Date : 05.03.2018
EGIS’s POSITION
As per the present status of deployment of our team, we have partially deployed and expect
to complete the deployment by 21st March.
As such we might lose the invoice value partially for first two months against partial
deployment.
Following table presents deployment status till date for various positions
Sl.N Dat
o. Key Experts Name Deployed at e
Team Leader cum project Varanasi/
1 management expert Sudipta Chakraborty Sahibganj
Resident Engineer cum Construction
2 Expert-1 J. P. Patel Varanasi
Resident Engineer cum Construction
3 Expert- 2 S. K. Patel Sahiganj
Sr. Quality Assurance cum Material Varanasi/
4 Engineer Vinod Kumar Sahibganj
5 Sr. Electrical / Electronics Engineer Suraj Chaudhary Varanasi
Varanasi/
6 Sr. Mechanical Engineer Pranab Thakur Sahibganj
Contract Specialist and Commercial Varanasi/
7 Manager Amit Jain Sahibganj
Operational and Occupational Safety
8 Expert (Dy. TL) Pushpendra Srivastav Sahiganj
Dipankar Majumdar/ Sajjal Varanasi/
9 Environment Specialist Vowmick Sahibganj
10 MIS Expert cum project co-ordinator Manoj Gupta IWAI
Varanasi/
11 Social Specialist Satya Vrat Pandey Sahibganj
Sl.N Dat
o. Non-Key Experts Name Deployed at e
1 Civil Engineer-1
2 Civil Engineer 2 Jibeesh Rajan Varanasi
3 Jr.QC Engineer-1
4 Jr.QC Engineer-2
5 Safety Office-1 Kanta Chabra Varanasi
6 Safety officer-2 Anand Tripathy Sahibganj
Varanasi/
7 Surveyor Mukesh Raghuvansi Sahebganj
8 Senior Civil Engineer (Defect Liability) TBA
9 Office Admin-1
10 Office Admin-2
11 Office Support Staff Mohit Varanasi
12 Office Support Staff
IWAI has already gone ahead with the start of construction of both the project, prior to
signing of our contract and is targeting the completion of Varanasi terminal by Nov.-18 &
Sahibganj terminal by May-19.
About 35% of Varanasi & 22% Sahibganj construction has already been completed, without
availing the services of TSSC.
CONTRACT SYNOPSIS
Contract starts from Feb.-18 & end of defects liability period as Jan.-20.
Contract Value of INR 8.30 Cr. Mainly belongs to deployment of 140 man-months of key
experts and 172 man-months of non-key experts.
As per contractual deployment schedule, out of a total of 312 man-months, about 227 man-
months (73%) needs to be provided in construction period of 12 months, i.e. upto Jan.-19,
with an approx. invoice of INR 5.68 Cr.
Sd/-
Manoj Gupta
MIS Expert-cum-Project Coordinator
TSSC-1