenities 0 0
progress
4 Bank protection works 0 0
Removal of excess earth (berthing
4.1 Sqm 200 260 130% 7300 1903 26%
area)
4.2 Laying of stones (berthing area) Sqm 200 280 140% 7300 1660 23%
5 Retaining Wall 0 0
5.1 Excavation Rmt 50 50 100% 200 140 70%
5.2 Rubble Soling Sqm 175 175 100% 1400 343 25%
5.3 PCC Cum 16.8 15 89% 144 31.8 22%
5.4 Key Concrete Cum 0 0 204 20.4 10%
5.5 Raft Concrete Cum 0 0 1400 135 10%
5.6 Wall concrete Cum 0 0 1229 2.6 0%
6 MH Crane 0 0
Delivery of MH Crane FOB Port
6.1 Nos 2 2 100%
delivery
6.2 Receipt of MH Crane at site Nos 1.24 1.24 100% 2 1.54 77%

22
Areas of concern
 Delay in release of payment for RA bill:
Payment to be released by IWAI for RA bill 13 (Dec’17) & & RA bill 14 (Jan’18) Submitted vide
letter AFCONS/4551/MY/210 dated06.01.18 & AFCONS/4551/MY/229 dated 07.02.18 .
 Delay in Bank Protection work:
IWAI to expedite the approval of revised drawing for berthing area submitted vide transmittal
AFC-IWAI-4551-TRS-0066 dated 23.10.2017 & clarification submitted by vide letter
AFCONS/4551/MY/195 dated19.12.17, AFCONS/4551/MY/217 dated 17.01.18,
AFCONS/4551/MY/227 dated 05.02.18 & AFCONS/4551/MY/232 dated 15.02.18.
 Gangway & pontoon arrangement :
IWAI approved the revised GAD drawing submitted incorporating comments vide letter
AFCONS/551/MY/184 dated 08.12.17 on 30.01.18.
IWAI commented on AFCONS proposal of the Pontoon & Gangway during site meeting dated
31.01.18.
 AFCONS applied for Extension of time vide letter AFCONS/4551/MY/213 dated 10.01.18.
Approval awaited.