PROJECT REVIEW - TSSC-1 (Varanasi & Sahibganj), JMVP,IWAI

Date : 05.03.2018

EGIS’s POSITION

 As per the present status of deployment of our team, we have partially deployed and expect
to complete the deployment by 21st March.
 As such we might lose the invoice value partially for first two months against partial
deployment.
 Following table presents deployment status till date for various positions

Sl.N Dat
o. Key Experts Name Deployed at e
Team Leader cum project Varanasi/
1 management expert Sudipta Chakraborty Sahibganj
Resident Engineer cum Construction
2 Expert-1 J. P. Patel Varanasi
Resident Engineer cum Construction
3 Expert- 2 S. K. Patel Sahiganj
Sr. Quality Assurance cum Material Varanasi/
4 Engineer Vinod Kumar Sahibganj
5 Sr. Electrical / Electronics Engineer Suraj Chaudhary Varanasi
Varanasi/
6 Sr. Mechanical Engineer Pranab Thakur Sahibganj
Contract Specialist and Commercial Varanasi/
7 Manager Amit Jain Sahibganj
Operational and Occupational Safety
8 Expert (Dy. TL) Pushpendra Srivastav Sahiganj
Dipankar Majumdar/ Sajjal Varanasi/
9 Environment Specialist Vowmick Sahibganj
10 MIS Expert cum project co-ordinator Manoj Gupta IWAI
Varanasi/
11 Social Specialist Satya Vrat Pandey Sahibganj

Sl.N Dat
o. Non-Key Experts Name Deployed at e
1 Civil Engineer-1
2 Civil Engineer 2 Jibeesh Rajan Varanasi
3 Jr.QC Engineer-1
4 Jr.QC Engineer-2
5 Safety Office-1 Kanta Chabra Varanasi
6 Safety officer-2 Anand Tripathy Sahibganj
Varanasi/
7 Surveyor Mukesh Raghuvansi Sahebganj
8 Senior Civil Engineer (Defect Liability) TBA
9 Office Admin-1
10 Office Admin-2
11 Office Support Staff Mohit Varanasi
12 Office Support Staff

PROJECT CONSTRUCTION STATUS

 IWAI has already gone ahead with the start of construction of both the project, prior to
signing of our contract and is targeting the completion of Varanasi terminal by Nov.-18 &
Sahibganj terminal by May-19.
 About 35% of Varanasi & 22% Sahibganj construction has already been completed, without
availing the services of TSSC.

CONTRACT SYNOPSIS

 Contract starts from Feb.-18 & end of defects liability period as Jan.-20.
 Contract Value of INR 8.30 Cr. Mainly belongs to deployment of 140 man-months of key
experts and 172 man-months of non-key experts.
 As per contractual deployment schedule, out of a total of 312 man-months, about 227 man-
months (73%) needs to be provided in construction period of 12 months, i.e. upto Jan.-19,
with an approx. invoice of INR 5.68 Cr.

Sd/-

Manoj Gupta
MIS Expert-cum-Project Coordinator